{"document":{"slug":"rec-20260223-5189","title":"Initial Brief of PJM Interconnection, L.L.C","issued":"2026-02-23","accession":"20260223-5189","docket":"EL25-49-000","group":"PJM co-location compliance","filer":"PJM Interconnection, L.L.C.","kind":"brief","file":"sources/filings/text/20260223-5189_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260223-5189","tier":"record","sha256":"2c8e7693c6426b51524c08ac058be2656c7502393facb8432564683dd4b5c8d7","pages":89,"tokens":23538,"emptyPages":[],"textThemes":["colo","flex","study","adequacy"]},"pages":[{"page":1,"startToken":0,"endToken":187,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \nPJM Interconnection, L.L.C. \nPJM Interconnection, L.L.C. \nAllegheny Electric Cooperative, Inc. \nAmerican Transmission Systems, Incorporated \nAtlantic City Electric Company \nBaltimore Gas and Electric Company \nDelmarva Power & Light Company \nDuke Energy Ohio, Inc. \nDuke Energy Kentucky, Inc. \nEast Kentucky Power Cooperative, Inc. \nEssential Power Rock Springs, LLC \nHudson Transmission Partners, LLC \nJersey Central Power & Light Company \nMid-Atlantic Interstate Transmission, LLC \nNeptune Regional Transmission System, LLC \nOld Dominion Electric Cooperative \nPECO Energy Company \nPPL Electric Utilities Corporation \nPotomac Electric Power Company \nPublic Service Electric and Gas Company \nRockland Electric Company \nTrans-Allegheny Interstate Line Company \nTransource West Virginia, LLC \nUGI Utilities, Inc. \nMonongahela Power Company \nThe Potomac Edison Company \nCommonwealth Edison Company \nCommonwealth Edison Company of Indiana, \nInc. \nThe Dayton Power and Light Company  \nAEP Appalachian Transmission Company, Inc. \nAEP Indiana Michigan Transmission Company, \nInc. AEP Kentucky Transmission Company, Inc. \nAEP Ohio Transmission Company, Inc. \nAEP West Virginia Transmission Company, Inc. \nAppalachian Power Company \nIndiana Michigan Power Company \nKentucky Power Company \nKingsport Power Company \nOhio Power Company \nWheeling Power Company \nDuquesne Light Company \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n \n              Docket Nos. EL25-49-000\n                                   EL25-49-001"},{"page":2,"startToken":187,"endToken":372,"text":"Virginia Electric and Power Company \nLinden VFT, LLC \nCity of Cleveland, Department of Public \nUtilities, Division of Cleveland Public Power \nCity of Hamilton, OH \nSouthern Maryland Electric Cooperative, Inc. \nOhio Valley Electric Corporation \nAMP Transmission, LLC \nSilver Run Electric, LLC \nNextEra Energy Transmission MidAtlantic \nIndiana, Inc. \nWabash Valley Power Association, Inc. \nKeystone Appalachian Transmission Company \nLarge Loads Co-Located at Generating Facilities \nConstellation Energy Generation, LLC \nv.  \nPJM Interconnection, L.L.C. \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n \n \n \n \n \n \n \n \n \n \n \n \n \n \n                                  AD24-11-000\n \n                                   EL25-20-000\n                                 (Consolidated)\n                                                    \nINITIAL BRIEF OF PJM INTERCONNECTION, L.L.C. \nCraig Glazer \nVice President – Federal \nGovernment Policy \nPJM Interconnection, L.L.C. \n1200 G Street, NW, Suite 600 \nWashington, DC  20005 \n(202) 423-4743 \ncraig.glazer@pjm.com \n \nMark J. Stanisz \nAssociate General Counsel \nThomas DeVita \nAssociate General Counsel \nPJM Interconnection, L.L.C.  \n2750 Monroe Blvd, \nAudubon, PA  19403 \n(610) 666-8800 \nmark.stanisz@pjm.com \nthomas.devita@pjm.com \nWendy Warren \nRyan Collins \nVivian W. Chum \nQingliu (Mary) Yang \nWright & Talisman, P.C. \n1200 G Street, NW, Suite 600 \nWashington, DC  20005 \n(202) 393-1200  \nwarren@wrightlaw.com \ncollins@wrightlaw.com \nchum@wrightlaw.com \nyang@wrightlaw.com \n \n \n \n \n \n \n \nCounsel for PJM Interconnection, L.L.C."},{"page":3,"startToken":372,"endToken":559,"text":"TABLE OF CONTENTS \nI. \nINTRODUCTION AND BACKGROUND ............................................................ 1 \nII. \nRESPONSES TO THE PAPER HEARING QUESTIONS .................................... 5 \nQuestion 1 ............................................................................................................... 5 \nA. \nOverview of Contract Demand Transmission Services in Illustrative \nTariff, Part XI ........................................................................................ 5 \nB. \nFirm Contract Demand Transmission Service in Illustrative Tariff, \nPart XI ................................................................................................. 13 \nC. \nProvision of Contract Demand Transmission Services ....................... 13 \nD. \nNature of Contract Demand Transmission Services ........................... 15 \nE. \nApplication for Contract Demand Transmission Services .................. 17 \nF. \nConditions Precedent and Technical Requirements for Contract \nDemand Transmission Services .......................................................... 18 \nG. \nTermination of Service Agreement for Contract Demand Transmission \nServices ............................................................................................... 20 \nH. \nDesignation of Co-Located Load and Co-Located Generating \nFacility ................................................................................................ 22 \nI. \nRestrictions on Use of Service and Anti-Toggling Provision ............. 23 \nJ. \nInitial Study Procedures for Contract Demand Transmission Service 24 \nK. \nLoad Shedding and Curtailment for Contract Demand Transmission \nServices ............................................................................................... 25 \nL. \nRates and Charges for Firm Contract Demand Transmission Service 26 \nM. \nApplicability of Operating Agreement................................................ 28 \nN. \nPro Forma Contract Demand Transmission Service Agreement........ 28 \nQuestion 2 ............................................................................................................. 30 \nA. \nProvision of Non-Firm Contract Demand Transmission Service ....... 30 \nB. \nNature of Non-Firm Contract Demand Transmission Service ............ 31 \nC. \nInitiating Non-Firm Contract Demand Transmission Service ............ 32"},{"page":4,"startToken":559,"endToken":727,"text":"ii \nD. \nStudy Procedures for Non-Firm Contract Demand Transmission \nService................................................................................................. 33 \nE. \nCurtailment of Non-Firm Contract Demand Transmission Service ... 34 \nF. \nNecessary Control Technologies and Protection Systems to Protect the \nTransmission System by Limiting Energy Withdrawals ..................... 34 \nG. \nRates and Charges for Non-Firm Contract Demand Transmission \nService................................................................................................. 36 \nH. \nPro Forma Contract Demand Transmission Service Agreement........ 37 \nQuestion 3 ............................................................................................................. 38 \nQuestion 4 ............................................................................................................. 39 \nQuestion 5 ............................................................................................................. 40 \nA. \nDisqualification or Pause in Service ................................................... 41 \n1. \nDisqualification after first failure of Eligible Customer to shed \nload or curtail in accordance with established procedures.......41 \n2. \nMisoperation of necessary control technology and protection \nsystem schemes ........................................................................43 \na. \nPause in service after first misoperation of a necessary \ncontrol technology or protection system scheme .........44 \nb. \nDisqualification after second necessary control \ntechnology or protection system scheme \nmisoperation .................................................................45 \nc. \nOption to take NITS following disqualification ..........47 \nB. \nFinancial Penalty for Unreserved Use of the PJM Transmission \nSystem ................................................................................................. 50 \nQuestion 6 ............................................................................................................. 52 \nQuestion 7 ............................................................................................................. 53 \nQuestion 8 ............................................................................................................. 56 \nQuestion 9 ............................................................................................................. 59 \nQuestion 10 ........................................................................................................... 62"},{"page":5,"startToken":727,"endToken":875,"text":"iii \nQuestion 11 ........................................................................................................... 63 \nA. \nNew Curtailment Procedures Applicable to Eligible Customers Taking \nService on Behalf of a Co-Located Load During Emergency \nOperations ........................................................................................... 63 \nB. \nCurtailment of an Eligible Customer Taking Both Firm and Non-Firm \nContract Demand Transmission Service on Behalf of a Co-Located \nLoad During Emergency Operations .................................................. 65 \nIII. \nINTERIM NETWORK INTEGRATION TRANSMISSION SERVICE ............. 66 \nA. \nProvision of Interim NITS and Nature and Scope of Service ............. 67 \nB. \nInitiating Service ................................................................................. 68 \nC. \nDesignation of Co-Located Load ........................................................ 69 \nD. \nStudy Procedures for Interim NITS .................................................... 70 \nE. \nLoad Shedding and Curtailments ........................................................ 71 \nF. \nRates and Charges for Interim NITS .................................................. 73 \nG. \nOperating Agreement .......................................................................... 74 \nH. \nPro Forma Service Agreement Specific to Eligible Customers Serving \nCo-Located Load Via NITS or Interim NITS ..................................... 75 \nIV. \nOTHER ILLUSTRATIVE TARIFF REVISIONS ................................................ 76 \nV. \nRESERVATION OF RIGHTS TO SUPPLEMENT FILING ............................... 78 \nVI. \nIMPLEMENTATION AND EFFECTIVE DATE ................................................. 79 \nVII. \nDOCUMENTS ENCLOSED ................................................................................ 82 \nVIII. \nCONCLUSION ..................................................................................................... 83"},{"page":6,"startToken":875,"endToken":1163,"text":"INITIAL BRIEF OF PJM INTERCONNECTION, L.L.C. \n \nPursuant to paragraph 219 and ordering paragraphs (D) and (E) of the Order on \nShow Cause Proceeding, Directing Compliance Filings, Establishing Paper Hearing, and \nGranting in Part and Denying in Part Complaint issued by the Federal Energy Regulatory \nCommission (“FERC” or “Commission”) on December 18, 2025, in the above-captioned \nproceeding,1 PJM submits this initial brief.  The Commission found that additional record \nevidence was needed to set the appropriate replacement rates, terms, and conditions for \nseveral new transmission services for Eligible Customers2 serving Co-Located Load:  \nInterim Network Integration Transmission Service (“Interim NITS”), Firm Contract \nDemand Transmission Service, and Non-Firm Contract Demand Transmission Service.  \nAccordingly, the Show Cause Order established paper hearing procedures to develop a \nrecord regarding these issues.3  This initial brief responds to the Commission’s Briefing \nQuestions and sets forth non-rate terms and conditions for these new transmission services.   \nI. \nINTRODUCTION AND BACKGROUND \nPJM’s responses to the Briefing Questions and discussion of Interim NITS in \nSection III below focus on the non-rate terms and conditions of the new transmission \nservices for which the Show Cause Order seeks information.  Consistent with the allocation \nof rights between PJM and PJM Transmission Owners under the Consolidated \n \n1 PJM Interconnection, L.L.C., 193 FERC ¶ 61,217 (2025) (“Show Cause Order”); see also PJM \nInterconnection, L.L.C., Notice of Extension of Time, Docket Nos. EL25-49-000, et al., at 3 (Jan. 23, 2026) \n(granting a 7-day extension of the deadline in ordering paragraph (D) of the Show Cause Order for PJM to \nsubmit its initial brief). \n2 Capitalized terms not otherwise defined herein have the meanings set forth in PJM’s Open Access \nTransmission Tariff (“Tariff”). \n3 Show Cause Order at P 219."},{"page":7,"startToken":1163,"endToken":1582,"text":"2 \nTransmission Owners Agreement (“CTOA”),4 PJM expects the PJM Transmission Owners \nto file briefing in the paper hearing record generally addressing the rates for each of these \nnew transmission services.5   \nPJM has also attached the following materials in addition to PJM’s responses to the \nBriefing Questions and discussion of Interim NITS, which PJM will refer to and rely while \nresponding to the Briefing Questions and discussing Interim NITS.   \nFirst, Attachment A to this initial brief provides illustrative Tariff language for a \nnew Tariff, Part XI (among other illustrative language),6 which sets forth the non-rate terms \nand conditions for the new transmission services available to Eligible Customers taking \nservice on behalf of Co-Located Loads.  The language is “illustrative” in the sense that \nPJM is including the language in Attachment A as part of the paper hearing record and is \nnot formally filing it until the Commission rules on the record.  As reflected in PJM’s \nillustrative Tariff language, PJM places priority on the reliability of the transmission grid, \nwhich requires “maintaining an uninterrupted flow of high-voltage electricity, monitoring \n \n4 CTOA Rate Schedule FERC No. 42; see also Atl. City Elec. Co., 190 FERC ¶ 61,109, at P 3 (2025) \n(providing history and authority for the CTOA under Pa.-N.J.-Md. Interconnection, 105 FERC ¶ 61,294 \n(2003) (“Atlantic City Settlement Order”), order on compliance, 108 FERC ¶ 61,033 (2004) by explaining \nthat “[i]n the Atlantic City Settlement Order, the Commission explained that the settlement agreement \nessentially divides filing rights between ‘rate-related filings and terms and conditions-related filings – with \nthe PJM [Transmission Owners] filing the former and PJM the latter’”); Atl. City Elec., 190 FERC ¶ 61,109, \nat P 4 (“[I]ndividual transmission owners do not have a right to file under FPA section 205 to modify ‘terms \nand conditions of the PJM Tariff . . . .’” (footnote omitted)); Atl. City Elec. Co. v. FERC, 295 F.3d 1 (D.C. \nCir. 2002) (explaining that the initial Settlement Agreement between PJM and PJM Transmission Owners \n“established procedures for changes to rate design and other tariff terms for transmission services.  It \npermitted the transmission owners to file changes in transmission service rate design and non-rate terms and \nconditions to the tariff under section 205.”). \n5 However, PJM has rights associated with certain rates and charges, e.g., PJM’s administrative service \ncharges, which are discussed in response to several Briefing Questions below. \n6 Illustrative Language for New Tariff, Part XI; Attachments F-3A and F-4; and Other Illustrative Tariff \nRevisions (Attachment A) (“illustrative Tariff”)."},{"page":8,"startToken":1582,"endToken":1860,"text":"3 \ncongestion, and . . . preventing and, if necessary, addressing outages and emergencies \nwithin the PJM footprint.”7 \nOn compliance with a Commission decision determining the appropriate non-rate \nterms and conditions, PJM will submit a new Tariff, Part XI (in the manner shown in \nAttachment A), and other Tariff revisions necessary to integrate the new transmission \nservices into PJM’s markets and operations, as applicable.  That said, as detailed in this \ninitial brief, the illustrative language in Attachment A sets forth how PJM believes these \nnew transmission services should be requested and studied, and what their terms and \nconditions of service should be.   \nThe illustrative Tariff language setting forth the non-rate terms and conditions for \neach of these new transmission services (Interim NITS and the two Contract Demand \nTransmission Services) are based in large part on PJM’s existing (regional) Network \nIntegration Transmission Service (“NITS”) language from Tariff, Part III.8  By building \nfrom the existing Tariff, Part III for developing these new transmission services, PJM is \noffering terms and conditions that are already familiar to customers and stakeholders, \nfacilitating their implementation.   \nSecond, Attachments B through D consist of affidavits in support of PJM’s filing \nand as referenced in PJM’s responses to the Commission’s paper hearing questions below.  \nIn Attachment B, PJM provides the Affidavit of Dr. Sami Abdulsalam on Behalf of PJM \nInterconnection, L.L.C. (“Abdulsalam Aff.”).  Dr. Abdulsalam is Director of Transmission \n \n7 Wharton Aff. ¶ 12. \n8 References to PJM’s existing NITS refers to Regional NITS, which is for service with deliveries within the \nPJM Region, unless otherwise indicated.  PJM’s Cross-Border NITS generally is not relevant to these new \ntransmission services, as it is for delivery outside of PJM."},{"page":9,"startToken":1860,"endToken":2023,"text":"4 \nPlanning for PJM and testifies on the primacy of NITS for service within the PJM Region, \nthe complexity associated with Non-Firm Contract Demand Transmission Service from an \noperations and planning perspective, and limitations on Non-Firm Contract Demand \nTransmission Service.   \nIn Attachment C, PJM provides the Affidavit of Matthew Wharton, on Behalf of \nPJM Interconnection, L.L.C. (“Wharton Aff.”).  Mr. Wharton testifies as to how PJM \noperationally carries out its key responsibilities as the “air traffic controller” of the PJM \nRegion’s high-voltage electric Transmission System to ensure reliability, manage power \nflow, and handle emergency operations as the region’s North American Electric Reliability \nCorporation (“NERC”)-registered Reliability Coordinator, Balancing Authority, and \nTransmission Operator, as well as the operational complexities associated with RASs. \nIn Attachment D, PJM provides the Affidavit of Timothy Horger, on Behalf of PJM \nInterconnection, L.L.C. (“Horger Aff.”).  Mr. Horger provides support for an effective date \nof June 1, 2029, for Tariff revisions implementing the three new transmission services."},{"page":10,"startToken":2023,"endToken":2295,"text":"5 \nII. \nRESPONSES TO THE PAPER HEARING QUESTIONS \nQuestion 1:  \nWhat are the appropriate rates, terms, and conditions for the new Firm Contract \nDemand transmission service, including whether it would be just and reasonable \nto apply the current zonal firm PTPS charges to this new service and whether it \nwould be just and reasonable and consistent with cost causation to include charges \nfor any of PJM’s administrative services?9 \nResponse to Question 1:  \nBelow, PJM describes the specific non-rate terms and conditions for the new Firm \nContract Demand Transmission Service, but it is important to first understand the \nrelationship between the new Firm Contract Demand Transmission Service and the new \nNon-Firm Contract Demand Transmission Service.  Thus, PJM will first provide an \noverview of the two transmission services and how, together, they will provide an \nalternative to NITS for those Co-Located Loads willing and able to limit energy \nwithdrawals from the Transmission System.  Then, PJM will detail, in response to \nQuestion 1, the non-rate terms and conditions for Firm Contract Demand Transmission \nService, and then detail, in response to Question 2, the non-rate terms and conditions for \nNon-Firm Contract Demand Transmission Service. \nA. \nOverview of Contract Demand Transmission Services in Illustrative \nTariff, Part XI \nThe Show Cause Order requires PJM to develop and implement two new contract \ndemand transmission services, Firm Contract Demand Transmission Service and Non-Firm \nContract Demand Transmission Service.  These new services are to “serve as permanent \nalternatives to existing transmission services, unlike the new interim, non-firm \ntransmission service, . . . . and the new transmission services would not require the \n \n9 For simplicity, internal citations from the Show Cause Order have been omitted."},{"page":11,"startToken":2295,"endToken":2634,"text":"6 \nCo-Located Load to become Network Load.”10  Contract Demand Transmission Services \nare intended to provide options beyond full NITS to Eligible Customers taking service on \nbehalf of Co-Located Loads that are “willing and able to control their withdrawals from \nthe transmission system.”11   \nAs directed by the Show Cause Order, PJM has conceptualized Contract Demand \nTransmission Services based on two key principles:  (1) the services are designed to serve \nloads that are “willing and able to control their withdrawals from the transmission \nsystem;”12 and (2) the services are designed to allow PJM to maintain system reliability.13  \nThe two Contract Demand Transmission Services are designed to work together to provide \nthe opportunity for transmission service to serve the entire gross demand of the Co-Located \nLoad.   \nIn short, for reliability reasons, the portion of the Co-Located Load for which the \nCo-Located Generating Facility will dedicate its output (in whole or in part) may be \ncovered by Non-Firm Contract Demand Transmission Service, but any portion of the gross \ndemand of the Co-Located Load not served by the Co-Located Generating Facility must be \ncovered by Firm Contract Demand Transmission Service.  This approach is necessary to \nmaintain reliability, while allowing these loads to obtain transmission service based on their \n \n10 Show Cause Order at P 206.   \n11 Id. at PP 204, 206. \n12 Show Cause Order at P 204. \n13 See, e.g., id. at PP 201 (“[T]his new interim, non-firm transmission service will facilitate the timely \nprovision of transmission service to Eligible Customers taking transmission service on behalf of Co-Located \nLoads, while preserving reliability for other transmission customers.”), 212 (“We also note that, as discussed \nin the briefing questions below, PJM will determine the technical and engineering requirements of special \nprotection schemes to help address reliability risks associated with unreserved use of the transmission \nsystem.”) & 227 (discussing requirement that would “provide additional clarity and transparency regarding \nthe steps that PJM and Interconnection Customers are taking to maintain transmission system reliability \nbefore an existing generating facility can serve Co-Located Load”)."},{"page":12,"startToken":2634,"endToken":3054,"text":"7 \nwillingness and ability to limit energy withdrawals.  To ensure reliability PJM’s studies of \nthe transmission service requests for the Co-Located Load, and the Co-Located Load’s \nimpact on the Transmission System, must capture the effects of any unscheduled energy \nwithdrawals by the Co-Located Load, even if inadvertent or limited in duration (e.g., unit \ntrip, failure of control technologies or protective schemes) and validate that such events \nwould not jeopardize system reliability.14  In other words, there can be no “unstudied” \nand/or “unknown” portion of the Co-Located Load that is not covered by either Firm \nContract Demand Transmission Service or dedicated generation from the Co-Located \nGenerating Facility (as backed up by Non-Firm Contract Demand Transmission Service).  \nWithout such a requirement, PJM will not have visibility into situations that may jeopardize \ngrid reliability, including load taking service beyond levels for which PJM has properly \nstudied and planned.  This would expose the Transmission System to risk of equipment \ndamage, unintended relay operations, and cascading outages.  \nTo illustrate, assume a Co-Located Load with a gross demand of 900 megawatts \n(“MWs”), and a Co-Located Generating Facility of 500 MWs.  The Co-Located Generating \n \n14 Consistent with Commission directives in Order Nos. 845 and 845-A and language already embedded in \nPJM’s Tariff, PJM’s proposal here uses the term “necessary control technologies and protection systems,” \nwhich may include Remedial Action Schemes (“RASs”).  Reform of Generator Interconnection Procedures \nand Agreements, Order No. 845, 163 FERC ¶ 61,043, at P 396 (2018) (requiring “any interconnection \ncustomer that seeks interconnection service below its generating facility capacity install appropriate \nmonitoring and control technologies at its generating facility”), order on reh’g & clarification, Order \nNo. 845-A, 166 FERC ¶ 61,137, at P 114 (“[I]f the interconnection customer requests interconnection service \nbelow generating capacity, it commits to operate consistent with such a request under section 3.1 of the pro \nforma LGIP, which states that ‘[t]he necessary control technologies and protection systems . . . for exceeding \nthe level of Interconnection Service established in the executed, or requested to be filed unexecuted, LGIA \nshall be established in Appendix C of that executed, or requested to be filed unexecuted, LGIA.’” (alteration \nin original) (footnote omitted)), order on reh’g & clarification, Order No. 845-B, 168 FERC ¶ 61,092 (2019); \nsee also Tariff, Part IV, Subpart A, section 36.1.1A (“The necessary control technologies and protection \nsystems shall be established in Tariff, Attachment O, Schedule K (Requirements for Interconnection Service \nBelow Full Electrical Generating Capability) of the executed, or requested to be filed unexecuted \nInterconnection Service Agreement.”)."},{"page":13,"startToken":3054,"endToken":3350,"text":"8 \nFacility commits to dedicating 400 MWs of its output to the Co-Located Load.15  Here, the \nEligible Customer designated by the Co-Located Generating Facility16 must contract for \nFirm Contract Demand Transmission Service of at least 500 MWs to cover the difference \nbetween the dedicated output of the Co-Located Generating Facility (400 MWs) and the \ngross demand of the Co-Located Load (900 MWs).17  Given the quality of Firm Contract \nDemand Transmission Service, this means that, generally speaking, the gross demand of \nthe Co-Located Load (here, 900 MWs) should be met under most conditions by the portion \nof the Co-Located Generating Facility dedicated to the Co-Located Load (here, 400 MWs) \nplus the Firm Contract Demand Transmission Service the Eligible Customer takes from the \nTransmission System (here, 500 MWs).  This is illustrated by Figure 1 below. \n \n15 The Co-Located Generating Facility would be free to offer the 100 MWs of Installed Capacity into PJM’s \ncapacity market or be an energy-only resource.  However, the portion of Co-Located Generating Facility \ndedicated to the Co-Located Load would be ineligible to participate in PJM’s capacity market.  See PJM \nTransmittal Letter, section II.C (Necessary Studies and Necessary Studies Agreement). \n16 Depending on the status of the Co-Located Generating Facility, the designation of the Eligible Customer \nwill be in its Application or Service Agreements, such as its Generator Interconnection Agreement (“GIA”). \n17 The Eligible Customer is free to contract for greater amounts of Firm Contract Demand Transmission \nService than necessary to cover the portion of the Co-Located Load’s demand not met by the Co-Located \nGenerating Facility.  For example, in the illustration above, the Eligible Customer may choose to contract for \n500 MWs of Firm Contract Demand Transmission service and still dedicate 400 MWs of its Co-Located \nGenerating Facility to its Co-Located Load."},{"page":14,"startToken":3350,"endToken":3522,"text":"9 \nFigure 1:  Illustration of Relationship between Contract Demand Transmission \nServices and portion of Co-Located Generating Facility Dedicated to Co-Located Load \n \nA Co-Located Generating Facility will not always be available (e.g., due to planned \nor unforced outage).  To the extent that the gross demand of a Co-Located Load is not \ncovered by the Eligible Customer’s Firm Contract Demand Transmission Service, the \nEligible Customer must cover the remaining gross demand by applying for Non-Firm \nContract Demand Transmission Service.  In that case, the Non-Firm Contract Demand \nTransmission Service, if PJM determines it is available for the requested period, will act as \na backup to allow the Co-Located Load to meet its full demand, while the portion of the \nCo-Located Generating Facility dedicated to the Co-Located Load is on outage and unable \nto provide energy.    \nDr. Abdulsalam explains that Non-Firm Contract Demand Transmission Service \noffers non-firm withdrawals “on a pre-scheduled/requested basis and are not guaranteed.”18  \nThis is consistent with the Show Cause Order’s finding that the Non-Firm Contract \n \n18 Abdulsalam Aff. ¶ 12."},{"page":15,"startToken":3522,"endToken":3767,"text":"10 \nDemand Transmission Service is intended for “Eligible Customers seeking to use the \ntransmission system on behalf of a Co-Located Load in this more limited manner” by \nseeking a “transmission reservation for a Co-Located Load in advance for the duration of \nan expected outage of the associated generator.”19 \nMore specifically, PJM will offer and manage pre-scheduled Non-Firm Contract \nDemand Transmission Service “‘operationally’ and ensure that permanent monitoring and \naggressive, fast-acting protections are in place if conditions arise that may compromise \nreliable system operations.”20  This approach, as Dr. Abdulsalam explains, “allows for more \nreliable system operation, reduces the number of permanent protection systems on the \nsystem,” such as a RAS, on the PJM Transmission System, and thus “reduc[es] the \nlikelihood of unintended protection system misoperation that could lead to cascading \nevents.”21  \nIn addition, as explained further below, and by Dr. Abdulsalam, from an operations \nand planning perspective, the complexities associated with the provision of Non-Firm \nContract Demand Transmission Service call for relying on such service as a standby \nproduct only “under limited circumstances.”22  For example, an Eligible Customer that \ntypically supplies load “directly from the co-located generator without using the \ntransmission system” may rely on Non-Firm Contract Demand Transmission Service when \nthe “co-located generator is unavailable or operating at a reduced capacity,”23 to enable the \n \n19 Show Cause Order at P 214. \n20 Abdulsalam Aff. ¶ 12. \n21 Abdulsalam Aff. ¶ 12. \n22 Abdulsalam Aff. ¶ 14. \n23 Abdulsalam Aff. ¶ 14 (footnote omitted)."},{"page":16,"startToken":3767,"endToken":4014,"text":"11 \nEligible Customer to substitute energy from the PJM Transmission System for the energy \nprovided by the Co-Located Generating Facility. \nFlexibility is built into PJM’s approach, which allows Eligible Customers to mix \nand match between Firm and Non-Firm Contract Demand Transmission Service when \ntaking service on behalf of Co-Located Load, so long as the combination of the two services \ncovers the entire gross demand of the Co-Located Load.  PJM’s approach also ensures that \nthere is the opportunity to take transmission service even in the event a Co-Located \nGenerating Facility is unable to provide energy consistent with its dedicated quantity.   \nThis approach is compliant with the Show Cause Order’s statement that “Eligible \nCustomers taking transmission service on behalf of Co-Located Loads would . . . be able \nto take a combination of Firm Contract Demand transmission service and Non-Firm \nContract Demand transmission service.”24  Additionally, the Commission explained that \n“the Eligible Customer may combine Firm Contract Demand transmission service with \nNon-Firm Contract Demand transmission service to withdraw, on an as-available basis, \nmore energy than its firm entitlement.”25  Accordingly, PJM is allowing an Eligible \nCustomer taking transmission service on behalf of a Co-Located Load to choose either \nFirm or Non-Firm Contract Demand Transmission Service, or some combination of the \ntwo so long as the Eligible Customer takes service that fully covers the Co-Located Load’s \ntotal energy needs.   \n \n24 Show Cause Order at P 206.  \n25 Show Cause Order at P 208 n.437; illustrative Tariff, Part XI, Subpart B, section 708."},{"page":17,"startToken":4014,"endToken":4299,"text":"12 \nAlso, as discussed in PJM’s Transmittal Letter,26 PJM is filing Tariff revisions \nwhich, as required by the Show Cause Order,27 provide that an Eligible Customer taking \ntransmission service on behalf of a Co-Located Load that is taking Firm and/or Non-Firm \nContract Demand Transmission Service may not also take NITS or Interim NITS on behalf \nof the same Co-Located Load.  Thus, while an Eligible Customer may choose some \ncombination of Firm and Non-Firm Contract Demand Transmission Service, NITS and \nInterim NITS cannot be mixed with either one of the Contract Demand Transmission \nServices.28   \nConsistent with the directives and findings of the Show Cause Order, PJM \ndeveloped non-rate terms and conditions for offering Contract Demand Transmission \nService on firm and non-firm bases.  Attachment A to this initial brief includes an \nillustrative Tariff, Part XI, Subpart B, and sections 708 through 716 detail non-rate terms \nand conditions for the two new Contract Demand Transmission Services.  PJM also \ndeveloped an Attachment F-4 to be the new pro forma Service Agreement for both Firm \nContract Demand Transmission Service and Non-Firm Contract Demand Transmission \nService.  That is, an Eligible Customer taking Firm and Non-Firm Contract Demand \nTransmission Service on behalf of a Co-Located Load will require only a single Service \nAgreement setting for the applicable terms for each service.  Such an approach is \nreasonable, as the two services are generally going to be taken simultaneously to ensure \n \n26 PJM Transmittal Letter at 26-29 (discussing revisions to Part III). \n27 Show Cause Order at PP 189, 193.  \n28 See Show Cause Order at P 206 (Eligible Customer “would also be able to take a combination of Firm \nContract Demand transmission service and Non-Firm Contract Demand transmission service.”)."},{"page":18,"startToken":4299,"endToken":4560,"text":"13 \nthe entire gross demand of the Co-Located Load can be covered by the Transmission \nSystem.29   \nAlthough the “shell” of Attachment F-4 is being filed concurrently as part of PJM’s \ncompliance filing,30 the full illustrative text of Attachment F-4 is in Attachment A to PJM’s \ninitial brief.   \nB. \nFirm Contract Demand Transmission Service in Illustrative Tariff, \nPart XI \nAttachment A describes Firm Contract Demand Transmission Service as the \ntransfer of capacity and energy for an Eligible Customer on behalf of a designated \nCo-Located Load, up to a defined, predetermined MW level of transmission service as \nrequested by the Eligible Customer and confirmed by PJM, using capacity and energy \nprocured by PJM.31   \nPJM’s response to Question 1 below, covers (i) Tariff, Part XI provisions that apply \nto both Firm and Non-Firm Contract Demand Transmission Service; and (ii) Tariff, Part XI \nprovisions that only apply to Firm Contract Demand Transmission Service.  Provisions that \nonly apply to Non-Firm Contract Demand Transmission Service will be discussed further \nin response to Question 2 below. \nC. \nProvision of Contract Demand Transmission Services  \nIn Attachment A, section 708, PJM provides illustrative language detailing the \nscope of Contract Demand Transmission Service on both a Firm and Non-Firm basis.   \n \n29 Of course, to the extent an Eligible Customer takes only one of the two new contract demand transmission \nservices, the portions of the agreement unrelated to the subscribed service will be inapplicable. \n30 See PJM Transmittal Letter, Attachment A (Tariff Revisions (Clean)) and Attachment B (Tariff Revisions \n(Redline)). \n31 Illustrative Tariff, Part XI, Subpart B, section 708."},{"page":19,"startToken":4560,"endToken":4853,"text":"14 \nFirm Contract Demand Transmission Service will be provided to Eligible \nCustomers taking service on behalf of Co-Located Loads pursuant to the applicable terms \nand conditions in the Tariff and the Service Agreement for Contract Demand Transmission \nService, provided in proposed Attachment F-4.32  The Commission instructed PJM to \ndesign its Firm Contract Demand Transmission Service to allow customers to take capacity \nand energy from the Transmission System up to a defined, predetermined MW level.33  The \nCommission stated, however, that while “Firm Contract Demand transmission service will \nhave the same reservation and curtailment priority as existing firm transmission services, \nat the level of contract demand . . . unlike NITS customers, the Eligible Customer taking \nFirm Contract Demand transmission service on behalf of the Co-Located Load is not \npermitted to withdraw energy from the PJM transmission system beyond the contract \ndemand level.”34  For both Contract Demand Transmission Services, Eligible Customers \nmust be willing and able to limit withdrawals of energy from the Transmission System as \nrequired by PJM.35   \nA demonstrated and proven ability to limit withdrawals from the system is crucial \nto the reliability of the PJM system and to prevent Contract Demand Transmission Services \nfrom having an adverse impact on the electric system’s reliability and, per the Show Cause \nOrder, a fundamental characteristic of Contract Demand Transmission Service.36  \n \n32 Illustrative Tariff, Part XI, Subpart B, section 708. \n33 Show Cause Order at P 208; illustrative Tariff, Part XI, Subpart B, section 708. \n34 Show Cause Order at P 208 (footnote omitted).  \n35 Illustrative Tariff, Part XI, Subpart B, section 708.  \n36 Show Cause Order at P 204 (The Commission stated that Eligible Customers seeking Contract Demand \nTransmission Services must be “willing and able to control their withdrawals from the transmission \nsystem.”)."},{"page":20,"startToken":4853,"endToken":5185,"text":"15 \nRelatedly, Co-Located Loads must be separately metered from the Co-Located Generating \nFacility.37  For Firm Contract Demand Transmission Service to properly function, it is \nessential that any associated Non-Firm Contract Demand Transmission Service taken on \nbehalf of the same Co-Located Load has in place necessary control technologies and/or \nprotective systems, which may include RASs, that are approved by PJM and that can \neffectively limit withdrawals from the Transmission System that serve Co-Located \nLoads.38  While the details surrounding such protective technologies and systems are \ndetailed further below in response to Question 5, the need for such associated with the \nprovision of Non-Firm Contract Demand Transmission Service is also discussed in \nresponse to Question 2.   \nIllustrative Tariff, Part XI, Subpart B, section 708 also provides that Eligible \nCustomers must request both Firm and Non-Firm Contract Demand Transmission Service \nthrough their Transmission Provider by filing an Application, detailed further below. \nD. \nNature of Contract Demand Transmission Services \nAs required by the Show Cause Order, Firm Contract Demand Transmission \nService will also have priority over Non-Firm Contract Demand Transmission Service and \nwill have equal priority, at the level of the contract demand, with other firm transmission \nservices, including NITS.39   \n \n37 Show Cause Order at P 206; see illustrative Tariff, Part XI, Subpart B, section 710.4 (“[T]hese technical \nrequirements include, but are not limited to: (i) installation of necessary hardware and software to limit energy \nwithdrawals, including metering equipment . . . .”).  \n38 Illustrative Tariff, Part XI, Subpart B, section 708; see Show Cause Order at P 205 (“[I]n these instances \nwhere the Co-Location Arrangement includes special protection schemes that limit its energy withdrawals, \nwe find that it is a just and reasonable replacement rate to allow an Eligible Customer taking transmission \nservice on behalf of such load to take and be charged for new types of transmission service that are \nalternatives, and not equivalent, to NITS.”).  \n39 Illustrative Tariff, Part XI, Subpart B, section 709.1; Show Cause Order at P 208."},{"page":21,"startToken":5185,"endToken":5459,"text":"16 \nAttachment A, section 709.2 details the scope of service for both Firm and \nNon-Firm Contract Demand Transmission Service.  An Eligible Customer requesting Firm \nContract Demand Transmission Service will receive firm transmission service on behalf of \na Co-Located Load up to its contract demand amount, as detailed in the applicable Service \nAgreement.  An Eligible Customer taking service on behalf of a Co-Located Load must \nrequest Non-Firm Contract Demand Transmission Service equivalent to the MW level of \nthe Co-Located Generating Facility dedicated to serving the Co-Located Load, and an \nEligible Customer with an effective Service Agreement will be eligible to obtain Non-Firm \nContract Demand Transmission Service on a given Operating Day only to the extent the \nportion of the Co-Located Generating Facility dedicated to serving the Co-Located Load \nis on outage.   \nConversely, as discussed above in the overview section, an Eligible Customer \ntaking service on behalf of a Co-Located Load must request Firm Contract Demand \nTransmission Service for no less than the MW level of the gross demand of the Co-Located \nLoad that will not be served by the dedicated Co-Located Generating Facility.  As required \nby the Show Cause Order,40 for any given Co-Located Load, once an Eligible Customer \nhas taken, or is applying for NITS or Interim NITS on behalf of such Co-Located Load, an \nEligible Customer will not be eligible to apply for or take Firm Contract Demand \nTransmission Service or Non-Firm Contract Demand Transmission Service for that same \nCo-Located Load.41  Finally, any material change in the MW level of the gross-demand of \n \n40 Show Cause Order at P 200. \n41 Illustrative Tariff, Part XI, Subpart B, section 709.3."},{"page":22,"startToken":5459,"endToken":5767,"text":"17 \nthe Co-Located Load, or in the output of the Co-Located Generating Facility would require \na new Application.42 \nE. \nApplication for Contract Demand Transmission Services  \nIllustrative section 710 in Attachment A details how an Eligible Customer seeking \ntransmission service on behalf of a Co-Located Load will initiate service requests for Firm \nand Non-Firm Contract Demand Transmission Service.  Any request for Firm and/or \nNon-Firm Contract Demand Transmission Service must comply with the Commission’s \nrequirements for new transmission service requests in 18 C.F.R. § 2.20, plus several data \npoints specific to Contract Demand Transmission Service, including several items listed in \nsection 710.2:   \n• “a description of the supply characteristics of the Co-Located Generating \nFacility . . . , including the generation profile, its Maximum Facility Output, \nthe megawatt level dedicated to serving the Co-Located Load, and other \ntechnical specifications;” \n• “[a] description of the demand characteristics of the Co-Located Load . . . , \nincluding the demand profile and other technical specifications;” and  \n• “[t]he transmission capacity requested for the Delivery Point on the \nTransmission Provider’s Transmission System behind which the Co-\nLocated Load and Co-Located Generating Facility are located.” \nUpon receiving an Application, and the information required in section 710, PJM \nwould evaluate whether the requested level of Firm Contract Demand Transmission \nService and/or Non-Firm Contract Demand Transmission Service can be reliably provided.  \nTo do so, PJM would “coordinate with the affected Transmission Owner(s) to complete \nstudies, including load integration studies, [to obtain] data relevant to the determination of \n \n42 Illustrative Tariff, Part XI, Subpart B, section 709.2(e) (“After an Eligible Customer has submitted an \nApplication for Contract Demand Transmission Service for a given Co-Located Load, any material change \nin the megawatt level of the gross-demand of the Co-Located Load or in the megawatt level of the Co-Located \nGenerating Facility dedicated to the Co-Located Load would require a new Application.”)."},{"page":23,"startToken":5767,"endToken":6051,"text":"18 \nwhether (and to what level)” Firm or Non-Firm Contract Demand Transmission Service \n“can be reliably provided” and “identify any necessary enhancements to the Transmission \nSystem to accommodate the requested level of service.”43  PJM’s Tariff language also \nrecognizes that “[d]uring this study period, Transmission Provider may also perform other \nstudies.”44   \nBased on the studies, PJM, in consultation with the affected PJM Transmission \nOwner(s), will determine the level of Firm Contract Demand Transmission Service or \nNon-Firm Contract Demand Transmission Service that can be reliably provided and inform \nthe Eligible Customer.45 \nF. \nConditions Precedent and Technical Requirements for Contract Demand \nTransmission Services \nPrior to obtaining service, the Eligible Customer must meet several enumerated \nconditions precedent, many of which are ministerial in nature but have significant \nimportance in ensuring that the Eligible Customer can receive its service while preserving \nthe reliability of the Transmission System.   \nSpecifically, among several enumerated conditions precedent, the language would \nrequire the Eligible Customer to comply with the provisions of the “PJM Credit Policy” \nset forth in Tariff, Attachment Q; “certify[y] that it is willing and able to limit energy \nwithdrawals from the Transmission System when requested by [PJM];” “complete[] other \n \n43 Illustrative Tariff, Part XI, Subpart B, section 710.3 (“Descriptions of the Transmission Provider’s and/or \nthe applicable Transmission Owner(s)’ specific methodology for assessing whether Firm Contract Demand \nTransmission Service or Non-Firm Contract Demand Transmission Service, or both can be reliably provided, \nwill be set forth in Tariff, Part XI, Section 712, the PJM Manuals, and set forth in Transmission Owner \nstandards, as applicable.”). \n44 Illustrative Tariff, Part XI, Subpart B, section 710.3. \n45 Illustrative Tariff, Part XI, Subpart B, section 710.3."},{"page":24,"startToken":6051,"endToken":6316,"text":"19 \ncertification requirements provided in the PJM Manuals,” including to be an Electric \nDistributor, as applicable; and “otherwise execute, if necessary, and comply with the PJM \nGoverning Agreements.”46  In addition and crucially, the Eligible Customer must have \nbeen designated to take transmission service on behalf of a Co-Located Load in the relevant \nApplication, Service Agreement, or GIA for the Co-Located Generating Facility, and \nprovide PJM with “an authorization or certification from its Relevant Electric Retail \nRegulatory Authority which affirms that the Eligible Customer is authorized to provide \nenergy to the Co-Located Load.”47 \nIllustrative Tariff, Part XI, Subpart B, sections 710.4 and 710.5 provide that certain \nfacilities and necessary technical arrangements, such as an RAS, must be completed prior \nto commencement of requested service.48  Indeed, the Eligible Customer must “construct[], \nmaintain[], and operat[e] the facilities (i) on its side of the Delivery Point necessary to \nreliably deliver and receive energy and capacity; and (ii) only in the case of Non-Firm \nContract Demand Transmission Service, to implement the necessary control technologies \nand protection systems required pursuant to Tariff, Part XI, Subpart B, section 713 and \nspecified in the Service Agreement for Contract Demand Transmission Service, as \nTransmission Provider may require.”49  Such facilities are necessary for the Eligible \nCustomer to receive transmission service at its Delivery Point and to limit unauthorized \n \n46 Illustrative Tariff, Part XI, Subpart B, section 710.1. \n47 Illustrative Tariff, Part XI, Subpart B, section 710.1. \n48 Illustrative Tariff, Part XI, Subpart B, section 710.4. \n49 Illustrative Tariff, Part XI, Subpart B, section 710.5."},{"page":25,"startToken":6316,"endToken":6561,"text":"20 \nwithdrawals, consistent with the key principles underlying Contract Demand Transmission \nService.50 \nSection 710.6 details the required steps for execution and filing of Service \nAgreements for the requested transmission service type.51  These procedures are modeled \non those the Commission recently accepted for GIAs.52  \nG. \nTermination of Service Agreement for Contract Demand Transmission \nServices \nConsistent with the Show Cause Order’s holding that Contract Demand \nTransmission Services are to be a “permanent alternative” to NITS, PJM’s approach in \nsection 710.7 allows for a Service Agreement for Contract Demand Transmission Service \nto be “presumed to continue without expiration.”  PJM does set forth five circumstances \nunder which it may be terminated.53  Three of the circumstances are mundane in nature:  \n(i) where an incumbent Eligible Customer is replaced by a successor Eligible Customer;54 \n(ii) on 42-months’ notice prior to the commencement of a Delivery Year; and (iii) by \nmutual agreement.55  The 42-month notice period is appropriate because the contracted-for \nservice level under a Firm Contract Demand Transmission Service will be accounted for in \n \n50 See Abdulsalam Aff. ¶¶ 9-12. \n51 Illustrative Tariff, Part XI, Subpart B, section 710.6. \n52 Tariff, Part VIII, Subpart D, section 411 (Final Negotiation Phase); PJM Interconnection, L.L.C., 192 FERC \n¶ 61,077, at PP 66-70 (2024). \n53 Illustrative Tariff, Part XI, Subpart B, section 710.7. \n54 Illustrative Tariff, Part XI, Subpart B, section 710.7. \n55 Illustrative Tariff, Part XI, Subpart B, section 710.7."},{"page":26,"startToken":6561,"endToken":6954,"text":"21 \nPJM’s capacity market,56 as required by the Show Cause Order.57  Thus, given the 3-year \nforward nature of PJM’s capacity market—and the pre-auction development and posting \nor relevant auction parameters, PJM must have sufficient notice to not include such contract \ndemand in its Load Forecast for the relevant Delivery Year.58  The 42-months’ notice period \nis consistent with the termination provision in PJM’s pro forma pseudo-tie agreement and \nis designed to address the capacity market participation concerns.59 \nHowever, there are circumstances under which PJM could terminate the Service \nAgreement for cause.  One, where the Eligible Customer “is in breach of its obligations \nunder the Service Agreement or the Tariff, Part XI,” which could include, for example, \n“any material changes to the gross demand of the Co-Located Load or the design, \nconfiguration, or output of the Co-Located Generating Facility occur without being studied \nby [PJM] to determine whether such changes would affect [PJM’s] ability to reliably \nprovide the level of service specified in the Eligible Customer’s Contract Demand \nTransmission Service Agreement.”60  Two, the Eligible Customer is disqualified from \nreceiving Contract Demand Transmission Service upon an Eligible Customer’s failure to \nfollow an operating instruction to curtail or shed load, or after the misoperation, on more \n \n56 Illustrative Tariff, Part XI, Subpart B, section 708(b) (“Firm Contract Demand Transmission Service is for \nthe transfer of capacity and energy to an Eligible Customer on behalf of a designated Co-Located Load, up \nto a defined, predetermined megawatt level of transmission service as requested by the Eligible Customer \nand confirmed by the Transmission Provider, using capacity and energy procured by the Transmission \nProvider.”). \n57 See Show Cause Order at P 210 (“PJM will procure generation capacity on behalf of the Co-Located Load \nserved by Firm Contract Demand transmission service based on their contract demand[.]”).  \n58 See Horger Aff. ¶¶ 11-14. \n59 See PJM Interconnection, L.L.C., 162 FERC ¶ 61,086, at P 89 (2018) (“Regarding PJM’s proposal for 42-\nmonths’ notice of a request to terminate where there is no system reliability concern, we agree that 42-months’ \nnotice is an appropriate timeframe because it provides pseudo-tied resources with sufficient notice and allows \nPJM sufficient time to address changes in capacity market participation.”), reh’g denied, 167 FERC ¶ 61,069, \nat P 21 (2019). \n60 Illustrative Tariff, Part XI, Subpart B, section 710.7(d)."},{"page":27,"startToken":6954,"endToken":7204,"text":"22 \nthan one occasion, of any of the necessary control technologies or protection systems \nrequired under an Eligible Customer’s Non-Firm Contract Demand Transmission Service \nAgreement.  These latter circumstances are explained in response to Questions 5 and 6 \nbelow.   \nH. \nDesignation of Co-Located Load and Co-Located Generating Facility  \nThe Show Cause Order requires the Co-Located Generating Facility to “designat[e] \nan Eligible Customer . . . take transmission service on behalf of a Co-Located Load.”61  \nConsistent with this requirement, Attachment A, section 711 requires that an Eligible \nCustomer designate the individual Co-Located Load on behalf of which the Eligible \nCustomer is taking Contract Demand Transmission Service, whether it is Firm, Non-Firm, \nor both.62  The Eligible Customer must also designate the individual Co-Located \nGenerating Facility that will serve the individual Co-Located Load that is designated by \nthe Eligible Customer and provide the MW level of energy from the Co-Located \nGenerating Facility dedicated to serving the Co-Located Load.63  Upon designation, no \nchange in the Delivery Point for Contract Demand Transmission Service will be \npermitted.64   \nIn order to maintain PJM’s operational visibility of the system and support efforts \nto manage reliability, Eligible Customers shall have an ongoing obligation to provide the \nTransmission Provider with timely written or electronic notice of material changes in the \n \n61 Show Cause Order at P 226.  \n62 Illustrative Tariff, Part XI, Subpart B, section 711.1(a).  \n63 Illustrative Tariff, Part XI, Subpart B, section 711.1(b).  \n64 Illustrative Tariff, Part XI, Subpart B, section 711.2."},{"page":28,"startToken":7204,"endToken":7468,"text":"23 \ndemand characteristics of the Co-Located Load and the supply characteristics of the \nCo-Located Generating Facility.65   \nNecessary control technologies and protection systems for Non-Firm Contract \nDemand Transmission Service will be designed based on the specific circumstances and \ntechnical arrangements of each Co-Located Load arrangement, as outlined in each Service \nAgreement for Contract Demand Transmission Service.  Thus, any material changes to \nsuch control technologies and protection systems could have deleterious effects on the \nefficacy of the control technologies and protection systems and PJM’s ability to reliably \noperate the system.  Thus, failure to timely inform PJM of such material changes “may \nconstitute a breach of the Eligible Customer’s Service Agreement and subject to \ntermination under Tariff, Part XI, Subpart B, section 710.7.”66 \nI. \nRestrictions on Use of Service and Anti-Toggling Provision \nTo prevent retail sales, Eligible Customers will be prohibited from using Firm \nContract Demand Transmission Service for the sale of either capacity or energy to loads \nother than those Co-Located Loads designated in its Service Agreement or the direct or \nindirect provision of transmission services by the Eligible Customer to third parties.67  \nThe Commission recognized that an anti-toggling mechanism is necessary to avoid \na situation in which an Eligible Customer taking transmission service on behalf of a \nCo-Located Load attempts to switch between Firm and Non-Firm Contract Demand \nTransmission Service for the same portion of total contracted demand based on expected \n \n65 Illustrative Tariff, Part XI, Subpart B, section 711.3. \n66 Illustrative Tariff, Part XI, Subpart B, section 711.3. \n67 Illustrative Tariff, Part XI, Subpart B, section 709.3."},{"page":29,"startToken":7468,"endToken":7765,"text":"24 \ncapacity market conditions.68  PJM has included a proposed anti-toggling provision at \nAttachment A, section 709.4, which is described further below in response to Question 7.69   \nJ. \nInitial Study Procedures for Contract Demand Transmission Service  \nAfter receiving a completed Application for Firm Contract Demand Transmission \nService by an Eligible Customer, PJM will notify the affected Transmission Owner(s) of \nthe completed Application.70  The affected Transmission Owner(s) and PJM may need to \ncoordinate to study potential impacts of providing Firm Contract Demand Transmission \nService on the Transmission Owner’s system.71  PJM will then determine, in accordance \nwith PJM Manuals, any necessary studies to provide the requested transmission service.72  \nIf necessary studies are required, PJM will inform the Eligible Customer and will consider \nany results of the Transmission Owner studies.73  If PJM determines that necessary studies \nare needed to evaluate the requested transmission service request, PJM will provide an \nApplication and Studies Agreement to the Eligible Customer in which the Eligible \nCustomer will agree to reimburse PJM for the required study costs.  The Eligible Customer \nmust execute an Application and Studies Agreement within 15 days of receiving notice \nfrom PJM and pay the study fee.  An Eligible Customer that does not execute an \nApplication and Studies Agreement will be deemed withdrawn with the fee returned with \n \n68 Show Cause Order at P 213 (“[T]he terms and conditions for taking the new Firm Contract Demand \ntransmission service… must include an anti-toggling mechanism.”).  \n69 Illustrative Tariff, Part XI, Subpart B, section 709.4.  \n70 Illustrative Tariff, Part XI, Subpart B, section 712.1. \n71 Illustrative Tariff, Part XI, Subpart B, section 712.1.  \n72 Illustrative Tariff, Part XI, Subpart B, section 712.1. \n73 Illustrative Tariff, Part XI, Subpart B, section 712.1."},{"page":30,"startToken":7765,"endToken":8037,"text":"25 \ninterest.74  Finally, the Eligible Customer will be required to pay a study fee, as determined \nby PJM, to apply for Contract Demand Transmission Service.75 \nK. \nLoad Shedding and Curtailment for Contract Demand Transmission \nServices  \nThe Commission directed that, “[f]or the Eligible Customer taking transmission \nservice on behalf of a co-Located Load to be eligible for these new transmission services, \nthe co-Located Load must be able and willing to prevent or limit its energy \nwithdrawals . . . .”76   \nPJM addresses the reasoning underlying its Curtailment and Load Shedding \nprovisions in direct response to Question 11 below, but PJM takes the opportunity to \ndescribe those provisions here as requested by Question 1.  Consistent with the key \nprinciple that an Eligible Customer taking Contract Demand Transmission Service is \nwilling and able to limit energy withdrawals from the Transmission System, section 713 \ndetails the Curtailment and Load Shedding rules for the two Contract Demand \nTransmission Services.   \nSpecifically, an Eligible Customer must implement any Load Shedding or \nCurtailment directive ordered by PJM, and must respond 24 hours a day, 7 days a week, \n365 days a year, to any real-time instruction to reduce or curtail load within five minutes \nof the directive.77  PJM will make Curtailments on a non-discriminatory basis.78  Load Shed \ninstructions will be directed toward Eligible Customers in a manner that is consistent with \n \n74 Illustrative Tariff, Part XI, Subpart B, section 712.3. \n75 Illustrative Tariff, Part XI, Subpart B, section 712.4. \n76 Show Cause Order at P 206.  \n77 Illustrative Tariff, Part XI, Subpart B, section 713.1. \n78 Illustrative Tariff, Part XI, Subpart B, section 713.1."},{"page":31,"startToken":8037,"endToken":8293,"text":"26 \npreviously established procedures under the Service Agreement for Contract Demand \nTransmission Service.79   \nFor purposes of Curtailment, Firm Contract Demand Transmission Service is to be \ntreated as the equivalent of NITS.  Applying the same level of Curtailment priority as \nbetween Firm Contract Demand Transmission Service and NITS is reasonable, given that \nfor both services, PJM will plan the Transmission System and procure capacity to meet \ntheir resource adequacy needs.  Further, this is compliant with the Show Cause Order’s \nholding that “Firm Contract Demand transmission service will have the same reservation \nand curtailment priority as existing firm transmission services, at the level of the contract \ndemand.”80   \nPJM reserves the right to curtail Contract Demand Transmission Service to \nmaintain system reliability.81  Processes and procedures applicable to control technologies \nand protection systems (e.g., RAS), along with disqualification from Contract Demand \nTransmission Service and penalties for unreserved use of the system, are detailed further \nbelow in response to Question 5.82   \nL. \nRates and Charges for Firm Contract Demand Transmission Service \nConsistent with the allocation of rights between PJM and PJM Transmission \nOwners,83 PJM expects the PJM Transmission Owners to file briefing in the paper hearing \nrecord describing the proposed transmission rates for each of these new transmission \n \n79 Illustrative Tariff, Part XI, Subpart B, section 713.2. \n80 Show Cause Order at P 208.  \n81 Illustrative Tariff, Part XI, Subpart B, section 713.5.  \n82 See illustrative Tariff, Part XI, Subpart B, sections 713.6, 713.7 & 713.8.  \n83 See supra note 4."},{"page":32,"startToken":8293,"endToken":8594,"text":"27 \nservices for Co-Located Load.  However, Eligible Customers will be assessed other rates \nin addition to transmission service rates, and PJM has authority to institute such non-\ntransmission-related rates.  Thus, section 714 provides that PJM would assess:   \n• administrative services charges under Tariff, Schedule 1A; Tariff, Schedule \n9; and Tariff, Schedule 10 based on the total quantity of megawatt hours \n(“MWhs”) of energy delivered using Firm Contract Demand Transmission \nService, except in the case of any capacity-related charges under these \nschedules, which shall be based on the Eligible Customer’s Unforced \nCapacity Obligation;84 \n• Ancillary Services charges, except for Regulation, based on the total \nquantity in MWhs of energy delivered to the Co-Located Load using Firm \nContract Demand Transmission Service in accordance with Tariff, Part I, \nsection 3;85 \n• Black Start Service charges based on the gross demand of the Co-Located \nLoad in accordance with Tariff, Schedule 6A;86 \n• Regulation charges based on a gross demand of the Co-Located Load;87 and \n• any redispatch costs as set forth in Tariff, Attachment K.88 \nThese are standard charges associated with the use of the Transmission System over and \nabove the transmission service rates.  Also, consistent with the directives in the Show Cause \nOrder, PJM would assess Black Start and Regulation charges based on the gross demand \nof the Co-Located Load,89 while the other charges would be based on actual usage of the \nTransmission System, consistent with how other transmission services are charged.  \n \n84 Illustrative Tariff, Part XI, Subpart B, section 714.5. \n85 Illustrative Tariff, Part XI, Subpart B, section 714.5. \n86 Illustrative Tariff, Part XI, Subpart B, sections 714.5, 715.4. \n87 Illustrative Tariff, Part XI, Subpart B, section 715.4. \n88 Illustrative Tariff, Part XI, Subpart B, sections 714.3, 715.2. \n89 Show Cause Order at P 209."},{"page":33,"startToken":8594,"endToken":8879,"text":"28 \nFurther, as with all transactions in PJM, PJMSettlement will be the Counterparty to \nthe Firm Contract Demand Transmission Service and Non-Firm Contract Demand \nTransmission Service transactions under this Tariff.   \nM. \nApplicability of Operating Agreement \nConsistent with PJM’s requirements for NITS and the Commission’s pro forma \nOpen Access Transmission Tariff,90 PJM requires that the Eligible Customer taking \nContract Demand Transmission Service to plan, construct, operate, and maintain its \nfacilities in conformance with the Operating Agreement.91  Additionally, the terms and \nconditions under which the Eligible Customer will operate its facilities will be detailed in \nthe Operating Agreement.92   \nN. \nPro Forma Contract Demand Transmission Service Agreement \nPJM has provided in Attachment A an illustrative Tariff, Attachment F-4, a pro \nforma Service Agreement for Contract Demand Transmission Service, i.e., it will govern \nfor both Firm and Non-Firm Contract Demand Transmission Services.93  The new Service \nAgreement requires the parties to identify the Eligible Customer and provide business \ncontact information.  The parties will select whether facilities’ upgrades are necessary by \nthe Eligible Customer  to take Firm Contract Demand Transmission Service on behalf of \nthe Co-Located Load.94  The Service Agreement will also detail conditions for termination, \n \n90 Pro Forma Open Access Transmission, Federal Energy Regulatory Commission, § 35.1 (April 2020), \nhttps://www.ferc.gov/sites/default/files/2020-04/pro-forma-open-access.pdf.  \n91 The Commission’s pro forma Open Access Transmission Tariff uses the term “Network Operating \nAgreement.”  In PJM, the “Operating Agreement of the PJM Interconnection, L.L.C., as amended from time \nto time, shall constitute the Network Operating Agreement.”  Tariff, Attachment G. \n92 Illustrative Tariff, Part XI, Subpart B, section 716.1. \n93 Illustrative Tariff, Attachment F-4.   \n94 Illustrative Tariff, Attachment F-4, section 2.0."},{"page":34,"startToken":8879,"endToken":9061,"text":"29 \nsuch as misoperation of a necessary control technology or protection system under sections \n710.7 and 713.7 or failure to timely inform PJM of material changes to the Co-Located \nLoad or Co-Located Generating Facility.95  The Eligible Customer is also required to \nsubmit a single-line diagram as a part of Attachment F-4 to show the Delivery Point \nbetween the Co-Located Load and Co-Located Generating Facility.   \nAs noted, the pro forma Service Agreement is designed to provide applicable terms \nand conditions for Non-Firm Contract Demand Transmission Service.  This will allow an \nEligible Customer taking Firm Contract Demand Transmission Service and Non-Firm \nContract Demand Transmission Service on behalf of a Co-Located Load to consolidate its \nservices into one agreement.  Further, using a single agreement to cover both services is \nconsistent with the requirement that an Eligible Customer taking Contract Demand \nTransmission Service must use a combination of the two services to cover the entire gross \ndemand of the Co-Located Load.96   \n \n \n \n95 Illustrative Tariff, Attachment F-4, sections 3.0, 4.0.  \n96 See, e.g., Illustrative Tariff, Subpart B, section 709.2."},{"page":35,"startToken":9061,"endToken":9341,"text":"30 \nQuestion 2:  \nWhat are the appropriate rates, terms, and conditions for the new Non-Firm \nContract Demand transmission service, including whether it would be just and \nreasonable to apply the current zonal non-firm PTPS charges to this new \ntransmission service and whether it would be just and reasonable and consistent \nwith cost causation to include charges for any of PJM’s administrative services? \nResponse to Question 2: \nAs discussed above, many of the non-rate terms and conditions applicable to the \nnew Non-Firm Contract Demand Transmission Service are the same as those for the new \nFirm Contract Demand Transmission Service, and are as described in response to \nQuestion 1.  Thus, PJM details those terms and conditions specific to Non-Firm Contract \nDemand Transmission Service that were not discussed above.  \nA. \nProvision of Non-Firm Contract Demand Transmission Service \nThe Show Cause Order recognizes that “not all Co-Located Loads will necessarily \nplan to withdraw energy from the transmission system on a regular basis” and “Eligible \nCustomers taking service on behalf of such loads may . . . seek to withdraw energy from \nthe transmission system from time to time when transmission capacity is available.”97  To \nimplement this requirement, PJM has developed Non-Firm Contract Demand Transmission \nService as a service offering the transmission of energy for an Eligible Customer on behalf \nof a designated Co-Located Load, on an as-available basis, up to a defined, predetermined \nMW level of transmission service as requested by the Eligible Customer and confirmed by \nthe Transmission Provider, using energy procured by the Transmission Provider.98  Like \nFirm Contract Demand Transmission Service, the ability to request Non-Firm Contract \n \n97 Show Cause Order at P 214.  \n98 See Show Cause Order at PP 193, 214."},{"page":36,"startToken":9341,"endToken":9640,"text":"31 \nDemand Transmission Service on any given day, for any given period, is intended to be \npermanent—so long as the Service Agreement is effective.99 \nAs discussed in Section E below, Eligible Customers taking Non-Firm Contract \nDemand Transmission Service on behalf of Co-Located Loads must have the necessary \ncontrol technologies and protective systems (e.g., RAS) in place to appropriately limit their \nwithdrawals of energy from the Transmission System, consistent with their contractual \nrights and PJM’s operational instructions.   \nB. \nNature of Non-Firm Contract Demand Transmission Service \nNon-Firm Contract Demand Transmission Service allows an Eligible Customer \ntaking service on behalf of a Co-Located Load to access the Transmission System on a \nnon-firm, interruptible basis during normal operations, and receive that transmission \nservice up to a level defined in accordance with the terms of its Service Agreement.100  As \ndiscussed above in response to Question 1 and shown in Figure 1, such Eligible Customer \nmust request Non-Firm Contract Demand Transmission Service equivalent to the MW level \nof the Co-Located Load’s gross demand not covered by Firm Contract Demand \nTransmission Service as part of the Service Agreement, such that the Eligible Customer is \nseeking to obtain sufficient Contract Demand Transmission Service to allow access to the \nTransmission System at a level capable of serving the Co-Located Load’s entire gross \ndemand.   \n \n99 See Show Cause Order at P 215 (“Reservations for this service shall be available for terms ranging from \none hour to one month, consistent with the terms available for Non-Firm PTPS in the PJM Tariff.” (footnote \nomitted)). \n100 See Show Cause Order at P 215 (“Non-Firm Contract Demand transmission service must be available \nduring normal operations and curtailed during emergency operations (i.e., it will be curtailed before existing \nfirm transmission services and the new Firm Contract Demand Transmission Service.”))."},{"page":37,"startToken":9640,"endToken":9953,"text":"32 \nPJM anticipates that in practice, requests for Non-Firm Contract Demand \nTransmission Service will be at the MW level the Co-Located Generating Facility has \ndedicated to serving the Co-Located Load.101  The Eligible Customer may then, on any \ngiven day, reserve Non-Firm Contract Demand Transmission Service up to the amount \nspecified in the Service Agreement (but only up to the MW level that the Co-Located \nGenerating Facility is on outage).  However, such requests for Non-Firm service shall only \nbe granted when PJM has determined there is available transmission capacity.102    \nPer the requirements of the Show Cause Order, Eligible Customers seeking \nNon-Firm Contract Demand Transmission Service “will be charged for transmission and \nancillary services on an as-reserved contract demand [i.e., usage only] basis” and will be \ncharged “regulation and black start services based on a gross demand basis.”103  Finally, \nconsistent with the Show Cause Order, an Eligible Customer can seek a transmission \nreservation for Co-Located Load in advance for the duration of an expected outage of the \nassociated Co-Located Generating Facility.104 \nC. \nInitiating Non-Firm Contract Demand Transmission Service  \nAs with requests for Firm Contract Demand Transmission Service, upon receiving \na request for Non-Firm Contract Demand Transmission Service, PJM will coordinate with \nthe affected Transmission Owner(s) to complete necessary studies to determine whether—\nand at what level—Non-Firm Contract Demand Transmission Service can be reliably \n \n101 Illustrative Tariff, Part XI, Subpart B, section 709.2.   \n102 See Show Cause Order at P 215; Tariff, Part II, section 14.1.  This is consistent with the Show Cause \nOrder’s statement that an “Eligible Customer taking transmission service on behalf of Co-Located Loads that \nwill not withdraw energy from the transmission system must take Non-Firm Contract Demand transmission \nservice at 0 MW.”  Show Cause Order at P 206. \n103 Show Cause Order at P 216.  \n104 See Show Cause Order at P 214."},{"page":38,"startToken":9953,"endToken":10234,"text":"33 \nprovided.105  If PJM determines that only a portion or none of the Non-Firm Contract \nDemand Transmission Service requested by an Eligible Customer can be provided reliably, \nPJM will provide a written explanation of its reasons for denial of service.106  In such case, \nthe Eligible Customer may either apply for the amount of Firm Contract Demand \nTransmission Service necessary to cover the Co-Located Load’s entire gross demand, or \nalternatively, apply to serve the entire Co-Located Load through NITS.107 \nD. \nStudy Procedures for Non-Firm Contract Demand Transmission Service \nAs discussed, PJM will not study transmission service requests alone, but rather \nwill coordinate and consult with any affected Transmission Owners to determine whether \nand how the requested transmission service may be provided.  Thus, upon receipt of a \nrequest for Non-Firm Contract Demand Transmission Service, PJM will notify the affected \nTransmission Owner(s) of such request.108  PJM and the affected Transmission Owner(s) \nwill determine whether additional studies are required “to assess whether the Transmission \nSystem has sufficient available capacity to provide Non-Firm Contract Demand \nTransmission Service, and if so, which studies are appropriate.”109  To be clear, these \nstudies relate only to the maximum amount of Non-Firm Contract Demand Transmission \nService that would be allowed under a specific Service Agreement.  PJM expects to \nperform different evaluations to actually use such service on the Transmission System on \nany given day. \n \n105 Illustrative Tariff, Part XI, Subpart B, section 710.3. \n106 Illustrative Tariff, Part XI, Subpart B, section 710.3. \n107 Illustrative Tariff, Part XI, Subpart B, section 710.3. \n108 Illustrative Tariff, Part XI, Subpart B, section 712.2. \n109 Illustrative Tariff, Part XI, Subpart B, section 712.2."},{"page":39,"startToken":10234,"endToken":10545,"text":"34 \nE. \nCurtailment of Non-Firm Contract Demand Transmission Service \nNon-Firm Contract Demand Transmission Service will be Curtailed before Firm \nContract Demand Transmission Service and NITS as required by the Commission in the \nShow Cause Order.110  As discussed in greater detail in response to Question 11, PJM may \ncurtail Non-Firm Contract Demand Transmission Service prior to dispatching the Pre-\nEmergency Load Response Program as further set forth in the PJM Manuals,111 or in \nresponse to a transfer capability shortage.112    \nF. \nNecessary Control Technologies and Protection Systems to Protect the \nTransmission System by Limiting Energy Withdrawals \nAs part of implementing the key principles that (1) the services are designed to \nserve loads that are “willing and able to control their withdrawals from the transmission \nsystem;”113 and (2) the services are designed to allow PJM to maintain system reliability, \nPJM is requiring Eligible Customers taking Non-Firm Contract Demand Transmission \nService to work with PJM and affected Transmission Owners to “establish necessary \ncontrol technologies and protection systems, . . . which may include a [RAS], for each \nService Agreement for Non-Firm Contract Demand Transmission Service.”114 \nThe control technologies and protection systems necessary to provide Non-Firm \nContract Demand Transmission Service (and Interim NITS) is emblematic of the \n \n110 Show Cause Order at P 215; illustrative Tariff, Part XI, Subpart B, section 713.4.  \n111 The Tariff provides that the Pre-Emergency Load Response Program is “the program by which Curtailment \nService Providers may be compensated by PJM for Demand Resources that will reduce load when dispatched \nby PJM during pre-emergency conditions, and is described in Operating Agreement, Schedule 1, section 8 \nand the parallel provisions of Tariff, Attachment K-Appendix, section 8.”  Tariff, Definitions – O – P - Q. \n112 Illustrative Tariff, Part XI, Subpart B, section 713.4. \n113 Show Cause Order at P 204 (footnote omitted). \n114 Illustrative Tariff, Part XI, Subpart B, section 713.6."},{"page":40,"startToken":10545,"endToken":10786,"text":"35 \ncomplexity associated with Non-Firm Contract Demand Transmission Service from an \noperations and planning perspective.115 \nEach and every Service Agreement for Non-Firm Contract Demand Transmission \nmust include the necessary control technologies and protection systems to ensure the \nreliability and stability of PJM’s Transmission System.  As Dr. Abdulsalam explains, Non-\nFirm Contract Demand Transmission Service (or Interim NITS) “will need to be evaluated \non a per-request basis and will be tied to necessary control technologies or protection \nsystems, which may include RAS . . . to ensure that the contracted-for withdrawal level is \nnot exceeded and that the pre-scheduled, non-firm withdrawal level can only be reliably \nenabled under conditions that PJM has agreed to.”116  In his affidavit, Mr. Wharton, a \nManager of Reliability Engineering within PJM and a NERC Certified System Operator, \nfurther elaborates on the operational complexities that may be associated with RAS.117  As \nMr. Wharton explains, an RAS “is designed to detect abnormal system conditions and “to \nautomatically take appropriate corrective action to maintain system stability, acceptable \nsystem voltages, and acceptable facility loading.”118  Mr. Wharton testifies, however, that \nRAS “should not be installed as a substitute for good system design or operating \npractices.”119   \nTogether, Dr. Abdulsalam and Mr. Wharton explain why control technologies and \nprotection systems (e.g., RAS) are necessary to protect the Transmission System from \n \n115 See Abdulsalam Aff. ¶¶ 9-12. \n116 Abdulsalam Aff. ¶ 9. \n117 Wharton Aff. ¶ 16. \n118 Wharton Aff. ¶ 15.  \n119 Wharton Aff. ¶ 16."},{"page":41,"startToken":10786,"endToken":11075,"text":"36 \nsignificant unexpected events that may occur with Non-Firm Contract Demand \nTransmission Service (and Interim NITS).  Without the necessary control technologies and \nprotection systems tied to Non-Firm Contract Demand Transmission Service (and as \ndiscussed below, Interim NITS), an Eligible Customer may, for example, withdraw energy \nduring peak periods above what it had previously contracted (or contrary to PJM dispatch \ninstructions), for which PJM has not planned either adequate transmission or generation \ncapacity, putting other customers at risk.120  PJM has developed penalties that address, inter \nalia, instances where a control technology or protection system tied to an Eligible \nCustomer’s Non-Firm Contract Demand Transmission Service misoperates.  PJM \ndescribes these penalties in response to the Commission’s Briefing Questions 5 and 6 \nbelow.   \nG. \nRates and Charges for Non-Firm Contract Demand Transmission Service  \nConsistent with the allocation of rights between PJM and PJM Transmission \nOwners,121 PJM expects the PJM Transmission Owners to file briefing in the paper hearing \nrecord describing the proposed transmission rates for each of these new transmission \nservices, including Non-Firm Contract Demand Transmission Service.  However, with \nrespect to the other rates that PJM has authority to institute, as for Firm Contract Demand \nTransmission Service, PJM will assess Eligible Customers taking Non-Firm Contract \nDemand Transmission Service based on their actual usage of the system: \n• administrative services charges under Tariff, Schedule 1A; Tariff, \nSchedule 9; and Tariff, Schedule 10 based on the total quantity of MWhs of \n \n120 See Show Cause Order at P 211 (“PJM will only plan the transmission system and procure generation \ncapacity for the contract demand—not for load growth, like it does for NITS customers—and PJM will have \nno obligation to serve the Eligible Customer beyond the contract demand.”).   \n121 See supra note 4."},{"page":42,"startToken":11075,"endToken":11405,"text":"37 \nenergy delivered using Non-Firm Contract Demand Transmission Service, \nexcept any capacity-related charges under these schedules will not apply;122 \n• Ancillary Services charges, except for Regulation, based on the total \nquantity in MWhs of energy delivered to the Co-Located Load using Non-\nFirm Contract Demand Transmission Service in accordance with Part I, \nsection 3; and \n• any redispatch costs as set forth in Tariff, Attachment K. \nIn addition, Non-Firm Contract Demand Transmission Service customers will be \nresponsible for Regulation and Black Start Service charges based on the gross demand of \nthe Co-Located Load, to the extent the customer is not paying such charges associated with \nits Firm Contract Demand Transmission Service.123  Notably, given that there is one Service \nAgreement for both Contract Demand Transmission Services, any Eligible Customer \ntaking Contract Demand Transmission Service will not be double billed for the Regulation \nand Black Start Service for the Co-Located Load served under a given Service Agreement. \nH. \nPro Forma Contract Demand Transmission Service Agreement \nAs discussed, PJM has provided in Attachment A an illustrative Tariff, Attachment \nF-4, a pro forma Service Agreement for both Firm Contract Demand Transmission Service \nand Non-Firm Contract Demand Transmission Service.124  Thus, a single Service \nAgreement will detail an Eligible Customer’s subscription for both types of service, and \nallow one agreement to govern the Eligible Customer’s transmission service on behalf of \nthe Co-Located Load. \n \n122 Illustrative Tariff, Part XI, Subpart B, section 714.5. \n123 See Illustrative Tariff, Part XI, Subpart B, section 715.4 (“To the extent the Eligible Customer does not \nhave an effective Service Agreement for Firm Contract Demand Transmission Service, Eligible Customer \nshall pay Black Start Service charges based on the gross demand of the Co-Located Load in accordance with \nTariff, Schedule 6A.  To the extent the Eligible Customer does not have an effective Service Agreement for \nFirm Contract Demand Transmission Service, Eligible Customer shall pay Regulation charges based on a \ngross demand of the Co-Located Load.”). \n124 Illustrative Tariff, Attachment F-4."},{"page":43,"startToken":11405,"endToken":11556,"text":"38 \nQuestion 3:  \nAs noted above, a Co-Location Arrangement is synchronized to the transmission \nsystem.  Should the rate paid by an Eligible Customer on behalf of a Co-Located \nLoad taking only the new Non-Firm Contract Demand transmission service that \nelects to not reserve any amount of that service for a period of time (e.g., one month) \nreflect not only charges for regulation and black start services, but also an \nadditional charge given that regulation and black start services could not be \nprovided without the transmission system?  If so, how should that additional charge \nbe determined? \nResponse to Question 3:  \nConsistent with the allocation of rights between PJM and PJM Transmission \nOwners,125 PJM expects the PJM Transmission Owners to file briefing in the paper hearing \nrecord answering this question.  Upon review of that briefing, PJM may provide additional \ncommentary or perspectives in its reply brief. \n \n \n \n \n125 See supra note 4."},{"page":44,"startToken":11556,"endToken":11707,"text":"39 \nQuestion 4: \nAs noted above, a Co-Location Arrangement is synchronized to the transmission \nsystem. Should the rate paid by an Eligible Customer on behalf of a Co-Located \nLoad taking only a de minimis amount of the new Firm or Non-Firm Contract \nDemand transmission services reflect not only (i) charges for regulation and black \nstart service and (ii) the transmission service charges for that de minimis amount \nof service, but also an additional charge reflecting that the Co-Location \nArrangement is physically connected and synchronized to the PJM transmission \nsystem?  If so, how should that additional charge be determined? \nResponse to Question 4: \nConsistent with the boundaries between PJM and PJM Transmission Owners,126 \nPJM expects the PJM Transmission Owners to file briefing in the paper hearing record \nanswering this question.  Upon review of that briefing, PJM may provide additional \ncommentary or perspectives in its reply brief. \n \n \n \n \n126 See supra note 4."},{"page":45,"startToken":11707,"endToken":11883,"text":"40 \nQuestion 5: \nWhat is the appropriate penalty charge or other remedial action that PJM should \ntake to address any unreserved use of the PJM transmission system for an Eligible \nCustomer taking Firm Contract Demand transmission service on behalf of a Co-\nLocated Load? \nResponse to Question 5:   \nPJM addresses, below, the appropriate penalty charges or other remedial actions \n(together “penalties”) applicable to Eligible Customers taking transmission service on \nbehalf of a Co-Located Load using:  (i) Firm Contract Demand Transmission Service; \n(ii) Non-Firm Contract Demand Transmission Service; and (iii) Interim NITS prior to \nautomatically transitioning to NITS on behalf of a Co-Located Load.  PJM supports three \ndifferent penalties applicable where such Eligible Customers:  (i) fail to follow established \nLoad Shedding and Curtailment procedures; (ii) rely on necessary control technologies or \nprotection systems in accordance with the PJM Manuals, which may include a RAS, that \nfail (i.e., misoperate) more than once; and (iii) makes unreserved use of the PJM \nTransmission System. \nThe illustrative Tariff provisions governing the three penalties applicable to \nEligible Customers are as follows:"},{"page":46,"startToken":11883,"endToken":12174,"text":"41 \nTable 1.  Penalties Applicable to Eligible Customers Taking Contract Demand \nTransmission Service or Interim NITS \n \n Disqualification \n(First Failure to \nShed Load or \nCurtail) \nService \nPaused  \n(First Control \nTech or \nProtection \nSystem \nMisoperation) \nDisqualification \n(Second Control \nTech or Protection \nSystem \nMisoperation) \nFinancial Penalty \n(Unreserved Use) \nFirm Contract \nDemand \nIllustrative Tariff, \nPart XI, Subpart B, \nsections 713.7(a), \n713.7(c) \nN/A \nN/A \nTo be determined \nNon-Firm \nContract \nDemand \nIllustrative Tariff, \nPart XI, Subpart B, \nsections 713.7(a), \n713.7(c) \nIllustrative \nTariff, Part XI, \nSubpart B, \nsections \n713.7(b), \n713.7(c) \nIllustrative Tariff, \nPart XI, Subpart B, \nsections 713.7(b), \n713.7(c) \nTo be determined \nInterim NITS \nIllustrative Tariff, \nPart XI, Subpart A, \nsections 705.6(a), \n705.6(c) \nIllustrative \nTariff, Part XI, \nSubpart A, \nsections \n705.6(b), \n705.6(c) \nIllustrative Tariff, \nPart XI, Subpart A, \nsections 705.6(b), \n705.6(c) \nTo be determined \n \nA. \nDisqualification or Pause in Service  \n1. \nDisqualification after first failure of Eligible Customer to shed load \nor curtail in accordance with established procedures \nUnder PJM’s approach, Eligible Customers taking Firm Contract Demand \nTransmission Service, Non-Firm Contract Demand Transmission Service, or Interim NITS \non behalf of a Co-Located Load may be subject to remedial action in the event that the \nEligible Customer “fails to respond to established Load Shedding and Curtailment \nprocedures.”127  \nThe proposed remedial action is a strict liability rule that automatically applies after \nbeing triggered by one instance of an Eligible Customer failing to follow Curtailment or \nLoad Shed procedures.  