{"document":{"slug":"rec-20260120-5301","title":"PJM Interconnection, L.L.C. submits Informational Report addressing several categories of requested information in response to FERC’s 12/18/2025 Order","issued":"2026-01-20","accession":"20260120-5301","docket":"EL25-49-000","group":"PJM co-location compliance","filer":"PJM Interconnection, L.L.C.","kind":"filing","file":"sources/filings/text/20260120-5301_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260120-5301","tier":"record","sha256":"056b201c118e2f24c0f34a90035438e7d098d8eb366f0dd89438a8de2c5e2684","pages":25,"tokens":7719,"emptyPages":[],"textThemes":["adequacy","registry","flex","cost"]},"pages":[{"page":1,"startToken":0,"endToken":238,"text":"PJM Interconnection, L.L.C. \n2750 Monroe Boulevard \nAudubon, PA 19403  \nMark. J. Stanisz \nAssociate General Counsel \nT:  (610) 666-4707 ǀ F:  (610) 666-8211 \nmark.stanisz@pjm.com  \nJanuary 20, 2026 \nHonorable Debbie-Anne A. Reese, Secretary \nFederal Energy Regulatory Commission \n888 First Street, N.E., Room 1A \nWashington, D.C. 20426-0001 \nRe: \nPJM Interconnection, L.L.C., Docket Nos. EL25-49-000 and -001 \nInformational Report \nDear Secretary Reese: \nOn December 18, 2025, the Federal Energy Regulatory Commission (“Commission”) \nissued an order in part directing PJM Interconnection, L.L.C. (“PJM”) to submit an informational \nreport addressing several categories of requested information.1 PJM submits this informational \nfiling and encloses the PJM Board of Managers’ January 16, 2026 decisional letter2 outlining next \nsteps resulting from the Critical Issue Fast Path (“CIFP”) – Large Load Additions stakeholder \nprocess. \nI.\nINFORMATIONAL FILING\nAmong other things, the Order directs PJM to submit an informational filing to address \nseveral issues relating to the CIFP stakeholder process3 and associated efforts to maintain system \n1 PJM Interconnection, L.L.C., 193 FERC ¶ 61,217 (the “Order”), at PP 237–39 (2025). \n2 PJM Board Letter Regarding Results of the Critical Issue Past Path (CIFP) Process - Large Load Additions (Jan. 16, \n2026) (the “Decisional Letter”, attached as Exhibit A), at: https://www.pjm.com/-/media/DotCom/about-pjm/who-\nwe-are/public-disclosures/2026/20260116-pjm-board-letter-re-results-of-the-cifp-process-large-load-additions.pdf.   \n3 PJM, Critical Issue Fast Path – Large Load Additions, https://www.pjm.com/committees-and-groups/cifp-lla."},{"page":2,"startToken":238,"endToken":502,"text":"The Honorable Debbie-Anne A. Reese, Secretary   \nJanuary 20, 2026 \nPage 2 \n \nreliability while increasing the “pace of adding generating capacity in the PJM region.”4 PJM \naddresses each request as follows. \nFirst, the Commission requested information about the “status of the proposals considered \nin the CIFP stakeholder process, including—but not limited to—the status of the expedited \ninterconnection process to enable shovel-ready generation projects to serve PJM more quickly, \nmodifications to PJM’s reliability backstop mechanism to improve PJM’s ability to respond to \nacute resource adequacy shortfalls, and the development of enhanced load forecasting and demand \nflexibility measures to assist PJM in determining the amount of new capacity that is needed to \nmaintain system reliability.”5 In this regard, the Order refers to PJM’s October 20, 2025 letter to \nthen-Chairman Rosner’s letter on load forecasting, and it instructs PJM to “expand on its response \nto then-Chairman Rosner . . . by explaining, in detail, any changes or updates to its load forecasting \nprocesses that it is considering.”6 \nPJM Response:  PJM directs the Commission to the PJM Board’s January 16, 2026 \ndecisional letter enclosed as Exhibit A.  Among other things, this letter announces the following \nPJM actions that are specifically responsive to the informational filing directive: \n• Load forecasting:  continued implementation of significant load forecasting \nimprovements (many of which are already implemented) relating to state review, \naddressing duplicative load requests, load forecast benchmarking which may \ninclude third party review, enhanced transparency expectations that will require \nsharing necessary information with PJM related to large loads, additional Load \n \n4 Order at P 238. \n5 Id. \n6 Id. at n.487."},{"page":3,"startToken":502,"endToken":714,"text":"The Honorable Debbie-Anne A. Reese, Secretary   \nJanuary 20, 2026 \nPage 3 \n \nAnalysis Subcommittee enhancements, and engagement with Electric Distribution \nCompanies and Load Serving Entities to improve large load modeling assumptions \naround ramp rate and utilization (see Decisional Letter, pages 2-3 and Appendix B \nwhich sets forth applicable design components). \n• Expedited interconnection process:  imminent filing with the Commission, \nfollowing stakeholder review of proposed tariff language, to effectuate a voluntary \nBring Your Own New Generation (“BYONG”) construct paired with an Expedited \nInterconnection Track (see Decisional Letter, pages 3-4 and Appendix C which sets \nforth applicable design components). \n• Reliability backstop mechanism:  initiation of Reliability Backstop Procurement \nfollowing stakeholder engagement to develop potential changes to the design of the \nprocurement process (see Decisional Letter, pages 5-6). \n• Demand flexibility measures:  following additional stakeholder process, \nimplementation of a “Connect and Manage” construct for new large load additions \nthat do not BYONG, whereby the incremental demand associated with such load \ngrowth would be subject to curtailment prior to the deployment of pre-emergency \nDemand Respond (see Decisional Letter, pages 4-5). \nFurther, the Order requests a “detailed schedule of key milestones, such as stakeholder or \nPJM Board votes, that includes the estimated date on which PJM expects to file any such proposals \nwith the Commission.”7 \n \n7 Id. at P 238."},{"page":4,"startToken":714,"endToken":976,"text":"The Honorable Debbie-Anne A. Reese, Secretary   \nJanuary 20, 2026 \nPage 4 \n \n PJM Response:  PJM directs the Commission to the PJM Board’s January 16, 2026 \ndecisional letter enclosed as Exhibit A.  By way of further response, PJM provides the following \nresponse:   \n• Load forecasting:  PJM will continue to implement the PJM Board-directed load \nforecasting improvements.  These enhancements will be addressed using PJM’s \nexisting authority through the Manuals, and PJM will review any specific language \nrevisions with stakeholders in the February 2026 time period.  PJM does not \nanticipate needing to make a filing with the Commission to implement these \nenhancements.   \n• Expedited interconnection process:  PJM has already drafted the proposed \nExpedited Interconnection Track tariff language and intends to review the proposed \ntariff revisions with stakeholders on January 27, 2026 prior to filing with the \nCommission on or about January 30, 2026.  