{"document":{"slug":"rec-20251020-5079","title":"Pre-Technical Conference Remarks of Jason Connell Vice President, Planning PJM Interconnection, L.L.C. re Panel 2: Ensuring Reliability with Large Loads","issued":"2025-10-20","accession":"20251020-5079","docket":"EL25-49-000","group":"PJM co-location compliance","filer":"PJM Interconnection, L.L.C.","kind":"filing","file":"sources/filings/text/20251020-5079_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20251020-5079","tier":"record","sha256":"bc9689ccd752337fdf28121c278461eb62247f70d2eb0c88c8c12eb40631e06d","pages":13,"tokens":4214,"emptyPages":[],"textThemes":["registry","credit","study"]},"pages":[{"page":1,"startToken":0,"endToken":217,"text":"UNITED STATES OF AMERICA \nFEDERAL ENERGY REGULATORY COMMISSION \n \nReliability Technical Conference  \n \n \n \nDocket No. AD25-8-000 \n \n \n \nPre-Technical Conference Remarks of Jason Connell \nVice President, Planning \nPJM Interconnection, L.L.C. \n \nPanel 2: Ensuring Reliability with Large Loads \n \n \nThank you for the opportunity to participate in today’s important panel. \n \nI am Jason Connell, Vice President of Planning at PJM Interconnection, L.L.C.  I \nhave responsibility for transmission and interconnection planning, and the resource \nadequacy planning team that prepares the PJM Region’s wholesale load forecast. \n \nI look forward to discussing PJM’s ongoing work relating to enhancing the load \nforecasting process in the PJM Region.  On this topic, I will speak to the developments \nthat Manu Asthana, PJM’s President and Chief Executive Officer, has described in his \nresponse to Chairman Rosner’s September 18, 2025 correspondence regarding load \nforecasting.   A copy of that letter is enclosed with these remarks. \n \nI also note that PJM continues to engage in the ongoing efforts of NERC’s Large \nLoads Task Force.  PJM supports this work given the recognized impacts of large loads \non the bulk electric system, and PJM appreciates that opportunities exist to clarify the \nroles and responsibilities of large loads under the NERC Functional Model.   \n \nRespectfully submitted,  \n/s/ Jason Connell  \nJason Connell \nVice President, Planning  \nPJM Interconnection, L.L.C. \n \nDated: October 17, 2025"},{"page":2,"startToken":217,"endToken":549,"text":"“ \n610.666.8980 | www.pjm.com \nManu Asthana \nPresident & CEO, PJM Interconnection \n \n2750 Monroe Blvd. \nAudubon, PA 19403 \n \nVIA ELECTRONIC DELIVERY \n \nOctober 17, 2025 \nThe Honorable David Rosner \nChairman \nFederal Energy Regulatory Commission \n888 First Street, N.E. \nWashington, D.C. 20426 \n \nDear Chairman Rosner: \nThank you for your September 18, 2025 letter regarding load forecasting processes and enhancements.  PJM \nshares the Commission’s focus on enhancing the RTO’s wholesale load forecasting tool kit to support the \nconstruction of critical energy infrastructure needed to deliver maximum ratepayer value. We appreciate your call \nto action on this complex subject. PJM will continue to collaborate with the Commission, the PJM states, Electric \nDistribution Companies and Load Serving Entities, and all other PJM stakeholders regarding this important issue.  \nWe support the continued recognition that an RTO has authority under its tariffs to prepare a wholesale load \nforecast pursuant to a reasonable methodology.1 Today, PJM’s Load Forecast Adjustment Guidelines use those \nrequested load adjustments “deemed appropriate by PJM.”2   \nWe continue to actively engage with our stakeholders on enhancements to PJM’s wholesale load forecasting \nprocess. In the first half of 2025, PJM worked with stakeholders through its Load Analysis Subcommittee to \nenhance the clarity of its load forecasting processes where adjusted loads are projected to exceed 50 MW.  \nIn September, the PJM Board of Managers started an expedited stakeholder process to address potential resource \nadequacy challenges arising from the rapid interconnection of large loads.3  Enhancements to load forecasting are \namong the key priorities of this process, and PJM is aiming to complete the stakeholder process this year.  \n \n1 See PJM Interconnection, L.L.C., 123 FERC ¶ 61,163, at P 51 (2008) (“We find that PJM has complied with Order No. 890 \n[and Principle 4: Information Exchange] because it has a reasonable methodology for providing a load forecast report.”). \n2 PJM Manual 19: Load Forecasting and Analysis, Attachment B: Load Forecast Adjustment Guidelines (PDF), at page 26.    \n3 Critical Issue Fast Path – Large Load Additions."},{"page":3,"startToken":549,"endToken":1029,"text":"October 17, 2025 \nPage 2 \n610.666.8980 | www.pjm.com \nJust last week, the PJM Board and PJM staff also met with state utility commissioners, federal regulators, and \nindustry experts at the 2025 Annual Meeting of the Organization of PJM States, Inc.  