{"document":{"slug":"rec-20250523-5192","title":"Motion for Leave to Answer and Answer of Public Service Electric and Gas Company to the initial and reply comments re FERC's 02/20/2025 Show Cause Order","issued":"2025-05-23","accession":"20250523-5192","docket":"EL25-49-000","group":"PJM co-location compliance","filer":"Public Service Electric and Gas Company","kind":"answer","file":"sources/filings/text/20250523-5192_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20250523-5192","tier":"record","sha256":"850f4599c90fd3e7490a1ae2bd331e2605de13fae5857a047a79b0c9d8943fe0","pages":13,"tokens":3534,"emptyPages":[],"textThemes":["colo","flex"]},"pages":[{"page":1,"startToken":0,"endToken":284,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \n \n) \n \nPJM Interconnection, LLC et al. \n \n) \n) \nDocket Nos. EL25-49 \nLarge Loads Co-Located at Generating \nFacilities \n) \n) \nAD24-11 \nConstellation Energy Generation, LLC \nv. \nPJM Interconnection, L.L.C. \n) \n) \n) \nEL25-20 \n(Consolidated) \n \n) \n \n \nMOTION FOR LEAVE TO ANSWER AND ANSWER OF  \nPUBLIC SERVICE ELECTRIC AND GAS COMPANY  \n \nPursuant to Rules 212 and 213 of the Rules of Practice and Procedure of the \nFederal Energy Regulatory Commission’s (“FERC” or “Commission”), 18 C.F.R. §§ \n385.212 and 213 (2025), Public Service Electric and Gas Company (“PSE&G”)1 hereby \nsubmits this Motion for Leave to Answer and Answer to the initial and reply comments \nthat have been filed in response to the Commission’s Show Cause Order issued on \nFebruary 20, 2025 (the “Show Cause Order”).2   \nIn response to the Show Cause Order, a number of comments have been filed.  \nBased on those comments, as well as the comments submitted in other dockets regarding \nco-located load arrangements over the past year, the Commission now has a very \ncomprehensive, robust record before it upon which to establish just and reasonable rules \n \n1 PSE&G serves 2.4 million electric customers in its franchised service territory in New Jersey, \nincluding a number of large load customers who have onsite or Behind the Meter Generation \n(“BTMG”) to meet some or all of their power requirements. \n \n2 PJM Interconnection, L.L.C., et al., 190 FERC ¶ 61,115 at P 2 (2025) (“Show Cause Order”) \n(making a preliminary finding that the PJM Tariff may be “unjust and unreasonable or unduly \ndiscriminatory or preferential because it does not contain provisions addressing with sufficient \nclarity or consistency the rates, terms, and conditions that apply to co-location arrangements.”)."},{"page":2,"startToken":284,"endToken":662,"text":"2 \nunder the PJM Tariff governing co-located load arrangements.  As the Commission \nevaluates the issues and issues a decision, it should be guided by three key principles to \nensure compliance with the requirements of the Federal Power Act and longstanding \nprecedent and policies.   \n• First, any new rules governing co-location arrangements, including those \nregarding transmission pricing, must comply with the basic ratemaking \nprinciple of cost causation.  This means that charges for wholesale grid \nservices, if any, must reflect the customer’s actual use of the system.  For \ninstance, PJM’s Show Cause filing identifies two behind the meter \n(“BTM”) co-located load options (Options 4 and 5) under which the load \nuses the transmission system to a lesser degree than other configurations; \nPJM reasonably proposes cost responsibility reflecting the actual use of the \ntransmission system, consistent with cost causation.  On the other hand, a \ngross load transmission methodology that does not consider the customer’s \nactual use of the transmission system would not comport with cost \ncausation principles.   \n \n• Second, rules adopted by the Commission should not adversely impact \nexisting customers in PJM who have BMTG and who have long relied \nupon the netting provisions under the PJM Tariff for purposes of paying \nwholesale grid services (as set forth in Option 3 in PJM’s Show Cause \nfiling).  