{"document":{"slug":"rec-20260316-5222","title":"Comments of EDF Power Solutions, Inc. in response to the 60-Day Compliance Filing by PJM Interconnection, L.L.C. on 02/23/2026","issued":"2026-03-16","accession":"20260316-5222","docket":"ER26-1479-000","group":"PJM co-location compliance","filer":"EDF Power Solutions, Inc.","kind":"comments","file":"sources/filings/text/20260316-5222_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260316-5222","tier":"record","sha256":"0eb49a828c40e2394f71f1c69d31ff2f6aa50032d82e3376162cbcc48e6fd310","pages":10,"tokens":2695,"emptyPages":[],"textThemes":["colo","flex","cost","study"]},"pages":[{"page":1,"startToken":0,"endToken":259,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \n \nPJM Interconnection, L.L.C.  \n \n \n \n \nDocket No. ER26-1479-000 \n \n \nCOMMENTS OF EDF POWER SOLUTIONS, INC.  \n \n \nPursuant to Rules 212 and 213 of the Rules of Practice and Procedure of the Federal \nEnergy Regulatory Commission (Commission or FERC),1 EDF power solutions, Inc. (EDFps) \nrespectfully submits these comments in response to the 60-Day Compliance Filing2 filed by PJM \nInterconnection, L.L.C. (PJM) on February 23, 2026 (PJM Compliance Filing).  The PJM \nCompliance Filing was submitted in response to the Commission’s December 18, 2025 Order on \nShow Cause Proceeding,3 regarding the co-location of large loads in PJM. \nI. \nSUMMARY OF COMMENTS  \nPJM’s proposed framework for new transmission services presents an important \nopportunity to support the reliable and flexible integration of large load resources.  PJM’s \nproposed three new transmission service options will allow large loads to combine Firm and \nNon-Firm Contract Demand services, facilitating flexible co-location arrangements and efficient \ninterconnection. \nPJM’s proposed 50 MW Retail Behind the Meter Generation (BTMG) threshold, on the \nother hand, is arbitrary and too low.  It will disincentivize large loads from installing their own \ngeneration and thereby stifle innovation.  The Retail BTMG threshold should instead be based on \n \n1 18 C.F.R. §§ 385.212, 385.213 (2025). \n2 PJM Interconnection, L.L.C., 60-Day Compliance Filing for Co-Located Load Related to Revisions to \nOpen Access Transmission Tariff to Comply with Commission Order in Docket No. EL25-49, Feb. 23, \n2026.  \n3 PJM Interconnection, L.L.C., et al., 193 FERC ¶ 61,217 (2025) (December 18 Order)."},{"page":2,"startToken":259,"endToken":529,"text":"2 \npercentage of the load size. EDFps suggests 100% of the load size, at the electrical location, \ncombined with operational safeguards and appropriate transmission charges.  There are \nsignificant benefits of BTMG co-location that should be encouraged.  BTMG can reduce grid \ncongestion, avoid queue delays, lower network upgrade needs, and provide economic and \ncommunity benefits.  EDFps suggests a “bifurcated netting” approach, which allows netting of \ngeneration up to the Retail BTMG size while charging the full load for transmission service.  \nFinally, PJM’s proposed BTMG changes require modifications to ensure that (1) a Retail \nBTMG resource that exceeds the established threshold can still be netted up to the threshold \namount; and (2) a BTMG resource can continue to serve load (provide ride-through capacity) \nduring a grid curtailment event, similar to backup generation.   \nII. \nBACKGROUND \nEDFps develops, builds, operates, and manages renewable energy projects throughout \nNorth America, including in PJM, MISO, SPP, and ERCOT.  As a market-leading independent \npower producer and service provider for over 35 years, EDFps delivers grid-scale power, \nincluding wind (onshore and offshore), solar photovoltaic, and storage projects; distribution-\nscale power, including solar and storage; and asset optimization.  The company also provides \ntechnical, operational, and commercial expertise to maximize performance of generating \nprojects.  EDFps is an active participant in interconnection and large load-related policy \ndiscussions, rulemaking proceedings, and reform efforts.   \nOn February 23, 2026, PJM submitted the 60-Day Compliance Filing in response to the \nCommission’s December 18 Order.  Among other things, PJM proposes to adopt a revised \ndefinition of Retail BTMG to include a new 50 MW materiality threshold and to establish three \nnew transmission service options for large loads."},{"page":3,"startToken":529,"endToken":869,"text":"3 \nIII. \nCOMMENTS \nA. \nPJM’s Proposed 50 MW Materiality Threshold for New Retail BTMG is \nArbitrarily Too Low: The Threshold Should Vary Based on the Size of the \nLoad.  \n \nPJM proposes a materiality threshold of up to 50 MW for a new generator at the same \nelectrical location as the Network Load to qualify for Retail BTMG.4  According to PJM, its \nproposed 50 MW threshold corresponds with the PJM Board’s definition of large load additions, \nwhich are individual loads of 50 MW or greater at a single point of interconnection.5  However, \nthe 50 MW Retail BTMG threshold is arbitrary and could disincentivize retail customers from \ninstalling their own generation.  The benefits of “bring your own generation” to the grid has been \nrecognized as an essential element of the drive to meet the demand of new large loads.6  To meet \nthis goal, the Retail BTMG threshold should be established based on 100% of the size of the \nlarge load it serves at that electrical location, coupled with operational safeguards and a \nrequirement that the appropriate transmission service charges are paid. \nLarge loads come in all sizes and co-location arrangements can vary significantly.  The \nRetail BTMG threshold should be flexible and non-discriminatory to account for these \ndifferences.  For example, with a 50 MW Retail BTMG threshold, a 50 MW large load could \ntheoretically cover 100% of its load with Retail BTMG.  A large load of 200 MW, on the other \nhand, could only cover 25% of its load with the 50 MW threshold.  PJM’s proposed 50 MW \nthreshold will stifle innovation and arbitrarily incentivize the development of smaller loads rather \n \n4 PJM Compliance Filing at p. 6-7. \n5 Id. at p. 11-12. \n6 December 18 Order, Rosner concurring at P 8.  See also Energy Secretary Encourages Data Centers to \nBring Their Own Generation, The Ohio Mfrs.’ Ass’n (Oct. 10, 2025), available at: \nhttps://www.ohiomfg.com/our-communities/energy-secretary-encourages-data-centers-to-bring-their-\nown-generation/; “Behind-the-Meter” AI Projects Surge in the U.S., Nam News Room (Feb. 6, 2026), \navailable at: https://nam.org/behind-the-meter-ai-projects-surge-in-u-s-35696/."},{"page":4,"startToken":869,"endToken":1179,"text":"4 \nthan designing the loads to meet the needs of the large load customer.  It may also incentivize \nlarge loads to be segmented in close but separate electrical locations, resulting in inefficient and \nredundant construction of interconnection facilities.  \nThe optimal sizing of Retail BTMG, such as solar plus battery energy storage systems \n(BESS) or some other combination, to support an AI data center would most certainly exceed 50 \nMW.  An arbitrary 50 MW limit will require that these new large loads develop new grid-\nconnected resources instead of BTMG resources.  This would force new generation resources – \nwhich are solely intended to serve new large loads – into the generation interconnection queue \nwith full wholesale interconnection studies that would otherwise be unnecessary.  It may also \ncall for network upgrades that would also otherwise be unnecessary.   \nStripping the new large load with BTMG of netting rights penalizes the very co-located \nconfigurations that can ease grid congestion.  BTMG arrangements can benefit the transmission \nsystem in many ways, such as by serving load on a streamlined basis, avoiding queue delays in \nthe generator interconnection process, and reducing the need for expensive grid upgrades.  \nBTMG co-locating with large loads can also reduce congestion costs and allow the load to \nprovide demand response services if the power demands are flexible.  