{"document":{"slug":"rec-20260202-5197","title":"Motion for Leave to Answer and Answer of Constellation Energy Generation, LLC in response to the rehearing request filed by the Indicated PJM Transmission…","issued":"2026-02-02","accession":"20260202-5197","docket":"EL25-49-000","group":"PJM co-location compliance","filer":"Constellation Energy Generation, LLC","kind":"rehearing request","file":"sources/filings/text/20260202-5197_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260202-5197","tier":"record","sha256":"512705ae2b37f07c8d6866f505c7891ba9044ed9f6f1a10d9512fd908e7b242c","pages":18,"tokens":6549,"emptyPages":[],"textThemes":["colo","flex","study","cost"]},"pages":[{"page":1,"startToken":0,"endToken":225,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \nPJM Interconnection, L.L.C., et al. \nLarge Loads Co-Located at Generating Facilities \nConstellation Energy Generation, LLC \n    v. \nPJM Interconnection, L.L.C. \n) \n \n \n)  \n \n \n)  \n) \n) \n) \n) \nDocket Nos. EL25-49-000 \nEL25-49-002 \n \nAD24-11-000 \nAD24-11-001 \n \n \nEL25-20-000 \nEL25-20-001  \n    (Consolidated) \nMOTION FOR LEAVE AND ANSWER OF \nCONSTELLATION ENERGY GENERATION, LLC  \nConstellation moves for leave and submits this answer1 in response to the rehearing request \nfiled by the Indicated PJM Transmission Owners2 in the above-captioned dockets. Remarkably, in \na proceeding with over 135 parties3 and a record spanning multiple dockets and thousands of pages, \nthere were only two requests for rehearing of the Commission’s December 18, 2025 Order.4 Of \nthese, only the Indicated TOs—now reduced from sixteen parties to two, Exelon and \n \n1 Constellation Energy Generation, LLC (“Constellation”) submits this answer and motion for leave pursuant to \nRules 212 and 213 of the Commission’s Rules of Practice and Procedure, 18 C.F.R. §§ 385.212 and 385.213.  \n2 Request for Rehearing of the Indicated PJM Transmission Owners (Jan. 16, 2026) (“Rehearing Request”). The \nIndicated PJM Transmission Owners (“Indicated TOs”) include Exelon and FirstEnergy and their subsidiaries. \n3 PJM Interconnection, L.L.C., 193 FERC ¶ 61,217, at App. A (2025) (“December 18th Order”). \n4 See Request for Clarification or, in the Alternative, Rehearing of the Industrial Customer Coalitions (Jan. 20, 2026)."},{"page":2,"startToken":225,"endToken":562,"text":"2 \nFirstEnergy5—argued that the Commission’s findings regarding Co-Located Load6 under \nsection 206 of the Federal Power Act (“FPA”) were arbitrary and capricious. Exelon and \nFirstEnergy’s position remains the same—Co-Located Loads should only be able to take Network \nIntegration Transmission Service (“Network Service” or “NITS”) and pay gross rates. But PJM \nand nearly every other party, including nearly all other PJM transmission owners, support or do \nnot contest that the Commission met its two-step showing under section 206 of the FPA to change \nthe PJM Tariff. \nConstellation respectfully submits there is good cause for the Commission to accept this \nanswer as it elaborates on points in the December 18th Order and is intended to aid the Commission \nin its decision-making to affirm the December 18th Order and deny Exelon and FirstEnergy’s \nrehearing request.7 \nI. \nThe Commission Satisfied the First Step of Section 206 of the FPA by Demonstrating \nthat PJM’s Tariff is Unjust and Unreasonable \nA. Record Evidence Shows Transmission Owners Interpret PJM’s Tariff \nDifferently \nExelon and FirstEnergy seek rehearing of the Commission’s finding that PJM’s Tariff “is \nunjust and unreasonable because it does not contain provisions addressing with sufficient clarity \nor consistency the rates, terms, and conditions of service,”8 arguing that the Commission’s finding \n \n5 Of the sixteen transmission owners joining Indicated PJM Transmission Owners’ March 24 Answer, two remain in \nsupport of the Rehearing Request. Compare Indicated PJM Transmission Owners March 24 Answer at 1 n.2 with \nsupra n.2. \n6 Unless otherwise defined, all capitalized terms have the same meaning as in the December 18th Order. \n7 See Alaska Gasline Dev. Corp., 171 FERC ¶ 61,134, at P 7 (2020) (accepting answers that “clarify the concerns \nraised and provide information that has assisted in our decision making”); Saltville Gas Storage Co., 164 FERC \n¶ 61,212, at P 2, n.6 (2018) (accepting answers that “assist the Commission in understanding the issues raised[] and \nwill ensure a complete record”). \n8 December 18th Order, 193 FERC ¶ 61,217 at PP 2, 159."},{"page":3,"startToken":562,"endToken":1100,"text":"3 \n“has no citation to evidence.”9 They claim “[t]here is none.”10 They further claim Sections 31 and \n32 of PJM’s Tariff “already … explain[] how Network Service works and how loads of Network \nCustomers will be served.”11 \nExelon and FirstEnergy are incorrect. Citing to the record, the December 18th Order states, \n“[m]any parties to this proceeding filed comments supporting the Commission’s preliminary \nfinding that PJM’s Tariff lacks sufficient clarity or consistency as to the rules for Co-Location \nArrangements.”12 In that proceeding, the Commission stated, “the record of proceedings before \nthe Commission appear to suggest that Transmission Owners are taking different approaches to \nperforming the steps necessary to accommodate a co-location arrangement and in the transmission \nservice that they are requiring entities to take.”13 The Commission acknowledged, “there are \n \n9 Rehearing Request at 14. \n10 Id. \n11 Id. at 15. \n12 December 18th Order, 193 FERC ¶ 61,217 at P 175 n.376 (citing Constellation May 8 Answer at 9 (“In sum, the \nrecord in this proceeding unequivocally supports the Commission’s preliminary finding that the PJM Tariff lacks \nclear co-location rules and is unjust and unreasonable.”); Advanced Energy