{"document":{"slug":"rec-20250423-5262-5","title":"Exhibit 4 (Herling)","issued":"2025-04-23","accession":"20250423-5262","docket":"EL25-49-000","group":"PJM co-location compliance","filer":"Constellation Energy Generation, LLC","kind":"attachment","file":"sources/filings/text/20250423-5262_005.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20250423-5262","tier":"record","parent":"rec-20250423-5262","sha256":"00da0b435184c0d15914c4063798d50d0580eb9640e65a3d7c03512561585d09","pages":20,"tokens":5002,"emptyPages":[],"textThemes":["colo","study","cost"]},"pages":[{"page":1,"startToken":0,"endToken":6,"text":"EXHIBIT 4\nAFFIDAVIT OF STEVEN HERLING"},{"page":2,"startToken":6,"endToken":57,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \nPJM Interconnection, L.L.C., et al. \n \n \nLarge Loads Co-Located at Generating Facilities \n \n \nConstellation Energy Generation, LLC. \n \nv. \n \nPJM Interconnection, L.L.C. \n) \n \n \n) \n \n \n) \n) \n) \n) \n) \nDocket No. EL25-49-000 \n \n \nDocket No. AD24-11-000 \n \n \nDocket No. EL25-20-000 \n      (Consolidated) \n \n \n \n \n \n \nAFFIDAVIT OF  \nSTEVEN R. HERLING \n \nApril 23, 2025"},{"page":3,"startToken":57,"endToken":335,"text":"1 \n \nI. \nQUALIFICATIONS AND PURPOSE OF AFFIDAVIT \n \n1. \nMy name is Steven R. Herling.  I am currently President of Herling Power Grid \nConsulting, Inc. (“HPGC”), which provides consulting services related to planning, operational, \nand regulatory issues facing the electric power industry. My business address is 513 William \nSalesbury Drive, Downingtown, PA 19335. Through HPGC, I have served as a subcontractor to \nother consulting firms, such as The Brattle Group and Charles River Associates, advising on \nprojects related to off-shore wind development and utility investment opportunities. I have also \nadvised clients on generator and merchant transmission interconnection issues as well as a range \nof PJM Interconnection, L.L.C. (“PJM”) Regional Transmission Expansion Plan (“RTEP”) \nprocess issues. \n2. \nIn July 2020, I retired from PJM, where I had been employed since May 1990. At PJM, I \nheld a number of positions in the Operations and Planning Divisions and was promoted to Vice \nPresident of Planning in May 2004. While at PJM, I contributed to or led initiatives that resulted \nin a wide range of milestone achievements in PJM’s evolution and growth as a regional \ntransmission organization (“RTO”), including the creation of the RTEP process, the development \nof procedures and standard terms and conditions for generation and merchant transmission \ninterconnections, the development of the competitive transmission process, and the reliability \nand resource adequacy aspects of successive integrations of additional control areas that more \nthan doubled the size of the PJM market area. In addition to my work for PJM, I contributed to a \nwide range of activities for the North American Electric Reliability Corporation (“NERC”) and \nserved on various regional industry working groups and committees addressing reliability and \nplanning matters."},{"page":4,"startToken":335,"endToken":642,"text":"2 \n3.\nPrior to PJM, I worked for the General Public Utilities Service Corporation (“GPU”) for\nthree years in systems operations, where I was responsible for dispatcher training and \ncertification, operations and planning activities, and energy management system and operational \nsupport tools. Prior to GPU, I worked for the American Electric Power Service Corporation \n(“AEP”) for eight years in bulk transmission planning. In that position, I performed a range of \npower system analyses related to the AEP 765 kV transmission system, generator and circuit \nbreaker dynamic modeling, and the mechanical behavior of turbine-generator shaft systems. \n4.\nI hold a Bachelor of Science in Electric Power Engineering and a Master of Engineering\nin Electric Power Engineering, both from Rensselaer Polytechnic Institute.1 \n5.\nI have testified on a number of occasions in proceedings before the Federal Energy\nRegulatory Commission (“FERC”), as well as various state commissions and legislative task \nforces, on matters relating to system planning and reliability issues.  I have also testified in \ntransmission line Certificate of Public Convenience and Necessity (“CPCN”) proceedings in \nPennsylvania, Maryland, West Virginia, Virginia, and New Jersey, and I have testified in a \ntransfer of ownership case for a public utility in Kentucky. \n6.