{"document":{"slug":"rec-20260316-5303","title":"Joint Protest of the PJM Industrial Customer Coalition et al. in response to PJM Interconnection, L.L.C.’s 60-Day Compliance Filing for Co-Located Load…","issued":"2026-03-16","accession":"20260316-5303","docket":"ER26-1479-000","group":"PJM co-location compliance","filer":"PJMICC, IECA, AF&PA, and Amtrak","kind":"protest","file":"sources/filings/text/20260316-5303_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260316-5303","tier":"record","sha256":"550029d9f6ed934d7666ac3745311217b69853b643e34fbd9d8d81da01f4238c","pages":101,"tokens":28739,"emptyPages":[],"textThemes":["colo","retail","adequacy","flex"]},"pages":[{"page":1,"startToken":0,"endToken":250,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \n  \n \nPJM Interconnection, L.L.C. \n \n) \n) \n) \n)\n \n \nDocket No. ER26-1479-000 \n \n \nJOINT PROTEST AND COMMENTS OF  \nINDUSTRIAL CUSTOMER ORGANIZATIONS AND AMTRAK \n \nPursuant to Rule 211 of the Federal Energy Regulatory Commission’s (“FERC” or \n“Commission”) Rules of Practice and Procedure1 and the Combined Notice of Filings #1 issued \non February 24, 2026,2 the PJM Industrial Customer Coalition (“PJMICC”), the Industrial Energy \nConsumers of America (“IECA”), the American Forest and Paper Association (“AF&PA”) \n(collectively, “Industrials”), and the National Railroad Passenger Corporation (“Amtrak”) hereby \nfile this Joint Protest and Comments in response to PJM Interconnection, L.L.C.’s (“PJM”) 60-\nDay Compliance Filing for Co-Located Load Related Revisions to Open Access Transmission \nTariff to Comply with Commission Order in Docket No. EL25-49, et al. (“Compliance Filing”), \nwhich was filed on February 23, 2026, in the above-captioned docket.  \nAs demonstrated herein and in the supporting affidavit of James R. Dauphinais \n(“Dauphinais Affidavit”), the Commission should find that certain material components of the \nCompliance Filing are not compliant with the December 18, 2025, Order (“Order”) issued in \nDocket No. EL25-49.3 The Industrials/Amtrak respectfully request that the Commission reject \n \n1 18 C.F.R. § 385.211 (2025). \n2 Combined Notice of Filings #1, PJM Interconnection, L.L.C., Docket No. ER26-1479-000. \n3 Order on Show Cause Proceeding, Directing Compliance Filings, Establishing Paper Hearing, and Granting In Part \nand Denying In Part Complaint, Docket Nos. EL25-49-000, EL25-49-001, AD24-11-000, EL25-20-000 \n(“Consolidated Dockets”) (Dec. 18, 2025) (“Order”)."},{"page":2,"startToken":250,"endToken":524,"text":"2 \n \nPJM’s Compliance Filing and direct PJM to file a new compliance filing, consistent with the \nProtest and Comments herein. \nI. \nBACKGROUND \nOn December 18, 2025, the Commission issued the Order, finding that the PJM Tariff is \nunjust and unreasonable due to the lack of specificity for the rates, terms, and conditions that apply \nto Co-Located Load and directing PJM to make several compliance and informational filings. The \nOrder also addressed PJM’s Retail Behind-the-Meter Generation (“BTMG”) rules, finding that \n“circumstances have changed since the Commission approved PJM’s retail BTMG rules such that \nthese rules are no longer just and reasonable.”4 Specifically, the Commission stated, “We therefore \nfind that PJM’s BTMG rules are no longer consistent with cost causation principles, because large \nloads configured in a BTMG arrangement with significant generation will raise cost shifting \nconcerns compared to loads pursuing smaller amounts of netting.”5 The Commission directed PJM \nto file a compliance filing within 60 days of the Order, to: (1) revise the BTMG rules pursuant to \nthe Order; (2) propose a “new MW [megawatt] threshold for the amount of load that Network \nCustomers may net by using BTMG” (“Retail Threshold”); and (3) “establish a transition period \nfor Network Customers already using the BTMG rules.”6 The Commission later extended PJM’s \ndeadline to file its compliance filing by seven days.7  \nOn February 23, 2026, PJM filed the Compliance Filing in Docket No. ER26-1479-000.  \nPJM convened several stakeholder workshops to solicit input on PJM’s compliance filing. \n \n4 Id. at P 186. \n5 Id. \n6 Id., Ordering Paragraph (F).  \n7 Notice of Extension of Time, Docket Nos. EL25-49-000, EL25-49-001, AD24-11-000, EL25-20-000 (Jan. 23, 2026)."},{"page":3,"startToken":524,"endToken":890,"text":"3 \n \nOn February 24, 2026, the Industrials separately intervened in the above-captioned docket.8 \nOn March 11, 2026, Amtrak intervened in the above-captioned docket. Many other parties \nsubsequently intervened, as well.9 \nII. \nTHE INDUSTRIALS/AMTRAK \nThe Industrials include associations of leading American manufacturing companies, trade-\nexposed electricity users, institutional users, and other energy-intensive customers. Together, \nIndustrials represent well over $1 trillion in sales, including thousands of manufacturing facilities \nand millions of family-sustaining jobs in the United States. The Industrials produce the raw \nmaterials and inputs necessary for sustaining commerce and our overall standard of living. \nManufacturing employs over 15 million people in the United States10 and contributed $2.3 trillion \nto U.S. Gross Domestic Product (“GDP”) in 2023 (amounting to 10.2 % of total U.S. GDP, \nmeasured in chained 2017 dollars).11 Manufacturing is unique compared to all other sectors. \nManufacturers are energy intensive, frequently operate 24/7, are price sensitive, and compete \nglobally. Small changes in electricity prices can have significant impacts on the competitiveness \nof existing facilities and serious implications for reshoring and expanding facilities and production \ncapabilities in the United States. Unlike the surge in large-load demands from data centers and \ncomputational workloads, most manufacturers are simply trying to survive and keep their facilities \n \n8 PJMICC and IECA (together, “Requestors”) jointly filed a Request For Clarification or, in the Alternative, Rehearing \nof the Industrial Customer Coalitions (“Rehearing Request”) on January 20, 2026, in Docket No. EL25-49-000 and \nthe other Consolidated Dockets. Nothing herein should be construed to modify the Rehearing Request. The Requestors \nand the Industrials/Amtrak reserve their rights to supplement or modify this Protest and Comments in response to any \norder on rehearing. \n9 PJM filed a letter on February 24, 2026, in Docket Nos. EL25-49 and ER26-1479, confirming that the Compliance \nFiling was filed on February 23, 2026, and requesting a placeholder effective date for the proposed tariff revisions.  \n10 See U.S. Bureau of Labor Statistics (2024 data), available at https://www.bls.gov/cps/cpsaat18.htm (last accessed \nMar. 12, 2026). \n11 \nSee \nU.S. \nManufacturing \nEconomy, \nNIST, \navailable \nat \nhttps://www.nist.gov/el/applied-economics-\noffice/manufacturing/manufacturing-economy/total-us-manufacturing (last accessed Mar. 12, 2026)."},{"page":4,"startToken":890,"endToken":1187,"text":"4 \n \noperational and financially healthy amid ever-rising operational costs. For manufacturers \npositioned to expand facilities, expansion is done in a careful and deliberate manner, with years of \nplanning and investment prior to committing to a facility addition or expansion. Many of the \nIndustrials’ members have constructed, maintained, and operate substantial BTMG units that are \ndesigned for operational efficiency and are deeply integrated into their industrial processes.  These \nindustrial customers span industries as diverse as chemicals, plastics, steel, iron ore, aluminum, \npaper, food processing, fertilizer, insulation, glass, industrial gases, pharmaceuticals, building \nproducts, automotive, independent oil refining, cement, and more. The Industrials also comprise \nother institutional and service customers, such as universities and hospitals, some of which also \noperate retail BTMG and, as such, will suffer the same economic consequences described herein. \nAmtrak is a corporation authorized by the Rail Passenger Service Act of 1970, currently \nset forth at 49 U.S.C. §§ 24101, et seq. Amtrak provides passenger rail service across the \ncontinental United States, including within the PJM footprint. Amtrak consumes substantial \namounts of electricity in its operations and requires reliable electric service to support its \noperations.  While Amtrak is not a manufacturer, it is also an industrial customer of utility services. \nFor many years, Amtrak has harnessed retail BTMG within PJM to support its business operations \nand reliability imperatives. Amtrak’s interests align with the Industrials and reflect the wide-\nranging types of bespoke retail BTMG arrangements that support the region’s and the nation’s \neconomy.  \nConsidering the significant impact of BTMG rule changes on these customers, as well as \nthe important role BTMG plays in resource adequacy considerations, the Industrials/Amtrak \nrespectfully file this Protest and Comments. The Industrials/Amtrak sincerely appreciate PJM’s \noutreach to stakeholders in developing its Compliance Filing. PJM has identified and included the"},{"page":5,"startToken":1187,"endToken":1591,"text":"5 \n \nkey compliance issues within its filing. While the identified issues are on target, a few key changes \nare necessary to meet the objectives set forth in the Order. As described further below: (1) PJM’s \nproposed retail netting eligibility for qualifying facilities (“QF”) under the Public Utility \nRegulatory Policies Act of 1978 (“PURPA”) is appropriate, but it should not be linked to QF status \nas of the date of the Order; (2) the Retail Threshold should be at least 200 MW or more, not 50 \nMW;12 and (3) eligibility for BTMG netting should be “up to” the Retail Threshold, as indicated \nin the Order,13 rather than categorically disqualifying a retail customer from netting any of its load \nif the retail customer’s on-site generation exceeds the Retail Threshold. With these changes, the \nCommission can approve BTMG rules that effectuate the goals of the Order while maintaining a \nvibrant piece of the resource adequacy puzzle, currently built and maintained by America’s \nindustrial and transportation backbone. \nIII. \nEXECUTIVE SUMMARY \nThe Order advances changes designed to address the rapid and sweeping emergence of \nsuper-sized computational load additions with speed-to-power requirements across the PJM \nfootprint.14 For generators with on-site load (and load with on-site generation), the Order \nsubstantially overhauls how transmission services are procured, reserved, and paid.  \nAlthough focused on Co-Located Load, the Commission’s broader, potentially unlimited \n \n12 As explained in the supporting Dauphinais Affidavit, evidence from the Midcontinent Independent System \nOperator, Inc. (“MISO”), region supports a threshold of at least 300 MW. See Dauphinais Affidavit at PP 65-67 \n(referencing Michigan Public Service Commission Case No. U-21859).  \n13 See Order at PP 221 (directing PJM “to propose a new MW threshold for the amount of load at a particular electrical \nlocation that Network Customers may net by using BTMG”). \n14 Order at P 4 (“As explained in the Show Cause Order, Co-Location Arrangements are becoming increasingly \ncommon in PJM and, since the issuance of the Show Cause Order, entities continue to raise issues involving Co-\nLocation Arrangements with the Commission”); id. at P 186 (“We find that circumstances have changed since the \nCommission approved PJM’s retail BTMG rules such that these rules are no longer just and reasonable”); id., \nConcurrence of David Rosner at P 10 (stating that the Order “protects existing customers . . . by directing PJM to \nassign transmission costs to ensure that a co-located load, such as a data center, always pays its fair share”)."},{"page":6,"startToken":1591,"endToken":1934,"text":"6 \n \nfindings regarding BTMG have profound implications for existing and future retail customers who \nhave built—or want to build—on-site generation outside the data center industry. Over decades, \nbillions of dollars have been invested by American manufacturers, nonprofit institutions, the \ntransportation sector, and others in support of a more efficient, powerful, and resilient grid. \nCustomers have developed on-site generation to minimize the amount of load they place on the \ntransmission system and, in many cases, to support thermal needs such as heating facilities, \noperating chillers, or using steam in the manufacturing process. These behind-the-meter facilities \nare all products of long-term investments, but they come in countless configurations, unique to \nindustry or institutional need, built for efficiency, and operated over long periods of time.  \nAs demonstrated herein and in the attached Dauphinais Affidavit, these on-site generating \nfacilities also provide critical benefits to the larger grid. These benefits are both 1) indirect: \nreducing large loads on the system and operating efficiently to reduce congestion and/or \ntransmission system build-out; and 2) direct: being able to operate during system emergencies.15 \nThis is true for manufacturers that produce essential products for everyday life as well as for \nAmtrak. For example, the retail BTMG that Amtrak relies on, generated at 25 Hertz (“Hz”), \nprovides the only black-start capability for Amtrak’s south end of its Northeast Corridor (“NEC”) \ntraction power system if the 60 Hz power grid goes out of service. \nThese traditional loads differ from most of today’s large-load entrants in both size and type. \nThese traditional load configurations are neither the essential cause of the current changed \ncircumstances on the grid, nor do they present the reliability risks posed by super-sized, inverter-\n \n15 Compliance Filing at 13. Notably, the Department of Energy (“DOE”) recently issued an order indicating that it \nmay rely on industrial customers’ generation during emergencies. See U.S. Department of Energy, Emergency Order \nNo. 202-26-06 (issued Jan. 26, 2026). The generation that DOE refers to in Order No. 202-26-06 is, to a great extent, \nthe retail BTMG at issue in this docket."},{"page":7,"startToken":1934,"endToken":2328,"text":"7 \n \nbased loads rapidly seeking to come online today.16 Consequently, the Commission should \nestablish a sufficiently high Retail Threshold to prevent damage to industrial, institutional, \ntransportation, and other customers who wish to invest in (and maintain) existing on-site \ngeneration. \nIt is difficult to overstate the importance of how FERC ultimately defines the Retail \nThreshold. A too-low Retail Threshold will dramatically increase energy costs for many existing \nbusinesses with BTMG, to the point that many major on-site generation units will become \nuneconomic.17 For units remaining in operation, it will remove a crucial incentive to operate \nefficiently and during key hours.18 Further, it will raise legal questions about how PURPA QFs \nwill obtain the back-up power required under current law and regulation. Perhaps most concerning, \na too-low Retail Threshold will discourage future on-site generation investments by institutions \nand industry at the very time the energy industry is desperately seeking new resources, and the \nnation is seeking to reshore and expand U.S. manufacturing. Failure to get the Retail Threshold \n“right-sized” will harm both resource adequacy and the broader economy.   \nAdditionally, a too-low Retail Threshold creates substantially more work for PJM to study \nand process generators seeking to enter the wholesale market, as well as generator deactivations \nthat will occur. A too-low Retail Threshold will create the need for significantly expanded and \ncomplex metering installation at some sites; it will cause projects in the planning process at various \n \n16 See Dauphinais Affidavit at PP 22-26, 32. \n17 See id. at P 17 (“The ability to continue operation in a safe and environmentally compliant manner within the bounds \nof what can be supported by the remaining thermal capability of the Cogeneration Facility at just and reasonable \nelectric power rates is a critical requirement to ensure the retail customer can economically meet the needs of its own \ncustomers and clients.  If that ability cannot be assured, cogeneration may fail to be a practical and/or economic \nsolution to the retail customer’s needs, causing the efficiency benefits of cogeneration to be forgone and/or the retail \ncustomer to become economically unviable.”). See also Compliance Filing at 12-15. \n18 Dauphinais Affidavit at P 36 (explaining that the netting construct “sends a strong cost signal for retail behind the \nmeter generation to operate and fully serve the electric load of their host retail customer during times of grid stress”)."},{"page":8,"startToken":2328,"endToken":2645,"text":"8 \n \nindustrial, manufacturing, or institutional customers to be reworked or abandoned; and it will \ngenerate confusion as scores of retail customers will have to evaluate, and perhaps undertake, PJM \nmembership and compliance with a vastly different set of rules than retail customers are \naccustomed. For many retail customers, these are substantial burdens that will materially impact \ninvestment decisions as well as decisions on whether to continue to operate their retail BTMG.19 \nThe Industrials/Amtrak respectfully submit that the FERC should avoid imposing these burdens \nany further than necessary to effectuate the Order’s broader reliability goals.  \nWhile the Compliance Filing takes positive steps toward optimal resolutions of questions \nin the Order, the Industrials/Amtrak protest several particulars of the Compliance Filing, as \nfollows: \nFirst, PURPA QFs should be eligible for retail netting for their full load, but such eligibility \nshould not be linked to QF status as of the date of the Order. As explained below and in the \nDauphinais Affidavit, the efficiency and configuration of QFs are such that retail BTMG netting \nis an appropriate mechanism to ensure QFs have their back-up power needs met; without retail \nnetting, QFs may be denied the back-up service to which they are entitled by law under PURPA. \nAdditionally, for cogeneration QFs (which are the only QFs larger than 80 MW), the BTMG \nnetting construct aligns with their efficient, reliable energy production configurations, matching \nthe intent of Congress and the FERC. Finally, not all QF-eligible entities have maintained QF \nstatus because PURPA permits the Commission to deem certain QFs as having sufficient market \naccess that it removes (for those QFs) the utility’s obligation to purchase excess power generated \nby the QF. In some cases, units that could qualify as QFs did not seek or maintain QF status. \nHowever, these units operate on the same principles and could seek QF status to ensure they retain \n \n19 See Compliance Filing at 12-13."},{"page":9,"startToken":2645,"endToken":2952,"text":"9 \n \naccess to back-up power, as set forth in PURPA’s implementing regulations. As a result, without \na reasonable back-up transmission option, limiting retail BTMG eligibility to units with QF status \nas of December 18, 2025, would put PURPA’s requirements and the order on compliance in this \nproceeding in conflict. Additionally, maintaining retail netting for QFs effectuates Congressional \nintent, with QFs serving as a statutorily authorized vehicle to support policies favoring \ncogeneration.20 \nSecond, the FERC should approve a Retail Threshold of at least 200 MW. PJM’s proposed \nRetail Threshold of 50 MW is not only factually unsupported, but it is also insufficient to address \nthe worst of the harms to industrial, institutional, and other retail customers. In contrast, a Retail \nThreshold of at least 200 MW best addresses the FERC’s reliability concerns while limiting the \nharm to resource adequacy if the Retail Threshold is set too low. As set forth below and in the \nDauphinais Affidavit, the typical data center coming online today consumes more than 200 MW, \nand concrete evidence supports a Retail Threshold of up to 300 MW.21 A 200 MW Retail \nThreshold better captures the large load growth driving reliability and cost-shifting concerns, while \nmaintaining a structure that prompts critical smaller resource adequacy investments and avoids \nsevere economic damage to America’s industrial, institutional, and transportation sectors. A 200 \nMW Retail Threshold also eliminates most grandfathering issues, thereby simplifying the major \ntransition process initiated by the Order. \nThird, retail netting eligibility should be “up to” the full amount of the Retail Threshold, \nas indicated in the Order, rather than disqualifying a retail customer from retail netting for any \namount of load if their on-site generation were to exceed the Retail Threshold. PJM is proposing \n \n20 16 U.S. Code § 824a-3(a). \n21 See Section IV.B, infra; see also Dauphinais Affidavit at PP 65-69."},{"page":10,"startToken":2952,"endToken":3270,"text":"10 \n \nthat, if the Retail Threshold is 50 MWs, and a retail customer’s BTMG is 57 MWs, the retail \ncustomer would not be eligible for any netting for the initial 50 MWs. PJM’s approach conflicts \nwith the intent of the Order. The Industrials/Amtrak’s proposal, which is based on the plain \nlanguage of the Order, would mean if the Retail Threshold were 50 MWs (and as argued herein, \nevidence supports a much higher Retail Threshold), and a retail customer’s BTMG is 57 MWs, \nthe retail customer should be eligible for netting for the first 50 MWs and not be eligible for netting \nfor the remaining 7 MWs. Not only does an “up to” approach comply with the Order, but it also \nreduces discrimination concerns and avoids an incentive “cliff” that encourages retail customers \nto size their generation smaller than they otherwise would, or that causes projects slightly over the \nlimit to change dramatically. \nBeyond these areas of Protest, the Industrials/Amtrak offer brief Comments on two other \naspects of the Compliance Filing. Regarding grandfathering of existing contracts, the \nIndustrials/Amtrak emphasize that the agreements under which existing BTMG customers operate \nare varied and include agreements with utilities, some of which renew year-to-year. These \nagreements should be recognized as eligible for grandfathering, consistent with PJM’s Compliance \nFiling, to enable these facilities to continue operating. Due to the dramatic cost increases that will \noccur for existing units removed from BTMG status, it is critical that BTMG retail customers be \nable to easily verify their grandfathering status. Most retail customers, particularly manufacturing \ncompanies whose load and generation are tightly interwoven (i.e., cogeneration facilities), cannot \nafford regulatory ambiguity about whether their units qualify for retail BTMG netting. \nFinally, if the Commission opts for a generation-based Retail Threshold, the \nIndustrials/Amtrak support PJM’s proposed tariff provision clarifying that back-up generation \nusable only during specified conditions should not count toward the Retail Threshold."},{"page":11,"startToken":3270,"endToken":3637,"text":"11 \n \nIV. \nPROTEST \nIn the Order, the Commission recognized an inherent tension: PJM’s retail BTMG rules, \nwhich have been deemed just and reasonable in the past, still provide significant benefits and \nshould be maintained—but with limits beyond which loads sited with generation would be treated \ndifferently. The FERC asked PJM to propose a Retail Threshold because “not all loads using \nBTMG are large loads that create the reliability and resource adequacy risks described” in the \nOrder.22 The Commission also stated that other parties would have an opportunity to weigh in on \nthe proposed Retail Threshold. \nThe FERC reviews compliance filings for whether the public utility has complied with the \nrequirements of the underlying order.23 Consequently, the principles that should guide the ultimate \nselection of a Retail Threshold are set forth in the Order itself—namely, to define and respond to \nthe “reliability and resource adequacy” risks and the cost-shifting risks that the Commission sought \nto address in the Order.24 Specifically, the FERC expressed concern about the potential for large \nloads to rely on the transmission system and grid without PJM adequately planning for them.25 \nThe Commission found that “circumstances have changed” since the existing BTMG rules were \ninitially approved, such that the PJM retail netting rules are no longer just and reasonable.26 The \n \n22 Order at P 221. \n23 See, e.g., Southwest Power Pool, Inc., Order on Compliance, 194 FERC ¶ 61,047 at P 1, available at \nhttps://www.spp.org/documents/75765/20260122_order_order%20nos.%202023%20and%202023-\na%20second%20compliance%20filing_er24-2026-001%2C%20002.pdf. \n24 Order at P 179. \n25 Id. at P 186. As to retail BTMG, the Commission found that BTMG rules “are no longer just and reasonable because \nloads with BTMG are not fully accounted for in resource adequacy planning and shift costs onto other transmission \ncustomers contrary to the Commission’s cost causation principles.” Order at P 2. The Commission also stated, “PJM’s \nBTMG rules are no longer consistent with cost causation principles, because large loads configured in a BTMG \narrangement with significant generation will raise cost shifting concerns compared to loads pursuing smaller amounts \nof netting.” Id. at P 186. \n26 Id."