{"document":{"slug":"rec-20250507-5143","title":"Answer of the Indicated PJM Transmission Owners to the 04/22/2025 Joint Comments, Motion to Stay Proceedings and Request to Establish Settlement Judge…","issued":"2025-05-07","accession":"20250507-5143","docket":"EL25-49-000","group":"PJM co-location compliance","filer":"Exelon CorporationAmerican Electric Power Service CorporationAMP Transmission, LLC ,CITY OF CLEVELAND V CLEV ELEC ILLUM ,City of Hamilton, OH ,Dominion Energy Services, Inc. ,Duke Energy Corporation ,Duquesne Light Company ,FirstEnergy Service Company ,East Kentucky Power Cooperative, Inc. ,Old Dominion Electric Cooperative ,PPL Electric Utilities Corporation ,Rockland Electric Company ,Southern Maryland Electric Cooperative, Inc. ,Wabash Valley Power Association, Inc. ,UGI Utilities Inc. ,","kind":"answer","file":"sources/filings/text/20250507-5143_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20250507-5143","tier":"record","sha256":"081cc00b855f5abe1a8f93c38c5d334258988755b2fd7ce79eb768d7bbe72b46","pages":10,"tokens":2321,"emptyPages":[],"textThemes":["colo"]},"pages":[{"page":1,"startToken":0,"endToken":350,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \nPJM Interconnection, L.L.C., et al. \n \n) \nDocket No. EL25-49-000 \n \nLarge Loads Co-Located at Generating \nFacilities \n) \nDocket No. AD24-11-000 \nConstellation Energy Generation, LLC \n \nv. \n \nPJM Interconnection, L.L.C. \n) \nDocket No. EL25-20-000 \n(consolidated) \n \nANSWER OF THE INDICATED PJM TRANSMISSION OWNERS \n TO THE MOTION TO STAY PROCEEDINGS  \n \nPursuant to Rules 212 and 2131 of the Rules of Practice and Procedure of the Federal \nEnergy Regulatory Commission (“FERC” or “Commission”), the Indicated PJM Transmission \nOwners (hereinafter, “Indicated TOs”)2 submit this Answer to the April 22, 2025 Joint Comments \nand Motion to Stay Proceedings and Request to Establish Settlement Judge Procedures (“Stay \n \n \n1  18 C.F.R. §§ 385.212, 385.213 (2024). \n2  The Indicated PJM Transmission Owners include: American Electric Power Service Corporation, on behalf of \nAppalachian Power Company, Indiana Michigan Power Company, Kentucky Power Company, Kingsport Power \nCompany, Ohio Power Company, Wheeling Power Company, AEP Appalachian Transmission Company, Inc., AEP \nIndiana Michigan Transmission Company, Inc., AEP Kentucky Transmission Company, Inc., AEP Ohio \nTransmission Company, Inc., and AEP West Virginia Transmission Company, Inc.; AMP Transmission, LLC; City \nof Cleveland, Department of Public Utilities, Division of Cleveland Public Power; City of Hamilton, OH; Dominion \nEnergy Services, Inc. on behalf of Virginia Electric and Power Company d/b/a Dominion Energy Virginia; Duke \nEnergy Corporation on behalf of its affiliates Duke Energy Ohio, Inc., Duke Energy Kentucky, Inc., and Duke \nEnergy Business Services LLC; Duquesne Light Company; East Kentucky Power Cooperative; Exelon Corporation, \non behalf of Atlantic City Electric Company, Baltimore Gas and Electric Company, Commonwealth Edison \nCompany, Commonwealth Edison Company of Indiana, Inc., Delmarva Power & Light Company, PECO Energy \nCompany, and Potomac Electric Power Company; FirstEnergy Service Company, as agent for its affiliates American \nTransmission Systems, Incorporated, Jersey Central Power & Light Company, Mid-Atlantic Interstate Transmission \nLLC, Keystone Appalachian Transmission Company, The Potomac Edison Company, Monongahela Power \nCompany and Trans-Allegheny Interstate Line Company (collectively, the “FirstEnergy Transmission Companies”); \nOld Dominion Electric Cooperative; PPL Electric Utilities Corporation; Rockland Electric Company; Southern \nMaryland Electric Cooperative, Inc.; UGI Utilities Inc; and Wabash Valley Power Association, Inc."