{"document":{"slug":"rec-20260219-5002","title":"Motion for Leave to Answer and Answer of Pennsylvania Office of Consumer Advocate in support of PJM Industrial Customer Coalition's et al. 1/20/2026 Request…","issued":"2026-02-19","accession":"20260219-5002","docket":"EL25-49-000","group":"PJM co-location compliance","filer":"Pennsylvania Office of Consumer Advocate","kind":"rehearing request","file":"sources/filings/text/20260219-5002_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260219-5002","tier":"record","sha256":"5e9f36d8c03feb3779240eaf5ae2f93aab39126f866641e5930b804001f38330","pages":13,"tokens":3867,"emptyPages":[],"textThemes":["colo","adequacy","cost"]},"pages":[{"page":1,"startToken":0,"endToken":324,"text":"1 \n \nUNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \n \n) \nPJM Interconnection, L.L.C., et al. \n) \nDocket No. EL25-49-000 \n \n)  \n \nLarge Loads Co-Located at Generating \n) \nDocket No. AD24-11-000 \nFacilities \n) \n \n) \nConstellation Energy Generation, LLC \n) \nDocket No. EL25-20-000 \n \n) \nv. \n) \n \n) \nPJM Interconnection, L.L.C. \n) \n(Consolidated) \n \n) \n \n \nMOTION FOR LEAVE TO ANSWER AND ANSWER OF THE PENNSYLVANIA \nOFFICE OF CONSUMER ADVOCATE \n \n \nThe Pennsylvania Office of Consumer Advocate (PA OCA) moves for leave to answer \n(Motion) and submits this Answer1 in support of the PJM Industrial Customer Coalition and the \nIndustrial Energy Consumers of America’s (collectively, ICC) Request for Clarification or \nRehearing (ICC’s Request) filed on January 20, 2026, to the Commission’s December 18 Order \nissued in the above-captioned docket (Order). Good cause exists for the Commission to accept this \nAnswer because it contributes an end-use consumer voice2 to the Commission’s decision-making \nto clarify the Order according to its consumer-protective intent regarding behind-the-meter \n \n1 18 C.F.R. §§ 385.212 and 385.213 (listing Commission rules for Motions and Answers; Section 385.212(a)(2) \nprovides that “[a]n answer may not be made to . . . a request for rehearing, unless otherwise ordered by the \ndecisional authority.”); Alaska Gasline Dev. Corp., 171 FERC ¶ 61,134, at P 7 (2020) (accepting answers that \n“clarify the concerns raised and provide information that has assisted in [the Commission’s] decision making”). \n2 See Xcel Energy Services, Inc. v. FERC, 815 F.3d 947, 952 (D.C. Cir. 2016) (“It is long-established that the ‘primary \naim [of the FPA] is the protection of consumers from excessive rates and charges.’” (quoting Mun. Light Bds. Of \nReading & Wakefield v. FPC, 450 F.2d 1341, 1348 (D.C. Cir. 1971))); Nat’l Ass’n of Regulatory Util. Comm’rs v. \nFERC, 964 F.3d 1177, 1186 (D.C. Cir. 2020) (noting FPA’s “‘core purposes’ of ‘curb[ing] prices and enhanc[ing] \nreliability in the wholesale electricity market’” (quoting FERC v. Elec. Power Supply Ass’n, 577 U.S. 260, 273 \n(2016)))."},{"page":2,"startToken":324,"endToken":652,"text":"2 \n \ngeneration (BTMG) and co-located load.3 In support of the ICC’s Request, because the proceeding \ndid not develop a legally sufficient record on BTMG, FERC and PJM should approach BTMG by \ncontinuing to focus where FERC and PJM have been focusing: on “the scale of large data centers” \nand “very large loads like data centers” trying to evade or manipulate the Co-Location rules in \nways that create a “potential transmission and resource adequacy planning problem” and “raise \ncost shifting concerns.”4  \nI. \nSummary of Answer to the ICC’s Request \nFor context, in Pennsylvania, certain existing industrial customers have invested \nsignificantly in combined heat and power (CHP) cogeneration facilities that support their \nmanufacturing processes and offset their electricity consumption. The cogeneration facilities \ngenerate combined electrical and thermal energy. Thermal energy, or heat, is used in the \nmanufacturing process and the electricity byproduct is used to power their business. These CHP \ncogeneration