{"document":{"slug":"rec-20260120-5298","title":"Constellation Energy Generation, LLC submits Request for Clarification or, in the Alternative, Rehearing of the 12/18/2025 Order","issued":"2026-01-20","accession":"20260120-5298","docket":"EL25-49-002","group":"PJM co-location compliance","filer":"Constellation Energy Generation, LLC","kind":"rehearing request","file":"sources/filings/text/20260120-5298_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260120-5298","tier":"record","sha256":"b140828cda1ad3e01401beb8586deabd63ab9e6be35477d8cfbaae1eeb9f9ec3","pages":10,"tokens":3053,"emptyPages":[],"textThemes":["colo","flex","retail"]},"pages":[{"page":1,"startToken":0,"endToken":238,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION\n \nPJM Interconnection, L.L.C., et al. \n \n \nLarge Loads Co-Located at Generating Facilities \n \n \nConstellation Energy Generation, LLC \n \n     v. \n \nPJM Interconnection, L.L.C. \n) \n \n \n)  \n \n \n)  \n) \n) \n) \n) \nDocket No. EL25-49-000 \n \n \nDocket No. AD24-11-000 \n \n \n \n \nDocket No. EL25-20-000 \n(Consolidated) \nREQUEST FOR CLARIFICATION OR, IN THE ALTERNATIVE, REHEARING \nOF CONSTELLATION ENERGY GENERATION, LLC \nConstellation Energy Generation, LLC (“Constellation”) requests clarification, or in the \nalternative, rehearing, of the order issued by the Commission on December 18, 2025, in the above-\ncaptioned dockets.1 The Commission should clarify two discrete issues. First, consistent with \nexisting rules for non-firm exports, a capacity resource should not be required to delist when it is \nserving Co-Located Load2 taking non-firm contract demand transmission service, so long as the \ncapacity resource has no obligation to serve the Co-Located Load during a capacity emergency. In \nthat scenario, the capacity resource remains available to serve the grid when needed for resource \nadequacy; forcing the capacity resource nevertheless to delist would needlessly remove available \ncapacity from serving the grid. Moreover, the Commission should seek to encourage this type of \narrangement—in which the generation resource remains available to the grid in capacity \nemergencies, and the Co-Located Load either curtails or self-supplies using backup generation—\n \n1 PJM Interconnection, L.L.C., 193 FERC ¶ 61,217 (2025) (“December 18th Order”). \n2 Unless otherwise defined, all capitalized terms have the same meaning as in the December 18th Order."},{"page":2,"startToken":238,"endToken":627,"text":"2 \nbecause such an arrangement allows for the interconnection of new data center load, vital to our \nnational interest, without any impact on the capacity price or reliability. Second, the Commission \nshould clarify that it did not intend to change the scope of its jurisdiction over a generator’s \nwholesale sales and transmission and, specifically, that (i) the sales and transmission between a \ngenerator and any wholesale entity are not a “question of state law,”3 and (ii) states may not use \ntheir jurisdiction over the allocation of the costs of interstate wholesale sales to indirectly regulate \nthe interconnection of generators serving Co-Located Load. To the extent that these clarifications \nare denied, we respectfully seek rehearing. \nLIST OF ERRORS/STATEMENT OF ISSUES \nWe seek clarification or rehearing on two issues:  \n1. The Commission should clarify, that consistent with PJM’s existing tariff, capacity \nresources are not required to delist their capacity before making interruptible commitments \nto serve Co-Located Load taking non-firm contract demand transmission service, provided \nPJM can verify that the generator will be available to support the grid during capacity \nemergencies because the load is interruptible or has its own backup generation \narrangements. See 5 U.S.C. § 706(2)(A); Motor Vehicle Mfrs. Ass’n of U.S., Inc. v. State \nFarm Mut. Auto. Ins. Co., 463 U.S. 29, 43 (1983) (State Farm); Consol. Edison Co. of N.Y., \nInc. v. FERC, 45 F.4th 265 (D.C. Cir. 2022); Elec. Consumers Res. Council v. FERC, 747 \nF.2d 1511, 1513-14 (D.C. Cir. 1984). \n2. The Commission should clarify that the December 18th Order did not change the scope of \nits jurisdiction over a generator’s wholesale sales and transmission. Specifically, the \nCommission should clarify that (i) sales and transmission between a generator and any \nwholesale entity are not a “question of state law”4 and (ii) that states may not use their \njurisdiction over the allocation of the costs of interstate wholesale sales among retail \ncustomers to indirectly regulate the interconnection of generators serving Co-Located \nLoad. See 5 U.S.C. § 706(2)(A); State Farm, 463 U.S. at 43; Elec. Consumers Res. Council \nv. FERC, 747 F.2d at 1513-14. \nTo the extent that the requested clarifications are denied, we respectfully request rehearing. \n \n3 December 18th Order, 193 FERC ¶ 61,217 at P 169. \n4 Id."