{"document":{"slug":"rec-20250627-5146","title":"Motion For Leave to Answer and Limited Answer of the Indicated PJM Transmission Owners to Constellation Energy Generation, LLC's 06/12/2025 Answer","issued":"2025-06-27","accession":"20250627-5146","docket":"EL25-49-000","group":"PJM co-location compliance","filer":"Exelon CorporationAmerican Electric Power Service CorporationAMP Transmission, LLC ,City of Cleveland, Department of Public Utilities, Division ,City of Hamilton, OH ,Duke Energy Corporation ,Wabash Valley Power Association, Inc. ,The FirstEnergy Transmission Companies ,Southern Maryland Electric Cooperative, Inc. ,East Kentucky Power Cooperative, Inc. ,Old Dominion Electric Cooperative ,PPL Electric Utilities Corporation ,Rockland Electric Company ,UGI Utilities Inc. ,","kind":"answer","file":"sources/filings/text/20250627-5146_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20250627-5146","tier":"record","sha256":"7c8577ffe4045867d06a4204969daf88aa4866934a60dc1a198d91aba4d12d4f","pages":11,"tokens":3581,"emptyPages":[],"textThemes":["colo"]},"pages":[{"page":1,"startToken":0,"endToken":358,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \nPJM Interconnection, L.L.C., et al. \n \n) \nDocket No. EL25-49-000 \nLarge Loads Co-Located at Generating \nFacilities \n) \nDocket No. AD24-11-000 \nConstellation Energy Generation, LLC \nv. \nPJM Interconnection, L.L.C. \n) \n) \n) \nDocket No. EL25-20-000 \n(consolidated) \nMOTION FOR LEAVE TO ANSWER AND LIMTED ANSWER \nOF THE INDICATED PJM TRANSMISSION OWNERS \nPursuant to Rules 212 and 2131 of the Rules of Practice and Procedure of the Federal \nEnergy Regulatory Commission (“FERC” or “Commission”) and the Commission’s show cause \norder,2 the Indicated PJM Transmission Owners (hereinafter, “Indicated TOs”)3 submit this \nMotion for Leave to Answer and Limited Answer to the June 12, 2025 Answer of Constellation \nEnergy Generation, LLC (“Constellation”) made in the above-captioned dockets.  Under Rule \n1\n18 C.F.R. §§ 385.212, 385.213 (2025). \n2\nPJM Interconnection, L.L.C., 190 FERC ¶ 61,115, at Ordering Paragraph (D) (2025). \n3\nThe Indicated PJM Transmission Owners include: American Electric Power Service Corporation, on behalf of \nAppalachian Power Company, Indiana Michigan Power Company, Kentucky Power Company, Kingsport Power \nCompany, Ohio Power Company, Wheeling Power Company, AEP Appalachian Transmission Company, Inc., \nAEP Indiana Michigan Transmission Company, Inc., AEP Kentucky Transmission Company, Inc., AEP Ohio \nTransmission Company, Inc., and AEP West Virginia Transmission Company, Inc.; AMP Transmission, LLC; \nCity of Cleveland, Department of Public Utilities, Division of Cleveland Public Power; City of Hamilton, OH; \nDuke Energy Corporation on behalf of its affiliates Duke Energy Ohio, Inc., Duke Energy Kentucky, Inc., and \nDuke Energy Business Services LLC; East Kentucky Power Cooperative; Exelon Corporation, on behalf of \nAtlantic City Electric Company, Baltimore Gas and Electric Company, Commonwealth Edison Company, \nCommonwealth Edison Company of Indiana, Inc., Delmarva Power & Light Company, PECO Energy Company, \nand Potomac Electric Power Company; FirstEnergy Service Company, as agent for its affiliates American \nTransmission Systems, Incorporated, Jersey Central Power & Light Company, Mid-Atlantic Interstate \nTransmission LLC, Keystone Appalachian Transmission Company, The Potomac Edison Company, \nMonongahela Power Company and Trans-Allegheny Interstate Line Company (collectively, the “FirstEnergy \nTransmission Companies”); Old Dominion Electric Cooperative; PPL Electric Utilities Corporation; Rockland \nElectric Company; Southern Maryland Electric Cooperative, Inc.; UGI Utilities Inc; and Wabash Valley Power \nAssociation, Inc."