},{"page":2,"startToken":350,"endToken":616,"text":"2 \n \nMotion”) of the Electric Power Supply Association, the PJM Power Providers Group, Calpine \nCorporation, Cogentrix Energy Power Management, LLC, Constellation Energy Generation, LLC, \nand LS Power Development, LLC (“Joint Movants”). \nI. ARGUMENT \n \nThe Stay Motion is unnecessary as the record in this proceeding is clear on two \nfundamental points.  First, all parties have expressed interest in the Commission providing \nregulatory guidance as soon as possible to bring clarity and assist with the current challenges and \ndisputes.  Second, the existing PJM Open Access Transmission Tariff (“PJM Tariff”) is just and \nreasonable in regard to co-location arrangements and therefore the Commission has everything it \nneeds to provide the expeditious regulatory guidance everyone seeks.   \nIn order to take any action imposing changes to the PJM Tariff in a Federal Power Act \n(“FPA”) section 206 proceeding,3 the Commission must first find that the existing PJM Tariff is \nnot just and reasonable.  No such showing has been made and thus there is no basis to pause the \nCommission’s effort to expeditiously provide guidance without first satisfying that threshold \nrequirement.  Indeed, the record in this proceeding demonstrates that the existing PJM Tariff \nremains just and reasonable.  Unless and until the Commission finds to the contrary under FPA \nsection 206, there are no grounds to amend the PJM Tariff.      \nNumerous commenters in this proceeding address the national security implications of \nservice to these new large loads.  The truth is that the national interest will be best served by a \nquick dismissal of this proceeding, and a ruling that the existing PJM Tariff remains just and \n \n \n3  16 U.S.C. § 824e."},{"page":3,"startToken":616,"endToken":920,"text":"3 \n \nreasonable.  Rather than fighting about a wish list of new rules, the parties will then instead begin \nto focus on obtaining service under the rules in place today.   \na. The PJM Tariff Has Not Been Shown to Be Unjust and Unreasonable. \nIn a proceeding under section 206 of the FPA, the Commission can only remedy a “rate \n[or] charge” or “any rule, regulation, practice, or contract affecting such rate [or] charge” after it \nis found to be “unjust [or] unreasonable.”4  “The burden of proving an unjust or unreasonable rate \nrests with the party that initiated the proceeding—the Commission [(as in this case)] or the third-\nparty complainant.”5  Only after a successful showing that the prevailing rate is unjust and \nunreasonable may the Commission order a replacement rate.6  No such showing has been made \nhere. \nThe Stay Motion succinctly summarizes the arguments for why the existing rate is \npurportedly unjust and unreasonable.7  The arguments boil down to the following: while the PJM \nTariff provides that wholesale customers serving load in the PJM Interconnection L.L.C. (“PJM”) \nregion should do so with Network Integration Transmission Service, a certain class of wholesale \ncustomer would rather take some new and different type of service that would cost them less.   \nOf course, nearly everyone who buys nearly any service would rather pay less.  But in PJM, \nthe transmission owners, as in virtually every other piece of the grid regulated by the Commission, \nassess on a postage-stamp basis, without consideration of the distance between load and \ngeneration, the embedded costs of their respective portions of the transmission grid from network \n \n \n4  Id. § 824e(a). \n5  Pub. Citizen, Inc. v. FERC, 7 F.4th 1177, 1183 (D.C. Cir. 2021). \n6  16 U.S.C. § 824e(a). \n7  See Stay Motion at 3–4."