The rule is triggered after one failure and applied automatically on \n \n127 Illustrative Tariff, Part XI, Subpart A, section 705.6(a); id., Part XI, Subpart B, section 713.7(a)."},{"page":47,"startToken":12174,"endToken":12445,"text":"42 \na strict liability basis because of the significant reliability risk posed by Eligible Customers \nwho disregard Load Shed or Curtailment procedures.   \nSuch an approach is just and reasonable and consistent with the two key principles:  \n(1) these Eligible Customers are “willing and able to control their withdrawals from the \ntransmission system;”128 and (2) the services are designed to allow PJM to maintain system \nreliability.  Allowing customers that are allowed on the system on the promise that they \nwill control their energy withdrawals as necessary, and then not penalizing them for failing \nto honor that promise runs counter to the Show Cause Order and would implicitly bless \nsuch dangerous behavior.   \nUnder illustrative Tariff, Part XI, Subpart B, section 713.7(a), an Eligible Customer \ntaking Firm or Non-Firm Contract Demand Transmission Service on behalf of a Co-\nLocated Load is disqualified from taking Firm or Non-Firm Contract Demand \nTransmission Service if the Eligible Customer fails to respond to Load Shedding and \nCurtailment under established procedures set forth in illustrative Tariff, Part XI, Subpart B, \nsection 713.  Importantly, however, an Eligible Customer disqualified from taking Firm or \nNon-Firm Contract Demand Transmission Service may continue taking transmission \nservice on behalf of Co-Located Load by either taking NITS or by qualifying for Interim \nNITS.   \nUnder illustrative Tariff, Part XI, Subpart A, section 705.6(a), an Eligible Customer \ntaking Interim NITS on behalf of a Co-Located Load is disqualified from taking Interim \nNITS, Firm Contract Demand Transmission Service, and Non-Firm Contract Demand \nTransmission Service if the Eligible Customer fails to respond to established Load \n \n128 Show Cause Order at P 204 (footnote omitted)."},{"page":48,"startToken":12445,"endToken":12721,"text":"43 \nShedding and Curtailment procedures set forth in illustrative Tariff, Part XI, Subpart A, \nsection 705.  Importantly, however, such an Eligible Customer may take NITS, which \nwould begin after all necessary upgrades are placed into service.     \n2. \nMisoperation of necessary control technology and protection system \nschemes \nEligible Customers taking Interim NITS or Non-Firm Contract Demand \nTransmission Service must, pursuant to illustrative Tariff, Part XI, Subpart A, section \n705.5 and illustrative Tariff, Part XI, Subpart B, section 713.6, respectively, must \nimplement all necessary control technology and protection system schemes, as outlined \nand agreed upon in their respective transmission Service Agreements.  As discussed above \nin response to Question 2, these control technology and protection schemes, which may \ninclude RAS, must be developed by PJM, the affected Transmission Owner(s), and the \nEligible Customer and approved by PJM and operate in accordance with PJM Manuals and \napplicable NERC reliability requirements.129   \nWhen a control technology or protection scheme misoperates, there can be serious \nconsequences.  Misoperation, as contemplated by PJM, relies on and incorporates the term \nas defined by NERC (e.g., PRC-004-6).130 \nAccording to PJM witness Mr. Wharton, “the consequences of an RAS \nmisoperation are often more severe than those of fault protection schemes.  While an RAS \nmay be a temporary solution until the transmission system is reinforced, PJM Manuals \nindicate that PJM’s systems and operating procedures were designed to be served by NITS, \n \n129 See illustrative Tariff, Part XI, Subpart A, section 705.6(b). \n130 See, e.g., PRC-004-6 – Protection System Misoperation Identification and Correction, North American \nElectric Reliability Corporation (June 12, 2025), https://www.nerc.com/globalassets/standards/reliability-\nstandards/prc/prc-004-6.pdf."},{"page":49,"startToken":12721,"endToken":13090,"text":"44 \neliminating the need for RAS while ensuring generation can be dispatched to serve \nload.”131  “For any RAS, PJM, in its role as the Reliability Coordinator, reviews the scheme \nand provides feedback to the RAS-entity within four full calendar months or a schedule \nthat is mutually agreed upon in keeping with R2 of NERC Reliability Standard PRC-012-\n02.”132  The illustrative Tariff provides PJM a similar authority as the ultimate decider for \nany necessary control technology or protective system for these services.133 \na. \nPause in service after first misoperation of a necessary \ncontrol technology or protection system scheme   \nPJM’s approach calls Eligible Customers taking Contract Demand Transmission \nService (both Firm and Non-Firm) or Interim NITS on behalf of a Co-Located Load be \nsubject to remedial action in the first instance where an Eligible Customer’s necessary \ncontrol technology or protection system scheme misoperates.134  After one instance of \nmisoperation, the Eligible Customer will be prohibited from taking transmission service or \notherwise withdrawing energy from the Transmission System for a period up to 120 days \nfrom misoperation, which may be shortened or extended per mutual agreement, to allow \nfor an analysis of the necessary control technology or protection system scheme’s \noperational performance.135  The up to 120-day pause pending evaluation of the \n \n131 Wharton Aff. ¶ 16. \n132 Wharton Aff. ¶ 18; PRC-012-2 – Remedial Action Schemes, North American Electric Reliability \nCorporation (June 12, 2025), https://www.nerc.com/globalassets/standards/reliability-standards/prc/prc-012-\n2.pdf. \n133 See Illustrative Tariff, Part XI, Subpart A, section 705.5 (“The necessary control technologies and \nprotection systems must: be developed in accordance with the PJM Manuals and be approved by the \nTransmission Provider.”); id., Part XI, Subpart B, section 713.6 (same). \n134 Illustrative Tariff, Part XI, Subpart A, section 705.6(a)-(b); id., Part XI, Subpart B, section 713.7(a)-(b). \n135 PJM is also evaluating whether modifications would be needed to the Co-Located Generating Facility’s \nGIA to preclude it from directly serving the Co-Located Load during this investigatory period following the \nfailure of a necessary control technology or protection system.  Such preclusion of direct service is necessary \nbecause the underlying premise of permitting these Contract Demand Transmission Services is a functional"},{"page":50,"startToken":13090,"endToken":13385,"text":"45 \nmisoperation of the necessary control technology or protection system scheme is consistent \nwith NERC requirements for an investigation into the operation of a RAS (e.g., PRC-004-6 \nand PRC-012-02).136  Such a pause in service will allow PJM (and the affected \nTransmission Owner(s), as necessary) time to investigate, identify, and implement fixes to \nbetter protect the Transmission System, while respecting the Eligible Customer’s desire to \nretain this type of service based on its promised willingness to limit energy withdrawals.   \nb. \nDisqualification after second necessary control technology \nor protection system scheme misoperation \nAfter a second instance of a necessary control technology or protection system \nscheme misoperating, the Eligible Customer will be disqualified from taking Contract \nDemand Transmission Service (both Firm and Non-Firm) or Interim NITS on behalf of a \nCo-Located Load.   \nThe proposed remedial action is a strict liability rule that automatically applies after \nbeing triggered by two instances of an Eligible Customer’s necessary control technology \nor protection system scheme misoperation.  The rule is triggered after two instances in \nwhich a necessary control technology or protection system scheme(s) misoperates.  The \nrule is applied automatically on a strict liability basis because of the significant reliability \nrisk posed by necessary control technology or protection system scheme misoperations.   \nThis two-strike rule appropriately implements the two key principles, in that it \nproperly balances the desire of these loads to obtain a transmission service lesser than NITS \nbecause they are willing and able to limit their energy withdrawals, against the need to \n \nscheme in place that limits energy withdrawals from the Transmission System—and if the scheme has failed \nto operate or misoperates, it cannot be considered functional. \n136 Illustrative Tariff, Part XI, Subpart A, section 705.6(b); id., Part XI, Subpart B, section 713.7(b)."},{"page":51,"startToken":13385,"endToken":13642,"text":"46 \nprotect system reliability and maintain reliable service to the 67+ million customers in the \nPJM Region.  After the second time a necessary control technology or protection system \nmisoperates, it is evident that the necessary control technology or protection system cannot \nadequately protect the system from the Co-Located Load’s unreserved (and unscheduled) \nenergy withdrawals.137 \nAccordingly, under illustrative Tariff, Part XI, Subpart B, section 713.7, an Eligible \nCustomer taking Non-Firm Contract Demand Transmission Service on behalf of a Co-\nLocated Load is disqualified from taking Firm or Non-Firm Contract Demand \nTransmission Service if the Eligible Customer experiences more than one misoperation of \na necessary control technology or protection system scheme.  Importantly, however, an \nEligible Customer disqualified from taking Contract Demand Transmission Service (both \nFirm and Non-Firm) may continue taking transmission service on behalf of a Co-Located \nLoad by either taking NITS or by qualifying for Interim NITS.   \nUnder illustrative Tariff, Part XI, Subpart A, section 705.6, an Eligible Customer \ntaking Interim NITS on behalf of a Co-Located Load is disqualified from taking Interim \nNITS, Firm Contract Demand Transmission Service, and Non-Firm Contract Demand \nTransmission Service if the Eligible Customer experiences more than one necessary control \ntechnology or protection system scheme misoperation.  Importantly, however, such an \nEligible Customer may take NITS, which would begin after all necessary upgrades are \nplaced into service.     \n \n137 With respect to RAS in particular, Mr. Wharton details the cascading adverse effects a RAS misoperation \ncould have the Transmission System, particularly when RASs are clustered geographically and electrically.  \nSee Wharton Aff. ¶¶ 21-22."},{"page":52,"startToken":13642,"endToken":14004,"text":"47 \nc. \nOption to take NITS following disqualification \nEligible Customers that have been disqualified from taking Firm Contract Demand \nTransmission Service, Non-Firm Contract Demand Transmission Service, or Interim NITS \non behalf of Co-Located Load nonetheless retain the option to take NITS on behalf of that \nCo-Located Load, as Network Load, or, if not already taking Interim NITS, to qualify to \ntake Interim NITS prior to transitioning to NITS pursuant to illustrative Tariff, Part XI, \nSubpart A, section 705.6(c) and illustrative Tariff, Part XI, Subpart B, section 713.7(c).  \nThis rule recognizes that NITS, in and of itself, addresses Curtailment, Load Shed, and \ncontrol technology or protection scheme misoperation risk.  In PJM, as Dr. Abdulsalam \nnotes, “NITS is used for internal (non-border) transmission service in the PJM Region.”138  \nAs Mr. Wharton testifies on behalf of PJM, “a reliable centrally dispatched Balancing \nAuthority relies on [NITS] to ensure that generation is not ‘bottled’ and is deliverable to \nload[.]”139  Likewise, Dr. Abdulsalam testifies that, in PJM: \nThe NITS type of transmission service enables a high level of \nreliability across the region under system normal and abnormal \noperating conditions.  This type of service ensures the transmission \nnetwork and the needed capacity to serve such load and allows PJM \nto plan for and secure the requisite level of service needed to \naccommodate changes in system conditions and the resource mix, \nas it shifts with time.  NITS also ensures the system overall is \n“proactively” planned to a forecasted level of service and the needed \nresource capacity to maintain the reliability of service is secured \nahead of time.  Given the level of reliability offered by the NITS to \nits transmission service loads, such loads rarely face situations of \ncurtailments or load shedding, as they are usually limited to extreme \ntransmission outage conditions or resource emergency conditions.  \nIn addition, PJM serves a system load that is high in density \ncompared to its geographic footprint.  The high load density in the \nPJM Region means that a higher load level is served from a single \npoint of service/delivery.  As a result, a higher number of customers \n \n138 Abdulsalam Aff. ¶ 7. \n139 Wharton Aff. ¶ 10 (footnote omitted)."},{"page":53,"startToken":14004,"endToken":14337,"text":"48 \ncould be exposed to interruption risk under malfunction, \nmisoperation, or unplanned interaction between more than one \nnecessary control technologies and protection systems, which may \ninclude [RAS].140  \nSince at least its establishment as an Independent System Operator in 1997, PJM’s \nprocesses have been built around the long-held practice and expectation that load internal \nto PJM will receive NITS.  This has significant implications for PJM’s planning, markets, \nand operations functions, which are focused on serving Network Load.     \nWithin the existing PJM framework, transmission customers must elect one of two \ntransmission services—NITS or Point-to-Point Transmission Service (“PTP Transmission \nService”).  Load Serving Entities serving end-use load within PJM take NITS,141 while \nPTP Transmission Service is used for the transmission of capacity and/or energy into, out \nof, or through the PJM Region.  More specifically, PTP Transmission Service is the use of \ntransmission facilities for the transmission of capacity and energy between a Point of \nReceipt and a Point of Delivery.  While all NITS is firm, PTP Transmission Service may \nbe either firm or non-firm.  Unlike PTP Transmission Service, NITS is flexible, \nincorporated into PJM’s system planning studies and processes as well as PJM’s capacity \nmarket, and always firm.  Unlike customers with PTP Transmission Service, a Network \nCustomer taking NITS must also obtain or provide Ancillary Services.   \nAt bottom, NITS is not only the default transmission service taken by load internal \nto PJM, it is also significantly more comprehensive and a higher quality of service than \nPTP Transmission Service.  The choice to take NITS, in and of itself, decreases the \n \n140 Abdulsalam Aff. ¶¶ 7-8. \n141 Pa.-N.J.-Md. Interconnection, 81 FERC ¶ 61,257, at 62,272 (1997), order on reh’g, 82 FERC ¶ 61,047, \norder on clarification, 82 FERC ¶ 61,068, modified sub nom., Potomac Elec. Power Co., 83 FERC ¶ 61,068 \n(1998), order on reh’g & clarification, 92 FERC ¶ 61,282 (2000), vacated, in part, and remanded sub nom., \nAtl. City Elec. Co. v. FERC, 295 F.3d 1 (D.C. Cir. 2002)."},{"page":54,"startToken":14337,"endToken":14667,"text":"49 \nlikelihood of significant issues arising from failure to curtail, load shed, or misoperation of \na necessary control technology or protection system.  Network Customers may “call upon \nthe transmission provider to supply not just some, but all of their load at any given moment, \nwhen for instance they experience blackouts or brownouts.”142  Furthermore, NITS “allows \n[a] Network Customer to integrate, economically dispatch and regulate its current and \nplanned Network Resources to serve its Network Load in a manner comparable to that in \nwhich each Transmission Owner utilizes the Transmission System to serve its Native Load \nCustomers.  [NITS] also may be used by the Network Customer to deliver economy energy \npurchases to its Network Load from non-designated resources on an as-available basis \nwithout additional charge.”143  \nThe split in PJM, in which NITS serves load within PJM and PTP Transmission \nService serves load beyond PJM’s borders, is the natural outgrowth of PJM’s formation.  \nIn the 1997 order on PJM’s transition to an Independent System Operator, the Commission \nnoted that it is important that: \n[T]he [PJM] tariff was designed to replicate the network integration \nservice each utility had historically provided itself within the \nconfines of its individual service area.  By allowing transmission \nservice customers to integrate resources across eight utility systems, \nthe PJM Transmission Tariff will permit customers to obtain a \ntransmission service that goes beyond the requirements of the Open \nAccess Rule. . . . We believe that . . . a single transmission service \ncharge for multi-system use, in conjunction with its congestion \npricing proposal, will foster the creation of more competitive bulk \npower markets, help to ration constrained capacity among \ncompeting transactions on the basis of price, and simplify the \n \n142 Transmission Access Pol’y Study Grp. v. FERC, 225 F.3d 667, 725 (D.C. Cir. 2000).   \n143 Tariff, Part III, Preamble; Transmission Service Department, PJM Manual 2: Transmission Service \nRequest, PJM Interconnection, L.L.C., section 1.1.2 (Jan. 22, 2026), https://www.pjm.com/-\n/media/DotCom/documents/manuals/m02.pdf."},{"page":55,"startToken":14667,"endToken":14951,"text":"50 \nreassignment of transmission capacity.  This is consistent with our \npolicy goals in the Open Access Rule.144  \nPJM’s illustrative Tariff provision offers a balanced and conservative approach that \nenables Eligible Customers to take transmission service that is less than NITS on behalf of \nCo-Located Load, while also recognizing that permitting Eligible Customers to take non-\nNITS transmission services on behalf of Co-Located Load may pose additional reliability \nand operational risks to the PJM Region.     \nB. \nFinancial Penalty for Unreserved Use of the PJM Transmission System  \nPJM supports a penalty for unreserved use in addition to the disqualification and \npause-in-service rules discussed above.  As PJM has previously noted, an operational \npenalty for unreserved use is “not intended to operate as a punishment for a tariff \nviolation.”145  PJM expects that many, if not most, Eligible Customers taking service on \nbehalf of a Co-Located Load could foreseeably elect to absorb financial penalties for \nunreserved use rather than follow Curtailment or Load Shed procedures or avoid \nmisoperation of the protective technology or system.  Thus, in PJM’s view, financial \npenalties, alone, are not sufficient to incentivize Eligible Customers to comply with Load \nShed, Curtailment, and control technology and protection system obligations.  As such, \nPJM has additionally proposed the disqualification and pause-in-service remedial actions \ndiscussed above.   \nWith regard to the financial penalty, PJM intends to work with the PJM \nTransmission Owners to explore such a financial penalty. As such, PJM has “reserved” \nillustrative Tariff, Part XI, Subpart A, section 705.7 and illustrative Tariff, Part XI, Subpart \n \n144 Pa.-N.J.-Md. Interconnection, 81 FERC ¶ 61,257, at 62,241 (footnote omitted). \n145 PJM Interconnection, L.L.C., 134 FERC ¶ 61,040, at P 8 (2011) (footnote omitted)."},{"page":56,"startToken":14951,"endToken":14992,"text":"51 \nB, section 713.8 in anticipation of the development of financial penalty provisions.  \nUnreserved use penalties should apply to Eligible Customers taking Firm Contract Demand \nTransmission Service, Non-Firm Contract Demand Transmission Service, or Interim NITS \non behalf of Co-Located Load."},{"page":57,"startToken":14992,"endToken":15067,"text":"52 \nQuestion 6:  \nWhat is the appropriate penalty charge or other remedial action that PJM should \ntake to address any unreserved use of the PJM transmission system for an Eligible \nCustomer taking Non-Firm Contract Demand transmission service on behalf of a \nCo-Located Load? \nResponse to Question 6:  \n \nSee Response to Question 5 above, which addresses penalty charges and remedial \nactions applicable to Non-Firm Contract Demand Transmission Service, Firm Contract \nDemand Transmission Service, and Interim NITS."},{"page":58,"startToken":15067,"endToken":15371,"text":"53 \nQuestion 7:  \nWhat are the appropriate mechanisms for an anti-toggling feature for the Firm \nContract Demand transmission service, including the appropriate minimum service \nperiod and minimum notice period for discontinuing or modifying the level of \nservice? \nResponse to Question 7: \n \nThe Show Cause Order found that the terms and conditions for taking new Firm \nContract Demand Transmission Service should include a mechanism that prevents a \ntransmission customer from switching from Firm to Non-Firm Contract Demand \nTransmission Service so as to avoid charges associated with PJM’s capacity market.146  To \nimplement this directive, PJM includes a two-pronged approach.  One, illustrative Tariff, \nPart XI, Subpart B, section 709.4 provides an anti-toggling mechanism to prevent \ntransmission customers from switching between the Firm and Non-Firm Contract Demand \nTransmission Services, by providing that the portion of the Co-Located Load served by \nFirm Contract Demand Transmission Service is not eligible to be served by Non-Firm \nContract Demand Transmission Service “for five years following the effective date of the \nService Agreement for Contract Demand Transmission Service.”   \nConversely, there is no prohibition on any portion of the Co-Located Load served \nby Non-Firm Contract Demand Transmission Service from being served by Firm Contract \nDemand Transmission Service in future years.  This is reasonable, as Firm Contract \nDemand Transmission Service is a higher quality of service and presents less risk to system \n \n146 Show Cause Order at P 213 (“[W]e find that it is just and reasonable that the terms and conditions for \ntaking the new Firm Contract Demand transmission service must prevent transmission customers from \nswitching between the Firm Contract Demand and Non-Firm Contract Demand transmission services, i.e., \nmust include an anti-toggling mechanism.  