{"document":{"slug":"rec-20251208-5309","title":"Answer of Old Dominion Electric Cooperative in Opposition to Motion for Expedited Action of Constellation Energy Generation, LLC,","issued":"2025-12-08","accession":"20251208-5309","docket":"EL25-49-000","group":"PJM co-location compliance","filer":"Old Dominion Electric Cooperative","kind":"answer","file":"sources/filings/text/20251208-5309_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20251208-5309","tier":"record","sha256":"b1815447d9b31d62004fff52db7a066bd7d909e92dc7c0e241f4a6eb1b656c44","pages":8,"tokens":1971,"emptyPages":[],"textThemes":["colo","adequacy"]},"pages":[{"page":1,"startToken":0,"endToken":196,"text":"1 \n \nUNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \nPJM Interconnection, L.L.C., et al.\n)\nDocket No. EL25-49-000\n \n)\n \nLarge Loads Co-Located at Generating \nFacilities\n) \nDocket No. AD24-11-000 \n \n)\n \nConstellation Energy Generation, LLC\n)\n \n \n)\n \nv.\n)\n)\nPJM Interconnection, L.L.C. \n) \nDocket No. EL25-20-000 \n(Consolidated)\n \nANSWER OF OLD DOMINION ELECTRIC COOPERATIVE \nIN OPPOSITION TO  \nMOTION FOR EXPEDITED ACTION OF \nCONSTELLATION ENERGY GENERATION, LLC \n \nPursuant to Rule 213 of the Commission’s Rules of Practice and Procedure, 18 C.F.R. § \n385.213, Old Dominion Electric Cooperative (“ODEC”) submits this Answer in opposition to the \nMotion for Expedited Action of Constellation Energy Generation, LLC (“Constellation”) filed in \nthe above-captioned proceedings on November 21, 2025 (“Motion”). As discussed below, ODEC \nurges the Commission to reject Constellation’s Motion.1 Instead, the Commission should address \nthe urgent need for clarity and guidance regarding large load interconnections, including co-\nlocated loads, on a generic basis in the ongoing rulemaking proceeding in Docket No. RM26-7-\n \n1 ODEC joined the Answer of the Indicated PJM Transmission Owners to the Motion for Expedited Action \nof Constellation Energy Generation, LLC, filed today in this proceeding. ODEC submits this brief Answer \nto raise additional concerns against Constellation’s Motion."},{"page":2,"startToken":196,"endToken":532,"text":"2 \n \n000.2 Such final action should allow for regional differences and be issued by the Commission no \nlater than April 30, 2026, as expected by the Secretary of Energy.3 \nI. \nRELEVANT BACKGROUND \nOn November 22, 2024, Constellation filed a complaint under Federal Power Act (“FPA”) \nsection 2064 against PJM in Docket No. EL25-20-000. In short, Constellation argued that the PJM \nOpen Access Transmission Tariff (“Tariff”) is unjust, unreasonable and unduly discriminatory \nbecause it does not contain specific rules for interconnecting generators that will serve co-located \nloads. Constellation requested that the Commission grant the complaint on a fast-track basis, \ndetermine that the PJM Tariff is unjust, unreasonable and unduly discriminatory or preferential, \nand direct PJM to adopt in its Tariff certain portions of PJM’s Guidance on Co-Located Load.  \nOn November 1, 2024, the Commission held a technical conference in Docket No AD24-\n11-000, to discuss issues related to co-location of loads at generating facilities. The Commission \nnoted several proceedings initiated by entities in the PJM Region that involved similar issues. \nInitial and reply comments were filed following the technical conference.5  \nOn February 20, 2025, the Commission issued an order in Docket No. EL25-49-000, \ninstituting a proceeding under FPA section 206.6 The Show Cause Order followed several filings \nthat addressed the co-location of large loads at generating facilities in PJM, as well as the \nCommission’s technical conference in Docket No. AD24-11-000. The Show Cause Order directed \n \n2 Ensuring the Timely and Orderly Interconnection of Large Loads, Docket No. RM26-4-000 (“Proposed \nANOPR”). \n3 U.S. Dep’t of Energy, Letter from Sec’y Chris Wright to Fed. Energy Regulatory Comm’n (Oct. 23, 2025), \nhttps://www.energy.gov/sites/default/files/2025-10/403%20Large%20Loads%20Letter.pdf. See \nReply \nComments of Old Dominion Electric Cooperative, Docket No. RM26-4-000 at 3-6 (Dec. 5, 2025).  \n4 16 U.S.C. § 824e. \n5 Large Loads Co-Located at Generating Facilities, Notice of Request for Comments (Nov. 8, 2024). \n6 PJM Interconnection, L.L.C., 190 FERC ¶ 61,115 (2025) (“Show Cause Order”)."