{"document":{"slug":"rec-20260120-5293","title":"Public Interest Organizations submit Limited Request for Clarification of the 12/18/2025 Order","issued":"2026-01-20","accession":"20260120-5293","docket":"EL25-49-002","group":"PJM co-location compliance","filer":"EARTHJUSTICE","kind":"rehearing request","file":"sources/filings/text/20260120-5293_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260120-5293","tier":"record","sha256":"53fc7945f7d8b33aae6ea405a83f6df78928135cbacfe7cad9c8670b3e2798a2","pages":10,"tokens":2990,"emptyPages":[],"textThemes":["registry","adequacy","colo","study"]},"pages":[{"page":1,"startToken":0,"endToken":310,"text":"1 \n \nUNITED STATES OF AMERICA \nBEFORE THE  \nFEDERAL ENERGY REGULATORY COMMISSION  \n \n \n \n \n \n \n \n \n) \nPJM Interconnection, et al.   \n)  \nDocket No. EL25-49-000, et al. \n \n \n \n \n \n \n) \n \n \n \nLIMITED REQUEST FOR CLARIFICATION OF PUBLIC INTEREST \nORGANIZATIONS \n \nPursuant to Section 313 of the Federal Power Act (“FPA”),1 and Rules 212 \nand 713 of the Commission’s Rules of Practice and Procedure,2 Earthjustice, \nEnvironmental Defense Fund, and Sierra Club (Public Interest Organizations) \nrequest clarification of the Commission’s December 18, 2025 order in the above-\ncaptioned proceeding, 193 FERC ¶ 61,217 (2025) (“Order”), pursuant to the reasons \nmore fully described below. \n \nI. \nBackground \n \nLast February, the Commission took on the tough task of prompting PJM to \nrevisit its processes for addressing large load arrangements.3  As part of the show \ncause proceeding, the Commission sought feedback from PJM and stakeholders on \nover thirty comprehensive briefing questions covering topic areas that required \nfurther clarity to support colocation arrangements, including cost allocation for \ntransmission service4 and resource adequacy concerns, such as whether PJM should \nconsider changes to its “planning processes” or “load forecasting methods” to “better \nplan for and address resource adequacy and reliability impacts of co-location \narrangements.”5 \n \nThe Commission’s Show Cause Order specifically asked whether PJM should \n“consider changes to load forecasting methods, informational postings, or the \nreserve margin study process to better plan for and address the resource adequacy \nand reliability impacts of co-location arrangements.”6 As further detailed below, on \n \n1 16 U.S.C. § 825l. \n2 18 C.F.R. §§ 385.212, 385.713. \n3 PJM Interconnection, L.L.C., 190 FERC ¶ 61,115 (2025) (Show Cause Order).  \n4 Show Cause Order P 88, b.i – b.iv. \n5 Id. P 88, e.v.  In addition, the Commission consolidated with this proceeding the \nrecord from the technical conference in Docket No. AD24-11-000 and Constellation’s \ncomplaint in Docket No. EL25-20-000. \n6 Show Cause Order P 88 (e)(v)."},{"page":2,"startToken":310,"endToken":672,"text":"2 \n \nApril 23, 2025, Public Interest Organizations (PIOs) filed comments that \ncomprehensively responded to, among other things, this question.7 On September \n18, 2025, Commissioner Rosner issued a follow-up letter to PJM specifically \nrequesting information relating to PJM’s existing process and future expectations \nregarding its load forecasting process.8 PJM responded to that letter on October 17, \n2025.9 \n \nBased on the responses to its Show Cause Order, the Commission issued a \ndecision on December 18, 2025.10  While we agree that the Order takes several \nmeasures to ensure that rates are just and reasonable for consumers,11 it is unclear \nhow the timing and format of some of the measures will serve their stated purpose, \nand if so, whether they will be implemented in a timely manner.  As explained in \nour response, certain prerequisite revisions to PJM’s planning processes, like \nreformed load forecasting procedures, are necessary before PJM can serve large \nloads using its existing transmission services and its processes for forecasting \ncapacity market demand and planning regional transmission projects (RTEP) while \nmaintaining rates that are just and reasonable.12 \n \nII. \nLimited Request for Clarification \n \nA. We request clarification on how the rates for PJM’s \nCommission-jurisdictional services will be just and \nreasonable during the interim period before PJM \nimplements procedures to avoid using speculative load \ninformation \n \n1. Accurate demand forecasts are needed to support imminent \nphases of PJM’s next capacity market and RTEP processes \nPJM’s RTEP and capacity market processes are in the midst of using PJM’s \nload forecasts to plan system needs that will drive energy infrastructure \ninvestments and impact wholesale electricity rates.  