{"document":{"slug":"rec-20250505-5241","title":"Answer of PJM Interconnection, L.L.C. to Joint Comments and Motion to Stay Proceedings and Request to Establish Settlement Judge Procedures","issued":"2025-05-05","accession":"20250505-5241","docket":"EL25-49-000","group":"PJM co-location compliance","filer":"PJM Interconnection, L.L.C.","kind":"answer","file":"sources/filings/text/20250505-5241_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20250505-5241","tier":"record","sha256":"93f05372a51713b168477b336092f0b12b4866f1c24c59e9366dcb94646e4fec","pages":7,"tokens":1780,"emptyPages":[],"textThemes":["colo"]},"pages":[{"page":1,"startToken":0,"endToken":169,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \n  \nPJM Interconnection, L.L.C. \nAllegheny Electric Cooperative, Inc. \nAmerican Transmission Systems, \nIncorporated \nAtlantic City Electric Company \nBaltimore Gas and Electric Company \nDelmarva Power & Light Company \nDuke Energy Ohio, Inc. \nDuke Energy Kentucky, Inc. \nEast Kentucky Power Cooperative, Inc. \nEssential Power Rock Springs, LLC \nHudson Transmission Partners, LLC \nJersey Central Power & Light Company \nMid-Atlantic Interstate Transmission, LLC \nNeptune Regional Transmission System, \nLLC \nOld Dominion Electric Cooperative \nPECO Energy Company \nPPL Electric Utilities Corporation \nPotomac Electric Power Company \nPublic Service Electric and Gas Company \nRockland Electric Company \nTrans-Allegheny Interstate Line Company \nTransource West Virginia, LLC \nUGI Utilities, Inc. \nMonongahela Power Company \nThe Potomac Edison Company \nCommonwealth Edison Company \nCommonwealth Edison Company of \nIndiana, Inc. \nThe Dayton Power and Light Company  \nAEP Appalachian Transmission Company, \nInc. \nAEP Indiana Michigan Transmission \nCompany, Inc. AEP Kentucky \nTransmission Company, Inc. \nAEP Ohio Transmission Company, Inc. \nAEP West Virginia Transmission \nCompany, Inc. Appalachian Power \nCompany \nIndiana Michigan Power Company \nKentucky Power Company \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n)  \n) \n) \n) \n) \n) \n) \n)  \n) \n) \n) \n) \n) \n) \n)  \n) \n) \n) \n) \n) \n) \n)  \n) \n) \n) \n) \n) \n) \nDocket Nos. EL25-49-000"},{"page":2,"startToken":169,"endToken":326,"text":"2 \nKingsport Power Company \nOhio Power Company \nWheeling Power Company \nDuquesne Light Company \nVirginia Electric and Power Company \nLinden VFT, LLC \nCity of Cleveland, Department of Public \nUtilities, Division of Cleveland Public \nPower \nCity of Hamilton, OH \nSouthern Maryland Electric Cooperative, \nInc. \nOhio Valley Electric Corporation \nAMP Transmission, LLC \nSilver Run Electric, LLC \nNextEra Energy Transmission MidAtlantic \nIndiana, Inc. \nWabash Valley Power Association, Inc. \nKeystone Appalachian Transmission \nCompany \n \nLarge Loads Co-Located at Generating \nFacilities  \n \n \nConstellation Energy Generation, LLC \n \nv.  \n \nPJM Interconnection, L.L.C. \n)  \n) \n) \n) \n) \n) \n) \n)  \n) \n) \n) \n) \n) \n) \n)  \n) \n) \n) \n) \n) \n) \n)  \n) \n) \n) \n) \n) \n) \n)  \n) \n) \n \n \n \n \n \n \n \n \n \n \n \n \n \n \n \n \n \n \n \n \n \nAD24-11-000 \n \n \n \nEL25-20-000 \n(Consolidated) \n \n \n \n \n \n \nANSWER OF PJM INTERCONNECTION, L.L.C. TO JOINT COMMENTS AND \nMOTION TO STAY PROCEEDINGS AND REQUEST TO ESTABLISH \nSETTLEMENT JUDGE PROCEDURES \nPursuant to Rule 213 of the Rules of Practice and Procedure of the Federal Energy \nRegulatory Commission (“Commission”),1 PJM Interconnection, L.L.C. (“PJM”) submits \nthis answer to the April 22, 2025 Joint Comments and Motion to Stay Proceedings and \n                                                 \n1 18 C.F.R § 385.213."