{"document":{"slug":"rec-20250423-5262-3","title":"Exhibit 2 (Ming)","issued":"2025-04-23","accession":"20250423-5262","docket":"EL25-49-000","group":"PJM co-location compliance","filer":"Constellation Energy Generation, LLC","kind":"attachment","file":"sources/filings/text/20250423-5262_003.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20250423-5262","tier":"record","parent":"rec-20250423-5262","sha256":"f10dfb0e3dca875540971091b1e456fbd8cbcdc3976d834f5a439ac8982a0144","pages":69,"tokens":15918,"emptyPages":[],"textThemes":["colo","flex","adequacy","cost"]},"pages":[{"page":1,"startToken":0,"endToken":6,"text":"EXHIBIT 2\nTESTIMONY OF ZACHARY MING"},{"page":2,"startToken":6,"endToken":71,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \nPJM Interconnection, L.L.C., et al. \n \n \nLarge Loads Co-Located at Generating \nFacilities \n \n \nConstellation Energy Generation, LLC \n \nv. \n \nPJM Interconnection, L.L.C. \n) \n \n \n) \n) \n \n \n) \n) \n) \n) \n) \n \nDocket No. EL25-49-000 \n \n \nDocket No. AD24-11-000 \n \n \n \nDocket No. EL25-20-000 \n(Consolidated) \n \n \nTestimony of Zachary Ming \n Partner \nEnergy and Environmental Economics, Inc. (“E3”) \n \n \nOn behalf of \nConstellation Energy Generation, LLC (“Constellation”) \n \nApril 23, 2025"},{"page":3,"startToken":71,"endToken":139,"text":"2 \nTable of Contents \n1 \nIntroduction .............................................................................................. 3 \n2 \nBackground ............................................................................................... 8 \n3 \nCurrent Rate is Unjust and Unreasonable .............................................. 19 \n4 \nIdeal Rate Structures for Co-Location Configurations .......................... 24 \n4.1 \nTransmission Charges .................................................................................................... 27 \n4.2 \nAncillary Service Charges ............................................................................................... 42 \n4.3 \nEnergy Charges .............................................................................................................. 44 \n4.4 \nCapacity Charges ........................................................................................................... 45 \n4.5 \nNon-PJM Charges .......................................................................................................... 48 \n4.6 \nSummary ........................................................................................................................ 48 \n5 \nAssessment of PJM Proposed Rate Options .......................................... 52 \n6 \nRecommendations & Summary .............................................................. 66"},{"page":4,"startToken":139,"endToken":339,"text":"3 \nConstellation \n1 \n \n2 \nTransmission Tariffs for Co-Located Load \n3 \n \n4 \n \n5 \nTestimony of Zachary Ming, Partner, Energy and Environmental Economics, Inc. \n6 \n(“E3”) \n7 \n1 Introduction \n8 \nQ1. \nPLEASE STATE YOUR NAME, OCCUPATION, AND BUSINESS \n9 \nADDRESS. \n10 \nA1. \nMy name is Zachary Ming. My current position is Partner at Energy and \n11 \nEnvironmental Economics (“E3”). My business address is 44 Montgomery Street \n12 \nSuite 1500, San Francisco, California 94104. \n13 \nQ2. \nPLEASE STATE ON WHOSE BEHALF YOU ARE FILING TESTIMONY. \n14 \nA2. \nI am filing this testimony as an independent expert, and it represents my own \n15 \npositions and perspectives. Constellation compensated for my testimony, but my \n16 \ncompensation did not depend on my conclusions. \n17 \nQ3. \nPLEASE DESCRIBE YOUR PROFESSIONAL BACKGROUND AND \n18 \nEXPERIENCE. \n19 \nA3. \nI received a B.S. in Civil and Environmental Engineering (Atmosphere and Energy \n20 \nprogram) with a Minor in Economics, and an M.S. in Management Science and \n21 \nEngineering (Energy track), both from Stanford University. For over a decade I \n22 \nhave held various roles at E3, an energy consulting firm specializing in the \n23 \neconomics of the electricity system where I am currently a Partner. In addition to \n24"},{"page":5,"startToken":339,"endToken":617,"text":"4 \nfull-time consulting work at E3, I teach a graduate-level course at Stanford \n1 \nUniversity titled Electricity Economics. \n2 \nQ4. \nPLEASE DESCRIBE YOUR QUALIFICATIONS AS IT RELATES TO THE \n3 \nTOPIC OF TRANSMISSION TARIFF DESIGN FOR CO-LOCATED \n4 \nLOADS. \n5 \nA4. \nIn my role as Partner, I oversee E3 projects across a number of areas including rate \n6 \ndesign, system planning, marginal/avoided cost analysis, and resource adequacy. I \n7 \nhave authored several reports related to system planning that evaluate the role that \n8 \ngeneration and transmission serve in reliably and cost-effectively meeting long-\n9 \nterm system needs, including Long-Run Resource Adequacy under Deep \n10 \nDecarbonization Pathways for California1 and Net-Zero New England: Ensuring \n11 \nElectric Reliability in a Low-Carbon Future.2 I have also developed the methods \n12 \nthat are used in both California and across the industry to quantify the transmission \n13 \nbenefits of co-locating generation and load.3 I have worked with utilities to develop \n14 \nrate designs that accurately reflect the costs of the customers being served, \n15 \nincluding for large loads in Nova Scotia and Alberta. I have testified before utility \n16 \nCommissions in South Carolina on the topic of rate design4 and New Brunswick on \n17 \nthe topic of cost allocation.5 Most broadly, I lead an E3 team to support clients to \n18 \n \n1 https://www.ethree.com/wp-content/uploads/2019/06/E3_Long_Run_Resource_Adequacy_CA_Deep-\nDecarbonization_Final.pdf. \n2 https://www.ethree.com/wp-content/uploads/2020/11/E3-EFI_Report-New-England-Reliability-Under-\nDeep-Decarbonization_Full-Report_November_2020.pdf. \n3 https://www.ethree.com/wp-content/uploads/2025/02/2024-ACC-Documentation-v1b_clean.pdf. \n4 Docket Nos. 2023-15-E, 2023-16-E, and 2023-17-E. \n5 Matter No. 554."},{"page":6,"startToken":617,"endToken":832,"text":"5 \nunderstand the current challenges facing the electricity system and to implement \n1 \nsolutions that are economic and reliable. \n2 \nQ5. \nHAVE YOU PREVIOUSLY TESTIFIED BEFORE THE FEDERAL \n3 \nENERGY REGULATORY COMMISSION (“FERC”)? \n4 \nA5. \nYes, I have testified multiple times before FERC. My previous testimony has \n5 \ncovered various topics related to rate design and wholesale markets in PJM, \n6 \nincluding the capacity market price cap,6 the participation of reliability must run \n7 \n(“RMR”) units in the capacity market,7 and PJM’s filing to use marginal effective \n8 \nload carrying capability (“ELCC”) as the basis for resource accreditation in the \n9 \ncapacity market.8 I have also testified to FERC on behalf of MISO in their proposal \n10 \nto implement the direct loss of load (“DLOL”) methodology for resource \n11 \naccreditation.9 Additionally, I have testified before state and provincial public \n12 \nutility commissions in Oregon, Texas, South Carolina, Colorado, and New \n13 \nBrunswick on topics relating to reliability, resource adequacy, market design, and \n14 \nrate design.  \n15 \nQ6. \nPLEASE PROVIDE A SUMMARY OF YOUR TESTIMONY. \n16 \nA6. \nMy testimony demonstrates that there are three fundamental configurations of co-\n17 \nlocated load, each with different transmission system impacts and costs: \n18 \n \n6 Docket EL25-46-000. \n7 Docket EL24-148. \n8 Docket ER24-99-000. \n9 Docket ER24-1638."},{"page":7,"startToken":832,"endToken":1091,"text":"6 \n• Firm: can take service from co-located generation but has the firm right to \n1 \ndraw from the grid when the co-located generation is not available \n2 \n• Generator-contingent: can take service from co-located generation when \n3 \nit is available but has no right to draw from the grid when co-located \n4 \ngeneration is not available \n5 \n• Interruptible: can be interrupted by PJM, regardless of whether the co-\n6 \nlocated generator is online and available \n7 \n \n8 \nProviding a rate design for each configuration that aligns with the impacts \n9 \nand costs that it imposes on the transmission system is necessary to align with the \n10 \nrate design principles of 1) fair apportionment of costs and 2) economic efficiency. \n11 \nBecause the current PJM tariff does not provide a clear mechanism for customers \n12 \nto take service in any of these configurations, I conclude that it does not align with \n13 \nrate design principles and is therefore unjust and unreasonable.  \n14 \nUsing rate design principles and the transmission system impacts and costs, \n15 \nI outline ideal rate structures that should be applied through various tariff \n16 \ncomponents (transmission, energy, capacity, ancillary services, etc.) for each of the \n17 \nthree fundamental co-location configurations. \n18 \nPJM has proposed eight different rate design options that could potentially \n19 \nbe applied to co-located loads, including five new rate options “developed by PJM \n20 \nin response to issues raised in the various predecessor co-located load \n21 \nproceedings.”10 I demonstrate how each of these options can be generally mapped \n22 \n \n10 PJM Filing, page 5."},{"page":8,"startToken":1091,"endToken":1315,"text":"7 \nto one of the three fundamental configurations of co-located load that I outline \n1 \nabove. While the introduction of these options positively contributes to the \n2 \nconversation, I demonstrate that the ideal rates I outline better align with rate design \n3 \nprinciples for each of the three fundamental configurations of co-located load and \n4 \nI show how the PJM options can be modified to align with these ideal rates.  \n5 \nQ7. \nPLEASE PROVIDE AN OUTLINE OF YOUR TESTIMONY. \n6 \nA7. \nMy testimony is organized as follows:  \n7 \n• In Section 2, I provide the background on rate design principles, discuss drivers \n8 \nof transmission costs, and introduce and describe three distinct configurations \n9 \nfor co-located loads and their impact on transmission costs; \n10 \n• In Section 3, I describe how the current PJM tariff does not provide a clear \n11 \nmechanism or incentive for customers to interconnect in a lower cost co-\n12 \nlocation configuration, does not align with rate design principles, and is \n13 \ntherefore unjust and unreasonable; \n14 \n• In Section 4, I outline theoretically ideal rate structures for each of the three co-\n15 \nlocation configurations based on well-established ratemaking principles and \n16 \nobjectives; and \n17 \n• In Section 5, I evaluate the extent to which PJM’s eight proposed rate options \n18 \nalign with the three configurations and their corresponding ideal rate structures.  \n19"},{"page":9,"startToken":1315,"endToken":1592,"text":"8 \n2 Background \n1 \nQ8. \nPLEASE PROVIDE AN OVERVIEW OF THE CURRENT PJM OPEN-\n2 \nACCESS TRANSMISSION TARIFF (“TARIFF”). \n3 \nA8. \nThe current tariff provides rates that are assessed to loads for transmission service, \n4 \nancillary services, energy, and capacity. The primary relevant service for which \n5 \nloads take service is Network Integration Transmission Service (“NITS”). This \n6 \nprovides a mechanism for new load to interconnect to the transmission system and \n7 \npurchase system energy. Loads are charged for transmission service based on their \n8 \ncontribution to their zone’s annual peak load, with specific calculation \n9 \nmethodologies that vary by transmission owner.11 Loads are charged for ancillary \n10 \nservices based on their monthly energy, monthly contribution to the zone’s annual \n11 \npeak load, or monthly non-coincident peak demand depending on the specific \n12 \nservice. \n13 \nQ9. \nWHAT \nRATE \nDESIGN \nPRINCIPLES \nARE \nAPPROPRIATE \nTO \n14 \nCONSIDER IN THE DEVELOPMENT OF A TRANSMISSION TARIFF? \n15 \nA9. \nThe Bonbright rate design principles are well-established as the seminal standard \n16 \nfor establishing electric utility rates across North America.12 Underscoring their \n17 \nrelevance in PJM, FERC has cited these principles on numerous occasions.13 \n18 \n \n11 Common PJM Network Service Peak Load (“NSPL”) methods include 1 CP (customer load during \nsingle annual peak hour), 5 CP or 12 CP (average customer load over 5 or 12 annual peak hours). \n12 James C. Bonbright, Principles of Public Utility Rates, page 291, https://www.raponline.org/wp-\ncontent/uploads/2023/09/powellgoldstein-bonbright-principlesofpublicutilityrates-1960-10-10.pdf. \n13 For instance, Docket No. EL00-66-000 (Louisiana Public Service Commission & Council of the City of \nNew Orleans v Entergy Corp) and AD06-2-000 (Assessment of Demand Response & Advanced Metering \nReport)."},{"page":10,"startToken":1592,"endToken":1803,"text":"9 \nQ10. WHICH SPECIFIC BONBRIGHT RATE DESIGN PRINCIPLES ARE \n1 \nRELEVANT \nTO \nTHE \nISSUE \nOF \nCO-LOCATED \nLOAD \nAND \n2 \nGENERATION? \n3 \nA10. There are two rate design principles that are most relevant to the development of \n4 \ntariffs for co-located load and generation: \n5 \n• Fair apportionment of costs: this principle establishes that costs should be \n6 \nborne by the customers that cause the costs. Fair apportionment of costs \n7 \ndrives equity among customers. \n8 \n• Economic efficiency: this principle discourages wasteful infrastructure \n9 \ndevelopment and use while promoting all justified types and amounts of \n10 \nuse. Application of this principle yields an electricity system that serves \n11 \nload at minimum total cost.  \n12 \n \n13 \n \nIn addition, Bonbright also establishes that rates should be “free from \n14 \ncontroversies as to improper interpretation” and “non-discriminatory.”14 Finally, \n15 \nBonbright also establishes several other principles that are less relevant to the topic \n16 \nof co-located loads because all rate design proposals in this proceeding perform \n17 \nsimilarly.15 For example, all rate options under consideration recover the total \n18 \nrevenue requirement. \n19 \n \n14 James C. Bonbright, Principles of Public Utility Rates, page 291. \n15 Other rate design principles include recovery of the total revenue requirement, practicality, stability of \nrates and revenues, and simplicity and understandability."