{"document":{"slug":"rec-20260120-5280","title":"PJM Industrial Customer Coalition et al. submit Request for Clarification or, in the Alternative, Rehearing of the 12/18/2025 Order","issued":"2026-01-20","accession":"20260120-5280","docket":"EL25-49-002","group":"PJM co-location compliance","filer":"PJM Industrial Customer Coalition and Industrial Energy Cons","kind":"rehearing request","file":"sources/filings/text/20260120-5280_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260120-5280","tier":"record","sha256":"e1ff2cc4aacabdbb8f2a7f503632ca7f3d6e4a8d85f5d6160893b1acbc8c912d","pages":46,"tokens":14975,"emptyPages":[],"textThemes":["colo","adequacy","flex","retail"]},"pages":[{"page":1,"startToken":0,"endToken":203,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \n \nPJM Interconnection, L.L.C., et al.  \n \n \nLarge Loads Co-Located at Generating \nFacilities \n \nConstellation Energy, LLC \n        v.  \nPJM Interconnection, L.L.C.\n \n) \n) \n) \n) \n) \n) \n) \n) \n) \n)\n \n \nDocket Nos. EL25-49-000 \n                     EL25-49-001 \n \n \nAD24-11-000 \n \n \nEL25-20-000 \n(Consolidated)\n \nREQUEST FOR CLARIFICATION OR, IN THE ALTERNATIVE, REHEARING  \nOF THE INDUSTRIAL CUSTOMER COALITIONS \n \nPursuant to Rule 713 of the Federal Energy Regulatory Commission’s (“Commission” or \n“FERC”) Rules of Practice and Procedure,1 the PJM Industrial Customer Coalition (“PJMICC”) \nand the Industrial Energy Consumers of America (“IECA”) (collectively, “Industrials” or \n“Industrial Customer Coalitions”) respectfully request clarification or, in the alternative, rehearing \nof portions of the Commission’s December 18, 2025 Order  (“Co-Located Load Order” or “Order”) \nin the above referenced proceeding.2 \nI. \nINTRODUCTION \nThe Co-Located Load Order provides PJM Interconnection, L.L.C. (“PJM”) with sweeping \nguidance to address customer electrical configurations involving both generation and load behind \na retail customer’s meter. The Order lays some groundwork for additional flexibility, clarity, and \nchoice for consumers, and the Industrials welcome positive movement on these fronts. Yet, \nwithout key clarifications or modifications, the Order threatens to create dramatic, unwanted \n \n1 See 18 C.F.R. § 385.713. \n2 193 FERC ¶ 61,217 (Order entered Dec. 18, 2025)."},{"page":2,"startToken":203,"endToken":462,"text":"2 \n \n \nconsequences to the large industrial customer base that has invested in on-site generation in the \nPJM region for decades to control their energy costs and advance their own reliability needs.  \nWhile technical and nuanced, these questions are not minor—not for manufacturers and other \ntraditional large users, not for the economy, and not for the grid, upon which all stakeholders \ndepend. \nThe Industrials respectfully deliver a critical message from the industrial backbone of the \nAmerican economy: without key clarifications, the Order threatens to weaken some of the \nlargest manufacturers in the PJM region, render hundreds of megawatts – if not more -- of \nexisting retail behind-the-meter generation uneconomic, stall new projects, and further \nstress the resource adequacy of the electric grid at an inopportune time. These are concrete, \nmeasurable harms to both American industry and the PJM grid. Therefore, the Industrials \nrespectfully urge the Commission to grant all of the requested clarifications herein to avoid these \ndevastating results. Further, because these critical issues remain unclarified in the Order currently, \nand because an inadequate record was developed on the impact of the retail behind-the-meter \ngeneration (“BTMG”) rule changes and the shift to a “gross load” approach for transmission cost \nresponsibility, the Industrials also respectfully submit the Request for Rehearing herein in the \nevent that the Commission does not grant all of the requested clarifications herein. \nII. \nTHE CRITICAL ISSUE: EXECUTIVE SUMMARY \nThe Industrial Customer Coalitions include associations of leading manufacturing \ncompanies, trade-exposed electricity users, institutional users, and other energy-intensive \ncustomers representing well over $1 trillion in sales, including thousands of manufacturing"},{"page":3,"startToken":462,"endToken":808,"text":"3 \n \n \nfacilities and millions of family-sustaining jobs in the United States.3 The predominant represented \ncustomers in the Industrial Customer Coalitions are American manufacturers, spanning industries \nas diverse as chemicals, plastics, steel, iron ore, aluminum, paper, food processing, fertilizer, \ninsulation, glass, industrial gases, pharmaceuticals, building products, automotive, independent oil \nrefining, cement, and more.4 Many of the members of both coalitions have facilities throughout \nthe PJM Region.  \nMany of these traditional industrial users have been investing in and building the PJM grid \nfor decades. These organizations are energy-intensive, price-sensitive, frequently operate 24/7, and \ncompete globally. For many manufacturers, energy can rank with raw materials and labor as a key \ncost driver. Many customers represented by the Industrial Customer Coalitions have on-site \ngeneration to offset their load and support the thermal needs of their business and manufacturing \noperations, and thus, many of these businesses will be directly impacted by the sweeping changes \nof the Order. These manufacturers and businesses are already facing significant headwinds, \nincluding labor shortages and rising electricity costs. \nUnlike traditional industrial manufacturing loads, which typically evolve through \ndeliberate, methodical planning, a substantial portion of today’s large loads pursue highly \naccelerated interconnection timelines and unprecedented size and scale. These “super-sized” loads \nare driving demand for new generation and transmission infrastructure with an urgency that is \nreshaping the landscape of power system planning and investment and risks short-circuiting the \n \n3 Manufacturing employs over 15 million people in the United States3 and contributed $2.3 trillion to U.S. Gross \nDomestic Product (“GDP”) in 2023 (amounting to 10.2 % of total U.S. GDP, measured in chained 2017 dollars). See \nU.S. Bureau of Labor Statistics (2024 data), https://www.bls.gov/cps/cpsaat18.htm (last accessed Jan. 16, 2026). See \nU.S. Manufacturing Economy, NIST, https://www.nist.gov/el/applied-economics-\noffice/manufacturing/manufacturing-economy/total-us-manufacturing (last accessed Jan. 16, 2026). \n4 The Industrials also represent other institutional and service customers, such as schools, data centers, and hospitals, \nsome of which also operate retail BTMG and, as such, will suffer the same economic consequences described \nherein."},{"page":4,"startToken":808,"endToken":1099,"text":"4 \n \n \ntraditional manufacturing sector’s ability to expand and grow as a key anchor in the nation’s \neconomy. \nIn light of this rapid growth, the Industrials support the Commission’s goal of adding clarity \nand choice to the operation of the transmission system. The Industrials also welcome faster \nenergization for generation and new loads, and improved flexibility for connecting loads. \nHowever, without key clarifications, the Order threatens to add significant expense to long-term \nretail behind-the-meter investments or to render them economically unviable for the retail \ncustomers who own and operate them.  \nThe Industrials’ central concern revolves around sweeping changes to the retail BTMG \nrules, including the removal of “netting” for on-site generation. In particular, the removal of retail \nBTMG rules above a certain, yet-undetermined threshold will dramatically increase costs for many \nbusinesses with BTMG. It will also discourage future investments in generation at the exact time \nthe energy community is seeking resource adequacy. For over 20 years, industrial customers have \nrelied on PJM’s retail BTMG rules, making major investments in on-site generation with the \nunderstanding that key billing determinants would be based on netted (that is, actual) use of the \nsystem. Simply affording existing retail BTMG a three-year transition period or grandfathering \nexisting contractual arrangements and then eliminating the netting approach will not resolve the \nunderlying concern for multi-decade capital investments.  \nGiven the limited record on retail customers’ use of BTMG, the Commission may not be \nfully aware of the damaging effects on industrial customers of abandoning the long-held netting \napproach. Removal of retail BTMG rules is a dramatic change of direction—for some industrial \ncustomers, transmission and capacity cost savings are a critical factor that makes it worth the \ninvestment to build and operate generation on their premises. Absent a reasonable alternative,"},{"page":5,"startToken":1099,"endToken":1410,"text":"5 \n \n \napplying a “gross load” measurement to retail BTMG for Network Integration Transmission \nService (“NITS”) and, subject to the clarification requested herein, capacity could seriously \ndamage existing users’ economic viability by requiring transmission and capacity payments that \nignore power flow and demands at the meter during peak hours.  \nSuch an approach implicates not only the economic viability of on-site generation but also \nfoundational cost-causation principles. Because there is currently a significant financial incentive \nfor on-site generation to operate consistently at key hours, retail BTMG owners design, plan, and \noperate their systems accordingly to avoid straining the grid. This has significant benefits for the \ngrid, making it extremely rare for retail BTMG units to be down during peak hours. However, the \nOrder does not take into consideration the performance of such generating units, many of which \nare cogeneration Qualifying Facilities (“QFs”) under the Public Utility Regulatory Policies Act of \n1978 (“PURPA”).5 BTMG operators, including cogeneration QFs, have every incentive to \nmaximize generation output during key hours. Removal of the “netting” measurement for NITS \nand other key billing determinants creates a void of incentives and cost management for energy-\nintensive businesses. While the Order provides for new transmission service offerings that meet \ncertain needs, including Firm Contract Demand service and Non-Firm Contract Demand service, \nthese services do not necessarily account for back-up and maintenance power. Thus, retail BTMG \ncustomers may lose their ability to manage costs even if they have a perfect record of generator \noperation at key times. Worse, retail BTMG customers may lose their ability to manage costs even \nif their load and generation are synchronized or if they never rely on transmission services. This \ncreates an enormous cost-causation gap, contrary to long-standing Commission precedent. \n \n5 Public Utility Regulatory Policies Act, Pub. L. 95–617, title II, § 210, Nov. 9, 1978, as amended (codified at 16 \nU.S.C § 824a-3)."},{"page":6,"startToken":1410,"endToken":1713,"text":"6 \n \n \nAs a result, removal of retail BTMG “netting” rules should not be implemented without \nensuring retail BTMG customers can access alternatives that enable them to manage capacity and \ntransmission costs in accordance with actual system use. This is particularly true for businesses \noperating cogeneration QFs, which have a right to be served with back-up and maintenance power \nunder regulations enacted to implement PURPA.6 \nWhile the Industrials recognize the importance of PJM planning for loads that may \nsuddenly come online, the PJM system has never been designed based on “potential load.” No \nreasonable system could be designed this way. Consequently, it would be unjust and \nunreasonable—not to mention unfair—to charge retail BTMG on a gross basis without either \n(1) accounting for the reliability of the generating unit; or (2) allowing the retail customer to choose \ntransmission and capacity options that fit with the retail BTMG configuration (e.g., back-up \npower). Put simply, generating units behind a customer’s meter have long been a part of creating \na stable power system and have incentivized generators to operate during key hours of grid \ncongestion. \nAn additional concern is that the Order is not clear whether the new transmission services \nPJM must create for Co-Located Load (“New Services”) must also be offered to load with minimal \nor no on-site generation. To best effectuate the Commission’s attempt to introduce choice, \nflexibility, and clarity into the transmission and capacity planning process in PJM, the Commission \nshould clarify that all load—including Co-Located Load, retail customers with BTMG, and retail \ncustomers without BTMG—must be provided access to the New Services. Such an approach \nreduces the risk of an unduly discriminatory result by providing similarly situated customers with \nidentical transmission and capacity service options; offers optionality and choice; promotes greater \n \n6 18 C.F.R. § 292.305."