{"document":{"slug":"rec-20250507-5129","title":"Answer of American Municipal Power, Inc. in Opposition to Motion for Stay and Settlement Judge Procedures","issued":"2025-05-07","accession":"20250507-5129","docket":"EL25-49-000","group":"PJM co-location compliance","filer":"American Municipal Power, Inc.","kind":"answer","file":"sources/filings/text/20250507-5129_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20250507-5129","tier":"record","sha256":"f432bd6c043e903a64924da2b40eeedbee5af609c2115c23524f661f87555edb","pages":11,"tokens":2660,"emptyPages":[],"textThemes":["colo"]},"pages":[{"page":1,"startToken":0,"endToken":253,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \nPJM Interconnection, L.L.C., et al. \n) \nDocket No. EL25-49-000 \n \n) \n \nLarge Loads Co-Located at \n  Generating Facilities \n) \n) \nDocket No. AD24-11-000 \n \n) \n \nConstellation Energy Generation, LLC \n \n  v. \n \n) \n) \n) \n) \nDocket No. EL25-20-000 \n   (Consolidated) \nPJM Interconnection, L.L.C. \n) \n \n \nANSWER OF AMERICAN MUNICIPAL POWER, INC. \nIN OPPOSITION TO MOTION FOR STAY AND  \nSETTLEMENT JUDGE PROCEDURES \n \nPursuant to Rule 213 of the Rules of Practice and Procedure of the Federal Energy \nRegulatory Commission (“Commission” or “FERC”), American Municipal Power, Inc. \n(“AMP”) hereby submits its answer in opposition to the Joint Parties’ April 22, 2025 motion \nto stay the above-captioned proceedings and establish settlement judge procedures.1  \nThe Commission should deny the Joint Motion. The Joint Parties have not \nestablished the basis for their proposed settlement discussions. Contrary to Joint Parties’ \nassertions, the record supports a finding that the Open Access Transmission Tariff \n(“Tariff”) of PJM Interconnection, L.L.C. (“PJM”) remains just and reasonable and not \nunduly discriminatory or preferential, and, thus, there is no reason to convene settlement \njudge proceedings to develop a replacement rate. The Commission should instead \nconfirm the justness and reasonableness of the existing Tariff, while providing guidance \n                                            \n1  Joint Parties, Joint Comments and Motion to Stay Proceedings and Request to Establish Settlement \nJudge Procedures, Docket Nos. EL25-49-000, et al. (April 22, 2025) (“Joint Motion”). The Joint Parties \nare the Electric Power Supply Association; the PJM Power Providers Group; Calpine Corporation; \nCogentrix Energy Power Management, LLC; Constellation Energy Generation, LLC (“Constellation”); \nand LS Power Development, LLC."},{"page":2,"startToken":253,"endToken":516,"text":"2 \non the application of the Tariff to co-located load arrangements, as discussed in the \nanswer filed by the Indicated PJM Transmission Owners.2 Even if the Commission were \nto find that the existing PJM Tariff is unjust and unreasonable, or unduly discriminatory or \npreferential, the best course of action would be for the Commission to provide clear \nguidance on the design of a replacement rate to address any identified deficiencies in the \nTariff, rather than consigning the myriad participants in this proceeding (some of which \nare not even PJM stakeholders) to an additional round of unwieldy negotiations on issues \nthat have long evaded resolution in prior stakeholder discussions. \nI. \nBACKGROUND \nIn its February 20, 2025 order in the above-captioned proceedings,3 the \nCommission preliminarily found that the PJM Tariff “appears to be unjust and \nunreasonable or unduly discriminatory or preferential because it does not contain \nprovisions addressing with sufficient clarity or consistency the rates, terms, and conditions \nof service that apply to co-location arrangements.”4 The Commission accordingly initiated \na new proceeding under section 206 of the Federal Power Act (“FPA”) (“Show Cause \nProceeding”) and directed PJM and the PJM Transmission Owners: (1) to show cause as \nto why the PJM Tariff remains just and reasonable and not unduly discriminatory or \npreferential; or (2) explain what Tariff changes “would remedy the Commission’s identified \n                                            \n2  Indicated PJM Transmission Owners, Answer, Docket Nos. EL25-49-000, et al. (March 24, 2025) \n(“Indicated PJM TOs Answer”). \n3  PJM Interconnection, L.L.C., 190 FERC ¶ 61,115 (2025) (“Show Cause Order”). \n4  Show Cause Order at P 74."