},{"page":12,"startToken":3637,"endToken":4078,"text":"12 \n \nCommission referenced PJM’s statement that retail BTMG rules were “conceived for, and [have] \nbeen implemented for, substantially smaller loads (like a warehouse or solar panels) and not on \nthe scale of large data centers” (although PJM’s example is incomplete and not representative of \nlarge traditional BTMG that has existed for decades, as discussed below).27 The Commission also \nquoted PJM’s statement that “[a]llowing very large loads like data centers to net is problematic \nbecause loads in this configuration do not carry reserves.”28 The FERC also raised cost shifting \nconcerns, finding that the existing PJM rules “do not limit the amount of qualifying load that a \nNetwork Customer may net by using BTMG and do not provide any protections against this \npotential transmission and resource adequacy planning problem or against the costs of maintaining \nsufficient resources to serve these loads being shifted onto other customers.”29 Finally, the \nCommission expressed concern that “existing BTMG rules may lead to both reliability and \nresource adequacy risks because PJM, per its Tariff, is obligated to serve transmission customers \nusing BTMG but does not consider such customers in transmission and resource adequacy \nplanning.”30 \n \n27 Id. The Industrials/Amtrak note that PJM’s example of warehouses with solar panels fails to capture BTMG's use \nby a wide array of industrial, institutional, and commercial customers over many years. Even when PJM’s BTMG \nrules were approved in 2004, behind-the-meter units were operating and involved in the FERC proceeding approving \nBTMG rules. For example, a refining company intervenor described its on-site generation as a “60 megawatt combined \ncycle cogeneration facility.” Motion to Intervene of Valero Refining Company – New Jersey, Docket No. ER04-608-\n000 (Mar. 23, 2004). AF&PA, one of the joint protestors in the instant proceeding, also indicated at the time that its \nmembers owned cogeneration and small power production facilities QFs, including approximately 100 small \nhydroelectric plants. Motion for Leave to Intervene Out of Time of the American Forest & Paper Association, Docket \nNo. ER04-608-000 (Apr. 2, 2004). An agricultural company informed FERC that its Decatur, Illinois site includes \n“substantial facilities for the processing of corn, soybeans, and bio-products, as well as a research center.” The \ncompany reported that these facilities “have a combined load, net of the capabilities of [the company’s] onsite \ncogeneration, of between 200 and 300 MW.” Motion to Intervene of Archer-Daniels-Midland Company (“ADM”), \nDocket No. ER04-608-000 (Mar. 22, 2024). ADM did not specify the size of its on-site generation, but considering \nthe size of the net load and the fact that the facilities were cogeneration, the on-site generation was presumably \nsubstantial in size. \n28 Order at P 186. \n29 Id.  \n30 Id."},{"page":13,"startToken":4078,"endToken":4353,"text":"13 \n \nFurther, the Commission acknowledged that “not all loads using BTMG are large loads \nthat create the reliability and resource adequacy risks described above.”31 The FERC directed PJM \nto “propose a new MW threshold for the amount of load at a particular electrical location that \nNetwork Customers may net by using BTMG.”32 The Commission directed that the threshold \n“should reduce the reliability and resource adequacy risks discussed above that large loads may \npose to PJM, while also allowing for Network Customers to reduce their transmission charges in \na transparent, not unduly discriminatory fashion.”33  \nThe principles outlined in the Commission’s statements above provide guidance on the \npath forward. The Retail Threshold should be set in such a way that: (1) identifies and addresses \nthe changed circumstances referenced by the FERC; (2) strikes the balance between super-sized \ndata center computational loads (new to the grid) and traditional BTMG loads, some of which are \nlarge in their own right; (3) pays attention to the unique and varied load/generation configurations \nthat exist; (4) avoids cost-shifting; (5) reduces reliability and resource adequacy risks; and (6) \nallows Network Customers to reduce transmission charges “in a transparent, not unduly \ndiscriminatory fashion.”34 \nAs to the changed circumstances referenced by the FERC, the record and industry \nexperience demonstrate that today’s system challenges are not driven by existing manufacturers \nand institutional customers with retail BTMG. From the beginning, large manufacturers have \noperated behind-the-meter generating facilities that offset their load. At the establishment of \nBTMG rules in PJM over 20 years ago, large on-site generation units already existed and \n \n31 Id. at P 221. \n32 Id. \n33 Id. \n34 See id."},{"page":14,"startToken":4353,"endToken":4749,"text":"14 \n \nparticipated in the proceeding approving BTMG Rules. For example, a refining company \nintervenor at the time described its on-site generation as a “60 megawatt combined cycle \ncogeneration facility,” and an agricultural company described its operational location as having “a \ncombined load, net of the capabilities of [the company’s] onsite cogeneration, of between 200 and \n300 MW,” implying a substantial presence of on-site generation.35  \nIn other words, the “changed circumstances today” cited by the Order are not the result of \n“traditional” types of BTMG load—load that has existed for decades without creating the \nreliability concerns cited in the Order. This stands in contrast to the data center loads seeking to \ninterconnect today. These new loads do not have substantial cogeneration,36 do not generally \noperate large motors (which help with stability on the grid),37 can turn off and on nearly \ninstantaneously, and can reach extremely large sizes, well beyond the traditional “large” BTMG, \nand well beyond the 200 MW Retail Threshold being proposed in this Protest.38 The planning of \nnew AI data centers, with speed-to-power demands, is also distinct from more long-term, drawn-\nout planning by manufacturers examining facility additions.   \nTo that point, the Order did not find that BTMG rules were unjust and unreasonable as \nused by manufacturers with cogeneration, other QFs (which are size limited under PURPA), or \neven traditional “large” loads with BTMG, as discussed above. This “traditional” BTMG \n \n35 Motion to Intervene of Valero Refining Company – New Jersey, Docket No. ER04-608-000 (Mar. 23, 2004). \n36 See Dauphinais Affidavit at P 50 (“[V]ery large computational load processes are generally not highly thermally \nintegrated, if integrated at all, with any co-located generation facilities whose meter they may be located behind. This \nis because those generation facilities will either not be Cogeneration Facilities or would only be Cogeneration \nFacilities of greatly limited electrical capability relative to the total magnitude of the electrical load of their host retail \ncustomer.”) See also id. at PP 22-24. \n37 See Assessment of Gaps in Existing Practices, Requirements, and Reliability Standards for Emerging Large Loads: \nNERC \nLarge \nLoads \nWorking \nGroup \nWhite \nPaper \n(March \n2026), \nat \np. \n29, \navailable \nat \nhttps://www.nerc.com/globalassets/our-work/guidelines/reliability/white-paper---assessment-of-gaps.pdf. \n38 See Dauphinais Affidavit at PP 65-69 (providing evidence that most load added by large load additions is by \nadditions of 300 MW and higher)."},{"page":15,"startToken":4749,"endToken":5049,"text":"15 \n \ncomprises factories, hospitals, universities, transportation networks, and more. Yet, these are \ncustomers for whom BTMG has been implemented for over twenty years. Absent appropriate \nexemptions and an appropriate Retail Threshold, these types of customers will bear the brunt of \nchanges to BTMG-related netting rules.  \nFor some industrial and institutional customers, transmission and capacity cost savings are \na critical factor that makes it worth the investment to build and operate generation on their \npremises—investments these customers have already made (sometimes over decades).39 Absent a \nreasonable alternative, applying a “gross load” measurement to retail BTMG for Network \nIntegration Transmission Service (“NITS”) and capacity (subject to requests for clarification) \ncould seriously damage existing users’ economic viability by requiring customers to be charged \nfor transmission and capacity as if their behind-the-meter generation were not operating. \nAddressing cogeneration units in particular, Mr. Dauphinais explained that if the ability to operate \n“in a safe and environmentally compliant manner within the bounds of what can be supported by \nthe remaining thermal capability of the Cogeneration Facility at just and reasonable electric power \nrates” cannot be assured, “cogeneration may fail to be a practical and/or economic solution to the \nretail customer’s needs, causing the efficiency benefits of cogeneration to be forgone and/or the \nretail customer to become economically unviable.”40 Even if the customer were to monetize the \nenergy output of its on-site generation, substantial risks exist that the value that could be earned in \nthe PJM market would be substantially less, with much more attendant risk, than the value of \nnetting and may require the customer to undertake transmission upgrades such that its generation \nis deliverable to all of PJM, not just the proximate load. In contrast, BTMG with netting (up to a \n \n39 See Dauphinais Affidavit at P 17. \n40 Id."},{"page":16,"startToken":5049,"endToken":5316,"text":"16 \n \nreasonable degree) not only (1) makes it more likely that hospitals, manufacturers, factories, \nuniversities, and transportation networks’ on-site generation is economically viable to operate, \nspurring investment;41 but (2) it is designed in such a way that on-site generation is incentivized \nto align with resource adequacy goals by operating efficiently and at times of system stress.42 \nConsequently, the FERC’s path forward to implement the Order should consider the \nperformance of these units and the substantial resource adequacy contributions of BTMG, \nincluding in developing a reasonable Retail Threshold. There is simply no need for the “one-two \npunch” of making industrial and institutional BTMG uneconomic and removing an incentive to \noperate them efficiently. Instead, the FERC has the opportunity to implement its  Order in a way \nthat: (1) limits collateral damage to resource adequacy; (2) avoids making development by retail \ncustomers of small power production complicated or prohibitive; (3) recognizes the unique \nconfigurations, incentives, and contributions of industrial and institutional retail customers, which \ndo not neatly fit into a wholesale PJM context; and (4) avoids unnecessarily counteracting the \ngoals for onshoring and economic development expressed by the Administration and PJM \nGovernors.43 By setting appropriate applicability standards for BTMG, the FERC will empower \nthe industrial and institutional sectors to continue to make investments in support of resource \nadequacy, a critical need in the coming years across PJM. \n \n \n \n41 See id. at PP 17, 43. \n42 See id. at P 36. \n43 See, e.g., The White House, Made in America Agenda Delivers Manufacturing Boom (Aug. 13, 2025), available at \nhttps://www.whitehouse.gov/articles/2025/08/made-in-america-agenda-delivers-manufacturing-boom/."},{"page":17,"startToken":5316,"endToken":5637,"text":"17 \n \nA. \nPJM’s proposed exemption for PURPA Qualifying Facilities is appropriate, \nbut it should not be linked to QF status as of the date of the Order. (Protest \nIssue #1) \nCongress’s mandate under PURPA is to encourage cogeneration, small power production, \nand geothermal energy production.44 PURPA has played an important role for manufacturers and \nthe electric grid for nearly five decades. It has provided market access where none previously \nexisted, taken strain off the grid, and supported American industry by enabling economic means \nto reduce energy costs, even in vertically integrated territories. \nPJM has proposed a PURPA-related grandfathering provision that would allow facilities \nthat were QFs as of December 18, 2025, to continue to net. As explained below, exempting PURPA \nQFs is appropriate and aligns with the goals of the FERC’s Order.45 In fact, due to the PURPA \nrequirements regarding back-up generation, the benefits of QFs to the grid, and the operating \nprofile of QFs, the BTMG rules should be applied to all QFs, not only those that were certified as \nof the date of the issuance of the Commission’s Order. \nBy way of background, QFs fall into two broad categories: “qualifying small power \nproduction facilities,” which can be sized up to 80 MW, and “qualifying cogeneration facilities,” \nwhich have no size limit.46 However, cogeneration QFs must achieve certain efficiency standards \nand are highly efficient in their use of input fuels.47 Cogeneration QFs, which produce both \nelectricity and heat from the same fuel source, make use of the “waste heat” in their manufacturing, \nheating, or cooling process. As explained by Mr. Dauphinais, “Cogeneration Facilities can achieve \n \n44 16 U.S. Code § 824a-3(a). \n45 Importantly, the Order did not address PURPA or otherwise modify or address the Commission’s PURPA \nregulations. Therefore, exempting PURPA QFs is consistent with the Order. See Dauphinais Affidavit at P 49. \n46 16 U.S. Code § 824a-3. \n47 Dauphinais Affidavit at P 11."},{"page":18,"startToken":5637,"endToken":5986,"text":"18 \n \nefficiencies in excess of 80%, by using waste heat and avoiding electrical losses, compared to the \nefficiency of approximately 50% for conventional electricity generation with a steam boiler.”48 \nIn its Compliance Filing, PJM explained its reasoning for applying a grandfathering \nexemption to allow existing QFs to operate under BTMG rules:  \nPJM understands that there exists today Retail BTMG that were QFs as of \nDecember 18, 2025, with many being cogeneration QFs that are often used in \nmanufacturing and other processes to produce both electricity and useful thermal \nenergy that often lead to economic and energy efficiency benefits. Under \nCommission regulations, QFs have built-in size limits or, for cogeneration, meet \nstrict efficiency requirements. Specifically, for a cogeneration QF, the generating \nfacility and its load are closely integrated. For example, some retail customers’ \nloads may be configured such that the load reduces if on-site generation is \nunavailable because manufacturing processes reliant on thermal heat will \ndiscontinue.49  \n \nPJM’s rationale for the inclusion of QFs in BTMG touches on several of the Order’s key \nfindings and observations. For example, the Order’s finding that “circumstances have changed,” \nresulting in BTMG rules no longer being just and reasonable, does not apply particularly to QFs, \nwho have been operating similarly for decades.50 PJM specifically notes that “existing retail \nBTMG arrangements with such contractual agreements and that otherwise have QF status have \nbeen in place and netted against Network Loads within PJM without operational issues to date.”51  \nThe grid's resource adequacy and reliability challenges are not traceable to QFs; in contrast, \nQFs make a substantial contribution to both. As to the size and configuration of the facilities, as \nPJM notes, the cogeneration QFs must meet strict efficiency requirements, and other QFs are size-\nlimited (to 80 MW). Some are limited in their use of the transmission system due to the deep \n \n48 Id. \n49 Compliance Filing at 9-10. \n50 See, e.g., supra n. 25, demonstrating that large on-site generation existed from the beginning of the implementation \nof retail BTMG rules in PJM over 20 years ago. \n51 Compliance Filing at 10."},{"page":19,"startToken":5986,"endToken":6283,"text":"19 \n \nintegration between load and on-site generation. Mr. Dauphinais explains in the Affidavit that \nwhen an outage of a cogeneration facility occurs, “significant electric load of the host retail \ncustomer can be lost immediately following, or very shortly following, the outage.”52 This can be \ndue either to certain industrial or commercial processes “not being able to operate without thermal \nenergy from the Cogeneration Facility if it is a Topping-Cycle facility” or due to “a thermal process \nbeing unable to operate because of the inability to dump its waste heat to the Cogeneration Facility \nif it is a Bottoming-Cycle facility.” Put simply, the very configuration of many industrial \ncogeneration facilities directly limit use of the transmission system. All of these reasons \ndemonstrate low cost-shifting or reliability risks, and warrant remaining within the longstanding \nBTMG netting rules. \nIn addition, BTMG netting directly meets the legal requirements of PURPA—namely, \nenabling QFs to access the back-up power to which they are entitled by law.53 Upon request, QFs \nare entitled to access to supplementary power, back-up power, maintenance power, and \ninterruptible power, pursuant to long-established enacting regulations.54 Rates for back-up or \nmaintenance power “[s]hall not be based upon an assumption (unless supported by factual data) \nthat forced outages or other reductions in electric output by all qualifying facilities on an electric \nutility's system will occur simultaneously, or during the system peak, or both.”55 As explained in \ndetail in the Dauphinais Affidavit, the netting construct permits QFs to receive the back-up power \nthey are guaranteed—back-up power that is charged without assuming they will be needed during \n \n52 See Dauphinais Affidavit at P 16. \n53 See id. at PP 17-21.  \n54 18 C.F.R. § 292.305(b). \n55 18 C.F.R. § 292.305(c)(1)."},{"page":20,"startToken":6283,"endToken":6671,"text":"20 \n \npeak times.56 The current BTMG construct (with netting) meets this need perfectly; if such services \nare needed during peak times, the current design ensures customers pay for them by appropriately \nmeasuring peak usage.57 \nIn contrast, transitioning to a gross-only approach would subvert this alignment with \nPURPA’s Regulations. Assuming a QF had access to the Firm Contract Demand service (which is \nnot clear from the Order), that service would be calculated based on the maximum the load might \ndraw from the grid, which is not a service that makes sense for extremely rare needs to use the \ngrid.58 Similarly, Non-Firm Contract Demand service is not designed for back-up service, as it \nmust be scheduled in advance.59 Without clarity on how QFs will obtain back-up and maintenance \npower across all contexts, QFs should be permitted to continue under the current netting regime. \nA further reason to continue netting for QFs is that cogeneration QFs are deeply integrated \nwith the operations of the adjacent plant or facility.60 Strong operational and financial incentives \nexist for cogeneration facilities to operate reliably and efficiently, even above the ordinary cost-\nsavings incentives of all generators. Further, to maintain QF status, the Regulations require certain \nQFs to meet specified efficiency standards.61  \n \n56 See Dauphinais Affidavit at P 29 (explaining that the netting approach “is consistent with FERC’s rule for backup \nand maintenance power for Qualifying Facilities as it does not assume that a retail customer’s behind the meter \nQualifying Facility will be experiencing an outage at the time of the annual transmission system peak and instead \nrelies on factual data, in the form of the behind the meter Qualifying Facility’s historical performance during the time \nof the annual peak of the transmission pricing zone, when allocating transmission costs to the retail customer.”). See \nalso id. at P 49. \n57 Id. at 29. \n58 See id. at PP 44-45. \n59 While the back-up power is often in retail tariffs, transmission services are part of the costs to the retail supplier that \nmust be passed along to the retail customer. Broadly speaking, retail customers’ transmission charges flow through \nthe supplier or local utility and are not directly charged by PJM.  \n60 See Dauphinais Affidavit at P 16. \n61 See 16 U.S. Code § 824a-3(n); 18 C.F.R. § 292.205."},{"page":21,"startToken":6671,"endToken":7209,"text":"21 \n \nIn some cases, generation and load are tightly coupled, so that if the generator goes offline, \nthe load promptly follows because the manufacturing facility cannot function without the steam \noutput from the generation process. This, by nature, limits grid impacts, in contrast with data \ncenters, which may experience rapid, sudden load shifts. For cogeneration QFs, neither a gross \nload approach nor a Firm Contract Demand service, nor a non-Firm Contract Demand service (as \ndesigned) aligns with the costs or risk profile of cogeneration QFs. Without access to netting or a \ncomparable alternative, QF customers may lose their ability to manage costs even if their load and \ngeneration are synchronized or if they never rely on transmission services. This creates an \nenormous cost-causation gap,62 contrary to long-standing Commission precedent.63 Consequently, \nwithout netting or a reasonable alternative, cogeneration QFs that are operating excellently with a \nhigh capacity factor will suddenly be paying for transmission service that they do not use.64 \nAdditionally, many QFs size their cogeneration units based on the thermal or steam needs at their \nfacility (such as to provide heating, operate chillers, or make productive use of steam). As stated \n \n62 Under the cost causation principle, “costs are to be allocated to those who cause the costs to be incurred and reap \nthe resulting benefits.” Nat’l Ass’n of Reg. Util. Comm’rs v. FERC, 475 F.3d 1277, 1285 (D.C. Cir. 2007). See also \nOld Dominion Elec. Coop. v. FERC, 898 F.3d 1254, 1255 (D.C. Cir. 2018) (adding that the “cost-causation principle” \nhas been recognized “for decades” by “the Commission and the courts”); K N Energy, Inc. v. FERC, 968 F.2d 1295, \n1300 (D.C. Cir. 1992); City of Lincoln v. FERC, 89 F. 4th 926, 930 (D.C. Cir. 2024); see BNP Paribas Energy Trading \nGP v. FERC, 743 F.3d 264, 268 (D.C. Cir. 2014) (ensuring that “the burden is matched with benefit”); see also \nMidwest ISO Transmission Owners v. FERC, 373 F.3d 1361, 1368 (D.C. Cir. 2004) (“we evaluate compliance with \nthis unremarkable [cost causation] principle by comparing the costs assessed against a party to the burdens imposed \nor benefits drawn by that party.”).   \n63 See, e.g., Occidental  Chem.  Corp. v. PJM Interconnection, 102 FERC ¶ 61,275, 61,852. The Industrials note that, \nas the North American Electric Reliability Council (“NERC”) works to develop reliability standards for large loads, \nit has thus far avoided setting a bright-line MW-based threshold, as other factors besides load size affect reliability \nconsiderations. The NERC Large Load Task Force has focused its recent reliability impact review on computational \nloads, recently observing that “[t]he penetration of large loads on the [Bulk Power System] is growing, especially \ncomputational loads.” Assessment of Gaps in Existing Practices, Requirements, and Reliability Standards for \nEmerging Large Loads: NERC Large Loads Working Group White Paper (March 2026), at p. 46, available at \nhttps://www.nerc.com/globalassets/our-work/guidelines/reliability/white-paper---assessment-of-gaps.pdf. \n64 The Firm Contract Demand and Non-Firm Contract Demand combination of new transmission service options \noutlined in the Order might work for planned generation outages, but they do not appear to account for forced \ngeneration outages. See Dauphinais Affidavit at PP 42-45."},{"page":22,"startToken":7209,"endToken":7527,"text":"22 \n \nby Mr. Dauphinais, “[T]he thermal energy needs of the retail customer typically dictate how much \nelectric power must be produced by the Cogeneration Facility. For example, if an industrial retail \ncustomer has a very high steam need for its processes relative to its electrical needs, the \nCogeneration Facility serving that customer will likely have to produce electric power well in \nexcess of that retail customer’s needs for its electrical load.”65 This approach may result in excess \nenergy being produced. PURPA generally requires local utilities to purchase this excess energy \n(“must-purchase obligation”). However, the law permits the Commission to deem certain QFs as \nhaving sufficient market access that the applicable utility is excused from its must-purchase \nobligation.66  \nAfter many utilities terminated their mandatory purchase obligations in the wake of the \ndevelopment of organized wholesale markets, retail customers with QFs that had excess power \nwere required to secure Interconnection Service Agreements (“ISA”) with PJM and the applicable \ntransmission owner and market-based rate authority to enable sales of excess energy to the PJM \nmarket. This history should not limit the ability of retail customers with cogeneration facilities to \navail themselves of retail BTMG netting for energy production behind the retail meter.  \nCogeneration facilities that are (or could be) QFs are well-positioned to benefit the grid and their \nmanufacturing operations in an efficient, cost-effective manner. \nIn the wake of the termination of the mandatory purchase obligation, many QF-eligible \ncustomers did not seek or maintain QF status due to a combination of (1) having access to cost-\nbased back-up power via BTMG netting rules,67 and (2) their utilities’ must-purchase obligations \n \n65 Dauphinais Affidavit at P 15.  \n66 16 U.S. Code § 824a-3(m). \n67 Dauphinais Affidavit at P 48 (“PJM’s proposal fails to recognize there may be some Cogeneration Facilities within \nthe PJM footprint that fully meet FERC’s requirements to be a Qualifying Cogeneration Facility (and, thus, a"},{"page":23,"startToken":7527,"endToken":7895,"text":"23 \n \nbeing terminated. However, these units operate on the same principles and could seek QF status – \nor re-certify their QF status – to ensure they retain access to back-up power, as set forth in \nPURPA’s implementing regulations under the current “changed circumstances.” Without a \nreasonable back-up transmission option, limiting BTMG eligibility to units with QF status as of \nDecember 18, 2025, would put PURPA’s requirements and the FERC’s direction in this \nproceeding in conflict.68  \nFinally, the same factors listed above will also apply to future QFs, particularly \ncogeneration facilities. Because PURPA’s policy objectives as implemented by the FERC remain \nintact, and because QFs are outside the key concerns set forth in the Order, the date limitation in \nPJM’s proposed definition of Retail Behind-the-Meter Generation should be removed. \nEncouraging more QFs aligns with the goals established by federal statute, which remain as \nrelevant today as they were in the 1970s. QFs should be moved from grandfathered status to full \ninclusion as BTMG. \nB. \nPJM’s Proposed 50 MW Retail Threshold is insufficient to balance the \nFERC’s stated resource adequacy concerns with the harm to existing \nmanufacturers, retail customers, and their contributions to resource \nadequacy. PJM’s alternative Retail Threshold of 200 MW more appropriately \nbalances these concerns, while simplifying compliance and supporting \neconomic development. (Protest Issue #2) \nIn its Order, the FERC directed PJM to propose a Retail Threshold, below which retail \nBTMG netting rules will continue in effect. The Order did not specify at what level the Retail \nThreshold should be set. In its Compliance Filing, PJM proposes a Retail Threshold of 50 MW “to \n \nQualifying Facility), except they do not currently have a FERC-approved certification or self-certification of their \nQualifying Cogeneration Facility status because they do not [make] sales of excess power either at avoided cost to \nelectric utilities or into the wholesale power market. In addition, these Cogeneration Facilities have historically not \nneeded certification or self-certification as a Qualifying Cogeneration Facility in order for the electrical load of their \nhost retail customer to have reliable access to backup and maintenance power through just and reasonable rates through \nPJM’s current retail behind the meter generation netting provisions for NITS charges and capacity requirements.”) \n68 Dauphinais Affidavit at P 49."},{"page":24,"startToken":7895,"endToken":8263,"text":"24 \n \navoid unneeded regulatory uncertainty for retail customers whose grid impacts on reliability are \nmore limited and have been in existence without noted impact for decades.”69 PJM also offers an \nalternative concept of a higher threshold, specifically naming the minimum 200 MW threshold of \nPJMICC, as an interim solution in the event the Commission does not accept PJM’s proposed \nlegacy treatment for existing on-site generation greater than 50 MW.70 \nPJM makes important points in its Compliance Filing about the damaging impact a low \nRetail Threshold would have on some retail customers and their on-site generation, noting that \nwithout sufficient grandfathering exemptions, a too-low Retail Threshold could cause existing \nRetail BTMG resources to “cease operations and in turn exacerbate in an unintended fashion the \nresource adequacy issues in the PJM Region.”71 Unfortunately, this concern is not limited to \ngeneration sized at 50 MW and less. While many retail customer facilities are, in fact, smaller than \n50 MW, heavy industry and manufacturing facilities as well as transportation providers often have \nmore than 50 MW of generation operating behind their retail meters, including facilities producing \naluminum, paper, steel, chemicals, oil refineries, and more. While PJM recognizes the concern \nabout affecting existing resources above 50 MW, the Industrials/Amtrak believe it is critical that \nthe Commission choose a Retail Threshold that preserves the reliability contributions of these \nkinds of facilities—both existing and planned. While no bright-line MW threshold will perfectly \ndelineate grid impacts, the fact is that a significant number of dependable, on-site generation units \n \n69 Compliance Filing at 12. PJM proposed a generation-based threshold, as opposed to a load-based threshold. This \ndiscussed in more detail in Section IV.C., infra. \n70 PJM states that if the Commission adopts a “higher interim materiality threshold of this sort at the start of the \ntransition period, PJM commits to reviewing additional data from Transmission Owners on the extent and size of \nexisting Retail BTMG. This data could inform whether the interim materiality threshold should be further refined in \nthe future through a separate filing on compliance in this docket or, if necessary, pursuant to section 205 of the Federal \nPower Act.” Compliance Filing at 15. \n71 Compliance Filing at 14."},{"page":25,"startToken":8263,"endToken":8582,"text":"25 \n \nwith negligible reliability risks to the grid exist in this range up to 200 MW and even up to 300 \nMW.72 If the Commission sets the Retail Threshold too low, it will risk creating additional cost-\ncausation concerns for industrial, institutional, and transportation facilities with high capacity \nfactors and minimal downtime.  \nConsequently, PJM’s alternative Retail Threshold of at least 200 MW is superior to the \nmain proposal of 50 MW for several reasons, summarized as follows:  \n1. A 200 MW Retail Threshold maintains incentives that bolster resource adequacy \nand grid efficiency, thereby avoiding inefficient transmission investment. \n \n2. A 200 MW Retail Threshold preserves the focus on reliability challenges caused by \nsuper-sized load, while avoiding economically devastating outcomes for \nmanufacturing, institutional and transportation facilities. \n \n3. A 200 MW Retail Threshold avoids major administrative disincentives to operate \non-site generation by avoiding the need to force existing retail customers into new and \nunfamiliar regulation, requiring them to become FERC-regulated public utilities, \nsecure PJM membership, and undertake related credit and risk requirements.   \n \n4. A 200 MW Retail Threshold aligns with regulatory logic that identifies various \n“tiers” of large load.  \n \n5. A 200 MW Retail Threshold avoids burdening PJM with a significant number of \nstudies for existing generators (for generator deactivations or for BTMG that \nbecomes Co-Located Generation). \n \n6. A 200 MW Retail Threshold de-emphasizes grandfathering and emphasizes stable \nrules for customers, a more durable approach. \n \n7. A 200 MW Retail Threshold respects the importance of onshoring manufacturing, \nconsistent with federal and state economic development goals. \n \nBelow, the Industrials/Amtrak elaborate on and support each of the above points. \n#1. Resource adequacy and grid efficiency. The Commission did not provide an \nexhaustive list of all reasons for seeking input on a Retail Threshold. However, the \n \n72 See Dauphinais Affidavit at 67 (referencing data and regulatory developments in Michigan demonstrating that a \n300 MW threshold is supportable considering data center MW load requests)."},{"page":26,"startToken":8582,"endToken":8945,"text":"26 \n \nIndustrials/Amtrak respectfully suggest that one of the primary considerations should be the \nresource adequacy contributions of retail BTMG. On-site generation—particularly larger units—\nprovides substantial benefits to the grid. Rapid retirement of these resources would create a near-\nterm surge in forecast load and, thus, transmission planning needs, resulting in extremely high \ntransmission rates being pushed, artificially, even higher. As noted by PJM in its Compliance \nFiling, removing netting from existing retail BTMG could result in many older retail BTMG units \ndeciding to “forego the option of interconnecting into the PJM system altogether,” resulting in \n“higher Network Loads requiring grid service, as loads that are currently netted by the retail BTMG \nwould not be matched with additional supply of Capacity Resources.”73 One reason that a customer \nmay elect not to continue operating its retail BTMG is that, in order to become a PJM Capacity \nResource, the behind-the-meter generation would need to become deliverable to all PJM load, \nwhich could result in costly transmission upgrades, which may render the generation unit \nuneconomic. From a resource adequacy perspective, this is an undesirable outcome, as these \nbehind-the-meter resource and reliability benefits are needed as the industry faces an \nunprecedented reliability challenge.74  \nPart of the benefits to the grid derive from the fact that these large generating units are \nincentivized by the netting structure to operate their on-site generation during times of grid stress \nbecause it is those very times when the billing determinants for capacity or back-up service are \nestablished for retail customers, including those with BTMG.75 Maintenance and other outages are \n \n73 Compliance Filing at 13. \n74 The PURPA construct indirectly demonstrates the value of proliferation of “small” (in PURPA’s case, up to 80 \nMW), on-site generation as an important piece of the resource adequacy puzzle. PURPA was developed during the \nenergy crises of the 1970s, and while FERC is not bound to 80 MW as a Retail Threshold (indeed, the \nIndustrials/Amtrak believe it should be higher with grid expansion and growth), PURPA’s design and logic emphasize \nthe value of policies that facilitate generation projects, including on-site generation supporting a retail customer’s load. \n75 Dauphinais Affidavit at P 36."},{"page":27,"startToken":8945,"endToken":9295,"text":"27 \n \nplanned or minimized in accordance with these incentives. As explained by Mr. Dauphinais, the \nnetting construct “sends a strong cost signal for retail behind the meter generation to operate and \nfully serve the electric load of their host retail customer during times of grid stress.”76 The \nCommission should avoid a compounded danger that would occur from setting the Retail \nThreshold too low, where (1) some BTMG (existing or planned) becomes uneconomic, reducing \nthe amount of generation on the grid; and (2) the remaining BTMG is not incentivized to operate \nduring times of system stress. Such a “one-two punch” could be substantially avoided by a Retail \nThreshold that aligns with how most existing on-site generation located with retail customers is \ndesigned and operates.  \n#2. Avoiding economic damage to retail customers. The Commission’s Order addresses \nchanging circumstances transforming the grid. These changes, however, are not largely driven by \n50, 100, or even 200 MW facilities. As stated by a large group of PJM transmission owners in the \ncurrently pending Large Load ANOPR Proceeding, large data centers of 200 MW or greater are \nthe primary drivers of load growth.77 These new entrants frequently have massive capital behind \nthem, enabling them to develop massive centers of load more quickly than any manufacturer or \nindustrial seeking to expand operations. \nIn contrast to a super-sized load currently planning its entrance onto the grid, the removal \nof netting rules will fall most heavily on existing customers and the industry that is “stuck” with \nthe economics of their sector. For many of these customers, particularly heavy industry, energy is \none of the top costs of doing business. The on-site generation facilities these customers have \n \n76 Id. \n77 See Reply Comments of the Indicated PJM Transmission Owners, Interconnection of Large Loads to the Interstate \nTransmission System, Docket No. RM26-4-000 (Dec. 5, 2025) at 2-3 (“To the extent the Commission asserts \njurisdiction over large load interconnections, it should adopt a sufficiently narrow definition of ‘large load customer’ \nlimited to large (200 MW or greater) data center customers. It is those customers that are primarily driving load \nincreases.”)."},{"page":28,"startToken":9295,"endToken":9609,"text":"28 \n \ndeveloped were built based on certain assumptions and have been operated under those \nassumptions. For some customers, changes to a gross-load approach for transmission and/or \ncapacity will render those units uneconomic, forcing them to operate at a loss, close and seek \npower from the grid, or shutter the plant entirely.  \nThese customers and the industries that make up the “middle range” of up to around 200 \nMW or 300 MW—who have been relying on netting rules for decades—should not be lumped in \nwith super-sized forces that are transforming the grid and its attendant costs. In the recent \nStatement of Principles Regarding PJM (“Statement of Principles”), the White House’s National \nEnergy Dominance Council and the PJM governors explain that the “size and the risks [of data \ncenters] pose to resource adequacy make today’s data centers unique.”78 The Statement of \nPrinciples expresses a commitment to ensure that data centers bear the costs of new capacity, where \nthey have not secured their own capacity or agreed to be curtailed. In a similar fashion, this “middle \nrange” of industrial, institutional, and transportation customers, up to around 200 MW or 300 MW, \nshould not bear the costs driven by rapid, super-sized data center growth. \n#3. Avoiding regulatory burdens. To the extent practicable, the Commission should avoid \nrequiring retail customers to enter and comply with a complex federal regulatory regime. Large \nmanufacturers and institutional customers are focused on their core business. Forcing such retail \ncustomers into new and unfamiliar regulation, PJM membership, and other federal requirements \ncreates a substantial burden. As PJM indicated in its Compliance Filing, this added burden may \ncompound resource adequacy concerns. PJM stated in its Compliance filing, “Further, concerns \nwere raised that a lower threshold could force many existing Retail BTMG resources offline during \n \n78 \nDepartment \nof \nEnergy, \nStatement \nof \nPrinciples \nRegarding \nPJM, \navailable \nat \nhttps://www.energy.gov/documents/statement-principles-regarding-pjm."},{"page":29,"startToken":9609,"endToken":9850,"text":"29 \n \nthe transition period because such resources do not intend to enter into PJM’s interconnection queue \nto become a market resource.”79 \nWhile the Order is primarily aimed at new arrangements involving wholesale generators, \nthe BTMG changes are directly impactful for retail customers who have built, supported, and \nstrengthened the PJM grid for decades. A low Retail Threshold will have a chilling effect on \nmanufacturers’ interest in on-site generation solutions that could otherwise mitigate existing \nresource adequacy challenges. A low Retail Threshold will render some manufacturers with on-\nsite generation uneconomic, including, but not limited to, the case where the retail BTMG \ncustomer may be forced to incur inefficient costs so that its generation can be generally deliverable \nfor all PJM load, even if the generation was built to serve the proximate load. These potential costs \nand risks of transforming retail BTMG into a PJM Capacity Resource could reasonably be \nexpected to remove generation resources from the system at a time of high resource adequacy \nrisks. \nFurther, the BTMG netting structure recognizes and works with diverse operational \nconfigurations of retail customers. Retail BTMG configurations are varied and often complex. \nNetting up to a reasonable threshold allows industrial and institutional configurations to be \ndeveloped, maintained, and expanded without triggering complicated wholesale market rules, \nmetering configurations, PJM studies, PJM filings, and more. For retail customers, being able to \nplan and develop under stable, existing rules has immeasurable value. \n \n79 Compliance Filing at 12."},{"page":30,"startToken":9850,"endToken":10288,"text":"30 \n \nFinally, while not directly controlling on the “gross/net” issue, PURPA, as a long-\nestablished resource adequacy statute, offers a regulatory logic that supports this notion.80 \nSpecifically, PURPA demonstrates the importance of power production that is integrated with \nindustrial and institutional operations, primarily through PURPA’s recognition of qualifying \ncogeneration facilities. The facilities, which are frequently situated on-site with industrial \nfacilities, make use of both power produced and steam or heat simultaneously to power heating, \nchillers, or other industrial processes. As demonstrated by PURPA, there are sound policy and \nlegislative reasons to not treat those integrated facilities as public utilities or to burden them with \nthe regulatory demands required of wholesale generators in PJM. The FERC should do the same \nhere by setting a sufficiently high threshold to avoid “death by 1000 cuts” to the industrial and \ninstitutional customers who are retail customers and are accustomed to operating as such. PJM has \noffered to review data on the extent and size of existing retail BTMG.81 This proposal could \nmitigate the FERC’s concern about PJM not planning for the full extent of behind-the-meter load, \nas it relates to BTMG under a reasonable Retail Threshold. \n#4. Regulatory Logic of 200 MW. In seeking input on the Retail Threshold question, the \nCommission noted possible points of reference. In particular, the Commission mentioned that “the \n \n80 While “ancient wisdom” may be a bridge too far in describing an Act of Congress from nearly 50 years ago, PURPA \nprovides a timely, enduring, and relevant perspective on today’s issues. Passed in the 1970s during the energy crisis \nof that era, PURPA offers value in this proceeding as a regulatory roadmap that may inform FERC’s consideration of \nan appropriate Retail Threshold. In addition to the value of proliferation of on-site generation as an important piece \nof the resource adequacy puzzle, PURPA also emphasizes the importance of power production that is integrated with \nindustrial and institutional operations and the essential nature of cost-driven back-up and maintenance power options. \nThese points do not provide precise answers to the questions FERC asked PJM to weigh in on, but they do provide \nvaluable regulatory context for addressing them.  \n81 Compliance Filing at 15 (“Should the Commission adopt a higher interim materiality threshold of this sort at the \nstart of the transition period, PJM commits to reviewing additional data from Transmission Owners on the extent and \nsize of existing Retail BTMG. This data could inform whether the interim materiality threshold should be further \nrefined in the future through a separate filing on compliance in this docket or, if necessary, pursuant to section 205 of \nthe Federal Power Act.”)."},{"page":31,"startToken":10288,"endToken":10596,"text":"31 \n \nCommission’s definition of a small generator is 20 MW.”82 While many reference points could be \nproposed, the Industrials/Amtrak agree with PJM that 10 MW or 20 MW are far too low for this \npurpose. Instead, the Industrials/Amtrak have selected 200 MW as a proposed minimum Retail \nThreshold based on industry data, including the size of new large load and the typical size of long-\nestablished generation that would otherwise have to rely on grandfathering.83 Yet, there is \nregulatory logic that supports a 200 MW Retail Threshold, as well.  \nAcross the country, in state proceedings and other proceedings at the FERC, debates are \nraging about how exactly “large load” should be defined. While “large load” may mean different \nthings in different contexts, the Industrials/Amtrak respectfully suggest that the Commission \nshould consider a size framework that recognizes that “large load” and “large generation” come in \ndifferent iterations. While various cutoffs have been proposed, one federal reference point for \n“small” generation is PURPA’s cutoff for non-cogeneration QFs at 80 MW. These types of QFs \nare termed “qualifying small power production facilities,” suggesting that medium or larger \ngeneration categories would be above 80 MW. To that end, the Industrials note that many of their \nmembers, who are large manufacturers, come in this “middle” zone between “small” (under 80 \nMW) and “super-sized” (above 200 or 300 MW).  \nMore recently, Order 2023 and Order 2023-A also provide logical groupings for generation \nsizing purposes. There, the Commission set forth tiers of study deposits, with the lowest tier being \n \n82 Order at P 221 (citing Order No. 2006, 111 FERC ¶ 61,220 at P 1). \n83 See Dauphinais Affidavit at PP 65-69. See also Reply Comments of the Indicated PJM Transmission Owners, \nInterconnection of Large Loads to the Interstate Transmission System, Docket No. RM26-4-000 (Dec. 5, 2025) at 2-\n3."},{"page":32,"startToken":10596,"endToken":10896,"text":"32 \n \ngeneration under 80 MW (reflecting the PURPA “small” generation cutoff), the middle tier being \n80 MW to under 200 MW, and the upper tier being 200 MW or above.84  \nWhile the Commission is not bound to any of these reference points, the Industrials/Amtrak \nbelieve that the Commission faces a critically important decision on the “middle tier” up to 200 \nMW. In that band sits some of America’s biggest manufacturing facilities, including steel, \nconsumer good producers, chemicals, pharmaceuticals, oil refineries, transportation providers, and \nothers, who have demonstrated for decades their reliable contributions to the grid. Many of these \nfacilities are cogeneration facilities and QFs, demonstrating efficiency and integrated load and \ngeneration, especially when there are thermal processes involved. The Industrials/Amtrak \nrespectfully request that the Commission set a Retail Threshold that allows for netting up to the \ntop of this “middle tier” at 200 MW. How the FERC resolves this may determine the future of \nhundreds of megawatts of existing and planned on-site generation that would support resource \nadequacy efforts in the region.  \n#5. PJM staffing. A 200 MW Retail Threshold avoids burdening PJM with a significant \nnumber of studies for existing generators (or for generator deactivations). Without a reasonably \nhigh Retail Threshold, PJM staff will likely have to process a considerable number of deactivation \nrequests, interconnection studies, and other activities, all at a time when PJM is facing tremendous \nchallenges with resource adequacy and reliability. \n#6. De-emphasizing grandfathering. By setting a higher threshold, the FERC would \nrelieve customers, PJM, and the FERC from most grandfathering questions and uncertainty. While \ngrandfathering rules should be clear and confirmable, as discussed below, the higher the FERC \n \n84 See Order on Rehearing and Clarification, Improvements to Generator Interconnection Procedures and Agreement, \n186 FERC ¶ 61,199 at PP 187-188 (Mar. 21, 2024)."},{"page":33,"startToken":10896,"endToken":11175,"text":"33 \n \nsets the Retail Threshold, the more retail customers will have a solid, ongoing basis for making \nfuture investments and expanding. This issue is addressed further in Section V.A, infra. \n#7. Federal and state economic development goals. The Administration and various PJM \ngovernors’ offices are pursuing economic development agendas that emphasize the importance of \nmaking things in the United States.85 Most of the Industrials’ members do just that, producing \ngoods that are sold domestically and worldwide. They and similarly-situated businesses employ \nmillions of Americans as part of the United States’ industrial backbone. In the case of Amtrak, \nlosing the ability to net transmission charges with the contracted behind-the-meter generation will \nsignificantly increase Amtrak’s operating costs and seriously affect the Northeast Corridor. As \nexplained previously, Amtrak relies on retail BTMG, generated at 25 Hz, to provide energy supply \nand black-start capability to support the south end of Amtrak’s Northeast Corridor traction power. \nGiven Amtrak’s need for redundancy to support the reliability imperatives of Amtrak’s operations, \nAmtrak’s retail BTMG exceeds the 50 MW Retail Threshold proposed by PJM. Increasing the \nRetail Threshold to 200 MW would safely accommodate Amtrak’s contractual arrangement \nwithout relying solely on grandfathered arrangements.    \nThese retail customers watch this proceeding with grave concern, seeing a regulatory \nregime that appears to be focused on the highly-capitalized data center industry, unsure if the \nFERC and other regulatory bodies will recognize the “middle” area that many industrial and \ninstitutional customers and other significant energy users that have invested in retail BTMG \noccupy. \n \n85 See, e.g., The White House, Made in America Agenda Delivers Manufacturing Boom (Aug. 13, 2025), available at \nhttps://www.whitehouse.gov/articles/2025/08/made-in-america-agenda-delivers-manufacturing-boom/."},{"page":34,"startToken":11175,"endToken":11557,"text":"34 \n \nC. \nThe FERC should direct PJM to remove the “all-or-nothing” approach to the \nRetail Threshold; netting should be based on the amount of load, not the \namount of generation. (Protest Issue #3) \nThe Order directs PJM to “propose a new MW threshold for the amount of load at a \nparticular electrical location that Network Customers may net by using BTMG.”86 However, \ninstead of proposing a load amount for netting, PJM proposed a generation threshold. Further, \npursuant to PJM’s “all-or-nothing” design, if generation is sized above the Retail Threshold, the \nelectrical location is entirely disqualified from netting. Both of these design choices are contrary \nto a plain reading of the Order, create an unfortunate economic “cliff” effect, and mark an \nunjustified shift from the current definition of BTMG. \nPJM’s Compliance Filing contradicts the Order’s plain language in several respects. First, \nthe plain reading of the Order does not suggest a “cliff.” In fact, the Order gives no indication that \nsome electrical locations with BTMG would qualify for this netting and not others. Paragraph 221 \nof the Order places no limiting language on which Network Customers or electrical locations may \n“reduce their transmission charges in a transparent, not unduly discriminatory fashion.” If the \nCommission intended to limit netting to certain electrical locations (i.e., those with an on-site \ngeneration nameplate rating less than the Retail Threshold), it presumably would have indicated \nsuch. Instead, it appears that the Commission’s intent was for retail netting to continue at all \nelectrical locations but only up to the Retail Threshold that the Commission ultimately approves.87  \nSecond, PJM’s choice to base the Retail Threshold on a generator’s nameplate contradicts \nthe FERC’s direction to “maintain the current BTMG rules for customers that fall below a new \n \n86 Order at P 221 (emphasis added). See also Order at P 179 (“we direct PJM to maintain the current BTMG rules for \ncustomers that fall below a new MW materiality threshold for the amount of load at a particular electrical location that \nNetwork Customers may net using BTMG”). \n87 For example, if the Retail Threshold is 50 MW and the load is 300 MW at applicable hours, the 300 MW could be \nreduced to 250 MW as long as at least 50 MW of generation was active during those hours."},{"page":35,"startToken":11557,"endToken":11863,"text":"35 \n \nMW materiality threshold for the amount of load at a particular electrical location that Network \nCustomers may net using BTMG.”88 PJM justifies a threshold based on the size of the generator \nin part because “BTMG is defined as a generation unit, rather than a load.”89 However, the issue \nbeing addressed by the Commission is “the amount of load … that Network customers may net.”90 \nFurther, PJM states that “a threshold based on the size of the generator provides a clear and bright \nline for what can continue qualifying as retail BTMG.”91 However, a plain reading of the Order \nseeks only one “bright line”—the amount of load that may be netted at an electrical location. In \nhis affidavit, Mr. Dauphinais provides additional reasons why a generation-based Retail Threshold \nis inappropriate.92  \nThird, despite the Commission’s direction to “maintain the current BTMG rules for \ncustomers that fall below” the Retail Threshold, PJM’s proposal on this issue works against, rather \nthan maintains, current BTMG rules. As explained by Mr. Dauphinais, “nameplate capacity does \nnot necessarily indicate the actual electrical capability of behind-the-meter generation.”93 Mr. \nDauphinais provides the example of generation served from a common steam system, where the \ngeneration output is limited by the steam system’s capability—meaning a retail customer could be \ndisqualified by an above-threshold nameplate rating on their generation, even though that \ngeneration could never produce that much power. In addition to PJM’s mistaken interpretation of \nthe Order, if the FERC adopts PJM’s interpretation, it will result in a punitive “cliff effect” that \nwould serve as a disincentive to additional investment for retail customers (e.g., manufacturers, \n \n88 Order at P 179 (emphasis added). \n89 Compliance Filing at 14. \n90 Order at P 179. \n91 Compliance Filing at 14. \n92 Dauphinais Affidavit at PP 55-60. \n93 Id. at P 56."},{"page":36,"startToken":11863,"endToken":12201,"text":"36 \n \nhospitals, and universities) that may want to develop additional generation. Just as taxes increase \nmarginally when a taxpayer advances into a new tax bracket, rather than eliminating the benefits \nof the lower tax bracket, PJM’s rules should not impose a binary regime where a facility 1 MW \nabove the Retail Threshold loses BTMG netting status altogether, while a facility 1 MW below the \nRetail Threshold preserves it fully. Such cliffs distort investment decisions, encourage inefficient \ndownsizing of generation projects, and produce outcomes disconnected from actual system needs, \nresulting in harm to resource adequacy, as explained previously, as well as to economic \ndevelopment opportunities in the PJM region, particularly those connected to the lower tiers of \nlarge load (that is, under 200 MW). \nOn a related note, the fact that a retail customer engages in sales of excess energy must not \ndisqualify the customer from netting its retail BTMG. Wholesale sales into the PJM market are, \nby definition, currently not part of BTMG. The current BTMG definition clearly states that BTMG \ndoes not include generation output that uses the Transmission System.94 There are a variety of \nreasons retail customers may make wholesale sales of excess energy. Many QFs were forced to \nsell excess energy when mandatory must-purchase requirements were terminated.95 As a result, \nthese retail customers with on-site generation were essentially forced to sell into the market (make \nwholesale sales). As explained by Mr. Dauphinais, other cogeneration QFs are sized to the steam \nor heat needs on-site, which means there may be excess power.96 It would be unreasonable to \ndisqualify these units entirely based on a portion of the output going into the wholesale market. \nThey are still retail customers and should operate under a retail construct. These customers’ (and \nother similarly situated customers’) output should not be deemed as putting the entire unit into the \n \n94 Compliance Filing at 5-6 (citing Tariff, Part I, Definitions A-B (“Behind The Meter Generation”)). \n95 See Dauphinais Affidavit at PP 15, 48. \n96 See id. at P 15."},{"page":37,"startToken":12201,"endToken":12478,"text":"37 \n \nCo-Located Load category, which triggers a cascade of regulatory burdens and financial \nchallenges. Likewise, netting of load should be available to retail customers up to the Retail \nThreshold, regardless of the size of the generation or QF certification status. Similarly, excess \ngeneration should still be eligible to sell without disrupting the core BTMG status of offsetting \ngeneration/up to the selected Retail Threshold.  \nV. \nCOMMENTS \nThe Industrials/Amtrak believe that PJM’s proposals on back-up generation and \ngrandfathering are reasonable interpretations and implementation of the Order. The \nIndustrials/Amtrak offer brief comments on these proposals. \nA. \nGrandfathering rules and confirmation of grandfathered status should be \nclear and unambiguous, including existing agreements with renewal terms. \n(Comments Issue #1) \n \nIn the context of this compliance phase of the proceeding, the Industrials/Amtrak support \nPJM’s current approach of grandfathering existing retail BTMG based on existing agreements with \ntheir local utility or other agreements. PJM’s approach provides reasonable latitude, recognizing \nthe diverse and complex array of BTMG configurations and structures that exist, as well as the \ndiverse and complex array of contracts and arrangements used to effectuate and continue these \noperations. \nPart of the complexity of retail BTMG is that it has been relied upon by industry and \ninstitutions who have explored innovative and varied means of building assets that help power \ntheir operations and reduce their costs. Many larger retail BTMG customers have operated existing \nfacilities for years, even decades. These sites often have utility contracts that are not long-term; \nthe sites are mature, so long-term agreements have frequently given way to agreements that renew \nperiodically or year by year. Many do not have long-term fuel or maintenance agreements. Yet,"},{"page":38,"startToken":12478,"endToken":12796,"text":"38 \n \nthe existence of those contracts (past or present) has shaped the contours of how these units \noperate. These customers have relied on the BTMG rules and should be able to continue as long \nas their current contract is in force, including any renewal terms. Such grandfathering should also \naccommodate any amendments to such agreements. \nFor example, one example (changed only slightly for confidentiality) of a manufacturer \nrepresented by one of the Industrial organizations shows the following features: several dozen \ncombined heat and power (“CHP”) assets, which are primarily designed to meet the thermal load; \nthermal energy required for industrial processes; a significant decrease in electricity generation \noccurs, thermal generation also declines, resulting in a simultaneous load shedding event \ndecreasing the need for any external electricity purchases; there are physical limitations on \namounts of power that can be drawn from the grid; due to the sizing of generation to meet thermal \nneeds, excess power is produced under an industrial purchased power contract; standby service \ncontract is in force, with decades of demand history informing the contract; a purchased power \ncontract has been in effect for decades, as well, and is renewed on a year-to-year basis; the CHP \nassets are fueled by a mixture of coal and natural gas, for which multi-year fuel supply contracts \nand firm natural gas pipeline capacity reservation contracts are maintained; the facility falls \nbetween 80 MW and 200 MW in production capability. \nThe above example is an organization that has operated in a stable, consistent manner over \ndecades. The on-site generation may not have QF status, and if the FERC chooses a Retail \nThreshold less than 200 MW, it may not qualify for retail BTMG netting. Consequently, if the \norganization cannot rely on clear, stable grandfathering rules to know it can continue to operate in \na manner that is consistent with how it has operated for decades, the effects will be profound and \ndevastating."},{"page":39,"startToken":12796,"endToken":13098,"text":"39 \n \nAs another example, Amtrak, a retail customer, has a contractual arrangement for retail \nbehind-the-meter generation to support its Northeast Corridor operations. As a legacy of the \nbuildout of the Northeast Corridor, Amtrak requires service at 25 Hz, which it receives, at least for \nsome of its requirements, through a contractual arrangement with a third-party generator that is \nneither a small power production QF nor a cogeneration QF. This arrangement provides the only \nblack-start capability for Amtrak’s south end of its Northeast Corridor traction power system if the \n60 Hz power grid goes out of service. This retail behind-the-meter generation exceeds the 50 MW \nRetail Threshold that PJM has proposed. While Amtrak expects that its existing arrangement \nwould be grandfathered under PJM’s compliance filing approach, there is tremendous risk and \ncost to Amtrak to rely upon such grandfathered status.97 \nConsequently, the Industrials/Amtrak recommend that the grandfathering rules be clear, \nbroadly construed, and confirmable with relative ease for existing BTMG customers. All existing \nBTMG-related contracts, including those that renew year by year, must be honored to avoid \nserious, unwarranted harm to these retail customers, such as Amtrak. Amendments to a \ngrandfathered contract should not impair or affect grandfathered status. Grandfathered status of an \nelectrical location should be confirmable through a clear, straightforward process to minimize \nregulatory hurdles. In this time of rapid policy and price changes, shaken by the emergence of \nsuper-sized load driving scarcity and price volatility, all existing retail customers require a stable \nplatform for investment. Regulatory ambiguity creates additional issues and concerns, particularly \nfor retail customers, for whom the FERC-jurisdictional markets are not within their core business. \n \n \n97 Because of the risk associated with relying upon grandfathered status, Amtrak strongly supports the Retail Threshold \nbeing set at least at 200 MW, with netting accommodated below the Retail Threshold."},{"page":40,"startToken":13098,"endToken":13416,"text":"40 \n \nB. \nPJM’s exemption for back-up generation is appropriate and should be \nmaintained. (Comments Issue #2) \nPJM’s proposed BTMG tariff definition includes the following exclusion: “not including \nback-up generation at the same electrical location as the retail load that can only be used to serve \nsuch retail load during conditions that may threaten the integrity or reliability of the PJM Region \nor the regional power system.” If the Commission agrees with PJM’s proposal that the Retail \nThreshold be set based on the amount of behind-the-meter generation (not load), this emergency \nback-up exclusion is appropriate and reasonable for several reasons. \nFirst, if PJM’s proposed “all-or-nothing” approach to the Retail Threshold is maintained, \nlack of the back-up exclusion would force retail customers to choose between (a) abandoning back-\nup generation on-site to support their main generation, and (b) going above the Retail Threshold98 \nThe first choice puts more reliance on the grid, but the second choice could have profound financial \nconsequences for some customers. Emergency generation is often sized similarly to other on-site \ngeneration to be able to function as a full back-up power source; consequently, without the \nexemption, this would effectively cut the Retail Threshold in half for any customers who want to \ninstall emergency generation. \nSecond, the value of incentivizing back-up generation extends beyond reducing customers’ \nown use of the grid in case their own primary generation goes down. It also potentially provides \nadditional resource adequacy strength to be prepared for emergencies. For example, DOE, in its \nrecent Order during Winter Storm Fern, stated that it may issue an order directing the operation of \nprivate, behind-the-meter generation to get through the storm.99 PJM reiterated this point in its \n \n98 The Industrials/Amtrak note that removal of the “all-or-nothing” “cliff effect” in PJM’s proposal would lessen or \neliminate the concern about emergency back-up generation.  \n99 U.S. Department of Energy, Emergency Order No. 202-26-06 (issued Jan. 26, 2026)."},{"page":41,"startToken":13416,"endToken":13596,"text":"41 \n \nCompliance Filing, noting that “during the recent Winter Storm Fern, [DOE] issued an Order \napplicable in the PJM Region pursuant to Section 202(c) of the Federal Power Act that directed \n“PJM, in collaboration with its Transmission Owners . . . to direct backup generation resources . . \n. to operate as a last resort before declaring an Energy Emergency Alert (EEA) 3 (i.e., before firm \nload interruption) or during an EEA 3.”100 PJM argues that such generation may serve as a \n“reliability tool.” Considering the tariff language limiting the back-up exclusion to generation “that \ncan only be used to serve such retail load during conditions that may threaten the integrity or \nreliability of the PJM Region or the regional power system,” this is a narrow exception, which the \nIndustrials/Amtrak interpret to be rarely-used generation (such as diesel) that could keep the \nindustrial or institutional load (that does not normally draw from the grid due to the regular on-site \ngeneration) from suddenly needing grid power, creating localized reliability concerns; it could also \noperate during broader grid emergencies. \n \n \n \n   \n \n \n \n \n \n100 Compliance Filing at 13."},{"page":42,"startToken":13596,"endToken":13704,"text":"42 \n \nVI. \nCONCLUSION & REQUEST FOR RELIEF \nThe Industrials/Amtrak respectfully request that the Commission reject PJM’s Compliance \nFiling, consistent with this Protest, and direct PJM to file a new compliance filing, consistent with \nthe above Protest and Comments. \n \n \n \n \n \nRespectfully submitted, \n \nBy: \n/s/ Susan E. Bruce \n \n \n \nSusan E. Bruce \nKenneth R. Stark \nMatthew L. Garber \nMcNees Wallace & Nurick LLC  \n100 Pine Street \nHarrisburg, PA  17101 \nTel:  717-232-8000 \nE-mail: sbruce@mcneeslaw.com \nE-mail: kstark@mcneeslaw.com \nE-mail: mgarber@mcneeslaw.com \n \nCounsel to the PJM Industrial Customer Coalition, \nthe Industrial Energy Consumers of America, the \nAmerican Forest and Paper Association, and the \nNational Railroad Passenger Corporation (Amtrak) \n \nDated:  March 16, 2026"},{"page":43,"startToken":13704,"endToken":13765,"text":"CERTIFICATE OF SERVICE \n \nI hereby certify that I have this day served via electronic transmission the foregoing upon \neach person designated on the official service list compiled by the Secretary in this proceeding.  \nDated this 16th day of March, 2026.  \n \n \n     /s/ Matthew L. Garber \n \nMatthew L. Garber \n100 Pine Street \nHarrisburg, PA  17101 \nTel:  717-232-8000 \nFax:  717-237-5433 \nE-mail: mgarber@mcneeslaw.com"},{"page":44,"startToken":13765,"endToken":13768,"text":"EXHIBIT NO. IA-1"},{"page":45,"startToken":13768,"endToken":13794,"text":"Exhibit No. IA-1 \n \n \n \n \n \n \n \nUNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \n \n \nPJM Interconnection, L.L.C. \n \n  \n \n) \n \n \n \nDocket No. ER26-1479-000 \n \n \n \n \n \nAFFIDAVIT OF JAMES R. DAUPHINAIS"},{"page":46,"startToken":13794,"endToken":13948,"text":"Exhibit No. IA-1 \n \n \n \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \n \n \nPJM Interconnection, L.L.C. \n \n \n) \n \n \nDocket No. ER26-1479-000 \n \n \n \n \nAFFIDAVIT OF JAMES R. DAUPHINAIS \n \nTable of Contents \n \n \nI. \nINTRODUCTION .................................................................................................... 1 \n \n \nAffiant Description ................................................................................................... 1 \n \nII. \nBACKGROUND ON THE USE OF COGENERATION FACILITIES BY \nTRADITIONAL LARGE INDUSTRIAL, INSTITUTIONAL AND \nCOMMERCIAL RETAIL CUSTOMERS ............................................................... 5 \n \n \nWhat are Cogeneration Facilities? ............................................................................ 5 \n \n \nCogeneration Efficiency ........................................................................................... 7 \n \n \nThe Integration of Cogeneration with Commercial, Industrial, and Institutional \nProcesses and the Critical Need for Reliable Backup and Maintenance Power \nat Just and Reasonable Rates .................................................................................... 8 \n \nIII. \nCOMMERCIAL, INDUSTRIAL AND INSTITUTIONAL CUSTOMERS \nUSING COGENERATION ARE NOT THE SAME AS VERY LARGE \nCOMPUTATIONAL LOADS CO-LOCATED BEHIND THE METER \nOF GENERATION FACILITIES .......................................................................... 12 \n \nIV. \nFOR TRADITIONAL LARGE LOADS SERVED BY COGENERATION \nFACILITIES, PJM’S CURRENT RETAIL BEHIND THE METER \nGENERATION PROVISIONS ARE CONSISTENT WITH COST \nCAUSATION AND FERC’S OWN BACKUP AND MAINTENANCE \nPOWER RULES FOR QUALIFYING FACILITIES ............................................ 13 \n \n \nRetail BTMG Netting for Transmission ................................................................. 13 \n \n \nRetail BTMG Netting for Capacity ......................................................................... 17"},{"page":47,"startToken":13948,"endToken":14079,"text":"Exhibit No. IA-1 \n \n \n \nV. \nFIRM CONTRACT DEMAND TRANSMISSION SERVICE AND \nNON-FIRM CONTRACT DEMAND TRANSMISSION SERVICE \nARE UNABLE TO PROVIDE JUST AND REASONABLE \nBACKUP AND MAINTENANCE SERVICE TO QUALIFYING \nCOGENERATION FACILITIES ........................................................................... 19 \n \nVI. \nPJM’S PROPOSAL WITH RESPECT TO ALLOWING EXISTING \nCERTIFIED QUALIFYING FACILITIES AS OF DECEMBER 18, 2025 \nTO CONTINUE TO USE RETAIL BTMG NETTING FOR NITS \nAND CAPACITY REQUIREMENTS FALLS SHORT OF BEING \nJUST AND REASONABLE .................................................................................. 23 \n \nVII. \nPJM’S PROPOSED 50 MW AND SMALLER LIMITATION FOR \nNON-QUALIFYING FACILITIES TO USE RETAIL BEHIND THE METER \nGENERATION NETTING ALSO FALLS SHORT OF BEING JUST AND \nREASONABLE ...................................................................................................... 26 \n \n \nThe Proposed 50 MW Limit is Inappropriately Applied to Cumulative \nNameplate Capacity Rather than the Amount of Retail Load that can be Netted .. 29 \n \n \nPJM’s Proposed 50 MW Limit is Too Low ............................................................ 32 \n \nVIII. \nCONCLUSION ....................................................................................................... 36"},{"page":48,"startToken":14079,"endToken":14160,"text":"Exhibit No. IA-1 \n \n \n \nUNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \n \n \nPJM Interconnection, L.L.C. \n \n) \n \nDocket No. ER26-1479-000 \n \n \n \n \nAFFIDAVIT OF JAMES R. DAUPHINAIS \n \nList of Attachments \n \n1 Qualifications of James R. Dauphinais \n2 \n \n \nAnalysis of MW Size of Consumers Energy Company Data Center Load \nAddition Inquiries \n \n3 \n \nMichigan Public Service Commission Case No. U-21859, Consumers Energy \nCompany Data Request Response U21859-DCC-CE-0045  \n4 \n \nIllinois Commerce Commission Docket No. 25-0677, Commonwealth Edison \nCompany Response to Data Request NRG-ComEd 1.02"},{"page":49,"startToken":14160,"endToken":14308,"text":"Exhibit No. IA-1 \n \n \n \nUNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \n \n \nPJM Interconnection, L.L.C. \n \n) \n \nDocket No. ER26-1479-000 \n \n \n \n \nAFFIDAVIT OF JAMES R. DAUPHINAIS \n \nGlossary of Abbreviations and Acronyms \n \nAF&PA \nAmerican Forest and Paper Association \nAmtrak \nNational Railroad Passenger Corporation \nBAI \nBrubaker & Associates, Inc.  \nBTMG \nBehind the Meter Generation \nCHP \nCombined Heat and Power \nComEd \nCommonwealth Edison Company \nDCPZ \nZonal Daily Load \nFERC \nFederal Energy Regulatory Commission  \nFPA \nFederal Power Act \nIECA \nIndustrial Energy Consumers of America \nICC \nIllinois Commerce Commission \nMISO \nMidcontinent Independent System Operator, Inc.  \nMPSC \nMichigan Public Service Commission \nNERC \nNorth American Electric Reliability Corporation \nNITS \nNetwork Integration Transmission Service \nNU \nNortheast Utilities Service Company, now Eversource \nPJM \nPJM Interconnection, L.L.C.  \nPJMICC \nPRA \nPJM Industrial Customer Coalition \nPlanning Resource Auction \nPURPA \nPublic Utility Regulatory Policies Act of 1978 \nRAA \nReliability Assurance Agreement  \nRAR \nResource Adequacy Requirements \nSMR \nSmall Modular Reactors"},{"page":50,"startToken":14308,"endToken":14527,"text":"Exhibit No. IA-1 \nPage 1 of 38 \n \n \nUNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \n \n \nPJM Interconnection, L.L.C. \n \n) \n \nDocket No. ER26-1479-000 \n \n \n \n \n \nAFFIDAVIT OF JAMES R. DAUPHINAIS \n \nI. \nINTRODUCTION \n \nTHE UNDERSIGNED, James R. Dauphinais, of Chesterfield, Missouri having been duly \nsworn on oath before a Notary Public, states the following: \n \nAffiant Description \n \n1. \nI am a Managing Principal of Brubaker & Associates, Inc. (“BAI”), an energy, \neconomic and regulatory consulting firm.  My business address is 16690 Swingley Ridge Road, \nSuite 140, Chesterfield, Missouri 63017.  