{"document":{"slug":"rec-20251208-5354","title":"Answer of Indicated PJM Interconnection, L.L.C. Transmission Owners to the 11/21/2025 Motion for Expedited Action filed by Constellation Energy Generation, LLC","issued":"2025-12-08","accession":"20251208-5354","docket":"EL25-49-000","group":"PJM co-location compliance","filer":"Exelon CorporationAMP Transmission, LLCOld Dominion ,City Of Cleveland, Ohio ,City of Hamilton ,Duquesne Light Company ,FIRST ENERGY CORPORATION ,East Kentucky Power Cooperative, Inc. ,PPL Corporation ,Wabash Valley Power Association ,","kind":"answer","file":"sources/filings/text/20251208-5354_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20251208-5354","tier":"record","sha256":"758ba0eb715e62a00e5a3e1e85baf47ad20b317dd0c4f3869827ac2c1611c75b","pages":18,"tokens":5518,"emptyPages":[],"textThemes":["colo","cost","study"]},"pages":[{"page":1,"startToken":0,"endToken":350,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \nPJM Interconnection, L.L.C., et al. \n \n) \nDocket No. EL25-49-000 \n \nLarge Loads Co-Located at Generating \nFacilities \n) \nDocket No. AD24-11-000 \nConstellation Energy Generation, LLC \n \nv. \n \nPJM Interconnection, L.L.C. \n) \n \n) \n \n) \nDocket No. EL25-20-000 \n(consolidated) \n \nANSWER OF THE INDICATED PJM TRANSMISSION OWNERS TO THE MOTION \nFOR EXPEDITED ACTION OF CONSTELLATION ENERGY GENERATION, LLC  \n \nPursuant to Rule 2131 of the Rules of Practice and Procedure of the Federal Energy \nRegulatory Commission (“FERC” or “Commission”), the Indicated PJM Interconnection, L.L.C. \n(“PJM”) Transmission Owners (“Indicated TOs”)2 submit this Answer to the Motion for Expedited \nAction that was filed by Constellation Energy Generation, LLC (“Constellation”) on November \n21, 2025 (“Constellation’s Motion”).3 \n \n1  \nSee 18 C.F.R. § 385.213(d)(1) (“Any answer to a motion or to an amendment to a motion must be made within \n15 days after the motion or amendment is filed, except as described below or unless otherwise ordered.”). \n2  \nThis filing was prepared on behalf of the following PJM Transmission Owners: AMP Transmission, LLC; City \nof Cleveland, Department of Public Utilities, Division of Cleveland Public Power; City of Hamilton, OH; \nDuquesne Light Company; East Kentucky Power Cooperative; Exelon Corporation, on behalf of Atlantic City \nElectric Company, Baltimore Gas and Electric Company, Commonwealth Edison Company, Commonwealth \nEdison Company of Indiana, Inc., Delmarva Power & Light Company, PECO Energy Company, and Potomac \nElectric Power Company; FirstEnergy Service Company, as agent for its affiliates American Transmission \nSystems, Incorporated, Jersey Central Power & Light Company, Mid-Atlantic Interstate Transmission LLC, \nKeystone Appalachian Transmission Company, The Potomac Edison Company, Monongahela Power Company \nand Trans-Allegheny Interstate Line Company (collectively, the “FirstEnergy Transmission Companies”); Old \nDominion Electric Cooperative; PPL Electric Utilities Corporation; Rockland Electric Company; Southern \nMaryland Electric Cooperative, Inc.; UGI Utilities Inc; and Wabash Valley Power Association, Inc. \n3  \nConstellation attached its comments filed in Docket No. RM26-4-000 to its motion in this proceeding.  The \nIndicated TOs are not addressing all of the issues with the RM26-4-000 filing in the instant filing—those issues \nwill instead be addressed where they belong in Docket No. RM26-4-000."},{"page":2,"startToken":350,"endToken":686,"text":"2 \n \nFor the reasons discussed herein, the Commission should reject Constellation’s Motion, \nwhich if granted would result in affordability concerns for customers, market uncertainty, \nreliability risks, and a jurisdictional overreach on the part of the Commission.  Should the \nCommission decide to act in this proceeding prior to resolution of Docket No. RM26-4-000, the \nonly action that should be taken, as the Indicated TOs have previously explained, is to terminate \nthe above-captioned complaint dockets because the PJM Open Access Transmission Tariff (“PJM \nTariff”) has not been shown to be unjust and unreasonable.4 \nI. \nBACKGROUND \nOn October 23, 2025, the Secretary (“Energy Secretary”) of the U.S. Department of Energy \n(“DOE”) “direct[ed] [FERC] to initiate rulemaking procedures and [to] consider [an] Advance \nNotice of Proposed Rulemaking (ANOPR) presenting potential reforms to ensure the timely and \norderly interconnection of large loads to the transmission system.”5  The Energy Secretary \nsubmitted the proposal through his authority under section 403 of the Department of Energy \nOrganization Act6 and asked that the Commission act on the proposal “no later than April 30, \n2026.”7  On October 27, 2025, the Commission issued a notice inviting comments on the ANOPR \nin a new rulemaking docket, Docket No. RM26-4-000.8  Among other things, the ANOPR is \nexploring the possibility of standardizing interconnection procedures and agreements for “hybrid \n \n4  \nSee Answer of Indicated TOs at 24–25 (June 3, 2025). \n5  \nSecretary Chris Wright, DOE, Ensuring the Timely and Orderly Interconnection of Large Loads: Advance Notice \nof Proposed Rulemaking (“ANOPR”), Docket No. RM26-4-000,  at P 1 (Oct. 27, 2025) (footnote omitted) (“DOE \nANOPR Filing”). \n6  \nSee 42 U.S.C. § 7173(a) (“The Secretary and the Commission are authorized to propose rules, regulations, and \nstatements of policy of general applicability with respect to any function within the jurisdiction of the Commission \nunder section 7172 of this title.”). \n7  \nDOE ANOPR Filing, Transmittal Letter at 2. \n8  \nInterconnection of Large Loads to the Interstate Transmission System, Docket No. RM26-4-000, Notice Inviting \nComments (Oct. 27, 2025)."