{"document":{"slug":"rec-20251205-5321","title":"Motion to File Supplemental Comments of Constellation Energy Generation, LLC","issued":"2025-12-05","accession":"20251205-5321","docket":"EL25-49-000","group":"PJM co-location compliance","filer":"Constellation Energy Generation, LLC","kind":"comments","file":"sources/filings/text/20251205-5321_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20251205-5321","tier":"record","sha256":"7d3b43d3177bcdbe999007e3e2ab2d62dc2144a6fd627a4331bac4d1afc040ba","pages":65,"tokens":23424,"emptyPages":[62],"textThemes":["study","colo","flex","adequacy"]},"pages":[{"page":1,"startToken":0,"endToken":236,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION\n \nPJM Interconnection, L.L.C., et al. \n \n \nLarge Loads Co-Located at Generating Facilities \n \n \nConstellation Energy Generation, LLC \n \n     v. \n \nPJM Interconnection, L.L.C. \n) \n \n \n)  \n \n \n)  \n) \n) \n) \n) \nDocket No. EL25-49-000 \n \n \nDocket No. AD24-11-000 \n \n \n \n \nDocket No. EL25-20-000 \n(Consolidated) \nMOTION TO FILE SUPPLEMENTAL COMMENTS OF \nCONSTELLATION ENERGY GENERATION, LLC \nPursuant to Rule 212 of the Rules of Practice and Procedure of the Federal Energy \nRegulatory Commission,1 Constellation respectfully moves to submit these Supplemental \nComments in the above-captioned proceeding. \nRule 212 provides that a party may file a motion at any time in a proceeding.2 These \nSupplemental Comments attach Constellation’s Supporting Reply Comments3 filed today in \nresponse to the Secretary of Energy’s proposed ANOPR4 that continue to seek an immediate \nCommission order in the PJM Show Cause proceedings. The Commission has granted motions \nwhen they assist the Commission in understanding the issues presented, provide additional \n \n1 18 C.F.R. § 385.212 (2025). \n2 Id. § 385.212(a)(1). \n3 See Attachment (Supporting Reply Comments of Constellation Energy Generation, Docket No. RM26-000 (filed \nDec. 5, 2025)). \n4 U.S. Department of Energy, Secretary of Energy, Letter to FERC re: “Ensuring the Timely and Orderly \nInterconnection of Large Loads,” Advance Notice of Proposed Rulemaking (Oct. 23, 2025) (issued pursuant to \nDepartment of Energy Organization Act § 403, 42 U.S.C. § 7173) (cover letter, “Secretary’s Letter,” and Advanced \nNotice of Proposed Rulemaking (“ANOPR”))."},{"page":2,"startToken":236,"endToken":414,"text":"2 \ninformation for the Commission’s decision-making process and help ensure a complete and \naccurate record.5 Constellation respectfully requests the Commission accept these Supplemental \nComments because they meet these criteria. \n \n \n \n \n \n \n \n    Respectfully submitted, \n \n \n \n \n \n \n \n    /s/ Paul F. Wight \n \n \nDecember 5, 2025 \n \n \n \n5 See, e.g., Equitrans, L.P., 134 FERC ¶ 61,250, at P 6 (2011); Cal. Indep. Sys. Operator Corp., 132 FERC ¶ 61,023, \nat P 16 (2010). \nCarrie Hill Allen \nSr. Vice President & Deputy General Counsel \nSeth Lucia \nAssistant General Counsel \nConstellation Energy Generation, LLC \n250 Massachusetts Ave. NW, Suite 760 \nWashington, D.C. 20001 \ncarrie.allen@constellation.com \nseth.lucia@constellation.com \n  \nChristopher A. Wilson \nManaging Director, Federal Regulatory Affairs \nConstellation Energy Generation, LLC \n250 Massachusetts Ave. NW, Suite 760 \nWashington, D.C. 20001 \n202-347-7500 \nFERCe-filings1@constellation.com \n \nPaul F. Wight \nDLA Piper LLP (US) \n500 Eighth Street NW \nWashington, D.C. 20004 \n703-773-4058 \npaul.wight@us.dlapiper.com  \n \nJacob I. Chefitz \nDLA Piper LLP (US) \n1251 Avenue of the Americas \nNew York, NY 10020 \n212-335-4500 \njacob.chefitz@us.dlapiper.com  \n \nCounsel for Constellation Energy \nGeneration, LLC"},{"page":3,"startToken":414,"endToken":496,"text":"CERTIFICATE OF SERVICE \nI hereby certify that I have on this 5th day of December, 2025, caused to be served a copy \nof the foregoing upon all parties on the service lists in these proceedings in accordance with the \nrequirement of Rule 2010 of the Commission’s Rules of Practice and Procedure, 18 C.F.R. \n§ 385.2010 (2025). \n/s/ Semhal Fissehaye Gebrekirstos \nSemhal Fissehaye Gebrekirstos \nDLA Piper LLP (US) \n500 Eighth Street NW \nWashington, DC 20004 \n202-799-4471 \nsemhal.gebrekirstos@us.dlapiper.com"},{"page":4,"startToken":496,"endToken":510,"text":"Attachment \nSupporting Reply Comments of Constellation Energy \nGeneration, LLC Filed in Docket No. RM26-4-000"},{"page":5,"startToken":510,"endToken":747,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \nInterconnection of Large Loads to the Interstate\nTransmission System \n \n \nPJM Interconnection, L.L.C., et al. \n \nLarge Loads Co-Located at Generating Facilities \n \nConstellation Energy Generation, LLC \n \n     v. \n \nPJM Interconnection, L.L.C. \n)  \n)  \n \n \n)  \n \n)  \n \n)  \n)  \n)  \n) \n) \nDocket No. RM26-4-000 \n(Not consolidated) \n \n \nDocket No. EL25-49-000 \n \nDocket No. AD24-11-000 \n \n \n \nDocket No. EL25-20-000 \n(Consolidated) \nSUPPORTING REPLY COMMENTS OF \nCONSTELLATION ENERGY GENERATION, LLC \nConstellation supports the ANOPR and submits this reply to discuss four areas of \nconsensus in the record that provide the path forward on large load interconnection reform. The \ncomments reveal broad agreement among the overwhelming majority who support reform that the \nCommission should (i) act quickly, (ii) focus relief in regions where there is evidence of undue \ndiscrimination, undue preference or unjust and unreasonable service, (iii) respect regional \ndifferences, and (iv) avoid unnecessary jurisdictional fights.1  \nAccordingly, the Commission should issue the following two items:  \nFirst, by the end of the year, the Commission should issue an order on the merits in the \nPJM Show Cause proceedings2 and thereby: (i) take swift action to kickstart development on \n \n1 See infra, Section I (citations to comments in the record on each of these four points).  \n2 PJM Interconnection, L.L.C., Docket No. EL25-49-000, Large Loads Co-Located at Generating Facilities, Docket \nNo. AD24-11-000, Constellation Energy Generation, LLC v. PJM Interconnection, L.L.C., Docket No. EL25-20-\n000 (consolidated) (collectively, “PJM Show Cause proceedings”)."},{"page":6,"startToken":747,"endToken":1295,"text":"2 \nseveral stalled hyperscale data center projects in PJM; (ii) conclude, based on the comprehensive \nrecord in those proceedings, that the lack of clear rules allows the PJM Transmission Owners to \nunduly discriminate by still refusing to process large load behind-the-meter projects, while \nleveraging unfiled procedures for processing in front-of-the-meter interconnections to favor \nfacilities and over which they have a monopoly; (iii) provide relief tailored to the PJM region while \nstill advancing the rulemaking process; and (iv) avoid the most controversial jurisdictional \nquestions over large load interconnections. Commissioners and key parties also support prompt \nguidance in PJM, and an order there can capitalize on consensus in the ANOPR record.3 \nOn jurisdiction, the only immediate call the Commission must make in PJM is whether to \nexercise jurisdiction over hybrid facilities’ shared point of interconnection to the grid. This is an \neasy call since the Commission already exercises jurisdiction over the generator’s interconnection, \nand jurisdiction over the same shared facilities does not bifurcate between state and federal \n \n3 See Comments of PJM Interconnection, L.L.C. at 2 (filed Nov. 21, 2025) (“PJM encourages FERC to seize available \nopportunities to issue nearer-term regulatory guidance on matters squarely within its wholesale and transmission \njurisdiction”) (“PJM Comments”); see also id. at 8 (“PJM recommends FERC consideration of the robust record in \nDocket No. EL25-49, including PJM’s previously-filed response in that show cause proceeding.”); Comments of \nPPL Companies at 16 (filed Nov. 21, 2025) (“FERC also opened a Show Cause docket specifically for PJM’s \nconsideration of co-located loads, examining whether the PJM Tariff remains just and reasonable for not providing \nsufficient guidance as to their treatment. These dockets remain open. Commission action to provide guidance on this \nsubject would be welcome.”) (“PPL Comments”); Comments of AES Corporation at 14 (filed Nov. 21, 2025) (“AES \nnotes that some of these issues are already before the Commission in existing proceedings, including the \nCommission’s FPA Section 206 Proceeding addressing co-location of large loads within PJM. To promote \nregulatory certainty, the Commission should ensure that any rules developed through this proceeding related to \ncollocated generation and transmission service address and take into account the records as well.”) (footnote omitted) \n(“AES Comments”); Comments of the Electric Power Supply Association at 3 (filed Nov. 21, 2025) (“It would be \nentirely inconsistent with the intent of the ANOPR to further delay resolution of the Show Cause proceeding to \nclarify the rules applicable to large load interconnections in PJM, which has been awaiting Commission action based \non an extensive record for over six months.”) (“EPSA Comments”); see also, e.g., PJM Interconnection, L.L.C., 191 \nFERC ¶ 61,025, at P 30, n.106 (2025) (“We fully intend to act as expeditiously as possible to address those issues, \nas we know how important it is to investors, utilities, and all interested parties to have regulatory certainty.”); FERC, \nNovember 20, 2025 Open Meeting, YOUTUBE (Nov. 20, 2025), at 19:39, https://www.ferc.gov/news-\nevents/events/november-20-2025-open-meeting-10022024 (Commissioner David Rosner expressing he is \n“confident that we can make some progress” on the open co-location proceeding in PJM); Transcript of Oct. 16, \n2025 Open Meeting at 7:14-18 (Then-Chairman David Rosner states “I’m very optimistic that the Commission will \nbe ready to act later this year on our work on colocation.”)."},{"page":7,"startToken":1295,"endToken":1695,"text":"3 \nauthority depending on the services of the moment.4 Regardless, it is now essential for the \nCommission to exercise its authority to prevent Transmission Owners from denying or \nencumbering interconnection services for large load configurations that they disfavor. \nSecond, by the end of the year or as soon as possible thereafter, the Commission should \nissue a Notice of Proposed Rulemaking (“NOPR”) that builds upon the principles in the ANOPR \nand responds to the four areas of consensus. The NOPR should: (i) establish deadlines to meet the \nSecretary’s timeline for a final rule by April 30, 2026; (ii) solicit specific evidence of unjust and \nunreasonable service for large loads and/or undue discrimination or preference by Transmission \nOwners to support the Commission’s required Federal Power Act (“FPA”) section 206 showing in \neach region and state, as it already has in PJM; (iii) accommodate regional differences; and \n(iv) expand its jurisdictional analysis and findings based on the record, including a finding that the \nCommission has jurisdiction over hybrid facilities’ shared point of interconnection. \nIn both the PJM order and the NOPR, the Commission could also address reliability \nconcerns by considering improvements to load forecasting, additional demand response, and \nenhanced reliability backstop mechanisms. Constellation joined Amazon, Calpine, Google, \nMicrosoft, and Talen in sponsoring a package of such reliability reforms in PJM, and Constellation \n \n4 See Comments of the Pennsylvania Public Utility Commission at 11 (filed Nov. 21, 2025) (“There is no clear \nCongressional authorization to expand FERC jurisdiction to pure load interconnection of any size. However, if \nlimited to hybrid interconnections of load and generation at the same point of interconnection, there may be greater \nroom for discussion.”) (“Pennsylvania PUC Comments”); EPSA Comments at 12 (“the interconnection of the hybrid \nfacility will plainly be a practice directly affecting the Commission-jurisdictional wholesale rates of the \ninterconnected or interconnecting generation facilities.”); Comments of the Solar Energy Industries Association at \n10, 14 (filed Nov. 21, 2025) (“Jurisdiction should be limited to interconnections directly to transmission facilities” \nand noting that the ANOPR defines “Hybrid Facilities” as loads that “share a point of interconnection with new or \nexisting generation facilities.”) (“SEIA Comments”); Comments of Eolian L.P. at 5 (filed Nov. 21, 2025) (“the \ninterconnection of large loads to the interstate transmission system is a transmission service in precisely the same \nway that the interconnection of generators to the transmission system is a transmission service.”) (“Eolian \nComments”)."},{"page":8,"startToken":1695,"endToken":2084,"text":"4 \nfurther proposed those reforms in its initial comments in this proceeding.5 However, the \nCommission should reject “Bring Your Own Generation” or “BYOG” proposals (such as PJM \nOption 6 in the Show Cause proceeding)6 that would allow state-favored resources to leapfrog the \nPJM queue, and should likewise reject proposals discussed in the ANOPR comments or in the \nIMM’s recent complaint that would condition new large load interconnections (or expedited \ninterconnection) upon the load bringing its own new generation.7 Discrimination against existing \ngeneration resources will undermine resource adequacy by signaling that existing capacity is less \nvaluable than new capacity in serving load, even when existing capacity can serve load more \nefficiently. The Commission should let existing market mechanisms work to ensure resource \nadequacy. If it determines that reform is needed, it should adopt competitive market fixes that \npreserve market-based incentives for capital investment, such as the Joint Stakeholders’ Reliability \nBackstop Alternative that we proposed in our initial comments8 and that we further explain in the \nattached Affidavit of Aaron T. Patterson of the NorthBridge Group, Inc., an expert in electric \nmarket design.9  \nIssuance of the PJM order by the end of the year and the NOPR by then or as soon thereafter \nas possible is the Commission’s best path forward to build upon the principles in the ANOPR and \n \n5 See Supporting Comments of Constellation Energy Generation, LLC at 40-43 (filed Nov. 19, 2025) (discussing \nreliability proposals) (“Constellation Comments”); see also id., Exh. 1, Joint Stakeholder Package (Amazon, \nCalpine, Constellation, Google, Microsoft, Talen), PJM CIFP – Large Load Additions, Stage 4 (Nov. 19, 2025). \n6 Constellation Comments at 15-17. \n7 See Indep. Market Monitor for PJM v. PJM Interconnection, L.L.C., FERC Docket No. EL26-30-000 (filed Nov. 25, \n2025) (“IMM Complaint”). \n8 See Constellation Comments at 42-43. PJM has the authority to file to ensure resource adequacy of its own accord \nand could submit this proposed Reliability Backstop Mechanism (a proposal with which it is very familiar given it \nwas vetted extensively in the recent Critical Issue Fast Path (CIFP) stakeholder process) pursuant to section 205 of \nthe FPA in time to be considered by the Commission, accepted and in place for the 2028/29 capacity auction in June \n2026.  \n9 Patterson Aff., Exh. 1 hereto (discussing the “Enhanced Backstop,” which is the Reliability Backstop Alternative)."},{"page":9,"startToken":2084,"endToken":2469,"text":"5 \nfortify America’s leadership in AI consistent with Chairman Laura V. Swett’s “priority … to \nensure that our country can connect and power data centers as quickly and as durably as \npossible.”10 \nI. \nThere Is Broad Consensus in the Record for How the Commission Should Act \nFour areas of consensus emerge from the initial comments and should guide the \nCommission’s next steps on large load interconnection reform.  \nA. The Commission Should Act Quickly \nThe Department of Energy,11 members of the Commission,12 and most parties agree that \n“the time has come for the Commission to act expeditiously by establishing rules that will provide \n \n \n \n10 \nVideo \nof \nNovember \n20, \n2025 \nCommission \nMeeting \nat \n6:14-22 \n(available \nat \nhttps://www.youtube.com/watch?v=_Cxq0gORq8c&embeds_referring_euri=https%3A%2F%2Fwww.ferc.gov%2\nF&source_ve_path=OTY3MTQ). \n11 See U.S. Department of Energy, Secretary of Energy, Letter to FERC re: “Ensuring the Timely and Orderly \nInterconnection of Large Loads,” Advance Notice of Proposed Rulemaking (Oct. 23, 2025) (cover letter, \n“Secretary’s Letter,” and Advanced Notice of Proposed Rulemaking “ANOPR”), passim. \n12 See supra 2, n.3; id. 5, n.10; see also Ethan Howland, New FERC commissioners say connecting data centers is key \npriority, Utility Dive (Nov. 21, 2025), https://www.utilitydive.com/news/ferc-data-centers-swett-lacerte-\nlng/806145/ (“The AI data race requires ‘bold action’ to protect the economy and national security, [Commissioner \nLaCerte] said. ‘The risks of inaction or delayed action are simply too great,’ he added. ‘I look forward to partnering \nwith all stakeholders … to accomplish these goals.’”); Ethan Howland, Surging load growth requires flexibility, new \napproaches: FERC’s See, Utility Dive (Oct. 27, 2025), https://www.utilitydive.com/news/load-growth-\ntransmission-incentive-ferc-see/803840/ (quoting Commissioner See as stating “We’re at a time where we need \nelectrons to be able to get where they need to in an efficient and a cost effective manner, and that’s going to require \nnew investments and new development, and we need that quickly”); Judy W. Chang, et. al, It’s all one system: \nIntegrate transmission and interconnection planning to support load growth, Utility Dive (Sept. 26, 2025), \nhttps://www.utilitydive.com/news/its-all-one-system-integrate-transmission-and-interconnection-plan… \n(“Generational change is occurring in the nation’s energy sector. While FERC is considering urgent short-term fixes, \nit also must evaluate longer-term solutions that shape the sector.”)."