},{"page":3,"startToken":326,"endToken":717,"text":"3 \nRequest to Establish Settlement Judgment Procedures.2  At a later date, PJM intends to \nsubmit a targeted response to the more than forty comments filed in response to PJM’s and \nvarious Transmission Owner submissions.  PJM submits this answer in the interim to assist \nthe Commission in resolving the Motion.   \nI. \nPJM’S TARIFF REMAINS JUST AND REASONABLE \nContrary to the Motion’s conclusory assertions, the ever-growing record in this \nproceeding reflects substantial support for a finding that PJM’s existing Tariff is just and \nreasonable in regards to co-location arrangements.3  As noted, PJM intends to submit a \ntargeted response to the many comments filed in this docket and will further demonstrate \nthat the existing Tariff is just and reasonable. \nII. \nNO STAY SHOULD ISSUE \nThe Motion seeks a 90 day stay of this proceeding.  The Commission should not \npause its work on offering the industry guidance on a path forward for co-location \narrangements.  Accordingly, the Commission should not issue any stay in the proceeding.   \nAny stay request runs contrary to the actions and representations of countless \nparties in this proceeding that are seeking Commission guidance and further would appear \nto prejudice the interests expressed by certain parties.  By way of example, one of the \n                                                 \n2 PJM Interconnection, L.L.C., Joint Comments and Motion to Stay Proceedings and Request to Establish \nSettlement Judge Procedures of the Electric Power Supply Association, the PJM Power Providers Group, \nCalpine Corporation, Cogentrix Energy Power Management, LLC, Constellation Energy Generation, LLC \nand LS Power Development, LLC, Docket Nos. EL25-49-000, et al. (April 22, 2025) (“Motion”). \n3 See, e.g., PJM Interconnection, L.L.C., Answer of PJM Interconnection, L.L.C., Docket Nos. EL25-49, et \nal., at 4-5 32-33 (Mar. 24, 2025) (“PJM Answer”); PJM Interconnection, L.L.C., Answer of the Indicated \nPJM Transmission Owners to the Order Instituting the Proceeding Under Section 206 of the Federal Power \nAct and Consolidating with Other Proceedings, Docket Nos. EL25-49, et al., at 10-14 (Mar. 24, 2025) \n(“Indicated TO Answer”); PJM Interconnection, L.L.C., Comments of Talen Energy Corporation, Docket \nNos. EL25-49, et al., at 2 (Apr. 23, 2025); PJM Interconnection, L.L.C., Comments of Northern Virginia \nElectric Cooperative, Inc., Docket Nos. EL25-49, et al. (April 23, 2025); PJM Interconnection, L.L.C., \nResponse of American Municipal Power, Inc., Docket Nos. EL25-49, et al. (April 23, 2025)."},{"page":4,"startToken":717,"endToken":1200,"text":"4 \nmovants now seeking a stay filed a co-located load-related complaint requesting fast track \nprocessing.4  When PJM filed a motion to extend the answer deadline, that request was \nfirmly opposed – with one of the Motion’s sponsors then claiming “‘justice delayed is \njustice denied.’”5   The Commission relied on this opposition in denying PJM’s extension \nrequest.6  That sponsor and other movants cannot explain how “justice so requires” a stay \nnow, on their say so, several months later, and for a substantially longer period of time than \nwhat at least one sponsor previously opposed.7  \nAdditionally, the many co-located load dockets brim with requests for expeditious \nCommission action and calls for certainty and clarity.8  The Commission heeded these \nrequests and set a 30 day response deadline to the Show Cause Order.9  The Commission \n                                                 \n4 Constellation Energy Generation, LLC v. PJM