{"document":{"slug":"rec-20260220-5263","title":"Motion for Leave to Answer and Answer of Constellation Energy Generation, LLC in response to the Independent Market Monitor for PJM’s Answer et al","issued":"2026-02-20","accession":"20260220-5263","docket":"EL25-49-000","group":"PJM co-location compliance","filer":"Constellation Energy Generation, LLC","kind":"answer","file":"sources/filings/text/20260220-5263_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260220-5263","tier":"record","sha256":"a29fa2f0483d2fe09b9f564980e54adf7620d406e5749e7619290b5ce788a087","pages":7,"tokens":1920,"emptyPages":[],"textThemes":["colo","flex","adequacy"]},"pages":[{"page":1,"startToken":0,"endToken":286,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \nPJM Interconnection, L.L.C., et al. \n \n \nLarge Loads Co-Located at Generating Facilities \n \n \nConstellation Energy Generation, LLC \n \n     v. \n \nPJM Interconnection, L.L.C. \n) \n \n \n)  \n \n \n)  \n) \n) \n) \n) \n \nDocket No. EL25-49-000 \n \n \nDocket No. AD24-11-000 \n \n \n \n \nDocket No. EL25-20-000 \n(Consolidated) \nMOTION FOR LEAVE AND ANSWER OF \nCONSTELLATION ENERGY GENERATION, LLC \nConstellation1 moves for leave and submits this answer in response to the Independent \nMarket Monitor for PJM’s answer2 to Constellation’s Request for Clarification, or in the \nAlternative, Request for Rehearing3 of the Commission’s December 18, 2025 Order.4 In relevant \npart, Constellation sought clarification that generators selling non-firm electricity to co-located \nlarge loads do not need to delist their capacity.5 The Commission should not force a generator to \ndelist its capacity when the generator’s co-located load obligation is non-firm and service can be \ncurtailed by both PJM and the generator. In such an arrangement, the generator’s output remains \n \n1 Constellation Energy Generation, LLC (“Constellation”) submits this answer and motion for leave pursuant to \nRules 212 and 213 of the Commission’s Rules of Practice and Procedure, 18 C.F.R. §§ 385.212 and 385.213. \nConstellation respectfully submits there is good cause for the Commission to accept this answer as it is intended to \naid the Commission in its decision-making. \n2 Answer and Motion for Leave to Answer of the Independent Market Monitor for PJM (Feb. 5, 2026) (“Market \nMonitor Answer”). Hereafter, the Independent Market Monitor for PJM is referred to as “Market Monitor.” \n3 Request for Clarification or, in the Alternative, Rehearing of Constellation Energy Generation, LLC (Jan. 20, 2026) \n(“Clarification Request”). \n4 PJM Interconnection, L.L.C., 193 FERC ¶ 61,217 (2025) (“December 18th Order”). \n5 See Clarification Request at 2."},{"page":2,"startToken":286,"endToken":822,"text":"2 \n \navailable to the grid when needed to support resource adequacy. In opposing the request, the \nMarket Monitor mischaracterizes Constellation’s position and misstates the law, facts, and record.6 \nThe Commission should reject the Market Monitor Answer, consistent with past practice.7   \nFirst, the Market Monitor mischaracterizes the Clarification Request as “advocat[ing] for \nthe ability to sell capacity twice.”8 That is wrong. The generator’s capacity would be sold only \nonce – to PJM. The Market Monitor is conflating energy and capacity. They are not the same \nproduct. “Electric energy is the actual electricity that electric generators produce and which \nresidential and business customers ultimately use. By contrast, electric capacity is the ability to \nproduce [energy] when called upon.”9 The Clarification Request contemplated allowing existing \ngenerators to continue “serving”—that is, selling non-firm energy to—Co-Located Load without \n \n6 Market Monitor Answer at 2-7. \n7 The Commission prohibits answers to rehearing requests unless otherwise ordered by the decisional authority. 18 \nC.F.R. §§ 385.213(a)(2), 385.713(d)(1); see also PJM Interconnection, L.L.C., 190 FERC ¶ 61,081, at P 27 (2025) \n(rejecting IMM answer to rehearing request); Indep. Mkt. Monitor for PJM Interconnection, L.L.C. v. Am. Elec \nPower Serv. Corp., 166 FERC ¶ 61,043, at P 8 (2019) (rejecting IMM answer to rehearing request). Unauthorized \nanswers are only accepted if the Commission finds good cause to waive Rule 213(a)(2), e.g., if the unauthorized \nanswer “provides … information … that … assist[s] in our decision-making process and [does] not cause undue \ndelay.” Dominion Transmission, Inc., 163 FERC ¶ 61,128, at P 8 (2018). \n8 Market Monitor Answer at 4; see also id. at 3 (claiming that Constellation “asserts that even when capacity is sold \nto a data center that it can also sell