facilities are BTMG, are not used in PJM’s energy or capacity markets, and do not \nuse the PJM transmission system because when the generation trips offline, the load connected to \nthe BTMG (or almost all of the load) automatically trips offline. Such a configuration ensures that \nthe load with BTMG does not materially “lean” on PJM.5 \nIn addressing PJM’s BTMG rule, FERC should adhere to the jurisdictional limits expressed \nin the Order to preserve exclusive state retail authority and protect consumers from cost shifts, \nbecause doing so will improve the Order’s legal durability and effectuate its purpose. Furthermore, \nFERC should evaluate whether and how to set an appropriate threshold(s) with continued attention \nto the distinction between unique new large loads—primarily data center large loads—and existing \n \n3 PJM Interconnection, L.L.C., 193 FERC ¶ 61,217, at P 186 (2025) (December 18 Order) (expressing consumer-\nprotective intent).  \n4 Id. (quoting PJM March 24 Response at 13, 36). \n5 See ICC’s Request, at pp. 28, 32 (identifying potential effects on Combined Heat and Power Units)."},{"page":3,"startToken":652,"endToken":946,"text":"3 \n \nBTMG facilities, like Pennsylvania industrial consumers with CHP cogeneration facilities, that \nFERC explicitly sought to protect through the threshold. Alternatively, a qualitative distinction \nbased on reliability implications can be used to separate existing BTMG facilities within PJM from \ndata center large loads because the existing CHP cogeneration facilities in Pennsylvania, for \nexample, do not use PJM’s energy or capacity markets and do not use the PJM transmission system, \nand these particular qualities could be a way to ensure appropriate treatment of these existing CHG \ncogeneration facilities.  Throughout this proceeding, the Commission should continue its vital \nfocus on addressing new data center large load configurations that shift costs and create \ntransmission and resource adequacy planning problems. \nII. \nBackground on the Order’s BTMG Provisions \nIn the Order, the Commission found PJM’s existing BTMG rules to be no longer just and \nreasonable because “loads with BTMG are not fully accounted for in resource adequacy planning,” \nwhich creates a “potential transmission and resource adequacy planning problem” and “raise[s] \ncost shifting concerns.”6 FERC reasoned that the existing rules may present “both reliability and \nresource adequacy risks because PJM, per its Tariff, is obligated to serve transmission customers \nusing BTMG but does not consider such customers in transmission and resource adequacy \nplanning.”7 On that basis, FERC directed “PJM to revise its BTMG rules.”8  \nIn recognition of “concerns raised in the record about the potential impacts on existing \nBTMG customers of the Commission changing PJM’s BTMG rules, however, [the Commission] \ndirect[ed] PJM to maintain the current BTMG rules for customers that fall below a new [megawatt] \n[(MW)] materiality threshold for the amount of load at a particular electrical location that Network \n \n6 December 18 Order, at PP 179, 186. \n7 Id. at 179. \n8 Id."},{"page":4,"startToken":946,"endToken":1262,"text":"4 \n \nCustomers may net using BTMG.”9 Furthermore, FERC directed  “PJM to implement a two-part \ntransition process for retail BTMG . . . including: (1) the establishment of a three-year transition \nperiod; and (2) the ability to grandfather certain entities with existing contracts . . . .”10 \nIn making these decisions, FERC noted that “PJM explains that the BTMG rules were \n‘conceived for, and [have] been implemented for, substantially smaller loads (like a warehouse \nwith solar panels) and not on the scale of large data centers.’”11 Moreover, FERC identified that \n“PJM’s existing BTMG rules do not limit the amount of qualifying load that a Network Customer \nmay net by using BTMG and do not provide any protections against this potential transmission \nand resource adequacy