{"document":{"slug":"rec-20251208-5345","title":"Answer of Exelon Corporation to the Motion for Expedited Action of Constellation Energy Generation, LLC,","issued":"2025-12-08","accession":"20251208-5345","docket":"EL25-49-000","group":"PJM co-location compliance","filer":"Exelon Corporation","kind":"answer","file":"sources/filings/text/20251208-5345_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20251208-5345","tier":"record","sha256":"0ec8911b712cf55a673571d4646e5d6844cafceaf7c9012cb791e41ca1ba3f84","pages":22,"tokens":6249,"emptyPages":[],"textThemes":["study","colo","retail"]},"pages":[{"page":1,"startToken":0,"endToken":290,"text":"PUBLIC VERSION \nUNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \nPJM Interconnection, L.L.C., et al. \nLarge Loads Co-Located at Generating \nFacilities \nConstellation Energy Generation, LLC \nv. \nPJM Interconnection, L.L.C. \nDocket No. EL25-49-000 \nDocket No. AD24-11-000 \nDocket No. EL25-20-000 \n(consolidated) \nANSWER OF EXELON CORPORATION TO THE MOTION FOR EXPEDITED \nACTION OF CONSTELLATION ENERGY GENERATION, LLC \n(PUBLIC VERSION) \nPursuant to Rule 2131 of the Rules of Practice and Procedure of the Federal Energy \nRegulatory Commission (\"FERC\" or \"Commission\"), Exelon Corporation on behalf of its \nsubsidiaries2 (collectively, \"Exelon\") submits this Answer to the Motion for Expedited Action that \nwas filed by Constellation Energy Generation, LLC (\"Constellation\") on November 21, 2025 \n(\"Constellation's Motion\").3\nFor the reasons discussed in the Answer of the Indicated PJM Interconnection, L.L.C. \n(\"PJM\") Transmission Owners to Constellation's Motion, the Commission should reject \nConstellation's Motion.4 Exelon also files this Answer to correct any misapprehension regarding \n1 \nSee 18 C.F.R. § 385.213(d)(1) (\"Any answer to a motion or to an amendment to a motion must be made within \n15 days after the motion or amendment is filed, except as described below or unless otherwise ordered.'\"). \nExelon's subsidiaries are as follows: Atlantic City Electric Company, Baltimore Gas and Electric Company, \nCommonwealth Edison Company (\"ComEd\"), Commonwealth Edison Company of Indiana, Inc., Delmarva \nPower and Light Company, PECO Energy Company (\"PECO\"), and Potomac Electric Power Company. \n3 \nConstellation attached its comments filed in Docket No. RM26-4-000 to its motion in this proceeding. Exelon is \nnot addressing all of the issues with that RM26-4-000 filing here and will respond to those comments in Docket \nNo. RM26-4-000. \n4 \nSee Answer of the Indicated PJM Interconnection, L.L.C. Transmission Owners (Dec. 8, 2025)."},{"page":2,"startToken":290,"endToken":621,"text":"PUBLIC VERSION \nthe ability of large loads and their load serving entities to receive transmission services in the \nExelon service territories. \nI. \nREQUEST FOR CUU/PRIVIIIIC TREATMENT \nIn accordance with section 388.112 of the Commission's regulations,5 Exelon requests \nprivileged treatment for a portion of this Answer containing confidential information concerning \npending retail customer service applications. Exelon understands that the involved customers may \nview this information as competitively sensitive and ComEd (the relevant Exelon utility) also treats \nsuch information as non-public. Accordingly, good cause exists for the Commission to grant this \nrequest for privileged treatment of this information. \nExelon is filing both a public version of this Answer with necessary redactions and a non-\npublic version of this Answer that contains the confidential information. The non-public version \nhas been labelled \"CUI//PRIV//HC\" and should be made subject to privileged document protection \nby the Commission. In accordance with 18 C.F.R. § 388.112(b)(2)(i), a proposed form of \nprotective agreement modeled on the Commission's Model Protective Order is enclosed as \nAttachment A. To respect the competitive concerns of its customer, the Protective Order has been \nmodified to provide additional protections for material deemed \"Highly Confidential Privileged \nMaterial.\" Similar provisions have been included in other approved protective orders in recent \nyears.' Any questions regarding this request for privileged treatment should be directed to the \nundersigned. \n5 \n18 C.F.R. § 388.112. \n6 \nSee, e.g., PJ.,11 Interconnection, L.L.C., Docket No. ER23-2214-000, Order of Chief Judge Adopting Protective \nOrder, at P 1 (Dec. 4, 2023) (adopting proposed protective order that \"deviates from the Commission's Model \nProtective Order by deleting inapplicable provisions related to oil pipeline proceedings\" and also \"includes \nprovisions to bar disclosure of commercially sensitive information to `Competitive Duty Personnel.'\" (citation \nomitted)); DCR Transmission, L.L('., Docket No. ER23-2309-000, Order of Chief Judge Adopting Protective \nOrder, at P 16 (Jan. 18, 2024); see also Duke Energy Progress, LLC, Docket No. ER25-3483-000, Application, \n(cont'd) \n2"},{"page":3,"startToken":621,"endToken":899,"text":"PUBLIC VERSION \nII. \nANSWER \nIn its motion, Constellation points to the Commission's statement that there are \"allegations \nin the record that Exelon has delayed work on Constellation's requests to co-locate load with its \ngenerators at certain facilities due to Exelon's concerns that such requests are not allowed under \nthe [PJM Open Access Transmission Tariff (\"PJM Tariff')] without arranging for wholesale \ntransmission or retail distribution service.\"' To be clear, these are merely allegations. Exelon has \nnot \"delayed\" or refused service in response to any lawful request. \nIn Attachment 1 of Exhibit 5 to Constellation's November 22, 2024 Complaint filed in \nDocket No. EL25-20-000,8 Constellation produced a November 12, 2024 letter from ComEd to \nConstellation concerning interconnection requests at the LaSalle and Byron nuclear facilities. In \nthat letter, ComEd details certain design issues with Constellation's proposal and then explains \nthat the \"end use load is retail load under both Illinois and federal law and cannot be interconnected \nsolely through amendments to the LaSalle or Byron [interconnection service agreements].