},{"page":3,"startToken":686,"endToken":1035,"text":"3 \n \nfacilities,” which the ANOPR defines as loads, “seeking to share a point of interconnection with \nnew or existing generation facilities.”9  Hundreds of comments and reply comments were \nsubmitted by numerous parties on the ANOPR.   \nConstellation’s Motion asks that FERC quickly move forward and rule on co-located load \nissues in PJM, rather than waiting until it has considered and ruled in the aforementioned \nrulemaking proceeding.10 \nII. \nANSWER \nA. Constellation’s Desire for a PJM-Specific Outcome Is Inappropriate \nWhere the Commission Is Evaluating These Issues at a National Level in \nthe Pending ANOPR Proceeding. \nPJM’s existing tariff is just and reasonable and should be upheld for that reason.  Further, \nit would cause confusion and unwarranted expense and upheaval for the Commission to modify \nthe PJM Tariff in this proceeding on an interim basis before addressing issues nationwide in \nDocket No. RM26-4-000.  Would an early ruling in PJM mean that PJM will have different rules \nfrom the rest of the country?  Or would the rules be changed again once a ruling is issued in RM26-\n4-000?  Any changes to the PJM Tariff should be informed by the principles or rules established \nthrough the ANOPR process, to adhere to the policy direction and solutions, which FERC is now \ncontemplating on a national basis.  A patchwork of rules that may or may not change in the near-\nterm is a recipe for market uncertainty that could stifle rather than assist sensible forward \nmovement on data center development, including investment delays in energy infrastructure \n \n9  \nDOE ANOPR Filing at P 12. \n10  Constellation’s Motion suggests transmission owners are delaying large load interconnections.  See \nConstellation’s Motion at 2.  Nothing could be further from the truth.  The Indicated TOs are fully supportive of \ninterconnecting large loads, co-located or otherwise, as quickly, safely, equitably, and reliably as possible, \nconsistent with the existing just and reasonable PJM Tariff and with applicable state laws.  Concurrently with this \nanswer, Exelon is filing a separate answer to correct any misapprehension regarding the ability of large loads and \ntheir load serving entities to receive transmission services in the Exelon service territories."},{"page":4,"startToken":1035,"endToken":1389,"text":"4 \n \nneeded to support increasing demand.  The expedited action in this docket that Constellation seeks \nwould potentially pre-judge issues to be decided in the ANOPR proceeding without adequate \nconsideration of the full record being developed there and potentially result in conflicting \noutcomes.   \nConstellation argues that an early ruling for PJM is supported by the fact that the DOE \nANOPR Filing explains that it “is not intended in any way to discourage public utilities from \nmaking filings to address these and similar issues under [Federal Power Act (“FPA”)] section \n205.”11  But allowing filings under FPA section 20512 is simply a reflection of the statute—public \nutilities have a right under FPA section 205 “to file rates and terms for services rendered with \n[their] assets.”13  This reservation of rights to transmission owners to modify tariffs at any time for \nservice provided with their assets does not alter the far stricter rules applicable to FPA section \n20614 actions, which can only proceed when the rate is found “unjust [and] unreasonable.”15  That \nburden has not been met, nor would it be appropriate to make such a finding while the hundreds \nof comments on the ANOPR are in the midst of their review.  Should the Commission decide to \nact in this proceeding prior to action in the ANOPR docket, as the Indicated TOs have explained \nin prior filings, the appropriate course of action would be to terminate the complaint and show \ncause proceedings for failure to meet the burden established under FPA section 206.16 \n \n11  DOE ANOPR Filing at P 32. \n12  16 U.S.C. § 824d. \n13  Atl. City Elec. Co. v. FERC, 295 F.3d 1, 9 (D.C. Cir. 2002) (citing 16 U.S.C. § 824d). \n14  16 U.S.C. § 824e. \n15  Id. § 824e(a). \n16  See, e.g., Answer of Indicated TOs at 2–3 (June 3, 2025) (“Neither the Commission nor any of the parties \nsupporting the initiation of this FPA section 206 proceeding have demonstrated that the existing [PJM Tariff] is \nunjust and unreasonable.  