},{"page":3,"startToken":516,"endToken":801,"text":"3 \nconcerns if the Commission were to determine that the Tariff has in fact become unjust \nand unreasonable or unduly discriminatory or preferential.”5 \nPJM responded to the Show Cause Order on March 24, 2025.6 In addition to the \nanswer filed by PJM, most PJM Transmission Owners (“Indicated PJM Transmission \nOwners”) submitted a joint answer to the Show Cause Order.7 The Indicated PJM \nTransmission Owners explained that the existing PJM Tariff remains just and reasonable, \nand not unduly discriminatory or preferential,8 and PJM took the same position.9 \nNumerous parties, including non-PJM stakeholders, filed responses to the PJM \nand Transmission Owner filings, or to the questions raised in the Show Cause Order. \nAMP submitted a response supporting the Indicated PJM Transmission Owners’ \nanswer.10 AMP’s response also emphasized the continuing reasonableness of the PJM \nTariff’s treatment of load served by Behind the Meter Generation (“BTMG”) and Non-\nRetail BTMG, as those terms are defined in the Tariff, and said that any action taken by \nthe Commission in this proceeding should avoid prejudice to entities that have relied on \nthe longstanding Tariff provisions allowing for netting of Network Load served by BTMG \nand Non-Retail BTMG.11 \n                                            \n5  Id. P 87. The Commission also consolidated the Show Cause Proceeding with Docket No. EL25-20-\n000, involving a complaint filed by Constellation, and with the Commission’s technical conference \naddressing Large Loads Co-Located at Generating Facilities in Docket No. AD24-11-000. \n6  PJM, Answer, Docket Nos. EL25-49-000, et al. (March 24, 2025) (“PJM Answer”). \n7  See Indicated PJM TOs Answer. \n8  Id. at 2. \n9  PJM Answer at 4, 32. \n10  AMP, Response, Docket Nos. EL25-49-000, et al. (April 23, 2025) (“AMP Response”). \n11  Id. at 3-4, 10."},{"page":4,"startToken":801,"endToken":1050,"text":"4 \nBased only on the PJM and Transmission Owner submissions, Joint Parties now \nask the Commission to “conclusively find the PJM Tariff to be unjust, unreasonable and \nunduly discriminatory and preferential.”12 Assuming such a finding, the Joint Parties argue \nthat the Commission “should defer to the parties in this proceeding to develop a new \nreplacement rate through a Commission-supported settlement process.”13 Specifically, \nJoint Parties request that the Commission stay the Show Cause Proceeding for ninety \ndays and “appoint a settlement facilitator and/or settlement judge to actively engage, \nthrough publicly-noticed settlement conferences, with PJM, the Transmission Owners, \nand any other interested intervenors in a concerted, focused, and good faith effort to \nresolve this proceeding within a 90 day period.”14 \nII. \nANSWER \nThe Commission should deny the Joint Motion. The Joint Parties have neither \nsupported their assertion that the PJM Tariff is unjust and unreasonable or unduly \ndiscriminatory or preferential, nor shown that settlement judge procedures would be an \neffective way to establish a replacement rate if the Commission were to find deficiencies \nin the existing Tariff. \nA. \nThe record supports a finding that the PJM Tariff remains just and \nreasonable. \nThe Joint Parties’ request for a stay and settlement judge procedures is premised \non the assumption that the Commission will make a “conclusive” finding that the PJM \nTariff is unjust, unreasonable and unduly discriminatory and preferential.15 The record, \n                                            \n12  Joint Motion at 3. \n13  Id. at 4. \n14  Id. at 2. \n15  Id. at 3."