},{"page":3,"startToken":627,"endToken":916,"text":"3 \nARGUMENT \nI. \nThe Commission Should Clarify that Capacity Resources are Not Required to Delist \nBefore Making Interruptible Commitments. \nRead by its terms, the December 18th Order could appear to require the delist of capacity \nresources even when the capacity resources remain fully capable of serving the grid during \ncapacity emergencies. The Order states, “[i]n accordance with the existing rules for removing \nCapacity Resource status, … an existing generating facility may not begin serving Co-Located \nLoad that is not Network Load until it has delisted its [capacity interconnection rights] for the \nportion of the generating facility to be designated to serve any Co-Located Load that is not \nreceiving [Network Integration Transmission Service (NITS)].”5  \nBut generators and Co-Located Load may seek contractual arrangements in which, during \na capacity emergency, the generator will serve the grid rather than the Co-Located Load. The Co-\nLocated Load, in turn, could either curtail or rely on its own backup generation. Constellation \nseeks clarification that the Commission did not intend to discourage or frustrate those \narrangements or insist the generation that is capable of supplying the grid during a capacity \nperformance event delist.    \nIndeed, the Commission should encourage arrangements in which Co-Located Load can \nreceive non-NITS service (such as non-firm contract service) and also curtail its reliance on the \nCo-Located generator during capacity emergencies. Such an arrangement allows the \ninterconnection of new data center load, important to our economic competitiveness and national \nsecurity; the co-location of that load, minimizing the need for grid upgrades; and the continued \n \n5 December 18th Order, 193 FERC ¶ 61,217 at P 230 (citing PJM, Intra-PJM Tariffs, OATT, attach. DD.6, § 6.6 Offer \nRequirement for Capacity Resources (3.0.0); PJM March 24 Response at 58) (emphasis added)."},{"page":4,"startToken":916,"endToken":1310,"text":"4 \navailability of the co-located generator to serve the grid when it is needed to ensure resource \nadequacy. In other words, such an arrangement facilitates the prompt interconnection of new data \ncenter load without any impact on capacity prices or reliability. Requiring the delist of capacity in \nsuch an arrangement would needlessly reduce the capacity available for existing customers.  \nIt would also be inconsistent with PJM’s existing rules, which only require capacity \nresources entering external sales to delist capacity interconnection rights if a resource “has a \nfinancially and physically firm commitment to an external sale of its capacity.”6 But again, not all \nagreements by Co-located Generators to serve Co-Located Load will be “physically firm \ncommitments.” Some may be interruptible. As the Commission recognizes, “the record \ndemonstrates … Co-Located Loads are willing and able to limit their energy withdrawals from the \ntransmission system under certain conditions.”7 Co-Located Load may likewise agree to limit their \nreliance on a co-located generator under certain conditions, such as a capacity emergency, and \nagree either to curtail itself or be served by backup generation or batteries.8   \nAccordingly, it is vitally important for the Commission to clarify that it did not intend to \nrequire capacity resources to delist to serve co-located loads that are taking non-firm contract \ndemand transmission service, so long as PJM can verify that co-located customer has no \n \n6 PJM Tariffs, OATT, Attachment DD.6, § 6.6 (emphasis added); see also PJM Interconnection, L.L.C. September 17, \n2007 Filing, Docket No. ER07-1050-001, at 4-5 (“[A]s set forth in the must-offer rule of section 6.6, a PJM resource \nthat can qualify as a capacity resource must offer its capacity into the RPM auctions unless it can show that it is \ncommitted to a firm export, will be physically unavailable in the relevant delivery year, or was interconnected to the \nsystem as an ‘energy-only’ resource.”). \n7 December 18th Order, 193 FERC ¶ 61,217 at P 199; id. P 204 (“We note that, in general, special protection schemes \nallow Eligible Customers on behalf of Co-Located Load to effectively limit their withdrawals from the transmission \nsystem.”) (citing Constellation April 23 Reply Comments Herling Aff. ¶ 23). \n8 Constellation April 23, 2025 Reply Comments at 98 (“‘[d]ata centers almost always have their own backup power \nsupply ….’”) (quoting Michael Kormos, The Co-Located Load Solution at 10; Kormos Aff., Appendix)."