},{"page":11,"startToken":1803,"endToken":1972,"text":"10 \nQ11. PLEASE DISCUSS THE CONCEPTS OF “GROSS” AND “NET” BILLING. \n1 \nA11. A key issue at hand is whether co-located loads should pay for transmission service \n2 \nbased on “gross” or “net” load. A gross load construct would apply transmission \n3 \ncharges to the load-only portion of the co-located customer, while a net load \n4 \nconstruct would subtract any generation from the load before applying charges. A \n5 \nnet load construct is consistent with measuring the actual energy flowing between \n6 \nthe entire co-location configuration and the transmission system as demonstrated \n7 \nin the figure below. These concepts are discussed in more detail in later sections of \n8 \nmy testimony. \n9 \n Figure 1: Graphical Depiction of Gross and Net Load for Co-Located Loads \n10 \n  \n11 \nQ12. PLEASE \nPROVIDE \nAN \nOVERVIEW \nOF \nWHAT \nCAUSES \n12 \nTRANSMISSION COSTS. \n13 \nA12. Transmission is built to allow for delivery of generation to loads. The sizing of the \n14 \ntransmission grid is primarily determined by the need to deliver generation to loads \n15"},{"page":12,"startToken":1972,"endToken":2277,"text":"11 \nduring peak demand. In its Electric Utility Cost Allocation Manuel, the National \n1 \nAssociation of Regulatory Utility Commissioners (“NARUC”) states that \n2 \n“investment in the transmission system is generally assumed to be driven by \n3 \nincrements in system peak load.” 16 FERC has similarly acknowledged this in \n4 \nmultiple ratemaking decisions; for instance, while defending a peak load-based \n5 \ntransmission cost allocation in Docket No. EL00-66-000, FERC stated that:  \n6 \n“A utility builds its bulk power facilities, i.e., generating units and transmission \n7 \nlines, to meet the maximum or peak demand of its firm customers. Because the \n8 \nutility incurs the cost of these facilities to meet the peak demand of its firm \n9 \ncustomers, those customers should pay for the facilities. The peak responsibility \n10 \nmethod accomplishes this by allocating the cost of the facilities among the firm \n11 \ncustomers in the same proportion as each customer's demand bears to the system \n12 \npeak.”17 \n13 \nFrom this first principle, it naturally follows that the integration of new \n14 \nloads within an electricity system in a manner that does not increase peak demand \n15 \nwill result in lower transmission system costs than integration of new loads that do \n16 \nincrease peak demand. This notion is also well-supported in literature – for \n17 \nexample, a recent study authored by researchers at Duke University states that “[t]o \n18 \nthe extent a new load can temporarily reduce (i.e., curtail) its electricity \n19 \nconsumption from the grid during these peak stress periods, however, it may be \n20 \nable to connect while deferring—or even avoiding—the need for certain \n21 \nupgrades.”18 \n22 \n \n16 Page 128, https://www.pubmanitoba.ca/pdf/cos_review/exhibits/mipug-28.pdf. \n17Order page 22, Docket No. EL00-66-000. \n18 Page 5, https://nicholasinstitute.duke.edu/sites/default/files/publications/rethinking-load-growth.pdf."},{"page":13,"startToken":2277,"endToken":2510,"text":"12 \nQ13. HOW DOES THE RELATIONSHIP BETWEEN PEAK DEMAND AND \n1 \nTRANSMISSION COSTS IMPACT RATE DESIGN? \n2 \nA13. The fact that transmission costs are incurred by a need to serve peak demand is the \n3 \nbasis for demand charges, which are the industry-standard approach to recovering \n4 \ntransmission costs across the U.S. 19  Customers with higher coincident peak \n5 \ndemands20 on the transmission system cause a higher portion of total system costs \n6 \nand are therefore allocated a higher share of total system costs. In PJM, the Network \n7 \nService Peak Load metric represents a customer’s contribution to peak load of the \n8 \ntransmission system and is used to allocate transmission service charges for \n9 \ncustomers that take Network Service.21  \n10 \nThe fact that these demand charges are nearly universal in the industry to \n11 \nrecover transmission costs is a direct reflection of the relationship between \n12 \ntransmission costs and peak demand. Put differently, if the size of a customer’s load \n13 \non the transmission system during the system peak were not indicative of the costs \n14 \nthis customer caused, then there would be no basis for differentiating charges based \n15 \non the size of a customer’s peak load. \n16 \n \n19 https://pubs.naruc.org/pub.cfm?id=5378847A-2354-D714-5165-3DDAA31643D2. \n20 Coincident peak demand is defined as a customer’s demand during the system peak. \n21 https://www.pjm.com/markets-and-operations/billing-settlements-and-credit/guide-to-billing."},{"page":14,"startToken":2510,"endToken":2754,"text":"13 \nQ14. CAN THE COST ASSOCIATED WITH EXPANSION OF THE \n1 \nTRANSMISSION SYSTEM TO MEET INCREASES IN PEAK DEMAND \n2 \nBE QUANTIFIED? \n3 \nA14. Yes. The impact on transmission costs from peak load increases is quantified \n4 \nthrough marginal cost analysis. 22  These methods quantify transmission cost \n5 \nincreases ($) for a given increase in peak load (MW), resulting in a $/MW value. \n6 \nSimilarly, avoiding or deferring an increase in peak load reduces transmission \n7 \nsystem costs.  \n8 \nQ15. HOW ARE TRANSMISSION MARGINAL COST VALUES USED? \n9 \nA15. Transmission marginal cost values are used in a multitude of ways in the industry, \n10 \nincluding system planning, cost allocation, rate design, program compensation, and \n11 \nmore. 23 Another notable use of marginal costs is to quantify the benefits of \n12 \ndistributed energy resources, including energy efficiency, demand response, and \n13 \ndistributed generation. 24  These values are used to set program incentives, \n14 \ncompensation structures, and more.  \n15 \n \n22 For example, Section 20 https://www.raponline.org/wp-content/uploads/2023/09/rap-lazar-chernick-\nmarcus-lebel-electric-cost-allocation-new-era-2020-january.pdf. \n23 See summary of marginal cost allocation and pricing in Section 18 of Regulator Assistance Project’s \nElectric Cost Allocation for a New Era, https://www.raponline.org/wp-content/uploads/2023/09/rap-lazar-\nchernick-marcus-lebel-electric-cost-allocation-new-era-2020-january.pdf. \n24 Examples include California Public Utilities Commission’s Avoided Cost Calculator, \nhttps://www.cpuc.ca.gov/dercosteffectiveness and New York State Public Service Commission’s Value of \nDistributed Energy Resources, https://www.nyserda.ny.gov/All-Programs/NY-Sun/Contractors/Value-of-\nDistributed-Energy-Resources."},{"page":15,"startToken":2754,"endToken":2962,"text":"14 \nQ16. CAN EFFECTIVE RATE DESIGN ENABLE TRANSMISSION SYSTEM \n1 \nCOST REDUCTIONS? \n2 \nA16. Yes. Developing rate designs in which costs incurred by customers mirror the costs \n3 \nthat are being imposed (or avoided) on the transmission system incentivizes loads \n4 \n(and, similarly, distributed energy resources) to engage in behavior that reduces the \n5 \npeak load on the transmission system – for example by shifting load, participating \n6 \nin demand response, investing in energy efficiency, investing in distributed \n7 \ngeneration, co-locating loads and generation, and more. \n8 \nQ17. WHY IS INCENTIVIZING THIS BEHAVIOR BENEFICIAL? \n9 \nA17. Without incentivizing behavior to reduce the system peak, this beneficial behavior \n10 \nwould simply not happen. This well-established concept has encouraged \n11 \npolicymakers to implement rate structures and designs precisely to incentivize \n12 \nchanges in behavior, recognizing that without price signals, loads have no incentive \n13 \nto act in ways that reduces system costs.25 \n14 \nQ18. WHAT ARE THE IMPACTS OF REDUCING SYSTEM COSTS? \n15 \nA18. Utilities recover their total revenue requirement from customers – a well-\n16 \nestablished rate design principle. Therefore, reducing the total revenue requirement \n17 \nhas the impact of reducing total customer costs and improving affordability.  \n18 \n \n25 https://www.esig.energy/wp-content/uploads/2023/03/ESIG-Retail-Pricing-dynamic-rates-E3-wp-\n2023.pdf."},{"page":16,"startToken":2962,"endToken":3128,"text":"15 \nQ19. PLEASE DEFINE “CO-LOCATED LOAD.” \n1 \nA19. “Co-located load” refers to an electrical load that is electrically connected behind \n2 \nthe same point of interconnection as a generator, enabling it to be served directly \n3 \nby the generator without the associated energy flowing over the transmission \n4 \nsystem. An illustration of a standard load and co-located load configuration is \n5 \nprovided in the figure below. \n6 \nFigure 2: Simplified Illustration of Standard and Co-Located Load Configurations \n7 \n \n8 \nQ20. ARE THERE DIFFERENT POTENTIAL CONFIGURATIONS OF CO-\n9 \nLOCATED LOADS WITH DIFFERENT TRANSMISSION SYSTEM \n10 \nIMPACTS? \n11 \nA20. Yes. There are a range of different potential configurations for co-located loads that \n12 \nimpact the transmission system differently. Broadly speaking, these can be \n13 \norganized into three fundamental configurations of co-located load: \n14 \n• Firm: This represents a co-located load configuration that uses co-located \n15 \ngeneration when it is available but has the right to draw from the grid when \n16 \nthe co-located generation is not available. \n17"},{"page":17,"startToken":3128,"endToken":3368,"text":"16 \n• Generator-contingent: This represents a configuration where co-located \n1 \nload uses co-located generation when it is available but has no right to draw \n2 \nfrom the grid when it is not. In other words, if the co-located generator is \n3 \navailable, the co-located load cannot be interrupted. However, if the co-\n4 \nlocated generator is not available, the co-located load can be interrupted. \n5 \nTherefore, the co-located load is contingent on the availability of the \n6 \ngenerator. \n7 \n• Interruptible: This represents a configuration where co-located load can \n8 \nbe interrupted by PJM at any time, regardless of whether the co-located \n9 \ngenerator is online and available. Interruptions may be facilitated through \n10 \neither load curtailment or additional backup generation, but it must be \n11 \nenforceable and long-duration. This means that PJM must be certain that \n12 \nthe co-located load will interrupt whenever system conditions require \n13 \nwithout any limit applied to the length of the interruption.  \n14 \n \n15 \nBoth the “generator-contingent” and “interruptible” configurations can be \n16 \ndesigned such that the co-located load can draw energy from the transmission \n17 \nsystem on an as-available basis.  \n18 \nQ21. HOW DO THESE DIFFERENT POTENTIAL CONFIGURATIONS \n19 \nIMPACT TRANSMISSION SYSTEM COSTS? \n20 \nA21. The impact of a co-located load on the transmission system and corresponding costs \n21 \ndepends on its configuration. PJM acknowledges this in its statement that \n22 \n“incremental load gives rise to incremental system costs. But the extent of those \n23"},{"page":18,"startToken":3368,"endToken":3632,"text":"17 \ncosts appears to vary based on the nature of the particular co-location \n1 \narrangement.”26 For any potential co-location configuration, cost impacts to the \n2 \ntransmission system are driven by the impact on grid power flows primarily during \n3 \nthe system peak. Different configurations have different transmission system \n4 \nimpacts:  \n5 \n• Firm: Under this configuration, the transmission system must be planned \n6 \nand built to serve the co-located load, even if on-site generation is not \n7 \navailable. At the same time, it is not necessary to plan and build the \n8 \ntransmission system to serve the entirety of all co-located load, as the \n9 \nnatural diversity of loads and resources across the system make it \n10 \nimplausible that all co-located generation will be unavailable at the same \n11 \ntime (just as it is implausible that all PJM generation will be unavailable). \n12 \nUsing statistical methods that account for generator outage diversity, \n13 \nplanners can calculate the aggregate contribution toward the system peak \n14 \nand corresponding transmission system requirements for firm loads with co-\n15 \nlocated or behind-the-meter generation. \n16 \n• Generator-contingent: Under this configuration, the transmission system \n17 \ndoes not need to be sized to serve the co-located load during the peak period, \n18 \nas the load is dependent on the on-site generator for supply and is not \n19 \nentitled to be served from the grid when the generator is not available. At \n20 \nthe same time, the addition of co-located load in this configuration may \n21 \nimpact power flows that could potentially overload parts of the system, \n22 \n \n26 Page 38, PJM Filing."},{"page":19,"startToken":3632,"endToken":3845,"text":"18 \nmeaning that transmission upgrades may still be necessary to ensure the \n1 \nreliability of the system. \n2 \nHowever, if the co-located load in this configuration is added in \n3 \ncertain areas of the transmission system (such as a local generation pocket \n4 \nthat requires exporting electricity) or in conjunction with an increase in \n5 \ngeneration, there may be minimal if any required transmission system \n6 \nupgrades. In fact, these co-located loads may even reduce potential \n7 \ntransmission system overloads and future potential upgrades.27 \n8 \n• Interruptible: Under this configuration, because PJM has the ability to \n9 \ninterrupt the co-located load to ensure transmission system reliability, there \n10 \nis minimal, if any, impact to transmission system costs.28 \n11 \n \n12 \nFor any energy that is withdrawn on an “as-available” basis in the \n13 \n“generator-contingent” or “interruptible” configuration, this energy would only be \n14 \nprovided if the transmission system, as built, is capable of delivering it. This would \n15 \ntherefore not require any additional investment in transmission infrastructure. \n16 \n \n27 Page 11, \nhttps://ferc.gov/libraries/pdf.js/web/viewer.html?file=https%3A%2F%2Fferc.gov%2Fsites%2Fdefault%2Ff\niles%2F2024-10%2FCo-located%2520Load%2520Solution%2520Paper.pdf. \n28 Note that PJM would also have the ability to interrupt for issues related to resource adequacy."