},{"page":10,"startToken":2469,"endToken":3276,"text":"6 \nclarity and finality.”13 Certain states and the minority of parties that urge delay largely are \nconcerned about federal-state jurisdiction and disruption to ongoing state and regional efforts.14 \n \n13 Comments of the PSEG Companies at 2 (filed Nov. 21, 2025) (“PSEG Comments”); see also, e.g., PJM Comments \nat 2, 8 (“PJM encourages FERC to seize available opportunities to issue nearer-term regulatory guidance….”); \nComments of Southern Maryland Electric Cooperative, Inc. at 1-2 (filed Nov. 21, 2025) (“SMECO respectfully \nsubmits that a final rule … is needed at the present time.”); Comments of Advanced Energy United at 32-33 (filed \nNov. 21, 2025) (“Advanced Energy United encourages the Commission to meet DOE’s April 30, 2026 deadline for \nfinal action to the extent feasible…. The Commission should expend every possible effort to deliver a timely \nrulemaking … [and] consider moving forward on a more expedited basis on those elements … that have more \nuniform stakeholder support.”); Comments of the Electricity Customer Alliance at 6 (filed Nov. 21, 2025) \n(“Commission action is needed now to facilitate speed to power for large load customers, resolve lingering questions \nholding back progress, and protect existing customers”) (initial capitalization omitted) (“ECA Comments”); \nComments of Talen Energy Corporation at 6 (filed Nov.21, 2025) (“…the President’s recent executive orders … \nunderscore the urgency of action. The United States cannot afford to wait years for lengthy regulatory processes to \nplay out while reliability risks mount, critical infrastructure projects stall, and the nation loses investment in \ngroundbreaking technology to other countries because of lack of regulatory certainty. Every delay compounds the \nchallenge of meeting demand and maintaining resilience while supporting economic growth.”) (“Talen Comments”); \nInitial Comments of Iron Mountain Data Centers at 1 (filed Nov. 21, 2025) (“Iron Mountain largely supports the \nCommission expeditiously moving the Secretary’s proposed ANOPR forward to a NOPR and eventually a FERC \norder”); Comments of Americans for a Clean Energy Grid at 11-12 (filed Nov. 21, 2025) (“The Commission should \ndeploy every tool at its disposal to meet the goals set forth in the ANOPR, which fundamentally relies on our ability \nto build well-planned comprehensive high-capacity regional and interregional transmission as soon as possible.”); \nComments of Geronimo Power, LLC at 1 (filed Nov. 21, 2025) (“Geronimo Power urges the Commission to \npromptly move forward with a notice of proposed rulemaking and final rule in this proceeding….”) (“Geronimo \nComments”); Comments of WIRES at 2 (filed Nov. 21, 2025) (“To that end, WIRES generally supports the urgent \nneed, as recognized by the Secretary, to expedite and streamline the interconnection of large loads.”); Initial \nComments of Microsoft Corp. at 8 (filed Nov. 21, 2025) (“In consideration of the urgent need for action….”); \nComments of the Institute for Progress at 2 (filed Nov. 21, 2025) (“We urge the Commission to move swiftly to a \nfinal rule that both enables innovation and hardens our grid infrastructure.”); EPSA Comments at 5 (“EPSA … urges \nthe Commission to act on these matters in as timely and clearly a manner possible.”); Comments of Chevron U.S.A., \nInc. at 4 (filed Nov. 21, 2025) (“the Commission should promptly issue a Notice of Proposed Rulemaking (NOPR) \nthat fleshes out DOE’s initial recommendations and includes specific regulatory text”). \n14 See Comments of the Organization of PJM States, Inc. at 2-3 (filed Nov. 21, 2025) (“Rather than relitigating the \nlong-standing division of authority related to load interconnections, it would be more efficient to search for solutions \nthat promote consensus between the states and the Commission rather than rushing questionable modifications to \nlong-standing, statutorily defined jurisdictional divisions.”) (“OPSI Comments”); Initial Comments of the New \nEngland States Committee on Electricity at 3 (filed Nov. 21, 2025) (“If the Commission decides to move forward \nwith a rulemaking, it should first engage in a significant collaborative process with states, regional transmission \norganizations (‘RTOs’), and other stakeholders. Absent this, the Commission risks creating a one-size-fits-all rule \nthat is vulnerable to legal challenge and results in significant unintended consequences due to large state and regional \ndifferences and existing state regulation of large load interconnection customers.”); Initial Comments of the \nOrganization of MISO States, Inc. at 4 (filed Nov. 21, 2025) (“It is essential that the Commission, DOE, states, \nutilities, and large-load customers work together in this proceeding to identify a clear and coordinated path forward \nwhile acknowledging that the implications of any final rule are significant. If outcomes of this proceeding cause \nregulatory gaps, unintended consequences, or are or not in alignment with the FPA (and other long-standing systems \nof cooperative federalism established in settled case law that have governed the electric grid for decades) the desired \nspeed of interconnecting large loads could come to a standstill through unintended system inefficiencies, new \nbottlenecks, and most likely – legal challenges.”) (“MISO States Comments”); Comments of the New York State \nPublic Service Commission at 3 (filed Nov. 21, 2025) (“the Commission should pause the Proposed ANOPR"},{"page":11,"startToken":3276,"endToken":3897,"text":"7 \nOthers seek to maintain the status quo.15 But most of the parties who support reform desire prompt \naction and the policy imperative for quick reform is obvious. The Commission should issue an \norder on the merits in PJM16 by the end of the year and a NOPR by then or as soon thereafter as \npossible.  \nB. The Commission Should Act on Record Evidence of Undue Preference, Undue \nDiscrimination and Unjust and Unreasonable Service for Large Load \nInterconnections \nSince the Commission can only issue a rule after making a showing under section 206 of \nthe FPA,17 several parties argue that the Commission must make specific showings in each region \n \nproceeding and work with stakeholders to identify other efforts that should be pursued, particularly those within the \nCommission’s jurisdiction.”) (“NYS PSC Comments”); Comments of the New York Transmission Owners at 5 \n(filed Nov. 21, 2025) (“[A]ny federal action that interferes with New York’s retail regulatory framework would \nnecessarily invite dispute over whether the Commission has stepped beyond its statutory authority.”) (“NY \nTransmission Owners Comments”); Initial Comments of the Public Service Commission of the State of Missouri at \n13 (filed Nov. 21, 2025) (“The Secretary’s abbreviated deadline of April 2026 … should warrant a cautious \napproach.”); Comments of Consumers Energy Company at 13 (filed Nov. 21, 2025) (“Attempting to finalize a \nrulemaking of this potential magnitude within approximately six months may increase the risk of legal challenges \nconcerning the Commission’s authority.… If the Commission does not take adequate time, there is a risk that \nimplementation of desired reforms will be delayed and potentially frustrated.”). \n15 See Initial Comments of the PJM Transmission Owners at 2 (filed Nov. 21, 2025) (“Any Commission action [must] \nbe appropriately targeted and respect existing paradigms and precedent regarding cost-allocation, federal and state \njurisdiction, and protecting reliability.”) (“PJM Transmission Owners Comments”); PPL Comments at 8-9 (“Our \nstates are not slowing data center interconnections down in any measurable way.… Even if a standard, federalized \nprocess makes sense elsewhere, it is simply not able to speed things up in Pennsylvania”); Comments of the Ohio \nFederal Energy Advocate at 2 (filed Nov. 21, 2025) (“we recommend the Commission continue to defer to state \naction and utility-specific tariffs to manage the interconnection of load.”); NYS PSC Comments at 3 (“[T]he \nCommission should pause the Proposed ANOPR rulemaking proceeding and work with stakeholders to identify if \nthere are other efforts that should be pursued, particularly those within the Commission’s jurisdiction.”); Initial \nComments of the WEC Companies at 4 (filed Nov. 21, 2025) (“The general statements in the ANOPR … do not \nmeet [the] burden. And, such a finding would conflict with the demonstrable success of the current regulatory \nprocess in Wisconsin and the MISO region.… Wisconsin is a ‘hot spot’ for attracting data centers today and has \nbeen a success story in terms of interconnecting large loads to the grid.… Introducing a new, federal regulatory \nprocess at this stage would have the unintended effect of stalling the positive momentum.…”) (“WEC Comments”); \nPreliminary Rulemaking Comments of the Southern Companies at 6 (filed Nov. 21, 2025) (“[T]he Southeast… large \nloads have presented new and valuable opportunities for economic growth, while at the same time demanding that \nutilities and regulators remain flexible and capable of adapting to changing conditions.… The Southeast has swiftly \nmet this challenge because of an existing productive and healthy market structure built on a foundation of effective \nstate regulation.”) (“Southern Companies Comments”). \n16 See supra at 2, n .3 (citing parties supporting prompt action in PJM). \n17 16 U.S.C. § 824e(a). Section 206 requires a two-step showing: the Commission must first find that the existing \n“rate, charge, classification, rule, regulation, practice, or contract” is “unjust, unreasonable, unduly discriminatory"},{"page":12,"startToken":3897,"endToken":4469,"text":"8 \n(RTO) and state (or utility service territory) “that the existing tariffs unduly discriminate or are \notherwise unjust and unreasonable pursuant to section 206 of the FPA.”18 In PJM, the Commission \nalready has a comprehensive record of undue discrimination and need not wait further while it \ndevelops a record with respect to other regions. \n1. The Commission Should Act on Record Evidence in PJM \nIn PJM, the Commission already has a comprehensive record, including substantial, \nunrebutted evidence of undue discrimination by PJM Transmission Owners against any behind-\nthe-meter configuration, and any in front-of-the-meter configuration that avoids interconnection \nthrough the Transmission Owners’ distribution facilities.19 The Commission’s November 1, 2024 \n \nor preferential,” and then “determine the just and reasonable” replacement and “fix the same by order.” See Answer \nof Constellation Energy Generation, LLC, Docket No. EL25-49-000, et al., at 108 (Apr. 23, 2025) (explaining that \nany FPA section 206 rule must rest on a finding that the existing PJM Tariff is unjust and unreasonable and must \nspecify a just and reasonable replacement rate). \n18 WEC Comments at 4; see, e.g., NYS PSC Comments at 4-5 (“Notably absent from the Proposed ANOPR is any \nevidence that utilities across the nation, or within a particular region, have unduly delayed or burdened the \ninterconnection of large loads, leading to inefficient, untimely, or discriminatory load interconnections. Before \ntaking the extraordinary step of exerting jurisdiction over matters that the FPA reserves to the states, it is incumbent \non the Commission to demonstrate that an adequate basis exists warranting such unprecedented reform.”); Initial \nComments of the Louisiana Public Service Commission and Mississippi Public Service Commission at 6 (filed \nNov. 21, 2025) (“The ANOPR provides no sufficient demonstration that the current load interconnection process in \nMISO, SPP, Mississippi, or Louisiana violates the Federal Power Act.… The FPA requires that substantial evidence \nbe presented showing that the existing rate is unjust, unreasonable, unduly discriminatory, or preferential.”); \nSouthern Companies Comments at 11 (“[T]he Commission should craft rules applicable to specific regions or \nconsider exempting regions that have demonstrated success in this area and do not need to adopt new rules.”); \nComments of Entergy Operating Companies at 20 (filed Nov. 21, 2025) (“Where State processes are working well, \nthere is no need to inject additional rules.”) (“Entergy Comments”); Comments of Duke Energy Corporation at 2 \n(filed Nov. 21, 2025) (“To the extent FERC can identify specific and concrete problems within its statutory authority, \nFERC should narrowly tailor any proposed reforms to solving those specific problems.”) (“Duke Comments”). \n19 The Commission’s evidentiary record in PJM has been assembled over numerous proceedings: Exelon filed six \nseparate rate cases seeking to amend the PJM Tariff to prohibit behind-the-meter co-location, which the Commission \nrejected as procedurally improper after extensive briefing before and after a deficiency notice. Atl. City Elec. Co., \n190 FERC ¶ 61,109 (2025) (Exelon cannot amend the PJM Tariff).  \nTwo Exelon affiliates filed a Petition for Declaratory Order on jurisdictional issues, which were fully briefed and \nremain pending. See, e.g., Protest of Constellation Energy Generation, Baltimore Gas and Elec. Co. and PECO \nEnergy Co., FERC Docket No. EL24-149-000 (filed Oct. 30, 2024).  \nConstellation filed a complaint against PJM seeking to memorialize prior PJM guidance on co-location and establish \nclear rules of the road, which spurred several more rounds of briefs and led to the Commission’s Show Cause Order. \nSee Complaint Requesting Fast Track Processing of Constellation Energy Generation, LLC, Constellation Energy"},{"page":13,"startToken":4469,"endToken":4997,"text":"9 \norder rejecting the Susquehanna Nuclear amended Interconnection Service Agreement (“ISA”) \ncemented the Transmission Owners’ refusal to process certain large load requests – effectively \nimposing their litigation position on others – even as these issues remain pending before the \nCommission20 Constellation has documented this discrimination in the Show Cause Proceedings.21 \nSome Transmission Owners act as if all large load interconnection and co-location issues have \nbeen resolved in their favor. Numerous projects have been stalled. This led the Commission to \npreliminarily find in the Show Cause Order that “this lack of applicable Tariff provisions raises \nthe potential for undue discrimination or preferential treatment.”22  \n \nGeneration, LLC v. PJM Interconnection, L.L.C., FERC Docket No. EL25-20-000 (filed Nov. 22, 2024) \n(“Constellation Complaint”); see PJM Interconnection, L.L.C., 190 FERC ¶ 61,115 (2025) (“PJM Show Cause \nOrder”).  \nThe Show Cause Order itself included 38 specific briefing questions on nearly every issue raised by the ANOPR, \nwith scores of parties filed responses. See Motion for Leave and Answer of Constellation Energy Generation, LLC, \nPJM Interconnection, L.L.C., FERC Docket No. EL25-49-000 (filed May 8, 2025) (demonstrating overwhelming \nrecord support in filed responses to meet the section 206 of the FPA showing that the existing PJM Tariff is unjust \nand unreasonable because it lacks clear rules for co-location).  \nFinally, the Commission previously convened its own Large Loads technical conference with written statements and \nmore rounds of comments (and a heavy focus on PJM). Large Loads Co-Located at Generating Facilities, FERC \nDocket No. AD24-11-000. \n20 PJM Interconnection, L.L.C., 189 FERC ¶ 61,078, at P 87 (2024) (rejecting the amended ISA because it “raise[d] \nquestions regarding whether PJM intends to offer these terms to all similarly-situated interconnection customers”) \n(emphasis added); see also id. PP 87, 89 (finding that “PJM has not demonstrated that the proposed non-conforming \nprovisions in the Amended ISA are necessary deviations from the pro forma ISA” because it did not “show that \nthese provisions are necessary for any interest unique to the interconnection of the Susquehanna Customer Facility”). \n21 See Constellation Complaint at Exh. 5, Declaration of James R. McCoskey (“McCoskey Declaration”) (detailing \nTransmission Owner refusal to process co-location project at LaSalle Clean Energy Center); see also id., Att. 1 to \nMcCoskey Declaration (Letter from E. Glenn Rippie to Carrie Allen (Nov. 12, 2024) (demanding that co-located \nloads take retail service from Transmission Owner before any further processing of interconnection studies).  \nIncluded in the record in the Show Cause Proceedings is extensive Transmission Owner correspondence \ndocumenting their refusals to process co-location projects. See Constellation Complaint at 6-8 (and notes therein) \n(citing Protest of Constellation Energy Generation, Baltimore Gas and Elec. Co. and PECO Energy Co., Docket \nNo. EL24-149-000 (filed Oct. 30, 2024), Exh. 2 (Correspondence with Exelon)) (attaching 13 letters). See also \nConstellation Comments at 4 n.8 (citing evidence and discussion of Transmission Owners’ refusal to cooperate).   \n22 PJM Show Cause Order, 190 FERC ¶ 61,115 at P 75 (citing Constellation Complaint at 17); see also id. P 74 (“[t]he \nabsence of such provisions may leave entities unable to determine what steps they can or must take to effectuate co-\nlocation arrangements of various configurations.”)."},{"page":14,"startToken":4997,"endToken":5288,"text":"10 \nIt has only gotten worse. Some Transmission Owners have blocked behind-the-meter \nconfigurations and are extending that discrimination to front-of-the-meter connections to the grid \n(hybrid facilities), requiring that these facilities take distribution service or adopt configurations \nthat would make net billing impossible. At a time when innovation and efficiency are needed, they \nare instead leveraging their monopoly over interconnection to block innovative and efficient \nconfigurations that would provide customers with alternatives to the other services (e.g., gross-\nbilled network transmission service and distribution service) these Transmission Owners provide. \nThe Commission should not allow Transmission Owners to continue to engage in this unduly \ndiscriminatory and preferential treatment. \n2. The Commission Should Request Further Evidence in Other Regions \nThe NOPR should solicit specific additional evidence of unjust and unreasonable \ninterconnection service for large loads and/or undue discrimination against configuration \ndisfavored by Transmission Owners to support the Commission’s required showing under section \n206 of the FPA in each region or state, as it already has in PJM. This should address some states’ \nconcerns that there has been no showing in the ANOPR of undue discrimination.23 The request for \nadditional evidence should include Governor Shapiro and Governor Youngkin’s joint \n“suggest[ion] that FERC examine interconnection study processes, and whether it should be \nconsidered not just and reasonable for an interconnection request to take longer than six months, \nas recently requested by thirteen governors of both parties.”24 In the event that the Commission \n \n23 See, e.g., MISO States Comments at 7 (“the ANOPR provides no evidence or examples demonstrating that current \nstate- or utility-administered interconnection processes are discriminatory or inadequate.”); OPSI Comments at 6 \n(similar); NYS PSC Comments at 4-5 (similar). \n24 Shapiro & Youngkin Comments at 2 (filed Nov. 21, 2025)."},{"page":15,"startToken":5288,"endToken":5655,"text":"11 \ndetermines it lacks a sufficient record in non-RTO regions, the NOPR may also initially focus the \nrule on RTOs.25 \nThe Commission should reject arguments that “utilities have no incentive to discriminate \nagainst large loads, which represent new retail sales and rate-base investment opportunities.”26 The \nMaryland Public Service Commission, for example, argues that “FERC issued Orders Nos. 888 \nand 2003 to correct inefficiencies and discrimination by vertically integrated utilities favoring their \nown generation resources” but asserts “utilities have no comparable incentive to discriminate \nagainst large load, as these customers represent valuable opportunities for new retail sales and \ninvestment.”27 These comments overlook that Transmission Owners are transmission and \ndistribution monopolists, and as Order No. 888 recognized, it is “inherent” and “inevitable” that \ntransmission monopolists will “act in their own self-interest to the detriment of others by refusing \ntransmission and/or providing inferior transmission to competitors”28—in this case, to force \ncustomers to take types of monopoly service, including gross-billed network transmission service \nand distribution service, that they do not need and do not want. It is not a question of whether \nTransmission Owners want more load—of course they do, but only in the configuration and \ndesigns that favor them. Utilities are discriminating against large load projects with configurations \nthat they disfavor because these configurations do not allow them to build more rate base and \n \n25 See, e.g., Initial Comments of International Energy Credit Association at 7 (filed Nov. 21, 2025) (stating load \ninterconnection delays are less prevalent in non-RTO regions, such as the Southeast) (“International Energy \nComments”). \n26 MISO States Comments at 8 (emphasis in original); see also Comments of MISO Transmission Owners at 16 (filed \nNov. 21, 2025) (stating there is “robust competition among utilities” and there is “every incentive to interconnect \nloads as efficiently as possible”) (“MISO Transmission Owners Comments”).  \n27 Comments of Maryland Public Service Commission at 4 (filed Nov. 21, 2025) (emphasis added) (“Maryland PSC \nComments”). \n28 Promoting Wholesale Competition Through Open Access Non-Discriminatory Transmission Servs. by Pub. Utils.; \nRecovery of Stranded Costs by Pub. Utils. & Transmitting Utils., Order No. 888, FERC Stats. & Regs. ¶ 31,036, \n31,682 (1996) (cross-referenced at 75 FERC ¶ 61,080 (1996)) (emphasis added)."},{"page":16,"startToken":5655,"endToken":6279,"text":"12 \nmaximize service charges. As discussed in the prior section, the record in the PJM Show Cause \nproceedings demonstrates this.29  \nC. The Commission Should Accommodate Regional Differences \nRTOs and numerous other entities highlight a third area of consensus, cautioning the \nCommission to “be mindful of regional differences that might limit the success of a ‘one size fits \nall’ mandate” as “[s]hifting to standardized large load interconnection procedures could nullify \ncurrently effective processes and/or delay significant work that has been undertaken and currently \nongoing.”30 The NOPR should continue to accommodate regional differences. While the NOPR is \n \n29 See, e.g., Constellation Energy Generation, LLC, Complaint Requesting Fast Track Processing, Docket No. EL25-\n20-000, et al., at 8 (filed Nov. 22, 2024) (“Co-locating a new large load with a generator results in faster service on \ndifferent terms but such projects are being held hostage by a few monopolies refusing to cooperate with reliability \nstudies related to interconnection modifications.”). \n30 Comments of the Midcontinent Independent System Operator, Inc. at 3 (filed Nov. 21, 2025) (“Consequently, the \nCommission should be mindful of regional differences that might limit the success of a ‘one size fits all’ mandate.