{"document":{"slug":"rec-20250423-5262-4","title":"Exhibit 3 (Patterson)","issued":"2025-04-23","accession":"20250423-5262","docket":"EL25-49-000","group":"PJM co-location compliance","filer":"Constellation Energy Generation, LLC","kind":"attachment","file":"sources/filings/text/20250423-5262_004.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20250423-5262","tier":"record","parent":"rec-20250423-5262","sha256":"46ffe58b99cc4a3133fae9f17a99f7b8261f95079a7621adf50aea7c06821a05","pages":33,"tokens":11124,"emptyPages":[31],"textThemes":["adequacy","study","flex","colo"]},"pages":[{"page":1,"startToken":0,"endToken":6,"text":"EXHIBIT 3 \nAFFIDAVIT OF AARON PATTERSON"},{"page":2,"startToken":6,"endToken":57,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \nPJM Interconnection, L.L.C., et al. \n \n \nLarge Loads Co-Located at Generating Facilities \n \n \nConstellation Energy Generation, LLC. \n \nv. \n \nPJM Interconnection, L.L.C. \n) \n \n \n) \n \n \n) \n) \n) \n) \n) \nDocket No. EL25-49-000 \n \n \nDocket No. AD24-11-000 \n \n \nDocket No. EL25-20-000 \n      (Consolidated) \n \n \n \n \n \n \nAFFIDAVIT OF \nAARON T. PATTERSON  \n \nApril 23, 2025"},{"page":3,"startToken":57,"endToken":403,"text":"1 \n \nI. QUALIFICATIONS, BACKGROUND, AND PURPOSE OF AFFIDAVIT \nA. QUALIFICATIONS \n1. \nMy name is Aaron T. Patterson.  I am a partner of The NorthBridge Group, Inc \n(“NorthBridge”).  NorthBridge is a consulting firm that provides economic and strategic advice to \nthe electric and natural gas industries.  My business address is 30 Monument Square, Concord MA \n01742. \n2. \nI joined NorthBridge in 2001.  Before that, I was an analyst at Lexecon, Inc. which I joined \nin 1996.  I have over 20 years of experience working with clients in the electric and natural gas \nindustries.  My electric industry business consulting work has focused on market design, \nenvironmental policy, finance, and mergers and acquisitions.  I received a Bachelor of Arts in \nEnvironmental Science and Public Policy from Harvard University, and a Master of Business \nAdministration from the Tuck School of Business at Dartmouth.  I have previously testified before \nthe Commission and have also submitted expert reports in proceedings before the U.S. Department \nof the Treasury, the Public Utility Commission of Texas and the New York State Public Service \nCommission. \n3. \nA list of my past prepared testimony is provided as Attachment A. \nB. BACKGROUND AND PURPOSE OF AFFIDAVIT \n4. \nThe Commission recently issued an order instituting this proceeding that requires PJM \nInterconnection, L.L.C. (“PJM”) and the Transmission Owners (“TOs”) in the PJM region to show \ncause as to whether the PJM Open Access Transmission Tariff (“Tariff”) remains just and \nreasonable with respect to how it handles additions of large loads, such as datacenters, that are co-\nlocated with generation and to offer potential changes to the Tariff that could remedy concerns \naround the addition of large co-located loads.1  PJM’s Answer stated that PJM believes the Tariff \nremains just and reasonable but offered, and requested guidance from the Commission and others \non, several potential changes to the Tariff that PJM asserts could improve the way in which PJM \n \n1 Docket Nos. EL25-49-000, AD24-11-000, and EL25-20-000 (consolidated), Order Instituting Proceeding Under \nSection 206 of the Federal Power Act and Consolidating with Other Proceedings, Feb 20, 2025. (“Instituting Order”)"},{"page":4,"startToken":403,"endToken":791,"text":"2 \n \nhandles additions of large load to its system, both co-located and otherwise.2  Among the issues \non which the Commission has requested comment, and which PJM discussed in its Answer, is the \npotential impact that co-located large load, and large loads in general, may have on resource \nadequacy within PJM. \n5. \nMy testimony addresses two separate topics related to both the Commission’s Order and \nPJM’s Answer.  First, I examine the resource adequacy issues raised in the proceeding and the \npotential remedies offered by PJM and others.  I offer several potential constructive policies that \nthe Commission could support to improve the performance of PJM’s resource adequacy construct \nin the face of rapid additions of large loads while also identifying those policies which the \nCommission should avoid.  Second, to facilitate the discussion of the appropriate means of \nallocating the costs of integrating large loads onto the system, I provide data that I have collected \non the estimated integration costs of large loads onto the PJM system from 2022 onwards. \n6. \nI reach five primary conclusions as a result of my analysis. \n7. \nFirst, resource adequacy concerns associated with rapid large load additions such as \ndatacenters stem from all large load additions, regardless of whether or not they are co-located, \nand are fundamentally driven by the large individual size of large load projects and their rapid \ndevelopment time from conception to energization.  These characteristics make load growth very \nlumpy, hard to predict, and may lead to load needing service before the market can respond with \nadditional new capacity.  PJM’s market design, including its competitive capacity market, the \nReliability Pricing Model (“RPM”), and other elements such as its interconnection queue and load \nforecasting function must continue to evolve to meet the new challenges posed by the rapid growth \nin large load additions. \n8. \nSecond, however, the RPM market design has not exhibited any general market failure nor \nare load large additions a reason to jettison the RPM altogether.  The RPM has performed very \nwell historically in terms of maintaining resource adequacy at cost-effective prices for customers.  \nThe RPM remains the best underlying platform for meeting the challenges created by large load \nadditions, and certain improvements could better optimize it to meet this challenge. \n \n2 Docket Nos. EL25-49-000, AD24-11-000, and EL25-20-000 (consolidated), Answer of PJM Interconnection, LLC, \nMarch 24, 2025. (“PJM Answer”)"},{"page":5,"startToken":791,"endToken":1235,"text":"3 \n \n9. \nThird, there are a number of concrete steps that the Commission and PJM can take to improve \nthe RPM’s efficacy in reliably, speedily, and cost-effectively integrating large load.  These steps \nparticularly focus on facilitating the timely entry of short lead-time supply; providing better signals \nfor the entry of all types of supply in response to changing trends in load growth; and removing \nbarriers to entry for all resource types.  First, PJM should continue efforts to improve the accuracy \nof price formation in both its energy and capacity markets, with particular emphasis on removing \nout-of-market price distortions that lead prices to diverge from system fundamentals.  Second, \nPJM should improve its forecasting of large load by standardizing and making mandatory the \nprocess whereby TOs report new large loads to PJM, and it should incorporate large load into the \nload forecast more frequently than the present once-per-year cadence and provide as much \ntransparency and detail on this process as possible.  Third, PJM should continue to improve the \nspeed at which new projects are able to clear the generation interconnection queue and the \nresponsiveness of the queue to emergent capacity supply needs.  This should foremost take the \nform of streamlining, automating, and accelerating the current queue process as much as possible.  \nIf further enhancements beyond improving the base queue process are needed, PJM could consider \nadding a fast-track interconnection process similar to the current one-off Reliability Resource \nInitiative (“RRI”) that offers accelerated treatment for capacity supply resources that have the \ngreatest impact on resource adequacy and can enter quickly that would be triggered when PJM has \nan acute need for incremental new supply.  Fourth, PJM should seek ways to allow datacenters \nand other large loads to participate in the RPM as demand response as much and as easily as \npossible, such as by harmonizing the PJM and EPA rules regarding run-time limits for backup \ndiesel generators.  Finally, PJM should consider adding an improved backstop reliability \nprocurement mechanism to the RPM that seeks to procure additional short-lead or higher-cost \ncapacity supply resources in cases where the RPM does not clear sufficient supply to meet a \nminimum adequate level of resource adequacy. \n10. Fourth, PJM and the Commission should avoid policies that undermine, distort, or \ncircumvent PJM’s markets.  In particular, PJM should avoid policies that tie load’s entry to it \nbringing with it self-supplied or contracted new supply, or that offer benefits or subsidies to \ngenerators that are tied to new entrant loads.  Such policies distort markets because they effectively \nsubsidize a certain set of supply resources – new resources tied to new entrant loads – whose \nreliability attributes are not otherwise distinguishable from other capacity supply.  In addition to"},{"page":6,"startToken":1235,"endToken":1655,"text":"4 \n \ndiscriminating against existing resources in favor of new ones, this harms the market by \nsuppressing prices, reducing entry of non-advantaged supply resources, and furthering the \npotential exit of existing resources, all of which undermine reliability and frustrate the original \nobjective of reliably integrating new load.  One of the options PJM offers as potential avenues for \nlarge load integration – Options 6 – is of this nature and should be rejected.  