},{"page":5,"startToken":1050,"endToken":1396,"text":"5 \nhowever, supports the opposite conclusion. Both PJM and the PJM Transmission Owners \nexplained in their respective answers to the Show Cause Order that the existing PJM \nTariff remains just and reasonable and not unduly discriminatory or preferential.16  \nGiven the detailed answers filed by PJM and the Indicated PJM Transmission \nOwners defending the justness and reasonableness of the Tariff, there is no validity \nwhatsoever to the Joint Parties’ assertion that “no party responding to the Co-Location \nShow Cause Order has demonstrated that the PJM Tariff is just, reasonable and not \nunduly discriminatory or preferential, or even made a meaningful effort to do so.”17 PJM \nand the Indicated PJM Transmission Owners each made just such a demonstration in \nresponse to the Show Cause Order, and the Joint Parties offer no meaningful rebuttal; \nthey simply make a number of conclusory assertions reflecting their own positions on the \nTariff’s alleged lack of clarity regarding co-location agreements.18 \nBecause the record supports a finding that the PJM Tariff remains just and \nreasonable, and not unduly discriminatory or preferential, there is no reason to convene \nsettlement judge proceedings (or any other process) to develop a replacement rate under \nFPA section 206 as proposed by the Joint Parties.19  \n                                            \n16  PJM Answer at 4, 32; Indicated PJM TOs Answer at 2. \n17  Joint Motion at 4. \n18  See id. at 3-4. \n19  The Commission should reject out of hand Joint Parties’ suggestion that even if “the Commission \nprefer[s] not to make such a conclusive finding . . . it should still set the matter for the settlement \nproceedings described herein to develop a replacement rate as if it had made such a finding.” Id. at 4 \nn.6. Absent a predicate finding that the existing Tariff is unjust, unreasonable and unduly discriminatory \nand preferential, there is no reason to “develop a replacement rate.” Further, such an approach would \ncontravene the Joint Parties’ own logic that the requested predicate finding by the Commission would \n“provide a clear signal for the parties to engage in meaningful discussions towards resolving their \nconcerns.” Id. at 5."},{"page":6,"startToken":1396,"endToken":1692,"text":"6 \nB. \nThe Commission should provide guidance on application of the \nexisting Tariff to co-located load arrangements. \nAlthough the existing PJM Tariff remains just and reasonable, AMP noted in its \nresponse that additional clarification and guidance concerning the treatment of co-located \nload could be beneficial.20 Such guidance should clarify that load co-located behind the \ninterconnection point of an adjacent generator in PJM must be considered Network Load \n(or load taking Point-to-Point Transmission Service). Further, the Commission should \nconfirm that the existing PJM Tariff provisions addressing netting of load served by BTMG \nand Non-Retail BTMG remain just and reasonable, which would provide assurances to \nentities that have relied on the longstanding provisions allowing for netting of Network \nLoad served by BTMG and Non-Retail BTMG to support investment in numerous small \ngenerating facilities that contribute significantly to maintaining resource adequacy in PJM. \nThe Commission can provide this guidance based on the extensive paper record that has \nalready been developed in these dockets. \nThe Commission could also provide guidance regarding possible Tariff changes \nthat PJM could propose to clarify the treatment of co-located load arrangements, \nparticularly given the concerns expressed by the Joint Parties about the lack of such \nclarity. The Indicated PJM Transmission Owners, for example, suggested a reasonable \ndefinition of “Co-located Load” that would appropriately clarify how co-located \narrangements fit within the existing PJM Tariff framework.21 Thus, instead of the \nunwarranted settlement judge procedures proposed by the Joint Parties, the Commission \n                                            \n20  See, e.g., AMP Response at 5; see also Indicated PJM TOs Answer at 2. \n21  See Indicated PJM TOs Answer at 9. AMP noted that the definition suggested by the Indicated PJM \nTransmission Owners would appropriately preserve the current treatment of load served by BTMG and \nNon-Retail BTMG. AMP Response at 6."