{"document":{"slug":"rec-20260316-5323","title":"Comments of Data Center Coalition in response to PJM Interconnection, L.L.C.’s 02/23/2026 tariff filing in compliance","issued":"2026-03-16","accession":"20260316-5323","docket":"ER26-1479-000","group":"PJM co-location compliance","filer":"Data Center Coalition","kind":"comments","file":"sources/filings/text/20260316-5323_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260316-5323","tier":"record","sha256":"9f6ac6cfd38aecf1a0eefebc598ce0b8b64666221face26ffcfd010570b6d304","pages":10,"tokens":2461,"emptyPages":[],"textThemes":["colo","flex","study"]},"pages":[{"page":1,"startToken":0,"endToken":209,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \n \nPJM Interconnection, L.L.C.​ ​\n​\n)​\n​\nDocket No. ER26-1479-000 \n​\n​\n​\n​\n​\n​\n)​\n \n \nCOMMENTS OF THE DATA CENTER COALITION \nPursuant to Rule 211 of the Rules of Practice and Procedure of the Federal Energy \nRegulatory Commission’s (“Commission”)1, the Data Center Coalition (“DCC”), respectfully \nsubmits these formal comments in response to PJM Interconnection, L.L.C.’s (“PJM”) February \n23, 2026 tariff filing in compliance (“PJM’s Compliance Filings”) to the Commission's \nDecember 18, 2025 order.2  \nI.​\nIntroduction  \nDCC respectfully submits these comments on PJM’s proposed revisions to the PJM Open \nAccess Transmission Tariff to comply with the Commission’s directives in its Order to Show \nCause to (1) revise its behind-the-meter generation Tariff provisions, (2) establish three new \ntransmission services for Eligible Customers seeking to take service on behalf of Co- Located \nLoad, and (3) revise its necessary studies processes, among other changes. This proceeding arises \nat a pivotal moment for the nation’s energy grid and digital infrastructure, as regional grid \noperators face rising demand, constrained transmission capacity, increased local opposition to \ninfrastructure development, and growing uncertainty around supply adequacy. \n2  PJM Interconnection, L.L.C., 193 FERC   61,217, (2025) (Order to Show Cause). \n1 18 C.F.R. § 385.211 (2025). \n1"},{"page":2,"startToken":209,"endToken":541,"text":"DCC is the membership organization for the U.S. data center industry, representing \nleading data center owners and operators with infrastructure and employees across the country.3 \nDCC member companies are making significant, multi-billion dollar investments in America’s \ninfrastructure. These investments support hundreds of thousands of quality jobs across the nation \nand contribute billions of dollars in local, state, and federal tax revenue, providing consistent \nfunding for important community priorities like public safety, education, and transportation.  \nBetween 2017 and 2023, the data center industry’s total contribution to U.S. GDP was \n$3.5 trillion. In 2023, the U.S. data center industry directly employed more than 600,000 workers \nand supported 4.7 million jobs in total. The sector generated $404 billion in total labor income \nand contributed $162.7 billion in federal, state, and local taxes in 2023.4 \nData centers are foundational to the modern economy and the digital services on which it \ndepends. They support essential services across nearly every sector, including finance, \nhealthcare, education, communications, manufacturing, defense, and government. As the \nbackbone of the nation’s digital infrastructure, data centers host the computing platforms that \npower artificial intelligence and machine learning workloads, cybersecurity systems that protect \ncritical institutions, and data processing capabilities relied upon by federal agencies and national \nsecurity entities. These facilities support real-time digital operations that are now inseparable \nfrom the functioning of core public and private systems. \nIn recent years, energy demand has accelerated—driven by Artificial Intelligence (“AI”) \ndevelopment, cloud computing, electrification of buildings, industry and transportation, \nhydrogen fuel production, and the reshoring of U.S. advanced manufacturing. This has created a \n4 PwC, “Economic Contributions of Data Centers in the United States,” February 2025. \n3 The Data Center Coalition is a membership organization of leading data center owners and operators. Public \ntestimony and written comments submitted by DCC do not necessarily reflect the views of each individual DCC \nmember. A list of current DCC Members is accessible at https://www.datacentercoalition.org/members.  \n2"},{"page":3,"startToken":541,"endToken":812,"text":"step change in electricity needs, particularly in regions like PJM, where demand is outpacing \noutdated planning frameworks. Data center operators are responding with urgency—but face \ngrowing constraints from generator interconnection delays, opaque infrastructure planning, and \nlimited transparency into available capacity. \nIn this context, co-location of load with generation—whether front-of-the-meter or \nbehind-the-meter—is a pragmatic, common, and commercially legitimate strategy to secure \ntimely access to power as markets grapple with years-long interconnection queue backlogs. \nThese arrangements provide critical flexibility and efficiency, enabling data center developers to \nmeet emerging needs on faster timelines and without undue reliance on already-congested grid \ninfrastructure should they pursue this option. \nThe Commission has the opportunity in this proceeding to ensure PJM is complying with \nits Order to Show Cause and ensure co-location arrangements are a viable pathway in the future \nfor large load customers. To assist in that effort, these comments: (1) provide an overview of \nPJM’s Compliance Filing; and (2) point to the unworkable nature of PJM’s compliance filing and \nrecommend solutions.  \nII.​\nPJM’s Compliance Filing \nIn response to the Order to Show Cause, PJM filed revisions to its Tariff addressing \nRetail Behind-the-Meter Generation (BTMG) and transmission service for large loads. The \nproposal establishes a 50 MW materiality threshold for Retail BTMG, under which facilities with \na cumulative nameplate rating of 50 MW or less may qualify for retail netting treatment. PJM \nindicated this threshold aligns with its definition of large load additions and reflects stakeholder \nfeedback. The filing also includes an emergency generation exemption, which excludes on-site \nbackup generators from the BTMG calculation so that facilities such as data centers can maintain \n3"},{"page":4,"startToken":812,"endToken":1059,"text":"diesel or natural gas backup generation for reliability purposes, provided those units are not used \nfor routine retail netting. \nPJM also proposes grandfathering provisions intended to protect existing arrangements. \nFacilities with BTMG capacity exceeding 50 MW may be permanently grandfathered if they \noperate under a contractual arrangement that was in effect before December 18, 2025. In \naddition, the proposal exempts certain Qualifying Facilities that achieved operational status \nbefore that date under the Public Utility Regulatory Policies Act of 1978. PJM stated these \nprovisions are designed to avoid disrupting existing investments while establishing clearer limits \nfor future projects. \nFinally, PJM proposed three new transmission service options for Eligible Customers. \nFirm Contract Demand Transmission Service would allow customers to receive service up to a \ndefined maximum megawatt level. Non-Firm Contract Demand Transmission Service would \nallow co-located loads to withdraw power from the grid on an as-needed and as-available basis. \nPJM also proposed Interim Network Integration Transmission Service (“Interim NITS”), which \nwould allow customers that have requested full Network Integration Transmission Service \n(“NITS”) to begin operations on a non-firm, interruptible basis while transmission upgrades \nnecessary for long-term firm service are constructed. These proposed service options form the \nbasis of DCC’s concerns discussed below. \nIII.​\nDCC Comments  \nCo-location is a commercial arrangement that enables load and generation to be sited \ntogether in ways that facilitate timely power delivery, reduce dependence on constrained \ntransmission systems, and enhance investment certainty. These arrangements involve \nsophisticated engineering, contractual, and regulatory compliance components. When properly \n4"},{"page":5,"startToken":1059,"endToken":1379,"text":"structured, they can preserve and improve overall grid reliability while expanding the set of \nviable options available to new large loads. \nDCC has previously urged the Commission to direct PJM to develop clear, enforceable \ntariff language that affirms the permissibility of multiple co-location configurations, including \nthose where load is served directly from a generation resource located on or near the same site. \nThe Commission did just that with its Order to Show Cause. Tariff clarity is essential to reduce \nunnecessary disputes, avoid case-by-case confusion, and enable transmission providers to \nprocess interconnection and load addition requests efficiently and predictably. The Commission \nprovided clear guidance to PJM on how PJM should implement the Commission’s co-location \norder and facilitate the interconnection of new large loads such as data centers.  \nIn its filing, PJM states it “understands the importance of, and remains committed to, \nadvancing our nation’s leadership in connecting large loads, including supporting the \ndevelopment of Artificial Intelligence (“AI”) infrastructure. PJM continues to work with its \nmembers to support efforts to accelerate the speed and increase the scale with which the United \nStates can build the next generation of AI infrastructure, especially the necessary capacity to \nsupport this load while also ensuring reliability and fair treatment for all users of the grid.” 5 \nHowever, PJM’s proposal falls short of the Commission’s clear directive and the goals \nPJM itself identifies. As a result, the data center industry is left without viable pathways to bring \nsolutions that accelerate the interconnection of critical load and generation and address the \nongoing capacity shortfalls in PJM. FERC’s direction to provide a materiality threshold, which \nPJM set at 50 MW for BTMG, was to coincide with a suite of changes that also included a viable \nand efficient co-location path that is not BTMG. But PJM’s compliance filing leaves several core \noperational questions unanswered. For example, PJM’s proposed Interim NITS will be difficult \n5 PJM’s Compliance Filing at 2. \n5"},{"page":6,"startToken":1379,"endToken":1677,"text":"for customers to rely upon unless several key issues are resolved. As proposed, the framework \nleaves significant uncertainty regarding how the service would operate in practice, including the \ninteraction between Interim NITS and co-located generation arrangements. This uncertainty \ncreates substantial risk for customers considering major infrastructure investments and may \nrender the service largely unusable in its current form.  \na.​ Interim NITS Is Not Workable If Customers Cannot Use Co-Located \nGeneration During Curtailment \nThe proposal leaves unresolved a critical question regarding whether customers receiving \nInterim NITS may take energy from a co-located generator when their network service is \ncurtailed. Interim NITS is intended to provide an incentive for load to bring generation behind \nthe meter in exchange for getting energized more quickly while awaiting for transmission \nupgrades. However, PJM has proposed to prohibit customers from relying on co-located \ngeneration during curtailment events. In its January 23, 2026 Preliminary Proposal, PJM outlined \nits curtailment procedures for Interim NITS. As part of those procedures, PJM stated “[i]f \ncurtailed, EC cannot take energy from co-located generator.”6 This is unworkable because \ncurtailment should limit use of the grid, not prevent the customer from using the co-located \nresource it supplied, which supports Interim NITS in the first place. If the customer cannot use \nthat generation during curtailment, Interim NITS provides no practical value.  \nMaintaining such a limitation would significantly undermine the operational value of \nco-located generation arrangements. If co-located customers are expected to bring new resources \nto market, they should have access to those resources in time of curtailment.   \nFurther, PJM must define the trigger, scope, and sequence of Interim NITS curtailment \nwith respect to the operational limitations identified in the study and should not be able to curtail \n6PJM Staff Preliminary/Working Draft of Concepts as of January 23, 2026.  \n6"},{"page":7,"startToken":1677,"endToken":1967,"text":"load for unrelated broader resource adequacy concerns, particularly where the colocated load has \nbrought sufficient new supply to meet its demand. Curtailment direction unrelated to the result of \nthe NITS studies should be outside the scope of this proceeding.  \nb.​ PJM Must Establish a Defined Process and Timeline for Necessary Studies \nand CIR Review \nIn its filing PJM also provides guidance on interconnection rules for existing generators. \nPJM proposes any existing power plant seeking to serve co-located load must now go through a \nformal Necessary Studies process, reduce its Capacity Interconnection Rights (CIRs) \naccordingly, and execute a new Generation Interconnection Agreement before a single megawatt \nof co-located load can be served. However, clearer interconnection rules for existing generators \nalso require more concrete timelines to review and approve these Necessary Studies and CIR \nrevisions. PJM also needs to account for CIRs going to the specific co-located customer in a \nmanner that doesn't force a generator to reduce more CIRs than necessary, which may happen \nwhen this is done on a 3-year look ahead. Clarity on the timeline for these reviews is needed so \nlarge load customers can plan their investment accordingly.   \nc.