Another of PJM’s \noptions – Option 7 – as currently written also carries the potential to undermine markets and \ndiscriminate against non-favored resources because it appears to contemplate giving PJM broad \ndiscretion to condition new large load entry on vague PJM-determined resource adequacy concerns \nwith new load entry under such conditions only allowed if the load provides PJM with interruption \nrights, distorting capacity prices when a clear signal for new entry and retention of existing \nresources is needed.  While it is reasonable to reflect the ability and willingness of large loads to \ninterrupt in the load integration process, interruption rights should not be a condition for new entry \nbased on resource adequacy concerns. \n11. Finally, with respect to costs of integrating large loads into the transmission network, I find \nthat recent historical integration costs are generally proportionate to the size of the load seeking to \nenter the market, but costs are extremely variable even after accounting for size differences.  This \nvariability generally appears to be due to unique locational factors that vary from load to load such \nas the position of the load within the broader system topology and the physical environment around \nthe new load site.  While load size is a significant determinant of the cost of integrating large loads, \nlocation clearly matters a great deal and can cause the cost to vary in idiosyncratic and \nunpredictable ways.  This location-dependence suggests that sending the correct incentives via \ntransmission rates to new load to locate at efficient places on the grid is important for integrating \nsuch load efficiently with respect to total system costs. \nII. RESOURCE ADEQUACY ISSUES RELATED TO ADDITIONS OF LARGE LOADS TO THE PJM \nSYSTEM \nA. RESOURCE ADEQUACY CONCERNS RELATED TO LARGE LOAD \nADDITIONS ARE REASONABLE, BUT DO NOT REFLECT A GENERAL \nFAILURE OF MARKETS, OR OF THE CAPACITY MARKET IN PARTICULAR, \nTHAT JUSTIFY PJM’S PROPOSALS \n12. Both the Commission and PJM have voiced concerns about the resource adequacy \nimplications of rapid additions of large loads to the PJM system, both with respect to large loads \nthat are co-located with generation specifically, as well as large loads more generally regardless"},{"page":7,"startToken":1655,"endToken":2037,"text":"5 \n \nof configuration.3    The Commission and PJM both raise concerns that the fast pace of large load \nadditions may lead to capacity shortfalls regardless of configuration.4  PJM states that “as to the \nresource adequacy dimension to co-location arrangements where conditions are tight, any \nadditional load on the system requires either the addition of supply resources to serve that load \nreliably, or flexibility on the part of the load to curtail its consumption from the transmission \nsystem when necessary to maintain reliability.”5   \n13. In response to these resource adequacy concerns, PJM offers three “preferred” new options \nfor interconnecting large loads “relating to adding additional supply and flexibility” in response to \nconcerns around resource adequacy.6  While couched as responses to co-located load particularly, \nthe proposed policies nonetheless appear to be applicable to all types of large load, co-located or \notherwise.  One of these options (Option 8) merely envisions the potential for new large loads to \nparticipate in PJM markets as demand response resources in line with the current tariff, but with \nsome modifications to facilitate participation by datacenters.  But the other two options – Option \n6 and (as described in PJM’s Answer) Option 7 – both represent a significant departure from PJM’s \nnon-discriminatory resource adequacy construct in that they offer unique benefits to certain forms \nof capacity supply tied to large loads.  For Option 6, this takes the form of faster processing of \ninterconnection for generators that are tied to large loads. Option 7, as currently proposed by PJM \nin its Answer, conditions integration of large load on the load providing PJM with interruption \nrights (that is, effectively self-supplying demand response), depending on whether PJM determines \nthat there would otherwise be a resource adequacy “imbalance.”  These proposed options appear \nto be a response to the general resource adequacy concerns arising from rapid large load additions, \nbut their discriminatory and market-circumventing elements suggest that PJM desires more control \nthan its markets afford or lacks confidence that PJM’s existing resource adequacy construct is fully \nup to the task of bringing forth the supply needed to maintain resource adequacy in the face of \nincreasing load growth driven by large load additions. \n \n3 Instituting Order at PP 83-86 and PJM Answer at 8-9. \n4 Ibid. \n5 PJM Answer at 8 (emphasis added).  \n6 Ibid. at 9."},{"page":8,"startToken":2037,"endToken":2458,"text":"6 \n \n14. While questions about resource adequacy in the face of rapid load growth are valid, it is \nimportant to first get the right problem diagnosis and then develop solutions that address the \nproblem directly, without harming markets or causing other unintended consequences. \n15. First, at bottom, the potential for resource adequacy problems related to large load additions \narise primarily from the very fast and very lumpy load growth caused by large load interconnecting \nwith the system, regardless of whether or not it is co-located with generation.  From a resource \nadequacy perspective, a megawatt of load added to the system creates a need for the same amount \nof incremental supply regardless of whether the load is co-located with generator or not.  And even \nin configurations where the load does not take network service and takes supply from a generator \nthat does not participate as a capacity resource, the net effect is the same – the system has a need \nfor incremental supply because it must replace the generation offering direct supply to the load.  \nThus, any consideration of resource adequacy issues driven by large load should consider all such \nload, regardless of whether it is co-located with generation.   \n16. Second, the resource adequacy concern surrounding large loads arises from the desire or need \non the part of large load customers to enter the market faster and in larger quantities than many \ntypes of capacity supply resources can respond.  New datacenter loads can be constructed and \ncome online in as little as two to three years and can be as large as two gigawatts or potentially \neven more at a single point of interconnection.  And the emerging business models surrounding \nartificial intelligence and other datacenter applications place high value on the ability to rapidly \ndeploy large amounts of additional datacenter processing capacity.  Figure 1 below demonstrates \nthe speed at which data center load can potentially enter the market, as reflected by PJM’s evolving \nload forecasts from January 2023 to January 2025.  Over this period the forecast for the 2027 \nsummer peak, just over two years from the present date, increased by about 10 gigawatts (from \n154 to 164 gigawatts).  As of 2023, these loads were not part of the planning process or in the load \nforecast used to set demand for the RPM, but over a two-year span they progressed development \nto the point where they are now projected to enter in about two years from the present.  Increases \nin the load forecast for later years suggest this trend is likely to continue."},{"page":9,"startToken":2458,"endToken":2725,"text":"7 \n \nFigure 1 \n \nSource: PJM Load Forecasts (various years) at https://www.pjm.com/planning/resource-\nadequacy-planning/load-forecast-dev-process. \n \n17. Several aspects of the RPM could be better optimized to serving such large, rapid and \ndifficult to predict load additions as depicted in Figure 1.  First, capacity from conventional \ngeneration resources can take longer to enter the market than the 2-to-3-year development cycle \nfor a datacenter load.  PJM’s consultants are currently assuming a 44-month construction cycle \ntime for a new combustion turbine for the purposes of developing parameters for future RPM \nauctions, exclusive of pre-construction development activity, suggesting a floor on conventional \ngeneration development cycle time of at least 4 to 5 years.7  And the ability of conventional \ngeneration to “anticipate” load growth and thus start development prior to a firm demand signal \nfrom the capacity market is currently limited by uncertainties around PJM’s longer-term load \nforecast and market structure.  In such an environment – large but difficult to predict demand from \n \n7 Sixth Review of PJM’s RPM VRR Curve Parameters: Updated Gross CONE and VRR Curve Analysis, Presentation \nby the Brattle Group to the PJM Market Implementation Committee, Feb 21, 2025, slides 6-8.  https://www.pjm.com/-\n/media/DotCom/committees-groups/committees/mic/2025/20250221-special/pjm-qr-cone-and-vrr-curve-deck.pdf \n140,000\n145,000\n150,000\n155,000\n160,000\n165,000\n170,000\n175,000\n180,000\n185,000\n190,000\n2021\n2022\n2023\n2024\n2025\n2026\n2027\n2028\n2029\n2030\nPJM RTO Summer Peak Load Forecast Evolution, 2023 to 2025\n(Summer Peak MW)\nActual Weather-\nNormalized Load\nJan 2023 Load \nForecast\nJan 2024 Load \nForecast\nJan 2025 Load \nForecast"},{"page":10,"startToken":2725,"endToken":3003,"text":"8 \n \nlarge loads of all types coupled with limitations on the ability of conventional capacity supply to \nrespond in a timely fashion – concerns about resource adequacy are warranted. \n18. Third, while concerns around resource adequacy due to large load additions have merit and \nthe specific issues with the RPM described above are quite real, they do not amount to a \ngeneralized failure of PJM markets or the RPM in particular.  