Consequently, the only action that may lawfully be taken is to terminate this \nproceeding.”)."},{"page":5,"startToken":1389,"endToken":1699,"text":"5 \n \nB. Constellation Would Have the Commission Improperly and Prematurely \nMake a Broad Jurisdictional Determination in this Proceeding. \nUnder FPA section 201(b)(1), FERC has jurisdiction over “the transmission of electric \nenergy in interstate commerce and . . . the sale of electric energy at wholesale in interstate \ncommerce.”17  Except as otherwise provided for under the FPA, carved out from FERC’s \njurisdiction are “facilities used for the generation of electric energy[,] . . . facilities used in local \ndistribution or only for the transmission of electric energy in intrastate commerce, . . . [and] \nfacilities for the transmission of electric energy consumed wholly by the transmitter.”18 \nThe National Association of Regulatory Utility Commissions (“NARUC”) recognizes in a \nrecent resolution that “the ANOPR asserts FERC jurisdiction over the interconnection of large \nloads to the transmission system” and asks FERC to “make clear that it is affirmatively not \nasserting jurisdiction over end-use sales, which falls squarely within the exclusive jurisdiction of \nstate retail energy regulatory authorities.”19 \nIn the Show Cause Order in this proceeding, FERC explained that, \n[T]he Commission has exercised authority over the terms of certain \ninterconnections to the transmission system as “an essential element \nof [t]ransmission [s]ervice.”  Although the Commission reached that \nconclusion based on the nature of interconnection to the \ntransmission system generally, not the purpose for such \ninterconnection (i.e., to make a wholesale sale or to make a \nwholesale or retail purchase), it has not historically exercised \n \n17  16 U.S.C. § 824(b)(1). \n18  Id. \n19  NARUC, EL-1 Resolution Urging the Federal Energy Regulatory Commission to Preserve and Affirm State Retail \nRegulatory Jurisdiction in its Large Load Interconnection Proceeding, Substantive Resolutions Passed by the \nNARUC Board of Directors, at 6, https://pubs.naruc.org/pub/97FE08D1-CF4D-9199-BA7F-\n5884DD427E55?_gl=1*1cgs1pd*_ga*MTEwMTgwNTA4OS4xNzUxNTQ3Nzc0*_ga_QLH1N3Q1NF*czE3\nNjI5NTMxNTAkbzExJGcxJHQxNzYyOTUzMTY4JGo0MiRsMCRoMA (adopted by the NARUC Board of \nDirectors on Nov. 11, 2025)."},{"page":6,"startToken":1699,"endToken":2035,"text":"6 \n \njurisdiction over any and all transmission-level interconnections of \nretail load.20      \n \nThe Commission further explained that it has “examine[d] whether certain facilities had a \n‘dual use,’ (i.e., the facilities were used for both wholesale and retail purposes), but the \nCommission limited its assertion of jurisdiction to distribution level interconnections.”21  And in \nanother recent proceeding, FERC declined to address “jurisdiction over the process of \ninterconnecting loads to the Commission-jurisdictional transmission system.”22 \nConstellation would have the Commission decide in this proceeding that co-located load \ninterconnections should be treated as entirely FERC-jurisdictional, disregarding the fact that retail \nservice to the loads is definitely not subject to FERC authority.  Consistent with their prior \ncomments,23 the Indicated TOs reiterate that it is the Network Integration Transmission Service \n(“Network Service”) customer that is taking FERC-jurisdictional transmission service in serving \nthe co-located load, which is typically a load serving entity, but if a state allows, it may be the load \nitself.  The only part of such an arrangement that is FERC jurisdictional is the transmission service \nprovided by the interstate grid to the load serving entity. \nThe Commission may decide, to the extent it has jurisdiction, how transmission costs \nassociated with large load customer interconnections will be recovered in FERC Docket No. \nRM26-4-000.  In the context of this proceeding, for FERC to determine what transmission costs \n \n20  PJM Interconnection, L.L.C., 190 FERC ¶ 61,115, at P 72 (2025) (alterations in original) (footnotes omitted) \n(“Show Cause Order”); see also id. PP 66–72. \n21  Id. P 72 n.224 (citation omitted). \n22   Tri-State Generation and Transmission Ass’n, Inc., 193 FERC ¶ 61,070, at P 50 (2025)  (“Because it appears that \nTri-State’s proposal before us sets the terms of retail sales, we need not elaborate in this order on other matters \nraised by parties regarding the extent of the Commission’s jurisdiction, such as jurisdiction over the process of \ninterconnecting loads to the Commission-jurisdictional transmission system.”). \n23  See Answer of Indicated TOs at 15–16 (June 3, 2025)."},{"page":7,"startToken":2035,"endToken":2343,"text":"7 \n \nshould appear on a particular retail customer’s (including a large load customer’s) bill would have \nFERC tread into questionable jurisdictional territory that would have broad national implications. \nNotably, Network Service addresses many of the jurisdictional issues raised by NARUC \nand others.  