{"document":{"slug":"rec-20260212-5155","title":"Answer of Exelon Corporation et al. in Opposition to Constellation Energy Generation LLC's 02/02/2026 Motion and Answer to the 01/16/2026 Rehearing Request","issued":"2026-02-12","accession":"20260212-5155","docket":"EL25-49-000","group":"PJM co-location compliance","filer":"Exelon CorporationThe FirstEnergy Transmission Companies","kind":"rehearing request","file":"sources/filings/text/20260212-5155_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260212-5155","tier":"record","sha256":"2e72b196bf164bd93e50385d949df4ead21032020e083df2154e4697e710dfd7","pages":6,"tokens":1453,"emptyPages":[],"textThemes":["colo"]},"pages":[{"page":1,"startToken":0,"endToken":247,"text":"1 \n \nUNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \nPJM Interconnection, L.L.C., et al. \n \n) \nDocket Nos. EL25-49-000 \n                     EL25-49-002 \n \n \nLarge Loads Co-Located at Generating \nFacilities \n \n) \n                    AD24-11-000 \n                    AD24-11-001 \n                    \nConstellation Energy Generation, LLC \n \nv. \n \nPJM Interconnection, L.L.C. \n) \n \n) \n \n) \n                    EL25-20-000 \n                    EL25-20-001 \n \n(consolidated) \n \n \nTHE INDICATED PJM TRANSMISSION OWNERS’ ANSWER IN OPPOSITION TO \nCONSTELLATION’S MOTION \n \n \nThe Indicated PJM Interconnection, L.L.C. (“PJM”) Transmission Owners (“Indicated \nTOs”)1 file this answer under 18 C.F.R. § 385.2132 in response to Constellation Energy \nGeneration, LLC’s (“Constellation”) February 2, 2026 motion for leave to answer and answer \n(“Constellation’s Answer” or “Answer”).  Constellation filed its motion and answer in response to \nthe Indicated TOs’ January 16, 2026 rehearing request.  The Federal Energy Regulatory \nCommission’s (“FERC”) regulations are clear:  “The Commission will not permit answers to \n \n1  \nThis filing was prepared on behalf of the following PJM Transmission Owners:  Exelon Corporation \n(“Exelon”), on behalf of Atlantic City Electric Company, Baltimore Gas and Electric Company, \nCommonwealth Edison Company, Commonwealth Edison Company of Indiana, Inc., Delmarva Power & Light \nCompany, PECO Energy Company, and Potomac Electric Power Company; and FirstEnergy Service Company, \nas agent for its affiliates American Transmission Systems, Incorporated, Jersey Central Power & Light \nCompany, Mid-Atlantic Interstate Transmission LLC, Keystone Appalachian Transmission Company, The \nPotomac Edison Company, Monongahela Power Company and Trans-Allegheny Interstate Line Company \n(collectively, the “FirstEnergy Transmission Companies”). \n2  \n18 C.F.R. § 385.213(a)(3) (permitting an answer to any other pleading if not otherwise prohibited under the \nregulations)."},{"page":2,"startToken":247,"endToken":753,"text":"2 \n \nrequests for rehearing.”3  Thus, Constellation’s Answer is barred under the Commission’s own \nregulations, its motion should be denied, and its Answer should be rejected.4   \nSignificantly, Constellation has not demonstrated good cause to accept its impermissible \nAnswer.  If Constellation thought that the Commission’s 206 Order5 needed “elaborat[ion],”6 it \ncould have, and should have, raised that point in its request for clarification or rehearing.7  It did \nnot.     \nFor example, Constellation’s Answer provides no new information and points to no record \nevidence that contradicts the Indicated TOs’ request for rehearing.  Nothing in the 206 Order or in \nthe uncorroborated/uncross-examined “record” assertions demonstrate that just and reasonable \nservice to co-located load is not available under Network Integration Transmission Service \n(“Network Service”).  