planning problem or against the costs of maintaining sufficient resources \nto serve these loads being shifted onto other customers.”12 For these reasons, FERC determined \nthat large load BTMG arrangements violate cost causation principles because “large loads \nconfigured in a BTMG arrangement with significant generation will raise cost shifting concerns \ncompared to loads pursuing smaller amounts of netting.”13 FERC applied this finding that the PJM \nTariff’s BTMG provisions are unjust and unreasonable “to all Network Load.”14 \nIn directing PJM’s Tariff revisions, FERC carefully noted that “not all loads using BTMG \nare large loads that create the reliability and resource adequacy risks” that caused FERC’s finding.15 \nFERC posited that electricity output in MW is an essential variable in distinguishing BTMG that \ncreates reliability and resource adequacy risks from BTMG that does not. On this basis, FERC \ndirected PJM “to propose a new MW threshold for the amount of load at a particular electrical \n \n9 Id. \n10 Id. \n11 December 18 Order, at P 186. \n12 Id. at P 186 (citing PJM, Intra-PJM Tariffs, OATT, § III.34.2 Netting of Behind the Meter Generation (0.0.0)). \n13 Id. \n14 Id. \n15 Id. at P 221."},{"page":5,"startToken":1262,"endToken":1565,"text":"5 \n \nlocation that Network Customers may net by using BTMG.”16 The threshold seeks to “reduce the \nreliability and resource adequacy risks” from large loads identified in the Order “while also \nallowing for Network Customers to reduce their transmission charges in a transparent, not unduly \ndiscriminatory fashion.”17 \nFERC’s BTMG determination concerns only retail BTMG, not non-retail BTMG.18 “PJM \ndefines Non-Retail BTMG as BTMG that is ‘used by municipal electric systems, electric \ncooperatives, or electric distribution companies to serve load.’”19 FERC defined Co-Located Load, \nthe true focus of the Order, as “a configuration that refers to end-use customer load that is \nphysically connected to the facilities of an existing or planned Customer Facility on the \nInterconnection Customer’s side of the Point of Interconnection to the PJM Transmission \nSystem.”20 In adopting this definition, FERC limited the Order’s jurisdictional scope to \n“jurisdiction to oversee the interconnection of generating facilities, including the generators that \nare used to serve Co-Located Load, to the interstate transmission system, as well as jurisdiction \nover the provision of transmission service in interstate commerce used by an Eligible Customer to \nserve Co-Located Load.”21 FERC framed this discussion in terms of its statutorily limited \njurisdictional role in the federalist system,22 highlighting “that the FPA’s jurisdictional divide ‘was \n \n16 December 18 Order, at P 221. \n17 Id. \n18 Id. at P 222. \n19 Id. at P 222 n. 456 (quoting PJM, Intra-PJM Tariffs, OATT, § I.1 Definitions – L-M-N (51.0.1) (defining Non-\nRetail BTMG)), \n20 Id. at P 164 (citation omitted). “PJM defines Interconnection Customer as a Generation Interconnection Customer \nand/or a Transmission Interconnection Customer.” Id. at P 2 n.5 (citing PJM, Intra-PJM Tariffs, OATT, § I.1 \nDefinitions – I – J - K (15.0.0)). \n21 December 18 Order, at P 170. \n22 Id. at P 166."},{"page":6,"startToken":1565,"endToken":1880,"text":"6 \n \ndrawn with meticulous regard for the continued exercise of state power, not to handicap or dilute \nit in any way.’”23 \nIII. \nFERC Should Adhere to the Jurisdictional Limits Expressed in the Order to Preserve \nExclusive State Retail Authority and Protect Consumers from Cost Shifts, Because Doing So \nWill Improve the Order’s Legal Durability and Effectuate Its Purpose. \n \nThe ICC’s Request correctly notes that “the Order does not sufficiently explain the legal \nbasis for asserting jurisdiction over retail customers with [BTMG] that is not otherwise used in \nPJM’s energy or capacity markets and does not use the PJM transmission system.”24 In accordance \nwith