… \nShifting to standardized large load interconnection procedures could nullify currently effective processes and/or \ndelay significant work that has been undertaken and currently ongoing.”) (“MISO Comments”); see Comments of \nthe Southwest Power Pool, Inc. at 2 (filed Nov. 21, 2025) (“SPP encourages the Commission to provide flexibility \nin any rules adopted based on the vast regional differences across the country.… Rather than pursuing a ‘one-size \nfits all’ approach, the Commission should consider allowing each Regional Transmission Organization (‘RTO’) and \nIndependent System Operator (‘ISO’) … the latitude to design for these differences.”) (“SPP Comments”); PJM \nComments at 4 (“If required, PJM would take all necessary steps to implement a federally-regulated large load \ninterconnection process…any centralized and uniform process must not exclude EDCs and TOs from the study and \nagreement process”); Comments of the New York Independent System Operator, Inc. at 3-4 (filed Nov. 21, 2025), \n(“Uniform solutions will not account for variations among regions resulting from unique region-specific planning, \ninterconnection approaches, and market structures.… [T]he NYISO urges the Commission to provide flexibility … \nto account for the unique circumstances and challenges that exist in its regions.”); Comments of ISO New England \nInc. at 5 (filed Nov. 21, 2025) (“The Commission should provide flexibility for the New England region to formulate \ninterconnection procedures that apply to transmission facilities that are already classified as PTF or Non-PTF.”) \n(“ISO-NE Comments”); see also, e.g., Comments of the State Attorneys General and Consumer Advocates at 6 \n(filed Nov. 21, 2025) (“[T]he commission should also ensure that any final rule does not preclude states and regional \ntransmission organizations (“RTO”) from instituting their own specific, tailored rules regarding large load \ninterconnections within their territories. While the State Entities support the development of baseline federal \nstandards grounded in statutory authority, different regions across the country should be allowed to build upon \nfederal standards to create rules that address unique regional challenges and opportunities.”); Comments of National \nGrid PLC at 3 (filed Nov. 21, 2025) (“Any Commission rule in this proceeding should allow regional flexibility to \nbuild on procedures already in effect or to adapt general requirements to the unique needs of each region.”) \n(“National Grid Comments”); Comments of the National Rural Electric Cooperative Association at 6 (filed Nov. 21, \n2025) (“any assertion of jurisdiction over large-load interconnections should be flexible enough to accommodate \nregional differences”) (“NRECA Comments”); Comments of Eversource Energy at 5 (filed Nov. 21, 2025) \n(encouraging the Commission to provide flexibility either “in the process described in the final rule or through the \naccommodation of regional variations as part of the compliance process”)."},{"page":17,"startToken":6279,"endToken":6681,"text":"13 \nunderway, the Commission should also continue to act expeditiously on pending large load \ninterconnection adjudications. This includes issuing a region-specific order in PJM.  \nD. The Commission Should Avoid Unnecessary Jurisdictional Fights \nA fourth area of consensus is that the Commission should avoid unnecessary jurisdictional \nfights in any national rule because a “jurisdictional dispute over load interconnection would be \ncounterproductive.”31 In Constellation’s view, the Commission has the authority to assert \njurisdiction over all large load interconnections to transmission facilities. But to the extent the \nCommission chooses to proceed on narrower, less-controversial grounds, it should assert \njurisdiction over hybrid facilities at a shared point of interconnection. The Commission’s \njurisdiction is over the interconnection facilities, not any retail sale. As discussed immediately \nbelow under Principle 1, the record demonstrates that hybrid facilities provide a “crystal clear” \nand “straightforward” case for federal authority.32 In the PJM proceedings, Constellation advocates \na replacement rate that only requires the Commission to exercise jurisdiction over hybrid facilities \n \n31 Maryland PSC Comments at 5 (“A jurisdictional dispute over load interconnection would be counterproductive.”); \nsee OPSI Comments at 2-3 (“Rather than relitigating the long-standing division of authority … it would be more \nefficient to search for solutions that promote consensus … rather than rushing questionable modifications to long-\nstanding, statutorily defined jurisdictional divisions.”); NY Transmission Owners Comments at 11 (“Prescriptive \nfederal mandates … could unsettle the well-established division of federal and state roles and disrupt ongoing state \nand regional work ….”); Comments of the Pennsylvania Office of Consumer Advocate and the Delaware Division \nof the Public Advocate at 10 (filed Nov. 21, 2025) (“The ANOPR risks lengthy, burdensome, and meritorious legal \nchallenges … and ignores the FPA’s explicit acknowledgements of state jurisdiction.”) (“PA Office of Consumer \nAdvocate & DE Division of Public Advocate Comments”); Motion to Intervene and Comments of DTE Electric \nCompany at 13 (filed Nov. 21, 2025) (“Expanding federal jurisdiction … risks jurisdictional disputes and regulatory \nuncertainty, stifling investment … any decision to pursue such expanded jurisdiction is likely to be challenged … \nand could impede investment for years.”). \n32 Constellation Comments at 7, 10; see also EPSA Comments at 12 (“The ANOPR states that ‘the interconnection of \nlarge loads to the transmission system falls under a practice directly affecting Commission-jurisdictional wholesale \nelectricity rates.’ That is clearly correct where hybrid facilities are concerned, for the same reason it is correct where \nthe generation portion of the hybrid facility is interconnecting on a stand-alone basis.”) (citation omitted)."},{"page":18,"startToken":6681,"endToken":6951,"text":"14 \nwith a shared point of interconnection (PJM Option 2), thereby avoiding broad jurisdictional \nquestions.33  \nII. \nConstellation Continues to Support the ANOPR’s Principles with Qualifications \nConstellation reaffirms its support for the ANOPR’s fourteen principles, with limited \nqualifications.34 Constellation offers additional comments on Principles 1, 4, 7, 8, 9, 10, 11, and \n14 below. \nPrinciple 1—Confirming Federal Jurisdiction Over Large Load Interconnections to \nInterstate Transmission Facilities \nConstellation agrees with the ANOPR’s principle that the Commission has jurisdiction \nover interconnections directly to transmission facilities.35 As Constellation explained in its initial \ncomments, such interconnections—as opposed to the rates applicable to retail customers—are well \nwithin the scope of the Commission’s jurisdiction under the FPA.36 But the Commission need not \naddress the full scope of its jurisdiction over large load interconnections in order to resolve the \npending PJM Show Cause proceedings. Rather, the Commission can rule immediately that it has \njurisdiction over the interconnection of hybrid facilities—that is, configurations with a shared \npoint of interconnection (i.e. the proposed PJM Option 2)—while further considering its \njurisdiction over large load interconnections more generally during the rule-making process.37 \n \n33 PJM Option 2 is firm Network Integrated Transmission Service with in-front-of-the-meter co-location. \n34 Constellation Comments at 7-43. \n35 ANOPR at ¶ 18. While the ANOPR adds that this principle is “consistent with the Commission’s seven-factor test,” \nthe Commission need not resort to that test to conclude that it has jurisdiction over large load interconnections to \ninterstate transmission facilities, as explained further below. \n36 See Constellation Comments at 7-13. \n37 See Constellation’s April 23, 2025 Show Cause Answer at 6."},{"page":19,"startToken":6951,"endToken":7378,"text":"15 \nHybrid facilities present an easy jurisdictional call.38 Hybrid large loads, such as the \nconfiguration in PJM Option 2,39 are transmission customers that can draw power both from the \nco-located generator as well as the grid. Regulation of the interconnection between a generator and \nthe interstate transmission grid is well within the scope of the Commission’s jurisdiction,40 and the \nCommission does not lose its jurisdiction over that interconnection simply because a load also \nhappens to interconnect at the same point. Even the ANOPR’s critics acknowledge that “hybrid \nconfigurations,” among others, should be “FERC-jurisdictional.”41    \nWhether the Commission has previously exercised its jurisdiction to regulate the \ninterconnection of hybrid facilities does not affect its ability to do so now. And the Commission \nhas good reason to exercise that jurisdiction now. As Constellation discussed in its comments and \nas demonstrated in the PJM Show Cause record, the current jurisdictional uncertainty over hybrid \nfacilities has given Transmission Owners the ability to delay or deny hybrid facility proposals and \nimpose terms that are neither just nor reasonable.42 \n \n38 See Constellation Comments at 7-9; see also Comments of Vistra Corporation at 31-32 (filed Nov. 21, 2025) (“[T]he \nco-location of load and generation at a single point of interconnection—represents the lowest hanging fruit for the \nCommission to make significant progress quickly in facilitating the infrastructure needed to win the AI race.”) \n(“Vistra Comments”); Entergy Comments at 12 (“If the Commission’s action is limited to providing new rules for \nexisting load that co-locates with new generation or existing generation interconnections, the Commission does not \nneed to expand its exercise of jurisdiction to interconnections of retail customers.”); EPSA Comments at 12 (“The \nANOPR states ‘the interconnection of large loads to the transmission system falls under a practice directly affecting \nCommission-jurisdictional wholesale electricity rates.’ That is clearly correct where hybrid facilities are \nconcerned.”).  \n39 See Constellation’s April 23, 2025 Show Cause Answer at 38. \n40 Pac. Gas & Elec. Co., 115 FERC ¶ 61,193, at P 36 (2006). \n41 Initial Comments of R Street Institute at 6-7 (filed Nov. 21, 2025); see also Pennsylvania PUC Comments at 11 \n(“There is no clear Congressional authorization to expand FERC jurisdiction to pure load interconnection of any \nsize. However, if limited to hybrid interconnections of load and generation at the same point-of-interconnection, \nthere may be greater room for discussion.”); SEIA Comments at 8 (“This jurisdictional finding should extend to any \ngeneration that may be co-located with the large load.”).  \n42 See Constellation Comments at 17-18; Constellation’s April 23, 2025 Show Cause Answer at 14-15."},{"page":20,"startToken":7378,"endToken":7665,"text":"16 \nThe Commission, in fact, has repeatedly asserted its statutory jurisdiction to root out undue \ndiscrimination. For instance, in Order No. 888, the Commission asserted its jurisdiction over \nunbundled retail transmissions because “electric utilities were discriminating in the ‘bulk power \nmarkets,’ in violation of § 205 of the FPA, by providing either inferior access to their transmission \nnetworks or no access at all to third-party wholesalers of power.”43 Likewise, in Order No. 841, \nthe Commission asserted its jurisdiction “to remove existing barriers to the participation of electric \nstorage resources (‘ESRs’) in the Regional Transmission Organization and Independent System \nOperator markets.”44 Although various trade groups representing utilities argued that the \nCommission lacked jurisdiction to “bar[] States from ‘broadly prohibiting’ local ESRs from \nparticipating in RTO/ISO markets,”45 the D.C. Circuit held that the Commission properly \nexercised its jurisdiction.46 And, in Order No. 2222, the Commission similarly asserted its \njurisdiction to remove “barriers to the participation of distributed energy resource aggregations in \nthe RTO/ISO markets,” as those barriers were “reduc[ing] competition and fail[ing] to ensure just \nand reasonable rates.”47  \nSo too here. Transmission Owners have erected artificial barriers to the interconnection of \nlarge loads to the interstate grid, and the Commission should therefore exercise its jurisdiction over \ninterconnections to stamp out such undue discrimination.  \n \n43 New York v. FERC, 535 U.S. 1, 11 (2002) (affirming Order No. 888).  \n44 Nat’l Ass’n of Regulatory Util. Comm’rs v. FERC, 964 F.3d 1177, 1182 (D.C. Cir. 2020). \n45 Id. at 1184. \n46 Id. at 1189. \n47 Participation of Distributed Energy Res. Aggregations in Markets Operated by Regional Transmission Org. & \nIndep. Sys. Operators, 172 FERC ¶ 61,247 at PP 26, 38-44 (2020)."},{"page":21,"startToken":7665,"endToken":8122,"text":"17 \nSome commenters wrongly argue that Section 212(h) of the FPA limits the Commission’s \njurisdiction over all large load interconnections.48 But that section does not change the analysis. \nSection 212(h) prohibits the Commission from issuing an order that is “conditioned upon or \nrequire[s] the transmission of electric energy: (1) directly to an ultimate consumer, or (2) to, or for \nthe benefit of, an entity if such electric energy would be sold by such entity directly to an ultimate \nconsumer.”49 That provision, in short, “prohibits the Commission from ordering retail wheeling \ndirectly to an ultimate consumer.”50 That, however, in no way limits the Commission’s jurisdiction \nto regulate a hybrid facility’s point of interconnection. As the Commission has explained, “section \n212(h) only applies to transmission orders, not requests for interconnection.”51 Transmission \nservice and interconnection service are two separate Commission-regulated services,52 and an \norder regulating the terms of an interconnection—even if that interconnection is necessary to \ntransmit energy—is not the same as an order directing the transmission of energy.53 Section 212(h) \n \n48 See, e.g., Initial Comments of the National Association of Regulatory Utility Commissioners at 4 (filed Nov. 21, \n2025) (“In addition, FPA section 212(h) prohibits FERC from directing the provision of transmission directly to end \nusers (retail wheeling).”); Comments of the Edison Electric Institute at 27 (filed Nov. 21, 2025) (“Congress’s \naddition of section 212(h) to the FPA, many decades after section 201 was enacted, may prevent a large load or its \nagent from obtaining transmission service absent state approval.”) (“EEI Comments”); NRECA Comments at 13-\n14 (“[T]he Commission is prohibited from using load-interconnection service to provide transmission service to an \nultimate consumer in violation of section 212(h) of the FPA.”).  \n49 16 U.S.C. § 824k(h). \n50 Detroit Edison Co. v. FERC, 334 F.3d 48, 54 (D.C. Cir. 2003). \n51 THSI bn, LLC, 185 FERC ¶ 61,032, at P 60 (2023); see also Pac. Gas & Elec. Co. v. FERC, 44 F. App’x 170, 173 \n(9th Cir. 2002).  \n52 United States DOE, 124 FERC ¶ 61,018, at P 27 (2008) (“While we recognize that there may be a practical linkage \nbetween interconnection and transmission (i.e., which the Commission has sometimes described as delivery) service, \nthe two services are nevertheless distinct, and the Commission has not required that they be linked.”). \n53 See Laguna Irrigation Dist., 95 FERC ¶ 61,305, 62,038 (2001) (“[S]ection 212(h), and its provisions, taken together, \nindicate an intent to preclude Commission orders requiring the delivery of energy either directly to retail customers, \nor indirectly to retail customers under certain circumstances. We did not do that here. We ordered only an \ninterconnection.”)."},{"page":22,"startToken":8122,"endToken":8537,"text":"18 \ntherefore does not prohibit the Commission from asserting jurisdiction over a hybrid facility’s \ninterconnection.  \nSimilarly, the Commission should reject the argument that its jurisdiction over large load \ninterconnection is limited to “where transmission service is provided to customers as an unbundled \nproduct.”54 The FPA does not limit the Commission’s jurisdiction over interstate transmissions—\nand, accordingly, interconnections to the interstate grid—based on whether the ultimate retail sale \nof that energy is bundled or unbundled.55 As the Commission has itself recognized, it has \njurisdiction over interconnections “based on the nature of interconnection to the transmission \nsystem generally, not the purpose for such interconnection (i.e., to make a wholesale sale or to \nmake a wholesale or retail purchase).”56 And, again, the ANOPR does not purport to regulate retail \nsales. \nThe Commission should also confirm that its jurisdiction over the interconnection extends \nto hybrid facilities’ low-voltage facilities that step down the power from the interstate grid at the \nshared point of interconnection to the load. Some commenters suggest that “last mile” facilities \nshould be deemed distribution facilities that are outside the Commission’s jurisdiction.57 But that \n \n54 Duke Comments at 7-9; see also Initial Comments of the National Association of State Utility Consumer Advocates \nat 7 (filed Nov. 21, 2025) (“[T]he plain language of the ANOPR would allow large loads in states without retail \nchoice to bypass retail distribution utilities to take service directly from wholesale markets or from third-party \ngenerators that are located at a hybrid facility and directly impinge on States’ authority over retail electricity sales.”); \nComments of the Northeastern Rural Electric Membership Corporation at 2-3 (filed Nov. 21, 2025) (“Granting a \nfederal right of interconnection to large loads could enable these loads to obtain de facto retail access to alternative \nsuppliers across the transmission system, even in states that maintain exclusive monopoly service territories and \nprohibit retail competition.”) (“NREMC Comments”).  \n55 See 16 U.S.C. § 824(b)(1). \n56 PJM Show Cause Order, 190 FERC ¶ 61,115 at P 72. \n57 See, e.g.,  Pennsylvania PUC Comments (“[L]ast mile facilities used exclusively for delivering energy sold for end-\nuse to customers satisfy all the factors to be classified as local distribution.”); PA Office of Consumer Advocate & \nDE Division of Public Advocate Comments at 6-7 (arguing that the ANOPR “bypasses the consideration that end-\nuse interconnection does not generally occur directly to transmission facilities, but through local distribution \nfacilities, which fall squarely within state jurisdiction” (internal quotations omitted))."},{"page":23,"startToken":8537,"endToken":8853,"text":"19 \nargument misstates the role that step-down facilities play with respect to large load \ninterconnections. A large load physically cannot interconnect to the grid without a step-down \nfacility that properly reduces the voltage.58 And because the step-down facility is part and parcel \nof the interconnection between the large load and the interstate grid, and because “interconnection \nis part and parcel of transmission of electric energy in interstate commerce,”59 it follows that that \nstep-down facility is part and parcel of the transmission system as well.   \nThis conclusion is supported by the plain text of the FPA. The statute provides the \nCommission with jurisdiction over “all facilities for [the interstate] transmission of … electric \nenergy.”60 Plainly understood, that means that any facility that is necessary for the interstate \ntransmission of energy—and, thus, interconnections to the interstate grid—is within the scope of \nthe Commission’s jurisdiction.  \nWhile it is true that, generally, “[l]ocal distribution systems will be of reduced voltage,”61 \nthat does not mean that every low-voltage facility is a distribution facility. For instance, the \nCommission has previously recognized its jurisdiction over “low-voltage transmission facilities” \nwhen “they are used to transmit electric energy in interstate commerce on behalf of a wholesale \npurchaser.”62 Here, the purpose of low-voltage step down facilities is precisely to enable a \nCommission-jurisdictional interconnection—they exist to allow the large load to interconnect with \n \n58 See U.S. Dep’t of Energy, “How It Works: Electric Transmission & Distribution and Protective Measures” at 1, \navailable \nat \nhttps://www.energy.gov/sites/default/files/2023-\n11/FINAL_CESER%20Electricity%20Grid%20Backgrounder_508.pdf.  \n59 Pac. Gas & Elec. Co., 115 FERC ¶ 61,193, at P 36 (2006). \n60 16 U.S.C. § 824(b)(1) (emphasis added). \n61 S. Cal. Edison Co., 153 FERC ¶ 61,384, at P 4 (2015). \n62 Midwest Indep. Transmission Sys. Operator, 109 FERC ¶ 61,157, at P 403 (2004)."},{"page":24,"startToken":8853,"endToken":9288,"text":"20 \nthe interstate grid.63 The facilities are not embedded within a distribution network or distribution \nsystem, nor are they used to serve multiple customers in a local area—hallmarks of typical \ndistribution facilities.64 Rather, their sole purpose is to enable a Commission-jurisdictional \ninterconnection, and because that is their sole purpose and function, they are within the scope of \nthe Commission’s jurisdiction as well. \nAnd it does not matter, as some commenters observe, that “power flows into [them] … \nwithout being reconsigned for wholesale sale.”65 That is but one factor of the Commission’s seven-\nfactor test, and it alone is not dispositive. As the Supreme Court has made clear, “[t]here is no \nlanguage in the [FPA] limiting FERC’s transmission jurisdiction to the wholesale market.”66 The \nSupreme Court in fact rejected the notion of a “bright jurisdictional line between wholesale \ntransactions and retail transactions” when it comes to the Commission’s jurisdiction over the \ntransmission of energy.67 Accordingly, the fact that power flows from the step-down facility to the \nlarge load (and not the wholesale market) has no bearing on the Commission’s transmission \njurisdiction.   \n \n63 Cf. Nat’l Ass’n of Regulatory Util. Comm’rs v. FERC, 475 F.3d 1277, 1282 (D.C. Cir. 2007) (affirming FERC’s \njurisdiction over “interconnections to a ‘distribution’ facility when the facility is included in a public utility’s \nCommission-filed OATT and  the interconnection is for the purpose of facilitating a jurisdictional wholesale sale of \nelectric energy.”).  \n64 See Cal. Pac. Elec. Co., LLC, 133 FERC ¶ 61,018, at P 46 (2010). \n65 Maryland PSC Comments at 3. \n66 New York, 535 U.S. at 16. Some commenters point to the Commission’s statement in Order 888 that “even when \nour technical test for local distribution facilities identifies no local distribution facilities for a specific transaction, \nwe believe that states have authority over the service of delivering electric energy to end users.” PA Office of \nConsumer Advocate & DE Division of Public Advocate Comments at 9 (quoting Order 888). But that statement was \nmade specifically “in the context of retail wheeling,” not step-down facilities. Promoting Wholesale Competition \nThrough Open Access Non-discriminatory Transmission Services by Public Utilities and Recovery of Stranded Costs \nby Public Utilities and Transmitting Utilities, Order No. 888, FERC Stats. & Regs. ¶ 31,783 (1996). Regardless, \nthat statement simply acknowledges that, consistent with the FPA, states have jurisdiction over the local distribution \nof energy. It did not purport to curtail the Commission’s clear jurisdiction over facilities for the transmission of \nenergy, especially hybrid facilities over which the Commission has long and properly asserted jurisdiction.  \n67 New York, 535 U.S. at 17."},{"page":25,"startToken":9288,"endToken":9657,"text":"21 \nAt any rate, the Commission’s seven factor test is of limited utility in this context. PJM, \nfor example, questions whether “the Commission’s seven-factor test [is] sufficiently workable to \napply on a case-by-case basis, with regulatory uncertainty, to inform the dividing line between \nfederal and retail jurisdiction over transmission versus distribution facilities.”68 As other \ncommenters have noted, the seven-factor test “would result in substantial uncertainty for loads” \nand result in a “lengthy process [that] would defeat the core purposes—speed and efficiency—\nwhich the ANOPR had in mind.”69 And there is no need for that here. Step-down facilities, as \nintegral elements of any large load interconnection, should be considered as part and parcel with \nthe interconnection and thus within the Commission’s jurisdiction. \nAsserting such jurisdiction, moreover, is necessary to protect the Commission’s \njurisdiction over interconnection. If the Commission does not assert jurisdiction over “last mile” \n(or, more accurately, “last meter”) large load interconnection facilities, Transmission Owners can \nleverage their control over that portion of those facilities to retain control over the interconnection \nof large loads more generally. That would defeat both the ANOPR’s purpose and the broad \nstatutory grant of jurisdiction to the Commission over all interstate transmission, including retail \ntransmissions and including interconnections. As noted above, the Commission has repeatedly \n \n68 PJM Comments at 4; see also Order No. 888-A, 62 Fed. Reg. at 12,370-71 (1996) (rejecting state commission’s \nargument that state jurisdiction should extend “to the ‘service’ of delivering electric energy to retail customers, \nwhich [the] state commission] would define to give it jurisdiction regardless of the nature and extent of the facilities \nused to make the delivery”). \n69 EPSA Comments at 14; see also Eolian Comments at 7 (“Unfortunately, the seven-factor test is no model of clarity, \nas evidenced by the volume of litigation it has engendered.”); Comments of NRG Energy, Inc. at 7 (filed Nov. 19, \n2025) (“As the Commission knows, application of the seven factor test can be complex and time-consuming. Indeed, \nin a number of the cases where the Commission has been tasked with applying the test, the issues have been \nsufficiently complex as to require hearing procedures, with the result that full adjudication of the issues has taken \nyears.”)."},{"page":26,"startToken":9657,"endToken":10057,"text":"22 \nasserted its jurisdiction to end undue discrimination by Transmission Owners in a variety of \ncontexts.70 It should do so again here.    \nPrinciple 4—Adopting Standardized Interconnection Rules and Expediting Service \nto Large Loads \nThe ANOPR’s fourth principle proposes standardized study deposits, readiness \nrequirements, and withdrawal penalties to large loads and hybrid facilities.71 Constellation and \nnumerous other commenters agree that standards for large loads and hybrid facilities are necessary \nto deter speculative load requests, undue discrimination, and unjust and unreasonable \ninterconnection terms and conditions.72 There are lessons to be learned from the standard generator \ninterconnection procedures established in Order No. 2003 and revised by Order No. 2023.73 Even \nso, perfect should not be the enemy of the good. \nWe also note that the Commission should be wary of arguments to adopt Transmission \nSecurity Agreements (“TSAs”) as a “model” for emulation.74 TSAs are only a “valuable tool to \n \n70 See supra at 16. \n71 ANOPR at ¶ 21. \n72 See, e.g., Comments of Buckeye Power, Inc. at 3 (filed Nov. 21, 2025) (supporting requirements to deter speculative \nprojects) (“Buckeye Power Comments”); Comments of American Transmission Company at 12 (filed Nov. 21, 2025) \n(similar) (“American Transmission Comments”); PA Office of Consumer Advocate & DE Division of Public \nAdvocate Comments at 19-20 (similar); Eolian Comments at 20-21 (stating standards are necessary to deter the \nincentive and ability to discriminate against their competitors.); Vistra Comments at 24 (stating standards are \nnecessary to deter the incentive and ability to discriminate against their competitors); Comments of Invenergy Wind \nDevelopment North America LLC, et al. at 7 (filed Nov. 21, 2025) (similar) (“Invenergy Comments”). \n73 See, e.g., MISO States Comments at 14-16 (discussing challenges arising under Order No. 2003 standard generator \ninterconnection procedures); Geronimo Comments at 8-11 (similar); Comments of Exelon Corporation at 15-18 \n(stating reliance on Order No. 2003 as a supportive analog may be “problematic”) (“Exelon Comments”); Comments \nof Southeast Public Interest Organizations (stating Order No. 2003 can inform the Commission’s approach to \nstandardized interconnection procedures and requirements) (“Southeast PIO Comments”); Comments of Electricity \nAlliance at 9 (filed Nov. 21, 2025) (stating the current situation resembles the circumstances leading to Order No. \n2003). \n74 Exelon Comments at 6 (commenting on the interconnection queues); see also Constellation Comments at 18; \nComments of Indicated PJM TOs at 16-17 (filed Nov. 21, 2025); Buckeye Power Comments at 26-29; AES Comments \nat 6, 9-11."},{"page":27,"startToken":10057,"endToken":10596,"text":"23 \nmeet the moment”75 if bounded by clear guideposts to avoid delay, deterrence of legitimate \nprojects, and anti-competitive conduct. \nPrinciple 7—Expediting Interconnection Studies for Curtailable Loads \nThe ANOPR proposes that interconnection studies for “large loads that agree to be \ncurtailable and hybrid facilities that agree to be curtailable and dispatchable should be \nexpedited.”76 There is strong record support for curtailable service.77 Voluntary curtailable load \nprovisions are being developed78 and adopted.79 Commenters recognize the benefits of voluntary \ncurtailable load as a bridge to firm service and a product itself. Stated simply, “[l]arge loads that \n \n75 Exelon Comments at 6; see also Constellation Comments at 19 (“Another current example of Transmission Owners \nleveraging their control over interconnection is in the negotiation of Transmission Security Agreements (“TSAs”). \nWhile Constellation is supportive of the concept of TSAs to deter speculative load interconnection requests, it is \nimportant that those TSAs contain some component reflective of upgrade costs (to create an incentive to locate most \nefficiently), and that they do not discourage legitimate projects by locking in one-size fits all gross billing \narrangements.”). \n76 ANOPR at ¶ 24. \n77 See, e.g., Comments of the Office of the Ohio Consumers’ Counsel at 8 (filed Nov. 21, 2025) (“OGC recognizes \nthe potential value of large loads that agree to be curtailable or dispatchable as system resources.”); Maryland PSC \nComments at 9 (“The Maryland PSC understands … incentivizing a willingness by large load customers to curtail—\nmay yield system benefit.”); see also Comments of California Independent System Operator Corporation at 12-13 \n(filed Nov. 21, 2025); MISO States Comments at 25; Comments of Tri-State Generation and Transmission \nAssociation, Inc. at 7-8 (filed Nov. 21, 2025) (“Tri-State Comments”); Comments of American Electric Power \nService Corporation at 3 (filed Nov. 21, 2025) (“AEP Comments”); Comments of Splight Inc. at 3 (filed Nov. 21, \n2025); Eolian Comments at 1-2, 18, 24-27, 29-33; Comments of Vantage Data Centers at 7-8 (filed Nov. 21, 2025); \nComments of Digital Power Network at 4 (filed Nov. 21, 2025); Southeast PIO Comments at 48-50; ECA Comments \nat 21; Comments of Engie North America, Inc. at 9-10 (filed Nov. 21, 2025); Comments of the Distributed Capacity \nParties at 1-2 (filed Nov. 21, 2025); Comments of the Information Technology Industry Council at 2 (filed Nov. 21, \n2025); Comments of Verrus at 2 (filed Nov. 21, 2025); Comments of Microsoft, Inc. at 10-11 (filed Nov. 21, 2025); \nComments of Thermal Battery Alliance at 4 (filed Nov. 21, 2025). \n78 See, e.g., SPP Comments at 6 (discussing SPP’s proposed new conditional non-firm Transmission Service process, \nknown as Conditional High Impact Large Load Service (“CHILLS”) that SPP states will “allow the expedited \nconnection of large loads” that are “subject to curtailment or interruption until they have the requisite transmission \nand sufficient Designated Resources.”). \n79 See Duke Comments at 6 (“[d]ue to near-term resource planning sensitivities, Duke Energy has incorporated \ntemporary curtailment provisions into new retail Electric Service Agreements to provide limited-term operational \nflexibility until new resources are placed into service.”); see also Comments of Longroad Energy Holdings, LLC to \nAdopt Open Access 2.0 at 7 (filed Nov. 21, 2025) (recommending ERCOT’s “Connect and Manage” process as a \nbest practice); AEP Comments at 7-10 (similar)."},{"page":28,"startToken":10596,"endToken":10885,"text":"24 \nagree to curtailment or other flexibility can help reduce or defer costly network upgrades, make \nbetter use of existing transmission capacity, and accelerate interconnection timelines.”80 \nIn the PJM Show Cause proceedings, PJM proposed Option 7 that would allow \ninterruptible large loads to interconnect at a faster pace.81 The Commission should approve PJM \nOption 7 as modified by Constellation.82 \nPrinciple 8—Allocating Network Upgrade Costs Based on Appropriate Studies \nConstellation takes no position on the ANOPR’s eighth principle about directly assigning \n100% of the network upgrades to large loads,83 but highlights two points raised in the ANOPR \ncomments: First, numerous Transmission Owners oppose direct assignment of network upgrade \ncosts to large loads, preferring to rate base these costs because according to them “it is in the \ninterest of all parties to protect native retail load customers.”84 Rolling billions of dollars of \nnetwork upgrades into rate base is not an intuitive way of “protecting customers.”85 Regardless, \nthe Commission’s policy should create strong incentives for co-location because co-location \nminimizes upgrade costs, and that is ultimately what protects consumers. This means that the \nCommission should ensure that Transmission Owners’ own favored configuration—directly to \ntheir transmission facilities, rolled-in, and charged gross rates—is not the exclusive means to \ninterconnect large loads as it creates comparatively weak incentives to co-locate. \n \n80 National Grid Comments at 5. \n81 See Answer of PJM Interconnection, L.L.C., Docket No. EL25-49-000, et al., at 18-19 (filed Mar. 24, 2025). \n82 See Constellation Comments at 26; see also Answer of Constellation Energy Generation, LLC, Docket No. EL25-\n49-000, et al., at 9 (filed Apr. 23, 2025). \n83 ANOPR at ¶ 25. \n84 National Grid Comments at 13. \n85 Id. (initial capitalization omitted)."},{"page":29,"startToken":10885,"endToken":11286,"text":"25 \nSecond, like jurisdiction, this is another fight that the Commission does not need to tackle \nhead on to issue an order in PJM. Using Susquehanna Nuclear as an example, PJM explained that \nunder its “Necessary Studies” process to modify an existing generator interconnection, any \nnecessary cost upgrades already are assigned “directly to the cost causer, which would seem to \naddress ANOPR Principle 8 without requiring any additional FERC action.”86 PJM also pointed \nout that its Necessary Studies process already studies the generator and the load together in a \nconfiguration like Susquehanna Nuclear’s proposed behind-the-meter service to the data center.87 \n“In this sense, at least some of the reliability impacts of load integrations (in particular, the \ntransmission impacts) can be accounted for where hybrid facilities are studied and implemented \nsubject to necessary study and local [utility] load integration processes today.”88 \nPrinciple 9—Granting the Customer the Option to Build \nConstellation supports extending the option to build to large-load interconnection \ncustomers on terms equivalent to those afforded to generator interconnection customers under \nOrder No. 845.89 Providing qualified customers the ability to construct interconnection facilities \nunder host-utility standards reduces delay, increases certainty, and mirrors the efficiency benefits \nthe Commission recognized when adopting the generator option to build.90 Several categories of \n \n86 PJM Comments at 8-9 (emphasis added).  \n87 Id. at 8. This is also relevant to ANOPR Principle 3 on combined studies, which Constellation discussed in its initial \ncomments. See Constellation Comments at 13-17. \n88 PJM Comments at 9. We discuss this further infra at Principle 14. \n89 ANOPR at ¶ 26; see Reform of Generator Interconnection Procedures and Agreements, Order No. 845, 163 FERC \n¶ 61,043, at PP 85-87 (2018) (“Order No. 845”), order on reh’g, Order No. 845-A, 166 FERC ¶ 61,137 (2019), \norder on reh’g & clarification, Order No. 845-B, 168 FERC ¶ 61,092 (2019). \n90 See Order No. 845, 163 FERC ¶ 61,043 at P 86 (finding that an interconnection customer may be able to complete \nthe transmission provider’s interconnection facilities and stand-alone network upgrades more quickly and at lower \ncost than the transmission provider, and citing evidence that a NextEra affiliate completed a “project one year sooner \nand for $6 million less than estimated by the transmission provider”); id. P 85 (explaining that the option to build \n“provid[es] interconnection customers more control and certainty during the design and construction phases of the \ninterconnection process”)."},{"page":30,"startToken":11286,"endToken":11827,"text":"26 \ncommenters support extending option-to-build parity, explaining that customers capable of \nconstructing facilities often do so more quickly and cost effectively than transmission owners and \nthat customer construction is consistent with efficient planning practices for both load and hybrid \nresources.91 Other commenters note that customers may build sole-use facilities so long as \nconstruction complies with utility standards and the facilities are transferred to the utility before \nenergization, a model Constellation fully supports.92 \nOpposition to extending the option to build comes largely from utilities and Transmission \nOwners who argue, without meaningful evidence, that only incumbents should construct \ninterconnection facilities, that large load customers lack the expertise or NERC status to do so, and \n \n91 See Comments of EDF Power Solutions, Inc. at 17 (filed Nov. 21, 2025) (“Load and hybrid facility interconnection \ncustomers should be afforded the same option to build interconnection facilities and network upgrades as currently \nprovided to generator interconnection customers. In hybrid facility interconnections especially, co-located \ngeneration is in a good position to undertake the option to build on behalf of the co-located facilities to expedite the \nconstruction of eligible upgrades.”) (“EDF Comments”); Comments of LS Power Development, LLC at 10 (filed \nNov. 21, 2025) (Large load developers should not be held back by transmission owner construction delays and cost.); \nNREMC Comments at 5 (“Interconnection customers who are not transmission owners should absolutely be \nafforded the same or equivalent option to build as generator interconnection customers. Transmission owners should \nnot be permitted to delay or impede the interconnection process if the customer has the capability to construct the \nnecessary facilities themselves. Allowing interconnection customers to exercise this option ensures timely project \ndevelopment, maintains a level playing field, and prevents unnecessary bottlenecks in the interconnection process.”); \nECA Comments at 22 (“Given the scale of needed infrastructure investment needed to meet large load growth driven \nby AI, data centers, advanced manufacturing and growth in the industrial sector, the Commission should ensure that \nlarge load customers have the opportunity to fund and build needed upgrades to support their growth. This approach \nhelps protect existing customers from inappropriate cost shifts by facilitating the ability for growing loads to pay for \ntheir own needs. Without this option … costs ... [are] allocated to all customers (including existing residential \nratepayers) in their zone.”); see also NY Transmission Owners Comments at 17-18 (“Option-to-build authority is \nappropriate only for facilities used exclusively by the requesting customer … [and] [f]or any facility planned, \nmodeled, or dispatched as part of the transmission network, the Transmission Owner must retain the right to fund, \nbuild, own, and operate the asset.”); Tri-State Comments at 8, (“Tri-State supports the interconnection customer’s \nright to build, as long as the same rules apply to the transmission owner and the interconnection customer … the \nupgrades eligible under the option to build must be stand alone upgrades and must be consistent with transmission \nowner’s design standards/requirements.”); American Transmission Comments at 20 (ATC encourages the \nCommission to incorporate transmission owner initial-funding in any future requirements related to load \ninterconnection procedures.) \n92 See Comments of the Pacific Gas & Electric Company at 18 (filed Nov. 21, 2025) (“Ownership of the customer \nconstructed facilities must be transferred to the utility after the facilities are completed and before energization.”) \n(“PG&E Comments”)."