{"document":{"slug":"rec-20250424-5023","title":"Comments of RMI on the Answers of PJM Interconnection, L.L.C. to the Order Instituting Proceeding under Section 206 of the Federal Power Act and…","issued":"2025-04-24","accession":"20250424-5023","docket":"EL25-49-000","group":"PJM co-location compliance","filer":"RMI","kind":"comments","file":"sources/filings/text/20250424-5023_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20250424-5023","tier":"record","sha256":"764707ea30fa1563a6289376f43fd15071cecd0309b082cc49e8d96bbd9dba47","pages":5,"tokens":1478,"emptyPages":[],"textThemes":["colo","study"]},"pages":[{"page":1,"startToken":0,"endToken":101,"text":"Basalt, CO  /  Boulder, CO  /  New York, NY  /  Oakland, CA  /  Washington, D.C.  /  Beijing, China \nhttp:///www.rmi.org /  303.567.8716 \n \n \n \n \nApril 23, 2025 \n \n \nHonorable Debbie-Anne A. Reese, Secretary \nFederal Energy Regulatory Commission \n888 First Street, NE \nWashington, DC 20426 \n \n \nRe: Comments of RMI; Docket No. EL25-49-000 (consolidated) \n \n \nDear Secretary Reese: \n \nAttached, please find comments of RMI on the Answers of PJM Interconnection, L.L.C. to the Order \nInstituting Proceeding under Section 206 of the Federal Power Act and Consolidating with Other \nProceedings. \n \n \nSincerely, \n \n/s/Uday Varadarajan \n \nUday Varadarajan \nSenior Principal \nRMI \n2490 Junction Place, Suite 200 \nBoulder, CO 80301"},{"page":2,"startToken":101,"endToken":527,"text":"1\n \nUNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \n \nOrder Instituting Proceeding under Section 206 \nof the Federal Power Act and Consolidating with \nOther Proceedings \n) \nDocket No. AD24-11-000 \n) \nDocket No. EL25-20-000 \n) \nDocket No. EL25-49-000 (consolidated)\n \n \n \n \n \nCOMMENTS OF RMI  \n \nI. \nIntroduction \nRMI thanks the Federal Energy Regulatory Commission (the “Commission”) for its examination of issues \nrelated to the co-location of large loads at generating facilities in PJM Interconnection L.L.C (“PJM”), as \nconsolidated in Docket No. EL25-49-000, and hereby submits these comments pursuant to the invitation \nto address “(1) whether the existing Tariff remains just and reasonable and not unduly discriminatory or \npreferential; and (2) if not, what changes to the Tariff should be implemented as replacement rates.” \nRMI analysis finds that a behind the meter co-location strategy — which we call “Power Couples” — can \nhelp rapidly supply clean electricity to new, large loads without risking grid reliability, offering an \nimportant example of a non-network load option that provides reliability benefits at least on par with \nPJM’s preferred network load options. A Power Couple is the pairing of a large electricity consumer with \nnew-build solar, wind, and battery storage resources sized to meet the on-site load, all located near an \nexisting gas generator with an approved interconnection. The load draws no energy from the grid and is \nequipped with physical protections to prevent the potential emergence of a load sink should co-located \ngeneration trip, while the gas generator continues to offer the network priority access to capacity, energy, \nand ancillary services whenever called upon.1 Surplus clean electricity from the renewables will often be \navailable to serve the grid while reducing emissions, in all likelihood achieving a net reduction of the \nhistorical emissions of the co-located gas generator. \nIn addition to describing Power Couples — a co-location strategy that is not replicated by any of PJM’s \ncurrent or newly proposed options — in its first comment, RMI in its second comment questions the \nreasonableness of PJM’s application of the “Necessary Study” to loads co-locating with an existing \ngeneration resource but not seeking to be network load. \nFounded in 1982 as Rocky Mountain Institute, RMI is an independent, nonpartisan, nonprofit that \ntransforms global energy systems through market-driven solutions to secure a clean, prosperous, zero-\ncarbon future for all. We work in the world’s most critical geographies and engage businesses, \npolicymakers, communities, and nongovernmental organizations to identify and scale energy system \ninterventions that will cut climate pollution at least 50 percent by 2030. \n \n \n \n1 RMI has modelled these network responsibilities based on historical operating data of individual gas generators."},{"page":3,"startToken":527,"endToken":794,"text":"2\nII. \nComments \n \n1) Fully or wholly isolated co-located load configured as a Power Couple is consistent with \nengineering and economic principles, and PJM contention to the contrary is unduly \ndiscriminatory \nPJM expresses a clear preference for co-locations solutions featuring Network Load. Adumbrating two \nproposed co-location options (4 and 5) in which the Network Load designation (and responsibilities) \nwould not apply, PJM stipulates the installation of “system protection facilities…to prevent delivery of \nenergy from the grid” and then proceeds to question the efficacy and economic fairness of those same \nfacilities.2 As PJM tells it,  \nThis configuration has been described as “fully” or “wholly” isolated by others, but this \ncharacterization is inconsistent with engineering and economic principles. This \nconfiguration relies on and takes grid services (for example, ancillary services) and \nshould pay its fair share of those charges. Additionally, this configuration carries \noperational risk in that there is a dependency on the protection system to support \nreliability.  \nThe allegation that fully or wholly isolated co-load is inconsistent with engineering and economic \nprinciples is not substantiated by PJM.  \nIn the Power Couples approach, power electronics offer protection on two fronts: 1) preventing \nthe co-located load from drawing energy from the grid if the gas generator is insufficient or \nunavailable to meet any of the load’s otherwise unmet needs and 2) by curtailing dispatch from \nthe renewables and discharge of storage in the event the co-located load cannot absorb such \noutput and the grid has no call for it. \nRMI’s Power Couples Architecture \n \n \n2 EL25-49-000, Answer of the PJM Interconnection, L.L.C., (March 24, 2025), at 14."},{"page":4,"startToken":794,"endToken":1327,"text":"3\n \nThe Power Couples architecture does not prevent the System Operator from managing the gas \ngenerator’s output as it did prior to co-location, and the same communications controls should be \ncapable of managing the export of surplus renewables under export conditions.  \nTo reiterate, with this architecture the co-located load never takes energy from the grid. At times \nwhen the gas generator is not called upon by system operator, it may deliver energy to the co-\nlocated load, but RMI is hard-pressed to identify the use of grid services: the onsite inverter and \nstorage resources are fully capable of maintaining voltage and following load fluctuations locally. \nIn a black start eventuality, it stands to reason that the grid would be in distress and availing itself \nof its claim on the legacy gas generator; it follows that the benefits and the costs of black start \nservice should accrue to Network Load, not the co-located load that would not be relying on any \ngrid resources during the event. Thus, the only change from the grid’s perspective would from the \nvariability of surplus exports from the existing interconnection; logically, the costs of managing \nthis variability are the networked loads that benefit in real-time from the clean and affordable \nexport electricity, not the co-located load managing power quality onsite with self-funded power \nelectronics. The Power Couples option is in effect a rebuttal of PJM’s insistence that “At a \nminimum, co-located arrangements implicate the Commission’s transmission jurisdiction due to \nPJM’s provision of ancillary services and in light of the wholesale sales taking place over certain \nfacilities.”3 \nPJM adds that its Option 4 “configuration carries operational risk” because it creates a \n“dependency” on technology “to support system reliability.” RMI is curious whether PJM can \nidentify any load-serving configuration, networked or otherwise, that is devoid of technology-\ndependent risk. Failing such demonstration, if PJM could show that the protection systems \nenvisioned for the RMI Power Couples solutions (and conceivably other solutions suitable for \nservice under proposed Option 4) create more risk than current configurations, then there would \nbe a case for a developing a tariff element to compensate the network service accordingly. PJM, \nhowever, has offered no facts in this regard. \n \n2) PJM should rectify the current lack of a “tariffed study process for load (that is not PJM \nNetwork locating behind a generator’s Point of Interconnection,”4 implementing study \nprocesses tailored specifically for assessing such co-locations solutions \nIn these comments, RMI has described a co-location architecture where load sits behind an existing \ngenerator’s interconnection but cannot draw energy from the grid (thanks to physical protections), \notherwise benefit from grid services, or occasion adverse impacts on the grid. \nIn the absence of a suitable tariffed study process, PJM currently employs the Necessary Study “for a load \nco-locating with an existing generation resource and not seeking to be a Network Load,”5 evaluating it \n“for the full amount of load and reflecting any Capacity Interconnection Rights reductions, and involve \ngeneration deliverability, N-1 and N-1-1 thermal and voltage studies, special protection systems review, \nbaseline stability, and, if applicable, a nuclear plant interface requirements voltage analysis.”6 \n \n \n3 PJM, at 30. \n4 PJM, at 47. \n5 PJM, at 48. \n6 PJM, at 49."},{"page":5,"startToken":1327,"endToken":1478,"text":"4\nAssessing co-located load for the full amount of load without first assessing the efficacy and \nreliability of the protection systems intended to prevent the addition of any load imposes, in \nRMI’s opinion, unnecessary costs and burdens on a Power Couple or similar architecture. \nFurthermore, since Power Couples do not alter the use of the existing interconnection other than \nby potentially delivering additional energy within previously studied limits (under Surplus \nInterconnection Service allowed by the Commission’s Order 845), thermal and voltage studies \nare superfluous. PJM’s Necessary Study application to co-location solutions like Power Couples \nis, thus, both poorly sequenced and poorly integrated with other regulatory study procedures. The \nCommission must give PJM clear instructions to address these deficiencies.  \n \n \nIII. \nConclusion \nRMI respectfully requests that the Commission accept the comments herein.  \n \n \n \n \n \nSincerely, \n \n/s/Uday Varadarajan \n \nUday Varadarajan \nSenior Principal \nRMI \n2490 Junction Place, Suite 200 \nBoulder, CO 80301 \nEmail: uvaradarajan@rmi.org"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":2,"endAt":325,"startToken":0,"endToken":141},{"p":2,"at":325,"title":"I. Introduction","method":"printed heading","endPage":3,"endAt":2,"startToken":141,"endToken":528},{"p":3,"at":2,"title":"II. Comments","method":"printed heading","endPage":5,"endAt":843,"startToken":528,"endToken":1445},{"p":5,"at":843,"title":"III. Conclusion","method":"printed heading","endPage":5,"endAt":1103,"startToken":1445,"endToken":1478}]}