},{"page":7,"startToken":1713,"endToken":1992,"text":"7 \n \n \nuniformity, simplicity, and efficiency; and encourages greater competition and investment. This \napproach also has the potential to clarify and streamline the PJM Regional Transmission \nExpansion Planning (“RTEP”) process, thereby avoiding transmission system overbuilding and \nunjust and unreasonable cost shifts. \nIn sum, if the Commission proceeds to remove large users (above a yet-undetermined \nthreshold) from eligibility under the retail BTMG rules, the Industrials request the following \nclarifications: \n1. QFs under PURPA will be provided a stand-by rate and/or credited for capacity based \non the reliability of the generating unit.  \n \n2. New transmission services outlined in the Order will be made available to retail BTMG \ncustomers and load-only customers, not just Co-Located Load. \n \n3. Removal of the retail BTMG “netting” rules will be applicable to transmission services \nand specified ancillary services only, not capacity obligations. \n \n4. Any retail BTMG applicability threshold implemented by the Commission will be \nsufficiently high to permit traditional manufacturers and institutional customers to \ncontinue to net generation, consistent with actual use of the transmission system.   \n \nThe Industrials value stability and clarity in managing their energy costs, investments, and \nrelated issues. The Industrials seek a durable resolution of the issues raised in the above-captioned \nproceeding. The above clarifications would substantially mitigate concerns about the Order while \nmaintaining the positive momentum the Commission seeks by offering a suite of transmission \nservices tailored to different customer types.  \nIII. \nSTATEMENT OF ISSUES/ERRORS FOR ALTERNATIVE REHEARING \nREQUEST \nIf the Commission grants all of the above requested clarifications in full, then the \nCommission will have absolved the issues and errors raised in the Industrials’ request for \nrehearing. However, if the Commission does not grant the requested clarifications in full, the"},{"page":8,"startToken":1992,"endToken":2365,"text":"8 \n \n \nIndustrials seek rehearing with respect to the several violations of the Administrative Procedures \nAct, on the following issues: \n1. The Co-Located Load Order errs because the changes to retail BTMG rules in the Order \nare outside the scope of the Show Cause Order. \n2. The Co-Located Load Order errs because it does not reflect reasoned decision-making \nregarding retail BTMG because the Commission did not develop a sufficient record on \nwhich to base its retail BTMG decisions, resulting in conclusions that are arbitrary and \ncapricious.  \n3. The Co-Located Load Order indirectly effectuates an unlawful taking of private \nproperty without providing just compensation in violation of the Fifth Amendment. \n4. The Co-Located Load Order errs by failing to address its own prior precedent on cost-\ncausation or to demonstrate that the retail BTMG rules were unjust and unreasonable.  \n5. The Co-Located Load Order errs by failing to establish Commission jurisdiction over \ncustomer generation behind the meter that is not used in PJM’s energy or capacity \nmarkets, as defined in the PJM Tariff.  \n6. The Co-Located Load Order’s grandfathering provision and megawatt-based \napplicability threshold fail to correct the defects created in the Order. \nIV. \nPROCEDURAL HISTORY \nOn February 20, 2025, the Commission unanimously voted to launch a review of issues \nassociated with the co-location of large loads at generating facilities in PJM, including whether \nthe PJM tariff should establish rules to provide clarity while ensuring grid reliability. The February \n20, 2025, Order7 (“Show Cause Order”) instituted a show cause proceeding involving PJM and \nthe PJM Transmission Owners8 and combined the records of two pending proceedings due to the \ncommon issues associated with each docket.9 The Show Cause Order found that PJM’s tariff did \n \n7 Order Instituting Proceeding Under Section 206 of the Federal Power Act and Consolidating with Other \nProceedings, 190 FERC ¶ 61,115 (Order entered Feb. 20, 2025). \n8 The PJM Transmission Owners are a group of transmission owners who are named parties in the Show Cause Order. \n9 The Commission combined the FERC’s November 2024 technical conference on large load co-location (Docket \nNo. AD24-11) and a complaint filed on November 22, 2024, by Constellation Energy Generation, LLC, against PJM \n(Docket No. EL25-20) to form a consolidated proceeding, identified under Docket No. EL25-49."},{"page":9,"startToken":2365,"endToken":2635,"text":"9 \n \n \nnot appear to sufficiently address the rates, terms, and conditions of service that apply to co-\nlocation arrangements. The Commission directed PJM and the PJM Transmission Owners to \nexplain why the PJM Tariff remains just and reasonable or, alternatively, what changes to the PJM \nTariff would remedy the Commission’s identified concerns.10 The Commission also directed that \ninterested entities may respond within 30 days of PJM’s filing, addressing either or both of: \n(1) whether the Tariff remains just and reasonable and not unduly discriminatory or preferential; \nand (2) if not, what changes to the Tariff should be implemented as a replacement rate.11 On March \n24, 2025, Answers were filed by PJM and several other parties, including some PJM Transmission \nOwners. Many other parties filed responsive Answers, including the Industrials. \nOn December 18, 2025, the Commission issued the Co-Located Load Order, requiring PJM \nto implement changes to its tariff and initiating a paper hearing, among other instructions. The \nIndustrials respectfully submit this Request for Clarification or, in the Alternative, Rehearing in \nresponse to the Co-Located Load Order. \nV. \nREQUEST FOR CLARIFICATION \nThe Industrials respectfully request clarification regarding four issues: (1) the ability for \ncogeneration QFs and other customers with retail BTMG to have access to back-up power service \nor another reasonable alternative under the “gross load” calculation approach; (2) the applicability \nof the new transmission services PJM must implement under the Order; (3) the applicability of \n“netting” rule changes to capacity obligations; and (4) a minimum applicability threshold for \ninclusion in retail BTMG netting rules. \n \n10 Show Cause Order at P 65. \n11 Show Cause Order at P 87."},{"page":10,"startToken":2635,"endToken":2977,"text":"10 \n \n \nA. Issue #1. The Industrials seek clarification on whether cogeneration QFs under \nPURPA will be provided access to back-up and maintenance power at just and \nreasonable rates and/or be credited for capacity based on the reliability of their \ngenerating units.  \nPURPA is codified as Section 210 of the Federal Power Act (“Section 210”).12 Congress \nsets forth the policy behind PURPA in Section 210(a), explaining that the purpose of Commission \nrules implementing PURPA are to “encourage cogeneration and small power production, and to \nencourage geothermal small power production facilities of not more than 80 megawatts \ncapacity.”13 Under PURPA, electric utilities are required to offer QFs the opportunity to sell \nelectric energy and to purchase electric energy output from those QFs.  \nPURPA has been a boon to manufacturers and the electric grid for well over four decades, \nproviding market access where such access did not previously exist, taking strain off the grid, and \nsupporting American industry by allowing for economic means of reducing energy costs. Many \nQFs are highly efficient facilities, including cogeneration facilities, which produce both electricity \nand heat from the same fuel source, then making use of the “waste heat” in industrial operations. \nQFs are entitled to have access to supplementary power, back-up power, maintenance power, and \ninterruptible power, pursuant to enacting regulations.14 \nWhile PURPA permits many kinds of generation to qualify as QFs, many QFs come in the \nform of cogeneration facilities. Pursuant to PURPA, “the electrical, thermal, and chemical output” \nof a qualifying cogeneration facility must be “used fundamentally for industrial, commercial, or \ninstitutional purposes and is not intended fundamentally for sale to an electric utility.”15 As set \n \n12 16 U.S.C. § 824a-3.  \n13 16 U.S.C. § 824a-3(a) (emphasis added). PURPA requires electric utilities to offer to “(1) sell electric energy to \nqualifying cogeneration facilities and qualifying small power production facilities” and to offer to “(2) purchase \nelectric energy from such facilities.” Id. \n14 18 C.F.R. § 292.305. \n15 16 U.S.C. § 824a-3 (n)(1)(A)(ii)."},{"page":11,"startToken":2977,"endToken":3276,"text":"11 \n \n \nforth in greater detail in the Request for Rehearing below, these facilities are deeply integrated \nwith the operations of the adjacent plant or facility. In some cases, generation and load are tightly \ncoupled, so that if the generator goes offline, the load promptly follows because the manufacturing \nfacility cannot function without the steam output from the generation process. \nConsequently, strong operational and financial incentives exist for cogeneration facilities \nto operate efficiently, even above the ordinary cost-savings incentives of all generators. Even more \nnotably, to maintain QF status, Commission regulations require certain QFs to meet specified \nefficiency standards.16 Consequently, for both operational and regulatory reasons, many QFs \noperate with a high capacity factor, reliably operating during transmission peaks. As a result, the \nIndustrials are deeply concerned that the Co-Located Load Order has been issued without \nclarification of whether and how the Order will apply to cogeneration QFs. The removal of netting \nrules will directly harm large American manufacturing facilities that have invested substantial \nresources into developing and maintaining on-site generation. The removal of netting rules, \nwithout consideration of back-up and maintenance service rights and obligations, also may \ncontradict Commission regulations that require such services for cogeneration QFs.  \nAs described above, Congress’s mandate under PURPA is to encourage cogeneration, \nsmall power production, and geothermal energy production. In contrast to this mandate, with the \nremoval of netting rules and without reasonable alternatives (such as a PJM-based back-up \ntransmission rate, or an exemption from the “gross load” approach), cogeneration QFs that are \noperating excellently with a high capacity factor will suddenly be paying for transmission service \nthat they do not use.  Moreover, the Firm Contract Demand and Non-Firm Contract Demand \ncombination of new transmission service options outlined in the Order might work for planned \n \n16 18 C.F.R. § 292.205."},{"page":12,"startToken":3276,"endToken":3670,"text":"12 \n \n \ngeneration outages, but they do not appear to account for forced generation outages. For example, \nwhile Non-Firm Contract Demand service would be available on an hourly basis, it does not appear \nto provide for occasional forced outages—instead, it forces a customer to choose between paying \nfull price for occasional or back-up service or risk penalties. Removal of netting without an \navailable alternative will be devastating to many industrial entities, including those that own \ncogeneration QFs, and in turn, damage the grid by rendering on-site generation uneconomic (and \neffectuating an unlawful taking of private property), chilling future on-site generation investment, \nand harming both American manufacturing and efforts to resolve the pending resource adequacy \ncrisis in PJM. Vivid illustrations of the damage this will cause American manufacturers and other \nlarge businesses and institutions are provided in greater detail in the Request for Rehearing below. \nWhile the Commission’s goal of uniformity and contract-based transmission services \noffers some potential benefits, the Order, absent appropriate clarifications, strikes a blow against \nresource adequacy—a critical issue that FERC is addressing in other dockets.17 By harming QFs \nand other retail BTMG arrangements, the Order also threatens to harm American industry at a time \nwhen it is under pressure from, among other things, labor shortages and international competition. \nTo avoid these results, the Commission should clarify that either (1) cogeneration QFs are exempt \nfrom the “gross load” approach mandated under the Order; or (2) PJM must include a reasonable \n“Back-up Power” transmission option that retail BTMG customers, including QFs, can purchase \n \n17 The pending resource adequacy crisis in PJM has gained significant attention in recent months, at FERC and \nelsewhere. In addition to various FERC proceedings, PJM and its stakeholders have been working for months to \naddress pending resource adequacy concerns through the Critical Issue Fast Path (“CIFP”) process. Further, a \ncollaboration of the White House and PJM regional governors recently announced a proposal to address the resource \nadequacy and cost crisis. However, the Commission’s Order threatens to go the wrong direction by disincentivizing \nexisting generation—essentially, what PJM was criticized for in the Department of Energy’s Fact Sheet announcing \nits initiative to provide long-term revenue certainty to promote development of new generation. See FACT SHEET: \nTrump Administration Outlines Plan To Build Big Power Plants Again, available at \nhttps://www.energy.gov/articles/fact-sheet-trump-administration-outlines-plan-build-big-power-plants-again (last \nvisited Jan. 19, 2026)."