Here, there is no material distinction between BTMG and BTM \nload arrangements as both configurations result in a reduced use or impact \non the power grid in the same way, and should be allowed to net their co-\nlocated generation against their load in a comparable manner; any disparate \ntreatment of similarly-situated customers would be unjustified and unduly \ndiscriminatory under the Federal Power Act; and  \n \n• Third, in recognition of the vital importance of data centers to the United \nStates, the Commission should endeavor to remove barriers and provide \nregulatory flexibility for customers to select the configuration that best \nsuits their circumstances. \n \nNow is the time for the Commission to act and provide needed certainty to the \nindustry – including data center developers, utilities, generation owners, existing \ncustomers and other relevant stakeholders. The lack of clarity and certainty over the past \nyear has had a chilling effect on data center development, and we respectfully urge the \nCommission to act in a timely manner to establish new rules on co-location."},{"page":3,"startToken":662,"endToken":958,"text":"3 \nI. \nMOTION FOR LEAVE TO ANSWER \nWhile Rule 213 of the Commission’s Practice and Procedure does not provide for \nanswers to answers, the Commission permits such pleadings where, as here, the \ninformation provided will facilitate the Commission’s decision-making process and aid in \nthe resolution of issues.3  There is good cause for the Commission to accept this Answer \nbecause it will clarify certain issues and assist the Commission with its decision-making.   \nII. \nANSWER \n  In response to the Show Cause Order, over fifty sets of comments presenting a \nwide range of views and positions have been filed with the Commission.  Most parties \nagreed with the Commission’s preliminary finding that there is a gap in the PJM Tariff \ngoverning co-located loads and urged the Commission to expeditiously establish rules \ngoverning co-location arrangements.  PJM, while maintaining that the Tariff remains just \nand reasonable, acknowledges that “clarifications” to the PJM Tariff may be warranted, \nand has identified eight options for the interconnection of large co-located load.  And as \nrelevant to this proceeding, PJM has proposed that the “participants involved in the co-\nlocation arrangement should pay the costs of any grid services they consume,” including a \nreduced level of charges for certain configurations that result in a lesser use of the \ntransmission system.  On the other hand, certain parties, continue to argue that the existing \nPJM Tariff is just and reasonable, no revisions are needed, and all co-location \narrangements (regardless of the physical configuration used) should be required to take \n \n3 See, e.g., Green Island Power Auth. & Albany Eng’g Corp., 168 FERC ¶ 61,033 at P 37 (2019); \nCarolina Power & Light Co., 97 FERC ¶ 61,048 at 61,278 (2001) (finding good cause to waive \nRule 214 when a pleading helped to ensure a complete and accurate record)."},{"page":4,"startToken":958,"endToken":1318,"text":"4 \nnetwork transmission service (or point-to-point transmission service) and pay wholesale \ngrid charges based a gross load basis.4  As the Commission evaluates the various \narguments presented and make rulings in this proceeding, PSE&G respectfully urges the \nCommission to keep several key principles in mind, as discussed below.   \nA. \nAny Transmission Pricing Rules Governing Co-Location \nArrangements Must Comply With Well-Established Cost Causation \nPrinciples.  \nA bedrock ratemaking principle that the Commission and the courts have \narticulated and applied under the Federal Power Act over a number of decades is that \n“rates and charges must reflect to some degree the costs actually caused by the customer \nwho must pay for them,”5 and that costs must be allocated in a manner that is “roughly \ncommensurate” with benefits that entity receives.6  This is such a core ratemaking \nprinciple that is well understood and accepted such that the Court of Appeals for the \nSeventh Circuit has characterized it as really an “unremarkable principle.”  In a 2009 \ndecision, the Seventh Circuit instructed that under this cost causation principle, “FERC is \nnot authorized to approve a pricing scheme that requires a group of  utilities to pay for \nfacilities from which its members derive no benefits, or benefits that are trivial in relation \n \n4 These parties take this position even though the Commission is looking to establish transmission \npricing rules under which the imposition of charges is commensurate with the use of the transmission \nsystem, as required by cost causation.  