{"document":{"slug":"rec-20260223-5189-5","title":"Att. D - Horger Affidavit","issued":"2026-02-23","accession":"20260223-5189","docket":"EL25-49-000","group":"PJM co-location compliance","filer":"PJM Interconnection, L.L.C.","kind":"attachment","file":"sources/filings/text/20260223-5189_005.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260223-5189","tier":"record","parent":"rec-20260223-5189","sha256":"ad4bf4d0ce7c26fb7ac688b18593257215eb7a6e3fb83323753144a0455bd16c","pages":8,"tokens":2129,"emptyPages":[],"textThemes":["colo","registry","study"]},"pages":[{"page":1,"startToken":0,"endToken":11,"text":"Attachment D \n \n \n \n \n \n \n \nAffidavit of Timothy Horger, \nSenior Director, Forward Market Operations"},{"page":2,"startToken":11,"endToken":192,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \nPJM Interconnection, L.L.C. \nPJM Interconnection, L.L.C. \nAllegheny Electric Cooperative, Inc. \nAmerican Transmission Systems, Incorporated \nAtlantic City Electric Company \nBaltimore Gas and Electric Company \nDelmarva Power & Light Company \nDuke Energy Ohio, Inc. \nDuke Energy Kentucky, Inc. \nEast Kentucky Power Cooperative, Inc. \nEssential Power Rock Springs, LLC \nHudson Transmission Partners, LLC \nJersey Central Power & Light Company \nMid-Atlantic Interstate Transmission, LLC \nNeptune Regional Transmission System, LLC \nOld Dominion Electric Cooperative \nPECO Energy Company \nPPL Electric Utilities Corporation \nPotomac Electric Power Company \nPublic Service Electric and Gas Company \nRockland Electric Company \nTrans-Allegheny Interstate Line Company \nTransource West Virginia, LLC \nUGI Utilities, Inc. \nMonongahela Power Company \nThe Potomac Edison Company \nCommonwealth Edison Company \nCommonwealth Edison Company of Indiana, \nInc. \nThe Dayton Power and Light Company  \nAEP Appalachian Transmission Company, Inc. \nAEP Indiana Michigan Transmission Company, \nInc. AEP Kentucky Transmission Company, \nInc. \nAEP Ohio Transmission Company, Inc. \nAEP West Virginia Transmission Company, \nInc. Appalachian Power Company \nIndiana Michigan Power Company \nKentucky Power Company \nKingsport Power Company \nOhio Power Company \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n \n              Docket Nos. EL25-49-000 \n                                   EL25-49-001"},{"page":3,"startToken":192,"endToken":458,"text":"2 \nWheeling Power Company \nDuquesne Light Company \nVirginia Electric and Power Company \nLinden VFT, LLC \nCity of Cleveland, Department of Public \nUtilities, Division of Cleveland Public Power \nCity of Hamilton, OH \nSouthern Maryland Electric Cooperative, Inc. \nOhio Valley Electric Corporation \nAMP Transmission, LLC \nSilver Run Electric, LLC \nNextEra Energy Transmission MidAtlantic \nIndiana, Inc. \nWabash Valley Power Association, Inc. \nKeystone Appalachian Transmission Company \nLarge Loads Co-Located at Generating \nFacilities  \nConstellation Energy Generation, LLC \nv.  \nPJM Interconnection, L.L.C. \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n \n \n \n \n \n \n \n \n \n \n \n \n \n \n \n \n                                  AD24-11-000 \n \n \n                                   EL25-20-000 \n                                 (Consolidated) \n                                                    \n \nAFFIDAVIT OF TIMOTHY HORGER,   \nON BEHALF OF PJM INTERCONNECTION, L.L.C. \n \n1. \nMy name is Timothy Horger.  I am the Senior Director of Forward Market Operations for \nPJM Interconnection, L.L.C. (“PJM”).  My business address is 2750 Monroe Boulevard, \nAudubon, Pennsylvania 19403.  I am submitting this affidavit in support of PJM’s proposed \nrevisions to the PJM Open Access Transmission Tariff (“Tariff”) to comply with the \nFederal Energy Regulatory Commission’s (“Commission” or “FERC”) directives in its \nDecember 18, 2025 order1 to establish three new transmission services for Eligible \nCustomers seeking to take transmission service on behalf of Co-Located Load.     \n \n2. \nSpecifically, in this affidavit, I provide support for an effective date of June 1, 2029, for \nthe Tariff revisions relating to the three new transmission services for Eligible Customers \nseeking to take transmission service on behalf of Co-Located Load. \nI. \nQUALIFICATIONS  \n3. \nI joined PJM in 2002.  