{"document":{"slug":"rec-20250508-5081","title":"Motion for Leave to Answer and Answer of Vistra Corp. to the 04/23/2025 comments filed by North American Electric Reliability Corporation, et al","issued":"2025-05-08","accession":"20250508-5081","docket":"EL25-49-000","group":"PJM co-location compliance","filer":"Vistra Corp.","kind":"answer","file":"sources/filings/text/20250508-5081_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20250508-5081","tier":"record","sha256":"9a9bbdadde625f87d5046fe355bb8d5364c53c481e6d9aa7f9f9d41d6c5db3c8","pages":29,"tokens":7492,"emptyPages":[],"textThemes":["colo","study","registry","adequacy"]},"pages":[{"page":1,"startToken":0,"endToken":176,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \n \nPJM Interconnection, L.L.C. \nAllegheny Electric Cooperative, Inc. \nAmerican Transmission Systems, Incorporated \nAtlantic City Electric Company \nBaltimore Gas and Electric Company \nDelmarva Power & Light Company \nDuke Energy Ohio, Inc. \nDuke Energy Kentucky, Inc. \nEast Kentucky Power Cooperative, Inc. \nEssential Power Rock Springs, LLC \nHudson Transmission Partners, LLC \nJersey Central Power & Light Company \nMid-Atlantic Interstate Transmission, LLC \nNeptune Regional Transmission System, LLC \nOld Dominion Electric Cooperative \nPECO Energy Company \nPPL Electric Utilities Corporation \nPotomac Electric Power Company \nPublic Service Electric and Gas Company \nRockland Electric Company \nTrans-Allegheny Interstate Line Company \nTransource West Virginia, LLC \nUGI Utilities, Inc. \nMonongahela Power Company \nThe Potomac Edison Company \nCommonwealth Edison Company \nCommonwealth Edison Company of Indiana, Inc. \nThe Dayton Power and Light Company  \nAEP Appalachian Transmission Company, Inc. \nAEP Indiana Michigan Transmission Company, Inc. \nAEP Kentucky Transmission Company, Inc. \nAEP Ohio Transmission Company, Inc. \nAEP West Virginia Transmission Company, Inc. \nAppalachian Power Company \nIndiana Michigan Power Company \nKentucky Power Company \nKingsport Power Company \nOhio Power Company\nDocket Nos. EL25-49-000 \nEL25-49-001"},{"page":2,"startToken":176,"endToken":342,"text":"-2- \nWheeling Power Company \nDuquesne Light Company \nVirginia Electric and Power Company \nLinden VFT, LLC \nCity of Cleveland, Department of Public Utilities, \nDivision of Cleveland Public Power \nCity of Hamilton, OH \nSouthern Maryland Electric Cooperative, Inc. \nOhio Valley Electric Corporation \nAMP Transmission, LLC \nSilver Run Electric, LLC \nNextEra Energy Transmission MidAtlantic Indiana, Inc.\nWabash Valley Power Association, Inc. \nKeystone Appalachian Transmission Company \n \nLarge Loads Co-Located at Generating Facilities  \n \n \nConstellation Energy Generation, LLC \n \nv.  \n \nPJM Interconnection, L.L.C. \n \n \n \n \n \n \n \n \n \n \n \n \n \n \n \n \nAD24-11-000 \n \n \nEL25-20-000 \n(Consolidated) \n \n \n \n \nMOTION FOR LEAVE TO ANSWER AND ANSWER OF VISTRA CORP. \n \nPursuant to Rules 212 and 2131 of the Federal Energy Regulatory Commission’s \n(“Commission”) Rules of Practice and Procedure, Vistra Corp. (“Vistra”) hereby moves to answer \nand answers the comments filed on April 23, 2025, by the North American Electric Reliability \nCorporate (“NERC”), Americans for a Clean Energy Grid (“ACEG”), Organization of PJM States \n(“OPSI”), and Public Interest Organizations (“PIOs”) in response to the Commission’s February \n \n1  \n18 C.F.R. §§ 385.212, 385.213 (2024)."},{"page":3,"startToken":342,"endToken":791,"text":"-3- \n20, 2025 Order (“Show Cause Order”)2 and PJM Interconnection, L.L.C.’s (“PJM”) answer (“PJM \nAnswer”).3  \nI. \nMOTION FOR LEAVE TO ANSWER \nAlthough the Commission’s procedural rules generally do not allow answers to answers, \nthe Commission may permit them for good cause.4  The Commission frequently accepts answers \nthat clarify the issues before the Commission, ensure a complete record, or otherwise assist the \nCommission in its decision-making.5  Vistra respectfully requests that the Commission accept this \nanswer to clarify certain issues and assist the Commission with its decision-making. \nII. \nANSWER \nThe record in this proceeding provides strong support for the Commission to set a \nreplacement rate to require PJM to accommodate behind-the-meter co-located load. There is \ngeneral agreement that there is a need for PJM to accommodate new, large loads to support our \nnational security and economic growth.6  There is also a general consensus that PJM’s current \n \n2  \nPJM Interconnection, L.L.C., 190 FERC ¶ 61,115 (2025) (“Show Cause Order”). \n3  \nAnswer of PJM Interconnection, L.L.C., Docket No. EL25-49 (filed Mar. 24, 2025) (“PJM Answer”). \n4  \n18 C.F.R. § 385.213(a)(2) (“An answer may not be made to a protest, an answer, a motion for oral argument, or \na request for rehearing, unless otherwise ordered by the decisional authority.”). \n5  \nSee, e.g., PJM Interconnection, L.L.C., 182 FERC ¶ 61,073, at P 13 (2023) (accepting answers to answers that \n“provided information that assisted us in our decision-making process”); New Fortress Energy LLC, 174 FERC ¶ \n61,207, at P 7 (2021) (accepting answers because they provided information that assisted the Commission’s decision-\nmaking process); Alaska Gasline Dev. Corp., 171 FERC ¶ 61,134, at P 7 (2020) (accepting answers that “clarify the \nconcerns raised and provide information that has assisted in our decision making”); Saltville Gas Storage Co., L.L.C., \n164 FERC ¶ 61,212, at P 2 n.6 (2018) (accepting answers that “assist the Commission in understanding the issues \nraised, and will ensure a complete record”). \n6  \nSee, e.g., Comments of Chevron U.S.A. Inc, Docket No. EL25-49, at 2-4 (filed April 23, 2025); Answer of \nConstellation Energy Generation, LLC, Docket No. EL25-49, at 3 (filed April 23, 2025) (“Constellation Comments”); \nComments of Advanced Energy United, Docket No. EL25-49, at 2 (filed April 23, 2025); Comments of the Data \nCenter Coalition, Docket No. EL25-49, at 1-2 (filed April 23, 2025); Comments of the Edison Electric Institute, \nDocket No. EL25-49, at 3-4 (filed April 23, 2025); Comments of the Business Council for Sustainable Energy, Docket \nNo. EL25-49, at 2 (filed April 23, 2025); Comments of Electricity Consumers Resource Council, Docket No. EL25-\n49, at 10."},{"page":4,"startToken":791,"endToken":1258,"text":"-4- \ntariff does not sufficiently accommodate the co-location of large loads behind a generator’s meter.7  \nThe disagreement, as distilled by the filed comments, appears to be over whether that lack of \naccommodation of behind-the-meter co-location is lawful.  Some commenters agree with PJM that \nthe tariff remains just and reasonable even though it does not accommodate behind-the-meter co-\nlocated load.8  However, consistent with the Show Cause Order and the Susquehanna ISA \nRehearing Order,9 many commenters recognize that the existing tariff is not just and reasonable \nand/or that the tariff is being implemented in an unduly discriminatory manner.10   \nAs discussed further below, there is no valid basis to discriminate against behind-the-meter \nco-located load.  