\"9\nComEd went on to explain: \nWe continue to believe there is no lawful path to interconnect end \nuse load at LaSalle and Byron without that load taking service as a \nretail customer of ComEd and we cannot continue to review \nproposals for co-location of end use load at LaSalle and Byron on \nsome other basis.1°\nat Attach. G (Sept. 22, 2025) (protective order in Federal Power Act section 205 filing with Highly Confidential \nPrivileged Material provisions). \nSee Constellation's Motion at 2 (citation omitted). \n8 \nSee Constellation, Complaint, Docket No. EL25-20. at Ex. 5 Attach. 1 (Nov. 22, 2024). \n9 \nId., Ex. 5 Attach. 1, at 2. \n10 \nId. \n3"},{"page":4,"startToken":899,"endToken":1195,"text":"PUBLIC VERSION \nComEd appropriately suggested that Constellation move forward by making the requested design \nchanges and submitting \"an application for retail service.\"11 \nThe decision was left with \nConstellation. ComEd cannot unilaterally provide retail electric service to a customer that does \nnot request it. \nRather than deciding to move forward by then submitting an application for retail service \n(or attempting to challenge ComEd's assessment that this was retail service), Constellation instead \ndecided to file its complaint seeking to change the PJM Tariff. Notwithstanding Constellation's \nallegations, the documentation submitted in this proceeding unambiguously shows that ComEd \nexplained to Constellation how to move forward and how to do so expeditiously. It is Constellation \nthat chose delay by disregarding Illinois retail regulation and established tariff mechanisms for \nentities that serve retail customers to obtain and ensure adequate transmission service. \nConstellation has chosen this path of litigation. \nThe tariff changes that Constellation seeks in the pending motion are not necessary for \nlarge load interconnection requests to move forward, regardless of whether the load is proposed to \nbe co-located with a generator or not. To the contrary, those requests are moving forward \nexpeditiously, including in the Exelon footprint. Exelon agrees that \"Nile United States' ability \nto remain at the forefront of technological innovation depends on a reliable supply of energy from \nall available electric generation sources and the integrity of our Nation's electric grid.\"12 Indeed, \nExelon is furthering those efforts. As shown in the chart below, Exelon' s service territories have \nbeen and are projected to continue to be a focal point for data center interconnection. \n11 \nId. \n12 \nStrengthening the Reliability & Security of the U.S. Electric Grid, Exec. Order No. 14,262, at Section 1 (Apr. 8, \n2025), https://www.whitehouse.gov/presidential-actions/2025/04/strengthening-the-reliability-and-security-of-\nthe-united-states-electric-grid/. \n4"},{"page":5,"startToken":1195,"endToken":1430,"text":"VIILIC VERSION \nProjected Data Center Load Growth in Exelon's Footprint \n3 \nal Phase 3 \nPhase 2 \nPhase 1 \nl Awaiting Cluster Studies 12026.1 \nF l Active Modatlantic Cluster Study \nI Active ComEd Cluster Study \nAwaiting Signed ISM \n6 \n1 \n04 22 \nO4 23 \n11 \n16 \n18+ \nr \n-6 \n03 24 \nO424 \nQ3'25 \nFour, \nPowwow \nAddbons \nOM. \nStudies expected \nto start in 2026 \nStudies expected \nto conclude in \n2026 \nExpected late \n2025 / early 2026 \nSource of Chart: Exelon, Earnings Conference Call Third Quarter 2025, at 13 (Nov. 4, 2025), \nhttps://investors.exeloncorp.com/static-files/3a3d9993-324a-456f-9ffl-db901e7dacde. \nAs explained by Max Leichtman, the Director of Economic and Workforce Development \nat ComEd, \"ComEd has experienced an unprecedented number of applications for service from \nnew customers with relatively large forecasted demand,\"\" and at the time of his direct testimony, \nComEd had 75 unique projects totaling over 28,000 megawatts (\"MW\") of maximum demand, \ni.e., approximately 4,000 MW higher than ComEd's all-time system peak demand in its 118-year \nhi story.14 Moreover, the Leichtman testimony notes that \"the average size of a unique large \n13 \nDirect Testimony on behalf of Commonwealth Edison Company, Ill. Commerce Commission, Docket No. 25-\n0679, \nEx. \n1.0. \nDirect \nTestimony \nof \nMax \nLeichtman, \nat \n3:58-59 (filed \nAug. \n21, \n2025), \nhttps://www.icc.illinois.gov/docket/P2025-0679/documents/369551 (choose -2. ComEd Ex. 1.0\" from list). \n14 \nId. at 6:108-111. \n5"},{"page":6,"startToken":1430,"endToken":1694,"text":"PUBLIC VERSION \ndemand project that began the process of obtaining electric service from ComEd in the [twelve \nmonths prior to the testimony] [was] approximately 700 MWs, roughly equivalent to the demand \nof 1,400 big box retail stores.\"15\nIn ComEd's service territory, data center demand has grown at an annual rate of 27 percent \nthrough June 2025, and ComEd's most recent large load adjustment request to PJM included a \nfuture expected demand increase of 11 gigawatts (\"GW\") by 2040, 6 GW higher than ComEd's \nsubmission relative to the prior year.16 Moreover, the 2025 actuals year to date, as of September \n30, 2025, for historical on-peak hourly demand for data centers in the ComEd service territory in \nNorthern Illinois was 600 MW.17 The foregoing underscores that Exelon is actively engaged in \nfurthering the objectives of the Administration in the artificial intelligence race. \nIn 2025, ComEd has received more than 25 customer service applications associated with \nrequests for large load interconnections, representing new load in excess of 20 GW. These \napplications are moving forward, showing that Constellation is seeking a solution to a problem \nthat does not exist. <BEGIN CUI//PRIV//HC> \n<END CUI//PRIV//HC> Any argument that co-located load applications are stalled or \nthat the requested relief is somehow necessary to ensure that interconnections proceed is patently \nfalse. \n15 \nId. at 6:113-115. \n16 \nExelon, Docket No. RM26-4-000, Comments at 2 (Nov. 21, 2025). \n17 \nSee Exelon, Earnings Conference Call Third Quarter 2025, at 13 (Nov. 4, 2025), \nhttps://inve sto rs.e xelo nc o rp. com/static-files/3a3d9993-324a-456f-9ff1-db901e7dacde. \n6"},{"page":7,"startToken":1694,"endToken":1883,"text":"PUBLIC VERSION \nFurther, to leave no doubt that Exelon is working to help interconnect data centers, last \nmonth, in Docket No. ER25-3492-000, FERC issued an Order Accepting Transmission Security \nAgreement, an agreement by and between PECO and Amazon Data Services, Inc. (\"Amazon\"). \nAmazon is constructing a new data center campus in Falls Township, Pennsylvania, and PECO \nwill provide retail electric delivery services for the data center campus, pursuant to its electric \nretail service tariff on file with the Pennsylvania Public Utility Commission. In addition, Network \nIntegrated Transmission Service will be procured by the responsible Load Serving Entity, as such \nterm is defined in the PJM Tariff. The Transmission Security Agreement \"ensures that a \ncontribution to the transmission revenue requirement is made by Amazon commensurate with its \nrequested end-use load relating to the construction of and service to its Data Center.\"18 This is \nanother example of Exelon, in compliance with the PJM Tariff, providing a feasible path forward \nfor data centers. \nConstellation's Motion and requested PJM Tariff changes are unwarranted and should be \ndenied. \n18 \nPECO, Docket No. ER25-3492-000, Tariff Filing, Transmittal Letter at 1 (Sept. 23, 2025). \n7"},{"page":8,"startToken":1883,"endToken":1946,"text":"PUBLIC VERSION \nRespectfully submitted, \n,'s/ William Sauer \nWilliam Sauer \nVice President, Federal Regulatory \nAffairs \nExelon Corporation \n701 Ninth St., NW \nWashington, DC 20001 \nTelephone: 202-868-7499 \nEmail: \nwilliam.sauer@exeloncorp.com \n/s,' Max Minzner \nMax Minzner \nSenior Vice President & Deputy General Counsel -\nCorporate \nExelon Corporation \n701 Ninth St., NW \nWashington, DC 20001 \nTelephone: 202-934-4740 \nEmail: max.minzner@exeloncorp.com \nOn behalf of Exelon Corporation"},{"page":9,"startToken":1946,"endToken":1950,"text":"PUBLIC VERSION \nATTACHMENT A"},{"page":10,"startToken":1950,"endToken":2277,"text":"PUBLIC VERSION \nUNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \nPJM Interconnection, L.L.C., et al. \nLarge Loads Co-Located at Generating \nFacilities \nConstellation Energy Generation, LLC \nv. \nPJM Interconnection, L.L.C. \nDocket No. EL25-49-000 \nDocket No. AD24-11-000 \nDocket No. EL25-20-000 \n(consolidated) \nPROTECTIVE AGREEMENT \nThis Protective Agreement (\"Agreement\"), entered into this \nday of \n, 20_ by \nand between Exelon Corporation on behalf of its subsidiaries' (\"Exelon\") and  \n(\"Intervenor\"), shall govern the use of all Privileged, Highly Confidential Privileged Material, \nand/or Critical Energy/Electric Infrastructure Information (\"CEII\") Material produced by Exelon \nto Intervenor, or vice versa, in connection with the captioned proceeding before the Federal Energy \nRegulatory Commission (the \"Commission\"). Exelon and Intervenor are sometimes referred to \nherein individually as a \"Participant\" or jointly as the \"Participants.\" \n1. Exelon filed in the above-referenced proceeding Privileged Material, Highly Confidential \nPrivileged Material, and/or CEII, as those terms are defined herein. \nIntervenor is a \nParticipant in such proceeding, as the term Participant is defined in 18 C.F.R. Section \n385.102(b), or has filed a motion to intervene or a notice of intervention in such proceeding. \nExelon and Intervenor enter into this Agreement to govern the use of Privileged Material, \nHighly Confidential Privileged Material, and/or CEII produced by, or on behalf of, Exelon \nand/or Intervenor in the above-referenced proceeding. \nNotwithstanding any order \nterminating such proceeding, this Agreement shall remain in effect unless and until \nspecifically modified or terminated by the Commission or a court of competent jurisdiction. \nIn the event this Agreement terminates, the obligations of Reviewing Representatives to \nmaintain the confidentiality of Privileged Material, Highly Confidential Privileged Material, \nand/or CEII as provided hereunder shall remain in effect for 18 months following the date of \ntermination. \nExelon's subsidiaries are as follows: Atlantic City Electric Company, Baltimore Gas and Electric Company, \nCommonwealth Edison Company, Commonwealth Edison Company of Indiana, Inc., Delmarva Power and Light \nCompany. PECO Energy Company, and Potomac Electric Power Company."},{"page":11,"startToken":2277,"endToken":2741,"text":"PUBLIC VERSION \n2. The Commission's regulations' and its policy governing the labelling of controlled \nunclassified information (\"CUI\")3 establish and distinguish the respective designations of \nPrivileged Material and CEII. As to these designations, this Protective Agreement provides \nthat a Participant: \nA. may designate as Privileged Material any material which customarily is treated \nby that Participant as commercially sensitive or proprietary or material subject \nto a legal privilege, which is not otherwise available to the public, and which if \ndisclosed, would subject that Participant or its customers to risk of competitive \ndisadvantage or other business injury; and \nB. must designate as CEII, any material that meets the definition of that term as \nprovided by 18 C.F.R. §§ 388.113(a), (c). \n3. For the purposes of this Protective Agreement, the listed terms are defined as follows: \nA. Participant(s): As defined at 18 C.F.R. § 385.102(b). \nB. Privileged Material:4\ni. \nMaterial (including depositions) provided by a Participant in response \nto discovery requests or filed with the Commission, and that is \ndesignated as Privileged Material by such Participant;5\nii. \nMaterial that is privileged under federal, state, or foreign law, such as \nwork-product privilege, attorney-client privilege, or governmental \nprivilege, and that is designated as Privileged Material by such \nParticipant;6\nCompare 18 C.F.R. § 388.112, with 18 C.F.R. § 388.113. This Protective Agreement does not alter the respective \nrequirements imposed by these sections on Privileged Material or CEII. \n3 \nNotice of Document Labelling Guidance for Documents Submitted to or Filed with the Commission or \nCommission Staff, 82 Fed. Reg. 18,632 (Apr. 20, 2017) (issued by Commission Apr. 14, 2017). \n4 \nThe Commission's regulations state that \"[f]or the purposes of the Commission's filing requirements, non-CEII \nsubject to an outstanding claim of exemption from disclosure under FOIA will be referred to as privileged \nmaterial.