{"document":{"slug":"rec-20260223-5190-2","title":"Exhibit No. PTO-0001 - Direct Joint Testimony of Blazunas, Shafer, & Hammer","issued":"2026-02-23","accession":"20260223-5190","docket":"EL25-49-000","group":"PJM co-location compliance","filer":"Indicated PJM Transmission Owners","kind":"attachment","file":"sources/filings/text/20260223-5190_002.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260223-5190","tier":"record","parent":"rec-20260223-5190","sha256":"0f308db2d97c18c58a8520d48eb26d3f6a96e5f8a5484042750ea82b11147e11","pages":42,"tokens":11841,"emptyPages":[41],"textThemes":["flex","colo","cost","study"]},"pages":[{"page":1,"startToken":0,"endToken":205,"text":"Exhibit No. PTO-0001 \nPage 1 of 39 \nUNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \nPJM Interconnection, L.L.C., et al.   \n)  \nDocket No. EL25-49-000 \n)  \nDocket No. EL25-49-001 \n) \nLarge Loads Co-Located at Generating Facilities  \n) \nDocket No. AD24-11-000 \n) \nConstellation Energy Generation, LLC  \n)  \nDocket No. EL25-20-000 \nv.  \n \n) \nPJM Interconnection, L.L.C.   \n)  \n(Consolidated) \nDIRECT JOINT TESTIMONY \nOF \nPETER BLAZUNAS, LANCE SCHAFER \nAND \nHANHAN HAMMER \nI. \nINTRODUCTION  \n1 \nQ.  \nPlease state your name, title, business address, and provide your professional \n2 \nbackground and relevant experience. \n3 \nA. \n[Blazunas] My name is Peter Blazunas, and my business address is 293 Boston Post Road \n4 \nWest, Marlborough, MA 01752. I am a Vice President with Concentric Energy Advisors, \n5 \nInc. (“Concentric”). I joined Concentric in 2021, and I provide regulatory strategy and rate \n6 \ncase expertise to regulated electric and gas utilities, especially with respect to the topics of \n7 \ncost of service and rate design. Prior to Concentric, I managed a team overseeing the cost \n8 \nof service, rate design, and rate administration functions for Potomac Electric Power \n9 \nCompany’s (“Pepco”) Maryland and District of Columbia jurisdictions. Prior to Pepco, I \n10 \nworked as an analyst in the FirstEnergy Rates and Regulatory Affairs department. I have \n11"},{"page":2,"startToken":205,"endToken":492,"text":"Exhibit No. PTO-0001 \nPage 2 of 39 \ntestified before regulatory commissions in Delaware, the District of Columbia, Maryland, \n1 \nOhio, and Rhode Island. \n2 \n[Schafer] My name is Lance Schafer, and my business address is 293 Boston Post \n3 \nRoad West, Marlborough, MA 01752. I am a Senior Project Manager with Concentric. I \n4 \nspecialize in regulatory strategy, rate design, and cost of service for regulated electric and \n5 \ngas utilities. Prior to joining Concentric in 2024, I was the Manager of Rate Administration \n6 \nat Pepco, where I was responsible for overseeing the cost of service, rate design, and rate \n7 \nadministration functions for Pepco’s Maryland and District of Columbia jurisdictions. I \n8 \nhave testified before regulatory commissions in Delaware, the District of Columbia, \n9 \nKentucky, Maryland, Missouri, and Rhode Island. \n10 \n[Hammer] My name is Hanhan Hammer, and my business address is 293 Boston \n11 \nPost Road West, Marlborough, MA 01752. I am a Senior Project Manager with Concentric. \n12 \nIn my current role, I advise regulators, utilities, grid operators, and developers on complex \n13 \nregulatory and market issues, including wholesale market participation, compliance with \n14 \nFERC directives, transmission planning and cost allocation, large load tariffs, and \n15 \nintegrated resource planning. Prior to joining Concentric in 2024, I spent approximately 15 \n16 \nyears working at various Independent System Operators and Regional Transmission \n17 \nOrganizations. My experience includes designing wholesale market rules at ISO New \n18 \nEngland (“ISO-NE”) and overseeing competitive market performance monitoring at the \n19 \nMidcontinent Independent System Operator (“MISO”) and the Southwest Power Pool \n20 \n(“SPP”). I have provided expert testimony before FERC.   \n21 \n[Blazunas, Schafer, and Hammer] Our professional background and relevant \n22 \nexperience are also shown in Exhibit No. PTO-0002. \n23"},{"page":3,"startToken":492,"endToken":749,"text":"Exhibit No. PTO-0001 \nPage 3 of 39 \nII. \nBACKGROUND \n1 \nQ. \nWhat is the background for this proceeding? \n2 \nA. \n[Blazunas, Schafer, and Hammer] On December 18, 2025, the Commission issued its \n3 \norder in PJM Interconnection. L.L.C., 193 FERC ¶ 61,217, at P 193 (2025) (“Order”). In \n4 \nthe Order, the Commission found that PJM’s Open Access Transmission Tariff (“Tariff”) \n5 \n“is unjust and unreasonable because it does not contain provisions addressing with \n6 \nsufficient clarity or consistency the rates, terms, and conditions of service that apply to \n7 \ngenerators serving Co-Located Load and Eligible Customers taking transmission service \n8 \non behalf of Co-Located Load.”1 Specifically, the Commission found PJM’s Tariff “unjust \n9 \nand unreasonable because it does not include types of transmission service that reflect \n10 \nEligible Customers taking service on behalf of Co-Located Loads that are willing and able \n11 \nto limit their use of the transmission system under certain conditions.”2\n12 \nThe Commission ordered PJM to offer three new forms of transmission service \n13 \nunder its Tariff, and identified these three new forms of transmission service as: (i) Firm \n14 \nContract Demand transmission service; (ii) Non-Firm Contract Demand transmission \n15 \nservice; and (iii) interim, non-firm transmission service. The Commission also established \n16 \na paper hearing to determine the just and reasonable rates, terms, and conditions for these \n17 \nnew transmission services. The paper hearing process provides for initial briefs, responses \n18 \nto initial briefs, and replies to those responses. \n19 \n20 \n21 \n1 Order at P 2. \n2 Id."},{"page":4,"startToken":749,"endToken":1219,"text":"Exhibit No. PTO-0001 \nPage 4 of 39 \nIII.  \nPURPOSE OF TESTIMONY \n1 \nQ. \nWhat is the purpose of your testimony?  \n2 \nA.   \n[Blazunas, Schafer, and Hammer] The PJM Transmission Owners, acting through the \n3 \nSection 205 Working Group,3 have developed rate design proposals in response to the \n4 \nOrder’s requirement that PJM implement new transmission services and for submission in \n5 \nthe paper hearing process.4 The purpose of this testimony is to describe and support the \n6 \nPJM Transmission Owners’ rate design proposals for the three new transmission services \n7 \nthe Commission required in the Order. We also support the PJM Transmission Owners’ \n8 \nrate design proposals for a new Grid Reliance Charge. We also address penalty provisions \n9 \nand planning and operational issues relating to Eligible Customers5 that choose to take one \n10 \nor more of these new services. In particular, we discuss appropriate practices and \n11 \nrequirements relating to protective systems and other components that will be necessary to \n12 \nensure ongoing system reliability. \n13 \n3\nThe Section 205 Working Group is established under the authority of the Transmission Owner Agreement \nAdministrative Committee (“TOAAC”) pursuant to the Consolidated Transmission Owners Agreement (“CTOA”).  \nSee CTOA § 8.1. These proposals have not yet been submitted to the TOAAC for approval. \n4\nFor purposes of this testimony and the accompanying responses to the Commission’s paper hearing \nquestions, the PJM Transmission Owners are: American Electric Power Service Corporation on behalf of its affiliates, \nAppalachian Power Company, Indiana Michigan Power Company, Kentucky Power Company, Kingsport Power \nCompany, Ohio Power Company, Wheeling Power Company, AEP Appalachian Transmission Company, AEP \nIndiana Michigan Transmission Company, AEP Kentucky Transmission Company, AEP Ohio Transmission \nCompany, and AEP West Virginia Transmission Company; The Dayton Power and Light Company d/b/a AES Ohio; \nDuquesne Light Company; Dominion Energy Services, Inc. on behalf of Virginia Electric and Power Company d/b/a \nDominion Energy Virginia; Duke Energy Business Services, LLC for Duke Energy Kentucky, Inc. and Duke Energy \nOhio, Inc.; East Kentucky Power Cooperative; Exelon Corporation on behalf of its affiliates Atlantic City Electric \nCompany, Baltimore Gas and Electric Company, Commonwealth Edison Company, Commonwealth Edison \nCompany of Indiana, Inc., Delmarva Power & Light Company, PECO Energy Company (“PECO”), and Potomac \nElectric Power Company; FirstEnergy Service Company, on behalf of its affiliates American Transmission Systems, \nIncorporated, Jersey Central Power & Light Company, Mid-Atlantic Interstate Transmission LLC, The Potomac \nEdison Company, Monongahela Power Company, Keystone Appalachian Transmission Company, and Trans-\nAllegheny Interstate Line Company (collectively, the “FirstEnergy Companies”); PPL Electric Utilities Corporation; \nPublic Service Electric and Gas Company (“PSE&G”); Rockland Electric Company; and the Southern Maryland \nElectric Cooperative (“SMECO”). \n5\nAll capitalized terms that are not otherwise defined herein shall have the meaning set forth in the PJM Tariff \nor Amended and Restated Operating Agreement of PJM Interconnection, L.L.C."},{"page":5,"startToken":1219,"endToken":1493,"text":"Exhibit No. PTO-0001 \nPage 5 of 39 \nIV. \nNEW TRANSMISSION SERVICE CATEGORIES AND RATE DESIGNS \n1 \nA. \nFirm Contract Demand Transmission Service \n2 \nQ. \nWhat is Firm Contract Demand transmission service?   \n3 \nA.  \n[Blazunas] Pursuant to the Order, under the new Firm Contract Demand transmission \n4 \nservice (“Firm Contract Demand Service”), Eligible Customers will have the right to \n5 \nrequest transmission service on behalf of a Co-Located Load up to a specified megawatt \n6 \n(“MW”) quantity (“Firm Contract Demand”). The Firm Contract Demand Service will \n7 \nhave the same reservation and curtailment priority as existing firm transmission services at \n8 \nthe level of the contract demand. However, unlike Network Integration Transmission \n9 \nService (“NITS”) customers, the Eligible Customer taking Firm Contract Demand Service \n10 \non behalf of the Co-Located Load is not permitted to withdraw energy from the PJM \n11 \ntransmission system beyond the firm contract demand level under this service.  \n12 \nQ. \nWhat is the PJM Transmission Owners’ proposed rate design for the new Firm \n13 \nContract Demand Service? \n14 \nA. \n[Blazunas] The PJM Transmission Owners propose that the rate for Firm Contract \n15 \nDemand Service be based on zonal NITS rates and the underlying NITS revenue \n16 \nrequirements. Under this approach, Eligible Customers taking Firm Contract Demand \n17 \nService will pay the same base charge per MW as NITS customers, except that, unlike \n18 \nNITS customers, their applicable billing determinant will be their specified firm contract \n19 \ndemand. The transmission charge for a Firm Contract Demand Service customer will be \n20 \ncalculated by multiplying: (i) the customer’s firm contract demand amount (in MWs) by \n21 \n(ii) the applicable zonal NITS rate.   \n22"},{"page":6,"startToken":1493,"endToken":1811,"text":"Exhibit No. PTO-0001 \nPage 6 of 39 \nIn zones with formula transmission rates, the single annual rate applicable to both \n1 \nNITS and Firm Contract Demand Service customers will be established in the same manner \n2 \nas NITS rates are today.6 This rate will be calculated based on each transmission owner’s \n3 \nannual net revenue requirement, as determined pursuant to the formula rates contained in \n4 \nAttachment H to the PJM Tariff, divided by the single zonal coincident peak load, which \n5 \nwill include NITS customer load, the total contract demand for all Firm Contract Demand \n6 \nService customers, and load associated with interim, non-firm transmission service.7 This \n7 \nwill result in a single $/MW-year rate that will apply to both NITS and Firm Contract \n8 \nDemand Service customers.   \n9 \nEligible Customers will also pay a Grid Reliance Charge for the portion of their \n10 \nremaining on-site load not covered by Firm Contract Demand Service. The Grid Reliance \n11 \nCharge is discussed in further detail below.   \n12 \nThe procedures for establishing zonal NITS/Firm Contract Demand transmission \n13 \nservice rates and updating the underlying annual revenue requirements will remain \n14 \nunchanged, and Firm Contract Demand Service customers will be treated the same as NITS \n15 \ncustomers under each PJM Transmission Owner’s formula rate protocols.   \n16 \nA detailed example showing how the Firm Contract Demand Service rate and other \n17 \ncharges associated with the new services will be calculated is set forth below. \n18 \n6\nA handful of PJM transmission owners continue to utilize stated rates, which in some cases are based on \nblack-box settlements, which may need to be accounted for in specific stated rates for the new firm and non-firm \ncontract demand services. \n7\nAny changes to a transmission owner’s procedure for assigning a Network Service Peak Load (“NSPL”) tag \nto a Load Serving Entity (“LSE”) may need to be addressed in a future filing."},{"page":7,"startToken":1811,"endToken":2138,"text":"Exhibit No. PTO-0001 \nPage 7 of 39 \nQ. \nWhy are the PJM Transmission Owners proposing to base the rate for Firm Contract \n1 \nDemand Service on the NITS rate, as opposed to the firm Point-to-Point rate or some \n2 \nother rate? \n3 \nA. \n[Blazunas] The PJM Transmission Owners are proposing to charge the same rate for Firm \n4 \nContract Demand Service and NITS because the level of service provided to both \n5 \ncustomers is, for all relevant purposes, the same. Both NITS and Firm Contract Demand \n6 \nService are firm services for which Network Upgrades will be planned and constructed as \n7 \nnecessary, with the only difference being that upgrades for NITS customers are identified \n8 \nbased on anticipated load growth while upgrades for Firm Contract Demand Service \n9 \ncustomers will be identified based on their contracted demand level. Firm Contract \n10 \nDemand Service customers will be able to serve their contracted demand through capacity \n11 \nprocured by PJM just like NITS customers and will not be required to designate specific \n12 \npoints of receipt and delivery.   \n13 \nThere is no need or benefit to utilizing existing Firm Point-to-Point Service \n14 \n(“PTPS”) rates. Firm PTPS rates are generally based on the same revenue requirement as \n15 \nthe NITS rate, and the nature of Firm Contract Demand Service as contemplated in the \n16 \nOrder is essentially a variation of NITS service with a specified contract demand level. The \n17 \nFirm Contract Demand Service customer will be serving its full contract demand from all \n18 \nresources on the grid, not on a point-to-point basis. Consequently, PJM will treat Firm \n19 \nContract Demand Service load during system emergencies in the same manner as load \n20 \nusing NITS, thus providing service to the Firm Contract Demand Service load on a \n21 \ncomparable basis with NITS load. Furthermore, Firm Contract Demand transmission \n22 \nService will enjoy the same firmness as NITS load, as well as the same ability to make use \n23"},{"page":8,"startToken":2138,"endToken":2452,"text":"Exhibit No. PTO-0001 \nPage 8 of 39 \nof PJM resources to serve their full contract demand and ensure guaranteed grid energy \n1 \ndelivery. Given the similarities between NITS and Firm Contract Demand Service, it would \n2 \nbe inappropriate to charge Firm Contract Demand Service customers a rate lower than one \n3 \nbased on the NITS rate because doing so would result in subsidizing these customers at the \n4 \nexpense of other ratepayers.    \n5 \nFinally, in PJM, PTPS is generally only utilized for purposes of service at the PJM \n6 \nborder. That will not be the case for Co-Located Load customers taking Firm Contract \n7 \nDemand Service to serve their on-site, contract demand within PJM. Basing the rate for \n8 \nFirm Contract Demand Service on the zonal NITS rate also has the advantage of \n9 \nminimizing changes to current PJM billing and settlements practices. As it does for NITS \n10 \nnow, for Firm Contract Demand Service, PJM will perform the billing function for \n11 \ntransmission, capacity, and energy charges, while electric distribution companies will \n12 \nperform their current roles of submitting the metrics that PJM uses to calculate those \n13 \ncharges, such as customers’ peak load share information.  \n14 \nQ. \nDo the PJM Transmission Owners have suggestions regarding interconnection \n15 \nrequirements or operational practices that are necessary for an Eligible Customer to \n16 \ntake Firm Contract Demand Service on behalf of Co-Located Load? \n17 \nA. \n[Hammer] Yes. The PJM Transmission Owners have identified several requirements and \n18 \noperational considerations that are necessary to ensure the reliable operation of the Bulk \n19 \nElectric System and consistency with established planning and operational practices. In \n20 \nparticular, the provision of Firm Contract Demand Service on behalf of Co‑Located Load \n21 \nshould be conditioned on demonstrating that such load is physically and operationally \n22 \ncapable of being managed in a manner consistent with its firm service designation.  \n23"},{"page":9,"startToken":2452,"endToken":2737,"text":"Exhibit No. PTO-0001 \nPage 9 of 39 \nAccordingly, the PJM Transmission Owners recommend the Commission adopt \n1 \nrequirements that may include, among other things: (1) compliance with applicable \n2 \ninterconnection requirements, including the ability to control and measure load consistent \n3 \nwith PJM operating needs; (2) demonstrated capability to respond to curtailment or \n4 \noperational instructions, including the ability to reduce or interrupt loads as necessary to \n5 \nsupport system reliability; and (3) adherence to defined operating practices, including \n6 \ntelemetry, metering, and communications requirements necessary for real‑time monitoring \n7 \nand control.  \n8 \nIn addition, further consideration may also be warranted in a transmission \n9 \nconstrained area where a significant amount of Co-Located Load taking Firm Contract \n10 \nDemand Service relies on operational controls, such as Special Protection Schemes \n11 \n(“SPS”) and Remedial Action Schemes (“RAS”), to curtail load back to the level of \n12 \ncontract demand following the loss of on-site generation. In such circumstances, customers \n13 \nmay be required to either take a higher level of contract demand or to take NITS for their \n14 \ngross load, because the risk of simultaneous SPS/RAS failure in the local area may be \n15 \nelevated and could result in cascading grid failure.   \n16 \nQ. \nWhat are appropriate mechanisms for an anti-toggling feature for Firm Contract \n17 \nDemand Service? \n18 \nA. \n[Blazunas] Pursuant to the Order, Firm Contract Demand Service will have a minimum \n19 \nterm of one year. However, as the Commission recognized, there are concerns regarding a \n20 \ncustomer’s ability to toggle between firm and non-firm service levels.8 There also is a \n21 \nconcern that Firm Contract Demand Service customers will cause the need for transmission \n22 \n8\nOrder at P 213."},{"page":10,"startToken":2737,"endToken":3081,"text":"Exhibit No. PTO-0001 \nPage 10 of 39 \nupgrades and capacity resource procurement to accommodate their Firm Contract Demand \n1 \nService and then exit the system, thereby shifting costs to other customers.9 To partially \n2 \naddress these concerns, the PJM Transmission Owners recommend a five-year minimum \n3 \ncommitment period for Firm Contract Demand Service, consistent with the five-year \n4 \nminimum commitment noted by the Commission for loads seeking to procure their own \n5 \ncapacity.10\n6 \nQ. \nDo the PJM Transmission Owners have a proposal with respect to notice obligations? \n7 \nA. \n[Blazunas] Yes. With respect to notice obligations, the PJM Transmission Owners suggest \n8 \nthat the Commission adopt the same requirements that currently apply to notices of \n9 \ntermination for NITS under Section 2.5 of the PJM Tariff.11\n10 \nB. \nNon-Firm Contract Demand Transmission Service \n11 \nQ. \nWhat is Non-Firm Contract Demand transmission service?   \n12 \nA.   \n[Blazunas] Under the Order, the Commission established a new Non-Firm Contract \n13 \nDemand transmission service (“Non-Firm Contract Demand Service”) to be offered to \n14 \nEligible Customers taking service on behalf of Co-Located Loads. This new service will \n15 \npermit Eligible Customers taking service on behalf of such loads to seek to withdraw \n16 \n9\nId. at P 213.   \n10\nId. \n11\nPJM Tariff, Section 2.5 (“Although Regional Network Integration Service is presumed to continue without \nexpiration, it may be terminated where:  \n1)\nAn incumbent Network Customer will be replaced by a successor Network Customer, in which case the \nincumbent’s service shall only terminate if the successor agrees to commence the taking of service, the \nappropriate service agreement is executed, and all other applicable terms and conditions of the PJM \nGoverning Agreements are satisfied; \n2)\nAn incumbent Network Customer seeks to terminate its service and no successor Network Customer \nexists, in which case the incumbent must provide PJM with forty-two (42) months’ notice prior to the \ncommencement of a Delivery Year, subject to receiving all necessary regulatory approvals for such \ntermination, if any; or  \n3)\nOn such other date mutually agreed upon by the parties.”)."},{"page":11,"startToken":3081,"endToken":3362,"text":"Exhibit No. PTO-0001 \nPage 11 of 39 \nenergy from the transmission system from time to time when transmission capacity is \n1 \navailable and not needed by firm customers.12\n2 \nPursuant to the Order, the new Non-Firm Contract Demand Service will be \n3 \navailable during normal operations and curtailed during emergency operations (i.e., it will \n4 \nbe curtailed before existing firm transmission services and the new Firm Contract Demand \n5 \nService). Under this service, Eligible Customers may reserve transmission service on \n6 \nbehalf of a Co-Located Load as needed during normal, non-emergency system operating \n7 \nconditions.   \n8 \nAs specified in the Order, reservations for Non-Firm Contract Demand Service will \n9 \nbe permitted only when there is available transmission capacity, similar to existing non-\n10 \nfirm transmission service options in the PJM Tariff. Moreover, reservations will be \n11 \navailable for terms ranging from one hour to one month, consistent with the terms available \n12 \nfor non-firm PTPS currently in the PJM Tariff. Finally, Eligible Customers may use Non-\n13 \nFirm Contract Demand Service to make use of the transmission system above their Firm \n14 \nContract Demand Service level, if transmission capacity is available.13\n15 \nQ. \nWhat is the PJM Transmission Owners’ proposed rate design for the new Non-Firm \n16 \nContract Demand Service? \n17 \nA. \n[Blazunas] As with Firm Contract Demand Service, the PJM Transmission Owners \n18 \npropose that the rate design for Non-Firm Contract Demand Service be based on zonal \n19 \nNITS rates in PJM. Under this approach, the maximum rate for Non-Firm Contract \n20 \nDemand Service on behalf of Co-Located Load will be calculated by multiplying (i) their \n21 \n12\nOrder at P 214. \n13\nId. at P 215."},{"page":12,"startToken":3362,"endToken":3728,"text":"Exhibit No. PTO-0001 \nPage 12 of 39 \nreserved, non-firm contract demand amount (in MWs) by (ii) the applicable zonal NITS \n1 \nrate. In the same manner as non-firm PTPS today, PJM will have the ability to offer a \n2 \ndiscount off of this maximum rate based on rules and criteria established by the PJM \n3 \nTransmission Owners. \n4 \nFinally, as with Firm Contract Demand transmission service, Eligible Customers \n5 \ntaking Non-Firm Contract Demand Service also will pay a Grid Reliance Charge \n6 \nrepresenting the remaining on-site load not covered by either Firm Contract Demand \n7 \nService or Non-Firm Contract Demand Service. The base rate for Non-Firm Contract \n8 \nDemand Service is adjusted to reflect the impact of the Grid Reliance Charge in order to \n9 \nprevent double-recovery. The Grid Reliance Charge is discussed in further detail below. \n10 \nA detailed example of the calculation of the Non-Firm Contract Demand Service \n11 \nrate and other new service charges is set forth below.  \n12 \nQ. \nWhy is it appropriate to use the same rate for Firm Contract Demand Service to \n13 \nestablish the maximum rate for the Non-Firm Contract Demand Service? \n14 \nA. \n[Blazunas] For the reasons outlined above with respect to Firm Contract Demand Service, \n15 \nusing the applicable zonal NITS rate to establish the base rate for Non-Firm Contract \n16 \nDemand Service is appropriate. In addition, using the same maximum base rate for Firm \n17 \nContract Demand Service and Non-Firm Contract Demand Service is just and reasonable. \n18 \nThe Commission has traditionally permitted non-firm PTPS to be priced up to (but not \n19 \nabove) the rate used for firm PTPS,14 and many transmission owners have identical \n20 \n14\nSee Promoting Wholesale Competition Through Open Access Non-Discriminatory Transmission Servs. by \nPub. Utils.; Recovery of Stranded Costs by Pub. Utils. and Transmitting Utils., Order No. 888, FERC Stats. & Regs. \n¶ 31,036, at 31,780 (1996) (cross-referenced at 75 FERC ¶ 61,080) (noting the importance of allowing pricing \nflexibility and indicating that the non-firm rate is capped at the firm rate), on reh’g, Order No. 888-A, FERC Stats. & \nRegs. ¶ 31,048 (cross-referenced at 78 FERC ¶ 61,220), on reh’g, Order No. 888-B, 81 FERC ¶ 61,248 (1997), on"},{"page":13,"startToken":3728,"endToken":4152,"text":"Exhibit No. PTO-0001 \nPage 13 of 39 \nmaximum base rates for firm and non-firm service, including in PJM. Also, Non-Firm \n1 \nContract Demand Service will represent a superior level of service compared to non-firm \n2 \nPTPS because pursuant to PJM’s proposed operational procedures, Non-Firm Contract \n3 \nDemand Service customers will have the benefit of PJM re-dispatching generation prior to \n4 \ncurtailing Non-Firm Contract Demand Service. Combined with the additional flexibility \n5 \nthat Non-Firm Contract Demand Service customers will have with respect to arranging and \n6 \nscheduling Non-Firm Contract Demand Service, and the fact that Non-Firm Contract \n7 \nDemand Service customers will not pay for generation capacity,15 it is just and reasonable \n8 \nto set the maximum Non-Firm Contract Demand Service rate equal to the rate for Firm \n9 \nContract Demand Service customers on a $/MWh basis.16\n10 \nQ. \nUnder what circumstances would the PJM Transmission Owners offer a discount for \n11 \nNon-Firm Contract Demand Service? \n12 \nA. \n[Blazunas] First, under the current PJM Tariff, maximum rates for non-firm PTPS are set \n13 \nequal to rates for firm PTPS, although PJM has the ability to offer discounts for Non-Firm \n14 \nPTPS subject to certain requirements, and based on rules and criteria established by the \n15 \nPJM Transmission Owners.17 The PJM Transmission Owners propose a similar flexibility \n16 \nreh’g, Order No. 888-C, 82 FERC ¶ 61,046 (1998), aff’d in relevant part sub nom., Transmission Access Pol’y Study \nGrp., v. FERC, 225 F.3d 667 (D.C. Cir. 2000), aff’d sub nom., N.Y. v. FERC, 535 U.S. 1 (2002).\n15\nSee Order at P 218 (“The new Non-Firm Contract Demand transmission service will not include a charge for \ngeneration capacity.”). \n16\nThis would be comparable to the rules the Commission established in Order No. 888 with respect to the \nrelationship between firm and non-firm point-to-point transmission service rate. See Order No. 888 at 31,780. \n17\nSchedules 7 and 8 of the PJM Tariff state: \n[t]hree principal requirements apply to discounts for transmission service as follows: (1) any offer \nof a discount made by the Transmission Provider must be announced to all Eligible Customers solely \nby posting on the OASIS, (2) any customer-initiated requests for discounts (including requests for \nuse by one’s wholesale merchant or an Affiliate’s use) must occur solely by posting on OASIS, and \n(3) once a discount is negotiated, details must be immediately posted on the OASIS. For any \ndiscount agreed upon for service on a path, from point(s) of receipt to point(s) of delivery, the"},{"page":14,"startToken":4152,"endToken":4484,"text":"Exhibit No. PTO-0001 \nPage 14 of 39 \nfor Non-Firm Contract Demand Service. The Commission directed the implementation of \n1 \na Non-Firm Contract Demand Service to act as a limited supplemental service that may be \n2 \nneeded for the benefit of Firm Contract Demand Service customers to ensure that such \n3 \ncustomers can serve on-site load, for instance, when its on-site generator is on outage, but \n4 \nnot as a substitute for Firm Contract Demand Service. Also relevant is the fact that the \n5 \nhistorical purpose of a discount on non-firm transmission service is to encourage the \n6 \nefficient use of the transmission system – i.e., to ensure that the system is being utilized \n7 \noptimally. Before determining whether a discount is appropriate, and at what level it should \n8 \nbe set, it is necessary for the PJM Transmission Owners to gather data on how Non-Firm \n9 \nContract Demand Service customers are utilizing the service, taking into account the \n10 \nintended purposes of the service, and the effect of that utilization on the system. \n11 \nAccordingly, the PJM Transmission Owners will consider on a going-forward basis \n12 \nwhether a discount is appropriate for Non-Firm Contract Demand Service based on system \n13 \nconditions and use patterns and, if so, the criteria and limits under which PJM will apply \n14 \nthe discount. \n15 \nIt is worth re-emphasizing that Non-Firm Contract Demand Service will represent \n16 \na superior level of service compared to non-firm PTPS because Non-Firm Contract \n17 \nDemand Service customers will have the benefit of PJM re-dispatching generation prior to \n18 \ntheir curtailment based on PJM’s proposed operational procedures. Non-Firm Contract \n19 \nDemand Service customers will also have additional flexibility with respect to arranging \n20 \nand scheduling their service and will not pay for generation capacity.   \n21 \nTransmission Provider must offer the same discounted transmission service rate for the same time \nperiod to all Eligible Customers on all unconstrained transmission paths that go to the same point(s) \nof delivery on the Transmission System."},{"page":15,"startToken":4484,"endToken":4773,"text":"Exhibit No. PTO-0001 \nPage 15 of 39 \nAny discount offered for Non-Firm Contract Demand Service would be offered by \n1 \nPJM based on rules and  criteria established by the PJM Transmission Owners designed to \n2 \nincentivize the efficient use of Non-Firm Contract Demand Service and the transmission \n3 \nsystem.  \n4 \nQ. \nHow do the PJM Transmission Owners propose to treat the revenues received from \n5 \nNon-Firm Contract Demand Service charges? \n6 \nA. \n[Blazunas] To ensure against double recovery, all revenues received from Non-Firm \n7 \nContract Demand Service charges will be credited to NITS and Firm Contract Demand \n8 \nService customers based on their share of the coincident peak load, inclusive of the contract \n9 \ndemand associated with Firm Contract Demand Service, of the zone where the Co-Located \n10 \nLoad is physically located. These credits will reduce the total transmission costs for these \n11 \ncustomers, and ensure that these customers, who pay rates based on all of the costs of the \n12 \ntransmission system, receive the credits associated with Non-Firm Contract Demand \n13 \nService customers’ use of excess capacity on that system. The credits will be applied to \n14 \nNITS and Firm Contract Demand Service customers through their PJM bills. This will \n15 \nminimize or eliminate the need for the PJM Transmission Owners to modify their formula \n16 \nrates. \n17 \nC. \nInterim, Non-Firm Transmission Service \n18 \nQ. \nWhat is interim, non-firm transmission service?  \n19 \nA.  \n[Blazunas] Under the Order, interim, non-firm transmission service, also sometimes \n20 \nreferred to as “Interim NITS,” allows an Eligible Customer that has requested NITS on \n21 \nbehalf of a Co-Located Load to take non-firm transmission service that can be interrupted \n22 \nuntil the network upgrades necessary to provide NITS are complete and the Co-Located \n23"},{"page":16,"startToken":4773,"endToken":5051,"text":"Exhibit No. PTO-0001 \nPage 16 of 39 \nLoad can be designated as network load. Interim, non-firm transmission service is \n1 \ntemporary. That is, it is only available to Eligible Customers that have requested NITS on \n2 \nbehalf of Co-Located Loads that cannot yet be reliably served with NITS, and it is available \n3 \nonly until the necessary network upgrades are completed and the Co-Located Load is \n4 \ndesignated as network load. Moreover, this new service is optional for an Eligible \n5 \nCustomer seeking NITS on behalf of a Co-Located Load and is available only to the extent \n6 \nPJM determines that it can provide some level of interim service reliably.18\n7 \nQ. \nWhat is the PJM Transmission Owners’ proposed rate design for the new interim, \n8 \nnon-firm transmission service? \n9 \nA. \n[Blazunas] The PJM Transmission Owners propose that the rate design for interim, non-\n10 \nfirm transmission service be based on the full, zonal NITS rates, as permitted under the \n11 \nOrder.19 Under this approach, Eligible Customers taking interim, non-firm transmission \n12 \nservice will pay a transmission service charge calculated by multiplying: (i) their measured \n13 \ndemand amount (in MWs) multiplied by (ii) the applicable zonal NITS rate. The measured \n14 \ndemand amount will be the MW level that PJM determines the transmission system can \n15 \nreliably support under all pre-upgrade operating conditions. \n16 \nCharging the full, zonal NITS rate is consistent with the Order, which stated that \n17 \ninterim, non-firm transmission service would be charged the NITS rate.20 Essentially, \n18 \ninterim, non-firm transmission service is a temporary, “speed-to-market” tool that allows \n19 \n18\nOrder at P 200. \n19\nId. at P 200. \n20\nId."},{"page":17,"startToken":5051,"endToken":5354,"text":"Exhibit No. PTO-0001 \nPage 17 of 39 \na Co-Located Load project to energize on an as-available basis while permanent, necessary \n1 \ntransmission upgrades are in the PJM queue.   \n2 \nV. \nGRID RELIANCE CHARGE \n3 \nQ. \nAbove, you explained that Eligible Customers taking Firm Contract Demand Service \n4 \nand Non-Firm Contract Demand Service also will pay a Grid Reliance Charge.  Please \n5 \nexplain that charge.   \n6 \nA. \n[Schafer] As contemplated under the Order, the PJM Transmission Owners are proposing \n7 \nto include a Grid Reliance Charge as part of the charges associated with the new Co-\n8 \nLocated Load terms and conditions under the PJM Tariff. The intent of the Grid Reliance \n9 \nCharge is to reflect the inherent benefits that Firm Contract Demand Service and Non-Firm \n10 \nContract Demand Service customers receive as a result of their reliance upon the grid. It is \n11 \ndesigned to recover the costs of delivering ancillary services, including the delivery of \n12 \nblack start and regulation, and providing synchronization and grid reliance support, thereby \n13 \nensuring Co‑Located Loads pay their appropriate share of the transmission system that they \n14 \nrely on regardless of whether they withdraw energy from the grid. The Grid Reliance \n15 \nCharge also recognizes the benefits associated with monitoring and other activities that \n16 \ntransmission owners will need to perform associated with the increased number of \n17 \nprotective systems that will be required for Co-Located Load customers.   \n18 \nAs the Commission recognized, Co-Located Loads are electrically connected to the \n19 \ntransmission system (not islanded) and therefore benefit from the system and should \n20 \ncontribute to the ongoing operation and maintenance of the transmission system, consistent \n21 \nwith foundational cost causation principles. Commissioner Chang’s concurrence to the \n22 \nOrder stressed the need for a minimum charge for the two new contract demand services.  \n23"},{"page":18,"startToken":5354,"endToken":5705,"text":"Exhibit No. PTO-0001 \nPage 18 of 39 \nThe Commissioner noted that a customer selecting a de minimis contract demand could \n1 \npay almost nothing despite its continuous reliance on the grid. \n2 \nEven with a zero MW contract demand, a large Co‑Located Load still depends on \n3 \nthe grid for the delivery of various ancillary services and a suite of synchronization support \n4 \nservices, such as a stable frequency, inertia, stability services (damping, angle stability), \n5 \nfault current capability, and ride-through and protection coordination. For example, adding \n6 \na 1,000 MW load to the transmission system inherently imposes electrical impacts at the \n7 \npoint of interconnection and beyond. In summary, zero net withdrawals are not indicative \n8 \nof a load’s actual reliance on the grid. And, of course, a large Co-Located Load, such as a \n9 \ndata center, would not be interested in locating in PJM if the system did not also support \n10 \nan extensive network of customers and communications infrastructure. \n11 \nQ. \nWhat is the PJM Transmission Owners’ proposed rate design for the new Grid \n12 \nReliance Charge? \n13 \nA. \n[Schafer] The PJM Transmission Owners propose to apply a new Grid Reliance Charge \n14 \nrate to an Eligible Customer’s gross on-site load not covered by Firm Contract Demand \n15 \nService.21 Practically speaking, this means that Firm Contract Demand Service customers \n16 \nwill pay the full zonal NITS/Firm Contract Demand rate on their Firm Contract Demand \n17 \nand the Grid Reliance Charge rate on the difference between their gross load and their Firm \n18 \nContract Demand. This approach is reasonable because it recognizes the fact that Firm \n19 \nContract Demand Service customers are already paying for the services recovered via the \n20 \nGrid Reliance Charge through the full zonal NITS rate assessed on their Firm Contract \n21 \n21\nA handful of PJM transmission owners continue to utilize stated rates, which in some cases are based on \nblack-box settlements and may need to be accounted for in specific stated rates for the new firm and non-firm contract \ndemand services.  This also applies to the Grid Reliance Charge."},{"page":19,"startToken":5705,"endToken":5985,"text":"Exhibit No. PTO-0001 \nPage 19 of 39 \nDemand. Consequently, the Grid Reliance Charge rate only needs to be assessed on any \n1 \nincremental gross load in excess of their Firm Contract Demand. Eligible Customers taking \n2 \nonly Non-Firm Contract Demand Service would pay the Grid Reliance Charge on their \n3 \nentire load, but as noted above, the Non-Firm Contract Demand Service rate is calculated \n4 \nso as to remove the Grid Reliance Charge, so there will be no double-charging of Non-\n5 \nFirm Contract Demand Service customers. \n6 \nQ. \nHow do the PJM Transmission Owners propose to calculate the new Grid Reliance \n7 \nCharge rate? \n8 \nA. \n[Schafer] The PJM Transmission Owners propose to calculate the Grid Reliance Charge \n9 \nrate using a standardized, percentage-based methodology that relies on publicly available \n10 \nFERC Form No. 1 (“FERC Form 1”) data for PJM Transmission Owners22 to determine \n11 \nthe portion of transmission depreciation and operation and maintenance (“O&M”) expense \n12 \nassociated with grid reliance capability, and then applies that portion (expressed as a \n13 \npercentage) to each transmission owner’s Attachment H annual transmission revenue \n14 \nrequirement (“TRR”).  \n15 \nThe first step in the proposed methodology is to identify transmission plant \n16 \naccounts and transmission O&M FERC accounts that provide grid reliance capability, \n17 \ndescribed above as related to: (1) supporting the delivery of ancillary services; and (2) \n18 \nproviding synchronization support required to accommodate the load’s electrical \n19 \ncharacteristics. Tables 1 and 2 below summarize the FERC accounts identified as \n20 \nsupporting grid reliance capability: \n21 \n22\nFERC Form 1 data is publicly available for PJM Transmission Owners, representing approximately 95 \npercent of the total transmission assets in PJM."},{"page":20,"startToken":5985,"endToken":6198,"text":"Exhibit No. PTO-0001 \nPage 20 of 39 \n1 \nTable 1: FERC Accounts Identified as Supporting Grid Reliance Capabilities - Depreciation \nFERC \nAccount \nAccount Description \nBasis for Retention \nSupported Grid Reliance Charge \nFunctions \n(A) \n(B) \n(C)  \n(D) \nDepreciation Expense Related to the Following Accounts \n350 \nLand and Land Rights \nPhysical footprint required for \nsubstations and transmission \nfacilities.\n352 \nStructures and \nImprovements \nHouses essential transmission and \ncontrol equipment. \nControl center housing, restoration facilities, \nAS control rooms, black-start interfaces\n353 \nStation Equipment \nCore equipment required to energize, \nsynchronize, and control the grid. \nSynchronization, protection, voltage \nstability, AS interfaces, regulation & \nreactive delivery\n354 \nTowers and Fixtures \nPhysical support of energized \ntransmission facilities. \nBaseline transmission support, AS signal \nrouting, restoration paths\n355 \nPoles and Fixtures \nPhysical support of energized \ntransmission facilities. \nBaseline transmission support, AS signal \nrouting, restoration paths\n356 \nOverhead Conductors \nand Devices \nPrimary electrical pathways required \nfor synchronization. \nBaseline connectivity, control, telemetry, AS \nsignal paths\n357 \nUnderground Conduit \nPrimary electrical pathways required \nfor synchronization. \nBaseline connectivity, control, telemetry, AS \nsignal paths\n358 \nUnderground \nConductors and \nDevices\nPrimary electrical pathways required \nfor synchronization. \nBaseline connectivity, control, telemetry, AS \nsignal paths\n359 \nRoads and Trails \nAllows access to the infrastructure in \nthe above accounts.