Moreover, none of the commenters that support discriminating against behind-\nthe-meter load provide any analytic support to justify that position.  Their comments rely on vague \nand unsupported assertions that behind-the-meter co-located load raises reliability and resource \n \n7 \nSee, e.g., Comments of the Independent Market Monitor for PJM, Docket No. EL25-49, at 2 (filed April 23, 2025) \n(“The Market Monitor agrees that clear rules governing all aspects of the addition of large loads are required.”); \nConstellation Comments at 3 (“The Commission was right that the existing PJM Tariff lacks requisite clarity, and this \nhas paralyzed co-location efforts and service to data centers.”); Comments of Northern Virginia Electric Cooperative, \nDocket No. EL25-49, at 8 (filed April 23, 2025) (“NOVEC Comments”); Comments of Indicated PJM Transmission \nOwners, Docket No. EL2-49, at 4 (filed April 23, 2025) (“Indicated PJM TOs Comments”). \n8  \nSee NOVEC Comments at 8; Indicated PJM TOs Comments at 4.  \n9 \nShow Cause Order at P 3 (directing PJM to explain why its tariff remains just and reasonable without provisions \naddressing behind-the-meter co-location or to explain what changes to the tariff would remedy the absence of such \nprovisions); PJM Interconnection, L.L.C., 191 FERC ¶ 61,025, at P 60 (2025) (“Susquehanna ISA Rehearing Order”) \n(“[W]e clarify that the Rejection Order does not prevent entities from filing non-conforming interconnection \nagreements to address matters related to a generator serving co-located load, or prejudge any such future filing.”). \n10 \nSee, e.g., Constellation Comments at 3; Comments of BrightNight Power Marketing, LLC, Docket No. EL25-49, \nat 3; Comments of Electric Power Supply Association, Docket No. EL25-49, at 2-3 (filed April 23, 2025); Comments \nof Solar Energy Industries Association, Docket No. EL25-49, at 5 (filed April 23, 2025); Comments of Talen Energy \nCorporation, Docket No. EL25-49, at 12 (filed April 23, 2025); see also Comments of Engie North America, Inc., \nDocket No. EL25-49, at 4-5 (filed April 23, 2025) (explaining that the “current tools in PJM’s existing tariff” are \ninadequate); Comments of PJM Industrial Customer Coalition, Docket No. EL25-49, at 7 (filed April 23, 2025) \n(“Indicated TO’s proposed approach is also unduly discriminatory.”)."},{"page":5,"startToken":1258,"endToken":1619,"text":"-5- \nadequacy concerns.11  To contrast, Vistra’s initial comments included an affidavit by Dr. Roy \nShanker, which provided a robust and analytically sound assessment of the various configurations \nin which new large loads can be added to the system.12  Dr. Shanker found that Options 4 and 5 \nare “dominant” configurations, in that they provide benefits to all parties, including other market \nparticipants, when compared to other potential load configurations, such as Option 1.13  \nIn its initial comments, Vistra suggested a specific replacement rate to ensure that the tariff \naccommodates Option 4 and 5 configurations in a just and reasonable and not unduly \ndiscriminatory manner.14  That proposal would ensure that co-location configurations that fit \nwithin Options 4 and 5 pay their fair share and that other customers are not harmed.  The \nCommission can and should adopt that replacement rate quickly to remedy undue discrimination \nand ensure that PJM accommodates Options 4 and 5 in a just and reasonable and not unduly \ndiscriminatory manner.  Vistra also continues to believe that Options 6-8 should be further \nexplored to provide customers with flexibility to engage in other types of beneficial transactions.  \nHowever, each of these configurations also appears likely to require more involved tariff \nmodifications than those needed for Options 4 and 5.  The Commission should direct PJM to \nengage with stakeholders to implement further reforms to facilitate Options 6-8.   \nBeyond the general issues discussed above, this Answer addresses certain specific issues \nraised in the record, including the reliability concerns associated with the addition of new large \n \n11 \nSee, e.g., NOVEC Comments at 11 (“If co-location arrangements like the configuration advanced by the \nConstellation complaint are permitted, they will present reliability challenges.”); Comments of Buckeye Power, Inc., \nDocket No. EL25-49, at 2-3 (filed April 23, 2025) (arguing that front-of-the-meter co-located loads are “a better \nalternative for reliability and resource adequacy[.]”). \n12 \nComments of Vistra Corp., Docket No. EL25-49, Attach. A, Affidavit of Dr. Roy J. Shanker, PhD on Behalf of \nVistra Corp. (filed April 23, 2025) (“Dr. Shanker Aff.”). \n13 \nId. PP 52-70. \n14 \nSee Comments of Vistra Corp., Docket No. EL25-49, at 22-31 (filed April 23, 2025) (“Vistra Initial Comments”)."},{"page":6,"startToken":1619,"endToken":1931,"text":"-6- \nloads, the transparency of the necessary study process, and improvements to PJM’s load \nforecasting practices.  As discussed below, the reliability concerns raised in the docket relate to all \nnew large loads, not just those that are co-located with a generator.  Therefore, such concerns do \nnot justify discrimination against behind-the-meter co-located loads.  Concerns about the \ntransparency of the necessary study process are reasonable, but can be addressed in a \nstraightforward manner, by posting necessary study results online in a manner similar to other \ninterconnection study results (and with appropriate measures to protect confidential or sensitive \ninformation).  These concerns do not justify discrimination against behind-the-meter co-located \nloads, nor do they require an overhaul of the necessary study process itself.  Finally, Vistra agrees \nwith the suggestions made in the record to improve PJM’s load forecasting process.  In particular, \nACEG’s proposal to require new large loads to make substantial financial commitments before \nthey can be included in PJM’s load forecast would help prevent the inclusion of duplicative load \ninterconnection requests in the load forecast.  Development of such a reform would be a natural \nfit within a separate, broader proceeding focused on standardizing the transmission-level load \ninterconnection process, which Vistra also suggested in its initial comments.   \nA. The Reliability Concerns Raised in Comments Apply to All New Large Loads, \nRegardless of Whether They Are Co-Located  \nNERC’s comments provided insight into its recent “initiatives addressing large loads.”15  \nTo provide further context regarding these reliability concerns, attached to this Answer is an \naffidavit by Steven Herling, PJM’s former VP of Planning, an electrical engineer with 30 years of \nexperience with reliability analyses in PJM.16  As Mr. Herling explains, the reliability concerns \n \n15 \nComments of the North American Electric Reliability Corporation, Docket No. EL25-49, at 2-10 (filed April 23, \n2025) (“NERC Comments”). \n16 \nAffidavit of Steven R. Herling on Behalf of Vistra Corp., Attach. A (“Herling Aff.”)