},{"page":4,"startToken":920,"endToken":1357,"text":"4 \n \ncustomers.8  As the Commission has explained, “PJM recovers the full revenue requirements of \nexisting facilities (embedded costs) through its firm transmission rates.”9  And the Commission \nhas in recent years continued to reject requests that loads that claim reduced system impact merit \nsome new third category of lower-cost transmission service.10  \nThe Joint Movants seek to move past the need for a finding that the existing rate is unjust \nand unreasonable and thus ask for procedures that investigate the second step of an FPA section \n206 proceeding (fixing a new rate) while bypassing the first step.  But the first step matters.  Unless \nand until the Commission makes a finding that the existing rate is unjust and unreasonable, any \nnegotiation will be unproductive.11  Most importantly, the Commission has no authority to direct \nrelief under FPA section 206 absent a finding that the existing tariff is unjust and unreasonable. \nb. Reliability Is at Stake. \nThe Indicated TOs, which include investor-owned utilities, municipalities, and \ncooperatives, all believe that treating co-located load as anything other than Network Load would \nincrease the risk of reliability failures and resource inadequacy in PJM.  Much of what is being \n \n \n8  See, e.g., Pennsylvania-New Jersey-Maryland Interconnection, et al., 81 FERC ¶ 61,257 (1997) (adopting PJM \npricing proposal to allow recovery of embedded transmission revenue requirement from network customers), \ncorrected by, 82 FERC ¶ 61,103 (1998), and clarified in part by, 92 FERC ¶ 61,282 (2000), and review granted in \npart, vacated in part by, 295 F.3d 1 (D.C. Cir. 2002); PJM Tariff, Section 34.1 (providing for payment by network \ncustomers of load ratio share of embedded cost of their zone); PJM Tariff, Attachments H-1, H-1A, H-2, H-2A, H-\n3, H-3D, H-7, H-7A, H-9, H-9A, H-13, and H-13A (establishing network revenue requirements for each of the \nExelon Utilities based on the embedded costs of their respective transmission systems). \n9  PJM Interconnection L.L.C., 139 FERC ¶ 61,243, at P 78 n.105 (2012). \n10  See, e.g., Nat’l R.R. Passenger Corp. v. PPL Elec. Utils. Corp. et al., 171 FERC ¶ 61,237, order on reh’g, 173 FERC \n¶ 61,043 (2020). \n11  If the Commission were to determine that something about the existing PJM Tariff is unjust and unreasonable, the \nCommission would no doubt provide guidance on what aspect needs reform, allowing the parties to hone the \ndiscussion and focus on the parts that are really at issue.  Absent such guidance and direction, any settlement talks \nwould be truly gargantuan in scope—and likely set the stage for further delay followed unfortunately by failure and \nthen even more delay."},{"page":5,"startToken":1357,"endToken":1577,"text":"5 \n \nproposed involves obscuring loads from the grid operator and hoping that the grid is not impacted.  \nQuestions raised by the North American Electric Reliability Corporation highlight the importance \nof these concerns.12  The record is clear—no matter how connected to the PJM Transmission \nSystem, large loads pose both a safety and a reliability concern.  It is unrealistic to ask the Indicated \nTOs to accede to these demands in the context of settlement procedures while those questions \nremain unresolved. \nII. CONCLUSION \nThe national interest will not be well served if service requests under the existing rules are \nfurther delayed by the outcome of this proceeding in which a number of parties attempt to rewrite \nthe PJM Tariff.  