},{"page":2,"startToken":358,"endToken":743,"text":"2 \n \n213(a)(2)4 of the Commission’s Rules of Practice and Procedure, the Commission may authorize \nan answer to an answer.  Good cause exists to accept this answer because it ensures a further \ndeveloped record for the Commission’s decision making.5 \nConstellation continues to argue points that the record does not support.  For example, the \nallegation that several parties would like clarifications to enable alternatives does not justify \ndiscarding the PJM Open Access Transmission Tariff (“PJM Tariff”) as unjust and unreasonable.6  \nThe Indicated TOs have explained at length why these alternative proposals would harm, rather \nthan help, the ability of PJM Interconnection, L.L.C. (“PJM”) to accommodate co-located \ninterconnection arrangements.7  In response, no party has demonstrated that it has been unable to \nreceive service under the existing PJM Tariff or that it is experiencing an undue delay for a request \nfor service under the PJM Tariff.   \nIndeed, recent events plainly indicate that existing types of service can be used.  On \nNovember 1, 2024 in Docket No. ER24-2172, the Commission rejected proposed amendments to \nthe \nInterconnection \nService \nAgreement \namong \nPJM, \nSusquehanna \nNuclear, \nLLC \n(“Susquehanna”), and PPL Electric Utilities Corporation that would have increased the amount of \n \n4  \n18 C.F.R. § 385.213(a)(2). \n5  \nSee, e.g., PJM Interconnection, L.L.C., 191 FERC ¶ 61,112 at P 29 (2025) (accepting “answers because they . . . \nprovided information that assisted [the Commission] in [its] decision-making process”). \n6  \nConstellation Answer at 1, 3.  Notably, Constellation’s representation that “[n]early every party in this \nproceeding agrees” with its position is simply false.  Constellation attempts to support this erroneous claim by \nciting to its own May 8, 2025 Answer in this proceeding.  Yet, Constellation’s May 8, 2025 Answer identified \nonly seven intervenors—seven out of the more than 40 intervenors in Docket No. EL25-20 alone—that agree \nwith Constellation’s position.  \n7  \nSee Answer of the Indicated PJM TOs to the Order Instituting the Proceeding Under Section 206 of the Federal \nPower Act and Consolidated with Other Proceedings (Mar. 24, 2025); see also Answer of the Indicated PJM \nTOs (Apr. 23, 2025); see also Answer of the Indicated PJM TOs to the Motion to Stay Proceedings (May 7, \n2025); see also Motion for Leave to Answer and Answer of the Indicated PJM TOs (June 3, 2025)."},{"page":3,"startToken":743,"endToken":1061,"text":"3 \n \nco-located load at that facility from 300 MW to 480 MW.8  Susquehanna is owned by Talen Energy \nCorporation (“Talen”).  On June 11, 2025, after months of failure by various parties to demonstrate \nthat the existing PJM Tariff is unjust and unreasonable, Talen announced that it has “expanded its \nexisting nuclear energy relationship with Amazon to provide carbon-free energy from \nSusquehanna to Amazon Web Services (“AWS”) data centers in the region.”9  Significantly, Talen \nstated that   \n[t]he existing Susquehanna co-located load arrangement between Talen and \nAmazon will transition to a “front-of-the-meter” arrangement after the completion \nof transmission reconfigurations expected in the Spring of 2026, concurrent with \nSusquehanna’s refueling outage.  Under the terms of the new agreement, \nSusquehanna will provide its carbon-free power to the PJM grid, Talen will act as \nthe retail electric generation supplier to Amazon, and PPL Electric Utilities (“PPL”) \nwill be responsible for transmission and delivery.10 \n \nIn this same announcement, Amazon references its $20 billion investment in data center campuses \nin the Commonwealth of Pennsylvania.11  The front of the meter configuration, consistent with the \nexisting PJM Tariff, has not stopped this significant investment, “the largest private sector \ninvestment in state history,” from moving forward.12  The PJM Tariff will not stop other such \ninvestments.    \nUltimately, Constellation’s preference for alternative rate structures is not evidence that \nthe existing forms of transmission service are unjust and unreasonable.  It remains true that section \n \n8  \nSee Order Rejecting Amendments to Interconnection Service Agreement, 189 FERC ¶ 61,078, Docket No. \nER21-2172 (Nov. 1, 2024); order on reh’g, Order Addressing Argument on Rehearing and Granting \nClarification, in Part, 191 FERC ¶ 61,025 (Apr. 10, 2025). \n9  \nSee Talen Energy Expands Nuclear Energy Relationship with Amazon, Talen, June 11, 2025, available at \nhttps://ir.talenenergy.com/node/8671/pdf (“Talen Press Release”).  The Talen Press Release is appended hereto \nas Attachment A.     \n10  Id. \n11  Id. \n12  Id."},{"page":4,"startToken":1061,"endToken":1384,"text":"4 \n \n206 of the Federal Power Act (“FPA”), requires a finding that the existing rate or charge is unjust \nand unreasonable before alternatives may be considered.13  Only after a successful showing that \nthe existing rate is unjust and unreasonable, may the Commission order a replacement rate.14  And, \n“[t]he burden of proving an unjust or unreasonable rate rests with the party that initiated the \nproceeding—that is, the Commission or the third-party complainant.”15  Even now, neither the \nCommission nor any of the parties supporting the initiation of this FPA section 206 proceeding \nhave demonstrated that the existing PJM Tariff is unjust and unreasonable.  Consequently, as the \nIndicated TOs have consistently stated, the only action that may lawfully be taken is to terminate \nthis proceeding.  Doing so promptly would ensure that interested stakeholders are able to continue \noperating under the same tariff provisions that have already successfully encouraged significant \ninvestments like the one described in the Talen Press Release.  \nFor the reasons stated above, and in the prior comments and answers of the Indicated TOs, \nthe Commission should terminate this show cause proceeding, affirming that the existing PJM \nTariff and existing transmission service categories remain just and reasonable. \n \n \n13  16 U.S.C. § 824e(a); Emera Me. V. FERC, 854 F.3d 9, 25 (D.C. Cir. 2017) (holding that “[w]ithout a showing \nthat the existing rate is unlawful,” the Commission “has no authority to impose a new rate”). \n14  16 U.S.C. § 824e(a); see also N.J. Bd. of Pub. Utils. v. FERC, 744 F.3d 74, 94–95 (3d Cir. 2014) (“[U]nder § 206, \nFERC may change a rate in response to a complaint or on its own motion, only if the moving party demonstrates \nthat the existing rate is unjust and unreasonable and the proposed alternative is just and reasonable.”). \n15  Pub. Citizen, Inc. v. FERC, 7 F.4th 1177, 1183 (D.C. Cir. 2021)."},{"page":5,"startToken":1384,"endToken":1592,"text":"5 \n \nRespectfully submitted, \n \n \n \n/s/ William Sauer \nWilliam Sauer \nVice President, Federal Regulatory Affairs  \nExelon Corporation  \n701 Ninth St. N.W.  \nWashington, DC 20001  \nTelephone: 202-868-7499  \nEmail: william.sauer@exeloncorp.com   \n/s/ Max Minzner \n \nMax Minzner \nVice President and Deputy General Counsel \nExelon Corporation \n701 Ninth St. N.W.  \nWashington, DC 20001  \nTelephone: 202-934-4740 \nEmail: max.minzner@exeloncorp.com \n \n \nOn behalf of Exelon Corporation \n \n/s/ Jessica Cano \nJessica Cano \nAssistant General Counsel – Regulatory East \nAmerican Electric Power Service Corporation \n1 Riverside Plaza  \nColumbus, OH 43215 \nTelephone: 614-716-2921  \nEmail: jacano@aep.com \n \n/s/ Lisa G. McAlister \nLisa G. McAlister \nAMP Transmission, LLC \n1111 Schrock Road, Suite 100 \nColumbus, Ohio 43229 \nTelephone: 614-540-6400 \nEmail: lmcalister@amppartners.org \n \nOn behalf of American Electric Power \nService Corporation \n \nOn behalf of AMP Transmission, LLC \n \n/s/ Martin J. Keane \nMartin J. Keane \nDirector of Public Utilities \nCleveland Public Power \n1300 Lakeside Ave. \nCleveland, OH 44114 \nTelephone: 216-664-2444 ext. 75604 \nEmail: martin_keane@clevelandwater.com \n \n/s/Debra D. Roby \nDebra D. Roby \nWashington Energy Law LLP \n900 17th Street N.W., Suite 500-A \nWashington, D.C. 20006 \nTelephone: 703-785-9270 \nEmail: droby@washingtonenergylaw.com \n \nOn behalf of City of Cleveland, Department of \nPublic Utilities, Division of Cleveland Public \nPower \n \nOn behalf of the City of Hamilton, OH"},{"page":6,"startToken":1592,"endToken":1825,"text":"6 \n \n/s/ Damon L. Krieger \nDamon L. Krieger \nGroup Vice President, Legal, Strategy, and \nSustainability, and Deputy General Counsel \nSouthern Maryland Electric Cooperative, Inc. \n15035 Burnt Store Road \nP.O. Box 1937 \nHughesville, Maryland 20637-1937 \nTelephone: 301-274-4323 \nEmail: Damon.Krieger@SMECO.coop \n \n/s/ Molly Suda  \nMolly Suda \nAssociate General Counsel \nAnnelise Rickert  \nFederal Government Affairs Director \nDuke Energy Corporation \n1301 Pennsylvania Ave NW, Suite 200 \nWashington, DC 20004 \nTelephone: 202-824-8011 \nEmail:  molly.suda@duke-energy.com  \nAnnelise.rickert@duke-energy.com         \n   \nOn behalf of Southern Maryland Electric \nCooperative \n \nOn behalf of Duke Energy \n \n/s/ Jeremy L. Fetty \n \nJeremy L. Fetty \nParr Richey \n251 N. Illinois, Suite 1800 \nIndianapolis, Indiana 46204  \nTelephone: 317-269-2500 \nEmail: j_fetty@wvpa.com \n \n \n/s/   Amanda P. Parker \nAmanda P. Parker \nAttorney \nFirstEnergy Service Company \n76 South Main Street \nAkron, OH 44308 \nTelephone: (330) 384-4592 \nEmail: aparker@firstenergycorp.com  \n \nOn behalf of Wabash Valley Power \nAssociation, Inc. \n \nOn behalf of The FirstEnergy Transmission \nCompanies \n \n/s/ Denise R. Foster Cronin \nDenise R. Foster Cronin \nVice President, Federal and RTO Regulatory \nAffairs \nEast Kentucky Power Cooperative, Inc. \n4775 Lexington Road, P.O. Box 707 \nWinchester, KY 40392-0707 \nTelephone: 859-745-9615 \nEmail: denise.cronin@ekpc.coop \n \n/s/ Daniel E. Frank                  \nDaniel E. Frank \nKelly Cuthbertson \nEversheds Sutherland (US) LLP \n700 Sixth St., N.W., Suite 700 \nWashington, DC 20001-3980 \nTelephone: 202-383-0100 \nEmail:  \ndanielfrank@eversheds-sutherland.com \nkellycuthbertson@eversheds-sutherland.com \n \n \n \nOn Behalf of East Kentucky Power \nCooperative, Inc."},{"page":7,"startToken":1825,"endToken":2020,"text":"7 \n \n/s/ Adrienne E. Clair \nAdrienne E. Clair \nThompson Coburn LLP \n1909 K Street, N.W., Suite 600 \nWashington, D.C.  20006-1167 \nTelephone: 202-585-6900 \nEmail: aclair@thompsoncoburn.com \n \n/s/ Steve Nadel \nSteven M. Nadel \nSenior Counsel \nPPL Services Corp.  \n645 Hamilton Street, Suite 601 \nAllentown, PA 18101 \nTelephone: 610-774-4775   \nEmail: SMNadel@pplweb.com \n \nOn behalf of Old Dominion Electric \nCooperative \n \nOn behalf of PPL Electric Utilities Corp. \n \n/s/David Burns  \nDavid Burns  \nSenior Manager,  \nFERC Policy & Regulatory Affairs  \nConsolidated Edison Company of New York, \nInc.   \n4 Irving Place \nNew York, NY 10003   \nTelephone: 571-678-9152  \nEmail: burnsd@coned.com \n/s/Joshua Kirstein \nJoshua A. Kirstein  \nSenior Attorney  \nLaw Department \nConsolidated Edison Company of New York, \nInc.  \n4 Irving Place, 18th Floor  \nNew York, NY 10003  \nTelephone: 929-656-5971 \nEmail: kirsteinj@coned.com \n \n \nOn behalf of Rockland Electric Company \n \n/s/ Lindsay Berkstresser \nLindsay Berkstresser \nCounsel – Energy & Regulatory \nUGI Corporation \n500 North Gulph Road \nKing of Prussia, PA 19406 \nTelephone: 717-504-9925 \nEmail: berkstresserl@ugicorp.com \n \n/s/ Richard P. Bonnifield \nRichard P. Bonnifield \nHusch Blackwell \n1801 Pennsylvania Avenue, NW, \nSuite 1000 \nWashington, DC 20006-3606 \nTelephone: 202-243-8844 \nEmail: \nrichard.bonnifield@huschblackwell.com \n \n \nOn behalf of UGI Utilities Inc. \nJune 27, 2025"},{"page":8,"startToken":2020,"endToken":2022,"text":"Attachment A"},{"page":9,"startToken":2022,"endToken":2957,"text":"Talen Energy Expands Nuclear Energy Relationship with Amazon\nJune 11, 2025\nTalen enters power purchase agreement for 1,920 megawatts of carbon-free electricity at full quantity to support Amazon operations, and\nexplore SMR technology\nHOUSTON, June 11, 2025 (GLOBE NEWSWIRE) -- Talen Energy Corporation (“Talen,” “we,” or “our”) (\nNASDAQ: TLN), an independent power\nproducer dedicated to powering the future, announced today that it has expanded its existing nuclear energy relationship with Amazon to provide\ncarbon-free energy from Talen’s Susquehanna nuclear power plant to Amazon Web Services (“AWS”) data centers in the region.\nUnder the terms of a new power purchase agreement (“PPA”), Talen will supply electricity to Amazon for operations that support AI and other cloud\ntechnologies at Amazon’s data center campus adjacent to Susquehanna, with the ability to deliver to other sites throughout Pennsylvania. Talen and\nAmazon will also explore building new Small Modular Reactors (“SMRs”) within Talen’s Pennsylvania footprint and pursue expanding the nuclear\nplant’s energy output through uprates, with the intent to add net-new energy to the PJM grid.\nUnder the expanded PPA, at the full contract quantity, Talen will provide Amazon with 1,920 megawatts of carbon-free nuclear power through 2042,\nwith options to further extend its duration. The power delivery schedule will ramp over time, expecting to achieve the full volume no later than 2032,\nwith the potential to meaningfully accelerate. This long-term transaction will significantly decrease Talen’s market risk and minimize its reliance on the\nFederal nuclear production tax credit.\n“Our agreement with Amazon is designed to provide us with a long-term, steady source of revenue and greater balance sheet flexibility through\ncontracted revenues. We remain a first mover in this space and intend to continue to execute on our data center strategy,” said Talen President and\nChief Executive Officer Mac McFarland. “Talen is well-positioned to support Amazon’s energy needs as it invests further in the Commonwealth of\nPennsylvania.”\n“Amazon is proud to help Pennsylvania advance AI innovation through investments in the Commonwealth’s economic and energy future,” said AWS\nVice President of Global Data Centers Kevin Miller. “That’s why we’re making the largest private sector investment in state history – $20B – to bring\n1,250 high-skilled jobs and economic benefits to the state, while also collaborating with Talen Energy to help power our infrastructure with carbon-free\nenergy.”\nThe existing Susquehanna co-located load arrangement between Talen and Amazon will transition to a “front-of-the-meter” arrangement after the\ncompletion of transmission reconfigurations expected in the Spring of 2026, concurrent with Susquehanna’s refueling outage. Under the terms of the\nnew agreement, Susquehanna will provide its carbon-free power to the PJM grid, Talen will act as the retail electric generation supplier to Amazon,\nand PPL Electric Utilities (“PPL”) will be responsible for transmission and delivery.\n“PPL Electric Utilities is investing in the resiliency of its transmission system so we can better serve our customers, meet growing energy demands,\nand ensure power is delivered reliably,” said Christine Martin, president of PPL Electric Utilities. “Connecting large load customers like data centers to\nour transmission system helps lower the transmission component of energy bills for all customers, as large load customers pay significant\ntransmission charges on our network. We’re excited to be part of Amazon’s broader investment in Pennsylvania and look forward to the positive\neffects it can have for our customers and the local economy.”