{"document":{"slug":"rec-20250423-5261","title":"Response of Advanced Energy United to PJM Interconnection, L.L.C.’s Answer to the Show Cause Order","issued":"2025-04-23","accession":"20250423-5261","docket":"EL25-49-000","group":"PJM co-location compliance","filer":"Advanced Energy United","kind":"answer","file":"sources/filings/text/20250423-5261_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20250423-5261","tier":"record","sha256":"6c00247cb31a832bcb15eb4b7b9dc868e1dfdf47c7091b7b89d25e8859c4e2d3","pages":26,"tokens":7254,"emptyPages":[],"textThemes":["colo","flex","adequacy","study"]},"pages":[{"page":1,"startToken":0,"endToken":223,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \n \nPJM Interconnection, L.L.C. et al.                                             \n \n \nLarge Loads Co-Located at Generating Facilities  \n \n \nConstellation Energy Generation, LLC \nv.  \nPJM Interconnection, L.L.C. \n \n \n \n \n \nDocket Nos. EL25-49-000 \n \n \nAD24-11-000 \n \n \nEL25-20-000 \n(Consolidated) \n \n \n \n \n \nRESPONSE OF ADVANCED ENERGY UNITED \n \n \nPursuant to the Ordering Paragraph (D) of the Show Cause Order issued by the Federal \nEnergy Regulatory Commission (“Commission” or “FERC”)1 and Rule 212 of the Rules of \nPractice and Procedure of the Commission, Advanced Energy United (“United”)2 submits this \nresponse to the Answer of PJM Interconnection, L.L.C. (“PJM”)3 to the Show Cause Order.  \n \n \n \n1 PJM Interconnection, L.L.C et al 190 FERC ¶ 61,115 (2025) (“Show Cause Order”). \n2 Advanced Energy United is a national association of businesses that are making the energy we use secure, \nclean and affordable. Advanced Energy United is the only industry association in the United States that represents \nthe full range of advanced energy technologies and services, both grid-scale and distributed. Advanced energy \nincludes energy efficiency, demand response, energy storage, wind, solar, hydro, nuclear, electric vehicles, and \nmore. The comments expressed in this filing represent the position of Advanced Energy United but may not \nrepresent the views of any particular member. \n3 “Answer of PJM Interconnection, L.L.C.” FERC Docket EL25-49-000 March 23, 2025 (“PJM Answer”)."},{"page":2,"startToken":223,"endToken":499,"text":"2 \nI. \nEXECUTIVE SUMMARY \nThe issue of co-location of large load and generation represents an emerging and \nstrategically important development in the evolution of the electric grid. Data centers that hold \nimportant, sensitive data and support growing artificial intelligence capabilities run applications \nthat need large amounts of power to fuel the economy and provide national security. Advanced \nmanufacturing facilities that support economic development and onshoring of critical supply \nchains will also require access to reliable, affordable power to compete in a global economy. Co-\nlocation arrangements offer the potential for increased reliability and faster interconnection to the \ngrid, but their rapid emergence and different configurations are raising concerns about the \npotential for compromised resource adequacy, reliability, and resiliency. Commission direction \nis critical to bring clarity to this pressing issue, and the Commission has placed appropriate \nattention and urgency on co-location through the Show Cause Order and the Technical \nConference convened last November.4 United agrees with PJM that the industry needs guidance, \nand urges the Commission to act quickly to reduce regulatory uncertainty and allow large loads \nand generation to interconnect to the grid in a fast and efficient manner while avoiding cost shifts \nto other customers and preserving or even bolstering reliability.  \nThe Commission should direct PJM to take further action in its evaluation of its Tariffs, \nwhich include the Open Access Transmission Tariff (“OATT”), Operating Agreement (“OA”), \nand Reliability Assurance Agreement (“RA”). In its Answer, PJM set forth eight variations on \nco-location arrangement structure, of which only three are currently available under PJM’s \n \n4 “Large Loads Co-Located at Generating Facilities” FERC Docket No AD24-11-000, Commissioner Led \nTechnical Conference on November 1, 2024. (“Technical Conference”)"},{"page":3,"startToken":499,"endToken":781,"text":"3 \nexisting tariffs.5 PJM rescinded its guidance document, which had been issued as an “initial \nattempt to provide limited guidance after over a year’s worth of unfruitful stakeholder \ndiscussions.”6  Although PJM blames a lack of stakeholder consensus for the lack of clarity in \nthis guidance document,7 continued stakeholder discussion is likely the best approach to work \nthrough the nuanced considerations of the different co-location configurations and their \nimplications for cost allocation, planning, and resource adequacy. Commission guidance—\nproviding a roadmap and a clear timeline toward a Federal Power Act Section 205 filing from \nPJM— would focus PJM and its stakeholders around a set of solutions and ensure a clear \npathway for more co-location arrangements under PJM’s tariffs.        \nAlthough this proceeding is focused on PJM and the PJM transmission owners, the \ngrowing demand for co-location opportunities extends beyond PJM’s boundaries to all regions of \nthe United States within FERC’s jurisdiction. A one-size-fits-all solution may not result in \noptimal outcomes—each region of the country has unique reliability challenges and market \nstructures; each large customer has different load requirements, generation preferences, and \noperational flexibility; and potential co-location arrangements and technology solutions are \nevolving quickly. After initially resolving some of the key questions regarding co-location in the \nPJM region and gathering pertinent information from the Commissioner-led Technical \nConference on Meeting the Challenge of Resource Adequacy,8 FERC could issue broad guidance \nbut require each transmission provider to independently demonstrate that it addresses co-location \n \n5 Id at Exhibit A.  \n6 PJM Answer at 33.  \n7 Id. \n8 Meeting the Challenge of Resource Adequacy in Regional Transmission Organization and Independent System \nOperator Regions, Docket No. AD25-7-000 (supplemental notice of agenda issued Apr. 3, 2025)."