United April 23 Reply Comments at 19 \n(“Loads and generators pursuing [C]o-[L]ocation [A]rrangements need clarity as to how these arrangements will be \nstudied, and how those studies will be evaluated. There must be a level of uniformity and detail outlining study \nrequirements to ensure regulatory certainty for large loads and new generation and storage resources seeking to serve \nlarge loads. This level of uniformity is currently lacking in PJM’s interconnection procedures and cost allocation \nmethodology ....”); EPSA/P3 April 23 Reply Comments at 2 (“EPSA and P3 agree with the Commission that PJM \nneeds to establish tariff provisions and rules to accommodate the array of [C]o-[L]ocated [L]oad arrangements that \nwill facilitate the timely and effective integration of large loads locating in the region.”); Data Center Coalition \nApril 23 Reply Comments at 7 (“... [T]he Commission should direct PJM to develop clear, enforceable tariff \nlanguage that affirms the permissibility of multiple co-location configurations, including those where load is served \ndirectly from a generation resource located on or near the same site. Tariff clarity is essential to reduce unnecessary \ndisputes, avoid case-by-case confusion, and enable transmission providers to process interconnection and load \naddition requests efficiently and predictably.”)); see also Invenergy Renewables LLC, et al. April 23 Comments at \n4 (“[T]here is little, if any, transparency on how M-3 studies are conducted, or the timeline for completing such \nstudies. Large load interconnection customers are already facing interconnection delays as a result of this \nuncertainty, and the lack of transparency is creating opportunities for undue discrimination that will decrease \ncompetition and raise systemwide costs.”); Complaint Requesting Fast Track Processing of Constellation Energy \nGeneration, LLC, Constellation Energy Generation, LLC v. PJM Interconnection, L.L.C., FERC Docket No. EL25-\n20-000 (filed Nov. 22, 2024) at 6 (“Even before the Susquehanna ISA Order, local utilities were taking advantage \nof the lack of clarity in the Tariff to block or delay competition to serve data centers.”). \n13 PJM Interconnection, L.L.C., 190 FERC ¶ 61,115, at P 75 (2025) (“Order Instituting Show Cause”)."},{"page":4,"startToken":1100,"endToken":1493,"text":"4 \nallegations in the record that Exelon has delayed work on Constellation’s requests to co-locate \nload with its generators … due to Exelon’s concerns that such requests are not allowed under the \nTariff” and “[o]n the other hand, as a factual matter, … PPL allowed a generator in its service \nterritory to enter into a co-location arrangement without requiring the co-located load to take \nNetwork Integration Transmission Service.”14 \nThe record affirms that PJM’s Tariff is being inconsistently interpreted. Exelon’s own \nwitness agreed, “what we could really use is … some clarity around the rules of the road, so that \n… we don’t have non-conforming agreements, and we don’t have language that doesn’t exist in \nthe tariffs. And we’re in a place where … we’re all handling and interconnecting these important \nloads in the same manner.”15 The testimony of Zach Ming demonstrated that the lack of clarity in \nPJM’s Tariff has “result[ed] in different interpretations and applications of the tariff by different \ntransmission owners within PJM.”16 Like the Commission, Mr. Ming found that “[s]everal \ntransmission owners have interpreted the tariff as requiring all loads (co-located or not) to be \nserved under NITS” and “[o]ther transmission owners have interpreted the tariff as allowing co-\nlocated configurations.”17 Mr. Ming’s testimony also discussed how even PJM’s interpretation of \nits Tariff changed over time.18 \n \n14 Id.  \n15 Transcript of November 1, 2024 Large Loads Co-Located at General Facilities Technical Conference, Docket No. \nAD24-11-000, at 100-101 (Comments of Dave Weaver, Vice President of Transmission Strategy, Exelon Utilities).  \n16 Constellation April 23 Answer, Exh. 2 at 19:5-6 (Testimony of Zach Ming) (“Ming Testimony”). \n17 Id. at 19:6-20.  \n18 Id. at 20:3-6 (“Even PJM until recently supported the notion that ‘[c]o-located must either be PJM Network Load \n(with applicable firm transmission service[)] or not PJM Network Load (load without applicable transmission \nservice[)].’”); see also Constellation April 23 Reply Comments at 13 n.30 (“PJM recently rescinded the Guidance \nDocument despite previously relying on that Guidance Document in developing changes to the ISA for \nSusquehanna. Similarly, PPL Electric Utilities Corporation (‘PPL’) agreed to the co-located load arrangement for \nSusquehanna without requiring NITS, but now, as an Indicated Transmission Owner, takes the view that co-located \nload must be a Network Customer, taking NITS. Even earlier, PJM had issued guidance in the form of a ‘Frequently"},{"page":5,"startToken":1493,"endToken":1896,"text":"5 \n“The fact that different transmission owners are interpreting the tariff differently is an \nobvious indicator of the ambiguity of the existing tariff.”19 As the Order Instituting Show Cause \npreliminarily found, “this lack of applicable Tariff provisions raises the potential for undue \ndiscrimination or preferential treatment.”20 There is ample record evidence of transmission owner \nmonopolistic behavior for the Commission to conclude with finality that undue discrimination has \noccurred.21 The Commission did not tolerate such monopolistic behavior when it justified \nimposing open access requirements, and it should not do so here.22 \nB. Record Evidence Supports that PJM’s Tariff is Unjust and Unreasonable \nBecause it Does Not Include Flexible Load Transmission Services \nExelon and FirstEnergy argue there is no evidentiary support for the “building-block \nassumptions”23 upon which the Commission found “PJM’s Tariff is unjust and unreasonable \nbecause it does not include transmission services that reflect an Eligible Customer taking service \non behalf of a Co-Located Load that is willing and able to limit its energy withdrawals from the \n \nAsked Questions’ document on co-location, which also contemplated co-location configurations other than the \nNITS-only approach now prevailing at some transmission owners’ instigation.”) (citations removed). \n19 Ming Testimony at 20:10-12. \n20 Order Instituting Show Cause, 190 FERC ¶ 61,115 at P 75; see also id. (“We find that these dynamics raise the \npotential for undue discrimination—albeit, in this example, by the Transmission Owners, not PJM—due to the lack \nof Tariff provisions governing colocation arrangements.”). \n21 See, e.g., Constellation April 23 Reply Comments at 14 (“Some of the Indicated Transmission Owners have refused \nto process necessary studies, demanded expensive upgrades under their unfiled interconnection procedures, and \nforced a generator seeking to serve co-located load to procure additional services not required by the Tariff.”) (citing \nComplaint Requesting Fast Track Processing of Constellation Energy Generation, LLC, Docket No. EL25-20- 000, \nat 7 (filed Nov. 22, 2024) (citing Protest of Constellation Energy Generation, LLC, Docket No. EL24-149-000, \nExh. 2 (correspondence with Exelon) (filed Oct. 30, 2024); Motion to Lodge of Constellation Energy Generation, \nLLC, Docket No. EL24-149-000, Exh. 1 (November 12, 2024 Exelon Letter) (filed Nov. 18, 2024))). \n22 Promoting Wholesale Competition Through Open Access Non-Discriminatory Transmission Servs. by Pub. Utils.; \nRecovery of Stranded Costs by Pub. Utils. & Transmitting Utils., Order No. 888, FERC Stats. & Regs. ¶ 31,036, \n31,682 (1996) (cross-referenced at 75 FERC ¶ 61,080 (1996)). \n23 Rehearing Request at 22."},{"page":6,"startToken":1896,"endToken":2503,"text":"6 \ntransmission system under certain conditions.”24 First, Exelon and FirstEnergy state that \narguments stating large loads are “unable to interconnect or are experiencing delays” are “false \nand any delay is of their own making.”25 The record is replete with evidence “suggesting \notherwise.”26 As stated in the Affidavit of Michael Kormos, the former Chief Operating Officer of \nPJM, “traditional utility models for connecting large load directly to the grid are proving \nineffective at keeping pace with demands of new large loads and are taking five years or longer to \nconnect such load.… [W]ait times for new large load connections in PJM are taking even longer \n– as long as seven to ten years.”27 Other record evidence shows the same.28 \n \n24 December 18th Order, 193 FERC ¶ 61,217 at PP 2, 159. In support of the Commission’s finding, the Commission \nstated, “[r]equiring [NITS] could necessitate inefficient and costly transmission buildout and costs paid by \ntransmission customers that may not be necessary if Eligible Customers taking transmission service on behalf of \nCo-Located Loads are willing to limit their energy withdrawals and take a transmission service that requires fewer \nNetwork Upgrades to provide.” Id. P 199. The Commission also stated, “requiring … Eligible Customers to take \nNITS on behalf of … Co-Located Loads may in some circumstances result in costly and inefficient transmission \nsystem buildout that may not be necessary if such Eligible Customers are willing and able to take a transmission \nservice that requires fewer Network Upgrades to provide, and therefore may result in lower Network Upgrade costs, \nthan would NITS.” Id. P 177. \n25 Rehearing Request at 6. \n26 Id. at 18. \n27 Constellation April 23 Reply Comments, Exh. 5, at ¶ 3 (Affidavit of Michael Kormos). \n28 See, e.g., Michael Kormos, The Co-Located Load Solution, Docket No. AD24-11-000, at 2 (Nov. 4, 2024) (“The \nstandard utility models are struggling to accommodate large data center projects on a workable timeline, and can \ntake five years or longer.”); Intersect Power, LLC Dec. 9 Comments, Docket No. AD24-11-000, at 2 (“Large loads \nface backlogs and multi-year delays, similar to those faced by generating resources in standard interconnection \nprocesses. Large loads cannot wait years for power supply arrangements, or they risk losing business to their \ncompetition, including overseas competition.”) (citing Todd Shatzki, Joseph Cavicchi, Megan Accordino, Co-\nLocated Load: Market, Economic, and Ratemaking Implications, Analysis Group, at 14 (Oct. 28, 2024) (“Co-\nLocated \nLoad”), \nhttps://www.analysisgroup.com/globalassets/insights/publishing/2024_co_located_load_market_economic_and_ra\ntemaking_implications.pdf); Co-Located Load at 12 (“Several utilities have reported that the expected wait time for \nconnecting new large loads is as long as 7 to 10 years. AEP Ohio has responded to the influx of requests by \nsuspending acceptance of new load service agreements from data center customers, to give the utility time to study \nthe potential impacts of the proposed additions on its transmission and distribution systems.”); id. at 12 n.43 (“Grant \nPUD estimates a wait time of 7-10 years. Dominion Energy expects the time it takes to connect large data centers to \nthe electric grid to increase by one to three years amid a surge in requests, bringing the total wait time to as long as \nseven years…. AEP Ohio has stated that, because Central Ohio lacks RTO-controlled generation, serving new data \ncenter load will require investment in extra high voltage transmission to import power from other parts of the grid. \nThat investment, AEP says, could take 7-10 years to plan, design, site, and construct.”); see also Joint Electricity \nCustomer Alliance Oct. 30 Comments, Docket No. AD24-11-000, at 