Otherwise, Eligible Customers taking transmission service on \nbehalf of Co-Located Loads may attempt to switch between the two new transmission services based on \nexpected capacity market conditions.”)."},{"page":59,"startToken":15371,"endToken":15729,"text":"54 \nreliability and fewer operational complexities for PJM’s dispatchers to manage.  That is, \nbecause PJM will plan the Transmission System to ensure the Firm Contract Demand \nTransmission Service MW quantity and PJM will consider such amount in resource \nadequacy planning,147 the system will be designed to serve the Firm Contract Demand \nTransmission Service, minimizing much of the system reliability risks presented by Non-\nFirm Contract Demand Transmission Service. \nHowever, the foregoing limitations will “not apply in the event of (i) a physical \nchange to the Co-Located Generating Facility that would materially and permanently alter \nthe [MW] level dedicated to the Co-Located Load; or (ii) a physical change to the \nCo-Located Load that would materially and permanently alter the [MW] level of its gross \ndemand.”148  These exceptions are necessary to ensure that, should an Eligible Customer \nor Co-Located Load materially and permanently change either the generation capacity or \nthe load on a gross demand basis, the Tariff provides flexibility to determine whether  Firm \nor Non-Firm Contract Demand Transmission Service should be taken for the new \nincremental portion.  \nTwo, the 42-month notice of termination also acts as an anti-toggling device in a \nmanner similar to the five-year commitment period applicable to the Fixed Resource \nRequirement alternative in PJM’s capacity market.149  This notice period also is identical \n \n147 Illustrative Tariff, Part XI, Subpart B, section 708(b) (“Firm Contract Demand Transmission Service is \nfor the transfer of capacity and energy to an Eligible Customer on behalf of a designated Co-Located Load, \nup to a defined, predetermined megawatt level of transmission service as requested by the Eligible Customer \nand confirmed by the Transmission Provider, using capacity and energy procured by the Transmission \nProvider[.]”). \n148 Illustrative Tariff, Part XI, Subpart B, section 709.4. \n149 See Reliability Assurance Agreement Among Load Serving Entities in the PJM Region, Schedule 8.1.C, \nsection C.2 (“RA Agreement”) (“An FRR Entity may terminate its election of the FRR Alternative effective \nwith the commencement of any Delivery Year following the minimum five Delivery Year commitment by \nproviding written notice of such termination to the Office of the Interconnection no later than two months"},{"page":60,"startToken":15729,"endToken":15942,"text":"55 \nto the one used for NITS agreements,150 and recognizes that PJM is incorporating these \nloads in the capacity market, and has procured capacity on their behalf.  Allowing Co-\nLocated Loads to avoid capacity charges that have been incurred on their behalf by \nterminating their agreement prematurely would unreasonably shift those costs to other \nloads in the PJM Region and contrary to Commission precedent.151  \n \n \n \n \nprior to the Base Residual Auction for such Delivery Year.  An FRR Entity that has terminated its election of \nthe FRR Alternative shall not be eligible to re-elect the FRR Alternative for a period of five consecutive \nDelivery Years following the effective date of such termination.”).  \n150 See Tariff, Part I, section 2.5(2) (“An incumbent Network Customer seeks to terminate its service and no \nsuccessor Network Customer exists, in which case the incumbent must provide PJM with forty-two (42) \nmonths’ notice prior to the commencement of a Delivery Year, subject to receiving all necessary regulatory \napprovals for such termination, if any[.]”). \n151 See Duquesne Light Co., 122 FERC ¶ 61,039, at P 86 (2008) (“[W]e conclude that Duquesne’s obligations \nto pay Locational Reliability Charges, under the RA Agreement, became set at such time as Duquesne’s loads \nwere included by PJM in its auction parameters.”)."},{"page":61,"startToken":15942,"endToken":16223,"text":"56 \nQuestion 8:  \nWhat interconnection requirements and operational practices are necessary for \nspecial protection schemes to maintain system reliability (e.g. the need for full \nredundancy of such schemes) in the event that a Co-Located Load itself or its \nassociated generator trips offline? \nResponse to Question 8: \nPJM understands the “special protection schemes” referenced in Question 8 to \nmean the “necessary control technology and protection systems” that Eligible Customers \ntaking Interim NITS and Non-Firm Contract Demand Transmission Service on behalf of \nCo-Located Load will need to outline in their respective Service Agreements.   \nSimilar to the current requirement to include any agreed upon “necessary control \ntechnologies and protection systems” in an executed, or requested to be filed, unexecuted \nGIA, Service Agreements for Interim NITS and Non-Firm Contract Demand Transmission \nService will each outline the specific necessary control technology and protection schemes, \nincluding for example a RAS, required to ensure the reliability and stability of PJM’s \nTransmission System.   \nNERC has established various reliability standard requirements for the various \nforms of control technologies that may be relied upon for grid stability, which Eligible \nCustomers are expected to adhere to.  For example, RAS, which PJM and NERC have also \nhistorically referred to as Special Protection Systems,152 is among the “control technology \nand protection systems” that PJM may deem necessary for an Eligible Customer to have.  \nPJM includes an illustrative definition of RAS in Attachment A, which is explained in \nSection IV further below.   \n \n152 In 2014, NERC replaced references to Special Protection Systems with the term RAS.  “Remedial Action \nScheme” Definition Development, North American Electric Reliability Corporation (June 2014), \nhttps://www.nerc.com/globalassets/standards/projects/2010-05.2/faq_ras_definition_0604_final.pdf."},{"page":62,"startToken":16223,"endToken":16559,"text":"57 \nThe interconnection requirements and operational practices necessary for necessary \ncontrol technologies and protection systems to maintain system reliability in the event that \na Co-Located Load or associated generator trips offline will be set forth in the PJM \nManuals and, as applicable, NERC reliability standards.   \nThe NERC reliability standards form baseline interconnection requirements and \noperational practices, while PJM, through its Manuals, provides additional details and, at \ntimes, more stringent standards for RAS.  The requirements set forth in NERC reliability \nstandards and PJM Manuals are extensive.  An illustrative, non-exhaustive list of \ninterconnection requirements and operational practices that ensure that RAS maintain \nsystem reliability includes, but is not limited to: \n• Requirements and measures set forth in NERC PRC-012 associated with \nplacing a new or functionally modified RAS in service to ensure that RAS \ndo not introduce unintentional or unacceptable reliability risks to the Bulk \nElectric System, including the requirement that operational performance \nanalyses are properly conducted and verify that RAS operation was \ntriggered correctly.  PJM Manual 3, section 1.7 expands on how PJM will \nreview RAS to ensure that sufficient analysis, notice, documentation, and \ntraining on these RAS are established ahead of implementation and that \nNERC PRC-012-2 requirements are met.153   \no RAS are evaluated to ensure, for example, full redundancy of critical \ncomponents, multiple independent tripping paths, and that RAS settings \nand operation avoids adverse interactions with other RAS and \nprotection and control systems. \n• PJM Manual 3, section 1.8 sets forth RAS operating criteria and the actions \nthat PJM, the Transmission Owner, and the Generation Owner will take \nwhen PJM’s Energy Management System indicates that a simulated N-1 \ncontingency will result in an overload on the facility that can be mitigated \nby an RAS.154  Due to the redundancy built into each RAS, PJM considers \n \n153 Transmission Operations, PJM Manual 03: Transmission Operations, PJM Interconnection, L.L.C., § 1.7 \n(Rev. 69, Nov. 20, 2025), https://www.pjm.com/-/media/DotCom/documents/manuals/m03.pdf (“PJM \nManual 3”). \n154 PJM Manual 3, section 1.8.."},{"page":63,"startToken":16559,"endToken":16790,"text":"58 \nthe loss of a facility and the subsequent failure of the associated RAS to be \na double contingency.155 \n• PJM Manual 7, section 17.2 sets forth installation requirements that govern \nRAS, particularly in light of the complexity of the scheme and the \nconsequences of RAS misoperation.   \n• NERC PRC-017 requires RAS maintenance and testing to ensure that RAS \nare properly designed, meet performance requirements, and are coordinated \nwith other protection systems, as well as to ensure that maintenance and \ntesting programs are developed and that misoperations are analyzed and \ncorrected. \nImportantly, while interconnection requirements and operational practices are in \nplace to decrease the risk of relying on necessary control technologies and protection \nsystems, the decision to employ necessary control technologies and protection systems is \nnot taken lightly and requires weighing the complexity of the scheme and the risk and \nconsequences of misoperation against the potential benefits.  Necessary control \ntechnologies and protection systems, which may include RASs, should not be installed as \na substitute for good system design or operating practices.  Their implementation is \ngenerally limited to temporary conditions involving the outage of critical equipment.156  \n \n \n \n \n155 PJM Manual 3, section 1.8. \n156 System Planning Division Transmission Planning Department, PJM Manual 07: PJM Protection \nStandards, PJM Interconnection, L.L.C., § 17.2 (Rev. 05, Sep. 25, 2025), https://www.pjm.com/-\n/media/DotCom/documents/manuals/m07.pdf (“PJM Manual 7”)."},{"page":64,"startToken":16790,"endToken":17101,"text":"59 \nQuestion 9: \nWhat communications, alarm, SCADA452 or other requirements are necessary for \nPJM to monitor Co-Located Load transmission system demand status; ensure that \nrelay settings are consistent with special protection scheme design; and inform \nsystem operator action, in order to limit withdrawals from Eligible Customers on \nbehalf of Co-Located Load that exceed the amount of Firm or Non-Firm Contract \nDemand transmission services? \nResponse to Question 9: \nPJM understands this question to be focused on the requirements currently in place \nand that PJM will need to put into place in order to: \n• Monitor Co-Located Load Transmission System demand status;  \n• Ensure relay settings are consistent with special protection scheme designs, \nas shown in illustrative Tariff, Part XI, Subpart A, section 705.6 and \nillustrative Tariff, Part XI, Subpart B, section 713.7; and  \n• Otherwise inform system operator action in order to limit withdrawals from \nEligible Customers on behalf of Co-Located Load that exceed Contract \nDemand Transmission Services or Interim NITS.     \nFirst, to monitor the status of the demand placed on PJM’s Transmission System by \nCo-Located Load in order to ensure adequate reliability and stability of the Transmission \nSystem, PJM will need to develop telemetry requirements and require Co-Located Load to \nmeet such requirements in order to monitor Co-Located Load’s use of the Transmission \nSystem.  PJM will need to develop data exchange and metering requirements for Co-\nLocated Load that may be similar to those currently applicable to generation, as set forth \nin PJM Manual 14D, section 4.157  The kind of requirements PJM will need to develop \ninclude, for example, specific data paths, networking requirements, and measurement types \nand measurement points for any given topology or generation type.  Because the different \n \n157 Operations Planning Division, PJM Manual 14D: Generator Operational Requirements, PJM \nInterconnection, \nL.L.C., \n§ \n4 \n(Rev. \n70, \nDec. \n17, \n2025), \nhttps://www.pjm.com/-\n/media/DotCom/documents/manuals/m14d.pdf."},{"page":65,"startToken":17101,"endToken":17403,"text":"60 \ntypes of services being made available to Eligible Customers taking service on behalf of \nCo-Located Load are prioritized differently, PJM would need to develop the capability to \nmore granularly differentiate, at a minimum, between NITS and Interim NITS, and \nbetween Firm Contract Demand Transmission Service and Non-Firm Contract Demand \nTransmission Service.  Eligible Customers, acting on behalf of Co-Located Load, would \nneed to take these different forms of transmission service on different feeders, or cables \nleaving substations, to ultimately serve the Co-Located Load. \nSecond, to adequately ensure that relay settings are consistent with the design of \nthe necessary control technologies and protection systems (e.g., RAS), as agreed to by PJM \nand set forth in each Service Agreement for Interim NITS and Non-Firm Contract Demand \nTransmission Service put into place in order for an Eligible Customer to serve Co-Located \nLoad, PJM will need to develop requirements and identify any relevant NERC rules.158   \nIn addition, Transmission Owners will need to be heavily involved in ensuring that \nnecessary control technology and/or protective system is properly designed and, where \nappropriates, operates as intended.   \nGiven that the complexity introduced by the necessary control technology and \nprotection systems (e.g., RAS) introduces significant risks,159 including possible failure to \ncommunicate material information about such protective technology or system, the \nillustrative Tariff includes technical requirements that must be in place prior to the \ncommencement of service, including that the Eligible Customer “is staffed with PJM \n \n158 NERC requirements already set forth requirements that ensure relay settings are consistent with the design \nof the RAS.  An RAS must comply with PJM Manual 3, sections 1.7 and 1.8; PJM Manual 7, section 17; and \nall applicable NERC requirements; and the new illustrative Tariff, sections 705.5 and 713.6. \n159 See Wharton Aff. ¶¶ 16, 22 & 23."},{"page":66,"startToken":17403,"endToken":17603,"text":"61 \nCertified Operators pursuant to PJM Manual 40” and has the “ability to receive voice and \nelectronic signals from [PJM].”160 \nThird, as discussed above, PJM will need to rely on developing telemetry to remain \ninformed of unreserved use by Eligible Customers taking Contract Demand Transmission \nService or Interim NITS.  PJM is still determining the scope of the tools and requirements \nthat will need to be developed in order to limit withdrawals that exceed reserved use. \nIn addition to developing new requirements, as Senior Director of Forward Market \nOperations for PJM Mr. Horger testifies, PJM will need to make changes to core Markets \nand Operations systems in order to incorporate the information provided by Eligible \nCustomers and Co-Located Load, as needed, to ensure reliability and stability of the PJM \nTransmission System.161  Changes to these systems will necessarily be dependent on \nvendor availability, the speed with which the system changes can be designed, and the \ninteraction of these requested changes with other competing priorities, including system \nchanges to implement other Commission-directed initiatives.162   \n \n \n \n160 See Illustrative Tariff, Part XI, Subpart A, section 702.4; id., Part XI, Subpart B, section 710.4. \n161 Horger Aff. ¶ 16. \n162 Horger Aff. ¶ 16."},{"page":67,"startToken":17603,"endToken":17687,"text":"62 \nQuestion 10:  \nWhat other eligibility requirements, e.g., interconnection requirements or \noperational practices, are necessary for an Eligible Customer to take Firm \nContract Demand or Non-Firm Contract Demand transmission service on behalf \nof Co-Located Load? \nResponse to Question 10:  \nPlease see PJM’s above answers to Questions 1 and 2, as well as Section III below \ndiscussing Interim NITS, which, among other non-rate terms and conditions, discusses \ninterconnection requirements or operational practices that PJM envisions would be \nnecessary to implement these new transmission services."},{"page":68,"startToken":17687,"endToken":17957,"text":"63 \nQuestion 11:  \nWhat are the appropriate procedures to govern the circumstances under which PJM \ncurtails an Eligible Customer taking the interim, non-firm transmission service, \nFirm Contract Demand transmission service, or Non-Firm Contract Demand \ntransmission service on behalf of a Co-Located Load during emergency \nprocedures? In particular, can PJM shed all or a portion of a Co-Located Load on \nwhose behalf an Eligible Customer takes Non-Firm Contract Demand transmission \nservice while continuing to serve all or a portion of a Co-Located Load on whose \nbehalf an Eligible Customer takes Firm Contract Demand transmission service? \nResponse to Question 11:   \nQuestion 11 focuses on Curtailment of Eligible Customers taking transmission \nservice on behalf of a Co-Located Load “during emergency procedures,” or to avoid the \nneed to implement escalating emergency procedures, which PJM understands to mean \n“Emergency Operations,” as set forth in Tariff, Attachment K-Appendix, section 8 and PJM \nManual 13.   \nPJM has included, in the illustrative Tariff provisions and Service Agreements, \nprovisions that address Curtailment procedures during Emergency Operations.   \nA. \nNew Curtailment Procedures Applicable to Eligible Customers Taking \nService on Behalf of a Co-Located Load During Emergency Operations \nUnder the illustrative Tariff provisions, Interim NITS and Non-Firm Contract \nDemand Transmission Service will be curtailed before Firm Contract Demand \nTransmission Service and NITS.  The Transmission Provider may also curtail Interim NITS \nor Non-Firm Contract Demand Transmission Service prior to dispatching the Pre-\nEmergency Load Response Program as further set forth in the PJM Manuals, or in response \nto a transfer capability shortage as a result of system reliability conditions.  This effectively \nmeans that Interim NITS and Non-Firm Contract Demand Transmission Service will be"},{"page":69,"startToken":17957,"endToken":18232,"text":"64 \ncurtailed before Demand Response resources are called upon to reduce load.163  For \npurposes of Curtailment, Firm Contract Demand Transmission Service will be treated as \nthe equivalent of NITS.164   \nTo the extent that a system contingency exists on the Transmission Provider’s \nTransmission System and the Transmission Provider determines that it is necessary for the \nTransmission Owners and an Eligible Customer taking Interim NITS, Firm Contract \nDemand Transmission Service, or Non-Firm Contract Demand Transmission Service to \nshed load, the Eligible Customer and the affected Transmission Owner(s) must shed load \nin accordance with previously established procedures under the relevant Service \nAgreement for Interim NITS (Attachment F-3A) or for Contract Demand Transmission \nService (Attachment F-4). \nConsistent with PJM’s provision of NITS,165 PJM is reserving the right, consistent \nwith Good Utility Practice and on a not unduly discriminatory basis, to curtail Interim \nNITS, Firm Contract Demand Transmission Service, and/or Non-Firm Contract Demand \nTransmission Service without liability on PJM’s part “for the purpose of making necessary \nadjustments to, changes in, or repairs on its lines, substations and facilities,” and in cases \nwhere the continuance of Interim NITS, Firm Contract Demand Transmission Service, \nand/or Non-Firm Contract Demand Transmission Service would endanger persons or \nproperty.166  PJM will give the Eligible Customer as much advance notice as is practicable \nin the event of such Curtailment.    \n \n163 Illustrative Tariff, Part XI, Subpart A, section 705.2; id., Part XI, Subpart B, section 713.4. \n164 Illustrative Tariff, Part XI, Subpart A, section 713.3. \n165 Tariff, section 33.7. \n166 Illustrative Tariff, Part XI, Subpart A, section 705.4, id., Part XI, Subpart B, section 713.5."},{"page":70,"startToken":18232,"endToken":18491,"text":"65 \nB. \nCurtailment of an Eligible Customer Taking Both Firm and Non-Firm \nContract Demand Transmission Service on Behalf of a Co-Located Load \nDuring Emergency Operations \nQuestion 11 asks, “in particular, whether PJM can shed all or a portion of a Co-\nLocated Load on whose behalf an Eligible Customer takes Non-Firm Contract Demand \ntransmission service while continuing to serve all or a portion of a Co-Located Load on \nwhose behalf an Eligible Customer takes Firm Contract Demand transmission service.”  \nPJM understands the Commission to be asking whether PJM has the operational capability \nto appropriately prioritize Load Shed based on level of transmission service when an \nEligible Customer serves a Co-Located Load under both a Firm Contract Demand \nTransmission Service Agreement and a Non-Firm Contract Demand Transmission Service \nAgreement.   \nFor example, if a 15-MW Co-Located Load is served by an Eligible Customer with \na Firm Contract Demand Transmission Service Agreement for 5 MWs and a Non-Firm \nContract Demand Transmission Service for 10 MWs, can PJM operationally differentiate \nbetween and appropriately prioritize the 5 MWs of Firm Contract Demand Transmission \nService and the 10 MWs of Non-Firm Contract Demand Transmission Service?  Currently, \nPJM’s core Markets and Operations Systems including modifying the Intermediate and \nReal-Time Security Constrained Economic Dispatch (IT SCED and RT SCED), \nDay-Ahead Market software, and PJM dispatch tools, do not automate Curtailment of Non-\nFirm Contract Demand Transmission Service (or Interim NITS) before Firm Contract \nDemand Transmission Service.  