},{"page":4,"startToken":781,"endToken":1100,"text":"4 \nof large loads and generation in a just and reasonable manner. Specifically, United urges the \nCommission to direct all jurisdictional transmission providers in FERC Order No. 1000 \ntransmission planning regions to either demonstrate that their open access transmission tariffs \nremain just and reasonable in light of the growing demand for co-location, or submit Federal \nPower Act Section 205 filings that specifically address co-location of large loads and generation. \nRegardless of how the Commission proceeds in the above-captioned dockets, it should \nmove quickly and decisively. Reducing regulatory uncertainty and allowing for flexibility in how \nco-location arrangements are treated in wholesale markets should be foremost in the \nCommission’s consideration.   \nII. \nCOLOCATION AND THE BROADER ENERGY LANDSCAPE \nIn its 2024 Long-Term Reliability Assessment, the North American Electric Reliability \nCorporation (“NERC”) found that most of the North American bulk power system faces \nmounting resource adequacy challenges over the next 10 years.9 The assessment found that \ndemand growth is higher than any point in the past two decades; specifically citing the size of \ndata centers and the speed at which they can connect to the electric grid.10 This is a serious \nchallenge for PJM and other transmission providers across the country. These new loads are \nlarge and can be built quickly. In 2023, data centers consumed 4.4% of total US electricity; this \nnumber has nearly tripled from 2014.11 Data centers can be built in 18-24 months,12 which \n \n9 NERC, 2024 Long-Term Reliability Assessment (December 2024), at 6. \n10 Id at 31.  \n11 Shehabi, A., Smith, S.J., Hubbard, A., Newkirk, A., Lei, N., Siddik, M.A.B., Holecek, B., Koomey, J., Masanet, \nE., Sartor, D. 2024. “2024 United States Data Center Energy Usage Report” Lawrence Berkeley National \nLaboratory, Berkeley, California at page 52. \n12 Stack Infrastructure, “How speed-to-market is transforming data center design and construction,” (Nov. 25, 2020), \navailable at https://www.stackinfra.com/resources/thought-leadership/how-speed-to-market-is-transforming-data-\ncenter-design-and-construction/."},{"page":5,"startToken":1100,"endToken":1382,"text":"5 \nallows limited lead time for system planners to prepare for these large additions to the market. \nBut finding solutions that allow these loads and the resources that serve them to connect quickly \nand reliably is an economic and national security imperative. Moreover, meeting the challenge \nwill unlock the opportunity to deliver grid reliability and affordability benefits that large, high-\nload factor demand can unleash.    \nEfficiently meeting the demand from new large loads while also maintaining reliability \nand affordability for existing customers requires well-functioning markets and planning \nprocesses that can fairly and cost-effectively accommodate growing demand for electricity. \nThrough recent rulemakings, the Commission has developed tools to increase integration of \nDistributed Energy Resources (“DER”),13 speed the interconnection of generation and storage to \nthe grid,14 and improve transmission planning.15 In addition, Dynamic Line Ratings (“DLR”) are \nalready being investigated by the Commission, with dozens of comments and reply comments \nfiled in support of further Commission action.16 Other alternative transmission technologies \n(“ATT”), such as advanced conductors and energy management systems, can help to enhance the \nreliability, efficiency and flexibility of the electric grid. Robust implementation and/or \nfinalization of these new rules by the Commission and transmission providers is critical to ensure \nthat reliability and national security needs are being met.  \nCo-located load is an issue in part because FERC Orders No. 2222, 2023 and 1920 are \nnot yet fully in place to bring about the needed change to optimize DER participation, \n \n13172 FERC ¶ 61,247 (2020) (FERC Order No. 2222). \n14 184 FERC ¶ 61,054 (2023) (FERC Order No. 2023). \n15 189 FERC ¶ 61,126 (2024) (FERC Order No. 1920). \n16 “Implementation of Dynamic Line Rating” FERC Docket AD22-5."},{"page":6,"startToken":1382,"endToken":1725,"text":"6 \ninterconnect generation to the wholesale electric grid at a rate fast enough to meet growing \ndemand and build out the transmission system proactively and cost-effectively to meet future \nreliability needs. As Brian George, US Federal Lead for Google, stated during the November 1, \n2024 Technical Conference, co-locating load with large generation facilities is “the result of \nmarket inadequacy.”17 Co-located load is a manifestation of a broader set of challenges that the \nCommission has already been working to address. The Commission must continue to focus on \nthe larger issues causing resource adequacy shortages across the country, including through the \nupcoming Resource Adequacy Technical Conference.18  \nNevertheless, within this broader context of ongoing regulatory reforms and rapid load \ngrowth, co-location presents an important tool to bring online new load and new generation in a \nfast and efficient way. Co-location has emerged out of a necessity for data centers and other \nlarge loads to interconnect quickly to the electric grid, offering a pathway to smooth the \nintegration of large loads into the grid by resolving the disconnect between grid planning and \ninfrastructure construction timelines (which are generally slow) and data center and advanced \nmanufacturing deployment timelines (which can be very fast). Co-location should not be used to \navoid or shift costs from the large loads to other consumers, and indeed large energy users have \nconfirmed that their interest in co-location is motivated by speed to market, not opportunities for \ncost savings.19  \n \n17 George, B (November 1, 2024) “Commissioner-led Technical Conference Regarding Large Loads Co- \nLocated at Generating Facilities” (2:32:40) https://www.ferc.gov/news-events/events/commissioner-led-\ntechnicalconference-regarding-large-loads-co-located. \n18 Meeting the Challenge of Resource Adequacy in Regional Transmission Organization and Independent System \nOperator Regions, Docket No. AD25-7-000 (supplemental notice of agenda issued Apr. 3, 2025). \n19 Post-Conference Comments of Google LLC in AD24-11, at 3 (“co-location is driven by a need to secure sufficient \nresources to ensure our timely growth, not a desire to avoid infrastructure costs.” Emphasis original.) Post-\nConference Comments of the Clean Energy Buyers Alliance in AD24-11, at 10."