Instead, the best way to promote co-located load customers is to provide certainty, \nwhich the Commission can accomplish quickly by simply clarifying that co-located loads should \nseek service under the well-established, just and reasonable terms of the existing PJM Tariff.   \nFor the reasons stated above, the Indicated TOs respectfully request that the Commission \nreject the Stay Motion.   \n \n \n \n \n \n12  There are profound reliability issues associated with large data center loads that are being actively investigated right \nnow.  See, e.g., Comments of the North American Electric Reliability Corporation (“NERC”) (Apr. 23, 2025); Item \nE-4 Presentation by NERC at April 17, 2025 Commission meeting."},{"page":6,"startToken":1577,"endToken":1786,"text":"6 \n \nRespectfully submitted, \n \n \n \n \n/s/ William Sauer \nWilliam Sauer \nVice President, Federal Regulatory Affairs  \nExelon Corporation  \n701 Ninth St. N.W.  \nWashington, DC 20001  \nTelephone: 202-868-7499  \nEmail: william.sauer@exeloncorp.com   \n/s/ Max Minzner \n \nMax Minzner \nVice President and Deputy General Counsel \nExelon Corporation \n701 Ninth St. N.W.  \nWashington, DC 20001  \nTelephone: 202-934-4740 \nEmail: max.minzner@exeloncorp.com \n \n \nOn behalf of Exelon Corporation \n \n/s/ Stacey Burbure \nStacey Burbure \nVice President FERC, RTO Strategy & Policy \nAmerican Electric Power Service Corporation \n1 Riverside Plaza  \nColumbus, OH 43215 \nTelephone: 614-716-2502  \nEmail: slburbure@aep.com \n \n/s/ Lisa G. McAlister \nLisa G. McAlister \nAMP Transmission, LLC \n1111 Schrock Road, Suite 100 \nColumbus, Ohio 43229 \nTelephone: 614-540-6400 \nEmail: lmcalister@amppartners.org \n \nOn behalf of American Electric Power \nService Corporation \n \nOn behalf of AMP Transmission, LLC \n \n/s/ Martin J. Keane \nMartin J. Keane \nDirector of Public Utilities \nCleveland Public Power \n1300 Lakeside Ave. \nCleveland, OH 44114 \nTelephone: 216-664-2444 ext. 75604 \nEmail: martin_keane@clevelandwater.com \n \n/s/ Debra D. Roby \nDebra D. Roby \nWashington Energy Law LLP \n900 17th Street N.W., Suite 500-A \nWashington, D.C. 20006 \nTelephone: 703-785-9270 \nEmail: droby@washingtonenergylaw.com \n \nOn behalf of City of Cleveland, Department of \nPublic Utilities, Division of Cleveland Public \nPower \n \nOn behalf of the City of Hamilton, OH"},{"page":7,"startToken":1786,"endToken":1999,"text":"7 \n \n/s/ Wesley Walker \nWesley Walker \nSenior Assistant General Counsel \nDominion Energy Services, Inc. \n120 Tredegar Street \nRichmond, VA 23219 \nTelephone: 804-819-2345 \nEmail: wesley.walker@dominionenergy.com \n \n/s/ Molly Suda  \nMolly Suda \nAssociate General Counsel \nAnnelise Rickert  \nFederal Government Affairs Director \nDuke Energy Corporation \n1301 Pennsylvania Ave NW, Suite 200 \nWashington, DC 20004 \nTelephone: 202-824-8011 \nEmail:  molly.suda@duke-energy.com  \nAnnelise.rickert@duke-energy.com         \n   \nOn behalf of Dominion Energy \nOn behalf of Duke Energy \n \n/s/ Michael Brechlin \nMichael Brechlin \nPA Bar # 335424 \nDuquesne Light Company \n411 7th Ave \nPittsburgh, PA 15219 \nTelephone: 412-393-6431 \nEmail: mbrechlin@duqlight.com \n/s/   Amanda P. Parker \nAmanda P. Parker \nAttorney \nFirstEnergy Service Company \n76 South Main Street \nAkron, OH 44308 \nTelephone: (330) 384-4592 \nEmail: aparker@firstenergycorp.com  \n \nOn behalf of Duquesne Light Company \nOn behalf of The FirstEnergy Transmission \nCompanies \n \n/s/ Denise R. Foster