\nI have been asked by Constellation Energy Generation, LLC (“Constellation”) to provide\nan affidavit that discusses, from an engineering perspective, transmission and related services \ntaken by load under the PJM Tariff for a range of co-located load configurations based on the \noptions discussed in the Answer of PJM Interconnection, L.L.C. filed on March 24, 2025, in the \nabove-captioned consolidated proceedings (“PJM Answer”). The PJM options range from load \nconnected to the grid, separate from any generating resources, to a variety of co-location \nconfigurations. This affidavit and the opinions expressed herein are based on my experience in \n1 Please refer to my resume attached as Attachment A."},{"page":5,"startToken":642,"endToken":959,"text":"3 \n \nthe field of electric power system planning, operation, and regulation and my knowledge of the \nelectric power industry. My opinions and analyses are subject to change if additional information \nbecomes available. \n7. \nMy affidavit will describe eight possible configurations of large co-located load projects, \nidentified by PJM as Option 1 through Option 8, to provide an engineering basis for a discussion \nof the transmission and related services taken, or not taken, by co-located loads. For each \nconfiguration, I will discuss the extent to which the configuration imposes incremental burden on \nthe PJM system with respect to the services and the circumstances under which the co-located \nload takes service. My conclusions are further summarized at the end of the affidavit. \nII. \nDESCRIPTION OF CO-LOCATION PROJECT OPTIONS \n \n8. \nAs a general matter, co-located loads rely on direct connection to co-located generation \nfacilities for the delivery of energy without reliance on grid transmission facilities or Network \nIntegration Transmission Service (“NITS”).   \n9. \nA number of the PJM options, however, contemplate continued connection of the load to \nthe grid, even following the loss of the co-located generating facility. These include PJM Options \n1, 2, 3, 6, 7, and 8. In those cases, the co-located load will rely on the grid and NITS for energy.  \n10. \nIn contrast, in PJM Option 4, the co-located load will not be able to draw energy from the \ngrid. Instead, fully redundant relaying will trip the co-located load in the event of (i) the \nunplanned loss of the co-located generation or (ii) a reduction in generation level, thereby \npreventing the co-located load from being able to draw energy from the grid.  In such \nconfigurations, no energy will flow under any circumstances from the co-located generation \nfacilities over grid transmission to the co-located load and, therefore, no grid transmission \nservice is used by or required by the co-located load. The same fully redundant relaying is true of"},{"page":6,"startToken":959,"endToken":1265,"text":"4 \n \nPJM Option 5 with the limited exception of the load taking back-up service, if permitted by PJM, \nfollowing the loss of the co-located generation resource, from generating resources to which it is \nnot directly connected. \nPJM Options: \n11. \nPJM’s Option 1 is based on load connected to the grid at a separate Point of \nInterconnection from any generator. The load is Network Load and any generator that might be \ncontractually serving the load is a capacity resource. The load and generation may be physically \nlocated at the same location, but they are electrically connected to the grid, separately, and not \nelectrically co-located. \n12. \nPJM’s Option 2 is based on co-located load and generation connected to the grid at the \nsame Point of Interconnection, but separately metered. The load is Network Load and the \ngenerator is a capacity resource. While physically co-located at the same Point of \nInterconnection, Option 2 treats the load and generator as separate entities with respect to all \nservices, regardless of any bilateral arrangements that may exist.   \n13. \nPJM’s Option 3 is based on the existing Behind the Meter Generation (“BTMG”) \nconstruct, where load is the primary customer, netting with a co-located generator at the same \nPoint of Interconnection.  Electrically, the physical connection of load and generation behind the \nsame Point of Interconnection is the same in Option 3 as in Option 2. The load is Network Load \nwhen it consumes energy in excess of what the co-located generator produces, and the portion of \nthe generator designated as BTMG is not a capacity resource.  \n14. \nPJM’s Option 4 is based on co-located load and generation connected to the grid at the \nsame Point of Interconnection. The load is located behind the generator with protection \nmechanisms in place to prevent the delivery of energy from the grid to serve the load when the"},{"page":7,"startToken":1265,"endToken":1429,"text":"5 \n \nNuclear Generator  #1\nNuclear Generator  #2\nNew transformers \n34.8kV\nNew BTM equipment\nNew BTM equipment\nNormally Open \nManual Cross-tie\nGRID TRANSMISSION SYSTEM 1\nGRID TRANSMISSION SYSTEM 2\n34.5 kV\nassociated generator is out of service. The load is not Network Load, and the portion of the \ngenerator committed to the load is not a capacity resource. \n15. \nI include Figure 1 as a sample design to illustrate such a co-located load configuration \nassociated with a nuclear generating facility with two generating units.  In Figure 1, the co-\nlocated load is served at 34.5 kV on a number of new buses, connected, behind-the-meter, by \nmultiple transformers stepping down from generator step-up transformer high-side voltages to \n34.5 kV. The co-located load can be served from either one of the generating units or split and \nserved by the two units.    \n \n \n \n \n \n \n \n \n \n \n \n \n \n \nFigure 1 - One-Line Diagram of a Sample Co-Located Load Project Incorporating Redundant Relaying to \nFacilitate Disconnection from the Grid During Generation Outages"},{"page":8,"startToken":1429,"endToken":1746,"text":"6 \n \n16. \nAs a point of reference, Constellation has previously submitted co-located load projects \nsimilar in configuration and design to PJM’s Option 4 or Option 5 to PJM for evaluation through \nNecessary Studies, as provided for in the PJM Tariff, to determine whether planned \nmodifications will have a permanent material impact on the transmission system and to identify \nthe additions, modifications, or replacements to the transmission system, if any, that are \nnecessary. \n17. \nPJM’s Option 5 is the same as Option 4 from a configuration perspective, including \nprotection mechanisms, but allows for back-up service to be provided to the load from the PJM \ngrid. Under PJM’s description, such back-up service would only be provided with PJM’s \napproval and such approval could be denied or withdrawn by PJM based on system conditions.   \n18. \nOption 6 is similar to Option 2, except that under PJM’s proposal the new load brings \nnew generation to the grid with which it will be co-located to obtain the opportunity for faster \ninterconnection. The new load does not include the type of special protection relay scheme \nenvisioned in Option 4. \n19. \nPJM’s Option 7 is similar to Option 2, except that the service received by the load will be \ninterruptible. The status of the generator does not change, i.e., the generator can remain a \ncapacity resource. The load receiving interruptible service is separately metered but does not \ninclude the type of special protection relay scheme envisioned in Option 4.  \n20. \nPJM’s Option 8 is similar to Option 2, but provides the opportunity for the co-located \nload to participate in an expanded form of Demand Response. \nIII. \nPROTECTIVE RELAY SCHEMES \n21. \nAs discussed, Options 4 and 5 will require protective relay schemes that will prevent load \nfrom drawing energy from the grid. These protective relay schemes can be designed so that there \nare completely redundant primary and backup protective schemes to perform this function."},{"page":9,"startToken":1746,"endToken":2088,"text":"7 \n \n22. \nSuch a configuration uses electric current transformers to measure the flow of power \nfrom between the co-located load and the grid, which is communicated with relays via fiber optic \nchannels that will trip behind-the-meter circuit breakers associated with the co-located load when \nthe electric current transformers sense the power flow from the grid to the co-located load. This \ncan occur in the event of the sudden loss of the co-located generating unit or following a \nreduction in the level of energy produced by the co-located generating unit so that it is not fully \nsupplying the co-located load.  