},{"page":7,"startToken":1725,"endToken":2012,"text":"7 \nWhile demand for co-location and the variety of co-location arrangements customers are \nseeking have increased rapidly, co-location itself is nothing new. Large energy users have been \nco-locating with generation both in front of and behind the meter for decades, deploying \ntechnologies such as solar, wind, combined heat and power, and battery storage. These resources \nprovide additional reliability and resiliency and help customers to control costs and (if \napplicable) meet sustainability goals. Customers have pursued these arrangements in many \ndifferent jurisdictions, including traditional vertically integrated utilities and competitive \ngeneration markets, and through different means, including net metering agreements and special \ncommercial or industrial tariffs. The success of these existing co-location agreements should not \nbe disrupted and can be viewed as a starting point for further innovation. Competitive markets \nare helping to bring new products and services as well. As Marjorie Phillips of LS Power stated \nduring the Technical Conference, “let markets work…[they] can be very innovative.”20  \nLoad growth is an economic opportunity, but it may present a crisis if we fail to mobilize \nall available solutions to meet it. This means continuing the Commission’s ongoing efforts to \nimprove regional market and planning processes, pursuing additional reforms to meet broader \nmarket and grid needs, and simultaneously taking steps to ensure that a variety of flexible co-\nlocation arrangements are available as another viable path to accommodate new large loads. A \ncomprehensive approach that includes clear and fair rules for co-location will allow us to meet \nload growth cost-effectively, reliably, and in a manner that is fair to all customers. \n \n \n20 Phillips, M.,(November 1, 2024) “Commissioner-led Technical Conference Regarding Large Loads Co-Located \nat Generating Facilities” (2:20:22) https://www.ferc.gov/news-events/events/commissioner-led-\ntechnicalconference-regarding-large-loads-co-located"},{"page":8,"startToken":2012,"endToken":2319,"text":"8 \nIII. \nPERSPECTIVES ON CO-LOCATION ISSUES \nA. The Commission Should Act Within its Jurisdiction to Facilitate Fair Co-\nLocation Options While Preserving State Jurisdiction Over Retail Issues \nAs FERC recognized in its Show Cause Order, there is a shared responsibility between \nstates and the Commission with respect to service to co-located load and generation. While \nFERC, PJM, or another RTO/ISO cannot infringe on a states’ ability to regulate retail sales of \nenergy and distribution services to retail load, the Federal Power Act does grant FERC \njurisdiction over transmission service and wholesale energy sales in interstate commerce.21 This \njurisdiction gives FERC and PJM an important role in the co-location of large loads and \ngeneration.   \nStates, along with RTOs/ISOs, are grappling with the issues of increasing demand and \nretirement of existing generation without new resources replacing them fast enough. Solutions to \nthese issues must be weighed against state policies and goals pertaining to economic \ndevelopment, generation mix, energy affordability, and other priorities. Some states have opened \nproceedings, developed special tariffs, or are taking other steps to address issues related to the \nrapid rise in large load additions.22 These developments at the state level are emergent, and are \nsubject to change at the discretion of the relevant state regulatory authorities. \nGiven the evolving nature of this issue and the fact that each state has a different \nregulatory structure and faces different issues and circumstances, there must be flexibility in any \ntariff changes put forward by PJM to accommodate states’ different and evolving regulatory \nframeworks with respect to large loads. In its Answer, PJM observes that not all co-location \n \n21 16 U.S.C. §§ 824(a)-(c).   \n22 See, e.g., Utility Commission of Nevada, Docket No. 24-05022, Order Approving Stipulation (March 11, 2025); ” \nIndiana Utility Regulatory Commission, Cause No. 46097, Order of the Commission, Settlement Agreement."},{"page":9,"startToken":2319,"endToken":2636,"text":"9 \noptions outlined as potential solutions will be available in all states.23 State regulatory structures \nand state laws may prevent or encourage any of the arrangements that are listed in PJM’s \nAnswer; this will differ across the PJM footprint and may change over time. PJM’s observation \nthat not all options will be available in all states does not warrant excluding any of the options—\nin fact, it argues for broad availability of options in PJM’s tariff so that states in the PJM region \ncan decide whether changes to state law are needed to either expand or constrain access to co-\nlocation options, according to state-specific circumstances and policy goals. This is consistent \nwith long-standing Commission precedent, whereby broadly applicable rules are crafted with \nsufficient flexibility to accommodate state differences.24 The more flexibility granted within \nPJM’s tariff to facilitate different kinds of co-location arrangements, the more discretion states \nwill have to determine how to best address co-location within their jurisdiction, including \nwhether to pursue changes to their laws and policies in light of co-location arrangements made \npossible under PJM’s tariff.  \nThe Commission and PJM should also keep in mind that states play a pivotal role in who \npays for transmission costs, as they are responsible for the allocation of costs at the retail level. \nThus, while the Commission and PJM have the authority to determine wholesale costs that \nwould be allocated to load serving entities, states still have authority to determine how the costs \nare distributed among customer classes, and some states have already taken action to adjust the \nallocation of transmission costs in response to the influx of large loads.25   \n \n23 PJM Answer at 29. \n24 172 FERC ¶ 61,041 at P 36, Order No. 1920-A at P 275, 345, 352, Order No. 2222 at P 18. \n25 See Indiana Utility Regulatory Commission, Cause No. 46097, Order of the Commission, Settlement Agreement \nAttachment A."},{"page":10,"startToken":2636,"endToken":2898,"text":"10 \nAny co-location scenario inherently involves a sharing of jurisdictional responsibility, \nand any tariff or rule changes resulting from this proceeding must reflect the authority that is \ngranted to the different regulatory bodies. Codifying a range of co-location options in PJM’s \ntariffs will give states flexibility within their jurisdictional purview to encourage, constrain, or \ndisallow different co-location options according to their priorities and circumstances.     \nB. PJM Tariffs Regarding Co-Location Agreements Do Not Provide Sufficient \nClarity and Consistency \nPJM states that its tariffs are just and reasonable26 while also acknowledging that \nclarifications and enhancements could be made to accommodate additional co-location \nconfigurations.27 PJM also recognizes that only three of the co-location eight scenarios it \ndescribes in its Answer are available under the current tariffs.28 PJM’s tariffs must be both clear \nand flexible to allow for a variety of fair and effective co-location solutions to emerge and \nevolve. Large loads looking to interconnect to PJM must have regulatory certainty that the \nproverbial rug will not be pulled out from under them after investing in a co-location \narrangement. Clear tariff provisions are the basis for such regulatory certainty and will invite \ninnovative solutions that bring about economic development while supporting reliability and fair \nand affordable rates for all customers. \nAs discussed further below, each of the eight co-location scenarios described in PJM’s \nanswer may prove viable for certain customers, depending on their capabilities and needs, and all \neight should be accommodated. PJM and the Commission must also keep an open mind to \n \n26 PJM Answer at 32. \n27 Id. \n28 Id. at 5"},{"page":11,"startToken":2898,"endToken":3163,"text":"11 \npossibilities that may be unavailable in the current environment but could bring reliability and \neconomic benefits in the future, and work to ensure sufficient flexibility within the available co-\nlocation options to accommodate variations among customers and over time. Lack of clarity and \nflexibility in PJM’s Tariffs should not be the reason that new and innovative projects are not \ninterconnected to the system.    \n1. \nAll Eight Co-location Options Should be Accommodated, but \nRequire Additional Development \nPJM lays out eight potential co-location options, of which three are currently accounted \nfor in its tariffs and five are not. It is important to recognize and preserve the three existing \nconfigurations, but these scenarios fail to address the new kinds of co-location arrangements that \nlarge loads and generators are interested in pursuing (indeed, PJM freely admits that Option 1 is \nnot an example of co-location at all). The five new arrangements may all be of interest to certain \ncustomers depending on their specific needs and capabilities, but they lack detail. Further \ndevelopment of these options, consideration of variants, and evaluation of additional options \nthrough an expedient but iterative stakeholder process is necessary to provide regulatory \ncertainty and proactively address the variety of co-location arrangements that will likely come \nbefore PJM and the Commission. PJM and the Commission should also clarify that the options \nare not mutually exclusive, and that combinations or variations of the eight listed options may be \nallowable.  \nOption 1 describes an arrangement in which the load and the generator are treated \nentirely separately—they may share a contractual arrangement and a physical location, but do"},{"page":12,"startToken":3163,"endToken":3449,"text":"12 \nnot share a Point of Interconnection (“POI”).29 The generator and load may or may not be \ngeographically proximate, and from PJM’s perspective, there is no “co-location.” Option 2, \nsimilarly, is a regular network load contracted with a generator that is behind the same POI, but \nseparately metered.30 These are both routine arrangements that have a limited impact on PJM’s \nsystem, but they ignore the drivers leading new large loads to seek out co-location agreements. \nWhile these options should not be removed, they also do not resolve the need for clarity \nregarding co-location.   \nOption 3 reflects Behind-the-Meter Generation (“BTMG”) primarily serving the load \nrather than participating in PJM markets as a Capacity Resource.31 Existing options to pursue \nBTMG are critical to preserve. These arrangements have provided reliability benefits to the \nsystem and to the host load. However, this type of generation, for the most part, has not scaled up \nto accommodate large loads interconnecting to the system, and as PJM notes, there is a cap on \nBTMG opportunities with just 700 MW remaining32—a tiny quantity relative to the demand of \nnew large loads in the PJM region. Given the amount of innovation in new BTMG technologies, \nthis option has potential to enhance grid reliability while lowering costs for end use customers, \nbut it does not address demand for co-location opportunities for new large loads.  \nThe three existing co-location options allowed under PJM’s current tariff therefore fail to \nanticipate the different co-location arrangements that are likely to be pursued in the PJM region. \nThe availability of these existing options does not address “with sufficient clarity or consistency \n \n29 Id., at 9-10. \n30 Id., at 10-11. \n31 Id., at 11-12. \n32 Id., at 5."},{"page":13,"startToken":3449,"endToken":3754,"text":"13 \nthe rates, terms, and conditions of service that apply to co-location arrangements.”33 The new \noptions that PJM presents in its Answer but that are not yet accommodated in its tariff would go \na long way toward providing regulatory certainty for new large loads and generation pursing co-\nlocation arrangements. Developing these options proactively and generically—but with sufficient \nflexibility to accommodate individual circumstances and evolution of co-location \nopportunities—before more individual requests come before PJM and the Commission would \nnot only provide clarity for large loads and generation, but also allow the Commission to resolve \ncost allocation, resource adequacy, and planning implications to ensure that co-location does not \npose a threat to the grid or shift costs to other customers. Each of the remaining five options has \nits merits, but they all require additional development. \nOption 4 offers co-located load the opportunity to be served fully by a co-located \nresource and avoid consuming energy from the grid by using system protection facilities to \nprevent such delivery in the case that the co-located generation experiences an outage.34 \nSimilarly, Option 5 allows such a configuration, but gives the co-located load the option to \nreceive back-up service from PJM if authorized in advance.35 Both options may be viable for \nsome customers and should be accommodated in PJM’s tariff. For example, a large data center \nthat brings its own backup generation or storage resource in addition to the co-located load may \nbe willing to tolerate the risk of a generator outage without use of grid delivered energy as its \n“backup” supply. Specifically, some large loads, including many data centers, place such a high \npremium on reliability that they already invest in their own backup on-site generation that is not \n \n33 Show Cause Order at P 2. \n34 PJM Answer at 13-14. \n35 Id., at 14-15."