1 (“When properly executed, co-location aims"},{"page":7,"startToken":2503,"endToken":3095,"text":"7 \nSecond, Exelon and FirstEnergy argue there is “no evidence” for finding “Co-Located \nLoads may be able to receive transmission service faster with use of a new, limited transmission \nservice product than they would if they selected NITS, to the extent that providing NITS would \nrequire Network Upgrades that the limited transmission service would not.”29 Again, record \nevidence contradicts Exelon and FirstEnergy’s claim. In his testimony, Mr. Ming states, “[m]aking \ninterruptible service available on an interim basis provides the important benefit of facilitating \nfaster interconnection for loads …. This is because transmission reinforcements and network \nupgrades required for a generator-contingent or firm configuration can take many years to plan \nand build.”30 Other evidence states similarly.31 \n \nto reduce overall costs, not shift them. It is a rational response given the slow pace of transmission and generation \ndevelopment across the grid, driven by interconnection delays, for both load and generation, and poor regional \ntransmission planning.”); Mainspring Energy, Inc. April 23 Comments, at Attachment at 2 (“New load \ninterconnection also faces significant delays. Some data center customers report that they’re being given 3-5 year \nestimates for grid delivery of data center power. For a 100 MW data center, assuming US$150,000/MW of revenue \nper month (~US$150/month/kW), three years of delay translates to over US$500M in lost revenue.”); Dr. Paul \nStockton, et al. April 22 Letter from National Security Experts, at 1 (“In some states, including those in the Eastern \nUS served by PJM Interconnection, L.L.C., data centers seeking to connect and take service from the grid may face \ndelays of seven to ten years before they can receive power. Those delays are unconscionable, given the DOD’s \nrapidly growing requirements for AI services and the imperative to counter China’s drive for AI primacy.”); \nConstellation April 23 Reply Comments, Exh. 1 at 9 n.38 (Declaration of Dr. Paul Stockton) (“AI, data center \nelectricity demand could drive advanced nuclear investment: NERC head Jim Robb,” Utility Dive (June 6, 2024) \n(“it takes me about four years to build a substation,” according to David Schleicher, Northern Virginia Electric \nCooperative \nCEO), \nhttps://www.utilitydive.com/news/ai-datacenter-electricity-demand-advanced-nuclear-\ninvestment-Robb/718181/; “Elk Grove Mayor Meets With ComEd on Substations for Data Centers,” Journal & \nTopics (Mar. 14, 2024) (Mayor of Elk Grove, Illinois, “expressed frustration with ComEd, saying the electricity \nutility was ‘dragging their feet’ in building substations to support the growing data center industry”), \nhttps://www.journal-topics.com/articles/elk-grove-mayor-meets-with-comed-on-substations-for-data-centers/); \nStatement of Cole Muller, Executive Vice President of Strategic Ventures Talen Energy Corporation, Docket \nNo. AD24-11, at 2 (Oct. 16, 2024) (“Co-locating data center load with generation allows the load to be served \nefficiently and economically. The alternative in many cases is years-long delays to connect in front of the meter, \ni.e., directly to the grid.”). \n29 Rehearing Request at 20 (quoting December 18th Order, 193 FERC ¶ 61,217 at P 205). \n30 Ming Testimony at 49:6-10; id. at 22:14-16 (“[U]nnecessary and inefficient costs may slow down–or even \ndiscourage–the interconnection of new beneficial load, which would hinder the interests of the United States.”). \n31 See Enchanted Rock April 23 Reply Comments at 5 (“Enabling a temporary flexibility option that large loads can \nopt into would therefore mitigate some of these risks and allow for faster load interconnection.”); id. at 9 (“The \nLCDG option provides more than a traditional demand response or peak shaving program during the operating \nperiod. The flexibility provided by the LCDG option would be considered in the planning and study process for"},{"page":8,"startToken":3095,"endToken":3564,"text":"8 \nThird, Exelon and FirstEnergy argue “there is no evidence that the cost of paying for \nNetwork Service deters service or has any impact whatsoever on development of data centers.”32 \nThe Commission did not find that the cost for Network Service deters data centers. The \nCommission found that “[i]t would be inconsistent with cost causation principles” to charge Co-\nLocated Loads the same as Network Load, and that “Co-Located Loads should be allowed to \nchoose the transmission service that aligns with their use of the transmission system and therefore \naligns the charges for service with the benefits received.”33 This too is supported by record \nevidence. “Charging customers that impose different costs on the system in an equivalent manner \nis misaligned with the principle of fair apportionment of costs and is inequitable.”34 \nC. The Commission’s Precedent Prohibiting “Split Load” for Network Service Is \nInapplicable \nExelon and FirstEnergy argue that the Commission’s Contract Demand services depart \nfrom its precedent on “split load” without explanation.35 This argument misses the mark. The \n \nlarge load interconnection, local and regional planning, and resource adequacy. The LCDG option therefore permits \nlarge loads to utilize flexibility to achieve faster interconnection through the deployment of dispatchable, co-located \ngeneration. Under the LCDG option, the firm commitment to dispatch co-located generation would serve as a bridge \nto permanent grid upgrades for projects that would otherwise be delayed while new infrastructure is planned, \npermitted, and constructed.”); id. at 14 (“it may defer the need for certain upgrades for reliable interconnection until \nsuch time that infrastructure