},{"page":20,"startToken":3845,"endToken":4111,"text":"19 \n3 Current Rate is Unjust and Unreasonable \n1 \nQ22. HOW DOES THE CURRENT PJM TRANSMISSION TARIFF APPLY TO \n2 \nCO-LOCATED LOADS? \n3 \nA22. The current tariff does not provide sufficient clarity on how co-located loads should \n4 \nbe charged for transmission service, resulting in different interpretations and \n5 \napplications of the tariff by different transmission owners within PJM. Several \n6 \ntransmission owners have interpreted the tariff as requiring all loads (co-located or \n7 \nnot) to be served under NITS, take firm service, and pay for transmission service \n8 \nbased on their full gross load, even if no electricity is being withdrawn from the \n9 \ntransmission system. For example, in its proposed revisions to its Open Access \n10 \nTransmission Tariff (“OATT”), Exelon—through Atlantic City Electric \n11 \nCompany—states that “[s]ervice to such co-located load is Network Integration \n12 \nTransmission Service (“NITS”) as defined in the PJM OATT.” 29  Other \n13 \ntransmission owners have interpreted the tariff as allowing co-located \n14 \nconfigurations. For example, PSE&G has stated that “data centers should have the \n15 \noption to select a configuration that best fits their particular circumstances and \n16 \nneeds – whether this is in front of the meter or a co-location arrangement.”30 PPL \n17 \nalso supported a co-location arrangement without requiring the co-located load to \n18 \ntake NITS service; in their proposed Interconnection Service Agreement (“ISA”) \n19 \nwith Susquehanna Nuclear, LLC, PPL states that “[t]he Co-Located Load is not \n20 \n \n29 Transmittal, page 4, Docket No. ER24-2888-000. \n30 Response of Public Service Electric and Gas Company to the Show Order Cause, page 1, EL25-49."},{"page":21,"startToken":4111,"endToken":4370,"text":"20 \nNetwork Load, and it is intended that the Co-Located Load will never consume \n1 \ncapacity and/or energy from the PJM Transmission System, including the \n2 \nInterconnected Transmission Owner’s transmission facilities.”31 Even PJM until \n3 \nrecently supported the notion that “[c]o-located must either be PJM Network Load \n4 \n(with applicable firm transmission service or not PJM Network Load (load without \n5 \napplicable firm transmission service.”32  \n6 \nQ23. IS THE TARIFF’S LACK OF CLARITY ALIGNED WITH RATE DESIGN \n7 \nPRINCIPLES? \n8 \nA23. No. One of Bonbright’s foundational rate design principles states that rates should \n9 \nbe “free from controversies as to improper interpretation.”33 The fact that different \n10 \ntransmission owners are interpreting the tariff differently is an obvious indicator of \n11 \nthe ambiguity of the existing tariff. Additionally, Bonbright states that rates should \n12 \nbe “non-discriminatory.” The fact that the possibility exists that some co-located \n13 \nloads may be charged for transmission based on their gross behind-the-meter load \n14 \nwhile others may be charged based on net withdrawal from the transmission system \n15 \npurely based on the local transmission owner’s tariff interpretation is unduly \n16 \ndiscriminatory and not aligned with this principle.  \n17 \nQ24. CONSIDERING THE AMBIGUITY PRESENT IN THE CURRENT \n18 \nTARIFF, IS THE INTERPRETATION THAT REQUIRES CO-LOCATED \n19 \nLOAD TO TAKE NITS SERVICE AND PAY TRANSMISSION CHARGES \n20 \n \n31 Susquehanna ISA Amended, page 106, Docket No. ER24-2172-000. \n32 Page 4, https://www.pjm.com/-/media/DotCom/markets-ops/rpm/rpm-auction-info/pjm-guidance-on-co-\nlocated-load.pdf. \n33 James C. Bonbright, Principles of Public Utility Rates, page 291."},{"page":22,"startToken":4370,"endToken":4624,"text":"21 \nBASED ON GROSS LOAD ALIGNED WITH PRECEDENT AND \n1 \nTREATMENT OF OTHER LOADS IN PJM? \n2 \nA24. No. Requiring all load to be served under NITS (or Point-to-Point service) and \n3 \nassessing charges based on gross load is inconsistent with treatment of other loads \n4 \nin PJM. Neither PJM nor any of its transmission owners (including the ones that \n5 \nassert above that co-located load is network load) require full NITS service for load \n6 \nserved directly by behind-the-meter generation, whose transmission charges are \n7 \ndetermined based on their net load served by the transmission system. 34 This \n8 \napplies to both non-retail and retail behind-the-meter generation. While one \n9 \nsubcategory of behind-the-meter generation, called non-retail behind-the-meter \n10 \ngeneration, is capped at 3,000 MW, 35  the amount of retail behind-the-meter \n11 \ngeneration is much larger; PJM estimates that retail behind-the-meter solar capacity \n12 \nacross its footprint in 2025 totaled more than 10,000 MW.36  \n13 \nQ25. IS A TARIFF THAT REQUIRES CO-LOCATED LOAD TO PAY NITS \n14 \nBASED ON GROSS LOAD CONSISTENT WITH THE PRINCIPLE OF \n15 \nFAIR APPORTIONMENT OF COSTS? \n16 \nA25. No. None of the configurations of co-located load (firm, generator-contingent, or \n17 \ninterruptible) impose the same costs on the transmission system as a NITS customer \n18 \nthat is directly connected to the transmission system. Charging customers that \n19 \n \n34 Appendix A: https://www.pjm.com/-/media/DotCom/documents/manuals/m14d.pdf. \n35 Id. \n36 Page 2, https://www.pjm.com/-/media/DotCom/about-pjm/newsroom/fact-sheets/distributed-energy-\nresources.pdf."},{"page":23,"startToken":4624,"endToken":4901,"text":"22 \nimpose different costs on the system in an equivalent manner is misaligned with \n1 \nthe principle of fair apportionment of costs and is inequitable.  \n2 \nQ26. IS A TARIFF THAT REQUIRES CO-LOCATED LOAD TO PAY NITS \n3 \nBASED ON GROSS LOAD CONSISTENT WITH THE PRINCIPLE OF \n4 \nECONOMIC EFFICIENCY? \n5 \nA26. No. Requiring all co-located loads to take firm NITS (or Point-to-Point service) \n6 \nbased on gross load stands in direct conflict with the principle of economic \n7 \nefficiency for two reasons. First, if all load is charged equivalently regardless of its \n8 \nimpact on the transmission system, load will have no incentive to seek \n9 \nconfigurations that could lower transmission system costs, and they therefore will \n10 \nnot. This will cause total costs to rise due to inefficient and ultimately unnecessary \n11 \ninvestments in the transmission system. Serving all load in a manner that does not \n12 \nminimize costs stands directly in conflict with the principle of economic efficiency. \n13 \nSecondly, unnecessary and inefficient costs may slow down – or even discourage \n14 \n– the interconnection of new beneficial load, which would hinder the interests of \n15 \nthe United States. Dr. Paul Stockton states “[t]hat speed advantage should constitute \n16 \na key factor in assessing the national security implications of co-location.”37 This \n17 \nwould additionally forego opportunities for these new loads to contribute to the \n18 \ncosts of the grid above and beyond the costs they are imposing on the grid, as I \n19 \ndemonstrate in the subsequent section, which would ultimately increase costs for \n20 \nother ratepayers. \n21 \n \n37 Constellation Answer, Docket Nos. EL25-49-000, et al., Exh. 1, Affidavit of Paul Stockton at 2."},{"page":24,"startToken":4901,"endToken":5137,"text":"23 \nQ27. WHAT IS YOUR OVERALL ASSESSMENT OF THE CURRENT TARIFF? \n1 \nA27. The current tariff does not provide clarity to transmission owners regarding how \n2 \nco-located loads should be treated, which does not align with the principle that rates \n3 \nshould be “free from controversies as to improper interpretation.” Additionally, the \n4 \ninterpretation of some transmission owners to require co-located load to be served \n5 \nunder NITS and charged for transmission on a gross load basis while \n6 \nsimultaneously allowing other loads to net their transmission charges using behind-\n7 \nthe-meter generation also conflicts with the principle of “non-discrimination.” \n8 \nFurthermore, failing to provide an option for loads to interconnect and use \n9 \nthe system in a lower cost co-location configuration impacts not just how costs are \n10 \nallocated between customers but how system costs are incurred. Loads without an \n11 \nincentive to interconnect and use the system in a lower cost way impose higher \n12 \ntransmission costs on the system, if they even materialize at all. Recognizing that \n13 \nproducers and consumers respond to incentives is one of the most fundamental \n14 \nprinciples of economics, and indeed the concept that the entire PJM competitive \n15 \nmarket is based on. \n16 \nThe failure of the current tariff to provide a clear, non-discriminatory, fair \n17 \nand equitable, and economically efficient rate for co-located loads that impose \n18 \nlower transmission system costs is unjust and unreasonable.  \n \n19"},{"page":25,"startToken":5137,"endToken":5352,"text":"24 \n4 Ideal Rate Structures for Co-Location Configurations \n1 \nQ28. PLEASE PROVIDE AN OVERVIEW OF A JUST AND REASONABLE \n2 \nRATE DESIGN FRAMEWORK FOR CO-LOCATED LOADS. \n3 \nA28. A just and reasonable rate design framework for co-located loads would provide \n4 \ndifferent rate options for each of the three different configurations of co-located \n5 \nload based on the cost impacts that are caused by the load: “firm,” “generator-\n6 \ncontingent,” and “interruptible.” Each rate design would adhere to the principles \n7 \nof:  \n8 \n▪ Fair apportionment of costs: rates should be designed in a manner \n9 \nsuch that co-located loads with lower impacts on the transmission \n10 \nsystem should be responsible for a lower proportion of transmission \n11 \ncosts. Notably, PJM’s statement that “whether the transmission system \n12 \nneeds to be planned to be able to serve these large loads if they are co-\n13 \nlocated and operate behind the meter of a generator will be instructive \n14 \nto the question of transmission cost allocation”38 is aligned with this \n15 \nprinciple. \n16 \n▪ Economic efficiency: rates should encourage loads to site and \n17 \nconfigure in an economically optimal manner that, all else equal, results \n18 \nin lower transmission system costs. \n19 \n \n38 Page 8, Bresler, Overview of Large Co-Located Load Issues, FERC Technical Conference, November \n2024"},{"page":26,"startToken":5352,"endToken":5571,"text":"25 \nThese rates would also be implemented in a manner that is clear in interpretation \n1 \nand non-discriminatory. \n2 \nQ29. WHY IS IT IMPORTANT TO OFFER MULTIPLE OPTIONS FOR RATE \n3 \nDESIGNS FOR CO-LOCATED SERVICE? \n4 \nA29. The existence of multiple options for co-located loads to interconnect under \n5 \ndifferent arrangements is, itself, foundational to economically efficient tariff \n6 \ndesign. Large customers seeking interconnection as co-located loads will have a \n7 \nrange of expectations and preferences for the level of reliability of service, and \n8 \nproviding multiple options enables those customers to evaluate trade-offs between \n9 \nreliability and cost. To the extent that each individual rate design is aligned with \n10 \nprinciples of fair apportionment of costs and economic efficiency, those choices \n11 \nwill also promote lowest cost outcomes for the system as a whole. This result can \n12 \nonly be achieved if co-located loads can tailor their requests for service to match \n13 \ntheir needs and values. In contrast, the current tariff, which a number of \n14 \ntransmission owners interpret as requiring all co-located customers to subscribe to \n15 \na firm service, will invariably result in some customers paying higher costs to fund \n16 \ntransmission upgrades that are not needed to provide the level of service they desire. \n17 \nThis concept is illustrated in the figure below. \n18"},{"page":27,"startToken":5571,"endToken":5661,"text":"26 \nFigure 3: Efficiency of Multiple Rate Options \n1 \n \n2 \nQ30. WHAT TARIFF COMPONENTS DO YOU CONSIDER IN THE \n3 \nDEVELOPMENT OF A JUST AND REASONABLE RATE DESIGN? \n4 \nA30. I consider multiple tariff components in the development of a just and reasonable \n5 \nrate design for each co-location configuration. Each of these components may be \n6 \nstructured differently depending on co-location configuration. I address each of the \n7 \nfollowing tariff components in a standalone subsection below. \n8 \n• Transmission \n9 \n• Ancillary services  \n10 \n• Energy \n11 \n• Capacity \n12 \n• Non-PJM charges \n13"},{"page":28,"startToken":5661,"endToken":5910,"text":"27 \n4.1 Transmission Charges \n1 \nQ31. PLEASE PROVIDE AN OVERVIEW OF HOW TRANSMISSION \n2 \nCHARGES SHOULD BE IDEALLY APPLIED TO THE THREE \n3 \nDIFFERENT CONFIGURATIONS OF CO-LOCATED LOAD. \n4 \nA31. For each of the three configurations of co-located load, I describe a transmission \n5 \ncharge that is consistent with principles of 1) fair apportionment of costs and 2) \n6 \neconomic efficiency, recognizing the impacts that each arrangement will have on \n7 \nthe system. \n8 \n• Firm: Co-located loads with firm service would be assessed charge equal \n9 \nto the greater of 1) standard NITS applied to the load’s net usage and 2) a \n10 \nstandby charge based on a customer-designated firm load subscription level. \n11 \nThe standby rate would be discounted relative to the NITS rate to reflect the \n12 \ncustomers’ reduced impact on the transmission system. These customers \n13 \nwould have the right to