{"document":{"slug":"rec-20250509-5126","title":"Errata to the 5/8/2025 Motion for Leave and Answer of Constellation Energy Generation, LLC","issued":"2025-05-09","accession":"20250509-5126","docket":"EL25-49-000","group":"PJM co-location compliance","filer":"Constellation Energy Generation, LLC","kind":"answer","file":"sources/filings/text/20250509-5126_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20250509-5126","tier":"record","sha256":"d18436d56d4cd9c4a71d2d333d111535b415ab5f2fac76b7422c53f90a4433bc","pages":19,"tokens":7288,"emptyPages":[],"textThemes":["colo","adequacy","flex","study"]},"pages":[{"page":1,"startToken":0,"endToken":174,"text":"Seth Lucia \nAssistant General Counsel \nConstellation Energy Generation, LLC \n250 Massachusetts Avenue, NW \nSuite 760 \nWashington, DC 20001 \nSeth.Lucia@constellation.com \nMay 9, 2025 \nVia eFiling \nHonorable Debbie-Anne A. Reese, Secretary \nFederal Energy Regulatory Commission \n888 First Street, N.E. \nWashington, DC 20426 \nRe:  PJM Interconnection, L.L.C., et al., Docket Nos. EL25-49, AD24-11, and EL25-20 \nErrata to Motion for Leave and Answer \nDear Secretary Reese:  \nOn May 8, 2025, Constellation Energy Generation, LLC (“Constellation”) filed a Motion \nfor Leave and Answer in the above-captioned proceedings (Accession No. 20250508-5131) (“May \n8 Answer”).  It has come to Constellation’s attention that footnote 27 in our May 8 Answer did not \ninclude language Constellation intended for filing.  Attached is a clean version of Constellation’s \ncorrected May 8 Answer reflecting the following correction to footnote 27 shown in redline below:  \n \nOther than the above change to footnote 27, the rest of Constellation’s May 8 Answer \nremains the same.  Please contact the undersigned with any questions.  \nRespectfully submitted, \n   /s/ Seth Lucia  \nSeth Lucia \nConstellation Energy Generation, LLC"},{"page":2,"startToken":174,"endToken":241,"text":"CERTIFICATE OF SERVICE \nI hereby certify that I have on this 9th day of May 2025, caused to be served a copy of this \nfiling upon all parties on the service list in these proceedings in accordance with the requirements \nof Rule 2010 of the Commission’s Rules of Practice and Procedure, 18 C.F.R. § 385.2010 (2024). \n \n/s/ Shawn Whites \n \n \n \n \n \n \n \nShawn Whites \n \n \n \n \n \n \n \nConstellation Energy Generation, LLC"},{"page":3,"startToken":241,"endToken":585,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \nPJM Interconnection, L.L.C., et al. \n \n \nLarge Loads Co-Located at Generating Facilities \n \n \nConstellation Energy Generation, LLC \nv. \nPJM Interconnection, L.L.C. \n) \n \n \n) \n \n \n) \n) \n) \nDocket No. EL25-49-000 \n \n \nDocket No. AD24-11-000 \n \n \nDocket No. EL25-20-000 \n(Consolidated) \n \n \n \n \nMOTION FOR LEAVE AND ANSWER OF \nCONSTELLATION ENERGY GENERATION, LLC \nConstellation Energy Generation, LLC (“Constellation”) moves for leave and submits this \nanswer1 in support of the Commission’s preliminary finding that the PJM Tariff is unjust and \nunreasonable and unduly discriminatory and preferential2 because, as recent filings plainly show, \nno one knows the rules for the co-location of large loads and generation.  That lack of clarity is \nallowing certain transmission owners to erect discriminatory roadblocks to safe and reliable \ninterconnection configurations that would reduce the need for costly transmission upgrades and \npreserve each state’s jurisdiction to decide how to regulate sales to end-use customers.  The need \nfor clarity in the tariff cannot wait any longer.  President Trump has emphasized that the United \nStates’ competitiveness with other nations depends on the development of Artificial Intelligence \n(“AI”) infrastructure and that co-location enables such development “on a very rapid basis.”3  \n \n1 Constellation submits this answer and motion for leave pursuant to Rules 212 and 213 of the Commission’s Rules \nof Practice and Procedure, 18 C.F.R. §§ 385.212 and 385.213, and respectfully submits there is good cause for the \nCommission to accept the motion for leave.  See Alaska Gasline Dev. Corp., 171 FERC ¶ 61,134, at P 7 (2020) \n(accepting answers that “clarify the concerns raised and provide information that has assisted in our decision making”); \nSaltville Gas Storage Co., 164 FERC ¶ 61,212, at P 2 n.6 (2018) (accepting answers that “assist the Commission in \nunderstanding the issues raised[] and will ensure a complete record”). \n2 See PJM Interconnection, L.L.C., et al., 190 FERC ¶ 61,115, at P 74 (2025) (“Show Cause Order”). \n3 The White House, Remarks by President Trump at the World Economic Forum, January 23, 2025, 11-12, \nhttps://www.whitehouse.gov/remarks/2025/01/remarks-by-president-trump-at-the-world-economic-forum/."},{"page":4,"startToken":585,"endToken":1027,"text":"2 \nAccordingly, the Commission should affirm its preliminary finding and fix a replacement rate by \nadopting rules for a variety of co-location configurations as already fully supported in the record. \n \nTHE RECORD CONCLUSIVELY DEMONSTRATES THAT THE PJM TARIFF \nIS UNJUST AND UNREASONABLE \nThis is “a show cause proceeding pursuant to section 206” of the Federal Power Act \n(“FPA”)4 which includes “a two-step procedure that requires … an explicit finding that the existing \nrate is unlawful before setting a new rate.”5  Thus, as a threshold matter, the Commission must \nfirst “determine whether an existing [rule] is ‘unjust, unreasonable, unduly discriminatory or \npreferential….’”6  The Commission initiated this proceeding with a preliminary finding under \nsection 206 of the FPA that \nthe existing PJM Tariff appears to be unjust and unreasonable or unduly \ndiscriminatory or preferential because it does not contain provisions addressing \nwith sufficient clarity or consistency the rates, terms, and conditions of service that \napply to co-location arrangements.  