In my current role, I oversee PJM’s Financial Transmission Rights, \nCapacity, and Demand Side Markets, including the design, development, and execution of \n \n1 PJM Interconnection, L.L.C., 193 FERC ¶ 61,217 (2025) (“December 18, 2025 Order”)."},{"page":4,"startToken":458,"endToken":922,"text":"3 \nthose markets, the facilitation of PJM stakeholder initiatives related to those markets, and \nthe professional development of PJM Staff who work in the departments administering \nthose markets.  I am also responsible for overseeing all activities associated with the Market \nEfficiency Economic Planning process at PJM.  In addition, I am responsible for efforts \nassociated with Strategic Market initiatives. \n \n4. \nPrior to my current position, I served as Director of Market Operations and also held \nmanager positions in the Interregional Market Operations and Market Simulation groups.  \nPrior to my employment at PJM, I worked as a Power Systems and Control Engineer at \nLaser Technology, Inc. \n \n5. \nI hold a Bachelor of Science degree in Electrical Engineering from Drexel University, and \na Masters degree in Systems Engineering from Penn State Great Valley School of Graduate \nProfessional Studies. \n \nII. \nPJM’S PROPOSED EFFECTIVE DATE OF JUNE 1, 2029, IS APPROPRIATE \nFOR IMPLEMENTATION OF THE THREE NEW TRANSMISSIONS SERVICES. \n6. \nThe forward nature of PJM’s capacity market, the Reliability Pricing Model (“RPM”), \ndirectly informs PJM’s proposed effective date of June 1, 2029, for the three new \ntransmission services described in the December 18, 2025 Order.   \n \n7. \nPJM’s RPM auctions procure capacity for future Delivery Years based on expected \ndemand for that given Delivery Year.  The expected demand is, in turn, based on the PJM \nLoad Forecast for that Delivery Year.  It is important that the PJM Load Forecast includes \nall load expecting to be served for the relevant RPM Auction Delivery Year.  The three \nnew transmission services for Eligible Customers seeking to take transmission service on \nbehalf of a Co-Located Load will significantly impact the PJM Load Forecast and expected \ndemand, which will, in turn, have significant implications for the RPM.  \n \n8. \nThe amount of capacity PJM’s RPM procures has significant impacts on both physical and \nfinancial expectations.  For example, eligible capacity must demonstrate that it can be \nphysically “deliverable” to the PJM system before the RPM Auction is conducted.  \nAdditionally, in times when supply is tight and demand is growing, an increase in the \namount of demand can significantly impact the auction clearing price.  \n \n9. \nIn PJM, one of the ways in which deliverability is demonstrated is through Capacity \nInterconnection Rights (“CIRs”) that are verified for each Capacity Resource.  This \ndeliverability concept ensures that any capacity cleared in an RPM auction is reliable and \naccountable.  Under PJM’s Capacity Performance construct, each Capacity Resource that \nclears an RPM auction is (except in very limited circumstances) required to be available, \nand is subject to severe penalties if not available.  \n \n10. \nIn light of the interaction between the RPM and the impact on expected demand that \nEligible Customers taking the three new transmissions services on behalf of Co-Located \nLoad will have, PJM has proposed an effective date of June 1, 2029."},{"page":5,"startToken":922,"endToken":1423,"text":"4 \n \n11. \nThe RPM is premised primarily on a three-year forward Base Residual Auction (“BRA”), \nand while it is currently operating under a compressed auction schedule, PJM has been on \ntrack to return to a normal three-year forward auction for its capacity market by May 2027 \n(for the 2030/2031 Delivery Year).  The BRA for the 2027/2028 Delivery Year took place \nin December 2025.   \n \n12. \nThe next BRA is currently scheduled for June 30, 2026, and will be conducted for the \n2028/2029 Delivery Year beginning June 1, 2028.  Importantly, as of today, the PJM Load \nForecast for the 2028/2029 Delivery Year BRA is already determined, and eligible capacity \nhas already been determined for the 2028/2029 Delivery Year BRA.   \n \n13. \nThus, it is no longer possible to update the PJM Load Forecast, update the RPM auction \ninput parameters (planning parameters), and implement necessary changes before the \n2028/2029 RPM BRA is conducted, even if the Commission were to theoretically approve \nthe proposed changes today.  Accordingly, any new load or Capacity Resource coming \nonline or, for example, existing generation delisting of CIRs to allow a Capacity Resource \nto leave the market and dedicate capacity to serving a Co-Located Load affected by the \nproposed changes associated with this filing would not be accounted for in the RPM \nAuction planning parameters or the PJM Load Forecast for the 2028/2029 Delivery Year \nBRA.  \n \n14. \nThe next available BRA that can include the updated demand and potential new or removed \ncapacity (including accounting for any change in CIRs) is the BRA for the 2029/2030 \nDelivery Year starting June 1, 2029.  The 2029/2030 Delivery Year BRA is scheduled to \ntake place in December 2026, and the expected demand and eligible capacity for the \n2029/2030 Delivery Year have not yet been determined.  Thus, because this would be the \nfirst BRA in which the effects of these new transmission services could be considered \n(including procuring necessary capacity for firm transmission services), PJM is proposing \na June 1, 2029, implementation date for the three new transmission services. \n \n15. \nIt is unlikely that generation associated with these three new transmission service products \nwould be included in the intervening, incremental RPM auctions.  Incremental Auctions \nare conducted to allow for replacement resource procurement, along with increases and \ndecreases in resource commitments due to reliability requirement adjustments.  These \nadjustments are typically small. \n \n16. \nSecond, implementing the three new transmission services will necessitate modifications \nto the PJM core Markets and Operations systems, including modifying the Intermediate \nand Real-Time Security Constrained Economic Dispatch (“IT SCED” and “RT SCED”), \nDay-Ahead Market software, and PJM dispatch tools.  Two of the new transmission service \nproducts, specifically Interim NITS and Non-Firm Contract Demand Transmission \nService, will be among the first to be curtailed under certain conditions.  Curtailment can \naffect prices and dispatch instructions, for which automation will be necessary to avoid \nnon-optimal, untimely, and inefficient outcomes.  Development and implementation of \nchanges to these core systems is dependent on design, vendor availability, costs, and"},{"page":6,"startToken":1423,"endToken":1773,"text":"5 \nmanaging competing priorities that include other Commission-directed initiatives.  Given \nthe significant uncertainty surrounding these novel services, PJM cannot initiate the \nnecessary work (including software changes) until the Commission’s final order in the \npaper hearing is issued in this docket, and the specific rates, terms, and conditions of these \nnew transmission services are correspondingly finalized.  \n \n17. \nFinally, it is unlikely that Eligible Customers and associated generation will be online and \ntaking service under any of the new transmission services before June 1, 2029, as the \nprocess of getting through the interconnection queue, being constructed, and becoming \noperational will likely be more than three years, particularly in light of current supply chain \nissues, Transmission Owner and PJM Interconnection queue requirements, and RPM \nauction timelines.2  There is a known challenge to procure equipment, such as turbines,3 \nand it is not currently expected that a generator could be physically built in less than three \nyears.4  The earliest expected Delivery Year a new generator can participate in an RPM \nBRA or an existing capacity resource can delist, which includes required interconnection \nmodified studies, is for the 2029/2030 Delivery Year.   \n \n18. \nThis concludes my Affidavit. \n \n2 Notably, however, as the Commission recently reiterated, for purposes of the RPM, “Capacity prices are intended to \nsend longer-term investment signals to which developers respond over time[]” and “delays in the interconnection \nqueue, compressed auction schedules, and supply chain issues” do not render RPM auction results unjust and \nunreasonable.  