},{"page":13,"startToken":3670,"endToken":3996,"text":"13 \n \n \nalongside the other New Services PJM must offer. Otherwise, QFs and other similarly situated \nBTMG customers will pay for full use of the transmission system based on “potential” use, which \nis inconsistent with Commission precedent supporting charging customers based on “actual use” \nof the system.18 \nB. Issue #2. The Industrials seek clarification that PJM’s new transmission services \nmust be made available to load-only customers with load flexibility. \nThe Order defines “Co-Located Load” as a “configuration [that] refers to end-use customer \nload that is physically connected to the facilities of an existing or planned Customer Facility on \nthe Interconnection Customer’s side of the Point of Interconnection to the PJM Transmission \nSystem.”19 In turn, the PJM Tariff defines “Customer Facility” as “Generation Facilities or \nMerchant Transmission Facilities interconnected with or added to the Transmission System \npursuant to an Interconnection Request under Tariff, Part IV.”20 The Tariff does not define \n“Generation Facilities,” but uses the term broadly.21   \nIn light of this language, the Industrials seek clarification that, to the extent PJM must make \nthe New Services available to Co-Located Load, it must make the New Services available broadly \nto load customers with minimal retail BTMG or even no retail BTMG. Such an approach would \nalign with the natural gas industry's long history of large gas consumers electing how much service \nthey purchase. Making the New Services available to all load customers avoids unduly \n \n18 It is worth noting that qualifying cogeneration facilities, which must be “used fundamentally for industrial, \ncommercial, or institutional purposes and is not intended fundamentally for sale to an electric utility,” share \ncharacteristics with other non-QF BTMG units, which are generally developed behind the retail meter to support on-\nsite operations and offset retail load. \n19 Co-Located Load Order at P 3. \n20 PJM, Intra-PJM Tariffs, OATT, § I.1 Definition – C-D (45.0.1). \n21 In contrast, the term “Generating Facility” is defined in Parts VII and VIII of the Tariff."},{"page":14,"startToken":3996,"endToken":4308,"text":"14 \n \n \ndiscriminatory treatment; provides benefits to all customers; supports PJM and the PJM \nTransmission Owners in system planning; and reduces the risk of cost shifts. \nFirst, providing the New Services to all transmission customers reduces the risk of an \nunduly discriminatory result. If the PJM Tariff changes directed by the Commission go into effect \nas designed—treating large retail BTMG configurations and Co-Location Arrangements \nsimilarly—the New Services should be available to retail BTMG customers and load-only \ncustomers to avoid undue discrimination between customers with generation and customers \nwithout generation. Many large load customers can curtail their load at key times and control the \namount of transmission service they use and when they use it. Allowing those customers to access \nFirm Contract Demand, non-Firm Contract Demand services, and the interim, as-available NITS \nservice, would provide the same planning and investment benefits to customers and avoid giving \nundue preference to one group of customers over another where grid impacts are similarly situated. \nSecond, ensuring the New Services are available to all load avoids potential cost shifts that \nwould occur if similarly situated customers were given radically different options depending only \non whether they had a small/perfunctory generating facility on site to qualify them.  \nThird, the New Services offer optionality and choice, potentially increasing uniformity, \nsimplicity, and efficiency, which in turn could lead to greater competition and investment. The \ndesign of the New Services, as explained in the Order, is similar to how interstate natural gas \npipeline service works in the United States; in the natural gas context, customers may choose \nbetween firm and interruptible options, with associated curtailment hierarchy. In contrast, there is \ncurrently little guidance on curtailment procedures in the event of transmission congestion or \nresource adequacy shortfalls. In theory, the New Services provide additional options for customers \nto balance reliability and cost efficiently. If these benefits are offered to Co-Location"},{"page":15,"startToken":4308,"endToken":4630,"text":"15 \n \n \nArrangements, they should also be made available to retail BTMG customers and load-only \ncustomers. \nFinally, enabling load to contract ahead for needed transmission and capacity has the \npotential to make the PJM RTEP planning process more efficient, leading to efficient investment \nand avoiding overbuilding the transmission system. Like in the natural gas context, contract-based \noptions provide transparency not only to customers but also to system planners. \nC. Issue #3. The Industrials seek clarification that the removal of “netting” rules for \nretail BTMG will be applicable to transmission and specified ancillary services \nonly, not to capacity obligations. \nThe Co-Located Load Order does not provide clear direction on the removal of “netting” \nrules as they apply to PJM Capacity obligations. The Industrials seek clarity that the Order’s \nremoval of the “netting” rules for retail BTMG is applicable only to transmission and specified \nancillary services and does not affect the netting for capacity obligations. Schedule 8 of the PJM \nReliability Assurance Agreement (“RAA”) specifically states that the “Obligation Peak Load” is \nnet of operating Behind the Meter Generation. This directive in the RAA is not part of the retail \nBTMG rules but rather addresses the determination of LSE obligations rather than individual retail \ncustomer obligations. The determination of retail customers’ capacity tags is made by individual \nelectric distribution companies. Like with transmission services, large industrial and institutional \nusers have a variety of configurations and approaches to meeting their capacity requirements, \nincluding behind-the-meter configurations, direct contracts, and purchases from PJM’s capacity \nmarket. As demonstrated in Section VI.B.2 below (part of the Request for Rehearing) regarding \ntransmission services, the Commission should develop a full record before making major changes \nto the operations of American manufacturing plants and other large users that depend on long-\nestablished PJM rules. The same applies to major changes to the PJM capacity construct. As \nSection VI.B.2 illustrates, many large manufacturers have made enormous capital outlays to create"},{"page":16,"startToken":4630,"endToken":4987,"text":"16 \n \n \nand maintain on-site generation. For many of these customers, the capacity and transmission \nsavings by reducing reliance on the electric grid is substantial.  \nIn its Order, the Commission has not provided an analysis or reasoning concerning the \nimpact of the BTMG rule changes on retail customers’ capacity obligations. Nor does the Order \naddress alternate capacity products that a retail customer with BTMG could elect. The Industrials \nseek clarification on whether this lack of specificity means that, in the Order, the Commission is \nnot directing changes to “netting” rules pertaining to capacity.  \nD. Issue #4. The Industrials seek clarification that any retail BTMG applicability \nthreshold implemented by the Commission will be sufficiently high to permit \ntraditional manufacturers and institutional customers to continue to net \ngeneration, consistent with actual use of the transmission system. \nAs explained in greater detail in Section VI.B.5 of the Request for Rehearing below, if the \nCommission maintains a “gross load” approach and pursues a mandatory threshold, the FERC \nshould clarify that the threshold will be set at a sufficiently high level to permit traditional \nmanufacturers and industrial load to continue netting, to avoid stranded costs, and to continue to \nbenefit from their own decades-long energy infrastructure investments.22 As demonstrated by the \nexamples in VI.B.2 below, a threshold of at least 200 MW would, as a practical matter, \nappropriately recognize the major energy investments most existing industrial and institutional \nloads have made over decades, consistent with the “actual use” principle, without making \nuneconomic their resource adequacy contributions.23 Such a threshold would permit the \n \n22 Such investments are not limited to capital outlay, but also include personnel, expertise, fuel, maintenance contracts, \nand much more. Loss of these facilities, which may occur in some cases if a sufficiently high threshold is not set, \nwould be a significant setback to PJM’s resource adequacy efforts and to grid reliability generally. \n23 We understand that industrial combined heat and power (“CHP”) units may, in certain cases, exceed 200 MW. \nGiven the Administration’s interest in reshoring American manufacturing and the pressing need to keep long-\nestablished generation units economic, 200 MW may be insufficient."},{"page":17,"startToken":4987,"endToken":5340,"text":"17 \n \n \nCommission to still address the primary concern driven by new, super-sized, large load entrants.24 \nAs stated by a large group of PJM transmission owners in the currently pending Large Load \nANOPR Proceeding, large data centers of 200 MW or greater are the primary drivers of load \ngrowth.25  \nIndustrial and institutional users require stability and clarity with which to plan, invest, and \ngrow. The Industrials respectfully request that the Commission grant the clarifications requested \nabove. \nVI. \n REQUEST FOR REHEARING \nThe Industrial Coalitions respectfully request rehearing on the Co-Located Load Order, as \nset forth below. \nA. \nSTATEMENT OF ISSUES / SPECIFICATION OF ERRORS \nPursuant to Rule 713(c),26 the Industrials respectfully submit that the Co-Located Load \nOrder’s determinations with respect to PJM’s retail Behind-the-Meter Generation rules are \narbitrary and capricious, do not reflect reasoned decision-making, are insufficiently supported, and \nresult in a rate outcome that is unjust, unreasonable, unduly discriminatory, and preferential. Due \nto the specific errors identified herein and the lack of a record upon which to base these \ndeterminations, the Co-Located Load Order should be modified on rehearing if any of the \n \n24 Paragraph 186 of the Order explains that the Commission’s finding on BTMG is because “circumstances have \nchanged since the Commission approved PJM’s retail BTMG rules.” The Commission cites to PJM’s explanation that \nthe BTMG rules were designed for “substantially smaller loads (like a warehouse with solar panels) and not on the \nscale of large data centers.” Historically, large industrial and institutional customers have relied on retail BTMG rules \nfor many years. However, super-sized new load entrants, which dwarf even the largest industrial customers, are raising \nnew questions about transmission planning and cost allocation. \n25 Reply Comments of the Indicated PJM Transmission Owners, Interconnection of Large Loads to the Interstate \nTransmission System, Docket No. RM26-4-000 (Dec. 5, 2025) (“To the extent the Commission asserts jurisdiction \nover large load interconnections, it should adopt a sufficiently narrow definition of ‘large load customer’ limited to \nlarge (200 MW or greater) data center customers. It is those customers that are primarily driving load increases.”). \n26 18 C.F.R. § 385.713(c)."},{"page":18,"startToken":5340,"endToken":5882,"text":"18 \n \n \nClarifications requested herein are not granted. The Industrials respectfully specify the following \nerrors: \n1. \nThe Co-Located Load Order errs because the changes to retail BTMG rules in the \nOrder are outside the scope of the February 20, 2025 Show Cause Order. 18 \nC.F.R. § 385.209; PJM Interconnection, L.L.C., 185 F.E.R.C. ¶61,158 (Order \nentered Nov. 30, 2023); Tex. E. Transmission, LP, 179 F.E.R.C. ¶61,201; Am. \nElec. Power Serv. Corp. Aquila Merch. Servs., 103 FERC ¶61,020 (Order entered \nJan. 22, 2004). \n2. \nThe Co-Located Load Order errs because it does not reflect reasoned decision-\nmaking regarding retail BTMG, because the Commission did not develop a \nsufficient record on which to base its retail BTMG decisions, resulting in \nconclusions that are arbitrary and capricious. 