There are two circuit breakers placed in series supplying the co-\nlocated load, so that if one fails, the second will still open the circuit. Each circuit breaker has \ntwo trip coils such that either the primary or backup protective relay can successfully trip the \nload. All elements of the protective scheme, including the electric current transformers, the fiber \nchannels, and the trip relays, are redundant resulting in a single-failure-proof design.  The \nprotective scheme referred to above in Figure 1 will trip the co-located load from the grid in \nthree cycles (0.05 seconds) following a trip of the co-located generating unit or after sensing that \nthe energy produced by the co-located generating unit has been reduced to a level such that the \nco-located load is attempting to draw energy from the grid. \n23. \nPJM raises the concern that “[t]he challenge with an arrangement where there is load \nlocated behind a generator Point of Interconnection lies in how such a configuration or special \nprotection scheme could be designed to never fail . . . .”2  PJM plans for N-1 conditions followed \nby a single protection system failure, such as a stuck breaker, and requires transmission system \nupgrades when such events result in violations of applicable NERC standards. In this instance, a \nstuck breaker becomes a second contingency. In most instances, the solution to stuck breaker \ncriteria violations is to add a redundant series breaker, making the failure of both breakers \n \n2 PJM Answer at 44."},{"page":10,"startToken":2088,"endToken":2410,"text":"8 \n \nfollowing an N-1 event a third contingency. PJM does not plan for or require upgrades for such \nthird contingencies, nor would it be reasonable to do so, short of events that would result in a \ncascading outage of grid facilities. The protection system, discussed above, is fully redundant \nand, while it cannot be guaranteed to never fail, it is unreasonable to treat the failure of both \nprimary and secondary relay system facilities following the loss of a generator as anything other \nthan a third contingency.  In fact, when I was directing transmission planning for PJM, I cannot \nthink of an instance in which we treated such a situation otherwise.  In practice, protection \nschemes are regularly employed on the PJM transmission system, and the successful operation of \nsuch protective systems is a common observance within PJM.  There is no technical reason from \nmy perspective to expect that protective relaying in the context of co-location would perform any \nless reliably.  If anything, suggesting that protective relaying – a common and technically sound \ntool for managing the grid – cannot be used in the context of co-located configurations or must \nbe designed to a different standard strikes me as an unduly discriminatory position.  \nIV. \nGRID SERVICES \n24. \nWith the different technical configurations for co-located load in mind, I discuss below \nthe various transmission and related services and the extent to which the co-located load imposes \nincremental burden on the PJM system with respect to the services it takes or does not take.  \na. Network Integration Transmission Service \n25. \nNITS is the means by which Network Load in the PJM region is served over the PJM \ntransmission system, utilizing identified Network Resources as well as other non-designated \ngeneration resources.3 The PJM RTEP ensures the on-going reliability and ability of the PJM \ntransmission system to provide service to load customers via NITS and long-term firm point-to-\n \n3 PJM Tariff, Part III, Sections 28.1 and 28.3."},{"page":11,"startToken":2410,"endToken":2743,"text":"9 \n \npoint transmission service. Transmission facilities necessary to connect new load customers to \nthe grid are identified and integrated into the RTEP to ensure the integrity of the models used in \nanalyses and the on-going reliability of service to all customers.  \n26. \nIn PJM’s Option 1, a new Network Load would be fully dependent on NITS for delivery \nof capacity and energy, would be included in the PJM load forecast, and would be modeled and \nplanned for in future RTEP cycles. This is the manner in which the vast majority of load is \nconnected to the PJM grid. \n27. \nIn PJM’s Option 2, a new load and the co-located generator are separately metered. The \nload is considered Network Load and the generator is a capacity resource. While energy will \nflow directly from the generator (when it is in service) to the load without flowing over the \nfacilities of the PJM grid, the load would be dependent on NITS for delivery of capacity and \nenergy at some times, would be included in the PJM load forecast, and would be modeled and \nplanned for in future RTEP cycles. The dependence of the load on NITS covers all \ncircumstances, whether the generator is in or out of service.  \n28. \nPJM’s Option 3 is based on the existing BTMG construct and can involve two \nconfigurations where load and generation can be co-located or connected via the distribution \nsystem of a municipal utility.  The existing PJM Tariff bills for transmission and related services \nbased on the netting of such load with its BTMG.  \n29. \nIn PJM’s Option 4, a new load is co-located behind a generating resource. As shown in \nFigure 1 above, the connection is radial, behind the Point of Interconnection of the generator. \nTherefore, energy can only flow directly from the co-located generator’s grid voltage substations \nto the behind-the-meter co-location project’s substations (at the same grid voltage level) and, \nfrom there, over step-down transformers to the co-located load connected at 34.5 kV. There is no"},{"page":12,"startToken":2743,"endToken":3097,"text":"10 \n \nother transmission path from the co-located generation to the co-located load, i.e., there is no \nparallel path for energy to flow out from the co-located generator onto the transmission grid and \nback, eventually, to the co-located load.  Because the associated special-purpose relay scheme \nwill remove the co-located load from the grid in the event of a sudden loss of the generating \nfacility, no energy will flow to the co-located load over the transmission grid following a \ncontingency; no new transmission infrastructure will be required on the grid to facilitate the \ninterconnection and to ensure reliability for existing load customers other than what might be \nidentified in the Necessary Study performed to determine whether the generator’s modification \nto serve the behind-the-meter load has any reliability impact, and no NITS service will be \nprovided by the grid to the co-located load. Excess energy, beyond the level required by the load, \nwill flow from the generator to the grid. Accordingly, the load is not dependent on NITS for \ndelivery of capacity and energy, would not be included in the PJM load forecast, and would not \nbe modeled and planned for in future RTEP cycles. \n30. \nIn PJM’s Option 5, a new load is co-located behind a generating resource in the same \nmanner as Option 4. As shown in Figure 1 above, the connection is radial, behind the Point of \nInterconnection of the generator and, therefore, energy is delivered from the generator directly to \nthe load without flowing on any grid transmission facilities. Excess energy, beyond the level \nrequired by the load, will flow from the generator to the grid. Protection mechanisms are in place \nto prevent the delivery of energy from the grid to the load in the event that the generator is \noffline. The significant difference with Option 5 is that the load can take back-up service from \nPJM with advance authorization. The load is not dependent on NITS for delivery of capacity and \nenergy while the primary generation source is in service, but may rely on transmission facilities \nof the PJM grid for back-up service, depending on the electrical location of the back-up"},{"page":13,"startToken":3097,"endToken":3378,"text":"11 \n \ngeneration source. To the extent that back-up service is supplied by a second generating resource \nat the same electrical location, energy from that resource would also not flow on any grid \ntransmission facilities. \n31. \nWith respect to PJM Option 4 and PJM Option 5, PJM notes that co-location \narrangements may involve the sale of power from generators to intermediaries and then to load \nunder certain circumstances.4 This, however, is a contractual difference, not a physical, \nelectrical, or interconnection design-based difference. The delivery of energy from generation to \nload in co-location arrangements such as PJM’s Option 4 and Option 5 does not involve the flow \nof that energy over the transmission facilities of the grid. This fact is a function of the design of \nthe interconnection between the co-located load and generation and is not impacted by the \nownership of the generation facility or the co-located load or any contractual relationship \nbetween those parties. BTMG arrangements and co-located load arrangements can be designed \nfrom an engineering perspective in exactly the same manner. In one, the load is typically greater \nin magnitude than the generating facility. In the other, the load is typically lesser in magnitude \nthan the generating facility. The physics of energy delivery are the same in both arrangements \nand are not related to contractual arrangements or rate structures.  \n32. \nFinally, Option 7 contemplates the ability to curtail load in advance of \nemergency conditions. While not specifically a co-location configuration feature, this contractual \narrangement can provide a valuable tool to PJM operators with which to manage operational \nemergencies. It could be implemented as a transitional service while required transmission \nsystem upgrades are under construction.  \n \n4 PJM Answer at 25."},{"page":14,"startToken":3378,"endToken":3712,"text":"12 \n \nb. Synchronization \n33. \nComparing PJM’s Option 4 and PJM’s Option 5 with the BTMG construct (the basis for \nPJM Option 3), clearly both arrangements involve load and generation that is synchronized to the \ngrid. However, synchronization does not require or suggest that energy delivery from that \ngeneration to that load flows on the transmission facilities of the grid. Synchronization is clearly \nimportant and even necessary to the stability of the generating facility and the ability of the \ngenerating facility to deliver energy to the co-located load on an on-going basis, but that does not \nchange the fact that the energy does not flow on the transmission facilities of the grid.  \n34. \nWhether synchronization could be conceptualized and designated as an ancillary service, \none thing is clear: it is not an ancillary service within PJM. The ability to provide other ancillary \nservices, if they are required or used, is facilitated by synchronization, but one is not the \nequivalent of the other. Synchronization may allow black start service to be provided, but if \nblack start service is not required or used by a co-located load, the fact that the load is \nsynchronized to the grid does not make the service required or used. In response to question \nb.vi., PJM states that “[s]ynchronizing to the grid means the generator matches the voltage, \nfrequency, and phase of the entire grid (including all load connected to the system) before \nconnecting to the grid in order to facilitate safe and stable power transfer. As noted above, co-\nlocated load is connected to and synchronized with the multi-state bulk power system. At bare \nminimum, it is benefiting from ancillary services.”5 Load benefits from being synchronized to \nthe grid, but not from services that it does not use. One standard on which charges for grid \nservices can be properly based is use of those services. This applies to both transmission service \nand ancillary services. Synchronization, alone, should not be the standard for such charges.  \n \n5 Id. at 43."},{"page":15,"startToken":3712,"endToken":4006,"text":"13 \n \nc. Other Grid Services \nI have previously analyzed grid services in connection with a co-located load \nconfiguration that, while synchronized to the grid, provides for disconnection from the grid when \nthe co-located generation facility is unavailable.  In short, my prior analysis shows that co-\nlocated load configurations that include sufficiently redundant protective relay systems, e.g., \nconfigurations consistent with PJM’s Options 4 and 5, prevent the physical flow of power to the \nco-located load and do not use transmission service from the grid.6  Moreover, my prior analysis \nshows that these configurations do not impose burdens on the PJM system that would require the \nprocurement of additional amounts of ancillary services.7  \n35. \nFurther, the PJM Tariff, which establishes the procedures for calculating charges for \nservices provided in PJM markets, dictates for all of the services discussed herein, that the \nobligation of a behind-the-meter co-located load is based on the amount of such load, netted by \nthe generation that is operating behind-the-meter.    \n36. \nMy presentation here is an engineering analysis that, among other things, considers \nwhether non-grid connected co-location configurations consistent with PJM Options 4 and 5 \nimpose additional burdens on the PJM grid.  