."},{"page":7,"startToken":1931,"endToken":2216,"text":"-7- \nthat NERC flagged relate to the voltage sensitivity of new large loads.17  This voltage sensitivity, \nhowever, “is not a co-location issue,” because it is “equally, or perhaps even more appliable to \nfront-of-the-meter interconnections of large data centers, such as contemplated in PJM’s Option \n1.”18  In fact, the particular incident that NERC discussed in Attachment 2 does not appear to have \ninvolved any co-located data centers.  There is no reason to believe that a behind-the-meter co-\nlocated data center would have worsened this event; in fact, co-location may actually make such \nevents less likely because “co-located generators are, themselves, a voltage source with automatic \nvoltage regulators, reducing the likelihood that grid disturbances will exceed the threshold \nassociated with voltage-sensitive data center loads.”19  Nonetheless, NERC concluded that the \nevent “did not cause significant operating issues with the grid.”20 \nMinimizing any reliability concerns associated with the co-location of large loads would \nincorporate the same processes and studies utilized to address all other reliability concerns.  As \nMr. Herling explains, “the modeling elements required to perform power flow, short circuit, and \ndynamic analysis for the various co-location options proposed by PJM are all knowable and any \noperational actions included in PJM’s proposed options are readily modeled.”21  The necessary \nstudy process includes all of the same models and analytic tools to evaluate contingencies that are \nused in RTEP studies.22  The reliability impacts of new large loads, either alone or in combination \nwith a generator, are knowable and can be addressed by proper coordination between PJM, the \n \n17 \nId. PP 15, 21. \n18 \nId. P 21. \n19 \nId.  \n20  NERC Comments, Attach. B, at 8.  \n21 \nHerling Aff. at P 19.  \n22 \nId. P 18."},{"page":8,"startToken":2216,"endToken":2472,"text":"-8- \napplicable transmission owner, and the co-located load customer.  This type of coordination is not \nnovel in managing reliability impacts of new load of all types.23  NERC recommends that PJM \nshould ensure the availability of data and information to support reliability analysis, coordination, \nload balancing, and accurate modeling for co-located large loads.  These recommendations are \nsensible, but there is nothing groundbreaking or new about them.24  Sufficient data and information \nsharing has always been necessary to study the reliability of any new addition on the grid.  Any \nnew requirements must apply to all new large loads, not just those that are co-located with a \ngenerator.   \nThe existence of reliability concerns related to new, large loads in general does not justify \nprohibiting or delaying the addition of behind-the-meter load.  In fact, as NERC explained: \nProximity between large loads and power generation sources can \nreduce energy loss while improving transmission reliability.  This \nco-location fosters improved coordination, leading to better load \nmanagement and reduced strain on the BPS . . . NERC noted that \nnuclear power is a particularly advantageous resource for co-located \nlarge loads due to its inherent high-capacity factor, load-carrying \nability, and steady performance even in extreme weather \nconditions.25  \n \nWhile transmission owners argue against behind-the-meter co-location, despite its \nreliability benefits compared to Option 1 configurations, transmission owners are moving full \nsteam ahead interconnecting new front-of-the-meter large loads.  For example, Exelon utilities \nrecently announced on an earnings call that their load interconnection queue includes 16 GW of \n \n23 \nSee id. P 22. \n24 \nId. \n25 \nNERC Comments at 6."},{"page":9,"startToken":2472,"endToken":2837,"text":"-9- \nnew large loads that have already paid deposits.26  Exelon expects to connect 1.6 GW of that load \nby 2028, 5.3 GW by 2030, and 12 GW by 2034.27  Exelon anticipates that these front-of-the-meter \nload interconnections will trigger up to $15 billion in transmission upgrades,28 which will go \ndirectly into Exelon’s rate base.29  Given that front-of-the-meter large loads raise similar reliability \nconcerns as behind-the-meter co-located loads, one can infer that these reliability concerns are not \ninsurmountable.  It would be unduly discriminatory to permit front-of-the-meter arrangements and \nprohibit or delay co-location arrangements based on alleged reliability concerns.  \nMr. Herling also provided additional detail about the necessary study process, which \nillustrates that it sufficiently assesses the reliability of behind-the-meter co-located loads, using the \nsame models and analytic tools as RTEP studies.30  Some commenters, however, raised questions \nregarding the transparency of the necessary study process for interconnecting new large loads.31  \nWhile these concerns are reasonable, there is a straightforward solution.  PJM posts other \ninterconnection study results on a publicly available website.32  PJM could post necessary study \nresults there as well, subject to appropriate confidentiality protections for Critical Energy/Electric \nInfrastructure Information and commercially sensitive information, like the identity of the co-\n \n26 \nExelon data center pipeline doubles to 36 GW since year-end, Utility Dive (May 2, 2025), \nhttps://www.utilitydive.com/news/exelon-data-center-pipeline-pjm-maryland-\nearnings/746971/?utm_source=Sailthru&utm_medium=email&utm_campaign=Issue:%202025-05-\n02%20Utility%20Dive%20Newsletter%20%5Bissue:72830%5D&utm_term=Utility%20Dive.  \n27 \nSee id. \n28 \nId. \n29 \nSee Vistra Initial Comments at 15, 37. \n30 \nHerling Aff. at PP 10-11, 18-19. \n31 \nSee Comments of the Organization of PJM States, Inc., Docket No. EL25-49, at 3 (filed April 23, 2025) (“OPSI \nhas emphasized that PJM’s current process of using interconnection modifications to accommodate behind the meter \nco-located load arrangements lacks transparency and public oversight noting these modifications are privately \nnegotiated and under non-disclosure agreements.”); Comments of Public Interest Organizations, Docket No. EL25-\n49, at 11 (filed April 23, 2025) (“Moreover, the Necessary Study Process occurs entirely behind closed doors.”). \n32  See PJM, Cycle Service Request Status, https://www.pjm.com/planning/m/cycle-service-request-status."},{"page":10,"startToken":2837,"endToken":3200,"text":"-10- \nlocated load customer.  These concerns do not require an overhaul of the necessary study process, \nnor do they justify discrimination against the addition of behind-the-meter co-located load.  