expansion can occur. Consideration for colocated arrangements in the retail load \nintegration process would also allow for faster load interconnections and mitigates commercial risks for both load \nand generation developers”); Advanced Energy United April 23 Reply Comments at 16-17 (discussing a co-location \narrangement that “co-locates load with dispatchable generation to allow for load flexibility and use of as-available \ntransmission service until necessary transmission upgrades make it possible for the load to fully integrate into the \nsystem” and “would allow for faster interconnection for load that brings its own generation and has the ability to be \nflexible.”) (citation omitted). \n32 Rehearing Request at 18. \n33 December 18th Order, 193 FERC ¶ 61,217 at P 199. \n34 Ming Testimony at 21:19 to 22:1-2. \n35 Rehearing Request at 22-30 (citing Nat’l R.R. Passenger Corp. v. PPL Elec. Utils. Corp., 173 FERC ¶ 61,043 \n(2020); Promoting Wholesale Competition Through Open Access Non-Discriminatory Transmission Services by \nPublic Utilities; Recovery of Stranded Costs by Public Utilities and Transmitting Utilities, Order No. 888-A, 78 \nFERC ¶ 61,220 (1997), order on reh’g, Order No. 888-B, 81 FERC ¶ 61,248 (1997), order on reh’g, Order No. 888-\nC, 82 FERC ¶ 61,046 (1998), aff’d in relevant part sub nom. Transmission Access Pol’y Study Grp. v. FERC, 225"},{"page":9,"startToken":3564,"endToken":3890,"text":"9 \nCommission has explained, “splitting a discrete load is antithetical to the concept of network \nservice” because “a load at a discrete point of delivery cannot be partially integrated—it is either \nfully integrated or not integrated.”36 Contract Demand services are not Network Service. Nor do \nContract Demand services raise the same cost causation concerns as the split load contemplated in \nOrder No. 888-A.37 “Firm Contract Demand transmission service customers will be charged based \non their contract demand irrespective of usage and therefore will not be able to reduce their load-\nratio cost responsibility.”38 In addition, “PJM will only plan the transmission system and procure \ngeneration capacity for [Firm Contract Demand]—not for load growth, like it does for NITS \ncustomers—and PJM will have no obligation to serve … beyond the contract demand.”39 \nSimilarly, PJM has no obligation to plan the transmission system or procure generation for Non-\nFirm Contract Demand service.40 \nII. \nThe Commission Satisfied the Second Prong of Section 206 of the FPA by Fixing a Just \nand Reasonable Replacement Rate \nA. The Commission Has the Authority to Establish New Transmission Services \nContrary to Exelon and FirstEnergy’s argument, the Commission’s order did not exceed \nits jurisdiction. As the Commission correctly observed, the FPA provides the Commission with \n \nF.3d 667 (D.C. Cir. 2000), aff’d sub nom. New York v. FERC, 535 U.S. 1 (2002); Fla. Power & Light, 113 FERC \n¶ 61,290 (2005), aff’d on rehearing, 116 FERC ¶ 61,012 (2006), aff’d on appeal, 264 F. App’x 4 (D.C. Cir. 2008); \nIdaho Power Co., 106 FERC ¶ 61,329 (2004); Ameren Servs. Co. v. Prairieland Energy Inc., 131 FERC ¶ 61,125 \n(2010); Ariz. Pub. Serv. Co., 151 FERC ¶ 61,191 (2015)). \n36 December 18th Order, 193 FERC ¶ 61,217 at P 196 (quoting Order No. 888-A, FERC Stats. & Regs. ¶ 31,048 at \n30,262) (emphasis added). \n37 Id. P 211. \n38 Id. \n39 Id. \n40 Id. P 218."},{"page":10,"startToken":3890,"endToken":4234,"text":"10 \njurisdiction over “the transmission of electric energy in interstate commerce.”41 The FPA does not \nlimit the Commission’s “transmission jurisdiction to the wholesale market”42; to the contrary, “the \nFPA authorizes FERC’s jurisdiction over interstate transmissions, without regard to whether the \ntransmissions are sold to a reseller or directly to a consumer.”43 The Commission therefore \ncorrectly concluded that it “has exclusive jurisdiction over the provision of transmission service \nused by an Eligible Customer to serve Co-Located Load” when the transmission is in interstate \ncommerce.44 And because the Commission has jurisdiction over the provision of such transmission \nservice, it has the authority to regulate the type of transmission service taken by “an Eligible \nCustomer taking transmission service on behalf of a Co-Located Load,” whether that service is \nNetwork Service (to which Exelon and FirstEnergy do not object) or Contract Demand services.    \nIn nonetheless asserting that the Commission has exceeded its jurisdiction, Exelon and \nFirstEnergy make two arguments, neither of which has merit. First, they argue that the \nCommission’s replacement rate violates the major questions doctrine.45 But the major questions \ndoctrine has no role to play here. It is reserved for “extraordinary cases” where an agency leverages \na statute’s “modest words,” “vague terms,” or “subtle devices” to give itself “sweeping and \nconsequential authority.”46 That is not the case here. The FPA clearly and “unambiguously”47 gives \nthe Commission broad authority over “the transmission of electric energy in interstate \n \n41 16 U.S.C. § 824(b)(1); see also December 18th Order, 193 FERC ¶ 61,217 at P 166. \n42 New York v. FERC, 535 U.S. 1, 17 (2002). \n43 Id. at 20. \n44 December 18th Order, 193 FERC ¶ 61,217 at P 173; see also New York, 535 U.S. 1, 16 (“[W]e agree with FERC \nthat transmissions on the interconnected national grids constitute transmissions in interstate commerce.”). \n45 Rehearing Request at 12, 52-53. \n46 West Virginia v. EPA, 597 U.S. 697, 721, 723 (2022) (quotations omitted and alteration removed).  \n47 New York, 535 U.S. 1, 19."