I note that I do not take a position here, nor did I in \nmy prior analysis, whether the co-located load under the non-grid connected configurations of \nPJM Options 4 and 5 may nevertheless benefit indirectly by virtue of synchronization through \nthe host generator’s interconnection to the grid. To date, however, FERC has not allocated \ncharges for any such synchronization benefits. \n37. \nThis concludes my affidavit. \n \n6 Protest of Constellation Energy Generation, LLC to the Exelon Companies’ Rate Filings, Docket Nos. ER24-2888-\n000, et al., Att. 1, Affidavit of Steven R. Herling at ¶¶ 14-34 (Oct. 2, 2024).  \n7 Id."},{"page":16,"startToken":4006,"endToken":4041,"text":"VERIFICATION \nI declare under penalty of perjury that the foregoing Affidavit is true and correct to the best of \nmy knowledge, information, and belief.  \nExecuted this 23rd day of April 2025. \n \n \n \n \n \n \n \n \n________________________ \n \n \n \n \n \n \n \nSteven R. Herling \nSatze"},{"page":17,"startToken":4041,"endToken":4046,"text":"Attachment A to Herling Affidavit"},{"page":18,"startToken":4046,"endToken":4298,"text":"Page 1\n \nSteven R. Herling \n \nPROFESSIONAL EXPERIENCE \n \nHerling Power Grid Consulting, Inc. (2020 – Present) \nPresident \nProvide expertise to support strategic decision making related to the development of planning \nprocesses and the integration with electric power grid market structures. \nProvide expertise to support strategic decision making related to the integration of renewable \ntechnologies onto the electric power grid. \nProvide expert witness services in transmission line siting proceedings.  \n \nYoh Staffing Services (2020 – 2021) \nExecutive Consultant (2020 – 2021) \nProvide expert witness services in transmission line siting proceedings.  \n \nPJM Interconnection, LLC (1990 – 2020) \n \nExecutive Consultant, Planning (2019 – 2020) \nProvide expert witness services in support of the Transource 500/230 kV IEC Project. \nProvide leadership to the development of planning processes related to aging infrastructure and grid \nresilience. \nProvide leadership to the development of planning processes related to the integration of off-shore \nwind into the grid. \nSupport the transition of responsibility to the new Vice President, Planning. \nVice President, Planning (2004 – 2019) \nThe Vice President, Planning reports directly to the CEO. \nResponsible for the oversight of System Planning division of PJM which includes Transmission Planning, \nInterregional Planning, Interconnection Analysis, Interconnection Projects, Infrastructure Coordination \nand Resources Adequacy Planning.  \nPosition Summary: \n \nDevelop long range strategies to achieve PJM’s Planning business objectives. \n \nProvide overarching methodology for the monitoring and analysis of Planning studies as well as the \nintroduction of improved and emerging technologies in the Planning space.  \n \nSupport the leadership of the Planning organization in large and complex engineering assignments to \nsupport present and future needs of the PJM system."},{"page":19,"startToken":4298,"endToken":4737,"text":"Page 2\n \nSupport the activities of PJM and industry committee or task forces involved with issues related to \nplanning and engineering. \n \nPrepare board reports, presentations as well as expert testimony regarding Planning and \nInterconnection recommendations. \n \nIn conjunction with subject matter experts, coordinate delivery of all communication regarding the \nregional transmission expansion and enhancement plans. \n \nEnsure the Planning division and staff can support the requests of PJM as well as external entities \nregarding Interconnection queue activities and feasibility studies. \n \nEnsure relationships with the PJM community as well as other regulatory entities are productive and in \nalignment with the PJM strategic plan. \n \nVarious Staff and Management Positions at PJM (1990 – 2004) \n \nGeneral Public Utilities Service Corporation (1987 – 1990) – System Operations \n \nAmerican Electric Power Service Corporation (1979 – 1987) – Bulk Transmission Planning \n \nExpert Witness Testimony: \n \nKentucky proceeding related to the transfer of ownership and control of Kentucky Power Company. \n \nPennsylvania and Maryland CPCN proceedings related to the Transource 500/230 kV IEC Project. \n \nPennsylvania and New Jersey CPCN proceedings related to Susquehanna – Roseland 500 kV \ntransmission line. \n \nPennsylvania, West Virginia, and Virginia CPCN proceedings related to TRAIL and Meadowbrook – \nLoudoun 500 kV transmission lines. \n \nWest Virginia, Virginia, and Maryland CPCN proceedings related to PATH 765 kV transmission line. \n \nMaryland CPCN proceeding related to MAPP HVDC and 500 kV transmission lines. \n \nVirginia CPCN proceeding related to Surry – Skiffes Creek 500 kV transmission line. \n \nNumerous FERC hearings, settlement proceedings, and technical conferences, most recently including: \no Panelist at FERC’s Competitive Transmission Development Technical Conference (Docket No. AD16-\n18) regarding Regional Transmission Planning and Other Transmission Development Issues relative \nto Order No. 1000 implementation and compliance.  