I have worked in the electric utility industry for over \n40 years, and during my twenty-eight (28) years of my employment by BAI I have been engaged \nwith respect to resource planning, transmission planning, wholesale power market structure, \nmarket power, transmission access, transmission line routing, fuel cost, power procurement and \nrate issues throughout the United States and portions of Canada.  For at least twenty (20) of my \nover twenty-eight (28) years with BAI, I have monitored developments in the PJM \nInterconnection, L.L.C. (“PJM”) stakeholder process on behalf of a group of large end-use \ncustomers in Illinois.  This work has included, but not been limited to, providing \nrecommendations with respect to various market proposals made by PJM either in the \nstakeholder process or in filings with the Federal Energy Regulatory Commission (“FERC”)."},{"page":51,"startToken":14527,"endToken":14840,"text":"Exhibit No. IA-1 \nPage 2 of 38 \n \n \n \nI have also assisted end-use customers with establishing themselves as a load-serving PJM \nMember and understanding their obligations as a load-serving PJM Member.  For at least \ntwenty-six (26) years, I have also participated in the Midcontinent Independent System Operator, \nInc. (“MISO”) stakeholder process on behalf of several large end-use customer groups.1  This \nhas included, but not been limited to, providing extensive feedback to MISO and other MISO \nstakeholders during the design of MISO’s day-ahead and real-time energy markets and MISO’s \nResource Adequacy Requirements (“RAR”) construct including the MISO Planning Resource \nAuction (“PRA”).  It has also included extensive involvement with respect to treatment of Load \nModifying Resources and Non-Load Modifying Resource behind the meter generation within the \nMISO market.  During my time with BAI, I have also had over twenty-four (24) years of \nexperience with issues related to the purchase and sale of electric power from or to Public Utility \nRegulatory Policies Act of 1978 (“PURPA”) Qualifying Facilities that are large industrial or \ninstitutional customer cogeneration facilities.  This has included providing testimony on the \nutility purchase of excess electric power from such facilities at avoided cost, the sale of excess \nelectric power by such facilities into the wholesale market, and the sale of backup and \nmaintenance power to such facilities to serve their host load when the facilities are experiencing \noutages or derates.  Prior to my employment with BAI, I was a Senior Engineer in the \nTransmission Planning Department of the Northeast Utilities Service Company (“NU,” now \nEversource).  During my over twelve (12) years of employment with NU, I was extensively \ninvolved with transmission planning, transmission operation and open access transmission \n \n1 These groups have members who have facilities with traditional large industrial and institutional \nelectric loads located in the MISO portions of Illinois, Indiana, Iowa, Louisiana, Michigan and Texas or \nelsewhere within the MISO footprint."},{"page":52,"startToken":14840,"endToken":15197,"text":"Exhibit No. IA-1 \nPage 3 of 38 \n \n \n \nservice issues.  I have testified previously before FERC as well as many state and provincial \nregulatory commissions.  Attachment 1 to this Affidavit provides a more complete summary of \nmy background and experience. \n2. \nMy firm has been retained by the PJM Industrial Customer Coalition \n(“PJMICC”), the Industrial Energy Consumers of America (“IECA”), the American Forest and \nPaper Association (“AF&PA”) and the National Railroad Passenger Corporation (“Amtrak”) \n(collectively, “Industrials/Amtrak”) to: (i) provide background on the use of cogeneration \nfacilities by traditional large industrial, commercial and institutional retail customers, (ii) explain \nthe differences between the traditional use of cogeneration facilities by large retail customers \nversus co-location of very large computational loads2 behind the meter of very large generation \nfacilities, (iii) explain how PJM’s current retail behind the meter generation provisions are \nconsistent with cost causation for the traditional use of cogeneration facilities by large retail \ncustomers and FERC’s own longstanding rules with respect to the provision of backup and \nmaintenance power to those retail customers, (iv) explain why the new Firm Contract Demand \nService and Non-Firm Contract Demand Service options that FERC has proposed for co-location \nof large loads behind the meter of generation facilities do not reasonably provide for the backup \nand maintenance service required by traditional use of cogeneration facilities by large retail \ncustomers, (v) explain why PJM’s proposal with respect to the treatment of Qualifying Facilities \n \n2 For purposes of this affidavit, when I use the term “computational load”, I am referring to crypto \ncurrency, data center and other large computer system electric loads including the electric load of the \nauxiliary systems necessary to operate the foregoing.  The North American Electric Reliability Corporation \n(“NERC”) Large Load Task Force has focused its recent reliability impact review on computational loads, \nrecently observing that “[t]he penetration of large loads on the [Bulk Power System] is growing, especially \ncomputational loads.” Assessment of Gaps in Existing Practices, Requirements, and Reliability Standards \nfor Emerging Large Loads: NERC Large Loads Working Group White Paper (March 2026), at p. 46, \navailable at https://www.nerc.com/globalassets/our-work/guidelines/reliability/white-paper---assessment-\nof-gaps.pdf."},{"page":53,"startToken":15197,"endToken":15546,"text":"Exhibit No. IA-1 \nPage 4 of 38 \n \n \n \nin its compliance filing in this proceeding falls short of being just and reasonable with respect to \nthe provision of backup and maintenance power to retail customers using cogeneration facilities, \nand (vi) explain why PJM’s proposed 50 MW and smaller limitation for non-Qualifying Facility \nretail behind the meter generation netting falls short of being just and reasonable. \n3. \nAttachments 1 through 4 to this Affidavit were either prepared or obtained under \nmy direction and control.  They are part of my Affidavit. \n4. \nI conclude the following in this affidavit: \n Very large computational loads co-located behind the meter of generation \nfacilities are not similarly situated to traditional large commercial, \nindustrial, and institutional loads using Cogeneration Facilities located \nbehind their meter, as very large computational loads generally are not \nhighly thermally integrated with co-located generation facilities. \n \n For traditional large loads served by Cogeneration Facilities, PJM’s \ncurrent retail behind-the-meter generation netting provisions for NITS \ncharges and capacity requirements are consistent with cost causation \nprinciples and FERC’s own backup and maintenance power rules for \nQualifying Facilities, as they rely on factual data regarding each \nQualifying Facility’s historical performance rather than assumptions about \nwhen outages will occur and whether they will occur simultaneously. \n \n Firm Contract Demand Transmission Service and Non-Firm Contract \nDemand Transmission Service are not capable – either alone or in tandem \n– of providing reliable backup and maintenance power to traditional large \nretail customers that utilize Qualifying Cogeneration Facilities at rates \nconsistent with cost causation principles and FERC’s rules for providing \nbackup and maintenance service to Qualifying Facilities. \n \n PJM’s proposal to limit legacy retail behind-the-meter generation \ntreatment for Qualifying Facilities to those certified or self-certified as of \nDecember 18, 2025 falls short of being just and reasonable, and should be \nmodified to cover all Qualifying Facilities regardless of the date they \nentered service or the date of their certification or self-certification. \n \n PJM’s proposed 50 MW cumulative nameplate capacity limit for \ncontinued retail behind-the-meter generation netting for non-Qualifying \nFacility generation is not just and reasonable because the limit is \ninappropriately applied to cumulative nameplate capacity rather than to"},{"page":54,"startToken":15546,"endToken":15841,"text":"Exhibit No. IA-1 \nPage 5 of 38 \n \n \n \nthe amount of retail load that can be netted, and 50 MW is too low given \nthat the large computational load additions driving the Co-Located Loads \nissue are overwhelmingly 300 MW or larger in size; any limit should \ninitially be set no lower than 200 MW (if not closer to 300 MW). \n \n \nII. \nBACKGROUND ON THE USE OF COGENERATION FACILITIES BY \nTRADITIONAL LARGE INDUSTRIAL, INSTITUTIONAL AND \nCOMMERCIAL RETAIL CUSTOMERS \n  \nWhat are Cogeneration Facilities? \n \n5. \nFERC defines a Cogeneration Facility to be “equipment used to produce electric \nenergy and forms of useful thermal energy (such as heat or steam), used for industrial, \ncommercial, heating, or cooling purposes, through the sequential use of energy”.3  Given that on \na combined basis these facilities provide both thermal and electric energy, cogeneration facilities \nare also commonly referred to as Combined Heat and Power (“CHP”) facilities. \n6. \nThere are two types of Cogeneration Facilities – Topping-Cycle Cogeneration \nFacilities and Bottoming-Cycle Cogeneration Facilities. \n7. \nFERC defines a Topping-Cycle Cogeneration Facility as “a cogeneration facility \nin which the energy input to the facility is first used to produce useful power output, and at least \nsome of the reject heat from the power production process is then used to provide useful thermal \nenergy”.4  A common example of a Topping-Cycle Cogeneration Facility would be a facility \nwith combustion turbine generation fired by natural gas, combustible waste gases, or some \ncombination of the two, that produces electricity and provides steam for heating, cooling, and/or \nindustrial processes via heat recovery steam generators that collect waste heat from the \ncombustion turbine generator.  Another example would be a facility with boilers fired by fossil \n \n3 18 C.F.R. § 292.202(c). \n4 18 C.F.R. § 292.202(d)."},{"page":55,"startToken":15841,"endToken":16176,"text":"Exhibit No. IA-1 \nPage 6 of 38 \n \n \n \nfuel, combustible waste gases, other forms of combustible waste material, or some combination \nof the foregoing producing high pressure steam that is run through a steam turbine to produce \nelectricity with the lower pressure steam exiting the steam turbine then being used for heating, \ncooling, or industrial processes. 5 \n8. \nFERC defines a Bottoming-Cycle Cogeneration Facility as “a cogeneration \nfacility in which the energy input to the system is first applied to a useful thermal energy \napplication or process, and at least some of the reject heat emerging from the application or \nprocess is then used for power production”.6  A common example of a Bottoming-Cycle \nCogeneration Facility would be the use of a heat recovery steam generator to recover heat from \nan industrial process to produce steam that is then used to generate electricity via a steam \nturbine. \n9. \nCogeneration Facilities can include some amount of Supplementary Firing.  \nFERC defines Supplementary Firing as “an energy input to the cogeneration facility used only in \nthe thermal process of a topping-cycle cogeneration facility, or only in the electric generating \nprocess of a bottoming-cycle cogeneration facility”.7  An example of Supplementary Firing for a \nTopping-Cycle Cogeneration Facility would be the use of duct burners within the exhaust stream \nof a combustion turbine to increase the amount of steam that can be produced in the heat \nrecovery steam generator associated with the combustion turbine. An example of Supplementary \nFiring for a Bottoming-Cycle Cogeneration Facility would be the use of duct burners to stabilize \n \n5 It should be noted the use of Nuclear Small Modular Reactors (“SMR”) as the thermal source for \nTopping-Cycle Cogeneration Facilities is currently being actively explored in the industry and in at least \none case in the ERCOT portion of Texas is being actively pursued by X-Energy Reactor Company, LLC at \na Dow site.  See https://x-energy.com/media/news-releases/dow-and-x-energy-submit-construction-permit-\napplication-to-the-us-nuclear-regulatory-commission-for-proposed-advanced-nuclear-project-in-texas.  \n6 18 C.F.R. § 292.202(e). \n7 18 C.F.R. § 292.202(f)."},{"page":56,"startToken":16176,"endToken":16462,"text":"Exhibit No. IA-1 \nPage 7 of 38 \n \n \n \nthe steam produced from heat recovery from a waste heat source prior to that steam being used to \ngenerate electricity via a steam turbine. \nCogeneration Efficiency \n10. \nAs I have noted, FERC’s definition of Cogeneration Facility requires the \n“sequential use of energy”.8  Specifically, for a Topping-Cycle Cogeneration Facility, FERC \nrequires “the use of reject heat from a power production process in sufficient amounts in a \nthermal application or process to conform to the requirements of the operating standard”,9 where \nthe “operating standard” is “the useful thermal energy output of the facility must be no less than \n5 percent of the total energy output during the 12-month period beginning with the date the \nfacility first produces electric energy, and any calendar year subsequent to the year in which the \nfacility first produces electric energy.”10  For a Bottoming-Cycle Cogeneration Facility, FERC \nrequires “the use of reject heat from a thermal application or process, at least some of which is \nthen used for power production”. \n11. \nCogeneration Facilities, which, as I have noted, are also commonly referred to as \nCHP systems, are typically highly efficient because they capture heat that would otherwise be \nwasted and avoid electrical losses by generating electricity at the location where it will largely, if \nnot entirely, be consumed.  Specifically, Cogeneration Facilities can achieve efficiencies in \nexcess of 80%, by using waste heat and avoiding electrical losses, compared to the efficiency of \napproximately 50% for conventional electricity generation with a steam boiler.11 \n \n8 18 CFR § 292.202(c). \n9 18 CFR § 292.202(s)(1). \n10 18 CFR § 292.205(a)(1). \n11 https://www.epa.gov/chp/what-chp (last accessed 3/8/2026)."},{"page":57,"startToken":16462,"endToken":16762,"text":"Exhibit No. IA-1 \nPage 8 of 38 \n \n \n \n12. \nIn addition, pursuant to the Federal Power Act (“FPA”),12 FERC has a rule that \ndictates the requirements (including requirements respecting minimum size, fuel use and fuel \nefficiency) for a Cogeneration Facility to be a Qualifying Cogeneration Facility pursuant to \nPURPA.  Specifically, to be a Qualifying Cogeneration Facility, a Cogeneration Facility must \nmeet any applicable standards and criteria specified in 18 C.F.R. §§ 292.205(a), (b) and (d) and, \nunless exempted, has filed with the Commission a notice of self-certification, or has filed with \nthe Commission an application for Commission certification, that has been granted.13  Section \n292.205(a) is the operating and efficiency standard for Topping-Cycle Cogeneration Facilities.14  \nSection 292.205(b) is the efficiency standard for Bottoming-Cycle Cogeneration Facilities.15  \nSection 292.205(d) applies certain additional requirements to Cogeneration Facilities that do not \nmeet certain grandfathering requirements.16 \nThe Integration of Cogeneration with Commercial, Industrial, and Institutional Processes \nand the Critical Need for Reliable Backup and Maintenance Power at Just and Reasonable \nRates  \n \n13. \nBecause of the “sequential use of energy” requirement for Cogeneration Facilities \nthat I have discussed, Cogeneration Facilities are typically highly integrated with the industrial \nprocesses, commercial processes, heating processes and/or cooling processes of their host retail \ncustomer.  This has four major implications. \n14. \nFirst, there is a need for very high availability from the Cogeneration Facility to \nmeet the host retail customer’s thermal energy needs in order to assure the retail customer can \noperate its commercial or industrial processes that require thermal energy or to assure the retail \n \n12 Section 3(18)(A) of the FPA. \n13 18 CFR § 292.203(b). \n14 18 CFR § 292.205(a). \n15 18 CFR § 292.205(b). \n16 18 CFR § 292.205(d)."},{"page":58,"startToken":16762,"endToken":17102,"text":"Exhibit No. IA-1 \nPage 9 of 38 \n \n \n \ncustomer can operate its commercial or institutional cooling and heating systems.  This has the \nside effect of the Cogeneration Facility operating at a high electrical capacity factor, either due to \nthe need to produce the necessary thermal energy at a Topping-Cycle Cogeneration Facility or \ndue to the abundance of waste (i.e., reject) heat from the need to run the retail customer’s \nprimary thermal process at a Bottoming-Cycle Cogeneration Facility. \n15. \nSecond, the electrical output of the Cogeneration Facility can be much less than or \nmuch greater than the electrical load of the host retail customer.  This is because the thermal \nenergy needs of the retail customer typically dictate how much electric power must be produced \nby the Cogeneration Facility.  For example, if an industrial retail customer has a very high steam \nneed for its processes relative to its electrical needs, the Cogeneration Facility serving that \ncustomer will likely have to produce electric power well in excess of that retail customer’s needs \nfor its electrical load.  This requires there to be a reasonable outlet available to sell that excess \nelectric power at utility-avoided cost or at just and reasonable prices in the wholesale market.  In \ncontrast, if an industrial retail customer has a very limited steam need for its processes relative to \nits electrical needs, the Cogeneration Facility serving that customer will likely produce electric \npower well below the level that the retail customer needs for its electrical load.  This requires \nthat the retail customer be able to purchase supplementary (or supplemental) electric power to \ncover the deficit from either a utility under a regulated retail electric service rate or from the \nwholesale power market through a retail supplier at just and reasonable rates where retail \ncustomer choice is available. \n16. \nThird, when an outage of Cogeneration Facility occurs, significant electric load of \nthe host retail customer can be lost immediately following, or very shortly following, the outage \neither due to certain retail customer industrial or commercial processes not being able to operate"},{"page":59,"startToken":17102,"endToken":17438,"text":"Exhibit No. IA-1 \nPage 10 of 38 \n \n \n \nwithout thermal energy from the Cogeneration Facility if it is a Topping-Cycle facility or due to \na thermal process being unable to operate because of the inability to dump its waste heat to the \nCogeneration Facility if it is a Bottoming-Cycle facility. \n17. \nFinally, most relevant to this current proceeding, there is a very high need for the \nCogeneration Facility to be able to purchase reliable backup and maintenance electrical power \nfor the host retail load of the Cogeneration Facility from the local utility, or from the wholesale \nmarket via a retail supplier where there is retail customer choice, at a cost that is consistent with \ncost causation principles.  This is necessary to ensure the retail customer can, in a safe and \nenvironmentally compliant manner, continue to operate its processes at just and reasonable \nelectric power rates within the bounds of what the remaining thermal energy capability of the \nCogeneration Facility can support while it is under a full or partial outage or derate.   The ability \nto continue operation in a safe and environmentally compliant manner within the bounds of what \ncan be supported by the remaining thermal capability of the Cogeneration Facility at just and \nreasonable electric power rates is a critical requirement to ensure the retail customer can \neconomically meet the needs of its own customers and clients.  If that ability cannot be assured, \ncogeneration may fail to be a practical and/or economic solution to the retail customer’s needs, \ncausing the efficiency benefits of cogeneration to be forgone and/or the retail customer to \nbecome economically unviable. \n18. \nFERC’s rules recognize this critical need by requiring all electric utilities, except \nwhere exempted from doing so under FERC’s rules, to provide backup and maintenance power \nto Qualifying Facilities, including Qualifying Cogeneration Facilities, and placing two additional \nspecific requirements on the rates under which that backup and maintenance power is provided \nin addition to generally requiring the rates be just and reasonable and in the public interest; and"},{"page":60,"startToken":17438,"endToken":17729,"text":"Exhibit No. IA-1 \nPage 11 of 38 \n \n \n \nnot discriminate against any Qualifying Facility in comparison to rates for sales to other \ncustomers served by the electric utility.17 \n19. \nFERC defines backup power as “electric energy or capacity supplied by an \nelectric utility to replace energy ordinarily generated by a facility's own generation equipment \nduring an unscheduled outage of the facility.”18  This is electric power beyond the host retail \ncustomer’s supplemental power consumption that is required by the host retail customer when \nthe Cogeneration Facility experiences a full or partial forced outage or a forced deration.  \n20. \nFERC defines maintenance power as “electric energy or capacity supplied by an \nelectric utility during scheduled outages of the qualifying facility.”19  This is electric power \nbeyond host retail customer’s supplemental power consumption that is required by the host retail \ncustomer when the Cogeneration Facility experiences a full or partial scheduled maintenance \noutage or a scheduled maintenance derate. \n21. \nConsistent with cost causation principles, the aforementioned two additional \nspecific requirements for backup and maintenance power rates under FERC’s rules require that \nelectric utility rates for sales of back-up power or maintenance power to Qualifying Facilities, \nincluding Qualifying Cogeneration Facilities: \n(1) Shall not be based upon an assumption (unless supported by factual data) that \nforced outages or other reductions in electric output by all qualifying facilities on \nan electric utility's system will occur simultaneously, or during the system peak, \nor both; and \n \n(2) Shall take into account the extent to which scheduled outages of the qualifying \nfacilities can be usefully coordinated with scheduled outages of the utility's \nfacilities.20  \n \n17 18 CFR § 292.305. \n18 18 CFR § 292.101(b)(9). \n19 18 CFR § 292.101(b)(11). \n20 18 CFR § 292.305(c)."},{"page":61,"startToken":17729,"endToken":17991,"text":"Exhibit No. IA-1 \nPage 12 of 38 \n \n \n \nIII. \nCOMMERCIAL, INDUSTRIAL AND INSTITUTIONAL CUSTOMERS USING \nCOGENERATION ARE NOT THE SAME AS VERY LARGE \nCOMPUTATIONAL LOADS CO-LOCATED BEHIND THE METER OF \nGENERATION FACILITIES \n   \n22. \nVery large computational loads co-located behind the meter of generation \nfacilities are not similarly situated to traditional large commercial, industrial and institutional \nloads using Cogeneration Facilities located behind their meter. \n23. \nIn particular, very large computational loads by their very nature generally do not \nhave a high thermal energy need relative to the magnitude of their total electric load and do not \nproduce large amounts of waste heat relative to the magnitude of their total electrical load.  As \nsuch, they are not candidates for Cogeneration Facilities beyond potentially addressing their \ncooling and heating needs. \n24. \nThus, very large computational load processes are generally not highly thermally \nintegrated, if integrated at all, with the co-located generation facilities whose meter they may be \nlocated behind.  This is because those generation facilities will either not be Cogeneration \nFacilities or be Cogeneration Facilities of greatly limited electrical capability relative to the total \nmagnitude of the electrical load of their host retail customer. \n25. \nWithout such integration, the co-located generation facilities will not provide the \nefficiency benefits that are provided by Cogeneration Facilities in serving commercial, industrial, \nand institutional customers.  In addition, depending on the specific nature of the co-located \ngeneration facilities, the generation may be operated only intermittently rather than at the high \ncapacity factor typically required of Cogeneration Facilities to ensure their host retail customer \nthermal process needs are being reliably fully met."