16 U.S.C. § 824d, 16 U.S.C. § \n825l(b); South Carolina Pub. Serv. Auth. v. FERC, 762 F.3d 41 (D.C. Cir. 2014); \nSacramento Mun. Util. Dist. v. FERC, 616 F.3d 520 (D.C. Cir. 2010); Midwest \nISO Transmission Owners v. FERC, 373 F.3d 1361 (D.C. Cir. 2004); Motor \nVehicle Mfrs. Ass’n v. State Farm Mut. Auto. Ins. Co., 463 U.S. 29 (1983); New \nEng. Power Generators Ass’n v. FERC, 881 F.3d 202 (D.C. Cir. 2018); \nExxonMobil Oil v. FERC, 487 F.3d 945 (D.C. Cir. 2007); New York v. FERC, \n535 U.S. 1 (2002); Transmission Access Policy Group v. FERC, 225 F.3d 667 \n(D.C. Cir. 2000); North Carolina Util. Comm’n v. FERC, 42 F.3d 659 (D.C. Cir. \n1994); N.J. Bd. of Pub. Utils. v. FERC, 744 F.3d 74 (3d Cir. 2014). \n3. \nThe Co-Located Load Order errs by indirectly effectuating takings of private \nproperty at several manufacturing facilities in the PJM grid without providing just \ncompensation pursuant to the Fifth Amendment of the United States Constitution.  \nU.S. Const. amend. V.; Lingle v. Chevron U.S.A., 544 U.S. 528 (2005); Loretto \nv. Teleprompter Manhattan CATV Corp., 458 U.S. 419 (1982); Lucas v. South \nCarolina Coastal Council, 505 U.S. 1003 (1992); Penn Central Trans. v. New \nYork City, 438 U.S. 104 (1978).  \n4. \nThe Co-Located Load Order errs by failing to address its own prior precedent on \ncost-causation or to demonstrate that the retail BTMG rules were unjust and \nunreasonable. 16 U.S.C. § 824d(a)-(e); 16 U.S.C. § 824e(a),(d); Emera Maine v. \nFERC, 854 F.3d 9 (D.C. Cir. 2017); FERC v. Elec. Power Supply Ass’n, 577 U.S. \n260, (2016), as revised (Jan. 28, 2016); Farmers Union Cent. Exch., Inc. v. FERC, \n734 F.2d 1486 (D.C. Cir. 1984); New England Power Generators Ass’n, Inc. v. \nFERC, 881 F.3d 20 (D.C. Cir. 2018); Missouri Public Service Com’n v. FERC, \n234 F.3d 36 (D.C. Cir. 2000); Hughes v. Talen Energy Mktg., LLC, 578 U.S. 150 \n(2016); New York v. FERC, 535 U.S. 1 (2002). \n5. \nThe Co-Located Order errs by failing to establish Commission jurisdiction over \ncustomer generation behind a retail meter that is not used in PJM’s energy or \ncapacity markets, as defined in the PJM Open Access Transmission Tariff. 16"},{"page":19,"startToken":5882,"endToken":6201,"text":"19 \n \n \nU.S. Code § 824d(a), 16 U.S. Code § 824(b)(1); Detroit Edison Co. v. FERC, 334 \nF.3d 48, 53 (D.C. Cir. 2003). \n6. \nThe Co-Located Load Order’s transition and grandfathering provisions and \nundefined megawatt-based applicability threshold fail to correct the defects \ncreated in the Order. \nB.  \nARGUMENT \nFor many years, industrial and institutional customers have constructed, maintained, and \nexpanded on-site generation as a part of their strategy to manage energy costs. Many of these \nentities have invested tens or even hundreds of millions of dollars to build, connect, deploy, and \noperate these units. These generating facilities have, in turn, produced many benefits—reducing \ntransmission congestion, decreasing dependence on the capacity and energy markets, and \nproviding additional stability to the grid. They have enabled manufacturers and other energy-\nintensive customers to reduce energy spend and increase their own economic viability. The “net \nload” approaches of PJM’s NITS and capacity constructs have provided significant incentives for \nretail BTMG customers to operate their generating units efficiently and at the proper times, thereby \nreducing net flow from the grid when the grid is congested.  \nThe Commission’s Co-Located Load Order poses a significant threat to these multi-decade \ninvestments. At a high level, the Order fails to demonstrate that the changes to retail BTMG rules \nare consistent with cost causation. Instead, the Order appears to weaken a structure that has \nincentivized efficient use of the grid for decades. Further, the Order acts in an unduly \ndiscriminatory manner by appropriately retaining peak management for the load side of the \nequation but not for customers with generation. For industrial customers who have limited \ncurtailment options but who have invested in on-site generation, this may prove to be the worst of \nboth worlds—they will be charged “as if” they were fully using the transmission system, while \nsophisticated new data centers that do regularly use the transmission system can shift load to other"},{"page":20,"startToken":6201,"endToken":6541,"text":"20 \n \n \nfacilities during peak times. In other words, the Commission’s approach is “Peak management for \nme (load) but not for thee (generation).” This approach is unduly discriminatory because it treats \nsimilarly situated customers differently based on their behind-the-meter configurations, rather than \non actual grid impacts. The Order, if not modified, will measure “actual use” for some customers \nand “potential use” for others. This hybrid structure is unduly discriminatory and without a \nreasoned basis. To be clear, the Industrial Customer Coalitions support facilitating customers’ \nability to manage their loads efficiently and effectively, especially during times of high prices and \nsystem stress. The Commission’s policies should advance such customer-directed actions, not \npenalize them. \nIn fulfilling its duty to determine just and reasonable rates, courts have consistently \naffirmed the Commission’s responsibility to substantiate its decisions with reasoned, principled \ndecision-making. The D.C. Circuit has held that FERC must “adequately explain how the evidence \nit relied on supported the conclusion it reached.”27 Elsewhere, the D.C. Circuit held that the \nFERC’s broad mandate to set just and reasonable rates under the FPA did not relieve FERC of the \nrequirement to engage in reasoned decision-making.28 The D.C. Circuit also found that the FERC \nfailed to meet its obligation when the Commission did not adequately explain the rationale for its \nrate-setting decisions, emphasizing that reasoned and principled decision-making is essential.29 \nWhile the Commission’s determinations regarding technical issues are entitled to deference, \n \n27 Emera Maine v. FERC, 854 F.3d 9, 28 (D.C. Cir. 2017) (citing Wis. Gas Co. v. FERC, 770 F.2d 1144, 1156 (D.C. \nCir. 1985)). \n28 New England Power Generators Ass’n, Inc. v. FERC, 881 F.3d 202, 210 (D.C. Cir. 2018). \n29 See Missouri Public Service Com’n v. FERC, 234 F.3d 36, 40 (D.C. Cir. 2000). This comports with the design of \nthe FPA, where Commissioners are directed to give their reasoning even where the Commission cannot come to a \ndecision due to a tie vote. 16 U.S. Code § 824d(g)(1)."},{"page":21,"startToken":6541,"endToken":6873,"text":"21 \n \n \ndeference is not owed if the FERC “has not substantiated the application of its policy, either \nthrough the development of specific facts or by making a reasoned explanation.”30 \nHere, the Commission has failed to adequately explain how the evidence it relied on led to \nthe conclusion it reached. The Order suffers from defects of due process and substance. First, the \nOrder requires changes that are outside the scope of the Show Cause Order. The Order did not \nmake clear that retail BTMG rules were being considered for major changes. Second, the \nCommission did not develop a sufficient record to support major decisions concerning retail \nBTMG. Third, the Order indirectly effectuates an unlawful taking of private property. Fourth, the \nCommission did not address its own contrary precedent on retail BTMG, particularly as regards to \nits prior determinations on cost causation. Fifth, the Order does not sufficiently explain the legal \nbasis for asserting jurisdiction over retail customers with generation behind their meter that is not \notherwise used in PJM’s energy or capacity markets and does not use the PJM transmission system. \nFinally, the megawatt-based threshold proposed by the Commission and the proposed transition \nand grandfathering provisions, while possibly mitigating some negative effects of the Order, do \nnot resolve the fundamental flaws of the Order. However, if the Commission selects a sufficiently \nhigh threshold to allow traditional industrial users to continue net generation, consistent with their \nactual use of the system, it will substantially reduce the negative impact of the Order and avoid \ncreating stranded costs and lost investments for America’s manufacturing sector. A threshold of at \nleast 200 MW for retail BTMG, or an exemption for cogeneration QFs, would allow the \nCommission to focus on the impacts of new, super-sized load entrants without damaging the long-\ndeveloped behind-the-meter systems built by industrial and institutional customers. \n \n30 El Paso Elec., 832 F.3d 495, 503 (5th Cir. 2016) (quoting Fla. Gas Transmission Co. v. FERC, 876 F.2d 42, 45 (5th \nCir. 1989))."},{"page":22,"startToken":6873,"endToken":7376,"text":"22 \n \n \n1. The Co-Located Load Order errs because the changes to retail BTMG rules in the \nOrder are outside the scope of the Show Cause Order. \nThe Administrative Procedures Act provides that a reviewing court shall “hold unlawful \nand set aside agency action, findings, and conclusions found to be … arbitrary, capricious, an \nabuse of discretion, or otherwise not in accordance with law.”31 When factual issues are in dispute \nin an adjudicated proceeding, a hearing is appropriate.32  \nThe Commission’s Rules of Practice and Procedure (“Rules”) govern the show cause order \nprocess. Rule 209(b) states, “A notice of examination or an order to show cause will contain a \nstatement of the matters about which the Commission is inquiring, and a statement of the authority \nunder which the Commission is acting. The statement is tentative and sets forth issues to be \nconsidered by the Commission.”33 Here, the Commission’s Show Cause Order that set the scope \nof the proceeding to Co-Located Load and Co-Location Arrangements, not to “all behind-the-\nmeter arrangements.”34 This is evident for several reasons. First, the Show Cause Order stated that \n \n31 5 U.S.C. § 706. \n32 Gen. Motors Corp. v. Fed. Energy Regulatory Com., 211 U.S. App. D.C. 202, 656 F.2d 791, 794-95, 798 (1981). \n(D.C. Circuit explained that “FERC need not hold an evidentiary hearing when no issue of material fact is in dispute,” \nbut also “remind[ed] the Commission, however, that it bears a weighty burden in justifying a denial of an evidentiary \nhearing” (citing Public Service Co. of New Hampshire v. FERC, 195 U.S. App. D.C. 130, 600 F.2d 944, 955 (D.C. \nCir. 1979); Citizens for Allegan County, Inc. v. FPC, 134 U.S. App. D.C. 229, 414 F.2d 1125, 1128 (D.C. Cir. 1969; \nIndependent Bankers Ass'n of Georgia v. Board of Gov. of Federal Reserve System, 170 U.S. App. D.C. 278, 516 F.2d \n1206, 1270 (D.C.Cir.1975)). \n33 18 C.F.R. § 385.209. \n34 The Show Cause Order stated: \nAs discussed below, based on the combined records of the technical conference and the \nConstellation complaint proceeding, we find that PJM’s Tariff appears to be unjust, unreasonable, \nunduly discriminatory or preferential.  We institute a show cause proceeding pursuant to section 206 \nof the FPA, and we direct PJM and the Transmission Owners, within 30 days of the date of the \norder, to either:  (1) show cause as to why the OATT, the Amended and Restated Operating \nAgreement of PJM, and Reliability Assurance Agreement Among Load Serving Entities in the \nPJM Region (the Tariff) remains just and reasonable and not unduly discriminatory or \npreferential without provisions addressing with sufficient clarity or consistency the rates, \nterms, and conditions of service that apply to co-location arrangements; or (2) explain what \nchanges to the Tariff would remedy the identified concerns if the Commission were to determine \nthat the Tariff has in fact become unjust and unreasonable or unduly discriminatory or preferential"},{"page":23,"startToken":7376,"endToken":7723,"text":"23 \n \n \nthe PJM Tariff “appears to be unjust, unreasonable, unduly discriminatory or preferential” because \nof a lack of clear or consistent provisions for Co-Location Arrangements. In contrast, retail BTMG \nhas existed in PJM’s Tariff for decades.  \nSecond, a Co-Location Arrangement (as newly defined, as it does not exist currently in the \nTariff) is a wholesale-system-impacting load integration construct, in contrast to retail BTMG, \nwhich is a retail load-modification construct. In the Show Cause Order, the Commission adopted \nPJM’s definition of “Co-Located Load” in a PJM-published guidance document, PJM Guidance \non Co-Located Load (“Guidance Document”) (since rescinded by PJM, pending the Commission's \ndirection in this docket).35 The definition, as quoted in the Show Cause Order, is: \nA co-located load configuration refers to end-use customer load that is physically \nconnected to the facilities of an existing or planned Customer Facility on the \nInterconnection Customer’s side of the Point of Interconnection (“POI”) to the PJM \nTransmission System (co-located Customer Facility).36 \nThe Show Cause Order defined Co-Location Arrangements as referring to both the Co-Located \nLoad and the associated generator.37 The Co-Located Load Order adopted these definitions. It is \nclear from the Guidance Document, upon which the Commission relied, that Co-Location \nArrangements include a “Generating Facility” as the term is used in the Generation Interconnection \nAgreement (“GIA”) and Wholesale Market Participation Agreement (“WMPA”) in Part IX of the \nPJM Tariff and “Participant Facility” as used in the pre-Transition Date WMPA.38 Further, the \n \nand, therefore, proceeds to establish a replacement Tariff.  