draw power from the transmission system up to their \n14 \nsubscribed level if co-located generation is unavailable. \n15 \n• Generator-contingent: Co-located loads with generator-contingent service \n16 \nwould be subject to a one-time system impact charge for any transmission \n17 \nupgrades identified as necessary to preserve transmission system reliability \n18 \nat the time of their interconnection. To the extent that energy is allowed to \n19 \nbe drawn from the system on an as-available basis, this would be assessed \n20 \na discounted $/MWh transmission charge. \n21 \n• Interruptible: No standby or one-time system impact charges for \n22 \ntransmission service would be applied to co-located loads that are \n23"},{"page":29,"startToken":5910,"endToken":6168,"text":"28 \ninterruptible, reflecting the fact that such loads should have no impact on \n1 \nthe transmission system design, as PJM would have the ability to curtail \n2 \nthose loads when system conditions require (even if the co-located \n3 \ngenerator is available) to manage transmission system reliability. Any \n4 \nenergy that is drawn from the system on an as-available basis would be \n5 \nassessed a discounted $/MWh transmission charge. \n6 \nQ32. PLEASE PROVIDE MORE DETAIL ON THE TRANSMISSION CHARGE \n7 \nFOR A FIRM CO-LOCATION CONFIGURATION. \n8 \nA32. Consistent with FERC precedent and non-discriminatory treatment with behind-\n9 \nthe-meter generation, the starting point for a co-located load configuration should \n10 \nbe a net billing construct that measures the actual energy flowing between the entire \n11 \nco-location configuration and the transmission system. To the extent that the entire \n12 \nconfiguration is drawing energy during the coincident peak hours, the co-located \n13 \nload should be charged for any net draw from the transmission system at full NITS \n14 \nrate, which is consistent with all NITS customers. \n15 \nHowever, there is a high likelihood that the co-located generator will be \n16 \navailable during the coincident peak hours, meaning that the co-located load is \n17 \nunlikely to be withdrawing energy during coincident peak hours. For this reason, \n18 \nconventional NITS charges based on net system energy withdrawals may not fully \n19 \ncapture the costs associated with designing the transmissions system to ensure the \n20 \nco-located load could be served (including during coincident peak load hours) even \n21 \nif the on-site generation is unavailable. \n22"},{"page":30,"startToken":6168,"endToken":6430,"text":"29 \nBecause of this, the appropriate rate for a firm co-located load customer is \n1 \na standby charge to reflect the fact that the transmission system must be built to a \n2 \ncertain extent to serve the load on a firm basis. The standby charge would be applied \n3 \nnot to any specific metered gross or net usage but rather a customer-designated firm \n4 \nload subscription level of what the customer could draw from the transmission \n5 \nsystem.  \n6 \nThe appropriate $/MW standby charge rate would be discounted relative to \n7 \nNITS to reflect the diversity of co-located generation and that most will be available \n8 \nduring the coincident peak, which means that the transmission system does not need \n9 \nto be designed assuming that all co-located generation is unavailable at the same \n10 \ntime. This concept is well-established in the industry, for example, a \n11 \nStandby/Capacity Reservation Charge Best Practices and Review prepared for the \n12 \nPennsylvania Public Utility Commission states that “standby rate design should not \n13 \nassume that all forced outages of on-site generators occur simultaneously, or at the \n14 \nsame time as the utility peak.” 39  Further, the Pennsylvania Public Utility \n15 \nCommission supports discounting standby charges relative to firm charges based \n16 \non its statement “it is reasonable and just to pro-rate distribution charges for standby \n17 \ncustomers.”40 \n18 \n \n39 Page 12, https://www.puc.pa.gov/Electric/pdf/CHPWG/Standby_Cap_Res_Best_Practices_Review-\n071618.pdf. \n40 Page 12, https://hunterstonconsulting.com/Hunterston%20Consulting%20-\n%20Where%20Things%20Stand%20on%20Standby%20Aug%202019.pdf."},{"page":31,"startToken":6430,"endToken":6717,"text":"30 \nQ33. HOW WOULD A DISCOUNT BE DETERMINED? \n1 \nA33. Such a discount should be calculated through a study conducted by PJM that \n2 \nreflects the cost of serving these customers, which is aligned with best practices for \n3 \ndeveloping standby rates.41 Other important best practices include that rate should \n4 \nbe simple and transparent and reflect the specific attributes of the co-located \n5 \ngenerator in question. This could be accomplished through discounts that are a \n6 \nfunction of the 1) type of resource, i.e. nuclear, solar, storage, etc. and 2) resource-\n7 \nspecific performance data, such as historical forced outage rates of the generation \n8 \nwith which the load is co-located. Such an approach would not be dissimilar from \n9 \nthe PJM capacity accreditation process that accredits resources based on their \n10 \ntechnology “class” combined with an individual “resource performance \n11 \nadjustment.”42 The discounts resulting from these calculations can be meaningful. \n12 \nFor example, the Pennsylvania Public Utility Commission approved a discounted \n13 \nrate of $2.50/kW relative to the utility proposed $8/kW for Duquesne Light \n14 \nCompany based on the rationale that “it is reasonable and just to pro-rate \n15 \ndistribution charges for standby customers.”43 \n16 \nQ34. IS THERE PRECEDENT IN PJM FOR SUCH DISCOUNTED STANDBY \n17 \nCHARGES RELATIVE TO FULL REQUIREMENTS SERVICE? \n18 \nA34. Yes, multiple utilities offer discounted standby service in PJM. For example, \n19 \nExelon subsidiary Delmarva Power offers a “Standby Service” applicable to \n20 \n \n41 Page 24, https://betterenergy.org/wp-content/uploads/2021/04/best-practices-for-standby-rates-for-\ncombined-heat-and-power.pdf. \n42 https://www.pjm.com/-/media/DotCom/documents/manuals/m21a.pdf. \n43 Page 12, https://hunterstonconsulting.com/Hunterston%20Consulting%20-\n%20Where%20Things%20Stand%20on%20Standby%20Aug%202019.pdf."},{"page":32,"startToken":6717,"endToken":6970,"text":"31 \ncustomers whose power is normally supplied through on-site generation. The rates \n1 \nare discounted by 20% relative to standard service.44  \n2 \nQ35. HOW WOULD THE STANDBY CHARGE INTERACT WITH THE NITS \n3 \nCHARGE APPLIED TO THE NET DRAW OF THE CO-LOCATION \n4 \nCONFIGURATION DURING THE COINCIDENT PEAK? \n5 \nA35. The transmission charges to the customer in a firm configuration should be the \n6 \ngreater of the standby charge or net load NITS charges. This ensures that firm \n7 \ncustomers that avoid net usage from the system during the coincident peak \n8 \ncontribute to the costs they impose on the system but are not charged more than \n9 \nother firm customers. This construct has the additional benefit of incentivizing \n10 \navoidance of net usage during the coincident peak through strategies such as \n11 \nperforming maintenance and nuclear refueling outside of summer months. This has \n12 \nthe impact of reducing coincident peak and transmission system costs.   \n13 \nQ36. PLEASE PROVIDE MORE DETAIL ON THE ONE-TIME SYSTEM \n14 \nIMPACT \nCHARGE \nFOR \nA \nGENERATOR-CONTINGENT \nCO-\n15 \nLOCATION CONFIGURATION. \n16 \nA36. As described in Section 2, a co-located load whose ability to use electricity is \n17 \ncontingent upon the availability of on-site generation would not impose the costs \n18 \nin the same manner as a firm load, as PJM would have no obligation to serve the \n19 \n \n44 Pdf Page 166, Rider “S”, \nhttps://www.delmarva.com/cdn/assets/v3/assets/blt47b6e332b18fb457/bltefc1a0bec7ba2be7/67ed6ee63c65\n952497e53e9c/2025-03-05_MASTER_MD_DPL_Tariff_Book_1.pdf?branch=prod_alias."},{"page":33,"startToken":6970,"endToken":7271,"text":"32 \nload from the grid. For this reason, a rate design that charges this load equivalently \n1 \nto a firm configuration is inappropriate.  \n2 \nHowever, a generator-contingent configuration may impact grid power \n3 \nflows in a way that requires transmission system upgrades as quantified through a \n4 \nstudy process (either a “necessary study” or additional studies45) that evaluates \n5 \ngeneration interconnection modification. This study process would identify any \n6 \ntransmission reinforcements or network upgrades needed to resolve reliability \n7 \nviolations due to the addition of co-located load in this configuration and quantify \n8 \nthe cost of these modifications as part of the study results. The appropriate rate \n9 \ndesign for a generator-contingent co-located load customer is a one-time system \n10 \nimpact charge based on the cost of these transmission system reinforcements and \n11 \nupgrades. \n12 \nQ37. HOW DOES YOUR PROPOSAL TO ALLOCATE A ONE-TIME SYSTEM \n13 \nIMPACT \nCHARGE \nTO \nCUSTOMERS \nUSING \nGENERATOR-\n14 \nCONTINGENT SERVICE ALIGN WITH RATE DESIGN PRINCIPLES? \n15 \nA37. The construct I describe for generator-contingent service provides a natural \n16 \nincentive for loads to co-locate with existing generators in locations where requisite \n17 \ntransmission reinforcements or network updates upgrades associated with the \n18 \ngenerator interconnection modification would be lower or perhaps non-existent at \n19 \n \n45 Pages 4-5. “The necessary studies (emphasis added) process provides PJM an opportunity to perform \nstudies to evaluate the potential reliability impact of a proposed addition or reduction of a co-located load \nconfiguration on the PJM Transmission System, and determine what, if any, system reinforcements are \nrequired prior to the addition or reduction of the planned co-located load configuration […] Transmission \nOwner may require additional studies (emphasis added) based on the planned co-located load \nconfiguration, and such studies may result in additional study costs. https://www.pjm.com/-\n/media/DotCom/markets-ops/rpm/rpm-auction-info/pjm-guidance-on-co-located-load.pdf."},{"page":34,"startToken":7271,"endToken":7549,"text":"33 \nall, much like how current interconnection charges incentivize generators to do the \n1 \nsame. Similarly, when new loads are co-located with new or increased generation, \n2 \nthe co-location of new load and generation could provide for lower system impact \n3 \ncharges if transmission reinforcements or network upgrades are minimal. Both \n4 \noutcomes adhere to the principle of economic efficiency by reducing transmission \n5 \nsystem costs through more efficient siting and by substituting lower cost generation \n6 \nfor transmission system upgrades where feasible. \n7 \nThis construct also ensures that other network loads are not allocated any \n8 \ncosts associated with the interconnection or modification of a generator, which is \n9 \nconsistent with prior FERC orders.46 Finally, this charge appropriately recognizes \n10 \nany costs due to changes to the configuration of a generator should be borne by the \n11 \ngenerator and not other ratepayers. \n12 \nQ38. HOW WOULD A SYSTEM IMPACT CHARGE BE ASSESSED IN A \n13 \nSITUATION \nWHERE \nNO \nREQUIRED \nTRANSMISSION \n14 \nREINFORCEMENTS OR NETWORK UPGRADES ARE IDENTIFIED?  \n15 \nA38. In the case where a co-located load taking generator-contingent service does not \n16 \nrequire transmission reinforcements or network upgrades, no system impact charge \n17 \nwould be assessed. There are several possible scenarios where such an outcome \n18 \nmay occur. For example, if the co-located load is interconnecting in certain areas \n19 \nof the transmission system (such as a local generation pocket that requires exporting \n20 \n \n46 For example, FERC Order 2003-B states that “This order reaffirms that an important objective of the \nCommission's pricing policy is the protection of the Transmission Provider's existing Transmission \nCustomers, including native load, from subsidizing Network Upgrades required to interconnect merchant \ngenerators.”"},{"page":35,"startToken":7549,"endToken":7764,"text":"34 \nelectricity), the co-located load may actually reduce congestion and defer or \n1 \neliminate future transmission system investments. In this case, the co-located load \n2 \nwould not be assessed a system impact charge. Another potential scenario is when \n3 \na co-located load interconnects in a part of the system that has some level of excess \n4 \ntransmission capacity that can accommodate the new load without any near-term \n5 \nadditional investment. In this case, not assigning a system impact charge is \n6 \nconsistent with how generators are charged for their use of the system on a first-\n7 \ncome, first-served basis.  \n8 \nQ39. PLEASE PROVIDE MORE DETAIL ON WHY A STANDBY CHARGE OR \n9 \nSYSTEM \nIMPACT \nCHARGE \nARE \nINAPPROPRIATE \nFOR \nAN \n10 \n“INTERRUPTIBLE” CO-LOCATION CONFIGURATION? \n11 \nA39. As described in Section 2, an interruptible co-located load does not require the \n12 \ntransmission system to be planned, built, or adapted in any way to accommodate \n13 \nthe load because PJM can interrupt the load when needed to avoid system impacts. \n14 \nTherefore, no standby or system impact charges are appropriate. To the extent that \n15 \nco-located load withdraws energy from the system on an as-available basis, a \n16 \ndiscounted $/MWh transmission charge would be applied (described more below), \n17 \nmeaning that there is no potential free-riding. \n18"},{"page":36,"startToken":7764,"endToken":8029,"text":"35 \nQ40. HOW WOULD PJM ENSURE THAT CO-LOCATED LOADS INTERRUPT \n1 \nWHEN NECESSARY AND DO NOT DRAW SYSTEM ENERGY \n2 \nWITHOUT APPROVAL? \n3 \nA40. While interruption would primarily be accomplished through the co-located load’s \n4 \nresponse to an instruction from PJM, this would ultimately be enforced through \n5 \nphysical protection schemes. In other words, the operational security of the grid \n6 \nwould not be solely premised on actions of co-located loads themselves. PJM \n7 \nmaintains the operational security of the grid today through physical protections, \n8 \nand the use of these components for a co-located load are not manifestly different \n9 \nthan at any other part of the grid. One common mechanism that system operators \n10 \nuse is a remedial action scheme, which are automatic controls to take predefined \n11 \ncorrective actions to prevent system impacts.47 To the extent that PJM incurs costs \n12 \nto install or operate the remedial action scheme, this cost should appropriately be \n13 \nborne by the co-located load.  \n14 \nQ41. ARE THE IDEAL TRANSMISSION CHARGES THAT YOU OUTLINE \n15 \nABOVE CONSISTENT WITH THE CONCEPTS OF GROSS OR NET \n16 \nBILLING? \n17 \nA41. All the rate designs that I describe above are consistent with a net billing construct \n18 \nin the sense that none of them apply transmission charges to a separately metered \n19 \nco-located gross load. Such a construct is consistent with precedent for all other \n20 \nPJM customers that are billed on a net basis. A net billing construct is necessary to \n21 \n \n47 https://www.nerc.com/pa/stand/prjct201005_2spclprtctnsstmphs2/faq_ras_definition_0604_final.pdf."},{"page":37,"startToken":8029,"endToken":8290,"text":"36 \ndifferentiate customers who impose different costs on the transmission system. For \n1 \navoidance of doubt, a gross billing construct is incapable of differentiating \n2 \ncustomers who impose different costs on the transmission system through co-\n3 \nlocation. With that said, the ideal rate designs that I outline do not simply assess \n4 \nzero charges for zero net use of the transmission system as described above.  \n5 \nQ42. EVEN THOUGH THESE IDEAL RATE STRUCTURES DO NOT RELY ON \n6 \nGROSS \nBILLING \nFOR \nTRANSMISSION \nCHARGES, \nDO \nYOU \n7 \nRECOMMEND \nTHAT \nCO-LOCATED \nLOAD \nBE \nSEPARATELY \n8 \nMETERED? \n9 \nA42. Yes. Co-located load should have separate revenue metering and telemetering for \n10 \nmultiple reasons. First, telemetering provides PJM operational visibility and \n11 \ncontrol. Second, separate revenue metering enables gross billing that may be \n12 \nappropriate for some charges. Separate metering is also consistent with rules for \n13 \nbehind-the-meter generation.48 \n14 \nQ43. DO THE CONFIGURATIONS YOU OUTLINE ALLOW THE CO-\n15 \nLOCATED LOADS TO DRAW ENERGY FROM THE TRANSMISSION \n16 \nSYSTEM? \n17 \nA43. The firm configuration allows the co-located load to draw energy from the grid on \n18 \na firm basis if the co-located generator is offline. The interruptible configuration \n19 \nallows co-located load to draw energy from the grid on an as-available basis if there \n20 \n \n48 “BTMG that is 10 MW or greater (or has been identified as requiring metering for operational security \nreasons) must have both revenue metering and telemetering for operational security purposes.” \nPage 180, Appendix A, PJM Manual 14D. https://www.pjm.com/-\n/media/DotCom/documents/manuals/m14d.pdf."},{"page":38,"startToken":8290,"endToken":8540,"text":"37 \nare no system impacts. The generator-contingent configuration can be optionally \n1 \ndesigned to allow for as-available energy purchases as well. In both cases, as-\n2 \navailable energy purchases would only be allowed to the extent such withdrawals \n3 \ndid not compromise transmission system reliability or system resource adequacy. \n4 \nAny as-available energy purchases would be assessed an additional transmission \n5 \ncharge. \n6 \nQ44. WHAT IS THE APPROPRIATE BASIS FOR TRANSMISSION CHARGES \n7 \nFOR AS-AVAILABLE ENERGY PURCHASES? \n8 \nA44. On the one hand, any use of the transmission system associated with as-available \n9 \nenergy purchases does not impose any costs on the transmission system because, \n10 \nby definition, the very ability to supply as-available energy implies that the system \n11 \nas built has available headroom to meet additional load without compromising or \n12 \nthreatening reliability. In this sense, assessing no charge would be aligned with both \n13 \ncost causation and economic efficiency principles. On the other hand, withdrawing \n14 \nenergy from the transmission system clearly reflects a “use” of the transmission \n15 \nsystem, and assessing no charge would be free-riding.  \n16 \nThe appropriate transmission charge for as-available energy purchases is \n17 \nnot to provide free service but rather to discount charges by marginal cost to reflect \n18 \nthe eliminated cost impacts on the system. Providing a discount to the firm rate is \n19 \nconsistent with ensuring that all customers using the system contribute to the \n20 \nrecovery of embedded system costs and that no customers receive a free ride.  \n21"},{"page":39,"startToken":8540,"endToken":9020,"text":"38 \nQ45. PLEASE PROVIDE AN EXAMPLE OF HOW A TRANSMISSION \n1 \nMARGINAL COST COULD BE CALCULATED IN PJM. \n2 \nA45. One well-accepted methodology for calculation transmission marginal costs is the \n3 \ndiscounted total investment method. 49  PJM’s 2024 Regional Transmission \n4 \nExpansion Plan (“RTEP”)50 and its associated 2024 Load Forecast vintage51 can be \n5 \nused as inputs into this method. 52  The 2024 RTEP report indicates that \n6 \napproximately $15.8 billion in transmission capital expenditures (net present value, \n7 \n“NPV”) are expected over the next ten years.53 While not all of these expenditures \n8 \nare driven by load growth, a reasonable assumption is that approximately 50% are \n9 \ndriven by growing loads, totaling $7.9 billion. Over this same ten-year time \n10 \nhorizon, PJM forecasts approximately 20.3 GW54 of peak demand growth (NPV).55 \n11 \nFinally, a real economic carrying cost (“RECC”) can be estimated as 6.6%, \n12 \nassuming a transmission asset lifetime of 40 years and a real weighted average cost \n13 \nof capital (“WACC”) of 6.0%.56 Dividing the long-run marginal transmission cost \n14 \n \n49 For example, see Section 20.1 https://www.raponline.org/wp-content/uploads/2023/09/rap-lazar-\nchernick-marcus-lebel-electric-cost-allocation-new-era-2020-january.pdf. \n50 https://www.pjm.com/-/media/DotCom/library/reports-notices/2024-rtep/2024-rtep-report.pdf. \n51 https://www.pjm.com/-/media/DotCom/library/reports-notices/load-forecast/2024-load-report.pdf. \n52 RTEP provides one potential methodology to estimate transmission marginal costs by estimating \nrepresentative transmission projects that are load growth-driven and using their costs to determine the \nincremental cost required to meet an additional kW of peak load. \n53 Based on sum of “Estimated Cost, Inflation Adjusted ($M)” for “Baseline” and “Supplemental” projects. \nNote that these values, sourced directly from the 2024 RTEP, are assumed to be a NPV of the transmission \ninvestment forecast. Page 341, https://www.pjm.com/-/media/DotCom/library/reports-notices/2024-\nrtep/2024-rtep-report.pdf. \n54 20.3 GW of peak demand growth is lower than the latest 2025 PJM load forecast. However, using this \nvalue is necessary for the purposes of calculating transmission marginal cost because it aligns with the \n2024 RTEP report. An RTEP that uses higher load growth projections would also likely have significantly \nhigher forecasted costs. The impact of higher load growth and higher costs would likely offset each other, \nand so the value presented in the main body reasonably represents long-run transmission marginal costs. \n55 20.3 GW represents the net present value of peak load growth. Value is calculated by discounting the \n2024-2034 forecasted annual peak load growth in PJM’s 2024 Load Forecast report using a 6.0% real \nweighted average cost of capital (“WACC”), and then summing those values.  \n56 Note that the values presented for the transmission asset lifetime (40 years) and the real WACC (6.0%) \nare both assumptions. Real economic carrying charge = 6.0% * (1 + 6.0%)^40 / ( (1+6.0%)^40 - 1 )."},{"page":40,"startToken":9020,"endToken":9321,"text":"39 \n($7.9 billion) by the long-run load growth (20.3 GW) and then multiplying by the \n1 \nRECC (6.6%) yields an estimated transmission marginal cost of $26/kW-year. A \n2 \nfull overview of this calculation is provided below. \n3 \nFigure 4: Transmission Marginal Cost Formula \n4 \n𝑇𝑟𝑎𝑛𝑠𝑚𝑖𝑠𝑠𝑖𝑜𝑛 𝑀𝑎𝑟𝑔𝑖𝑛𝑎𝑙 𝐶𝑜𝑠𝑡= 𝑁𝑃𝑉 𝑜𝑓 𝑃𝑒𝑎𝑘 𝐷𝑟𝑖𝑣𝑒𝑛 𝐼𝑛𝑣𝑒𝑠𝑡𝑚𝑒𝑛𝑡𝑠\n𝑁𝑃𝑉 𝑜𝑓 𝑃𝑒𝑎𝑘 𝐿𝑜𝑎𝑑 𝐺𝑟𝑜𝑤𝑡ℎ\n× 𝑅𝐸𝐶𝐶× 𝑃𝑒𝑎𝑘 𝐿𝑜𝑎𝑑 𝐷𝑟𝑖𝑣𝑒𝑛 𝐼𝑛𝑣𝑒𝑠𝑡𝑚𝑒𝑛𝑡𝑠 \n5 \n𝑇𝑟𝑎𝑛𝑠𝑚𝑖𝑠𝑠𝑖𝑜𝑛 𝑀𝑎𝑟𝑔𝑖𝑛𝑎𝑙 𝐶𝑜𝑠𝑡= $15,808 𝑚𝑖𝑙𝑙𝑖𝑜𝑛\n20,258 𝑀𝑊\n× 6.6% × 50% = $25.93 𝑘𝑊\n𝑦𝑟 \n6 \nThis is just one reasonable methodology to estimate the marginal cost of \n7 \ntransmission in PJM. For instance, Mr. Patterson utilizes another methodology in \n8 \nhis Affidavit, which results in a transmission marginal cost estimate of $27/kW-yr \n9 \nfor a 100 MW large load when levelized using the same RECC assumed above.57 \n10 \nThe general alignment of these two approaches demonstrates that different \n11 \nmethodologies can yield robustly similar results.58 \n12 \nQ46. HOW CAN THIS MARGINAL COST VALUE BE USED TO DEVELOP A \n13 \nTRANSMISSION \nDISCOUNT \nFOR \nAS-AVAILABLE \nENERGY \n14 \nPURCHASES?  \n15 \nA46. The marginal cost of transmission can be used as the basis to discount the firm \n16 \nNITS transmission rate. The firm NITS rate varies in PJM by transmission operator, \n17 \nwith a weighted average value across the entire RTO of approximately $63/kW-\n18 \nyr. 59  This indicates that an appropriate discount for interruptible use of the \n19 \n \n57 Constellation Answer, Docket Nos. EL25-49-000, et al., Exh. 3, Affidavit of Aaron T. Patterson at ¶ 52 \n($41 million / 100 MW * 6.6% = $27/kW-year). \n58 Id. \n59 Weighted average NITS rate calculated by dividing the 2024 transmission revenue requirement across all \nof PJM’s transmission owners ($10,990 million) by the 2024 peak load across all of PJM’s transmission \nowners (175,243 MW)."},{"page":41,"startToken":9321,"endToken":9632,"text":"40 \ntransmission system is approximately 41%.60 Importantly, applying this level of \n1 \ndiscount would result in both interruptible and firm customers contributing equally \n2 \nto the non-marginal costs of the system. In other words, both types of customers \n3 \nwould be making equivalent contributions to the fixed costs of the system. \n4 \nQ47. HOW CAN THIS DISCOUNT BE USED TO DEVELOP A SPECIFIC \n5 \nTRANSMISSION RATE FOR AS-AVAILABLE ENERGY PURCHASES? \n6 \nA47. As-available energy purchases are interruptible and can only be made with explicit \n7 \napproval from PJM if there are no anticipated system impacts due to the purchases. \n8 \nFor these purchases, the relevant “use” of the transmission system is the quantity \n9 \nof energy that is being withdrawn from it. This is different from firm customers \n10 \nwhose “use” of the system is their coincident peak demand that drives transmission \n11 \ninvestment. Therefore, the appropriate transmission rate for as-available energy \n12 \npurchases is a $/MWh transmission charge, applied to net energy withdrawals from \n13 \nthe transmission system.  \n14 \nTo calculate this charge, PJM could divide the annual transmission revenue \n15 \nrequirement ($/year) by annual system energy (MWh/year) to yield a $/MWh value. \n16 \nDiscounting this value by 41% yields a final as-available energy transmission \n17 \ncharge of approximately $8/MWh.61 \n18 \n \n60 $26/kW-yr marginal cost of transmission divided by $63/kW-yr weighted average PJM NITS rate = \n41%. \n61 PJM’s transmission revenue requirement across all transmission owners totaled $10,990 million in 2024, \nwhile the annual system-wide load totaled 813,328 GWh. This would equate to an undiscounted energy \ncharge of $13.40/MWh to cover all transmission system costs. Discounting this value by 41% yields an \nenergy charge of $7.91/MWh. https://www.pjm.com/-/media/DotCom/markets-ops/settlements/network-\nintegration-trans-service-january-2024.pdf; https://www.pjm.com/-/media/DotCom/library/reports-\nnotices/load-forecast/2024-load-report.ashx."},{"page":42,"startToken":9632,"endToken":9874,"text":"41 \nI perform this calculation not to be overly prescriptive with a specific value \n1 \nbut rather to illustrate a methodological framework for how loads that use the \n2 \nsystem but do not impose any cost on the system can fairly contribute to the \n3 \nrecovery of fixed costs of the system.  \n4 \nQ48. IS THERE PRECEDENT FOR SUCH A $/MWH TRANSMISSION \n5 \nCHARGE FOR AS-AVAILABLE ENERGY PURCHASES? \n6 \nA48. Yes. One example of such a service is the Alberta Electric System Operator \n7 \n(“AESO”) Demand Opportunity Service, which is designed to utilize surplus \n8 \ntransmission capacity.62 This service is offered on an interruptible basis, meaning \n9 \nthe AESO can recall service to ensure that system operations are not compromised. \n10 \nThis rate for this service is a $/MWh transmission charge of approximately \n11 \n$7/MWh CAD, which is calculated using a methodology similar to what I describe \n12 \nabove.63  \n13 \nQ49. WHAT \nIS \nTHE \nIMPACT \nON \nEXISTING \nRATEPAYERS \nOF \n14 \nCOLLECTING AS-AVAILABLE TRANSMISSION CHARGES FROM CO-\n15 \nLOCATED LOADS? \n16 \nA49. Collection of as-available transmission charges would directly benefit existing \n17 \nratepayers by reducing rates since as-available energy purchases by co-located \n18 \nloads would contribute to the recovery of transmission costs without requiring any \n19 \nadditional costs be incurred. This is consistent with the AESO’s assessment of the \n20 \n \n62 https://www-integ.aeso.ca/market/market-participation/demand-opportunity-service/. \n63 Pdf page 11, https://www.aeso.ca/assets/documents/ISO-Tariff-Combined-2025-04-15.pdf."