\nSupports the above-listed functions\n2 \n3 \n4 \n5 \n6 \n7 \n8 \n9 \n10 \n11 \n12"},{"page":21,"startToken":6198,"endToken":6518,"text":"Exhibit No. PTO-0001 \nPage 21 of 39 \n1 \nTable 2: FERC Accounts Identified as Supporting Grid Reliance Capabilities - O&M \nFERC \nAccount \nAccount \nDescription \nBasis for Retention \nSupported Grid Reliance \nCharge Functions \n(A) \n(B) \n(C)  \n(D) \nOperation and Maintenance Expense From the Following Accounts \n561 \nLoad Dispatch \nThe cost of labor, materials, and expenses incurred in \ndirecting the operation of the electric transmission system \nand dispatching loads.  \n[O&M accounts support the \nfunctions identified for the plant \naccounts]\n562 \nStation Expenses \nOperation expense required to keep substations energized, \nprotected, and operational. \n563 \nOverhead Line \nExpenses \nOperation necessary to maintain synchronized transmission \npaths. \n564 \nUnderground Line \nExpenses \nOperation expense related to Primary electrical pathways \nrequired for synchronization. \n570 \nMaintenance of \nStation Equipment \nMaintenance of Core equipment required to energize, \nsynchronize, and control the grid. \n571 \nMaintenance of \nOverhead Lines \nMaintenance of Primary electrical pathways required for \nsynchronization. \n572 \nMaintenance of \nUnderground Lines \nMaintenance of Primary electrical pathways required for \nsynchronization. \n2 \nIn the second step, for the identified transmission plant accounts and transmission \n3 \nO&M accounts, FERC Form 1 data is used to calculate the percentage of Grid Reliance \n4 \nCharge-related depreciation and O&M expenses by summing 100 percent of the expense \n5 \nassociated with each identified account and then dividing by the category total. FERC \n6 \naccounts 561-564 and 570-572 are identified as Grid Reliance Charge-related O&M \n7 \naccounts, and the amounts in those accounts will be summed and then divided by the total \n8 \nTransmission O&M amount from the FERC Form 1 to derive the percentage of Grid \n9 \nReliance Charge-related O&M.23 FERC accounts 350-359 are identified as Grid Reliance \n10 \nCharge-related plant accounts. These accounts constitute 100 percent of the transmission \n11 \n23\nNote that the O&M percentage calculations will include the removal of Account 565 – Transmission of \nElectricity by Others, consistent with the treatment of this account in Attachment H."},{"page":22,"startToken":6518,"endToken":6817,"text":"Exhibit No. PTO-0001 \nPage 22 of 39 \ndepreciation category. Therefore, 100 percent is used as the appropriate percentage of \n1 \ntransmission depreciation to include in the calculation.  \n2 \nThese percentages are developed exclusively from FERC Form 1 account-level \n3 \ndata. Account balances are either included in full or excluded in full. This ensures that the \n4 \npercentage calculations are transparent, replicable, and based entirely on recorded \n5 \naccounting data.   \n6 \nIn the third step, the FERC Form 1-developed percentages are applied to the \n7 \ntransmission depreciation expense and transmission O&M expense reported in the \n8 \ntransmission owner’s annual TRR filing, Attachment H. The sum of the resulting Grid \n9 \nReliance Charge-related depreciation and O&M amounts constitutes the Grid Reliance \n10 \nCharge revenue requirement. Note that only amounts directly related to the transmission \n11 \nportions of depreciation and O&M are included in this calculation. Amortization and \n12 \ngeneral-plant depreciation are not included in the depreciation calculation. Likewise, \n13 \nAdministrative and General expenses are not included in the O&M calculation.  \n14 \nIn the fourth step, the Grid Reliance Charge revenue requirement is divided by the \n15 \nnet revenue requirement from the transmission owner’s TRR, Attachment H to derive a \n16 \nGrid Reliance Charge percentage of the net revenue requirement. This Grid Reliance \n17 \nCharge percentage is calculated as described above for all PJM Transmission Owners.  \n18 \nFinally, the average of all the PJM Transmission Owners’ calculated Grid Reliance \n19 \nCharge percentages is taken. This average Grid Reliance Charge percentage will be used \n20 \nin the calculation of all the PJM Transmission Owners’ Grid Reliance Charge calculations \n21 \nand employed in the following manner to derive the final Grid Reliance Charge rate. First, \n22 \nthe average Grid Reliance Charge percentage will be applied to a transmission owner’s \n23"},{"page":23,"startToken":6817,"endToken":7142,"text":"Exhibit No. PTO-0001 \nPage 23 of 39 \nNITS rate to determine the initial Grid Reliance Charge rate. Second, this initial Grid \n1 \nReliance Charge rate must be adjusted to account for the difference between the measure \n2 \nof demand used to calculate the NITS rate (i.e., NITS customer load at zonal peak plus \n3 \ncontract demand for Firm Contract Demand Service) and the appropriate measure of \n4 \ndemand used to design the final Grid Reliance Charge rate.  \n5 \nThe Grid Reliance Charge will apply to the difference between the customers’ gross \n6 \nload and firm contract demand for Firm Contract Demand Service and Non-Firm Contract \n7 \nDemand Service customers. Consequently, the appropriate measure of demand to use to \n8 \ndesign the Grid Reliance Charge should include this additional load above Firm Contract \n9 \nDemand. Therefore, the final step in the development of the Grid Reliance Charge rate is \n10 \nto multiply the initial Grid Reliance Charge rate by a ratio equal to the demand used to \n11 \ncalculate NITS divided by the demand equal to that used to calculate NITS plus the \n12 \nadditional load above Firm Contract Demand. This will reduce the initial Grid Reliance \n13 \nCharge rate and ensure that the Grid Reliance Charge does not over-recover from Firm \n14 \nContract Demand and Non-Firm Contract Demand Service customers.  \n15 \nIn summary, the proposed methodology for the calculation of the Grid Reliance \n16 \nCharge rate uses FERC Form 1 data to identify the relative share of depreciation and O&M \n17 \nthat supports grid reliance, translates that share to the Attachment H revenue-requirement \n18 \nframework, and expresses it as a standardized percentage of the total transmission revenue \n19 \nrequirement. That percentage is then applied consistently across transmission owners to \n20 \ndevelop the Grid Reliance Charge rate.   \n21 \nAn exhibit that calculates the Grid Reliance Charge percentage for a single \n22 \ntransmission owner according to the methodology described above is provided as Exhibit \n23"},{"page":24,"startToken":7142,"endToken":7434,"text":"Exhibit No. PTO-0001 \nPage 24 of 39 \nNo. PTO-0003. Furthermore, the exhibit provides the average Grid Reliance Charge \n1 \npercentage for all PJM Transmission Owners, which will be applied to their respective \n2 \nNITS rates in order to calculate their individual Grid Reliance Charges. The initial \n3 \npercentage is 25.8 percent, subject to adjustment as discussed below. \n4 \nQ. \nDo the PJM Transmission Owners recommend that the Grid Reliance Charge be \n5 \nupdated and if so, how frequently? \n6 \nA. \n[Schafer] Yes. The PJM Transmission Owners propose that the resulting average Grid \n7 \nReliance Charge percentage be updated approximately every five years. A five-year term \n8 \nis reasonable for several reasons. Transmission depreciation rates and O&M structures \n9 \nchange gradually over time; they do not generally fluctuate greatly from year to year. A \n10 \nmulti-year period therefore avoids unnecessary annual recalculations while maintaining \n11 \nalignment with underlying cost structures. In addition, leaving the percentage in place for \n12 \nfive years promotes rate stability, reduces administrative burden for both utilities and \n13 \nregulators, and provides customers with predictable charges.  \n14 \nQ. \nWhy is the PJM Transmission Owners proposed Grid Reliance Charge methodology \n15 \njust and reasonable? \n16 \n[Schafer] The proposed Grid Reliance Charge methodology is just and reasonable for a \n17 \nnumber of reasons. First, the Grid Reliance Charge is intentionally limited to depreciation \n18 \nand O&M. Depreciation reflects the annualized consumption of the transmission \n19 \ninfrastructure that enables customers to rely on the grid, while O&M reflects the ongoing \n20 \nexpense required to keep that infrastructure functional. By excluding return on rate base \n21 \nand associated income taxes, the methodology produces a conservative result focused on \n22 \ncost recovery rather than investment return. This provides transparency, administrative \n23"},{"page":25,"startToken":7434,"endToken":7726,"text":"Exhibit No. PTO-0001 \nPage 25 of 39 \nsimplicity, and stability. Second, it relies on publicly reported and audited accounting data \n1 \nfrom those PJM Transmission Owners with formula rates that have reported O&M and \n2 \ndepreciation balances associated with assets in service.  This covers the vast majority \n3 \n(approximately 95 percent) of transmission facilities in PJM. Third, it avoids re-litigating \n4 \nor recalculating each utility’s rate base, return, or tax components. Fourth, it eliminates the \n5 \nneed for company-specific engineering allocations. Fifth, by expressing the Grid Reliance \n6 \nCharge as a percentage of the total transmission revenue requirement, it scales \n7 \nproportionally with each utility’s size and cost structure. Finally, the Grid Reliance Charge-\n8 \npercentage averaging component further promotes administrative efficiency and rate \n9 \nstability. Individual transmission owners may exhibit modest year-to-year variations in \n10 \naccount structure or expense classification. Averaging the calculated Grid Reliance Charge \n11 \npercentages across all PJM Transmission Owners smooths those variations, reduces \n12 \nvolatility, and produces a reasonable proxy for the portion of transmission costs attributable \n13 \nto grid reliance on a regional basis. \n14 \nQ. \nHow do the PJM Transmission Owners propose to treat the revenues received from \n15 \nthe Grid Reliance Charge? \n16 \nA. \n[Schafer] Revenues from the Grid Reliance Charge will be applied as bill credits to \n17 \ncustomers receiving service via NITS (including interim, non-firm transmission service) \n18 \nand Firm Contract Demand Service, thereby reducing total transmission costs for these \n19 \ncustomers. This will ensure that the Grid Reliance Charge does not result in a double \n20 \nrecovery for the PJM Transmission Owners or inappropriate cost shifts. The credit will be \n21 \napplied to the bills of these customers in the zone where the Co-Located Load is physically \n22 \nconnected.   \n23"},{"page":26,"startToken":7726,"endToken":8012,"text":"Exhibit No. PTO-0001 \nPage 26 of 39 \nVI. \nEXAMPLE OF RATE DESIGNS FOR NEW SERVICES \n1 \nQ. \nAbove you described the rate designs for Firm Contract Demand Service, Non-Firm \n2 \nContract Demand Service, and interim, non-firm transmission service. Please provide \n3 \nan example of how each of these services will be calculated. \n4 \nA. \n[Blazunas] An example of the rate designs for each of these three services is provided as \n5 \nExhibit No. PTO-0004 and is described below.24\n6 \nFirst, the transmission rate for Firm Contract Demand Service will be the same rate \n7 \nas the rate for NITS and interim, non-firm transmission service. Practically speaking, the \n8 \ncalculation of the transmission rate for NITS, interim, non-firm transmission service, and \n9 \nFirm Contract Demand Service, will be the same as the calculation for NITS currently \n10 \nexcept that the divisor in the calculation of the rate will necessarily need to include, in \n11 \naddition to the measure of the single coincident peak (“CP”) for NITS and interim, non-\n12 \nfirm transmission service customers, the firm contract demand associated with Firm \n13 \nContract Demand Service. Hence, the rate for NITS, Firm Contract Demand Service, and \n14 \ninterim, non-firm transmission service will be calculated using the net revenue requirement \n15 \nfrom the PJM Transmission Owner’s Attachment H divided by the CP, taking into account \n16 \nall NITS, interim, non-firm transmission service, and Firm Contract Demand Service \n17 \ndemand. Table 3 below shows an example calculation of the transmission rates for NITS, \n18 \ninterim, non-firm transmission service, and Firm Contract Demand Service: \n19 \n20 \n21 \n24\nThe example calculates a maximum rate for Non-Firm Contract Demand Service although, as discussed \nabove, this rate may be discounted, if appropriate."},{"page":27,"startToken":8012,"endToken":8273,"text":"Exhibit No. PTO-0001 \nPage 27 of 39 \n1 \nTable 3: Example Calculation of Transmission Rate for NITS, interim, non-firm transmission service, and Firm \nContract Demand Service \nComponent \nSource/Calculation \nAmount \n(a) Gross Revenue Requirement\n$1,000,000,000\n(b) Revenue Credits\n($50,000,000)\n(c) True-Up Adjustment\n($50,000,000)\n(d) Net Revenue Requirement \n= (a) + (b) + (c) \n$900,000,000 \n(e) 1 CP – NITS (MW/Year)\n7,250\n(f) 1 CP – interim, non-firm transmission service \n(MW/Year)\n500 \n(g) Firm Contract Demand – Firm Contract Demand \nService (MW/Year)\n2,000 \n(h) Total MW/Year \n= (e) + (f) + (g) \n9,750 \n(i) Transmission Rate ($/MW/Year)  \n= (d) ÷ (h) \n$92,308 \n2 \nAs discussed above, the PJM Transmission Owners propose to calculate the Grid \n3 \nReliance Charge rate using a standardized, percentage-based methodology that relies on \n4 \npublicly available FERC Form 1 data to determine the portion of transmission depreciation \n5 \nand O&M expense associated with grid reliance capability, and then applies that portion \n6 \n(expressed as a percentage) to each transmission owner’s calculated transmission rate for \n7 \nNITS, interim, non-firm transmission service, and Firm Contract Demand Service. The \n8 \nGrid Reliance Charge rate is also adjusted to account for the difference between the \n9 \nmeasure of demand used to calculate the transmission rates for NITS, interim, non-firm \n10 \ntransmission service, and Firm Contract Demand Service, and the appropriate measure of \n11 \ndemand used to design the final Grid Reliance Charge rate. Table 4 below shows an \n12 \nexample of the calculation of the Grid Reliance Charge rate: \n13 \n14 \n15 \n16 \n17"},{"page":28,"startToken":8273,"endToken":8496,"text":"Exhibit No. PTO-0001 \nPage 28 of 39 \n1 \nTable 4: Example Calculation of the Grid Reliance Charge \nComponent \nSource/Calculation \nAmount \n(i) Transmission Rate ($/MW/Year) – NITS, \ninterim, non-firm transmission service, and Firm \nContract Demand Service\nTable 3, (i) \n$92,308 \n(j) Grid Reliance Charge Percentage\n25.8%\n(k) Grid Reliance Charge ($/MW/Year) \n(Unadjusted)\n= (i) x (j) \n$23,815 \n(l) Total MW/Year (Transmission Service)\nTable 3, (h)\n9,750\n(m) Contract Demand Gross Load in Excess of \nFirm Contract Demand (MW/Year)\n522 \n(n) Total MW/Year (Transmission Service Plus \nContract Demand Gross Load in Excess of Firm \nContract Demand)\n= (l) + (m) \n10,272 \n(o) Ratio of Total MW/Year (Transmission \nService) to Total MW/Year (Transmission \nService Plus Contract Demand Gross Load in \nExcess of Firm Contract Demand)\n= (l) ÷ (n) \n0.9492 \n(p) Grid Reliance Charge ($/MW/Year) \n= (k) x (o)\n$22,605\n2 \nThe revenues received from Firm Contract Demand Service and Non-Firm Contract \n3 \nDemand Service customers will consequently be returned to NITS, interim, non-firm \n4 \ntransmission service, and Firm Contract Demand Service customers as bill credits on the \n5 \nbasis of the same billing determinants used to design the transmission rate for NITS, \n6 \ninterim, non-firm transmission service, and Firm Contract Demand Service, as shown in \n7 \nTable 5 below: \n8 \n9 \n10 \n11 \n12 \n13 \n14"},{"page":29,"startToken":8496,"endToken":8775,"text":"Exhibit No. PTO-0001 \nPage 29 of 39 \n1 \nTable 5: Example Calculation of Bill Credits (Grid Reliance Charge) \nComponent \nSource/Calculation \nAmount \n(p) Grid Reliance Charge ($/MW/Year) \nTable 4, (p)\n$22,605\n(q) Contract Demand (Firm Contract Demand \ntransmission service and Non-Firm Contract \nDemand Service) Gross Load (MW/Year)\nTable 3, (g) + Table 4, (m) \n2,522 \n(r) Firm Contract Demand (MW/Year)\n2,000\n(s) Contract Demand Gross Load in Excess of \nFirm Contract Demand (MW/Year) \n= (q) – (r) \n522 \n(t) Grid Reliance Charge Revenue \n= (p) x (s) \n$11,799,810 \n(u) Total MW/Year\nTable 3, (h)\n9,750\n(v) Bill Credit ($/MW/Year) \n= (t) ÷ (u) \n($1,210) \n2 \nThe maximum rate for Non-Firm Contract Demand Service is calculated as the \n3 \nsame rate for NITS, interim, non-firm transmission service, and Firm Contract Demand \n4 \nService exclusive of the Grid Reliance Charge itself, as shown in Table 6 below. As \n5 \ndiscussed above, the PJM Transmission Owners will consider whether a discount to the \n6 \nNon-Firm Contract Demand Service is appropriate upon implementation: \n7 \n8 \nTable 6: Example Calculation of Transmission Maximum Rate for Non-Firm Contract Demand Service \nComponent \nSource/Calculation \nAmount \n(w) Transmission Rate ($/MW/Year) – NITS, \ninterim, non-firm transmission service, and Firm \nContract Demand Service\nTable 3, (i) \n$92,308 \n(x) Grid Reliance Charge ($/MW/Year) \nTable 4, (p)\n$22,605\n(y) Transmission Maximum Rate \n($/MW/Year) – Non-Firm Contract Demand \nService \n= (w) – (x) \n$69,703 \n9 \nThe revenues received from Non-Firm Contract Demand Service customers will \n10 \nconsequently be returned to NITS, interim, non-firm transmission service, and Firm \n11 \nContract Demand Service customers as bill credits on the basis of the same billing \n12"},{"page":30,"startToken":8775,"endToken":9077,"text":"Exhibit No. PTO-0001 \nPage 30 of 39 \ndeterminants used to design the transmission rate for NITS, interim, non-firm transmission \n1 \nservice, and Firm Contract Demand Service, as shown in Table 7 below: \n2 \n3 \nTable 7: Example Calculation of Bill Credits (Non-Firm Contract Demand Service) \nComponent \nSource/Calculation \nAmount \n(y) Transmission Maximum Rate ($/MW/Year) – \nNon-Firm Contract Demand Service\nTable 6, (y) \n$69,703 \n(z) Non-Firm Contract Demand (MW/Year)\n275\n(aa) Non-Firm Contract Demand Service \nRevenue \n= (y) x (z) \n$19,168,325 \n(bb) Total MW/Year\nTable 3, (h)\n9,750\n(cc) Bill Credit ($/MW/Year) \n= (aa) ÷ (bb) \n($1,966) \n4 \nBased on the above, NITS, interim, non-firm transmission service, Firm Contract \n5 \nDemand Service, and Non-Firm Contract Demand Service customers would pay rates for \n6 \ntransmission service as shown in Table 8 below: \n7 \n8 \nTable 8: Example Rates for NITS, interim, non-firm transmission service, Firm Contract Demand Service, and \nNon-Firm Contract Demand Service \nComponent \nSource/Calculation \nBilling Determinant \nAmount \n(dd) NITS – Transmission Service \n($/MW/Year)\nTable 3, (i) \nPer MW/Year (1CP) \n$92,308 \n(ee) Grid Reliance Charge Bill \nCredit ($/MW/Year)\nTable 5, (v) \nPer MW/Year (1CP) \n($1,210) \n(ff) Non-Firm Contract Demand \nService Bill Credit ($/MW/Year)\nTable 7, (cc) \nPer MW/Year (1CP) \n($1,966) \n(gg) NITS - Transmission Service \n($/MW/Year) (Effective Rate)  \n= (dd) + (ee) + (ff) \nPer MW/Year (1CP)\n$89,132 \n(hh) interim, non-firm transmission \nservice – Transmission Service \n($/MW/Year)\nTable 3, (i)\nPer MW/Year (1CP) \n$92,308\n(ii) Grid Reliance Charge Bill \nCredit ($/MW/Year)\nTable 5, (v) \nPer MW/Year (1CP) \n($1,210) \n(jj) Non-Firm Contract Demand \nService Bill Credit ($/MW/Year)\nTable 7, (cc) \nPer MW/Year (1CP) \n($1,966) \n(kk) interim, non-firm \ntransmission service – \nTransmission Service \n($/MW/Year) (Effective Rate) \n= (hh) + (ii) + (jj)\nPer MW/Year (1CP)\n$89,132"},{"page":31,"startToken":9077,"endToken":9429,"text":"Exhibit No. PTO-0001 \nPage 31 of 39 \n(ll) Firm Contract Demand Service \n– Transmission Service \n($/MW/Year)\nTable 3, (i)\nPer MW/Year (Firm \nContract Demand) \n$92,308\n(mm) Grid Reliance Charge Bill \nCredit ($/MW/Year)\nTable 5, (v)\nPer MW/Year (Firm \nContract Demand)\n($1,210)\n(nn) Non-Firm Contract Demand \nService Bill Credit ($/MW/Year)\nTable 7, (cc)\nPer MW/Year (Firm \nContract Demand)\n($1,966)\n(pp) Firm Contract Demand \ntransmission service – \nTransmission Service \n($/MW/Year) (Effective Rate) \n= (ll) + (mm) + (nn) \nPer MW/Year (Firm \nContract Demand)\n$89,132 \n(oo) Firm Contract Demand Service \n– Grid Reliance Charge \n($/MW/Year)\nTable 4, (p) \nPer MW/Year (Gross Load \nin Excess of Firm Contract \nDemand)\n$22,605 \n(pp) Non-Firm Contract Demand \nService – Transmission Service \n($/MW/Year)25\nTable 6, (y)\nMW/Year (Non-Firm \nContract Demand) \n$69,703\n(qq) Non-Firm Contract Demand \nService – Grid Reliance Charge \n($/MW/Year)\nTable 4, (p) \nPer MW/Year (Gross Load \nin Excess of Firm Contract \nDemand)\n$22,605 \n1 \nAs demonstrated above, based on the proposed rate designs, customers taking NITS, \n2 \ninterim, non-firm transmission service, and Firm Contract Demand Service pay the same effective \n3 \nbase rates for transmission service. Firm Contract Demand Service customers only pay the Grid \n4 \nReliance Charge on their gross load in excess of their firm contract demand.  \n5 \nVII. \nPENALTY CHARGE \n6 \nQ. \nAre the PJM Transmission Owners proposing new penalty charges? \n7 \nA. \n[Hammer] No, not at this time. I understand that PJM intends to propose operational \n8 \npenalties, and I agree the imposition of such penalties is appropriate. The PJM \n9 \nTransmission Owners believe that any penalty regime should rely on both operational \n10 \nconsequences as well as complementary financial penalties. The PJM Transmission \n11 \nOwners understand that, at a high level, PJM’s proposal would be to refer to FERC \n12 \nenforcement or applicable reliability organizations any failure to comply with PJM \n13 \n25\nConsistent with the Order, Non-Firm Contract Demand Service would be available for terms from one hour \nto one month, and rates for these terms would be calculated based on the annual rate.  Id. at P 215."},{"page":32,"startToken":9429,"endToken":9703,"text":"Exhibit No. PTO-0001 \nPage 32 of 39 \noperating instructions. In addition, PJM is proposing a “Two Strike, You’re NITS” \n1 \napproach pursuant to which if a customer’s protective systems fail to operate as required, \n2 \nPJM would first determine whether to impose a 120-day “pause” in service and, with the \n3 \nsecond failure, PJM would terminate the customer’s service under contract demand and the \n4 \ncustomer would be required to become a NITS customer if it wished to resume service.  \n5 \nThe PJM Transmission Owners believe this proposal is a good starting point conceptually \n6 \nbut recognize that additional details will need to be developed as to how these operational \n7 \nconsequences would be applied.   \n8 \nI believe that a financial penalty structure is appropriate to complement and \n9 \nsupplement operational penalties implemented by PJM. Although operational penalties \n10 \nwill likely serve as the primary deterrent against Co-Located Load customers exceeding \n11 \ntheir reserved use, financial penalties could still play a valuable role in enhancing this \n12 \ndeterrent as well as ensuring the market and other ratepayers are made whole if a Co-\n13 \nLocated Load customer exceeds its contract demand. In addition, it may also be appropriate \n14 \nto impose financial penalties when a Co-Located Load customer exceeds its contract \n15 \ndemand even if such exceedances are mitigated by an SPS or RAS installed on the \n16 \nTransmission Owner side of the point of interconnection. The PJM Transmission Owners \n17 \nintend to work with PJM in continuing to explore penalty options and will, if appropriate, \n18 \noffer a proposal at a subsequent stage of this paper hearing process. \n19 \n20 \n21 \n22 \n23"},{"page":33,"startToken":9703,"endToken":9994,"text":"Exhibit No. PTO-0001 \nPage 33 of 39 \nVIII. INTERCONNECTION REQUIREMENTS AND OPERATIONAL PRACTICES \n1 \nQ. \nWhat are NERC’s transmission planning standards and why is transmission owner \n2 \nand transmission provider compliance with those standards important? \n3 \nA. \n[Hammer] The North American Electric Reliability Corporation’s (“NERC”) \n4 \nTransmission Planning (“TPL”) standards establish mandatory planning requirements to \n5 \nensure the Bulk Electric System can reliably withstand credible contingencies over \n6 \nplanning horizons. TPL-001 Transmission System Planning Performance Requirements is \n7 \nthe foundational and currently enforceable transmission planning standard. Its purpose is \n8 \nto ensure that the Bulk Electric System is planned so it will operate reliably across a broad \n9 \nrange of system conditions and contingencies, from normal conditions to extreme events.   \n10 \nCompliance with the NERC TPL-001 requirements is important because they \n11 \nensure the transmission system is planned to reliably withstand credible outages and system \n12 \nstresses, reducing the risk of cascading failures and large-scale blackouts. For transmission \n13 \nowners and providers, TPL-001 compliance also minimizes regulatory and financial risk, \n14 \nsupports coordinated regional planning, and provides a defensible technical basis for \n15 \ntransmission investments needed to maintain long-term grid reliability. \n16 \nQ. \nDoes the Order’s proposal to rely on SPS/RAS to accommodate Co-Located Load \n17 \ntransmission service requests present any reliability or planning concerns? \n18 \nA. \n[Hammer] Yes. Under the principle of TPL-001, transmission planners must plan for load \n19 \nthat has the ability to draw power from the transmission system, not merely for load that is \n20 \nexpected or intended to do so under normal operating conditions. Reliance on SPS/RAS as \n21 \na substitute for timely network upgrades raises significant concerns under established good \n22 \nutility practices and applicable NERC reliability standards. SPS/RAS are generally \n23"},{"page":34,"startToken":9994,"endToken":10257,"text":"Exhibit No. PTO-0001 \nPage 34 of 39 \nintended as supplemental or last-resort reliability measures, not a primary tool to \n1 \naccommodate incremental transmission services on a routine or ongoing basis. In \n2 \nparticular, substituting SPS/RAS for network upgrade identification, design, coordination, \n3 \ntesting, and commissioning risks undermining the transparency and predictability of the \n4 \ntransmission planning process. Transmission Owners must ensure that all applicable \n5 \nperformance requirements under NERC Standard TPL‑001 remain satisfied, including \n6 \nunder stressed system conditions and under reasonable worst‑case assumptions such as \n7 \nSPS/RAS failure, mis-operation, or unavailability. \n8 \nAccordingly, any planning assumptions that rely on SPS/RAS must demonstrate \n9 \nacceptable system performance both with and without successful SPS/RAS operation.  \n10 \nAbsent such demonstrations, reliance on SPS/RAS to accommodate Co‑Located Load \n11 \ntransmission service requests could defer necessary upgrades, increase operational risk, \n12 \nand impede prudent transmission planning and reliable operation of the Bulk Electric \n13 \nSystem. \n14 \nQ. \nAre there any other grid challenges associated with utilizing SPS/RAS to ensure \n15 \nreliability in connection with Co-Located Load taking contract demand transmission \n16 \nservice? \n17 \nA.  \n[Hammer] Yes. SPS/RAS are operational tools rather than transmission facilities. While \n18 \nthey can be effective when properly designed and operated, they introduce dependencies \n19 \nrelated to system protection performance, communications, and coordination during \n20 \nstressed system conditions. Individual SPS/RAS-backed Firm Contract Demand Service \n21 \nrequests may appear manageable in isolation; however, the cumulative impact of multiple \n22 \nlarge Firm Contract Demand Service loads relying on SPS/RAS – particularly within the \n23"},{"page":35,"startToken":10257,"endToken":10491,"text":"Exhibit No. PTO-0001 \nPage 35 of 39 \nsame transmission constrained area – may present risks that are not fully reflected in \n1 \nexisting planning models. \n2 \nThere is also a broader planning precedent concern. If major reliability drivers \n3 \nidentified in planning are routinely mitigated through SPS/RAS in lieu of network \n4 \nupgrades, clarification is needed regarding the boundaries of this approach. Specifically, \n5 \nstakeholders should understand when infrastructure investment becomes necessary \n6 \nregardless of a customer’s willingness to curtail, particularly as load magnitude, geographic \n7 \nconcentration, and/or system stress increases. \n8 \nQ. \nGiven these grid challenges, what steps can PJM and the PJM Transmission Owners \n9 \ntake to ensure grid reliability while relying on SPS/RAS to provide contract demand \n10 \ntransmission service?  \n11 \nA. \n[Hammer] To ensure that any reliance on SPS/RAS remains consistent with transmission \n12 \nplanning practices and applicable reliability standards, the Commission should permit PJM \n13 \nand the PJM Transmission Owners to implement necessary guardrails in several areas, \n14 \nincluding: \n15 \n\nClearly defined eligibility criteria for Firm Contract Demand Service supported by \n16 \nSPS/RAS; \n17 \n\nFull redundancy of SPS/RAS, which could include permitting PJM Transmission \n18 \nOwners to require the implementation of SPS or RAS on the Transmission Owner’s \n19 \nside of the point of interconnection; \n20 \n\nEstablished reasonable limits on the size, aggregation, and geographic concentration of \n21 \nthe use of SPS/RAS; \n22"},{"page":36,"startToken":10491,"endToken":10756,"text":"Exhibit No. PTO-0001 \nPage 36 of 39 \n\nDefined thresholds under which network upgrades are required notwithstanding the \n1 \navailability of operational curtailment; and \n2 \n\nAppropriate rules as to how SPS/RAS supported contract demand service is evaluated \n3 \nin PJM’s transmission planning study and PJM Transmission Owners’ interconnection \n4 \nfacilities studies. \n5 \nImplementation of contract demand transmission services must preserve the integrity of \n6 \nthe transmission planning process and continued compliance with NERC reliability \n7 \nstandards. From the transmission owners’ perspective, the central implementation issue is \n8 \nhow reliance on SPS/RAS is appropriately bounded, monitored, and integrated into \n9 \nplanning and study analyses to ensure that firm transmission service obligations do not \n10 \nincreasingly depend on operational controls in lieu of durable network infrastructure \n11 \nsolutions. \n12 \nQ. \nPlease explain the above-mentioned “full redundancy of SPS/RAS” in more detail. \n13 \nA. \n[Hammer] In this context, “full redundancy of SPS/RAS” refers to a layered protection \n14 \nframework under which reliability risks associated with Co‑Located Load taking the new \n15 \ncontract demand transmission services are addressed through both primary, \n16 \ncustomer‑owned protection and an optional, transmission‑owner‑owned backstop, rather \n17 \nthan reliance on a single protection scheme.  \n18 \nUnder this framework, the primary responsibility for limiting withdrawals from the \n19 \ntransmission system remains with the interconnection customer or Co‑Located Load, \n20 \ntypically through customer-owned SPS/RAS that are designed, operated, and maintained \n21 \nin accordance with applicable NERC standards and reviewed by PJM. To help accomplish \n22 \nthis, the Commission should direct NERC to establish requirements that Co-Located Load \n23"},{"page":37,"startToken":10756,"endToken":11042,"text":"Exhibit No. PTO-0001 \nPage 37 of 39 \nCustomers register with NERC so that those customers may be responsible for meeting \n1 \nNERC’s reliability standards. These customer‑owned schemes serve as the first line of \n2 \ndefense and are expected to operate under normal and reasonably foreseeable contingency \n3 \nconditions. \n4 \n“Full redundancy” does not mean duplicative or parallel protection for every \n5 \ncontingency, nor does it imply that transmission owners must install SPS/RAS in all cases. \n6 \nRather, it means that, where system studies identify elevated reliability risk, transmission \n7 \nowners should have the option to implement a transmission-owner-owned SPS/RAS as a \n8 \nsecondary backstop to protect the Bulk Electric System in the event of customer‑owned \n9 \nscheme failure, mis-operation, or unavailability. \n10 \nQ. \nHow does this concept of redundancy align with NERC reliability standards, \n11 \nincluding PRC-012? \n12 \nA.  \n[Hammer] This approach is fully consistent with NERC Reliability Standard PRC‑012, \n13 \nwhich expressly contemplates that SPS/RAS may be owned by Transmission Owners, \n14 \nGenerator Owners, or Distribution Providers, provided that ownership and accountability \n15 \nare clearly defined. Importantly, PRC‑012 does not prohibit multiple SPS/RAS acting on \n16 \nthe same system condition, nor does it require exclusive reliance on a single owner’s \n17 \nprotection scheme. Allowing a Transmission Owner to own and operate a backstop \n18 \nSPS/RAS therefore fits within the PRC‑012 framework. \n19 \nQ. \nWhy is reliance on a single, customer‑owned SPS/RAS insufficient in some cases? \n20 \nA.  \n[Hammer] Transmission planning and operating standards, including TPL‑001, require \n21 \nplanners to account for credible contingencies and protection system failures, including \n22 \nsingle points of failure and mis-operations. In configurations where Co‑Located Load \n23"},{"page":38,"startToken":11042,"endToken":11312,"text":"Exhibit No. PTO-0001 \nPage 38 of 39 \ndepends on SPS/RAS to limit transmission system withdrawals, exclusive reliance on a \n1 \nsingle, customer‑controlled protection scheme can introduce reliability risk, particularly if \n2 \nthe equipment is unavailable due to outage or maintenance. In high‑impact scenarios, \n3 \nfailure of the primary SPS/RAS could result in unexpected load appearing on the \n4 \ntransmission system, potentially leading to overloads, stability concerns, or emergency \n5 \noperating actions. A transmission-owner‑owned backstop SPS/RAS provides an additional \n6 \nlayer of assurance that these risks can be mitigated before they affect other transmission \n7 \ncustomers or system reliability. \n8 \nQ. \nDoes “full redundancy” shift responsibility or cost from customers to Transmission \n9 \nOwners? \n10 \nA.  \n[Hammer] No. The concept of full redundancy does not shift responsibility away from \n11 \ncustomers. The presence of a transmission-owner‑owned backstop does not relieve \n12 \ncustomers of compliance obligations, nor does it entitle customers to rely on transmission-\n13 \nowner‑owned protection in lieu of their own facilities. \n14 \nQ. \nWhy is the ability to selectively curtail load essential to the contract demand \n15 \ntransmission service framework adopted by the Commission, and how is that \n16 \ncapability implemented in practice at the point of interconnection? \n17 \nA. \n[Hammer] The Commission directed PJM to create contract demand transmission service \n18 \nto reflect loads that are willing and able to limit their withdrawals from the transmission \n19 \nsystem. Load taking contract demand transmission service is granted access to the \n20 \ntransmission system without corresponding reliability reinforcements to support the full \n21 \ngross load, therefore, the reliability condition is curtailment.  \n22"},{"page":39,"startToken":11312,"endToken":11598,"text":"Exhibit No. PTO-0001 \nPage 39 of 39 \nUnder certain system conditions, PJM and the PJM Transmission Owners have the \n1 \nauthority to shed the non‑firm portion of load, either preemptively or immediately \n2 \nfollowing a contingency. For example, PJM may arm a SPS/RAS to instantaneously drop \n3 \na large block of load upon the trip of the on-site generator, thereby preventing a thermal or \n4 \nstability overload. \n5 \nWhere a point of interconnection serves both firm and non‑firm contract demand, \n6 \nthe interconnection must be designed to allow selective curtailment. Operationally, this \n7 \ntypically requires that firm and non‑firm load be served through separate breakers, feeders, \n8 \nor other independently controllable facilities. The Transmission Owner may structure the \n9 \ninterconnection so that the non‑firm portion can be shed without interrupting firm service. \n10 \nExamples could include: \n11 \n\nSeparate feeder lines or breakers dedicated to firm versus non‑firm load; \n12 \n\nPartial load‑shedding schemes that trip only designated non‑firm MW; or \n13 \n\nFor large facilities such as data centers, multiple transformer banks, with some \n14 \ndesignated as “firm service” and others as “non‑firm service,” allowing independent \n15 \ntripping. \n16 \nCritically, the ability to distinguish and shed the non‑firm portion of load \n17 \nindependently is a prerequisite for a contract demand service model. Curtailment cannot \n18 \nbe all‑or‑nothing; the firm portion of load is expected to remain in service except under \n19 \nlast‑resort system conditions. As a result, compliance may require the installation of special \n20 \nprotection or control equipment at the substation or within the customer’s facilities. \n21 \nQ. \nDoes this complete your testimony at this time? \n22 \nA. \n[Blazunas, Schafer, and Hammer] Yes. \n23"},{"page":40,"startToken":11598,"endToken":11718,"text":"UNITED STATES OF AMERICA\nBETORE THE\nFEDERAL ENERGY REGULATORY COMMISSION\nPJM Interconnection, L.L.C., et al.\nDocket No. EL25-49-000\nDocket No. EL25-49-001\nLarge Loads Co-Located at Generating Facilities\nConstellation Energy Generation, LLC\nv.\nPJM Interconnection. L.L.C.\nDocket No. AD24-11-000\nDocket No. EL25-20-000\n(Consolidated)\nDECLARATION OF PETER BLAZUNAS\nI depose and state under penalty of perjury that the foregoing exhibits were prepared or\nassembled by me or under my direction, and that I have read the foregoing questions and answers\nlabeled as my testimony: that if asked the same questions my answ'ers in response would be as\nshown; and that the facts contained in my answers are true to the best of my knowledge,\ninformation, and belief.\nF\n)\n)\n)\n)\n)\n)\n)\n)"},{"page":41,"startToken":11718,"endToken":11718,"text":""},{"page":42,"startToken":11718,"endToken":11841,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \nPJM Interconnection, L.L.C., et al.   \n \n)  \nDocket No. EL25-49-000 \n \n \n \n \n \n \n \n)  \nDocket No. EL25-49-001 \n \n \n \n \n \n \n \n) \nLarge Loads Co-Located at Generating Facilities  \n) \nDocket No. AD24-11-000 \n \n \n \n \n \n \n \n) \nConstellation Energy Generation, LLC  \n \n)  \nDocket No. EL25-20-000 \nv.  \n \n \n \n \n \n) \nPJM Interconnection, L.L.C.   \n \n \n)  \n(Consolidated) \n \n \nDECLARATION OF HANHAN HAMMER \n \n \nI depose and state under penalty of perjury that the foregoing exhibits were prepared or \nassembled by me or under my direction, and that I have read the foregoing questions and answers \nlabeled as my testimony: that if asked the same questions my answers in response would be as \nshown; and that the facts contained in my answers are true to the best of my knowledge, \ninformation, and belief. \n \n \n \n \n \n \n \n \n \n \n \n \n \n \n \n \n/s/__________________ \n \n \n \n \n \n \n \nFebruary 23, 2026"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":1,"endAt":497,"startToken":0,"endToken":64},{"p":1,"at":497,"title":"I. INTRODUCTION","method":"printed heading","endPage":3,"endAt":36,"startToken":64,"endToken":499},{"p":3,"at":36,"title":"II. BACKGROUND","method":"printed heading","endPage":4,"endAt":36,"startToken":499,"endToken":756},{"p":4,"at":36,"title":"III. PURPOSE OF TESTIMONY","method":"printed heading","endPage":5,"endAt":36,"startToken":756,"endToken":1226},{"p":5,"at":36,"title":"IV. NEW TRANSMISSION SERVICE CATEGORIES AND RATE DESIGNS","method":"printed heading","endPage":5,"endAt":98,"startToken":1226,"endToken":1235},{"p":5,"at":98,"title":"A. Firm Contract Demand Transmission Service","method":"printed heading","endPage":10,"endAt":832,"startToken":1235,"endToken":2869},{"p":10,"at":832,"title":"B. Non-Firm Contract Demand Transmission Service","method":"printed heading","endPage":15,"endAt":1380,"startToken":2869,"endToken":4703},{"p":15,"at":1380,"title":"C. Interim, Non-Firm Transmission Service","method":"printed heading","endPage":17,"endAt":181,"startToken":4703,"endToken":5080},{"p":17,"at":181,"title":"V. GRID RELIANCE CHARGE","method":"printed heading","endPage":26,"endAt":37,"startToken":5080,"endToken":7733},{"p":26,"at":37,"title":"VI. EXAMPLE OF RATE DESIGNS FOR NEW SERVICES","method":"printed heading","endPage":31,"endAt":1385,"startToken":7733,"endToken":9295},{"p":31,"at":1385,"title":"VII. PENALTY CHARGE","method":"printed heading","endPage":33,"endAt":37,"startToken":9295,"endToken":9710},{"p":33,"at":37,"title":"VIII. INTERCONNECTION REQUIREMENTS AND OPERATIONAL PRACTICES","method":"printed heading","endPage":42,"endAt":962,"startToken":9710,"endToken":11841}]}