We also consolidate the show cause \nproceeding with the technical conference and Constellation complaint proceeding. \nShow Cause Order at P 2 (emphasis added). \n35 PJM Guidance on Co-Located Load (Mar. 22, 2024) (updated Apr. 17, 2024), available at https://www.pjm.com/-\n/media/DotCom/markets-ops/rpm/rpm-auction-info/pjm-guidance-on-co-located-load.pdf (last visited Jan. 16, 2026). \n36 Show Cause Order at P 3, footnote 4 (citing PJM Guidance Document at 1). The Show Cause Order defines Co-\nLocation Arrangement as “[…]the entire arrangement, both the co-located load and the co-located generator […].” \n37 Id. \n38 Guidance Document at 1, footnote 1."},{"page":24,"startToken":7723,"endToken":8032,"text":"24 \n \n \nGuidance Document clarifies that it uses the term “Interconnection Customer” synonymously with \n“Project Developer” as used in the GIA and WMPA and “Wholesale Market Participant” as used \nin the pre-Transition Date WMPA.39 \nIn contrast to Co-Location Arrangements, retail BTMG is defined in the context of retail \nload, and retail BTMG generation by definition does not include sales for resale or capacity \ndesignated as a Generation Capacity Resource. The PJM Tariff states:  \n“Behind The Meter Generation” shall refer to a generation unit that delivers energy \nto load without using the Transmission System or any distribution facilities (unless \nthe entity that owns or leases the distribution facilities has consented to such use of \nthe distribution facilities and such consent has been demonstrated to the satisfaction \nof the Office of the Interconnection); provided, however, that Behind The Meter \nGeneration does not include (i) at any time, any portion of such generating unit’s \ncapacity that is designated as a Generation Capacity Resource; or (ii) in an hour, \nany portion of the output of such generating unit that is sold to another entity for \nconsumption at another electrical location or into the PJM Interchange Energy \nMarket.40 \nAs seen in the Tariff definition, retail BTMG definitionally does not use the PJM Transmission \nSystem. BTMG is a retail load-modification construct, whereas Co-Located Load is a wholesale-\nsystem-impacting load integration construct.  \nThird, the Show Cause Order refers to BTMG as a distinct arrangement from Co-Location \nArrangements. BTMG, as a defined PJM Tariff construct, is scarcely mentioned in the Show Cause \nOrder. In Paragraphs 87-88 of the Show Cause Order, the Commission instructed PJM and the \nTransmission Owners to address a large number of specific topics (“Briefing Questions”).41 \n \n39 Guidance Document at 1, footnote 2. \n40 PJM, Intra-PJM Tariffs, OATT, § I.1 Definition – A-B (22.0.0).  \n41 Show Cause Order at PP 87-88."},{"page":25,"startToken":8032,"endToken":8389,"text":"25 \n \n \nBTMG is mentioned only once in the Briefing Questions, and it is discussed as a distinct \narrangement from Co-Location Arrangements.42 Specifically, the Show Cause Order states: \nParties may also address how co-located loads are similar to or disparate from other \ntypes of arrangements where load and generation share the same point of \ninterconnection (such as Behind the Meter Generation as defined in PJM’s Tariff \nor non-retail behind the meter generation) and should consider how any proposed \nreplacement rate would interact with these other arrangements.43  \nClearly, retail BTMG is a distinct concept from Co-Located Load. The Commission did not direct \nparties to “show cause” as to the justness and reasonableness of Tariff rules concerning retail \nBTMG. Instead, it directed PJM and the Transmission Owners to show cause why the Tariff, the \nPJM Operating Agreement, and the RAA were just and reasonable without adequate provisions \naddressing the rates, terms, and conditions of service. In contrast to this show cause directive, retail \nBTMG is defined and outlined in PJM’s Tariff. \nBecause both the PJM Tariff and this proceeding treat Co-Located Load (with its associated \ngeneration) and retail BTMG (with its associated load) as distinct concepts, a determination \naffecting retail BTMG must not be treated as a mere corollary of a Co-Located Load ruling. Each \nconstruct carries independent legal and operational consequences and therefore requires \nindependent notice and analysis.44 To avoid an arbitrary and capricious result under Rule 209 and \nthe Administrative Procedures Act, the Commission should reconsider any determinations that \nwere not properly noticed as within the scope of the Show Cause Order.45 Consequently, he \n \n42 Show Cause Order at P 88(iv). \n43 Show Cause Order at P 88 (emphasis added). \n44 5 U.S. Code § 706(2)(A). \n45 The Commission often limits its holdings to the scope set for hearing in its initial orders. See, e.g., PJM \nInterconnection, L.L.C., 185 F.E.R.C. ¶ 61,158 (Order entered Nov. 30, 2023); Tex. E. Transmission, LP, 179 F.E.R.C. \n¶ 61,201; Am. Elec. Power Serv. Corp. Aquila Merch. Servs., 103 FERC ¶ 61,020 (Order entered Jan. 22, 2004)."},{"page":26,"startToken":8389,"endToken":8928,"text":"26 \n \n \nCommission should reconsider its determinations concerning retail BTMG determination in the \nOrder, as it was outside the stated scope of this proceeding. \n2. The FERC’s decision in the Co-Located Load Order does not reflect reasoned \ndecision-making because it did not develop a sufficient record on which to base its \ndeterminations on the retail BTMG rules in PJM’s Tariff, resulting in conclusions \nthat are arbitrary and capricious. \nA Commission order will be reversed on review if it is arbitrary or capricious, reflects an \nabuse of discretion, is not otherwise in accordance with law, or is not supported by substantial \nevidence.46 To satisfy its obligation to engage in reasoned decision-making, the Commission must \nexamine the relevant data and articulate a rational connection between the facts found and the \nchoices made.47 The Commission must reach its conclusion through decision-making that is \n“reasoned, principled, and based upon the record.”48 Further, if the FERC “does not provide a \nrational explanation for its action based on relevant data, then that action is arbitrary and \ncapricious.”49 To avoid an arbitrary and capricious decision or one that does not reflect reasoned \ndecision-making, the Commission must consider all important aspects of the problem at issue.50 It \n \n46 5 U.S.C. § 706(2)(A); Vistra Corp. v. FERC, 80 F.4th at 312; South Carolina Pub. Serv. Auth. v. FERC, 762 F.3d \n41, 55 (D.C. Cir. 2014); Sacramento Mun. Util. Dist. v. FERC, 616 F.3d 520, 528 (D.C. Cir. 2010).   \n47 Sacramento, 616 F.3d at 528; Midwest ISO Transmission Owners v. FERC, 373 F.3d 1361, 1368 (D.C. Cir. 2004) \n(quoting Motor Vehicle Mfrs. Ass’n v. State Farm Mut. Auto. Ins. Co., 463 U.S. 29, 43 (1983)).   \n48 New Eng. Power Generators Ass’n v. FERC, 881 F.3d 202, 210-11 (D.C. Cir. 2018); West Deptford Energy, LLC, \n766 F.3d 10, 20 (D.C. Cir. 2014); ExxonMobil Oil v. FERC, 487 F.3d 945, 953 (D.C. Cir. 2007); see New York v. \nFERC, 535 U.S. 1, 36 (2002); see also Transmission Access Policy Group v. FERC, 225 F.3d 667, 705, 716 (D.C. \nCir. 2000) (citing Associated Gas Distributors v. FERC, 824 F.2d 981, 1021 (D.C. Cir. 1987)); Colo. Interstate Gas \nCo. v. FERC, 146 F.3d 889, 893 (D.C. Cir. 1998).   \n49 La. PSC. V. FERC, 20 F.4th 1, 6-7 (D.C. Cir. 2021) (citing 5 U.S.C. § 706(2)(A) and Motor Vehicle Mfrs. Ass’n, \n463 U.S. at 43)).  \n50 See, e.g., Motor Vehicle Mfrs. Ass’n, 463 U.S. at 43 (1983) (“an agency rule would be arbitrary and capricious if \nthe agency . . . failed to consider an important aspect of the problem”); NorAm Gas Transmission Co. v. FERC, 148 \nF.3d 1158, 1165 (D.C. Cir. 1998) (“In previous cases, we have rejected agency orders when the Commission neglected \nto deal with an important part of the problem…”) (citing Laclede Gas Co. v. FERC, 997 F.2d 936, 945-48 (D.C. Cir. \n1993)); North Carolina Util. Comm’n v. FERC, 42 F.3d 659, 666 (D.C. Cir. 1994) (given the complexity of the issue, \nthe FERC must more fully explain its decision)."},{"page":27,"startToken":8928,"endToken":9232,"text":"27 \n \n \nis “well established that the Commission must ‘respond meaningfully to the arguments raised \nbefore it.’”51  \nIn the present case, the Co-Located Load Order does not have a well-developed record to \nsupport its determinations on retail BTMG rules. Without a well-developed record, the \nCommission may not be able to fully recognize the cost-causation implications of the removal of \nall netting rules. As a result, the Order fails to adequately account for the economic realities and \nunique configurations of retail BTMG, the customer base that has invested many millions of \ndollars in reliance on those rules, and the impact on the grid of radical changes to those rules.  \nThe following are several examples of hypothetical but realistic Co-Location \nArrangements and/or retail BTMG configurations. Similar examples can be found in PJM’s \nterritory and will be deeply affected by the Order, unless it is appropriately modified or clarified. \nAll examples are offered as representative of potential impacts of the Order as it stands currently. \n- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - \nExample 1: Synced Load and Generation Means Paying for 200 MW with Minimal Use. \n Context: 200 MW of retail behind-the-meter generation offsetting factory load. \n Operations: Large boilers produce steam, which is used to turn generation turbines \nand support manufacturing operations. \n Key Fact: If the generation is down, load immediately comes offline.  \n \nThe first example is a large-scale production facility. This entity has well-developed retail \nBTMG configurations that are tightly tied to its manufacturing process. Because the manufacturing \nprocess requires steam produced for generation, the bulk of the load can remain online only if \ngeneration is operational. If the generation goes down, the load will largely cease as well. Beyond \na potential momentary spike in power as the load powers down, the configuration does not allow \n \n51 TransCanada Power Mktg. Ltd. v. FERC, 811 F.3d 1, 12 (D.C. Cir. 2015)."},{"page":28,"startToken":9232,"endToken":9545,"text":"28 \n \n \nfor the use of 200 MW of transmission service. A business like this, if situated in PJM and not \notherwise exempted, will likely experience substantial transmission payments or penalties under \nthe new “gross load” approach because the approach does not consider the customer’s “actual use” \nof the transmission system in the event of a generation outage. \n- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - \nExample 2: Over 100 MW of Combined Heat & Power Rendered Uneconomic. \n Context: Two CHP units totaling approximately 100 MW. \n Operations: NITS and Capacity offsets provide over half the value of these units. \n Key Fact: Losing NITS and Capacity savings will likely render these units no longer \ncommercially viable. \n \nA large manufacturing facility has two behind-the-meter CHP units totally approximately \n100 MW. The facilities have been operational for an extended period of time and are QFs under \nPURPA, with full rights to export and sell power onto the PJM grid. Due to its exceptional track \nrecord of consistent operations, this retail customer has been able to control its NITS and Capacity \nobligations for these facilities, paying the distribution utility for back-up power when the units trip \noffline. The NITS and Capacity savings provide more than half of the value of the CHP units, \nallowing the organization to continue maintaining and operating these assets. Other benefits from \nthe CHP units include the value of waste heat. However, removal of the NITS savings alone would \nlikely render the customer’s retail BTMG no longer commercially viable, resulting in the shutdown \nof the existing units and a lack of further expansion or new behind-the-meter CHP installations. \nThat result would mean a loss of more than 100 MW of generation—the exact opposite direction \nof where the FERC and PJM have expressed that they need to go with regard to resource adequacy \nissues. The loss of the CHP units would also result in increased energy costs, burdening \nmanufacturing viability at the site. \n- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -"},{"page":29,"startToken":9545,"endToken":9877,"text":"29 \n \n \nExample 3: Two Cogeneration Facilities: Different Efficiency, Same NITS. \n \n Context: Two customers with approximately 50 MW of gross load each; each customer \nhas a 30 MW cogeneration plant (“Cogen”) on site. \n Operations: The Cogen of Customer #1 operates at a 95% capacity factor, while the \nCogen of Customer #2 operates at a 60% capacity factor. \n Key Fact: Under a gross-load only approach, both customers will pay approximately \nthe same in NITS charges, despite dramatically different grid impacts.    \n \nThis example demonstrates how disconnected the “gross load” approach is from the “actual \nuse” standard that the Commission has endorsed on multiple occasions.52 The difference between \na 95% capacity factor and a 60% capacity factor is dramatic – essentially, the Cogen of Customer \n#2 is out of commission 8 times more (40% downtime vs. 5% downtime). Yet, under the new \nregime, NITS charges would be the same for both customers (based only on how much of the total \nbehind-the-meter load was operational during peak hours). \n- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - \nExample 4: Battery Storage Investment No Longer Reasonable. \n Context: Manufacturer is currently considering adding over 11 MW of behind-the-\nmeter battery energy storage. \n Operations: The intended use for battery storage is to reduce capacity and \ntransmission obligations by reducing energy purchases from the grid at peak times, \nwhich reduces congestion at appropriate times on the system. \n Key Fact: The primary driver for adding over 11 MW of load-reduction capability may \nbe eliminated by a change in the retail BTMG netting rules.    \n \nBattery storage is a rapidly developing field that was not addressed in the Order. Battery \nstorage technology offers significant potential for improving grid efficiency. It is unclear from the \nOrder how large-scale battery storage would be treated for purposes of measuring transmission \nobligations. If output from battery storage is deemed to be impermissible “netting” under the \nOrder, a significant incentive to develop this technology on-site will be removed. \n \n52 Occidental Chem. Corp. v. PJM Interconnection, 102 FERC ¶ 61,275; PJM Interconnection, L.L.C., 167 FERC \n¶61,268."},{"page":30,"startToken":9877,"endToken":10168,"text":"30 \n \n \n- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - \nExample 5: Multiple Units Behind the Meter; QF Agreement with Utility Terminated. \n \n Context: Manufacturer with nearly 60 MW of load and approximately 35 MW of \nbehind-the-meter generation.  \n Operations: Multiple generation units comprise a full on-site generation fleet, \nanchored by a large CHP unit. \n Key Fact: Legacy QF, whose agreement with the local utility was terminated when the \nutility’s mandatory purchase obligation was eliminated.    \n \nThis manufacturing customer operates multiple generation units behind the meter. \nPreviously, the customer had an active QF agreement with its local distribution utility; the utility \nterminated this agreement many years ago due to the customer having market access. Changes to \na gross load approach would significantly impact pricing for this customer and would fail to \naccount for the longevity and stability of the multiple generation units operating behind the meter. \n- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - \nExample 6: Non-QF Relies on Netting Rules for Long-Established BTMG Operation. \n Context: Manufacturer with approximately 150 MW of load; facility is interconnected \nto a vertically integrated utility.  \n Operations: Generates most power on-site; receives approximately 20 MW of power \nflow from the local utility. \n Key Fact: Not a QF.    \n \nThis manufacturer self-generates a substantial portion of its required power on site; it has \nused this configuration for decades. Though operating with substantial BTMG, this customer does \nnot operate as a QF under PURPA. Rather, the manufacturer relies on netting rules to accurately \nmeasure its use of the grid. It works directly with its local utility to purchase its supplemental and \nback-up power requirements. If the customer’s BTMG were to trip offline, the customer’s own \ninfrastructure would prevent it from relying on the grid for all its requirements. As such, if this \ncustomer were charged on a gross basis, it would be required to purchase service that it cannot"},{"page":31,"startToken":10168,"endToken":10445,"text":"31 \n \n \nphysically utilize. Changes to netting rules threaten to change how this manufacturer has operated \nin conjunction with its vertically integrated distribution utility for many years.  \n- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - \nThe above “parade of horribles” are based on real-life facility configurations, offered as \nexamples of how retail BTMG may be impacted by the Order. There are various other possible \nconfigurations and issues that may arise, as well. For example, the Commission has not clarified \nhow the New Services will interact with Demand Response offerings or other load-balancing/load-\nshifting strategies designed to maximize grid efficiencies; and it has not addressed what the impact \nto the grid will be if key incentives that drive those innovations are removed. \nThe lack of a record on these issues warrants rehearing. Each of the above scenarios \ndemonstrates the danger of the Commission taking such sweeping action without developing a full \nrecord. In the Industrials’ view, the Commission’s half-measure of trying to impose charges based \non “potential load” for some customers and based on “actual load” for other customers is not \nsupported by the limited factual record. The Industrials respectfully request that the Commission \nreconsider its changes to retail BTMG rules. \n3. The Co-Located Load Order indirectly effectuates an unlawful taking of private \nproperty without providing just compensation, in violation of the Fifth \nAmendment. \nThe Fifth Amendment of the United States Constitution prohibits the federal government \nfrom taking private property for public use without just compensation.53 The United States \nSupreme Court has explained that there are two kinds of regulatory actions that will be deemed \nper se takings under the Fifth Amendment: (1) where an owner suffers permanent physical \n \n53 U.S. Const. amend. V."},{"page":32,"startToken":10445,"endToken":10863,"text":"32 \n \n \ninvasion due to the government action;54 and (2) where the owner is deprived of “all economically \nbeneficial us[e]” of the property due to the government action.55  The latter applies here.   \nAs demonstrated above in Example 1 and Example 2 in the prior specification of error, the \nCo-Located Load Order will render certain manufacturing facilities with on-site generation \ncompletely uneconomic, thereby forcing a closure of the manufacturing facility and making the \ngenerating unit(s) no longer commercially viable. The Co-Located Load order threatens to directly \nput certain manufacturing facilities out of business, causing a total economic loss. \n Example 1: Assume a large-scale production facility with well-developed retail BTMG \nconfigurations (200 MW) that are tightly tied to its manufacturing process and help offset \nthe load/consumption. Because the manufacturing process requires steam produced for \ngeneration, the bulk of the load can remain online only if generation is operational. If the \ngeneration goes down, the load will immediately come offline and cease production.  The \noperations and configuration at this site does not allow for the use of 200 MW of \ntransmission service.  The customer will experience substantial transmission payments or \npenalties under the Co-Located Load Order’s new “gross load” approach because the \napproach does not consider the customer’s “actual use” of the transmission system in the \nevent of a generation outage. \n Example 2: Assume a large manufacturing facility with two behind-the-meter CHP units \ntotaling approximately 100 MW. The facilities have been operational for an extended \nperiod of time and are QFs under PURPA, exporting and selling power into the PJM grid.  \nThe NITS and Capacity savings provide more than half of the value of the CHP units.  Yet, \nthe Co-Located Load order directly threatens to put this manufacturer out of business, as \nremoval of the NITS savings alone would likely render the customer’s retail BTMG \nuneconomic, resulting in the shutdown of the existing units and inability of the \nmanufacturer to continue operating.  \nAs a result of the Co-Located Load Order’s abrupt shift to a “gross load” approach for transmission \ncost responsibility, the property at the manufacturing sites in Example 1 and Example 2 will have \nlittle to no economically beneficial remaining uses. The Co-Located Load Order fails to consider \n \n54 Lingle v. Chevron U.S.A., 544 U.S. 528, 538 (2005) (citing Loretto v. Teleprompter Manhattan CATV Corp., 458 \nU.S. 419 (1982)). \n55 Lingle, 544 U.S. at 538 (quoting Lucas v. South Carolina Coastal Council, 505 U.S. 1003, 1019 (1992) (emphasis \nin original)."},{"page":33,"startToken":10863,"endToken":11193,"text":"33 \n \n \nsuch circumstances at manufacturing sites and fails to provide a pathway toward providing just \ncompensation if the Commission proceeds to deny the Industrials’ Request for Clarification.   \n \nOutside of the context where a per se taking deprives an owner of all economically \nbeneficial use of the property, the United States Supreme Court in Lingle also explained that \nregulatory taking challenges are governed by the factors in Penn Central Trans. v. New York City, \n438 U.S. 104 (1978) where the primary factor is the economic impact of the regulatory action on \nthe owner.56 The Penn Central factors will be utilized when the regulatory action causes \nsubstantial, but perhaps not total, evisceration in the owner’s property value or use of the \nproperty.57 However, the extent to which the regulatory action “has interfered with distinct \ninvestment-backed expectations” is a relevant consideration.58 The existence of a public program \npromoting the common good is also relevant to the takings analysis.59       \n \nIn some instances, the Co-Located Load Order will cause devastating economic impacts to \nseveral manufacturing facilities, but perhaps not total deprivation of the use of the property, \nthereby triggering the application of the Penn Central factors. Importantly, the Co-Located Load \nOrder’s shift to the “gross load” approach causes substantial economic impacts and “has interfered \nwith distinct investment-backed expectations.”60 Several manufacturing facilities have relied on \nthe long-established PURPA framework for QFs, as noted in Example 2. Additionally, as noted in \nExample 6 in the previous section, a manufacturer may generate a substantial portion of its energy \n \n56 Lingle, 544 U.S. at 538-539 (quoting Penn Central, 438 U.S. at 124). \n57 See Lingle, 544 U.S. at 539 (explaining that “ the Penn Central inquiry turns in large part, albeit not exclusively, \nupon the magnitude of a regulation's economic impact and the degree to which it interferes with legitimate property \ninterests.”). \n58 Penn Central, 438 U.S. at 124. \n59 Id. \n60 See Penn Central, 438 U.S. at 124."},{"page":34,"startToken":11193,"endToken":11575,"text":"34 \n \n \non site, using such a configuration for decades, but may not operate as QF under PURPA. This \nmanufacturer has long relied on the well-established netting rules to ensure accurate measurement \nfor the manufacturer’s use of the PJM transmission grid. The Co-Located Load Order interferes \nwith these investment-backed expectations and does not promote or facilitate a public program or \npublic good to justify the economic interference with the longstanding uses of private property at \nmanufacturing facilities in the PJM grid.   \n \nAccordingly, the Co-Located Load Order errs by indirectly effectuating takings of private \nproperty at several manufacturing facilities in the PJM grid without providing just compensation \npursuant to the Fifth Amendment of the United States Constitution. \n4. The Co-Located Load Order errs by failing to address its own prior precedent on \ncost-causation or to demonstrate that the retail BTMG rules were unjust and \nunreasonable. \nAs is well established, cost causation is a bedrock principle of just and reasonable rates.  \nAs stated by the D.C. Circuit, “For decades, the Commission and the courts have understood [the \njust and reasonable] requirement to incorporate a ‘cost-causation principle’—the rates charged for \nelectricity should reflect the costs of providing it.”61 As expressed by the Fifth Circuit in El Paso \nElectric Co. vs. FERC, “This principle is ‘foundational’ and a ‘basic tenet’ of ratemaking.”62 Cost-\ncausation jurisprudence has addressed two aspects of cost causation: those who cause the costs \nand those who reap the benefits. As stated in El Paso, “Courts have generally held that costs ‘are \nto be allocated to those who cause the costs to be incurred and reap the resulting benefits.’”63 \n \n61 Old Dominion Elec. Coop. v. FERC, 898 F.3d 1254, 1255 (D.C. Cir. 2018); see also El Paso Elec. Co. v. FERC \n(“El Paso”), 76 F.4th 352, 357 (5th Cir. 2023). \n62 El Paso at 357 (citing El Paso Elec. v. FERC, 832 F.3d 495, 505 (5th Cir. 2016)); S.C. Pub. Serv. Auth. v. FERC, \n762 F.3d 41, 85 (D.C. Cir. 2014) (per curiam). \n63 El Paso (citing NARUC at 1285); see also BNP Paribas Energy Trading GP v. FERC, 743 F.3d 264, 268 (D.C. \nCir. 2014) (The principle is a “matter of making sure that burden is matched with benefit.”)"