},{"page":31,"startToken":11827,"endToken":12396,"text":"27 \nthat customer construction could disrupt traditional utility roles or reliability obligations.93 These \nconcerns repeat arguments previously raised and rejected when the Commission adopted the \ngenerator option to build, where the Commission determined that customers can successfully \nconstruct facilities under utility oversight without undermining reliability and that customer \nconstruction can reduce cost and accelerate timelines.94 The Commission should therefore \nmaintain an option to build for large load customers.  \nPrinciple 10—Assigning Appropriate Upgrade Costs to Co-Locating Existing \nGeneration \nAs Constellation anticipated, Principle 10 was seized upon by parties who claim that \nexisting generators must always serve the grid—and only the grid—even though Principle 10 said \n \n93 See Comments of FirstEnergy Service Company at 10 (filed Nov. 21, 2025) (“Providing large load customers an \noption to build will … frustrate the ANOPR’s goal of accelerating the interconnection of large loads… The most \nefficient and cost-effective approach is to have experienced transmission-owning utilities continue to build the \ntransmission facilities associated with large load customers.”); PJM Transmission Owners Comments at 32, 33, 35. \n36 (“The Commission should not grant large load customers an option to build.… [T]here is no indication that these \nentities possess the relevant knowledge, expertise, or staffing sufficient to undertake the development and \nconstruction of electric transmission facilities…. As end-use customers, large load customers have no obligations to \nprotect or maintain the reliability of the transmission system.… An option to build … is likely to lead to disputes \nover what facilities qualify for the option.”); NY Transmission Owners Comments at 17 (“[A]ny extension of option-\nto-build authority to large load customers beyond customer-specific attachment facilities could conflict with a \nTransmission Owner’s obligation to ensure safe design, construction, and operation of the network facilities that it \nowns or operates.”); MISO Comments at 26 (“[L]oads are not currently required to register with NERC” and \ntherefore, Principle 9 is impractical.); see also PPL Comments at 15 (discussing allegedly poor history to generator \noption to build without citing any evidence). \n94 See Order No. 845, 163 FERC ¶ 61,043 at P 91 (2018) (“Concerns that the option to build, as revised by the Final \nRule, will compromise system reliability are misplaced because they ignore the safeguards for reliability already in \nplace for the existing option to build.… These safeguards, embodied in article 5.2 of the pro forma LGIA, require, \namong other things, that the interconnection customer exercise good utility practice and adhere to the standards and \nspecifications provided in advance by the transmission providers. Further, these safeguards give the transmission \nprovider the right to approve the engineering design, equipment acceptance tests, and the construction itself…In this \nFinal Rule, we make no changes to the requirements in article 5.2.”); id. P 39 (“[W]e emphasize that the Final Rule \ndoes not relieve interconnection customers of their existing responsibilities. Nor does it alter the ownership structure \nestablished in Order No. 2003 for interconnection facilities or network upgrades.”); id. P 40 (“We also disagree with \narguments that the NOPR will compromise system reliability. We find that, for those reforms for which commenters \nhave expressed reliability concerns, the Commission has either maintained existing safeguards or provided \ntransmission providers with sufficient discretion to ensure that the reforms will not interfere with system \nreliability…. [T]he option to build, as modified by this Final Rule, does not relax any of the safeguards that the \nCommission first established in Order No. 2003.”)."},{"page":32,"startToken":12396,"endToken":12808,"text":"28 \nno such thing.95 Old Dominion Electric Cooperative states that large load interconnections “should \nnot include any existing generators that deactivate all or part of their capacity to execute more \nlucrative large-load bilateral supply contracts with large loads.”96 Old Dominion Electric \nCooperative further seeks to disqualify existing generators who undertake significant uprates, \nalleging without any evidence that this “is simply a scheme that allows merchant generation \ncompanies to negotiate lucrative supply contracts with wealthy new large loads at the expense of \neveryday consumers.”97 The Maryland Public Service Commission adds that “[e]xisting \ngeneration currently serving customers should not be allowed to suspend their existing service, in \nwhole or in part, simply to serve new large load. Such a suspension would have an adverse impact \non cost and raise energy prices. Simply upgrading the transmission network does not resolve this \nproblem.”98 \nBut there is no rule that generators must only serve the grid, and any such rule would be \nillegal. Generators cannot physically or economically withhold their power, and with few \nlimitations, they can sell it to anyone they want.99 None of the RTO, the grid, network customers, \nsociety at large, or previous owners acquire (or reacquire) ownership interests in a power plant no \n \n95 See Constellation Comments at 27-32 (discussing potential confusion created by the language of Principle 10). \nPrinciple 10 states that “an existing generating facility that seeks to enter a partial suspension to serve a new load at \nthe same location must go through a system support resource (SSR)/reliability must run (RMR) type study. The \nstudy must consider system conditions, including forecasted load growth, at least three years after the proposed \nsuspension date…. We invite comments on whether and how resource adequacy should be considered in the \nSSR/RMR type study.” ANOPR at ¶ 27. \n96 Comments of Old Dominion Electric Cooperative at 10 (filed Nov. 21, 2025) (emphasis added) (“ODEC \nComments”). \n97 Id. \n98 Maryland PSC Comments at 11-12 (emphasis added); see also PG&E Comments at 20 (“It is important that existing \ngenerators be available for or otherwise ensure reliability for all customers on the electrical grid rather than agreeing \nto serve a single large load customer at the expense of other customers.”). \n99 More precisely, generators can sell their power to any willing customer in their region. If they seek to sell outside \ntheir region, limitations may apply. The co-location configurations commonly discussed with large load \ninterconnections would not involve non-regional sales."},{"page":33,"startToken":12808,"endToken":13489,"text":"29 \nmatter how long the plant has been in service.100 The concept that generators may only serve the \ngrid is itself antithetical to competitive power markets, which have been a core focus of federal \nelectric policy for at least thirty years.101  \nIt also is wrong to treat an existing generator as if it is retiring when it starts serving a large \nload102 because—first and foremost—it is not retiring and is instead continuing to serve load. To \nassert otherwise would require assuming that there is no obligation to serve the large load. But \nlarge loads must be served like any other load.103 The Electric Power Supply Association also \nexplained that even if an existing generator “is moved behind-the-meter to serve data center load,” \n \n100 Imagine a scenario where RTO price outcomes do not reflect supply and demand fundamentals (i.e., they are \nregularly too low) or are subject to frequent intervention (reduction) by other forces. Is an existing generator’s only \nrecourse to declare bankruptcy? Of course not. They can look for buyers who attribute greater value to their product, \nthe same as for nearly every other product in America’s free enterprise capitalist system. \n101 Promoting Wholesale Competition Through Open Access Non-Discriminatory Transmission Servs. by Pub. Utils.; \nRecovery of Stranded Costs by Pub. Utils. & Transmitting Utils., Order No. 888, FERC Stats. & Regs. ¶ 31,036, \n31,682 (1996) (cross-referenced at 75 FERC ¶ 61,080 (1996)), order on reh’g, Order No. 888-A, FERC Stats. & \nRegs. P 31,048 (cross-referenced at 78 FERC ¶ 61,220), order on reh’g, Order No. 888-B, 81 FERC 61,248 \n(1997), order on reh’g, Order No. 888-C, 82 FERC ¶ 61,046 (1998), aff’d in relevant part sub nom. Transmission \nAccess Pol’y Study Grp. v. FERC, 225 F.3d 667, 343 U.S. App. D.C. 151 (D.C. Cir. 2000), aff’d sub nom. N.Y. v. \nFERC, 535 U.S. 1, 122 S. Ct. 1012, 152 L. Ed. 2d 47 (2002). \n102 See Motion to Intervene and Initial Comments of the New England Consumer-Owned Systems and Energy New \nEngland, LLC, at 14 (filed Nov. 21, 2025) (asserting that “retirement undertaken for the purpose of serving new \nprivate load outside of market constructs presents significant market integrity and consumer-protection concerns”) \n(“New England Consumer-Owned Systems Comments”). “Retirement … for the purpose of serving new private \nload” is akin to transferring within the company, not retiring.  \n103 The Independent Market Monitor for PJM’s ANOPR Comments attach a complaint it filed against PJM claiming \nthat PJM cannot serve large loads until it first assures reliability. See Comments of the Independent Market Monitor \nfor PJM at 6 (filed Nov. 25, 2025). There is no such exception to the general duty to serve load. See Constellation \nComments at 39 (“Nearly every jurisdiction in the United States has promulgated regulations establishing a duty to \nserve.”); see, e.g., 220 Ill. Comp. Stat. 5/8-101 (“[a] public utility shall, upon reasonable notice, furnish to all persons \nwho may apply therefor and be reasonably entitled thereto, suitable facilities and service, without discrimination \nand without delay”); N.J. Stat. Ann. § 48:3-3(a) (“No public utility shall provide or maintain any service that is \nunsafe, improper or inadequate, or withhold or refuse any service which reasonably can be demanded or \nfurnished….”); Va. Code Ann. § 56-234(A) (“It shall be the duty of every public utility to furnish reasonably \nadequate service and facilities at reasonable and just rates to any person, firm or corporation along its lines desiring \nsame.”); see also PJM Transmission Owners Comments at 26 (“transmission owners have a duty to meet the \ndemands of their customers”). In the same vein, the Maryland Public Service Commission cited a PJM Independent \nMarket Monitor study that “removing 10,000 MW of nuclear generation in the entire PJM footprint would have \nincreased capacity prices in the state of Maryland by approximately 47% ($526 million) relative to the 2025/2026 \nBase Residual Auction (‘BRA’) results.” See Maryland PSC Comments at 10 (emphasis added). But there is no \n“removing” or “retiring” of nuclear generation when it will continue to serve load."},{"page":34,"startToken":13489,"endToken":13905,"text":"30 \nit “could still be serving the grid, depending on whether and how the load is connected, and the \nnature of the flexibility of the load….”104 Thus “[a]ny reliability assessment for co-located or \nhybrid arrangements must be limited to whether and how the proposed new load can be reliably \nand safely interconnected to the grid. As an example, PJM’s Necessary Study process engages in \nsuch an assessment.”105  \nConstellation agrees that the correct reading of Principle 10 is that a “partial suspension” \nmay arise “in situations in which the RTO requires the generator to delist capacity when a generator \nserves load directly behind-the-meter and the load takes no transmission service,” and that PJM’s \n“Necessary Study” process is the “reliability-type study” the ANOPR had in mind.106 The \nSouthwest Power Pool Transmission Owner Group explained these “reliability” and other “RMR-\ntype studies” as follows: \nThe [Southwest Power Pool Transmission Owner] Group agrees that an existing \ngeneration resource that intends to divert a material amount of its capacity to serve \na new large load at the same location should first submit to a study by the \ntransmission provider to determine whether the diversion of that generation \ncapacity will undermine reliable transmission. That approach is consistent with the \ncurrent use of studies in all organized markets (e.g., Necessary Studies in PJM, \n \n104 EPSA Comments at 17-18; see also MISO Comments at 27, explaining:  \nIn MISO, there can be no suspension (partial or otherwise) of a generator if it is still synchronously \nconnected to the transmission system. Under MISO’s Tariff, a disconnected generator would be \nconsidered a generator retirement, which is reviewed pursuant to Attachment Y and includes MISO \nconducting a reliability study to determine if the proposed retirement will result in local reliability \nissues. If the study finds local reliability issues, MISO could require the generator to remain connected \nto the transmission system until necessary transmission upgrades are constructed and operational. \nMISO load would pay for the upgrades required to resolve the local reliability issues. However, if the \ndisconnected generator later proposes to reconnect to the MISO transmission system, it would be \nassessed the costs of the upgrades. \n105 EPSA Comments at 18. \n106 See Constellation Comments at 27-28, citing ANOPR at ¶ 27; see also New England Consumer-Owned Systems \nComments at 16 (opposing use of “SSR/RMR constructs” to study an existing generation’s “partial suspension” to \nserve large load as “misconceived” and “misguided for several reasons,” asserting that this would likely “impose \nsubstantial costs on consumers”)."},{"page":35,"startToken":13905,"endToken":14447,"text":"31 \nSSR studies in MISO, and other RMR-type studies) to evaluate the reliability \nimpacts caused by the loss of network generation.107 \n \nThis is a reasonable reading of the ANOPR. But even if, arguendo, the ANOPR intended \nthat a “partial suspension” should be treated as a retirement, Shell Energy explains that “[e]xisting \ngenerators that retire are not typically allocated these network upgrade costs, existing generators \nthat exit a region to serve load in a different region are not allocated these network upgrade costs, \nand other generators selling power bilaterally are not allocated these network upgrade costs.”108 \nFinally, if, as the ANOPR suggests, the concerns animating Principle 10 are resource \nadequacy and problems with current load forecasts, the solution is to fix the market so it is better \nable to respond to the resource adequacy issue and to fix the load forecast.109 Constellation has \nproposed solutions in its initial comments.110 \n \n107 Comments of the Southwest Power Pool Transmission Owner Group at 10 (filed Nov. 21, 2025) (emphasis added); \nsee also MISO Transmission Owners Comments at 29-30 (“If [an] existing generation resource … remains \nconnected synchronously to the transmission system, such an arrangement would likely not implicate the same \nreliability concerns associated with a generator completely disconnecting from the transmission system, warranting \na different type of study” than MISO’s “SSR studies and related provisions [that] only apply in situations where a \ngenerator completely disconnects from the grid because it is suspending operations or is retiring”) (emphasis \nadded). \n108 See Comments of Shell Energy North America (US), L.P. at 8 (filed Nov. 24, 2025) (“Shell Energy does not support \nexisting generation having discriminatory and punitive provisions that it must pay for network upgrades for engaging \nin a bilateral capacity sale.”) (“Shell Energy Comments”); see also id., seeking clarification:  \n“One of the clarifications needed under this principle is how generators, new or existing, that sell to \nload under a hybrid or co-located agreement are accounted for in centralized capacity markets or \nbroader RA programs—if such sales are treated as retired resources, or if such sales are treated as \ntraditional bilateral contracts. The proposal as written could imply that the generation component of \nhybrid/co-located load and generation resources does not have a must-offer obligation into capacity \nmarkets or may not be tracked under existing RA and procurement programs. This is not the current \ntreatment of bilateral capacity sales under RA programs….” \n109 See ANOPR at ¶ 27 (“The study must consider system conditions, including forecasted load growth, at least three \nyears after the proposed suspension date…. We invite comments on whether and how resource adequacy should be \nconsidered in the SSR/RMR type study.”) (emphasis added); see also Talen Comments at 10 (“Without greater \naccuracy in the load forecast, the likely outcome [of an RMR-type study] is an overestimate of anticipated load \ncausing overstudy and more upgrades than actually necessary. In addition, requiring an analysis based on three years \nof forecasted load data seems punitive and discriminatory as no other load classes are required to perform ‘forward-\nlooking’ studies that assess their potential impact on the transmission system.”).  \n110 See Constellation Comments at 40-43 (proposing load forecast improvements and enhancements to PJM’s existing \nreliability backstop mechanism already offered in PJM’s stakeholder process)."},{"page":36,"startToken":14447,"endToken":14733,"text":"32 \nPrinciple 11—Basing Transmission Rates on the Quantity of Capacity and Energy \nBeing Transmitted Across the Transmission System to the Load  \nConstellation agrees with netting charges for hybrid facilities “as that value amount reflects \nthe quantity of capacity and energy that is being transmitted across the transmission system to the \nload.”111 Several Transmission Owners disagree, claiming that “to ensure fairness and avoid \nimplementation complexity, the Commission should make a gross load approach the default for \nboth ancillary services and transmission, subject to exception only if a utility supports and the state \napproves a different approach.”112 But it is not “fair” to ignore the fact that a hybrid facility load \nis being directly served by a generator and thus not relying on “capacity and energy … being \ntransmitted across the transmission system” in assessing charges. And “complexity” is unlikely \ngiven that meters exist to measure precise flows. PJM and ISO-NE, moreover, have been netting \nBehind-the-Meter Generation and load for years.113 And allowing a customer to avoid gross \ncharges “only if a utility supports” it would just license the very discrimination that the \nCommission should be eradicating. \nSPP raises a legitimate issue with netting: “the hybrid resource requires transmission to be \nbuilt and maintained, yet the hybrid facility avoids the coincident peak upon which billing is \ncurrently calculated.”114 This is exactly why Constellation has proposed that the appropriate \ntransmission rate would be the greater of net transmission usage or a standby charge based on a \n“customer-designated firm load subscription level of what the customer could draw from the \n \n111 ANOPR at ¶ 28. \n112 EEI Comments at 16. \n113 See Constellation Comments at 33-34 (citing PJM and ISO-NE netting cases). \n114 SPP Comments at 13"},{"page":37,"startToken":14733,"endToken":15069,"text":"33 \ntransmission system.”115 Large loads have never tried to escape paying their fair share of \ntransmission charges, but it would not be fair to assume hybrid facilities use the grid like any other \nload. \nWe further note that there is wide support in the record for different levels of transmission \nservice to be elected by the load, including curtailable service (see Principle 7), or non-firm or “as-\navailable” service for various large load configurations.116 The modern grid cannot thrive in the \nTransmission Owners’ preferred service model of one-size-fits-all and everyone-pays-the-same. \nThe model does not accommodate efficient outcomes needed for current load configurations, is \nnot as absolute as the Transmission Owners suggest (at least not in PJM and ISO-NE where netting \nis routine for some customers) and, even if it were, is a relic whose time has passed.  \nPrinciple 14—Meeting Reliability Standards \nThe ANOPR states that “utilities serving large loads must meet all applicable NERC \nreliability standards and OATT provisions.”117 PJM highlighted the Necessary Studies process \nunder its Tariff and the Susquehanna Nuclear example of its application (a proposed behind-the-\nmeter co-location with a data center) and concluded “at least some of the reliability impacts of \nload integrations (in particular, the transmission impacts) can be accounted for where hybrid \nfacilities are studied and implemented subject to [N]ecessary [S]tudy and local [utility] load \nintegration processes today.”118 If there are any additional reliability concerns (in PJM or \n \n115 See Constellation Comments at 34-35 (citing Testimony of Zachary Ming at 29 (Exh. 2 to Constellation’s April 23, \n2025 Show Cause Answer)). \n116 See, e.g., SPP Comments at 14 (“SPP and its stakeholders are currently developing … a flexible, non-firm, \nTransmission Service option” and a “usage-based transmission charge is a fundamental change in how SPP currently \ncharges for Transmission Service across the SPP Transmission System.”); Eolian Comments at 34-35 (“Non-firm \ninjection and withdrawal rights will be necessary to realize the economic benefits of hybrid resources”). \n117 ANOPR at ¶ 31. \n118 PJM Comments at 9."},{"page":38,"startToken":15069,"endToken":15513,"text":"34 \nelsewhere), Constellation urges that the Commission adopt the three measures that Constellation \ndeveloped jointly with Amazon, Calpine, Google, Microsoft, and Talen to remedy reliability \nconcerns without delaying large load interconnections: (1) load forecasting and modeling \nimprovements, (2) new demand side products, and (3) reliability backstop enhancements. \nCommenters universally agree accurate load forecasts are critical to addressing resource \nadequacy,119 and consensus is building for new demand side products and reliability backstop \nenhancements.120 \n \n119 See, e.g., Shapiro & Youngkin Comments at 1-2 (stating a large load addition proposal “could be even more \nimpactful if FERC were to develop national standards and guidelines for RTO [large load addition] forecasts.”); \nBuckeye Power Comments at 20 (“Deterring speculative projects will improve load forecasts and right-size \ntransmission investment.”); PSEG Comments at 9 (“[R]eforms must be implemented to ensure the accuracy of the \nregional load forecast, which is a key input into both transmission planning and capacity market parameters.”); SEIA \nComments at 4 (“Improving the accuracy of load projections will, in turn, support more effective transmission \nplanning and generation development…. When forecasts reflect realistic expectations of future demand, they help \nsend accurate price signals to both suppliers and consumers, supporting the development of a reliable and cost-\neffective grid. Accurate load forecasting is essential to ensure that rates remain just and reasonable.”); Comments of \nIndustrial Customer Organizations at 4 (filed Nov. 21, 2025) (recommending that the Commission focus on \n“enhancing the transparency of load forecasting and assumptions underlying transmission system studies”) \n(“Industrial Customer Comments”); Invenergy Comments at 6 (recommending that the Commission require \ntransmission providers to “produce transparent, publicly accessible, and timely load forecast information that \ndistinguishes between confirmed and speculative load” to incentivize generation development); Shell Energy \nComments at 5-6 (stating security deposits should be constructed to discourage speculative or duplicate applications \nand enhances the accuracy of load projections); Comments of Google LLC at 14 (filed Nov. 21, 2025) \n(recommending forecasts include only large new loads backed by meaningful financial commitments); Vistra \nComments at 31 (stating the Commission has “many tools” to improve resource adequacy including supporting load \nforecasting reforms). \n120 ISO-NE Comments at 9 (filed Nov. 21, 2025) (“a large load that agrees to be curtailed should participate in a \nwholesale-market based program (e.g., as a Demand Response Resource or Dispatchable Asset Related Demand).”); \nEDF Comments at 18 (“Services provided by curtailable load should be eligible for demand response revenues.”); \nIndustrial Customer Comments at 4 (recommending the Commission incentivize “load flexibility commitments, \ndemand response, and bring-your-own generation options”); Talen Comments at 2 (“[T]he Commission should \ndirect each RTO/ISO to adopt Reliability Backstop Auctions, which is already present in PJM’s Tariff.”) (citation \nomitted)."},{"page":39,"startToken":15513,"endToken":15901,"text":"35 \nGeneral Principle—Rejecting Undue Discrimination Against Existing Generation \nWhile there is not a specific principle on discrimination in the ANOPR, it is one of its \ncentral themes.121 The “Need for Reform” section specifically calls out non-discrimination against \n“existing generation facilities:” \nIn light of the unprecedented current and expected growth of large loads seeking to \ninterconnect to the transmission system, and to provide open access and non-\ndiscriminatory access to the transmission system, it has become necessary to \nstandardize interconnection procedures and agreements for such loads, including \nthose seeking to share a point of interconnection with new or existing generation \nfacilities (hybrid facilities).122 \n \nUnfortunately, this has not stopped discrimination, and some parties even re-define “hybrid \nfacilities”—some expressly, some more subtly—to exclude “existing generation resources.”123  \nThere are at least three types of undue discrimination against existing generation resources \neither already occurring or being contemplated that the Commission must affirmatively reject: \nFirst, as discussed above in Section I.A.,124 Transmission Owners continue to refuse to process \nhybrid facility interconnections involving existing generation or condition service on the large \nloads arranging for other services from the Transmission Owner. Constellation previously \nproposed—and the Commission should adopt—a rule that “[n]o Transmission Owner can expedite \n \n121 See Secretary’s Letter at 1 (“large loads, including AI data centers, served by public utilities must be able to connect \nto the transmission system in a timely, orderly, and non-discriminatory manner”) (emphasis added); id. at 2 (“My \nproposal today sets forth a series of principles that are intended to ensure efficient, timely, and non-discriminatory \nload interconnections.”) (emphasis added).  \n122 ANOPR at ¶ 12 (the “Need for Reform”) (emphases added). \n123 See Maryland PSC Comments at 6 (“To the extent that hybrid arrangements are to be encouraged and incentivized, \nthe Maryland PSC believes that a “hybrid facility” could be defined as new load and new generation and/or storage \nthat are physically located together, with the load situated in front-of-the-meter.”) (excluding “existing”); PPL \nComments at 17 (“The ANOPR adopts two options for co-located load: those sited ‘near … a new generation \nfacility’ and those ‘at the same point of interconnection as a new generation facility,’ the latter of which it defines \nas ‘hybrid facilities.’”). This is misleading as the definition of “hybrid facilities” includes “existing generation \nresources.” \n124 See supra at 5-7."},{"page":40,"startToken":15901,"endToken":16291,"text":"36 \nservice or study processing for projects taking the Transmission Owner’s preferred type of service \nor configuration, or refuse to process a complete large load interconnection request on the ground \nthat the large load has not ‘arranged for wholesale transmission or retail distribution service.’”125 \nSecond, as discussed above in Principle 10,126 some parties propose onerous studies or \ndisproportionate costs on existing generation seeking to serve large loads, including “reliability” \nstudies that assume the existing generator is retiring and must goldplate the grid to accommodate \nits departure. These resources are not retiring and, even if they were, this exaggerated level of \nupgrades is not what retiring resources are required to fund. These punitive measures are designed \nto prevent existing generators from serving any other customer than the grid. If reliability is the \nconcern, the Commission should order appropriate reliability enhancements instead of \ndiscriminating against existing resources.127 \nThird, many parties propose discriminatory “Bring Your Own Generation” proposals in \nwhich large loads can only interconnect to the grid or receive interconnection favors (expedited or \nseparate interconnection process) if they bring new generation resources.128 There is not a specific \nprinciple on this issue in the ANOPR, but it is related to Principle 3 on “combined studies” because \nBYOG proposals typically combine interconnection studies or provide other interconnection \n \n125 Constellation Comments at 50-51 (citing PJM Show Cause Order, 190 FERC ¶ 61,115 at P 75). \n126 See supra at 27-31. \n127 See supra at 33-34. \n128 See, ODEC Comments at 10 (“While ODEC does support an option for customers to interconnect and build their \nown generation if it is located on the same parcel with a single interconnection point, the generation should be ‘new.’ \nThis should not include any existing generators that deactivate all or part of their capacity to execute more lucrative \nlarge-load bilateral supply contracts with large loads that possess unlimited financial resources. The definition of \nnew resources should be resources that have not previously injected energy into the grid.”); International Energy \nComments at 7 (“Under the DCC’s proposed BYOG Pathway, Data Center applicants will be given an expedited \nreview and approval of their interconnection of both a large load (e.g., a Data Center) and a new electric generator, \nif both are brought together to the local utility in the ‘same Locational Deliverability Area’”); see also IMM \nComplaint."},{"page":41,"startToken":16291,"endToken":16777,"text":"37 \nfavors.129 Rather than opening the floodgates to the type of discrimination that most BYOG \nproposals contemplate, the Commission should first consider measures such as improved load \nforecasting, additional voluntary demand response products, and market-based solutions that \nminimize price discrimination between new and existing resources, such as the Reliability \nBackstop Alternative (“Enhanced Backstop”) advanced by the Joint Stakeholders, including \nConstellation, in the PJM stakeholder process and discussed in our initial comments.130 In the event \nPJM’s capacity auction fails to procure sufficient resources, this proposal adds to PJM’s existing \nReliability Backstop to target incremental capacity while minimizing harms to the market.131 The \nproduct being procured is the Capacity Performance product, eliminating the need for the \ndevelopment of complicated qualification and performance criteria. Eligibility includes both new \nand existing resources that did not clear in the BRA, likely because they are “facing large capital \n \n129 See Constellation Comments at 14-17 (discussing discriminatory BYOG proposals). PJM Option 6 is a BYOG \nproposal that would extend favorable interconnection treatment to generation associated with large loads, but only \nnew generation is eligible. Id. at 15. Other proposals would go further, extending favorable interconnection treatment \nto loads with their own new generation, “effectively creating a powerful disincentive for new load to contract with \nexisting resources.” Id. at 16.  \n130 See Constellation Comments at 42-43; see also Exh. 1, Patterson Aff. (discussing Enhanced Backstop proposal). \n131 See Exh. 1, Patterson Aff. at P 25 (“Enhanced Backstop … creates an additional supplemental pool of supply that \nkicks in to improve reliability only under very tight market conditions without suppressing the capacity price signal \nbelow where it would have otherwise cleared.”); id. (“Setting the Procurement Threshold at 98% of the Reliability \nRequirement strikes a balance between ensuring that the market is able to achieve a reasonable minimum level of \nreliability and also providing a cushion for clearing lumpy offers while still staying below the point on the demand \ncurve (99% of the Reliability Requirement) where the backstop would have a suppressive impact on the clearing \nprice.”); id. at P 26 (“The Procurement Threshold also limits the impact of the Enhanced Backstop on market \noutcomes in subsequent years following the year in which it is initially triggered because the Procurement Threshold \nlimits the volume of supply that receives multi-year capacity commitments.”); id. at P 27 (“Limiting the maximum \nterm for multi-year price cap offers to seven years and clearing these offers in increasing order of term when the \nEnhanced Backstop is triggered, with shortest-term offers cleared first, also limits the potential for long-term price \ndistortion due to the operation of the Enhanced Backstop.”); id. at P 29 (“[L]imiting the Enhanced Backstop to the \nfour delivery years covered by the most recent Periodic Review of the RPM limits any impact that the Enhanced \nBackstop may have on long-term market expectations and thus reduces any chilling impact it may have on market \nparticipants’ investment decisions.”)."},{"page":42,"startToken":16777,"endToken":17193,"text":"38 \nexpenditure requirements” to continue operating.132 While existing market mechanisms should be \nsufficient to ensure resource adequacy even during periods of rapid demand growth, the Joint \nStakeholders’ Enhanced Backstop proposal, as described in more detail in the Affidavit of Aaron \nPatterson, allows capacity resources to obtain capacity price certainty for more than one year and \nshould resolve any doubts and with far less market harm than discriminatory BYOG proposals. \nThe FPA prohibits undue discrimination, with specific provisions against discrimination \nduring shortage conditions such as those identified in the ANOPR.133 It is unlawful, for example, \nto favor new generation over existing generation in taking measures to remedy the shortage,134 or \nto decide not to serve large loads to ensure service to others.135  \nPolicies in favor of new resources are called “vintaging,” and they have long been \ndiscredited. Over a half century ago, the Commission analyzed the practice of establishing prices \nfor natural gas based on contract date vintaging whereby one rate applied to “‘old’ or ‘flowing’ \ngas (based principally on historic test year costs) and another for ‘new’ gas (based on current costs \n \n132 Old Dominion Electric Cooperative asserts that “[t]he definition of new resources should be resources that have \nnot previously injected energy into the grid” and opposes eligibility for existing resource that have invested in \nsignificant uprates. ODEC Comments at 10. Old Dominion Electric Cooperatives calls uprate eligibility “simply a \nscheme that allows merchant generation companies to negotiate lucrative supply contracts with wealthy new large \nloads at the expense of everyday consumers.” Id. To the contrary, the market signal should be for investment in \nuprates. \n133 See 16 U.S.C. § 824a(g). \n134 Id. (the “manner” of addressing “any anticipated shortage of electric energy or capacity” to “insure continuity of \nservice to customers,” must ensure that all persons served by a public utility are treated “without undue prejudice or \ndisadvantage”) (emphasis added). \n135 This is a fourth type of discrimination that has been prominent, at least in some proposals in PJM, which is \ndiscrimination against large load as compared to “regular” load. PJM’s ill-fated non-capacity-backed load (“NCBL”) \nproposal would have allowed PJM to curtail large load before other load. This is distinct from large loads voluntarily \nchoosing to be curtailable (see, e.g., ANOPR Principle 7) where “the load is electing to receive a lower quality \ntransmission service.” Constellation Comments at 55-57 (citing Testimony of Zachary Ming at 34 (Exh. 2 to \nConstellation’s April 23, 2025 Show Cause Answer))."},{"page":43,"startToken":17193,"endToken":17407,"text":"39 \nand designed to provide incentives for future development).”136 The Commission held that \n“vintaging by contract date is an anachronism which should be eliminated.”137 The Commission’s \nrationale was that contract vintaging did not “respond[] to the present need for increased \nexploration and development” because the incentives applied to “‘new’ gas ratemaking are totally \nlost as to undeveloped acreage committed under old contracts.”138 Vintaging suffers from the same \nold “anachronistic” flaws today as it did in 1973 when the Commission rejected it. \nBut vintaging is the zombie of energy policy; no matter how many times it is struck down, \nit rises from the grave. It is a nearly irresistible policy temptation to target new resources and pay \nthem extra or grant them special treatment to bring them into existence. The problem is that it takes \nmore than just new resources to supply the power system—we also must retain existing resources. \nThe inevitable consequence of vintaging is a constant churning of resources caused by the \ndistortion of price signals designed to create resource adequacy at lowest cost via market \ncompetition—not special favors. \n \n136 Re Area Rate Proceeding for Rocky Mountain Area, 49 FPC 924, 942 (1973) (citing Opinion No. 468, Permian I, \n34 FPC 159, 185 (1965)). \n137 Id. \n138 Id."},{"page":44,"startToken":17407,"endToken":17612,"text":"40 \nCONCLUSION \nWHEREFORE, Constellation respectfully requests that the Commission issue an order on \nthe merits in PJM139 by the end of the year and a NOPR by the end of the year or as soon as possible \nthereafter.  \n \n \n \n \n \n \n \n    Respectfully submitted, \n \n \n \n \n \n \n \n     \nDecember 5, 2025 \n \n \n139 If the Commission determines it is not ready to issue a full order, it should still rule on hybrid facilities with a \nshared point of interconnection (resolving jurisdiction and rates) and timeliness provisions. See Constellation \nComments at 47-51. \n \nCarrie Hill Allen \nSr. Vice President & Deputy General Counsel \nSeth Lucia \nAssistant General Counsel \nConstellation Energy Generation, LLC \n250 Massachusetts Ave. NW, Suite 760 \nWashington, D.C. 20001 \ncarrie.allen@constellation.com \nseth.lucia@constellation.com \n  \nChristopher A. Wilson \nManaging Director, Federal Regulatory Affairs \nConstellation Energy Generation, LLC \n250 Massachusetts Ave. NW, Suite 760 \nWashington, D.C. 20001 \n202-347-7500 \nFERCe-filings1@constellation.com \n \n/s/ Paul F. Wight  \n \n \nPaul F. Wight \nCarolyn E. Clarkin \nDLA Piper LLP (US) \n500 Eighth Street NW \nWashington, D.C. 20004 \n703-773-4058 \npaul.wight@us.dlapiper.com  \ncarolyn.clarkin@us.dlapiper.com  \n \nJacob I. Chefitz \nDLA Piper LLP (US) \n1251 Avenue of the Americas \nNew York, NY 10020 \n212-335-4500 \njacob.chefitz@us.dlapiper.com  \n \nCounsel for Constellation Energy \nGeneration, LLC"},{"page":45,"startToken":17612,"endToken":17619,"text":"Exhibit 1 \n \nAffidavit of Aaron T. Patterson"},{"page":46,"startToken":17619,"endToken":17680,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \nInterconnection of Large Loads to the \nInterstate Transmission System \n)\n)\n)\nDocket No. RM26-4-000\n(Not consolidated)\nPJM Interconnection, LLC., et al. \n)\n)\n)\nDocket No. EL25-49-000\nLarge Loads Co-Located at Generating \nFacilities \n \nConstellation Energy Generation, LLC \n         v. \nPJM Interconnection, LLC \n)\n)\n)\n)\n)\n)\nDocket No. AD24-11-000\nDocket No. EL25-20-000\n(Consolidated)\n \n \nAFFIDAVIT OF \nAARON T. PATTERSON  \n \nDecember 5, 2025"},{"page":47,"startToken":17680,"endToken":18022,"text":"1 \n \nI. QUALIFICATIONS, BACKGROUND, AND PURPOSE OF AFFIDAVIT \nA. QUALIFICATIONS \n1. \nMy name is Aaron T. Patterson.  I am a partner of The NorthBridge Group, Inc \n(“NorthBridge”).  NorthBridge is a consulting firm that provides economic and strategic advice to \nthe electric and natural gas industries.  My business address is 30 Monument Square, Concord MA \n01742. \n6. \nI joined NorthBridge in 2001.  Before that, I was an analyst at Lexecon, Inc., which I joined \nin 1996.  I have over 20 years of experience working with clients in the electric and natural gas \nindustries.  My electric industry business consulting work has focused on market design, \nenvironmental policy, finance, and mergers and acquisitions.  