Finally, BTMG resources \nwill provide benefits to states and communities by facilitating new large load facilities that can \nprovide a host of benefits to local communities in the form of tax revenues, construction jobs, \nand employment.   \nEDFps understands that there could be impacts to operation of the transmission system if \nthe Retail BTMG is not available.  This possibility can be managed to preserve the benefits of \nBTMG to the new load and to the grid while also protecting the grid from negative impacts if the \nBTMG is unavailable.  For example, PJM could establish a “bifurcated netting” approach:"},{"page":5,"startToken":1179,"endToken":1509,"text":"5 \n• If a Retail BTMG system exceeds 50 MW, the large load should still be permitted to \nnet its generation against its load for the purposes of energy and capacity market \nsettlements. \n• To satisfy concerns regarding transmission cost shifting, PJM could establish a \nframework where facilities with BTMG that exceeds 50 MW pay transmission and/or \ndistribution network charges without the benefit of netting (i.e., paying transmission \nand/or distribution charges based on the gross load or agreed-upon contract demand). \nThis bifurcated netting approach is beneficial in that it preserves the economic incentive \nto build various resources with storage configurations directly at the load center (such as large-\nscale renewables plus storage, or natural gas resources plus storage).  Setting the Retail BTMG \nthreshold at 100% of the load it serves at that electrical location is consistent with the \nCommission’s “beneficiary pays” principle when it is coupled with transmission charges that \nappropriately reflect the full loads potential usage of the transmission system.7   \nB. \nFor Retail BTMG Resources that Exceed the Materiality Threshold Size, \nPJM Should Allow Netting Up to the Threshold Amount.  \n \nPJM states that going forward any new large Retail BTMG that is greater than the \nproposed threshold would not qualify as Retail BTMG and that “a Retail BTMG cannot both net \nup to a certain threshold but still potentially have generation and load above that threshold which \n \n7 Under the “beneficiary pays” cost causation principle, rates must “reflect to some degree the costs \nactually caused by the customer who must pay them.” Midwest ISO Transmission Owners v. FERC, 373 \nF.3d 1361, 1368 (D.C. Cir. 2004).  Costs must be allocated in a manner that is at least roughly \ncommensurate with the benefits an entity receives.  Ill. Com. Comm’n v. FERC, 576 F.3d 470, 474-78 \n(7th Cir. 2009) (remanding Commission order for further proceedings in light of Commission’s failure to \nprovide substantial evidence supporting Commission’s approval of cost allocation method as complying \nwith “beneficiary pays” principle)."},{"page":6,"startToken":1509,"endToken":1820,"text":"6 \ncannot be netted.”8  PJM claims that this provision is consistent with its interpretation of the \nCommission’s directive in the December 18 Order.9   \nIn the December 18 Order, the Commission found that PJM’s existing Retail BTMG \nrules were no longer just and reasonable for use by large loads because large loads do not carry \nreserves and such loads must nevertheless be served, which would allow them to “lean on the \nPJM system when the co-located generation is on a full or partial outage or if the load exceeds \nthe rating of the co-located generation.”10   \nPJM’s filing in response to the December 18 Order, however, makes significant changes \nto the transmission service requirements that alleviate the ability of large loads with Retail \nBTMG to lean on the system.  PJM states that its proposed contract demand service (consisting \nof Firm and Non-Firm Contract Demand Transmission Service) provides “an alternative to NITS \nfor those Co-Located Loads willing and able to limit energy withdrawals from the Transmission \nSystem.”11  PJM states that “there can be no ‘unstudied’ and/or ‘unknown’ portion of the Co-\nLocated Load that is not covered by either Firm Contract Demand Transmission Service or \ndedicated generation from the Co-Located Generating Facility (as backed up by Non-Firm \nContract Demand Transmission Service).”12   \nThus, in the case of a Retail BTMG resource, the load being served would be required to \npurchase Non-Firm Contract Demand up to the amount covered by the Retail BTMG and Firm \n \n8 PJM Compliance Filing at p. 10-11.  \n9 Id. at p. 11. \n10 December 18 Order at P 186, citing PJM Interconnection, L.L.C., Answer in Docket No. EL25-49, \nMar. 24, 2025 at P 13 n. 5.  \n11 PJM Interconnection, L.L.C., Initial Brief in Docket No. EL25-49, Feb. 23, 2026 at p. 5 (emphasis \nadded) (PJM Brief).   \n12 Id. at p. 7."},{"page":7,"startToken":1820,"endToken":2108,"text":"7 \nContract Demand for the remainder of the load.  If the Retail BTMG was equal to the size of the \nload and the load is fully covered by Non-Firm Contract Demand, the load would be limited to \ntaking energy “on an as-needed and as-available basis,”13 for its entire load and could not lean on \nthe system. \nPJM indicates that a “hybrid approach,” where a Retail BTMG can both net up to a \ncertain threshold and have generation and load above the threshold that cannot be netted, would \n(1) impose significant metering costs all Retail BTMG that would have to install previously \nunnecessary equipment; and (2) amplify compliance risks in monitoring and reporting different \ngenerator and load thresholds.14   \nPJM’s rejection of a hybrid approach is unwarranted.  First, grandfathered Retail BTMG \nwould not face any additional metering costs, nor would entities that installed Retail BTMG that \ndid not exceed the threshold.  Only entities choosing to install larger Retail BTMG resources \nwould have to install the appropriate metering.  These entities can decide whether the costs and \ncompliance risks (if any) are cost-effective for their business.  Rejecting a hybrid approach \naltogether would discourage investment in BTMG.  \nC. \nCo-Located Retail BTMG Resources Must Be Permitted to Provide Ride-\nThrough Capacity During Curtailments.  \n \nPJM proposes that the Retail BTMG threshold excludes backup generation “at the same \nelectrical location as the retail load that can only be used to serve such retail load during \nconditions that may threaten the integrity or reliability of the PJM Region or the regional power \nsystem.”15  EDFps interprets this to mean that backup generation can be used during a grid \n \n13 PJM Compliance Filing at p. 21. \n14 Id. at p. 11. \n15 Id. at p. 7."},{"page":8,"startToken":2108,"endToken":2387,"text":"8 \ncurtailment event.  However, it is not clear whether the Retail BTMG itself can operate during a \ngrid curtailment event.  \nLarge loads electing to take “Interim NITS” accept the risk of grid curtailment but they \nshould not have to accept a complete operational downtime during a grid curtailment.  Like \nbackup generation, discharging a BTMG BESS (or a BESS charged by BTM solar) directly to \nthe data center load during a grid curtailment event is a necessary self-supply function.  The \nCommission should direct PJM to explicitly clarify that BESS and hybrid systems functioning in \na load-following, non-exporting capacity manner during a curtailment event qualify under the \n“backup generation” exemption, and can continue to serve the load, regardless of their size. \nD. \nPJM’s Proposed Three New Transmission Services Should Be Accepted.  \nEDFps supports PJM’s proposal to add three new transmission service options to benefit \nlarge load customers.  According to PJM, large load customers will have the option to take a \ncombination of Firm and Non-Firm Contract Demand service as long as the combined service \nfully covers the co-located loads total load.16  The Non-Firm Contract Demand service provides \na useful option for large loads that do not necessarily intend to withdraw energy from the grid on \na regular basis and instead plan to rely on Retail BTMG for all or a portion of its load.  \nThe new transmission service options will encourage flexible co-location structures that \nwill enable speedy and reliable interconnection for large loads.  