\nStrengthening Pennsylvania’s Energy Future\nThe Talen and Amazon relationship will help safe, reliable nuclear energy continue to be generated at Susquehanna for years to come, maintaining its\ncontributions to the local community and supporting Pennsylvania’s energy future while also helping to power Amazon’s AI innovation investments in\nthe Commonwealth. Talen is a major employer and significant local taxpayer, and the agreement supports the jobs of more than 900 employees\ncurrently working at the Susquehanna facility, as well as new construction jobs.\nWhile Pennsylvania maintains a position as a net energy exporter, producing more power than the Commonwealth requires, Talen’s strategic\npartnership with Amazon will help send the necessary market signals to spur new investment in additional generation and grid modernization within\nthe Commonwealth.\nPennsylvania Policy and Stakeholder Support\nThe following key policymakers and stakeholders expressed their support for the transaction.\n“This partnership between Talen Energy and Amazon taps into Pennsylvania’s strengths as a national energy leader and will power the largest\neconomic development project in Commonwealth history – creating good-paying jobs, growing our economy, and ultimately adding more power to the\nPJM energy grid,” said Governor Josh Shapiro. “I am an all-of-the-above energy governor, and as part of my economic development plan, my\nAdministration is working to generate even more power in the Commonwealth – with more power comes more national security, more independence,\nand more economic freedom. My Administration is going to continue to bring people together to attract new investment to Pennsylvania, and we stand\nready to work with Talen Energy and its partners to review permits for this project as efficiently as possible.” – Pennsylvania Governor Josh Shapiro\n(D) \n“Talen and Amazon’s expanded nuclear energy relationship not only strengthens the future of the Susquehanna plant and maintains its contributions\nto the community, but also helps to support the development of AI technology in Pennsylvania. Adding data centers that support AI strengthens\nAmerican national security, provides a wide variety of economic opportunities, and positions the Commonwealth, and the U.S., as a leader in AI\ninnovation.” –  U.S. Senator Dave McCormick (R-PA)\n“I’m pleased about the economic development opportunities the Commonwealth and the Ninth District will receive thanks to Talen and Amazon’s\nlong-term arrangement. Our communities will not only benefit from the economic development that will occur, but also from the contributions that the"},{"page":10,"startToken":2957,"endToken":3535,"text":"Susquehanna plant provides as a large employer within the district. Thank you, Talen, Amazon and PPL for working together to bring these benefits to\nPennsylvania.” – U.S. Representative Dan Meuser (R-PA), who represents Pennsylvania’s 9 th U.S. Congressional District\n“IBEW Local 1600 strongly supports the new transaction. Our members, friends, and families all benefit from the jobs and community growth this\ninvestment in Susquehanna will bring. This sets up a great career path for young students coming out of high school or college who are looking for a\ncareer in the electrical industry.” - John “Rusty” Clausius, President, IBEW Local 1600\nInvestor Call\nTalen will host an investor call at 8:00 a.m. EDT today, Wednesday, June 11, 2025. To participate in the call, please register for the webcast via the\npage linked here. Participants can also join by phone by registering via the form linked here prior to the start time of the call to receive a conference\ncall dial-in number. For those unable to participate in the live event, a digital replay will be archived for approximately one year and available on the\nEvents page of Talen's Investor Relations website linked here.