},{"page":62,"startToken":17991,"endToken":18325,"text":"Exhibit No. IA-1 \nPage 13 of 38 \n \n \n \n26. \nDue to these differences, from a cost causation perspective, very large \ncomputational load co-located behind the meter of generation facilities are more akin to \nwholesale customer load served by utility behind the meter generation21 than traditional large \ncommercial, industrial, and institutional load served by behind the meter Cogeneration Facilities. \n \nIV. \nFOR TRADITIONAL LARGE LOADS SERVED BY COGENERATION \nFACILITIES, PJM’S CURRENT RETAIL BEHIND THE METER \nGENERATION PROVISIONS ARE CONSISTENT WITH COST CAUSATION \nAND FERC’S OWN BACKUP AND MAINTENANCE POWER RULES FOR \nQUALIFYING FACILITIES \n  \n27. \nPJM’s longstanding provisions22 for the netting of retail customer load with \ngeneration located behind the meter of those customers are consistent with cost causation for \ntraditional large commercial, industrial, and institutional customers using Cogeneration \nFacilities, and consistent with FERC’s rules for backup and maintenance power for Qualifying \nFacilities. \nRetail BTMG Netting for Transmission \n  \n28. \nWith respect to the transmission component of backup and maintenance power, \nSection 34.2 of the PJM Open Access Transmission Tariff (“PJM Tariff”) currently excludes the \nload served by the operating behind the meter generation of a retail customer from that retail \ncustomer’s daily load for Network Integration Transmission Service (“NITS”).23  This has the \n \n21 An example of utility behind the meter generation, also known in PJM as non-retail behind the \nmeter generation, is a transmission dependent utility whose load is being served in part by the transmission \ndependent utility’s conventional generation facilities that are located on its side of the meter between it and \nits transmission provider.   \n22 I have been advised by counsel that the Commission found that these provisions may be subject \nto change in light of the Commission’s December 18, 2025 order issued in Docket No. EL25-49-000.  I am \nalso aware that PJMICC and IECA have a pending rehearing request, filed on January 20, 2026, challenging \nthe Commission’s determination with respect to findings concerning PJM’s rules for netting and retail \nbehind-the-meter generation.    \n23 PJM Tariff § 34.2 (Effective 9/17/2010 Docket No. ER10-2710-000)."},{"page":63,"startToken":18325,"endToken":18661,"text":"Exhibit No. IA-1 \nPage 14 of 38 \n \n \n \neffect of excluding the portion of a retail customer’s load served by its operating behind the \nmeter generation from its zonal daily load (“DCPZ”), which is the retail customer’s daily load \nwithin a transmission pricing zone coincident with the time of the annual peak of the zone.24   \nThis nets the output of the behind the meter generation from the retail customer’s load such that \nthe retail customer’s DCPZ is the retail customer’s demand placed on the transmission system at \nthe time of the annual peak of the transmission pricing zone the retail customer is located within, \njust like it is for retail customers who do not have behind the meter generation.  The DCPZ is \napplied to 1/365th of the annual NITS rate for the zone to determine the retail customer’s NITS \ncharges for each day.  Hence, whether a retail customer has behind the meter generation or not, \nits NITS charges are based on the demand the retail customer has historically put on the \ntransmission system at the time of the annual peak of the transmission pricing zone. \n29. \nGiven zonal transmission costs under the PJM Tariff are currently allocated to \nload on an annual coincident peak demand basis, this netting approach is consistent with cost \ncausation.  Furthermore, it is consistent with FERC’s rule for backup and maintenance power for \nQualifying Facilities25 as it does not assume that a retail customer’s behind the meter Qualifying \nFacility will be experiencing an outage at the time of the annual transmission system peak and \ninstead relies on factual data, in the form of the behind the meter Qualifying Facility’s historical \nperformance during the time of the annual peak of the transmission pricing zone, when allocating \ntransmission costs to the retail customer.  Also consistent with FERC’s backup and maintenance \nrule,26 this approach inherently avoids assuming that all Qualifying Facilities will be \n \n24 PJM Tariff § 34.1 (Effective 2/18/2020 Docket No. ER20-646-000). \n25 18 CFR § 292.305(c). \n26 Id."},{"page":64,"startToken":18661,"endToken":18978,"text":"Exhibit No. IA-1 \nPage 15 of 38 \n \n \n \nexperiencing an outage at the same time.  Again, it instead relies on factual data, in the form of \nthe historical performance of each Qualifying Facility, not an assumption with respect to whether \nthey will all be out of service at the same time. \n30. \nIt is also important to note the retail behind the meter generation netting approach \nwould work under different cost allocation methods besides the annual coincident peak demand \nmethod.  For example, if future facts and circumstances warranted a change from the annual \nzonal transmission system peak to the use of 12 monthly coincident peaks for the zone, to the top \n100 transmission system demand hours for the zone, or to the evening hours of annual \ntransmission peak day for the zone, the current retail behind the meter netting approach would \nstill properly allocate transmission costs to retail customers based on the historical demand they \nplace on the transmission system during the hours being used for the cost allocation consistent \nwith using factual data, not assumptions. \n31. \nFurthermore, given the high capacity factor typically associated with Qualifying \nCogeneration Facilities that I discussed earlier, Qualifying Facility Cogeneration would not be \nexpected to perform significantly less effectively using a larger number of hours for allocation \nrather than a smaller number of hours. \n32. \nIt is also important to understand that the transmission system is not planned \nassuming that all Cogeneration Facilities will experience an outage at the same time or will not \notherwise be running.  Based on my experience, consistent with their high capacity factor nature, \nCogeneration Facilities are generally modeled in power flow and stability analysis as electrically \nproducing power at the level necessary to support the thermal process needs of their retail host \nload, with only any stretch in electrical capability they may have through supplementary firing \npotentially being subject to economic dispatch.  Furthermore, in my experience, transmission"},{"page":65,"startToken":18978,"endToken":19261,"text":"Exhibit No. IA-1 \nPage 16 of 38 \n \n \n \nplanners do not study or examine scenarios where it is assumed large numbers of Cogeneration \nFacilities will be offline at the same time, as there is no factual basis to support such an \nassumption.  Both of these points further reinforce why transmission costs should be allocated to \nretail customers with Cogeneration Facilities on the basis of the net demand they place on the \ntransmission system during the hours used for cost allocation rather than their gross load during \nthose hours, as the sum of their individual gross loads is never under any circumstance placed on \nthe transmission system. \n33. \nAlso from my experience, while transmission planners do consider the \ncontingency loss of individual generation assets at Cogeneration Facilities, when those \ncontingencies are examined by transmission planners, those planners take into consideration how \nthe electrical load of the host retail customer will change both immediately following the \ncontingency and shortly thereafter due to the highly integrated nature of the Cogeneration \nFacility and its host retail customer.  Regardless, such contingencies at best drive local \ntransmission needs and only if the contingency is most severe generation contingency in that \nlocal area after subtracting off the electrical load that will be lost by the Cogeneration Facility’s \nhost retail customer.  As such, these contingencies are not driver of the bulk majority of \ntransmission system costs any more than the non-coincident peak demand of individual loads is a \ndriver of the bulk majority of transmission system costs.  Instead, the bulk majority transmission \nsystem costs are driven by total system demand on the transmission system, which is why \ntransmission costs are typically allocated to load using a coincident peak demand cost allocation \nmethod."},{"page":66,"startToken":19261,"endToken":19624,"text":"Exhibit No. IA-1 \nPage 17 of 38 \n \n \n \nRetail BTMG Netting for Capacity27 \n \n34. \nWith respect to the capacity component of backup and maintenance power, \nSchedule 8 of the PJM Reliability Assurance Agreement Among Load Serving Entities in the \nPJM Region (“PJM Reliability Assurance Agreement” or “RAA”) currently establishes the \nObligation Peak Load of a party to the RAA as the daily summation of the weather-adjusted \ncoincident summer peak, last preceding the Delivery Year, of the retail customers in the zone net \nof the operating behind the meter generation of those customers.28  The Daily Unforced Capacity \nObligation of the party is then determined as its Obligation Peak Load multiplied by the \napplicable Final Zonal Reliability Pricing Model  Scaling Factor and the PJM Forecast Pool \nRequirement.29 Thus, the PJM capacity requirement for retail customers is based on the weather \nadjusted demand of those customers at the time of the summer coincident peak net of the output \nof any behind the meter generation at that time of that summer coincident peak.  This nets the \noutput of the behind the meter generation from the retail customer’s load such that the retail \ncustomer’s capacity requirement is based the retail customer’s demand placed on the PJM \nmarket at the time of the summer coincident peak, just like it is for retail customers who do not \nhave behind the meter generation.  Hence, whether a retail customer has behind the meter \ngeneration or not, its PJM capacity requirement is based on the demand the retail customer has \nhistorically put on the PJM market at the time of the PJM summer coincident peak. \n \n27 While PJM did not include any proposed changes to the PJM Reliability Assurance Agreement \nin its filing in ER26-1479-000, PJM, in Footnote 2 of the first page of its transmittal letter for its February \n23, 2026 Compliance Filing, indicated it anticipates needing to make subsequent conforming clean-up \nfilings to the PJM Reliability Assurance Agreement, among other documents, in regard to the compliance \nfilings being submitted in response to the FERC’s Order to Show Cause in Docket No. EL25-49, et al.   \n28 PJM RAA, Schedule 8, Section A (Effective: 8/31/2024 – Docket No. ER24-2447-003). \n29 Id."},{"page":67,"startToken":19624,"endToken":19924,"text":"Exhibit No. IA-1 \nPage 18 of 38 \n \n \n \n \n35. \nGiven capacity requirements under the PJM RAA are currently allocated to load \non a summer coincident peak demand basis, this netting approach is consistent with cost \ncausation.  Furthermore, like with retail behind the meter generation netting for NITS charges, it \nis consistent with FERC’s rule for backup and maintenance power for Qualifying Facilities30 as it \ndoes not assume that a retail customer’s behind the meter Qualifying Facility will be \nexperiencing an outage at the time of the summer coincident peak and instead relies on factual \ndata, in the form of the behind the meter Qualifying Facility’s historical performance during the \ntime of the summer coincident peak, when allocating transmission costs to the retail customer.  \nAlso consistent with FERC’s backup and maintenance rule,31 this approach inherently avoids \nassuming that all Qualifying Facilities will be experiencing an outage at the same time.  Again, it \ninstead again relies on factual data, in the form of the historical performance of each Qualifying \nFacility, not an assumption with respect to whether they will all be out of service at the same \ntime. \n \n36. \nAlso, like with retail behind-the-meter netting for NITS charges, the current retail \nbehind-the-meter generation netting approach for capacity requirements would still work under \ndifferent cost allocation methods than the current summer coincident peak demand method.  \nSpecifically, regardless of the hours used for allocation, the current retail behind-the-meter \nnetting approach would still properly allocate capacity requirements to retail customers based on \nthe historical demand they place on the transmission system during the hours being used for the \nallocation of capacity requirements, consistent with using factual data, not assumptions.  This \nsends a strong cost signal for retail behind the meter generation to operate and fully serve the \n \n30 18 CFR § 292.305(c). \n31 Id."},{"page":68,"startToken":19924,"endToken":20187,"text":"Exhibit No. IA-1 \nPage 19 of 38 \n \n \n \nelectric load of their host retail customer during times of grid stress.  It does so because the times \nof grid stress generally align with the time periods used for cost allocation and it is at those very \ntimes that NITS billing units and capacity requirements are determined under retail behind the \nmeter generation netting.  \n \n37. \nFinally, just as with retail behind-the-meter generation netting for NITS charges, \ngiven the high capacity factor typically associated with Qualifying Cogeneration Facilities that I \ndiscussed earlier above, Qualifying Facility Cogeneration would not be expected to perform \nsignificantly less effectively using a larger number of hours allocating capacity requirements \nrather than a smaller number of hours. \n \nV. \nFIRM CONTRACT DEMAND TRANSMISSION SERVICE AND NON-FIRM \nCONTRACT DEMAND TRANSMISSION SERVICE ARE UNABLE TO \nPROVIDE JUST AND REASONABLE BACKUP AND MAINTENANCE \nSERVICE TO QUALIFYING COGENERATION FACILITIES  \n  \n38. \nFERC in its December 18, 2025 order in Docket No. EL25-49, et al., ordered \nPJM to provide two new transmission services for large loads co-located behind the meter of \ngeneration facilities (“Co-Located Loads”) – who would not be permitted to take NITS based on \ntheir net load --  as an alternative to taking NITS based on their gross load: (i) Firm Contract \nDemand Service and (ii) Non-Firm Contract Demand Service.32  While I understand from \ncounsel that these services are subject to the paper hearing in Docket No. EL25-49-000, these \nnew  services have direct bearing on the just and reasonableness of continued availability of \nretail behind-the-meter generation netting for Qualifying Facilities. \n \n32 193 FERC ¶ 61,127 (2025), at P 193."},{"page":69,"startToken":20187,"endToken":20497,"text":"Exhibit No. IA-1 \nPage 20 of 38 \n \n \n \n39. \nFirm Contract Demand Transmission Service would allow Co-Located Loads to \ntake firm transmission service up to a pre-specified MW quantity rather than having to take \nNITS based on their gross demand.33 \n40. \nNon-Firm Contract Demand Transmission Service would allow non-firm \ntransmission service when such service is not needed on a regular basis.34  It would need to be \nreserved in advance on an as-available basis during normal, non-emergency operating conditions \nand would be subject to curtailment during emergency conditions.35  There would be no charge \nfor generation capacity for the portion of the load taking the service, and PJM would have no \nobligation to obtain generation capacity for the load.36 \n41. \nWhile its specific provisions for these two transmission services are the subject of \na paper hearing in Docket No. EL25-49-000, PJM in its February 23, 2026 initial brief in that \npaper hearing (“PJM Paper Hearing Initial Brief”) in part proposed: \n The entire gross load of the Co-Located Load be covered by a \ncombination of Firm Contract Demand Transmission Service and Non-\nFirm Contract Demand Transmission Service.37 \n \n Actual deliveries of power under Non-Firm Contract Demand \nTransmission Service would need to be pre-scheduled with, and approved \nby, PJM.38 \n \n To the extent the Co-Located Load takes any Non-Firm Contract Demand \nService it must install control technologies, potentially in the form of a \nRemedial Action Scheme (“RAS”), to assure its load can be curtailed \n \n33 Id. at P 208 through P 213. \n34 Id. at P 214. \n35 Id. at P 215. \n36 Id. at P 218. \n37 Docket No. EL25-49-000, et al., Initial Brief of PJM Interconnection, LLC, February 23, 2026, \nAttachment A at Section 709.2(c).  \n38  Docket No. EL25-49-000, et al., Initial Brief of PJM Interconnection, LLC, February 23, 2026 \nat 9-10 and Attachment B at ¶ 12."},{"page":70,"startToken":20497,"endToken":20815,"text":"Exhibit No. IA-1 \nPage 21 of 38 \n \n \n \nwhen required by PJM and the Non-Firm Contract Demand Service taken \nby the Co-Located Load does not exceed the amount approved by PJM.39 \n \n Penalties and potential disqualification that would apply when a Co-\nLocated Load takes Contract Demand Service in excess of that authorized \nby PJM, fails to respond to load shedding and curtailment procedures, or \nhas a misoperation of control technologies and protection systems.40  \n \n42. \nFirm Contract Demand Transmission Service and Non-Firm Contract Demand \nTransmission Service, neither alone nor in tandem, are capable of providing reliable backup and \nmaintenance power to traditional large commercial, industrial and institutional retail customers \nthat utilize Qualifying Cogeneration Facilities at a cost that is consistent with cost causation \nprinciples and FERC’s rules for providing backup and maintenance service to Qualifying \nFacilities. \n43. \nAs I noted earlier, reliable backup and maintenance power consistent with cost \ncausation principles and FERC’s rules for backup and maintenance power is necessary for these \nretail customers to ensure they can in a safe and environmentally compliant manner continue to \noperate their processes at just and reasonable electric power rates within the bounds of what the \nremaining thermal energy capability of their Qualifying Cogeneration Facility can support while \nit is under a full or partial outage or derate.   The ability to continue operation in a safe and \nenvironmentally compliant manner within the bounds of what can be supported by the remaining \nthermal capability of the Cogeneration Facility at just and reasonable electric power rates is a \ncritical requirement to ensure the retail customer can economically meet the needs of its own \ncustomers and clients.  If that ability cannot be assured, cogeneration may fail to be a practical \n \n39  Docket No. EL25-49-000, et al., Initial Brief of PJM Interconnection, LLC, February 23, 2026, \nAttachment A at Sections 708(c) and 713.6. \n40 Id. at Sections 713.7 and 713.8."},{"page":71,"startToken":20815,"endToken":21096,"text":"Exhibit No. IA-1 \nPage 22 of 38 \n \n \n \nand/or economic solution to the retail customer’s needs, causing the efficiency benefits of \ncogeneration to be forgone and/or the retail customer to become economically unviable. \n \n44. \nWhile Contract Demand Transmission Service would provide reliable backup and \nmaintenance power, it would not provide it at rates that are consistent with cost causation or \nFERC’s rules for the rates for the provision of backup and maintenance power to Qualifying \nFacilities.  Specifically, it requires payments for the service based on the contracted amount.  As \na result, it would inherently assume, in violation of FERC’s rules for backup and maintenance \npower for Qualifying Facilities,41 that forced outages or other reductions in electric output by all \nqualifying facilities on an electric utility's system will occur simultaneously, or during the system \npeak, or both, without any factual data to support such an assumption.  As I have discussed at \nlength in this affidavit, this is not a reasonable assumption for Qualifying Cogeneration \nFacilities. \n \n45. \nNon-Firm Contract Demand Transmission Service would fall short in two \nrespects.  First, it is incapable of providing backup power for forced outages of Qualifying \nCogeneration Facilities because the actual usage Non-Firm Contract Demand Transmission \nService would have to be pre-scheduled with, and approved by, PJM in advance of its use, and \nforced outages cannot be known beforehand.  Second, the service is not reliable and risky to use \nas it is only available on an as-available basis, subject to interruption during emergencies, and \nsubject to automated interruption.  It is not a product that could be used to provide safe and \nenvironmentally compliant maintenance power to traditional commercial, industrial and \n \n41 18 CFR 292.305(c)."},{"page":72,"startToken":21096,"endToken":21380,"text":"Exhibit No. IA-1 \nPage 23 of 38 \n \n \n \ninstitutional retail customers with Qualifying Cogeneration Facilities, never mind backup power \nto them.     \n \nVI. \nPJM’S PROPOSAL WITH RESPECT TO ALLOWING EXISTING CERTIFIED \nQUALIFYING FACILITIES AS OF DECEMBER 18, 2025 TO CONTINUE TO \nUSE RETAIL BTMG NETTING FOR NITS AND CAPACITY REQUIREMENTS \nFALLS SHORT OF BEING JUST AND REASONABLE \n \n46. \nPJM in its February 23, 2026 compliance filing in this proceeding has proposed to \nallow all retail customer behind-the-meter generation that as of December 18, 2025 was a \nQualifying Facility under PURPA to continue to be able to be netted with its load for NITS \ncharges and capacity requirements after the completion of three-year transition period that would \notherwise end such netting for this generation.42  PJM indicates it made this proposal in its \ncompliance filing as an extension of the legacy treatment of this generation under PURPA.43  \nPJM also notes that given these retail behind-the-meter generation arrangements have been in \nplace and netted against Network Loads within PJM without known operational issues to date, \nPJM proposes to allow such arrangements (some of which have been in place for decades) to \nqualify for legacy treatment and continue to be eligible to net under existing behind-the-meter \ngeneration rules.44 \n47. \nPJM’s proposal for legacy retail behind-the-meter generation treatment for retail \ncustomers with behind-the-meter generation that, as of December 18, 2025, was a Qualifying \nFacility is a step toward providing a just and reasonable outcome for Qualifying Cogeneration \n \n42 PJM February 23, 2026 Compliance Filing Transmittal Letter at Section III.A.2. and Attachment \nA, Definitions R-S, Retail behind the Meter Generation. \n43 PJM February 23, 2026 Compliance Filing Transmittal Letter at Section III.A.2.a. \n44 Id."},{"page":73,"startToken":21380,"endToken":21689,"text":"Exhibit No. IA-1 \nPage 24 of 38 \n \n \n \nFacilities.  However, the step falls short of providing a just and reasonable outcome for \nQualifying Cogeneration Facilities in two respects. \n \n48. \nFirst, PJM’s proposal fails to recognize there may be some Cogeneration \nFacilities within the PJM footprint that fully meet FERC’s requirements to be a Qualifying \nCogeneration Facility (and, thus, a Qualifying Facility), except they do not currently have a \nFERC-approved certification or self-certification of their Qualifying Cogeneration Facility status \nbecause they do not makes sales of excess power either at avoided cost to electric utilities or into \nthe wholesale power market.  In addition, these Cogeneration Facilities have historically not \nneeded certification or self-certification as a Qualifying Cogeneration Facility in order for the \nelectrical load of their host retail customer to have reliable access to backup and maintenance \npower through just and reasonable rates through PJM’s current retail behind the meter generation \nnetting provisions for NITS charges and capacity requirements.  To address this first \nshortcoming that prevents PJM’s Qualifying Facility proposal from being just and reasonable, \nthe proposal would need to be modified to cover all Qualifying Facilities that were in service on \nor prior to December 18, 2025, regardless of the date of their certification or self-certification as \na Qualifying Facility.  This would ensure that generation facilities that were in service on \nDecember 18, 2025 that were fully able to meet FERC’s requirements to be a Qualifying \nFacility, except for not having a FERC-approved certification or self-certification due to not \npreviously having a need for such certification or self-certification, would be able to remedy \ntheir lack of certification or self-certification prior to the conclusion of the proposed three-year \ntransition period for the end of the current PJM retail behind the meter generation netting \nprovisions in order to preserve their ability to use those provisions after the end of the transition \nperiod."},{"page":74,"startToken":21689,"endToken":21989,"text":"Exhibit No. IA-1 \nPage 25 of 38 \n \n \n \n49. \nSecond, PJM has effectively erroneously concluded FERC’s rules for the provision of \nbackup and maintenance power to Qualifying Facilities45 ceased to be applicable in PJM \nfootprint upon FERC’s issuance of its December 18, 2025, Show Cause Order in Docket No. \nEL25-49-000, et al.  FERC made no such finding in its December 18, 2025, Show Cause Order \nas it does not address its PURPA backup and maintenance power rules for Qualifying Facilities \nin that order.  