{"document":{"slug":"rec-20260223-5181","title":"Co-Located Load Tariff Revisions to Comply with Order in EL25-49, et al","issued":"2026-02-23","accession":"20260223-5181","docket":"ER26-1479-000","group":"PJM co-location compliance","filer":"PJM Interconnection, L.L.C.","kind":"tariff filing","file":"sources/filings/text/20260223-5181_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260223-5181","tier":"record","sha256":"d00276ca9e0324892134bfc43f5ed988f31932690dd9bddecbd700f132c89ee1","pages":39,"tokens":11373,"emptyPages":[],"textThemes":["colo","study","flex","adequacy"]},"pages":[{"page":1,"startToken":0,"endToken":333,"text":"PJM Interconnection, L.L.C. \n2750 Monroe Boulevard \nAudubon, PA 19403 \n \nMark J. Stanisz \nAssociate General Counsel \nPh: (610) 666-4707   \nMark.Stanisz@pjm.com \n \nFebruary 23, 2026 \n \n \n \n \n \n \n \n \nHonorable Debbie-Anne A. Reese \nSecretary  \nFederal Energy Regulatory Commission  \n888 First Street, NE, Room 1A \nWashington, DC 20426 \n \nRe: \nPJM Interconnection, L.L.C., Docket No. ER26-____-000 \n60-Day Compliance Filing for Co-Located Load Related Revisions to Open Access \nTransmission Tariff to Comply with Commission Order in Docket No. EL25-49, et \nal. \nDear Secretary Reese:  \nPursuant to section 206 of the Federal Power Act,1 PJM Interconnection, L.L.C. \n(“PJM”) hereby submits proposed revisions to the PJM Open Access Transmission Tariff \n(“Tariff”)2 of PJM Interconnection to comply with the Federal Energy Regulatory \nCommission’s (“Commission” or “FERC”) directives in its December 18, 2025 order3 to \n(1) revise its behind-the-meter generation Tariff provisions, (2) establish three new \ntransmission services for Eligible Customers4 seeking to take service on behalf of Co-\nLocated Load, and (3) revise its necessary studies processes,5 among other changes \n(collectively, the “February 23 Compliance Filing”).  In response to the Order to Show \n \n1 16 U.S.C. § 824e. \n2 Terms not otherwise defined herein shall have the same meaning as set forth in the Tariff.  PJM anticipates \nneeding to make subsequent conforming clean-up filings to the Tariff, Amended and Restated Operating \nAgreement (“Operating Agreement”), and the Reliability Assurance Agreement Among Load-Serving \nEntities in the PJM Region (“RAA”) in regards to the compliance filings being submitted in response to the \nOrder to Show Cause.  Based on continued stakeholder engagement and in the Commission’s active dockets, \nPJM may also seek leave to submit additional compliance filings to, among other things, streamline \nCommission resolution of issues and enhance Tariff clarity. \n3 PJM Interconnection, L.L.C., 193 FERC ¶ 61,217, at PP 2, 161, 231-36 (2025) (“Order to Show Cause”). \n4 Capitalized terms not otherwise defined herein shall have the meanings given to them in the Tariff. \n5 Order to Show Cause at P 160."},{"page":2,"startToken":333,"endToken":587,"text":"Cause, PJM already filed a first compliance filing (in Docket No. ER26-1088-000) and an \ninformational report. \nIn response to twin Commission directives in the Order to Show Cause, PJM is \nconcurrently filing two packages:  (1) this Transmittal Letter, including filed Tariff \nrevisions, which respond to Commission’s specific compliance directives, and (2) an Initial \nBrief, including “illustrative” Tariff language that is not filed in eTariff, specifically \ndescribing the non-rate terms and conditions for new transmission services.  PJM \nunderstands that the PJM Transmission Owners will be making a submission regarding the \nrates for these new services. \nI. \nINTRODUCTION AND BACKGROUND  \nPJM understands the importance of, and remains committed to, advancing our \nnation’s leadership in connecting large loads, including supporting the development of \nArtificial Intelligence (“AI”) infrastructure.  PJM continues to work with its members to \nsupport efforts to accelerate the speed and increase the scale with which the United States \ncan build the next generation of AI infrastructure, especially the necessary capacity to \nsupport this load while also ensuring reliability and fair treatment for all users of the grid.   \nA. \nCommission Order \nOn December 18, 2025, the Commission issued the Order to Show Cause finding \nthe Tariff unjust and unreasonable due to the lack of specificity for the rates, terms, and \nconditions that apply to Co-Located Load and directing PJM to make several compliance \nand informational filings.6  In the Order to Show Cause, the Commission directed PJM to \nfile several 60-day compliance directives which are discussed here.  As noted above, the \n \n6 Id. at PP 1-2."},{"page":3,"startToken":587,"endToken":903,"text":"Commission also required PJM to submit a brief to build a record on the appropriate rates, \nterms, and conditions of these new services.  PJM is submitting that brief concurrently with \nthis February 23 Compliance Filing.   \nB. \nStakeholder Engagement \nPJM consulted with stakeholders in its development of the proposed revisions.  PJM \nheld a workshop on January 9, 2026 to give stakeholders an opportunity to provide \nfeedback for PJM to consider as it developed the proposed revisions filed on January 20.7  \nAdditional stakeholder workshops followed on January 23,8 January 26,9 February 5,10 \nFebruary 10,11 and February 20.12   \nOn February 19, 2026, PJM posted a preliminary draft of the proposed revisions \nfor stakeholder awareness and discussion prior to submission.13  PJM also solicited and \nreceived written stakeholder input on posted proposed tariff language and concepts related \nto meeting the compliance directives.  PJM appreciates the extensive stakeholder \n \n7 PJM, Co-Located Load Order Workshop Meetings Materials (2026), https://www.pjm.com/committees-\nand-groups/workshops/cllsco (postings of Co-Located Load Order Workshop upcoming meetings schedule \nand past meeting materials on PJM’s website). \n8 \nPJM, \nCo-Located \nLoad \nOrder \nWorkshop \nMeeting \nMaterials \n(Jan. \n23, \n2026), \nhttps://www.pjm.com/committees-and-groups/workshops/cllsco. \n9 \nPJM, \nCo-Located \nLoad \nOrder \nWorkshop \nMeeting \nMaterials \n(Jan. \n26, \n2026), \nhttps://www.pjm.com/committees-and-groups/workshops/cllsco. \n10 \nPJM, \nCo-Located \nLoad \nOrder \nWorkshop \nMeeting \nMaterials \n(Feb. \n5, \n2026), \nhttps://www.pjm.com/committees-and-groups/workshops/cllsco. \n11 \nPJM, \nCo-Located \nLoad \nOrder \nWorkshop \nMeeting \nMaterials \n(Feb. \n10, \n2026), \nhttps://www.pjm.com/committees-and-groups/workshops/cllsco. \n12 \nPJM, \nCo-Located \nLoad \nOrder \nWorkshop \nMeeting \nMaterials \n(Feb. \n20, \n2026), \nhttps://www.pjm.com/committees-and-groups/workshops/cllsco. \n13 \nPJM, \nPreliminary \nDrafts \nof \nProposed \nRevisions \nfor \nStakeholders \n(Feb. \n20, \n2026), \nhttps://www.pjm.com/committees-and-groups/workshops/cllsco (follow “Meeting Materials” subheading; \nthen choose “2026” from dropdown; then choose “2.20.2026 Item 01 – 1” and “2.20.2026 Item 01 – 2” \nPDFs)."},{"page":4,"startToken":903,"endToken":1158,"text":"engagement and considered that feedback in refining and developing the proposed \nrevisions. \nIII. \nDESCRIPTION OF PROPOSED TARIFF REVISIONS \nA. \nRevisions to Behind The Meter Generation (“BTMG”) Rules  \nThe Commission found that PJM’s existing Retail Behind The Meter Generation \n(“Retail BTMG”) rules in the Tariff are no longer just and reasonable, in part, because \n“PJM’s existing [Retail] BTMG rules may lead to both reliability and resource adequacy \nrisks.”14  Accordingly, in the Order, the Commission required PJM to revise the rules for \n“retail BTMG” to (1) establish a “materiality threshold,” (2) set a three-year transition \nperiod for implementation of the threshold, and (3) establish a legacy arrangement to allow \nentities with existing contracts effectuating retail BTMG arrangements above the newly \nestablished threshold to continue utilizing the existing retail BTMG rules through the \nremainder of the current contract terms.15   \n1. \nExisting BTMG Rules \n \nPJM’s BTMG rules originated in 2004, when the Commission accepted PJM’s \nproposal to allow market participants to net BTMG against load “at the same electrical \nlocation for the purposes of calculating applicable PJM charges.”16  The Commission found \nthat the BTMG rules would “encourage demand response programs” and “provide a benefit \nto qualifying behind the meter generation that contributes to network load reductions by \nallocating a fairer share of transmission system and other operating costs.”17  The use of \n \n14 Order to Show Cause at P 186. \n15 Id. at PP 179, 221-24.   \n16 PJM Interconnection, L.L.C., 107 FERC ¶ 61,113, at P 1 (2004).   \n17 Id. at PP 27, 29."},{"page":5,"startToken":1158,"endToken":1488,"text":"netting between BTMG and load that are located “at a single electrical location such that \nno transmission or distribution facilities are used to deliver energy from the generating unit \nto the load”18 is commonly referred to as “Retail BTMG.”  As originally conceived, there \nis no limit on the size of a BTMG that could be netted with load in a retail BTMG \nconfiguration.19 \n \nIn 2005, the Commission initiated an investigation into whether PJM should expand \nBTMG netting to “include generation connected to electric distribution systems.”20  Later \nthat year, the Commission accepted a settlement between PJM and several municipal \nsystems, which “expands applicability of PJM’s BTM generation netting provisions to \nBTM generation used by municipal electric systems, electric cooperatives and municipal \nelectric distribution companies . . . to serve load so long as permission is obtained from the \nfacility owner, lessee or operator.”21  BTMG used to net against load through a distribution \nsystem is defined as Non-Retail Behind The Meter Generation.22   \n \nAs a result of these proceedings, the current Tariff specifies netting rules and \nincludes definitions for Behind The Meter Generation and Non-Retail Behind the Meter \nGeneration.  