},{"page":11,"startToken":4234,"endToken":4598,"text":"11 \ncommerce,”48 and the Commission is entitled to regulate such transmission consistent with its \nstatutory authority, just as it did in promulgating Order No. 88849 and just as it did here. \nSecond, Exelon and FirstEnergy argue that the Firm and Non-Firm Contract Demand \nservices provided in the Commission’s replacement rate “interfere with States’ regulation of the \nterms of sale at retail,” thereby indirectly intruding on the States’ authority. But whether the \nCommission’s replacement rate has “natural consequences at the retail level”50 does not change \nthe fact that the Commission is acting here pursuant to its express jurisdiction over the transmission \nof electricity in interstate commerce. As the Supreme Court has explained, “[w]hen FERC \nregulates what takes place on the wholesale market, as part of carrying out its charge to improve \nhow that market runs, then no matter the effect on retail rates, §824(b)[’s limitation on FERC’s \nretail sale jurisdiction] imposes no bar.”51 That is no less true of the Commission’s transmission \njurisdiction, and ensuring that transmission rates remain just and reasonable—as the Commission \ndid here by allowing for Contract Demand services—“falls within the sweet spot of FERC’s \nstatutory charge.”52 \nIndeed, Exelon and FirstEnergy have it exactly backward. To conclude that the States’ \nauthority over retail sales prohibits the Commission from regulating interstate transmission rates—\nas Exelon and FirstEnergy urge—would upend the FPA’s balance of federal and State jurisdiction. \n \n48 16 U.S.C. § 824(b)(1). \n49 See New York, 535 U.S. 1, 23 (2002). \n50 FERC v. Elec. Power Supply Ass’n, 577 U.S. 260, 281 (2016); see also id. (“When FERC sets a wholesale rate, \nwhen it changes wholesale market rules, when it allocates electricity as between wholesale purchasers—in short, \nwhen it takes virtually any action respecting wholesale transactions—it has some effect, in either the short or the \nlong term, on retail rates. That is of no legal consequence.”) \n51 Id. at 281-82 (emphasis added); see also id. at 281 (“[A] FERC regulation does not run afoul of §824(b)’s \nproscription just because it affects – even substantially – the quantity or terms of retail sales.”). \n52 Id. at 287."},{"page":12,"startToken":4598,"endToken":5015,"text":"12 \nIn fact, “even when States exercise their traditional authority over retail rates,” the “States may not \nseek to achieve ends, however legitimate, through regulatory means that intrude on FERC’s \nauthority over interstate wholesale rates.”53 The Commission should reject any argument that the \nStates’ jurisdiction over retail sales limits the Commission’s jurisdiction to allow for non-Network \nService in Co-Located Load arrangements and thereby regulate the interstate transmission of \nelectricity.  \nB. The Replacement Rate is Not Unduly Discriminatory or Preferential \nExelon and FirstEnergy argue that Interim Service and Contract Demand services “would \ngrant an undue preferential rate for co-located loads.”54 This argument is unavailing. Courts have \nlong held that, “undue discrimination occurs only if the entities are ‘similarly situated,’ such that \n‘there is no reason for the difference.’”55 The courts have also given the Commission “‘wide \ndiscretion … to determine what constitute[s]’ undue discrimination.”56 \nCo-located loads that are subject to express limitations on their right to service are not \nsimilarly situated to traditional network load that relies on NITS. The December 18th Order \n \n53 Hughes v. Talen Energy Mktg., LLC, 578 U.S. 150, 164-65 (2016); see also Nantahala Power & Light Co. v. \nThornburg, 476 U.S. 953, 966 (1986) (“Once FERC sets such a rate, a State may not conclude in setting retail rates \nthat the FERC-approved wholesale rates are unreasonable.”). \n54 Rehearing Request at 34; see also id. at 3 (“The Commission’s replacement rate that imposes new CD Service and \nInterim Service options could … grant an undue preference to certain categories of customers.”); id. at 36 (“The \nCommission, by requiring the new forms of service discussed above, would establish rates that grant an undue \npreference or advantage to co-located loads.”); id. at 38 (“the new service grants an undue preference for co-located \nloads.”); id. at 52 (“[T]he replacement rate directed by FERC—because it favors a narrow category of customers \n(i.e., co-located load) without reasoned explanation—violates the requirement in the FPA that no rate by a public \nutility grants an undue preference or advantage or unreasonable difference in rates.”). \n55 Mo. River Energy Servs. v. FERC, 918 F.3d 954, 958 (D.C. Cir. 2019) (quoting State Corp. Comm’n v. FERC, 876 \nF.3d 332, 335 (D.C. Cir. 2017); Transmission Access Policy Study Grp. v. FERC, 225 F.3d 667, 721 (D.C. Cir. \n2000)). \n56 Mo. River Energy Servs., 918 F.3d at 958 (quoting Transmission Access Policy Study Grp. v. FERC, 225 F.3d \nat 721)."},{"page":13,"startToken":5015,"endToken":5444,"text":"13 \nexplains co-location arrangements will have a “reduced impact on the transmission system … as \ncompared to traditional Network Load.”57 In addition, the December 18th Order states co-located \nload arrangements will “not require PJM to plan the transmission system to serve these Co-Located \nLoads to the same extent as PJM must plan the transmission system to serve Network Load, \npossibly reducing the need for new Network Upgrades.”58 These findings are neither “fiction” nor \n“false presumption[s].”59 Indeed, as Mr. Ming stated, “[n]one of the configurations of co-located \nload … impose the same costs on the transmission system as a NITS customer that is directly \nconnected to the transmission system.”60 \nC. The Replacement Rate Promotes Competition \nExelon and FirstEnergy argue the new transmission services are “an illegal effort to stifle \ncompetition” that “flout” the Commission’s open-access policies.61 This argument