},{"page":5,"startToken":1310,"endToken":1764,"text":"5 \ncontractual right to energy from the generator during a capacity emergency9 and has the ability to \n(i) interrupt and/or (ii) turn on back-up diesels or other back-up power or draw on batteries when \ntransmission under the non-firm contract demand service is interrupted and the co-located \ngenerator is serving the grid.  \nTo the extent there are concerns that PJM would be “in competition with non-capacity \nbacked co-located loads for output of a Capacity Resource,”10 the Commission could require the \nCo-Located Load to disclose information regarding protective relay scheme and its interruptible \ncommitment, and impose penalties on that Co-Located Load for failure to comply with its \ncommitment.11 Those assurances could be provided by the Co-located Load confirming its \nwillingness and the ability to interrupt or demonstrating that it has back-up diesels or batteries that \nwill take over its supply. If such assurances are provided, it is not reasonable for the Commission \nto require a Co-Located Generator to delist.   \nInterruptible commitments are not firm. To treat them otherwise would needlessly deprive \nPJM of capacity that would be committed to serve its load, compounding resource adequacy \n \n9 As Constellation stated in its April 23, 2025 Reply Comments, “Constellation’s view is that any Existing Generation \nCapacity Resources that would prioritize serving co-located load over following PJM dispatch should instead seek \nremoval of Capacity Resource status or otherwise seek appropriate replacement capacity to cover its capacity supply \nobligation.” Constellation April 23, 2025 Reply Comments at 92-93. \n10 PJM March 24, 2025 Answer at 59; id. (“PJM cannot be simultaneously responsible for ensuring the energy needs \nof the PJM Region and unsure whether a Capacity Resource will decide to serve PJM loads or co-located loads.”) \n(emphasis in original). \n11 See December 18th Order, 193 FERC ¶ 61,217 at P 219 (requesting that parties answer “What are the appropriate \nrates, terms, and conditions” for new Firm Contract Demand and Non-Firm Contract Demand transmission service \nand “What is the appropriate penalty charge or other remedial action that PJM should take to address any unreserved \nuse of the PJM transmission system” for an Eligible Customer taking Firm Contract Demand or Non-Firm Contract \nDemand). On rehearing, Indicated PJM Transmission Owners repeat their prior arguments that protective relays \nmight fail. See Indicated PJM Transmission Owners, January 16, 2026 Request for Rehearing, at 39-41, 49. The \nCommission should continue to reject these arguments. As supported by Michael Kormos, the former Chief \nOperations Officer of PJM, “[p]rotective mechanisms are commonplace and frequently used by PJM and others in \nsituations beyond co-located load to ensure safe and reliable grid operations, including for example, primary and \nsecondary relays and redundant protection systems.” Constellation April 23, 2025 Reply Comments at 48-49 (citing \nKormos Aff. at ¶ 6)."},{"page":6,"startToken":1764,"endToken":2155,"text":"6 \nchallenges. In the event the Commission disagrees, we seek rehearing. Requiring capacity \nresources to delist when arrangements other than a co-located generator are in place to curtail or \nserve the large load when transmission service is interrupted would be a failure of reasoned \ndecision making.12 It would also be unduly discriminatory, and therefore arbitrary and capricious, \nto require capacity resources serving large load to delist for entering into interruptible \ncommitments to serve Co-Located Load, but not requiring capacity resources to delist before \nmaking other non-firm commitments.13 \nII. \nThe Commission