{"document":{"slug":"rec-20250513-5078","title":"Answer of Talen Energy Corporation to Joint Comments and Motion to Stay Proceedings and Request to Establish Settlement Judge Procedures","issued":"2025-05-13","accession":"20250513-5078","docket":"EL25-49-000","group":"PJM co-location compliance","filer":"Talen Energy Corporation","kind":"answer","file":"sources/filings/text/20250513-5078_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20250513-5078","tier":"record","sha256":"b15e3b1b0653a618b6f65e11157dea5484fc4fc2d304a439814a6197779b42cb","pages":6,"tokens":1399,"emptyPages":[],"textThemes":["colo"]},"pages":[{"page":1,"startToken":0,"endToken":305,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \nPJM Interconnection, L.L.C., et al. \n) \n Docket No. EL25-49-000 \n \n \nLarge Loads Co-Located at Generating  \n) \n Docket No. AD24-11-000 \nFacilities  \n) \n \nConstellation Energy Generation, LLC \n) \nDocket No. EL25-20-000 \n \n) \n(consolidated) \nv.  \n) \n \n) \nPJM Interconnection, L.L.C.  \n) \n \nANSWER OF TALEN ENERGY CORPORATION \nTO JOINT COMMENTS AND MOTION TO \nSTAY PROCEEDINGS AND REQUEST TO ESTABLISH \nSETTLEMENT JUDGE PROCEDURES1 \nTalen Energy Corporation (“Talen”) asserts and reiterates that all eight options \npresented by PJM Interconnection, L.L.C. (“PJM”) for the co-location of large load in its \nAnswer2 to the Show Cause Order3 are, when taken as a whole, just and reasonable and not \nunduly discriminatory.  Therefore, there is no need for a 90-day period of settlement judge \nprocedures.  Time is of the essence.  The Commission already has before it a record to find \nthat the PJM solutions to the issues presented by large load co-location are just and \n \n1 This answer is submitted pursuant to Rule 213 of the Rules of Practice and Procedure of the Federal Energy \nRegulatory Commission (“Commission” or “FERC”).  To the extent this answer may be considered an \nanswer to the Answer of PJM Interconnection, L.LC. to Joint Comments and Motion to Stay Proceedings \nand Request to Establish Settlement Judge Procedures filed in by PJM Interconnection, L.L.C., in Docket \nNo. EL25-49-000 on May 5, 2025, Talen requests that the Commission consider this answer as a Request for \nLeave to Answer and Answer.  \n2 PJM Interconnection, L.L.C., et al., Docket No. EL25-49-000, Answer of PJM Interconnection, L.L.C. \n(filed Mar. 24, 2025). (“Answer to the Show Cause Order”) \n3 PJM Interconnection, L.L.C, et al., Docket No. EL25-49-000, Order Instituting Proceeding Under Section \n206 of the Federal Power Act and Consolidating with Other Proceedings (filed Feb. 20, 2025) (“Show Cause \nOrder”)."},{"page":2,"startToken":305,"endToken":613,"text":"2 \n \nreasonable.  Once PJM makes all changes necessary to implement the latter five options in \nits Open Access Transmission Tariff (“OATT” or “Tariff”), to the extent necessary, its \nTariff will be just and reasonable.  Accordingly, Talen respectfully requests that the \nCommission deny the Motion to Stay Proceedings and Request Settlement Judge \nProcedures4 and instead order PJM to revise its OATT and file amended Tariff language \nno later than thirty (30) days after such a Commission order. \nI. ANSWER \n \nA.  \nPJM’s Tariff Will Become Just and Reasonable Once it Incorporates \nLanguage Effectuating All Eight Co-Located Load Configuration Options \nPresented in its Answer to the Show Cause Order.  \nTalen does not agree that PJM’s Tariff is just and reasonable as it currently stands \ntoday.  PJM presented eight options for co-located load configurations in its Answer to the \nShow Cause Order.5  The eight options presented by PJM include both front-of-the-meter \nand behind-the-meter arrangements, including options that allow for co-located load to not \nbe network load and/or not take any FERC-jurisdictional services.  Taken together, the \neight configuration options permit entities seeking to enter into co-located load \narrangements to select the configuration that best meets their needs from a considerable \nvariety of configuration options.  Thus, this framework, when adopted as a whole, will \nresult in PJM’s Tariff being just and reasonable and not unduly discriminatory.  There is \nan ample record of evidence already to support this finding. \n \n4 PJM Interconnection, L.L.C., et al., Docket No. EL25-49-000, Joint Comments and Motion to Stay \nProceedings and Request to Establish Settlement Judge Procedures of the Electric Power Supply Association, \nthe PJM Power Providers Group, Calpine Corporation, Cogentrix Energy Power Management, LLC, \nConstellation Energy Generation, LLC, and LS Power Development, LLC (filed April 22, 2025). (“Motion \nto Stay Proceedings and Request to Establish Settlement Judge Procedures”) \n5 Answer to the Show Cause Order."},{"page":3,"startToken":613,"endToken":902,"text":"3 \n \nHowever, PJM’s current Tariff language only allows entities pursuing large load \narrangements to configure these arrangements in three ways: as network load with its own \npoint of interconnection (“POI”) to the grid (Option 1); as network load that shares the \nsame POI with the generator but is separately metered (Option 2); or as network load that \nhas a behind-the-meter generation agreement with a co-located generator (Option 3).6  \nThese three options do not presently outline regulatory guardrails for many of the potential \nconfigurations that co-located load arrangements may take, despite there being an \nimmediate need for such guidelines.  