In the Show Cause Order, the Commission stated that \n“different co-location arrangements are likely to use or benefit from the transmission system in \ndifferent ways” and any charges must be consistent with cost causation principles as well the \nCommission’s recent actions in other related proceedings.  See also Atlantic City Electric Co, et al., \n190 FERC ¶ 61,109 (2025) (rejecting Section 205 filings proposing that all co-located load \narrangements pay full network transmission service and ancillary services on a gross load basis). \n \n5 KN Energy, Inc. v. FERC, 968 F.2d 1295, 1300 (D.C. Cir. 1992). \n \n6 Ill. Com. Comm’n v. FERC, 576 F.3d 470, 476 (7th Cir. 2009) (“2009 ICC Decision”) (emphasis \nadded)."},{"page":5,"startToken":1318,"endToken":1587,"text":"5 \nto the costs sought to be shifted to its members.”7  According to the court, compliance \nwith cost causation is a simple exercise –i.e., comparing of the “costs assessed against a \nparty to the burdens imposed  or benefits drawn by that the party.”8  And the court warned \nthat a “claim of generalized system benefits” is not enough to justify the imposition of \ncharges upon a market participant.9 \nAdherence to cost causation is clearly on the Commission’s mind in this \nproceeding.  Throughout the Show Cause Order, the Commission repeatedly emphasized \nthe importance of compliance with cost causation principles in establishing what \nwholesale grid charges, if any, should be imposed on co-location arrangements.  For \ninstance, the Commission stated that “the record demonstrates that different co-location \narrangements are likely to use or benefit from the transmission system in different ways \ndepending on how they are configured and, moreover, that those different configurations \nwill themselves likely have different impacts on the transmission system.”10  This \nobservation indicates that the Commission is looking for a calibrated and reasonable \ntransmission pricing methodology for the allocation of costs to co-located load based on \nits actual level of usage or benefits.     \nTo date, none of the comments submitted in this proceeding warrant a change to \nthe Commission’s preliminary finding that co-located load should pay for the grid services \n \n7 2009 ICC Decision, 576 F.3d at 476 (emphasis added). \n \n8 2009 ICC Decision, 576 F.3d at 476 (citing Midwest ISO Transmission Owners v. FERC, 373 \nF.3d 1361, 1368 (D.C. Cir. 2004). \n \n9 Id. (emphasis added). \n \n10 Order at P 76."},{"page":6,"startToken":1587,"endToken":1884,"text":"6 \nthat it uses or from which it benefits.  PJM’s March 24, 2025 filing identifies eight \noptions; for each option, PJM proposes varying levels of charges for transmission and/or \nancillary services depending upon the use of the grid.  Specifically, PJM’s filing proposes \ntwo BTM/co-location load arrangements: (i) Option 4 (co-located load with connection to \nthe grid with protections to avoid delivery of system energy to serve the load); and (ii) \nOption 5 (co-located load with connection to the grid with protections to avoid delivery of \nsystem energy to serve the load or receive back-up service from PJM with permission).  \nFor both options, because the load would not be designated as Network Load (and if there \nis no withdrawal of energy during coincident peak), PJM proposes that “traditional NTS \ncharges” would not apply but that certain ancillary services should apply.11  This appears \nto be a reasonable approach to assess charges based on the load’s actual use of the system.  \nSimilarly, Option 3 (BTMG with netting) appropriately recognizes the load’s actual use of \nthe transmission system and assesses charges based on netting.  \nIn this proceeding, to resolve the principal controversy pending before the \nCommission over the past year, the Commission needs only to apply what the Seventh \nCircuit characterized as the “unremarkable principle” of cost causation; this means that \nany transmission pricing methodology must reflect the customer’s actual use of the \ntransmission system and allocate costs based on the customer’s usage to ensure that each \ncustomer pays for the costs it imposes on the system.  