Rather, \nthey can be quickly adopted through surgical tariff revisions similar to those Vistra identified in \nits initial comments. \nB. Generation Asset Owners Should Not Be Prohibited from Maximizing the Use of \nTheir Assets \nNOVEC argued that nuclear power plants should not be permitted to serve new large loads \nbecause they were “largely constructed by or for vertically integrated utilities who funded the \nprojects from cost-of-service rates collected by captive retail customers.”33  NOVEC states that it \n“agrees in principle that owners of generation assets should be able to seek to maximize the \nbeneficial ownership of those assets,” but asserts that the Commission should reject the co-location \nof large loads at these generating facilities “because the Federal Power Act is a consumer-\nprotection statute.”34  \nVistra agrees with the principle that owners of generation assets should be able to seek to \nmaximize the beneficial ownership of those assets.  PJM may not prohibit sellers from seeking \nbeneficial bilateral arrangements in an effort to commandeer the sellers’ resources for the PJM \ncapacity market.35  Attempts to do so may even rise to a regulatory taking.36  Moreover, NOVEC’s \n \n33 \nNOVEC Comments at 15. \n34 \nId. at 16. \n35 \nSee PJM Interconnection, L.L.C., 178 FERC ¶ 61,121, at P 97 (2022) (“If a seller deems PJM’s capacity market \nrules undesirable, it can elect to pursue selling its capacity through other avenues, including via bilateral contracts \nwithin PJM, external sales outside of PJM, and other arrangements.”). \n36 \nSee ISO New England, Inc., 135 FERC ¶ 61,029, at P 255 (2011) (rejecting regulatory takings arguments in large \npart because “resources are not compelled to participate in the [ISO-NE capacity market.]”); see also Palazzolo v. \nRhode Island, 533 U.S. 606, 617–18 (2001) (listing factors relevant to determining whether there is a taking, including \n“the regulation’s economic effect on the [property owner], the extent to which the regulation interferes with reasonable \ninvestment-backed expectations, and the character of the government action.”); Hodel v. Irving,  481 U.S. 704, 716"},{"page":11,"startToken":3200,"endToken":3545,"text":"-11- \nargument rests on a fundamental misunderstanding of the impacts of co-location on other \nconsumers.  As Dr. Roy Shanker previously explained, when compared to an appropriate \ncomparison case, Option 4 and 5 configurations provide significant benefits to other market \nparticipants, both in terms of planning reliability and energy and capacity market prices.37  \nSpecifically, Dr. Shanker explained that in an Option 4 case, Network Integration Transmission \nService (“NITS”) costs for other ratepayers remain the same where the parties to the co-location \narrangement pay for all necessary upgrades; to contrast, in an Option 1 configuration, NITS costs \nfor other ratepayers could increase because the costs of transmission facilities would be socialized \nto the entire rate base.38  Dr. Shanker explained that LMPs would be the same in both an Option 4 \nand Option 1 case.39  Dr. Shanker also explained that while capacity prices increase in both Option \n4 and Option 1 cases, capacity prices increase more in the Option 1 case than the Option 4 case.40  \nNOVEC has provided no analytic basis for its conclusions that co-location is unfair to existing \nratepayers.  NOVEC’s vague and analytically flawed assertions about consumer protection do not \njustify prohibiting owners of an asset from seeking the most beneficial use of those assets. \nAdditionally, as Constellation explained, the premise underlying NOVEC’s argument \nignores that fact that these “generating resources were sold by most utilities to merchant owners \nover 20 years ago,” at which point merchant owners assumed all risks associated with the \n \n(1987) (federal regulation constituted a taking where it abrogated essential property rights, even though the property \nowners retained other rights, because “the right to pass on property . . . has been part of the Anglo-American legal \nsystem since feudal times.”); Yancey v. United States, 915 F.2d 1534, 1541 (Fed. Cir. 1990) (noting that regulatory \ntaking precedent does not create “an automatic numerical barrier preventing compensation, as a matter of law, in cases \ninvolving a smaller percentage diminution in value.”). \n37 \nDr. Shanker Aff. at PP 52-70. \n38 \nId. P 58. \n39 \nId. P 61. \n40 \nId. P 62."},{"page":12,"startToken":3545,"endToken":3832,"text":"-12- \ngenerating facility.41  There are many merchant generators that were once built by a vertically \nintegrated utility.  The merchant owners of these plants have always been able to choose how to \noperate their assets, whether that involves capacity market participation or not.  Nuclear plants are \nno different.  Moreover, even under previous the rate-base model, “consumers paid for service, \nnot for assets.”42  There is no reason that rates paid to a vertically integrated utility over 20 years \nago should prevent a private merchant generator from seeking beneficial commercial arrangements \nfor facilities that it now owns.  Nor would doing so even benefit ratepayers, as explained above.   \nC. Reforms to Load Forecasting Are Warranted, But Should Occur Through a \nStandardized Load Interconnection Process \nACEG proposed improvements to PJM’s load forecasting process.  Specifically, ACEG \nproposed to require load-serving entities and electric distribution companies that request load \nadjustments demonstrate that any new large loads interconnections are backed by stringent \nfinancial commitments.  ACEG asserts that the additional financial commitments would not \nimpose a new FERC-jurisdictional rate.  Rather, ACEG’s proposal contemplates that these reforms \noccurring primarily through retail tariffs, with “[m]inimal changes to BPM Manual 19.”43   \nVistra agrees that requiring such financial commitments would help improve the accuracy \nof PJM’s load forecasting by disincentivizing load customers from submitting multiple duplicative \ninterconnection requests.  However, while Vistra agrees with the overall proposal, Vistra submits \nthat these reforms would constitute a FERC-jurisdictional rate—not a retail rate—and, under the \nCommission’s rule of reason, should be placed in the PJM tariff rather than a business practice \n \n41 \nConstellation Comments at 107. \n42 \nId. at 108. \n43 \nComments of Americans for a Clean Energy Grid, Docket No. EL25-49, at 8 (filed April 23, 2025)."},{"page":13,"startToken":3832,"endToken":4161,"text":"-13- \nmanual.44  As Vistra explained in its initial comments, load interconnection is within the \nCommission’s jurisdiction over the interstate transmission system.45  Load forecasting and the \nrequirement to provide additional financial security in the transmission-level load interconnection \nprocess similarly fall under the Commission’s transmission jurisdiction46 and is a matter “readily \nsusceptible of specification” that significantly affects the rates for service.47  Vistra encourages the \nCommission to explore this issue in a separate proceeding focused on standardized transmission-\nlevel load interconnection. \nIII. \nConclusion \nResponses to PJM’s Answer to the Show Cause Order provide a strong record for the \nCommission to act quickly to implement a replacement rate that ensures PJM accommodates \nbehind-the-meter co-located load in a just and reasonable and not unduly discriminatory manner.  \nThere is no valid basis to discriminate against behind-the-meter co-located load given that the \nreliability issues of new large loads apply regardless of the specific configuration in which they \nare added to the system.  Based on Dr. Shanker’s analysis of behind-the-meter co-located loads \nagainst a proper comparison case,48 and Mr. Herling’s conclusions that the relevant reliability \nconcerns are equally or even more applicable to non-co-located large loads,49 it is clear that co-\n \n44 \nSee Energy Storage Ass’n v. PJM Interconnection, L.L.C., 162 FERC ¶ 61,296, at P 103 (2018) (“[P]rovisions \nthat ‘significantly affect rates, terms, and conditions’ of service, are readily susceptible of specification, and are not \ngenerally understood in a contractual agreement must be included in a tariff, while items better classified as \nimplementation details may be included only in the business practice manual.”).  \n45 \nSee Vistra Initial Comments at 38. \n46  Vistra asserts that the Commission has a second basis for exercising jurisdiction over load forecasting because, \nto the extent such forecasts are used in PJM’s markets, load forecasting is a practice directly affecting rates for the \nsale of electric energy. \n47 \nSee supra note 44. \n48 \nShanker Aff. at PP 52-70. \n49 \nHerling Aff. at P 21."},{"page":14,"startToken":4161,"endToken":4363,"text":"-14- \nlocation is part of the solution for reliably serving new loads without adversely impacting current \ncustomers.  Furthermore, concerns about the transparency of the necessary study process can be \naddressed through narrow reforms to ensure that the results of such studies are posted in a manner \nconsistent with other interconnection studies.  None of these issues prevent the Commission from \nexpeditiously implementing a replacement rate to remedy undue discrimination and ensure PJM \nfacilitates Options 4 and 5 configurations.  The record also indicates that the Commission should \n(a) direct PJM to initiate a stakeholder process to determine what tariff revisions would be needed \nto accommodate Options 6-8, and (b) open a proceeding to explore standardized transmission-\nlevel load interconnection procedures, which could include reforms to improve load forecasting \nthrough financial commitments.   \n \n \n \nRespectfully submitted, \n  \n \n/s/ J. Arnold Quinn \nJ. Arnold Quinn \nSVP of Regulatory Policy  \n \nAndrew Weinstein \nVice President, FERC Market Policy \n \nVistra Corp. \n325 7th Street NW \nSuite 520 \nWashington, DC 20004 \narnie.quinn@vistracorp.com  \nandrew.weinstein@vistracorp.com \n \nNicholas M. Gladd \nSarah Greenberg \nWilson Sonsini Goodrich & Rosati \n1700 K Street NW \nFifth Floor \nWashington, DC 20006 \n(617) 598-7871 \nngladd@wsgr.com  \nsgreenberg@wsgr.com  \n \nCounsel for Vistra Corp. \n \nDated:  May 8, 2025"},{"page":15,"startToken":4363,"endToken":4427,"text":"CERTIFICATE OF SERVICE \n \nI hereby certify that I have this day served the foregoing document upon each person \ndesignated on the official service lists compiled by the Secretary of the Commission in these \nproceedings. \n \nDated: May 8, 2025 \nWashington, D.C. \n \n \n/s/ Sarah Greenberg \nSarah Greenberg \nWilson Sonsini Goodrich & Rosati \n1700 K Street NW \nFifth Floor \nWashington, DC 20006 \n(202) 431-5231 \nsgreenberg@wsgr.com"},{"page":16,"startToken":4427,"endToken":4434,"text":"Attachment A \n \nAffidavit of Steven R. Herling"},{"page":17,"startToken":4434,"endToken":4666,"text":"1 \n \n \nUNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \nPJM Interconnection, L.L.C., et al. \n \n \nLarge Loads Co-Located at Generating Facilities \n \n \nConstellation Energy Generation, LLC. \n \nv. \n \nPJM Interconnection, L.L.C. \n)\n)\n)\n)\n)\n)\n)\n)\n)\n)\n)\nDocket No. EL25-49-000 \n \n \nDocket No. AD24-11-000 \n \n \nDocket No. EL25-20-000 \n(Consolidated) \n \nAFFIDAVIT OF STEVEN R. HERLING \nI. \nQUALIFICATIONS AND PURPOSE OF AFFIDAVIT \n \n1. \nMy name is Steven R. Herling.  I am currently President of Herling Power Grid Consulting, \nInc. (“HPGC”), which provides consulting services related to planning, operational, and regulatory \nissues facing the electric power industry.  My business address is 513 William Salesbury Drive, \nDowningtown, PA 19335.  Through HPGC, I have served as a subcontractor to other consulting \nfirms, such as The Brattle Group and Charles River Associates.  I have advised clients on generator \nand merchant transmission interconnection issues as well as a range of PJM Interconnection, L.L.C. \n(“PJM”) Regional Transmission Expansion Plan (“RTEP”) process issues. \n2. \nIn July 2020, I retired from PJM, where I had been employed since May 1990.  At PJM, I held \na number of positions in the Operations and Planning Divisions and was promoted to Vice President \nof Planning in May 2004.  While at PJM, I contributed to or led initiatives that resulted in a wide \nrange of milestone achievements in PJM’s evolution and growth as a regional transmission \norganization (“RTO”), including the creation of the RTEP process, the development of procedures"},{"page":18,"startToken":4666,"endToken":4954,"text":"2 \n \nand standard terms and conditions for generation and merchant transmission interconnections, the \ndevelopment of the competitive transmission process, and the reliability and resource adequacy \naspects of successive integrations of additional control areas that more than doubled the size of the \nPJM market area.  In addition to my work for PJM, I contributed to a wide range of activities for the \nNorth American Electric Reliability Corporation (“NERC”) and served on various regional industry \nworking groups and committees addressing reliability and planning matters. \n3. \nPrior to joining PJM, I worked for the General Public Utilities Service Corporation (“GPU”) \nfor three years in systems operations, where I was responsible for dispatcher training and \ncertification, operations and planning activities, and energy management system and operational \nsupport tools.  Prior to GPU, I worked for the American Electric Power Service Corporation (“AEP”) \nfor eight years in bulk transmission planning.  In that position, I performed a range of power system \nanalyses related to the AEP 765 kV transmission system, generator and circuit breaker dynamic \nmodeling, and the mechanical behavior of turbine-generator shaft systems. \n4. \nI hold a Bachelor of Science in Electric Power Engineering and a Master of Engineering in \nElectric Power Engineering, both from Rensselaer Polytechnic Institute.  