That is, there are no jurisdictional complications if loads are served by a state-\nauthorized load serving entity that procures Network Service to serve that load and, perhaps, other \nloads.  Affirmation by FERC that this is Network Service, and that FERC has jurisdiction over that \nservice, will clarify the contentious jurisdictional debate.  Once it is made clearer that this service \nis Network Service, the process for seeking service is unambiguous under the existing PJM Tariff \nand has not been shown to be a problem.  Of course, network customers have to pay for embedded \ncosts of transmission—something Constellation objects to—but that has not been shown to be \nunjust and unreasonable. \nC. Constellation’s Preferred Outcome Raises Significant Affordability and \nReliability Concerns. \nWhat Constellation proposes would result in large loads avoiding their share of the cost of \nthe transmission services that they rely upon.  But the services are not free.  If the large loads do \nnot pay for the transmission system and related services that they use, someone else must pay \ninstead.  Constellation’s continued push to subsidize co-located load would result in significant \ncost-shifts to other customers.24 \nWhile transmission and ancillary service charges are the primary issue in this proceeding, \nload impacts should certainly be taken into consideration.  PJM’s independent market monitor, \nMonitoring Analytics, LLC, warned in its recent 2025 Quarterly State of the Market Report that \nrapid data center growth is driving tight supply-demand conditions, higher capacity prices, and \n \n24  See Exelon Comments in Opposition to Complaint, Docket No. EL25-20, at Attach. 2, Declaration of John J. \nReed & Danielle S. Powers (filed Dec. 12, 2024)."},{"page":8,"startToken":2343,"endToken":2652,"text":"8 \n \nincreased transmission and energy costs for all customers.25  The Market Report asserts that \nproposals to let data centers remove existing capacity from the market and dedicate it to themselves \nwould create cost shifts and reliability risks until new generation is built.26  Constellation’s Motion \nnot only evades this issue entirely but attempts to sidestep regulatory and PJM oversight of the \nissue by not measuring the actual consumption of large loads that the grid must be prepared to \nsupport. \nIncreased transmission investment will be needed to ensure continued reliability of the grid \nwhen massive and diverse new loads become connected to the system.  The lack of visibility into \nthe operation of these loads, as discussed further below, could adversely affect grid stability and \nprevent adequate planning on the part of PJM.  This underscores the proposition that new large \nloads, whether or not co-located with generation, should pay their share of the embedded cost of \nthe transmission system. \nAs PJM’s independent market monitor explained, it would be inappropriate to “shift the \ncosts of serving data center load to all other customers.”27  But that is exactly what would happen \nif Constellation’s plan were to go forward, permitting data centers to receive the benefits of the \nelectric grid without bearing their fair share of costs for that service.  Constellation’s proposal to \nallow certain categories of customers to avoid paying for transmission service would only frustrate \nthe purpose of the FPA, which is “to encourage the orderly development of plentiful supplies of \nelectricity . . . at reasonable prices.”28   \n \n25  Monitoring Analytics, LLC, Q3 State of the Market Report for PJM: January Through September, at 1–3 (Nov. \n13, 2025), https://www.monitoringanalytics.com/reports/PJM_State_of_the_Market/2025/2025q3-som-pjm.pdf \n(“Market Report”). \n26  See id. \n27  Id. at 3. \n28  NAACP v. FPC, 425 U.S. 662, 669–70 (1976)."},{"page":9,"startToken":2652,"endToken":3146,"text":"9 \n \nAffordability should remain top of mind for the Commission.  In PJM, demand has \noutpaced the development of supply.29  The transmission system requires maintenance to ensure \nreliability, resilience, and quality of service.  Maintenance comes at a cost, and all customers that \nbenefit from that maintenance and that rely upon the transmission system should bear that cost.  \nDoing otherwise would place disproportionate financial risks on an ongoing basis to other \ncustomers and unduly benefit large loads that avoid paying for Network Service.   \nAnother problem is visibility by transmission system operators and planners into critical \ninformation and operating conditions that bear on system stability and reliability.  When co-located \nload is hidden and not appropriately accounted for in transmission planning and operations, it \ncreates reliability risks by undermining accurate system modeling and resource adequacy \nassessments.  