Specifically, Behind The Meter Generation is defined as: \na generation unit that delivers energy to load without using the \nTransmission System or any distribution facilities (unless the entity \nthat owns or leases the distribution facilities has consented to such \nuse of the distribution facilities and such consent has been \ndemonstrated \nto \nthe \nsatisfaction \nof \nthe \nOffice \nof \nthe \n \n18 Id. at P 4.   \n19 See Order to Show Cause at P 186.   \n20 PJM Interconnection, L.L.C., 112 FERC ¶ 61,034, at P 1 (2005).   \n21 PJM Interconnection, L.L.C., 113 FERC ¶ 63,024, at P 8 (2005) (Order certifying uncontested settlement); \nPJM Interconnection, L.L.C., 113 FERC ¶ 61,279 (2005) (Order accepting settlement and dismissing \nrehearing request).   \n22 Tariff, Part I, Definitions A-B (“Behind The Meter Generation”); Tariff, Part I, Definitions L-M-N (“Non-\nRetail Behind The Meter Generation”)."},{"page":6,"startToken":1488,"endToken":1831,"text":"Interconnection); provided, however, that Behind  The Meter \nGeneration does not include (i) at any time, any portion of such \ngenerating unit’s capacity that is designated as a Generation \nCapacity Resource; or (ii) in an hour, any portion of the output of \nsuch generating unit that is sold to another entity for consumption at \nanother electrical location or into the PJM Interchange Energy \nMarket.23   \nThe term Non-Retail Behind The Meter Generation refers to the Behind the Meter \nGeneration definition and is further defined as: “Behind the Meter Generation that is used \nby municipal electric systems, electric cooperatives, or electric distribution companies to \nserve load.”24  Currently, there is no definition of “Retail BTMG.”   \n \nAs discussed above, the Tariff permits netting of load with BTMG to reduce \napplicable PJM charges.25  Accordingly, Section 34.2 of the Tariff states, “[t]he daily load \nof a Network Customer does not include load served by operating Behind The Meter \nGeneration.  The daily load of a Network Customer shall not be reduced by energy \ninjections into the transmission system by the Network Customer.”26  Section 34.3 sets \nforth a cap on the netting of Non-Retail BTMG not to exceed 3000 MW across the PJM \nRegion.27  Thus, under the current rules, retail BTMG is not capped, but Non-Retail BTMG \nis limited to 3000 MW across the PJM Region.   \n2. \nSatisfaction of the Commission’s Compliance Directive \nPursuant to the Commission’s order, PJM is updating the definition of Behind the \nMeter Generation and adding a new definition for Retail Behind the Meter Generation to: \n \n23 Tariff, Part I, Definitions A-B (“Behind The Meter Generation”). \n24 Tariff, Part I, Definitions L-M-N (“Non-Retail Behind The Meter Generation”). \n25 See PJM Interconnection, L.L.C., 107 FERC ¶ 61,113, at P 1.   \n26 Tariff, Part III, section 34.2.   \n27 Tariff, Part III, section 34.3.  The cap for the PJM Region was initially set at 1500 MW in 2006, and \n“proportionately increased based on load growth in the PJM Region [thereafter] but shall not be greater than \n3000 megawatts.”  Id."},{"page":7,"startToken":1831,"endToken":2207,"text":"(1) establish a “materiality threshold” for Retail BTMG, (2) implement a “three-year \ntransition period,” and (3) provide the ability to “grandfather certain entities with existing \ncontracts.”28  In accordance with the Commission’s clarification, this compliance filing is \nlimited to retail BTMG and did not direct any changes to Non-Retail BTMG rules.29   \nSpecifically, PJM’s proposed definition for Retail Behind the Meter Generation (to \nbe added to Parts I and VIII of the Tariff, and not Part VII which relates to a transition \nprocess no longer accepting new applications) is: \n“Retail Behind The Meter Generation” shall refer to Behind \nThe Meter Generation that is used to serve a retail load \nserved by a Network Customer located at the same electrical \nlocation, where such generation has a cumulative nameplate \nrating of no greater than 50 MW (not including back-up \ngeneration at the same electrical location as the retail load \nthat can only be used to serve such retail load during \nconditions that may threaten the integrity or reliability of the \nPJM \nRegion \nor \nthe \nregional \npower \nsystem).  \nNotwithstanding the foregoing and for a transition period \nthrough December 18, 2028, Retail Behind The Meter \nGeneration includes any generation with a cumulative \nnameplate rating greater than 50 MW used to serve a retail \nload served by a Network Customer to net load prior to \nDecember 18, 2025. Provided further, Retail Behind The \nMeter Generation includes any generation used to serve a \nretail load served by a Network Customer to net load if it is \nthe subject of a contractual arrangement (including but not \nlimited to a bilateral agreement or interconnection \nagreement) that was in effect as of December 18, 2025 \nthrough the end of the term of such agreement, which may \nbe renewed or extended per the terms of such agreement.  \nFurther, Retail Behind The Meter Generation also includes \nany generation with a cumulative nameplate rating greater \nthan 50 MW used to serve a retail load served by a Network \nCustomer to net load that, as of December 18, 2025, was a \nQualifying Facility consistent with the requirements of the \nPublic Utility Regulatory Policies Act of 1978, as amended, \nand its implementing regulations.  Any facility that qualifies \n \n28 Order to Show Cause at P 179.   \n29 Id. at P 222."},{"page":8,"startToken":2207,"endToken":2466,"text":"as Retail Behind The Meter Generation shall be excluded \nfrom Co-Located Load configurations. \n \na. \nLegacy Treatment of Contracts that Effectuate Retail BTMG \nArrangements \nThe Commission recognized that certain parties “may . . . have contracted for the \nspecific purpose of effectuating a BTMG arrangement.”30  Accordingly, the Commission \ndirected that, “[t]o the extent that an entity is a party to an existing contract for such a \npurpose, we find that it is appropriate to grandfather such entity so that it may continue \nusing BTMG for the current term remaining under the existing contract.”31  In other words, \nany existing retail BTMG with a contract that was entered into for the purpose of \neffectuating a BTMG arrangement as of the date of the Commission’s order (i.e., December \n18, 2025) through the term of such agreement would be permitted to remain eligible to net \nagainst Network Loads as Retail BTMG irrespective of the threshold proposed below.   \nBusinesses and institutions operating on-site generation have relied on the Retail \nBTMG rules for over two decades, some investing substantial sums in building and \nmaintaining units that are deeply embedded into their own operations.  Considering the \ncomplexity and maturity of these configurations, a wide variety of contracts may be \nemployed and relied on for the operation of these units, including utility contracts, fuel \ncontracts, maintenance contracts, and more.  PJM understands the Commission’s contract-\nexception to the three-year transition mandate to be designed to generally enable these \nestablished generation investments to operate under existing assumptions while those \ncontracts remain effective. \n \n30 Id. at P 224.   \n31 Id."},{"page":9,"startToken":2466,"endToken":2802,"text":"Specifically, PJM interprets the Commission’s compliance directive to allow \nexisting BTMG arrangements to qualify for legacy treatment so long as there is an existing \ncontractual agreement for the purpose of effectuating a BTMG arrangement (e.g., bilateral \nagreement, interconnection agreement, etc.)32 that was in effect prior to December 18, \n2025.  And to recognize contracting parties’ expectation of renewal or extension rights \nunder such existing agreements and to avoid interference with such reliance expectations \nupon which investment decisions likely have been made (the specific terms and conditions \nof which PJM does not have knowledge of), PJM further interprets the Commission’s use \nof the phrase “the current term remaining under the existing contract” to encompass \nexisting renewal or extension rights recognized under such existing contracts.     \nIn addition, the Commission’s compliance directive was issued against the \nbackdrop of the Public Utility Regulatory Policies Act of 1978, as amended, and its \nimplementing regulations.  While the Order to Show Cause does not reference this \nregulatory regime and its impacts, PJM interprets the Commission’s compliance directive \nas allowing the extension of legacy treatment to any generation with a cumulative \nnameplate rating greater than 50 MW used to serve a retail load served by a Network \nCustomer to net load that, as of December 18, 2025, was a Qualifying Facility (“QFs”).  In \nlight of stakeholder engagement and pleadings submitted in this proceeding, PJM \nunderstands that there exists today Retail BTMG that were QFs as of December 18, 2025, \nwith many being cogeneration QFs that are often used in manufacturing and other \nprocesses to produce both electricity and useful thermal energy that often lead to economic \n \n32 If accepted by the Commission, PJM will explore with stakeholders whether Manual language should be \ndeveloped to help elaborate on what types of agreements may qualify.  Further, PJM notes that some of the \nprerequisites for participation are compliance obligations Retail BTMG must be able to establish and verify \nfor purposes of their own compliance even if PJM may not have a role in reviewing such information."},{"page":10,"startToken":2802,"endToken":3165,"text":"and energy efficiency benefits.33  Under Commission regulations, QFs have built-in size \nlimits or, for cogeneration, meet strict efficiency requirements.34  Specifically, for a \ncogeneration QF, the generating facility and its load are closely integrated.  For example, \nsome retail customers’ loads may be configured such that the load reduces if on-site \ngeneration is unavailable because manufacturing processes reliant on thermal heat will \ndiscontinue.     \nGiven that existing retail BTMG arrangements with such contractual agreements \nand that otherwise have QF status have been in place and netted against Network Loads \nwithin PJM without known operational issues to date, PJM proposes to allow such \narrangements, which in some cases have been in place for decades, to qualify for legacy \ntreatment and continue to be eligible to net under the existing BTMG rules.  \nGoing forward, however, consistent with the Commission’s directive, any new \nlarge Retail BTMG that is greater than the proposed threshold would not be eligible to \nqualify as Retail BTMG given that significant increases of new large loads generally on \nthe system that the Commission determined could increase operational risks and costs \nshifting concerns.35  Specifically, the Commission directed PJM to “maintain the current \nBTMG rules for customers that fall below a new MW materiality threshold.”36  Given the \n \n33 PJM Interconnection, L.L.C., et al., PJM Industrial Customer Coalition’s Request for Clarification or \nRehearing, Docket No. EL25-49-000, et al., at 10 (Jan. 20, 2026).  Indeed, the PJM Industrial Customer \nCoalition asserts that, “PURPA has been a boon to manufacturers and the electric grid for well over four \ndecades, providing market access where such access did not previously exist, taking strain off the grid, and \nsupporting American industry by allowing for economic means of reducing energy costs.  Many QFs are \nhighly efficient facilities, including cogeneration facilities, which produce both electricity and heat from the \nsame fuel source, then making use of the ‘waste heat’ in industrial operations.  QFs are entitled to have access \nto supplementary power, back-up power, maintenance power, and interruptible power, pursuant to enacting \nregulations.”  Id. \n34 16 U.S. Code § 824a-3; 18 C.F.R. § 292.204. \n35 Order to Show Cause at PP 179, 186.   \n36 Id. at P 179."},{"page":11,"startToken":3165,"endToken":3434,"text":"Commission’s identified cost causation, transition, and resource adequacy concerns with \nthe existing Retail BTMG rules, the proposal is based on an interpretation of the \ncompliance directive that demands an “all or nothing” approach to Retail BTMG \nqualification – meaning that a Retail BTMG cannot both net up to a certain threshold but \nstill potentially have generation and load above that threshold which cannot be netted.  PJM \nunderstands that such a hybrid approach would impose significant costs on all Retail \nBTMG that would have to install previously unnecessary metering equipment (that, for \nsome facilities, may be cost prohibitive) and it amplifies compliance risks for units because \nit might require many facilities to monitor and report different generator output and load \nthresholds in relation to the threshold.     \nb. \nThree-Year Transition Period \nTo “minimize the impact” of changing the BTMG rules on existing customers, the \nCommission ordered PJM “to allow Network Customers already using the BTMG rules to \ncontinue to do so for a transition period of three years . . . from the date of issuance of this \norder.”37  Thus, in the event there are any existing Retail BTMG larger than the proposed \nthreshold discussed below and not the subject of an existing contractual agreement in effect \nor qualifying QF status as of December 18, 2025, such resources would continue to be \neligible to participate as retail BTMG for up to three additional years (i.e., through \nDecember 18, 2028).  \nc. \nMateriality Threshold \nIn accordance with the Commission’s compliance directive, PJM proposes to \nestablish a materiality threshold of up to 50 MW for a generator at the same electrical \n \n37 Id. at P 223."},{"page":12,"startToken":3434,"endToken":3759,"text":"location as the Network Load for generation units to qualify as Retail BTMG.  This 50 MW \nthreshold aligns with the PJM Board’s definition of large loads additions, which comprise \nof individual loads at or above 50 MW at a single point of interconnection.38  Based on \nstakeholder feedback and engagement on this point, PJM understands the proposed 50 MW \nthreshold to avoid unneeded regulatory uncertainty for retail customers whose grid impacts \non reliability are more limited and have been in existence without noted impact for \ndecades.39   \nFurther, the proposed threshold and proposed exclusion for backup generation from \nthe threshold (along with the proposed legacy treatment) will avoid the unintended \nconsequence of causing Retail BTMG resources to prematurely cease operations and \ndiscontinue investment in grid-enhancing backup generation, outcomes which would \nfrustrate system reliability in an unintended fashion.  In developing the materiality \nthreshold, PJM discussed with stakeholders that a lower threshold of 10 or 20 MW would \nlikely exclude from Retail BTMG a much larger volume of retail customers whose grid \nimpacts are small or de minimis when compared with the Co-Located Load coming online \ntoday.  Further, concerns were raised that a lower threshold could force many existing \nRetail BTMG resources offline during the transition period because such resources do not \nintend to enter into PJM’s interconnection queue to become a market resource.  PJM \nunderstands that many of the existing Retail BTMG are decades old and may need \nsignificant upgrades prior to directly interconnecting into the PJM system.  However, given \n \n38 PJM, Board Decisional Letter on Critical Issue Fast Path – Large Load Additions, at 2 (Jan. 16, 2026), \nhttps://www.pjm.com/-/media/DotCom/about-pjm/who-we-are/public-disclosures/2026/20260116-pjm-\nboard-letter-re-results-of-the-cifp-process-large-load-additions.pdf. \n39 Order to Show Cause at P 221 (“Such a threshold should reduce the reliability and resource adequacy risks \ndiscussed that large loads may pose to PJM, while also allowing for Network Customers to reduce their \ntransmission charges in a transparent, not unduly discriminatory fashion.”)."},{"page":13,"startToken":3759,"endToken":4032,"text":"the costs associated with such significant upgrades, the owners of such resources may \ndecide to forgo the option of interconnecting into the PJM system altogether.  The effect of \nsuch an outcome would result in higher Network Loads requiring grid service, as loads that \nare currently netted by the retail BTMG would not be matched with additional supply of \nCapacity Resources.  Because the Order to Show Cause’s BTMG reforms are directed at \nstemming reliability concerns, not exacerbating them, the 50 MW threshold is a justified \nthreshold for Retail BTMG eligibility. \nAdditionally, excluding true on-site back-up power from determining whether the \nthreshold has been reached critically avoids disincentivizing and discouraging retail \ncustomers from installing back-up power installations that would have positive reliability \nimplications for the region.  The Department of Energy recently observed that \n“[d]eployment of backup generation resources . . . can prevent avoidable blackouts, thereby \nsaving lives and reducing costs to the American people.”40  The proposed Retail BTMG \nthreshold should not frustrate investment by such resources in such reliability enhancing \nbackup generation.  In the PJM Region specifically, it is notable that during the recent \nWinter Storm Fern, the Department of Energy issued an Order applicable in the PJM \nRegion pursuant to Section 202(c) of the Federal Power Act that directed “PJM, in \ncollaboration with its Transmission Owners, . . . to direct backup generation resources . . . \nto operate as a last resort before declaring an Energy Emergency Alert (EEA) 3 (i.e., before \nfirm load interruption) or during an EEA 3.”41  The language in the proposal excepting \n \n40 US Department of Energy, Order No. 202-26-06 (Jan. 26, 2026), https://www.energy.gov/documents/doe-\norder-no-202-26-06-pjm.  \n41 Id."},{"page":14,"startToken":4032,"endToken":4333,"text":"certain on-site back-up power from the materiality threshold will preserve the availability \nof this potential reliability tool.   \nPJM proposes to establish a threshold based on the size of the generator that may \nqualify as retail BTMG, which is consistent with the Commission’s points of reference to \npotential threshold sizes based on various generator sizes.42  Establishing a threshold based \non the size of the generator to qualify as retail BTMG is similarly consistent with the \nrecognition that BTMG is defined as a generation unit, rather than a load.  Further, a \nthreshold based on the size of the generator provides a clear and bright line for what can \ncontinue qualifying as retail BTMG.  That is, load sizes can fluctuate, unlike the nameplate \nrating of a generator, which is static.  In short, proposing a threshold based on the size of \nthe generator to qualify as retail BTMG is superior to or consistent with the Commission’s \ncompliance directive and underlying goal of limiting the risk of the resource adequacy \nconcerns43 arising from allowing large BTMG to net against Network Loads.  \nWhile a 50 MW materiality threshold for new retail BTMG is appropriate going \nforward, in the event the Commission does not accept PJM’s proposed legacy treatment for \nthe purpose of effectuating BTMG discussed above, PJM requests that the Commission \nallow an interim initial materiality threshold to be in place for the start of the transition \nperiod to avoid setting an initial threshold that is too low and that could, for the reasons \nstated above, cause Retail BTMG resources to cease operations and in turn exacerbate in \nan unintended fashion the resource adequacy issues in the PJM Region.  In this \ncircumstance, as a potential short-term stopgap, if PJM’s proposed Retail BTMG revisions \n \n42 Order to Show Cause at P 221.   \n43 Id. at P 186."},{"page":15,"startToken":4333,"endToken":4665,"text":"are not accepted, PJM observes that the PJM Industrial Customer Coalition (“PJM ICC”)44 \nindicated that “a threshold of 200 MW would, as a practical matter, permit most existing \nindustrial and institutional loads to continue to benefit from the major energy investments \nthey have made over decades, consistent with the ‘actual use’ principle.  