the same capacity to PJM customers in the PJM capacity market”); id. at 2 \n(“generators should not be permitted to sell capacity twice”) (capitalization removed); id. at 5 (“CEG proposes to \nextend the concept to mean that any generation owner could remove its capacity from the PJM Capacity Market by \nselling the capacity to a data center.”); id. (“CEG is not content to simply remove its capacity from the capacity \nmarket. CEG proposes to sell its capacity to a data center and also sell the same capacity for the same time period \nto the PJM market.”). \n9 PPL EnergyPlus, LLC v. Solomon, 766 F.3d 241, 247 (3d Cir. 2014) (internal citations omitted); see also Affirmed \nEnergy, LLC v. FERC, No. 25-1091, Slip Op. at 42 (D.C. Cir. Feb. 10, 2026) (“Capacity is not actual electricity, but \nrather a ‘commitment to produce electricity or forgo the consumption of electricity’ in a future delivery year.”); \nCent. Hudson Gas & Elec. Corp. v. FERC, 783 F.3d 92, 98 (2d Cir. 2015) (“[S]uppliers sell a commitment to produce \nelectric energy if called upon to do so during a specified future time period, rather than electric energy itself.”); \nFERC, \nUnderstanding \nWholesale \nCapacity \nMarkets \n(last \nvisited \nFeb. \n12, \n2026), \nhttps://www.ferc.gov/media/understanding-wholesale-capacity-markets (“A capacity market does not pay for the \nenergy produced but instead pays for the ability to produce power when needed.”) (emphasis omitted)."},{"page":3,"startToken":822,"endToken":1265,"text":"3 \n \ndelisting as a capacity resource so long as “the capacity resource remains available to serve the \ngrid when needed,”10 consistent with its obligations.  \nSecond, the Market Monitor suggests that such an arrangement is inconsistent with “[t]he \nobligations of capacity resources,” which “include the requirement to offer their full [capacity] in \nthe energy and reserves markets every day.”11 But the Commission has previously clarified that \nPJM’s “must-offer requirement, when implemented, should not impede resources from exporting \nenergy on a non-firm or recallable basis, i.e., that the must-offer requirement will not operate in \n[a] manner that requires the resource to sit idle.”12 Thus, a capacity resource is not required to sit \nidle by the phone 8,760 hours per year waiting to see if PJM might call.13 To the extent the \ngenerator can demonstrate that its obligation to provide energy to the co-located load is non-firm \nor recallable, and the load demonstrates that it will either curtail or be served by backup supply \nwhen generator and grid supply are unavailable, there is simply no reason for the generator to \ndelist and exacerbate any supply shortfall. To the contrary, there is every reason for the \nCommission to encourage such arrangements, which allow new large loads to interconnect without \n \n10 Clarification Request at 1 (emphasis added). The Clarification Request also stated, “[a]s Constellation stated in its \nApril 23, 2025 Reply Comments, ‘Constellation’s view is that any Existing Generation Capacity Resources that \nwould prioritize serving co-located load over following PJM dispatch should instead seek removal of Capacity \nResource status or otherwise seek appropriate replacement capacity to cover its capacity supply obligation.’” Id. at \n5 n.9 (quoting Constellation April 23, 2025 Reply Comments at 92-93). \n11 Market Monitor Answer at 4. \n12 PJM Interconnection, L.L.C., 139 FERC ¶ 61,057, at P 205 (2012). \n13 See generally PJM Manual 11, § 2.3.3.1 (stating Capacity Resource Offer Rules); Constellation April 23, 2025 \nReply Comments, Exhibit 2 at 46:7-14 (Testimony of Zachary Ming) (“For any generator to participate in the \ncapacity market, it is expected to provide output to the grid when system conditions require and when ordered to by \nPJM. If a co-located generator clears in the capacity market, this means that, at a minimum, it must output to the \ngrid when needed or face performance penalties, even if that means interruption of the co-located load, either through \ncurtailment or backup generation. I agree with PJM’s statement that ‘no portion of a committed Capacity Resource \n(whether composed of one or multiple physical generating units) may prioritize serving load that PJM is not \nresponsible for serving.’”) (citations omitted)."