North American Electric Reliability Corporation (“NERC”) has explained in this \nproceeding that (1) “system operators may lack sufficient information to perform reliability \nanalysis on co-located large loads”; (2) “large loads may or may not be visible to system operators \ndepending on the load’s operation and interconnection type”; (3) “[i]f a load is connected but \n \n29  NERC, 2025–2026 Winter Reliability Assessment, at 8 (Nov. 2025), https://www.nerc.com/globalassets/our-\nwork/assessments/nerc_wra_2025.pdf (“Winter electricity demand is rising at the fastest rate in recent years, \nparticularly in areas where data center development is occurring. . . . Most assessment areas are projecting an \nincrease in peak demand.  SaskPower, PJM, the U.S. Southeast, and parts of the U.S. West have the largest \nincrease in peak demand forecasts.”); see PJM, PJM Auction Procures 134,311 MW of Generation Resources; \nSupply Responds to Price Signal, at 1 (July 22, 2025), https://www.pjm.com/-/media/DotCom/about-\npjm/newsroom/2025-releases/20250722-pjm-auction-procures-134311-mw-of-generation-resources-supply-\nresponds-to-price-signal.pdf (explaining that PJM’s 2026/2027 Base Residual Auction “cleared volume was just \nover (by 139 MW UCAP) the projected reliability requirement, underscoring the region’s tightening supply-\ndemand balance”); NERC, 2024 Long-Term Reliability Assessment Report, at 16 (Dec. 2024, corrected July 11, \n2025), https://www.nerc.com/globalassets/our-work/assessments/2024-ltra_corrected_july_2025.pdf (“PJM’s \nprojections for generator additions in 2025 and 2026 are scaled back dramatically from the 2023 LTRA while \ndemand forecasts continue to rise.”); id. at 92 (“Overall, new generation is coming on-line slower than anticipated. \nGenerator retirements are outpacing the new generation replacing them.  As a result, PJM could face future \nresource adequacy challenges, impacting system reliability and PJM’s ability to serve load. PJM could be at risk \nof facing resource adequacy challenges if these trends continue.  PJM has applied an 11% reduction to the \nnameplate value of Tier 1 resources to reflect the historical rate of slower-than-anticipated addition of new \ngeneration.”); id. at 93 (“Driven by discrete and localized load growth, like Data Center Alley in Loudoun County, \nVirginia, in 2022, PJM and stakeholders conducted a review of data center load growth and identified growth \nrates of over 300% in some instances.”)."},{"page":10,"startToken":3146,"endToken":3411,"text":"10 \n \noperating conditions are providing only partial or no generation, there is a risk of thermal overloads \nand voltage or stability issues”; and (4) “[f]luctuations from large loads during faults or switching \ncan cause issues with voltage support, frequency response, stability, and protection system \ncoordination.”30  \nIn other words, behind-the-meter loads “can pose reliability risks if their generation \nunexpectedly trips off-line and appropriate protection or ride-through systems are not in place \n[because] [t]he operational visibility and controllability of [behind-the-meter] loads are limited, \nmaking it more challenging to predict system impacts, especially during uncontrolled transitions \nbetween on-site generation and grid supply that may arise due to protection system failures.”31  “If \nthe load unexpectedly shifts to expecting grid supply after the co-located generation fails, the \nutility supply sees a rapid demand spike, which may stress the transmission system.”32 \nIncreased demand without appropriate planning due to hidden load will result in \ntransmission and generation constraints.  Large loads that are not visible as part of the PJM \nplanning process can very well deplete transmission and generation capacity in times of increased \ndemand.  The effect will be increased costs and decreased quality of service for other customers.  \nThe way to mitigate this is by maintaining the requirement for these large co-located loads to be \nsubject to Network Service and the costs that should attend that service. \n \n30  NERC Comments at 7 (Apr. 23, 2025). \n31  NERC, Characteristics and Risks of Emerging Large Loads: Large Loads Task Force White Paper, at 13 (July \n2025), https://www.nerc.com/globalassets/who-we-are/standing-committees/rstc/whitepaper-characteristics-\nand-risks-of-emerging-large-loads.pdf. \n32  Id."},{"page":11,"startToken":3411,"endToken":3772,"text":"11 \n \nD. Nothing Has Changed: The Standard Under Federal Power Act Section \n206 Has Not Been Met. \nAs a legal matter, nothing has changed since the commencement of this proceeding.  As \ndiscussed in the prior submissions of the Indicated TOs, the existing forms of transmission service \nin PJM—Network Service and Point-to-Point Transmission Service (“PTP Service”)—continue to \nbe just and reasonable methods of providing transmission service to loads in PJM, including loads \nco-located with generation facilities.   \nConstellation continues to ignore a fundamental part of FPA section 206:33 only after a \nsuccessful showing that the existing rate is unjust and unreasonable can the Commission order a \nreplacement rate.34  No such showing has been made.  