I received a Bachelor of Arts in \nEnvironmental Science and Public Policy from Harvard University, and a Master of Business \nAdministration from the Tuck School of Business at Dartmouth.  I have previously testified before \nthe Commission and have also submitted expert testimony and/or expert reports in proceedings \nbefore the U.S. Department of the Treasury, the Illinois Commerce Commission, the Public Utility \nCommission of Texas and the New York State Public Service Commission. \n2. \nA list of my past prepared testimony is provided as Attachment A.  \nB. BACKGROUND AND PURPOSE OF AFFIDAVIT \n3. \nThis affidavit describes how the Enhanced Reliability Backstop Mechanism (the “Enhanced \nBackstop”) to PJM Interconnection, LLC’s (“PJM”) Reliability Pricing Model (“RPM”) discussed \nin Constellation Energy Generation’s (“Constellation”) supporting comments in this proceeding1 \nand originally proposed by a group of stakeholders2 (“Joint Stakeholders”) in PJM’s Critical Issue \nFast Path – Large Load Additions (“CIFP-LLA”) stakeholder process would work at a high level \nin practical application for the PJM RPM auction for the 2028/29 delivery year and beyond.  I \ndiscuss how the Enhanced Backstop increases the ability of PJM to attract additional capacity \nsupply under tight market conditions while limiting harm to competitive markets.  Finally, I \n \n1 Supporting Comments of Constellation Energy Generation LLC, Nov 21, 2025, at 42-43 and Exhibit 1. \n2 Joint Stakeholders comprise Amazon.com Inc., Calpine Corp., Constellation Energy, Google LLC, Microsoft Inc., \nand Talen Energy."},{"page":48,"startToken":18022,"endToken":18409,"text":"2 \n \nidentify certain parameters of the Enhanced Backstop that could potentially be varied relative to \nthe baseline proposal and discuss the tradeoffs of varying each parameter. \n4. \nI have previously provided testimony in the PJM Show-Cause Proceeding where I suggested \nat a high level that the Commission consider enhancements to the PJM RPM of a similar \nconceptual nature to the Enhanced Backstop.3  Subsequent to that testimony, in my capacity as an \neconomic consultant, I have consulted with Constellation as it developed the Enhanced Backstop \nin conjunction with the Joint Stakeholders. \nII. PURPOSE AND OPERATION OF THE ENHANCED BACKSTOP \nC. CERTAIN DESIGN FEATURES OF THE RPM POTENTIALLY LIMIT \nCONFIDENCE IN ITS ABILITY TO BRING FORTH NEW SUPPLY UNDER \nTIGHT MARKET CONDITIONS \n7. \nWhile the RPM has generally been successful in bringing forth sufficient supply to meet \nPJM’s need for capacity, PJM and others have in recent years raised concerns about the ability of \nthe RPM to continue to meet the market’s need for capacity under current and future tight market \nconditions.  As has been discussed in depth in this proceeding and others, PJM is currently \nexperiencing an unprecedented combination of high demand growth, increased costs of and \nconstraints on the installation of new generation, and retirement of existing, primarily fossil, \nresources.  This confluence of factors has led to a tightening of the capacity market in the most \nrecent two RPM Base Residual Auctions (“BRA”), with prices clearing around the current Net \nCost of New Entry (“Net CONE”) and quantity clearing around the Reliability Requirement, and \nan expectation from PJM that markets could potentially experience even greater degrees of \ntightness in future RPM auctions for 2027/28 and beyond.4  Such auction results are unsurprising \nand should be expected under these circumstances.   \n \n3 PJM Interconnection, L.L.C., Docket No. EL25-49-000, Large Loads Co-Located at Generating Facilities, Docket \nNo. AD24-11-000, Constellation Energy Generation, LLC v. PJM Interconnection, L.L.C., Docket No. EL25-20-000 \n(consolidated) (collectively, “PJM Show Cause proceedings”), Affidavit of Aaron T. Patterson attached as Exhibit 3 \nto Answer of Constellation Energy Generation LLC, April 23, 2025 (“Patterson Show-Cause Affidavit”). \n4 See PJM Interconnection, LLC, 2025 PJM Effective Load Carrying Capability and Reserve Requirement Study, \nOctober 22, 2025, at Table 4.  (“PJM ELCC/RRS Study”) https://www.pjm.com/-/media/DotCom/planning/res-\nadeq/elcc/2025-pjm-elcc-rrs.pdf."},{"page":49,"startToken":18409,"endToken":18877,"text":"3 \n \n8. \nThe design of the PJM RPM potentially limits its ability to bring forth new supply under very \ntight market conditions, for two reasons.  First, the clearing price of capacity is not allowed to \nincrease indefinitely as the market becomes ever-shorter but is instead administratively capped as \na long-standing consumer cost limitation measure via the design of PJM’s capacity demand curve, \nthe Variable Resource Requirement (“VRR”).  PJM’s proposed VRR curve for the 2028/29 BRA \ncaps the clearing price at a projected $550 per MW-day, or approximately 1.9 times Net CONE \nfor a generic new reference combustion turbine at the point where cleared capacity equals 99% or \nless of the Reliability Requirement.5  Resources whose economics require a price exceeding the \nadministrative price cap thus cannot clear at their competitive offer level and are effectively unable \nto participate in the market.  And to the extent that PJM mis-calibrates the cap and sets it at a level \nthat is insufficient to cover new entry costs for potential new entrants, the amount of affected \npotential new entrant capacity could be significant.   \n9. \nSecond, a given RPM auction only provides cleared capacity resources with a capacity \ncommitment and associated revenues for a single delivery year despite the fact that many types of \ncapacity resources have multi-decade economic lives.  When the market rules are fairly static and \nthere is a high degree of regulatory certainty, a series of one-year commitments has proven to \nincent new entry to meet normal load growth.  The RPM has procured sufficient resources to meet \nPJM’s resource adequacy target year after year for 20 years, despite a major transition in the nature \nof the generation fleet.6  However, when there is significant regulatory uncertainty, this limitation \nincreases risk for new entrant generation and raises the price they need to economically enter the \nmarket.  For example, a typical new entrant generation resource must weigh the commitment of \nits full construction capital versus its projected market revenues over a twenty year or more \neconomic life and decide whether the projected revenues are sufficient compensation for the up-\nfront capital expenditures.  But because the RPM in the year in which the resource enters only \nlocks in capacity revenues for its first year of operation, the resource must take the risk that the \nremaining nineteen or more years following that point will provide sufficient revenue to justify \nsinking the capital to enter the market.  Relative to a design where it is able to lock in capacity \n \n5  PJM Interconnection, L.L.C., Docket No. EL26-455-000, 2025 Period Review of the Variable Resource \nRequirement Curve Shape and Key Parameters, November 7, 2025, at 44-50. \n6 See Patterson Show-Cause Affidavit at PP 18-20 for an in-depth discussion of the historical performance of the RPM \nin meeting its reliability goals at reasonable cost."},{"page":50,"startToken":18877,"endToken":19271,"text":"4 \n \nrevenues for a longer period upon entering the market, and particularly during periods of \nsignificant regulatory uncertainty (such as when design features like a cap or a collar on prices \napply for some years and not others), a resource will have a higher price threshold for new entry, \nlimiting the supply of new entrant resources and increasing the population of potential new entrants \nthat are potentially excluded due to the administrative price cap.  \n10. The RPM does currently have a mechanism for procuring capacity on a supplemental basis \nif the RPM clears short of 99% of the reliability requirement for three consecutive years. 7  \nHowever, under current circumstances, the three-year trigger makes this mechanism somewhat \nunresponsive to address emerging reliability concerns – by the time the market has cleared short \nfor three years in a row the supply deficit could potentially get very large – and the supplemental \nprocurement would occur as a separate auction outside the normal operation of the RPM, \npotentially leading to market disruptions and harm that exacerbate the problem over the long run. \n11. Given these limitations, an improved reliability backstop mechanism that is both more \nresponsive and market friendly could increase confidence in the ability of the RPM to bring forth \nnew supply when needed under tight market conditions.  The Enhanced Backstop has been \ncarefully designed to provide increased confidence in RPM while limiting any harm to markets as \nmuch as possible. \nD. THE ENHANCED BACKSTOP WORKS WITHIN THE STRUCTURE OF THE \nRPM TO BRING FORTH ADDITIONAL SUPPLY UNDER TIGHT CONDITIONS \n11. The goal of the Enhanced Backstop is to offer a responsive in-market mechanism that \nexpands the universe of available supply to the RPM when needed under very tight market \nconditions in order to achieve a reasonable minimum level of reliability while also minimizing \ndistortions and harm to markets over time.  The Enhanced Backstop is intended to increase \nconfidence in the ability of markets to bring forth new supply in particularly challenging conditions \nwhile minimizing any distortions of market price signals that are needed to drive investment and \nretirement decisions across the full range of market conditions. \n12. The Enhanced Backstop proposal would allow (but not require) certain resources to enter a \nmuti-year offer in the RPM at the administrative price cap in lieu of making a conventional single-\n \n7 PJM Open Access Transmission Tariff, Attachment DD, Section 16."},{"page":51,"startToken":19271,"endToken":19743,"text":"5 \n \nyear offer at any allowable price level.  Resources eligible to make multi-year price-cap offers \nwould include all resources that are allowed to offer at the level of the administrative price cap \nunder current RPM rules.  Resources that are required to offer at a level below the price cap due \nto the operation of the Market Seller Offer Cap (“MSOC”) rules would not be eligible to make \nmulti-year price-cap offers.  Thus, new entrant generation resources (including uprates of existing \ngeneration resources), new external resources, and all types of demand response (“DR”) resources \n(which are all exempt from the MSOC) would be eligible to make multi-year offers at the price \ncap in the BRA.  This is the appropriate level as the Enhanced Backstop would only be utilized in \nsituations when the market is clearing at the price cap, and the offer level should not create an \nincentive for those resources that could offer into the BRA, but are not required to do so, to wait \nfor the Enhanced Backstop to be triggered to offer.  Existing generation resources which are able \nto support a MSOC at or above the price cap would also be eligible.  While most existing resources, \nincluding nuclear, natural gas, and renewables, are unlikely to meet the criteria to be eligible on \nthis basis, resources which face large avoidable capital expenditures, or existing external resources \nin high-priced external markets with resulting high opportunity costs could potentially qualify.  \nResources making multi-year price-cap offers would be subject to the same capacity accreditation \nrules as other capacity resources and would generally be subject to the same performance \nobligations if cleared.8 \n13. Resources choosing to make multi-year price-cap offers would be required to offer at the \nadministrative price cap for the delivery year of the RPM auction in question but could choose to \noffer a term of anywhere between two and seven years.  If cleared, they would assume a capacity \nobligation for each year of the term offered and would be paid their offer price in each year of that \nterm. \n14. When running the RPM auction with the Enhanced Backstop in place, PJM would clear the \nmarket without clearing any multi-year price cap offers if the amount of cleared supply meets or \nexceeds 98% of the Reliability Requirement (the “Procurement Threshold”).  If, however, the \n \n8 The one exception from the standard rules applicable to capacity resources would be the price at which the capacity \nresource with a multi-year commitment is incorporated into the supply curve into subsequent BRAs (since they are \nalready cleared with a commitment they would not make new offers in these BRAs).  For the reasons discussed below, \nsuch resources would be entered into the supply curve at their Net Avoidable Cost Rate to minimize price \ndiscrimination between the multi-year resource and the mostly existing resources that clear in the BRA."},{"page":52,"startToken":19743,"endToken":20045,"text":"6 \n \nRPM would otherwise clear below 98% of Reliability Requirement, PJM would clear multi-year \nprice-cap offers sufficient to increase the total amount of supply cleared to 98% of the Reliability \nRequirement, but no more, unless offer lumpiness requires that PJM clear some modest amount in \nexcess of the Procurement Threshold.  PJM would clear multi-year price-cap offers in order of the \nterm offered, with shortest term offers cleared first, and would account for ties and offer lumpiness \nby applying similar cost-minimization principles as it currently uses to resolve such issues in \nclearing the RPM.9  If insufficient multi-year price-cap offers exist to return the total amount of \ncleared supply to the Procurement Threshold, PJM would clear all available offers.  The Enhanced \nBackstop is thus not a separate procurement but rather occurs within the normal market clearing \noperation of the RPM auctions.  Figure 1 below provides an illustrative graphical depiction of how \nthe Enhanced Backstop would work in the RPM market clearing process: \nFigure 1 \n \n15. Cleared multi-year price cap offers would assume a capacity obligation, with all attendant \nrequirements, for their full offered term.  They would be paid their offer price (i.e., the price cap \nin the initial year in which they are cleared) for each year of the term regardless of the market \n \n9 See PJM Open Access Transmission Tariff, Attachment DD, Sections 5.12 a) and d). \n0\n100\n200\n300\n400\n500\n600\n700\n800\n95%\n96%\n97%\n98%\n99%\n100% 101% 102% 103% 104% 105% 106% 107%\n$/MW-Day\nUCAP as a % of Reliability Requirement\nIllustrative Operation of Enhanced Backstop\nVRR Curve \n(Proposed for \n28/29)\nAdministrative \nPrice Cap\nOrdinary RPM \nOffers\nCleared Multi-Year Price-\nCap Offers to 98% of \nReliability Requirement\nExcess Multi-Year Price \nCap Offers Not Cleared\nMarket clearing \noutcome: 98% of \nReliability Requirement \nat Price Cap"},{"page":53,"startToken":20045,"endToken":20403,"text":"7 \n \nclearing price in subsequent delivery years.  To the extent that the administrative price cap is \nincreased or decreased in subsequent delivery years, cleared multi-year price cap offers wouldstill \nbe paid their original offer price in the year in which they were originally cleared.  For the purposes \nof price formation in subsequent years, multi-year capacity cleared in prior years would be entered \ninto the supply curve at an offer price equal to their net avoidable cost rate as an existing resource, \ncalculated as the technology-specific gross existing-resource avoidable cost rate for their resource \nclass minus the unit-specific energy and ancillary services offset.  Demand response resources with \ncleared multi-year price-cap offers would be entered into the supply curve at an offer price of zero \nin subsequent years. \n16. The Enhanced Backstop would only apply at the PJM Regional Transmission Organization \n(“RTO”) level and not at the level of individual Locational Delivery Areas (“LDAs”).  Thus, the \nclearing of multi-year price-cap offers would only be triggered if the RTO as a whole were short \nof 98% of the Reliability Requirement, and multi-year price-cap offers would be accepted from \nany qualifying resource without regard to location within PJM.  While it may be possible to adapt \nthe Enhanced Backstop to include a locational element, doing so increases implementation \ncomplexity and thus increases the risk of market distortions and other unintended consequences.  \nFurther, given that the reliability concerns over the coming years raised by PJM appear to be \nprimarily applicable to the RTO as a whole, restricting application of the Enhanced Backstop to \nthe RTO level only provides a better balance of implementation speed and increased confidence \nin markets. \n17. To limit any long-term distortive impacts on the markets and to ensure that the mechanism \ndoes not outlast its need, the Enhanced Backstop would only be in place for the next four RPM \ndelivery years corresponding to the current Quadrennial Review (2028/29 through 2031/32) and \nwould sunset automatically thereafter. \n18. The existing reliability backstop provision in the tariff is not mutually exclusive with the \nEnhanced Backstop and could remain in place as an additional line of defense against sustained \nextreme market conditions."},{"page":54,"startToken":20403,"endToken":20782,"text":"8 \n \nIII. THE ENHANCED BACKSTOP WILL INCREASE CONFIDENCE IN PJM MARKETS WHILE \nMINIMIZING PRICE DISTORTIONS AND OTHER POTENTIAL HARMS \nE. THE ENHANCED RELIABILITY BACKSTOP WILL ALLOW PJM MARKETS \nTO IMMEDIATELY ACCESS A WIDE RANGE OF SUPPLY THAT WOULD \nOTHERWISE NOT PARTICIPATE IN MARKETS \n19. Compared to the existing reliability backstop provision in the Tariff, the Enhanced Backstop \nis far more responsive in immediately bringing forth new supply in response to tight market \nconditions because it is triggered within the same RPM auction in which the tight conditions \nthemselves first appear, rather than being triggered only after three years plus of tight market \nconditions.  And the Enhanced Backstop is also less disruptive to markets because it occurs in-\nmarket rather than as a separate procurement and is designed to limit its application in a manner \nthat does not affect the clearing price in the year in which it is triggered. \n20. While PJM has not yet returned to its normal three-year ahead RPM auction cadence, there \nlikely are substantial pools of potential supply that the Enhanced Backstop can activate to \nmaterially improve reliability as early as the 2028/29 delivery year.  Allowing eligible resources \nto lock in a price at the administrative price cap for a multi-year period increases the likelihood \nthat high-cost supply that would otherwise forgo participation altogether will enter a multi-year \nprice-cap offer.  In particular, even if incremental greenfield new generation development is not \nfeasible by 2028/29, many potential incremental sources of supply could still increase their \nparticipation, including: \n Demand response: DR has in the past historically participated at higher levels than \nit has in recent years10 and it stands to reason that the ability to lock in a relatively \nhigh, multi-year price could attract additional DR to the market.  Unlike generation, \nDR does not need to pass through the interconnection queue and can thus rapidly \nenter the market in substantial quantities if the price signal is sufficient. \n \n10 PJM Interconnection, LLC, 2026/27 Base Residual Auction Report, July 22, 2025, Figure 3. https://www.pjm.com/-\n/media/DotCom/markets-ops/rpm/rpm-auction-info/2026-2027/2026-2027-bra-report.pdf Between the 2016/17 and \n2026/27 BRAs the amount of offered demand response and price responsive demand has fallen from approximately \n15 Gigawatts of Unforced Capacity to 5.5 Gigawatts."},{"page":55,"startToken":20782,"endToken":21164,"text":"9 \n \n Existing external resources: many neighboring markets have tight capacity markets \nsimilar to PJM which could result in existing external resources facing a very high \nopportunity cost (and resulting high MSOC) to remain in the PJM market, which \ncould cause them to not clear under the status quo.  The ability to make multi-year \noffers at the price cap could provide a pathway for such resources to continue to \nclear in PJM rather than external markets. \n In-development new generation: PJM and neighboring regions have a large volume \nof new generation working through the interconnection queue process, and many \nsuch resources face unexpected challenges such as high interconnection costs \nand/or loss of federal tax subsidies (for renewables).  