The absence of such provisions may leave \nentities unable to determine what steps they can or must take to effectuate co-\nlocation arrangements of various configurations and how to do so in a manner that \nis just and reasonable.7  \n \nThe approximately fifty filings submitted in response to the Show Cause Order conclusively \ndemonstrate the correctness of the Commission’s preliminary finding. \n \n4 Show Cause Order at P 2; see 16 U.S.C. § 824e. \n5 Emera Me. v. FERC, 854 F.3d 9, 24 (D.C. Cir. 2017); see also MISO Transmission Owners v. FERC, 45 F.4th 248, \n253 (D.C. Cir. 2022) (“At step one, FERC decides if the old rate is unjust and unreasonable. … If so, then FERC \nproceeds to step two and sets a new rate.”) (citing 16 U.S.C. § 824e(a)). \n6 Emera Me., 854 F.3d at 21 (quoting 16 U.S.C. § 824e(a)).  In determining whether the existing rate is unreasonable, \nthe evidence must be “assessed in light of the FPA’s goals of promoting reliable service at reasonable rates and \ndeveloping plentiful energy supplies.”  Constellation Mystic Power, LLC v. FERC, 45 F.4th 1028, 1035 (D.C. Cir. \n2022) (per curiam) (citing Consol. Edison Co. v. FERC, 510 F.3d 333, 342 (D.C. Cir. 2007); NAACP v. FPC, 425 \nU.S. 662, 669–70 (1976)). \n7 Show Cause Order at P 74 (emphasis added); see also id. at P 75 (“In addition, we preliminarily find that this lack \nof applicable Tariff provisions raises the potential for undue discrimination or preferential treatment,” citing \n“allegations in the record that [an Indicated Transmission Owner] has delayed work on … requests to co-locate load \nwith … generation at certain facilities”)."},{"page":5,"startToken":1027,"endToken":1560,"text":"3 \nFirst, numerous parties agreed with the Commission’s preliminary finding that the PJM \nTariff is unjust and unreasonable because it lacks clear co-location provisions, and advocated the \nadoption of replacement rates pursuant to section 206 of the FPA:8     \n• Antora Energy LLC \n• Electric Power Supply Association and the PJM Power Providers, and individually,  \n• Calpine Corporation \n• Cogentrix Energy Power Management, LLC  \n• Constellation Energy Generation, LLC  \n• LS Power Development, LLC \n• Vistra Corp. \n• Enchanted Rock, LLC \n• Independent Market Monitor for PJM9 \n• Mainspring Energy, Inc. \n• Solar Energy Industries Association.10 \n \n8 Motion to Intervene Out of Time and Comments of Antora Energy LLC in Response to the Commission’s Co-\nlocation Order at 1-2 (filed Apr. 23, 2025); Joint Comments and Motion to Stay Proceedings and Request to Establish \nSettlement Judge Procedures of the Electric Power Supply Association, the PJM Power Providers Group, Calpine \nCorporation, Cogentrix Energy Power Management, LLC, Constellation Energy Generation, LLC, and LS Power \nDevelopment, LLC at 1-2 (filed Apr. 22, 2025); Response of Enchanted Rock, LLC at 2 (filed Apr. 23, 2025); \nComments of the Independent Market Monitor for PJM at 2, 13-14 (filed Apr. 23, 2025) (explaining that it “agrees \nthat the current [Tariff] rules are not clear” and because “[t]hese are issues that require a review process and decision \nby the Commission,” the IMM “recommends that the Commission decide the questions based on submissions by the \nparties and a hearing at the Commission’s discretion.”); Comments of Mainspring Energy, Inc. Regarding Co-located \nGeneration and Data Center Integration at 1 (filed Apr. 23, 2025); Comments of the Solar Energy Industries \nAssociation at 6 (filed Apr. 23, 2025); see also Comments of the Electric Power Supply Association and the PJM \nPower Providers (filed Apr. 23, 2025) (separate comments); Answer of Constellation Energy Generation, LLC (filed \nApr. 23, 2025) (“Constellation First Answer”) (individual company comments); Comments of Vistra Corp. at 4 (filed \nApr. 23, 2025) (individual company comments).   \n9 The Independent Market Monitor for PJM “agrees that the current [Tariff] rules are not clear” and because “[t]hese \nare issues that require a review process and decision by the Commission,” the IMM “recommends that the Commission \ndecide the questions based on submissions by the parties and a hearing at the Commission’s discretion.”  Comments \nof the Independent Market Monitor for PJM at 2, 13-14 (emphasis added).  In this FPA section 206 proceeding, this \nis equivalent to asking the Commission to fix a replacement rate.  Under FPA section 206, no replacement rate is \nestablished until the Commission makes the step one finding that the existing rate is unjust and unreasonable, in this \ncase because—as the IMM agrees—the “current rules are not clear.”  Id. at 2. \n10 Two additional parties, Clean Air Task Force and Public Interest Organizations, did not appear to assert that the \nlack of clear co-location rules rendered the Tariff unjust and unreasonable, but argued that numerous other aspects of \nthe current PJM Tariff are unjust and unreasonable under FPA section 206.  See Comments of Clean Air Task Force \nat 5-6  (filed Apr. 23, 2025) (asserting FERC jurisdiction under section 206 “[w]here, as here, the evidence \ndemonstrates that the existing tariff provisions are inadequate, unjust, and unreasonable” “to properly plan for and"},{"page":6,"startToken":1560,"endToken":1994,"text":"4 \nSecond, another large group of parties agreed with the Commission that the PJM Tariff \nlacks clear co-location rules and advocated for further clarity in the Tariff, but did not specify how \nthey thought the Commission should proceed under the FPA:   \n• Bloom Energy Corporation (“urg[ing] the Commission to provide detailed guidance to PJM \n… to implement co-location tariff rules”).11  \n• BrightNight Power Marketing, LLC (“Because PJM’s current open access transmission tariff \nis not sufficiently clear about the rules that apply to co-located load arrangements, BrightNight \nsupports the Commission establishing pro forma rules….).12 \n• Data Center Coalition (urging the Commission to “affirm the legitimacy of co-location,” \n“direct PJM to provide Tariff clarity,” and “reject one-size-fits-all treatment of network \nload”).13 \n• Delaware Public Service Commission (“The DEPSC is inclined to support these types of \nframeworks” [PJM Options 6-8]).14  \n• EDF Renewables, Inc. (“The Commission should act expeditiously to encourage flexible co-\nlocation structures that will enable speedy and reliable interconnection for large loads.”).15 \n• Electricity Consumers Resource Council (“the Commission should focus on facilitating co-\nlocation and other flexible arrangements” and “should reject the overarching premise in the \ncomments of the Indicated PJM Transmission Owners that only Network Service or Point-to-\nPoint Transmission Service arrangements should be permitted, and that no other flexibility \nshould be allowed”).16  \n• ENGIE North America Inc.  (“The Commission should provide clear guidance on co-location \narrangements.”)17 \n• Office of the Federal Energy Advocate of the Public Utilities Commission of Ohio (“The Ohio \nFEA supports further consideration of these options [PJM Options 6-8].”).18  \n \nallocate costs pertaining to … large co-located loads”) (emphasis added); Comments of Public Interest Organizations, \npassim  (filed Apr. 23, 2025) (asserting numerous aspects of the PJM Tariff are unjust and unreasonable as applied to \nco-location). \n11 Comments of Bloom Energy Corporation at 1-2, 13 (filed Apr. 23, 2025). \n12 Comments of BrightNight Power Marketing, LLC at 3 (filed Apr. 23, 2025). \n13 Comments of the Data Center Coalition at 12 (filed Apr. 23, 2025) (initial capitalization omitted). \n14 Comments and Intervention of the Delaware Public Service Commission at 6 (filed Apr. 23, 2025). \n15 Comments of EDF Renewables, Inc. at 6 (filed Apr. 23, 2025) (initial capitalization omitted). \n16 Motion to Intervene and Comments of the Electricity Consumers Resource Council to PJM Interconnection, \nL.L.C.’s Answer to the Section 206 Show Cause Order at 4, 6 (filed Apr. 23, 2025) (emphasis in the original). \n17 Comments of ENGIE North America Inc. at 5 (filed Apr. 23, 2025). \n18 Comments of the Public Utilities Commission of Ohio’s Office of the Federal Energy Advocate at 4 (filed Apr. 23, \n2025)."},{"page":7,"startToken":1994,"endToken":2548,"text":"5 \n• Pennsylvania Public Utility Commission (“PJM’s Tariff must be revised to require that PJM \nconduct long-term scenario analyses on the potential cumulative reliability and cost impacts of \nbehind-the-generator-meter co-located load arrangements”).19 \n• PJM Industrial Customer Coalition and Industrial Energy Consumers of America \n(“wholeheartedly agree[ing]” with the Commission’s concerns about the lack of “a common \nand consistent understanding” of the co-location rules and “urg[ing] the Commission to \nprovide sufficient guidance to PJM to enable a clear, cost-based structure, and understandable \nstudy process, and the ability to expedite projects that do not require transmission updates”).20 \n• Public Service Electric and Gas Company (“PSE&G proposes a principle-based approach to \naddress the Commission’s issues and concerns and suggests a path forward to obtain timely \nand needed clarity with respect to co-located load rules”).21 \n• Talen Energy Corporation (“Talen respectfully requests that the Commission direct PJM to \nsubmit Tariff modifications to address the five [new] co-location configuration options \nproposed by PJM”).22 \nThird, the American Council on Renewable Energy and Advanced Energy United both \ncalled for a process under section 205 of the FPA to clarify the PJM Tariff.23   \nFinally, several other parties apparently took no position on the PJM Tariff’s lack of clarity \nregarding the treatment of co-location, but still advocated prompt Commission guidance or other \npossible reforms on an expedited timeline.24   \n \n19 Comments of the Pennsylvania Public Utility Commission at 6-7 (filed Apr. 23, 2025). \n20 Joint Comments of PJM Industrial Customer Coalition and Industrial Energy Consumers of America at 14 (filed \nApr. 23, 2025) (emphasis in the original). \n21 Response of Public Service Electric and Gas Company to the Order to Show Cause (filed March 24, 2025) at 2. \n22 Comments of Talen Energy Corporation on Answer of PJM Interconnection L.L.C. to Order Instituting Proceeding \nunder Section 206 of the Federal Power Act and Consolidating with Other Proceedings at 12 (filed Apr. 23, 2025). \n23 Comments of the American Council on Renewable Energy at 1 (filed Apr. 23, 2025); Response of Advanced Energy \nUnited at 3 (filed Apr. 23, 2025).  \n24 Comments of Americans for a Clean Energy Grid at 5 (filed Apr. 23, 2025) (supporting adoption of “commitment-\nbacked load forecasting proposal”); Comments of the Business Council for Sustainable Energy at 2 (filed Apr. 23, \n2025) (“BCSE supports FERC taking action as soon as is practicable to address the issues related to the co-location \nof large loads”); Comments of Invenergy Renewables LLC and Invenergy Thermal LLC at 6 (filed Apr. 23, 2025) \n(during the “interim” while PJM is “completing its interconnection queue transition process … PJM’s Tariff should \nbe amended to include at least co-located loads in the standard generator interconnection procedures”); Comments of \nNatural Resource Defense Council at 9 (filed Apr. 23, 2025) (“urg[ing] the Commission to examine the extent to \nwhich RTO load forecasts apply appropriate rigor to exclude speculative data center projects”); Comments of the \nOrganization of PJM States, Inc. at 3 (filed Apr. 23, 2025) (“OPSI continues to call on the Commission to require that \ntransmission providers conduct transparent, publicly reviewable reliability studies pursuant to a PJM tariff for large \nco-located load arrangements to preserve system reliability.”); Comments of RMI at 3-5 (filed April 29, 2025) (“PJM \nshould rectify the current lack of a ‘tariffed study process for load’” and “require earlier standardized information"},{"page":8,"startToken":2548,"endToken":3231,"text":"6 \nThe preceding lists of parties expressing the lack of clarity in the PJM Tariff comprise an \nextensive record in support of the Commission’s preliminary finding that the Tariff is unjust and \nunreasonable because it lacks clear co-location rules.  