{"document":{"slug":"rec-20250423-5252","title":"Motion to Intervene and Comments of the Electricity Consumers Resource Council to PJM Interconnection, L.L.C. 's Answer to the Section 206 Show Cause Order","issued":"2025-04-23","accession":"20250423-5252","docket":"EL25-49-000","group":"PJM co-location compliance","filer":"Electricity Consumers Resource Council","kind":"answer","file":"sources/filings/text/20250423-5252_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20250423-5252","tier":"record","sha256":"f3048055aa333e26be97b629ca1558faded4dc25bc239cd3869d0f9dc8bfeb71","pages":11,"tokens":2231,"emptyPages":[],"textThemes":["colo","registry","flex","cost"]},"pages":[{"page":1,"startToken":0,"endToken":232,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \n \n \n \n \n \n \n \n \n) \n \n \nPJM Interconnection, L.L.C. et al. \n \n)  \n \nDocket No. EL25-49-000 \n \n \n \n \n \n \n \n) \n \nMOTION TO INTERVENE AND COMMENTS OF THE ELECTRICITY \nCONSUMERS RESOURCE COUNCIL TO PJM INTERCONNECTION, L.L.C.’S \nANSWER TO THE SECTION 206 SHOW CAUSE ORDER \n \nPursuant to Rules 212 and 214 of the Federal Energy Regulatory Commission’s \n(the “Commission”) Rules of Practice and Procedure,1 the Commission’s Order \nInstituting Proceeding Under Section 206 of the Federal Power Act and Consolidating \nwith Other Proceedings,2 and the Electricity Consumers Resource Council’s (“ELCON”) \n(doc-less) Motion to Intervene in this docket,3 ELCON respectfully submits these \ncomments in response to the March 24, 2025 Answer of PJM Interconnection, L.L.C.4 as \nto how their tariff remains just and reasonable in facilitating co-location arrangements \nwhile also protecting consumers.  \nELCON is the national association representing large industrial consumers of \nelectricity.  ELCON member companies create a wide range of products from virtually \nevery segment of the industrial community—we own and operate hundreds of major \n \n1 18 C.F.R. §§ 385.212 and 214. \n2 PJM Interconnection, L.L.C. et al., 190 FERC ¶ 61,115 (2025) (“Show Cause Order”).  \n3 Electricity Consumers Resource Council, (doc-less) Motion to Intervene, Docket No. EL25-49-000 (Mar. \n6, 2025). \n4 Answer of PJM Interconnection, L.L.C., Docket Nos. EL25-49-000, AD2411-000, and EL25-20-000 \n(Consolidated) (Mar. 24, 2025) (“PJM Answer”)."},{"page":2,"startToken":232,"endToken":490,"text":"2 \n \nfacilities and are significant consumers of electricity in the footprints of all organized \nmarkets and other regions throughout the United States.  Reliable electricity supply at \njust and reasonable rates is essential to our members’ operations.  Further, ELCON \nmembers have and will continue to pursue opportunities for co-locating with onsite \ngeneration to reliably meet their electricity operating demands. \nSUMMARY \nThe pursuit of co-location arrangements is primarily driven by projections of \nsignificant electric load growth coupled with persistent challenges facing the electric \npower industry. At the same time electricity demand is projected to grow exponentially \nin the next several decades, the nation continues to struggle with unprecedented \ninterconnection queue congestion, the need for substantial transmission buildout, \nretirement of existing dispatchable generation facilities, aging grid infrastructure, and \nextreme weather events. According to a recent report by the National Electrical \nManufacturer’s Association, electricity demand will grow by 2% annually and \napproximately 50% by 2050 (see Figure 1), driven in part by a 300% rise in data center \nconsumption.5 The U.S. Energy Information Administration projects that electricity \ndemand by the industrial sector alone will grow 3% in 2025.6 This growth is now. A \nwide variety of solutions are necessary to meet this growth now and in the longer term, \nincluding solutions that can be implemented in the shorter-term like grid enhancing \n \n5 NEMA, “A Reliable Grid for an Electric Future – Executive Summary” (Apr. 7, 2025); \nhttps://www.makeitelectric.org/wp-content/uploads/2025/04/nema-grid-study-executive-\nsummary.pdf.  \n6 U.S. Energy Information Administration, “Short-Term Energy Outlook” p. 13 (Mar. 2025)."},{"page":3,"startToken":490,"endToken":623,"text":"3 \n \ntechnologies, surplus interconnection service, and demand response, and longer-term \nsolutions like more holistic transmission planning and customer-centric market designs \nthat support flexible load capability and efficiently integrate large loads on the system. \nHowever, due to the complexity and rapid pace of emerging challenges and slow action \non regulatory and market changes, consumers are pursuing immediate stop-gap \nmeasures to meet their needs. Co-location is one such stop-gap measure aimed to serve \nneeds now until regulatory approaches and market structures are reformed to solve \nfundamental challenges.  \nTo be sure, co-location configurations raise jurisdictional questions, present \nunique challenges to traditional cost allocation methods, and impact generation access, \nSource: National Electrical Manufacturers Association, “A Reliable Grid for an Electric Future” (Apr. \n7, 2025); https://www.makeitelectric.org/wp-content/uploads/2025/04/grid-reliability-study-\nnema-deck.pdf  \nFigure 1:"},{"page":4,"startToken":623,"endToken":858,"text":"4 \n \nnecessitating updated policies from the Commission and the states to ensure fairness, \nefficiency, and grid reliability. Although there are legitimate concerns about ensuring \nfair treatment for all customers, co-location remains a valuable tool, and the \nCommission should focus on facilitating co-location and other flexible arrangements \nwhile ensuring sufficient customer protections are in place, rather than taking them off \nthe table (as Indicated PJM Transmission Owners suggest in this proceeding)7 or \ncomplicating them.  \nIn addition, as explained below, while resolving co-location concerns is \nimportant, more attention must be paid to the broader load forecasting and planning \nissues that are implicated by this current period of exponential load growth. The \nCommission should convene industry and state and federal policymakers to examine \nload forecasting methodologies and how to improve load forecasting across wholesale \nand retail markets. Convening this conservation and identifying potential solutions to \nload forecasting and planning challenges is essential to effectively integrate large loads \nin a way that improves overall system utilization and individual consumer costs. \nA. \nThe Commission Should Clarify Jurisdictional Boundaries Around Co-\nLocation Arrangements \nELCON appreciates PJM’s thorough response to the Commission’s Show Cause \nOrder detailing eight viable configurations for co-locating large loads with onsite \n \n7 See Answer of the Indicated PJM Transmission Owners to the Order Instituting the Proceeding Under \nSection 206 of the Federal Power Act and Consolidating with Other Proceedings, Docket No. EL25-49-000, \net al. (Mar. 24, 2025)."},{"page":5,"startToken":858,"endToken":1108,"text":"5 \n \ngeneration.8 PJM’s Answer presents comprehensive options for large loads to consider \nin negotiating with generators and transmission providers to serve their energy \ndemands while connecting to the grid for back-up support and ancillary services. As \nthe Commission solely has jurisdiction over wholesale electricity sales and PJM is \nentrusted with wholesale energy markets and transmission operations, it is reasonable \nfor the Commission to focus on co-location arrangements that are considered “Network \nLoad” as the preferred configuration as it is most squarely in the Commission’s \npurview. However, while Network Load may be the preferred solution by PJM and its \nutilities, it is not the only configuration to consider. Large load customers may consider \nentirely “islanded” configurations that are not contemplated in this docket and may fall \nunder state jurisdiction rather than federal jurisdiction.  \nConfigurations completely isolated from the grid may not be the norm but can be \na preferred choice for some large customers. In areas of insufficient reliable electricity, \nlarge consumers may look to onsite generation as a solution to maintain 24/7 \noperations at affordable costs. Some large consumers may find that relying on local \nsupply and grid services is insufficient to meet their unique needs or energy supply \npreferences and instead install resources at their facilities. Large consumers, at times, \nhave become frustrated with local utility resistance and outdated tariffs and instead \nopted for completely isolated configurations. \nWhile large consumers will largely prefer to access the grid for energy, back-up \n \n8 PJM Answer pp. 9-20, Exhibit A."