The co-location arrangement of Talen Energy and its subsidiary \n \n3  \nId. § 385.713(d)(1); see id. § 385.213(a)(2) (“An answer may not be made to . . . a request for rehearing[] unless \notherwise ordered by the decisional authority.”). \n4  \nSee, e.g., PJM Interconnection, L.L.C., 193 FERC ¶ 61,229, at P 13 (2025) (rejecting an answer filed to a \nrehearing request because “[t]he Commission’s Rules of Practice and Procedure prohibit answers to a request \nfor rehearing”) (citation omitted); Consumers Energy Co. v. Midcontinent Indep. Sys. Operator, Inc., 193 FERC \n¶ 61,228, at P 20 (2025) (stating that “Rule 713(d)(1) of the Commission’s Rules of Practice and Procedure \nprohibits an answer to a request for rehearing” and therefore rejecting the answer filed to the rehearing request) \n(citation omitted); Sw. Power Pool, Inc., 193 FERC ¶ 61,198, at P 43 (2025) (same); Appalachian Power Co., \n193 FERC ¶ 61,091, at P 8 (2025) (same); AEP Oklahoma Transmission Co., Inc., 193 FERC ¶ 61,092, at P 8 \n(2025) (same); Colonial Pipeline Co., 192 FERC ¶ 61,239, at P 12 (2025) (same); PJM Interconnection, L.L.C., \n192 FERC ¶ 61,233, at P 9 (2025) (same); H.A. Wagner LLC, 192 FERC ¶ 61,189, at P 23 (2025) (same); see \nalso, e.g., Midship Pipeline Co., LLC, 192 FERC ¶ 61,172, at P 12 (2025); QT Fuels Inc. v. Colonial Pipeline \nCo., 192 FERC ¶ 61,139, at P 18 (2025); E. Tennessee Nat. Gas, LLC, 192 FERC ¶ 61,153, at P 13 (2025); PJM \nInterconnection, L.L.C., 192 FERC ¶ 61,135, at P 16 (2025); Transcon. Gas Pipe Line Co., LLC, 192 FERC ¶ \n61,134, at P 24 (2025); BlackRock, Inc., 192 FERC ¶ 61,125, at P 19 (2025); PJM Interconnection, L.L.C., 191 \nFERC ¶ 61,221, at P 8 (2025). \n5  \nPJM Interconnection, L.L.C., 193 FERC ¶ 61,217 (2025) (“206 Order”). \n6  \nConstellation’s Answer at 2.  Constellation’s Answer states that “there is good cause for the Commission to \naccept this answer as it elaborates on points in the [206 Order] and is intended to aid the Commission in its \ndecision-making to affirm the [206 Order] . . . .”  Id. \n7  \nConstellation filed a request for clarification, or in the alternative, a request for rehearing on January 20, 2026."},{"page":3,"startToken":753,"endToken":1044,"text":"3 \n \nSusquehanna Nuclear, LLC has moved forward under Network Service.8  Likewise, suggestions \nthat Exelon delayed work on Constellation’s requests to interconnect have been demonstrated to \nbe false.9  The problem causing delays was Constellation’s attempts to circumvent Network \nService to obtain subsidized rates.10  To the extent that Constellation makes blanket claims of large \nloads having project delays,11 that is not due to the type of transmission services offered.  Nor is it \ndue to any actions on the part of the Indicated TOs.   \nIn its Answer, Constellation also attempts to stretch the testimony of Exelon’s witness, \nDavid Weaver, to suggest his testimony provides record evidence that PJM’s open access \ntransmission tariff (“PJM Tariff”) has been interpreted inconsistently.12  It does not.  Mr. Weaver \nstated the following during FERC’s technical conference: “[W]hat we could really use is . . . some \nclarity around the rules of the road, so that . . . we don’t have non-conforming agreements, and we \ndon’t have language that doesn’t exist in the tariffs.”13  Mr. Weaver’s desire for “clarity” was not \na statement that the PJM Tariff or Network Service were inadequate; it was a concern that \ncustomers were trying to avoid following the PJM Tariff, and avoid paying for Network Service, \nand that those attempts at evasion and bypass led to vague requests that violated tariff procedures \nand were thus causing problems.  