},{"page":14,"startToken":3754,"endToken":4072,"text":"14 \nproducing power unless the grid—or in this case, the co-located generator—experiences an \noutage. This backup power can be configured to provide “uninterruptible power supply” to avoid \nany lag time between a grid outage and availability of the backup power supply.36 This capability \nmakes Options 4 and 5 possible for large loads, which otherwise may not tolerate the risk of a \ngenerator outage, and also reduces the operational risks cited by PJM. Because a load customer \nselecting Options 4 or 5 is not relying on the system in the same way as a traditional network \nload, it is appropriate that PJM recognizes that such customers should not be assigned full \nnetwork transmission charges or ancillary services and should instead be part of a new rate \ndesign. This rate design must be carefully discussed by stakeholders and designed with flexibility \nto accommodate different co-location arrangements and to allow large load customers that want \nadditional services to have the option to take some services from PJM. Consideration of these \noptions should also consider FERC jurisdiction over wholesale energy, and fairness to existing \ncustomers that have paid for the interconnecting transmission grid.    \nOption 6 lays out the opportunity for co-located loads to “Bring Your Own Generation” \n(“BYOG”), which PJM says could be either new or existing generation, and could be either \nphysically co-located or have only a contractual connection to the load.37 The opportunity for \nlarge loads to bring their own new generation to the system is particularly promising as it would \ndirectly address the root causes of co-location while effectively zeroing out the new load’s \nimpact on resource adequacy. This is especially helpful in regions like PJM that are facing \nresource adequacy issues and capacity shortfalls. It is promising that PJM expresses a \n \n36 AI Data Centers Need Huge Power-Backup Systems (July 30, 2024), available at \nhttps://www.eetimes.com/unintended-consequences-ai-data-centers-need-huge-power-backup-systems/.  \n37 PJM Answer at 16-17."},{"page":15,"startToken":4072,"endToken":4376,"text":"15 \nwillingness to accelerate interconnection for new co-located generation under this option38 but, \nas discussed further below, pathways to do so must be further defined, and much more detail is \nneeded to consider and implement this solution. While PJM is open to exploring expedited \ngenerator interconnection under Option 6, it does not appear that this option contemplates \nopportunities to accelerate load interconnection, as PJM states that transmission system upgrades \nwould employ the currently applicable Attachment M-3 Process.39  \nPJM’s Option 6 does not address the different variants of BYOG, which would have \ndifferent system impact and cost allocation implications. For example, whether the generation is \nnew or existing, the choice to be physically co-located versus contractually “co-located,” and the \nnature of the physical co-location (i.e., is the load being served only by the co-located generator, \nwith protections in place to prevent delivery of system energy) would impact the customer’s net \nload obligation and the impact to the system, as well as the needed upgrades to the transmission \nsystem. As mentioned above, speed to market is key for large loads, and options to expedite \ninterconnection of both new load and new generation would benefit the customers and the \nsystem. In fact, these arrangements are already being considered in state proceedings and at the \nRTO/ISO level.40         \n \n38 Id., at 17. \n39 Id. \n40 Application of Nevada Power Company filed under Advice Letter No. 547, to implement Clean Transition Tariff \nSchedule No. CTT to allow eligible customers to receive bundled electric service from new clean energy resources.  \nUtility Commission of Nevada, Docket No. 24-05022 Order Approving Stipulation (March 11, 2025). Additionally \nthe Midcontinent Independent System Operator (“MISO”) has an open stakeholder process “Market Participation \nand Registration of Co-Located Load and Generation (behind the same POI) PAC-2024-4” \n(https://www.misoenergy.org/engage/MISO-Dashboard/market-participation-and-registration-of-co-located-load-\nand-generation-behind-the-same-poi/)."},{"page":16,"startToken":4376,"endToken":4709,"text":"16 \nUnder Option 7, the load is not backed by capacity on the PJM system during a \ntransitional period until additional capacity can be brought online, and the customer agrees to \ncurtail load during events that cause reliability shortages.41 Under this option, the load can use \non-site generation in lieu of reducing usage. While this option will likely not work for large loads \nthat are inflexible or lack backup generation, it may be attractive for those that are able to curtail \ntheir use of grid-delivered energy. For such customers, this option offers a mutually beneficial \narrangement: the customer does not contribute to the need for additional capacity, and in return \navoids capacity payments. Load flexibility can also prevent the need for costly and time-\nconsuming upgrades to the transmission system, but this does not appear to be contemplated in \nthe option, and must also be reflected in planning processes, as discussed below. A recent study \non Virginia’s data center load growth found “[f]lexibility in load is generally expected to offset \nthe need for capacity additions in a system, which could help mitigate the pressure of rapid \nresource and transmission expansion.”42 These potential iterations and/or enhancements to \nOption 7 warrant further stakeholder discussion.    \nOne possible adaptation of PJM’s Options 6 and 7 is brought up in the Response of \nEnchanted Rock, LLC in this proceeding. This variation lies between full isolation from the grid \nand full integration with the system. Enchanted Rock’s variation co-locates load with \ndispatchable generation to allow for load flexibility and use of as-available transmission service \nuntil necessary transmission upgrades make it possible for the load to fully integrate into the \n \n41 PJM Answer at 18-19. \n42 Patel, K., K. Steinberger, A. DeBenedictis, M. Wu, J. Blair, P. Picciano, and P. Oporto, et al. 2024. Virginia Data \nCenter Study: Electric Infrastructure and Customer Rate Impact. San Francisco: Energy and Environmental \nEconomics, Inc. https:// jlarc.virginia.gov/pdfs/presentations/JLARC%20Virginia%20Data%20Center%20 \nStudy_FINAL_12-09-2024.pdf."