},{"page":4,"startToken":1265,"endToken":1521,"text":"4 \n \nimpacting resource adequacy. The Clarification Request seeks nothing more than the same type of \ntreatment already afforded non-firm exports.14 Constellation acknowledges that there may have to \nbe adjustments to the energy offer price rules to accommodate the non-firm supply of co-located \nload from a capacity resource. Adjustments to energy offer price rules have occurred from time to \ntime over the years15 and Constellation is not advocating for a “radical change in the structure of \nPJM markets.”16   \nThird, the Market Monitor asserts that the Clarification Request proposed to “remove … \ncapacity from the capacity market.”17 The Clarification Request proposed the exact opposite. \nConstellation sought clarification to avoid a scenario where a capacity resource that remained \navailable to serve the grid when needed would be forced to delist and “needlessly remove available \ncapacity from serving the grid.”18 \nFourth, the Market Monitor incorrectly states “[t]he Commission has not approved” “that \nexisting generating capacity and its energy output can be sold directly to a data center, outside \nPJM markets….”19 The Commission expressly contemplated this scenario and, to effectuate it \nefficiently, “direct[ed] PJM to file Tariff changes” addressing “an Interconnection Customer \n \n14 Clarification Request at 1. \n15 See, e.g., PJM Interconnection, L.L.C., 126 FERC ¶ 61,145, order on clarification, 127 FERC ¶ 61,188 (2009) \n(directing PJM to propose an approach for addressing the incorporation of opportunity costs in mitigated offers). \n16 Market Monitor Answer at 2. \n17 Id. at 6.  \n18 Clarification Request at 1.  \n19 Market Monitor Answer at 2."},{"page":5,"startToken":1521,"endToken":1691,"text":"5 \n \nseeking to serve Co-Located Load using an existing generating facility….”20 If the Market Monitor \ndisagreed, it should have sought timely rehearing of the December 18th Order.21 \nFinally, the Market Monitor provides no substantive support for its bald assertion that \nConstellation’s “request for clarification on jurisdiction issues is not just and reasonable and should \nbe denied.”22 The Market Monitor neither specifically mentions nor engages with Constellation’s \nrequest that the “Commission … clarify that it did not intend to change the scope of its jurisdiction \nover a generator’s wholesale sales and transmission.”23 As such, the Market Monitor’s assertion \nshould be disregarded.   \nCONCLUSION \nFor the foregoing reasons, the Commission should reject the Market Monitor Answer as it \nfails to comply with Rule 213 of the Commission’s Rules of Practice and Procedure and cannot \nsupport the Commission in its decision making. \n \n20 December 18th Order, 193 FERC ¶ 61,217 at P 176. \n21 16 U.S.C. § 825l(a).  \n22 Market Monitor Answer at 7. \n23 Clarification Request at 2."},{"page":6,"startToken":1691,"endToken":1838,"text":"6 \n \n \n \n \n \n \n \n \n    Respectfully submitted, \n \n \n \n \n \n \n \n    /s/ Paul F. Wight \n \n \n \nFebruary 20, 2026 \n \n \nCarrie Hill Allen \nSr. Vice President & Deputy General Counsel \nSeth T. Lucia \nAssistant General Counsel \nConstellation Energy Generation, LLC \n250 Massachusetts Ave. NW, Suite 760 \nWashington, D.C. 20001 \ncarrie.allen@constellation.com \nseth.lucia@constellation.com \n  \nChristopher A. Wilson \nManaging Director, Federal Regulatory Affairs \nConstellation Energy Generation, LLC \n250 Massachusetts Ave. NW, Suite 760 \nWashington, D.C. 20001 \n202-347-7500 \nFERCe-filings1@constellation.com \n \nPaul F. Wight \nCarolyn E. Clarkin \nDLA Piper LLP (US) \n500 Eighth Street NW \nWashington, D.C. 20004 \n703-773-4058 \npaul.wight@us.dlapiper.com \ncarolyn.clarkin@us.dlapiper.com \n \nSophia Browning \n4365 Executive Drive \nSuite 1100 \nSan Diego, CA 92121 \n858-677-1455 \nsophia.browning@us.dlapiper.com \n \nJacob I. Chefitz \nDLA Piper LLP (US) \n1251 Avenue of the Americas \nNew York, NY 10020 \n212-335-4500 \njacob.chefitz@us.dlapiper.com  \n \nCounsel for Constellation Energy \nGeneration, LLC"},{"page":7,"startToken":1838,"endToken":1920,"text":"7 \n \nCERTIFICATE OF SERVICE \nI hereby certify that I have on this 20th day of February 2026, caused to be served a copy \nof the foregoing upon all parties on the service lists in these proceedings in accordance with the \nrequirement of Rule 2010 of the Commission’s Rules of Practice and Procedure, 18 C.F.R. \n§ 385.2010 (2024). \n/s/ Sophia Browning \nSophia Browning \nDLA Piper LLP (US) \n4365 Executive Drive \nSuite 1100 \nSan Diego, CA 92121 \nsophia.browning@us.dlapiper.com"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":5,"endAt":702,"startToken":0,"endToken":1624},{"p":5,"at":702,"title":"CONCLUSION","method":"printed heading","endPage":7,"endAt":5,"startToken":1624,"endToken":1839},{"p":7,"at":5,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":7,"endAt":474,"startToken":1839,"endToken":1920}]}