{"document":{"slug":"rec-20250522-5125","title":"Motion for Leave to Respond and Limited Response of Buckeye Power, Inc. to the 05/08/2025 Answer of Vistra Corp","issued":"2025-05-22","accession":"20250522-5125","docket":"EL25-49-000","group":"PJM co-location compliance","filer":"Buckeye Power, Inc.","kind":"answer","file":"sources/filings/text/20250522-5125_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20250522-5125","tier":"record","sha256":"d875379fb6328ddcd392023c444ec3035fa16f59946a054b496346d77692c894","pages":9,"tokens":2174,"emptyPages":[],"textThemes":["cost","retail"]},"pages":[{"page":1,"startToken":0,"endToken":175,"text":"UNITED STATES OF AMERICA\nBEFORE THE\nFEDERAL ENERGY REGULATORY COMMISSION\n      \nPJM Interconnection, L.L.C. \nAllegheny Electric Cooperative, Inc. American \nTransmission Systems, Incorporated \nAtlantic City Electric Company \nBaltimore Gas and Electric Company \nDelmarva Power & Light Company \nDuke Energy Ohio, Inc. \nDuke Energy Kentucky, Inc. \nEast Kentucky Power Cooperative, Inc. \nEssential Power Rock Springs, LLC \nHudson Transmission Partners, LLC \nJersey Central Power & Light Company \nMid-Atlantic Interstate Transmission, LLC \nNeptune Regional Transmission System, LLC \nOld Dominion Electric Cooperative \nPECO Energy Company \nPPL Electric Utilities Corporation \nPotomac Electric Power Company \nPublic Service Electric and Gas Company \nRockland Electric Company \nTrans-Allegheny Interstate Line Company \nTransource West Virginia, LLC \nUGI Utilities, Inc. \nMonongahela Power Company \nThe Potomac Edison Company Commonwealth \nEdison Company Commonwealth Edison \nCompany of Indiana, Inc. \nThe Dayton Power and Light Company \nAEP Appalachian Transmission Company, Inc. \nAEP Indiana Michigan Transmission Company, \nInc. \nAEP Kentucky Transmission Company, Inc\nAEP Ohio Transmission Company, Inc.\nAEP West Virginia Transmission Company, \nInc. \nAppalachian Power Company \nIndiana Michigan Power Company \nKentucky Power Company\nKingsport Power Company \nOhio Power Company \n)\n)\n)\n)\n)\n)\n)\n)\n)\n)\n)\n)\n)\n)\n)\n)\n)\n)\n)\n)\n)\n)\n)\n)\n)\n)\n)\n)\n)\n)\n)\n)\n)\n)\n)\n)\n)\n)\n)\n)\nDocket Nos. EL25-49-000"},{"page":2,"startToken":175,"endToken":386,"text":"- 2 -\nWheeling Power Company \nDuquesne Light Company \nVirginia Electric and Power Company \nLinden VFT, LLC \nCity of Cleveland, Department of Public \nUtilities, Division of Cleveland Public Power \nCity of Hamilton, OH \nSouthern Maryland Electric Cooperative, Inc. \nOhio Valley Electric Corporation \nAMP Transmission, LLC \nSilver Run Electric, LLC \nNextEra Energy Transmission\n MidAtlantic Indiana, Inc. \nWabash Valley Power Association, Inc. \nKeystone Appalachian Transmission Company\nLarge Loads Co-Located at Generating\nFacilities\nConstellation Energy Generation, LLC\nv.\nPJM Interconnection, L.L.C.\n)\n)\n)\n)\n)\n)\n)\n)\n)\n)\n)\n)\n)\n)\n)\n)\n)\n)\n)\n)\n)\n)\n)\n)\n)\nAD24-11-000\nEL25-20-000 (Consolidated)\nMOTION FOR LEAVE TO RESPOND AND \nLIMITED RESPONSE OF BUCKEYE POWER, INC.\nPursuant to Rules 212 and 213 of the Federal Energy Regulatory Commission’s \n(“Commission”) Rules of Practice and Procedure,1 Buckeye Power, Inc. (“Buckeye”) respectfully \nmoves for leave to respond and submits the following brief response to the May 8, 2025 Answer \nof Vistra Corp. (“Vistra”).2 The Limited Response below addresses only one aspect of Vistra’s \nAnswer: potential retail “financial commitment” requirements for new large load interconnection.3 \nSuch retail “financial commitments” may have some benefit, but on their own they do not go far \n1 18 C.F.R. §§ 385.212, 385.213.\n2 Motion for Leave to Answer and Answer of Vistra Corp. (May 8, 2025), eLibrary No. 20250508-5081 (“Vistra \nAnswer”). \n3 Vistra Answer at 12-13."},{"page":3,"startToken":386,"endToken":699,"text":"- 3 -\nenough to protect other customers against unjust and unreasonable Commission-jurisdictional \ntransmission rates. Such retail financial commitments alone fail to protect other wholesale \ntransmission customers from the risk of unreasonably bearing substantial stranded transmission \ncosts caused if those large loads fail to show up as expected, whether initially or after the load goes \ninto service.