June 2016. \no Panelist at FERC’s PJM Solution-Based DFAX Technical Conference related to the assignment of cost \nallocation using PJM’s solution-based distribution factor (DFAX) cost allocation method. January \n2016 \no Panelist at FERC’s Technical Conference related to the NIPSCO Complaint (Docket No. EL13-88) on \ntwo panels:  (i) Transmission Planning Cycles:  Whether the Commission should require the PJM-\nMISO cross-border transmission planning process to run concurrently with the RTOs regional \nplanning cycles as opposed to after the regional transmission planning cycles; and (ii) Lower Voltage \nTransmission Projects: Whether the Commission should require the RTOs to have a process for joint \nplanning and cost allocation of lower voltage and lower cost cross-border upgrades. June 2015 \no IMO Potomac-Appalachian Transmission Highline LLC and PJM Interconnection, L.L.C. (Docket No. \nER09-1256-002 and ER12-2708-003).  Offered expert testimony relative to the PATH Abandonment \nCosts matter.  April 2015 \no Duquesne Light Company (Docket No. ER13-90-002).  Provided Declaration in support of PJM \nTransmission Owners’ compliance filing with the March 22, 2013 Order to add more detail regarding"},{"page":20,"startToken":4737,"endToken":5002,"text":"Page 3\nhow the solution-based DFAX values will be used to calculate assignments of cost responsibility.  July \n2013 \no Public Service Electric and Gas Company (Docket No. ER13-90).  Provided expert testimony on \nbehalf of the PJM Transmission Owners revisions to the PJM Tariff to modify the cost allocation \nmethodology describing PJM’s current use of distribution factors (DFAX) in allocating the costs of \ncertain transmission upgrades and expansions and discuss how PJM would implement the \nsolution-based DFAX proposed by the PJM Transmission Owners. October 2012 \no Panelist at FERC’s Review of Small Generator Interconnection Agreements and Procedures \nTechnical Conference (Docket No. AD12-17) on a panel entitled:  Review of Required Upgrades, \nwhich explored improving the small generator interconnection process for identifying upgrades to \nsupport interconnection including whether interconnection customers should have the \nopportunity to engage in an expedited independent third-party expert review of upgrade \nrequirements that are perceived as excessive by the interconnection customer.  July 2012 \n \nMost Recent Publications: \nBefore the United States District Court for the Middle District of Pennsylvania, Case No. 1:21-cv-01101-\nJPW, Expert Report of Steven R. Herling in Transource Pennsylvania, LLC, vs. Pennsylvania Public Utility \nCommission, January 20, 2023. \n“New Jersey State Agreement Approach for Offshore Wind Transmission: Evaluation Report (with H. \nPfeifenberger, J.M. Hagerty, J. DeLosa, M. Kaplin, D. Sullivan, C. Peacock, E. Bennett, and E. Snyder), \nprepared for the New Jersey Board of Public Utilities, October 6, 2022 \n“The Sponsorship Model” – IEEE Power & Energy Magazine – July/August 2016 \n \nEducation: \nMEEPE, Rensselaer Polytechnic Institute, (1979) \nBSEPE, Rensselaer Polytechnic Institute, (1978) \nSenior Member of the Institute of Electrical and Electronics Engineers"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":3,"endAt":5,"startToken":0,"endToken":58},{"p":3,"at":5,"title":"I. QUALIFICATIONS AND PURPOSE OF AFFIDAVIT","method":"printed heading","endPage":5,"endAt":789,"startToken":58,"endToken":762},{"p":5,"at":789,"title":"II. DESCRIPTION OF CO-LOCATION PROJECT OPTIONS","method":"printed heading","endPage":8,"endAt":1673,"startToken":762,"endToken":1698},{"p":8,"at":1673,"title":"III. PROTECTIVE RELAY SCHEMES","method":"printed heading","endPage":10,"endAt":1260,"startToken":1698,"endToken":2287},{"p":10,"at":1260,"title":"IV. GRID SERVICES","method":"printed heading","endPage":20,"endAt":1917,"startToken":2287,"endToken":5002}]}