},{"page":17,"startToken":4709,"endToken":5026,"text":"17 \nsystem.43 This would allow for faster interconnection for load that brings its own generation and \nhas the ability to be flexible. New innovations such as this demonstrate the need for further \nstakeholder discussion, and flexibility in any tariff changes.   \nOption 8 is also promising in that it recognizes and incentivizes the benefits large load \ncan bring to the grid by allowing a large load to participate in PJM’s demand response (“DR”) \nprogram, also allowing load to utilize back-up generation to serve its demand.  This incentivizes \nvaluable demand flexibility by providing a revenue stream through DR capacity payments. A \nrecent study by the Nicholas Institute for Energy, Environment & Sustainability at Duke \nUniversity found that if large loads in PJM were curtailed only 0.25% of the time, that demand \nresponse could add 13.3 GW of new load with minimal capacity investment.44 PJM suggests that \nloosening federal or state emission restrictions impacting use of back-up generation may \nfacilitate use of this option.45 However, there are ample resource types capable of serving co-\nlocated loads under this arrangement without making such changes. Finally, as with the other \noptions, it is important to consider these as alternative options and not requirements for \ninterconnecting with the system.   \nC. Transmission, Ancillary, and Other Wholesale Service Charges for Co-Location \nShould Reflect Cost Causation Principles  \nAll loads, including co-located loads, should pay for the transmission service, ancillary \nservices, and other wholesale services they use, according to cost causation principles. Co-\n \n43 “Response of Enchanted Rock, LLC” FERC Docket Nos. EL25-49, AD24-11, EL25-20, at pages 7-8.  \n44 Norris, T. H., T. Profeta, D. Patino-Echeverri, and A. Cowie-Haskell. 2025. Rethinking Load Growth: Assessing \nthe Potential for Integration of Large Flexible Loads in US Power Systems. NI R 25-01. Durham, NC: Nicholas \nInstitute for Energy, Environment & Sustainability, Duke University at page 4. \nhttps://nicholasinstitute.duke.edu/publications/rethinking-load-growth  \n45 PJM Answer at 20."},{"page":18,"startToken":5026,"endToken":5353,"text":"18 \nlocation is a solution to enable speed to market and to incentivize arrangements that bring benefit \nto both the grid and the co-located load, but should not be a pathway to avoid or shift costs. \nLikewise, because of the benefits that some co-located load arrangements bring to the system, \nloads that pursue co-location should not be charged for services they do not use.  \nIn its Answer, PJM states that it will engage with stakeholders and Transmission Owners \nto work through questions about costs imposed on the system by the co-location agreements \nlisted in its Answer.46 However, PJM appears to have predetermined that that six of the eight co-\nlocation options it defines should be considered network load and assigned full Network \nIntegration Transmission Service (“NITS”), without having explored in detail the nuances and \ndifferent approaches that might be taken under the five scenarios that are not currently available \nin its Tariff. A new and innovative co-location arrangement should not be thrown into a bucket \nwith a list of assigned charges. Instead, any rules should be flexible based on the arrangements \nand abide by the cost causation principle.47 As mentioned above, large load customers are \nexploring co-location agreements due to inefficiencies in the market, and many would prefer to \nbe network load. But if these customers are investing in a co-location arrangement that avoids or \nreduces their use of transmission and wholesale services, they should also avoid the associated \ncosts. PJM does recognize that some Options (i.e., Options 4 and 5) may avoid some network \ncharges, but does not define how a “new rate design” would be developed, nor how flexible it \n \n46 PJM Answer at 38 \n47 “FERC must ensure that rates are just and reasonable and not unduly discriminatory, which requires that costs be \nallocated to those who cause them to be incurred and who benefit from them” (Illinois Commerce Commission v. \nFERC, 576 F. 3d 470, at pages 476-477 (7th Cir.)."},{"page":19,"startToken":5353,"endToken":5621,"text":"19 \nwould be. PJM and the Commission should also confirm that the options are not all mutually \nexclusive.         \nWith respect to ancillary services, both PJM and the Transmission Owners explain that \nco-located loads utilize a range of ancillary services. PJM notes that “[t]he load and generator are \nbenefiting from ancillary services (including but not limited to black start).”48 The Transmission \nOwners argue that co-located load use of ancillary services should be treated as any other load.49 \nUltimately, when large co-located loads come online, they will use some ancillary and other \nwholesale services, and should pay for the services as any customer would. Similarly, co-located \nloads should be compensated for any ancillary services their connections provide.  \nD. Interconnection Procedures and Cost Allocation Must be Adapted and Clarified, \nEspecially to Expedite New Generation Under BYOG \nLoads and generators pursuing co-location arrangements need clarity as to how these \narrangements will be studied, and how those studies will be evaluated. There must be a level of \nuniformity and detail outlining study requirements to ensure regulatory certainty for large loads \nand new generation and storage resources seeking to serve large loads. This level of uniformity is \ncurrently lacking in PJM’s interconnection procedures and cost allocation methodology, \nparticularly with respect to some of the new options PJM has outlined that are not yet \naccommodated in its tariffs.  \n With respect to retail load integration, PJM appropriately recognizes that states have \njurisdiction over interconnection of retail loads.50 However, it is important to recognize that PJM \n \n48 PJM Answer at 42. \n49 Answer of Transmission Owners, at 13. \n50 PJM Answer at 48."