\" 18 C.F.R. § 388.112(a). The regulations further state that \"[f]or material filed in proceedings set for \ntrial-type hearing or settlement judge proceedings, a participant's access to material for which privileged \ntreatment is claimed is governed by the presiding official's protective order.\" Id. § 388.112(b)(2)(v). \n5 \nSee infra P 11 for the procedures governing the labeling of this designation. \n6 \nThe Commission's regulations state that \"[a] presiding officer may, by order . . . restrict public disclosure of \ndiscoverable matter in order to . . . [p]reserve a privilege of a participant\" 18 C.F.R. § 385.410(c)(3). To \nadjudicate such privileges, the regulations further state that \"[i]n the absence of controlling Commission \nprecedent, privileges will be determined in accordance with decisions of the Federal courts with due consideration \nto the Commission's need to obtain information necessary to discharge its regulatory responsibilities.\" Id. \n§ 385.410(d)(1)(i). \n2"},{"page":12,"startToken":2741,"endToken":3102,"text":"PUBLIC VERSION \niii. \nAny information contained in or obtained from such designated \nmaterial; \niv. \nAny other material which is made subject to this Protective Agreement \nby the Presiding Administrative Law Judge (Presiding Judge) or the \nChief Administrative Law Judge (Chief Judge) in the absence of the \nPresiding Judge or where no presiding judge is designated, the \nCommission, any court, or other body having appropriate authority, or \nby agreement of the Participants (subject to approval by the relevant \nauthority); \nv. \nNotes of Privileged Material (memoranda, handwritten notes, or any \nother form of information (including electronic form) which copies or \ndiscloses Privileged Material);' or \nvi. \nCopies of Privileged Material. \nvii. \nPrivileged Material does not include: \n1. Any information or document that has been filed with and accepted \ninto the public files of the Commission, or contained in the public \nfiles of any other federal or state agency, or any federal or state \ncourt, unless the information or document has been determined to \nbe privileged by such agency or court; or \n2. Information that is public knowledge, or which becomes public \nknowledge, other than through disclosure in violation of this \nProtective Agreement. \nC. Highly Confidential Privileged Material: A Participant may use this designation \nfor those materials that are of such a commercially sensitive nature among the \nParticipants or of such a private, personal nature that the producing Participant is \nable to justify a heightened level of confidential protection with respect to those \nmaterials. Highly Confidential Privileged Material shall include Privileged \nMaterial that present a higher risk of competitive injury if disclosed to \nCompetitive Duty Personnel as determined in good faith by the producing \nParticipant and includes materials such as: (1) information regarding contract \nnegotiations and contract buyouts and (2) strategic business or financial plans. \nExcept for the more limited list of persons who qualify as Reviewing \nRepresentatives for the purposes of Reviewing Highly Confidential Privileged \nMaterial (i.e., Reviewing Representatives that are not Competitive Duty \nPersonnel), such materials are subject to the same provisions in the Protective \nAgreement as other Privileged Material. \nNotes of Privileged Material are subject to the same restrictions for Privileged Material except as specifically \nprovided in this Protective Agreement. \n3"},{"page":13,"startToken":3102,"endToken":3450,"text":"PUBLIC VERSION \nD. Critical Energy/Electric Infrastructure Information (\"CEII\"): As defined at 18 \nC.F.R. §§ 388.113(a), (c). \nE. Non-Disclosure Certificate: The certificate attached to this Protective \nAgreement, by which Participants granted access to Privileged Material, Highly \nConfidential Privileged Material, and or CEII must certify their understanding \nthat such access to such material is provided pursuant to the terms and restrictions \nof this Protective Agreement, and that such Participants have read the Protective \nAgreement and agree to be bound by it. All executed Non-Disclosure Certificates \nmust be served on all Participants on the official service list maintained by the \nSecretary of the Commission for this proceeding. \nF. Reviewing Representative: A person who has signed a Non-Disclosure \nCertificate and who is: \ni. \nCommission Trial Staff designated as such in this proceeding; \nii. \nAn attorney who has made an appearance in this proceeding for a \nParticipant; \niii. \nAttorneys, paralegals, and other employees associated for purposes of \nthis case with an attorney who has made an appearance in this \nproceeding on behalf of a Participant; \niv. \nAn expert or an employee of an expert retained by a Participant for the \npurpose of advising, preparing for, submitting evidence or testifying in \nthis proceeding; \nv. \nA person designated as a Reviewing Representative by order of the \nPresiding Judge, the Chief Judge, or the Commission; or \nvi. \nEmployees or other representatives of Participants appearing in this \nproceeding with significant responsibility for this docket. \nG. The term \"Reviewing Representative\" for purposes