PJM Interconnection, L.L.C., 194 FERC ¶ 61,049, at P 50 (2025) (citing PJM Interconnection, L.L.C., \n126 FERC ¶ 61,275, at P 150 (2009) (“RPM was designed to provide long-term forward price signals . . . .”)). \n3 Jared Anderson, US gas-fired turbine wait times as much as seven years; costs up sharply, S&P Global (May 20, \n2025), https://www.spglobal.com/energy/en/news-research/latest-news/electric-power/052025-us-gas-fired-turbine-\nwait-times-as-much-as-seven-years-costs-up-sharply.  \n4 See, e.g., The Brattle Group, et al., Brattle 2025 CONE Report for PJM, PJM Interconnection, L.L.C. (Apr. 9, 2025), \nhttps://www.pjm.com/-/media/DotCom/committees-groups/committees/mic/2025/20250411-special/item-1-02-\nrevised-cone-report-final.pdf."},{"page":7,"startToken":1773,"endToken":1954,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \nPJM Interconnection, L.L.C. \nPJM Interconnection, L.L.C. \nAllegheny Electric Cooperative, Inc. \nAmerican Transmission Systems, Incorporated \nAtlantic City Electric Company \nBaltimore Gas and Electric Company \nDelmarva Power & Light Company \nDuke Energy Ohio, Inc. \nDuke Energy Kentucky, Inc. \nEast Kentucky Power Cooperative, Inc. \nEssential Power Rock Springs, LLC \nHudson Transmission Partners, LLC \nJersey Central Power & Light Company \nMid-Atlantic Interstate Transmission, LLC \nNeptune Regional Transmission System, LLC \nOld Dominion Electric Cooperative \nPECO Energy Company \nPPL Electric Utilities Corporation \nPotomac Electric Power Company \nPublic Service Electric and Gas Company \nRockland Electric Company \nTrans-Allegheny Interstate Line Company \nTransource West Virginia, LLC \nUGI Utilities, Inc. \nMonongahela Power Company \nThe Potomac Edison Company \nCommonwealth Edison Company \nCommonwealth Edison Company of Indiana, \nInc. \nThe Dayton Power and Light Company  \nAEP Appalachian Transmission Company, Inc. \nAEP Indiana Michigan Transmission Company, \nInc. AEP Kentucky Transmission Company, \nInc. \nAEP Ohio Transmission Company, Inc. \nAEP West Virginia Transmission Company, \nInc. Appalachian Power Company \nIndiana Michigan Power Company \nKentucky Power Company \nKingsport Power Company \nOhio Power Company \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n \n              Docket Nos. EL25-49-000 \n                                   EL25-49-001"},{"page":8,"startToken":1954,"endToken":2129,"text":"Wheeling Power Company \nDuquesne Light Company \nVirginia Electric and Power Company \nLinden VFT, LLC \nCity of Cleveland, Department of Public \nUtilities, Division of Cleveland Public Power \nCity of Hamilton, OH \nSouthern Maryland Electric Cooperative, Inc. \nOhio Valley Electric Corporation \nAMP Transmission, LLC \nSilver Run Electric, LLC \nNextEra Energy Transmission MidAtlantic \nIndiana, Inc. \nWabash Valley Power Association, Inc. \nKeystone Appalachian Transmission Company \nLarge Loads Co-Located at Generating \nFacilities  \nConstellation Energy Generation, LLC \nv.  \nPJM Interconnection, L.L.C. \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n \n \n \n \n \n \n \n \n \n \n \n \n \n \n \n \n                                  AD24-11-000 \n \n \n                                   EL25-20-000 \n                                 (Consolidated) \n                                                    \n \n \nVERIFICATION OF TIMOTHY HORGER \n \nI, Timothy Horger, pursuant to 28 U.S.C. § 1746, state, under penalty of perjury, that I am \nthe Timothy Horger referred to in the foregoing “Affidavit of Timothy Horger on Behalf of PJM \nInterconnection, L.L.C.,” that I have read the same and am familiar with the contents thereof, and \nthat the facts set forth therein are true and correct to the best of my knowledge, information, and \nbelief. \n/s/ Timothy Horger \n \nTimothy Horger \nSenior Director \nForward Market Operatins \nPJM Interconnection, L.L.C. \n \n \nExecuted on: February 23, 2026"}],"sections":[{"p":1,"at":0,"title":"Attachment D","method":"printed heading","endPage":3,"endAt":1850,"startToken":0,"endToken":413},{"p":3,"at":1850,"title":"I. QUALIFICATIONS","method":"printed heading","endPage":4,"endAt":915,"startToken":413,"endToken":593},{"p":4,"at":915,"title":"II. PJM’S PROPOSED EFFECTIVE DATE OF JUNE 1, 2029, IS APPROPRIATE","method":"printed heading","endPage":8,"endAt":1487,"startToken":593,"endToken":2129}]}