Please refer to my resume \nattached as Exhibit B. \n5. \nI have testified on a number of occasions in proceedings before the Federal Energy \nRegulatory Commission (“FERC”), as well as various state commissions, and legislative task forces, \non matters relating to system planning and reliability issues.  I have also testified in transmission line \nCertificate of Public Convenience and Necessity (“CPCN”) proceedings in Pennsylvania, Maryland, \nWest Virginia, Virginia, and New Jersey, and I have testified in a transfer of ownership case for a \npublic utility in Kentucky."},{"page":19,"startToken":4954,"endToken":5237,"text":"3 \n \n6. \nI have been asked by Vistra Corp. (“Vistra”) to provide an affidavit that discusses the \nconcerns raised by PJM Interconnection, L.L.C. (“PJM”) and the North American Electric Reliability \nOrganization (“NERC”) with respect to the reliability impacts of the interconnection of large co-\nlocated loads to the grid and how those concerns can reasonably be managed.  This affidavit and the \nopinions expressed herein are based on my experience in the field of electric power system planning, \noperation, and regulation and my knowledge of the electric power industry.  My opinions and \nanalyses are subject to change if additional information becomes available. \nII. \nDESCRIPTION OF CO-LOCATION PROJECT OPTIONS \n \n7. \nThere are a number of potential options for the interconnection of co-location projects to the \ngrid, involving different physical configurations and different means by which the co-located load \nwill interact with the grid.  In its March 24, 2025 Answer in the above-captioned docket, PJM \npresents eight such options.  PJM Option 1 is not, in fact, a co-location configuration, but \ncontemplates load connected to the grid at a separate point of interconnection from any generator. \n8. \nThe remaining PJM options all involve load co-located with generation at the same point of \ninterconnection.  Two of the options include relaying that will prevent delivery of energy from the \ngrid following the loss of the co-located generating resource.  For example, Option 4 relies on a direct \nconnection to co-located generation facility for the delivery of energy without reliance on grid \ntransmission facilities.  Some of the PJM options also contemplate the ability of the co-located load to \ntake interruptible service or participate as a Demand Response resource, thereby serving as a tool for \noperators to manage operational emergencies."},{"page":20,"startToken":5237,"endToken":5530,"text":"4 \n \n9. \nThe design elements of these configurations and the associated operational/market behaviors \nare all well understood and able to be modeled in planning and operations analyses.  \nIII. \nRELIABILITY ISSUES RAISED BY PJM AND NERC \n10. \nIn discussing their proposed options for co-location, PJM describes the various studies that \nmay be performed to ensure compliance with applicable reliability criteria.1  As relevant here, PJM \nexplained that it performs a Necessary Study when a generator is involved and the co-location project \ninvolves a modification to the generator’s interconnection.  The Necessary Study is also reviewed by \nthe applicable transmission owner.  \n11. \nPJM goes on to describe the analyses that comprise the Necessary Study as including \ngeneration deliverability, N-1 and N-1-1 thermal and voltage studies, special protection systems \nreview, baseline stability, and, if applicable, a nuclear plant interface requirements voltage analysis.2   \n12. \nPJM also explains the other studies used to integrate new large loads in other configurations \ninclude 1) a “Transmission Owner retail load integration study,” performed by the local transmission \nowner to identify local upgrades needed to reliably accommodate the load based on the planning \ncriteria of that local transmission owner, 2) a “PJM Do No Harm study,” to evaluate whether \nupgrades identified by the local transmission owner will adversely impact the reliability of the \nTransmission System, and 3) Regional Transmission Expansion Planning (RTEP) studies when an \naggregation of large load additions could possibly trigger regional transmission needs.3 \n13. \nIn their response to FERC question D. iii., PJM states “In response to this question’s specific \nprompt about dynamic response models, today, PJM conducts dynamic studies for co-located load \nprojects. All applicable North American Reliability Corporation (“NERC”), PJM, and Transmission \n \n1 PJM Answer at 7. \n2 Id. at 49. \n3 Id. at 6-8."},{"page":21,"startToken":5530,"endToken":5831,"text":"5 \n \nOwner-specific contingencies and criteria are evaluated. For such dynamic studies, co-located loads \nare modeled in detail within both power flow and dynamic models.”4  \n14. \nPJM raises one concern with respect to co-location projects interconnected through its Option \n4 or Option 5.  PJM Options 4 and 5 include relaying that will prevent delivery of energy from the \ngrid following the loss of the co-located generating resource.  PJM raises the concern that “it is \npossible to develop a special protection scheme that could disconnect the load if the local generator \ntrips. This scheme could be developed with sufficient redundancy to help better ensure activation. \nHowever, it is always possible that the protection system could misoperate, be disabled, or degrade.”5  \n15. \nNERC raises reliability concerns related to the voltage sensitivity of co-location loads and the \npotential for disconnection from the grid and transfer to backup generation.6  As an example, NERC \ncites the loss of approximately 1,500 MW of load following a 230 kV transmission line fault when \nthe line locked out after three auto-reclose attempts.7  The loss occurred when voltage-sensitive data \ncenter load at 60 different load points across 25 different substations was automatically disconnected \nfrom the grid.8  NERC refers to a Commission comment in its Show Cause Order, suggesting that \nsystem operators may lack sufficient information and transient stability models to perform reliability \nanalysis on co-located large loads.9  \n16. \nBased on these concerns, NERC recommends “that the Commission and industry continue \nexamining specific reliability implications of co-located large loads. NERC also recommends that the \nCommission and industry consider requirements for data or information sharing, to support system \n \n4 Id. at 53. \n5 Id. at 44. \n6 NERC Comments at 3-10. \n7 Id. at 8. \n8 Id., Attach. A, at 4. \n9 NERC Comments at 7."},{"page":22,"startToken":5831,"endToken":6133,"text":"6 \n \noperators in performing reliability analyses as well as coordination, load balancing, and accurate \nmodeling for co-located large loads.”10  \nIV. \nOBSERVATIONS AND CONCLUSIONS \n17. \nPJM and the PJM transmission owners currently perform a wide range of analyses to establish \ncompliance of the grid with all NERC, PJM, and transmission owner planning criteria.  