of reviewing Highly \nConfidential Privileged Material defined in Paragraph 3(C) shall mean a person \nwho has signed a Non-Disclosure Certificate who is: \ni. \nListed in Paragraph 3(F), but is not Competitive Duty Personnel as \ndefined in Paragraph 3(H); or \nii. \nDesignated as a Reviewing Representative for purposes of reviewing \nHighly Confidential Privileged Material by agreement of the producing \nParticipant or by order of the Presiding Judge. \nH. The term \"Competitive Duty Personnel\" shall mean any individual(s) whose \nscope of employment or engagement includes the marketing, sale, or purchase \nof coal, natural gas, or electricity (collectively, \"Energy\"), the direct"},{"page":14,"startToken":3450,"endToken":3910,"text":"PUBLIC VERSION \nsupervision of any employee or employees whose duties include the marketing \nof Energy, or other Energy services in competition with the producing \nParticipant, all of which are considered \"Competitive Duties,\" except that \nCompetitive Duty Personnel shall not include employees of the Commission, \nany state utilities commission which is a Participant, in-house or outside \ncounsel, and/or an outside consultant retained by a Participant for the purpose \nof advising, preparing for, submitting evidence, or testifying in this proceeding. \n4. Privileged Material, Highly Confidential Privileged Material, and/or CEII shall be made \navailable under the terms of this Protective Agreement only to Participants and only to their \nReviewing Representatives as provided in Paragraphs 6-10 of this Protective Agreement. \nThe contents of Privileged Material, Highly Confidential Privileged Material, CEII or any \nother form of information that copies or discloses such materials shall not be disclosed to \nanyone other than in accordance with this Protective Agreement and shall be used only in \nconnection with this specific proceeding. \n5. All Privileged Material, Highly Confidential Privileged Material, and or CEII must be \nmaintained in a secure place. Access to those materials must be limited to Reviewing \nRepresentatives specifically authorized pursuant to Paragraphs 7-9 of this Protective \nAgreement. \n6. Privileged Material, Highly Confidential Privileged Material, and/or CEII must be handled \nby each Participant and by each Reviewing Representative in accordance with the Non-\nDisclosure Certificate executed pursuant to Paragraph 9 of this Protective Agreement. \nPrivileged Material, Highly Confidential Privileged Material, and/or CEII shall not be used \nexcept as necessary for the conduct of this proceeding, nor shall they (or the substance of \ntheir contents) be disclosed in any manner to any person except a Reviewing \nRepresentative who is engaged in this proceeding and who needs to know the information \nin order to carry out that person's responsibilities in this proceeding. A Reviewing \nRepresentative shall not disclose Highly Confidential Privileged Material to Competitive \nDuty Personnel, except as authorized pursuant to Paragraph 3(G). \nReviewing \nRepresentatives may make copies of Privileged Material, Highly Confidential Privileged \nMaterial, and/or CEII, but such copies automatically become Privileged Material, Highly \nConfidential Privileged Material, and/or CEII. Reviewing Representatives may make \nnotes of Privileged Material, which shall be treated as Notes of Privileged Material if they \nreflect the contents of Privileged Material. \n7. If a Reviewing Representative's scope of employment includes any of the activities listed \nunder this Paragraph 7, such Reviewing Representative may not use information contained \nin any Privileged Material, Highly Confidential Privileged Material, and/or CEII obtained \nin this proceeding for a commercial purpose (e.g., to give a Participant or competitor of \nany Participant a commercial advantage): \nA. Energy marketing; \nB. Direct supervision of any employee or employees whose duties include energy \nmarketing; or \n5"},{"page":15,"startToken":3910,"endToken":4416,"text":"PUBLIC VERSION \nC. The provision of consulting services to any person whose duties include energy \nmarketing. \n8. If a Participant wishes to designate a person not described in Paragraph 3(F) above as a \nReviewing Representative, the Participant must seek agreement from the Participant \nproviding the Privileged Material, Highly Confidential Privileged Material, and/or CEII. \nIf an agreement is reached, the designee shall be a Reviewing Representative pursuant to \nParagraph 3(E) of this Protective Agreement with respect to those materials. If no \nagreement is reached, the matter must be submitted to the Presiding Judge or the \nCommission for resolution. \n9. A Reviewing Representative shall not be permitted to inspect, participate in discussions \nregarding, or otherwise be permitted access to Privileged Material, Highly Confidential \nPrivileged Material, and/or CEII pursuant to this Protective Agreement until three business \ndays after that Reviewing Representative first has executed and served a Non-Disclosure \nCertificate.8 However, if an attorney qualified as a Reviewing Representative has executed \na Non-Disclosure Certificate, any participating paralegal, secretarial and clerical personnel \nunder the attorney's instruction, supervision or control need not do so. \nAttorneys \ndesignated Reviewing Representatives are responsible for ensuring that persons under their \nsupervision or control comply with this Protective Agreement, and must take all reasonable \nprecautions to ensure that Privileged Material, Highly Confidential Privileged Material, \nand/or CEII are not disclosed to unauthorized persons. Reviewing Representatives that are \nCompetitive Duty Personnel as defined in Paragraph 3(H) must execute a Non-Disclosure \nCertificate for Competitive Duty Personnel in the form attached hereto. All executed Non-\nDisclosure Certificates must be served on all Participants on the official service list \nmaintained by the Secretary of the Commission for