should be \nrejected. The new transmission services “promote competition”62 by allowing Co-Located Loads \n \n57 December 18th Order, 193 FERC ¶ 61,217 at P 205 (citing PJM March 24 Response at 13-15, 18-19; Glatz and \nSilverman April 23 Reply Comments at 12-13; Constellation April 23 Reply Comments at 65; Vistra April 23 Reply \nComments at 28) (emphasis added). See also SEIA April 23 Reply Comments at 8 (citing Duke University’s \nNicholas Institute for Energy, Environment & Sustainability, Rethinking Load Growth: Assessing the Potential for \nIntegration \nof \nLarge \nFlexible \nLoads \nin \nUS \nPower \nSystems \n(“Duke \nStudy”) \nhttps://nicholasinstitute.duke.edu/sites/default/files/publications/rethinking-load-growth.pdf (2025) (“Co-located \nloads with the ability to curtail or shift demand in coordination with generator output or grid constraints should be \ntreated differently than firm grid-dependent load, as these loads would be capable of reducing their demand on the \ngrid.”)). \n58 December 18th Order, 193 FERC ¶ 61,217 at P 205 (citing Enchanted Rock April 23 Reply Comments at 17) \n(emphasis added); see also id. P 211 (“PJM will only plan the transmission system and procure generation capacity \nfor the contract demand—not for load growth, like it does for NITS customers”); Kormos, The Co-Located Load \nSolution, at 8 (“By placing a data center where it can be directly served by a generator versus locating the load \nsomewhere remote from the ultimate generation needed to serve it, the grid requires fewer upgrades to serve that \nnew demand.”).  \n59 Rehearing Request at 4. \n60 Ming Testimony at 21:17-20. \n61 Rehearing Request at 40. \n62 FERC, Fact Sheet: FERC Directs Nation’s Largest Grid Operator to Create New Rules to Embrace Innovation and \nProtect Consumers (Dec. 18, 2025), https://www.ferc.gov/news-events/news/fact-sheet-ferc-directs-nations-largest-"},{"page":14,"startToken":5444,"endToken":5852,"text":"14 \nto take transmission services other than Network Service.63 With more options available, Co-\nLocated Load is no longer “beholden to taking Network or Point-to-Point firm transmission service \non the TO’s terms (and at their pace), or fully isolated and completely disconnected Behind-the-\nMeter subject to state jurisdiction.”64 Likewise, load seeking to co-locate with a generator is also \nno longer forced by transmission owners to procure additional services not required by the Tariff.65 \nD. The Replacement Rate Addresses Reliability \nThe Commission should reject Exelon and FirstEnergy’s argument that the replacement \nrate is not just and reasonable because the Commission “disregard[ed]” reliability considerations.66 \nA review of the December 18th Order shows otherwise.67 The Commission explained the new \nInterim Service “will facilitate the timely provision of transmission service to Eligible Customers \ntaking transmission service on behalf of Co-Located Loads, while preserving reliability for other \n \ngrid-operator-create-new-rules-embrace?new= (“As technology leaps forward, clear and fair regulations must keep \npace to support advancement, help prevent price volatility, and promote competition, ultimately benefitting \nconsumers by keeping electricity costs manageable.”). \n63 December 18th Order, 193 FERC ¶ 61,217 at P 195 (“While we find that NITS charged on a gross demand basis is \none just and reasonable transmission service option for Eligible Customers taking transmission service on behalf of \nCo-Located Loads, it is not the only option. This order establishes new transmission service options that Eligible \nCustomers taking transmission service on behalf of Co-Located Loads may use if they do not wish to take NITS on \na gross demand basis.”); see also Transcript of December 18, 2025 Open Meeting at 25, \nhttps://www.ferc.gov/media/transcript-december-18-2025-open-meeting (Commissioner See stating, “Today’s \norder chooses an options-based approach over a one-size-fits-all solution.”). \n64 EPSA/P3 April 23 Reply Comments at 12. \n65 See supra note 21. \n66 Rehearing Request at 49. \n67 See, e.g., December 18th Order, 193 FERC ¶ 61,217 at P 227 (“PJM’s necessary study process, as reflected in the \nrecord, assesses any special protection scheme that is a part of a Co-Location Arrangement.”); id. P 212 (“PJM will \ndetermine the technical and engineering requirements of special protection schemes to help address reliability risks \nassociated with unreserved use of the transmission system.”); id. P 227 (discussing measures that will “provide \nadditional clarity and transparency regarding the steps that PJM and Interconnection Customers are taking to \nmaintain transmission system reliability before an existing generating facility can serve Co-Located Load.”)."},{"page":15,"startToken":5852,"endToken":6223,"text":"15 \ntransmission customers.”68 PJM similarly described this option as “providing an opportunity for \nlarge load to integrate as a non-capacity backed load … if willing to curtail to support reliability \nin advance of emergency conditions” and as a preferred option as PJM “maintains resource \nadequacy.”69 \nThe Commission should also reject Exelon and FirstEnergy’s arguments that the \nDecember 18th Order does not address “risks associated with protective system failures or \nremoval” raised in the record and does not provide “guideposts” on Interim Service.70 These \narguments are at best premature. The Commission appropriately requested briefing on \ninterconnection requirements and operational practices necessary for special protection schemes \nand procedures for PJM to curtail Interim Service.71 In addition, as cited by the December 18th \nOrder, the testimony of Steven Herling, PJM’s former Vice President of Planning, addresses the \nrisks associated with protective system