FERC’s jurisdictional analysis in the Order, the ICC identifies that “any regulations the \nCommission fashions must be based on its statutory authority over interstate transmission and \nwholesale sales.”25 \nIn evaluating PJM’s tariff revisions, FERC should ensure that PJM has clarified exactly \nhow it interprets the definitions of BTMG and Co-Located Load, especially in relation to \njurisdiction. The Order “clarif[ied] that, consistent with the definition in 159, provided above, \nsupra P 164, BTMG is not Co-Located Load.”26 But the exact relationship between them remains \nunclear. \nFERC should ensure that PJM’s Tariff reaffirms and clearly demarcates distinctions \nbetween (1) retail BTMG, (2) retail BTMG that directly affects interstate transmission or interstate \nwholesale sales but retains an exclusively state-jurisdictional retail component, and (3) the FERC-\njurisdictional aspects of Co-Located Load configurations—which FERC carefully explained are \n \n23 Id. (quoting Oneok, Inc. v. Learjet, Inc., 575 U.S. 373, 384-85 (2015) (discussing the analogous provisions in the \nNatural Gas Act) (quoting Panhandle E. Pipe Line Co. v. Pub. Serv. Comm’n of Ind., 332 U.S. 507, 517-18 (1947))). \n24 ICC Request, at p. 21. \n25 Compare ICC Request at p. 39 with December 18 Order, at P 166 (identifying FERC’s statutory limits). \n26 December 18 Order, at P 221 n.453."},{"page":7,"startToken":1880,"endToken":2239,"text":"7 \n \nits wholesale generator interconnection and interstate transmission aspects. These are three distinct \ncategories. \n(1) Retail BTMG under PJM’s existing Tariff is, by definition, exclusively state \njurisdictional and therefore outside the scope of federal jurisdiction, including outside FERC’s \njurisdiction in the Co-Location Order.27 \n(2) Assuming that FERC has asserted jurisdiction over a narrow class of retail BTMG \nrelated to “very large loads like data centers,”28 or some interstate transmission aspect of a larger \nclass of retail BTMG, that jurisdiction would be valid only to the extent that it preserves states’ \nexclusive jurisdiction over retail sales and all other reserved state authority under the Federal \nPower Act.29  An overly broad reading of FERC’s assertion would appear to extend beyond the \nrecord and the scope of the proceeding on Co-Location. Because the proceeding did not develop a \nlegally sufficient record on BTMG, PJM should continue to focus where PJM and FERC have \nbeen focusing: on “the scale of large data centers” and “very large loads like data centers” that \n“raise cost shifting concerns” by trying to evade or manipulate the Co-Location rules.30 \n(3) FERC defined Co-Located Load as “a configuration that refers to end-use customer \nload that is physically connected to the facilities of an existing or planned Customer Facility on \nthe Interconnection Customer’s side of the Point of Interconnection to the PJM Transmission \nSystem.”31 In adopting this definition, FERC limited the Order’s jurisdictional scope to \n“jurisdiction to oversee the interconnection of generating facilities, including the generators that \n \n27 See ICC Request at pp. 40-42 (noting potential jurisdictional confusion); PJM Tariff, Section 1 (Definitions). \n28 December 18 Order, at P 186 (citation omitted). \n29 Id. at PP 165-170; see also Interconnection of Large Loads to the Interstate Transmission System, Joint Comments \nof the Pennsylvania Office of Consumer Advocate and Delaware Division of the Public Advocate, at pp. 5-16, Docket \nNo. RM26-4-000 (November 21, 2025) (commenting on large load jurisdiction); Tri-State Generation and \nTransmission Ass’n, Inc., 193 FERC ¶ 61,070, at PP 45-50 (2025) (discussing jurisdiction and states’ exclusive retail \nauthority). \n30 December 18 Order, at P 186 (citations omitted). \n31 Id. at P 164 (citation omitted)."