the proceeding. \n10. Any Reviewing Representative may, consistent with the requirements in Paragraph 3(G), \ndisclose Privileged Material, Highly Confidential Privileged Material, and/or CEII to any \nother Reviewing Representative as long as both Reviewing Representatives have executed a \nNon-Disclosure Certificate. In the event any Reviewing Representative to whom Privileged \nMaterial, Highly Confidential Privileged Material, and/or CEII are disclosed ceases to \nparticipate in this proceeding, or becomes employed or retained for a position that renders him \nor her ineligible to be a Reviewing Representative under Paragraph 3(F) of this Protective \nAgreement, access to such materials by that person shall be terminated. Even if no longer \nengaged in this proceeding, every person who has executed a Non-Disclosure Certificate shall \ncontinue to be bound by the provisions of this Protective Agreement and the Non-Disclosure \nCertificate for as long as the Protective Agreement is in effect.' \n11. All Privileged Material, Highly Confidential Privileged Material, and/or CHI in this \nproceeding filed with the Commission, submitted to the Presiding Judge, or submitted to any \n8 \nDuring this three-day period, a Participant may file an objection with the Presiding Judge or the Commission \ncontesting that an individual qualifies as a Reviewing Representative, and the individual shall not receive access \nto the Privileged Material, Highly Confidential Privileged Material, and/or CEII until resolution of the dispute. \n9 \nSee infra P 19. \n6"},{"page":16,"startToken":4416,"endToken":4874,"text":"PUBLIC VERSION \nCommission personnel, must comply with the Commission's Notice of Document Labelling \nGuidance for Documents Submitted to or Filed with the Commission or Commission Staff' \nConsistent with those requirements: \nA. Documents that contain Privileged Material must include a top center header \non each page of the document with the following text: CUI//PRIV or \nCUU/PRIV//HC for Highly Confidential Privileged Material. \nAny \ncorresponding electronic files must also include this text in the file name. \nB. Documents that contain CEII must include a top center header on each page of \nthe document with the following text: CUI//CEII. \nAny corresponding \nelectronic files must also include this text in the file name. \nC. Documents that contain both Privileged Material and CEII must include a top \ncenter header on each page of the document with the following text: \nCUU/CEII/PRIV. Any corresponding electronic files must also include this text \nin the file name. \nD. The specific content on each page of the document that constitutes Privileged \nMaterial and/or CEII must also be clearly identified. For example, lines or \nindividual words or numbers that include both Privileged Material and CEII \nshall be prefaced and end with \"BEGIN CUU/CEII/PRIV\" and \"END \nCUI//CEII/PRIV\". \n12. If any Participant desires to include, utilize, or refer to Privileged Material (or Highly \nConfidential Privileged Material) or information derived from Privileged Material (or Highly \nConfidential Privileged Material) in testimony or other exhibits during the hearing in this \nproceeding in a manner that might require disclosure of such materials to persons other than \nReviewing Representatives, that Participant first must notify both counsel for the disclosing \nParticipant and the Presiding Judge (or the Commission), and identify all such Privileged \nMaterial (or Highly Confidential Privileged Material). Thereafter, use of such Privileged \nMaterial (or Highly Confidential Privileged Material) will be governed by procedures \ndetermined by the Presiding Judge (or the Commission). \n13. Nothing in this Protective Agreement shall be construed as precluding any Participant from \nobjecting to the production or use of Privileged Material, Highly Confidential Privileged \nMaterial, and/or CEII on any appropriate ground. \n14. Nothing in this Protective Agreement shall preclude any Participant from requesting the \nPresiding Judge (or the Chief Judge in the Presiding Judge's absence or where no presiding \njudge is designated), the Commission, or any other body having appropriate authority, to find \nthis Protective Agreement should not apply to all or any materials previously designated \nPrivileged Material (or Highly Confidential Privileged Material) pursuant to this Protective \nAgreement. The Presiding Judge (or the Chief Judge in the Presiding Judge's absence or where \nno presiding judge is designated), the Commission, or any other body having appropriate \n10 \n82 Fed. Reg. 18,632 (Apr. 20, 2017) (issued by Commission Apr. 14, 2017). \n7"},{"page":17,"startToken":4874,"endToken":5377,"text":"PUBLIC VERSION \nauthority may alter or amend this Protective Agreement as circumstances \\\\ arrant at any time \nduring the course of this proceeding. \n15. Each Participant governed by this Protective Agreement has the right to seek changes in it as \nappropriate from the Presiding Judge (or the Chief Judge in the Presiding Judge's absence or \nwhere no presiding judge is designated), the Commission, or any other body having appropriate \nauthority. \n16. Subject to Paragraph 17, the Presiding Judge (or the Chief Judge in the Presiding Judge's \nabsence or where no presiding judge is designated), or the Commission shall resolve any \ndisputes arising under this Protective Agreement pertaining to Privileged Material (or \nHighly Confidential Privileged Material) according to the following procedures. Prior to \npresenting any such dispute to the Presiding Judge, the Chief Judge or the Commission, \nthe Participants to the dispute shall employ good faith best efforts to resolve it. \nA. Any Participant that contests the designation of material as Privileged Material \n(or Highly Confidential Privileged Material) shall notify the Participant that \nprovided the Privileged Material (or Highly Confidential Privileged Material) \nby specifying in writing the material for which