Should Clarify the Scope of its Jurisdiction Over a Generator’s \nWholesale Sales and Transmission. \nConstellation agrees with the Commission’s conclusions regarding the scope of its \njurisdiction but there are two statements in the December 18th Order that could be misinterpreted \nin a manner inconsistent with settled jurisdictional principles. Accordingly, Constellation \nrespectfully requests that the Commission clarify the following two points. \nFirst, in the December 18th Order, the Commission concludes that “states have authority \nover their generation resource mix, including through their siting authority” and that, therefore, \n“which generating facilities are sited and allowed to serve Co-Located Load is also a question of \nstate law.”14 Often, however, a generator will not serve Co-Located Load directly. Rather, the \n \n12 See Elec. Consumers Res. Council v. FERC, 747 F.2d 1511, 1513-14 (D.C. Cir. 1984) (“We defer to the agency’s \nexpertise ... so long as its decision is supported by ‘substantial evidence’ in the record and reached by ‘reasoned \ndecisionmaking,’ including an examination of the relevant data and a reasoned explanation supported by a stated \nconnection between the facts found and the choice made.”) (citing Burlington Truck Lines v. United States, 371 U.S. \n156, 168 (1962); Memphis Light, Gas & Water Div. v. FPC, 504 F.2d 225, 230 (D.C. Cir. 1974); 16 U.S.C. § 825l \n(1982)). \n13 5 U.S.C. § 706(2)(A) (a court must set aside any Commission order that is “arbitrary, capricious, an abuse of \ndiscretion, or otherwise not in accordance with law”); see also Consol. Edison Co. of N.Y., Inc. v. FERC, 45 F.4th \n265 (D.C. Cir. 2022) (finding the Commission violated the Administrative Procedure Act for failure to provide a \nsatisfactory explanation for treating projects differently). \n14 December 18th Order, 193 FERC ¶ 61,217 at P 169 (emphasis added)."},{"page":7,"startToken":2155,"endToken":2502,"text":"7 \ngenerator will first sell electricity at wholesale to an entity, such as a retail supplier, that will then \nengage in the ultimate retail sale to the Co-Located Load. Such sales for resale are exclusively \nwithin the Commission’s jurisdiction, not the states’.15 State jurisdiction is limited to the “ultimate \n[retail] sale of the energy.”16 The Commission should therefore clarify that state authority does not \nextend to the wholesale sale of energy by a generator to a retail supplier, even if the retail supplier \nthen resells that energy to a load co-located with the generator. Such jurisdiction lies exclusively \nwith the Commission. \nSecond, in the December 18th Order, the Commission asserts that “states have exclusive \njurisdiction over how to allocate the costs of all Commission-jurisdictional rates (including for \nenergy, capacity, and transmission) among retail customers, including allocating costs among \ndifferent classes of retail customers.”17 While states generally do have authority over the allocation \nof the costs of interstate wholesale sales among the wholesaler’s retail customers, that authority is \nnot unlimited. As the Supreme Court has repeatedly stated, “even when States exercise their \ntraditional authority over retail rates,” the “States may not seek to achieve ends, however \nlegitimate, through regulatory means that intrude on FERC’s authority over interstate wholesale \nrates.”18  \n \n15 See 16 U.S.C. § 824(b)(1); see also Orangeburg, S.C. v. FERC, 862 F.3d 1071, 1086-87 (D.C. Cir. 2017) (“FERC—\nnot state commissions—has ‘exclusive authority to regulate the transmission and sale at wholesale of electric energy \nin interstate commerce.’”) (quoting New England Power Co. v. New Hampshire, 455 U.S. 331, 340 (1982)). \n16 New York v. FERC, 535 U.S. 1, 23 (2002) (emphasis removed).  \n17 December 18th Order, 193 FERC ¶ 61,217 at P 167 (emphasis added).  \n18 Hughes v. Talen Energy Mktg., LLC, 578 U.S. 150, 164-65 (2016); see also Nantahala Power & Light Co. v. \nThornburg, 476 U.S. 953, 966 (1986) (“Once FERC sets such a rate, a State may not conclude in setting retail rates \nthat the FERC-approved wholesale rates are unreasonable.”)."