The PJM Tariff remains just and reasonable, \nand nothing in the record of this proceeding proves otherwise.  “The burden of proving an unjust \nor unreasonable rate rests with the party that initiated the proceeding—that is, the Commission or \nthe third-party complainant.”35  Neither the Commission nor any of the parties supporting the \ninitiation of this FPA section 206 proceeding have demonstrated that the existing PJM Tariff forms \nof transmission service are unjust and unreasonable.  The indisputable fact is that there is a path \nunder the existing PJM Tariff for all customers to get service in a timely fashion at reasonable, \nnon-preferential rates.  \nThe two options for transmission service under the PJM Tariff—Network Service and PTP \nService—allow for recovery of the embedded costs of the PJM grid.36  Constellation seeks to \n \n33  16 U.S.C. § 824e(a). \n34  Id.  See also N.J. Bd. of Pub. Utils. v. FERC, 744 F.3d 74, 94–95 (3d Cir. 2014) (“[U]nder § 206, FERC may \nchange a rate in response to a complaint or on its own motion, only if the moving party demonstrates that the \nexisting rate is unjust and unreasonable and the proposed alternative is just and reasonable.”). \n35  Pub. Citizen, Inc. v. FERC, 7 F.4th 1177, 1183 (D.C. Cir. 2021). \n36  See, e.g., Pennsylvania-New Jersey-Maryland Interconnection, 81 FERC ¶ 61,257 (1997) (adopting PJM pricing \nproposal to allow recovery of embedded transmission revenue requirement from network customers), corrected \n(cont'd)"},{"page":12,"startToken":3772,"endToken":4199,"text":"12 \n \nexempt large co-located loads from these costs, granting undue preference at the expense of other \ncustomers, contrary to the FPA’s mandate that all rates be just and reasonable and free from undue \ndiscrimination.37 \nCo-located loads rely on the transmission system for essential services and impose \nreliability challenges.  As the Indicated TOs have previously explained,38 the “assessment of \n[Network Integration Transmission Service] is not based on actual use over a particular \ntransmission path, but rather based on the network customer’s right to use the entire system”39 and \nits effects on that system.  Preferential treatment cannot be justified under the guise of national \nsecurity, as similar critical facilities that contribute to our national security already pay under the \nexisting PJM Tariff.  The real issue here is cost allocation and the attempt by some to shift to other \ncustomers the embedded costs of the transmission system. \nThe outcome in Docket Nos. ER24-2172-000 and ER24-2172-001 (“Susquehanna ISA \nProceeding”) illustrates this point.40  The proposal in that case was to avoid Network Service \n \nby 82 FERC ¶ 61,103 (1998), and clarified in part by 92 FERC ¶ 61,282 (2000), and review granted in part, \nvacated in part by 295 F.3d 1 (D.C. Cir. 2002); PJM OATT, Section 34.1 (providing for payment by network \ncustomers of load ratio share of embedded cost of their zone); PJM OATT Attachments H-1, H-1A, H-2, H-2A, \nH-3, H-3D, H-7, H-7A, H-9, H-9A, H-13, and H-13A (establishing network revenue requirements for each of the \nExelon Utilities based on the embedded costs of their respective transmission systems). \n37  16 U.S.C. § 824d(a) (“All rates and charges made, demanded, or received by any public utility for or in connection \nwith the transmission or sale of electric energy” must “be just and reasonable.”); id. § 824d(b) (“No public utility \nshall, with respect to any transmission or sale subject to the jurisdiction of the Commission, (1) make or grant any \nundue preference or advantage to any person or subject any person to any undue prejudice or disadvantage, or (2) \nmaintain any unreasonable difference in rates, charges, service, facilities, or in any other respect, either as between \nlocalities or as between classes of service.”). \n38  See Answer of Indicated TOs at 6, 23 (June 3, 2025) (quoting Nat’l R.R. Passenger Corp. v. PPL Elec. Utils. \nCorp., 173 FERC ¶ 61,043, at PP 13–14 (2020)). \n39  Nat’l R.R. Passenger Corp., 173 FERC ¶ 61,043 at P 14. \n40  See PJM Interconnection, L.L.C., 189 FERC ¶ 61,078 (2024) (“Susquehanna ISA Order”)."},{"page":13,"startToken":4199,"endToken":4556,"text":"13 \n \nthrough a behind-the-meter arrangement.41  That proposal sought essentially what Constellation \nseeks here, an exemption from responsibility for embedded costs.  The Commission rejected the \nproposal in the Susquehanna ISA Proceeding.42  What happened next is most instructive: the data \ncenter development continued anyway, and it did so under the existing Network Service option \navailable under the PJM Tariff.43  Which is to say that nothing about the arrangement or the current \nPJM Tariff required the behind-the-meter form of service.  Constellation’s claim that the PJM Tariff \nis unjust and unreasonable is misplaced; no basis exists for creating a new service or replacement \nrate.44 \nNo matter how quickly any party prefers action in this proceeding, the Commission cannot \norder any replacement rates merely to accommodate the type of service some customers would \nprefer.  