},{"page":8,"startToken":2239,"endToken":2559,"text":"8 \n \nare used to serve Co-Located Load, to the interstate transmission system, as well as jurisdiction \nover the provision of transmission service in interstate commerce used by an Eligible Customer to \nserve Co-Located Load.”32 FERC should ensure that PJM clarifies which, if any, configurations \nunder this definition may implement BTMG as a source of generation distinct from the \nInterconnection Customer, with a continued focus on “the scale of large data centers” and “very \nlarge loads like data centers” that create “potential transmission and resource adequacy planning \nproblem” and “raise cost shifting concerns.”33 \nIV. \nFERC Should Evaluate Whether and How to Set a MW Threshold(s) with Continued \nAttention to the Distinction Between New Large Loads—Primarily data center large loads—\nand Existing BTMG Facilities. \n \nIn determining the threshold for load being served by BTMG, FERC should keep in mind \nits choice to highlight PJM’s comments expressing concern specifically about “the scale of large \ndata centers.”34 The Commission remarked that “PJM has persuasively explained the problems that \ncould occur if Network Customers with large loads were allowed to use the existing BTMG rules \nin the Tariff. For example, PJM explains that ‘[a]llowing very large loads like data centers to net \nis problematic because loads in this configuration do not carry reserves.’”35 \nPJM did not support “PJM option 3,” a configuration in which Network Load may Co-\nLocate and use BTMG to engage in netting, because “historically, BTMG has supported relatively \nsmall loads, not on the scale of large data centers.”36  Furthermore, PJM commented that “charging \nload for its net use of the grid under the BTMG rules may not capture the costs caused by co-\n \n32 Id. at P 170. \n33 Id. at P 186 (citations omitted). \n34 Id. at P 186 (quoting PJM March 24 Response at 13). \n35 December 18 Order, at P 186 (citations omitted). \n36 Id. at P 16 (citation omitted)."},{"page":9,"startToken":2559,"endToken":2877,"text":"9 \n \nlocated data center arrangements because such arrangements could avoid all costs by netting to \nzero if the entire data center load is supplied by the associated generator.”37 \nFERC framed its discussion of BTMG in these terms, sharing PJM’s clear focus on “the \nscale of large data centers.”38 FERC stated “that, while the order is limited to Co-Located Loads, \nthis finding [that PJM’s existing BTMG rules may lead to both reliability and resource adequacy \nrisks because PJM, per its Tariff, is obligated to serve transmission customers using BTMG but \ndoes not consider such customers in transmission and resource adequacy planning] applies to all \nNetwork Load.”39 But an overly broad reading of this assertion would appear to extend beyond the \nrecord and the scope of the proceeding on Co-Location. Because the proceeding has not yet \ndeveloped a legally sufficient record on BTMG, FERC and PJM should approach the threshold by \ncontinuing to focus where FERC and PJM have been focusing: on “the scale of large data centers” \nand “very large loads like data centers” that “raise cost shifting concerns” and create “potential \ntransmission and resource adequacy planning problem[s].”40 \nMoreover, due to the clear focus on new large load configurations—primarily new large \ndata center large loads—FERC and PJM should consider whether the load threshold should be \ndifferent and higher for existing BTMG configurations and lower for new BTMG configurations. \nWhile this would be correctly categorized as “discriminatory,” the Federal Power Act only \nprohibits a “rate, charge, classification, rule, regulation, practice, or contract” that is “unduly \ndiscriminatory.”41 The best, most natural reading of the plain text is that Congress, by modifying \n“discriminatory” with the word “unduly,” acknowledged the need to duly discriminate when \n \n37 Id. \n38 Id. at P 186 (quoting PJM March 24 Response at 13). \n39 Id. \n40 December 18 Order, at P 186. \n41 16 U.S.C. § 824e(a)."