These studies \nspan the entire range of power flow, short circuit, and dynamics analyses and have been performed, \ncollaboratively, for decades, since the inception of PJM as an Independent System Operator.   \n18. \nThrough the Necessary Study process described above, PJM has the ability to evaluate all \naspects of a co-location project to ensure that it is designed such that the grid remains reliable, \nconsistent with all applicable criteria.  The Necessary Study relies on the same transmission system, \ngeneration, and load models that PJM uses throughout all aspects of the RTEP process.  It utilizes all \nof the same analytical tools and evaluates all of the same contingency sets to test compliance against \nall of the same reliability criteria. \n19. \nThe modeling elements required to perform power flow, short circuit, and dynamics analyses \nfor the various co-location options, proposed by PJM, are all knowable and any operational actions \nincluded in PJM’s proposed options are readily modeled.  PJM and the PJM transmission owners \nhave the ability to collaborate to perform all of the analyses required to ensure the continued \nreliability of the PJM grid.   \n20. \nWith respect to PJM’s concerns about potential failure of a special protective system, it is \nworth noting that PJM plans, in its RTEP analyses, for N-1 conditions followed by a single protection \nsystem failure, such as a stuck breaker.  In this instance, a stuck breaker becomes a second \ncontingency.  Based on my experience with the RTEP, the solution to stuck breaker criteria violations \n \n10 Id. at 3."},{"page":23,"startToken":6133,"endToken":6463,"text":"7 \n \nis to add a redundant series breaker, making the failure of both breakers following an N-1 event a \nthird contingency.  PJM does not plan for or require upgrades for such third contingencies, nor would \nit be reasonable to do so.  Assuming that the protection system associated with an Option 4 or 5 co-\nlocation project is fully redundant, it is unreasonable to treat the failure of both primary and \nsecondary relay system facilities following the loss of a generator as anything other than a third \ncontingency. \n21. \nIt is also important to note that the voltage-sensitivity issue underlying the 1,500 MW load \nloss event cited by NERC is not a co-location issue.  Nothing in the NERC Comments or the attached \nmaterials suggests that any of the data centers involved in the event were co-located with generating \nresources.  The voltage sensitivity issue at the core of the discussion is equally, or perhaps even more \napplicable to front-of-meter interconnections of large data centers, such as contemplated in PJM’s \nOption 1.  Co-located generators are, themselves, a voltage source with automatic voltage regulators, \nreducing the likelihood that grid disturbances will exceed the threshold associated with voltage-\nsensitive data center loads.  The loss occurred because the loads transferred from the grid to their own \nuninterruptible power supply (“UPS”) systems in order to protect data center cooling equipment, not \nbecause of any interaction with co-located generation.11  \n22. \nNERC’s recommendation to continue studying these issues and engage in information sharing \nis sensible.  Coordination of study efforts between PJM and the PJM transmission owners has always \nbeen a foundational element of the PJM planning process and must continue for the grid to remain \nreliable and for customer needs to be met in a timely, fair and non-discriminatory manner.  Consistent \nwith NERC’s stated concerns, PJM should have access to the data and information required to \nsupport operational actions and the performance of reliability analyses.  PJM as the planner and \n \n11 NERC Comments, Attach. B, at 4."},{"page":24,"startToken":6463,"endToken":6497,"text":"8 \n \noperator of the grid requires detailed data for large voltage-sensitive loads, whether they are co-\nlocated with generation sources or interconnected to the grid separate from any generator. \n23. \nThis concludes my affidavit."},{"page":25,"startToken":6497,"endToken":6529,"text":"9 \n \nVERIFICATION \n \n \nI declare under penalty of perjury that the foregoing Affidavit is true and correct to the best \nof my knowledge, information, and belief. \n \nExecuted May 8, 2025 \n \n \n \n \n \n \n \n \n \n \n \n \n \n \n \n \n \n________________________ \n \n \n \n \n \n \n \n \nSteve Herling \nSettin"},{"page":26,"startToken":6529,"endToken":6536,"text":"Attachment B \n \n \nResume of Steven R. Herling"},{"page":27,"startToken":6536,"endToken":6788,"text":"Page 1\n \nSteven R. Herling \n \nPROFESSIONAL EXPERIENCE \n \nHerling Power Grid Consulting, Inc. (2020 – Present) \nPresident \nProvide expertise to support strategic decision making related to the development of planning \nprocesses and the integration with electric power grid market structures. \nProvide expertise to support strategic decision making related to the integration of renewable \ntechnologies onto the electric power grid. \nProvide expert witness services in transmission line siting proceedings.  \n \nYoh Staffing Services (2020 – 2021) \nExecutive Consultant (2020 – 2021) \nProvide expert witness services in transmission line siting proceedings.  \n \nPJM Interconnection, LLC (1990 – 2020) \n \nExecutive Consultant, Planning (2019 – 2020) \nProvide expert witness services in support of the Transource 500/230 kV IEC Project. \nProvide leadership to the development of planning processes related to aging infrastructure and grid \nresilience. \nProvide leadership to the development of planning processes related to the integration of off-shore \nwind into the grid. \nSupport the transition of responsibility to the new Vice President, Planning. \nVice President, Planning (2004 – 2019) \nThe Vice President, Planning reports directly to the CEO. \nResponsible for the oversight of System Planning division of PJM which includes Transmission Planning, \nInterregional Planning, Interconnection Analysis, Interconnection Projects, Infrastructure Coordination \nand Resources Adequacy Planning.  \nPosition Summary: \n \nDevelop long range strategies to achieve PJM’s Planning business objectives. \n \nProvide overarching methodology for the monitoring and analysis of Planning studies as well as the \nintroduction of improved and emerging technologies in the Planning space.  \n \nSupport the leadership of the Planning organization in large and complex engineering assignments to \nsupport present and future needs of the PJM system."