\nI.\nMOTION FOR LEAVE TO RESPOND\nThe Commission’s Rules prohibit answers to answers unless otherwise authorized,4 but the \nCommission has the authority to waive this prohibition for good cause.5 It routinely grants motions \nfor leave to answer when doing so will assist the Commission’s decision-making process.6 The \nfollowing Response will aid the Commission’s understanding of the range of risks and concerns \nregarding new, large load interconnections, such as large data center loads. \nII.\nLIMITED RESPONSE\nFor the reasons described in our earlier comments in the now-consolidated proceedings, \nBuckeye disagrees with many of Vistra’s arguments on the treatment of co-location arrangements7 \nbut responds only to Vistra’s discussion of potential requirements for “financial commitments” by \nnew large loads.8 Vistra’s Answer regarding this issue addresses earlier comments by Americans \nfor a Clean Energy Grid (“ACEG”),9 which “proposed to require load-serving entities and electric \n4 18 C.F.R. § 385.213(a)(2).\n5 Id. § 385.101(e).\n6 See, e.g., Midcontinent Indep. Sys. Operator, Inc., 178 FERC ¶ 61,249, P 16 (2022) (accepting answers to answers \n“because they have provided information that assisted us in our decision-making process”).\n7 See Comments of Buckeye Power, Inc. (Apr. 23, 2025), eLibrary 20250423-5154 (“Buckeye April 2025 \nComments”); Comments of Buckeye Power, Inc. (Dec. 9, 2024), eLibrary No. 20241209-5210 (“Buckeye December \n2024 Comments”). Not addressing these other issues does not imply agreement or waiver of any argument.  \n8 Vistra Answer at 12-13. \n9 Comments of Americans for a Clean Energy Grid (Apr. 23, 2025), eLibrary No. 20250423-5217 (“ACEG \nComments”)."},{"page":4,"startToken":699,"endToken":1025,"text":"- 4 -\ndistribution companies that request load adjustments demonstrate that any new large loads \ninterconnections are backed by stringent financial commitments.”10 The idea behind such financial \ncommitments is to “place the risk of customer-specific forecasting inaccuracy on the individual \ncustomer,”11 rather than the load-serving entity (“LSE”). Although “Vistra agrees that requiring \nsuch financial commitments would help improve the accuracy of PJM’s load forecasting by \ndisincentivizing load customers from submitting multiple duplicative interconnection requests,” it \nargues that such reforms would need to be included in PJM’s Tariff and should be explored by the \nCommission in a separate proceeding.12\nBuckeye agrees that retail financial commitments can play a useful role in improving \nforecast accuracy and protecting the host LSE and its own retail customers from the excessive \ntransmission costs associated with overestimating new large loads.13 However, Vistra’s Answer \n(like ACEG’s Comments to which Vistra responds) fails to recognize that the risks of inaccurate \nforecasting go beyond just the allocation of risk between the host LSE and large end-use customer. \nAs presented, the financial commitments concept omits one critically important element needed to \nprotect other transmission customers from bearing stranded transmission costs when large loads \nfail to materialize as forecasted. To meet its Federal Power Act obligations, the Commission \nshould take additional actions to fill this problematic void. \n10 Vistra Answer at 12. See also ACEG Comments at 3-4 and Attachment. \n11 ACEG Comments, Attach. at 2. \n12 Vistra Answer at 12-13. \n13 See Buckeye April 2025 Comments at 12 (explaining that LSEs can enter into arrangements with large end-use \ncustomers “e.g., through a minimum demand charge, and minimum contract term, backed by appropriate credit \nsupport requirement” to encourage end-use customer loads to show up as expected).  Buckeye takes no position on \nwhether the requirement for forecasted load to be backed by “financial commitments” needs to be approved through \na separate Commission proceeding or can be addressed through revisions to PJM’s manuals without FERC approval."