As super-sized \nloads are a largely new phenomenon, the number of entities requiring grandfathering of \nexisting contracts and facilities would be far more limited at a 200 MW threshold.”45  \nShould the Commission adopt a higher interim materiality threshold of this sort at the start \nof the transition period, PJM commits to reviewing additional data from Transmission \nOwners on the extent and size of existing Retail BTMG.46  This data could inform whether \nthe interim materiality threshold should be further refined in the future through a separate \nfiling on compliance in this docket or, if necessary, pursuant to section 205 of the Federal \nPower Act. \nd. \nProposed Tariff Updates \nTo effectuate the foregoing updates to the rules for retail BTMG, PJM proposes to \nestablish a new definition for “Retail Behind The Meter Generation” and clarify that the \ndefinition of “Behind The Meter Generation” broadly reflects the two species of BTMG:  \nRetail BTMG and Non-Retail BTMG.  Consistent with the Commission’s clarification that \nit does “not direct PJM to change its rules for non-retail BTMG,”47 it is appropriate to \nestablish a new dedicated definition for Retail Behind The Meter Generation that clearly \n \n44 PJM Interconnection, L.L.C., et al., PJM ICC’s Request for Clarification or Rehearing, Docket No. EL25-\n49-000, et al., at 44 (Jan. 20, 2026). \n45 Id. \n46 PJM has existing authority to require Members to provide records and documentation of retail BTMG data \ngiven that it is necessary for the “coordination of operations” and “coordination of planning, including those \ndata required for capacity accounting under the Reliability Assurance Agreement” pursuant to Operating \nAgreement, section 11.3.1(a). \n47 Order to Show Cause at P 222."},{"page":16,"startToken":4665,"endToken":5050,"text":"distinguishes this type of resource.  PJM is also seeking to avoid any inadvertent changes \nto the substantive rules pertaining to Non-Retail Behind The Meter Generation.  For this \nreason, PJM also proposes to add clarifying language in Tariff, Part III, section 34.3 \nproviding that “The daily load of a Network Customer does not include load served by \noperating Non-Retail Behind The Meter Generation.”48  This insertion preserves the status \nquo on this issue for Non-Retail Behind The Meter Generation.  \nFor the new definition of Retail Behind The Meter Generation, PJM is defining that \nas “Behind The Meter Generation that is used to serve a retail load served by a Network \nCustomer located at the same electrical location, where such generation has a cumulative \nnameplate rating of no greater than 50 MW (not including back-up generation at the same \nelectrical location as the retail load that can only be used to serve such retail load during \nconditions that may threaten the integrity or reliability of the PJM Region or the regional \npower system).”49    \nTo effectuate the legacy treatment discussed above, PJM proposes to include \nlanguage in the newly defined Retail Behind The Meter Generation that states: “Retail \nBehind The Meter Generation includes any generation used to serve a retail load served by \na Network Customer to net load if it is the subject of a contractual arrangement (including \nbut not limited to a bilateral agreement or interconnection agreement) that was in effect as \nof December 18, 2025 through the end of the term of such agreement, which may be \n \n48 PJM understands Tariff, Section 34.2 was originally drafted to generally state that all BTMG, including \nNon-Retail BTMG, can be netted against a Network Customer’s daily load.  Tariff, Section 34.3 goes on to \nplace a limitation on the amount of Non-Retail BTMG that can be used for those netting purposes.  While it \nis implicit in Tariff, Section 34.3 that Non-Retail BTMG can net against load, the proposed revision to Tariff, \nSection 34.2 suggests clarification to Tariff, Section 34.3 is necessary since the Tariff otherwise no longer \nhas an explicit statement that says that the daily load of a Network Customer does not include load served by \nNon-Retail BTMG. \n49 Proposed Tariff Revisions, Part I, Definition of Retail Behind The Meter Generation."},{"page":17,"startToken":5050,"endToken":5332,"text":"renewed or extended per the terms of such agreement.  Further, Retail Behind The Meter \nGeneration also includes any generation with a cumulative nameplate rating greater than \n50 MW used to serve a retail load served by a Network Customer to net load that, as of \nDecember 18, 2025, was a Qualifying Facility consistent with the requirements of the \nPublic Utility Regulatory Policies Act of 1978, as amended, and its implementing \nregulations.”50   \nNext, consistent with the Commission’s order, PJM is also including language \nregarding the three-year transition that would be applicable to any existing retail BTMG \nthat does not have an agreement in effect as of December 18, 2025, in the definition of \nRetail Behind The Meter Generation.  Specifically, PJM proposes to specify that “for a \ntransition period through December 18, 2028, Retail Behind The Meter Generation \nincludes any generation with a cumulative nameplate rating greater than 50 MW used to \nserve a retail load served by a Network Customer to net load prior to December 18, 2025” \nmay continue to be included as Retail Behind The Meter Generation.   \nIn accordance with the Commission’s compliance directive, PJM’s compliance \nfiling “maintain[s] the current BTMG rules for customers that fall below [the] new \nmateriality threshold for the amount of load at a particular electrical location that Network \nCustomers may net using BTMG.”51  That is, PJM is proposing to only establish a generator \nsize threshold, along with the legacy and transition rules, for what can qualify as Retail \nBehind The Meter Generation while retaining all substantive existing netting provisions \nrelated to Retail BTMG, and BTMG in general, as part of this compliance filing. \n \n50 Id. \n51 Order to Show Cause at P 179."},{"page":18,"startToken":5332,"endToken":5580,"text":"Lastly, PJM proposes language for the definition of Retail BTMG that provides that \n“Any facility that qualifies as a Retail Behind The Meter Generation shall be excluded from \nCo-Located Load configurations.”  This language is intended to provide clarity and \ndirection to project developers about what pathways are available to serve load that is co-\nlocated, and to avoid unexpected and unintended hybrid scenarios mixing BTMG and the \nnew transmission service products the Commission has directed in the Order to Show \nCause.  \nB. \nTransmission Services for Co-Located Load \nIn compliance with the Order to Show Cause,52 PJM is proposing to add to its Tariff \nthree new transmission services that an Eligible Customer taking transmission service on \nbehalf of a Co-Located Load may select, in addition to existing Network Integration \nTransmission Service.  Furthermore, PJM is proposing three new transmission service \nagreements to reflect the rates, terms, and conditions for these new transmission service \noptions that are available to Eligible Customers.  Below, the Tariff revisions proposed here \neffectuate several discrete directives in the Order to Show Cause relating to the new \ntransmission services (while the rates, terms, and conditions of such services remain \nuncertain and the subject of an ongoing paper hearing). \n1. \nTariff Revisions in Transmittal Letter v. Illustrative Tariff Revisions \nin PJM’s Initial Brief. \n \nTo be clear, the Tariff changes proposed in this Transmittal letter comprise only a \nminority of the Tariff revisions that will be needed to effectuate these transmission services.  \n \n52 Id. at PP 160, 178."},{"page":19,"startToken":5580,"endToken":5890,"text":"Concurrently with this Transmittal Letter, PJM is filing an Initial Brief to address the paper \nhearing questions that the Commission required in its Order to Show Cause.53   \nIn that Initial Brief, PJM will provide illustrative Tariff language for the majority \nof the non-rate terms and conditions of service for these new transmission services.54  \nBecause such language will change upon a Commission action in the paper hearing, PJM \nis not filing the new transmission services Tariff language as part of this Transmittal Letter, \nbut is rather labeling the language in Attachment A to the Initial Brief as “illustrative” to \nsignal that it is subject to the outcome of the paper hearing.  \nPutting aside the non-rate terms and conditions that are the subject of PJM’s Initial \nBrief, the Order to Show Cause required PJM to file several specific Tariff revisions to \neffectuate these new transmission services.  PJM describes these Tariff revisions below. \n1. \nNew Part XI, Attachments F-3A and F-4 \nFirst, the Commission required PJM to establish several new transmission services \nfor Eligible Customer serving Co-Located Load.55   \nInterim Network Integration Transmission Service:  PJM is proposing to revise its \nTariff to allow an Eligible Customer serving Co-Located Load that is seeking to take NITS \nunder Tariff, Part III the option to seek Interim NITS subject to provisions in a new Tariff, \nPart XI.  With this Transmittal letter, PJM is filing a “shell” of Tariff, Part XI, to show that \nthis service will be housed in a new Part XI of PJM’s Tariff,56 and provides the proposed \n \n53 Id. at P 219; Ordering Paragraph E. \n54 PJM Interconnection, L.L.C., et al., PJM’s Initial Brief, Attachment A, Docket No. EL25-49-000, et al. \n(Feb. 23, 2026) (“PJM Initial Brief”). \n55 Order to Show Cause at PP 160, 178. \n56 See Attachment A (Clean Tariff Revisions); Attachment B (Redline Tariff Revisions)."},{"page":20,"startToken":5890,"endToken":6201,"text":"non-rate terms and conditions in PJM’s Initial Brief.57  As discussed further in PJM’s Initial \nBrief, this new transmission service, as required by the Order to Show Cause,58 would \nallow an Eligible Customer taking service on behalf of Co-Located Load that has requested \nNITS to receive transmission service on behalf of a Co-Located Load on a non-firm, \ninterruptible basis for the period until transmission upgrades required to provide NITS are \ncomplete and placed in service.   \nWith this Transmittal, PJM is proposing a new Attachment F-3A, which will serve \nas the service agreement for Eligible Customers taking on behalf of a Co-Located Load \nNetwork Integration Transmission Service and/or Interim Network Integration \nTransmission Service.59  The Commission requires PJM to establish “a transmission \nservice agreement that reflects the rates terms, and conditions of these new transmission \nservice options is available to Eligible Customers.”60  PJM is filing a “shell” of Attachment \nF-3A, to show that the service agreement will be a new Attachment F-3A,61 but notes that \nthe proposed language of Attachment F-3A is discussed in the Initial Brief.62  As explained \nin PJM’s Initial Brief, the new Attachment F-3A is based upon existing Attachment F-3 \nfor Network Integration Transmission Service, but is tailored to arrangements that involve \nCo-Located Load.   \nFirm Contract Demand Transmission Service and Non-Firm Contract Demand \nTransmission Service:  In compliance with the Order to Show Cause, PJM is also proposing \n \n57 PJM Initial Brief, Attachment A (new Part XI illustrative language, with sections 700-707 setting forth \nproposed non-rate terms and conditions for Interim Network Integration Transmission Service).   \n58 Order to Show Cause at PP 201, 203. \n59 See Attachment A (Clean Tariff Revisions); Attachment B (Redline Tariff Revisions).  \n60 Order to Show Cause at P 193. \n61 See Attachment A (Clean Tariff Revisions); Attachment B (Redline Tariff Revisions).   \n62 See PJM Initial Brief, Attachment A (Attachment F-3A)."},{"page":21,"startToken":6201,"endToken":6492,"text":"two new Contract Demand Transmission Services.  First, PJM is proposing a new Firm \nContract Demand Transmission Service which would allow an Eligible Customer taking \ntransmission service on behalf of a Co-Located Load to take service up to a pre-specified \nMW quantity.  Second, PJM is proposing a new Non-Firm Contract Demand Transmission \nService for those Eligible Customers taking service on behalf of Co-Located Loads that do \nnot necessarily plan to withdraw energy from PJM’s transmission system on a regular \nbasis.  These customers will only take energy on an as-needed and as-available basis.   \nWith this Transmittal, PJM is filing a “shell” of Tariff, Part XI, to show that these \ntwo services will be housed in a new Part XI of PJM’s Tariff,63 with the proposed Part XI \nlanguage contained in PJM’s Initial Brief.64  Firm Contract Demand Transmission Service \nand Non-Firm Contract Demand Transmission Service will be subject to a new Service \nAgreement specific to Contract Demand Transmission Service to be contained in Tariff, \nAttachment F-4.  PJM is filing a “shell” of Attachment F-4, to show that the service \nagreement will be a new Attachment F-4,65 but notes that the proposed language of \nAttachment F-4 is discussed in its Initial Brief.66   \nPJM will file the full text of Part XI, Attachment F-3A, and Attachment F-4 upon \nthe Commission’s decision following the conclusion of the paper hearing procedures. \n \n63 See Attachment A (Clean Tariff Revisions); Attachment B (Redline Tariff Revisions).   \n64 See PJM Initial Brief, Attachment A (new Part XI illustrative language).   \n65 See Attachment A (Clean Tariff Revisions); Attachment B (Redline Tariff Revisions). \n66 See PJM Initial Brief, Attachment A (new Part XI illustrative language, with sections 708-716 setting forth \nproposed non-rate terms and conditions for Contract Demand Transmission Services)."},{"page":22,"startToken":6492,"endToken":6749,"text":"2. \nPart III Revisions \nPJM is also proposing Tariff revisions to Part III (Network Integration \nTransmission Service), to comply with several discrete requirements in the Commission’s \nOrder to Show Cause.   \nEligible Customers remain eligible to take Network Integration Transmission \nService under Tariff, Part III on the same terms and conditions as before.  First, the \nCommission required PJM to file a new provision explaining that an Eligible Customer \ntaking transmission service on behalf of the Co-Located Load takes one of three \ntransmission services.67  PJM includes the following redline in Part III to comply with this \nrequirement.68   \nEligible Customers taking transmission service on behalf of \nCo-Located Load must take one of the following services:  \n(1) Network Integration Transmission Service under Tariff, \nPart III, with the option to seek Interim Network Integration \nTransmission Service subject to the provisions in Part XI; \n(2) Firm Contract Demand Transmission Service under \nTariff, Part XI; or (3) Non-Firm Contract Demand \nTransmission Service under Tariff, Part XI.  Co-Located \nLoad, which is not served through one of these services must \ntake all necessary steps to disconnect from the Transmission \nSystem.  \n \n \nAdditionally, the Commission provided that while Eligible Customers serving Co-\nLocated Load may take a “combination” of the Firm and Non-Firm Contract Demand \nservices,69 if the Eligible Customer elects to take NITS or Interim NITS, it may not \n \n67 Order to Show Cause at P 193. \n68 See Attachment A (Clean Tariff Revisions; Part III General); Attachment B (Redline Tariff Revisions, Part \nIII General). \n69 Order to Show Cause at PP 194, 197."},{"page":23,"startToken":6749,"endToken":7030,"text":"combine NITS with the Contract Demand services.70  Therefore, PJM also included the \nfollowing proposed revision in Tariff, Part III:71 \nAn Eligible Customer taking transmission service on behalf \nof a Co-Located Load may not take Network Integration \nTransmission Service or Interim Network Integration \nTransmission Service for that Co-Located Load at the same \ntime it is taking Firm Contract Demand Transmission \nService or Non-Firm Contract Demand Transmission \nService on behalf of that Co-Located Load.  \n \nAdditionally, the title of the initial section of Part III has been changed from \n“Preamble” to “General,” to reflect the broader nature of the provisions contained in the \nPart.72 \nOther changes have been made to Tariff, Part III.  In section 28.1, PJM has added \na sentence that Eligible Customers taking service on behalf of Co-Located Load may also \nreceive Network Integration Transmission Service.  This is compliant with the \nCommission’s order that Network Integration Transmission Service must be one of the \nseveral transmission service choices that Eligible Customers taking transmission service \non behalf of Co-Located Load may select.73   \nAdditionally, in Part III, section 29.1, PJM has clarified that such Network \nIntegration Transmission Service taken on behalf of Co-Located Load will be (1) subject \nto a new Form of Service Agreement (Attachment F-3A)74 and (2) must satisfy certain \n \n70 Id. at n.408, P 197. \n71 See Attachment A (Clean Tariff Revisions; Part III General); Attachment B (Redline Tariff Revisions, Part \nIII General). \n72 See Id. \n73 Order to Show Cause at P 193. \n74 This complies with the Commission’s requirement that PJM establish a new transmission service \nagreement for the transmission services available to Eligible Customers serving Co-Located Load.  Id. at P \n193."},{"page":24,"startToken":7030,"endToken":7310,"text":"requirements such as designation of an Eligible Customer and the individual Co-Located \nLoad.75  PJM also clarifies that the Network Integration Transmission Service that is \napplicable to Eligible Customers taking transmission service on behalf of Co-Located Load \nshall be Regional Network Integration Transmission Service, not Cross-Border Network \nIntegration Transmission Service.76   \nOther changes have been made throughout Part III to clarify that Eligible \nCustomers taking Network Integration Transmission Service on behalf of Co-Located \nLoad are subject to the same requirements as other Network Integration Transmission \nService Customers.77   \n \nFinally, PJM includes revisions to Part III, section 31.6, regarding submission of \nannual load and resource information, to clarify the additional information that PJM will \nrequire Eligible Customers taking Network Integration Transmission Service on behalf of \nCo-Located Load to provide, including the demand characteristics of the Co-Located Load, \nand the supply characteristics of the designated Co-Located Generating Facility. \nC. \nNecessary Studies and Necessary Studies Agreement \n \nPJM is further proposing Tariff revisions to Parts III and VIII of the Tariff to \ncomply with the Commission’s directives regarding the Necessary Study Process for \nExisting Interconnection Customers.78  These proposed revisions are intended to apply \nuniformly to all existing customers regardless of whether they have presently effective \n \n75 This complies with the Commission’s requirement that an Eligible Customer must be designated.  Id. at P \n188.  See also proposed revision to Tariff, Part IX, Subpart B (pro forma GIA), Schedule O (requiring \ndesignation of “Eligible Customer taking transmission service on behalf of the Co-Located Load” among \nother information). \n76 Proposed Tariff revisions, Part III, section 29.2. \n77 See, e.g., Tariff, Part III, Section 29.2. \n78 Order to Show Cause at PP 225-230."},{"page":25,"startToken":7310,"endToken":7626,"text":"interconnection agreements issued pursuant to Parts IV, VI, VII, or VIII of the Tariff.79  \nNotably, in some instances, a customer may not yet have a three-party interconnection \nagreement involving PJM in which case additional processes are required to convert to a \nthree-party agreement before the necessary study process can be followed. \n \nThe thrust of PJM’s proposed revisions require any Existing Interconnection \nCustomer that seeks to serve Co-Located Load to follow a clarified necessary study process \ndetailed in Part VIII of the Tariff and the related Form of Necessary Study Agreement set \nforth in Tariff, Part IX, Subpart G.  