{"document":{"slug":"rec-20260120-5256","title":"Answer of Constellation Energy Generation, LLC in Opposition to the Indicated PJM Transmission Owners' Motion for Extension of Time","issued":"2026-01-20","accession":"20260120-5256","docket":"EL25-49-000","group":"PJM co-location compliance","filer":"Constellation Energy Generation, LLC","kind":"answer","file":"sources/filings/text/20260120-5256_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260120-5256","tier":"record","sha256":"eaf5d820073b5b878f2c5c0b0b16433fa649efcfd4f60f0cb39b9336ba9edd0a","pages":5,"tokens":1301,"emptyPages":[],"textThemes":["colo"]},"pages":[{"page":1,"startToken":0,"endToken":308,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \nPJM Interconnection, L.L.C., et al. \n \n \nLarge Loads Co-Located at Generating Facilities \n \n \nConstellation Energy Generation, LLC \n \n     v. \n \nPJM Interconnection, L.L.C. \n) \n \n \n)  \n \n \n)  \n) \n) \n) \n) \nDocket No. EL25-49-000 \n \n \nDocket No. AD24-11-000 \n \n \n \n \nDocket No. EL25-20-000 \n    (Consolidated) \n \nANSWER OF CONSTELLATION ENERGY GENERATION, LLC \nIN OPPOSITION TO THE INDICATED PJM TRANSMISSION OWNERS’ \nMOTION FOR EXTENSION OF TIME \nConstellation respectfully opposes1 the Indicated Transmission Owners’ motion to delay \ncompliance2 with the Commission’s order establishing rules to promptly interconnect large loads \nin the PJM region.3 The TOs seek a thirty (30) day extension of time for submission of \n(i) compliance filings due 60 days from the date of the order; and (ii) initial and reply briefs in the \npaper hearing that the Commission established in the December Order.4 The Commission should \ndeny the TO’s Motion for three reasons.   \n \n1 Constellation Energy Generation, LLC (“Constellation”) files this answer pursuant to Rule 213 of the Commission’s \nRules of Practice and Procedure. See 18 C.F.R. § 385.213. \n2 Motion for Extension of Time, Shortened Answer Period, and Request for Expedited Action of the Indicated PJM \nTransmission Owners in the above-captioned proceedings (filed January 14, 2026) (the “TO’s Motion”). \n3 Per PJM Interconnection. L.L.C., 193 FERC ¶ 61,217, at Ordering Clause (C) (2025) (“December Order”) the \napplicable tariff revisions are due 60 days from the December Order, or February 16, 2026.  \n4 TO’s Motion at n. 12: “currently initial briefs are due on or before February 16, 2026 with responses to initial briefs \ndue March 18, 2026, and the replies to those responses due April 17, 2026. Under the 30-day extension, initial briefs \nwould be due on March 18, 2026, responses to initial briefs would be due on April 17, 2026, and the replies to those \nresponses would be due May 18, 2026.”"},{"page":2,"startToken":308,"endToken":691,"text":"2 \nFirst, the Commission’s 60-day deadline was appropriate in the circumstances given the \nnational imperative to facilitate the prompt interconnection of large loads and the long delays in \ndoing so in PJM. The Commission’s timeline is consistent with the Secretary of Energy’s proposed \nANOPR and the Secretary’s statement that the interconnection of large loads to the transmission \nsystem—the subject of both the ANOPR and this show cause proceeding—“is an urgent issue that \nrequires prompt attention.”5 The Commission’s compliance deadlines require timely action to \nbreak the logjam on serving these critical large loads. \nSecond, the TO’s interest in delaying compliance is troubling in light of positions \nCommonwealth Edison Company (“ComEd”)6 has taken in Illinois where ComEd asserts that its \nrates need not reflect the new Commission-mandated transmission services because these are not \nyet final and unappealable.7 ComEd’s approach would simply ignore the current circumstance, \nwhich is that the Commission has found the existing rate structure where there is only a single, \ngross wholesale transmission rate to be unjust and unreasonable and directed replacement rates. \nAmong other things, the replacement rates include a new class of interruptible or non-firm \nwholesale transmission service which, in turn, could reduce collateral and deposit requirements to \ntake service from ComEd. The TOs’ attempts to delay compliance in the Commission’s docket \n \n5 On October 23, 2025, the Secretary of Energy proposed an ANOPR under section 403 of the Department of Energy \nOrganization Act, 42 U.S.C. § 7173(a).  U.S. Department of Energy, Secretary of Energy, Letter to FERC re: \n“Ensuring the Timely and Orderly Interconnection of Large Loads,” Advance Notice of Proposed Rulemaking (Oct. \n23, 2025) (issued pursuant to Department of Energy Organization Act § 403, 42 U.S.C. § 7173) (cover letter, \n“Secretary’s Letter,” and Advanced Notice of Proposed Rulemaking, “ANOPR”); see Secretary’s Letter at 1. \n6 ComEd’s parent, Exelon, joined the TO’s Motion. \n7 ComEd Response to the Constellation’s Motion To Reopen The Evidentiary Record in IL ICC Docket Nos. 25-0677 \nand 25-0679, p. 6 (Jan. 8, 2026) (“[t]he proposed retail tariff ensures that large load customers contribute revenue in \naccordance with their load requests … regardless of any changes FERC might or might not make to the design of \ntransmission rates applicable to any particular transmission customer.”) (“ComEd January 8 Response”)."