the designation is contested. \nB. In any challenge to the designation of material as Privileged Material (or Highly \nConfidential Privileged Material), the burden of proof shall be on the Participant \nseeking protection. If the Presiding Judge, the Chief Judge, or the Commission \nfinds that the material at issue is not entitled to the designation, the procedures of \nParagraph 17 shall apply. \nC. The procedures described above shall not apply to material designated by a \nParticipant as CEII. \nMaterial so designated shall remain subject to the \nprovisions of this Protective Agreement, unless a Participant requests and \nobtains a determination from the Commission's CEII Coordinator that such \nmaterial need not retain that designation. \n17. The designator will have five (5) days in which to respond to any pleading requesting \ndisclosure of Privileged Material (or Highly Confidential Privileged Material). Should the \nPresiding Judge, the Chief Judge, or the Commission, as appropriate, determine that the \ninformation should be made public, the Presiding Judge, the Chief Judge, or the \nCommission will provide notice to the designator no less than five (5) days prior to the date \non which the material will become public. This Protective Agreement shall automatically \ncease to apply to such material on the sixth (6th) calendar day after the notification is made \nunless the designator files a motion with the Presiding Judge, the Chief Judge, or the \nCommission, as appropriate, with supporting affidavits, demonstrating why the material \nshould continue to be privileged. Should such a motion be filed, the material will remain \nconfidential until such time as the interlocutory appeal or certified question has been \naddressed by the Motions Commissioner or the Commission, as provided in the \nCommission's regulations, 18 C.F.R. §§ 385.714 and 385.715. No Participant waives its \nrights to seek additional administrative or judicial remedies after a Presiding Judge or Chief \nJudge decision regarding Privileged Material (or Highly Confidential Privileged Material) \n8"},{"page":18,"startToken":5377,"endToken":5742,"text":"PUBLIC VERSION \nor the Commission's denial of any appeal thereof or determination in response to any \ncertified question. The provisions of 18 C.F.R. §§ 388.112 and 388.113 shall apply to any \nrequests under the Freedom of Information Act (5 U. S.C. § 552) for Privileged Material (or \nHighly Confidential Privileged Material) and/or CEII in the files of the Commission. \n18. Privileged Material, Highly Confidential Privileged Material, and/or CEII shall remain \navailable to Participants until the later of 1) the date an order terminating this proceeding no \nlonger is subject to judicial review, or 2) the date any other Commission proceeding relating \nto the Privileged Material, Highly Confidential Privileged Material, and/or CEII is concluded \nand no longer subject to judicial review. After this time, the Participant that produced the \nPrivileged Material, Highly Confidential Privileged Material, and/or CEII may request (in \nwriting) that all other Participants return or destroy the Privileged Material, Highly \nConfidential Privileged Material, and/or CEII. This request must be satisfied with within \nfifteen (15) days of the date the request is made. However, copies of filings, official transcripts \nand exhibits in this proceeding containing Privileged Material, Highly Confidential Privileged \nMaterial, or Notes of Privileged Material, may be retained if they are maintained in accordance \nwith Paragraph 5 of this Protective Agreement. If requested, each Participant also must submit \nto the Participant making the request an affidavit stating that to the best of its knowledge it has \nsatisfied the request to return or destroy the Privileged Material, Highly Confidential Privileged \nMaterial, and/or CEII. To the extent Privileged Material, Highly Confidential Privileged \nMaterial, and/or CHI are not returned or destroyed, they shall remain subject to this Protective \nAgreement. \n19. Regardless of any order terminating this proceeding, this Protective Agreement shall \nremain in effect until specifically modified or terminated by the Presiding Judge, the Chief \nJudge, or the Commission. All CEII designations shall be subject to the \"[d]uration of the \nCEII designation\" provisions of 18 C.F.R. § 388.113(e). \n20. Any violation of this Protective Agreement and of any Non-Disclosure Certificate executed \nhereunder shall constitute a violation of an order of the Commission. \n9"},{"page":19,"startToken":5742,"endToken":5758,"text":"PUBLIC VERSION \nFor Exelon: \nSigned:  \nPrinted Name: \nDate: \nFor Inter enoi . \nSigned:  \nPrinted Name: \nDate: \n10"},{"page":20,"startToken":5758,"endToken":5942,"text":"PUBLIC VERSION \nUNITED STATES OF AMERICA \nFEDERAL ENERGY REGULATORY COMMISSION \nPJM Interconnection, L.L.C., et al. \nLarge Loads Co-Located at Generating \nFacilities \nConstellation Energy Generation, LLC \nv. \nPJM Interconnection, L.L.C. \nDocket No. EL25-49-000 \nDocket No. AD24-11-000 \nDocket No. EL25-20-000 \n(consolidated) \nNON-DISCLOSURE CERTIFICATE FOR NON-COMPETITIVE DUTY PERSONNEL \nI hereby certify my understanding that access to Privileged Material, Highly Confidential \nPrivileged Material, and/or Critical Energy/Electric Infrastructure Information (CEII) i s provided to \nme pursuant to the terms and restrictions of the Protective Agreement in this proceeding, that I have \nbeen given a copy of and have read the Protective Agreement, and that I agree to be bound by it. I \nunderstand that the contents of Privileged Material, Highly Confidential Privileged Material, and/or \nCEII, any notes or other memoranda, or any other form of information that copies or discloses such \nmaterials, shall not be disclosed to anyone other than in accordance with the Protective Agreement. \nI acknowledge that a violation of this certificate constitutes a violation of an order of the Federal \nEnergy Regulatory