The RPM has historically performed \nwell in delivering resource adequacy at affordable costs to PJM customers and provides a solid \nplatform for continuing to do so in the future, albeit with ongoing improvement to meet current \nand future challenges.  Over 19 delivery years to date for which RPM auctions have been held, the \nRPM has never failed to procure capacity in excess of the level needed to maintain its 1-in-10 \nyears loss of load expectation resource adequacy standard, as Figure 2 below shows: \nFigure 2 \n \nSource: PJM Base Residual Auction Reports (various years) at https://www.pjm.com/markets-\nand-operations/rpm.  PJM Reserve Requirement Studies (various years) at \nhttps://www.pjm.com/planning/resource-adequacy-planning/reserve-requirement-dev-process. \n \nWhile PJM has not faced load growth on the scale expected in coming years over this period, it \nhas over this period faced significant incremental supply needs driven by coal retirements and \nsuccessfully brought forth market-based replacement supply at the scale needed to maintain the \n0%\n5%\n10%\n15%\n20%\n25%\nDelivery Year\nPJM Installed Reserve Margins Cleared in RPM versus Target Needed \nto Maintain Resource Adequacy Standard\nReserve Margin Cleared in RPM Base \nResidual Auction (Including FRR)\nTarget Reserve Margin needed to Achieve One \nExpected Event per 10 Years Resource \nAdequacy Standard"},{"page":11,"startToken":3003,"endToken":3332,"text":"9 \n \ntarget level of resource adequacy.  Figure 3 below shows PJM generation capacity additions and \nretirements from inception of the RPM to present.  When needed, the RPM has brought forth new \ncapacity additions of as much as 5 to 8 gigawatts in a single year and has successfully procured \ntotal capacity in excess of the PJM resource adequacy target even in years in which as much as 5 \nto 8 gigawatts of capacity has retired.  The year-over-year average load growth for the next 5 years \nin PJM’s most recent load forecast (shown in Figure 1) is just under 6 gigawatts per year.  \nHistorically the RPM has been successful in bringing forth capacity at the scale needed to maintain \nresource adequacy of a similar order of magnitude as will be needed in the future. \nFigure 3 \n \n \nSource: Monitoring Analytics, LLC, 2024 State of the Market Report for PJM, Table 5-6. \nhttps://www.monitoringanalytics.com/reports/PJM_State_of_the_Market/2024/2024-som-pjm-\nsec5.pdf \n \n19. PJM’s competitive markets have not only continuously maintained resource adequacy but \nhave done so in a cost-effective manner for consumers.  Figure 4 below shows the combined real \n(in 2024 dollars) wholesale market energy, ancillary services, and capacity costs per megawatt-\nhour of load in PJM from the full first calendar year in which the RPM was in effect – 2008 - to \nthe most recently-completed RPM auction for the 2025/26 delivery year.   \n737\n2,041\n1,196\n506\n3,959\n2,347\n629\n2,828\n4,831\n4,631\n4,694\n8,462\n5,120\n990\n3,728\n5,160\n3,117\n(797) (1,031) (573) (1,064)\n(2,718)\n(5,854)\n(3,075)\n(5,276)\n(8,554)\n(866)\n(2,806)\n(6,819)\n(3,413) (3,778)\n(2,323)\n(7,763)\n(6,590)\n-10,000\n-8,000\n-6,000\n-4,000\n-2,000\n0\n2,000\n4,000\n6,000\n8,000\n10,000\nPJM Generation Capacity Additions and Retirements (ICAP MW)\nGeneration Additions\nGeneration Retirements"},{"page":12,"startToken":3332,"endToken":3500,"text":"10 \n \nFigure 4 \n \n \nSource: Monitoring Analytics, LLC, 2024 State of the Market Report for PJM, Table 11.  \nEstimated costs for 2025/26 based on RPM auction results and energy forward prices from S&P \nGlobal.  Adjusted for inflation using GDP deflator as reported by the U.S. Federal Reserve. \n \nIn real terms, combined energy, ancillary services, and capacity costs have fallen by about 34% \nover the period simply comparing 2008 and 2025/26.  And even ignoring the high prices in 2008, \ncosts have on average remained essentially flat in real terms from 2009 onward.  Over the same \nperiod transmission costs in PJM, which are not subject to competition but continue to be \ndetermined using traditional cost-based ratemaking, have more than tripled in real terms, as shown \nbelow in Figure 5. \n0\n20\n40\n60\n80\n100\n120\n140\nPJM Combined Energy and Capacity Customer Costs (2024 $/MWh)\nEnergy and Ancillary Services\nCapacity\n2008: First Full \nYear with RPM\n2025/26: Most \nRecent RPM \nAuction\nAverage Across \nEntire Period"},{"page":13,"startToken":3500,"endToken":3803,"text":"11 \n \nFigure 5 \n \nSource: Monitoring Analytics, LLC, 2024 State of the Market Report for PJM, Table 11.  Adjusted \nfor inflation using GDP deflator as reported by the U.S. Federal Reserve \n \n20. While competitive markets are challenged presently with the need to meet accelerating load \ngrowth coupled by delays in the processing of new generation due to reforms made to the \ninterconnection queue process, there is evidence that PJM’s markets are responding to this \nemergent need.  Higher market price signals in line with the cost of new entry in the most recent \nRPM auction coupled with recent PJM rule changes to accelerate the addition of capacity supply \nresources with a disproportionate impact on resource adequacy through the PJM Reliability \nResource Initiative have induced a strong supply response.  The RRI has attracted 94 projects (both \nnew builds and uprates) covering 26.6 Gigawatts of ICAP that had formerly not been able to enter \nthe generation queue but are able to achieve commercial operation on an accelerated basis.8  \nFurther, 1.1 gigawatts of generation that was scheduled to retire have reversed their retirement \ndecisions since the most recent RPM auction.9  And finally, certain large datacenter project \n \n8  PJM \nInside \nLines, \n“Reliability \nResource \nInitiative \nDraws \n94 \nApplications,” \nMar \n21, \n2025.  \nhttps://insidelines.pjm.com/reliability-resource-initiative-draws-94-applications/ \n9  See https://www.pjm.com/planning/service-requests/gen-deactivations.  Since the 2025/26 auction, seven \ncombustion turbine plants/units have reversed retirement decisions including Perryman 6 (55 MW), Morgantown 1-4 \n(216 MW), Fisk 31-34 ((171 MW), Vienna 8&10 (167 MW), Waukegan 31&32 (100 MW), Elgin 1-4 (480 MW), and \nKenilworth (15 MW). \n0\n2\n4\n6\n8\n10\n12\n14\n16\n18\n20\n2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024\nPJM Transmission Costs per MWh (2024$)"},{"page":14,"startToken":3803,"endToken":4170,"text":"12 \n \nannouncements have announced that the datacenter power supply contract will be used to support \nthe repowering of significant generation assets.10  This market response is unsurprising given the \nevolving market supply and demand fundamentals.  Specifically, as the supply side has contracted \n(e.g., due to recent retirements and queue-related slowdowns in the pace of new additions) and the \ndemand side has expanded (e.g. due to datacenters, increased electrification, use of EVs, etc.), that \nshift in fundamentals – a tighter supply/demand balance – has put upward pressure on prices.  As \nexpected, the increased prices are incenting supply side investment, some of which will be secured \nby long-term contracts.   \n21.  Pre-supposition of market failure is premature in the face of the present challenges brought \nby rapid addition of datacenter loads, as are policies which circumvent, obstruct, or even outright \nabandon markets.  Rather, the present circumstances comprise a challenge of how best for PJM \n(and the Commission) to respond to the very specific issues created by datacenter load growth in \na manner that builds on the solid foundation provided by competitive markets.  First, how can PJM \nfacilitate the timely entry of short lead-time capacity supply, particularly when such entry is most \ncritical for maintaining reliability?  And second, how can PJM improve the long-term entry signals \nfor all types of supply, including longer-lead-time conventional generation, to better anticipate \ntrends in load growth and other capacity needs and to better enable resources to initiate the \ndevelopment cycle in a sufficiently timely fashion to contribute to resolving resource adequacy \nchallenges in the future?  And finally, any tariff changes or other new policies should address these \nchallenges without harming markets or creating other unintended consequences that unwind any \nprogress or create new problems. \n \n10 For example, Constellation Energy is restarting the Three Mile Island Unit 1 nuclear plant in combination with a \n20-year \ncontract \nto \nsupply \ncarbon-free \nenergy \nto \nMicrosoft \ndatacenter \ndevelopments \n(See \nhttps://www.constellationenergy.com/newsroom/2024/Constellation-to-Launch-Crane-Clean-Energy-Center-\nRestoring-Jobs-and-Carbon-Free-Power-to-The-Grid.html), and an initiative was recently announced to construct up \nto 4.5 gigawatts of natural gas fired generation capacity at the site of the retired Homer City coal plant to support \ndatacenter development.  (See https://www.homercityredevelopment.com/post/former-homer-city-pa-coal-plant-\nofficially-reopens-as-state-of-the-art-natural-gas-facility)"},{"page":15,"startToken":4170,"endToken":4577,"text":"13 \n \nB. BOTH SHORT AND LONG LEAD TIME SUPPLY RESOURCES CAN \nCONTRIBUTE TO MEETING THE CHALLENGE OF LARGE LOAD \nGROWTH \n22. Facilitating entry of short-lead time capacity supply resources is a critical element to \nimproving the responsiveness of the RPM to large load additions. While long-lead-time \nconventional generation assets form the majority of PJM’s existing capacity supply portfolio, \ncertain types of capacity supply resource are able to enter the market on shorter lead times that are \ncomparable to the 2-to-3-year development cycle for new datacenter load.  First, demand response \nresources of all types can typically enter service less than three years after the start of initial \ndevelopment of the resource.  Unlike most resource classes, demand response does not need to \npass through the interconnection queue.  When qualifying their resources for the RPM Base \nResidual Auction (“BRA”), demand response providers are allowed to offer on the basis of a \nprojected marketing plan rather than actual contracted DR customers, effectively deferring the \nmarketing and contracting of the underlying DR resources to the three-year period between the \nBRA and the delivery year.  And finally, the physical investment required to qualify a new demand \nresponse resource is typically extremely modest compared to generation resources and is thus not \nsubject to the equipment supply chain and permitting challenges that can delay more traditional \nresources.   \n23. Second, demand response provided by curtailment of new entrant datacenters themselves is \na particularly compelling possible source of new short-lead time supply because by definition it \nwill have the same lead time and similar size/scale to the new entrant load.  A recent study from \nthe Nicholas Institute at Duke University found that a significant amount of datacenter load can \nreliably integrate with electric systems across the country without the need to incrementally expand \ntransmission or generation infrastructure if that load agrees to curtail in a small percentage of \nhours.  Specifically, the study found that if new datacenter loads were willing to curtail in 0.5% of \nthe hours in which they would normally operate, 98 GW of new load nationally and 18 GW in \nPJM (equivalent to about 11% of PJM’s current peak) could be integrated without the need to \nincrementally expand transmission or generation.11 \n \n11 Tyler H. Norris, Tim Profeta, Dalia Patino- Echeverri, and Adam Cowie-Haskell, Rethinking Load Growth: \nAssessing the Potential for Integration of Large Flexible Loads in US Power Systems, February 2025.  \nhttps://nicholasinstitute.duke.edu/sites/default/files/publications/rethinking-load-growth.pdf"},{"page":16,"startToken":4577,"endToken":4966,"text":"14 \n \n24. Third, even if they are not able to curtail, new datacenter loads often have backup diesel \ngenerators or batteries that can allow them to serve as demand response if they can be run in \nresponse to an instruction by PJM and thus be deployed under the same conditions and rules as \nother emergency or pre-emergency demand response resources. \n25. And finally, storage resources, while they must pass through the interconnection queue, \ntypically have much shorter development cycles than other types of generation because they are a \nscalable, land-use-efficient, off-the-shelf technology with no fuel infrastructure needs and much-\nreduced permitting requirements relative to traditional generation.  Taken together, these pools of \npotential short-lead supply represent a significant potential tool for integrating large loads while \nmaintaining resource adequacy. \n26. And while long-lead conventional generation cannot immediately respond to “surprise” load \ngrowth as shown in Figure 1, it still can play a significant role in maintaining reliability over the \nlonger term under such conditions.  Long-lead-time generation is able to respond to major \ndirectional trends as they emerge in the fundamental data such as the load forecast, and in market \nprice signals.  But to do so to the greatest extent, such resources need the best, most accurate \nfundamental data possible along with a robust market that produces accurate competitive market \nprice signals. \nC. THE COMMISSION SHOULD SUPPORT POLICIES THAT FACILITATE \nENTRY OF NEW SUPPLY WITHOUT HARMING MARKETS \n27. Given this backdrop, there are several Commission actions and policies that could both \nfacilitate the addition of short-lead-time capacity supply when needed while also increasing the \nresponsiveness of longer-lead conventional resources, all without harming the underlying market. \n28. First, the Commission should support ongoing efforts by PJM to improve the accuracy of the \ncompetitive market prices that generators and other capacity resources rely on to signal whether \nto enter, remain in, or exit the market.  This should clearly include the RPM but also energy and \nancillary services markets as well, which are an important source of revenue for many capacity \nresources.  Generally, the Commission should support policies that drive market prices to \naccurately reflect the underlying fundamentals and reliability requirements of the system as they \nevolve over time.  Examples of this include PJM’s recent changes to the RPM which improved the \naccuracy of its reliability modeling and resource accreditation to reflect the marginal contribution"},{"page":17,"startToken":4966,"endToken":5416,"text":"15 \n \nof individual resources to system resource adequacy, and PJM’s upcoming efforts to improve the \nability of energy and ancillary services markets to accurately reflect PJM’s full operational reserve \nneeds in real time and thus avoid excessively conservative operations (including out of market \nresource commitments) that are not reflected in market prices.  Accurate and robust competitive \nmarket prices flowing from a consistent, stable and well-conceived market design are the bedrock \non which all investment in new supply depends, and the Commission should support PJM’s efforts \nat continuous improvement towards this goal. \n29. Second, while forecasting load in the current environment is challenging, Figure 1 and the \nPJM analytic work and committee proceedings surrounding load forecasting strongly suggest that \nimprovements to the load forecast are possible to provide more information, and more accurate \ninformation on future large load additions to market participants.  PJM currently relies on \nTransmission Owners to provide estimates of future large load additions to their systems, based \non their interactions with customers.  This process is not fully standardized across the various TOs, \nnor is it mandatory that all TOs provide an assessment of the large load situation in their zones \nevery year (even if there is no activity).  As a result, PJM must make a number of judgment calls \nabout whether to include specific loads, and the timing which with the loads enter the market, in \nforming the load forecast.  The large load situation may be uncertain in parts of the RTO because \nnot all TOs have provided an assessment.  This ultimately reduces transparency and confidence in \nthe resulting forecast.  Further, this process only occurs once per year, which means that in the \ncurrent environment of rapid load growth the load forecast becomes obsolete within a couple \nmonths of issuance.  Creating detailed, consistent, mandatory rules around when and how TOs \nmust report load additions to PJM would help improve the accuracy of and confidence in the load \nforecast, and increasing the frequency with which large load additions are reported to PJM from \nonce per year to two to four times per year would improve the responsiveness of the information \nfor market participants.  Finally, PJM should publicly provide as much detail and transparency as \npossible on the large load information provided to it by TOs and on any adjustments and \nassumptions it makes in incorporating the information into the load forecast.   \n30. Third, policies which shorten the development lead time of all capacity resource types would \nclearly improve the responsiveness of the market to load growth.  One clear lead time constraint \nis the generation interconnection queue.  While PJM has recently reformed its queue process from \nthe prior first-come, first-served approach to a batch-based cycle approach which is likely to"},{"page":18,"startToken":5416,"endToken":5840,"text":"16 \n \nimprove processing speed substantially, there are likely still many incremental improvements to \nthe general process that can be made as more experience is gained with the new approach.  In \nparticular, deployment of software automation tools shows potential to greatly reduce \ninterconnection study times. 12   PJM should prioritize the continuous improvement of the \ninterconnection queue process with the aim of improving the entry-to-agreement cycle time, \nreducing administrative complexity, and improving accuracy.  To this end, PJM has recently \nannounced a collaboration with Google and Tapestry to utilize artificial intelligence tools to \nstreamline the generation interconnection process.13  The Commission should be supportive of this \neffort and further efforts to improve the interconnection process. \n31. If improvements to the base interconnection queue process ultimately are not enough to \nsignificantly improve the queue cycle time for new capacity resources, PJM could also consider \nimplementing a “fast lane” process modeled on its Reliability Resource Initiative available on an \nongoing basis that would be triggered when PJM faces an acute need for new supply.  