This is the same netting principle \nthat the Commission approved for BTMG arrangements under the PJM Tariff more than \n \n11 See PJM’s March 24, 2025 Filing, Exhibit A, New Option 4 and New Option 5 (Options for \nService to Large Loads)."},{"page":7,"startToken":1884,"endToken":2275,"text":"7 \ntwenty years ago.12  By contrast, it is clear that a transmission pricing methodology that is \nbased the customer’s gross load without any consideration for actual use of the \ntransmission system would be unjust and unreasonable and violative of cost causation \nprinciples.  \nB. \nThe Commission Should Ensure That Any Ruling Should Not Adversely \nImpact BTMG Customers, And Any Disparate Treatment of BTM Load \nWould Be Unjustified and Unduly Discriminatory. \nAs PSE&G explained in its initial comments, there are a number of customers in \nPSE&G’s service territory and across the PJM region that have BTMG to meet a portion \nor all of their power needs, including universities, industrial customers, pharmaceutical \ncompanies and rooftop solar customers.13  Under the PJM Tariff, those customers are \nallowed to net their BTMG against their Network Load for purposes of paying \ntransmission and other charges.  In approving these BTMG provisions, the Commission \napplied cost causation principles by recognizing that BTMG customers use the PJM grid \nto a lesser degree and should be responsible for paying transmission charges based on \ntheir actual or net use of the system.14  Importantly, the Commission explained that the \n \n12 In approving the BTMG provisions in the PJM Tariff, the Commission found emphasized that \nthe BTMG tariff provisions would “encourage qualifying entities with behind the meter generation \nto reduce their use of the PJM transmission system” and would allocate costs based on the \ncustomer’s “actual use of the PJM’s system . .  .” and this is “consistent with the principle of \ncost causation.”  See PJM Interconnection, L.L.C., 107 FERC 61,113 at P 17 (emphasis added). \n \n13 See PSE&G’s March 24, 2025 Show Cause Response at 2, 18.  \n14 See PJM Tariff, 34.22 and 34.33.  See also PJM Manual 14D, Appendix A at p. 179 (allowing \nBTMG customers to benefit from their reduced usage of the transmission system by “allowing \nsuch generation to net for the purposes of calculating transmission, capacity, ancillary services, \nand administrative fee charges.”).  To reflect that there is no use of the transmission system by \nBTMG arrangements and that customers do not need to pay transmission charges for load served \nby BTMG arrangements (either in whole or in part), the PJM Tariff specifically provides that the \nload of a network customer “does not include the load served by operating Behind the meter \nGeneration.”"},{"page":8,"startToken":2275,"endToken":2552,"text":"8 \nBTMG provisions in the PJM Tariff (and the netting approach) would encourage loads to \nreduce their use of the PJM transmission system and consequently the need for new \ntransmission facilities.  The Commission’s longstanding policy is to encourage BTMG co-\nlocation arrangements to reduce use of the transmission system and the need for new \ntransmission facilities to be constructed.  This paradigm benefits all transmission \ncustomers.  In this proceeding, the Commission should ensure that customers who have \nBTMG or onsite generation are not negatively impacted by any new rules that the \nCommission may require.   \nIn addition, as relevant to this proceeding, co-located BTM load arrangements use \nthe transmission system in the same way as BTMG customers.  Specifically, both \narrangements involve load and generation co-locating at the same site.  This results in a \nsimilar reduced use of the transmission system and a reduced need for transmission \nupgrades.15  As such, based on the Commission’s comparability principles, both \narrangements should be treated in the same manner and pay for transmission services \nbased on their actual system usage (i.e., based on net use of the transmission system).  To \ntreat BTM co-located load and BTMG differently would be improper, unjust and \nunreasonable and unduly discriminatory under the Federal Power Act.  \nC. \nThe Commission Should Provide Flexibility and Optionality to Support \nFuture Co-Location Arrangements \nThere is universal recognition of the importance of data centers to the economic \ndevelopment and national security in the United States.  Data centers are part of today’s \n \n15 See PSE&G’s March 24, 2025 Show Cause Answer at 14-16 (discussing that co-located loads \nand BTMG have similar reduced power flow or impact on transmission in the same way)."},{"page":9,"startToken":2552,"endToken":2858,"text":"9 \nmodern life, and virtually everyone is using services provided by data centers.16  During \nthe November 1, 2024 Technical Conference, Chairman Christie stated that the “reality” is \nthat “we all live life online” and “data center load growth is just part of modern life, and \nwe have to deal with it.”17  Chairman Christie added “we want to serve data centers,” and \n“data centers under the principle of universal service have a right to be served.”18 \nTo foster data center development and to maintain U.S. leadership in this \ntransformative industry, it is paramount that the Commission take action to reduce any \nregulatory barriers within its jurisdiction that may hinder their development.19  \nImportantly, the Commission should provide data centers with the flexibility and \noptionality to select a configuration that best fits their particular circumstances and needs.  \nPSE&G appreciates PJM’s efforts and thoughtfulness in identifying and developing a \nmenu of options that may be available to data centers (there could be more), including two \nBTM/co-location load arrangements (Option 4 and Option 5).  Importantly, for both BTM \noptions, to reflect a reduced use of the grid, PJM reasonably proposes that the load pays \n \n16 Routine, everyday uses of data centers include internet searches, social media, streaming \nservices, email services, and on-line shopping/e-commerce transactions.  \n17 November 1, 2024 Technical Conference, Transcript at 11. \n \n18 Id. \n \n19 The Commission’s longstanding policy is to remove regulatory barriers and to promote \ncustomer choice and competition.  See, e.g., Participation of Distributed Energy Resource \nAggregations in Markets Operated by Regional Transmission Organizations and Independent \nSystem Operators, Order No. 2222, 172 FERC ¶ 61,247 (2020) (the Commission amending its \nregulations to remove barriers to the participation of distributed energy resource aggregations in \nthe capacity, energy, and ancillary service markets operated by Regional Transmission \nOrganizations and Independent System Operators.”)."},{"page":10,"startToken":2858,"endToken":3207,"text":"10 \nfor ancillary services, but not NITS.20  On the other hand, PSE&G does not agree with \nPJM’s view that Option 3 (Existing BTMG with netting) does not or should not apply to \nco-located load arrangements.  As discussed above, there is no meaningful distinction \nbetween BTMG and BTM load given that both configurations involve generation and load \nco-located and adjacent to one another, resulting in a reduced use or impact on the power \ngrid in a comparable manner.21   \nD. \nThe Commission Should Expeditiously Complete this Proceeding and \nEstablish a Concrete Time Frame for the Implementation of Final Rules \nGoverning Co-Location Arrangements.  \nOver the past year, there has been significant uncertainty with respect to the rules \nthat would apply to co-location arrangements, with multiple dockets pending before the \nCommission.  While there have been a significant number of comments submitted \nexpressing a wide range of perspectives, the key issue before the Commission comes \ndown to a basic transmission ratemaking question – i.e., to what extent do co-located load \narrangements use or benefit from the transmission system, and if so, what level of \ntransmission or ancillary charges should apply?22  In the Show Cause Order, the \n \n20 See PJM’s March 24, 2025 Filing, Exhibit A, New Option 4 and New Option 5 (Options for \nService to Large Loads). \n \n21 See November 1 Technical Conference Transcript at 14 (Commissioner Rosner stating that \n“siting generation near load reduce system costs” and the “physics” of BTMG and BTM load “are \nkind of – they kind of work the same.”). \n \n22 To resolve this issue, the Commission simply needs to apply the well-established and \n“unremarkable” principle of cost causation.  