Commission. \nBy: \nPrinted Name: \nTitle: \nRepresenting: \nDate:"},{"page":21,"startToken":5942,"endToken":6188,"text":"PUBLIC VERSION \nUNITED STATES OF AMERICA \nFEDERAL ENERGY REGULATORY COMMISSION \nPJM Interconnection, L.L.C., et al. \nLarge Loads Co-Located at Generating \nFacilities \nConstellation Energy Generation, LLC \nv. \nPIM Interconnection, L.L.C. \nDocket No. EL25-49-000 \nDocket No. AD24-11-000 \nDocket No. EL25-20-000 \n(consolidated) \nNON-DISCLOSURE CERTIFICATE \nFOR COMPETITIVE DUTY PERSONNEL \nI hereby certify my understanding that access to Privileged Material in the above-captioned \ncase is provided to me pursuant to the terms and restrictions of the Protective Agreement in this \nproceeding, that I have been given a copy of and have read the Protective Agreement, and that I \nagree to be bound by it. I understand that the contents of Privileged Material, any notes or other \nmemoranda, or any other form of information that copies or discloses Privileged Material shall \nnot be disclosed to anyone other than in accordance with the Protective Agreement and shall be \nused only in connection with this proceeding. I acknowledge that my duties and responsibilities \ninclude \"Competitive Duties\" as described in the Protective Agreement and, as such, I understand \nthat I shall neither have access to, nor disclose, the contents of the Highly Confidential Privileged \nMaterial that are marked as \"CUI//PRIVAIC,\" any notes or other memoranda, or any other form \nof information that copies or discloses Privileged Material that is marked as \"CUI//PRIV//HC.\" I \nacknowledge that a violation of this certificate constitutes a violation of an order of the Federal \nEnergy Regulatory Commission. \nBy: \nPrinted Name: \nTitle: \nRepresenting: \nDate:"},{"page":22,"startToken":6188,"endToken":6249,"text":"PUBLIC VERSION \nCERTIFICATE OF SERVICE \nI hereby certify that I have this day served the foregoing document upon each person \ndesignated on the official service list in the above captioned dockets. \nDated this 8th day of December, 2025. \ns Alejandro Bautista \nAlejandro Bautista \nAssistant General Counsel \nExelon Corporation \n2301 Market Street \nPhiladelphia, PA 19101 \nTelephone: 267-533-0120 \nEmail: Alejandro.Bautista@exeloncorp.com"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":2,"endAt":145,"startToken":0,"endToken":311},{"p":2,"at":145,"title":"I. REQUEST FOR CUU/PRIVIIIIC TREATMENT","method":"printed heading","endPage":3,"endAt":16,"startToken":311,"endToken":623},{"p":3,"at":16,"title":"II. ANSWER","method":"printed heading","endPage":9,"endAt":16,"startToken":623,"endToken":1948},{"p":9,"at":16,"title":"ATTACHMENT A","method":"printed heading","endPage":11,"endAt":902,"startToken":1948,"endToken":2413},{"p":11,"at":902,"title":"A. Participant(s): As defined at 18 C.F.R. § 385.102(b).","method":"printed heading","endPage":11,"endAt":960,"startToken":2413,"endToken":2426},{"p":11,"at":960,"title":"B. Privileged Material:4","method":"printed heading","endPage":12,"endAt":1258,"startToken":2426,"endToken":2930},{"p":12,"at":1258,"title":"C. Highly Confidential Privileged Material: A Participant may use this designation","method":"printed heading","endPage":13,"endAt":127,"startToken":2930,"endToken":3122},{"p":13,"at":127,"title":"E. Non-Disclosure Certificate: The certificate attached to this Protective","method":"printed heading","endPage":13,"endAt":746,"startToken":3122,"endToken":3210},{"p":13,"at":746,"title":"F. Reviewing Representative: A person who has signed a Non-Disclosure","method":"printed heading","endPage":13,"endAt":1607,"startToken":3210,"endToken":3341},{"p":13,"at":1607,"title":"G. The term \"Reviewing Representative\" for purposes of reviewing Highly","method":"printed heading","endPage":13,"endAt":2109,"startToken":3341,"endToken":3417},{"p":13,"at":2109,"title":"H. The term \"Competitive Duty Personnel\" shall mean any individual(s) whose","method":"printed heading","endPage":14,"endAt":3100,"startToken":3417,"endToken":3892},{"p":14,"at":3100,"title":"A. Energy marketing;","method":"printed heading","endPage":14,"endAt":3122,"startToken":3892,"endToken":3895},{"p":14,"at":3122,"title":"B. Direct supervision of any employee or employees whose duties include energy","method":"printed heading","endPage":15,"endAt":16,"startToken":3895,"endToken":3912},{"p":15,"at":16,"title":"C. The provision of consulting services to any person whose duties include energy","method":"printed heading","endPage":16,"endAt":226,"startToken":3912,"endToken":4446},{"p":16,"at":226,"title":"A. Documents that contain Privileged Material must include a top center header","method":"printed heading","endPage":16,"endAt":516,"startToken":4446,"endToken":4492},{"p":16,"at":516,"title":"B. Documents that contain CEII must include a top center header on each page of","method":"printed heading","endPage":16,"endAt":730,"startToken":4492,"endToken":4528},{"p":16,"at":730,"title":"C. Documents that contain both Privileged Material and CEII must include a top","method":"printed heading","endPage":16,"endAt":977,"startToken":4528,"endToken":4569},{"p":16,"at":977,"title":"D. The specific content on each page of the document that constitutes Privileged","method":"printed heading","endPage":17,"endAt":985,"startToken":4569,"endToken":5023},{"p":17,"at":985,"title":"A. Any Participant that contests the designation of material as Privileged Material","method":"printed heading","endPage":17,"endAt":1308,"startToken":5023,"endToken":5066},{"p":17,"at":1308,"title":"B. In any challenge to the designation of material as Privileged Material (or Highly","method":"printed heading","endPage":17,"endAt":1673,"startToken":5066,"endToken":5123},{"p":17,"at":1673,"title":"C. The procedures described above shall not apply to material designated by a","method":"printed heading","endPage":22,"endAt":16,"startToken":5123,"endToken":6190},{"p":22,"at":16,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":22,"endAt":436,"startToken":6190,"endToken":6249}]}