},{"page":10,"startToken":2877,"endToken":3311,"text":"10 \n \nappropriate.42 New large loads—primarily data center large loads—have unique effects on the grid \nat a unique time for the PJM market that requires due discrimination to ensure that their integration \ndoes harm consumers and other grid users.43 \nThe White House National Energy Dominance Council and a bipartisan group of all \nthirteen Governors of the PJM states have jointly expressed that “today’s data centers [are] \nunique.”44 Specifically, they jointly asserted that the “size and the risks they pose to resource \nadequacy make today’s data centers unique.”45 Moreover, the PJM Independent Market Monitor \n(IMM) has asserted that “the PJM Capacity Market is currently actually significantly short as a \nresult of data center load.”46 These statements from the White House, all thirteen bipartisan PJM \ngovernors, the IMM, and consumer advocates support the notion that “cost shifting concerns” and \n“potential transmission and resource adequacy planning problem[s]” due to the unique challenges \nassociated with large data center loads justify treating those challenges on the unique terms that \nthey pose to the overall system.47 \nFERC, in the Order, made such a due discrimination about large data center loads. Because \nof the “concerns raised in the record about the potential impacts on existing BTMG customers of \nthe Commission changing PJM’s BTMG rules, . . . [the Commission] direct[ed] PJM to maintain \nthe current BTMG rules for customers that fall below a new MW materiality threshold for the \n \n42 Cf. ANTONIN SCALIA & BRYAN A. GARNER, READING LAW: THE INTERPRETATION OF LEGAL TEXTS 107-08 (2012) \n(explaining expressio unius est exclusio alterius, the negative-implication canon of statutory interpretation). \n43 Interconnection of Large Loads to the Interstate Transmission System, Reply Comments of the Pennsylvania Office \nof Consumer Advocate, Delaware Division of the Public Advocate, and People of the State of Illinois by the Office of \nthe Illinois Attorney General, at pp. 8-11, Docket No. RM26-4-000 (Dec. 5, 2025). \n44 Statement of Principles Regarding PJM, (Jan. 16, 2026), https://www.energy.gov/documents/statement-principles-\nregarding-pjm. \n45 Id. \n46 IMM Answer to CEG, at p. 6 (first citing Analysis of the 2026/2027 RPM Base Residual Auction–Part A, \nMONITORING ANALYTICS (Oct., 1, 2025), https://www.monitoringanalytics.com/reports/Reports/2025.shtml; and then \nciting Analysis of the 2027/2028 RPM Base Residual Auction – Part A, MONITORING ANALYTICS (Jan. 5, 2026), \nhttps://www.monitoringanalytics.com/reports/Reports/2026.shtml). \n47 See December 18 Order, at P 186. As an aside, the Commission should regard with serious skepticism efforts to \nremove existing capacity from the PJM market to serve new data centers. See IMM Answer to CEG, at p. 6."},{"page":11,"startToken":3311,"endToken":3632,"text":"11 \n \namount of load at a particular electrical location that Network Customers may net using BTMG.”48 \nThe threshold’s primary purpose is to protect “existing BTMG customers.”49 \nFERC should continue to effectuate this intent by ensuring that new rules for BTMG due \nto this unique situation do not unjustly harm other grid users and consumers. For example, BTMG \nunits that are CHP cogeneration facilities are longstanding facilities whose operations may be \nseverely disrupted if required to fundamentally change how they supply and procure electricity. \nFurthermore, some existing BTMGs that have CHP cogeneration facilities are configured such that \nwhen the generation trips offline, the load connected to the BTMG (or almost all of the load) \nautomatically trips offline. Such a configuration ensures that the load with BTMG does not \nmaterially “lean” on PJM. 50 Additionally, a Qualifying Facility (QF) under the Public Utility \nRegulatory Policies Act of 1978 (PURPA) occupies particular statutory and regulatory terrain that \nmay merit distinct consideration.51 For