},{"page":7,"startToken":1692,"endToken":1970,"text":"7 \nshould promote regulatory certainty by confirming the justness and reasonableness of the \nexisting Tariff, while providing guidance on the application of the existing Tariff to co-\nlocated load arrangements.  \nC. \nEven if the Commission concludes that the Tariff is unjust and \nunreasonable, unduly discriminatory or preferential, it should not \nconvene settlement judge procedures. \nEven if the Commission were to conclude that the existing PJM Tariff is unjust and \nunreasonable, or unduly discriminatory or preferential, it should not stay these \nproceedings or convene a settlement judge process as proposed by the Joint Parties. \nRather, given the importance of the issues relating to co-located arrangements and the \nneed for regulatory certainty in the PJM region on these issues, the Commission should, \nbased on the paper record developed in these dockets, provide clear instruction on the \ndesign of a replacement rate to address any deficiencies the Commission may identify in \nthe PJM Tariff.  \nSimply “defer[ring] to the parties in this proceeding to develop a new replacement \nrate”22 would unnecessarily delay resolution of the matter while participants engage in an \nadditional round of discussions on issues that they have thus far been unable to resolve \nwithout clear Commission guidance. As PJM has noted, for example, the PJM guidance \ndocument on co-located load arrangements – which PJM has now rescinded23 – was only \n“issued by PJM as an initial attempt to provide limited guidance after over a year’s worth \nof unfruitful stakeholder discussions.”24 There is no reason to believe that participants \nwould now be able to reach consensus on these issues in ninety days. While a predicate \n                                            \n22  Joint Motion at 4. \n23  PJM Answer at 33. \n24  Id. (emphasis added)."},{"page":8,"startToken":1970,"endToken":2269,"text":"8 \nfinding by FERC that the existing Tariff is unjust and unreasonable would require parties \nto focus on a replacement rate,25 such a finding would not necessarily make it any easier \nto resolve the competing views on how to address any Tariff deficiency absent clear \ndirection from the Commission. \nThere would also be practical challenges associated with a settlement judge \nprocess. Numerous parties that are not PJM members and that do not customarily \nparticipate in PJM-related proceedings before the Commission have intervened in the \nShow Cause Proceeding. These participants would presumably be entitled to participate \nin any settlement conferences, and would have an opportunity to comment on any \nproposed settlement.26 These parties may have valid and legitimate interests in the Show \nCause Proceeding that are not necessarily related to particular co-located load provisions \nin the PJM Tariff. Indeed, the Show Cause Order is not exclusively focused on the PJM \nTariff. The Commission, for example, also solicited input from interested parties on \njurisdictional issues related to co-located load arrangements generally.27 Non-PJM \nparties interested in general Commission guidance on jurisdictional and other generic \nissues might have limited incentive to support a non-precedential settlement limited to the \nPJM Tariff, all of which would likely complicate settlement discussions. \nFurther, as PJM observed in opposing Constellation’s similar request for \nsettlement judge procedures in consolidated Docket No. EL25-20, addressing these \nimportant co-located load issues – including issues that may impact stakeholders beyond \n                                            \n25  See, e.g., Joint Motion at 5 (arguing that “[t]he guidance provided by the Commission through an unjust \nand unreasonable and unduly discriminatory and preferential finding will provide a clear signal for the \nparties to engage in meaningful discussions towards resolving their concerns.”). \n26  18 C.F.R. § 385.602(f). \n27  See Show Cause Order at PP 65-73."