PJM has \nrecently begun implementing the one-time RRI to re-open the second transition cycle in its new \ninterconnection queue framework to a limited set of additional projects that did not originally enter \nthe queue in time for inclusion in the second transition cycle but nonetheless score highly on a set \nof metrics designed to select projects that are most likely to contribute highly to resource adequacy.  \nThe key metrics of likely project resource adequacy contribution include Unforced Capacity rating, \nEffective Load Carrying Capacity Rating, location in constrained regions, and several metrics \ntargeting development speed and certainty.  While the RRI is intended as a one-time process, the \nconcept has potential as an approach to accelerating the interconnection queue projects with a \nparticularly high resource adequacy contribution when the market has an acute need for accelerated \nsupply to meet a minimum acceptable standard of resource adequacy.  This could, for example, \ntake the form of separating queue cycles into a fast lane and slower lane based on weighting criteria \nsimilar to that used for RRI.  This queue separation could be implemented in the event that the \nRPM BRA clears at the price cap, indicating an acute need for additional supply to maintain \n \n12  See Letter from Commissioner Rosner to PJM regarding Interconnection Automation, March 17, 2025.  \nhttps://www.ferc.gov/media/commissioner-rosner-letter-pjm-interconnection-automation-letter \n13 PJM Interconnection, LLC News Release, “PJM, Google & Tapestry Join Forces to Apply AI To Enhance Regional \nPlanning, \nGeneration Interconnection,” \nApril 10, 2025.  \nhttps://www.pjm.com/-/media/DotCom/about-\npjm/newsroom/2025-releases/20250410-pjm-google-and-tapestry-join-forces-to-apply-ai-to-enhance-regional-\nplanning-generation-interconnection.pdf"},{"page":19,"startToken":5840,"endToken":6292,"text":"17 \n \nresource adequacy and could remain in effect for all cycles initiated from that point forward until \na subsequent BRA clears below the price cap.  Such an approach carries the potential for \ncompressing time to market for high resource adequacy value resources when needed while \nmaintaining a technology-neutral, non-discriminatory interconnection process.  Given the \npotential complexity of this concept, however, PJM’s primary initial focus should be on improving \nand accelerating the base queue process, particularly given that it is in the process of transitioning \nto the new cycle-based approach.  A fast lane process is a potential option in the longer term if an \neven more accelerated process is ultimately needed.  \n32. Fourth, as discussed above, demand response provided by new large loads themselves is a \nparticularly compelling source of short-lead supply because the size and entry time of that supply \nare by definition tied to the entry of the large load resources that themselves create the need for \nnew supply.  In its Answer PJM has identified facilitating demand response from large load \nresources resulting from either the ability to curtail the load or operate on-site backup generation \nas a potential option (“Option 8” in PJM’s listing) for addressing the resource adequacy concerns \nraised by the rapid growth of large loads.  In particular, PJM points to the need to harmonize PJM \nand EPA rules around the run-time limits for Reciprocating Internal Combustion Engines \n(“RICE”) to allow such resources to participate in the RPM as demand response resources to the \ngreatest extent possible.14  The Commission should support these efforts by PJM and others to \nmaximize the ability of large loads, whether co-located or otherwise, to provide demand response \ncapability to PJM markets, recognizing that in some instances, the state permit under which the \nfacility operates may further restrict run hours and thus the analysis is not as simple as just looking \nto change the EPA rules.   \n33. Finally, PJM and the Commission should carefully consider policies for contingent \nprocurement of short lead-time capacity supply resources in the event that the normal operation of \nthe RPM fails to clear enough supply to meet a minimum acceptable level of reliability in a given \nsingle BRA.15  While several potential approaches are possible, a workable potential design would \n \n14 PJM Answer at 20 and 69-70. \n15 PJM already has a backstop mechanism in the Tariff but it is considerably less responsive to emergent resource \nadequacy shortfalls that what I propose here.  The existing backstop mechanism is described in Tariff Attachment DD, \nSection 16.  The existing  mechanism is only triggered if the RTO clears at 1% below the Reliability Requirement for \nthree consecutive years and procures resources for multi-year terms in an amount needed to resolve the shortfall"},{"page":20,"startToken":6292,"endToken":6775,"text":"18 \n \nbe to trigger a supplemental procurement after the BRA if the BRA does not clear enough supply \nto meet a minimum acceptable level of reliability, which would be defined as a point no more than \nthe point where the demand curve transitions from downward sloping to flat at the price cap \n(currently set at 99% of the reliability requirement).  The supplemental procurement could be run \nseveral months after the conclusion of the BRA and would only be open to uncleared resources \nthat are able to come online for the BRA delivery year.  This supplemental procurement would \nhave a higher price cap (the specific value would need to be analyzed but could be as much as \ntwice as high or even more) than that of the BRA, but the quantity of supplemental supply cleared \nwould be limited to the amount needed to increase total supply to what is needed to achieve a \nminimum acceptable level of reliability.  The supplemental procurement would be limited to only \nthe delivery year of the triggering BRA (that is, it would not be a multi-year procurement) which \nwould in practice mostly limit it to relatively short-lead-time resources such as demand response \nand storage.16  The resulting price would only be paid to resources clearing in the supplemental \nauction (so that the resources that cleared the BRA would receive the BRA clearing price), and the \ncost of the supplemental auction would be allocated to loads under conventional allocation rules. \n34. This supplemental procurement concept is a departure from the basic single-clearing price \nRPM design in that it employs discriminatory pricing for high-cost resources that would normally \nbe unable to clear in the RPM due to the operation of the price cap.  While this is not an ideal \nmarket design feature, it is balanced by limiting the supplemental procurement to only those \ninstances where PJM has an acute resource adequacy shortfall, and limiting the quantity cleared to \nthe amount needed to achieve minimum acceptable resource adequacy. Limiting the procurement \nin this way greatly reduces the potential distortionary effects it may have on markets compared to \npolicies which are always in effect regardless of market conditions.  Further, the supplemental \nprocurement concept is effectively a workaround in response to another distortionary (albeit long-\nstanding) market feature – the price cap – which limits the ability of the market to procure very \nhigh-cost capacity when resource adequacy needs are acute.    That said, any design with multi-\n \nrelative to the trigger quantity.  Thus the existing mechanism is much less likely to be triggered in a timely fashion to \nresolve a resource adequacy shortfall than the supplemental procurement process I am proposing here. \n16 It may also be necessary to revise the RPM market power mitigation rules to address the potential for resources to \nhold back capacity from the BRA proper with the goal of accessing the higher prices in the supplemental procurement \nif it were triggered."},{"page":21,"startToken":6775,"endToken":7182,"text":"19 \n \ntiered pricing as proposed here requires extremely careful scrutiny to avoid distortions and \nunintended consequences, so it would be important to subject such a design change to a full \nstakeholder review per PJM’s processes.  The benefit is that the supplemental procurement \nprovides a safety valve that increases the ability of PJM to maintain an acceptable level of resource \nadequacy in the event that large load additions exceed the ability of the market to respond within \nthe normal parameters of the RPM design, while limiting customer costs by only paying above-\ncap prices to the relatively small slice of resources cleared in the supplemental procurement rather \nthan to the full capacity portfolio. If properly designed, these benefits likely outweigh the cost of \nmarket distortions of such a policy. \nD. THE COMMISSION SHOULD AVOID POLICIES THAT ARE UNDULY \nDISCRIMINATORY AND UNDERMINE MARKETS, INCLUDING PJM \nOPTION 6 AND OPTION 7 (AS PROPOSED) \n35. Two of the policy options outlined by PJM in their Answer, Option 6 and Option 7 (as \nproposed), are discriminatory and have distortionary and market-circumventing aspects that apply \nin a much broader set of circumstances than the supplemental procurement concept discussed \nabove.  Without modification, these policies discriminate in favor of new resources over existing \nones and are likely to harm the market, ultimately undermining reliability and increasing customer \ncosts. \n36. When considering how to handle large load additions, the Commission should generally \navoid policies that discriminate among similarly situated resources and circumvent, distort, or \notherwise undermine PJM markets.  