\nAbout Talen\nTalen Energy (NASDAQ: TLN) is a leading independent power producer and energy infrastructure company dedicated to powering the future. We own\nand operate approximately 10.7 gigawatts of power infrastructure in the United States, including 2.2 gigawatts of nuclear power and a significant\ndispatchable fossil fleet. We produce and sell electricity, capacity, and ancillary services into wholesale U.S. power markets, with our generation fleet\nprincipally located in the Mid-Atlantic and Montana. Our team is committed to generating power safely and reliably and delivering the most value per\nmegawatt produced. Talen is also powering the digital infrastructure revolution. We are well-positioned to capture this significant growth opportunity, as\ndata centers serving artificial intelligence increasingly demand more reliable, clean power. Talen is headquartered in Houston, Texas. For more\ninformation, visit https://www.talenenergy.com/.\nInvestor Relations:\nSergio Castro\nVice President & Treasurer\nInvestorRelations@talenenergy.com\nMedia:\nTaryne Williams\nDirector, Corporate Communications\nTaryne.Williams@talenenergy.com\nForward Looking Statements\nThis communication contains forward-looking statements within the meaning of the federal securities laws, which statements are subject to substantial\nrisks and uncertainties. These forward-looking statements are intended to qualify for the safe harbor from liability established by the Private Securities\nLitigation Reform Act of 1995. All statements other than statements of historical fact included in this communication, or incorporated by reference into\nthis communication, are forward-looking statements. Throughout this communication, we have attempted to identify forward-looking statements by\nusing words such as “anticipate,” “believe,” “continue,” “could,” “estimate,” “expect,” “forecasts,” “goal,” “intend,” “may,” “plan,” “potential,” “predict,”\n“project,” “seek,” “should,” “will,” or other forms of these words or similar words or expressions or the negative thereof, although not all forward-looking\nstatements contain these terms. Forward-looking statements address future events and conditions concerning, among other things, capital\nexpenditures, earnings, litigation, regulatory matters, hedging, liquidity and capital resources and accounting matters. Forward-looking statements are\nsubject to substantial risks and uncertainties that could cause our future business, financial condition, results of operations or performance to differ\nmaterially from our historical results or those expressed or implied in any forward-looking statement contained in this communication. All of our\nforward-looking statements include assumptions underlying or relating to such statements that may cause actual results to differ materially from\nexpectations, and are subject to numerous factors that present considerable risks and uncertainties."},{"page":11,"startToken":3535,"endToken":3581,"text":"CERTIFICATE OF SERVICE \n \nI hereby certify that I have this day served the foregoing document upon each person \ndesignated on the official service list in the above captioned dockets. \nDated at Chicago, IL this 27th  day of June, 2025. \n \n/s/ Geneva Kennedy  \nGeneva Kennedy  \nExelon Corporation"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":8,"endAt":0,"startToken":0,"endToken":2020},{"p":8,"at":0,"title":"Attachment A","method":"printed heading","endPage":11,"endAt":0,"startToken":2020,"endToken":3535},{"p":11,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":11,"endAt":295,"startToken":3535,"endToken":3581}]}