CHP cogeneration facilities and QFs, especially, FERC \nshould ensure that PJM’s selection of threshold(s) is accompanied by analysis regarding the \nthreshold’s reliability implications to PJM from disrupting these existing arrangements. Indeed, a \nqualitative distinction based on reliability implications can be used to separate existing BTMG \nfacilities within PJM from data center large loads because the existing CHP cogeneration facilities \nin Pennsylvania, for example, do not use PJM’s energy or capacity markets and do not use the PJM \ntransmission system, and these particular qualities could be a way to ensure appropriate treatment \nof these existing CHG cogeneration facilities.   \nAnd in general, FERC should ensure that PJM accompanies its selection of threshold(s) \nwith analyses regarding the thresholds’ reliability—including operational reliability and resource \n \n48 Id. \n49 Id. \n50 See ICC Request, at pp. 28, 32 (identifying potential effects on Combined Heat and Power Units). \n51 See ICC Request, at pp. 5-6, 10-13 (addressing the unique situation of PURPA QFs)."},{"page":12,"startToken":3632,"endToken":3823,"text":"12 \n \nadequacy—implications to PJM and the number of BTMG facilities that are above the \nthreshold(s). This information would help stakeholders to assess the threshold(s) and help to avoid \nextensive interconnection studies and other interference with existing BTMG that offer little \nimprovement to the Order’s goals of clarifying permissible Co-Located Load configurations and \naddressing “cost shifting concerns” and “potential transmission and resource adequacy planning \nproblem[s]” due to large loads that should configure as Co-Located Loads manipulating BTMG to \navoid paying their fair share of overall system costs.52 \nV. \nConclusion \nThe PA OCA respectfully requests that the Commission accept this Answer in support of \nthe ICC’s Request because it should assist the Commission in determining appropriate, end-use-\nconsumer-protective BTMG rules in PJM. \n \nCounsel for: \nDarryl Lawrence \nConsumer Advocate \n \nPennsylvania Office of Consumer Advocate \n555 Walnut Street \n5th Floor, Forum Place \nHarrisburg, PA 17101-1923 \n717-783-5048 \n \nDated: February 18, 2026 \nRespectfully submitted, \n \n \n/s/ Josiah B. Harmar \n  \nJosiah Harmar \nAssistant Consumer Advocate \nPA Attorney ID # 338426 \nJHarmar@paoca.org \n \nMelanie Joy El Atieh \nDeputy Consumer Advocate  \nPA Attorney ID # 209323 \nMElAtieh@paoca.org \n \n \n \n \n \n \n52 See December 18 Order, at P 186."},{"page":13,"startToken":3823,"endToken":3867,"text":"13 \n \nCERTIFICATE OF SERVICE \nI certify that today I served this document on this proceeding’s official service list.  \nHarrisburg, Pennsylvania; February 18, 2026. \n \n \n/s/ Josiah B. Harmar \n  \nJosiah Harmar \nAssistant Consumer Advocate \nPennsylvania Office of Consumer Advocate \nPA Attorney ID # 338426 \nJHarmar@paoca.org"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":2,"endAt":510,"startToken":0,"endToken":406},{"p":2,"at":510,"title":"I. Summary of Answer to the ICC’s Request","method":"printed heading","endPage":3,"endAt":836,"startToken":406,"endToken":768},{"p":3,"at":836,"title":"II. Background on the Order’s BTMG Provisions","method":"printed heading","endPage":6,"endAt":124,"startToken":768,"endToken":1587},{"p":6,"at":124,"title":"III. FERC Should Adhere to the Jurisdictional Limits Expressed in the Order to Preserve","method":"printed heading","endPage":8,"endAt":628,"startToken":1587,"endToken":2333},{"p":8,"at":628,"title":"IV. FERC Should Evaluate Whether and How to Set a MW Threshold(s) with Continued","method":"printed heading","endPage":12,"endAt":629,"startToken":2333,"endToken":3723},{"p":12,"at":629,"title":"V. Conclusion","method":"printed heading","endPage":13,"endAt":6,"startToken":3723,"endToken":3824},{"p":13,"at":6,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":13,"endAt":323,"startToken":3824,"endToken":3867}]}