Policies that offer discriminatory subsidies or advantages to \ncertain resource classes based on their vintage or the entities that they contract with are examples \nof this.  Such policies are counter-productive to the goal of ensuring resource adequacy in the face \nof rapid load growth because they undermine the very markets that are critically needed to bring \nforth supply to meet increasing demand, and thus ultimately risk a breakdown of markets \naltogether and a need to rely on high-cost, non-market approaches to an ever-increasing extent.  \nTo the extent that a policy does go outside the normal operation of markets it should be carefully \ndesigned to minimize market impacts and only go into effect when the reliability need is critical, \nsuch as the supplemental procurement concept I discuss above. \n37. Related to this, the Commission should also avoid policies that seek to ration new demand \nentry due to resource adequacy concerns either by outright denying or delaying demand entry or"},{"page":22,"startToken":7182,"endToken":7621,"text":"20 \n \nconditioning entry on the resource effectively bringing with it supply that matches its need.  \nFundamentally such policies harm markets and economic activity more generally because they \nimpede the ability of new demand that produces economic value to enter in a timely manner.  If \nnew entry is conditioned upon or incentivized  to bring new supply resources with the load, it is \nlikely to subsidize the new resources in a manner that will undermine and harm the market, , and \nwill discriminate against the supply (both new and existing) that is dependent upon the market. \n38. In violation of these principles, PJM’s Option 6 proposes that new large loads that build or \ncontract with new or otherwise-retiring capacity supply resources (whether co-located or not) \nwould secure favorable treatment for those supply resources in the PJM generator interconnection \nprocess.  PJM suggests that this favorable treatment could take the form of accelerated \ninterconnection studies and/or enhanced provisional interconnection service options that \naccelerate the ability of new generation to achieve commercial operation.17  The core problem with \nOption 6 is that it offers a thing of value – favored treatment in the generation interconnection \nprocess – in exchange for an action – contracting with a new large load - that is unrelated to the \nunderlying cost and resource adequacy aspects of a given capacity supply resource, and is only \navailable to a new resources that are able to secure a contract with a large load. \n39. Favorable interconnection queue treatment is unquestionably of high value in the present \ntight market environment: resources that get through the queue quicker incur lower financing costs \nduring development and are able to access market revenues sooner than resources without this \nadvantage.  But this advantage would only be conferred on a subset of resources that 1) are new \n(or would otherwise retire, although expedited interconnection service is not of value to retiring \nresources), and 2) are able to secure a contract with (or are self-built by) a new large load resource.  \nNeither of these features has any bearing on the ability of resources to physically supply capacity, \nnor does it have any bearing on their underlying cost of providing capacity.  Such treatment is \ndiscriminatory because it offers a benefit to a specific subset of new resources while denying that \nbenefit to existing resources and to new resources that are unable to contract with new large loads. \n \n  17 PJM Answer at 17.  PJM also suggests modifications to the State Agreement Approach to support large load \ninvestment in their jurisdictions as part of this option, but it is unclear if/how this change would be connected to large \nloads bringing their own new generation."},{"page":23,"startToken":7621,"endToken":8035,"text":"21 \n \n40. Consider two otherwise-identical gas combined cycle generation resources, one \ncontractually-tied to a new large load and one not.  The amount of Unforced Capacity awarded to \neach resource will be identical, and but-for any favored interconnection treatment awarded by PJM \nin connection with this proposed policy, their costs of construction and operation will be similarly \nidentical.  PJM Option 6 would nonetheless discriminate between these two resources, effectively \nlowering net cost of entry of the with-contract resource while not conferring such benefits to the \nother resource.  This approach is functionally equivalent to an out-of-market payment or subsidy \n(for the same resource adequacy services) which effectively lowers the cost of the with-contract \nclass and thus distorts and depresses market economics for all other resources (including all \nwithout-contract new resources and all existing resources).  The ultimate endpoint of such a policy \nis to drive all resource additions to seek contracts with large load and depress economics for other \nresources, leading to reduced new entry outside of the large load contract path and potentially \nretirements of existing resources.  Moreover, unlike the supplemental procurement concept that I \npreviously outlined, PJM Option 6 as proposed has no limitations that would restrict its application \nto only those instances when it is needed to avoid a resource adequacy shortfall, meaning that the \ndiscriminatory treatment and market distortions that it causes would be applicable under all types \nof market conditions.  It also potentially lays the foundation for entities serving large loads – which \nwould the incumbent TOs if they prevail in their tariff interpretation – to obtain an advantage in \nthe generation queue for proposed new build (developed by the TOs or others) that is tied to a \nspecific load rather than the market as a whole.   \n41. Option 6 is essentially a form of vintage pricing in that it offers an effective subsidy for a \nfavored class of new resources, while denying that subsidy to non-favored new resources and \nexisting resources.  This lowers the effective cost of procuring capacity from the favored resources \nrelative to their competitive level, which results in depression of market clearing prices below the \ncompetitive level within the RPM market clearing framework.  This depresses revenue for non-\nfavored resources with no offsetting benefits, which ultimately chills new entry from resources \nthat are unable to contract with new large loads and potentially leads to market exit by existing \nresources, undermining reliability and reducing overall market efficiency.  For these reasons, the \nCommission has indicated a preference for utilizing non-discriminatory, market-based solutions"},{"page":24,"startToken":8035,"endToken":8481,"text":"22 \n \nthat pay a single clearing price to similarly-situated resources to the greatest extent possible.18  \nThis principle remains correct and should lead the Commission to reject Option 6. \n42. PJM already has a market that is intended to bring forth new supply and a recently-reformed \nnon-discriminatory interconnection queue process.  And as discussed above, there are a range of \nimprovements that can be made to markets to improve their ability to accommodate new demand \nfrom large loads.  To the extent that PJM seeks to differentiate between resources within the queue \ncycle process, that differentiation should be made based on the underlying contribution to resource \nadequacy that resources provide, such as the factors considered in the RRI process, and not based \non contractual ties with specific loads that are unrelated to the underlying resource adequacy \ncontribution of the resource.  Or it should be targeted narrowly to address a demonstrated resource \nadequacy shortfall, as with the supplemental procurement discussed above.  Accordingly, Option \n6 should be rejected.  To the extent that the Commission nonetheless considers PJM Option 6 it \nshould at a minimum seek to limit its application to periods where the RPM clears at its price cap, \nand it should require that any generation resource benefiting from expedited interconnection under \nOption 6 be subject to the Minimum Offer Price Rule so as to reduce the detrimental price \nsuppressing effect of any subsidy. \n43. PJM’s Option 7, as proposed by PJM, presents similar conceptual problems as Option 6.  \nHowever, Option 7 can be revised and become a useful option that the Commission should \nincorporate into PJM’s tariff.  In Option 7, PJM proposes to offer expedited treatment of large load \nwith respect to the various local transmission studies needed to integrate as Network Load when \nnew loads would otherwise create a “resource adequacy supply/demand imbalance.”  To qualify \nfor this expedited treatment, large loads would need to offer to curtail (or run behind-the-meter \nbackup generation) at PJM’s request in response to reliability or resource adequacy issues on the \nsystem.19  The portion of the large load that is available for curtailment would be removed from \nthe demand curve and would not pay for capacity.  While the curtailment service provided by the \n \n18 PJM Interconnection LLC, 117 FERC ¶ 61,331 at P 141 (2006): \n“In a competitive market, prices do not differ for new and old plants or for efficient or inefficient \nplants; commodity markets clear at prices based on location and timing of delivery. . .  Such \ncompetitive market mechanisms provide important economic advantages to electricity \ncustomers. . .  This market result benefits customers, because over time it results in an industry \nwith more efficient sellers and lower prices.” \n19 PJM Answer at 18-19."