Given this, and the proposed Firm Contract Demand Transmission Service and \nNon-Firm Contract Demand Transmission Service options for Co-Located Loads are unable to \nprovide just and reasonable backup and maintenance power to Qualifying Cogeneration \nFacilities for the reasons I have discussed earlier in this affidavit, the proper legacy treatment for \nQualifying Facilities would be to allow all Qualifying Facilities to continue to be eligible to use \nPJM’s current retail behind-the-meter generation netting provisions for NITS charges and \ncapacity requirements regardless of when that Qualifying Facility entered service or was certified \nor self-certified as a Qualifying Facility.  Therefore, to address this second shortcoming that \nprevents PJM’s Qualifying Facility proposal from being just and reasonable, the proposal would \nneed to be modified to cover all Qualifying Facilities, regardless of the date they entered service \nor the date of their certification or self-certification as a Qualifying Facility. \n50. \nIt is important to note that providing legacy retail behind-the-meter generation \nnetting treatment for all Qualifying Facilities would not provide a “back door” for very large \ncomputational loads to bypass the Co-Located Load provisions of FERC’s December 18, 2025, \nShow Cause Order in Docket No. EL25-49-000, et al.  As I have discussed earlier in this \naffidavit, very large computational load processes are generally not highly thermally integrated, \n \n45 18 CFR § 292.305(c)."},{"page":75,"startToken":21989,"endToken":22286,"text":"Exhibit No. IA-1 \nPage 26 of 38 \n \n \n \nif integrated at all, with any co-located generation facilities whose meter they may be located \nbehind.  This is because those generation facilities will either not be Cogeneration Facilities or \nwould only be Cogeneration Facilities of greatly limited electrical capability relative to the total \nmagnitude of the electrical load of their host retail customer.  Furthermore, Qualifying Small \nPower Production Facilities, the other type of Qualifying Facility besides Qualifying \nCogeneration Facilities, are, except when a waiver is granted by FERC, limited to 80 MW in size \nunder FERC’s rules.46  As a result, the total electrical capability of a Qualifying Small \nProduction Facility would also be greatly limited relative to the total magnitude of a large \ncomputational load, which as I will discuss later in this affidavit, would likely be 300 MW or \nmore.  Therefore, providing legacy retail behind-the-meter generation netting treatment to all \nQualifying Facilities would not provide “back door” for very large computational loads to bypass \nFERC’s Co-Located Load provisions of its December 18, 2025, Show Cause Order in Docket \nNo. EL25-49-000, et al. \n \nVII. \nPJM’S PROPOSED 50 MW AND SMALLER LIMITATION FOR NON-\nQUALIFYING FACILITIES TO USE RETAIL BEHIND THE METER \nGENERATION NETTING ALSO FALLS SHORT OF BEING JUST AND \nREASONABLE \n \n51. \nIn addition to proposing to allow all retail customer behind-the-meter generation \nthat as of December 18, 2025 was a Qualifying Facility under PURPA to continue to be able to \nbe netted with its load for NITS charges and capacity requirements after the completion of three-\nyear transition period that would otherwise end such netting for this generation, PJM in its \nFebruary 23, 2026 compliance filing in this proceeding is also proposing two other such \n \n46 18 CFR §§ 292.203(a), 292.203(c) and 292.204(a)."},{"page":76,"startToken":22286,"endToken":22605,"text":"Exhibit No. IA-1 \nPage 27 of 38 \n \n \n \ncontinuations of retail behind the meter generation netting for NITS charges and capacity \nrequirements. \n \n52. \nFirst, PJM proposes to continue to allow retail behind the meter generation netting \nfor NITS charges and capacity requirements beyond the three-year transition period for all \ngeneration used to serve a retail load served by a Network Customer if the retail behind the meter \ngeneration is subject to contractual arrangements (including but not limited to a bilateral \nagreement or an interconnection agreement) that were in effect as of December 18, 2025 through \nthe end of the term of such agreement, which may be renewed or extended per the terms of such \nagreement. 47  PJM indicates it made this proposal in its compliance filing pursuant to the legacy \ntreatment of existing contractual agreements provided for by FERC under its December 18, \n2025, Show Cause Order in Docket No. EL25-49-000, et al.48  PJM also notes that, given these \nretail behind the meter generation arrangements, like those for PURPA Qualifying Facilities, \nhave been in place and netted against Network Loads within PJM without known operational \nissues to date, it proposes to allow such arrangements, which in some cases have been in place \nfor decades, to qualify for legacy treatment and continue to be eligible to net under existing \nbehind the meter generation rules.49  I agree with this first additional proposed extension of retail \nbehind-the-meter generation netting beyond the three-year transition period, and also agree with \nPJM’s arguments with respect to it. \n \n53. \nSecond, PJM proposes to continue to allow retail behind the meter generation \nnetting for NITS charges and capacity requirements beyond the three-year transition period for \n \n47 PJM February 23, 2026 Compliance Filing Transmittal Letter at Section III.A.2. and Attachment \nA, Definitions R-S, Retail behind the Meter Generation. \n48 PJM February 23, 2026 Compliance Filing Transmittal Letter at Section III.A.2.a. \n49 Id."},{"page":77,"startToken":22605,"endToken":22992,"text":"Exhibit No. IA-1 \nPage 28 of 38 \n \n \n \nall generation whose cumulative nameplate capacity rating is no greater than 50 MW (not \nincluding back-up generation at the same electrical location as the retail load that can only be \nused to serve such retail load during conditions that may threaten the integrity or the PJM Region \nor the regional power system). 50  PJM justifies its proposed cumulative nameplate capacity limit \nfor the continued retail behind the meter generation netting for generators not otherwise eligible \nfor continuation of netting under PJM’s Qualifying Facility and existing contract proposals as \nnot being too high when compared to a lower 10 or 20 MW limit: (i) excluding a much larger \nvolume of retail customers whose grid impacts are small or de minimis when compared with Co-\nLocated Loads coming online today and (ii) potentially causing loss of that generation altogether \ndue to significant transmission upgrades that may be required for that generation to become a \nmarket resource. 51  With respect to justifying why the 50 MW limit is not too low, PJM solely \nrelies on referencing a PJM Board letter defining large load additions as individual load additions \nat or above 50 MW at a single point of interconnection.52 Furthermore, PJM requests that, if its \nproposed Qualifying Facility continuation of retail behind-the-meter generation meeting for \nNITS charges and capacity requirements is not accepted, FERC accept as a potential stop gap a \nhigher limit of possibly as high as 200 MW to avoid the same potential loss of generation \ncapacity issue that it claims would be associated with a 10 or 20 MW limit.53  Under such an \napproach, PJM would commit to reviewing additional data on the size and extent of retail \n \n50 PJM February 23, 2026, Compliance Filing Transmittal Letter at Section III.A.2. and Attachment \nA, Definitions R-S, Retail behind the Meter Generation. \n51 PJM February 23, 2026, Compliance Filing Transmittal Letter at Section III.A.2.c. \n52 Id.  The January 16, 2026 PJM Board Letter does not include any factual or technical detail or \nsupport for the proposed 50 MW threshold.  See Board Decisional Letter on Critical Issue Fast Path - Large \nLoad Additions (Jan. 16, 2026) at p. 2, available at https://www.pjm.com/-/media/DotCom/about-\npjm/who-we-are/public-disclosures/2026/20260116-pjm-board-letter-re-results-of-the-cifp-process-large-\nload-additions.pdf. \n53 Id."},{"page":78,"startToken":22992,"endToken":23291,"text":"Exhibit No. IA-1 \nPage 29 of 38 \n \n \n \nbehind-the-meter generation, which could inform whether the initial higher stop gap limit should \nbe further refined through a separate future filing.54 \n \n54. \nPJM’s proposed 50 MW cumulative nameplate capacity limit for determining \nwhich retail behind-the-meter generation facilities, besides those who qualify under its \nQualifying Facility and existing contract proposals, would be eligible for continued retail behind \nthe meter generation netting treatment after the three-year transition period is not just and \nreasonable.  The proposed limit is not just and reasonable for two reasons.  First, it imposes a cap \nbased on the cumulative nameplate capacity of the generation behind the customer's meter, rather \nthan limiting the amount of load that can be netted behind the meter.  Second, the proposed \nthreshold amount of 50 MW is too low. \nThe Proposed 50 MW Limit is Inappropriately Applied to Cumulative Nameplate Capacity \nRather than the Amount of Retail Load that can be Netted \n     \n \n55. \nPJM’s proposal to apply its proposed 50 MW limit to cumulative nameplate \ncapacity rather than the amount of retail load that can be netted against generation located behind \nthat load’s meter is not just and reasonable for at least four reasons. \n56. \nFirst, nameplate capacity does not necessarily indicate the actual electrical \ncapability of behind-the-meter generation.  This can be particularly the case with generation \nserved from a common steam system, where it is the total capability of the steam system that \nlimits the combined electrical capability of the steam turbine generation facilities fed from it, not \nthe cumulative (i.e., the sum of the) nameplate capacity of the steam turbines.  In such situations, \nit would be inappropriate to apply the limit to cumulative nameplate capacity, as that amount \ncould be significantly higher than the actual electrical capability of the generation. \n \n54 Id."},{"page":79,"startToken":23291,"endToken":23626,"text":"Exhibit No. IA-1 \nPage 30 of 38 \n \n \n \n \n57. \nSecond, the cumulative nameplate capacity of the behind-the-meter generation, \neven when it does indicate the actual electrical capability of that behind-the-meter generation, \nmay be intentionally much larger than the retail load at its location in order to provide \nredundancy with respect to serving that load.  In this situation, it would also be inappropriate to \napply the limit to the cumulative nameplate capacity of the generation as that amount could be \nsignificantly higher than the actual retail load being served by that generation solely due to the \nredundancy being provided to improve the reliability of serving that load with behind the meter \ngeneration. \n \n58. \nThird, the proposal to use the cumulative nameplate capacity of the behind-the-\nmeter generation fails to account for a critical operational limitation.  Specifically, the generation \ncould not be operated in excess of the retail load it is serving behind the meter unless the \ngeneration has an interconnection agreement with PJM or the applicable transmission owner that \nallows it to put its power in excess of the retail load it is serving behind the meter onto the \ntransmission system.  Without such an agreement, the generation is effectively constrained to \nserving only the retail load behind the meter.  When limited in this matter, the largest generation \ncontingency the generator could place onto the PJM transmission system is a loss of generation \nequal to the amount of retail load the behind-the-meter generation is serving, not its cumulative \nnameplate capacity.  Furthermore, this concept is readily extendable to a situation where there is \na limit on the amount of retail load that can be served behind the meter by limiting the output of \nthe generation to the lesser of: (i) the current demand of the retail load or (ii) the MW limit \nplaced on retail behind the meter generation netting. \n59. \nFinally, the proposal fails to consider a large portion of behind the meter \ngeneration may not be associated with serving the electrical load of the host retail customer"},{"page":80,"startToken":23626,"endToken":23976,"text":"Exhibit No. IA-1 \nPage 31 of 38 \n \n \n \nbehind that customer’s meter but rather associated with either PURPA Qualifying Facility sales \nat avoided cost to an electric utility or sales into the wholesale market within the bounds the \ngeneration facility’s interconnection agreement.  As I noted earlier in this affidavit, this situation \nis not uncommon for Qualifying Cogeneration Facilities with a host retail customer that has a \nvery large steam need as the level of electric power production necessary by the Cogeneration \nFacility to produce the heat needed to meet the steam requirement of the host retail customer \nmay be much higher than the electrical load of the Cogeneration Facility’s host retail customer.55  \nIn addition, for non-Cogeneration Facilities, this situation can exist due the economy of scale \nbenefits of constructing a generation facility to not only serve the electrical load of the host retail \ncustomer behind the meter but to also make wholesale power sales.  Regardless of why the \nbehind the meter generation facility makes avoided cost or wholesale market sales, it is \nimportant to note the loss of the total electrical capability of the generation facility, less any \nelectrical load of the host retail customer that is lost with the loss of that electrical capability, has \nalready been considered as a generation contingency in determining the transmission upgrades \nthat were necessary to allow interconnection of the generation facility, and, as a result, the \ntransmission system has been built to accommodate that level of generation contingency.  \nTherefore, provided the generation operates within the bounds of its interconnection agreement \nand the bounds of PJM’s wholesale market rules, retail behind the meter generation with excess \npower sales does not introduce any circumstances that should preclude it from still being able to \nutilize retail behind the meter generation netting for NITS charges and capacity requirements for \n \n55 As an aside, it is important to note FERC’s rules for backup and maintenance power must be met \nfor all Qualifying Facilities regardless of whether a Qualifying Facility has any excess power sales either \nat avoided cost to an electric utility or into the wholesale power market."},{"page":81,"startToken":23976,"endToken":24312,"text":"Exhibit No. IA-1 \nPage 32 of 38 \n \n \n \nits host retail customer up to any MW limit on such netting.   This would be accomplished by \ncalculating the output of the generation to the PJM market (including any avoided costs sales to \nan electric utility) as the gross output of the generation less the lower of: (i) the current demand \nof the retail load being served by the generation behind the meter or (ii) the MW limit placed on \nretail behind the meter generation netting. \n \n60. \nFor the above reasons, the MW limit that is ultimately approved by FERC should \nbe a limit on the maximum MW of retail load that can be netted with behind-the-meter \ngeneration when determining NITS charges and capacity requirements for that retail load.  It \nshould not be a cumulative nameplate capacity limit that determines which locations where retail \nbehind-the-meter generation netting will be allowed, as proposed by PJM. \nPJM’s Proposed 50 MW Limit is Too Low \n \n61. \nPJM’s proposed 50 MW limit is too low for at least four reasons. \n \n62. \nFirst, PJM is solely relying on the PJM Board’s definition of large load additions \nas 50 MW at a single site to justify its proposed 50 MW limit as not being too low.  The PJM \nBoard is not a regulatory body that has made a finding of fact that 50 MW is the appropriate \nlimit for retail behind-the-meter generation netting.  Furthermore, the PJM Board did not develop \nits large load definition in the context of establishing a limit on retail behind-the-meter \ngeneration netting.  As such, it should be given no weight with respect to setting a limit on retail \nbehind-the-meter netting. \n \n63. \nSecond, PJM has not provided any evidence that the concerns it expressed with \nrespect to a limit of 10 or 20 MW – (i) excluding a large volume of retail customers whose grid \nimpacts are small or de minimis when compared with Co-Located Loads coming online today \nand (ii) potentially causing a loss of that generation altogether due to significant transmission"},{"page":82,"startToken":24312,"endToken":24628,"text":"Exhibit No. IA-1 \nPage 33 of 38 \n \n \n \nupgrades that may be required for them to become market resources – are not still present with a \n50 MW limit.  Also, it appears PJM is concerned its 50 MW limit may be too low in this respect, \nparticularly if its proposal for Qualifying Facilities is not accepted by FERC.  Specifically, as I \nnoted earlier in this affidavit, PJM has requested that FERC adopt a higher limit, potentially as \nhigh as 200 MW, as a stopgap if FERC chooses not to accept PJM’s proposal with respect to \nQualifying Facilities.56 \n \n64. \nThird, PJM, in its February 23, 2026 compliance filing in this proceeding, \nindicated that Qualifying Facility retail behind the meter generation and retail behind the meter \ngeneration with existing contracts have been in place and netted against Network Loads within \nPJM without known operational issues to date, and in some cases have been in place for decades.  \nWhile I certainly agree this is true for Qualifying Facilities and retail behind the generation with \nexisting contracts, it must also be generally true for all other existing retail behind-the-meter \ngeneration that has been in place for many years within the PJM footprint.  Furthermore, its \nexistence suggests that retail behind-the-meter generation netting at the MW level for individual \nretail customer locations for which it has historically occurred is something that can be readily \naccommodated in normal transmission planning and transmission operations such that it does not \nneed extraordinary treatment, such as prohibiting it.  This in turn suggests that a better basis for \ndeveloping a limit on how much retail behind the meter generation netting should be permitted \nbehind each retail customer’s meter would be to examine the largest amount of retail behind the \nmeter generation netting that has been readily accommodated in recent years and comparing that \n \n56 PJM February 23, 2026 Compliance Filing Transmittal Letter at Section III.A.2.c."},{"page":83,"startToken":24628,"endToken":24989,"text":"Exhibit No. IA-1 \nPage 34 of 38 \n \n \n \nto the typical size of the very large computational load additions that have triggered the need to \nconsider the Co-Located Loads issue in the first place. \n \n65. \nFinally, there is evidence that the typical size of very large computational load \nadditions, which are the load additions driving the need to examine the Co-Located Loads issue, \nis much larger than 50 MW. \n66. \nFor example, in the context of FERC’s Advanced Notice of Proposed Rulemaking \nin Docket No. RM26-4-000, Indicated PJM Transmission Owners stated: \nTo the extent the Commission asserts jurisdiction over large load \ninterconnections, it should adopt a sufficiently narrow definition of ‘large load \ncustomer’ limited to large (200 MW or greater) data center customers. It is those \ncustomers that are primarily driving load increases.57 \n \n \n67. \nIn addition, in early July 2025, in Michigan Public Service Commission \n(“MPSC”) Case No. U-21859, I performed and presented in rebuttal testimony an analysis of the \nMW size of the data center load addition inquiries that Consumers Energy Company had \nreceived up to that point in time.  A summary of the results of that analysis is presented in \nAttachment 2 of this affidavit, and the raw data upon which it was performed is provided in \nAttachment 3 of this affidavit.58  As shown in Attachment 2, my analysis indicated that the sum \nof the MWs of potential data center load addition inquiries Consumers Energy Company had \nreceived associated with a MW size of 300 MW or less makes up less than 7% (1,049 MW) of \nthe 15,249 MW in total large data center load addition inquiries that it had received.  In other \nwords, over 93% (14,200 MW) of the total MWs of large data center load addition inquiries \nConsumers Energy Company had received were from load additions greater than or equal to 300 \n \n57 Reply Comments of the Indicated PJM Transmission Owners, Interconnection of Large Loads to \nthe Interstate Transmission System, Docket No. RM26-4-000 (Dec. 5, 2025) at 2-3. \n58 The workpaper used to produce Attachment 2 of this affidavit is available on request to parties \nin this current proceeding from Industrials/Amtrak Counsel."},{"page":84,"startToken":24989,"endToken":25335,"text":"Exhibit No. IA-1 \nPage 35 of 38 \n \n \n \nMW in size.  While Consumers Energy Company is located within MISO rather than PJM, there \nis no reason to believe the results for Consumers Energy Company are not indicative of what a \nsimilar analysis would likely show for similar large electric utilities in PJM.  In other words, the \nlarge load additions to be concerned with are not all large load additions 50 MW and larger, but \nrather those 300 MW or higher, as evidenced by my analysis, since they make up the vast \nmajority of what is being proposed.  Accordingly, more concrete evidence exists to support a 300 \nMW threshold than a 50 MW threshold. \n \n68. \nIn addition, in September 2025, subsequent to the performance of my early July \n2025 analysis based on Consumers Energy Company data, I became involved in Illinois \nCommerce Commission (“ICC”) Docket No. 25-0677.  That Illinois proceeding concerned \nCommonwealth Edison Company (“ComEd”) – a very large Illinois electric utility located within \nPJM.  In that proceeding, ComEd Witness Max Leichtman in direct testimony indicated “the \naverage size of a unique large demand project that began the process of obtaining electric service \nfrom ComEd in the last twelve months is approximately 700 MWs, roughly the equivalent of \n1,400 big box stores.”59  Furthermore, in response to discovery in that proceeding, ComEd \nprovided a data request response that publicly disclosed the MW size of each of the \naforementioned projects.60  A copy of this ComEd discovery response in ICC Docket No. 25-\n0677 is provided as Attachment 4 to my affidavit.  As can be seen in Attachment 4, in 2025, \nthrough the August 29, 2025 date of the ComEd discovery response, twelve (12) load additions \nbegan the process of obtaining electric service from ComEd.  Ten (10) of the twelve (12) \nproposed load additions, representing 8,212 MW (98.86%) of the total of 8,307 MW of requested \n \n59 ICC Docket No. 25-0677, ComEd Ex. 1.0, Direct Testimony of Max Leichtman at 6. \n60 ICC Docket No. 25-0677, ComEd Response to Data Request No. NRG-ComEd 1.02."},{"page":85,"startToken":25335,"endToken":25644,"text":"Exhibit No. IA-1 \nPage 36 of 38 \n \n \n \nelectric service, were from proposed loads with a magnitude of 300 MW or greater.  This \nprovides further concrete evidence to support a 300 MW threshold rather than a 50 MW \nthreshold.   \n \n69. \nFor the foregoing reasons, PJM’s proposed limit of 50 MW is too low.  Concrete \nevidence exists to support a 300 MW threshold, and any limit should instead initially be set no \nlower than 200 MW (if not closer to 300 MW), regardless of whether PJM’s proposal for \nQualifying Facilities is accepted or that proposal is modified as I have recommended earlier in \nthis affidavit. \n          \nVIII. CONCLUSION \n70. \nIn summary, I conclude the following: \n Very large computational loads co-located behind the meter of generation \nfacilities are not similarly situated to traditional large commercial, \nindustrial, and institutional loads using Cogeneration Facilities located \nbehind their meter, as very large computational loads generally are not \nhighly thermally integrated with any co-located generation facilities. \n \n For traditional large loads served by Cogeneration Facilities, PJM’s \ncurrent retail behind-the-meter generation netting provisions for NITS \ncharges and capacity requirements are consistent with cost causation \nprinciples and FERC’s own backup and maintenance power rules for \nQualifying Facilities, as they rely on factual data regarding each \nQualifying Facility’s historical performance rather than assumptions about \nwhen outages will occur and whether they will occur simultaneously. \n \n Firm Contract Demand Transmission Service and Non-Firm Contract \nDemand Transmission Service are not capable – either alone or in tandem \n– of providing reliable backup and maintenance power to traditional large \nretail customers that utilize Qualifying Cogeneration Facilities at rates \nconsistent with cost causation principles and FERC’s rules for providing \nbackup and maintenance service to Qualifying Facilities. \n \n PJM’s proposal to limit legacy retail behind-the-meter generation \ntreatment for Qualifying Facilities to those certified or self-certified as of \nDecember 18, 2025 falls short of being just and reasonable, and should be"},{"page":86,"startToken":25644,"endToken":25765,"text":"Exhibit No. IA-1 \nPage 37 of 38 \n \n \n \nmodified to cover all Qualifying Facilities regardless of the date they \nentered service or the date of their certification or self-certification. \n \n PJM’s proposed 50 MW cumulative nameplate capacity limit for \ncontinued retail behind-the-meter generation netting for non-Qualifying \nFacility generation is not just and reasonable because the limit is \ninappropriately applied to cumulative nameplate capacity rather than to \nthe amount of retail load that can be netted, and 50 MW is too low given \nthat the large computational load additions driving the Co-Located Loads \nissue are overwhelmingly 300 MW or larger in size; any limit should \ninitially be set no lower than 200 MW (if not closer to 300 MW). \n \n \n71. \nFurther Affiant sayeth naught."