Potential load forecasting \nenhancements were discussed repeatedly across that two-day meeting. \nPJM also continues to engage with its Electric Distribution Companies and Load Serving Entities (and other \nrelevant stakeholders) to gather more granular information about their load interconnection processes and related \nstate-regulated processes in an effort to inform additional potential enhancements to PJM’s load forecasting \nefforts. I summarize updates from these various efforts below and provide specific responses to the questions in \nyour September 18 letter.  \nUpdate on PJM’s Load Analysis Subcommittee and the Development of a Load Adjustment Request \nImplementation Document \nIn the first half of 2025, PJM’s collaboration with stakeholders at the Load Analysis Subcommittee resulted in the \npreparation and publication of a Load Adjustment Request Implementation document that offers enhanced \ntransparency about PJM’s load adjustment request submission process in PJM Manual 19, Attachment B.4 This \nImplementation document speaks to the collaborative and iterative process involving Electric Distribution \nCompanies, Load Serving Entities, and PJM, and opportunities for Relevant Electric Retail Regulatory Authorities.  \nAmong other things, the Implementation document addresses load forecasting methodologies and sets forth PJM’s \nneed to receive from forecast submitters: capacity and demand values, ramp rates to reflect time until full demand \nis realized on the system, levels and details relating to electric service obligations to loads, construction \ncommitments, and other potentially relevant agreements that could help determine the likelihood projected load will \neventually come to market. The Implementation document also seeks to have submitters present PJM with \ninformation relating to new customer’s financial commitments regarding certain anticipated load interconnections. \nIn an effort to hedge against potential load forecast uncertainty, the Implementation document buckets load \ninterconnections into three categories that are assigned different probability factors for purposes of incorporating \nthese projections into the wholesale load forecast: large loads projected to come online in three years or less; large \nloads projected to come online in more than three but less than eight years; and large loads projected to come \nonline eight years and beyond. \nIt remains the case that load forecasting is grounded in statistical modeling that assesses historical load trends in \nthe context of other variables, including economic and demographic factors, electric usage trends and weather. \nStatistical models, however, may not fully account for trends that are not directly tied to one of these statistically \nderived factors. PJM’s approach to load forecasting, including the methodology in Manual 19, Attachment B, as \nfurther clarified by the Implementation document, helps identify additional inputs that statistical models may not \notherwise fully reflect.  \n \n4 PJM Interconnection, L.L.C., Load Adjustment Request Implementation (PDF), PJM Resource Adequacy Planning \nDepartment (July 1, 2025; revised Aug. 26, 2025)."},{"page":4,"startToken":1029,"endToken":1502,"text":"October 17, 2025 \nPage 3 \n610.666.8980 | www.pjm.com \nUpdate on PJM’s Load Forecasting Efforts in the Expedited Stakeholder Process \nThe issue charge for the expedited large load additions stakeholder process is focused on, “[e]xplor[ing] potential \nsolutions that include further changes to the Load Forecast process targeting resource adequacy challenges to the \nextent they are narrowly focused, such as [Large Load Additions] included in the load forecast (Manual 19, \nAttachment B), state roles in the large load adjustment process, and load bid into the auction, with objective for \nconsensus by EOY 2025.” There is also an effort to enhance transparency around forecasts, assumptions, \nparticipation, methodologies, interconnections, supply arrangements and costs where possible and practical.5   \nOn October 1, 2025, PJM presented an updated proposal in response to considerable feedback seeking \nimprovements in load forecasting processes.6 Although not finalized and the subject of ongoing discussion and \nrefinement, PJM proposed enhancements to its existing processes to reduce the potential for speculative load, \nincluding: \n• \nThe addition of a step for Relevant Electric Retail Regulatory Authorities to have an opportunity to review \nand provide feedback on large load adjustments prior to PJM’s finalization of the wholesale load forecast. \nAs I discuss below, some states appear to be taking steps to engage in these types of activities.   \n• \nFurther formalization of criteria to assess projected load’s degree of commitment to coming in service to \nhelp accurately capture the reliability landscape and reasonably cabin potential ratepayer exposure, to build \nupon the enhancements already reflected in the Implementation document described above  \n• \nDevelopment of a new required data point in PJM’s annual load adjustment template that would require \nsubmitters to inquire with their subject customers about whether any load interconnection requests received \nare duplicative with other such requests made to interconnect large load either within or outside of the PJM \nregion, such that only a subset of the requests are expected to actually achieve commercial operation. If any \nduplicative requests are identified, the submitters are required to provide the amount of megawatts that \nhave been determined to be duplicative in their submission. \n• \nConsideration of financial security requirements from large load customers (or other responsible entities) for \nthe capacity required to be purchased in a given Reliability Pricing Model auction, whether such \nrequirements arise from state law or retail tariffs. PJM will continue to evaluate with stakeholders \nopportunities to leverage existing templates to enhance load forecasting in our region.  \nPJM is presently receiving additional stakeholder packages and proposals and remains committed to ongoing \ncollaboration with the Commission, the PJM states, and all impacted stakeholders on identifying and implementing \nfurther enhancements to PJM’s load forecasting processes.  \n \n5 Changes to PJM’s load forecast schedule or an overhaul of the entire load forecast process are presently not in scope of the \nissues being worked.  \n6 Large Load Additions CIFP Update (PDF)."},{"page":5,"startToken":1502,"endToken":1942,"text":"October 17, 2025 \nPage 4 \n610.666.8980 | www.pjm.com \nPJM’s Answers to the Questions in the September 18 Letter \nTurning to the specific questions in your September 18 letter, I offer the following responses. PJM looks forward to \ncontinued dialogue with you, other Commissioners and Commission staff on these matters.  \n(1) How do you, the utilities in your footprint, and state regulators obtain information that verifies when and \nwhether prospective large loads in your region will reach commercial operation? \nThe large load adjustment process described above (including the recently developed Implementation document) \nwas developed because of challenges to reflecting large loads in traditional forecasting methods, including \nchallenges to verifying when and whether prospective large loads will come to market. Consistent with governing \ndocument and other information exchange requirements, PJM relies on the Electric Distribution Companies and \nLoad Serving Entities to provide data on large load requests. Unlike the PJM-administered generation \ninterconnection process, PJM does not presently have a load interconnection process. Because data centers and \nother large loads are retail loads, albeit interconnected in many cases at the transmission level, the load \ninterconnection process is generally administered through the application of retail tariffs. Electric Distribution \nCompanies and Load Serving Entities typically have load interconnection processes, which explains why forecast-\nrelated data (including, for example, customer-level requests or visibility into probability of reaching commercial \noperation) is available to these entities but not to the RTO in the first instance. \nPJM recently surveyed certain of its Electric Distribution Companies and Load Serving Entities to further inquire \nabout facets of their respective load interconnection and load forecasting processes with a particular aim at getting \nmore granular insights into how these entities assess the commercial probability of large loads. As part of that \nongoing effort, we can preliminarily share some general observations about the diversity of practices among these \nentities in PJM:   \n• \nThere are a wide range of approaches to load adjustment processes, and some approaches reflect more \nexperience with large load additions than others.  \no \nSome states and Electric Distribution Companies/Load Serving Entities have approved or have \nproposed required financial commitments upon formalizing a load interconnection based on a \ncontracted minimum demand.  \no \nOther states and Electric Distribution Companies/Load Serving Entities reflect less stringent \napproaches (like tracking milestones or developing alternative scoring criteria) that appear more \nfocused on recouping expenditures on customer-specific transmission upgrades. \n• \nDuplicative requests are generally not being explicitly accounted for by Electric Distribution Companies \nand Load Serving Entities submitting load adjustments to PJM unless a customer is known to be \nsubmitting multiple requests within a single utility territory or collection of utility territories owned by a"},{"page":6,"startToken":1942,"endToken":2422,"text":"October 17, 2025 \nPage 5 \n610.666.8980 | www.pjm.com \nsingle parent company.7 In short, whether the request is duplicative of other requests is information that \nresides with the large load customer that has submitted these duplicative requests. For competitive \nreasons, these customers are often not willing to provide this information.  \n• \nIn assessing the potential commercial viability of anticipated large loads, some entities are using historical \nexperience to understand anticipated load characteristics, such as load ramp or demand-to-capacity \ncharacteristics, and other entities appear to rely on customer-specified information included in \nagreements between the utility and load customer. \n• \nThere is a diversity of state engagement on retail load interconnections and forecasting. Some states \nappear to have annual reporting requirements on load expectations, although from PJM’s review of \navailable information, there may not yet be in place a formal validation/verification process on large loads \nor selection criteria.  \nBecause of the disparate state law regulatory regimes relating to large load interconnections and forecasting, \nPJM’s current stakeholder proposal invites continued discussion about a role for states in verifying and validating \nproposed load adjustments and forecast inputs. Such efforts will help PJM’s ability to uniformly collect comparable \ndata from Electric Distribution Companies and Load Serving Entities across its footprint. PJM also continues to \nmonitor ongoing developments that could impact load forecasting in the states across its footprint. To that end, \nPJM has prepared the attached summary chart of relevant state tariff and regulatory developments it is aware of to \ndate. PJM continues to engage with applicable state authorities and impacted stakeholders to appreciate any \nimpacts on PJM’s processes.  \nOne particularly notable (and recent) development is the introduction in Pennsylvania of the proposed Load \nForecast Accountability Act.8 As PJM understands this recent development, the proposed legislation is aimed at \nstrengthening the transparency and accuracy of load forecasting in Pennsylvania. It would authorize the \nPennsylvania Public Utility Commission (“PAPUC”) to review and validate the load forecasts submitted to PJM by \nPennsylvania utilities and empower the PAPUC to collaborate with PJM and other state regulators to avoid \nduplicative project requests. Other states, like Ohio, appear to have taken similar actions.   \nPJM remains open to other potential enhancements to its load forecasting process, including the potential use of \nexperts and vendors. That being said, PJM understands that many of these same experts and vendors struggle \nwith data availability and asymmetries. Furthermore, we understand that in certain locations, there may also be an \ninsufficiently small sample size of historical data from which to extrapolate forecasted loads given the \ntransformational industry changes currently underway. And since many large load projects are covered under \nconfidentiality arrangements between the data center and the utility, third-party vendors and forecasters may \nexperience challenges with accessing information that they may not be able to overcome.  \n \n7 See also the New Jersey development referenced in the enclosed chart. \n8 Load Forecast Accountability Act."},{"page":7,"startToken":2422,"endToken":2864,"text":"October 17, 2025 \nPage 6 \n610.666.8980 | www.pjm.com \n(2) To what extent are prospective large load requests subject to consistent, objective screening criteria before \nthey are included in the load forecast? \nAs discussed above, earlier this year PJM developed and published the Load Adjustment Request Implementation \ndocument that offers enhanced transparency about PJM’s load adjustment request submission process in PJM \nManual 19, Attachment B. This effort was necessary because approaches among submitting utilities reflected a \ndiversity of practices and procedures that were challenging for PJM to harmonize. While certainly these actions are \na step in the right direction, PJM looks forward to continued collaboration with its stakeholders, especially the \nElectric Distribution Companies and Load Serving Entities, to pursue additional enhancements and opportunities \nfor consistency across the region.  \n(3) How do you forecast how the actual electricity consumption of a large load will compare to its requested level of \ninterconnection service? \nPJM receives historical data on aggregate loads associated with a request. In some cases, a particular area may \nhave a historical record that can be used. In other areas, however, all of the load is prospective, and thus no \nhistorical data can be leveraged. Historical data, where available, can be used to track accuracy of load \ninterconnection projections over time. As such, PJM intends to promote its use in upcoming annual load \nadjustment processes.  \nHowever, when a utility has no historical record to leverage, the utility is instead relying on milestone tracking or \nhow far along they are in their specific interconnection process. They then would rely on customer representations \nabout expected demand. It remains unclear and uncertain how reliable such reliance is, which is why PJM’s \nImplementation document uses guidelines (e.g., probability factors, ramping, demand versus capacity) when \ndeveloping the forecast.  \n(4) How do you coordinate with utilities at the regional or interregional level to share best practices on large load \nforecasting and ensure that large load interconnection requests are not double-counted? \nPart of the load adjustment process described in Manual 19 and the Implementation document calls for requesters \nto present at the Load Analysis Subcommittee.9 This affords an opportunity to promote transparency and allows \nutilities to share best practices as our industry explores continued enhancements to the load forecasting process.  \nPJM will continue to monitor state regulatory developments (like the Load Forecast Accountability Act mentioned \nabove) and engage with stakeholders during its ongoing large load additions stakeholder process to pursue other \nopportunities to minimize the potential for double-counting proposed load additions in forecasts. As an example, \nPJM and its stakeholders will continue to explore how more stringent financial commitments and enhanced \n \n9  Load Analysis Subcommittee."},{"page":8,"startToken":2864,"endToken":2977,"text":"October 17, 2025 \nPage 7 \n610.666.8980 | www.pjm.com \ninformation sharing about specific proposed load additions could advance efforts to mitigate double-counting \nconcerns.  \nPJM will also explore with stakeholders the potential benefits of comparing the PJM-developed load forecast \nagainst third-party forecasts of national data center development. Such a comparison may prove to be a useful \nway to assess whether PJM’s forecast is in line with established national trends, supply chain constraints, and \nother realities relating to data center development.  \n* \n* \n* \nPJM looks forward to continued engagement with the Commission on the important topic of load forecasting, \nincluding at the upcoming October 21, 2025, reliability technical conference. \n \nRespectfully, \n/s/ Manu Asthana \nManu Asthana"},{"page":9,"startToken":2977,"endToken":3269,"text":"October 17, 2025 \nPage 8 \n610.666.8980 | www.pjm.com \nComparison Table of PJM State \nRegulatory Developments for Large Loads via Contracts, Fees and Rate Schedules \nState \nRegulation(s) \nD.C. \nN/A \nDelaware \nHB 233 (2025, Proposed) \n- \nRequires regulated utilities to establish separate rate for “large energy-use” \nfacilities \nIllinois \nCom-Ed (PDF), General Terms and Conditions Filing (2025, Proposed) \n- \nFor “large demand project applicants” (revised or new service of 50 MW or \ngreater in 10 years of service): \no A projected load ramp through the first 10 calendar years will include \nmonthly projections of the Maximum Kilowatts Delivered;  \no Payment of the costs of the initial engineering analysis;  \no Proposed deposit sufficient to secure the costs of procurement of long-\nlead materials; and \no Required to enter into a Transmission Security Agreement under the \njurisdiction of FERC (rate schedule must be calculated in accordance \nwith PJM OATT). \nIndiana \nIndiana Michigan Power (PDF), Update Tariff Industrial Power (2025, Passed) \n- \nLarge loads (new or expanded facilities with contract capacity of at least 70 MW \nor 150 MW aggregated) subject to the following Large Load Terms: 20 years \ninitial period contract term and termination fee given permanent closure during \nterm; 90% monthly minimum billing demand; increased minimum amount of \ncollateral to be provided by the customer.  \nKentucky \nN/A \nMaryland \nHB 0900 (2025, Proposed) \n- \nRequires Maryland electric companies to submit to the PSC for approval of a \nspecific rate schedule for certain data center customers (monthly maximum \ndemand more than 2,500 kW). \no Contract load ramp must be four years or less; \no Contracts for an initial period of not less than the load ramp plus 20 \nyears; \no Certain load ramp contract capacity specifications; \no Minimum service charges associated with the contract;"},{"page":10,"startToken":3269,"endToken":3670,"text":"October 17, 2025 \nPage 9 \n610.666.8980 | www.pjm.com \no Exit fee equal to the minimum charges for 120 months of service if \ncustomer decides to terminate contract; and \no Minimum monthly distribution billing demand and transmission billing \ndemand are not less than 90% of the customer’s load ramp contract \ncapacity. \nHB 1035/SB 937, Next Generation Energy Act (2025, Passed) \n- \nEach investor-owned electric company and electric cooperative to submit to PSC \nfor approval of a specific rate schedule for large load customers (projected to \nhave an aggregate monthly demand of at least 100 MW and a load factor of over \n80%; excludes existing large loads that do not expand by more than 25 MW). \n- \nRate schedule should protect residential retail electric customers from the \nfinancial risks of large load facilities through the use of: load ramps, minimum \nbilling demand, long-term contractual commitments and exit fees, and fees for \ncanceling or delaying the project. \n- \nBefore signing a contract for service under a specific rate schedule, a large load \nfacility must submit a request for a load study to determine the necessary \ncontract capacity for the large load customer and pay any applicable fees \nassociated with the study. \nMichigan \nMichigan Consumers Energy, Rate GPD Amendment (2025, Proposed) \n- \n“Project Proposal Fee” as an up-front administrative fee (not to exceed \n$100,000);  \n- \nRate contract for an initial 15-year period (with a one-time allowance for a \nreduction in the contract capacity), including a specified contract amount and \nramp-up period no longer than five years prior to the contract term.  \n- \nNew data centers be required to pay a monthly Minimum Billing Demand of 80% \nof the data center’s Contract Capacity and applied to their Maximum Demand \nand On Peak Demand.  \n- \nRights to suspension and exit fees.  \nNew Jersey \nBill A5462 (2025, Passed) \n- \nRequires that no later than 180 days after effective date, each electric public \nutility shall file an application with the BPU to create a tariff for the provision of \nelectricity to large loads (maximum monthly demand of 100 MW). \no Provides adequate financial guarantees that they will take at least 85% \nof service they request for a period of not less than 10 years from when \nservice commences; \no Requires any new large load data center customer to demonstrate that \nthe proposed project is not duplicative of any other, whether located in \nNew Jersey or elsewhere, or to identify the project’s interdependencies;"},{"page":11,"startToken":3670,"endToken":4027,"text":"October 17, 2025 \nPage 10 \n610.666.8980 | www.pjm.com \no Provide deposits or financial security if the large load data center project \nceases operations or takes less service than anticipated over the 10-\nyear period. \n- \nThe board may establish rates specific to large load data centers for use by any \nelectric public utility in formulating the tariff.  \nNorth \nCarolina \nN/A \nOhio \nOhio Power Company (PDF) (2025, Passed) \n- \nAEP proposed, and the PUCO approved (PDF), increased financial \nrequirements for new data centers (larger than 25 MW). Customers will be \nsubject to a 12-year contract term that includes a load ramp period of four years \nwith rising customer capacity during the load ramp.  \n- \nFollowing the ramp period, large data centers would pay for 90% of their \nprojected energy needs upfront each month, even if they don’t use all of it – \nessentially creating a new classification of customers specifically for data center \ncustomers.  \n- \nExit fee, applied to any project that is canceled or unable to meet the obligations \nover the course of the electric service agreement. \nPennsylvania Docket Number M-2025-3054271 (2025, Proposed) \n- \nEn Banc Hearing Concerning Interconnection and Tariffs for Large Load \nCustomers: \no At the Public Meeting of March 27, 2025, a motion by Chairman \nDeFrank was approved to convene a public hearing exploring the \ngrowing impact of large-scale electric customers – including data \ncenters and other high-energy users – on the state’s electric grid. \no The five PUC commissioners held an en banc hearing to seek \ninformation from industry leaders and interested parties concerning \ninterconnection and tariffs for large load customers in Pennsylvania. \no The intent of the hearing is to educate and inform the Commission on \nthe prudent design of a large load customer model tariff, seeking \ncomments on topics such as appropriate megawatt-size delegation, \ndeposits and financial security, exit or early termination fees, minimum \ncontract terms, etc. \n- \nFollowing the en banc hearing, the Office of Competitive Market Oversight, the \nBureau of Technical Utility Services and the Law Bureau are to review submitted \ntestimony and written markets and develop a proposed model tariff for large load \ncustomers seeking to interconnect in the Commonwealth. \nTennessee \nN/A"},{"page":12,"startToken":4027,"endToken":4156,"text":"October 17, 2025 \nPage 11 \n610.666.8980 | www.pjm.com \nAs of October 2025\nVirginia \nDominion (2025, Proposed) \n- \nProposal (PDF) for new base rates: requested increases of $8.51 per month in \n2026 and $2 per month in 2027 for a typical residential customer. \n- \nNew customer class (GS-5) for “large-scale users of electricity” (25 MW or \ngreater, measured or contracted load factor of at least 75%); New minimum \ndemand charges: 85% for the transmission and distribution functions and 60% \nfor the generation function. \n- \nMinimum 14-year contract term (four-year ramp period and 10 years) to pay for \ntheir requested power – even if they use less. \n- \nNew deposit and credit (collateral) requirements for these customers; and \n- \nProvisions with respect to potential capacity reassignments and exit fees. \nWest Virginia N/A"},{"page":13,"startToken":4156,"endToken":4214,"text":"CERTIFICATE OF SERVICE \n \n \nI hereby certify that I have this day, October 20, 2025, served the foregoing document on \nthose parties on the official Service Lists compiled by the Secretary in these proceedings.  \n \n \n \n/s/ Mark Stanisz \nMark Stanisz \nAssociate General Counsel \nPJM Interconnection, L.L.C. \n2750 Monroe Boulevard \nAudubon, PA 19403 \n(610) 666-4707 \nMark.Stanisz@pjm.com"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":13,"endAt":0,"startToken":0,"endToken":4156},{"p":13,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":13,"endAt":385,"startToken":4156,"endToken":4214}]}