},{"page":25,"startToken":8481,"endToken":8948,"text":"23 \n \nlarge load in Option 7 would not be offered into the RPM as demand response, it functionally has \na similar impact on the RPM because the associated load is removed from the RPM demand \ncurve.20  PJM states that this treatment would be “transitional” in that a given large load could only \nelect the treatment until the “resource adequacy supply/demand imbalances” associated with that \nparticular load are resolved, without providing any clarification as to how such a determination \nwould be made.  Option 7 thus effectively seeks to condition entry for new large loads on providing \ndemand response for as long as PJM determines there is a “resource adequacy supply/demand \nimbalance.”  As written, PJM appears to claim unfettered discretion to decide what constitutes a \n“supply/demand imbalance” and how long it lasts, with the further potential for political pressure \nto be brought to bear on any PJM decisions in this regard. This harms markets because the \nfunctional effect of Option 7 as written is that PJM would be conditioning the availability and term \nof valuable load integration rights on its subjectively determined view of resource adequacy.  \nResource developers that look to market price signals to decide whether to enter would rightfully \nbe concerned if PJM retained the ability to decide when, in its discretion, resource adequacy supply \nand demand balance had been achieved.  The very unpredictability of a core element of PJM’s \nproposal will undermine the price signal generated by the capacity market. \n44. Providing PJM with the capability to curtail large loads could in some cases provide benefits \nin terms of resolving local and regional transmission reliability issues related to integrating the \nlarge load.  If curtailment of the load would allow the new load to provisionally integrate with the \nsystem prior to completing some of the investments needed to otherwise integrate as network load, \nthen it would be reasonable to allow the load to integrate and qualify as network load on an interim \nbasis prior to completion of the upgrades, so long as the load offers PJM curtailment rights \nsufficient to resolve the operational concerns during the period prior to the completion of the \ntransmission upgrades needed to reliably serve it.  But the eligibility and term of such a transitional \nservice should be directly linked to the primary service being provided – transmission service – \nand not based on resource adequacy concerns as PJM proposes with Option 7.  Specifically, only \nloads that trigger transmission security violations that are resolved by curtailment should be \n \n20 The Option 7 curtailment service is not fully equivalent to demand response because demand response receives a \nDR-specific Effective Load Carrying Capacity rating in determining its UCAP, while simply removing load from the \ndemand curve shifts the demand curve inward by the load’s peak load contribution multiplied by the forecast pool \nrequirement."},{"page":26,"startToken":8948,"endToken":9412,"text":"24 \n \neligible for this type of treatment, and the term should be limited to the time needed to construct \nthe required transmission upgrades needed to resolve the violations.  But these benefits are separate \nand distinct from resource adequacy – PJM’s resource adequacy construct does not reflect or seek \nto address local transmission security issues but is rather concerned with the ability to meet load \nduring peak conditions with available capacity supply resources, which is a different problem and \nanalysis entirely.  PJM’s Option 7 as written inappropriately ties these two separate concerns \ntogether in a manner that is likely to distort the capacity market because it seeks to use the \ntransmission service policy as a means of rationing load entry in the face of resource adequacy \nconcerns.  The appropriate policy would be to keep transmission security and resource adequacy \nseparate.  If a large load’s ability to curtail provides benefits with respect to transmission security, \nthen those benefits should be reflected in the load integration process but should not act as a bar \nto entry when PJM determines that there are resource adequacy concerns.  And if a large load’s \nability to curtail allows it to contribute to resource adequacy, then it should offer that service as a \ndemand response capacity resource. \n45. It should be noted however, that when comparing PJM’s Options 6 and 7, Option 7 rates as \na more narrow intervention than Option 6 because it is limited in scope to only self-supplied \ndemand response from new entrant large loads, rather than any type of contracted or self-supplied \nnew capacity supply located anywhere on the grid as in Option 6.  Moreover, Option 7, unlike \nOption 6, is “transitional” in that it would only be in effect for the duration of a “supply/demand” \nbalance as determined by PJM.  As such, my opinion is that Option 7, even in the currently \nproposed form, is likely to be less damaging to the market than Option 6, although the specifics of \nimplementation, which have not been fully fleshed out in PJM’s Answer, matter a great deal in \nthis judgment. \n46. Beyond PJM’s proposals, various other types of market interventions are possible in response \nto the rapid growth of large load on the PJM system, both co-located and otherwise.  Concepts that \nhave been raised over the years in response to resource adequacy concerns include the building of \nregulated generation, state-backed contracts for new generation, and restrictions or rationing of the \nability of load to interconnect with the system above and beyond the normal load integration \nprocess.  Without getting into the details, the Commission should be wary of proposals that seek \nto intervene in, subsidize, or otherwise undermine PJM competitive markets.  The benefits of PJM \nmarkets are maximized when markets are allowed to respond to price signals and changes in"},{"page":27,"startToken":9412,"endToken":9811,"text":"25 \n \nfundamentals.  Policies which pre-empt, mask, or otherwise intervene in this response degrade the \nefficacy of markets over time and ultimately raise costs for consumers.  Further, all load has a right \nto seek service on the PJM system, and PJM has an existing non-discriminatory process for \nintegrating new load; while improvements to that process are possible the Commission should not \nsupport efforts to add discriminatory elements to it.   \nIII. LARGE LOAD INTEGRATION COSTS VARY WIDELY DUE TO SIZE AND LOCATION  \n47. I have analyzed the estimated costs incurred by PJM TOs to integrate new large loads onto \nthe system.  The purpose of this analysis is to support discussion of the appropriate approach to \nallocating and ultimately recovering these costs.  I do not myself offer any specific policy \nrecommendations on this topic – I leave that to others – but rather present the data on load \nintegration costs and provide observations on the main empirical trends that can be gleaned from \nit. \n48. As PJM discusses in their answer, when a singular new large load such as a datacenter seeks \nto interconnect with the PJM system and initiate transmission service, there are a number of steps \nthat PJM and others must take in order to ensure that the load can be integrated while preserving \ntransmission system reliability.21  First, the local TO must conduct what PJM refers to as a \n“Transmission Owner load integration study” to “identify local upgrades needed to reliably \naccommodate the load based on local transmission planning criteria.”22  This study will typically \nresult in a set of proposed upgrades that take the form of a Supplemental Project presented to the \nTransmission Expansion Advisory Committee (“TEAC”) or Sub-Regional RTEP Committees.  \nSuch upgrades typically take the form of a transmission line(s) to the site of the new load, \npotentially a new substation or upgrades to an existing substation, and sometimes more remote \nsystem reinforcements to reliably accommodate the load within the TO’s zone.  Once the TO has \nproposed a solution in the form of a Supplemental Project, PJM conducts a “PJM Do No Harm” \nstudy to “evaluate whether a proposed Supplemental Project will adversely impact the reliability \nof the Transmission System as represented in the planning models used in other PJM reliability \nstandard studies.”23  If the PJM Do No Harm study finds that the proposed Supplemental Project \n \n21 PJM Answer at 6-8. \n22 Ibid. at 7.  \n23 Ibid."},{"page":28,"startToken":9811,"endToken":10238,"text":"26 \n \ncauses violations, PJM will propose additional transmission upgrades as needed to resolve them.  \nThe upgrades that result from Supplemental Projects associated with the new load, as well as any \nadditional upgrades resulting from the PJM Do No Harm Study are fully cost-allocated to loads \nwithin the local TO’s zone and are not subject to PJM Board approval.   \n49. As PJM further discusses, integration of new large loads on the system may result in \nadditional costs beyond those revealed by the Transmission Owner load integration study and the \nPJM Do No Harm study because new loads are ultimately integrated into the PJM load forecast, \nwhich is an input into the PJM Regional Transmission Expansion Plan (“RTEP”) process.24  Large \nload additions may in part drive a need for additional baseline system projects identified through \nthe RTEP.  