},{"page":9,"startToken":2269,"endToken":2518,"text":"9 \nPJM – through confidential settlement discussions could raise transparency concerns.28 \nPJM cogently observed that “there are many parties interested in these matters and the \ntransparency demands of these parties (including state commissions) post challenges to \nsuch significant policymaking occurring through means of a contested hearing or \nsettlement procedures.”29 \nFinally, the settlement judge procedures used to resolve various Winter Storm \nElliott-related disputes do not provide an appropriate model for addressing any co-located \nload-related Tariff deficiencies that the Commission may identify.30 If the Commission \nwere to find the existing Tariff unjust and unreasonable, or unduly discriminatory or \npreferential, development of a replacement rate would need to account for numerous \npotentially competing considerations. In contrast, the Winter Storm Elliott complaint \nproceedings, while raising important questions about PJM’s Capacity Performance \nconstruct and its implementation, were ultimately “just about money,” making the matters \nmore amenable to compromise and settlement than the issues here.31 \n \n \n                                            \n28  See PJM, Answer and Motion to Dismiss, Docket No. EL25-20-000, at 4, 15-16 (Dec. 12, 2024). \n29  Id. at 4. \n30  See Joint Motion at 5 n.9 (citing Essential Power OPP, LLC v. PJM Interconnection, L.L.C., 183 FERC \n¶ 61,163, at PP 19-20 (2023)); see also id. at 7 n.18 (same). \n31  The same can be said of the settlement process established to resolve cost allocation issues in the \nGreenhat matter. See Joint Motion at 5 n.9 (citing PJM Interconnection, L.L.C., 167 FERC ¶ 61,209, at \nPP 28-29 (2019))."},{"page":10,"startToken":2518,"endToken":2596,"text":"10 \nIII. \nCONCLUSION \nWHEREFORE, for the foregoing reasons, American Municipal Power, Inc. \nrespectfully asks the Commission to deny the Joint Motion. \nRespectfully submitted, \n \n/s/ John McCaffrey             \nJohn McCaffrey \nStinson LLP  \n1775 Pennsylvania Avenue NW  \nSuite 800  \nWashington, DC 20006  \n(202) 728-3026  \njohn.mccaffrey@stinson.com \n \n/s/ Gerit F. Hull                          \nGerit F. Hull                                                  \nDeputy General Counsel for                       \n  Regulatory Affairs                                      \nAmerican Municipal Power, Inc.                   \n1111 Schrock Road, Suite 100  \nColumbus, OH 43229                                  \n(614) 540-1111 \nghull@amppartners.org \n \n \nMay 7, 2025"},{"page":11,"startToken":2596,"endToken":2660,"text":"CERTIFICATE OF SERVICE \n \nI hereby certify that I have this day served the foregoing document upon each \nperson designated on the official service lists compiled by the Secretary in these \nproceedings. \nDated at Washington, D.C., this 7th day of May, 2025. \n \n \n \n \n \n \n \n/s/ John McCaffrey                  \nJohn McCaffrey \nStinson LLP  \n1775 Pennsylvania Avenue NW  \nSuite 800  \nWashington, DC 20006  \n(202) 728-3026  \njohn.mccaffrey@stinson.com"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":2,"endAt":695,"startToken":0,"endToken":362},{"p":2,"at":695,"title":"I. BACKGROUND","method":"printed heading","endPage":4,"endAt":831,"startToken":362,"endToken":923},{"p":4,"at":831,"title":"II. ANSWER","method":"printed heading","endPage":4,"endAt":1209,"startToken":923,"endToken":980},{"p":4,"at":1209,"title":"A. The record supports a finding that the PJM Tariff remains just and","method":"printed heading","endPage":6,"endAt":3,"startToken":980,"endToken":1397},{"p":6,"at":3,"title":"B. The Commission should provide guidance on application of the","method":"printed heading","endPage":7,"endAt":213,"startToken":1397,"endToken":1722},{"p":7,"at":213,"title":"C. Even if the Commission concludes that the Tariff is unjust and","method":"printed heading","endPage":10,"endAt":4,"startToken":1722,"endToken":2519},{"p":10,"at":4,"title":"III. CONCLUSION","method":"printed heading","endPage":11,"endAt":0,"startToken":2519,"endToken":2596},{"p":11,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":11,"endAt":447,"startToken":2596,"endToken":2660}]}