},{"page":3,"startToken":691,"endToken":1095,"text":"3 \nthus are consistent with their efforts to avoid updating their rate structures until there is a final \nCommission order. Such delays are contrary to the December Order8 and the Federal Power Act.9   \nFinally, prompt compliance in this proceeding in PJM is also critical because the record \nreflects that Transmission Owners have long benefited by delaying existing large load co-location \nrequests unless customers agree in advance to take both transmission and distribution service from \nthem.10 The TO’s Motion now seeks further delay.   \nFor all the above reasons, Constellation opposes the TO’s Motion. The Commission should \ndeny the motion and continue with the deadlines as established in the December Order.   \n \n \n8 See News Release, FERC Directs Nation’s Largest Grid Operator to Create New Rules to Embrace Innovation and \nProtect Consumers, (Dec. 18, 2025) available at https://www.ferc.gov/news-events/news/ferc-directs-nations-\nlargest-grid-operator-create-new-rules-embrace-innovation-and (“As technology leaps forward, clear and fair \nregulations must keep pace to support advancement, help prevent price volatility, and promote competition, \nultimately benefiting consumers by keeping electricity costs manageable.”); see also  December Order, \nCommissioner Rosner Concurring (“a business-as-usual approach to load growth—planning for generation and load \nseparately—will not suffice to timely meet growing demand while also keeping prices reasonable. Today’s order \nhelps break the logjam.”). \n9 See 16 U.S.C. § 825l(c) (providing that the filing of an application for rehearing shall not, unless specifically ordered \nby the Commission, operate as a stay of the Commission’s order). In ComEd’s January 8 Response, ComEd alleges \nthat until the Commission issues an order on compliance, “no actionable framework is in effect.” ComEd January 8 \nResponse at p.6. ComEd is incorrect. Unless and until the December Order is set aside, it is a final order that binds \nPJM, the TOs, and other market participants unless and until the Commission or a court of appeals determines \notherwise.    \n10 See Constellation Complaint at 6-9 (citing Protest of Constellation Energy Generation, LLC, Docket No. EL24-\n149-000, Exh. 2 (correspondence with Exelon) (filed Oct. 30, 2024); Motion to Lodge of Constellation Energy \nGeneration, LLC, Docket No. EL24-149-000, Exh. 1 (November 12, 2024 Exelon Letter) (filed Nov. 18, 2024)); \nsee also Constellation Complaint, Exh. 5, Declaration of James R. McCoskey (detailing interaction with Exelon to \nstudy co-location projects); see also Atl. City Elec. Co., 190 FERC ¶ 61,109 (2025) (rejecting Exelon Transmission \nOwners’ attempt to force all co-located load to take full transmission service)."},{"page":4,"startToken":1095,"endToken":1221,"text":"4 \n \n \n \n \n \n \n \n    Respectfully submitted, \n \n \n \n \n \n \n \n    /s/ Paul F. Wight \n \n \nJanuary 20, 2026 \n \n \nCarrie Hill Allen \nSr. Vice President & Deputy General Counsel \nSeth Lucia \nAssistant General Counsel \nConstellation Energy Generation, LLC \n250 Massachusetts Ave. NW, Suite 760 \nWashington, D.C. 20001 \ncarrie.allen@constellation.com \nseth.lucia@constellation.com \n  \nChristopher A. Wilson \nManaging Director, Federal Regulatory Affairs \nConstellation Energy Generation, LLC \n250 Massachusetts Ave. NW, Suite 760 \nWashington, D.C. 20001 \n202-347-7500 \nFERCe-filings1@constellation.com \n \nPaul F. Wight \nCarolyn E. Clarkin \nDLA Piper LLP (US) \n500 Eighth Street NW \nWashington, D.C. 20004 \n703-773-4058 \npaul.wight@us.dlapiper.com \ncarolyn.clarkin@us.dlapiper.com \n \nSophia Browning \nDLA Piper LLP (US) \n4365 Executive Drive \nSan Diego, CA 92121 \n858-677-1455 \nsophia.browning@us.dlapiper.com   \n \nCounsel for Constellation Energy \nGeneration, LLC"},{"page":5,"startToken":1221,"endToken":1301,"text":"5 \n \nCERTIFICATE OF SERVICE \nI hereby certify that I have on this 20th day of January 2026, caused to be served a copy of \nthe foregoing upon all parties on the service lists in these proceedings in accordance with the \nrequirement of Rule 2010 of the Commission’s Rules of Practice and Procedure, 18 C.F.R. \n§ 385.2010. \n/s/ Sophia Browning \nSophia Browning \nDLA Piper LLP (US) \n4365 Executive Drive \nSan Diego, CA 92121 \n858-677-1455 \nsophia.browning@us.dlapiper.com"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":5,"endAt":5,"startToken":0,"endToken":1222},{"p":5,"at":5,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":5,"endAt":468,"startToken":1222,"endToken":1301}]}