Currently, the system does not differentiate between \ndifferent types of transmission service being used to serve load within PJM, because all"},{"page":71,"startToken":18491,"endToken":18756,"text":"66 \nload within PJM is currently served by NITS.167  Thus, as an initial matter, as Mr. Horger \nnotes, core systems, including software changes, would need to be implemented to enable \nthis level of granularity when shedding an Eligible Customer’s Co-Located Load being \nserved by two different levels of transmission service.168  Assuming that these core system \ndesign changes can be and are implemented, Eligible Customers taking transmission \nservice on behalf of Co-Located Load, would need to take these different forms of \ntransmission service on different feeders, or cables leaving substations, to ultimately serve \nthe Co-Located Load.169  PJM would need to develop these requirements, as outlined, \nabove, in PJM’s response to Question 9. \nIII. \nINTERIM NETWORK INTEGRATION TRANSMISSION SERVICE \nThe Commission in the Show Cause Order recognized that Co-Located Loads \ndesire a way to more rapidly interconnect to the PJM Transmission System and begin \noperation.170  The Commission ordered PJM to develop a new service transitional to \nobtaining NITS that would allow new Co-Located Load to withdraw electricity from the \nPJM Transmission System earlier than may be otherwise achievable if these loads were \nrequired to await completion of any necessary Network Upgrades for NITS.171  Therefore, \nPJM has developed a new, transitional Interim NITS that will accelerate the time needed \nfor an Eligible Customer to start taking service on behalf of a Co-Located Load than \notherwise would be required to provide a Co-Located Load with NITS equivalent to that a \n \n167 See Abdulsalam Aff. ¶ 7. \n168 See Horger Aff. ¶ 16. \n169 See Abdulsalam Aff. ¶ 11. \n170 Show Cause Order at P 200.  \n171 Id."},{"page":72,"startToken":18756,"endToken":19021,"text":"67 \nNetwork Load would receive.  This service will be interim until such time that the \nnecessary Network Upgrades, in order to serve the Co-Located Load as full Network Load, \nare placed in service and operational.  PJM has attached illustrative Tariff language setting \nforth non-rate terms and conditions for this service in Attachment A, Part XI, Subpart A, \nsections 700-707. \nHowever, the Briefing Questions above do not specifically focus on the non-rate \nterms and conditions for Interim NITS.  Nonetheless, the record in this proceeding could \nbenefit from PJM detailing non-rate terms and conditions applicable to this new \ntransmission service type for Eligible Customers willing and able to limit energy \nwithdrawals prior to their NITS being available (because the necessary transmission \nfacilities are not completed).  Accordingly, PJM includes this additional section to describe \nthose rules. \nA. \nProvision of Interim NITS and Nature and Scope of Service \nGenerally speaking, the non-rate terms and conditions for Interim NITS are the \nsame as for NITS,172 with modifications necessary to implement the interim and non-firm \nnature of the service.  As envisioned by the Show Cause Order, Interim NITS is designed \nto merely be a transition service until the system can support the customer’s NITS request.  \nThus, upon request to PJM and as determined through appropriate studies of the \nTransmission System by PJM and the affected Transmission Owner(s), Eligible Customers \nmay take, on behalf of a Co-Located Load, Interim NITS—a non-firm, interruptible \nnetwork transmission service until such time as the Network Upgrades necessary to provide \n \n172 Compare illustrative Tariff, Part XI, Subpart A, sections 700-07, with Tariff, Part III."},{"page":73,"startToken":19021,"endToken":19357,"text":"68 \nNITS are complete.173  Once the necessary Network Upgrades are completed, Interim NITS \ncustomers will automatically convert to NITS customers.174  An Eligible Customer \nreceiving Interim NITS will receive non-firm interruptible transmission service for the \ndelivery of energy to serve Co-Located Load.175   \nB. \nInitiating Service \nIllustrative section 702 in Attachment A details how an Eligible Customer seeking \nInterim NITS on behalf of a Co-Located Load will initiate service requests.  Given that \nInterim NITS is transitory before full NITS is available, an Eligible Customer must also be \nrequesting NITS176 and will need to pay an study fee “in addition to the study fee required \nunder an Application for Network Integration Transmission Service under Tariff, Part III, \nsection 32.2.”177  Upon receipt of the request and study fee, PJM, in consultation with the \naffected Transmission Owner(s) and based on the results of appropriate studies, will \ndetermine the amount of Interim NITS that can be reliably provided.178   \nAs with NITS,179 prior to obtaining Interim NITS, the Eligible Customer must meet \ncertain conditions precedent and meet the appropriate technical requirements.  Specifically, \namong several enumerated conditions precedent, the language would require the Eligible \nCustomer to comply with the provisions of the “PJM Credit Policy” set forth in Tariff, \n \n173 Illustrative Tariff, Part XI, Subpart A, sections 701.1, 701.4. \n174 Illustrative Tariff, Part XI, Subpart A, section 701.1. \n175 Illustrative Tariff, Part XI, Subpart A, section 701.2.  Similar restrictions on third-party sales as detailed \nin response to Question 1 above will also apply to Interim NITS.  See illustrative Tariff, Part XI, Subpart A, \nsection 701.3; supra section II, Response to Question 1. \n176 Illustrative Tariff, Part XI, Subpart A, section 702.2 (“[A]n Eligible Customer shall not apply for Interim \nNetwork Integration Service without applying for Network Integration Transmission Service.”). \n177 Illustrative Tariff, Part XI, Subpart A, section 702.2. \n178 Illustrative Tariff, Part XI, Subpart A, section 702.3. \n179 See Tariff, Part III, sections 29.1, 29.3."},{"page":74,"startToken":19357,"endToken":19644,"text":"69 \nAttachment Q; “certify[y] that it is willing and able to limit energy withdrawals from the \nTransmission System when requested by [PJM];” and “otherwise execute, if necessary, and \ncomply with the PJM Governing Agreements.”180   \nAs for the necessary technical requirements, the Eligible Customer must (i) install \n“necessary hardware and software to limit energy withdrawals, including metering \nequipment;” (ii) provide PJM an operational contact and backup contact that is to be \navailable 24 hours a day and 7 days a week, (iii) certify that it “is staffed with PJM Certified \nOperators pursuant to PJM Manual 40;” (iv) demonstrate “its ability to receive voice and \nelectronic signals from [PJM];” (v) demonstrate that it “has operational control to respond \nto operating instructions from [PJM] to reduce or disconnect the Co-Located Load within \n5 minutes or as specified in PJM Manuals;” and (vi) demonstrate that it “has operational \ncontrol of the necessary control technologies and protection systems set forth in \nSection 705, as applicable.”181  The illustrative Tariff also provides that the Eligible \nCustomer “shall be solely responsible” for constructing, maintaining, and operating all \nfacilities on its side of the Delivery Point.182 \nC. \nDesignation of Co-Located Load \nIllustrative Attachment A, section 703 would require that an Eligible Customer \ntaking Interim NITS designate the individual Co-Located Load on behalf of which the \nEligible Customer is taking Contract Demand Transmission Service, whether Firm, Non-\nFirm, or both.183  Given that the provision of Interim NITS is premised on how the \n \n180 Illustrative Tariff, Part XI, Subpart A, section 702.1. \n181 Illustrative Tariff, Part XI, Subpart A, section 702.4. \n182 Illustrative Tariff, Part XI, Subpart A, section 702.5. \n183 Illustrative Tariff, Part XI, Subpart A, section 703.1."},{"page":75,"startToken":19644,"endToken":19921,"text":"70 \nTransmission System can handle the special circumstances of the Co-Located Load \narrangement prior to the completion of necessary facilities, the Co-Located Load \narrangement cannot change during the term of the Interim NITS without discussion and \npossible further studies with PJM.  Thus, section 703.2 provides that “[p]rior to the Service \nCommencement Date of Network Integration Transmission Service, if an Eligible \nCustomer designates a new Co-Located Load, or increases the size of the designated Co-\nLocated Load, the new Co-Located Load shall be studied pursuant to a new Application.”   \nFurther, in order to maintain operational visibility by PJM of the system and thus \nto ensure reliability, Eligible Customers shall have an ongoing obligation to provide the \nTransmission Provider with timely written or electronic notice of material changes in the \ndemand characteristics of the Co-Located Load and the supply characteristics of the \nCo-Located Generating Facility.184  Given that each control technology or protection \nscheme will be designed based on the specific circumstances and technical arrangements \nof each Co-Located Load arrangement, such a material change could have deleterious \neffects on the efficacy of the necessary control technologies and protection schemes \nassociated with a Service Agreement for Interim NITS and PJM’s ability to reliably operate \nthe system.  Thus, failure to timely inform the PJM of such material changes “may \nconstitute a breach of the Eligible Customer’s Service Agreement.”185 \nD. \nStudy Procedures for Interim NITS  \nTo assess whether the Transmission System can accommodate a request for Interim \nNITS, PJM will determine whether additional studies beyond what is required to evaluate \n \n184 Illustrative Tariff, Part XI, Subpart A, section 703.3. \n185 Illustrative, Part XI, Subpart A, section 703.3."},{"page":76,"startToken":19921,"endToken":20205,"text":"71 \nthe Eligible Customer’s request for NITS is needed for Interim NITS.186  If additional \nstudies are deemed necessary, PJM will inform the Eligible Customer and will provide \nthem with an Application and Studies Agreement in which the Eligible Customer will agree \nto reimburse PJM for the cost of the required studies.187  The Eligible Customer must \nexecute the Application and Studies Agreement within fifteen days and provide the study \nfee, otherwise the Application will be deemed withdrawn and the study fee will be returned \nwith interest.188  \nE. \nLoad Shedding and Curtailments  \nAs envisioned by the Show Cause Order, Interim NITS is premised on the notion \nthat the Co-Located Load is willing and able to limit its energy withdrawals from the \nTransmission System prior to NITS being available.189  Accordingly, PJM developed Load \nShedding and Curtailment provisions applicable to Interim NITS in illustrative Tariff, Part \nXI, Subpart A, section 705.  In addition, Load Shed and Curtailment procedures applicable \nto Interim NITS are described above, in response to Question 11. \nUnder the provisions set forth in the illustrative Tariff, prior to the Service \nCommencement Date, an Eligible Customer seeking to take Interim NITS on behalf of a \nCo-Located Load would need to demonstrate its ability to comply with Load Shedding and \nCurtailment procedures as directed by PJM.190  Whenever ordered by PJM, an Eligible \nCustomer must implement any Load Shedding or Curtailment directive, including as \n \n186 Illustrative Tariff, Part XI, Subpart A, section 704.1.  \n187 Illustrative Tariff, Part XI, Subpart A, section 704.1. \n188 Illustrative Tariff, Part XI, Subpart A, sections 704.1, 704.2. \n189 Show Cause Order at P 178. \n190 Illustrative Tariff, Part XI, Subpart A, section 705.1."},{"page":77,"startToken":20205,"endToken":20494,"text":"72 \nnecessary responding to any real-time instruction to reduce or curtail load within five \nminutes of the directive.  PJM reserves the right to curtail Interim NITS to maintain system \nreliability,191 but any and all Curtailments will be on a non-discriminatory basis.192  Load \nShed instructions will be directed toward Eligible Customers in a manner that is consistent \nwith previously established procedures under the Service Agreement for Interim NITS, and \nInterim NITS will be curtailed before Firm Contract Demand Transmission Service and \nNITS and PJM may curtail Interim NITS prior to initiating a pre-emergency event.193  PJM \nmay also instruct Eligible Customers taking Interim NITS to shed load in accordance with \npreviously established procedures under the Service Agreement for Interim NITS \n(Attachment F-3A).194   \nAs discussed, as part of implementing the key principles that (1) the services are \ndesigned to serve loads that are “willing and able to control their withdrawals from the \ntransmission system;”195 and (2) the services are designed to allow PJM to maintain system \nreliability, PJM is requiring Eligible Customers taking Interim NITS to work with PJM and \naffected Transmission Owners to “establish necessary control technologies and protection \nsystems, which may include a Remedial Action Scheme, for each Service Agreement for \nInterim [NITS].”196   \nPJM’s response to Question 5, above, discusses the processes and procedures for \nestablishing these schemes for limiting the Co-Located Load’s withdrawal of energy from \n \n191 Illustrative Tariff, Part XI, Subpart A, section 705.5.  \n192 Illustrative Tariff, Part XI, Subpart A, section 705.1. \n193 Illustrative Tariff, Part XI, Subpart A, section 705.2. \n194 Illustrative Tariff, Part XI, Subpart A, section 705.3. \n195 Show Cause Order at P 204. \n196 Illustrative Tariff, Part XI, Subpart A, section 705.5."},{"page":78,"startToken":20494,"endToken":20776,"text":"73 \nthe Transmission System and for protecting the Transmission System from the adverse \noperational effects of unscheduled energy withdrawals.  As discussed, above, in PJM’s \nresponse to Question 5, Eligible Customers may be temporarily paused and subsequently \ndisqualified from taking Interim NITS following two misoperations of any necessary \ncontrol technology or protection system.  Likewise, as explained, above, in response to \nQuestion 5, an Eligible Customer that fails to respond to established Load Shedding and \nCurtailment procedures on one occasion will be disqualified from taking Interim NITS.197  \nTo the extent an Eligible Customer is disqualified from taking Interim NITS, the Eligible \nCustomer—having demonstrated that it is not willing (because it did not follow instruction) \nor able (because the protection scheme failed twice) to limit energy withdrawals—must \nwait until the facilities necessary to provide NITS are completed before it can resume \nservice to this Co-Located Load.198 \nF. \nRates and Charges for Interim NITS  \nConsistent with the allocation of rights between PJM and PJM Transmission \nOwners,199 PJM expects the PJM Transmission Owners to brief a transmission rate \nappropriate for Interim NITS.   \nHowever, Eligible Customers will be assessed other rates in addition to \ntransmission service rates, and PJM has authority to institute such non-transmission-related \nrates.  Thus, section 706 provides that PJM would assess:   \n• administrative services charges under Schedule 1A, Schedule 9, and Schedule \n10 of the Tariff, consistent with the charges assessed to loads taking NITS;200 \n \n197 See supra section II, response to Question 5. \n198 See illustrative Tariff, Part XI, Subpart A, section 705.6(c). \n199 Illustrative Tariff, Part XI, Subpart A, section 706.4; see supra note 4. \n200 Illustrative Tariff, Part XI, Subpart A, section 706.4."},{"page":79,"startToken":20776,"endToken":21085,"text":"74 \n• Ancillary Services charges, except for Regulation, based on the net demand of \nthe Co-Located Load in accordance with Part I, section 3;201 \n• Black Start Service charges based on the gross demand of the Co-Located Load \nin accordance with Tariff, Schedule 6A;202 and \n• any redispatch costs as set forth in Tariff, Attachment K.203 \nThese are standard charges associated with the use of the Transmission System over and \nabove the transmission service rates.   \nFurther, as with all settlements in PJM, PJMSettlement will be the Counterparty to \nthe Firm Contract Demand Transmission Service and Non-Firm Contract Demand \nTransmission Service transactions under this Tariff.204 \nG. \nOperating Agreement \nPJM requires that the Eligible Customer plan, construct, operate, and maintain its \nfacilities in conformance with the Operating Agreement.  Additionally, the terms and \nconditions under which the Eligible Customer will operate its facilities will be detailed in \nthe Operating Agreement.205  Consistent with PJM’s requirements for NITS and the \nCommission’s pro forma Open Access Transmission Tariff,206 PJM requires that the \nEligible Customer taking Interim NITS to plan, construct, operate, and maintain its \nfacilities in conformance with the Operating Agreement.207  Additionally, the terms and \n \n201 Illustrative Tariff, Part XI, Subpart A, section 706.4. \n202 Illustrative Tariff, Part XI, Subpart A, section 706.4. \n203 Illustrative Tariff, Part XI, Subpart A, section 706.2. \n204 Illustrative Tariff, Part XI, Subpart A, section 700; id., Attachment F-3A, section 1.0. \n205 Illustrative Tariff, Part XI, Subpart A, section 707.1 \n206Pro Forma Open Access Transmission Tariff, section 35.1.  \n207 See illustrative Tariff, Part XI, Subpart A, section 707.1.  The Commission’s pro forma Open Access \nTransmission Tariff uses the term “Network Operating Agreement.”  In PJM, the “Operating Agreement of \nthe PJM Interconnection, L.L.C., as amended from time to time, shall constitute the Network Operating \nAgreement.”  Tariff, Attachment G."},{"page":80,"startToken":21085,"endToken":21331,"text":"75 \nconditions under which the Eligible Customer will operate its facilities will be detailed in \nthe Operating Agreement.208   \nH. \nPro Forma Service Agreement Specific to Eligible Customers Serving \nCo-Located Load Via NITS or Interim NITS \nTo facilitate the automatic transition from Interim NITS to NITS and to best \nadminister the terms and conditions specific to serving Co-Located Loads, PJM has \ndeveloped a single Service Agreement specific to Eligible Customers serving Co-Located \nLoads via Interim NITS or NITS.  PJM’s illustrative Service Agreement for NITS and \nInterim NITS is included in Attachment A to this initial brief and has been designated as \nAttachment F-3A.209  In addition to the NITS terms carried over from the pro forma NITS \nService Agreement (Attachment F-3), PJM has added terms specific to Co-Located Load \narrangements, including, for example, a description of Co-Located Generating Facility and \nits Maximum Facility Output, and a description of Co-Located Load and its gross \ndemand.210 \nThe Service Agreement provides the optionality of applying to full NITS only, or \nboth full NITS and Interim NITS.211  The Eligible Customer is also required to submit a \nsingle-line diagram as a part of Attachment F-3A to show the Delivery Point between the \nCo-Located Load and Co-Located Generating Facility.  \n \n208 Illustrative Tariff, Part XI, Subpart A, section 707.1. \n209 Illustrative Tariff, Attachment F-3A.  The existing pro forma NITS Service Agreement is located at Tariff, \nAttachment F-3. \n210 Illustrative Tariff, Attachment F-3A. \n211 Illustrative Tariff, Attachment F-3A, section 2.0."},{"page":81,"startToken":21331,"endToken":21637,"text":"76 \nIV. \nOTHER ILLUSTRATIVE TARIFF REVISIONS \n \nOther than the new illustrative Tariff, Part XI discussed above, PJM also provides \nillustrative Tariff revisions to other parts of its Tariff, including Part I (Definitions), Part III \n(Network Integration Transmission Service), and the pro forma GIA.  Because these \nrevisions relate to the terms and conditions of transmission service for Co-Located Load, \nPJM has included them in the illustrative Tariff in Attachment A to this initial brief, rather \nthan in the compliance filing being submitted concurrently with this initial brief.   \n \nFirst, PJM provides illustrative Tariff language to the definition of “Curtailment” \nin Part I, which refers to the specific Curtailment procedures provided in the new Tariff, \nPart XI applicable to Interim NITS or Non-Firm Contract Demand Transmission \nService.212  This definitional change distinguishes between ordinary Curtailment \nprocedures and the ones that are specific to the new transmission services available to \nCo-Located Load arrangements.   \n \nSecond, PJM includes a definition of “Remedial Action Scheme” in the illustrative \nlanguage, which simply refers to the NERC Glossary of Terms.213 \n \nThird, PJM includes an additional set of Application Procedures for Eligible \nCustomers taking service on behalf of Co-Located Load seeking NITS in Part III.214  This \ninformation is necessary for PJM to perform the relevant studies and analyses needed to \n \n212 Illustrative Tariff, Part I (Definitions), Definitions – C – D. \n213 Illustrative Tariff, Part I (Definitions), Definitions – R.  Other Regional Transmission Organizations and \nIndependent System Operators have implemented RAS consistent with the NERC standards.  See, e.g., Cal. \nIndep. Sys. Operator Corp., 180 FERC ¶ 61,143, at PP 16, 40 (2022); Midcontinent Indep. Sys. Operator, \nInc., 177 FERC ¶ 61,233, at P 4 n.8 (2021) (“MISO notes that the RAS was adopted pursuant to North \nAmerican Electric Reliability Corporation standard PRC-012-1.”). \n214 Illustrative Tariff, Part III (Network Integration Transmission Service), section 29.2(x)."},{"page":82,"startToken":21637,"endToken":21876,"text":"77 \nprovide NITS for Eligible Customers taking transmission service on behalf of Co-Located \nLoad.   \n \nFinally, PJM includes additional operational procedures and data exchange \nrequirements for a Co-Located Generating Facility associated with Co-Located Load,215 in \ncompliance with the Show Cause Order.216  As described in the Transmittal Letter,217 PJM \nis proposing in that filing a new Schedule O which will include required information for a \nProject Developer who intends to use its Generating Facility to serve Co-Located Load \nthrough the new Tariff, Part XI.  In Attachment A, the text that is marked in grey has been \nproposed by PJM in the Transmittal Letter.  