},{"page":20,"startToken":5621,"endToken":5877,"text":"20 \nwill still need to play a critical role. As the regional planning authority, PJM must ensure its \nRegional Transmission Expansion Plan (“RTEP”) reliably and accurately accounts for new load \nadditions to meet NERC Transmission Planning (“TPL”) standards—especially given the MW \nscale of recent interconnection requests. To that end, PJM should work collaboratively with \nTransmission Owners and large load stakeholders via an Issue Charge/Problem Statement to \ndevelop a standardized interconnection process. This process should include clear tracking of \ninterconnection request statuses, associated financial commitments, and consistent treatment \nacross projects, as discussed further below. \nWith respect to interconnection of new generation to serve co-located load, guidance is \nneeded to develop expedited interconnection processes for new generation resources brought \nonline under the BYOG option (Option 6).51 PJM acknowledges that Tariff revisions would be \nrequired “for purposes of enhancing PJM’s existing provisional interconnection service construct \nor facilitating options to accelerate interconnection studies of new generation proposed as part of \nthis option.”52 PJM states that it ”awaits Commission guidance on New Option 6 and any \nguidance on enhancing the transparency of the necessary study process,” but argues that a \nseparate study process beyond the necessary study process or the existing interconnection queue \nis not needed. United agrees that Commission guidance is needed, but contents that a separate \nprocess may be warranted, and encourages the Commission to direct PJM to develop such tariff \nrevisions, which could take the form of a pro forma co-located interconnection process and \nagreement.  \n \n51 PJM Answer at 16. \n52 Id., at 18."},{"page":21,"startToken":5877,"endToken":6144,"text":"21 \nWithout an expedited process, customers seeking to bring new generation to serve their \nload under the BYOG option may be waiting several years to connect to the grid, defeating the \npurpose of this option. Further, keeping these projects waiting could cause cost allocation issues \nas well as reliability and resource adequacy concerns. There are also efficiencies, from both a \nstudy and a network upgrade perspective, from taking into account the intent for the new \ngeneration to serve new load when studying its impacts on the system. These efficiencies will \nsave money and time and reduce the need for grid components that are subject to supply chain \nconstraints. These efficiencies also differentiate projects interconnecting under a BYOG option \nsuch that a streamlined process to interconnect new generation under a BYOG arrangement is \nnot unduly discriminatory. \nAn expedited interconnection process to facilitate new resources brought online via the \nBYOG option must be fair, transparent, and not unduly discriminatory. The expedited process \nmust not harm projects in the standard interconnection queue, and must grant equal, \nnondiscriminatory opportunities for independently developed projects to participate. For new \ngeneration that is physically co-located with load and not exporting to the gird, the study itself \ncould be similar to the recently reformed surplus interconnection service process in PJM.53 The \nnew generation would be studied according to the intent to only serve the new load, thus \navoiding the need for new network upgrades.  \nE. PJM Should Enhance its Planning and Load Forecasting Processes to More \nConsistently, Transparently, and Accurately Plan for Large Load Additions \n \n53 Order Accepting Tariff Revisions, 190 FERC ¶ 61,083."},{"page":22,"startToken":6144,"endToken":6435,"text":"22 \nThe Commission’s upmost concern is and should remain to be the reliability of the grid \nas co-located loads come online. In its response to the Commission, PJM noted that “[a]s a \nbaseline, PJM does not believe any changes to capacity market rules are necessary to \naccommodate co-location arrangements.”54 United agrees that if co-location is pursued according \nto carefully developed, transparent, and flexible tariff provisions that account for the impact of \ndifferent co-location arrangements on the grid, co-location should have “the same implications \nfor resource adequacy as load that is not co-located.”55  \nHowever, given the pace, scale, and uncertainty of new load additions, some changes to \nPJM’s forecasting and planning processes are warranted. For example, the impact of large loads \non the transmission system should inform changes to the planning process. For example, PJM’s \nOption 7 acknowledges that some loads do not necessarily need to be studied and planned for \nfirm 24/7 continuous power, which will likely trigger transmission expansions in addition to \ngeneration additions. If there were a way to recognize the up-front value of a load’s flexibility to \ndrop from the grid in the transmission planning process and before load interconnection, loads \ncan take ‘non-firm’ interruptible service and allow grid operators to control their onsite \ndispatchable backup generators and/or batteries to manage the relatively infrequent annual peaks.  \nFurther, improving the transparency and responsiveness of the load forecasting process \nwill promote resource adequacy and reliability. Load forecasting within PJM must account for \nincreased data center load, but currently there is a lack of standardization with regard to how \nlarge loads are folded into RTO/ISO planning processes, which leads to a lack of certainty about \n \n54 PJM Answer at 57. \n55 PJM Answer at 57."},{"page":23,"startToken":6435,"endToken":6742,"text":"23 \nlarge loads that are included in the forecast. Large load customers are often seeking \ninterconnections at multiple sites; many of these will materialize (multiple requests do not mean \nrequests are speculative), but some will not. If we plan the system with the assumption that all \nload requests will show up, we will almost certainly over-build, potentially by a significant \nmargin. This over-building will add unnecessary costs for all customers. Inflated load forecasts \nmay also exaggerate concerns about imminent threats to resource adequacy and reliability that \ncould result in costly or harmful emergency solutions that ultimately prove unnecessary. \nCurrently, there is a lack of standardization across utilities in terms of how large load requests \nare incorporated into load forecasts passed to PJM. While PJM does take steps to vet the requests \nthat it receives via transmission owners as part of its load forecasting process,56 a more \nstandardized process that includes transparent mechanisms to discipline how large load additions \nshould be accounted for in load