},{"page":43,"startToken":9874,"endToken":10123,"text":"42 \nDemand Opportunity Service which states that “[t]he revenues from [Demand \n1 \nOpportunity Service] are applied toward lowering overall transmission costs.”64 \n2 \n4.2 Ancillary Service Charges \n3 \n \n4 \nQ50. PLEASE DESCRIBE ANCILLARY SERVICES AND THE IMPACT OF \n5 \nCO-LOCATED LOADS ON THESE SERVICES. \n6 \nA50. Ancillary services are procured by PJM to maintain reliability at all times. There \n7 \nare multiple ancillary service products including: \n8 \n• Regulation: Resources that quickly ramp up or down on a second-to-\n9 \nsecond basis to keep the grid in balance despite short-term variation in load \n10 \nand generation. The generation output may vary based on its service to co-\n11 \nlocated loads and could increase system variability in the same manner \n12 \nintermittent generation increases system variability. It may be appropriate \n13 \nto allocate co-located load a share of regulation costs. \n14 \n• Synchronized and Non-Synchronized Reserves: Resources that are held \n15 \nin standby and able to quickly ramp up in response to contingencies such as \n16 \na generator or transmission line tripping offline. The required quantity of \n17 \nthese services is often not based on load but rather by the size of the largest \n18 \ngenerator and transmission contingencies on the system. Increasing co-\n19 \nlocated loads would likely not increase the cost of these services. \n20 \n• Black Start: Resources that can start without grid power, which are \n21 \nrequired to re-start service in the event of a system-wide blackout. Today, \n22 \n \n64 https://www-integ.aeso.ca/market/market-participation/demand-opportunity-service/."},{"page":44,"startToken":10123,"endToken":10356,"text":"43 \nsome generators such as nuclear units require grid power to re-start after a \n1 \nsystem-wide blackout. However, generators in general have not been \n2 \nrequired to purchase and pay for this ancillary service and the costs have \n3 \nbeen allocated to load. An increase in co-located load would not increase \n4 \nthe requirement for black start services, but it would re-direct the output of \n5 \nnuclear units away from the network loads that are currently allocated black \n6 \nstart costs. For this reason, it may be appropriate to allocate black start costs \n7 \nto co-located loads, which I discuss more below.  \n8 \n• Reactive Supply and Voltage Control: Resources that can provide or \n9 \nabsorb reactive power to maintain voltage levels on the transmission system \n10 \nwithin acceptable limits for reliable system operation. To the extent that co-\n11 \nlocated loads produce or consume reactive power and the co-located \n12 \ngenerator is not required to maintain existing power factor requirements, \n13 \nthis may necessitate additional reactive supply to counteract this and \n14 \nmaintain stable grid voltage. \n15 \n• Day-ahead Scheduling Reserves: Resources procured in the Day-Ahead \n16 \nMarket to ensure sufficient online reserve capability is available to respond \n17 \nto forecasted system imbalances and contingencies during real-time \n18 \noperations. This service is similar to synchronized and non-synchronized \n19 \nreserves (with similar co-located load impacts), except it is procured on a \n20 \nday-ahead basis. \n21"},{"page":45,"startToken":10356,"endToken":10672,"text":"44 \nQ51. HOW SHOULD ANCILLARY SERVICES BE CHARGED TO CO-\n1 \nLOCATED LOADS? \n2 \nA51. There are reasonable arguments to support billing ancillary service costs to co-\n3 \nlocated loads on both a “net” and “gross” basis. On the one hand, there is a clearly \n4 \nestablished FERC precedent of using net demand as the basis for ancillary service \n5 \ncharges, as loads with behind-the-meter generation are charged in this manner.65 \n6 \nOn the other hand, whereas co-locating load and generation together reduces impact \n7 \nand cost on the transmission system, the same effect does not necessarily exist for \n8 \nancillary services, which represent a pool of costs allocated across all consumers of \n9 \nenergy. In this respect, billing ancillary services costs on a “gross” basis may also \n10 \nbe a sensible solution. In any case, the charges for ancillary services are likely to \n11 \nbe small relative to other cost categories such as transmission service. \n12 \n4.3 Energy Charges \n13 \nQ52. HOW SHOULD ENERGY CHARGES BE ASSESSED TO CO-LOCATED \n14 \nLOADS? \n15 \nA52. Energy charges should be assessed to co-located generators and loads based on the \n16 \nnet injection to or withdrawal from the transmission system. Note that this will yield \n17 \nthe same result as separately metering co-located load and co-located generation \n18 \neach on a gross basis.  \n19 \n \n65 See Motion for Leave to Answer and Joint Answer of Atlantic City Electric Company, Baltimore Gas \nand Electric Company, Commonwealth Edison Company, Delmarva Power & Light Company, PECO \nEnergy Company and Potomac Electric Power Company to Limited Protest of Natural Resource Defense \nCouncil, Atlantic City Elec. Co., Docket No. ER24-2888-000, Baltimore Gas and Elec. Co., Docket No. \nER24-2889-000, Commonwealth Edison Co., Docket No. ER24-2890-000, Delmarva Power & Light Co., \nDocket No. ER24-2891-000, PECO Energy Co., Docket No. ER24-2893-000, Potomac Elec. Power Co., \nDocket No. ER24-2894-000 (Sep. 27, 2024) (collectively, the “Exelon Answer”), at 6."},{"page":46,"startToken":10672,"endToken":10912,"text":"45 \n4.4 Capacity Charges \n1 \nQ53. WHAT IS THE IMPACT OF CO-LOCATED LOADS ON RESOURCE \n2 \nADEQUACY? \n3 \nA53. The resource adequacy impact of a new load is not dependent upon whether it is \n4 \nconnected directly to the transmission system or co-located, but instead upon the \n5 \ntype of arrangement under which PJM provides that load with transmission service. \n6 \nFor example: \n7 \n• If the load is connected directly to the transmission system and takes \n8 \nNITS, it increases demand for capacity which increases the capacity \n9 \nprice.  \n10 \n• If a load is co-located with a dedicated generator (for example in a \n11 \ngenerator-contingent configuration), this decreases the supply of \n12 \ncapacity (since the generator is dedicated to the load and no longer \n13 \noffering as a capacity resource) which increases the capacity price. \n14 \n \n15 \nIn both cases, increased load – either directly or indirectly – causes higher \n16 \ncapacity prices, which incentivizes more capacity to enter the market. This, in turn, \n17 \ndrives the capacity price back down into equilibrium. In fact, new capacity often \n18 \npre-emptively plans to enter the market in anticipation of higher demand (or lower \n19 \nsupply), meaning that a higher capacity price may never materialize in the first \n20 \nplace. Finally, because new capacity enters the market in response to higher prices, \n21 \nthere is no expected resource adequacy impact due to additional load, either in a \n22 \nco-located or NITS configuration. \n23"},{"page":47,"startToken":10912,"endToken":11166,"text":"46 \nIn both a separately metered or co-located configuration, the load can be \n1 \ninterruptible (either through load curtailment or backup generation) which would \n2 \neliminate its resource adequacy impact. Once again, the impact on resource \n3 \nadequacy is identical under either configuration. \n4 \nQ54. CAN A CO-LOCATED GENERATOR PARTICIPATE IN THE CAPACITY \n5 \nMARKET? \n6 \nA54. For any generator to participate in the capacity market, it is expected to provide \n7 \noutput to the grid when system conditions require and when ordered to by PJM. If \n8 \na co-located generator clears in the capacity market, this means that, at a minimum, \n9 \nit must output to the grid when needed or face performance penalties, even if that \n10 \nmeans interruption of the co-located load, either through curtailment or backup \n11 \ngeneration. 66  I agree with PJM’s statement that “no portion of a committed \n12 \nCapacity Resource (whether composed of one or multiple physical generating \n13 \nunits) may prioritize serving load that PJM is not responsible for serving.”67 \n14 \nQ55. HOW SHOULD CAPACITY CHARGES BE ASSESSED ON CO-LOCATED \n15 \nLOADS? \n16 \nA55. Capacity charges should be consistent with the configuration of the co-located load: \n17 \n• Firm: Because the load is firm with PJM obligation to serve, the entire \n18 \nsubscribed load should participate in the capacity market, similarly to any \n19 \nother load. This would assign a capacity requirement to the load based on \n20 \n \n66 Capacity resources also have a “must-offer obligation” into the day-ahead energy market. \n67 Pages 59-60, PJM Filing."},{"page":48,"startToken":11166,"endToken":11437,"text":"47 \nits coincident peak plus a reserve margin. Correspondingly, the entire co-\n1 \nlocated generator should also participate in the capacity market at a level \n2 \nequal to its accredited capacity. To the extent that the co-located load’s \n3 \ncapacity requirement and the co-located generator’s capacity accreditation \n4 \nare not exactly equal, there may be some net capacity sales or purchases.  \n5 \n• Generator-contingent: any capacity of the co-located generator \n6 \nexclusively dedicated to the co-located load would not offer into the \n7 \ncapacity market. The quantity of the co-located generator that is dedicated \n8 \nto the co-located load would be determined by a subscription designation \n9 \nmade by the co-located load. To the extent capacity of a co-located \n10 \ngenerator is exclusively dedicating its output to a co-located load, it should \n11 \nnot be able to offer that capacity into PJM’s capacity market (Reliability \n12 \nPricing Model, “RPM”) or to any other buyer. Capacity market sales from \n13 \nthe co-located generator may be made if the accredited capacity of the co-\n14 \nlocated generator exceeds the capacity dedicated to the co-located load. Co-\n15 \nlocated load would be required to curtail to the level of the designated \n16 \nsubscription, if necessary, in order to facilitate delivery of any co-located \n17 \ngenerator capacity sales to PJM or others. Because the co-located load \n18 \ncannot draw energy from the grid, no capacity charges are applied to the \n19 \nload. \n20 \n• Interruptible: the co-located load can be interrupted by PJM when system \n21 \nconditions require regardless of co-located generator availability. \n22 \nTherefore, the output of the co-located generator can be re-directed by PJM \n23"},{"page":49,"startToken":11437,"endToken":11669,"text":"48 \nfrom the co-located load to the broader system. Accordingly, no capacity \n1 \ncharges should be assessed to the co-located load, and the full accredited \n2 \ncapacity of the co-located generator should be able to participate in the \n3 \ncapacity market.  \n4 \n4.5 Non-PJM Charges \n5 \nQ56. HOW SHOULD NON-PJM CHARGES SUCH AS STATE PUBLIC \n6 \nPURPOSE PROGRAM CHARGES BE ADMINISTERED TO CO-\n7 \nLOCATED LOADS? \n8 \nA56. Non-PJM charges vary by state and local utility and may include non-bypassable \n9 \ncharges to fund energy efficiency programs, renewable programs, stranded cost \n10 \nrecovery, or more. The jurisdiction of these charges lies with the states.  \n11 \n4.6 Summary \n12 \nQ57. CAN THESE IDEAL RATE DESIGNS FOR CO-LOCATED LOADS BE \n13 \nMADE AVAILABLE ON AN INTERIM BASIS? \n14 \nA57. The ideal rate designs that I outline are consistent with rate design principles and \n15 \ncan be made available on a long-term or interim basis. To the extent that the \n16 \ncustomer desires a “firm” or “generator-contingent” configuration that requires \n17 \nsystem upgrades that are not immediately available, the “interruptible” \n18 \nconfiguration and rate design could be made available on an interim basis. PJM \n19 \nappears to agree with this position by stating that “certain studied co-located load \n20 \nconfigurations may require the construction and energization of transmission \n21 \nplanning solutions … if such solutions are not yet operational, it may be necessary \n22"},{"page":50,"startToken":11669,"endToken":11861,"text":"49 \nfor the studied co-located load to operate subject to interim operational procedures \n1 \nuntil the solutions are in service.”68 The relevant interim operational procedure is \n2 \ninterruptibility.  \n3 \nQ58. WHAT IS THE BENEFIT OF MAKING INTERRUPTIBLE SERVICE \n4 \nAVAILABLE ON AN INTERIM BASIS? \n5 \nA58. Making interruptible service available on an interim basis provides the important \n6 \nbenefit of facilitating faster interconnection for loads relative to a generator-\n7 \ncontingent or firm configuration. This is because transmission reinforcements and \n8 \nnetwork upgrades required for a generator-contingent or firm configuration can \n9 \ntake many years to plan and build. Faster interconnection in and of itself is an \n10 \nenormous efficiency enhancing improvement by allowing the opportunity for both \n11 \nthe loads themselves to benefit as well as other ratepayers through better utilization \n12 \nof the existing transmission system and collection of as-available energy \n13 \ntransmission charges.  \n14 \nQ59. PLEASE SUMMARIZE THE IDEAL RATE STRUCTURE FOR EACH \n15 \nCONFIGURATION OF CO-LOCATED LOAD IN THE TABLE BELOW. \n16 \nA59. The table below provides a summary of the ideal rate design for each potential \n17 \nconfiguration of co-located load. \n18 \n \n68 Page 7, Bresler."