But even among the parties professing \nopposition to the Commission’s preliminary section 206 finding, most (including PJM itself) still \neither expressly support clarification of the PJM Tariff or highlight Tariff provisions that could be \nclarified.25  PJM took the lead on suggesting possible clarifications, cataloguing eight co-location \nconfiguration options in its response to the Show Cause Order.26  This greatly facilitated efforts by \n \nsharing between itself, large load customers, and transmission owners”); Letter from Paul Stockton, Former Assistant \nSecretary of Defense for Homeland Defense and America’s Security Affairs, John B. Hashem, Major General, US \nArmy (Ret.), Robert G. F. Lee, Major General, US Army (Ret.), Joseph L. Lengyel, General, USAF (Ret.), Craig R. \nMcKinley, General, USAF (Ret.), Darryll D. M. Wong, Major General, USAF (Ret.), Chuck Wald, General, USAF \n(Ret.), and Benny M. Paulino, Major General, US Army (Ret.) to Mark C. Christie, Chairman, and Judy W. Chang, \nWillie L. Phillips, David Rosner, and Lindsay S. See, Commissioners at 1 (Apr. 22, 2025) (“We urge that the Federal \nEnergy Regulatory Commission act to ensure that data centers can meet their growing power requirements as quickly \nas possible.”) (emphasis added); see also Answer of Allegheny Electric Cooperative, Inc. to Show Cause Order Issued \nin Connection with the Treatment of Co-located Load within PJM Interconnection, L.L.C. (filed March 24, 2025) at \n2 (Allegheny “remains uncommitted as to whether the current PJM Tariff sufficiently addresses Co-Located Load” \nbut “Allegheny is certain that the need for clarity from the Commission is both essential and urgent.”). \n25 Answer of PJM Interconnection, L.L.C. (filed March 24, 2025) at 4, 32 (“What PJM and the industry need now is \nCommission guidance on a path forward based on the record developed in this proceeding” and “clarifications and \nenhancements could well be in order given that this is an evolving area and Tariff provisions did not contemplate the \ntype of arrangements at issue in this docket or their implications”); Answer of the Indicated PJM Transmission Owners \nat 2 (filed Apr. 23, 2025) (“to the extent FERC believes it would provide helpful clarity, the Indicated TOs recommend \nadopting a proposed definition of co-located load” in the Tariff); Comments of Buckeye Power, Inc. at 9 (filed Apr. \n23, 2025) (“Buckeye supports the Commission providing additional clarity or guidance to support” PJM Options 6-\n8); Answer of The Dayton Power and Light Company d/b/a AES Ohio to Order Instituting Proceeding under Section \n206 of the Federal Power Act and Consolidating with Other Proceedings (filed March 24, 2025) at 2 (“AES Ohio is \nopen to working with PJM and stakeholders to explore alternative transmission service arrangements for certain co-\nlocated load configurations that may be appropriate to reflect specific co-located load circumstances and associated \nsystem needs”); Response of American Municipal Power, Inc. at 2-3 (filed Apr. 23, 2025) (“additional clarification \nconcerning the treatment of co-located load may be beneficial”); Comments of the Maryland Office of Joint Consumer \nAdvocates at 7 (filed Apr. 23, 2025) (“the Commission should … clarify that co-located load should be classified as \nnetwork service under the PJM Tariff”).  At least one of the Indicated Transmission Owners also filed separate \ncomments.  See Answer of PPL Electric Utilities Corporation at 2 (filed Apr. 23, 2025) (“there are clearly areas where \nthe PJM Tariff … could benefit from increased clarity and FERC guidance” and “it is appropriate to set these rules of \nthe road directly in the tariffs….  PPL Electric believes that these rules can, and should, accommodate behind-the-\nmeter load where required by state law”). \n26 PJM has also initiated further stakeholder discussions on some of these options, which would be unnecessary if the \nTariff were clear.  See Tim Horger, Senior Dir., Forward Market Operations & Performance Compliance, PJM, Large \nLoad \nAdditions \nWorkshop \n(May \n9, \n2025), \nhttps://www.pjm.com/-/media/DotCom/committees-\ngroups/workshops/llaw/2025/20250509/20250509-item-02---large-load-additions-workshop---presentation.pdf."},{"page":9,"startToken":3231,"endToken":3925,"text":"7 \nparties to develop the record (which they have), so the Commission can fix an appropriate \nreplacement rate, as discussed below.27 \nOf the remaining filing parties who addressed the issue whether the PJM Tariff is just and \nreasonable, only two parties and two individuals are outliers that did not advocate for any Tariff \nchange or clarification.28  And no party pointed to any Tariff prohibition on co-location because \nthere is none.29   \nIn sum, the record in this proceeding unequivocally supports the Commission’s preliminary \nfinding that the PJM Tariff lacks clear co-location rules and is unjust and unreasonable.  Again, \n \n27 The Joint Comments and Motion to Stay Proceedings and Request to Establish Settlement Judge Procedures of the \nElectric Power Supply Association, the PJM Power Providers Group, Calpine Corporation, Cogentrix Energy Power \nManagement, LLC, Constellation Energy Generation, LLC, and LS Power Development, LLC (filed Apr. 22, 2025) \n(“Joint Motion”) included as a foundation that the Commission’s preliminary FPA section 206 showing has been met, \nbut this argument was made before additional overwhelming support was filed in the record that the PJM Tariff needs \nclarification (as established herein).  Four of the same parties opposing an FPA section 206 finding in this case also \nfiled comments in opposition to the 206 arguments in the Joint Motion, but all of them failed to cite to any record \nevidence or selectively cited only to conclusory statements in a few filings in the extensive record in this proceeding \nin support of a finding that the Tariff is just and reasonable.  See Answer of American Municipal Power, Inc. in \nOpposition to Motion for Stay and Settlement Judge Procedures at 4-5 (filed May 7, 2025) (citing only PJM’s and the \nIndicated Transmission Owners’ filings in the record); Answer of the Indicated PJM Transmission Owners to the \nMotion to Stay Proceedings at 3-4 (filed May 7, 2025) (failing to cite any filings in the record); Answer of Northern \nVirginia Electric Cooperative, Inc. and Northeastern Rural Electric Membership Corporation Opposing the Joint \nComments and Motion to Stay Proceedings and Request to Establish Settlement Judge Procedures at 3 (filed May 2, \n2025) (citing only the Indicated Transmission Owners’ Answer); Answer of PJM Interconnection, L.L.C. to Joint \nComments and Motion to Stay Proceedings and Request to Establish Settlement Judge Procedures at 3 & n.3 (filed \nMay 5, 2025) (claiming “the ever-growing record in this proceeding reflects substantial support for a finding that \nPJM’s existing Tariff is just and reasonable in regards to co-location arrangements” and citing its own answer, the \nIndicated Transmission Owners’ answer, AMP’s answer, and—erroneously—Talen Energy’s answer) (Talen has \nrequested the Commission to direct PJM to submit tariff modifications and believes that all eight options proposed by \nPJM, when implemented into the tariff and taken as a whole, will result in PJM’s tariff being just and reasonable). \n28 See Comments of Northeastern REMC on the Order Instituting the Proceeding under Section 206 of the Federal \nPower Act and Consolidating with Other Proceedings (filed Apr. 23, 2025); Comments of Northern Virginia Electric \nCooperative (filed Apr. 23, 2025).  