},{"page":87,"startToken":25765,"endToken":25813,"text":"Exhibit No.IA-1\nPage 38 of38\nes R. Dauph\nSTATE OF'MISSOURI\nCOUNTY OF ST. LOUIS\nSubscribed and sworn to before me this 16th day of March,2026.\nNotary Public\n)\n)\n)\nSS\nNotary Public - Notary Soal\nSTATE OF MISSOURI\nJetferson County\nCommission Expiresr Mar, 22,2029\nMy\n# 21989987\nADRIENNE J."},{"page":88,"startToken":25813,"endToken":26026,"text":"Exhibit No. IA-1 \nAttachment 1 \nPage 1 of 6 \n \n \n \nBRUBAKER & ASSOCIATES, INC. \nQualifications of James R. Dauphinais \n \nQ \nPLEASE STATE YOUR NAME AND BUSINESS ADDRESS. \n1 \nA \nJames R. Dauphinais.  My business address is 16690 Swingley Ridge Road, Suite 140, \n2 \nChesterfield, MO 63017, USA. \n3 \n \nQ \nPLEASE STATE YOUR OCCUPATION.    \n4 \nA \nI am a consultant in the field of public utility regulation and a Managing Principal with \n5 \nthe firm of Brubaker & Associates, Inc. (“BAI”), energy, economic and regulatory \n6 \nconsultants. \n7 \n \nQ \nPLEASE SUMMARIZE YOUR EDUCATIONAL BACKGROUND AND \n8 \nEXPERIENCE.  \n9 \nA \nI graduated from Hartford State Technical College in 1983 with an Associate's Degree \n10 \nin Electrical Engineering Technology.  Subsequent to graduation, I was employed by \n11 \nthe Transmission Planning Department of the Northeast Utilities Service Company1 as \n12 \nan Engineering Technician. \n13 \n \n \nWhile employed as an Engineering Technician, I completed undergraduate \n14 \nstudies at the University of Hartford.  I graduated in 1990 with a Bachelor's Degree in \n15 \nElectrical Engineering.  Subsequent to graduation, I was promoted to the position of \n16 \nAssociate Engineer.  Between 1993 and 1994, I completed graduate level courses in the \n17 \nstudy of power system analysis, power system transients and power system protection \n18 \n \n \n1In 2015, Northeast Utilities changed its name to Eversource Energy."},{"page":89,"startToken":26026,"endToken":26321,"text":"Exhibit No. IA-1 \nAttachment 1 \nPage 2 of 6 \n \n \n \nBRUBAKER & ASSOCIATES, INC. \nthrough the Engineering Outreach Program of the University of Idaho.  By 1996 I had \n1 \nbeen promoted to the position of Senior Engineer. \n2 \n \n \nIn the employment of the Northeast Utilities Service Company, I was \n3 \nresponsible for conducting thermal, voltage and stability analyses of the Northeast \n4 \nUtilities' transmission system to support planning and operating decisions.  This \n5 \ninvolved the use of load flow, power system stability and production cost computer \n6 \nsimulations.  It also involved examination of potential solutions to operational and \n7 \nplanning problems including, but not limited to, transmission line solutions and the \n8 \nroutes that might be utilized by such transmission line solutions.  Among the most \n9 \nnotable achievements I had in this area include the solution of a transient stability \n10 \nproblem near Millstone Nuclear Power Station, and the solution of a small signal (or \n11 \ndynamic) stability problem near Seabrook Nuclear Power Station.  In 1993 I was \n12 \nawarded the Chairman's Award, Northeast Utilities’ highest employee award, for my \n13 \nwork involving stability analysis in the vicinity of Millstone Nuclear Power Station. \n14 \nFrom 1990 to 1996, I represented Northeast Utilities on the New England Power \n15 \nPool Stability Task Force.  I also represented Northeast Utilities on several other \n16 \ntechnical working groups within the New England Power Pool (“NEPOOL”) and the \n17 \nNortheast Power Coordinating Council (“NPCC”), including the 1992-1996 New York-\n18 \nNew England Transmission Working Group, the Southeastern Massachusetts/Rhode \n19 \nIsland Transmission Working Group, the NPCC CPSS-2 Working Group on Extreme \n20 \nDisturbances and the NPCC SS-38 Working Group on Interarea Dynamic Analysis.  \n21 \nThis latter working group also included participation from a number of ECAR, PJM and \n22 \nVACAR utilities.  \n23"},{"page":90,"startToken":26321,"endToken":26608,"text":"Exhibit No. IA-1 \nAttachment 1 \nPage 3 of 6 \n \n \n \nBRUBAKER & ASSOCIATES, INC. \nFrom 1990 to 1995, I also acted as an internal consultant to the \n1 \nNuclear Electrical Engineering Department of Northeast Utilities.  This included \n2 \ninteractions with the electrical engineering personnel of the Connecticut Yankee, \n3 \nMillstone and Seabrook nuclear generation stations and inspectors from the Nuclear \n4 \nRegulatory Commission (“NRC”). \n5 \nIn addition to my technical responsibilities, from 1995 to 1997, I was also \n6 \nresponsible for oversight of the day-to-day administration of Northeast Utilities' Open \n7 \nAccess Transmission Tariff.  This included the creation of Northeast Utilities' pre-FERC \n8 \nOrder No. 889 transmission electronic bulletin board and the coordination of Northeast \n9 \nUtilities' transmission tariff filings prior to and after the issuance of Federal Energy \n10 \nRegulatory Commission (“FERC” or “Commission”) FERC Order No. 888.  I was also \n11 \nresponsible for spearheading the implementation of Northeast Utilities' Open Access \n12 \nSame-Time Information System and Northeast Utilities’ Standard of Conduct under \n13 \nFERC Order No. 889.  During this time, I represented Northeast Utilities on the Federal \n14 \nEnergy Regulatory Commission's \"What\" Working Group on Real-Time Information \n15 \nNetworks.  Later I served as Vice Chairman of the NEPOOL OASIS Working Group \n16 \nand Co-Chair of the Joint Transmission Services Information Network Functional \n17 \nProcess Committee.  I also served for a brief time on the Electric Power Research \n18 \nInstitute facilitated \"How\" Working Group on OASIS and the North American Electric \n19 \nReliability Council facilitated Commercial Practices Working Group. \n20 \nIn 1997 I joined the firm of Brubaker & Associates, Inc.  The firm includes \n21 \nconsultants with backgrounds in accounting, engineering, economics, mathematics, \n22 \ncomputer science and business.  Since my employment with the firm, I have filed or \n23"},{"page":91,"startToken":26608,"endToken":26870,"text":"Exhibit No. IA-1 \nAttachment 1 \nPage 4 of 6 \n \n \n \nBRUBAKER & ASSOCIATES, INC. \npresented testimony before the Federal Energy Regulatory Commission in Consumers \n1 \nEnergy Company, Docket No. OA96-77-000; Midwest Independent Transmission \n2 \nSystem Operator, Inc., Docket No. ER98-1438-000; Montana Power Company, Docket \n3 \nNo. ER98-2382-000; Inquiry Concerning the Commission’s Policy on Independent \n4 \nSystem Operators, Docket No. PL98-5-003; SkyGen Energy LLC v. Southern Company \n5 \nServices, Inc., Docket No. EL00-77-000; Alliance Companies, et al., Docket No. EL02-\n6 \n65-000, et al.; Entergy Services, Inc., Docket No. ER01-2201-000; Remedying Undue \n7 \nDiscrimination through Open Access Transmission Service, Standard Electricity \n8 \nMarket Design, Docket No. RM01-12-000; Midwest Independent Transmission System \n9 \nOperator, Inc., Docket No. ER10-1791-000; NorthWestern Corporation, Docket No. \n10 \nER10-1138-001, et al.; Illinois Industrial Energy Consumers v. Midcontinent \n11 \nIndependent System Operator, Inc., Docket No. EL15-82-000; Midcontinent \n12 \nIndependent System Operator, Inc., Docket No. ER16-833-000; Midcontinent \n13 \nIndependent System Operator, Inc., Docket No. ER17-284-000; and Midcontinent \n14 \nIndependent System Operator, Inc. and Ameren Services Company Docket No. ER18-\n15 \n463-000.  I have also filed or presented testimony before the Alberta Utilities \n16 \nCommission, the California Public Utilities Commission, the Colorado Public Utilities \n17 \nCommission, the Connecticut Department of Public Utility Control, the Florida Public \n18 \nService Commission, the Idaho Public Service Commission, the Illinois Commerce \n19 \nCommission, the Indiana Utility Regulatory Commission, the Iowa Utilities Board, the \n20 \nKentucky Public Service Commission, the Louisiana Public Service Commission, the \n21 \nMichigan Public Service Commission, the Missouri Public Service Commission, the \n22 \nMontana Public Service Commission, the Nevada Public Utilities Commission, the New \n23"},{"page":92,"startToken":26870,"endToken":27150,"text":"Exhibit No. IA-1 \nAttachment 1 \nPage 5 of 6 \n \n \n \nBRUBAKER & ASSOCIATES, INC. \nMexico Public Regulation Commission, the Council of the City of New Orleans, the \n1 \nState of New York Public Service Commission, the Oklahoma Corporation \n2 \nCommission, the Public Utility Commission of Texas, the Public Service Commission \n3 \nof Utah, the Virginia State Corporation Commission, the Wisconsin Public Service \n4 \nCommission, the Wyoming Public Service Commission, Federal District Court and \n5 \nvarious committees of the Illinois, Missouri and South Carolina state legislatures.  This \n6 \ntestimony has been given regarding a wide variety of issues including, but not limited \n7 \nto, ancillary service rates, avoided cost calculations, certification of public convenience \n8 \nand necessity, class cost of service, cost allocation, fuel adjustment clauses, fuel costs, \n9 \ngeneration interconnection, interruptible rates, market power, market structure, \n10 \noff-system sales, prudency, purchased power costs, resource adequacy, resource \n11 \nplanning, rate design, retail open access, standby rates, transmission losses, transmission \n12 \nplanning, transmission rates and transmission line routing. \n13 \nI have also participated on behalf of clients in the Southwest Power Pool \n14 \nCongestion Management System Working Group, the Alliance Market Development \n15 \nAdvisory Group and several committees and working groups of the Midcontinent \n16 \nIndependent System Operator, Inc. (“MISO”), including the Congestion Management \n17 \nWorking Group; Economic Planning Users Group; Loss of Load Expectation Working \n18 \nGroup; Market Subcommittee; Michigan Transmission Studies Task Force; Planning \n19 \nSubcommittee; Regional Expansion, Criteria and Benefits Working Group; Resource \n20 \nAdequacy Subcommittee (formerly the Supply Adequacy Working Group); and \n21 \nReliability Subcommittee.  I am currently a member of the MISO Advisory Committee \n22 \nin the end-use customer sector on behalf of industrial customer groups in Illinois, \n23"},{"page":93,"startToken":27150,"endToken":27234,"text":"Exhibit No. IA-1 \nAttachment 1 \nPage 6 of 6 \nBRUBAKER & ASSOCIATES, INC. \nLouisiana, Michigan and Texas.  I am also the past Chairman of the Issues/Solutions \n1 \nSubgroup of the MISO Revenue Sufficiency Guarantee (“RSG”) Task Force.   \n2 \nIn 2009, I completed the University of Wisconsin-Madison High Voltage Direct \n3 \nCurrent (“HVDC”) Transmission course for Planners that was sponsored by MISO.  I \n4 \nam a member of the Power and Energy Society (“PES”) of the Institute of Electrical and \n5 \nElectronics Engineers (“IEEE”).   \n6"},{"page":94,"startToken":27234,"endToken":27367,"text":"Exhibit No. IA-1 \nAtatchment 2 \nPage 1 of 1\n<100 MW\n< 150 MW\n< 200 MW\n< 250 MW\n< 300 MW\n< 350 MW\n< 400 MW\n< 1,000 MW <= 1,200 MW\nUknown MW\nTotal # of Load Inquiries\n2\n  \n5\n  \n5\n  \n7\n  \n8\n  \n16\n  \n16\n  \n26\n  \n32\n  \n6\n  \nTotal Amount of MW\n54\n  \n399\n  \n399\n  \n799\n  \n1,049\n  \n3,449\n  \n3,449\n  \n9,049\n  \n15,249\n  \n% of 15,249 MW\n0.35%\n2.62%\n2.62%\n5.24%\n6.88%\n22.62%\n22.62%\n59.34%\n100.00%\n% of 15,249 MW above\n99.65%\n97.38%\n97.38%\n94.76%\n93.12%\n77.38%\n77.38%\n40.66%\n0.00%\nSource:  Attachment to Consumers' Data Request Response U21859-DCC-CE-0045 (Exhibit No. IA-1, Attachment 3)\nAnalysis of MW Size of Consumers' Large Data Center Load Addition Inquiries"},{"page":95,"startToken":27367,"endToken":27470,"text":"U21859-DCC-CE-0045 \nPage 1 of 1 \nQuestion: \n21859-DCC-CE-0013. Please refer to Connolly Direct at 4:7-8. “The Company has data center inquiries that \ntotal over 15 gigawatts of electric load in the economic development pipeline.” Please provide a \nspreadsheet or other document listing each of the referenced “data center inquiries,” and identify, for \neach inquiry: a) the proposed location; b) the associated electric load and/or contract capacity; and c) the \ntimeline for energization and delivery of requested capacity, including any proposed load ramp. \nResponse: \nSee attached \nWitness: Laura M. Connolly \nDate: May 13, 2025 \nExhibit No. IA-1 \nAttachment 3\nPage 1 of 3"},{"page":96,"startToken":27470,"endToken":27812,"text":"1\nDescription\nDate of Inquiry\nPeak demand \nreached year\n50% of peak year\nRequested in-\nservice year\nLoad\n(MW)\nLocation\nId\nData Center\n10/7/2024\nUnknown\nUnknown\nAs soon as possible\n400\nEast Central Region\nA\nData Center\n10/4/2024\nQ1 2040\nQ2 2033\nQ1 2026\n1,000\nSouth Central Region\nB\nData Center\n11/6/2024\nUnknown\nUnknown\nUnknown\n300\nUnknown\nC\nData Center\n7/15/2024\nUnknown\nUnknown\nAs soon as possible\n300\nEast Central Region\nD\nData Center\n5/7/2024\nWithin 36 months\nUnknown\nAs soon as possible\n200\nUnknown\nE\nData Center\n12/3/2024\nUnknown\nUnknown\nUnknown\nUnknown\nSouthwest Region\nF\nData Center\n11/19/2024\nUnknown\nUnknown\nUnknown\n200\nUnknown\nG\nData Center\n3/10/2025\nUnknown\nUnknown\nAs soon as possible\n250\nUnknown\nH\nData Center\n2/26/2025\nWithin 36 months\nUnknown\nAs soon as possible\n1,000\nEast Central Region\nI\nData Center\n3/1/2024\nQ4 2033\nQ4 2030\nQ1 2029\n300\nWest Region\nJ\nData Center\n6/6/2024\nQ4 2033\nQ2 2030\nQ4 2029\n300\nUnknown\nK\nData Center\n1/9/2025\nUnknown\nUnknown\nUnknown\n100\nEast Region\nL\nData Center\n12/4/2024\nQ1 2030\nUnknown\nUnknown\n300\nUnknown\nM\nData Center\n2/4/2025\nUnknown\nUnknown\nUnknown\n700\nEast Region\nN\nData Center\n2/28/2025\nWithin 5-10 years\nUnknown\nWithin 2-3 years\n1,000\nUnknown\nO\nData Center\n3/10/2025\nUnknown\nUnknown\nUnknown\n300\nEast Central Region\nP\nData Center\n7/29/2024\nUnknown\nUnknown\nUnknown\nUnknown\nUnknown\nQ\nData Center\n8/7/2024\nUnknown\nUnknown\nUnknown\n500\nUnknown\nR\nData Center\n10/4/2024\nUnknown\nUnknown\nUnknown\n100\nSouth Central Region\nS\nData Center\n10/31/2024\nQ1 2031\nUnknown\nQ1 2027\nUnknown\nUnknown\nT\nData Center\n12/19/2024\nUnknown\nUnknown\nUnknown\n50\nSouthwest Region\nU\nData Center\n10/16/2024\nQ4 2030\nQ2 2029\nQ1 2028\n1,200\nUnknown\nV\nData Center\n8/19/2024\nUnknown\nUnknown\nUnknown\n300\nUnknown\nW\nExhibit No. IA-1 \nAttachment 3\nPage 2 of 3"},{"page":97,"startToken":27812,"endToken":28022,"text":"2\nDescription\nDate of Inquiry\nPeak demand \nreached year\n50% of peak year\nRequested in-service \nyear\nLoad\n(MW)\nLocation\nId\nData Center\n7/25/2024\n2024\n2024\n2024\n4\nSouthwest Region\nX\nData Center\n1/15/2025\nUnknown\nUnknown\nUnknown\n300\nUnknown\nY\nData Center\n10/31/2024\nUnknown\nUnknown\nUnknown\nUnknown\nUnknown\nZ\nData Center\n9/10/2024\nUnknown\nUnknown\nUnknown\n500\nUnknown\nAA\nData Center\n10/31/2024\nUnknown\nUnknown\nQ1 2029\n1,000\nUnknown\nAB\nData Center\n7/12/2024\nQ1 2029\nUnknown\nQ1 2026\n500\nUnknown\nAC\nData Center\n10/29/2024\nUnknown\nUnknown\nUnknown\nUnknown\nUnknown\nAD\nData Center\n7/25/2024\nQ3 2029\nQ3 2027\nQ3 2026\n500\nUnknown\nAE\nData Center\n10/10/2024\nUnknown\nUnknown\nUnknown\n500\nUnknown\nAF\nData Center\n12/11/2024\n2030\nUnknown\nQ4 2027\n600\nUnknown\nAG\nData Center\n7/31/2024\nUnknown\nUnknown\nUnknown\n145\nUnknown\nAH\nData Center\n2/4/2025\nUnknown\nUnknown\n2027\n1,000\nUnknown\nAI\nData Center\n1/6/2025\nQ1 2029\nUnknown\nUnknown\n500\nSoutheasterly Region\nAJ\nData Center\n9/11/2024\nQ4 2029\nQ4 2028\nQ4 2027\n900\nUnknown\nAK\nData Center\n11/21/2024\nUnknown\nUnknown\nUnknown\nUnknown\nEast Central\nAL\nExhibit No. IA-1 \nAttachment 3\nPage 3 of 3"},{"page":98,"startToken":28022,"endToken":28198,"text":"ICC Docket Nos. 25-0677 & 25-0679 (Cons.) \nCommonwealth Edison Company’s Response to \nNRG Energy, Inc. (“NRG”) Information Requests \nNRG-ComEd 1.01-NRG-ComEd 1.20 \nDate Received:  August 22, 2025 \nDate Served:  August 29, 2025 \nREQUEST NO. NRG-ComEd 1.02: \nPlease provide all workpapers, analyses, data, and information used or relied upon by Max \nLeichtman in relation to ComEd Ex. 1.0, the Direct Testimony of Max Leichtman. \nRESPONSE: \nComEd objects to this request as overly broad and unduly burdensome to the extent it seeks “all \n… data and information … relied upon” by ComEd witness Leichtman, and to the extent that \nmuch of the “data and information” is not relevant and not calculated to lead to the discovery of \nrelevant and admissible evidence.  Subject to and without waiving those objections, ComEd \nresponds as follows: \nSee NRG-ComEd 1.02_Attach 1 for the data supporting Figure 1 in the direct testimony of Max \nLeichtman (ComEd Ex. 1.0) at lines 122-123.  There are no other workpapers supporting Mr. \nLeichtman’s testimony. \n2025LLT 0000007\nExhibit No. IA-1 \nAttachment 4\nPage 1 of 4"},{"page":99,"startToken":28198,"endToken":28390,"text":"Year\nNew/Expansion\nComEd New \nUltimate \n2018\nNew\n2.000\n    \n2018\nNew\n14.000\n     \n2018\nNew\n22.000\n     \n2018\nNew\n24.000\n     \n2018\nNew\n4.000\n    \n2018\nExpansion\n24.000\n     \n2018\nNew\n3.500\n    \n2018 Total\n93.500\n  \n2019\nNew\n4.100\n    \n2019\nNew\n4.050\n    \n2019\nExpansion\n3.000\n    \n2019\nExpansion\n4.100\n    \n2019\nExpansion\n12.310\n     \n2019\nExpansion\n2.700\n    \n2019\nNew\n5.370\n    \n2019\nExpansion\n1.200\n    \n2019\nNew\n5.000\n    \n2019\nNew\n37.787\n     \n2019 Total\n79.617\n \n2020\nNew\n13.70\n2020\nNew\n0.10\n2020\nNew\n2.00\n2020\nNew\n71.80\n2020\nNew\n68.30\n2020\nNew\n48.00\n2020\nNew\n28.98\n2020\nNew\n16.00\n2020\nExpansion\n5.00\n2020\nNew\n5.30\n2020\nNew\n4.00\n2020\nNew\n1.25\n2020\nNew\n12.29\n2020\nNew\n5.80\n2020\nNew\n11.25\n2020\nNew\n15.70\n2020\nNew\n7.70\n2020\nNew\n208.00\n2020 Total\n525.16\n2021\nNew\n108.00\n2021\nNew\n4.00\n-\n-\nICC Dkt Nos. 25-0677 / 25-0679 (Cons.)\nNRG-ComEd 1.02_Attach 1 \nPage 1 of 3\n2025LLT 0000008\nExhibit No. IA-1 \nAttachment 4\nPage 2 of 4"},{"page":100,"startToken":28390,"endToken":28585,"text":"2021\nNew\n250.00\n2021\nExpansion\n10.00\n2021\nNew\n34.00\n2021\nNew\n3.00\n2021\nNew\n2.10\n2021\nNew/Expansion\n4.00\n2021\nNew\n24.00\n2021\nNew\n10.00\n2021\nNew\n24.00\n2021\nNew\n1.00\n2021\nNew\n6.50\n2021\nNew\n5.20\n2021\nNew\n8.00\n2021\nNew\n5.00\n2021 Total\n498.80\n2022\nNew\n24.00\n2022\nNew\n5.00\n2022\nNew\n120.00\n2022\nNew\n250.00\n2022\nExpansion\n135.00\n2022\nNew\n2.00\n2022\nExpansion\n92.00\n2022\nNew\n5.00\n2022\nNew\n3.00\n2022\nNew\n8.00\n2022\nNew\n2.00\n2022\nNew\n5.50\n2022 Total\n651.50\n2023\nNew\n612.00\n2023\nNew\n288.00\n2023\nNew\n378.00\n2023\nNew\n325.00\n2023\nNew\n7.00\n2023\nExpansion\n24.00\n2023\nExpansion\n12.00\n2023\nExpansion\n11.00\n2023\nNew\n250.00\n2023\nNew\n135.00\n2023\nNew\n6.50\n2023\nNew\n110.00\n2023\nNew\n2.00\n2023\nNew\n12.00\n-\n-\nICC Dkt Nos. 25-0677 / 25-0679 (Cons.)\nNRG-ComEd 1.02_Attach 1 \nPage 2 of 3\n2025LLT 0000009\nExhibit No. IA-1 \nAttachment 4\nPage 3 of 4"},{"page":101,"startToken":28585,"endToken":28739,"text":"2023\nNew\n49.00\n2023 Total\n2221.50\n2024\nNew\n16.00\n2024\nNew\n1500.00\n2024\nNew\n45.00\n2024\nNew\n94.00\n2024\nNew\n587.00\n2024\nNew\n480.00\n2024\nNew\n350.00\n2024\nNew\n600.00\n2024\nExpansion\n20.00\n2024\nExpansion\n40.00\n2024\nExpansion\n60.00\n2024\nNew\n10.00\n2024\nExpansion\n25.00\n2024\nNew\n50.00\n2024\nNew\n54.00\n2024 Total\n3931.00\n2025\nNew \n600.00\n2025\nNew \n505.00\n2025\nAttraction\n300.00\n2025\nAttraction\n860.00\n2025\nAttraction\n1000.00\n2025\nAttraction\n750.00\n2025\nAttraction\n1296.00\n2025\nAttraction\n600.00\n2025\nExpansion\n1870.00\n2025\nAttraction \n431.00\n2025\nAttraction\n54.00\n2025\nAttraction\n41.00\n2025 Total\n8307.00\nGrand Total\n16308.08\n-\n-\nICC Dkt Nos. 25-0677 / 25-0679 (Cons.)\nNRG-ComEd 1.02_Attach 1 \nPage 3 of 3\n2025LLT 0000010\nExhibit No. IA-1 \nAttachment 4\nPage 4 of 4"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":2,"endAt":128,"startToken":0,"endToken":270},{"p":2,"at":128,"title":"I. BACKGROUND","method":"printed heading","endPage":3,"endAt":222,"startToken":270,"endToken":556},{"p":3,"at":222,"title":"II. THE INDUSTRIALS/AMTRAK","method":"printed heading","endPage":5,"endAt":1027,"startToken":556,"endToken":1352},{"p":5,"at":1027,"title":"III. EXECUTIVE SUMMARY","method":"printed heading","endPage":11,"endAt":6,"startToken":1352,"endToken":3271},{"p":11,"at":6,"title":"IV. PROTEST","method":"printed heading","endPage":17,"endAt":6,"startToken":3271,"endToken":5317},{"p":17,"at":6,"title":"A. PJM’s proposed exemption for PURPA Qualifying Facilities is appropriate,","method":"printed heading","endPage":23,"endAt":1068,"startToken":5317,"endToken":7688},{"p":23,"at":1068,"title":"B. PJM’s Proposed 50 MW Retail Threshold is insufficient to balance the","method":"printed heading","endPage":34,"endAt":6,"startToken":7688,"endToken":11176},{"p":34,"at":6,"title":"C. The FERC should direct PJM to remove the “all-or-nothing” approach to the","method":"printed heading","endPage":37,"endAt":438,"startToken":11176,"endToken":12265},{"p":37,"at":438,"title":"V. COMMENTS","method":"printed heading","endPage":37,"endAt":676,"startToken":12265,"endToken":12296},{"p":37,"at":676,"title":"A. Grandfathering rules and confirmation of grandfathered status should be","method":"printed heading","endPage":40,"endAt":6,"startToken":12296,"endToken":13099},{"p":40,"at":6,"title":"B. PJM’s exemption for back-up generation is appropriate and should be","method":"printed heading","endPage":42,"endAt":6,"startToken":13099,"endToken":13597},{"p":42,"at":6,"title":"VI. CONCLUSION & REQUEST FOR RELIEF","method":"printed heading","endPage":43,"endAt":0,"startToken":13597,"endToken":13704},{"p":43,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":46,"endAt":190,"startToken":13704,"endToken":13816},{"p":46,"at":190,"title":"Table of Contents","method":"printed heading","endPage":46,"endAt":463,"startToken":13816,"endToken":13825},{"p":46,"at":463,"title":"II. BACKGROUND ON THE USE OF COGENERATION FACILITIES BY","method":"printed heading","endPage":46,"endAt":1184,"startToken":13825,"endToken":13877},{"p":46,"at":1184,"title":"III. COMMERCIAL, INDUSTRIAL AND INSTITUTIONAL CUSTOMERS","method":"printed heading","endPage":46,"endAt":1448,"startToken":13877,"endToken":13902},{"p":46,"at":1448,"title":"IV. FOR TRADITIONAL LARGE LOADS SERVED BY COGENERATION","method":"printed heading","endPage":47,"endAt":24,"startToken":13902,"endToken":13951},{"p":47,"at":24,"title":"V. FIRM CONTRACT DEMAND TRANSMISSION SERVICE AND","method":"printed heading","endPage":47,"endAt":317,"startToken":13951,"endToken":13979},{"p":47,"at":317,"title":"VI. PJM’S PROPOSAL WITH RESPECT TO ALLOWING EXISTING","method":"printed heading","endPage":47,"endAt":635,"startToken":13979,"endToken":14015},{"p":47,"at":635,"title":"VII. PJM’S PROPOSED 50 MW AND SMALLER LIMITATION FOR","method":"printed heading","endPage":50,"endAt":226,"startToken":14015,"endToken":14338},{"p":50,"at":226,"title":"I. INTRODUCTION","method":"printed heading","endPage":54,"endAt":325,"startToken":14338,"endToken":15605},{"p":54,"at":325,"title":"II. BACKGROUND ON THE USE OF COGENERATION FACILITIES BY","method":"printed heading","endPage":61,"endAt":39,"startToken":15605,"endToken":17736},{"p":61,"at":39,"title":"III. COMMERCIAL, INDUSTRIAL AND INSTITUTIONAL CUSTOMERS USING","method":"printed heading","endPage":62,"endAt":405,"startToken":17736,"endToken":18048},{"p":62,"at":405,"title":"IV. FOR TRADITIONAL LARGE LOADS SERVED BY COGENERATION","method":"printed heading","endPage":68,"endAt":791,"startToken":18048,"endToken":20041},{"p":68,"at":791,"title":"V. FIRM CONTRACT DEMAND TRANSMISSION SERVICE AND NON-FIRM","method":"printed heading","endPage":72,"endAt":152,"startToken":20041,"endToken":21116},{"p":72,"at":152,"title":"VI. PJM’S PROPOSAL WITH RESPECT TO ALLOWING EXISTING CERTIFIED","method":"printed heading","endPage":75,"endAt":1208,"startToken":21116,"endToken":22170},{"p":75,"at":1208,"title":"VII. PJM’S PROPOSED 50 MW AND SMALLER LIMITATION FOR NON-","method":"printed heading","endPage":85,"endAt":624,"startToken":22170,"endToken":25438},{"p":85,"at":624,"title":"VIII. CONCLUSION","method":"printed heading","endPage":101,"endAt":751,"startToken":25438,"endToken":28739}]}