If there is an Existing Interconnection Customer that \ndesires to serve Co-Located Load with a Service Agreement issued pursuant to Tariff, Parts \nIV and VI, proposed revisions to Part III of the Tariff will require such customers to begin \nthe process of amending such service agreements by following the tariffed necessary study \nprocess in Part VIII.80  The same process will be followed for any customers with effective \ninterconnection agreements issued pursuant to Parts VII or VIII.  In all situations, \ncustomers will be required to enter into a Necessary Study Agreement with PJM in the \nform already in the Tariff (subject to proposed modifications set forth in the filing).81   \nConsistent with the requirements in Paragraph 227 of the Order to Show Cause, \nPJM proposes to require customers to provide PJM with all information needed to perform \nthe Necessary Studies, as further detailed in the PJM Manuals, including but not limited \nto82: \n \n79 The next section of this transmittal letter notes revisions to PJM’s interconnection application for new \ngenerator interconnection requests that intend to serve Co-Located Load.  Order to Show Cause at P 188.   \n80 Proposed Tariff Revisions, Part III (General). \n81 Order to Show Cause at P 226. \n82 See generally proposed revisions to Tariff, Part VII, Subpart A, section 401.H.3.b.i - iii."},{"page":26,"startToken":7626,"endToken":8088,"text":"• the proposed configuration for the Co-Located Load and Co-Located Generating \nFacility, including a single-line diagram. \n• all Eligible Customer information required in the application including the type of \nTransmission Service the Eligible Customer will take on behalf of the Co-Located \nLoad. \n• the amount of Capacity Interconnection Rights (“CIRs”) reduction resulting from \nthe Co-Located Load configuration.83 \n• Details of any necessary control technologies and protection systems needed to \nprevent withdrawals of energy from the Transmission System in excess of the \nenergy withdrawals permitted under the Eligible Customer’s Service Agreement.84 \nFurther, consistent with the Commission’s directive in the Order to Show Cause, \nParagraph 230, PJM’s necessary study procedures are also being amended to leave no \ndoubt that “[a] Project Developer shall not implement any planned modifications to its \n \n83 The Order to Show Cause provides that an “existing generating facility may not begin serving Co-Located \nLoad that is not Network Load until it has delisted its CIRs for the portion of the generating facility to be \ndesignated to serve any Co-Located Load that is not receiving NITS.  In order for an existing generator to \nde-list its CIRs to serve Co-Located Load, the Interconnection Customer must revise its ISA or GIA and bear \nthe cost of all required system upgrades[.]”  Id. at P 230.  To promote clarity about this issue to readers of \nthe Tariff, PJM’s filing also proposes to memorialize this directive in the Tariff language itself.  See proposed \nrevisions to Tariff, Part VII, Subpart A, section 401.H.3.a - b. \n84 Consistent with Commission directives in Order Nos. 845 and 845-A and language already embedded in \nPJM’s pro forma LGIP, PJM’s proposal here uses the term “necessary control technologies and protection \nsystems,” which may include Remedial Action Schemes.  Reform of Generator Interconnection Procedures \nand Agreements, Order No. 845-A, 166 FERC ¶ 61,137, at P 116 (2019) (“if the interconnection customer \nrequests interconnection service below generating capacity, it commits to operate consistent with such a \nrequest under section 3.1 of  the pro forma LGIP, which states that ‘[t]he necessary control technologies and \nprotection systems … for exceeding the level of Interconnection Service established in the executed, or \nrequested to be filed unexecuted, LGIA shall be established in Appendix C of that executed, or requested to \nbe filed unexecuted, LGIA.’”); Order No. 845, 163 FERC P 61,043, at P 396 (2018) (requiring “any \ninterconnection customer that seeks interconnection service below its generating facility capacity install \nappropriate monitoring and control technologies at its generating facility”); see also Tariff, Part IV, Subpart \nA, section 36.1.1A (“The necessary control technologies and protection systems shall be established in Tariff, \nAttachment O, Schedule K (Requirements for Interconnection Service Below Full Electrical Generating \nCapability) of the executed, or requested to be filed unexecuted Interconnection Service Agreement.”)."},{"page":27,"startToken":8088,"endToken":8443,"text":"facilities until the Necessary Studies have been completed and the amended Generation \nInterconnection Agreement reflecting the results of such studies is fully executed and \neffective.”85  This necessarily includes reflecting any CIR reduction necessary and \nresulting from a pursued Co-Located Load configuration. \nPJM’s proposed Tariff revisions also provide that the Necessary Studies to be \nperformed include thermal, short circuit, and stability studies under various seasonal and \nload conditions, as specified in more detail in PJM’s Manuals.86  In addition, the proposed \nrevisions provide that PJM shall assess the impact of87 the reduction in CIRs associated \nwith the Co-Located Load and Co-Located Load Generating Facility, any necessary control \ntechnologies and protection systems required as part of the Co-Located Load configuration, \nand any other changed conditions identified by Project Developer or Transmission Owner \nassociated with the Co-Located Load configuration.88 \nIn addition, PJM is proposing other conforming changes to the pro forma Necessary \nStudy Agreement to operationalize the proposed Tariff revisions and facilitate PJM’s \ncollection of the information necessary to perform requested Necessary Studies.89 \nLastly, consistent with the directives in Paragraph 228 of the Order to Show Cause, \nPJM is also proposing revisions that clarify that the “Project Developer shall be responsible \n \n85 See proposed revisions to Tariff, Part VII, Subpart A, section 401.H.3.a. \n86 See proposed revisions to Tariff, Part VII, Subpart A, section 401.H.3.b.ii. \n87 The definition of “Necessary Study” in Tariff, Part VIII, Subpart A, section 400 explains that the necessary \nstudy is an “assessment[] undertaken by the Transmission Provider to determine whether a planned \nmodification . . . will have a permanent material impact on the Transmission System”, among other things. \nPJM does not interpret the Commission’s compliance directives to narrow the scope of the Necessary Study \ninquiry and PJM has not elected to do so in this filing.  In fact, the Commission is directing consideration \nand evaluation of necessary control technologies and protection systems.   \n88 See proposed revisions to Tariff, Part VII, Subpart A, section 401.H.3.b.iii.   \n89 See proposed revision to Tariff, Part IX, Subpart A (pro forma application and necessary study agreement)."},{"page":28,"startToken":8443,"endToken":8726,"text":"for the costs of any modifications or Network Upgrades identified by Transmission \nProvider, as applicable, as a result of the change to the Interconnection Service Agreement \nor Generation Interconnection Agreement to serve Co-Located Load, including to reflect \nany reduction in Capacity Interconnection Rights.  Subject to Project Developer having a \nfully executed and effective Generation Interconnection Agreement governing a Co-\nLocated Load configuration, Project Developer may not begin serving Co-Located Load \nfrom the existing Generating Facility until all required Network Upgrades, necessary \ncontrol technologies and protection systems and metering identified as necessary are \ncomplete and in service.”90 \nD. \nOther Tariff Revisions (Generation Interconnection Procedures, pro \nforma GIA, pro forma Application and Studies Agreement, Other \nDefinitions, etc.) \nThe Order to Show Cause further directs a number of prescriptive clarifications and \nrevisions.  The chart below reflects the various directives (including a citation to the \nrelevant paragraph of the Order to Show Cause), and explains how PJM’s February 23 \nCompliance Filing addresses the directive with a reference to the proposed governing \ndocument revision.   \n \nFERC Requirement \nHow PJM Complies \nRevise Tariff, Part VIII to add to \nthe list of requirements for a New \nService \nRequest \nthat \nan \nInterconnection Customer who will \nuse its generating facility to serve \nCo-Located Load must specify an \nEligible Customer who will take \ntransmission service on behalf of \nthe Co-Located Load.  (Order to \nShow Cause at P 188) \nPJM complies by making the revision in Part VIII, \nSubpart B, section 403(1), new subsection “r.”  See \nalso proposed revision to Tariff, Part IX, Subpart \nB (pro forma GIA), Schedule O; proposed revision \nto Tariff, Part III, General.  \n \n \n90 See proposed revisions to Tariff, Part VII, Subpart A, section 401.H.3.b.iii."},{"page":29,"startToken":8726,"endToken":9171,"text":"Revise Tariff, Part VIII to explain \nthat if Interconnection Customer \nwants to serve Co-Located Load \nbut \nnot \nidentify \nan \nEligible \nCustomer, then it may take steps to \nterminate its generating facility’s \ninterconnection and serve the Co-\nLocated Load fully islanded from \nPJM’s transmission system.  (Order \nto Show Cause at P 189) \nPJM complies by making the revision in two \nplaces:  (1) Part III (General), and (2) Part VIII, \nSubpart B, section 403(1), new subsection “r.” \n \nRevise Tariff, Part VIII to explain \nthat these above requirements \napply to “all” Interconnection \nCustomers \nrequesting \nto \ninterconnect generating facilities to \nserve Co-Located Load.  (Order to \nShow Cause at P 189) \nPJM complies by making revisions in two places:  \n(1) Part III (General), and (2) Part VIII, Subpart B, \nsection 403(1), new subsection “r.” \nRevise Tariff, Part VIII to specify \nany operational procedures or data \nexchange requirements that PJM \ndeems necessary for Co-Location \nArrangements.  (Order to Show \nCause at P 188) \nPJM complies by adding a new schedule in the pro \nforma GIA (Schedule O), in the form of a \nplaceholder for such information as the case may \nrequire.   \n \nThe remainder of Schedule O is discussed in the \nInitial Brief because it relates to specific non-rate \nterms and conditions of service for Co-Located \nLoad arrangements. \nRevise pro forma GIA to reflect \nabove requirement to specify an \nEligible Customer that will take \ntransmission service on behalf of \nthe Co-Located Load.  (Order to \nShow Cause at P 190) \nPJM complies by proposing revisions to the pro \nforma GIA, Schedule O. \nRevise \nTariff \nto \nestablish \na \ntransition mechanism for existing \ncustomers who wish to add Co-\nLocated Load.  (Order to Show \nCause at P 191)91 \nPJM complies by including the transition \nmechanism in three places (1) Part I (definition of \n“Co-Located Generating Facility”); (2) Part III \n(General), (3) Part VIII, Subpart A, Section 400, \nDefinition \nC’s \ndefinition \nof \n“Co-Located \n \n91 Order to Show Cause at P 191 (“Third, we direct PJM to submit, within 60 days of the date of issuance of \nthis order, a compliance filing to add a new provision to Part I, Common Service Provisions, of the Tariff \nthat requires Interconnection Customers with ISAs or GIAs executed, or requested to be filed unexecuted, \nprior to the effective date of the revised generation interconnection procedures and pro forma GIA directed \nin this order that wish to add Co-Located Load or are currently serving Co-Located Load to publicly notify \nPJM of that addition and identify the Eligible Customer that will take transmission service on behalf of that \nCo-Located Load.  As discussed further below, that Eligible Customer must abide by the terms of the Tariff, \nincluding terms regarding transmission service.”)."},{"page":30,"startToken":9171,"endToken":9416,"text":"Generating \nFacility”.92 \n \nBecause \nPJM \nis \naugmenting the Co-Located Generating Facility \ndefinition previously submitted in the January 20 \nCompliance Filing, for sake of clarity, PJM is \nsubmitting its proposed definition in full as part of \nthe February 23 Compliance Filing. \n  \nAlthough the Order to Show Cause suggested that \nthese changes would be in Part I (Common Service \nProvisions) and Attachment O,93 Appendix 2, PJM \nrespectfully offers that placement in Part III and \nPart VIII (in addition to Part I Definitions) is \nsuperior to or consistent with the Commission’s \ndirective because it promotes tariff readability and \nusability.  In particular, Attachment O is for \nInterconnection Service Agreements under Part VI \nof the Tariff, and since PJM’s Transition Date, \nPJM has not issued new Interconnection Services \nAgreements.  \n \n \n92 In all such places, the new transition mechanism language reads: “Any Generation Project Developer with \nan effective Service Agreement that plans to use a Generating Facility to serve Co-Located Load must provide \nPJM and the Transmission Owner with advance written notice to begin the Necessary Studies process provided \nin Tariff, Part VIII, Subpart A, section 401(H)(3)(b).  If such a Generation Project Developer has an effective \nInterconnection Service Agreement pursuant to Tariff, Part VI or a Generation Interconnection Agreement \npursuant to Tariff, Part VII, such agreement must be superseded by a Generation Interconnection Agreement \npursuant to Tariff, Part VIII and the pro forma GIA in Part IX, Subpart B.” \n93 Order to Show Cause at P 191."},{"page":31,"startToken":9416,"endToken":9684,"text":"Additionally, although PJM filed Tariff revisions on January 20, 2026 to include a \ndefinition of Co-Located Load in Parts VII and VIII of the Tariff, with this filing PJM is \nalso adding that same definition to Part I of the Tariff.94  Adding this proposed definition \nto Part I will allow more streamlined use of this term for Tariff, Part III and new Tariff, \nPart XI.   \n“Co-Located Load” shall mean a configuration that refers to \nend-use customer load that is physically connected to the \nfacilities of an existing or planned Generating Facility on the \nProject Developer’s side of the Point of Change in \nOwnership to the Transmission Provider’s Transmission \nSystem. \n \n \nPJM is also including a definition of Co-Located Generating Facility (as augmented \nby the transition language referenced in the chart above) to allow more streamlined use of \nthis term in Tariff Parts III, VIII, and new Part XI: \n“Co-Located Generating Facility” shall mean an existing or \nplanned Generating Facility that is physically connected to a \nCo-Located Load. \nThe modest change in the Co-Located Load definition from what is reflected in the \nOrder to Show Cause by using “Point of Change in Ownership” is consistent with or \nsuperior to the Order’s use of the term “Point of Interconnection” for a number of reasons:   \nclarity for the interconnection parties, ease of administration, and the realization of \nefficiencies for parties at the Regional Transmission Organization (“RTO”) level and \nbefore the Commission in the form of reduced litigation potential and costs (both in the \nform of alternative dispute resolution procedures and formal complaint and petition for \n \n94 See Attachment A and B."},{"page":32,"startToken":9684,"endToken":9928,"text":"declaratory order litigation).  The Commission should accept PJM’s modest clarifying \nrevision to the definition.95   \n“Point of change in ownership” establishes the legal and financial boundary where, \nas a general matter, ownership responsibility, maintenance, and liability change between \nthe utility and developer.  That point is clearly and plainly memorialized today (and long \nhas been) in both existing Interconnection Service Agreements and the newer Generator \nInterconnection Agreements.  Interconnection facilities owned by the developer are \nidentified and distinguished from interconnection facilities owned by the utility in the \nparties’ existing interconnection agreements.  Which interconnection party owns what \nfacilities is an essential component of an interconnection agreement and promotes clarity \nabout roles, responsibilities, and ownership.  Indeed, PJM’s proposed reforms to the \nNecessary Study Agreement and Generator Interconnection Agreement being filed in \ncompliance with the Order to Show Cause leverage this term because to know where a \nproposed Co-Located Load is “physically connected to the facilities of an existing or \nplanned Generating Facility,” the developer must identify the specific “Project Developer \nInterconnection Facilities” to which such load will be connected. \nTo be sure, “point of interconnection” is also a long-used and important term.  \nWhile Point of Change in Ownership describes where a developer’s portion of the \nInterconnection Facilities connect to the Transmission Owner’s portion of the \nInterconnection Facilities, Point of Interconnection is a technical and physical term about \n“where” those Interconnection Facilities connect to the PJM Transmission System.  As \n \n95 Proposed Tariff Revisions, Part I, Definition of Co-Located Load."},{"page":33,"startToken":9928,"endToken":10197,"text":"such, using the term “Point of Change in Ownership” provides greater clarity regarding the \nlocation of Co-Located Load, compared to “Point of Interconnection.”   \nThe helpful discussion of this issue in Docket No. ER26-1088 is corroborative of \nthese points about the consistency with or superiority of PJM’s modest revisions to the \ndefinition of Co-Located Load by using the more precise “Point of Change in Ownership.”  \nThese concerns have benefited from discussion and further consideration, and PJM \ncontinues to support and files again here the modestly modified Co-Located Load \ndefinition also filed on January 20, 2026 for at least the following reasons.   \nFirst, PJM has been focused on developing in consultation with stakeholders a \ncompliance filing that can be efficiently implemented across the RTO and that is reflective \nof considerations of import to the Commission and to all affected stakeholders.  Because \nof the inherent clarity in the term, use of Point of Change in Ownership appears poised to \nreduce the need for unique, one-off Co-Located Load filings of the sort that the \nCommission has previously rejected96 in favor of rules of generic applicability within \nPJM’s Tariff.   \nSecond, the Commission has broad authority to fashion a remedy under Section \n206 of the Federal Power Act in a proceeding such as this and can accept PJM’s proposed \nmodification on compliance.  Indeed, one stakeholder’s conditional protest in Docket No. \nER26-1088 offers another alternative for the Commission to consider in reliance on this \nCommission authority.   \nThird, using the term Point of Change in Ownership is consistent with the parties’ \nexisting PJM Service Agreements and affords greater certainty to all interconnection \n \n96 See Docket No. ER24-2172."},{"page":34,"startToken":10197,"endToken":10486,"text":"parties and reduces issues about what a “Point of Interconnection” is or is not that are likely \nto be litigated in RTO Alternative Dispute Resolution processes or before the Commission \nin formal regulatory litigation.  Parties today know what interconnection facilities they own \nand can plan the connection of Co-Located Load to such facilities accordingly.  The Docket \nNo. ER26-1088 conditional protest does not appear inconsistent with recognizing the \nprinciple that Co-Located Loads should only interconnect to a Project Developer’s portion \nof the Interconnection Facilities.   \nAs previously detailed in PJM’s January 20 compliance filing,97 which was about \ncertain clarifications applicable only to Project Developers/Interconnection Customers \nseeking to serve Co-Located Load with new Generating Facilities (as opposed to existing \nGenerating Facilities), PJM proposed a definition that uses the term “Point of Change in \nOwnership” rather than “Point of Interconnection” to comport with the use of this term in \nPJM’s new Generation Interconnection Process (“GIP”) set forth in Tariff, Parts VII and \nVIII.  