Two individuals also assert that the existing PJM Tariff is just and reasonable but \nalso state that the “current pro forma interconnection agreements do not contain sufficient [reliability] protections and \nshould, at a minimum, be updated accordingly if it is [sic] to be used for connecting co-located large loads.”  See \nReply Comments of Suzanne Glatz and Abraham Silverman at 14-16 (filed Apr. 23, 2025). \n29 For the sake of a full accounting of the record, several entities—most not PJM members—offered comments in the \nrecord without addressing the justness and reasonableness of the PJM Tariff, nor specifically requesting prompt \nCommission guidance.  See Response of the Center for Biological Diversity (filed Apr. 23, 2025); Comments of \nChevron U.S.A. Inc. (filed Apr. 23, 2025); Comment of Consumers’ Research (filed Apr. 23, 2025); Comments of the \nEdison Electric Institute (filed Apr. 23, 2025); Comments of the North American Electric Reliability Corporation \n(filed Apr. 23, 2025); Reply Comments of Southern California Edison Company and Pacific Gas and Electric \nCompany (filed Apr. 23, 2025); Comments of the Union of Concerned Scientists (filed Apr. 23, 2025)."},{"page":10,"startToken":3925,"endToken":4437,"text":"8 \neven the transmission interests clinging to a one-size-fits-all30 firm Network Integrated \nTransmission Service (“NITS”) approach based on gross load billing determinants admit that \n“there are clearly areas where the PJM Tariff … could benefit from increased clarity and FERC \nguidance” and argue that “it is appropriate to set these rules of the road directly in the tariffs.”31  \nOne of the most fundamental elements of just and reasonable rates is that customers must \nknow the rate in advance.32  “Predictability” is a “central purpose of the filed rate doctrine.”33  \nReview of the filings in this case highlights nearly universal acknowledgement that the PJM Tariff \nlacks “predictable” co-location rules.  Accordingly, and consistent with Commission precedent, \nthe Commission must find that the PJM Tariff is unjust and unreasonable because, first and \nforemost, no one knows the rules.34   \nThe Commission also preliminarily found in the Show Cause Order that the “absence of \n[clear co-location] provisions may leave entities unable to determine what steps they can or must \ntake to effectuate co-location arrangements of various configurations” and this “raises the \n \n30 Except—according to Indicated Transmission Owners—existing Behind-the-Meter Generation loads and \ngenerators, which would be grandfathered and allowed to net.  See Answer of the Indicated PJM Transmission Owners \nat 5 (filed Apr. 23, 2025). \n31 Answer of PPL Electric Utilities Corporation at 2 (filed Apr. 23, 2025).  Again, PPL Electric Utilities Corporation \nis an “Indicated Transmission Owner.” \n32 See, e.g., FPA section 205, 18 U.S.C. § 824d(d) (“No change shall be made by any public utility in any such rate, \n... rule, regulation, or contract relating thereto, except after sixty days’ notice to the Commission and to the public.”) \n(emphasis added); see also PJM Power Providers Group v. FERC, 96 F.4th 390 (3d Cir. 2024) (rejecting retroactive \nchange to PJM Base Residual Auction rules because parties were not on notice that Tariff rules could change). \n33 See PJM Power Providers Group, 96 F.4th 390, 401-02 (describing “predictability” as “a central purpose of the \nfiled rate doctrine”). \n34 See Dominion Energy Marketing, Inc., et al., v. ISO New England Inc., 155 FERC ¶ 61,121 at P 17 (2016) (“We \nfind that ISO-NE’s existing Tariff is unclear as to whether new incremental capacity and existing capacity at the same \ngeneration station must submit a composite offer to participate in the [forward capacity auction]” and “[a]s a result of \nthis lack of clarity the Tariff fails to provide adequate notice of what the requirement is and, thus, we find the Tariff \nis unjust and unreasonable.”); see also, e.g., New York Independent Sys. Operator, Inc., 162 FERC ¶ 61,107 at PP 160, \n173 (2018) (finding NYISO’s tariff revisions “unclear and, therefore, unjust and unreasonable” and finding that \ndifferences in definitions were also “unclear and, therefore, unjust and unreasonable”); Tennessee Gas Pipeline Co., \n123 FERC ¶ 61,217 at P 14 (2008) (finding that the pipeline’s revised tariff language “is ambiguous and, accordingly \n[] unjust and unreasonable” and conditioning acceptance of the tariff revisions on a compliance filing to clarify the \nlanguage at issue)."},{"page":11,"startToken":4437,"endToken":4792,"text":"9 \npotential for undue discrimination or preferential treatment.”35  Substantial unrebutted evidence in \nthe record confirms this is the case, including some Indicated Transmission Owners refusing to \n“work on … requests to co-locate load with … generators at certain facilities.”36   \nIn response to the Show Cause Order, Constellation included extensive record evidence \nsupported by sworn expert testimony of the significant injury the lack of clear co-location rules \nand delays in service to data centers are causing to economic and national security, and the host of \nother injuries inflicted by the current de facto NITS-only approach (including billions of dollars of \nunnecessary transmission upgrades, intrusion on state jurisdictional authority and flexibility, and \nviolation of cost-causation and other rate design fundamentals).37  No expert rebuttal to any of this \nevidence was filed by the Indicated Transmission Owners or any other opponent in response to the \nShow Cause Order, and argument in pleadings without an evidentiary basis is insufficient to rebut \nrecord evidence.38  Many parties not only failed to submit any expert analysis to demonstrate why \nthe current PJM Tariff is just and reasonable but also failed to respond to the Commission’s \nbriefing questions contained in the Show Cause Order.   \nBased on the record, the Commission should affirm its preliminary finding under section \n206 of the FPA that the PJM Tariff is unjust and unreasonable because it lacks “provisions \naddressing with sufficient clarity or consistency the rates, terms, and conditions of service that \napply to co-location arrangements.”39 \n \n35 Show Cause Order at PP 74-75. \n36 Id. \n37 See Constellation First Answer at Section I (pp. 13-36); see also id., Exh. 1, Declaration of Dr. Paul Stockton; Exh. \n2, Testimony of Zachary Ming.  Mr. Ming is the only rate design expert in the record to discuss the issue whether a \nNITS-only approach is unjust and unreasonable.   \n38 See, e.g., San Diego Gas & Elec. Co. v. Sellers of Energy & Ancillary Servs. Into Mkts. Operated by the Cal. Indep. \nOperator Corp., 153 FERC ¶ 61,144, at P 32 (2015) (“general arguments will not suffice to rebut the specific . . . \nevidence presented by [parties]”). \n39 Show Cause Order at P 74."},{"page":12,"startToken":4792,"endToken":5138,"text":"10 \n \nTHE RECORD SUPPORTS THE COMMISSION’S ADOPTION OF A \nREPLACEMENT RATE OF CO-LOCATION CONFIGURATION OPTIONS \nWith the step one showing made under section 206 of the FPA, the Commission must move \nto step two and fix a replacement rate.  Under the plain terms of the FPA, the Commission has no \ndiscretion to do otherwise.  The record in this proceeding already does the heavy lifting and \nprovides substantial evidence and support for adopting new “generator-contingent” options (PJM \nOptions 4 and 5) and a provisional “interruptible” option (PJM Option 7), as well as clarifying the \nTariff to allow a “firm” co-location configuration based on net generation and load at a point of \ninterconnection (PJM Option 2, which essentially would clarify that the same rules for PJM Option \n3 should be available at the co-located load and generator’s election).  With appropriate rate \ntreatment as demonstrated in the record, these three categories of potential co-location \nconfigurations collectively provide a just and reasonable rate that maximizes efficient use of \nexisting energy infrastructure and minimizes expansive transmission upgrades and other costs.  \nEach type of configuration also appropriately allocates costs commensurate with the level of \ntransmission service being used by the load.  Constellation introduced extensive record support for \nthe configurations and the proposed rate treatment for each option, and Vistra Corp. and Enchanted \nRock, LLC, also provided expert support for the generator-contingent configuration.40   \nWhile many of the proponents of a NITS-only approach—including the Indicated \nTransmission Owners—chose not to put forward any expert evidence in response to the Show \nCause Order or even meaningfully address PJM’s eight options in their March submittals, their \nsteadfast refusal to engage on the key issues, despite the overwhelming record evidence identifying \n \n40 See Constellation First Answer, Exh. 2, Testimony of Zachary Ming; Comments of Vistra Corp., Att. A, Affidavit \nof Dr. Roy J. Shanker (filed Apr. 23, 2025) (primarily addressing PJM Options 4 and 5); Response of Enchanted Rock, \nLLC, Att. A, Affidavit of Dr. Albert W. Bremser (filed Apr. 23, 2025) (addressing a new “as-available” transmission \nservice, which shares features with PJM Option 5)."},{"page":13,"startToken":5138,"endToken":5541,"text":"11 \nthe problems with their proposed approach, does not prevent the Commission from ruling on the \nrecord before it.41  Constellation previously moved for settlement discussions on a replacement \nrate, and while Constellation is willing to engage in good faith settlement talks on a replacement \nrate, there already is substantial evidence in the record for the Commission to adopt a replacement \nrate without providing the Indicated Transmission Owners another means to delay resolution. \nIn reviewing the record, the Commission should be wary of conclusory statements and \nunsupported policy posturing as opposed to expert evidence.  For example, Constellation offered \nextensive record expert evidence about why resource adequacy and reliability concerns—which \nalways are present with any large new load—nevertheless are not affected by co-location unless \nwe assume contrary to the law that new data center load does not need to be served.42  There is no \nexpert support in the record for the oft-repeated assertion that co-location jeopardizes resource \nadequacy.   \nThe Commission also must distinguish facts from half-truths.  Some parties highlight \nrecent voltage drops on the grid caused by data centers in Virginia,43 which in this proceeding that \nis focused on co-location may create the impression that co-located behind-the-meter data centers \ncause reliability problems.  But the full truth is that the Virginia data centers were connected to the \ngrid and taking service from remote generators using the exact same front-of-the-meter approach \nthat Indicated Transmission Owners advocate.  The voltage issue had nothing to do with co-\n \n41 The Commission provided notice to PJM and the Transmission Owners that it intended to “be able to issue our \n[final] decision within approximately three months of the filing of Tariff revisions.”  Show Cause Order at P 90.  The \nCommission thus should not countenance sandbagging by parties that demonstrably benefit from delay in adopting \nclear co-location rules.  The Commission should reject any late-filed answers by the Indicated Transmission Owners \nor others attempting to introduce rebuttal evidence when these parties chose not to present a case in chief with \nsupporting evidence in their initial filings.  Such delay is prejudicial to the parties like Constellation being refused \naccess to wholesale services to accommodate co-located loads under the Indicated Transmission Owners’ erroneous \ninterpretation of the PJM Tariff. \n42 Constellation First Answer at Section II.B. (pp. 58-64); see also id., Exh. 3, Affidavit of Aaron Patterson. \n43 See, e.g., Comments of the Union of Concerned Scientists at 11, 14."