These projects are identified through a holistic system-level analysis, however, and are \nnot explicitly tied to any particular new load or other discrete change in system topology. \n50. The TEAC and/or Sub-Regional RTEP Committees review all proposed Supplemental \nProjects associated with the integration of new large loads.  These reviews describe the location, \nsize, and development timetable of the new load, the nature of the proposed transmission solution \nto integrate the load, and an estimated cost and timeline to implement the solution.  If the PJM Do \nNo Harm study reveals the need for additional upgrades, then similar information is provided for \nthem as well.  The various proposed Supplemental Projects for individual new large loads are \npublicly available on PJM’s website in the sections for the relevant committees. \n51. I have gathered information on the integration costs of individual large loads in the form of \nSupplemental Projects proposed in the relevant PJM Committees from 2022 through the present \n(as of April 2025).25  The relevant data for each new large load includes its projected size (in \nsummer peak megawatts) and the estimated cost of transmission investments needed to reliably \nintegrate the load as determined by the Transmission Owner Load Integration and  PJM Do No \nHarm studies.  The results of this analysis are shown below in Figure 6: \n \n24 Ibid. at 7-8. \n25 The specific data utilized in forming this data includes various TO-specific presentations on Supplemental Projects \nto the Transmission Expansion Advisory Committee (located at https://www.pjm.com/committees-and-\ngroups/committees/teac), and the Sub-Regional RTEP Committees for the Western, Mid-Atlantic, and Southern Sub-\nRegions \n(located \nat \nhttps://www.pjm.com/committees-and-groups/committees/srrtep-w, \nhttps://www.pjm.com/committees-and-groups/committees/srrtep-ma, and https://www.pjm.com/committees-and-\ngroups/committees/srrtep-s, respectively)."},{"page":29,"startToken":10238,"endToken":10550,"text":"27 \n \nFigure 6 \n \nEach point shown on Figure 6 shows the integration cost and size of a discrete new large load \nseeking to integrate with the PJM system.  The data includes 144 load-integration supplemental \nprojects in total covering 42.3 gigawatts of summer peak load with a total cost of $8.5 billion.  The \nintegration costs include the estimated cost of Supplemental Projects identified through the \nTransmission Owner load integration study as well as the estimated cost of any additional projects \n(if any) identified through the PJM Do No Harm study.26  The costs do not include any regional \nprojects identified through the RTEP process (which cannot be tied to any specific discrete new \nload).  I have assumed that any singular load with an ultimate size of 50 megawatts or more is a \nlarge load for the purposes of this analysis. \n52. The trendline shown on Figure 6 is the result of a simple linear regression estimating \nintegration cost as linear function of size.  The trendline indicates that there is both a fixed and \nsize-dependent component to expected large load integration costs, with larger loads driving higher \ncosts.  Based on the trendline, each 100 MW of load size on average increases integration cost by \nabout $9.5 million, with a fixed, size-independent component of about $31 million.  Thus, for \n \n26 In certain cases, multiple individual large loads may trigger a shared project.  In these instances, I have allocated \nthe cost of the shared project equally across all large loads identified as contributing to the need. \n0\n50\n100\n150\n200\n250\n300\n350\n400\n0\n500\n1000\n1500\n2000\n2500\nIntegration Cost ($ millions)\nLoad Size (MW)\nLarge Load Integration Cost ($M) versus Size (MW) in PJM\n2022 through April 2025\nTrend:\nCost = $0.095M x Size (MW) + $31.3M\nTotals:\n144 projects\n42.3 GW of load\n$8.5 B total cost"},{"page":30,"startToken":10550,"endToken":10916,"text":"28 \n \nexample, the expected integration cost of a 100 MW large load is about $41 million ($9.5M size-\ndependent plus $31.3M fixed), while the expected integration cost of a 1,000 MW large load is \nabout $126 million ($95M size-dependent plus $31.3M fixed). \n53. There is a large amount of variation in the integration costs among large loads of similar \nsize.  The trendline relating integration cost to size only explains about 25% of the variation in \nintegration costs among individual new large loads. 27  Among loads in the 100 MW range \nintegration costs can range from close to zero to as high as $180 million.  For very large loads in \nthe 1,000 MW range, integration costs can range from as low as $70 million to as much as $240 \nmillion.  In general, this high degree of variation is present across the full range of load sizes. \n54. The high degree of size-independent variation in large load integration costs suggests that \nlocational factors specific to each load are a major additional driver of cost and can either result in \nmuch lower or higher costs than would be expected on average for a load of a given size.  A review \nof the nature of the actual supplemental projects that form this data confirms that this is the case.  \nKey factors driving load integration costs include the location of the large load site relative to \nexisting transmission elements, the terrain and land use around the large load site, whether \nintegrating the load requires construction of a new substation or allows use of an existing \nsubstation, and whether or not the existing transmission system in the local region is robust enough \nso as not to require additional reinforcements to reliably integrate the load.   \n55. It is clear that location matters a great deal for and can cause the cost to vary in idiosyncratic \nand unpredictable ways.  This location-dependence suggests that sending the correct incentives via \ntransmission rates to new large loads to locate efficiently is important for minimizing total system \ncosts.   \n56. This concludes my affidavit. \n \n \n \n27 More technically, the R-squared for the linear regression summarized by the trendline shown on Figure 6 is 0.25."},{"page":31,"startToken":10916,"endToken":10916,"text":""},{"page":32,"startToken":10916,"endToken":10921,"text":"Attachment A to Patterson Affidavit"},{"page":33,"startToken":10921,"endToken":11124,"text":"Aaron T. Patterson Testimony and Expert Reports \nDate \nOn Behalf Of \nCommission/Court \nSubject Matter \nDocket/Case Number \nJan-25 \nConstellation Energy FERC \nAffidavit – Treatment of RMR \nResources in PJM Capacity \nMarket \nER25-682-000 \nFeb-24 \nNuclear Energy \nInstitute \nU.S. Department of \nthe Treasury \nExpert Report (with Frank \nHuntowski and John \nHutchinson) – “Assessing the \nIncrementality Requirement \nof Treasury’s Proposed 45V \nRegulations” \nREG-117631-23 \nDec-23 \nConstellation Energy FERC \nReply Affidavit – PJM \nCapacity Market Reforms \nER24-99-000 and ER24-98-000 \nNov-23 \nConstellation Energy FERC \nAffidavit – Market Monitor \nComplaint regarding PJM \nCapacity Market \nEL24-12-000 \nNov-23 \nConstellation Energy FERC \nAffidavit – PJM Capacity \nMarket Reforms \nER24-99-000 and ER24-98-000 \nNov-22 \nConstellation Energy FERC \nJoint Affidavit (with Michael \nM. Schnitzer) – New England\nWinter Gas-Electric Forum\nAD22-9-000 \nJune-21 \nExelon Corporation \nFERC \nReply Affidavit – PJM \nCapacity Market Seller Offer \nCap \nEL-19-63-000 \nMay-21 \nExelon Corporation \nFERC \nAffidavit – PJM Capacity \nMarket Seller Offer Cap \nEL19-63-000 \nNov-20 \nExelon Corporation \nFERC \nDeclaration (with Michael M. \nSchnitzer) – NYISO Capacity \nMarket Buyer Side Mitigation \nEL21-07-000 \nNov-19 \nExelon Corporation \nState of New York \nPublic Service \nCommission \nExpert Report – “Impact of \nCarbon Pricing on Potential \nExpanded Buyer-Side \nMitigation in the NYISO \nMarkets” \n19-E-0530\nDec-17 \nExelon Corporation \nPublic Utility \nCommission of Texas \nExpert Report (with David \nColeman) – “Economic \nEquilibrium and Reliability in \nERCOT” \nProject No. 47199"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":3,"endAt":5,"startToken":0,"endToken":58},{"p":3,"at":5,"title":"I. QUALIFICATIONS, BACKGROUND, AND PURPOSE OF AFFIDAVIT","method":"printed heading","endPage":3,"endAt":62,"startToken":58,"endToken":65},{"p":3,"at":62,"title":"A. QUALIFICATIONS","method":"printed heading","endPage":3,"endAt":1216,"startToken":65,"endToken":246},{"p":3,"at":1216,"title":"B. BACKGROUND AND PURPOSE OF AFFIDAVIT","method":"printed heading","endPage":6,"endAt":2179,"startToken":246,"endToken":1566},{"p":6,"at":2179,"title":"II. RESOURCE ADEQUACY ISSUES RELATED TO ADDITIONS OF LARGE LOADS TO THE PJM","method":"printed heading","endPage":6,"endAt":2264,"startToken":1566,"endToken":1580},{"p":6,"at":2264,"title":"A. RESOURCE ADEQUACY CONCERNS RELATED TO LARGE LOAD","method":"printed heading","endPage":15,"endAt":6,"startToken":1580,"endToken":4171},{"p":15,"at":6,"title":"B. BOTH SHORT AND LONG LEAD TIME SUPPLY RESOURCES CAN","method":"printed heading","endPage":16,"endAt":1477,"startToken":4171,"endToken":4796},{"p":16,"at":1477,"title":"C. THE COMMISSION SHOULD SUPPORT POLICIES THAT FACILITATE","method":"printed heading","endPage":21,"endAt":823,"startToken":4796,"endToken":6903},{"p":21,"at":823,"title":"D. THE COMMISSION SHOULD AVOID POLICIES THAT ARE UNDULY","method":"printed heading","endPage":27,"endAt":454,"startToken":6903,"endToken":9480},{"p":27,"at":454,"title":"III. LARGE LOAD INTEGRATION COSTS VARY WIDELY DUE TO SIZE AND LOCATION","method":"printed heading","endPage":33,"endAt":1646,"startToken":9480,"endToken":11124}]}