},{"page":6,"startToken":1108,"endToken":1354,"text":"6 \n \ngeneration, and ancillary services, the Commission should ensure that there are no \nregulatory barriers to such islanded configurations should state law allow the use of \nonsite generation by large loads with no connections to the larger grid. In this regard, \nthe Commission should reject the overarching premise in the comments of the Indicated \nPJM Transmission Owners that only Network Service or Point-to-Point Transmission \nService arrangements should be permitted, and that no other flexibility should be \nallowed. Forcing all large loads into this box and limiting flexibility risks driving \nsignificant increased overall system costs and limits the ability of customers, state \nregulators, and utilities to find creative and cost-effective solutions based on individual \nneeds and circumstances. \nB. \nCost Allocation Policies Should Adhere to the Core Principles of “Cost \nCausation” and “Beneficiary Pays” \nThe economic principles of cost causation and beneficiary pays ensure equitable \nand fair allocation of grid costs so that one customer class does not subsidize the other. \nThe Commission should provide guidance, without being overly prescriptive, by \ndefining different co-location configurations and illustrating how cost allocation \nmethodologies that adhere to the principles of cost causation and beneficiary pays \nwould allocate costs based on the impact of such arrangements on grid investment \nneeds and use of grid services.  \nIf a large consumer in any co-location configuration impacts electricity flows on \nthe grid either through adding to congestion, creating voltage or frequency instability, \nor impacting access to generation, and such impacts that require upgrades to the"},{"page":7,"startToken":1354,"endToken":1600,"text":"7 \n \ndistribution or transmission system, those costs should be allocated to that large \nconsumer. This is classic “cost causation.” The Commission should ensure that \nregulatory authorities consider the long-term impacts of new large load projects in \nassessing cost causation to protect non-large load ratepayers from paying the \ngeneration and transmission costs to serve large load even after initial electric service \nagreement terms expire. \nCo-location arrangements that are configured to be connected to the grid for \nancillary services should be required to pay for those services based on the usage of \nthose services and any necessary upgrades to the transmission system to ensure access \nto grid ancillary services. This is an application of “beneficiary pays.” Similarly, if such \nconfigurations require power control systems to limit injection or taking of grid power, \nthose costs should be allocated to the load. \nLarge loads that choose to completely self-supply by connecting to their own \ngeneration and not taking any grid services should not be allocated any grid costs \nunless there is some concrete demonstration that such configuration has a direct cost \nimpact on other grid consumers.  \nC. \nThe Commission Should Give Greater Attention to Broader Load \nForecasting and Planning Issues Implicated by Exponential Load \nGrowth \nAs referenced above, co-location is just one tool to serve immediate operational \nneeds while more fundamental challenges with interconnection, transmission \ndevelopment, and market rules are improved. However, co-location is not merely a \n“stop-gap” but can also provide greater long-term benefits such as flexibility, sharing of"},{"page":8,"startToken":1600,"endToken":1832,"text":"8 \n \nresources, and deferring expensive transmission upgrades, among others. While the co-\nlocation of electric generation and load presents important considerations, the \nCommission's attention appears to be disproportionately focused on this issue. The \nlarger, more pressing challenge lies in developing effective strategies to forecast and \naccommodate exponential load growth. Addressing this fundamental issue is critical; a \nfailure to do so will have far more significant consequences for the industry and \nconsumers than any specific policies related to co-location. Throughout the history of \nthe industry, effectively integrating large loads has improved cost outcomes for \nconsumers across the system by improving system utilization and reducing per unit \ncosts. Without effective forecasting and planning, it will be difficult if not impossible to \nachieve this kind of effective integration in this latest wave of load growth. Moreover, \nwhether behind-the-meter or integrated into the grid, understanding the scope and \npotential impacts of large loads is crucial to ensure reliability.  \nThe Commission’s expertise and broad jurisdiction over wholesale rates and \npractices makes it uniquely positioned to convene industry and policymakers to \naddress these broader issues. The Commission should convene a dialogue addressing \nload forecasting methodologies and how to facilitate communication among state and \nfederal regulators, transmission operators, generators, and customers to ensure we are \npositioned to serve all customers reliably and affordably. Comments submitted by the \nData Center Coalition succinctly articulate the large load forecasting challenge and offer"},{"page":9,"startToken":1832,"endToken":2016,"text":"9 \n \nrecommendations for Commission action.9 While industrials and manufacturers \noperate differently and at different scales from data centers, we share the urgency in \nsecuring accurate forecasting practices and guidelines. Underestimating load growth \ncould cause reliability challenges where demand unexpectedly exceeds infrastructure \ncapacity and affordable generation. Overestimating load growth could lead to \nsubstantial overbuilding of infrastructure saddling consumers with exorbitant energy \ncosts for decades. \nTo ensure the accuracy of models and forecasts, it will be critical to establish \nstandard terminology across planners, operators, and users. Enhanced transparency \nregarding both front-of-the-meter and behind-the-meter loads is necessary to enable \noperators to ascertain real-time load behavior, including the potential for excess power \ninjection and reliance on back-up services during on-site interruptions. The \nstandardization of forecast data, modeling methodologies, and underlying assumptions \nwill be essential for comprehending the operational characteristics and grid impacts of \nspecific loads. Ultimately, the Commission should provide clear guidance on the roles \nand responsibilities of the entity or entities tasked with aggregating, validating, and \nreporting these forecasts. \n \n \n \n9 Post-technical Conference Comments of the Data Center Coalition, Docket No. AD24-11-000, pp. 9-13 \n(Dec. 9 2024)."},{"page":10,"startToken":2016,"endToken":2150,"text":"10 \n \n \nCONCLUSION \nELCON appreciates the Commission’s and PJM’s efforts to address whether \ncurrent tariff provisions provide just and reasonable terms for interconnecting and \naccounting for large loads co-located with onsite generation. The Commission has the \nopportunity to clarify jurisdictional authorities surrounding co-location arrangements, \ndevelop a cost allocation framework that supports the efficient and equitable \ndevelopment of electric generation co-location, while safeguarding the reliability of the \nelectric grid and protecting all consumer classes. However, we strongly recommend \nthat the Commission prioritize ensuring accurate forecasting for emerging load growth \nto guarantee resource adequacy and ensure sufficient infrastructure is in place to \nmaintain reliability and support economic growth. \n \nRespectfully submitted,  \n \n/s/ Karen Onaran  \n \nKaren Onaran \nPresident & CEO \nElectricity Consumers Resource Council \n700 12th Street NW, Suite 700 \nWashington, DC 20005 \nKOnaran@elcon.org  \n \n \nDated: April 23, 2025"},{"page":11,"startToken":2150,"endToken":2231,"text":"11 \n \nCERTIFICATE OF SERVICE \n \n \nPursuant to Rule 2010 of the Commission’s Rules of Practice and Procedure, 18 \nC.F.R. § 385.2010, I hereby certify on this day that I have served the foregoing document \nupon each person designated on the official service list compiled by the Secretary in the \nproceeding. \n \n \nDated the 23rd day of April 2025. \n \n \n/s/  Karen Onaran \n \n \nKaren Onaran \nPresident & CEO \nElectricity Consumers Resource Council \n700 12th Street, NW, Suite 700 \nWashington, DC 20005 \nKOnaran@elcon.org"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":2,"endAt":420,"startToken":0,"endToken":290},{"p":2,"at":420,"title":"SUMMARY","method":"printed heading","endPage":4,"endAt":1209,"startToken":290,"endToken":790},{"p":4,"at":1209,"title":"A. The Commission Should Clarify Jurisdictional Boundaries Around Co-","method":"printed heading","endPage":6,"endAt":811,"startToken":790,"endToken":1224},{"p":6,"at":811,"title":"B. Cost Allocation Policies Should Adhere to the Core Principles of “Cost","method":"printed heading","endPage":7,"endAt":1213,"startToken":1224,"endToken":1536},{"p":7,"at":1213,"title":"C. The Commission Should Give Greater Attention to Broader Load","method":"printed heading","endPage":10,"endAt":8,"startToken":1536,"endToken":2017},{"p":10,"at":8,"title":"CONCLUSION","method":"printed heading","endPage":11,"endAt":6,"startToken":2017,"endToken":2151},{"p":11,"at":6,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":11,"endAt":516,"startToken":2151,"endToken":2231}]}