PJM is preparing to hold the \n \n7 See generally Public Interest Organizations, Comments, Docket No. EL25-49-000, \nat 15-24 (filed Apr. 23, 2025) (hereinafter “PIO Comments”). \n8 See Commissioner Rosner, Letter to PJM, Docket Nos. EL25-49, et al. (Sept. 18, \n2025) (“Rosner Letter”). \n9 See Asthana, Manu, Letter in Response, Docket No. EL25-49, et al., (Oct. 17, \n2025), available at: https://www.ferc.gov/media/pjm-response-chairman-david-\nrosners-09192025-letter-re-large-load-forecasting-americas. (“PJM October Letter”). \n10 PJM Interconnection, L.L.C., 193 FERC ¶ 61,217 (2025) (Order). \n11 Order P 162; see also Rosner Concurrence P 1. \n12 PIO Comments at 6, 20."},{"page":3,"startToken":672,"endToken":1068,"text":"3 \n \nnext Base Residual Auction in June 2026.13  The auction will rely in part on PJM’s \ndemand forecast.  With respect to the RTEP, PJM will use data that it gathers from \nNovember 2025 through March 2026 to build base case modeling assumptions and \nperform initial case reviews.14  And from March 2026 to June 2026, PJM expects to \nperform its RTEP baseline studies,15 which will inform the transmission projects \nthat will be available in the competitive bidding window that PJM expects to open \nin July 2026. \n2. Without a specific directive, PJM is not likely to resolve the \nissues with its forecasting process in a timely manner \nIn the Order, the Commission did not directly address the load forecasting \nissues raised in the record; however, the Commission did require PJM to provide an \ninformational filing that includes, among other things, an update regarding the \ndevelopment of “enhanced load forecasting.”16 Here, we request clarification \nregarding how the Commission intends to respond to, or otherwise use, the \ninformation provided in the record, and any additional information provided by \nPJM pursuant to the Commission’s request in any subsequent order related to this \nseries of dockets.17 The issues raised by PIOs merit immediate consideration \nbecause of the way in which large load forecasting impacts whether the outcome of \nthe newly proposed colocation transmission service pathways ultimately result in \nrates that are just and reasonable. \nSpecifically, in our comments we noted that, “PJM’s Tariff is unjust and \nunreasonable because it lacks sufficient controls and standards to ensure large load \nforecast accuracy and to protect against speculative large load forecast estimates.”18 \nWe argued that “PJM’s large load forecasting process does not substantively \naccount for speculative load additions, thus rendering the process and resulting \nforecast, as well as everything that relies on that forecast, unjust and \n \n13 PJM Interconnection, L.L.C., News Release, at 4 (Dec. 17, 2025), \nhttps://www.pjm.com/-/media/DotCom/about-pjm/newsroom/2025-\nreleases/20251217-pjm-auction-procures-134479-mw-of-generation-resources.pdf. \n14 Yiming Mao, PJM Interconnection, L.L.C., Review of 2026 RTEP Assumptions, at \n3 (Jan. 6, 2026), https://www.pjm.com/-/media/DotCom/committees-\ngroups/committees/teac/2026/20260106/20260106-item-08---2026-rtep-\nassumptions.pdf. \n15 Id.   \n16 Order P 238. \n17 Note the Commission has stated that it “will not act on or notice this \ninformational Filing.” Order P 238, n.486. \n18 PIO Comments at 15."},{"page":4,"startToken":1068,"endToken":1471,"text":"4 \n \nunreasonable,” and also that PJM’s failure to include the provisions governing large \nload forecasting in the PJM Tariff violates the Commission’s Rule of Reason.19   \nPJM’s load forecasting procedure can largely be found on three pages in PJM \nManual 19, attachment B.20 We identified four primary problems with PJM’s \ncurrent process. First, the LSE/EDCs in PJM report their large load forecasts in \ncompletely different ways, posing a substantial gradient in uncertainty based on the \nstandards and criteria each participant uses in submitting its forecast to PJM.21 \nSecond, PJM has no way to cross-check whether a data center in, for example, \nExelon’s service territory has also made the same proposal in Dominion’s territory, \nand both proposals end up in PJM’s forecast even though only one will be built.22 \nThird, PJM’s process has no way to timely ensure that large data center \ncancellations are quickly identified and incorporated into PJM’s forecasts.23 