failures or removal.72 Based on his over 30-year experience \nat PJM, Mr. Herling explained, “protection schemes are regularly employed on the PJM \ntransmission system, and the successful operation of such protective systems is a common \nobservance within PJM.”73 “The protection system … is fully redundant and, while it cannot be \nguaranteed to never fail, it is unreasonable to treat the failure of both primary and secondary relay \n \n68 Id. P 205, n.436 (“Proper special protection scheme design is also subject to NERC standards to ensure they do not \nintroduce unintentional or unacceptable reliability risks to the system.”) (citing Remedial Action Schemes Reliability \nStandard, Order No. 837, 160 FERC ¶ 61,071 (2017) (approving Reliability Standard PRC-012-2)) (emphasis \nadded). \n69 PJM March 24 Answer at 18 (capitalization removed). \n70 Rehearing Request at 49-50. \n71 December 18th Order, 193 FERC ¶ 61,217 at P 219. \n72 Id. P 205, n.436. See also Vistra Corp. May 8 Answer, at Att. A ¶ 21 (Herling testifying that “It is also important to \nnote that the voltage-sensitivity issue underlying the 1,500 MW load loss event cited by NERC is not a co-location \nissue. Nothing in the NERC Comments or the attached materials suggests that any of the data centers involved in \nthe event were co-located with generating resources.”). \n73 Constellation April 23 Reply Comments, Exh. 3 at ¶ 23 (Affidavit of Steven Herling)."},{"page":16,"startToken":6223,"endToken":6320,"text":"16 \nsystem facilities following the loss of a generator as anything other than a third contingency.”74 \n“PJM does not plan for or require upgrades for such third contingencies, nor would it be reasonable \nto do so, short of events that would result in a cascading outage of grid facilities.”75 \nCONCLUSION \nConstellation submits that good cause exists to accept this answer because it should assist \nthe Commission as it determines whether to deny Exelon and FirstEnergy’s request for rehearing. \nThe Commission should deny the Rehearing Request and affirm its December 18th Order. \n \n \n74 Id.  \n75 Id."},{"page":17,"startToken":6320,"endToken":6468,"text":"17 \n \n \n \n \n \n \n \n    Respectfully submitted, \n \n \n \n \n \n \n \n    /s/ Paul F. Wight \n \nFebruary 2, 2026 \n \n \nCarrie Hill Allen \nSr. Vice President & Deputy General Counsel \nSeth Lucia \nAssistant General Counsel \nConstellation Energy Generation, LLC \n250 Massachusetts Ave. NW, Suite 760 \nWashington, D.C. 20001 \ncarrie.allen@constellation.com \nseth.lucia@constellation.com \n  \nChristopher A. Wilson \nManaging Director, Federal Regulatory Affairs \nConstellation Energy Generation, LLC \n250 Massachusetts Ave. NW, Suite 760 \nWashington, D.C. 20001 \n202-347-7500 \nFERCe-filings1@constellation.com \n \nPaul F. Wight \nCarolyn E. Clarkin \nDLA Piper LLP (US) \n500 Eighth Street NW \nWashington, D.C. 20004 \n703-773-4058 \npaul.wight@us.dlapiper.com \ncarolyn.clarkin@us.dlapiper.com \n \nSophia Browning \nDLA Piper LLP (US) \n4365 Executive Drive \nSan Diego, CA 92121 \n858-677-1455 \nsophia.browning@us.dlapiper.com  \n \nJacob I. Chefitz \nDLA Piper LLP (US) \n1251 Avenue of the Americas  \nNew York, NY 10020  \n212-335-4500 \njacob.chefitz@us.dlapiper.com \n \nCounsel for Constellation Energy \nGeneration, LLC"},{"page":18,"startToken":6468,"endToken":6549,"text":"18 \nCERTIFICATE OF SERVICE \nI hereby certify that I have on this 2nd day of February 2026, caused to be served a copy \nof the foregoing upon all parties on the service lists in these proceedings in accordance with the \nrequirements of Rule 2010 of the Commission’s Rules of Practice and Procedure, 18 C.F.R. \n§ 385.2010. \n/s/ Semhal Gebrekirstos \nSemhal Gebrekirstos \nDLA Piper LLP (US) \n500 Eighth Street NW \nWashington, D.C. 20004 \n202-799-4471 \nsemhal.gebrekirstos@us.dlapiper.com"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":2,"endAt":877,"startToken":0,"endToken":360},{"p":2,"at":877,"title":"I. The Commission Satisfied the First Step of Section 206 of the FPA by Demonstrating","method":"printed heading","endPage":2,"endAt":1011,"startToken":360,"endToken":382},{"p":2,"at":1011,"title":"A. Record Evidence Shows Transmission Owners Interpret PJM’s Tariff","method":"printed heading","endPage":5,"endAt":645,"startToken":382,"endToken":1587},{"p":5,"at":645,"title":"B. Record Evidence Supports that PJM’s Tariff is Unjust and Unreasonable","method":"printed heading","endPage":8,"endAt":840,"startToken":1587,"endToken":3230},{"p":8,"at":840,"title":"C. The Commission’s Precedent Prohibiting “Split Load” for Network Service Is","method":"printed heading","endPage":9,"endAt":997,"startToken":3230,"endToken":3721},{"p":9,"at":997,"title":"II. The Commission Satisfied the Second Prong of Section 206 of the FPA by Fixing a Just","method":"printed heading","endPage":9,"endAt":1121,"startToken":3721,"endToken":3742},{"p":9,"at":1121,"title":"A. The Commission Has the Authority to Establish New Transmission Services","method":"printed heading","endPage":12,"endAt":508,"startToken":3742,"endToken":4668},{"p":12,"at":508,"title":"B. The Replacement Rate is Not Unduly Discriminatory or Preferential","method":"printed heading","endPage":13,"endAt":717,"startToken":4668,"endToken":5127},{"p":13,"at":717,"title":"C. The Replacement Rate Promotes Competition","method":"printed heading","endPage":14,"endAt":497,"startToken":5127,"endToken":5520},{"p":14,"at":497,"title":"D. The Replacement Rate Addresses Reliability","method":"printed heading","endPage":16,"endAt":295,"startToken":5520,"endToken":6274},{"p":16,"at":295,"title":"CONCLUSION","method":"printed heading","endPage":18,"endAt":4,"startToken":6274,"endToken":6469},{"p":18,"at":4,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":18,"endAt":483,"startToken":6469,"endToken":6549}]}