The Expedited Interconnection Track \nis anticipated to be in place by August 2026, subject to Commission acceptance.  \n• Reliability backstop mechanism:  The PJM Board is directing stakeholders to give \nimmediate attention to discussing the design of the reliability backstop procurement \nmechanism in the tariff.  The process and deadlines for action will be discussed at \nthe January 22, 2026 Members Committee meeting.  The PJM Board intends that \nthe backstop be instituted as soon as practicable which may require changes to the \ncurrent tariff.  Among other things, the stakeholder process will also be informed \nby the January 16, 2026-released “Statement of Principles Regarding PJM” \nendorsed by the White House National Energy Dominance Council and Governors \nof the PJM States, and consider the implementation of these Principles in enhancing"},{"page":5,"startToken":976,"endToken":1238,"text":"The Honorable Debbie-Anne A. Reese, Secretary   \nJanuary 20, 2026 \nPage 5 \n \nPJM’s reliability backstop procurement mechanism.8  By February 27, 2026, PJM \nwill supplement this filing with additional detail regarding the timeline and process \nnecessary to move forward expeditiously on revisions to the backstop procurement \ntariff construct and the timing of commencing the revised backstop procurement \nprocess following stakeholder review of the Decisional Letter and Principles, as \nwell as stakeholder discussion on implementation.  \n• Demand flexibility measures:  Regarding the implementation of the “Connect and \nManage” construct for new large load additions that do not BYONG, the PJM \nBoard is directing that the requisite load shed prioritization and allocation should \nbe completed as soon as practicable. The PJM Board is directing that this matter \nfirst be addressed via the Consensus Based Issue Resolution (“CBIR”) process, and \nthe PJM Board is asking that the stakeholders proceed expeditiously such that \nchanges are in place by the end of 2026.  The PJM Board will continue to monitor \nthe progress of this stakeholder effort to determine whether to initiate an accelerated \nstakeholder process. \nIn addition, the Order directs “PJM to identify any problem statements, issue charges, or \nother ongoing stakeholder processes that aim to increase the pace of adding generating capacity in \nthe PJM region.”9 It requests that PJM “provide as detailed a schedule as is feasible on the timing \nof such initiatives, including updates on the stakeholder process and approximate dates of any \n \n8 \nDepartment \nof \nEnergy, \nStatement \nof \nPrinciples \nRegarding \nPJM \n(Jan. \n16, \n2026), \nat: \nhttps://www.energy.gov/documents/statement-principles-regarding-pjm (the “Principles”).   \n9 Id."},{"page":6,"startToken":1238,"endToken":1513,"text":"The Honorable Debbie-Anne A. Reese, Secretary   \nJanuary 20, 2026 \nPage 6 \n \nanticipated filings with the Commission.”10  The Order also requires that this informational report \n“identify specifically which of these initiatives would support the addition, on an expedited basis, \nof new generation that is sufficient to serve large loads, like data centers, while meeting PJM’s \nnear-term system resource adequacy needs.”11  Finally, the Order directs PJM to “explain the \nproposed effective date of any proposal that it intends to file so that the Commission can \nunderstand whether any of those proposals could be in place by the 2028/2029 Base Residual \nAuction (BRA) and subsequent BRAs to attract sufficient new generation to maintain regional \nresource adequacy.”12 \nPJM Response:  In response to these requests, the following proposals are or can be in \nplace by the 2028/2029 Base Residual Auction (BRA) and subsequent BRAs: \n• The Expedited Interconnection Track proposal will be imminently filed with the \nCommission.  If accepted, PJM will implement that mechanism with utmost haste \nby or before the summer of 2026. \n•  PJM already has in place, and will continue to implement, load forecast \nenhancements that are having a demonstrable impact on load projections in the PJM \nRegion.  On January 14, 2026, PJM posted its 2026 Load Forecast Report which \nconfirms the trend of significant growth in demand over the next 20 years but \nreflects a decrease in the expected load growth for near-term years compared with \nPJM’s 2025 load forecast analysis.13 \n \n10 Id. \n11 Id. \n12 Id. at P 239. \n13 2026 PJM Load Forecast Report (Jan. 14, 2026), at:  https://www.pjm.com/-/media/DotCom/library/reports-\nnotices/load-forecast/2026-load-report.pdf."},{"page":7,"startToken":1513,"endToken":1825,"text":"The Honorable Debbie-Anne A. Reese, Secretary   \nJanuary 20, 2026 \nPage 7 \n \n• In response to disappointing performance from load management resources that \nwere dispatched in the summer of 2025 and the expectation that PJM will likely \nneed to dispatch load management more frequently due to the lower reserve \nmargins, PJM initiated a stakeholder process to explore opportunities to incentivize \nbetter performance from load management resources.14  PJM is aiming to \nimplement such enhancements effective with the 2028/2029 Delivery Year and will \nendeavor to submit a filing with the Commission for approval prior to conducting \nthe Base Residual Auction associated with the 2028/2029 Delivery Year. \nFurther, PJM identifies the following additional problem statements, issue charges, or other \nongoing stakeholder processes (and, to the extent now known, schedules associated therewith) that \naim to increase the pace of adding generating capacity in the PJM region:  \n• In the fall of 2025, PJM initiated a stakeholder process to identify under what \ncircumstances generation projects that advance to the Phase III of a Cycle may be \npermitted to safely and reliably begin generating prior to the completion of certain \nCycle studies without impacting the timing or fundamentally altering PJM’s \nGeneration Interconnection Procedures (“GIP”).  This stakeholder process is \nseeking to expand PJM’s existing provisional service process to include projects in \nPhase III that meet particular criteria to generate on an energy-only basis.15 \n \n14 See PJM Problem/Opportunity Statement, Load Management and PRD Event Performance, at: \nhttps://www.pjm.com/-/media/DotCom/committees-groups/committees/mic/2025/20251203/20251203-item-07-1---\nload-management--prd-event-performance---problem-statement.pdf. \n15 See PJM’s Issue Tracker, Expansion of Provisional Service, at https://www.pjm.com/committees-and-groups/issue-\ntracking/issue-tracking-details.aspx?Issue=23fc7fe8-f851-4a46-b2aa-33ea23b606b7 (setting forth the timeline for \ntarget completion by July 2026 and additional details); see also Interconnection Process Subcommittee meeting \nmaterials (November 11.24.2025) (presenting the Problem Statement, Issue Charge, and Work Plan); see also"},{"page":8,"startToken":1825,"endToken":2072,"text":"The Honorable Debbie-Anne A. Reese, Secretary   \nJanuary 20, 2026 \nPage 8 \n \n• Since 2023, PJM has explored potential reforms to the reserve market to better \nincentivize the appropriate suite of ancillary service products coupled with the \nconfidence that resources with reserve assignments will actually perform when \ncalled upon.16 After the years-long stakeholder discussions, PJM is aiming to seek \na vote on the final package(s) that emerge through this process in September 2026, \nwith a potential filing with the Commission before the end of the year.   \n \nBy way of further response, the PJM Board has directed PJM to perform a holistic review \nof investment incentives in PJM’s Markets.  This review is to be completed in the first half of \n2026.  Thereafter, PJM Staff will engage with stakeholders to formulate a workplan to implement \nrecommendations made from the analysis.  The PJM Board is directing that the workplan be \npresented to the PJM Board with a recommendation for accelerated stakeholder processes to \nexpeditiously implement the recommendations set forth in the analysis.     \nPJM will continue to update the Commission on the timing of initiatives outlined in this \nletter after additional near term consultations with stakeholders on the need for prioritization of \nthese activities.  \n \nInterconnection Process Subcommittee meeting materials (December 18, 2025) (including the education regarding \nprovisional service).  Please note that “provisional service” is also referred to as “interim deliverability.”  \n16 \nSee \nPJM \nProblem/Opportunity \nStatement, \nReserve \nCertainty, \nat: \nhttps://www.pjm.com/-\n/media/DotCom/committees-groups/task-forces/rcstf/postings/problem-statement.pdf."},{"page":9,"startToken":2072,"endToken":2153,"text":"The Honorable Debbie-Anne A. Reese, Secretary   \nJanuary 20, 2026 \nPage 9 \n \nII. \nCONCLUSION  \n \nPJM respectfully requests the Commission accept this informational filing.  \n \nRespectfully submitted, \n \nBy:   /s/ Mark J. Stanisz \nCraig Glazer \nVice President–Federal Government Policy \nPJM Interconnection, L.L.C. \n1200 G Street, N.W, Suite 600 \nWashington, D.C. 20005 \n(202) 423-4743 \ncraig.glazer@pjm.com \n \n \nMark J. Stanisz \nAssociate General Counsel \nPJM Interconnection, L.L.C. \n2750 Monroe Blvd. \nAudubon, Pennsylvania 19403 \n(610) 666-4707 \nmark.stanisz@pjm.com"},{"page":10,"startToken":2153,"endToken":2155,"text":"EXHIBIT A"},{"page":11,"startToken":2155,"endToken":2593,"text":"610.666.8980 | www.pjm.com \nDavid Mills \nInterim President & CEO \nPJM Interconnection \n2750 Monroe Blvd. \nAudubon, PA 19403 \nJanuary 16, 2026 \n \nDear Stakeholders, \nBoard Decisional Letter on Critical Issue Fast Path - Large Load Additions \nAt the outset, the PJM Board of Managers (Board) would like to thank you for your participation in the Critical Issue \nFast Path (CIFP) accelerated stakeholder process for large load additions. Board members were able to listen in on \neach step of the CIFP, and the Board appreciated the opportunity to ask questions of presenters during the final \nstage. After significant deliberation, the Board is issuing this decisional letter that reflects components of the various \npresentations. Specific elements of presentations are credited in this letter, with the name of the presenter’s \norganization highlighted in bold print.1 \nExecutive Summary \nThe Board’s decision consists of the following components, some of which will serve as transitional measures while \nthe industry and government collectively work to bring more supply to the system to meet an unprecedented growth \nin demand. This is a dynamic period in the industry, and as such, the decisions made here can be revisited based on \na series of factors, namely whether the region’s supply/demand balance and reserve margin are restored to a level \nthat comfortably ensures resource adequacy for existing consumers and large load aditions. The primary \ncomponents of the Board’s decision are as follows, with a deeper explanation of each found within the body of this \nletter. \n• \nSignificant Load Forecasting Improvements \n• \nVoluntary Bring Your Own New Generation (BYONG) Paired With Expedited Interconnection Track \n• \nConnect and Manage for New Large Load Additions That Do Not BYONG and Curtailment Prior to \nEmergency Demand Response in Circumstances Necessitating Load Shed \n• \nImmediate Initiation of Reliability Backstop Procurement \n• \nHolistic Review of Investment Incentives in PJM’s Markets in 2026 \n• \nFeedback Request on Price Collar for 2028/2029 and 2029/2030 Capacity Auctions \nFraming the Board’s Review \nThe Board analyzed the various proposals through a particular frame that we thought would be helpful to explain. \nThat frame begins with the organization’s mandate to maintain grid reliability. As the results of the 2027/2028 Base \nResidual Auction (BRA) display, the RTO has cleared short of its reliability requirement for the first time in history. \nThe 2027/2028 BRA cleared 5.6% short of our target reserve margin indicating that the system is at higher risk than \n \n1 This correspondence satisfies the requirements of Manual 34 Section 8.6.4, and also represents the Board’s response to the \nmany thoughtful letters it received during the pendency of the CIFP, a list of which is attached here as Appendix A."},{"page":12,"startToken":2593,"endToken":3139,"text":"January 16, 2026 \nPage 2 \n610.666.8980 | www.pjm.com \nprevious years. The Board views this outcome as a clear signal that current trends are not acceptable and warrant \ncorrective action. \nReliability is PJM’s primary responsibility, and our Operating Agreement is clear that advancing competitive \nmarkets is also part of our charge. PJM continues to believe in the benefits of well-functioning competitive markets \nas these markets have saved consumers billions of dollars pursuant to our value proposition calculations. We will \ncontinue to leverage markets to pursue cost-efficient outcomes for consumers. \nThe Board recognizes the expressed interests at both the federal and state levels in facilitating the timely \ninterconnection of large loads to support continued economic and digital-sector growth. At this time, the Board is not \ntaking action to restrict the interconnection of new load through the creation of a dedicated load interconnection \nqueue or through other limiting measures. \nWhere PJM can support regional growth while maintaining system reliability and ensuring rates remain just and \nreasonable, the Board believes it is appropriate to pursue those outcomes. The Board also notes, consistent with the \nFederal Energy Regulatory Commission’s (FERC) recent colocation determination, the significant role of the states \nand their