Lastly, \nwe contend that because PJM’s large load forecasting processes are not codified in \nPJM’s Tariff, and they directly and significantly affect rates for jurisdictional \nCommission services, their omission violates the Commission’s Rule of Reason.24 We \npredicted that the combination of these four problems will necessarily result in \nhighly uncertain, and likely inflated load forecasts that will result in unjust and \nunreasonable rates. \nIn addition to the question posed in the Show Cause Order, as noted above, \nCommissioner Rosner submitted a letter to PJM on September 18, 2025, noting that \n“we cannot efficiently plan the electric generation and transmission needed to serve \nnew customers if we don’t forecast how much energy they will need as accurately as \npossible.”25 Commissioner Rosner then posed a series of questions for PJM to \nanswer that are largely consistent with the issues raised in PIOs’ comments: \n(1) How do you, the utilities in your footprint, and state regulators obtain \ninformation that verifies when and whether prospective large loads in your \nregion will reach commercial operation?  \n(2) To what extent are prospective large load requests subject to consistent, \nobjective screening criteria before they are included in the load forecast?  \n(3) How do you forecast how the actual electricity consumption of a large load \nwill compare to its requested level of interconnection service?  \n \n19 Id. \n20 PJM Manual 19, Attach. B, at 26-28. \n21 PIO Comments at 17. \n22 Id. \n23 Id. at 18-19. \n24 Id. at 20. \n25 Rosner Letter at 1."},{"page":5,"startToken":1471,"endToken":1843,"text":"5 \n \n(4) How do you coordinate with utilities at the regional or interregional level \nto share best practices on large load forecasting and ensure that large load \ninterconnection requests are not double-counted?26 \n \n \nOn October 17, 2025, PJM responded to Commissioner Rosner’s letter.27 PJM \nalso indicated that it has adopted a Load Adjustment Request Implementation \ndocument that “offers enhanced transparency about PJM’s load adjustment request \nsubmission process in PJM Manual 19, Attachment B.”28 With regard to PIOs’ \ncomments, while the document specifies generally what types of information PJM \ndesires from forecast submitters and explains a basic weighting criteria, it expressly \ndoes not require or “specify a particular methodology for forecasting large loads.”29 \nWithout a clear methodology, LSE/EDCs will continue to report data with widely \nvarying accuracy, which will necessarily result in uncertain forecasts. \nCommissioner Rosner also asked PJM to respond to the concern of double-counting \nof data centers; however, PJM’s response does not identify a concrete way in which \nit is currently, or plans to in the future, address this issue. Instead, it merely \nconcludes that PJM “looks forward to continued collaboration with its stakeholders . \n. . to pursue additional enhancements and opportunities for consistency across the \nregion.”30 This response is not sufficient to address this well-known issue across the \nindustry.31 Additionally, nothing in PJM’s response addresses the need for more \ntimely updates to the load forecasting process in PJM. Considering the way in \nwhich significant load proposals are dropped, or added, PJM needs a more dynamic \napproach for updating the load forecasts to reflect the current state of demand.32 \nThus, it is unclear how the informational report on PJM’s activities that the \nCommission directed in the Order will ensure PJM implements needed \nimprovements to its process in a timely manner.  \n3.  The inaccuracy of PJM’s demand forecasting was recently \ndemonstrated  \n \n26 Id. at 2. \n27 See generally PJM October Letter. \n28 Id. at 2. \n29 PJM Interconnection, L.L.C., Load Adjustment Request Implementation, PJM \nResource Adequacy Planning Department (July 1, 2025; revised Aug. 26, 2025), \navailable at: https://www.pjm.com/-/media/DotCom/committees-\ngroups/subcommittees/las/postings/load-adjustment-request-implementation.pdf. \n30 PJM October Letter at 6. \n31 PIO Comments at 17-18. \n32 Id. at 18."},{"page":6,"startToken":1843,"endToken":2253,"text":"6 \n \n \nUnfortunately, PIOs’ concerns regarding the accuracy of PJM’s load forecasts \nhave recently been actualized. PJM’s recent announcements call into question the \naccuracy of the inputs to PJM’s most recent capacity market auction and related \nwholesale electricity market rates as well as its transmission planning models.   \nShortly after PJM’s 2027/2028 Base Residual Auction, Stu Bresler, PJM’s former \nExecutive Vice President of Market Services and Strategy, indicated during a press \nconference that the 2026 Forecast would likely reflect a decrease in forecasted load \nfor that time period since PJM is revising its process for implementing load \nadjustments.33  However, that course correction came too late for ratepayers. As a \nreminder, the 2027/2028 auction resulted in a capacity shortfall and “record [high] \nprices” in part due to the projected demand, which included 5,100 MW for data \ncenters.  Regarding the next auction, PJM Chief Operating Officer Stu Bresler said \nthat “PJM’s overall power demand forecast for the year beginning in mid-2027 will \nbe ‘appreciably lower’ than current projections.”34  According to PJM’s most recent \n2026 PJM Load Forecast Report, its most recent analysis has “brought large load \nadjustments down in the near-term forecast years compared to the 2025 Long-Term \nLoad Forecast.”35  \nState representatives and industry experts are also sounding the alarms.36 \nFormer NARUC President, Travis Kavula, has stated that despite PJM now \n“applying a scintilla of judgment,” its forecast “remains a colossal act of \nspeculation.”37 Considering that PJM uses its load forecasts to essentially set the \ndemand curve for capacity obligations, for reliability studies, and to support the \n \n33 Devin Leith-Yessian, PJM Capacity Auction Clears at Max Price, Falls Short of \nReliability Requirement, (December 17, 2025), https://www.rtoinsider.com/121911-\npjm-capacity-auction-clears-max-price-falls-short-reliability-requirement/. \n34 Behr, Peter, PJM to ratchet down projected AI power demand for eastern US, \nEnergy Wire, available at: \nhttps://subscriber.politicopro.com/article/eenews/2026/01/06/pjm-to-ratchet-down-\nprojected-ai-power-demand-for-eastern-us-00711947. \n35 PJM Load Forecast Report, PJM (January 14, 2026), at 4, available at: \nhttps://www.pjm.com/-/media/DotCom/library/reports-notices/load-forecast/2026-\nload-report.pdf. \n36 John D. Wilson, et al, Energy Systems Integration Group Large Load Task Force, \nForecasting for large Loads, Current Practices and Recommendations, at 2-5 and 68 \nhttps://gridstrategiesllc.com/wp-content/uploads/ESIG-Large-Loads-Forecasting-\nreport-2025.pdf (“The massive scale of anticipated large load growth—for individual \nfacilities and collectively  within and across regions—increases the reliability  and \nfinancial consequences of load forecast errors.” \n37 See https://x.com/TKavulla/status/2011885773663191205?s=20"},{"page":7,"startToken":2253,"endToken":2646,"text":"7 \n \nRTEP,38 and those forecasts have been shown to be “appreciably,” and possibly \n“colossally” inaccurate, how can the resulting rates from these processes be just and \nreasonable without significant revisions to PJM’s process? \n \nWe request clarification regarding how the Commission intends to use the \ninformational report directed in its Decision,39 and further request that any \nsubsequent order from the Commission address the issues raised in the record \nregarding the continuing and ongoing deficiencies in PJM’s large load forecasting \nprocess. \nB. Evaluating whether the status quo transmission rate design \nfor large load customers is still just and reasonable \nGiven the unprecedented volume and scale of large-load requests, the \nCommission should evaluate whether existing transmission rate designs remain \njust and reasonable. In the Order, the Commission determined that co-located load \npaying for NITS service would be responsible for costs that are at least \"roughly \ncommensurate\" with benefits because zonal NITS rates include upgrades and \noperations and maintenance costs.40 However, this rate design relies on a standard \nthat assumes load growth is incremental and widely distributed. \nThe practical reality is that discrete large-load pockets trigger multi-million-\ndollar reliability solutions. Because customers pay only in proportion to billing \ndeterminants (usage shares) rather than incremental costs triggered, a significant \n“payer gap” can emerged. Under Schedule 12 of the PJM Tariff, a substantial share \nof the revenue requirement for RTEP projects are allocated regionally through the \nTransmission Enhancement Charge.41 For example, the Mars-Golden-Lockridge \nComplex (2022 RTEP Window 3) is now estimated at $725.3M following April 2025 \nscope updates. Under a 7% load-share illustrative, the triggering load pays only \n$50.8M, leaving $674.5M to be socialized among other customers.  \nThe gap is even more pronounced in the Southern Cluster / “Kraken” \npackage—a $5.08B portfolio centered on a 185-mile undergrounded HVDC line \napproved in the 2024 RTEP Window 1 to serve “Data Center Alley.”42 If a 1,000 MW \n \n38 PJM Manual 19, at 12, available at https://www.pjm.com/-\n/media/DotCom/documents/manuals/m19.pdf. \n39 Order P 238, n.486 (noting the Commission “does not intend to act on or notice \nthis informational filing”). \n40 Order P 198. \n41 PJM Open Access Transmission Tariff (OATT) Network Integration Transmission \nService (NITS) & Zonal Rates Schedule 9: Network Integration Transmission \nService Schedule 12: Charges for Required Transmission Enhancements. \n42 PIO Comments at 13."},{"page":8,"startToken":2646,"endToken":2890,"text":"8 \n \ndata center represents 7% of the zone’s peak determinants, it contributes only \n$203M, leaving a $4.877B gap for unrelated regional and zonal customers.  \nThe Commission has already recognized the need for a departure from the \nstatus quo allocation in other contexts. In its October 10, 2025 approval of SPP’s \nProvisional Load Process (Docket No. ER25-2430), the Commission accepted a cost \ncausation approach that initially assigns upgrade costs to transmission customers \nto protect existing users from “the uncertain nature of load and generation \nadditions.”43  \nAccordingly, we request that the Commission clarify how “roughly \ncommensurate” is evaluated when a discrete driver’s pro-rata contribution is \ndwarfed by the multi-billion-dollar infrastructure it necessitates. Furthermore, the \nCommission should direct PJM and its Transmission Owners to provide \ntransparent reporting for major projects that explicitly compares incremental cost \ncausation against pro-rata billing determinant recovery, ensuring the resulting \nallocation is not unjust and unreasonable, or unduly discriminatory or preferential.  \nIII. \nConclusion \nFor the foregoing reasons, Earthjustice, Environmental Defense Fund, and \nSierra Club respectfully request that the Commission clarify its December 18, 2025 \nOrder. \nDated: January 20, 2026  \n \nRespectfully submitted, \n/s/ Christine Powell \nChristine Powell \nEarthjustice \n180 Steuart St. #194330 \nSan Francisco, CA 94105 \nTelephone: (415) 217-2091 \nEmail: cpowell@earthjustice.org \n \n/s/ Aaron Stemplewicz \nAaron Stemplewicz  \nEarthjustice \n1617 John F. Kennedy Blvd., Suite 2020 \nPhiladelphia, PA 19103 \nTelephone: (917) 628-7411 \nEmail: astemplewicz@earthjustice.org \n \n/s/ Ted Kelly \n \n43  Southwest Power Pool, Inc., 193 FERC ¶ 61,018, at P 57 (2025)."},{"page":9,"startToken":2890,"endToken":2929,"text":"9 \n \nTed Kelly \nEnvironmental Defense Fund \n555 12th St. NW Suite 400 \nWashington, DC 20004 \nTelephone: (202)572-3317 \ntekelly@edf.org \n \n/s/ Justin Vickers \nJustin Vickers \nSenior Attorney \nSierra Club \nChicago, IL \nTelephone: (224) 420-0614 \njustin.vickers@sierraclub.org"},{"page":10,"startToken":2929,"endToken":2990,"text":"10 \n \nCERTIFICATE OF SERVICE \n \nThe undersigned certifies that a copy of this filing has been served this day \nupon each person designated on the official service list compiled by the Secretary in \nthis proceeding. \n \nDated: January 20, 2026. \n/s/ Aaron Stemplewicz \nAaron Stemplewicz  \nEarthjustice \n1617 John F. Kennedy Blvd., Suite 2020 \nPhiladelphia, PA 19103 \nTelephone: (917) 628-7411 \nEmail: astemplewicz@earthjustice.org"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":1,"endAt":683,"startToken":0,"endToken":91},{"p":1,"at":683,"title":"I. Background","method":"printed heading","endPage":2,"endAt":1195,"startToken":91,"endToken":491},{"p":2,"at":1195,"title":"II. Limited Request for Clarification","method":"printed heading","endPage":2,"endAt":1237,"startToken":491,"endToken":496},{"p":2,"at":1237,"title":"A. We request clarification on how the rates for PJM’s","method":"printed heading","endPage":7,"endAt":557,"startToken":496,"endToken":2334},{"p":7,"at":557,"title":"B. Evaluating whether the status quo transmission rate design","method":"printed heading","endPage":8,"endAt":1125,"startToken":2334,"endToken":2800},{"p":8,"at":1125,"title":"III. Conclusion","method":"printed heading","endPage":10,"endAt":6,"startToken":2800,"endToken":2930},{"p":10,"at":6,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":10,"endAt":428,"startToken":2930,"endToken":2990}]}