},{"page":5,"startToken":1025,"endToken":1359,"text":"- 5 -\nSpecifically, as explained in Buckeye’s earlier comments in greater detail, wholesale \ntransmission customers other than the host LSE face significant risks of stranded costs if large \nloads do not materialize as forecast.14 The costs of the significant transmission investments needed \nto serve new, large loads are shared among LSEs in the relevant PJM zone on a load-ratio share \nbasis pursuant to transmission owner (“TO”) formula rates filed as Attachment H to the PJM \nOATT. If the large loads do not materialize, the host LSE’s load does not increase (or may \nsubsequently decrease before the cost of transmission facilities built to serve the customer are fully \nrecovered through rates, even if the large load initially went into service at planned-for levels), and \na portion of the costs of transmission facilities built by the applicable transmission owner to serve \nthe large load would thus be shifted to other LSEs in the TO Zone. Although retail “financial \ncommitments” described by Vistra and ACEG may allow the host LSE to recover costs from the \nlarge load that failed to materialize (and potentially protect its retail customers), in the absence of \nfurther Commission action resulting in the crediting of the benefits of these financial commitments \nagainst the FERC jurisdictional wholesale transmission revenue requirement, the benefits of these \n“financial commitments” would be trapped at the host LSE’s retail level alone and would do \nnothing to protect other wholesale LSEs in the applicable TO Zone or their retail customers from \nthese stranded transmission costs. \nTo ensure just and reasonable wholesale transmission rates, any costs collected under such \nretail “financial commitments” would need to also be credited to the wholesale transmission \nrevenue requirement for the applicable TO Zone to ensure that the costs of any transmission \nfacilities built by the transmission owner to accommodate such large loads, as planned and \ncontracted for, are not shifted to other LSEs in the applicable PJM TO Zone. As Buckeye has \n14 Buckeye December 2024 Comments at 4-9; Buckeye April 2025 Comments at 10-12."},{"page":6,"startToken":1359,"endToken":1788,"text":"- 6 -\npreviously explained, the different approaches taken by AES Ohio and AEP Ohio illustrates how \n“financial commitments” at the retail level with regard to new large loads are not sufficient by \nthemselves to ensure that other LSEs in the TO Zone are protected against unreasonable \ntransmission cost shifts.15 Thus, additional mechanisms at the FERC-jurisdictional wholesale \nlevel, beyond the purely retail “financial commitments” describe by Vistra (and ACEG), are \nrequired to ensure just and reasonable Commission-jurisdictional transmission rates. \nAs noted in Buckeye’s April 2025 Comments (at 10-12), and the additional details in our \nDecember 2024 Comments (at 4-9), the PJM Tariff should be revised so that each LSE is \nresponsible, as part of the calculation of zonal transmission rates, for its large load demand.16 Such \nLSE responsibility will ensure that any stranded transmission costs associated with such large \nloads are not shifted to other LSEs through PJM transmission rates. Indeed, this approach would \nencourage LSEs to require financial commitments of their retail large load customers in order to \nbackstop their wholesale responsibility, avoiding the issue of whether PJM should require retail \nfinancial commitments from large loads to host LSEs (much less the issue of where such a \nrequirement should be located17). Critically, only the LSE where the large load is located has the \nability to push stranded cost responsibility and “financial commitments” to the large retail load. \n15 Buckeye December 2024 Comments at 7-9. While both AES Ohio and AEP Ohio required certain minimum \ndemand payments, backed by credit support, from large load customers for a period of time sufficient to recover \ninvestments in transmission facilities built to accommodate such large loads as planned and contracted for, the \ncritical difference is that “AES Ohio committed to apply any payments it receives from Amazon under this \narrangement to the wholesale transmission revenue requirement to ensure that all other wholesale transmission \ncustomers would similarly be held harmless from any stranded costs caused by the retail load not showing up as \nexpected.” Id. at 7 (footnote omitted). AEP Ohio, on the other hand, has not yet made any such commitment, \n“leaving other wholesale transmission customers in the AEP Zone (including Buckeye) bearing the stranded \ntransmission costs.” Id. at 8. \n16 The extent of such responsibility, whether 100% or something less, the length of time such responsibility would \nremain in place, and other details would be subject to further Commission proceedings.