},{"page":8,"startToken":2502,"endToken":2842,"text":"8 \nWe therefore respectfully request that the Commission clarify that, consistent with \nlongstanding Supreme Court precedent,19 states do not have unlimited authority “over how to \nallocate the costs of all Commission-jurisdictional rates” and that they cannot use their authority \nover retail allocation to indirectly regulate the interconnection of generators serving Co-Located \nLoad. For instance, a state cannot impose a requirement via the exercise of their jurisdiction over \nretail sales that attempts to contradict or prohibit a transaction or sale that the Commission has said \nis permitted. This is not a hypothetical concern. Some utilities have in fact asked their state \ncommission for authority to condition retail service in the state on the load’s acceptance of a \nTransmission Security Agreement that calculates its security requirement based on a gross NITS \nrate despite the fact that this Commission has said that other rates must be made available.20 The \nCommission should make clear that a state may not frustrate the Commission’s policy in this \nmanner, and, moreover, that any such Transmission Security Agreement would be unjust and \nunreasonable as a matter of federal law. \nCONCLUSION \nFor the foregoing reasons, the Commission should clarify the December 18th Order or, in \nthe alternative, grant rehearing. \n \n \n19 See, e.g., Hughes, 578 U.S. at 164-65; Thornburg, 476 U.S. at 966. \n20 See Commonwealth Edison Co., Constellation Energy Generation, LLC Motion to Reopen the Evidentiary Record \nfor Supplemental Discovery, Testimony, and Briefing, Illinois Commerce Comm’n Docket No. 25-0677, at 1-2 \n(filed \nDec. \n23, 2025), https://www.icc.illinois.gov/docket/P2025-0677/documents/374492/files/656364.pdf \n(“ComEd’s proposed changes to its General Terms and Conditions referencing a requirement to enter into a \nTransmission Security Agreement (‘TSA’), and the TSA general terms and conditions shared by ComEd in this \nproceeding, assume that all customers will take Network Integration Transmission Service (‘NITS’) billed based on \ngross billing determinants, and that service will begin when network upgrades are constructed…. ComEd’s \nassumptions regarding transmission service applicable to LDPACs are no longer valid under the recent FERC \norder.”)."},{"page":9,"startToken":2842,"endToken":2971,"text":"9 \n \n \n \n \n \n \n \n    Respectfully submitted, \n \n \n \n \n \n \n \n    /s/ Paul F. Wight \n \nJanuary 20, 2026 \n \n \nCarrie Hill Allen \nSr. Vice President & Deputy General Counsel \nSeth Lucia \nAssistant General Counsel \nConstellation Energy Generation, LLC \n250 Massachusetts Ave. NW, Suite 760 \nWashington, D.C. 20001 \ncarrie.allen@constellation.com \nseth.lucia@constellation.com \n  \nChristopher A. Wilson \nManaging Director, Federal Regulatory Affairs \nConstellation Energy Generation, LLC \n250 Massachusetts Ave. NW, Suite 760 \nWashington, D.C. 20001 \n202-347-7500 \nFERCe-filings1@constellation.com \n \nPaul F. Wight \nCarolyn E. Clarkin \nDLA Piper LLP (US) \n500 Eighth Street NW \nWashington, D.C. 20004 \n703-773-4058 \npaul.wight@us.dlapiper.com  \ncarolyn.clarkin@us.dlapiper.com  \n \nJacob I. Chefitz \nDLA Piper LLP (US) \n1251 Avenue of the Americas \nNew York, NY 10020 \n212-335-4500 \njacob.chefitz@us.dlapiper.com  \n \nCounsel for Constellation Energy \nGeneration, LLC"},{"page":10,"startToken":2971,"endToken":3053,"text":"CERTIFICATE OF SERVICE \nI hereby certify that I have on this 20th day of January, 2026, caused to be served a copy \nof the foregoing upon all parties on the service lists in these proceedings in accordance with the \nrequirement of Rule 2010 of the Commission’s Rules of Practice and Procedure, 18 C.F.R. \n§ 385.2010 (2025). \n/s/ Sophia Browning \nSophia Browning \nDLA Piper LLP (US) \n4365 Executive Drive \nSuite 1100 \nSan Diego, California 92121 \n858-677-1455 \nsophia.browning@us.dlapiper.com"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":3,"endAt":13,"startToken":0,"endToken":629},{"p":3,"at":13,"title":"I. The Commission Should Clarify that Capacity Resources are Not Required to Delist","method":"printed heading","endPage":6,"endAt":610,"startToken":629,"endToken":1853},{"p":6,"at":610,"title":"II. The Commission Should Clarify the Scope of its Jurisdiction Over a Generator’s","method":"printed heading","endPage":8,"endAt":1203,"startToken":1853,"endToken":2685},{"p":8,"at":1203,"title":"CONCLUSION","method":"printed heading","endPage":10,"endAt":0,"startToken":2685,"endToken":2971},{"p":10,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":10,"endAt":491,"startToken":2971,"endToken":3053}]}