Interconnection, L.L.C., Complaint Requesting Fast Track \nProcessing of Constellation Energy Generation, LLC, Docket No. EL25-20 (Nov. 22, 2024). \n5 See Constellation Energy Generation, LLC v. PJM Interconnection, L.L.C., Answer of Constellation Energy \nGeneration, LLC in Opposition to Motion for Extension, Docket No. EL25-20, at 1 (Dec. 2, 2024); \nConstellation Energy Generation, LLC v. PJM Interconnection, L.L.C., Motion to Intervene and Comments \nin Opposition to the Motion for Extension of Time of Talen Energy Corporation, Docket No. EL25-20 (Dec. \n3, 2024). \n6 Constellation Energy Generation, LLC v. PJM Interconnection, L.L.C., Notice Denying Extension of Time, \nDocket No. EL25-20 (Dec. 6, 2024). \n7 See Pub. Util. Dist. No. 1 of Okanogan Cnty., Washington, 162 FERC ¶ 61,040, at P 13 (2018) (finding that \nFPA section 309 gives the Commission stay authority and explaining that the Commission has elected to \nutilize the “justice so requires” standard set forth in section 705 of the Administrative Procedure Act).   \n8 See, e.g., PJM Interconnection, L.L.C., Response of Public Service Electric and Gas Company to the Order \nto Show Cause, Docket Nos. EL25-49, et al., at 3 (Mar. 24, 2025) (“PSE&G respectfully urges the \nCommission to effectuate a prompt resolution of this co-location proceeding, as expeditiously arriving at \nclear co-location rules is essential to allow states like New Jersey and data center customers to move forward \nwith their development plans.”); PJM Interconnection, L.L.C., Motion for Clarification of Vistra Corp. and \nRequest for Expedited Treatment, Docket No. EL25-49, at 2 (Apr. 4, 2025) (“Vistra fully supports the \nCommission’s stated objective to expeditiously reach a resolution in this proceeding.”); PJM \nInterconnection, L.L.C., Comments of Talen Energy Corporation, Docket Nos. EL25-49, et al., at 14 (Apr. \n23, 2025) (“It is urgent that the Commission act in accordance with its jurisdiction as soon as possible to \npromote economic growth and support PJM in maintaining reliability on its transmission system.”).   \n9 PJM Interconnection, L.L.C., et al., 190 FERC ¶ 61,115, at ordering paragraph (B) (2025)."},{"page":5,"startToken":1200,"endToken":1504,"text":"5 \nhas subsequently affirmed a commitment to quick action.10  The Commission has before it \na substantial record reflecting views from across the industry.  The Commission can now \nrule on the subject matter of the Show Cause proceeding.  A stay would frustrate the \nCommission’s stated intent to “act quickly” and “expeditiously, so [the Commission] can \nprovide clarity and certainty to all[.]”11   \nIII. \nPJM COMMENTS ON THE REQUEST FOR SETTLEMENT JUDGE \nPROCEDURES \nTwo generation supply associations and four generators filed the Motion seeking \nsettlement judge procedures.  As of the time of this filing, only the Data Center Coalition \nappears to support that request.  \nIf a broader consensus emerges in support of settlement procedures in this \nproceeding (that would necessarily include Transmission Owners, cooperatives, and public \npower), the Commission could consider supporting a settlement process without any stay.  \nBut first PJM observes that the PJM states are critical parties to any such settlement \ndiscussions given the unique interaction of federal and state jurisdictional issues in this \nproceeding.  However, it is not clear the extent to which the states can, through a FERC \nsettlement, make policy decisions that are binding upon state jurisdictional matters.  \nFurthermore, PJM is engaging with its stakeholders regarding large load interconnections \n                                                 \n10 See, e.g., FERC News Release, FERC Chairman Issues Statement on Review of Issues Associated with \nthe Co-Location of Large Loads at Generating Facilities (Feb. 21, 2025), available at:  https://ferc.gov/news-\nevents/news/ferc-chairman-issues-statement-review-issues-associated-co-location-large-loads \n(“FERC \nNews Release”); March 18, 2025 Letter from Office of the Chairman, Mark C. Christie, responding to \nOctober 2, 2024 Letter from Governor Josh Shapiro, Docket Nos. EL25-49, EL24-149, ER24-2172, and \nER24-2888 et al.; March 18, 2025 Letter from Office of the Chairman, Mark C. Christie, responding to \nOctober 31, 2024 letter from Governor Glenn Youngkin, Docket No. AD24-11. \n11 See FERC News Release."},{"page":6,"startToken":1504,"endToken":1705,"text":"6 \ngenerally, including at an upcoming May 9, 2025 Large Load Additions workshop,12 as \nwell as interrelated efforts pertaining to load forecasting and resource adequacy.  Any \nsettlement proceedings should not be permitted to interfere with these efforts.  Such \nstakeholder processes may indeed inform or constrain PJM’s position in any settlement \ndiscussions.  Accordingly, the Commission should only set this matter for settlement if \nthere is a broad coalition of support for such proceedings.  And even then, the Commission \nshould continue its efforts to provide necessary clarity and certainty to the industry through \nthe issuance of guidance on co-location arrangements.   \nIV. \nCONCLUSION \nPJM requests that the Commission consider this Answer when deciding the \nMotion. \nRespectfully submitted, \n \n \n \n \n \n \n \n \n/s/ Mark J. Stanisz \n \n  \nCraig Glazer \nVice President–Federal Government Policy \nPJM Interconnection, L.L.C. \n1200 G Street, N.W., Suite 600 \nWashington, D.C.  20005 \n(202) 423-4743 \ncraig.glazer@pjm.com \nMark J. Stanisz  \nAssociate General Counsel \nPJM Interconnection, L.L.C. \n2750 Monroe Blvd. \nAudubon, PA 19403 \n(610) 666-8800 \nmark.stanisz@pjm.com  \n \n \n \n \nAttorney for  \nPJM Interconnection, L.L.C. \nMay 5, 2025\n                                                 \n12 \nPJM \nLarge \nLoad \nAdditions \nWorkshop, \navailable \nat:  \nhttps://www.pjm.com/forms/registration/Meeting%20Registration.aspx?ID={af9810e3-fb39-49ef-85f3-\n6d05a03609c0}# ."},{"page":7,"startToken":1705,"endToken":1780,"text":"CERTIFICATE OF SERVICE \n \nI hereby certify that I have this day served the foregoing document upon each \nperson designated on the official service list compiled by the Secretary in this proceeding. \n \nDated at Audubon, Pennsylvania, this 5th day of May 2025. \n/s/ Mark J. Stanisz \n \n \n \n \n \n \n \n \n \nMark J. Stanisz  \nAssociate General Counsel \nPJM Interconnection, L.L.C. \n2750 Monroe Blvd. \nAudubon, PA 19403 \n(610) 666-8800 \nmark.stanisz@pjm.com \n \nAttorney for  \nPJM Interconnection, L.L.C."}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":3,"endAt":316,"startToken":0,"endToken":376},{"p":3,"at":316,"title":"I. PJM’S TARIFF REMAINS JUST AND REASONABLE","method":"printed heading","endPage":3,"endAt":765,"startToken":376,"endToken":444},{"p":3,"at":765,"title":"II. NO STAY SHOULD ISSUE","method":"printed heading","endPage":5,"endAt":402,"startToken":444,"endToken":1262},{"p":5,"at":402,"title":"III. PJM COMMENTS ON THE REQUEST FOR SETTLEMENT JUDGE","method":"printed heading","endPage":6,"endAt":685,"startToken":1262,"endToken":1603},{"p":6,"at":685,"title":"IV. CONCLUSION","method":"printed heading","endPage":7,"endAt":0,"startToken":1603,"endToken":1705},{"p":7,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":7,"endAt":493,"startToken":1705,"endToken":1780}]}