\n17 As noted above, Buckeye takes no position on the dispute between Vistra and ACEG on where any such \n“financial commitment” is located. What matters for PJM rates is LSE responsibility."},{"page":7,"startToken":1788,"endToken":2094,"text":"- 7 -\nOther LSEs that would be affected by material reduction in large loads through transmission cost-\nshifting at the wholesale level have no ability whatsoever to mitigate such transmission cost-\nshifting through the imposition of retail “financial commitments” on large loads located in the \nretail service territory of other LSEs. \nIt is therefore imperative that the Commission take steps to mitigate the potential for \nsignificant shifting of transmission costs at the wholesale level to LSEs that do not have the ability \nto mitigate the effects of such cost-shifting through the imposition of “financial commitments” at \nthe retail level on the large retail loads causing such cost-shifting.18  If the Commission does not \naddress this issue in this proceeding, the Commission should open a separate Section 206 \nproceeding to ensure the PJM Tariff contains sufficient provisions to mitigate transmission cost \nshifting caused by large loads.19  Regardless of the approach the Commission decides to take, these \nissues should be promptly addressed.20 \nIII.\nCONCLUSION\nBuckeye respectfully requests that the Commission accept and give full consideration to \nthis Limited Response in connection with its examination of the issues in this proceeding.\n18 Given the magnitude of the large, principally data center, loads currently being planned for by PJM transmission \nowners, and the uneven distribution of such large loads among PJM TOs and among LSEs within a PJM TO Zone, \nCommission inaction is not justified on the basis that the potential transmission costs shifting effects would be de \nminimis or that such effects, even if significant, would be evenly distributed.\n19 A separate Section 206 proceeding addressing standardized transmission-level load interconnection processes, as \nsuggested by Vistra, is overly broad and not necessary to address these concerns unless such a proceeding focuses \nsolely on interconnection processes for large loads exceeding a certain threshold.  \n20 Buckeye April 2025 Comments at 10-13."},{"page":8,"startToken":2094,"endToken":2134,"text":"- 8 -\nRespectfully submitted,\n/s/ Lija Kaleps-Clark\nKurt P. Helfrich\nGeneral Counsel\nLija Kaleps-Clark\nAssociate General Counsel\nBuckeye Power, Inc.\n6677 Busch Boulevard\nColumbus, Ohio 43229\nTelephone: (614) 681-5151\nkhelfrich@ohioec.org \nlkaleps@ohioec.org \nIts counsel\nDated:  May 22, 2025"},{"page":9,"startToken":2134,"endToken":2174,"text":"- 9 -\nCERTIFICATE OF SERVICE\nI hereby certify that on this 22nd day of May, 2025, I have caused the foregoing to be served \nupon each person listed on the Official Service List for this proceeding.\n /s/ Lija Kaleps-Clark\n Lija Kaleps-Clark"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":3,"endAt":407,"startToken":0,"endToken":441},{"p":3,"at":407,"title":"I. MOTION FOR LEAVE TO RESPOND","method":"printed heading","endPage":3,"endAt":896,"startToken":441,"endToken":516},{"p":3,"at":896,"title":"II. LIMITED RESPONSE","method":"printed heading","endPage":7,"endAt":1061,"startToken":516,"endToken":1949},{"p":7,"at":1061,"title":"III. CONCLUSION","method":"printed heading","endPage":9,"endAt":6,"startToken":1949,"endToken":2135},{"p":9,"at":6,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":9,"endAt":239,"startToken":2135,"endToken":2174}]}