Standardized yet flexible rules to \naccommodate different co-location structures with varying operational needs and capabilities are \nneeded to meet the challenges of serving the power needs of new large loads.   \n \n16 PJM Brief at p. 11."},{"page":9,"startToken":2387,"endToken":2611,"text":"9 \nIV. \nCONCLUSION \nPJM’s proposed framework for Retail BTMG thresholds and new transmission service \noptions presents an important opportunity to support the reliable and flexible integration of large \nload resources.  To ensure the effectiveness and fairness of these proposals, PJM should (1) set a \nRetail BTMG materiality threshold that is based on 100% of the load; (2) allow a hybrid \napproach to netting of Retail BTMG resources that exceed the threshold; and (3) expressly \npermit co-located Retail BTMG and backup generation—including BESS and hybrid systems—\nto operate during grid curtailment events.  These clarifications will preserve incentives for \ninvestment in innovative on-site generation and storage, enhance reliability, and provide large \nload customers with the operational flexibility they require. Adoption of the three new \ntransmission service options will further promote efficient interconnection and accommodate the \nevolving needs of large energy users. For these reasons, the Commission should approve PJM’s \nproposed changes, with the recommended modifications/clarifications. \nRespectfully submitted, \n \n \n \n \n \n \n \n \n/s/ Linda Walsh_____ \nTemujin Roach \n \n \n \nLinda Walsh \nEmma Nix Simon \n \n \n \nMichael Blackwell \nEDF power solutions, Inc. \n \n \nHusch Blackwell LLP  \n15445 Innovation Dr.  \n \n \n1801 Pennsylvania Ave., NW, Suite 1000 \n \nSan Diego, CA 92128  \n \n \nWashington, DC  20006 \nTel: (612) 486-4498  \n \n \nTel: (202) 378-2308 \nTemujin.Roach@edf-re.com  \n \nlinda.walsh@huschblackwell.com  \nEmmaNix.Simon@edf-re.com \n \nmichael.blackwell@huschblackwell.com \n \n \n \n \n \n \n \n \n \nCounsel to EDF power solutions, Inc. \nDated: March 16, 2026"},{"page":10,"startToken":2611,"endToken":2695,"text":"CERTIFICATE OF SERVICE \n \n \nPursuant to Rule 2010 of the Federal Energy Regulatory Commission’s Rules of Practice \nand Procedure, 18 C.F.R. § 385.2010, I certify that I served the foregoing document upon each \nperson designated on the official service list compiled by the Secretary in this proceeding. \n \n \nDated at Washington, D.C. this 16th day of March 2026. \n \n \n/s/ Emily Starobin \n \nEmily Starobin \nHusch Blackwell LLP  \n1801 Pennsylvania Ave. NW, Suite 1000  \nWashington, D.C. 20006 \nTel: (202) 378-2319 \nemily.starobin@huschblackwell.com"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":1,"endAt":711,"startToken":0,"endToken":106},{"p":1,"at":711,"title":"I. SUMMARY OF COMMENTS","method":"printed heading","endPage":2,"endAt":893,"startToken":106,"endToken":389},{"p":2,"at":893,"title":"II. BACKGROUND","method":"printed heading","endPage":3,"endAt":3,"startToken":389,"endToken":530},{"p":3,"at":3,"title":"III. COMMENTS","method":"printed heading","endPage":3,"endAt":19,"startToken":530,"endToken":532},{"p":3,"at":19,"title":"A. PJM’s Proposed 50 MW Materiality Threshold for New Retail BTMG is","method":"printed heading","endPage":5,"endAt":1083,"startToken":532,"endToken":1342},{"p":5,"at":1083,"title":"B. For Retail BTMG Resources that Exceed the Materiality Threshold Size,","method":"printed heading","endPage":7,"endAt":1235,"startToken":1342,"endToken":2014},{"p":7,"at":1235,"title":"C. Co-Located Retail BTMG Resources Must Be Permitted to Provide Ride-","method":"printed heading","endPage":8,"endAt":778,"startToken":2014,"endToken":2227},{"p":8,"at":778,"title":"D. PJM’s Proposed Three New Transmission Services Should Be Accepted.","method":"printed heading","endPage":9,"endAt":3,"startToken":2227,"endToken":2388},{"p":9,"at":3,"title":"IV. CONCLUSION","method":"printed heading","endPage":10,"endAt":0,"startToken":2388,"endToken":2611},{"p":10,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":10,"endAt":546,"startToken":2611,"endToken":2695}]}