This use of terminology promotes alignment with PJM’s generator interconnection \nreform efforts, and promotes greater clarity for interconnection parties about the facilities \nto which Co-Located Load can attach.   \nUnder PJM’s GIP, the Point of Change in Ownership represents the point where \nthe change in ownership over the Interconnection Facilities occurs.  The Project Developer \nInterconnection Facilities are the segment of the Interconnection Facilities between a \nGenerating Facility and the Point of Change in Ownership, and include “the facilities and \nequipment owned and/or controlled, operated and maintained by the Project Developer on \nProject Developer’s side of the Point of Changes in Ownership, including any \n \n97 PJM Interconnection, L.L.C., et al., PJM’s Compliance Filing to the Order to Show Cause, Docket No. \nEL25-49-000, et al. (Jan. 20, 2026)."},{"page":35,"startToken":10486,"endToken":10838,"text":"modifications, additions, or upgrades made to such facilities and equipment, that are \nnecessary to physically and electrically interconnect the Generating Facility.”     As set \nforth in this filing, an Existing Interconnection Customer seeking to develop a Co-Located \nLoad configuration would be required to enter a superseding Generation Interconnection \nAgreement to reflect the results of the necessary studies, including the planned \nmodifications, additions, or upgrades to the Project Developer Interconnection Facilities, \nand identification of the Point of Change in Ownership.  The proposed changes comply \nwith the Commission’s directive that PJM use the necessary studies process to evaluate the \nProject Developer’s planned modifications to its facilities, including changes to its \nInterconnection Facilities, in order to incorporate a Co-Located Load configuration.98 \nIV. \nREQUESTED EFFECTIVE DATE FOR TARIFF REVISIONS  \nBecause the timing of PJM’s implementation date will depend in part on the \nCommission’s issuance of an order or opinion on these Tariff revisions, as well as on the \nnon-rate terms and conditions proposed in PJM’s Initial Brief, PJM’s effective date for the \nrevisions proposed herein is uncertain.   \nGiven this uncertainty, PJM has entered a placeholder effective date of 12/31/9998 \nfor the tariff records associated with this proposal.  Once the Commission issues an order \nor opinion on this filing, and the non-rate terms and conditions subject to the paper hearing, \n \n98 Order to Show Cause at P 227 (“We disagree with parties such as PIOs who claim that the necessary study \nprocess is inappropriate for generation interconnection modification to serve Co-Located Load.”); id. (“To \nthe extent that PJM seeks to enhance the necessary study process, including as it gains experience evaluating \nrequests from Interconnection Customers to modify their interconnection to serve Co-Located Load, PJM \nmay submit such enhancements in an FPA section 205 filing.”); id. at P 225 ( “Based on our finding above \nthat the PJM Tariff is unjust and unreasonable because it lacks sufficient clarity and consistency with respect \nto the rules for Co-Location Arrangements, we direct PJM to revise its Tariff to provide sufficient clarity \nregarding the responsibilities of existing Interconnection Customers seeking to serve Co-Located Load using \ntheir generating facilities.”) (emphasis added)."},{"page":36,"startToken":10838,"endToken":10966,"text":"and PJM’s ability to implement the proposal becomes clearer, PJM will submit a clean-up \nfiling to enter the actual effective date. \nAs noted earlier, PJM anticipates needing to make subsequent conforming clean-\nup filings to the Tariff, Operating Agreement, and the RAA in regards to the compliance \nfilings being submitted in response to the Order to Show Cause.  Based on continued \nstakeholder engagement and in the Commission’s active dockets, PJM may also seek leave \nto submit additional compliance filings to, among other things, streamline Commission \nresolution of issues and enhance Tariff clarity.99 \nV. \nDOCUMENTS ENCLOSED \n \nIn addition to this transmittal letter, PJM encloses the following: \n1. \nAttachment A: \nTariff Revisions (Clean); and \n2. \nAttachment B: \nTariff Revisions (Redline). \n \n \n99 See also PJM’s Initial Brief at Part V."},{"page":37,"startToken":10966,"endToken":11109,"text":"VI. \nCORRESPONDENCE AND COMMUNICATIONS \n \nCorrespondence and communications with respect to this filing should be sent to, \nand PJM requests the Secretary to include on the official service list, the following:100 \n \nCraig Glazer \nVice President – Federal Government Policy \nPJM Interconnection, L.L.C. \n1200 G Street, N.W., Suite 600 \nWashington, D.C. 20005 \n(202) 423-4743 \nCraig.Glazer@pjm.com \n \n \n \nMark J. Stanisz \nAssociate General Counsel \nThomas DeVita \nAssociate General Counsel \nChenchao Lu \nAssociate General Counsel \n2750 Monroe Blvd, \nAudubon, PA 19403 \n(610) 666-8800 \nMark.Stanisz@pjm.com  \nThomas.Devita@pjm.com  \nChenchao.Lu@pjm.com  \n \n \n \n \n \n \n \n \n \n100 To the extent necessary, PJM requests waiver of Rule 203(b)(3) of the Commission’s Rules of Practice \nand Procedure, 18 C.F.R. § 385.203(b)(3), to permit all of the persons listed to be placed on the official \nservice list for this proceeding."},{"page":38,"startToken":11109,"endToken":11271,"text":"VII. \nSERVICE \n \nPJM has served a copy of this filing on all PJM Members and on the affected state \nutility regulatory commissions in the PJM Region by posting this filing electronically.  In \naccordance with the Commission’s regulations,101 \n \nPJM will post a copy of this filing to \nthe FERC filings section on its internet site, https://pjm.com/library/filing-order, and will \nsend an email on the same date as this filing to all PJM Members and all state utility \nregulatory commissions in the PJM Region,102 alerting them that this filing has been made \nby PJM and is available by following such link.  If the document is not immediately \navailable by using the referenced link, the document will be available through the \nreferenced link within 24 hours of the filing. \n \n101 See 18 C.F.R. §§ 35.2(e) & 385.2010(f)(3). \n102 PJM already maintains, updates, and regularly uses email lists for all PJM Members and affected state \ncommissions."},{"page":39,"startToken":11271,"endToken":11373,"text":"VIII. CONCLUSION \nPJM respectfully requests that the Commission accept the proposed revisions in \naccordance with the requirements of the Order to Show Cause. \nRespectfully submitted, \n/s/   Mark J. Stanisz \n \nCraig Glazer \nVice President – Federal \nGovernment Policy \nPJM Interconnection, L.L.C. \n1200 G Street, NW, Suite 600 \nWashington, DC  20005 \n(202) 423-4743 \ncraig.glazer@pjm.com  \n \n \n \nMark J. Stanisz \nAssociate General Counsel \nThomas DeVita \nAssociate General Counsel \nChenchao Lu \nAssociate General Counsel \n2750 Monroe Blvd, \nAudubon, PA 19403 \n(610) 666-8800 \nmark.stanisz@pjm.com  \nthomas.devita@pjm.com  \nchenchao.lu@pjm.com  \n \n \n \n \n \n \n \nCounsel for PJM Interconnection, L.L.C. \nFebruary 23, 2026"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":2,"endAt":664,"startToken":0,"endToken":427},{"p":2,"at":664,"title":"I. INTRODUCTION AND BACKGROUND","method":"printed heading","endPage":2,"endAt":1235,"startToken":427,"endToken":509},{"p":2,"at":1235,"title":"A. Commission Order","method":"printed heading","endPage":3,"endAt":225,"startToken":509,"endToken":622},{"p":3,"at":225,"title":"B. Stakeholder Engagement","method":"printed heading","endPage":4,"endAt":93,"startToken":622,"endToken":915},{"p":4,"at":93,"title":"III. DESCRIPTION OF PROPOSED TARIFF REVISIONS","method":"printed heading","endPage":4,"endAt":141,"startToken":915,"endToken":921},{"p":4,"at":141,"title":"A. Revisions to Behind The Meter Generation (“BTMG”) Rules","method":"printed heading","endPage":18,"endAt":532,"startToken":921,"endToken":5413},{"p":18,"at":532,"title":"B. Transmission Services for Co-Located Load","method":"printed heading","endPage":21,"endAt":1046,"startToken":5413,"endToken":6364},{"p":21,"at":1046,"title":"Attachment F-4. PJM is filing a “shell” of Attachment F-4, to show that the service","method":"printed heading","endPage":21,"endAt":1215,"startToken":6364,"endToken":6394},{"p":21,"at":1215,"title":"Attachment F-4 is discussed in its Initial Brief.66","method":"printed heading","endPage":24,"endAt":1096,"startToken":6394,"endToken":7177},{"p":24,"at":1096,"title":"C. Necessary Studies and Necessary Studies Agreement","method":"printed heading","endPage":28,"endAt":722,"startToken":7177,"endToken":8540},{"p":28,"at":722,"title":"D. Other Tariff Revisions (Generation Interconnection Procedures, pro","method":"printed heading","endPage":34,"endAt":1116,"startToken":8540,"endToken":10357},{"p":34,"at":1116,"title":"VIII. This use of terminology promotes alignment with PJM’s generator interconnection","method":"printed heading","endPage":35,"endAt":886,"startToken":10357,"endToken":10604},{"p":35,"at":886,"title":"IV. REQUESTED EFFECTIVE DATE FOR TARIFF REVISIONS","method":"printed heading","endPage":36,"endAt":613,"startToken":10604,"endToken":10931},{"p":36,"at":613,"title":"V. DOCUMENTS ENCLOSED","method":"printed heading","endPage":36,"endAt":712,"startToken":10931,"endToken":10945},{"p":36,"at":712,"title":"Attachment A:","method":"printed heading","endPage":36,"endAt":762,"startToken":10945,"endToken":10952},{"p":36,"at":762,"title":"Attachment B:","method":"printed heading","endPage":37,"endAt":0,"startToken":10952,"endToken":10966},{"p":37,"at":0,"title":"VI. CORRESPONDENCE AND COMMUNICATIONS","method":"printed heading","endPage":38,"endAt":0,"startToken":10966,"endToken":11109},{"p":38,"at":0,"title":"VII. SERVICE","method":"printed heading","endPage":39,"endAt":0,"startToken":11109,"endToken":11271},{"p":39,"at":0,"title":"VIII. CONCLUSION","method":"printed heading","endPage":39,"endAt":717,"startToken":11271,"endToken":11373}]}