Again, FPA section 206 only permits action when the existing rate is unjust and \nunreasonable—which has not been shown.  Additionally, as the Indicated TOs have previously \nexplained,45 Commission action to attempt to set a replacement rate that would accommodate a \nnarrow category of customers, such as co-located load, would conflict with the major questions \n \n41  See PJM Interconnection, L.L.C., Docket No. ER24-2172-000, Application Attach. A, Amended ISA, at Schedule \nF, Part F.4 (June 1, 2024). \n42  Susquehanna ISA Order, 189 FERC ¶ 61,078. \n43  See Press Release, Talen Energy, Talen Energy Expands Nuclear Energy Relationship with Amazon (June 11, \n2025), \nhttps://ir.talenenergy.com/news-releases/news-release-details/talen-energy-expands-nuclear-energy-\nrelationship-amazon (“The existing Susquehanna co-located load arrangement between Talen and Amazon will \ntransition to a ‘front-of-the-meter’ arrangement after the completion of transmission reconfigurations expected in \nthe Spring of 2026, concurrent with Susquehanna’s refueling outage.”). \n44  Constellation’s range of concerns at times go beyond the issue of the types of transmission service provided by \nPJM and instead relate to operation and timing of the interconnection queue and study process.  Undoubtedly, \nthere continues to be room for reform of the interconnection queue, but that is not a reason to revise transmission \nservices and charges that have proven to work for all customers. \n45  See Answer of Indicated TOs at 14–15 (June 3, 2025)."},{"page":14,"startToken":4556,"endToken":4901,"text":"14 \n \ndoctrine46 and the declaration in the FPA that rates that provide an undue preference or advantage \nare unlawful.47  Congress could have given FERC authority to require preferred transmission \nservice to benefit certain wholesale (or retail) customers, but it did not do so. \nIII. \nConclusion \nThere are important issues to consider such as possible reforms to the interconnection \nqueue process to minimize unjustified delays.  That is where the problem is—not with the type of \ntransmission services offered.  Constellation wants to avoid paying for Network Service and asks \nfor quick action to establish a new form of service in PJM to accommodate its desires while the \nCommission simultaneously considers related national policy direction and solutions.  There is no \nbasis for that and the standard under FPA section 206 has not been met to require such a change \nto the PJM Tariff.  For the reasons stated above, FERC should reject Constellation’s Motion.  \nShould FERC decide to act in this proceeding prior to resolution of the ANOPR proceeding, the \ncomplaint and show cause proceedings should be terminated, and FERC should find that the PJM \nTariff remains just and reasonable. \n \n \n \n \n \n46  See West Virginia v. EPA, 597 U.S. 697, 723 (2022) (“Agencies have only those powers given to them by \nCongress, and ‘enabling legislation’ is generally not an ‘open book to which the agency [may] add pages and \nchange the plot line.’” (alteration in original (citation omitted))); see also Midship Pipeline Co., L.L.C. v. FERC, \n45 F.4th 867, 877 (5th Cir. 2022) (vacating part of the Commission’s order and remanding the remainder because \n“[t]he FERC’s interpretation of the NGA to give the agency power to determine ‘the reasonable cost’ of \nremediation efforts ‘change[d] the plot line’ of its enabling legislation, and was therefore erroneous” and “[t]he \nFERC lacks such  authority under the NGA, and it likewise lacked authority to order an ALJ to make such a \ndetermination indirectly” (second alteration in original (quoting West Virginia v. EPA, 597 U.S. at 723))). \n47  See 16 U.S.C. § 824d(b)."},{"page":15,"startToken":4901,"endToken":5109,"text":"15 \n \n \n \n \n \n \n       Respectfully submitted, \n \n/s/ William Sauer \nWilliam Sauer \nVice President, Federal Regulatory Affairs  \nExelon Corporation  \n701 Ninth St. N.W.  \nWashington, DC 20001  \nTelephone: 202-868-7499  \nEmail: william.sauer@exeloncorp.com   \n/s/ Max Minzner \n \nMax Minzner \nSenior Vice President & Deputy General \nCounsel - Corporate \nExelon Corporation \n701 Ninth St. N.W.  \nWashington, DC 20001  \nTelephone: 202-934-4740 \nEmail: max.minzner@exeloncorp.com \n \n \nOn behalf of Exelon Corporation \n \n/s/ Lisa G. McAlister \nLisa G. McAlister \nAMP Transmission, LLC \n1111 Schrock Road, Suite 100 \nColumbus, Ohio 43229 \nTelephone: 614-540-6400 \nEmail: lmcalister@amppartners.org \n \n/s/ Adrienne E. Clair \nAdrienne E. Clair \nThompson Coburn LLP \n1909 K Street, N.W., Suite 600 \nWashington, D.C.  20006-1167 \nTelephone: 202-585-6900 \nEmail: aclair@thompsoncoburn.com \n \nOn behalf of AMP Transmission, LLC \n \n \nOn behalf of Old Dominion Electric \nCooperative \n/s/ Martin J. Keane \nMartin J. Keane \nDirector of Public Utilities \nCleveland Public Power \n1300 Lakeside Ave. \nCleveland, OH 44114 \nTelephone: 