jurisdiction over the interconnection of retail load. \nFurther, as a mission-driven organization that fundamentally exists as part of a larger system serving consumers, \nPJM must be conscious of the affordability challenges facing the 67 million consumers in our footprint today. There \nis much that our states can be doing to contend with higher wholesale costs at the retail level.2 At the same time, as \nthe market administrator, PJM should seek to balance the design of its markets to simultaneously set transparent \nprices that incent the desired behavior from market participants while not being punitive to consumers. \nIt is with these critical elements in mind that the Board analyzed all proposals set forth during CIFP Stage 4 and \nhereby directs the staff to advance the following proposals or components of proposals along with other directives. \nBoard Decision \n1. Defining Large Load Additions \nFor purposes of the proposed Tariff and manual provisions being developed as a result of this CIFP process, \nthe Board proposes to define large load additions as individual additions of load at or above 50 MW at a single \nPoint of Interconnection.3 The Board notes that this level was supported in the CIFP process and is consistent \nwith PJM’s definition of large load additions already being utilized in its large load adjustment process.  \n2. Load Forecasting Improvements \nIt became clear to the Board during the CIFP that additional improvements should be made to the load \nforecasting process, building on the progress made by PJM staff and stakeholders through the Load Analysis \nSubcommittee (LAS). Reforms vetted through the LAS should be implemented. Further, the improvements \nproposed in the PJM staff proposal in the CIFP should also be implemented. These improvements relate to \nstate review of large load additions, addressing duplicative requests, the use of additional third-party review and \nincreased transparency. These represent strong improvements that will continue to both refine the process and \n \n2 Op-Ed from SVP Asim Z. Haque, State Frameworks Are Critical To Addressing PJM Affordability \n3 EDC or LSE may request large loads under 50 MW for consideration on a case-by-case basis."},{"page":13,"startToken":3139,"endToken":3617,"text":"January 16, 2026 \nPage 3 \n610.666.8980 | www.pjm.com \nresulting load projections. The Board directs the PJM staff to implement the load forecasting improvements4 as \nset forth in Appendix B. PJM staff will review any specific language changes that are necessary or appropriate \nwith stakeholders prior to their adoption. Load forecasting improvements that have not already been \nimplemented for PJM’s 2026 Load Forecast should be in place for PJM’s 2027 Load Forecast.  \n3. Integrating Large Loads  \nWithin the CIFP process, there was significant discussion concerning PJM’s obligation to procure capacity to \nserve large load additions, the curtailment priority for such large load additions and whether capacity obligations \nshould differ where large loads are accompanied by incremental generation to offset their large load additions. \nThe Board appreciates the breadth of stakeholder proposals submitted on these issues and has adopted \nelements of several proposals with the following goals in mind: \n• \nProvide the appropriate price signals to support the timely development of new capacity \nresources necessary to serve all load in PJM at the required level of reliability; \n• \nAlign curtailment priority and implementation with frameworks established by the relevant states \nand/or Transmission Owners (TOs) – while PJM will determine the quantity of load requiring \ncurtailment to preserve grid reliability, the states and/or TOs retain responsibility for determining \nwhich loads are curtailed when necessary; \n• \nCreate incentives for Load Serving Entities (LSEs), large loads and/or states to bring new \ncapacity resources to offset their load additions consistent with cost causation principles; and \n• \nEstablish an expedited interconnection pathway for incremental generation advanced by LSEs, \nlarge loads and/or states.  \nFor these elements to be successful, the Board expects the data center community and other large loads, along \nwith the LSEs that serve them, to play a constructive role in addressing the reliability and affordability \nchallenges associated with the scale and pace of the forecasted large load additions in the PJM region. The \nBoard is therefore directing management to pursue the following components in accordance with the timelines \nset forth below. \na. Voluntary Bring Your Own New Generation (BYONG) Commensurate With Large Load \nAdditions and Expedited Interconnection Track \nThe Board is supportive of frameworks under which LSEs, large loads and states bring their own \nincremental generation to the system to offset, on an ELCC-measured basis, their load additions. The \nBoard is mindful of the jurisdictional limits of PJM’s authority, which apply to PJM’s relationship with \nLSEs rather than individual retail customers. As a result, although the Board is proposing Tariff \nrevisions that focus on aggregate new generation demonstrated by LSEs as available to offset their \nforecasted large load additions, the states within PJM’s footprint retain the authority to determine how \nsuch frameworks are applied to individual retail customers, including large loads. \n \n4 The primary components of PJM’s load forecast proposal and changes made via the LAS affixed here as Appendix B"},{"page":14,"startToken":3617,"endToken":4148,"text":"January 16, 2026 \nPage 4 \n610.666.8980 | www.pjm.com \nAs has been referenced by many stakeholders, including the Independent Market Monitor (IMM), data \ncenters in particular (which account for a substantial share of forecasted large load additions in the PJM \nfootprint) present characteristics not previously experienced at scale, both in terms of magnitude and \nspeed of deployment. According to McKinsey & Company, PJM is the largest data center market today \nand is expected to remain so at least until 2030. The Board does not support approaches that seek to \nlimit or eliminate this growth. Rather, the Board views engagement by the data center community as an \nimportant component to addressing the reliability and downstream affordability challenges associated \nwith rapid load growth.  \nAccordingly, the Board encourages voluntary “Bring Your Own New Generation” (BYONG) and directs \nthe PJM staff to implement its proposal and associated matrix components related to the Expedited \nInterconnection Track5 that will serve as an alternate path for any entity seeking to mitigate \ncurtailment risk by bringing their own new generation to the system on an accelerated basis. PJM staff \nwill review any specific language changes necessary or appropriate with stakeholders prior to adoption \nor any requisite filing. The Expedited Interconnection Track should be in place by August 2026. \nFinally, the Board notes ongoing efforts by several states within the PJM footprint, including initiatives \nproposed by the Governors of Pennsylvania, Virginia, New Jersey and Maryland to facilitate BYONG \nas reflected in their joint proposal with the Data Center Coalition, Exelon and PPL. While these efforts \nfall outside the jurisdiction of FERC and are not actions that PJM can implement directly, state-led \ninitiatives to advance new supply – including reforms to support permitting and siting of generation and \nthe transmission necessary to integrate it – will be important to accelerating the addition of needed \ngeneration to the system.  \nb. Connect and Manage \nWhere an LSE identifies a shortfall between forecasted load additions and the availability of new \nincremental generation to offset that growth, the Board is directing development of a similar framework \narticulated by the PJM Legislators Collaborative/NRDC and the Joint Consumer Advocates. Under \nthis framework, the incremental demand associated with such load growth would be subject to \ncurtailment prior to the deployment of pre-emergency Demand Response. This will help to preserve \nDemand Response as a valuable reliability tool by not disrupting its business model through a dramatic \nincrease in its use and will provide an incentive for new load to secure capacity or provide flexibility. \nConsistent with its operation of the system today, PJM will take all reasonable steps to maintain grid \nstability and avoid curtailment. However, should system conditions over a given period force PJM to \ninvoke its emergency procedures, the Board finds it reasonable for certain large loads, including data \ncenters, to move to their backup generators, or curtail their demand, for a limited number of hours \nduring the year to prevent a larger scale outage for residential and other consumers. Such curtailment \nwould be expected to occur infrequently, for limited durations, and only when necessary to prevent \nbroader system impacts, consistent with PJM’s longstanding operational practice of avoiding \ncurtailment whenever possible.  \n \n5 Details provided in Appendix C"},{"page":15,"startToken":4148,"endToken":4685,"text":"January 16, 2026 \nPage 5 \n610.666.8980 | www.pjm.com \nUltimately, the determination of which loads are curtailed during emergency conditions rests with TOs, \nand with LSEs that have direct relationships with their customers. PJM does not have authority to direct \nindividual retail loads to curtail demand. However, PJM will establish an allocation framework whereby \nTOs and LSEs have advanced notification of the potential magnitude of load reductions that may be \nrequired under such conditions. PJM intends to explore how to design curtailment allocations based on \nthe contributions of any shortfall to PJM’s required reserve margin.  \nThe Board does not propose that “connect and manage” new large load be removed from the capacity \nmarket. Based on current load projections, the system is expected to tighten to a degree that excluding \nthis demand would be unlikely to reduce capacity prices below point “A” on the Variable Resource \nRequirement (VRR) curve. Removing such load from the market would instead result in large new loads \navoiding capacity costs altogether, with those costs shifted to existing consumers.6 The capacity market is \ndesigned to support system-wide resource adequacy, recognizing that PJM may be required to direct load \ncurtailments to maintain system reliability, with TOs ultimately determining which customers to curtail. \nAs further detailed below, the Board believes a more comprehensive review of the mechanisms through \nwhich PJM’s markets produce investment signals is warranted. However, the markets should retain \nstructural integrity during the pendency of this review and beyond.  \nWith respect to this issue and others addressed in this letter, the Board recognizes that a number of \nfuture developments will be relevant to the design of longer-term approaches to large load integration. \nThese include, among other factors, the extent to which large loads contract for new generation to \noffset load additions, potential future actions by federal and state authorities, the resolution of supply \nchain constraints, success in siting and permitting, and other market and policy developments. \nIn light of these uncertainties, the Board views the capacity market-related actions outlined in this letter \nas interim measures intended to address near-term reliability risks. These measures may be refined or \nrevisited as additional data becomes available and their impacts can be assessed.  \nThe load shed prioritization and allocation should be completed as soon as practicable. This matter \nshould initially be addressed via the Consensus Based Issue Resolution (CBIR) process, but the Board \nasks that the stakeholders proceed expeditiously such that changes are in place by the end of 2026 \nand will monitor the progress to determine whether an accelerated stakeholder process should be \ninitiated.   \n4. Immediate Initiation of Reliability Backstop Procurement \nPJM’s primary responsibility is ensuring grid reliability, and an important component of this reliability mandate is \nresource adequacy. The results of the recent 2027/2028 capacity auction indicate that PJM will fall short of its \nFERC-required reliability requirement in that delivery year.  \nThe PJM Tariff currently allows PJM to run a backstop capacity procurement if the system clears short of the \nreliability requirement for three consecutive capacity auctions. In light of the evolving risk profile, the Board \n \n6 The Board reserves the right to look at this issue again as part of the design of the reliability backstop procurement described in \nthis letter."},{"page":16,"startToken":4685,"endToken":5216,"text":"January 16, 2026 \nPage 6 \n610.666.8980 | www.pjm.com \ndirects PJM staff to develop a proposal to both accelerate and execute this procurement. Accelerating a \nbackstop capacity procurement is especially necessary in light of FERC’s recent decision on colocation and its \nrequest for more information on utilization of this backstop procurement framework.  \nDuring the CIFP process, the coalition comprised of Constellation, Talen, CPower, Google, Amazon and \nMicrosoft proposed elements of a framework that the Board believes warrant further consideration by PJM \nstaff and the stakeholders. Any backstop procurement should specify price, term and quantity as core award \nparameters and be consistent with the Board’s direction to procure for the full reliability requirement for the \nfootprint. \nThe Board directs PJM staff to address cost allocation for any such procurement, including consideration of \nmechanisms that assign costs to those LSEs that are short as a result of incremental load growth within their \nservice areas. Those LSEs may, in turn, determine how such costs are allocated to incremental loads, \nconsistent with state law. \nOver the longer term, the Board does not view it as desirable for PJM to serve as the procuring authority to \nlong-term commitments resulting from backstop procurement. Accordingly, any such procurement should be \nviewed as a transitional measure intended to facilitate the timely integration of new supply, while options for a \nmore durable mechanism are evaluated as part of the broader market review directed below. \nThe Board recognizes that the existing backstop procurement rules are not sufficiently detailed, and that PJM \nand the stakeholders will need to discuss the design of the procurement. The Board is directing that immediate \nattention be provided to this matter with process and deadlines to be discussed at the upcoming January 22 \nMembers Committee meeting.   \n5. Holistic Review of Investment Incentives in PJM’s Markets in 2026 \nPJM has concluded that the investment environment for new generation has evolved materially in recent years, \nand in ways that differ significantly from conditions that prevailed at the inception of the Reliability Pricing Model \n(RPM) capacity market. As it is designed, the three-year forward capacity market was intended to produce a \ntransparent price signal reflecting the value of capacity in a given delivery year and, among other purposes, to \ninform bilateral contracting between willing buyers and sellers. \nThe resulting single-year commitment three years forward, however, provides a comparatively short-term \nsignal relative to the long-lived nature of the generation resources that underpin resource adequacy. On its \nown, this structure may not provide the stable revenue streams needed to justify new investment in today’s \nvolatile and uncertain investment environment, particularly when elevated costs are combined with external \nconstraints or intervention. \nIn addition, a combination of recent factors including heightened price volatility, external headwinds and \nfrequent rule changes has increased investment risk and reduced certainty around long-term procurement \ndecisions. Recent examples of existing resources entering into longer-term bilateral arrangements provide \nevidence that such contracts are increasingly relied upon to support investment decisions within the \nindependent power producer community. \nTo date, the current framework of a one-year capacity commitment procured three years forward has not \nproduced a sufficient level of bilateral contracting or price certainty to support the scale of new resource"},{"page":17,"startToken":5216,"endToken":5798,"text":"January 16, 2026 \nPage 7 \n610.666.8980 | www.pjm.com \ninvestment required to maintain resource adequacy. This is evidenced by the large quantity of prospective new \nresources with signed Generation Interconnection Agreements that are not rapidly moving to construction \ndespite historically high-capacity prices. Accordingly, the Board believes it is appropriate to undertake a \nfocused review of the capacity market to assess whether its design is appropriate for prevailing investment \nconditions and the incentives needed to attract timely new supply. \nThe Board also recognizes that PJM’s markets must operate in a coordinated manner to deliver clear and \ntransparent price signals regarding the resources needed to maintain grid reliability. In this regard, the Board \nviews the work underway in the Reserve Certainty Senior Task Force as an important foundation and expects \nthat those efforts be advanced in addition to any material changes to the capacity market, so that investment \nand performance incentives across markets remain cohesive, understandable and actionable. \nAccordingly, the Board directs PJM to analyze how the energy, reserve and capacity markets can evolve in a \ncoordinated manner to provide appropriate incentives for both investment and performance. Upon completion \nof this analysis, PJM should engage stakeholders to discuss a potential enhanced market framework. \nThe Board’s objectives for this work are twofold: (1) to advance necessary changes to the energy and reserve \nmarkets that are already underway and that support system operators in managing an increasingly dynamic \ngrid; and (2) to ensure that such changes are aligned with anticipated reforms to support resource adequacy, \nwhile continuing to provide a residual mechanism for states with vertically integrated structures. \nThe Board directs PJM staff to perform this analysis in the first half of 2026. Thereafter, the PJM staff should \ndiscuss this analysis with the stakeholders and work with them to formulate a work plan that would serve to \nimplement recommendations made from the analysis. That work plan should be presented to the Board with a \nrecommendation for accelerated stakeholder processes so as to more expeditiously implement the \nrecommendations set forth in the analysis.  \n6. Price Collar for 2028/2029 and 2029/2030 Capacity Auctions – Feedback Requested \nGiven the Board and PJM management’s acknowledgment of the challenges facing the current capacity market \nand need for further review, the Board seeks additional stakeholder input as to whether the price collar that was \nin place for the 2026/2027 and 2027/2028 auctions should be extended. The Board recognizes that there are \nboth advantages and disadvantages associated with such an extension. \nOn the one hand, a price collar may obscure the market’s underlying clearing price and, as a result, could \ndampen signals needed to support the entry of new supply. On the other hand, as discussed above, there are \nlegitimate questions regarding whether the current capacity market construct, on its own, is sufficient to \nincentivize new resource development in the absence of the longer-term bilateral arrangements contemplated \nat the time of the market’s design. \nAccordingly, the Board seeks additional feedback from stakeholders on this issue and requests that responses \naddress the questions set forth in Appendix D as soon as practicable, but before January 30, 2026. Please \nsend responses to these questions via this link. All feedback will be posted publicly on the CIFP LLA webpage. \nAfter review of the feedback, the Board will issue an additional letter discussing its decision to make a Federal \nPower Act (FPA) Section 205 filing related to the price collar, or not, in time for the July auction (2028/2029 \nDelivery Year)."