Cronin \nDenise R. Foster Cronin \nVice President, Federal and RTO Regulatory \nAffairs \nEast Kentucky Power Cooperative, Inc. \n4775 Lexington Road, P.O. Box 707 \nWinchester, KY 40392-0707 \nTelephone: 859-745-9615 \nEmail: denise.cronin@ekpc.coop \n \n/s/ Daniel E. Frank                  \nDaniel E. Frank \nKelly Cuthbertson \nEversheds Sutherland (US) LLP \n700 Sixth St., N.W., Suite 700 \nWashington, DC 20001-3980 \nTelephone: 202-383-0100 \nEmail:  \ndanielfrank@eversheds-sutherland.com \nkellycuthbertson@eversheds-sutherland.com \n \n \n \nOn Behalf of East Kentucky Power \nCooperative, Inc."},{"page":8,"startToken":1999,"endToken":2215,"text":"8 \n \n/s/ Adrienne E. Clair \nAdrienne E. Clair \nThompson Coburn LLP \n1909 K Street, N.W., Suite 600 \nWashington, D.C.  20006-1167 \nTelephone: 202-585-6900 \nEmail: aclair@thompsoncoburn.com \n \n/s/ Steve Nadel \nSteven M. Nadel \nSenior Counsel \nPPL Services Corp.  \n645 Hamilton Street, Suite 601 \nAllentown, PA 18101 \nTelephone: 610-774-4775   \nEmail: SMNadel@pplweb.com \n \nOn behalf of Old Dominion Electric \nCooperative \n \nOn behalf of PPL Electric Utilities Corp. \n \n/s/David Burns  \nDavid Burns  \nSenior Manager,  \nFERC Policy & Regulatory Affairs  \nConsolidated Edison Company of New York, \nInc.   \n4 Irving Place \nNew York, NY 10003   \nTelephone: 571-678-9152  \nEmail: burnsd@coned.com \n/s/Joshua Kirstein \nJoshua A. Kirstein  \nSenior Attorney  \nLaw Department \nConsolidated Edison Company of New York, \nInc.  \n4 Irving Place, 18th Floor  \nNew York, NY 10003  \nTelephone: 929-656-5971 \nEmail: kirsteinj@coned.com \n \n \nOn behalf of Rockland Electric Company \n \n/s/ Damon L. Krieger \nDamon L. Krieger \nGroup Vice President, Legal, Strategy, and \nSustainability, and Deputy General Counsel \nSouthern Maryland Electric Cooperative, Inc. \n15035 Burnt Store Road \nP.O. Box 1937 \nHughesville, Maryland 20637-1937 \nTelephone: 301-274-4323 \nEmail: Damon.Krieger@SMECO.coop \n \n/s/ Jeremy L. Fetty \n \nJeremy L. Fetty \nParr Richey \n251 N. Illinois, Suite 1800 \nIndianapolis, Indiana 46204  \nTelephone: 317-269-2500 \nEmail: j_fetty@wvpa.com \n \n \nOn behalf of Southern Maryland Electric \nCooperative \n \nOn behalf of Wabash Valley Power \nAssociation, Inc."},{"page":9,"startToken":2215,"endToken":2275,"text":"9 \n \n/s/ Lindsay Berkstresser \nLindsay Berkstresser \nCounsel – Energy & Regulatory \nUGI Corporation \n500 North Gulph Road \nKing of Prussia, PA 19406 \nTelephone: 717-504-9925 \nEmail: berkstresserl@ugicorp.com \n \n/s/ Richard P. Bonnifield \nRichard P. Bonnifield \nHusch Blackwell \n1801 Pennsylvania Avenue, NW, \nSuite 1000 \nWashington, DC 20006-3606 \nTelephone: 202-243-8844 \nEmail: \nrichard.bonnifield@huschblackwell.com \n \n \n \nOn behalf of UGI Utilities Inc. \n \nMay 7, 2025"},{"page":10,"startToken":2275,"endToken":2321,"text":"CERTIFICATE OF SERVICE \n \nI hereby certify that I have this day served the foregoing document upon each person \ndesignated on the official service list in the above captioned dockets. \nDated at Chicago, IL this 7th day of May, 2025. \n \n/s/ Geneva Kennedy  \nGeneva Kennedy  \nExelon Corporation"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":2,"endAt":238,"startToken":0,"endToken":381},{"p":2,"at":238,"title":"I. ARGUMENT","method":"printed heading","endPage":5,"endAt":516,"startToken":381,"endToken":1437},{"p":5,"at":516,"title":"II. CONCLUSION","method":"printed heading","endPage":10,"endAt":0,"startToken":1437,"endToken":2275},{"p":10,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":10,"endAt":292,"startToken":2275,"endToken":2321}]}