216-664-2444 ext. 75604 \nEmail: martin_keane@clevelandwater.com \n \n/s/Debra D. Roby \nDebra D. Roby \nWashington Energy Law LLP \n900 17th Street N.W., Suite 500-A \nWashington, D.C. 20006 \nTelephone: 703-785-9270 \nEmail: droby@washingtonenergylaw.com \n \nOn behalf of City of Cleveland, Department of \nPublic Utilities, Division of Cleveland Public \nPower \n \nOn behalf of the City of Hamilton, OH"},{"page":16,"startToken":5109,"endToken":5313,"text":"16 \n \n/s/ Michael Brechlin \nMichael Brechlin \nPA Bar # 335424 \nDuquesne Light Company \n411 7th Ave \nPittsburgh, PA 15219 \nTelephone: 412-393-6431 \nEmail: mbrechlin@duqlight.com \n/s/ Amanda P. Parker \nAmanda P. Parker \nAttorney \nFirstEnergy Service Company \n76 South Main Street \nAkron, OH 44308 \nTelephone: (330) 384-4592 \nEmail: aparker@firstenergycorp.com  \n \nOn behalf of Duquesne Light Company \nOn behalf of The FirstEnergy Transmission \nCompanies \n \n/s/ Denise R. Foster Cronin \nDenise R. Foster Cronin \nVice President, Federal and RTO Regulatory \nAffairs \nEast Kentucky Power Cooperative, Inc. \n4775 Lexington Road, P.O. Box 707 \nWinchester, KY 40392-0707 \nTelephone: 859-745-9615 \nEmail: denise.cronin@ekpc.coop \n \n/s/ Daniel E. Frank                  \nDaniel E. Frank \nKelly Cuthbertson \nEversheds Sutherland (US) LLP \n700 Sixth St., N.W., Suite 700 \nWashington, DC 20001-3980 \nTelephone: 202-383-0100 \nEmail:  \ndanielfrank@eversheds-sutherland.com \nkellycuthbertson@eversheds-sutherland.com \n \n \n \nOn Behalf of East Kentucky Power \nCooperative, Inc. \n \n/s/ Steve Nadel \nSteven M. Nadel \nSenior Counsel \nPPL Services Corp.  \n645 Hamilton Street, Suite 601 \nAllentown, PA 18101 \nTelephone: 610-774-4775   \nEmail: SMNadel@pplweb.com \n \n/s/ Jeremy L. Fetty \n \nJeremy L. Fetty \nParr Richey \n251 N. Illinois, Suite 1800 \nIndianapolis, Indiana 46204  \nTelephone: 317-269-2500 \nEmail: j_fetty@wvpa.com \n \n \nOn behalf of PPL Electric Utilities Corp. \n \nOn behalf of Wabash Valley Power \nAssociation, Inc."},{"page":17,"startToken":5313,"endToken":5459,"text":"17 \n \n/s/ Damon L. Krieger \nDamon L. Krieger \nGroup Vice President, Legal, Strategy, and \nSustainability, and Deputy General Counsel \nSouthern Maryland Electric Cooperative, Inc. \n15035 Burnt Store Road \nP.O. Box 1937 \nHughesville, Maryland 20637-1937 \nTelephone: 301-274-4323 \nEmail: Damon.Krieger@SMECO.coop \n \n/s/Joshua Kirstein \nJoshua A. Kirstein  \nSenior Attorney  \nLaw Department \nConsolidated Edison Company of New York, \nInc.  \n4 Irving Place, 18th Floor  \nNew York, NY 10003  \nTelephone: 929-656-5971 \nEmail: kirsteinj@coned.com \n \nOn behalf of Southern Maryland Electric \nCooperative \n \nOn behalf of Rockland Electric Company \n \n/s/ Lindsay Berkstresser \nLindsay Berkstresser \nCounsel – Energy & Regulatory \nUGI Corporation \n500 North Gulph Road \nKing of Prussia, PA 19406 \nTelephone: 717-504-9925 \nEmail: berkstresserl@ugicorp.com \n \n/s/ Richard P. Bonnifield \nRichard P. Bonnifield \nHusch Blackwell \n1801 Pennsylvania Avenue, NW, \nSuite 1000 \nWashington, DC 20006-3606 \nTelephone: 202-243-8844 \nEmail: \nrichard.bonnifield@huschblackwell.com \n \n \n \nOn behalf of UGI Utilities Inc. \n \n \n \n \n \n \nDecember 8, 2025"},{"page":18,"startToken":5459,"endToken":5518,"text":"CERTIFICATE OF SERVICE \n \nI hereby certify that I have this day served the foregoing document upon each person \ndesignated on the official service list in the above captioned dockets. \nDated this 8th day of December, 2025. \n \n/s/Alejandro Bautista \nAlejandro Bautista \nAssistant General Counsel \nExelon Corporation \n2301 Market Street  \nPhiladelphia, PA 19101 \nTelephone: 267-533-0120 \nEmail: Alejandro.Bautista@exeloncorp.com"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":2,"endAt":627,"startToken":0,"endToken":442},{"p":2,"at":627,"title":"I. BACKGROUND","method":"printed heading","endPage":3,"endAt":444,"startToken":442,"endToken":753},{"p":3,"at":444,"title":"II. ANSWER","method":"printed heading","endPage":3,"endAt":457,"startToken":753,"endToken":755},{"p":3,"at":457,"title":"A. Constellation’s Desire for a PJM-Specific Outcome Is Inappropriate","method":"printed heading","endPage":5,"endAt":5,"startToken":755,"endToken":1390},{"p":5,"at":5,"title":"B. Constellation Would Have the Commission Improperly and Prematurely","method":"printed heading","endPage":7,"endAt":1006,"startToken":1390,"endToken":2188},{"p":7,"at":1006,"title":"C. Constellation’s Preferred Outcome Raises Significant Affordability and","method":"printed heading","endPage":11,"endAt":6,"startToken":2188,"endToken":3412},{"p":11,"at":6,"title":"D. Nothing Has Changed: The Standard Under Federal Power Act Section","method":"printed heading","endPage":14,"endAt":282,"startToken":3412,"endToken":4600},{"p":14,"at":282,"title":"III. Conclusion","method":"printed heading","endPage":18,"endAt":0,"startToken":4600,"endToken":5459},{"p":18,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":18,"endAt":426,"startToken":5459,"endToken":5518}]}