},{"page":18,"startToken":5798,"endToken":5973,"text":"January 16, 2026 \nPage 8 \n610.666.8980 | www.pjm.com \n7. Summary of Actions, Associated Dates and Stakeholder Activity \nAction Taken \nAssociated Dates \nStakeholder Activity \nLoad Forecasting \nImprovements \n2027 Load Forecast (in place for) \nPage Turn of Manuals   \nExpedited Interconnection \nTrack \nAugust 2026 (in place by) \nPage Turn Prior to Requisite Filing \nConnect and Manage (Load \nShed Prioritization and \nAllocation) \nEnd of 2026 (in place by) \nConsensus Based Issue Resolution \nStakeholder Process \nReliability Backstop \nProcurement \nBegin Discussion Immediately \nInitial Discussion at Members Committee on \nJanuary 22, 2026 \nMarket Investment \nIncentives Review \nAnalysis Performed in First Half of \n2026 \nWork Plan to Implement Recommendations \nand Associated Stakeholder Processes \nPresented to Board \nCapacity Auction Price \nCollar \nWritten Feedback by January 30, \n2026.  \nFeedback to Board \nLink here. \n \nThe Board thanks the stakeholders for their engagement, and we look forward to continuing to address both the \ntremendous challenges and opportunities with which we have been presented. \n \nSincerely and on behalf of my colleagues,  \n \nDavid E. Mills \nChair, PJM Board of Managers \nInterim President & CEO, PJM Interconnection, LLC"},{"page":19,"startToken":5973,"endToken":6205,"text":"January 16, 2026 \nPage 9 \n610.666.8980 | www.pjm.com \nAppendix A \nList of Board Correspondences Regarding CIFP \n1. PJM Board Letter Regarding Implementation of Critical Issue Fast Path Process for Large Load Additions \n(PDF) \n2. Senator Fetterman Letter Regarding the Large Load Addition Critical Issues Fast Path (CIFP) Process \n(PDF) \n3. IL Legislative Letter Regarding Critical Issue Fast Path – Large Load Additions (PDF) \n4. Congressional Letter Regarding Critical Issue Fast Path – Large Load Additions (PDF) \n5. GEO*ESG Solutions Regarding Objection to the Use of CIFP Authority and Request for Clarification on \nStandby Generation Policy for Data Centers (PDF) \n6. Several Environment America Research & Policy Centers Regarding Inclusion of the Expedited \nInterconnection Track (EIT) in PJM’s Proposal in the CIFP Process for Large Load Additions (PDF) \n7. NJBPU Staff Regarding Critical Issue Fast Path – Large Load Additions (PDF) \n8. PJM Legislators’ Collaborative Letter Regarding Critical Issue Fast Path – Large Load Additions (PDF) \n9. Illinois Governor Pritzker Letter Regarding Critical Issue Fast Path – Large Load Additions (PDF) \n10. Apex Letter Regarding Critical Issue Fast Path – Large Load Additions (PDF) \n11. Several Governors' Letter Regarding Critical Issue Fast Path – Large Load Additions (PDF) \n12. Sierra Club Letter Regarding Critical Issue Fast Path – Large Load Additions (PDF) \n13. PJM Ratepayer Comments on the Large Load CIFP (PDF) \n14. CAPS Letter Regarding Consumer Advocate Voting on the SMECO Proposal in CIFP-Large Load Addition \n(PDF)"},{"page":20,"startToken":6205,"endToken":6700,"text":"January 16, 2026 \nPage 10 \n610.666.8980 | www.pjm.com \nAppendix B \nLoad Forecasting: PJM Proposal and Load Analysis Subcommittee Work \nPJM Staff CIFP Proposal Features: \nState Review: \nPJM will add a step to the large load adjustment annual submission process that will allow for state commissions to \nreview and provide feedback on the large load adjustments submitted by TOs prior to finalizing and issuing the PJM \nLoad Forecast. The state review would occur, from a timeline perspective, in parallel with the large load addition \nsubmission to PJM. Though informal and within the discretion of each state, Electric Distribution Company \n(EDC)/LSEs would be required to indicate the date the EDC/LSEs shared the large load additions with the Relevant \nElectric Retail Regulatory authority (RERRA) and provide any feedback received. \nDuplicative Requests:  \nAs part of the large load adjustment annual submissions to PJM, TOs shall inquire with their subject customers, and \nindicate to PJM accordingly, whether any load interconnection requests they’ve received (that do not have either an \nElectric Service Obligation [ESO] or Construction Commitment [CC]) are duplicative with other such requests made \nto interconnect large load either within or outside of the PJM region such that only a subset of such requests are \nexpected to achieve actual commercial operation. If so, the submitters are required to provide the number of sites \nand amount of megawatts that are duplicative that are included in their submission. If the submitter does not provide \nthe number of sites and megawatts, or further sufficient justification and explanation, then all such requests will be \nremoved from the forecast. This will be added to the annual submission template. \nAdditional Review:  \nProvide additional industry-specific review of the PJM load forecast (i.e., cross-check with national-level forecast and \nequipment projections), which may include a third-party review. This third-party review, initiated by PJM, would weigh \nboth the national level trends as well as the inter-PJM trends that would help inform PJM’s load forecast. This review \nwould be presented to stakeholders for opportunity for feedback prior to finalizing for PJM consideration. \nTransparency: \nTo be included in the PJM load forecast, EDC/LSE/TO must ensure customer NDAs include the ability to share all \ninformation with PJM related to large loads and such information must be shared. \nLoad Analysis Subcommittee Enhancements: \n• \nLarge load coming online during a delivery year covered by an RPM auction for that forecast cycle \nwith CC or ESO contract of the load within the electric service provider’s territory will be considered \nfor inclusion in the PJM forecast plus a meaningful/verifiable financial commitment (such as \ncredit/collateral support, financially significant infrastructure investment, or long-term supply \ncommitment with new or existing resources).  \n• \nLarge load coming online beyond a delivery year covered by an RMP auction but less than 8 years \nwithout construction commitments will be considered for inclusion in the PJM forecast if they have \ncleared demonstrable project milestones to be considered certain and may be de-rated to reflect its \ngreater uncertainty."},{"page":21,"startToken":6700,"endToken":6879,"text":"January 16, 2026 \nPage 11 \n610.666.8980 | www.pjm.com \n• \nRequestors should provide a ramp rate with supporting documentation. Absent an EDC/LSE-\nprovided ramp rate, PJM will initially use a default 3-year ramp rate subject to further adjustment \nbased on a comparison of this default value with actual ramp rates of new large loads. \n• \nUtilization factor: PJM uses default historical factor (typically 70%) unless EDC/LSE provides \nsupporting data.  \nPJM will convene a series of meetings with EDCs and LSEs to improve large load modeling assumptions around \nramp rate and utilization. These invite-only meetings would need to maintain strict confidentiality in order to ensure a \nrobust conversation. Any information made public coming out of these meetings would need to be aggregated and \nanonymized and would be used to help with the formulation of large load additions as well as in PJM’s evaluation of \nlarge load additions.   \n• \nFinancial commitment: Document and quantify the customer's financial responsibility. This may align \nwith the rates and agreement provided or be reflected in the capital project plan of the requested \nEDC/LSE."},{"page":22,"startToken":6879,"endToken":7217,"text":"January 16, 2026 \nPage 12 \n610.666.8980 | www.pjm.com \nAppendix C \nExpedited Interconnection Track \nPJM Staff CIFP Proposal Features:  \nNew Expedited Interconnection Track (EIT) for sponsored generation with a contractual commitment. This proposal \nwould be standalone outside of the PJM interconnection cycle process and operate in parallel. Expedited timing \nallows shovel-ready resources to execute Generation Interconnection Agreements (GIAs) sooner and allows an \nearlier path toward construction and network upgrade certainly. \nContract/No Contract Requirements: \nGeneration with a contractual agreement: Available to new generation or uprates to existing generation supported by \nevidence of state commitment to expedite consideration of permitting and siting and a financial commitment with a \nload that has an executed electric service agreement to interconnect with the TO. The new generation or uprate to \nexisting generation must have an accredited capacity value equal to or greater than the load with which it is \ncontracted. \nGeneration without a contractual agreement: Available to new generation or uprates to existing generation supported \nby evidence of state commitment to expedite consideration of permitting and siting. Requires additional financial \ncommitments in the form of higher readiness deposits. \nTime Frame:  \n10 months from application \nGeneration Eligibility:  \nAll of the following criteria must be met – \n• \nCapacity resource status must be requested with the application along with Capacity Interconnection \nRights relevant to the fuel type being interconnected. \n• \nCommercial operations must be achieved within three years of the application submission. Output to the \ngrid may still be limited based on completion of any network upgrades required.  \n• \nPoint of Interconnection (POI) – must be interconnecting to the transmission system in the relevant state \nsupporting the project \n• \nMegawatt requirements – requests must be for large scale generation greater than 250 MW (UCAP). \n• \nResource fuel type – all fuel types eligible, including storage \nGeneration Application: \n• \nCan be submitted to PJM at any time – there are no defined EIT application windows. \n• \nAre prioritized serially, in the order as each application is received by PJM \n• \nLarge nonrefundable study deposit ($500,000) and readiness deposit \n– \n$10k/MW for generation paired with load"},{"page":23,"startToken":7217,"endToken":7355,"text":"January 16, 2026 \nPage 13 \n610.666.8980 | www.pjm.com \n– \n$20k/MW for generation not paired with load \n• \nApplications are capped annually at 10 projects. \n• \nMust provide 3 full years of site control for 100% of generating site and interconnection facilities at time of \napplication. \nGeneration Post-Application, Costs and Agreement Requirements: \n• \nThere are no site control changes or other project changes allowed such as fuel type, megawatt size, \nequipment type, etc. Changes post-GIA execution will follow the existing Necessary Study process. \n• \nCost allocation – EIT resources are responsible for 100% of all identified required network upgrades. No \ncost sharing with other EIT projects or Cycle projects. \n• \nCost estimates – for mitigations will be planning-level estimates only \n• \nCommercial operation no more than 3 years from the date of EIT application. Milestone dates are eligible \nfor extensions according to existing procedures."},{"page":24,"startToken":7355,"endToken":7651,"text":"January 16, 2026 \nPage 14 \n610.666.8980 | www.pjm.com \nAppendix D \nBoard Questions Regarding Capacity Auction Price Collar \n1. The existing price collar includes a price cap of $325 and a price floor of $175 adjusted for ELCC changes \nbefore each auction. Do you support any extension of the existing price collar? If so, at what level and for \nwhat period?  \n2. If you support an extension of the price collar, please provide the justification that you believe should be \npresented to FERC that supports your proposed level and time period being just and reasonable. \n3. If you do not support any extension of the price collar, please provide the justification that you believe \nshould be presented to FERC to support the argument that a short-term extension of the price collar is not \njust and reasonable.  \n4. To the extent you support an extension of the price collar, please explain how you believe such an \nextension would not adversely impact reliability or investment and when you believe the price collar could be \nlifted. \n5. To the extent you oppose an extension of the price collar as inhibiting needed investment in the short term, \nplease indicate the type of projects you believe could come into service during the delivery years covered by \nthese auctions and the potential impact of a collar extension on those project types. \n6. The Quadrennial Review, cosponsored by the Pennsylvania Public Utility Commission, was overwhelmingly \napproved by the stakeholders. Should the Board consider a transition mechanism to move from the existing \ncollar to Point A on the demand curve? Please provide your views on whether such a transition would be \nappropriate and the length and stages of such a transition and its consistency with the stakeholder support \nof the Quadrennial Review."},{"page":25,"startToken":7651,"endToken":7719,"text":"CERTIFICATE OF SERVICE \nI hereby certify that I have this day served the foregoing document on those parties on the \nofficial Service List compiled by the Secretary in these proceedings.   \nDated at Audubon, Pennsylvania this 20th day of January, 2026. \n \n/s/ Mark J. Stanisz \nMark J. Stanisz \nAssociate General Counsel  \nPJM Interconnection, L.L.C. \n2750 Monroe Blvd. \nAudubon, PA 19403 \nPh: (610) 666-4707 \nmark.stanisz@pjm.com"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":1,"endAt":932,"startToken":0,"endToken":134},{"p":1,"at":932,"title":"I. INFORMATIONAL FILING","method":"printed heading","endPage":9,"endAt":77,"startToken":134,"endToken":2083},{"p":9,"at":77,"title":"II. CONCLUSION","method":"printed heading","endPage":11,"endAt":869,"startToken":2083,"endToken":2287},{"p":11,"at":869,"title":"Executive Summary","method":"printed heading","endPage":25,"endAt":0,"startToken":2287,"endToken":7651},{"p":25,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":25,"endAt":429,"startToken":7651,"endToken":7719}]}