The option to offer multi-year \nat the price cap provides a pathway for such challenged resources to potentially still \nenter the market if the need is high, rather than simply cancelling the project as \ntypically occurs under the status quo. \n \n21. From the 29/30 delivery year and beyond, the universe of potential incremental supply that \ncould be activated by the Enhanced Backstop mechanism will continue to expand as the supply of \nnew generation becomes more elastic and PJM continues to refine and optimize its recent reforms \nto the generation interconnection queue. \nF. THE ENHANCED BACKSTOP HAS BEEN CAREFULLY DESIGNED TO \nMINIMIZE ANY HARMS TO PJM COMPETITIVE MARKETS \n22. The Enhanced Backstop is a departure from the current RPM design in that it employs \ndiscriminatory pricing for certain high-cost resources that would normally be unable to clear in the \nRPM due to the operation of the price cap and the single-year commitment period.  Resources that \nare cleared as multi-year price-cap offers are paid the same price as other resources in the year in \nwhich they clear, but are potentially paid a different, and in most instances likely higher, price than \nother resources in subsequent years of their multi-year commitment term.  While the Enhanced \nBackstop will not have an impact on price in the year in which it is triggered, it does lead to the \nprocurement of high-cost resources that would not otherwise have been procured absent the \nmechanism, and the existence of those resources in subsequent years could lead to price distortions \nin those years because they represent additional infra-marginal supply that would not exist but-for"},{"page":56,"startToken":21164,"endToken":21580,"text":"10 \n \nthe Enhanced Backstop.  This is not normally an ideal market design feature, and the Commission \nshould rightfully be cautious about approving market design elements that discriminate between \ndifferent resources that are ultimately providing the same product.  However, in this case the \nEnhanced Backstop has been carefully designed to minimize any harm to markets that results from \nthis underlying discriminatory element. \n23. First, limiting the amount of multi-year price-cap supply cleared to the amount needed to \nincrease total cleared supply to the Procurement Threshold, but no more, is a key feature that \nreduces the distortive impact of the Enhanced Backstop on competitive markets in several \nimportant ways. \n24. As Figure 1 shows, setting the Procurement Threshold at 98% of the Reliability Requirement \ncauses the Enhanced Backstop to only come into play under very tight market conditions when the \nRPM would already clear at the price cap.   Thus, the Enhanced Backstop will not affect market \nclearing outcomes in years in which the RPM clears below the price cap (with the exception that \nmulti-year supply cleared in prior years may have an ongoing effect in subsequent years).  The \nEnhanced Backstop will also not have an effect on the clearing price in years in which it is triggered \nand any multi-year price cap offers cleared will be paid the same price as other resources cleared \nin that year because the amount of multi-year supply cleared will not push the total cleared quantity \npast the point where the demand curve begins sloping downward at 99% of the Reliability \nRequirement.  Rather, as Figure 1 shows, the operation of the Enhanced Backstop will simply \nmove the market clearing outcome along the flat portion of the demand curve at the administrative \nprice cap.   \n25. The Enhanced Backstop thus creates an additional supplemental pool of supply that kicks in \nto improve reliability only under very tight market conditions without suppressing the capacity \nprice signal below where it would have otherwise cleared.  Setting the Procurement Threshold at \n98% of the Reliability Requirement strikes a balance between ensuring that the market is able to \nachieve a reasonable minimum level of reliability and also providing a cushion for clearing lumpy \noffers while still staying below the point on the demand curve (99% of the Reliability \nRequirement) where the backstop would have a suppressive impact on the clearing price.   \n26. The Procurement Threshold also limits the impact of the Enhanced Backstop on market \noutcomes in subsequent years following the year in which it is initially triggered because the"},{"page":57,"startToken":21580,"endToken":21964,"text":"11 \n \nProcurement Threshold limits the volume of supply that receives multi-year capacity \ncommitments.  As Figure 1 shows, a higher Procurement Threshold, such as 99% of the Reliability \nRequirement, would result in more capacity being procured under the Enhanced Backstop \nwhenever it is triggered.  This capacity would generally remain in the market thereafter as infra-\nmarginal existing resources which would reduce prices relative to the but-for world where these \nincremental resources were never procured.  Thus, setting the Procurement Threshold to the \nrelatively low value of 98% of the Reliability Requirement limits long-term distortions to the \nmarket. \n27. Limiting the maximum term for multi-year price cap offers to seven years and clearing these \noffers in increasing order of term when the Enhanced Backstop is triggered, with shortest-term \noffers cleared first, also limits the potential for long-term price distortion due to the operation of \nthe Enhanced Backstop.  During the term of their multi-year commitment, capacity procured under \nthe Enhanced Backstop will remain in the market as relatively low-priced supply regardless of \nsubsequent market conditions or their private economics because they would be entered at an offer \nprice of either their Net ACR or zero (for DR).  As discussed above, this potentially distorts and \nsuppresses resource offers and thus market prices in those years, particularly for resources such as \ndemand response and external resources that often do not need to sink substantial capital to enter \nthe market and thus face an ongoing year-to-year marginal decision whether, and what price, to \nparticipate.  Limiting the maximum multi-year term to seven years and preferentially clearing the \nshortest-term offers limits this distortive effect. \n28. Similarly, the requirement that resources with multi-year capacity commitments be entered \ninto the capacity offer curve at their Net ACR, rather than as price-takers, in years two and beyond \nof their multi-year commitment simulates ongoing competitive offers from these resources for the \npurposes of RPM price formation and thus partially protects against price distortions if tight market \nconditions cease to prevail during the term of the multi-year capacity commitment. \n29. And finally, limiting the Enhanced Backstop to the four delivery years covered by the most \nrecent Periodic Review of the RPM limits any impact that the Enhanced Backstop may have on \nlong-term market expectations and thus reduces any chilling impact it may have on market \nparticipants’ investment decisions."},{"page":58,"startToken":21964,"endToken":22228,"text":"12 \n \nIV. CERTAIN FEATURES OF THE ENHANCED BACKSTOP COULD BE VARIED TO ACHIEVE A \nDIFFERENT BALANCING OF MARKET CONFIDENCE AND HARM LIMITATION \n30. In my opinion, the various features of the Enhanced Backstop discussed above strike the best \nbalance between increasing confidence in the ability of the RPM to bring forth supply when needed \non one hand while also limiting harm to the market on the other.  That said, there are several \nfeatures and parameters of the Enhanced Backstop that could be varied to the extent that the \nCommission or other stakeholders wish to recalibrate the balance between these two goals. \n31. First, in my view the Procurement Threshold of 98% of the Reliability Requirement is the \nmost important parameter in balancing between the two goals.  While setting the Procurement \nThreshold at 98% of the Reliability Requirement strikes the best balance in my opinion, setting it \nto a higher or lower number, within certain bounds, would still achieve a workable mechanism, \nalbeit one with a different tradeoff between reliability on one hand and potential harm to the market \non the other.  Specifically, reducing the Procurement Threshold below 98% of the Reliability \nRequirement would result in the market procuring less supplemental supply when the Enhanced \nBackstop is triggered, which would result in a lower level of reliability but also less potential price \ndistortion over time, while procuring more than 98% would have the opposite effect.  \n32.  Figure 2 below shows the approximate tradeoff in reliability between different levels of \nProcurement Threshold, based on my analysis of information provided by PJM during the CIFP-\nLLA process:"},{"page":59,"startToken":22228,"endToken":22584,"text":"13 \n \nFigure 2 \n \nSource: Based on PJM Interconnection, LLC, Estimated Preliminary Resource Adequacy \nMetrics for 2028/29 Under Different Shortage Levels, October 21, 2025.  https://www.pjm.com/-\n/media/DotCom/committees-groups/cifp-lla/2025/20251021/20251021-item-03---estimated-\npreliminary-resource-adequacy-metrics-for-2028-2029-under-different-shortage-levels---pjm-\npresentation.pdf.  I have calculated the Unforced Capacity Supply as a percentage of the \nreliability requirement from the values provided by PJM in this document by multiplying the \nprovided reserve margin expressed in ICAP terms by the pool average projected accredited \nUCAP factor for 2028/29 of 0.7616 and then dividing each value by the projected 2028/29 \nforecast pool requirement of 0.9193.  \n \nAs Figure 2 shows, if PJM procures supply equal to the Procurement Threshold of 98% of the \nReliability Requirement through operation of the Enhanced Backstop, PJM will achieve a loss of \nload expectation of about 0.21 events per year (1 event per 4.8 years), which is approximately \ndouble the long-term reliability target of 0.1 events per year (1 event per 10 years).  If the \nProcurement Threshold were raised to 99% of the Reliability Requirement, and sufficient multi-\nyear price cap offers existed to reach the higher threshold, the resulting reliability expectation in \nthat year would improve to 0.15 events per year (1 event per 6.7 years).  However, this would \ncome at the cost of procuring approximately 1.6 Gigawatts of additional unforced capacity (the \none percent differences between a Procurement Threshold at 99% versus 98% multiplied by PJM’s \n0.00\n0.10\n0.20\n0.30\n0.40\n0.50\n0.60\n0.70\n0.80\n96%\n97%\n98%\n99%\n100%\n101%\nLOLE\nUCAP Supply as a % of UCAP Reliability Requirement\nLoss of Load Expectation (LOLE) vs. Amount of Supply \nCleared as a % of Reliability Requirement\n0.1 LOLE / 1 in \n10 at 100% of \nReliability \nRequirement\nEvents per XX years = 1 / LOLE\n(so 0.1 LOLE = 1 event per 10 years)\n0.15 LOLE \n/ 1 in 6.7 at 99% \nof Reliability \nRequirement\n0.21 LOLE \n/ 1 in 4.8 at 98% \nof Reliability \nRequirement\n0.29 LOLE \n/ 1 in 3.5 at 97% \nof Reliability \nRequirement"},{"page":60,"startToken":22584,"endToken":22984,"text":"14 \n \n2028/29 projected Reliability Requirement of approximately 156 Gigawatts11) under multi-year \ncommitments, which would have distortive effects in subsequent years (while also increasing \ncustomer cost).  Conversely, setting the Procurement Threshold to 97% of the Reliability \nRequirement would result in expected reliability of 0.29 events per year (1 event per 3.5 years) if \nthe Enhanced Backstop is triggered in a given year and results in supply procurement at that level, \nbut would also result in a reduction in procured multi-year supply of about 1.6 Gigawatts of \nunforced capacity relative to a Procurement Threshold of 98% of the Reliability Requirement. \n33. In my opinion, a Procurement Threshold of 98% of the Reliability Requirement sets a \nreasonable balance between reliability assurance on one hand and limitation of market distortions \non the other.  Setting the threshold at or close to 99% increases the risk that the Enhanced Backstop \ncould affect market prices in the year in which it is triggered due to lumpy offers, and further \nresults in a higher volume of multi-year commitments that could potentially distort prices in \nsubsequent years.  Conversely, setting the procurement threshold at less than 98% would result in \nloss of load expectations more than doubling relative to the long-term reliability target in years in \nwhich the Enhanced Backstop is triggered, which is likely to be an unacceptably low minimum \nlevel of reliability for consumers.  However, a range of Procurement Threshold values between \n97% and approximately 98.5% (to allow for lumpy offers) is likely workable. \n34. Another potential lever that could be varied would be to increase the maximum allowable \nmulti-year offer term from seven years to potentially as high as ten years.  Increasing the maximum \nallowable term expands the universe of potential supply that may be willing to submit multi-year \nprice-cap offers because it increases the level of assured capacity revenue over time that resources \nare able to express in their offers.  This decreases the likelihood that PJM may end up in a situation \nwhere there are insufficient multi-year, price cap offers to reach the Procurement Threshold, with \na resulting degradation in reliability.  Conversely, as discussed previously, increasing the \nmaximum allowed term increases the potential for market distortions over the long term.  In my \nopinion, the proposed seven-year term limitation is reasonable but raising it to as high as ten years \nwould still be workable. \n \n11 PJM ELCC/RRS Study at Table 4."},{"page":61,"startToken":22984,"endToken":23144,"text":"15 \n \n35. Finally, another lever that could further reduce any potential harm on markets would be to \nrequire that PJM support the continuation of the Enhanced Backstop for delivery years after \n2028/29 with an analysis of projected capacity supply and demand for the upcoming year prior to \nthe BRA.  If such an analysis did not show a projected shortfall relative to the Reliability \nRequirement for that year, the Enhanced Backstop would be suspended for that year.  In any event \nthe Enhanced Backstop would still sunset following the 2031/32 delivery year but could be \nsuspended for some of the years prior to that point if PJM’s analysis shows that it is not needed.  \nThis measure would further increase confidence that the Enhanced Backstop will have a limited \nlong-term effect on market price signals but may be unnecessary given that the Enhanced Backstop \nis only designed to be triggered under shortage conditions in any case. \n36. This concludes my affidavit."},{"page":62,"startToken":23144,"endToken":23144,"text":""},{"page":63,"startToken":23144,"endToken":23150,"text":"16 \n \n \n \n \n \n \n \n \n \nAttachment A to Patterson Affidavit"},{"page":64,"startToken":23150,"endToken":23357,"text":"17 \n \nAaron T. Patterson Testimony and Expert Reports \nDate \nOn Behalf Of \nCommission/Court \nSubject Matter \nDocket/Case Number \nDec-2025 \nConstellation Energy Illinois Commer \nCommission \nRebuttal Testimony \nResponding to Joint NGO \nBring Your Own Generation \nProposal\n25-0680 \nOct-2025 \nConstellation Energy Illinois Commerce \nCommission \nRebuttal Testimony \nResponding to Joint NGO \nBring Your Own Generation \nProposal\n25-0679 and 25-0677 \nApr-2025 \nConstellation Energy FERC \nAffidavit – Resource \nAdequacy Issues in PJM \nEL25-49-000 \nAD24-11-000 \nEL25-20-000 \nJan-2025 \nConstellation Energy FERC \nAffidavit – Treatment of RMR \nResources in PJM Capacity \nMarket\nER25-682-000 \nFeb-2024 \nNuclear Energy \nInstitute \nU.S. Department of \nthe Treasury \nExpert Report (with Frank \nHuntowski and John \nHutchinson) – “Assessing the \nIncrementality Requirement \nof Treasury’s Proposed 45V \nRegulations”\nREG-117631-23 \nDec-2023 \nConstellation Energy FERC \nReply Affidavit – PJM \nCapacity Market Reforms \nER24-99-000 and ER24-98-000 \nNov-2023 \nConstellation Energy FERC \nAffidavit – Market Monitor \nComplaint regarding PJM \nCapacity Market\nEL24-12-000 \nNov-2023 \nConstellation Energy FERC \nAffidavit – PJM Capacity \nMarket Reforms \nER24-99-000 and ER24-98-000 \nNov-2022 \nConstellation Energy FERC \nJoint Affidavit (with Michael \nM. Schnitzer) – New England \nWinter Gas-Electric Forum\nAD22-9-000 \nJune-2021 Exelon Corporation \nFERC \nReply Affidavit – PJM \nCapacity Market Seller Offer \nCap\nEL-19-63-000 \nMay-2021 \nExelon Corporation \nFERC \nAffidavit – PJM Capacity \nMarket Seller Offer Cap \nEL19-63-000 \nNov-2020 \nExelon Corporation \nFERC \nDeclaration (with Michael M. \nSchnitzer) – NYISO Capacity \nMarket Buyer Side Mitigation \nEL21-07-000"},{"page":65,"startToken":23357,"endToken":23424,"text":"18 \n \nAaron T. Patterson Testimony and Expert Reports \nDate \nOn Behalf Of \nCommission/Court \nSubject Matter \nDocket/Case Number \nNov-2019 \nExelon Corporation \nState of New York \nPublic Service \nCommission \nExpert Report – “Impact of \nCarbon Pricing on Potential \nExpanded Buyer-Side \nMitigation in the NYISO \nMarkets”\n19-E-0530 \nDec-2017 \nExelon Corporation \nPublic Utility \nCommission of Texas \nExpert Report (with David \nColeman) – “Economic \nEquilibrium and Reliability in \nERCOT”\nProject No. 47199"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":3,"endAt":0,"startToken":0,"endToken":414},{"p":3,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":9,"endAt":199,"startToken":414,"endToken":2116},{"p":9,"at":199,"title":"I. There Is Broad Consensus in the Record for How the Commission Should Act","method":"printed heading","endPage":9,"endAt":420,"startToken":2116,"endToken":2151},{"p":9,"at":420,"title":"A. The Commission Should Act Quickly","method":"printed heading","endPage":11,"endAt":306,"startToken":2151,"endToken":3333},{"p":11,"at":306,"title":"B. The Commission Should Act on Record Evidence of Undue Preference, Undue","method":"printed heading","endPage":16,"endAt":134,"startToken":3333,"endToken":5676},{"p":16,"at":134,"title":"C. The Commission Should Accommodate Regional Differences","method":"printed heading","endPage":17,"endAt":181,"startToken":5676,"endToken":6303},{"p":17,"at":181,"title":"D. The Commission Should Avoid Unnecessary Jurisdictional Fights","method":"printed heading","endPage":18,"endAt":113,"startToken":6303,"endToken":6697},{"p":18,"at":113,"title":"II. Constellation Continues to Support the ANOPR’s Principles with Qualifications","method":"printed heading","endPage":44,"endAt":4,"startToken":6697,"endToken":17408},{"p":44,"at":4,"title":"CONCLUSION","method":"printed heading","endPage":47,"endAt":5,"startToken":17408,"endToken":17681},{"p":47,"at":5,"title":"I. QUALIFICATIONS, BACKGROUND, AND PURPOSE OF AFFIDAVIT","method":"printed heading","endPage":47,"endAt":62,"startToken":17681,"endToken":17688},{"p":47,"at":62,"title":"A. QUALIFICATIONS","method":"printed heading","endPage":47,"endAt":1276,"startToken":17688,"endToken":17877},{"p":47,"at":1276,"title":"B. BACKGROUND AND PURPOSE OF AFFIDAVIT","method":"printed heading","endPage":48,"endAt":599,"startToken":17877,"endToken":18113},{"p":48,"at":599,"title":"II. PURPOSE AND OPERATION OF THE ENHANCED BACKSTOP","method":"printed heading","endPage":48,"endAt":651,"startToken":18113,"endToken":18121},{"p":48,"at":651,"title":"C. CERTAIN DESIGN FEATURES OF THE RPM POTENTIALLY LIMIT","method":"printed heading","endPage":50,"endAt":1524,"startToken":18121,"endToken":19113},{"p":50,"at":1524,"title":"D. THE ENHANCED BACKSTOP WORKS WITHIN THE STRUCTURE OF THE","method":"printed heading","endPage":54,"endAt":5,"startToken":19113,"endToken":20404},{"p":54,"at":5,"title":"III. THE ENHANCED BACKSTOP WILL INCREASE CONFIDENCE IN PJM MARKETS WHILE","method":"printed heading","endPage":54,"endAt":135,"startToken":20404,"endToken":20422},{"p":54,"at":135,"title":"E. THE ENHANCED RELIABILITY BACKSTOP WILL ALLOW PJM MARKETS","method":"printed heading","endPage":55,"endAt":1338,"startToken":20422,"endToken":20990},{"p":55,"at":1338,"title":"F. THE ENHANCED BACKSTOP HAS BEEN CAREFULLY DESIGNED TO","method":"printed heading","endPage":58,"endAt":6,"startToken":20990,"endToken":21965},{"p":58,"at":6,"title":"IV. CERTAIN FEATURES OF THE ENHANCED BACKSTOP COULD BE VARIED TO ACHIEVE A","method":"printed heading","endPage":65,"endAt":501,"startToken":21965,"endToken":23424}]}