forecasts would increase the responsiveness of the planning \nprocess and thus ensure reliability for consumers. \nPJM should therefore require reasonable requirements as part of its own load forecast \nverification process that are consistent across Transmission Owners. These could include \nrequiring large loads to make reasonable financial commitments that increase by stage, along \nwith some level of site control or exclusivity. Following the November 1, 2024, technical \nconference, multiple commenters suggested how such requirements could be developed and \nadopted.57 This topic warrants further Commission guidance and discussion in the stakeholder \nprocess among PJM, transmission owners, large load customers, states, and other stakeholders. \n \n56 See comments of Stu Bressler, Nov. 1, 2024 Technical Conference in Docket No. AD24-11, Transcript at 28. \n57 Post-Conference Comments of the Clean Energy Buyers Alliance in AD24-11, at 13-15; Post-Conference \nComments of Google LLC in AD24-11, at 7-8."},{"page":24,"startToken":6742,"endToken":7027,"text":"24 \nFurther, PJM must align its internal M3 Supplemental process for load interconnections with its \nannual load forecast, which underpins regional transmission planning and resource adequacy \nneeds. This alignment would provide a level of standardization and uniformity that is currently \nlacking in the load forecasting process. It is of the utmost importance for PJM to establish clear \nprocesses at the RTO level and financial commitments tied to transmission charges to ensure \nconsistent treatment for all load requests. \nOverall, resource adequacy is a concern driven by load growth, not co-location. Co-\nlocation, if carefully managed, does not on balance undermine resource adequacy. But \nmaintaining resource adequacy requires accurately accounting for new load seeking to enter the \nsystem. \nF. Other Considerations \nMuch of the discussion regarding co-located loads is focused on the challenges and the \nneed to avoid adverse impacts, but co-location also has the potential to bring various benefits to \nthe grid. Many co-located loads can provide demand response and other services to benefit the \ntransmission system and should be compensated for those services, as contemplated by PJM’s \nOption 8. Any load that brings its own backup (as many data centers do) in addition to co-located \ngeneration brings less risk to the system. Further, loads that bring with them new generating \nresources via the BYOG option are effectively zeroing out their impact on the system, helping to \nresolve some the resource adequacy concerns and reducing necessary network upgrades. In \naddition to backup generation, behind the meter generation should be utilized, and compensated, \nto help resource adequacy and reliability. \nUltimately, not all co-location arrangements are equal and should thus not be treated as \nsuch. Any tariff changes PJM must make, while increasing standardization of the process, must"},{"page":25,"startToken":7027,"endToken":7207,"text":"25 \nalso allow for maximum flexibility to allow for new technologies. A standardized process can \nstill exist with a level of flexibility that protects reliability and resource adequacy.  \nPJM must also consider the increasing national security concerns as critical loads such as \nlarge data centers rely on reliable access to electricity. As data centers expand and grow quickly \nacross the nation, protecting the physical security and cybersecurity of the grid is a national \nsecurity imperative. As PJM addresses tariff changes to improve co-location growth and address \nreliability concerns, PJM must also continue to protect the grid and ensure national security.   \nIV. \nCONCLUSION \nFor the reasons above, Advanced Energy United respectfully requests that the \nCommission consider these comments and rule expeditiously to reduce regulatory uncertainty \nand allow large loads and new generation to enter the markets.   \nRespectfully submitted this 23rd day of April 2025. \n \n \n \n \n \n \n \n \n \n \n \n \n \n \n/s/ Mike Haugh \nCaitlin Marquis, Managing Director  \nMike Haugh, Director \nKelsey Koenig, Associate \nAdvanced Energy United  \n1801 Pennsylvania Ave. NW, Suite 410 \nWashington, D.C. 20006 \n(202) 380-1950  \ncmarquis@advancedenergyunited.org  \nmhaugh@advancedenergyunited.org  \nkkoenig@advancedenergyunited.org"},{"page":26,"startToken":7207,"endToken":7254,"text":"26 \nCERTIFICATE OF SERVICE \n \n \nThe undersigned certifies that a copy of this pleading has been served this day upon each \nperson designated on the official service list compiled by the Secretary in this proceeding. \n \nDated at Washington, DC this 23rd day of April, 2025. \n \n/s/ Mike Haugh"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":2,"endAt":3,"startToken":0,"endToken":224},{"p":2,"at":3,"title":"I. EXECUTIVE SUMMARY","method":"printed heading","endPage":4,"endAt":775,"startToken":224,"endToken":889},{"p":4,"at":775,"title":"II. COLOCATION AND THE BROADER ENERGY LANDSCAPE","method":"printed heading","endPage":8,"endAt":3,"startToken":889,"endToken":2013},{"p":8,"at":3,"title":"III. PERSPECTIVES ON CO-LOCATION ISSUES","method":"printed heading","endPage":8,"endAt":45,"startToken":2013,"endToken":2018},{"p":8,"at":45,"title":"A. The Commission Should Act Within its Jurisdiction to Facilitate Fair Co-","method":"printed heading","endPage":10,"endAt":482,"startToken":2018,"endToken":2700},{"p":10,"at":482,"title":"B. PJM Tariffs Regarding Co-Location Agreements Do Not Provide Sufficient","method":"printed heading","endPage":17,"endAt":1327,"startToken":2700,"endToken":4916},{"p":17,"at":1327,"title":"C. Transmission, Ancillary, and Other Wholesale Service Charges for Co-Location","method":"printed heading","endPage":19,"endAt":780,"startToken":4916,"endToken":5471},{"p":19,"at":780,"title":"D. Interconnection Procedures and Cost Allocation Must be Adapted and Clarified,","method":"printed heading","endPage":21,"endAt":1574,"startToken":5471,"endToken":6114},{"p":21,"at":1574,"title":"E. PJM Should Enhance its Planning and Load Forecasting Processes to More","method":"printed heading","endPage":24,"endAt":803,"startToken":6114,"endToken":6858},{"p":24,"at":803,"title":"F. Other Considerations","method":"printed heading","endPage":25,"endAt":672,"startToken":6858,"endToken":7127},{"p":25,"at":672,"title":"IV. CONCLUSION","method":"printed heading","endPage":26,"endAt":4,"startToken":7127,"endToken":7208},{"p":26,"at":4,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":26,"endAt":290,"startToken":7208,"endToken":7254}]}