{"document":{"slug":"rec-20250502-5173","title":"Answer of Northern Virginia Electric Cooperative, Inc. and Northeastern Rural Electric Membership Corporation Opposing the Joint Comments and Motion to Stay…","issued":"2025-05-02","accession":"20250502-5173","docket":"EL25-49-000","group":"PJM co-location compliance","filer":"Northern Virginia Electric Cooperative, Inc.NORTHEASTERN REMC","kind":"answer","file":"sources/filings/text/20250502-5173_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20250502-5173","tier":"record","sha256":"e8f05c9b275783604732ca01773bdb55bfceb2a04a225f83778f1932be395e3a","pages":6,"tokens":1195,"emptyPages":[],"textThemes":["colo"]},"pages":[{"page":1,"startToken":0,"endToken":186,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \n \n) \n \nPJM Interconnection, L.L.C. \nAllegheny Electric Cooperative, Inc. \nAmerican Transmission Systems, Incorporated \nAtlantic City Electric Company \nBaltimore Gas and Electric Company \nDelmarva Power & Light Company \nDuke Energy Ohio, Inc. \nDuke Energy Kentucky, Inc. \nEast Kentucky Power Cooperative, Inc. \nEssential Power Rock Springs, LLC \nHudson Transmission Partners, LLC \nJersey Central Power & Light Company \nMid-Atlantic Interstate Transmission, LLC \nNeptune Regional Transmission System, LLC \nOld Dominion Electric Cooperative \nPECO Energy Company \nPPL Electric Utilities Corporation \nPotomac Electric Power Company \nPublic Service Electric and Gas Company \nRockland Electric Company \nTrans-Allegheny Interstate Line Company \nTransource West Virginia, LLC \nUGI Utilities, Inc. \nMonongahela Power Company \nThe Potomac Edison Company \nCommonwealth Edison Company \nCommonwealth Edison Company of Indiana, Inc. \nThe Dayton Power and Light Company  \nAEP Appalachian Transmission Company, Inc. \nAEP Indiana Michigan Transmission Company, Inc. \nAEP Kentucky Transmission Company, Inc. \nAEP Ohio Transmission Company, Inc. \nAEP West Virginia Transmission Company, Inc. \nAppalachian Power Company \nIndiana Michigan Power Company \nKentucky Power Company \nKingsport Power Company \nOhio Power Company \nWheeling Power Company \nDuquesne Light Company \nVirginia Electric and Power Company \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \nDocket Nos. EL25-49-000"},{"page":2,"startToken":186,"endToken":425,"text":"2 \n \nLinden VFT, LLC \nCity of Cleveland, Department of Public Utilities, \nDivision of Cleveland Public Power \nCity of Hamilton, OH \nSouthern Maryland Electric Cooperative, Inc. \nOhio Valley Electric Corporation \nAMP Transmission, LLC \nSilver Run Electric, LLC \nNextEra Energy Transmission MidAtlantic Indiana, Inc.\nWabash Valley Power Association, Inc. \nKeystone Appalachian Transmission Company \n \nLarge Loads Co-Located at Generating Facilities  \n \n \nConstellation Energy Generation, LLC \n \nv.  \n \nPJM Interconnection, L.L.C. \n \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n \n \n \n \n \n \n \n \n \n \n \nAD24-11-000\n \nEL25-20-000\n(Consolidated)\n \n \n \n \nANSWER OF NORTHERN VIRGINIA ELECTRIC COOPERATIVE, INC. AND \nNORTHEASTERN RURAL ELECTRIC MEMBERSHIP CORPORATION OPPOSING \nTHE JOINT COMMENTS AND MOTION TO STAY PROCEEDINGS AND REQUEST \nTO ESTABLISH SETTLEMENT JUDGE PROCEDURES \n \nPursuant to Rule 213 of the Rules of Practice and Procedure of the Federal Energy \nRegulatory Commission (“FERC” or the “Commission”),1 Northern Virginia Electric \nCooperative, Inc. (“NOVEC”) and Northeastern Rural Electric Membership Corporation \n(“NREMC”) respectfully submit this answer in opposition to the Joint Parties’ April 22, 2025, \n“Joint Comments and Motion to Stay Proceedings and Request to Establish Settlement Judge \nProcedures” (“Motion”).2 \n \n1 18 C.F.R. § 385.213.  \n2 Joint Parties, Joint Comments and Motion to Stay Proceedings and Request to Establish Settlement Judge Procedures, \nDocket Nos. EL25-49-000, et al. (filed April 22, 2025) (Accession No. 20250422-5166) (“Motion”). The Joint Parties \nare a group of generators and trade associations that includes the Electric Power Supply Association, the PJM Power \nProviders Group, Calpine Corporation, Cogentrix Energy Power Management, LLC, Constellation Energy \nGeneration, LLC, and LS Power Development, LLC."},{"page":3,"startToken":425,"endToken":741,"text":"3 \n \nI. \nANSWER \n \nThe Joint Parties’ Motion asks that the Commission find the PJM Interconnection, L.L.C \n(“PJM”) Open Access Transmission Tariff (“Tariff”) to be unjust and unreasonable, stay the \nconsolidated proceeding, and establish settlement judge procedures to develop a replacement rate.3 \nThe Commission should deny the Motion and find that the PJM Tariff is just and reasonable and \ndoes not require revisions. \n \nThe Motion presupposes not only that the PJM Tariff is not just and reasonable, but that \nrevisions to the PJM Tariff that provide for unique treatment to co-located load would be just and \nreasonable and not unduly discriminatory. The first assumption is incorrect. Co-location can be \neffectively accommodated within the existing PJM Tariff through established transmission