The absence of any tariff language that outlines how \nthese loads may interconnect under other configurations results in the current PJM Tariff \nbeing unjust and unreasonable. \nPJM’s Tariff will be just and reasonable only if the Commission orders PJM to \nmake all necessary Tariff modifications to effectuate the selection of all eight configuration \narrangements it presented in its Answer to the Show Cause Order, including those \narrangements where: co-located load is non-network load connected directly to a generator \nconnected to the PJM transmission system with various protections in place to avoid the \npotential of delivery of system energy to serve the load (Option 4); co-located load is \nconfigured the same as Option 4 and also has conditional approval from PJM to take back-\nup power from the grid if necessary (Option 5); co-located load is network load and it \nbrings additional generation to the PJM transmission system that could serve as a capacity \nresource for PJM (Option 6); co-located load is network load but it uses a new transitional \nnon-capacity backed service offering until any resource adequacy issues associated with \n \n6 PJM Answer at 9-13; see PJM Answer Ex. A."},{"page":4,"startToken":902,"endToken":1236,"text":"4 \n \nits load addition are addressed (Option 7); or co-located load is network load and \nparticipates in PJM’s demand response programs (Option 8).7 \nOnce the Commission orders PJM to modify its Tariff to provide for the additional \nfive co-located load configuration options, and PJM submits a compliance filing \neffectuating such changes, the Tariff will be just and reasonable.   \nB.  \nThe Commission Should Deny the Motion to Stay Proceedings and Request \nfor Settlement Judge Procedures and Order PJM to Modify its Tariff Within \n30 Days.   \nTime is of the essence for the Commission to act.  PJM and its diverse stakeholders \nrely on the Commission to support to PJM in administering its transmission system in a \nreliable and stable way that also promotes economic growth.  As Talen has previously \nexplained, it is essential for the Commission to provide clarity and regulatory certainty on \nthe critical issues presented by the co-location of large load as quickly as possible.8 \nTalen does not agree that the Commission should establish a 90-day period of \nsettlement judge procedures to further discuss the issues.  The record already before the \nCommission has eight strong, viable options for co-located load configuration proposed by \nPJM which are just and reasonable and not unduly discriminatory.  A 90-day settlement \nperiod will only further delay crucial regulatory certainty for all stakeholders involved.  \nInstead of establishing a 90-day period of settlement judge procedures, the Commission \nshould order PJM to file amended Tariff language no later than thirty (30) days after the \norder is issued. \n \n7 Id. at 13-20; see PJM Answer Ex. A.  \n8 PJM Interconnection, L.L.C., et al., Docket No. EL25-49-000, Comments of Talen Energy Corporation on \nAnswer of PJM Interconnection, L.L.C. To Order Instituting Proceeding Under Section 206 of the Federal \nPower Act and Consolidating with Other Proceedings (filed April 23, 2025);  Large Loads Co-Located at \nGenerating Facilities, Docket No. AD24-11-000, Comments of Talen Energy Corporation on Issues Related \nto Co-Location of Large Loads at Generating Facilities (filed Dec. 9, 2024)."},{"page":5,"startToken":1236,"endToken":1347,"text":"5 \n \nII. CONCLUSION \nFor the aforementioned reasons, Talen respectfully requests that the Commission \ndeny the Motion to Stay Proceedings and Request to Establish Settlement Judge \nProcedures, and order PJM to make all necessary Tariff modifications to effectuate the \nselection of configuration Options 4 through 8 within 30 days of FERC’s order in this \nproceeding. \n \n                                                                      Respectfully submitted, \n \n \n/s/ William S. Scherman \nWilliam S. Scherman \nMelinda J. Warner \nVinson & Elkins LLP \n2200 Pennsylvania Avenue, NW \nSuite 500 West \nWashington, DC 20037 \n \nJennifer Mansh \nTalen Energy Corporation \nSenior Vice President, Regulatory and \nExternal Affairs \n600 Hamilton St., Suite 600 \nAllentown, PA  18101 \nJennifer.Mansh@TalenEnergy.com\n                                                                      Counsel for Talen Energy Corporation  \nMay 13, 2025"},{"page":6,"startToken":1347,"endToken":1399,"text":"6 \n \nCERTIFICATE OF SERVICE \n \nI hereby certify that I have this day served the foregoing document upon each \nperson designated on the official service lists compiled by the Secretary in these \nproceedings. \nDated at Washington, DC, this 13th day of May 2025. \n \n/s/ Melinda J. Warner  \n \nMelinda J. Warner \nVinson & Elkins LLP"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":2,"endAt":499,"startToken":0,"endToken":381},{"p":2,"at":499,"title":"I. ANSWER","method":"printed heading","endPage":2,"endAt":512,"startToken":381,"endToken":383},{"p":2,"at":512,"title":"A. PJM’s Tariff Will Become Just and Reasonable Once it Incorporates","method":"printed heading","endPage":4,"endAt":384,"startToken":383,"endToken":961},{"p":4,"at":384,"title":"B. The Commission Should Deny the Motion to Stay Proceedings and Request","method":"printed heading","endPage":5,"endAt":5,"startToken":961,"endToken":1237},{"p":5,"at":5,"title":"II. CONCLUSION","method":"printed heading","endPage":6,"endAt":5,"startToken":1237,"endToken":1348},{"p":6,"at":5,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":6,"endAt":327,"startToken":1348,"endToken":1399}]}