Even though certain other issues have been raised in \nthis proceeding (such as reliability and resource adequacy), those issues apply equally to both co-\nlocation and front of the meter large load additions.  For instance, at Paragraph 85 of the Show \nCause Order, the Commission stated, “we recognized, as does PJM, that these concerns, are not \nnecessarily unique to co-location arrangements and that significant load growth more generally \nmay generally raise many of the same concerns.”"},{"page":11,"startToken":3207,"endToken":3342,"text":"11 \nCommission established an accelerated schedule for the submission of initial and reply \ncomments, as well as a commitment to issue a decision promptly.23  The time has come \nfor the Commission to act to provide clarity and guidance as the “rules of the road” with \nrespect to co-location arrangements.  Here, PSE&G agrees with PJM that “[w]hat PJM \nand the industry need now is Commission guidance on a path forward based on the record \ndeveloped in this proceeding.” 24  Accordingly, PSE&G urges the Commission to \ncomplete its analysis and issue an order as soon as possible. \n \n \n \n23 See Show Cause Order at P 90 (“we estimate that we would be able to issue our decision within \napproximately three months of the filing of Tariff revisions.”). \n \n24 PJM’s March 24 Answer at 4-5."},{"page":12,"startToken":3342,"endToken":3487,"text":"12 \nIII. \nCONCLUSION  \nFor the reasons discussed herein, the Commission should expeditiously issue a \ndecision that provides timely and needed clarity with respect to co-located load rules and \nthat leads to a result that is (i) consistent with cost causation principles; (ii) avoids \nharming impacting existing BTMG customers in PJM and treats BTM load in a non-\ndiscriminatory manner; (iii) provides for regulatory flexibility and optionality to support \ndata center development; and (iv) establishes a concrete schedule for the implementation \nof final co-location rules.  \n \n \n \n \n \n \nRespectfully submitted,  \n \nJodi L. Moskowitz \nVice President, Regulatory, Deputy \nGeneral Counsel and RTO Strategy \nOfficer \nPSEG Services Corp. \n80 Park Plaza, T-20 \nNewark, NJ 07102 \n(973) 430-6409 \nJodi.Moskowitz@pseg.com \n \n \n \n/s/ Viet H. Ngo   \nViet H. Ngo \nAssociate Counsel – Federal Regulatory \nPSEG Services Corporation \n601 New Jersey Ave, NW Suite 310 \nWashington, DC 20001 \n(202) 460-9356 \nViet.Ngo@pseg.com"},{"page":13,"startToken":3487,"endToken":3534,"text":"CERTIFICATE OF SERVICE \n \nI hereby certify that I have this day served the foregoing document upon each \nperson designated on the official service list compiled by the Secretary in the proceeding.  \nDated at Newark, New Jersey this 23rd day of May, 2025. \n/s/ Robert Gardinor \n \n \nRobert Gardinor"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":3,"endAt":3,"startToken":0,"endToken":663},{"p":3,"at":3,"title":"I. MOTION FOR LEAVE TO ANSWER","method":"printed heading","endPage":3,"endAt":468,"startToken":663,"endToken":734},{"p":3,"at":468,"title":"II. ANSWER","method":"printed heading","endPage":4,"endAt":335,"startToken":734,"endToken":1007},{"p":4,"at":335,"title":"A. Any Transmission Pricing Rules Governing Co-Location","method":"printed heading","endPage":7,"endAt":279,"startToken":1007,"endToken":1927},{"p":7,"at":279,"title":"B. The Commission Should Ensure That Any Ruling Should Not Adversely","method":"printed heading","endPage":8,"endAt":1369,"startToken":1927,"endToken":2481},{"p":8,"at":1369,"title":"C. The Commission Should Provide Flexibility and Optionality to Support","method":"printed heading","endPage":10,"endAt":476,"startToken":2481,"endToken":2938},{"p":10,"at":476,"title":"D. The Commission Should Expeditiously Complete this Proceeding and","method":"printed heading","endPage":12,"endAt":4,"startToken":2938,"endToken":3343},{"p":12,"at":4,"title":"III. CONCLUSION","method":"printed heading","endPage":13,"endAt":0,"startToken":3343,"endToken":3487},{"p":13,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":13,"endAt":296,"startToken":3487,"endToken":3534}]}