In fact, the Commission rejected the non-conforming \nSusquehanna Nuclear, LLC interconnection service agreement on the same day Mr. Weaver \n \n8  \nSee Indicated TOs’ Rehearing Request at 17-18. \n9  \nSee id. at 15-17. \n10  See id.  \n11  See Constellation’s Answer at 6-7 & n.28. \n12  See id. at 4. \n13  Transcript, Large Loads Co-Located at General Facilities Technical Conference, Docket No. AD24-11-000, at \n100 (Nov. 1, 2024)."},{"page":4,"startToken":1044,"endToken":1307,"text":"4 \n \nprovided his testimony.14  Constellation has cited no example, i.e., not a single instance, where \ntransmission service was unable to be obtained.   \nConstellation’s Answer is merely a continuation of its debate with the Indicated TOs; it is \nnot worthy of acceptance by the Commission.  It begins with two pages dedicated to parsing the \nnumber of parties in the Indicated TOs’ coalition.  Constellation claims the Indicated TOs are \nincorrect in arguing that reliability concerns were ignored,15 but points to no record evidence \nundermining the Indicated TOs’ position.  Indeed, where Constellation says these arguments are \n“premature,”16 it underscores the Indicated TOs’ argument that the Commission has not yet \nengaged in the analysis.  Constellation claims that the Commission precedent regarding “split \nload,” which the Indicated TOs rely upon, is inapplicable.17  It is not.  The cases cited by the \nIndicated TOs were exactly on point,18 and Constellation’s continued need to debate the issue in \nits Answer does not serve the Commission’s decision-making process.   \n \nUltimately, there is no good cause for the Commission to disregard its own regulations by \ngranting Constellation’s request.  Nothing submitted in Constellation’s Answer undercuts any of \nthe arguments presented in the Indicated TOs’ rehearing request and Constellation had several \nopportunities throughout the course of this proceeding to raise its arguments in the record. \nConstellation’s motion should be denied, and its Answer should be rejected.   \n \n \n \n14  See PJM Interconnection, L.L.C., 189 FERC ¶ 61,078 (2024). \n15  See Constellation’s Answer at 14-16. \n16  Id. at 15. \n17  Id. at 8-9. \n18  See Indicated TOs’ Rehearing Request at 22-26."},{"page":5,"startToken":1307,"endToken":1407,"text":"5 \n \nRespectfully submitted, \n/s/ William Sauer \nWilliam Sauer \nVice President, Federal Regulatory \nAffairs  \nExelon Corporation  \n701 Ninth St. N.W.  \nWashington, DC 20001  \nTelephone: 202-868-7499  \nEmail: william.sauer@exeloncorp.com   \n/s/ Bradley R. Perkins \nBradley R. Perkins \nVice President and Deputy General Counsel \nExelon Corporation \nChase Building \n10 S. Dearborn, 52nd Floor \nChicago, IL 60603  \nTelephone: 312-394-2632 \nEmail: bradley.perkins@exeloncorp.com \n \n \nOn behalf of Exelon Corporation \n \n \n/s/ Amanda P. Parker \nAmanda P. Parker \nCorporate Counsel \nFirstEnergy Service Company \n341 White Pond Drive \nAkron, OH 44320 \nTelephone: (330) 384-4592 \nEmail: aparker@firstenergycorp.com  \n \nOn behalf of The FirstEnergy \nTransmission Companies"},{"page":6,"startToken":1407,"endToken":1453,"text":"CERTIFICATE OF SERVICE \n \nI hereby certify that I have this day served the foregoing document upon each person \ndesignated on the official service list in the above captioned dockets. \nDated at Chicago, IL this 12th day of February, 2026. \n \n \n/s/ Geneva Kennedy  \nGeneva Kennedy  \nExelon Corporation"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":6,"endAt":0,"startToken":0,"endToken":1407},{"p":6,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":6,"endAt":300,"startToken":1407,"endToken":1453}]}