},{"page":14,"startToken":5541,"endToken":5905,"text":"12 \nlocation.  Had the data centers been co-located behind-the-meter, PJM’s former head of operations \nsuggests that the voltage drops might not have occurred.44  The Commission should reject the \nconjectural narrative that co-location jeopardizes resource adequacy and reliability.  If anyone had \nevidence that co-location risks resource adequacy or reliability any more than any other service to \nnew load, they would have—and should have—provided it by now. \nA similarly inapt argument is that “[c]o-location arrangements involving existing \ngenerators can heighten concerns … by exacerbating certain market participants’ incentives to \nabuse market power and engage in market manipulation.”45  There is absolutely no support for this \nstatement, and to the extent this is a legitimate concern, it would be equally applicable to any \nscenario when supply and demand conditions are tightening.  Like the resource adequacy \n“concerns” discussed above, it has nothing to do with co-location.  Regardless, PJM, the IMM and \nthe Commission are well-equipped with rules and tools to screen and mitigate market power.  And \nexisting generators are not withholding power by selling it to co-located load.  Load is load, and \nyou cannot withhold supply while at the same time using that supply to serve load. \nWhile there already is full record support to adopt these co-location configurations (PJM \nOption 2 with a netting option, Options 4 and 5 for generator-contingent service, and Option 7 for \nprovisional interruptible service), we provide the following brief additional comments: \nFirst, for the “firm” co-location configuration (PJM Option 2), the correct rate treatment is \nto allow the load the choice whether to net the generation and the load, just as with PJM’s existing \nBehind-the-Meter Generation (“BTMG”) rules (PJM Option 3).  The Indicated Transmission \n \n44 See Constellation First Answer at 22; id., Exh. 5, Affidavit of Michael Kormos at ¶ 7 (“Large generators also \ntypically provide significant inertia that can help the local grid avoid or minimize the impact of many anomalies.  \nGiven the reduced likelihood of a voltage drop in the first place for load co-located with a generator, it is less likely \nthat such load will sense a voltage anomaly that will lead it to drop.”). \n45 Comments of Public Interest Organizations at 32-33 (filed Apr. 23, 2025)."},{"page":15,"startToken":5905,"endToken":6229,"text":"13 \nOwners assert that co-located load should pay gross NITS while BTMG load should continue to \nnet.  But as the PJM Industrial Customer Coalition and Industrial Energy Consumers of America \nargue, the Indicated Transmission Owners “do not dispute the fact that the configurations between \nBTMG and co-located load can be identical … yet [they] advocate for a radically different \napproach for all similarly situated customers that are defined as co-located load.”46  “This is unduly \ndiscriminatory.”47  It “would create an unreasonable preference for one type of users over another. \nIt would create dramatically different costs for different users with identical impact to the \ntransmission grid.”48  There is no principled way to sustain the Indicated Transmission Owners’ \narguments. \nSecond, for the “generator-contingent” co-location configurations (PJM Options 4 and 5), \nit is telling that the primary argument against this type of service is that protective relays—and \ntheir backup protective relays—all may suddenly fail, and that the transmission system allegedly \nmust be planned accordingly.49  No expert subscribes to this self-serving conjecture, as confirmed \nin affidavits in the record by two former senior PJM operators and planners.50   \nThe other leading argument against generator-contingent service is that co-located loads \nallegedly are attempting to avoid paying for ancillary services.  As the Commission is aware, every \nload interest at the technical conference and since has stated that it will pay any appropriate charges \nfor any services they use, including ancillary services.  The focus on ancillaries also is a distraction \nfrom the main issue, which is whether loads should be forced to take front-of-the-meter NITS \n \n46 Joint Comments of PJM Industrial Customer Coalition and Industrial Energy Consumers of America at 9 (filed Apr. \n23, 2025). \n47 Id. \n48 Id. (emphasis in the original). \n49 For a full discussion of this issues, see Constellation First Answer at 48-49. \n50 See id., Exh. 4, Affidavit of Steven R. Herling at ¶ 23; Exh. 5, Affidavit of Michael Kormos at ¶¶ 6-7."},{"page":16,"startToken":6229,"endToken":6596,"text":"14 \nservice on a gross basis, even though other configurations and rate structures better encourage \nefficient use of the grid, minimize cost to current customers, and more promptly connect data \ncenter load critical to our national security.  The cost of these ancillary services is only a small \nfraction of the costs of NITS.  To eliminate any debate and move past what always has been a \nperipheral issue, Constellation would support generator-contingent co-location rules that included \nancillary service charges as part of a replacement rate.   \nWith red herrings about relays and ancillary service charges cast aside, generator-\ncontingent service can be seen for what it is: an option to efficiently and promptly serve large loads \nwithout socializing upgrade costs or increasing resource adequacy or reliability risks.  While the \nIndicated Transmission Owners spill much ink about their desire to protect customers, nothing \nabout a rate design that encourages billions of dollars of transmission overbuild is in customers’ \nbest interests.  Customers already are shouldering the burden of massive transmission rate \nincreases,51 while supply costs have essentially held steady since PJM’s Reliability Pricing Model \n(“RPM”) was implemented.52 \nThird, for provisional “interruptible” service for co-located loads (PJM Option 7 with \nConstellation’s proposed rate treatment),53 the Commission should clarify that the provisional \nservice ends once the network upgrades are built.  