service \nstructures as Network Load or Point-to-Point Service.4 Every co-location arrangement that has \nbeen proposed, aside from true physical islanding, involves reliance on the transmission system \nfor ancillary services and backup supply. This is why, as the Indicated PJM Transmission Owners \nexplained, the PJM Tariff provides that co-located customers need to acquire firm transmission \nservice just like every other customer.5 The fact that the rules do not produce the Joint Parties’ \npreferred outcome does not mean that the rules are unclear or unable to accommodate co-location \narrangements. Viable and fair options exist under the current Tariff. There is no ambiguity, only \nthe desire for a different result. \n \nThe second assumption is also incorrect. The Motion implies that co-location arrangements \nshould not be subject to a “one-size-fits-all” solution.6 To the contrary, a uniform approach is \n \n3 Motion at 2.  \n4 PJM Interconnection, L.L.C., Answer, Docket Nos. EL25-49-000, et al., at 9 (filed March 24, 2025) (Accession No. \n20250324-5313); Indicated PJM Transmission Owners, Answer, Docket Nos. EL25-49-000, et al., at 10 (filed March \n24, 2025) (Accession No. 20250324-5298) (“Indicated PJM TOs Answer”). \n5 See Indicated PJM TOs Answer. \n6 Motion at 2-4."},{"page":4,"startToken":741,"endToken":1019,"text":"4 \n \nappropriate because, like other load, co-location arrangements rely on the transmission system. \nProspective co-location arrangements still seek to maintain a connection to the transmission \nsystem, despite claims that these arrangements will not use or rely on the transmission system. \nNOVEC and NREMC believe that all load should be served but cannot agree that certain new and \nprivileged large loads should receive preferential treatment at the expense of all other rate-paying \ntransmission customers and the load they serve.  \n \nBecause the Motion’s threshold presuppositions are incorrect, the relief the Motion \nrequests should not be granted. Staying the proceeding is unnecessary as the Commission should \ndismiss the consolidated proceeding on the record before it as the existing PJM Tariff is just and \nreasonable, and not unduly discriminatory or preferential. A settlement process would not be \nproductive because there is no ambiguity to resolve by settlement. If load chooses not to \ninterconnect to the transmission system, then it does not have to pay transmission costs. If, through \nany configuration, load interconnects to the transmission system, it must contribute to the costs of \nthe transmission system on which it relies – which can be adequately resolved through existing \nstructures in the PJM Tariff. NOVEC and NREMC also agree with the reasoning underlying the \nIndependent Market Monitor for PJM’s (“IMM”) opposition to resolving this proceeding through \nsettlement.7 As the IMM contends, these issues should be “resolved objectively, transparently and \nin the public interest.”8  \nII. \nCONCLUSION \nWHEREFORE, for the foregoing reasons, NOVEC and NREMC respectfully request that \nthe Commission deny the Motion. \n \n \n \n7 IMM, Comments, Docket Nos. EL25-49-000, et al., at 13-14 (filed April 23, 2025) (Accession No. 20250423-5260).  \n8 Id. at 13."},{"page":5,"startToken":1019,"endToken":1116,"text":"5 \n \nRespectfully submitted, \n \n//s// Alexandra Jones \nAlexandra Jones \nVice President & Senior Counsel \nof Energy and Regulatory Affairs \nNortheastern REMC \n4901 East Park 30 Drive \nColumbia City, IN 46725 \nTel: (317) 964-1752 \nEmail: a_jones@nremc.com \n \nOn behalf of Northeastern Rural Electric \nMembership Corporation \n//s// Alan I. Robbins \nAlan I. Robbins \nDebra D. Roby \nThomas B. Steiger III \nWashington Energy Law LLP \n900 17th Street. N.W., Suite 500-A  \nWashington, D.C. 20006 \nTel: (202) 326-9313 \nEmail: arobbins@washingtonenergylaw.com \ndroby@washingtonenergylaw.com \ntsteiger@washingtonenergylaw.com \n \nCounsel to Northern Virginia Electric \nCooperative, Inc.\n \nDated: May 2, 2025."},{"page":6,"startToken":1116,"endToken":1195,"text":"CERTIFICATE OF SERVICE \nI hereby certify that I have this day served the foregoing document upon each person \ndesignated on the official service list compiled by the Secretary of the Federal Energy \nRegulatory Commission in this consolidated proceeding. \nDated at Washington, D.C. this 2nd day of May, 2025. \n \n  //s// Jessika Dziechciowska  \n \nJessika Dziechciowska \nEnergy Practice Analyst \nWashington Energy Law LLP \n900 17th Street, N.W., Suite 500-A \nWashington, D.C. 20006 \nTel: (202) 326-9308 \nEmail: jdziechciowska@washingtonenergylaw.com"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":3,"endAt":5,"startToken":0,"endToken":426},{"p":3,"at":5,"title":"I. ANSWER","method":"printed heading","endPage":4,"endAt":1621,"startToken":426,"endToken":980},{"p":4,"at":1621,"title":"II. CONCLUSION","method":"printed heading","endPage":6,"endAt":0,"startToken":980,"endToken":1116},{"p":6,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":6,"endAt":546,"startToken":1116,"endToken":1195}]}