},{"page":3,"startToken":532,"endToken":829,"text":"3 \n \nPJM and the PJM Transmission Owners, including ODEC, to either “(1) show cause as to why the \nTariff, the Amended and Restated Operating Agreement of PJM, and Reliability Assurance \nAgreement Among Load Serving Entities in the PJM Region remain just and reasonable and not \nunduly discriminatory or preferential due to the lack of provisions specifically addressing co-\nlocation arrangements;” or (2) explain what changes to these governing documents would remedy \nthe identified concerns if the Commission were to determine that the governing documents have \nbecome unjust and unreasonable or unduly discriminatory or preferential and, therefore, proceeds \nto establish a replacement Tariff.7  \nOn October 23, 2025, the Secretary of Energy issued the Proposed ANOPR pursuant to \nsection 403 of the Department of Energy Organization Act. The Proposed ANOPR directed FERC \nto initiate a rulemaking procedure and proposal regarding the interconnection of large loads. On \nOctober 27, 2025, the Commission issued a Notice Inviting Comments on the Proposed ANOPR.8 \nODEC submitted Initial Comments and Reply Comments on the Proposed ANOPR on November \n1, 2025 and December 5, 2025, respectively. ODEC encouraged the Commission to provide clarity \nand establish a durable framework for the interconnection of large loads to the transmission system \nin a manner that ensures reliability and resource adequacy, and ensures that large loads pay their \nshare of the costs for the benefits they will receive. \nII. \nANSWER \nIn response to the Show Cause Order, the Indicated PJM Transmission Owners, including \nODEC, demonstrated that (1) neither the Commission nor any of the parties supporting initiation \nof the Show Cause proceeding have met the FPA section 206 burden to demonstrate that the \n \n7 Id. at P 2. \n8 By Notice issued November 7, 2025, the Commission extended the deadline for reply comments to \nDecember 5, 2025."},{"page":4,"startToken":829,"endToken":1155,"text":"4 \n \nexisting PJM Tariff is unjust, unreasonable or unduly discriminatory and preferential; and (2) the \nalternatives proposed by the Show Cause supporters would actually harm PJM’s ability to \naccommodate co-located interconnection arrangements.9 Therefore, the Commission should \nconfirm that the existing Tariff and governing documents are sufficient to accommodate co-located \nload arrangements and are just, reasonable and not unduly discriminatory or preferential. With that \nsaid, the Indicated PJM Transmission Owners agreed that clarity would be helpful, and encouraged \nthe Commission to clarify that Network Service and Point-to-Point Service are applicable to co-\nlocated load arrangements, ensure that the Commission’s principles for open access and non-\ndiscriminatory transmission service persist, and ensure beneficiaries pay for the service they \nreceive.10  \nPJM similarly demonstrated that its existing Tariff remains just and reasonable, although \nCommission guidance might be appropriate.11 To that end, PJM requested that if the Commission \ndecides to take action, it would issue guidance so that PJM can work with stakeholders to develop \na solution. To address timeliness, PJM suggested that the Commission could issue a compliance \ndirective to set a deadline for future filings, such as an FPA section 205 filing by PJM consistent \nwith the Commission’s guidance.12 \nAs detailed in the Indicated PJM Transmission Owners’ Answer, there still has not been \nany demonstration that the PJM Tariff is unjust, unreasonable or unduly discriminatory. Therefore, \n \n9 See Answer of the Indicated PJM Transmission Owners to the Order Instituting the Proceeding Under \nSection 206 of the Federal Power Act and Consolidated with Other Proceedings (Mar. 24, 2025); see also \nAnswer of the Indicated PJM Transmission Owners (Apr. 23, 2025), Answer of the Indicated PJM \nTransmission Owners to the Motion to Stay Proceedings (May 7, 2025), Motion for Leave to Answer and \nAnswer of the Indicated PJM Transmission Owners (June 3, 2025). \n10 See Indicated PJM Transmission Owners Answer submitted March 24, 2025, at 6. \n11 Answer of PJM (March 24, 2025). \n12 Id. at 5."},{"page":5,"startToken":1155,"endToken":1472,"text":"5 \n \nthe FPA section 206 burden has not been met. Moreover, the Indicated PJM Transmission Owners’ \nAnswer demonstrates that Constellation’s request for the Commission to make determinations \nregarding jurisdiction and adopt Constellation’s list of demands is both premature and raises \nsignificant concerns regarding reliability and affordability. Instead, as ODEC recommended in its \nReply Comments on the Proposed ANOPR, the Commission should (1) act swiftly to provide \nnecessary clarity, adopt generally applicable rules and/or standards, and direct compliance filings; \n(2) include specific directives to ensure reliability and resource adequacy; and (3) adopt \nrequirements to ensure that large loads pay their fair share of the costs. PJM can then work with \nstakeholders, as it has in its ongoing Critical Issue Fast Path (“CIFP”) process, to develop a \nproposal for consideration by its Board of Managers that can be submitted to the Commission in \ncompliance with the Commission’s guidance and directives.  \nThe Show Cause proceeding should be closed without further directive and Constellation’s \ncomplaint should be dismissed because there has been no demonstration that the existing Tariff is \nunjust, unreasonable or unduly discriminatory or preferential. However, even if the Commission \nfinds that this FPA section 206 burden has been met, Constellation’s specific relief has not been \nshown to constitute a just and reasonable replacement rate. In addition to the issues raised in the \nIndicated PJM Transmission Owners’ Answer, ODEC submits that Constellation’s request for the \nCommission to direct that large load interconnection requests must be processed without regard to \nwhether the load has arranged for wholesale transmission or distribution service, could lead to \nunreasonable cost allocation, as well as threats to reliability. In the Show Cause Order, the \nCommission stated that “[t]he record demonstrates that different co-location arrangements are \nlikely to use or benefit from the transmission system in different ways depending on how they are \nconfigured and, moreover, that those different configurations will themselves likely have different"},{"page":6,"startToken":1472,"endToken":1756,"text":"6 \n \nimpacts on the transmission system.”13 Further, the Commission noted that different co-location \nconfigurations can raise cost causation concerns.14 Constellation’s Motion does not resolve these \nconcerns, nor do its Comments on the Proposed ANOPR. To the contrary, Constellation’s \ncontentions in its Proposed ANOPR comments demonstrate the complexity of these configurations \nthat warrants the Commission adopting general principles for PJM to address through a compliance \nfiling.15  \nODEC also takes issue with Constellation’s continued attempts to equate its co-located \nload arrangements with the existing PJM provisions for netting with regard to behind-the-meter \ngeneration.16 The Indicated Transmission Owners have previously explained that the two are not \nsimilar and, therefore, different treatment of co-located load from behind-the-meter generation is \nnot unduly discriminatory.17 ODEC urges the Commission to reject Constellation’s attempt to \nargue otherwise. \nConstellation’s request for the Commission to grant Constellation’s specific measures, for \nthe PJM Region only, also fails to address critical issues regarding resource adequacy with co-\nlocated loads. In the Show Cause Order, the Commission advised that “the risk that co-located \nloads will not be reflected in resource adequacy planning mechanisms with sufficient forward \nnotice is particularly concerning given how long it takes to add new generation capacity or upgrade \ntransmission facilities.”18 Constellation’s request for the Commission to immediately adopt \n \n13 Show Cause Order at P 76. \n14 Id. \n15 See Constellation’s ANOPR Comments at 32-33, citing to Constellation’s Show Cause Answer and \naccompanying testimony. \n16 See, e.g., Constellation’s Supplemental Comments at 36 (Dec. 5, 2025).  \n17 See Indicated Transmission Owners’ Answer, June 3, 2025 in Docket No. EL25-49 at 12, 16-17; Indicated \nTransmission Owners’ Answer, Apr. 3, 2025 at 5-9. \n18 Show Cause Order at P 85."},{"page":7,"startToken":1756,"endToken":1929,"text":"7 \n \nConstellation’s requested relief in a vacuum does not resolve this significant concern and, \ntherefore, the Commission cannot determine that Constellation has proposed a just and reasonable \nreplacement rate.19 \nIII. \nCONCLUSION \nWHEREFORE, for the foregoing reasons, ODEC urges the Commission to reject \nConstellation’s Motion to Expedite, deny Constellation’s complaint and terminate the Show Cause \nproceeding without further action because the FPA section 206 burden has not been met, as \ndiscussed above and in the pleadings in these proceedings by the Indicated PJM Transmission \nOwners.  \nRespectfully submitted, \n \n /s/ Adrienne E. Clair \nAdrienne E. Clair \nJenna Cliatt \nThompson Coburn LLP \n1909 K Street, N.W., Suite 600 \nWashington, D.C.  20006-1167 \n(202) 585-6900 \n(202) 585-6969 (fax) \naclair@thompsoncoburn.com  \njcliatt@thompsoncoburn.com \n \nAttorneys for Old Dominion Electric \nCooperative \nDated: December 8, 2025 \n \n19 Constellation contends that “existing market mechanisms should be sufficient to ensure resource \nadequacy even during periods of rapid demand growth” then points to a proposal that is pending in the PJM \nstakeholder process. See Constellation Proposed ANOPR Reply Comments at 37-38."},{"page":8,"startToken":1929,"endToken":1971,"text":"CERTIFICATE OF SERVICE \n \nI hereby certify that on this 8th day of December 2025, I have caused a copy of the foregoing \nto be served upon each party designated on the Commission’s Official Service List for this \nproceeding. \n \n /s/Adrienne E. Clair"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":2,"endAt":172,"startToken":0,"endToken":227},{"p":2,"at":172,"title":"I. RELEVANT BACKGROUND","method":"printed heading","endPage":3,"endAt":1505,"startToken":227,"endToken":760},{"p":3,"at":1505,"title":"II. ANSWER","method":"printed heading","endPage":7,"endAt":217,"startToken":760,"endToken":1786},{"p":7,"at":217,"title":"III. CONCLUSION","method":"printed heading","endPage":8,"endAt":0,"startToken":1786,"endToken":1929},{"p":8,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":8,"endAt":249,"startToken":1929,"endToken":1971}]}