},{"page":35,"startToken":11575,"endToken":11914,"text":"35 \n \n \nThe rubber meets the road on this concept when the FERC determines how transmission \ninfrastructure and upgrade costs are allocated and how cost responsibility is measured. However, \nthe Commission has not contended with prior precedent in which it repeatedly has affirmed the \n“actual use” principle. Consequently, it has failed to provide a reasoned explanation to deem \n“netting” rules as applied to retail BTMG unjust and unreasonable. \nIn prior decisions, the Commission has determined that “actual use” of the transmission \nsystem is a just and reasonable approach for assessing transmission charges that comports with \ncost causation. In approving the implementation of Order 2003, the Commission approved PJM’s \nretail BTMG tariff provisions as just and reasonable and not unduly discriminatory, finding that \nno transmission or distribution facilities are used to deliver from the generating unit to the load.64 \nIn fact, the PJM Tariff definition of “Behind the Meter Generation” reflects that fact, definitionally \nexcluding any generation that uses the transmission system.65  \nLater, in Occidental Chemical Corp. v. PJM Interconnection, L.L.C., the Commission \ndeclared that “[network] access charges for use of PJM’s transmission system should be allocated \nto network customers based on a network customer’s actual use of PJM’s system, consistent with \nthe principle of cost causation.”66 At issue in Occidental was PJM’s use of a cost-allocation \nmethodology that added the value of curtailed load back to a customer’s actual load to determine \nthe customer’s network access charge based on a customer’s coincident peak usage.67 The \n \n64 See PJM Interconnection, L.L.C., 107 FERC ¶ 61,113 at P 4 (2004) (“2004 BTMG Order”), reh’g denied, 108 \nFERC ¶ 61,302 (2004).  \n65 The PJM Operating Agreement and Reliability Agreement contain the same “Behind the Meter Generation” term. \nSee also PJM Manual 14G, Section 1.6 (explaining that Behind the Meter Generation “must deliver energy to load \nwithout using the Transmission System”). \n66 Occidental Chem. Corp. v. PJM Interconnection (“Occidental”), 102 FERC ¶ 61,275 at P 14 (emphasis added) \n(2003).  \n67 Id. at PP 1, 3-7."},{"page":36,"startToken":11914,"endToken":12220,"text":"36 \n \n \nCommission expressed concerns that this “calculation appeared inconsistent with the underlying \nrationale,” and that such an approach would discourage demand response from customers.68 PJM \nsought to defend the practice that the Commission ultimately found to be unjust and unreasonable \nby arguing that PJM’s infrastructure would still serve the customers.69 The Commission rejected \nthat contention and instead embraced a netting approach. In its order on rehearing, the Commission \nstated that the netting approach is “in the public interest because it ensures that PJM allocates its \ntransmission charges to those using the system on peak periods and helps ensure that customers \nhave incentives to curtail load during peak periods.”70  \nThis principle, articulated in Occidental, has also been affirmed more recently by the \nCommission. In a 2019 opinion, the Commission rejected proposed revisions by PJM to its Tariff \nand RAA regarding Price Responsive Demand (“PRD”). The Commission affirmed the holding in \nOccidental, stating that “if load is reduced during a peak period used for billing, that load reduction \nshould be credited consistent with principles of cost causation”—regardless of whether the \nreduction in load at the peak period was due to interruptible load reductions required by PJM or \nwas voluntary by the customer.71 \nFERC reaffirmed the principle articulated in Occidental and PJM Interconnection, L.L.C., \nyet again in a 2022 opinion that accepted tariff revisions proposed by ISO New England, Inc. \n(“ISO-NE”) and the Participating Transmission Owners Administrative Committee (PTOAC). In \nISO New Eng., Inc., the proposed tariff revisions modified the calculation of Monthly Regional \nNetwork Load (Monthly RNL) to exclude load served by behind-the-meter generation, which does \n \n68 Id. at P 4. \n69 Id. at PP 1, 7, 14. \n70 Id. at P 2. \n71 PJM Interconnection, L.L.C., Order Rejecting Tariff Revisions, 167 FERC ¶ 61,268, at P 23 (2019)."},{"page":37,"startToken":12220,"endToken":12544,"text":"37 \n \n \nnot participate in the ISO-NE wholesale markets as a Generator Asset, as well as the portions of a \nGenerator Asset utilized to net load at the same retail meter.72 FERC found this approach was just \nand reasonable because each Network Customer's net load is a reasonable approximation of its \nactual use of the transmission system and is in line with cost causation principles.73  \nThe Industrials recognize that the Commission is responding to the data center boom, \nwhich is driving both resource adequacy and transmission concerns. Prior to the data center boom, \n100 MW would have been seen as a very large load; now, however, hyperscale data centers can \nbe (and often are) several times that size. The Industrials recognize that the size and speed-to-\nmarket needs of certain large loads, such as data centers, have essentially added a new layer to the \ncost-causation analysis. The Commission may need to explore new ways to ensure true costs and \nbenefits are borne by these super-sized large-load entrants—for example, the ancillary services \ncost-allocation discussion in this docket (which the Industrials are not opposing in this pleading). \nThese efforts and similar ones may be necessary; however, abandoning the “net load” approach, \ngrounded in actual use, does not follow logic or precedent. The “actual use” principle is critically \nimportant to the calculation of billing determinants and the assessment of various Commission-\njurisdictional charges for transmission service. While the Commission clearly must respond to the \nunprecedented size and scale of the new loads, it must do so in a manner consistent with cost \ncausation.  \nUnfortunately, the design of the Co-Located Load Order creates an unreasonable split \nbetween those who manage costs by managing load and those who manage costs by investing in \ngeneration. It weakens customers' ability to manage peaks (by discounting offsetting generation \n \n72 ISO New Eng., Inc., Order Accepting Tariff Revisions, 178 FERC ¶ 61,086 at P 1 (2022). \n73 Id. at P 51."},{"page":38,"startToken":12544,"endToken":12860,"text":"38 \n \n \nbehind the meter), but it does not prevent massive hyperscalers (who may be able to shift \nprocessing to other regions) from managing peaks fully on the load side and thereby avoiding most \nNITS costs. In other words, the effect of the “gross load” approach is unduly discriminatory, \nbecause it allows “actual use” to govern transmission costs for some (i.e., load-only customers), \nbut not for others (i.e., those who have invested in retail behind-the-meter generation).74   \nUnfortunately, the Co-Located Load Order, by eliminating retail BTMG rules for an \nunknown portion of customers (depending on the selected size threshold), creates a lopsided \nstructure that allows peak management only for customers with load flexibility—not for customers \nthat have made massive capital investments in on-site generation assets. The PJM rules should \nencourage and incentivize such load flexibility by all customers, regardless of the manner in which \nit is accomplished.  \nEliminating netting from the NITS and capacity calculations is like throwing the baby out \nwith the bathwater—without solving potential cost shifts. As the Commission has long recognized, \n“It is long-established that the ‘primary aim’ [of the Federal Power Act] is the protection of \nconsumers from excessive rates and charges.”75 If standby fees or other charges need to be \nconsidered in accordance with cost-causation principles, the Commission may explore those. But \neliminating altogether the assessment of charges based on “actual use” is unduly discriminatory \nand fails to reckon with well-established Commission precedent.  \n \n74 If the New Services are extended to all Eligible Customers, customers that do have load flexibility will be permitted \nto elect how much transmission and capacity they require for their business. This option may avoid both cost \nuncertainty and cost shifting, as customers opting into these services will focus on maintaining operations within the \ncontracted amounts. \n75 Xcel Energy Services v. FERC, 815 F.3d 947, 952-53 (D.C. Cir. 2016) (emphasis added)."},{"page":39,"startToken":12860,"endToken":13236,"text":"39 \n \n \n5. The Co-Located Load Order errs by failing to explain and justify the \nCommission’s assertion of jurisdiction over retail BTMG that merely offsets retail \nload. \nAs acknowledged by the Commission, pursuant to Sections 201 and 205 of the FPA, the \nCommission’s jurisdiction includes the “transmission of electric energy in interstate commerce \nand … the sale of electric energy at wholesale in interstate commerce.”76 Within these \njurisdictional limits, the Commission has been charged by Congress with ensuring just and \nreasonable rates.77 Consequently, any regulations the Commission fashions must be based on its \nstatutory authority over interstate transmission and wholesale sales.78  \nTo accomplish a durable result that stands the test of time, the Commission should ensure \nthat its holding respects federal-state jurisdictional authority as set forth in the Federal Power Act. \nThe Order affirms Commission jurisdiction “to oversee the interconnection of generating facilities \nto the interstate transmission system, including where generators serve Co-Located Load.”79 \nHowever, the Commission “decline[d] in this proceeding to comprehensively address \njurisdictional matters regarding the interconnection of retail loads served through a Co-Location \nArrangement to the interstate transmission system.”80  \n \n76 16 U.S. Code § 824(b). See also 16 U.S. Code § 824(a); Nat’l Ass’n of Regul. Util. Commissioners v. FERC, 964 \nF.3d 1177, 1181 (D.C. Cir. 2020) (Under the FPA “Congress gives the Federal Energy Regulatory Commission \nexclusive authority over the regulation of ‘the sale of electric energy at wholesale in interstate commerce,’ including \nboth wholesale electricity rates and any rule or practice “affecting” such rates,’ along with ‘jurisdiction over all \nfacilities for such transmission or sale of electric energy.’”). \n77 16 U.S. Code § 824d(a). As stated by Section 205(a) of the FPA:   \nAll rates and charges made, demanded, or received by any public utility for or in connection with \nthe transmission or sale of electric energy subject to the jurisdiction of the Commission, and all rules \nand regulations affecting or pertaining to such rates or charges shall be just and reasonable, and any \nsuch rate or charge that is not just and reasonable is hereby declared to be unlawful. \n78 16 U.S. Code § 824(b)(1). \n79 Co-Located Load Order at P 171. \n80 Co-Located Load Order at P 170."},{"page":40,"startToken":13236,"endToken":13570,"text":"40 \n \n \nMore significantly, the Commission blurs the distinction between Co-Located Load and \nretail BTMG and does not offer a reasoned explanation of the basis of its jurisdiction over activity \nbehind a customer’s meter that is wholly retail in nature. By definition, BTMG is produced by a \ngeneration unit “that delivers energy to load without using the Transmission System.”81 This aspect \nof the definition takes retail BTMG out of the Commission’s jurisdiction over the transmission of \nelectric energy in interstate commerce. Further, retail BTMG “does not include (i) at any time, any \nportion of such generating unit’s capacity that is designated as a Generation Capacity Resource; \nor (ii) in an hour, any portion of the output of such generating unit that is sold to another entity for \nconsumption at another electrical location or into the PJM Interchange Energy Market.” This \naspect of the definition excludes retail BTMG from the Commission’s jurisdiction over sales of \nelectric energy for resale in interstate commerce.  \nThe Industrials recognize the Commission’s practical concern about the PJM transmission \nsystem needing to account for super-sized loads that may appear quickly or suddenly on the \nsystem, and the Commission may have jurisdiction to address those concerns to the extent that \nthey directly impact the interstate transmission system. However, the Commission’s directed \nsolution extends beyond its jurisdictional reach when applied to certain behind-the-meter \nconfigurations of retail customers. The Commission’s directive necessarily entails piercing the \nretail meter veil, which serves as the bright-line boundary of the Commission’s statutory \nauthority—an intrusion that the Commission should reject. \nThe Commission has neglected to provide a well-reasoned basis for its assertion of \njurisdiction over the behind-the-meter configurations of retail customers whose BTMGs are not \n \n81 PJM Tariff, Section 1 (Definitions). BTMG also does not deliver energy to load using any distribution facilities \n“unless the entity that owns or leases the distribution facilities has consented to such use of the distribution facilities \nand such consent has been demonstrated to the satisfaction of the Office of the Interconnection.” Id."},{"page":41,"startToken":13570,"endToken":13985,"text":"41 \n \n \nselling wholesale power and are not using the transmission system,82 whose retail service is a state-\nregulated part of the electric system. Further, the Commission also acknowledged in the Show \nCause Order that the FERC has not historically exercised jurisdiction over any and all \ntransmission-level interconnections of retail load.83 As stated in the Show Cause Order: \n[T]he Commission has exclusive authority over the rates, terms, and conditions for \nthe sales from generating resources used to serve co-located loads, as well as the \npractices directly affecting such sales, provided that they are sales for resale in \ninterstate commerce. If they are not sales for resale—that is, if they are made \ndirectly to the end-use consumer—or if they are not in interstate commerce then the \nco-located generator’s sales are under state jurisdiction.84  \nIn National Association of Regulatory Utility Commissioners (“NARUC”) v. FERC, the \nD.C. Circuit upheld the FERC’s asserted authority over generation interconnections in Order No. \n2003 because it “applies to jurisdictional transactions only.”85 In other words, the essential purpose \nof a generator interconnection—to transmit power and sell it at wholesale—was squarely in line \nwith the FERC’s clear jurisdiction to regulate the transmission and wholesale sales of power. The \nD.C. Circuit contrasted its holding in NARUC with its decision in Detroit Edison, where the D.C. \nCircuit rejected the FERC’s attempt to assert jurisdiction over unbundled retail service.86 In Detroit \nEdison, the FERC had attempted to assert jurisdiction where “such service involved neither \njurisdictional sales nor jurisdictional transmission.”87 In this case, retail BTMG involves neither \n \n82 Some retail BTMG arrangements do make wholesale power sales, which are under FERC jurisdiction. For example, \ncogeneration QFs generally size their generation to satisfy their thermal needs, which may result in energy beyond the \nretail customer’s requirements. In some cases, the retail customer can sell its excess energy to the local utility under \nSection 210 of PURPA. In other instances, the retail customer must secure market-based rate authority from the \nCommission and a three-party interconnection service agreement or wholesale market participant agreement with PJM \nand the applicable utility. \n83 Show Cause Order at P 72. \n84 Show Cause Order at P 71. \n85 Nat’l Ass’n of Regul. Util. Comm’rs v. FERC (“NARUC”), 475 F.3d 1277, 1280 (D.C. Cir. 2007). \n86 Detroit Edison Co. v. FERC, 334 F.3d 48, 53 (D.C. Cir. 2003). \n87 NARUC at 1280 (explaining the court's holding in Detroit Edison)."},{"page":42,"startToken":13985,"endToken":14277,"text":"42 \n \n \njurisdictional sales nor jurisdictional transmission. Detroit Edison, and the provisions of the FPA \nthat it interprets, should control. \nThe Commission has not articulated a clear basis for its jurisdictional determination \nregarding retail BTMG, which, by definition, neither uses the transmission system nor provides \nelectric energy for resale. The Industrials respectfully request rehearing on this issue. \n6. The Co-Located Load Order’s megawatt-based applicability threshold, transition \nperiod, and grandfathering provision fail to correct the defects created in the \nOrder.  \nIn the Order, the Commission requires PJM to “propose a new MW threshold for the \namount of load at a particular electrical location that Network Customers may net by using \nBTMG,” and such threshold “should reduce the reliability and resource adequacy risks . . . that \nlarge loads may pose to PJM, while also allowing for Network Customers to reduce their \ntransmission charges in a transparent, not unduly discriminatory fashion.”88 While the Industrials \nwelcome exemptions as helpful in light of the overall removal of netting rules, they are the \nexception that proves the rule.  \nSetting an arbitrary megawatt-based threshold may yield unintended consequences that \ncontradict the Commission’s overall goals for resource adequacy, cost causation, and just and \nreasonable rates. For example: \n Setting an arbitrary limitation creates perverse incentives to size on-site generation \nprojects smaller. If the limit is 50 MW, a customer with a planned project of 75 MW \nof generation may downsize to comply with the retail BTMG rules—reducing \ngeneration investment and increasing reliance on external (and currently inadequate) \ncapacity resources. \n \n Establishing a bright-line threshold risks being challenged as unduly discriminatory, \nunless it is clearly grounded in the FERC’s authority to regulate the transmission of \nelectric energy in interstate commerce or in a reasonable connection to cost-causation \n \n88 Co-Located Load Order at P 221."},{"page":43,"startToken":14277,"endToken":14643,"text":"43 \n \n \nprinciples. Neither a MW-based threshold nor a grandfathering provision correct \njurisdictional deficiencies. \n \n More broadly, the projected transmission challenges and looming resource adequacy \ncrisis are primarily driven by substantially larger facilities than 10 MW or 20 MW. The \nIndustrial Customer Organizations believe a 20 MW limit is far too low and would \ncapture a significant number of manufacturing entities and other industrial and \ninstitutional organizations that have reliably provided on-site generation for many \nyears. \n \nThese are all issues of concern with an arbitrary MW-based threshold, untethered to any \njurisdictional limits. Rather than an arbitrary threshold, the Commission should maintain its \ntraditional netting approach but find alternative means to ensure that standby or backup costs are \naddressed for very large loads—that is, loads that can cause reliability challenges for the grid if \nthey suddenly come online.89 \nHowever, if the Commission maintains a “gross load” approach and pursues a mandatory \nthreshold, as suggested in the Order, it should choose a multi-pronged threshold aligned with the \nkey drivers of current transmission demand and the reliability risks posed. First, the Commission \nshould act in accordance with Congress’s express policy in PURPA and exempt all cogeneration \nQFs from the “gross load” rules. As explained above, PURPA states Congress’s goal of \nencouraging cogeneration and small power production.  \nSecond, if the Commission determines it must establish a megawatt-based threshold, it \nshould base that threshold at a high enough level to permit traditional manufacturers and industrial \nloads to continue netting. Drawing on PURPA as an example, QFs other than cogeneration \n \n89 The North American Electric Reliability Council (“NERC”) has been undertaking efforts to develop standards for \nnew large loads. In a July 2025 white paper, Characteristics and Risks of Emerging Large Loads, NERC defined large \nload as “[a]ny commercial or industrial individual load facility or aggregation of load facilities at a single site behind \none or more point(s) of interconnection that can pose reliability risks to the [Bulk Power System] due to its demand, \noperational characteristics, or other factors.” Characteristics and Risks of Emerging Large Loads, NERC at p. 1 (July \n2025), \navailable \nat \nhttps://www.nerc.com/globalassets/who-we-are/standing-committees/rstc/whitepaper-\ncharacteristics-and-risks-of-emerging-large-loads.pdf (last accessed Jan. 16, 2026)."},{"page":44,"startToken":14643,"endToken":14810,"text":"44 \n \n \nfacilities have 80 MW limits. Cogeneration facilities have no size limit but must meet certain \nefficiency requirements to qualify as QFs. The Industrials believe that a threshold of 200 MW \nwould, as a practical matter, permit most existing industrial and institutional loads to continue to \nbenefit from the major energy investments they have made over decades, consistent with the \n“actual use” principle. As super-sized loads are a largely new phenomenon, the number of entities \nrequiring grandfathering of existing contracts and facilities would be far more limited at a 200 \nMW threshold.  \nAmerican industry is a vital part of the nation’s electric grid. While the Commission’s \nOrder provides some positive movement, without modification or clarification on certain key \nissues, it threatens to harm American industry, weaken resource adequacy, and result in undue \ndiscrimination. The Industrials respectfully request that the Commission consider its Request for \nClarification or, in the Alternative, Rehearing and address the concerns raised herein, leading to a \nbetter and more durable resolution of relevant issues."},{"page":45,"startToken":14810,"endToken":14912,"text":"45 \n \n \nVII. \nCONCLUSION \nWHEREFORE, the PJM Industrial Customer Coalition and the Industrial Energy \nConsumers of America respectfully request that the Commission clarify the Co-Located Load \nOrder as set forth herein, or, alternatively, grant rehearing of the Co-Located Load Order for the \nreasons set forth herein.   \n \n \n \n \n \nRespectfully submitted, \n \nBy: \n/s/ Susan E. Bruce \n \n \n \nSusan E. Bruce \nKenneth R. Stark \nMatthew L. Garber \nMcNees Wallace & Nurick LLC  \n100 Pine Street \nHarrisburg, PA  17101 \nTel:  717-232-8000 \nE-mail: sbruce@mcneeslaw.com \nE-mail: kstark@mcneeslaw.com \nE-mail: mgarber@mcneeslaw.com \n \nCounsel to the PJM Industrial Customer Coalition \nand Industrial Energy Consumers of America \n \nDated: January 20, 2026"},{"page":46,"startToken":14912,"endToken":14975,"text":"CERTIFICATE OF SERVICE \n \nI hereby certify that I have this day served via first-class mail, electronic transmission, or \nhand-delivery the foregoing upon each person designated on the official service list compiled by \nthe Secretary in this proceeding.  \nDated this 20th day of January, 2026. \n \n \n     /s/ Matthew L. Garber \n \n \nMatthew L. Garber \n100 Pine Street \nHarrisburg, PA  17101 \nTel:  717-232-8000 \nE-mail: mgarber@mcneeslaw.com"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":1,"endAt":993,"startToken":0,"endToken":119},{"p":1,"at":993,"title":"I. INTRODUCTION","method":"printed heading","endPage":2,"endAt":1525,"startToken":119,"endToken":426},{"p":2,"at":1525,"title":"II. THE CRITICAL ISSUE: EXECUTIVE SUMMARY","method":"printed heading","endPage":7,"endAt":1660,"startToken":426,"endToken":1941},{"p":7,"at":1660,"title":"III. STATEMENT OF ISSUES/ERRORS FOR ALTERNATIVE REHEARING","method":"printed heading","endPage":8,"endAt":1257,"startToken":1941,"endToken":2183},{"p":8,"at":1257,"title":"IV. PROCEDURAL HISTORY","method":"printed heading","endPage":9,"endAt":1181,"startToken":2183,"endToken":2543},{"p":9,"at":1181,"title":"V. REQUEST FOR CLARIFICATION","method":"printed heading","endPage":10,"endAt":8,"startToken":2543,"endToken":2636},{"p":10,"at":8,"title":"A. Issue #1. The Industrials seek clarification on whether cogeneration QFs under","method":"printed heading","endPage":13,"endAt":312,"startToken":2636,"endToken":3717},{"p":13,"at":312,"title":"B. Issue #2. The Industrials seek clarification that PJM’s new transmission services","method":"printed heading","endPage":15,"endAt":474,"startToken":3717,"endToken":4375},{"p":15,"at":474,"title":"C. Issue #3. The Industrials seek clarification that the removal of “netting” rules for","method":"printed heading","endPage":16,"endAt":617,"startToken":4375,"endToken":4722},{"p":16,"at":617,"title":"D. Issue #4. The Industrials seek clarification that any retail BTMG applicability","method":"printed heading","endPage":17,"endAt":507,"startToken":4722,"endToken":5064},{"p":17,"at":507,"title":"VI. REQUEST FOR REHEARING","method":"printed heading","endPage":17,"endAt":645,"startToken":5064,"endToken":5083},{"p":17,"at":645,"title":"A. STATEMENT OF ISSUES / SPECIFICATION OF ERRORS","method":"printed heading","endPage":19,"endAt":298,"startToken":5083,"endToken":5932},{"p":19,"at":298,"title":"B. ARGUMENT","method":"printed heading","endPage":45,"endAt":8,"startToken":5932,"endToken":14811},{"p":45,"at":8,"title":"VII. CONCLUSION","method":"printed heading","endPage":46,"endAt":0,"startToken":14811,"endToken":14912},{"p":46,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":46,"endAt":439,"startToken":14912,"endToken":14975}]}