However, some additional details regarding \n \n51 See Md. Office of People’s Counsel, Motion for Leave to File Answer and Answer, Docket No. ER24-843-000, at \n15 (Mar. 20, 2024) (protesting allocation of over $500 million in costs to Maryland customers for transmission \nupgrades primarily needed to serve data centers located in Virginia). \n52 See Constellation First Answer, Exh. 3, Affidavit of Aaron Patterson at ¶ 19 (explaining that “[i]n real terms, \ncombined energy, ancillary services, and capacity costs have fallen by about 34% over the period simply comparing \n2008 and 2025/26. And even ignoring the high prices in 2008, [these] costs have on average remained essentially flat \nin real terms from 2009 onward. Over the same period transmission costs in PJM, which are not subject to competition \nbut continue to be determined using traditional cost-based ratemaking, have more than tripled in real terms…”).  \n53 See Constellation First Answer at 55-57."},{"page":17,"startToken":6596,"endToken":7050,"text":"15 \nwhen the service will be interrupted still need to be provided.  The Commission should require \nPJM to make a compliance filing with these details within 60 days.  \nFinally, the Commission should reject PJM’s Option 6 (Interconnection Preferences for \nBYOG) as unduly discriminatory and preferential for the reasons Constellation previously \naddressed.54  It creates risks of “vintaging” where new resources are paid out-of-market and then \nused to suppress market prices to all existing resources.  The Commission has long rejected such \nschemes after an initial failed foray into contract vintaging in the natural gas markets.55  Moreover, \nthis proposal will not achieve the apparent objective to address resource adequacy concerns: it \nprovides preferential treatment to resources regardless of their capacity attributes simply because \nthey have a contract.  This approach would undermine the investment signal sent by PJM’s \ncentralized capacity market, which explicitly values capacity resources according to their Effective \nLoad Carrying Capability.  The Commission should resist the siren call of extra-market BYOG \nincentives.  This is the precise time that the Commission should be staying the course with respect \nto RPM and providing for regulatory certainty.   \n \n54 See id. at 52-55. \n55 See id. at 53-54, citing Re Area Rate Proceeding for Rocky Mountain Area, 49 FPC 924, 942 (1973) (citing Opinion \nNo. 468, Permian I, 34 FPC 159, 185 (1965) (“vintaging by contract date is an anachronism which should be \neliminated”); PJM Interconnection, L.L.C., 126 FERC ¶ 61,275, at P 149 (2009) (finding that PJM’s proposal to \nincrease the RPM’s New Entry Price Adjustment provision from three years to seven years would “further bifurcate \ncapacity markets by giving new suppliers longer payments and assurances unavailable to existing suppliers providing \nthe same service”), order on reh’g, 128 FERC ¶ 61,157 (2009).  For more recent examples, see PJM Interconnection, \nL.L.C., 175 FERC ¶ 61,084, at PP 17 (2021) (rejecting an effective load carrying capability (“ELCC”) class rating \nfloor “transition mechanism” because “it would discount the accredited capacity value of some ELCC Resources \nbelow their actual capacity value in order to value other ELCC Resources above their actual capacity value” and \nbecause PJM would “unreasonably discount the capacity value of ELCC Resources that enter the market at a later \ndate”); id. at P 108 (further finding that the transition mechanism “would discriminate between resources in a class \nbased on vintage despite the fact that all resources in a class bear equal responsibility for the decrease in the capacity \ncontribution of their ELCC Class;” ISO New England Inc., 173 FERC ¶ 61,198 at PP 68, 73-74 (2020) (eliminating \nseven-year new entrant price lock because it “result[s] in unreasonable price distortion” by “reduc[ing] the price paid \nto all capacity suppliers” in the capacity auction)."},{"page":18,"startToken":7050,"endToken":7220,"text":"16 \nCONCLUSION \nWHEREFORE, Constellation respectfully requests that the Commission grant leave and \naccept this answer and adopt its preliminary finding that the PJM Tariff is unjust and unreasonable \nand unduly discriminatory and preferential because it lacks clear provisions for the treatment of \nlarge loads co-located with generation, and this lack of clarity has caused undue discrimination \nagainst large loads seeking to co-locate.  The Commission should fix replacement rates as set forth \nherein. \nRespectfully submitted, \n /s/ Paul F. Wight \nCarrie Hill Allen \nSr. Vice President & Deputy General Counsel \nSeth Lucia \nAssistant General Counsel  \nConstellation Energy Generation, LLC  \n250 Massachusetts Ave. NW, Suite 760 \nWashington, D.C. 20001     \ncarrie.allen@constellation.com   \nseth.lucia@constellation.com  \n \nChristopher A. Wilson  \nManaging Director, Federal Regulatory Affairs \nConstellation Energy Generation, LLC  \n250 Massachusetts Ave. NW, Suite 760 \nWashington, D.C. 20001  \n(202) 347-7500  \nFERCe-filings1@constellation.com \n \nPaul F. Wight \nKirkland & Ellis LLP \n1301 Pennsylvania Ave., NW \nWashington, D.C. 20004 \n(202) 389-3321 \npaul.wight@kirkland.com \n \n \n \n \n \n \n \n \n \n \n \n \nCounsel for Constellation Energy \nGeneration, LLC \n \nMay 8, 2025"},{"page":19,"startToken":7220,"endToken":7288,"text":"17 \nCERTIFICATE OF SERVICE \nI hereby certify that I have on this 8th day of May, 2025, caused to be served a copy of the \nforegoing upon all parties on the service list in these proceedings in accordance with the \nrequirements of Rule 2010 of the Commission’s Rules of Practice and Procedure, 18 C.F.R. \n§ 385.2010 (2024). \n \n/s/ Shawn Whites \n \n \n \n \n \n \n \nShawn Whites \n \n \n \n \n \n \n \nConstellation Energy Generation, LLC"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":2,"endAt":0,"startToken":0,"endToken":174},{"p":2,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":18,"endAt":4,"startToken":174,"endToken":7051},{"p":18,"at":4,"title":"CONCLUSION","method":"printed heading","endPage":19,"endAt":4,"startToken":7051,"endToken":7221},{"p":19,"at":4,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":19,"endAt":422,"startToken":7221,"endToken":7288}]}