},{"page":51,"startToken":11861,"endToken":12127,"text":"50 \nTable 1: Summary of Ideal Rate Design for Potential Co-location Configurations  \n1 \n \nCo-location Configuration \nRate \n Component \nFirm \nGenerator-\ncontingent \nInterruptible \nTransmission \nGreater of 1) \nStandby charge at \ndiscounted NITS \nrate applied to firm \nsubscription level \nor 2) standard \nNITS applied to \nnet usage \nOne-time system \nimpact charge \nbased on studied \nnetwork upgrade \ncosts. If as \navailable energy \npurchases are \nallowed, these are \nbilled at discounted \n$/MWh charge  \nDiscounted \n$/MWh charge for \nas-available energy \npurchases \nAncillary \nServices \nCharges for all \nancillary services \nconsumed based on \nnet load (if needed \nto avoid \ndiscrimination) or \ngross load \nCharges for all \nancillary services \nconsumed based on \nnet load (if needed \nto avoid \ndiscrimination) or \ngross load \nCharges for all \nancillary services \nconsumed based on \nnet load (if needed \nto avoid \ndiscrimination) or \ngross load \nEnergy \nLMP energy \ncharges based on \nnet injection or \nwithdrawal \nLMP energy \ncharges based on \nnet injection or \nwithdrawal \nLMP energy \ncharges based on \nnet injection or \nwithdrawal \nCapacity \nCo-located load \nparticipates in \ncapacity market at \nfirm subscription \nlevel. Co-located \ngenerator \nparticipates in \ncapacity market at \naccredited capacity \nlevel \nNo charges to co-\nlocated load served \nby dedicated \nportion of \ngenerator (PJM \ndoes not procure \ncapacity for co-\nlocated load); \ncapacity market \nsales from the co-\nlocated generator \nmay be made if the \naccredited capacity \nof the co-located \ngenerator exceeds \nthe capacity of the \nco-located load \nNo charges to load \n(PJM does not \nprocure for load); \nco-located \ngenerator is not \ndedicated to co-\nlocated load and \nco-located \ngenerator can \nparticipate in \ncapacity market at \nfull accredited \ncapacity \nNon-PJM \nStates decide  \nStates decide  \nStates decide  \n \n2"},{"page":52,"startToken":12127,"endToken":12183,"text":"51 \nQ60. DO THE RATE DESIGNS YOU SUMMARIZE ABOVE FOR EACH CO-\n1 \nLOCATION \nCONFIGURATION \nALIGN \nWITH \nRATE \nDESIGN \n2 \nPRINCIPLES? \n3 \nA60. Yes, each of the rate designs above aligns with well-established Bonbright rate \n4 \ndesign principles for each co-location configuration. For this reason, each of these \n5 \nrate designs is just and reasonable. \n6"},{"page":53,"startToken":12183,"endToken":12402,"text":"52 \n5 Assessment of PJM Proposed Rate Options \n1 \nQ61. PLEASE PROVIDE AN OVERVIEW OF THE RATE DESIGN OPTIONS \n2 \nTHAT PJM HAS PUT FORWARD IN THIS PROCEEDING. \n3 \nA61. PJM has put forward eight options for service to large loads, three of which they \n4 \ndescribe as “already existing” and five of which they describe as “potential options \n5 \nthat have been proposed by others or developed by PJM in response to issues raised \n6 \nin the various predecessor co-located load proceeding.” PJM’s description for each \n7 \noption is reproduced below.69 \n8 \n• Existing Option 1: Load with a separate Point of Interconnection (POI) \n9 \nthat is Network Load (Existing NITS rules) \n10 \n• Existing Option 2: Co-located load that is at the same Point of \n11 \nInterconnection (POI) but separately metered that is Network Load \n12 \n(Existing NITS rules) \n13 \n• Existing Option 3: Existing Behind The Meter Generation (BTMG) where \n14 \nthe load is the customer \n15 \n• New Option 4: Co-located load with connection to the grid with protections \n16 \nto avoid delivery of system energy to serve the load \n17 \n• New Option 5: Co-located load with connection to grid with protections to \n18 \navoid delivery of system energy to serve the load or receive back-up service \n19 \nfrom PJM with permission \n20 \n \n69 Exhibit A, PJM Filing."},{"page":54,"startToken":12402,"endToken":12591,"text":"53 \n• New Option 6: Co-located load that elects to be Network Load and bring \n1 \nown generation (BYOG) \n2 \n• New Option 7: Co-located load that takes Interruptible Service (load \n3 \nwilling to curtail in advance of emergency procedures) \n4 \n• New Option 8: Co-located load that elects to be Network Load and that \n5 \nparticipates as Demand Response \n6 \nQ62. HOW DO THESE EIGHT OPTIONS ALIGN WITH THE THREE CO-\n7 \nLOCATION CONFIGURATIONS AND RATE DESIGN THAT YOU HAVE \n8 \nOUTLINED? \n9 \nA62. Each of these eight options generally correspond to one of the three fundamental \n10 \nconfigurations (firm, generator-contingent, interruptible), as demonstrated in the \n11 \ntable below. \n12 \nTable 2: Mapping of PJM Rate Options to E3 Fundamental Configurations \n13 \nPJM \nRate \nOption \nDescription \nFundamental \nConfiguration \n(E3 Determination) \n1 \nNITS without co-location \nFirm \n2 \nNITS with co-location \nFirm \n3 \nLoad customer with BTMG \nFirm \n4 \nCo-located load with ‘generator-contingent’ \nprotections \nGenerator-contingent \n5 \nCo-located load with ‘generator-contingent’ \nprotections + as-available energy purchase \noption \nGenerator-contingent \n6 \nNITS with co-location + BYOG \nFirm \n7 \nNITS with co-location where load is \ninterruptible \nInterruptible \n8 \nNITS with co-location where load \nparticipates as demand response \nInterruptible \n \n14"},{"page":55,"startToken":12591,"endToken":12834,"text":"54 \nQ63. DO PJM’S PROPOSED RATE DESIGNS FOR EACH OF THE EIGHT \n1 \nOPTIONS ALIGN WITH RATE DESIGN PRINCIPLES FOR EACH \n2 \nCORRESPONDING CO-LOCATION CONFIGURATION? \n3 \nA63. While PJM’s initial eight rate designs provide a promising start for developing new \n4 \nrates for co-located loads, I believe changes are needed to improve their adherence \n5 \nto the key principles of 1) fair apportionment of costs and 2) economic efficiency. \n6 \nThe reasons that each proposed design falls short of the ideal rate design for co-\n7 \nlocated load are described below; later in this section, I show how three of these \n8 \ndesigns can be modified to more fairly allocate costs and improve economic \n9 \nefficiency.  \n10 \n• Existing Option 1: NITS without co-location \n11 \nWhile this rate fairly allocates costs and is efficient for firm customers that \n12 \ndirectly connect to the transmission system, it does not provide any incentive \n13 \nfor large loads to co-locate with generators in a manner that would reduce \n14 \nsystem costs.  \n15 \nOnly offering this rate without options for different co-location \n16 \nconfigurations would drive unnecessary transmission build that could be \n17 \navoided. Such an outcome is misaligned with the principle of economic \n18 \nefficiency.  \n19 \n• Existing Option 2: NITS with co-location \n20 \nThis rate provides an option for customers to co-locate in a firm \n21 \nconfiguration, indicated through PJM’s stated affirmative obligation to serve. \n22 \nAssessing transmission charges based on “full load during coincident peak” – \n23"},{"page":56,"startToken":12834,"endToken":13108,"text":"55 \nwhich appears to refer to the gross load of the co-located customer – does not \n1 \nprovide any discount to reflect the fact that many co-located generators will be \n2 \non and available during the system peak, offsetting the co-located load and \n3 \nreducing the system cost impact of all loads in this configuration. Because a co-\n4 \nlocated customer would incur the same costs as a similar customer connected \n5 \ndirectly to the transmission system despite a lesser impact on the transmission \n6 \nsystem, this option does not fairly apportion costs.  \n7 \nAdditionally, if this were the only co-location rate option that was made \n8 \navailable (as some parties have proposed) this would provide no incentive for \n9 \nlarge loads to interconnect in a lower cost ‘generator-contingent’ or \n10 \n‘interruptible’ manner. It would therefore drive unnecessary transmission build \n11 \nthat could be avoided and/or discourage new loads from seeking to interconnect \n12 \nin PJM. Such an outcome is misaligned with the principle of economic \n13 \nefficiency.  \n14 \n• Existing Option 3: Load customer with BTMG \n15 \nThis rate is aligned with PJM precedent for billing customers based on their \n16 \nnet use of the system. There is no physical, technical, or economic reason why \n17 \na netting construct should apply differently for customers with behind-the-\n18 \nmeter generation or co-located generation. Therefore, applying this rate option \n19 \nto firm customers in a co-located configuration would be non-discriminatory.  \n20 \nCustomers in this configuration would still represent firm loads, as \n21 \nevidenced by PJM’s stated affirmative obligation to serve, so the system must \n22 \nbe planned and built accordingly. While the aggregate BTMG reduces \n23"},{"page":57,"startToken":13108,"endToken":13377,"text":"56 \ntransmission system costs since some of it will be on and available during the \n1 \nsystem peak, some discount relative to gross billing is appropriate. However, a \n2 \n“net withdrawal during coincident peak” transmission rate structure does not \n3 \nnecessarily provide the appropriate discount that reflects the transmission costs \n4 \nsavings that should be determined through a study as described in Section 4. \n5 \nTherefore, this rate is mixed in its alignment of fair apportionment of costs. \n6 \nProviding customers a means to reduce their transmission charges through \n7 \nBTMG sends a price signal for customers to use BTMG, which ultimately \n8 \nreduces transmission system costs. However, price signals that do not align bill \n9 \nsavings with transmission cost savings may result in inefficiently high or low \n10 \ninvestment in BTMG. For this reason, this rate is mixed in its alignment with \n11 \neconomic efficiency.  \n12 \n• New Option 4: Co-located load with ‘generator-contingent’ protections \n13 \nThis rate provides an option for customers to interconnect in a co-location \n14 \nconfiguration that reduces or eliminates incremental transmission system costs \n15 \nby imposing protections that ensure the load cannot draw energy from the grid. \n16 \nThis is equivalent to a “generator-contingent” configuration that never elects to \n17 \ndraw as-available energy from the system. PJM appropriately reflects these \n18 \nlower transmission system costs through transmission charges based on net \n19 \nusage, which will by definition be zero due to no net usage. Additionally, PJM \n20 \nindicates that the generator would be “responsible for any system upgrades to \n21 \nserve the load.” Both charges are consistent with the ideal rate structure I \n22"},{"page":58,"startToken":13377,"endToken":13644,"text":"57 \ndescribe for a generator-contingent configuration. For these reasons, this rate is \n1 \naligned with the principle of fair apportionment of costs.  \n2 \nThe lower transmission charges assessed to customers in this configuration \n3 \nprovides a price signal for customers to configure in this manner and is therefore \n4 \nbroadly aligned with the principle of economic efficiency. However, this rate \n5 \ndoes not offer an as-available energy purchase option, and such transactions \n6 \nbetween the system and the co-located may be mutually beneficial. It therefore \n7 \nhas mixed alignment with the principle of economic efficiency. \n8 \n• New Option 5: Co-located load with ‘generator-contingent’ protections + \n9 \nas-available energy purchase option \n10 \nThe only apparent difference between Options 4 and 5 is that whereas \n11 \nOption 4 prohibits any draw of electricity from the grid, Option 5 allows for \n12 \n“back-up service from the PJM system with permission. This is equivalent to \n13 \n“as-available” energy that I describe in Section 4. However, this option does \n14 \nnot posit any potential charge for this “use” of the transmission system when \n15 \ngranted permission by PJM, which enables free-riding. For these reasons, it has \n16 \nmixed alignment with the principle of fair apportionment of costs. \n17 \nThe lower charges assessed to customers in this configuration provides a \n18 \nprice signal for customers to configure in this manner. Additionally, this rate \n19 \noffers an as-available energy purchase option, providing the opportunity for \n20 \nbeneficial transactions for co-located load. For these reasons, this option has \n21 \ngood alignment with the principle of economic efficiency. \n22 \n• New Option 6: NITS with co-location + BYOG \n23"},{"page":59,"startToken":13644,"endToken":13908,"text":"58 \nThis rate provides a means for customers to co-locate in a “firm” \n1 \nconfiguration, indicated through PJM’s stated affirmative obligation to serve. \n2 \nHowever, assessing transmission charges based on “full load during coincident \n3 \npeak” does not provide any discount to reflect the fact that a firm co-location \n4 \nconfiguration reduces transmission system costs as described above. For this \n5 \nreason, this option does not fairly allocate costs. \n6 \nAdditionally, if this were the only co-location rate option that was made \n7 \navailable, there would be no incentive for large loads to interconnect in either a \n8 \n“generator-contingent” or “interruptible” manner, both of which would reduce \n9 \noverall transmission system use and costs. Option 6 would drive unnecessary \n10 \ntransmission build that could be avoided. Such an outcome is misaligned with \n11 \nthe principle of economic efficiency. \n12 \nEven if this rate were one of several options, this rate does not offer any \n13 \ntransmission \ncost \nsavings \nto \ncustomers \ndespite \nPJM’s \nexplicit \n14 \nacknowledgement that it would provide transmission system benefits as \n15 \ndemonstrated through anticipated faster interconnection, likely due to avoided \n16 \ntransmission upgrades. Because this option does not provide an incentive for \n17 \ncustomers to configure in a manner that minimizes transmission system costs, \n18 \nit is misaligned with the principle of economic efficiency \n19 \nFinally, rate design principles aside, the suggestion that new generation that \n20 \ndirectly contracts with a customer – regardless of location, reliability impact, or \n21 \ndevelopment status – should be allowed to skip the generation interconnection \n22 \nqueue undermines PJM market signals, particularly those of the capacity \n23"},{"page":60,"startToken":13908,"endToken":14186,"text":"59 \nmarket. These generation developers will be, in effect, allowed to circumvent \n1 \nthe queue process that applies to all generation being built to serve PJM load in \n2 \na manner that is unfair and not competitive. It has the potential to afford \n3 \nincumbent utilities a distinct advantage against competitive suppliers in a \n4 \nmanner that appears misaligned with the premise of PJM competitive markets. \n5 \nAdditionally, the BYOG requirement in Option 6 could signal existing \n6 \ngenerators to deactivate – the opposite signal of what is needed to support \n7 \nresource adequacy. To the extent that loads choose to BYOG, they should be \n8 \nfree to do so, but they should not be required to do so.   \n9 \n• New Option 7: NITS with co-location where load is interruptible \n10 \nThis option offers a means for customers to interconnect in a “interruptible” \n11 \nconfiguration. As demonstrated above, this configuration would impose \n12 \nminimal if any costs on the transmission system and thus has the potential to \n13 \ninterconnect loads in a very beneficially low-cost manner. However, because \n14 \nthis option proposes to charge for transmission service based on “full load \n15 \nduring coincident peak”, it would not provide any discount relative to firm \n16 \ncustomers that directly connect to the transmission system, even though a firm \n17 \nco-location configuration reduces transmission system costs as described \n18 \nabove. It is therefore misaligned with the principle of fair apportionment of \n19 \ncosts.  \n20 \nAdditionally, while this rate highlights the benefits that interruptibility can \n21 \nprovide to the system, it does not actually provide a transmission price signal \n22 \nfor customers to operate in an interruptible manner, because customers are \n23"},{"page":61,"startToken":14186,"endToken":14437,"text":"60 \nbilled for transmission service equivalently to firm customers that directly \n1 \nconnect to the transmission system. It therefore is less likely that customers will \n2 \nconfigure and operate in this manner, driving unnecessary and inefficient \n3 \ntransmission build that could be avoided. Because it does not drive efficient \n4 \nbehavior that minimizes transmission system costs, this rate option (as proposed \n5 \nby PJM without modifications) is misaligned with the principle of economic \n6 \nefficiency. \n7 \n• New Option 8: NITS with co-location where load participates as demand \n8 \nresponse \n9 \nThis rate offers customers the option to interconnect in a “interruptible” \n10 \nconfiguration. Even though PJM affirmatively states an obligation to serve, \n11 \nPJM also retains the right to ask the co-located load to curtail through demand \n12 \nresponse. In any event, the load is proposed to be charged for transmission \n13 \nservice equivalently to firm customers that directly connect to the transmission \n14 \nsystem. Because this option does not provide any transmission discount relative \n15 \nto customers that impose higher costs on the system, it is misaligned with the \n16 \nprinciple of fair apportionment of costs. \n17 \nAdditionally, it provides no transmission price signal for customers to \n18 \nconfigure and provide demand response services. It is therefore less likely that \n19 \ncustomers will do so, driving unnecessary and inefficient transmission build \n20 \nthat could be avoided. Because it does not drive efficient behavior that \n21 \nminimizes transmission system costs, it is misaligned with the principle of \n22 \neconomic efficiency. \n23"},{"page":62,"startToken":14437,"endToken":14724,"text":"61 \nQ64. WHAT IS YOUR ASSESSMENT OF THE RESOURCE ADEQUACY \n1 \nFOCUS OF NEW OPTIONS 6, 7, AND 8 PROPOSED BY PJM? \n2 \nA64. PJM’s preference for these options appears to be premised on the notion that these \n3 \ntransmission rates “maintain Resource Adequacy.” This misplaced notion ignores \n4 \nthe fact that new load without any of these features (i.e. BYOG, interruptibility, or \n5 \ndemand response) increases demand in the capacity market which provides a price \n6 \nsignal to attract new capacity, which is the very mechanism to ensure resource \n7 \nadequacy that underpins the existence of the capacity market. To the extent that \n8 \nloads choose to BYOG, be interruptible, or participate as demand response, they \n9 \nshould be free to do so, but they should not be required to do so. \n10 \nPJM’s misplaced emphasis on resource adequacy has even led to several \n11 \nunclear statements in their filing. For example, they state that “large loads would \n12 \nbe offered the option to be classified as a non-capacity backed load for a transitional \n13 \nperiod until any resource adequacy supply/demand imbalances associated with the \n14 \nlarge load could be addressed.” The PJM capacity market is by definition designed \n15 \nto clear an equivalent quantity of supply and demand, meaning that there could only \n16 \nbe an “imbalance” relative to the reliability target, which would likely be entirely \n17 \noutside of the control of the load in question. Against this backdrop, how much \n18 \n“imbalance” would PJM tolerate? As proposed, this option is unlikely to be \n19 \n“free[…] from controversies as to proper interpretation,” which is a foundational \n20 \nBonbright principle.70 \n21 \n \n70 James C. Bonbright, Principles of Public Utility Rates, page 291."},{"page":63,"startToken":14724,"endToken":14975,"text":"62 \nQ65. WHAT IS YOUR ASSESSMENT OF PJM’S STATED PREFERENCE FOR \n1 \nOPTIONS 1, 2, 6, 7, AND 8? \n2 \nA65. The commonality among all of these rate options is that all loads interconnect as \n3 \nNetwork Load and pay NITS based on their gross load. While this construct \n4 \nreasonably allocates costs for customers wishing to interconnect in a “firm” \n5 \nconfiguration, it does not incentivize nor facilitate interconnection in a lower cost \n6 \nmanner through co-location. This ultimately drives unnecessary increases in \n7 \ntransmission system costs. \n8 \nQ66. HOW WOULD YOU RECOMMEND THESE OPTIONS BE USED IN THE \n9 \nDEVELOPMENT OF NEW RATES FOR CO-LOCATED LOADS? \n10 \nA66. First, I recommend that a different rate option be implemented for each of the three \n11 \nfundamental configurations of co-located load. Even if a single rate is “ideal” for \n12 \none customer type, it may not be ideal for another customer type, and providing \n13 \noptions that align with the services that each customer desires provides a means to \n14 \nonly invest in new transmission infrastructure that is necessary. Therefore, the \n15 \nexistence of multiple options for co-located loads to interconnect under different \n16 \nconfigurations is, itself, necessary to achieve economic efficiency in totality. \n17 \nQ67. HOW DO PJM’ PROPOSED “FIRM” OPTIONS ALIGN WITH RATE \n18 \nDESIGN PRINCIPLES RELATIVE TO THE IDEAL RATE? \n19 \nA67. The table below summarizes my conclusions regarding the alignment of rate \n20 \noptions that represent a “firm” configuration with the rate design principles of 1) \n21"},{"page":64,"startToken":14975,"endToken":15223,"text":"63 \nfair apportionment of costs and 2) economic efficiency.71 Because the ideal rate \n1 \nbills for transmission using the greater of NITS applied to net load and a discounted \n2 \nstandby charge, it performs well against both rate design principles. \n3 \nTable 3: Assessment of “Firm” Rate Options Alignment with Rate Design Principles \n4 \nRate Option \nDescription \nFair Apportionment \nof Costs \nEconomic \nEfficiency \nPJM Option 1 NITS without co-\nlocation \nN/A for Co-Location \nPJM Option 2 NITS with co-\nlocation \nPoor \nPoor \nPJM Option 3 Load customer \nwith BTMG \nMixed \nMixed \nIdeal “Firm” \nRate \nGreater of 1) NITS \nwith net billing or \n2) Discounted \nstandby charge \nGood \nGood \nQ68. HOW DO PJM’ PROPOSED “GENERATOR-CONTINGENT” OPTIONS \n5 \nALIGN WITH RATE DESIGN PRINCIPLES RELATIVE TO THE IDEAL \n6 \nRATE? \n7 \nA68. The table below summarizes my previous conclusions regarding the alignment of \n8 \nrate options that represent a “generator-contingent” configuration with the rate \n9 \ndesign principles of 1) fair apportionment of costs and 2) economic efficiency. \n10 \nBecause the ideal rate bills for transmission using a one-time system impact charge \n11 \nthat reflects the costs that the generation interconnection modification is imposing \n12 \non the system, instead of full gross load during coincident peak, it performs well \n13 \n \n71 Note that even though PJM Rate Option 6 appears to represent a “firm” option, it has been excluded from \nconsideration in the table below, as it is misaligned with the premise of open and fair competition as \ndescribed above."},{"page":65,"startToken":15223,"endToken":15426,"text":"64 \nagainst both rate design principles. Additionally, if this rate option is structured to \n1 \ninclude the efficiency-enhancing ability to draw energy from the transmission \n2 \nsystem on an as-available basis, this should be billed at a discounted $/MWh \n3 \ntransmission charge.  \n4 \nTable 4: Assessment of “Generator-contingent” Rate Options Alignment with Rate Design  \n5 \nPrinciples  \n6 \nRate \nOption \nDescription \nFair \nApportionment of \nCosts \nEconomic \nEfficiency \nPJM \nOption 4 \nCo-located load with \n‘generator-contingent’ \nprotections \nGood \nMixed \nPJM \nOption 5 \nCo-located load with \n‘generator-contingent’ \nprotections + as-\navailable energy \npurchase option \nMixed \nGood \nIdeal Rate Generator-contingent \nwith as-available energy \npurchases billed at \ndiscounted $/MWh \ncharge \nGood \nGood \nQ69. HOW DO PJM’ PROPOSED “INTERRUPTIBLE” OPTIONS ALIGN \n7 \nWITH RATE DESIGN PRINCIPLES RELATIVE TO THE IDEAL RATE? \n8 \nA69. The table below summarizes my previous conclusions regarding the alignment of \n9 \nrate options that represent an “interruptible” configuration with the rate design \n10 \nprinciples of 1) fair apportionment of costs and 2) economic efficiency. Because \n11 \nthe ideal rate does not assess a standby or system impact charge (since these \n12 \ncustomers have no impact or cost on the transmission system), it performs well \n13 \nagainst both rate design principles. Additionally, the inclusion of a discounted \n14"},{"page":66,"startToken":15426,"endToken":15512,"text":"65 \n$/MWh transmission charge for as-available energy purchases is important for the \n1 \nperformance of the ideal rate along both rate design principles. \n2 \nTable 5: Assessment of “Interruptible” Rate Options Alignment with Rate Design Principles \n3 \nRate Option \nDescription \nFair Apportionment \nof Costs \nEconomic \nEfficiency \nPJM Rate \nOption 7 \nNITS with co-location \nwhere load is \ninterruptible \nPoor \nPoor \nPJM Rate \nOption 8 \nNITS with co-location \nwhere load participates \nas demand response \nPoor \nPoor \nIdeal Rate \nInterruptible with As-\nAvailable discounted \n$/MWh charge \nGood \nGood \n \n \n4"},{"page":67,"startToken":15512,"endToken":15752,"text":"66 \n6 Recommendations & Summary \n1 \nQ70. IN LIGHT OF THE ARGUMENTS YOU MAKE, DO YOU HAVE A \n2 \nRECOMMENDATION? \n3 \nA70. Yes. Most broadly, I recommend that FERC ensure that loads have the opportunity \n4 \nand incentive to interconnect to the transmission system in a manner that reflects \n5 \nfair apportionment of costs and economic efficiency for the level of service that \n6 \nthey require. I recommend that FERC find the current transmission tariff unjust and \n7 \nunreasonable because it does not clearly provide this opportunity. I further \n8 \nrecommend that FERC implement this vision by developing three new distinct rate \n9 \noptions for three configurations of co-located load: firm, generator-contingent, and \n10 \ninterruptible. These rate options can be implemented by modifying PJM’s proposed \n11 \noptions.  \n12 \nQ71. PLEASE SUMMARIZE YOUR TESTIMONY. \n13 \nA71. Yes. The key takeaways of my testimony are: \n14 \n• The PJM tariff should align with rate design principles, including 1) fair \n15 \napportionment of costs and 2) economic efficiency; \n16 \n• Transmission costs are primarily caused by draw from the system during the \n17 \npeak, and loads that can configure or operate in a manner that reduce peak load \n18 \ndraw on the system can reduce transmission system costs – gross billing \n19 \nregardless of configuration undermines the incentive to minimize costs; \n20 \n• Co-location of generation and load provides one mechanism to reduce the \n21 \nload’s peak load draw on the system and reduce transmission system costs; \n22"},{"page":68,"startToken":15752,"endToken":15885,"text":"67 \n• There are multiple potential co-location configurations, each with different \n1 \ntransmission system impacts: firm, generator-contingent, and interruptible; \n2 \n• The current tariff lacks clarity, unfairly apportions costs, is inequitable, and \n3 \ndoes not provide the opportunity and incentive for loads to interconnect in a co-\n4 \nlocation configuration that reduces costs, which results in unnecessary and \n5 \ninefficient transmission buildout, harming affordability – for these reasons it is \n6 \nunjust and unreasonable; \n7 \n• PJM’s current proposed rate options do not align with rate design principles, \n8 \nbut I show how several options can be modified to improve alignment; and \n9 \n• PJM should immediately implement new tariff options for multiple co-location \n10 \nconfigurations: firm, generator-contingent, and interruptible, either as enduring \n11 \nor transitional rates. \n12 \nQ72. DOES THIS CONCLUDE YOUR TESTIMONY? \n13 \nA72. Yes \n14"},{"page":69,"startToken":15885,"endToken":15918,"text":"VERIFICATION \nI declare under penalty of perjury that the foregoing Testimony is true and correct to the best of \nmy knowledge, information, and belief.  \nExecuted this 23rd day of April 2025. \n \n \n \n \n \n \n \n \n________________________ \n \n \n \n \n \n \n \nZachary Ming"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":3,"endAt":3,"startToken":0,"endToken":72},{"p":3,"at":3,"title":"Table of Contents","method":"printed heading","endPage":69,"endAt":262,"startToken":72,"endToken":15918}]}