​ PJM’s Effective Date Should Be Earlier   \nPJM has proposed an effective date of June 1, 2029 for these new transmission services. \nGiven the immediate need to connect new generation and load in PJM, this presumably means \nthat PJM cannot start studying these innovative solutions for over three years. PJM should work \nwith stakeholders to implement workable solutions in a timely manner that ensures these services \ncan meet the immediate need within the PJM region. As discussed, PJM still has much work \nto-do to refine these services, but the goal should be to implement needed reforms earlier than \n2029.  \n7"},{"page":8,"startToken":1967,"endToken":2247,"text":"d.​ PJM Should Provide Greater Transparency Regarding how Customers Will \nTransition from Interim NITS to NITS \nWhile Interim NITS is intended to function as a temporary solution, the proposal does not \nprovide clear timelines to co-location customers to expect to be transitioned to NITS or how long \ncustomers may be required to rely on the interim framework. Without clear timelines, Interim \nNITS could persist indefinitely, creating regulatory and operational uncertainty for customers \nmaking long-term investments in load and generation resources.  \nIV.​\nConclusion \nDCC appreciates FERC’s leadership and innovation in pushing forward new transmission \nservices in PJM. At this pivotal moment in the global AI race and America’s economic growth, \nFERC has a critical role to play in ensuring these services are not simply theoretical, but can \nactually be implemented in practice in a timely manner. In light of the significant policy and \noperational questions, several issues require further clarification and development. Accordingly, \nthe Commission should require PJM to further clarify and revise its proposal to: (1) confirm that \nan Interim NITS customer may continue to use co-located generation when network service is \ncurtailed; (2) establish a defined process and timeline for Necessary Studies and associated CIR \nrevisions, and to ensure that any CIR reductions are tailored to the co-located service actually \nbeing provided; (4) PJM should endeavor to implement needed reforms in a timely manner; and \n(5) provide greater transparency regarding how customers will transition from Interim NITS to \nfull NITS. These matters, as well as additional concerns that may arise through stakeholder \nengagement, should be more fully addressed by PJM to ensure that the resulting framework is \nworkable and provides sufficient certainty for customers considering major infrastructure \ninvestments. \n8"},{"page":9,"startToken":2247,"endToken":2396,"text":"DCC looks forward to actively participating in the paper hearing proceeding and \ncontributing to the development of a comprehensive record on these issues. Given the \nconsequential nature of these issues and the scale of investments that will be affected, the \nCommission should take the time to get the framework right. A thoughtful and well-developed \nrecord will help ensure that any resulting policies provide regulatory certainty while maintaining \nthe reliability and integrity of the regional transmission system. \nRespectfully submitted, \n/s/ Aaron Tinjum \nAaron Tinjum \nVice President, Energy \nData Center Coalition \n1250 H Street, NW, Suite 880 \nWashington, DC, 20005 \naaron@datacentercoalition.org \n \n/s/ Cy McNeill \nCy McNeill \nSenior Director, Federal Affairs \nData Center Coalition \n1250 H Street, NW, Suite 880 \nWashington, DC, 20005 \ncy@datacentercoalition.org \n \n/s/ Lucas Fykes \nLucas Fykes \nSenior Director, Energy Policy  \n& Regulatory Counsel \n1250 H Street, NW, Suite 880 \nWashington, DC, 20005 \nlucas@datacentercoalition.org \n \n \n \n \n9"},{"page":10,"startToken":2396,"endToken":2461,"text":"CERTIFICATE OF SERVICE \n​\nI hereby certify that I have this day served the foregoing document upon each person \ndesignated on the official service list compiled by the Secretary in this proceeding. Dated at \nWashington, DC this 16th day of March 2026. \n \n/s/ Lucas Fykes \nLucas Fykes \nSenior Director, Energy Policy  \n& Regulatory Counsel \n1250 H Street, NW, Suite 880 \nWashington, DC, 20005 \nlucas@datacentercoalition.org \n \n \n \n \n \n \n \n \n \n \n \n \n \n \n \n \n \n \n \n \n \n \n \n \n \n \n \n \n \n10"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":1,"endAt":587,"startToken":0,"endToken":82},{"p":1,"at":587,"title":"Introduction","method":"printed heading","endPage":8,"endAt":562,"startToken":82,"endToken":2048},{"p":8,"at":562,"title":"Conclusion","method":"printed heading","endPage":10,"endAt":0,"startToken":2048,"endToken":2396},{"p":10,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":10,"endAt":484,"startToken":2396,"endToken":2461}]}