},{"page":28,"startToken":6788,"endToken":7227,"text":"Page 2\n \nSupport the activities of PJM and industry committee or task forces involved with issues related to \nplanning and engineering. \n \nPrepare board reports, presentations as well as expert testimony regarding Planning and \nInterconnection recommendations. \n \nIn conjunction with subject matter experts, coordinate delivery of all communication regarding the \nregional transmission expansion and enhancement plans. \n \nEnsure the Planning division and staff can support the requests of PJM as well as external entities \nregarding Interconnection queue activities and feasibility studies. \n \nEnsure relationships with the PJM community as well as other regulatory entities are productive and in \nalignment with the PJM strategic plan. \n \nVarious Staff and Management Positions at PJM (1990 – 2004) \n \nGeneral Public Utilities Service Corporation (1987 – 1990) – System Operations \n \nAmerican Electric Power Service Corporation (1979 – 1987) – Bulk Transmission Planning \n \nExpert Witness Testimony: \n \nKentucky proceeding related to the transfer of ownership and control of Kentucky Power Company. \n \nPennsylvania and Maryland CPCN proceedings related to the Transource 500/230 kV IEC Project. \n \nPennsylvania and New Jersey CPCN proceedings related to Susquehanna – Roseland 500 kV \ntransmission line. \n \nPennsylvania, West Virginia, and Virginia CPCN proceedings related to TRAIL and Meadowbrook – \nLoudoun 500 kV transmission lines. \n \nWest Virginia, Virginia, and Maryland CPCN proceedings related to PATH 765 kV transmission line. \n \nMaryland CPCN proceeding related to MAPP HVDC and 500 kV transmission lines. \n \nVirginia CPCN proceeding related to Surry – Skiffes Creek 500 kV transmission line. \n \nNumerous FERC hearings, settlement proceedings, and technical conferences, most recently including: \no Panelist at FERC’s Competitive Transmission Development Technical Conference (Docket No. AD16-\n18) regarding Regional Transmission Planning and Other Transmission Development Issues relative \nto Order No. 1000 implementation and compliance.  June 2016. \no Panelist at FERC’s PJM Solution-Based DFAX Technical Conference related to the assignment of cost \nallocation using PJM’s solution-based distribution factor (DFAX) cost allocation method. January \n2016 \no Panelist at FERC’s Technical Conference related to the NIPSCO Complaint (Docket No. EL13-88) on \ntwo panels:  (i) Transmission Planning Cycles:  Whether the Commission should require the PJM-\nMISO cross-border transmission planning process to run concurrently with the RTOs regional \nplanning cycles as opposed to after the regional transmission planning cycles; and (ii) Lower Voltage \nTransmission Projects: Whether the Commission should require the RTOs to have a process for joint \nplanning and cost allocation of lower voltage and lower cost cross-border upgrades. June 2015 \no IMO Potomac-Appalachian Transmission Highline LLC and PJM Interconnection, L.L.C. (Docket No. \nER09-1256-002 and ER12-2708-003).  Offered expert testimony relative to the PATH Abandonment \nCosts matter.  April 2015 \no Duquesne Light Company (Docket No. ER13-90-002).  Provided Declaration in support of PJM \nTransmission Owners’ compliance filing with the March 22, 2013 Order to add more detail regarding"},{"page":29,"startToken":7227,"endToken":7492,"text":"Page 3\nhow the solution-based DFAX values will be used to calculate assignments of cost responsibility.  July \n2013 \no Public Service Electric and Gas Company (Docket No. ER13-90).  Provided expert testimony on \nbehalf of the PJM Transmission Owners revisions to the PJM Tariff to modify the cost allocation \nmethodology describing PJM’s current use of distribution factors (DFAX) in allocating the costs of \ncertain transmission upgrades and expansions and discuss how PJM would implement the \nsolution-based DFAX proposed by the PJM Transmission Owners. October 2012 \no Panelist at FERC’s Review of Small Generator Interconnection Agreements and Procedures \nTechnical Conference (Docket No. AD12-17) on a panel entitled:  Review of Required Upgrades, \nwhich explored improving the small generator interconnection process for identifying upgrades to \nsupport interconnection including whether interconnection customers should have the \nopportunity to engage in an expedited independent third-party expert review of upgrade \nrequirements that are perceived as excessive by the interconnection customer.  July 2012 \n \nMost Recent Publications: \nBefore the United States District Court for the Middle District of Pennsylvania, Case No. 1:21-cv-01101-\nJPW, Expert Report of Steven R. Herling in Transource Pennsylvania, LLC, vs. Pennsylvania Public Utility \nCommission, January 20, 2023. \n“New Jersey State Agreement Approach for Offshore Wind Transmission: Evaluation Report (with H. \nPfeifenberger, J.M. Hagerty, J. DeLosa, M. Kaplin, D. Sullivan, C. Peacock, E. Bennett, and E. Snyder), \nprepared for the New Jersey Board of Public Utilities, October 6, 2022 \n“The Sponsorship Model” – IEEE Power & Energy Magazine – July/August 2016 \n \nEducation: \nMEEPE, Rensselaer Polytechnic Institute, (1979) \nBSEPE, Rensselaer Polytechnic Institute, (1978) \nSenior Member of the Institute of Electrical and Electronics Engineers"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":3,"endAt":111,"startToken":0,"endToken":362},{"p":3,"at":111,"title":"I. MOTION FOR LEAVE TO ANSWER","method":"printed heading","endPage":3,"endAt":605,"startToken":362,"endToken":434},{"p":3,"at":605,"title":"II. ANSWER","method":"printed heading","endPage":6,"endAt":1436,"startToken":434,"endToken":1821},{"p":6,"at":1436,"title":"A. The Reliability Concerns Raised in Comments Apply to All New Large Loads,","method":"printed heading","endPage":10,"endAt":332,"startToken":1821,"endToken":2884},{"p":10,"at":332,"title":"B. Generation Asset Owners Should Not Be Prohibited from Maximizing the Use of","method":"printed heading","endPage":12,"endAt":702,"startToken":2884,"endToken":3651},{"p":12,"at":702,"title":"C. Reforms to Load Forecasting Are Warranted, But Should Occur Through a","method":"printed heading","endPage":13,"endAt":626,"startToken":3651,"endToken":3913},{"p":13,"at":626,"title":"III. Conclusion","method":"printed heading","endPage":15,"endAt":0,"startToken":3913,"endToken":4363},{"p":15,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":16,"endAt":0,"startToken":4363,"endToken":4427},{"p":16,"at":0,"title":"Attachment A","method":"printed heading","endPage":17,"endAt":407,"startToken":4427,"endToken":4483},{"p":17,"at":407,"title":"I. QUALIFICATIONS AND PURPOSE OF AFFIDAVIT","method":"printed heading","endPage":19,"endAt":669,"startToken":4483,"endToken":5057},{"p":19,"at":669,"title":"II. DESCRIPTION OF CO-LOCATION PROJECT OPTIONS","method":"printed heading","endPage":20,"endAt":188,"startToken":5057,"endToken":5265},{"p":20,"at":188,"title":"III. RELIABILITY ISSUES RAISED BY PJM AND NERC","method":"printed heading","endPage":22,"endAt":147,"startToken":5265,"endToken":5851},{"p":22,"at":147,"title":"IV. OBSERVATIONS AND CONCLUSIONS","method":"printed heading","endPage":26,"endAt":0,"startToken":5851,"endToken":6529},{"p":26,"at":0,"title":"Attachment B","method":"printed heading","endPage":29,"endAt":1917,"startToken":6529,"endToken":7492}]}