However, the text that is marked in redline \nbelow the grey text includes additional illustrative Tariff language on operational \nprocedures and data exchange requirements that PJM believes are necessary for a Project \nDeveloper who intends to use its Generating Facility to serve Co-Located Load.218  This \nincludes: \n• Reference to, and incorporation of, operational or administrative \nrequirements necessary for the Co-Located Generating Facility based on \nfuel type; \n• Requirements relating to the revenue meter and necessary control \ntechnologies and protection systems; and \n• Requirements relating to communication about failure or malfunction of \nany equipment relating to such technologies and systems.219 \n \n215 Illustrative Tariff, Schedule O, pro forma GIA. \n216 Show Cause Order at P 188. \n217 PJM Transmittal Letter at 34-35. \n218 Illustrative Tariff, Schedule O, pro forma GIA. \n219 Illustrative Tariff, Schedule O, pro forma GIA."},{"page":83,"startToken":21876,"endToken":22132,"text":"78 \nAs discussed further in the following Section of the initial brief, PJM reserves its \nrights to supplement Schedule O to include additional operational procedures or data \nexchange requirements. \nV. \nRESERVATION OF RIGHTS TO SUPPLEMENT FILING \n \nAs discussed throughout this brief and shown in the illustrative Tariff provisions, \nthe addition of three new transmission services, and revisions to the NITS to accommodate \nEligible Customers serving Co-Located Load, requires complex revisions to PJM’s \ntransmission planning, interconnection, and operational procedures.  Indeed, the \nillustrative provisions represent most, but not all, of the potential tariff language and \nrevisions that would be necessary to implement these new services from a planning, \ninterconnection, and operational perspective.  \nHowever, further work is required to fully integrate these new services into PJM, \nincluding into PJM’s energy, ancillary services, and capacity markets.  PJM continues to \nreview its Governing Documents to determine the additional revisions necessary to \nproperly account for these new services.  For example, PJM anticipates that it will likely \nneed to revise its existing Tariff provisions addressing Real-time and Day-ahead Energy \nMarket settlements to account for the new transmission services—i.e., Firm and Non-Firm \nContract Demand Transmission Service and Interim NITS, particularly given that such \nprovisions often determine charges based on Network Load, and load served by Firm and \nNon-Firm Contract Demand Transmission Service cannot be Network Load.220  As another \nexample, PJM may need to revise existing Tariff provisions to address the applicability to \nAuction Revenue Rights and Financial Transmission Rights to Eligible Customers serving \n \n220 See Show Cause Order at P 205."},{"page":84,"startToken":22132,"endToken":22445,"text":"79 \nload with Contract Demand Transmission Service.  PJM will continue to review its \nGoverning Documents and reserves the right to supplement its filing with additional terms \nand conditions needed to effectuate these new transmission services to allow the paper \nhearing the benefit of such additional information. \nVI. \nIMPLEMENTATION AND EFFECTIVE DATE  \nAs explained by Mr. Horger, PJM believes an effective date of June 1, 2029, is \nnecessary for the three new transmission services—Interim NITS, Non-Firm Contract \nDemand Transmission Service, and Firm Contract Demand Transmission Service.221  Mr. \nHorger explains that June 1, 2029, is a reasonable and appropriate effective date for these \nnew transmission services because of the time required to:  (1) integrate these transmission \nservices into PJM’s capacity market, the Reliability Pricing Model (“RPM”), so that PJM \ncan procure capacity for those that are capacity-backed (e.g., Firm Contract Demand \nTransmission Service); and (2) make the necessary modifications to the PJM core Markets \nand Operations systems.  Regardless, it is unlikely that generation intended to serve \nCo-Located Load will be constructed and operational before June 1, 2029.   \nFirst, Mr. Horger explains that the three new transmission services that will be \navailable to Eligible Customers seeking to take transmission service on behalf of a \nCo-Located Load will significantly affect the PJM Load Forecast and expected demand, \nwhich will, in turn, have significant implications for the RPM, a three-year forward \nmarket.222  Given current tight conditions, it is of utmost importance that Eligible \n \n221 PJM notes that NITS is already a service that is available to Eligible Customers electing to take NITS on \nbehalf of Co-Located Load. \n222 Horger Aff. ¶ 11 (Although the next few RPM Base Residual Auctions (“BRAs”) will be operating on a \ncompressed auction schedule, “PJM has been on track to return to a normal three-year forward auction for \nits capacity market by May 2027 (for the 2030/2031 Delivery Year).”)."},{"page":85,"startToken":22445,"endToken":22722,"text":"80 \nCustomers’ expected demand be reflected in the RPM to ensure that PJM procures needed \ncapacity.   \nAs a forward market, the RPM relies on PJM Load Forecasts to ensure that the \nRPM auctions procure sufficient capacity for future Delivery Years based on expected \ndemand.  Each Delivery Year begins on June 1.  The RPM BRA for the 2027/2028 Delivery \nYear, for the Delivery Year beginning June 1, 2027, took place in December 2025.  While \nthe BRA for the 2028/2029 Delivery Year, for the Delivery Year beginning June 1, 2028, \nhas not yet taken place, “as of today, the PJM Load Forecast for the 2028/2029 Delivery \nYear BRA is already determined, and eligible capacity has already been determined for the \n2028/2029 Delivery Year BRA.”223  As a result, “it is no longer possible to update the PJM \nLoad Forecast, update the RPM auction input parameters (planning parameters), and \nimplement necessary changes before the 2028/2029 RPM BRA is conducted, even if the \nCommission were to theoretically approve the proposed changes today.”224  The BRA for \nthe 2029/2030 Delivery Year, starting June 1, 2029, is the first BRA in which the effects of \nthese transmission services for Eligible Customers can be considered (including procuring \nnecessary capacity for firm transmission services).   \nInclusion of these transmission services for Eligible Customers taking transmission \non behalf of Co-Located Load in Incremental Auctions, i.e., in the intervening period \nbetween the BRAs, would likewise be inappropriate.  As Mr. Horger testifies, “Incremental \nAuctions are conducted to allow for replacement resource procurement, along with \nincreases and decreases in resource commitments due to reliability requirement \n \n223 Horger Aff. ¶ 12. \n224 Horger Aff. ¶ 13."},{"page":86,"startToken":22722,"endToken":22957,"text":"81 \nadjustments.  These adjustments are typically small.”225  Thus, due to the interaction \nbetween the impact that Eligible Customers’ load will have on underlying Load Forecasts \nand expected demand, which in turn will significantly impact the RPM, PJM is proposing \na June 1, 2029 implementation date for the three new transmission services applicable to \nEligible Customers seeking service on behalf of Co-Located Load. \nSecond, Mr. Horger testifies that the addition of the three new transmission services \nwill require significant changes to PJM’s core Markets and Operations systems.226  \nChanges to these systems will necessarily be dependent on vendor availability, the speed \nwith which the system changes can be designed, and the interaction of these requested \nchanges with other competing priorities, including system changes to implement other \nCommission-directed initiatives.227  In particular, PJM anticipates that, implementing the \nproposed Curtailment priorities applicable to Interim NITS and Non-Firm Contract \nDemand Transmission Service, which can affect prices and dispatch instructions, will \nrequire PJM to work with vendors to develop system automation that will avoid \nnon-optimal, untimely, and inefficient outcomes.  Because the transmission services \nproposed herein are novel and subject to a paper hearing, efficient use of vendors to develop \nthe requisite system updates, including software changes, cannot commence until the \nspecific rates, terms, and conditions of these transmission services are correspondingly \nfinalized.228  \n \n225 Horger Aff. ¶ 15. \n226 Horger Aff. ¶ 16. \n227 Horger Aff. ¶ 16. \n228 Horger Aff. ¶ 16."},{"page":87,"startToken":22957,"endToken":23295,"text":"82 \nFurthermore, PJM does not expect that Eligible Customers and associated \ngeneration will be online and taking service under any of the proposed transmission \nservices before June 1, 2029.  In other words, the implementation and effective date will \nnot be a limiting factor.  Rather, the process of an Eligible Customer’s generation getting \nthrough the interconnection queue, being constructed, and becoming operational will likely \ntake more than three years, particularly in light of current supply chain issues, Transmission \nOwner and PJM queue requirements, and RPM auction timelines.229  There is a known \nchallenge to procure equipment, such as turbines,230 and it is not currently expected that a \ngenerator could be physically built in less than three years.  The earliest expected Delivery \nYear a new generator can participate in an RPM BRA or an existing capacity resource can \ndelist, which includes required interconnection modified studies, is for the 2029/2030 \nDelivery Year.  Thus, for the foregoing reasons, a June 1, 2029 implementation and \neffective date for the three new transmission services is just and reasonable.  \nVII. \nDOCUMENTS ENCLOSED  \n \nIn addition to this initial brief, PJM encloses the following: \n1. \nAttachment A: Illustrative Language for New Tariff, Part XI; Attachments \nF-3A and F-4; and Other Illustrative Tariff Revisions; \n2. \nAttachment B: Affidavit of \nDr. \nSami Abdulsalam, Director of \nTransmission Planning; \n \n229 Notably, however, as the Commission recently reiterated, for purposes of the RPM, “Capacity prices are \nintended to send longer-term investment signals to which developers respond over time[]” and “delays in the \ninterconnection queue, compressed auction schedules, and supply chain issues” do not render RPM auction \nresults unjust and unreasonable.  PJM Interconnection, L.L.C., 194 FERC ¶ 61,049, at P 50 (2025) (citing \nPJM Interconnection, L.L.C., 126 FERC ¶ 61,275, at P 150 (2009) (“RPM was designed to provide long-\nterm forward price signals . . . .”)). \n230 Jared Anderson, US gas-fired turbine wait times as much as seven years; costs up sharply, S&P Global \n(May 20, 2025), https://www.spglobal.com/energy/en/news-research/latest-news/electric-power/052025-us-\ngas-fired-turbine-wait-times-as-much-as-seven-years-costs-up-sharply."},{"page":88,"startToken":23295,"endToken":23470,"text":"83 \n3. \nAttachment C: Affidavit of Matthew Wharton, Manager, Reliability \nEngineering; and \n4. \nAttachment D: Affidavit of Timothy Horger, Senior Director, Forward \nMarket Operations. \nVIII. CONCLUSION  \nPJM respectfully requests that the Commission find that the illustrative Tariff \nrevisions included in Attachment A are part of a just and reasonable replacement rate in \naccordance with the requirements of the Show Cause Order. \nRespectfully submitted, \n/s/ Ryan J. Collins \n \nCraig Glazer \nVice President – Federal \nGovernment Policy \nPJM Interconnection, L.L.C. \n1200 G Street, NW, Suite 600 \nWashington, DC  20005 \n(202) 423-4743 \ncraig.glazer@pjm.com \n \nMark J. Stanisz \nAssociate General Counsel \nThomas DeVita \nAssociate General Counsel \nPJM Interconnection, L.L.C.  \n2750 Monroe Blvd, \nAudubon, PA  19403 \n(610) 666-8800 \nmark.stanisz@pjm.com \nthomas.devita@pjm.com \nWendy B. Warren \nRyan J. Collins \nVivian W. Chum \nQingliu (Mary) Yang \nWright & Talisman, P.C. \n1200 G Street, NW, Suite 600 \nWashington, DC  20005 \n(202) 393-1200  \nwarren@wrightlaw.com \ncollins@wrightlaw.com \nchum@wrightlaw.com \nyang@wrightlaw.com \n \n \n \n \n \n \n \nCounsel for PJM Interconnection, L.L.C.  \n \n \nFebruary 23, 2026"},{"page":89,"startToken":23470,"endToken":23538,"text":"CERTIFICATE OF SERVICE \n \nI hereby certify that I have this day served the foregoing document upon each \nperson designated on the official service list compiled by the Secretary in this proceeding.  \n \nDated at Washington, D.C., this 23rd day of February 2026. \n \n \n \n \n \n \n \n \n/s/ Ryan J. Collins \n \n \n \n \n \n \n \n \n \nRyan J. Collins \n \n \n \n \n \n \n \nWright & Talisman, P.C. \n \n \n \n \n \n \n \n1200 G Street, N.W., Suite 600 \n \n \n \n \n \n \n \nWashington, DC 20005-3802 \n \n \n \n \n \n \n \n(202) 393-1200 \n \n \n \n \n \n \n \ncollins@wrightlaw.com"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":3,"endAt":0,"startToken":0,"endToken":372},{"p":3,"at":0,"title":"TABLE OF CONTENTS","method":"printed heading","endPage":3,"endAt":327,"startToken":372,"endToken":391},{"p":3,"at":327,"title":"A. Overview of Contract Demand Transmission Services in Illustrative","method":"printed heading","endPage":3,"endAt":506,"startToken":391,"endToken":404},{"p":3,"at":506,"title":"B. Firm Contract Demand Transmission Service in Illustrative Tariff,","method":"printed heading","endPage":3,"endAt":935,"startToken":404,"endToken":440},{"p":3,"at":935,"title":"F. Conditions Precedent and Technical Requirements for Contract","method":"printed heading","endPage":3,"endAt":1093,"startToken":440,"endToken":452},{"p":3,"at":1093,"title":"G. Termination of Service Agreement for Contract Demand Transmission","method":"printed heading","endPage":3,"endAt":1273,"startToken":452,"endToken":463},{"p":3,"at":1273,"title":"H. Designation of Co-Located Load and Co-Located Generating","method":"printed heading","endPage":4,"endAt":4,"startToken":463,"endToken":560},{"p":4,"at":4,"title":"D. Study Procedures for Non-Firm Contract Demand Transmission","method":"printed heading","endPage":4,"endAt":250,"startToken":560,"endToken":579},{"p":4,"at":250,"title":"F. Necessary Control Technologies and Protection Systems to Protect the","method":"printed heading","endPage":4,"endAt":401,"startToken":579,"endToken":596},{"p":4,"at":401,"title":"G. Rates and Charges for Non-Firm Contract Demand Transmission","method":"printed heading","endPage":4,"endAt":1777,"startToken":596,"endToken":700},{"p":4,"at":1777,"title":"B. Financial Penalty for Unreserved Use of the PJM Transmission","method":"printed heading","endPage":5,"endAt":129,"startToken":700,"endToken":731},{"p":5,"at":129,"title":"A. New Curtailment Procedures Applicable to Eligible Customers Taking","method":"printed heading","endPage":5,"endAt":365,"startToken":731,"endToken":751},{"p":5,"at":365,"title":"B. Curtailment of an Eligible Customer Taking Both Firm and Non-Firm","method":"printed heading","endPage":5,"endAt":1334,"startToken":751,"endToken":830},{"p":5,"at":1334,"title":"H. Pro Forma Service Agreement Specific to Eligible Customers Serving","method":"printed heading","endPage":6,"endAt":1083,"startToken":830,"endToken":1024},{"p":6,"at":1083,"title":"I. INTRODUCTION AND BACKGROUND","method":"printed heading","endPage":10,"endAt":3,"startToken":1024,"endToken":2024},{"p":10,"at":3,"title":"II. RESPONSES TO THE PAPER HEARING QUESTIONS","method":"printed heading","endPage":10,"endAt":1261,"startToken":2024,"endToken":2214},{"p":10,"at":1261,"title":"A. Overview of Contract Demand Transmission Services in Illustrative","method":"printed heading","endPage":18,"endAt":298,"startToken":2214,"endToken":4348},{"p":18,"at":298,"title":"B. Firm Contract Demand Transmission Service in Illustrative Tariff,","method":"printed heading","endPage":18,"endAt":1114,"startToken":4348,"endToken":4471},{"p":18,"at":1114,"title":"C. Provision of Contract Demand Transmission Services","method":"printed heading","endPage":20,"endAt":1053,"startToken":4471,"endToken":5003},{"p":20,"at":1053,"title":"D. Nature of Contract Demand Transmission Services","method":"printed heading","endPage":22,"endAt":117,"startToken":5003,"endToken":5478},{"p":22,"at":117,"title":"E. Application for Contract Demand Transmission Services","method":"printed heading","endPage":23,"endAt":646,"startToken":5478,"endToken":5861},{"p":23,"at":646,"title":"F. Conditions Precedent and Technical Requirements for Contract Demand","method":"printed heading","endPage":25,"endAt":328,"startToken":5861,"endToken":6363},{"p":25,"at":328,"title":"G. Termination of Service Agreement for Contract Demand Transmission","method":"printed heading","endPage":27,"endAt":273,"startToken":6363,"endToken":6992},{"p":27,"at":273,"title":"H. Designation of Co-Located Load and Co-Located Generating Facility","method":"printed heading","endPage":28,"endAt":874,"startToken":6992,"endToken":7327},{"p":28,"at":874,"title":"I. Restrictions on Use of Service and Anti-Toggling Provision","method":"printed heading","endPage":35,"endAt":829,"startToken":7327,"endToken":9187},{"p":35,"at":829,"title":"A. Provision of Non-Firm Contract Demand Transmission Service","method":"printed heading","endPage":36,"endAt":540,"startToken":9187,"endToken":9420},{"p":36,"at":540,"title":"B. Nature of Non-Firm Contract Demand Transmission Service","method":"printed heading","endPage":37,"endAt":1155,"startToken":9420,"endToken":9814},{"p":37,"at":1155,"title":"C. Initiating Non-Firm Contract Demand Transmission Service","method":"printed heading","endPage":38,"endAt":516,"startToken":9814,"endToken":10034},{"p":38,"at":516,"title":"D. Study Procedures for Non-Firm Contract Demand Transmission Service","method":"printed heading","endPage":39,"endAt":4,"startToken":10034,"endToken":10235},{"p":39,"at":4,"title":"E. Curtailment of Non-Firm Contract Demand Transmission Service","method":"printed heading","endPage":39,"endAt":539,"startToken":10235,"endToken":10315},{"p":39,"at":539,"title":"F. Necessary Control Technologies and Protection Systems to Protect the","method":"printed heading","endPage":41,"endAt":872,"startToken":10315,"endToken":10906},{"p":41,"at":872,"title":"G. Rates and Charges for Non-Firm Contract Demand Transmission Service","method":"printed heading","endPage":42,"endAt":1057,"startToken":10906,"endToken":11230},{"p":42,"at":1057,"title":"H. Pro Forma Contract Demand Transmission Service Agreement","method":"printed heading","endPage":46,"endAt":1022,"startToken":11230,"endToken":12040},{"p":46,"at":1022,"title":"A. Disqualification or Pause in Service","method":"printed heading","endPage":55,"endAt":518,"startToken":12040,"endToken":14742},{"p":55,"at":518,"title":"B. Financial Penalty for Unreserved Use of the PJM Transmission System","method":"printed heading","endPage":68,"endAt":1184,"startToken":14742,"endToken":17854},{"p":68,"at":1184,"title":"A. New Curtailment Procedures Applicable to Eligible Customers Taking","method":"printed heading","endPage":70,"endAt":4,"startToken":17854,"endToken":18233},{"p":70,"at":4,"title":"B. Curtailment of an Eligible Customer Taking Both Firm and Non-Firm","method":"printed heading","endPage":71,"endAt":751,"startToken":18233,"endToken":18605},{"p":71,"at":751,"title":"III. INTERIM NETWORK INTEGRATION TRANSMISSION SERVICE","method":"printed heading","endPage":72,"endAt":911,"startToken":18605,"endToken":18889},{"p":72,"at":911,"title":"A. Provision of Interim NITS and Nature and Scope of Service","method":"printed heading","endPage":73,"endAt":314,"startToken":18889,"endToken":19065},{"p":73,"at":314,"title":"B. Initiating Service","method":"printed heading","endPage":74,"endAt":1259,"startToken":19065,"endToken":19548},{"p":74,"at":1259,"title":"C. Designation of Co-Located Load","method":"printed heading","endPage":75,"endAt":1545,"startToken":19548,"endToken":19871},{"p":75,"at":1545,"title":"D. Study Procedures for Interim NITS","method":"printed heading","endPage":76,"endAt":556,"startToken":19871,"endToken":20009},{"p":76,"at":556,"title":"E. Load Shedding and Curtailments","method":"printed heading","endPage":78,"endAt":1012,"startToken":20009,"endToken":20641},{"p":78,"at":1012,"title":"F. Rates and Charges for Interim NITS","method":"printed heading","endPage":79,"endAt":686,"startToken":20641,"endToken":20881},{"p":79,"at":686,"title":"G. Operating Agreement","method":"printed heading","endPage":80,"endAt":129,"startToken":20881,"endToken":21104},{"p":80,"at":129,"title":"H. Pro Forma Service Agreement Specific to Eligible Customers Serving","method":"printed heading","endPage":80,"endAt":667,"startToken":21104,"endToken":21186},{"p":80,"at":667,"title":"Attachment F-3A.209 In addition to the NITS terms carried over from the pro forma NITS","method":"printed heading","endPage":80,"endAt":1514,"startToken":21186,"endToken":21316},{"p":80,"at":1514,"title":"Attachment F-3.","method":"printed heading","endPage":81,"endAt":4,"startToken":21316,"endToken":21332},{"p":81,"at":4,"title":"IV. OTHER ILLUSTRATIVE TARIFF REVISIONS","method":"printed heading","endPage":83,"endAt":200,"startToken":21332,"endToken":21905},{"p":83,"at":200,"title":"V. RESERVATION OF RIGHTS TO SUPPLEMENT FILING","method":"printed heading","endPage":84,"endAt":318,"startToken":21905,"endToken":22178},{"p":84,"at":318,"title":"VI. IMPLEMENTATION AND EFFECTIVE DATE","method":"printed heading","endPage":87,"endAt":1148,"startToken":22178,"endToken":23131},{"p":87,"at":1148,"title":"VII. DOCUMENTS ENCLOSED","method":"printed heading","endPage":87,"endAt":1245,"startToken":23131,"endToken":23145},{"p":87,"at":1245,"title":"Attachment A: Illustrative Language for New Tariff, Part XI; Attachments","method":"printed heading","endPage":87,"endAt":1379,"startToken":23145,"endToken":23164},{"p":87,"at":1379,"title":"Attachment B: Affidavit of","method":"printed heading","endPage":88,"endAt":8,"startToken":23164,"endToken":23297},{"p":88,"at":8,"title":"Attachment C: Affidavit of Matthew Wharton, Manager, Reliability","method":"printed heading","endPage":88,"endAt":96,"startToken":23297,"endToken":23308},{"p":88,"at":96,"title":"Attachment D: Affidavit of Timothy Horger, Senior Director, Forward","method":"printed heading","endPage":88,"endAt":185,"startToken":23308,"endToken":23319},{"p":88,"at":185,"title":"VIII. CONCLUSION","method":"printed heading","endPage":89,"endAt":0,"startToken":23319,"endToken":23470},{"p":89,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":89,"endAt":525,"startToken":23470,"endToken":23538}]}