{"document":{"slug":"rec-20260316-5327","title":"Protest of Vistra Corp. to PJM Interconnection, L.L.C.'s 02/23/2026 compliance filing","issued":"2026-03-16","accession":"20260316-5327","docket":"ER26-1479-000","group":"PJM co-location compliance","filer":"Vistra Corp.","kind":"protest","file":"sources/filings/text/20260316-5327_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260316-5327","tier":"record","sha256":"9ebe34cc313d4cf112b5ab6b06283750fe1db467b2d880f3131e74d14e7e4fc7","pages":21,"tokens":7183,"emptyPages":[],"textThemes":["colo","study","adequacy","flex"]},"pages":[{"page":1,"startToken":0,"endToken":264,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \n \n \nPJM Interconnection, L.LC. \n \n) \n) \n) \n) \n) \n \nDocket No. ER26-1479-000 \n \nPROTEST OF VISTRA CORP. \n \nPursuant to Rule 211 of the Rules of Practice and Procedure of the Federal Energy \nRegulatory Commission (“Commission”),1 Vistra Corp. (“Vistra”) hereby submits this protest to \nPJM Interconnection, L.L.C.’s (“PJM”) compliance filing filed on February 23, 2026, in the above-\ncaptioned docket.2  On December 18, 2025, this Commission issued a landmark Order on Show \nCause Proceedings,3 which established a clear and principled roadmap for the development of co-\nlocated facilities in PJM in a manner that ensures both the reliability and affordability of the PJM \nsystem.  The Commission’s order clearly delineated a path for enabling the expeditious \ndevelopment and interconnection of co-located facilities.  This action was a critical step toward \nfacilitating the development of digital infrastructure in PJM—the single most important region of \nthe country for data centers and the other infrastructure necessary to develop and maintain our \nworld-leading artificial intelligence capabilities.   \nAccepting PJM’s compliance filing would be a step backward from the progress made in that \norder.  Where the Commission required clarity, PJM has proposed ambiguity by failing to propose \n \n1 18 C.F.R. § 385.211 (2026). \n2 PJM Interconnection, L.L.C., 60-Day Compliance Filing for Co-Located Load Related Revisions to Open \nAccess Transmission Tariff to Comply with Commission Order in Docket No. EL25-49, et al., Docket No. ER26-\n1479-000 (filed Feb. 23, 2026) (“PJM Compliance Filing”). \n3 PJM Interconnection, L.L.C., 193 FERC ¶ 61,217 (2025) (“Order on Show Cause Proceedings”)."},{"page":2,"startToken":264,"endToken":579,"text":"- 2 - \na clear transition mechanism to apply to the facilities that have diligently pursued and, in some \ncases, completed, the necessary study process.  Similarly, where the Commission mandated speed, \nPJM has chosen delay, by proposing a June 1, 2029 effective date for the new transmission services \nand a revised necessary study process that would appear to not even begin until 2029—a lifetime \nwhen it comes to digital infrastructure.  Collectively, these two elements, unless changed, could \ndelay integration of co-location configurations until the early 2030s.  And where the Commission \nrequired pragmatism, PJM has responded with a truly byzantine proposal for Capacity \nInterconnection Rights (“CIRs”) that is clear as mud and appears likely to limit backup resources’ \nability to support resource adequacy where they can.  To realize the potential of the December \nOrder, the Commission should direct PJM to file a further compliance that resolves these \nfundamental flaws, as discussed further below.   \nI. \nPJM Has Not Demonstrated That the Proposed Revisions to the Necessary Study \nProcess Are Just and Reasonable  \nIn its Order on Show Cause Proceedings, the Commission found the PJM tariff is unjust \nand unreasonable because it lacks sufficient clarity and consistency regarding how interconnection \ncustomers can serve co-located load using existing generating facilities.4  As a remedy, the \nCommission directed PJM to clarify that the necessary study process can facilitate the addition of \nco-located load behind the meter of an existing generating facility, and to propose tariff revisions \nto more clearly describe that process and the scope of the analysis PJM performs in such instances.5  \nPJM’s tariff revisions therefore must provide sufficient clarity and transparency on the steps \n \n4 Order on Show Cause Proceedings, 193 FERC ¶ 61,217 at P 225.  \n5 Id. PP 226-27.  The Commission directed PJM to describe the information that the interconnection customer \nmust provide about the co-located load for purposes of the necessary study.  Id. P 227."},{"page":3,"startToken":579,"endToken":807,"text":"- 3 - \nneeded for an existing generator to serve co-located load to remedy the unjust and unreasonable \nambiguity in PJM’s tariff.6   \nPJM’s proposal falls well short of providing the clarity necessary to remedy PJM’s tariff \nin several respects.  Specifically, PJM’s proposal does not:  (a) contain a transition mechanism or \notherwise address necessary studies that are already in progress or completed; (b) specify how \nPJM will calculate and study changes to CIRs; or (c) explain why existing customers with older \ninterconnection agreements must sign an entirely new version of interconnection agreement before \nserving co-located load.  Rather than adding clarity, PJM’s proposal introduces new sources of \nambiguity that will cause additional delays and further hinder efforts to add co-located load and \npower digital infrastructure in PJM.   \nA. \nPJM’s Proposal Fails to Include a Transition Mechanism for Customers \nAlready in the Necessary Study Process   \n \nAlthough some existing generators have worked diligently to pursue co-location \narrangements with large load customers via PJM’s existing necessary study process, PJM’s \nproposal would ignore those efforts altogether and press reset on significant commercial \nopportunities for large load customers.  Indeed, PJM’s proposal does not acknowledge that some \nexisting generators have already executed necessary study agreements and even received study \nresults, much less address whether and how the proposed tariff revisions apply to such customers.  \n \n6 Order on Show Cause Proceedings, 193 FERC ¶ 61,217 at P 229."},{"page":4,"startToken":807,"endToken":1211,"text":"- 4 - \nThis is a critical issue in this proceeding, given the Commission’s emphasis on facilitating speed \nto power,7 and PJM’s replacement rate must directly address that issue to pass muster.8  \nWithout any clear transition mechanism, PJM’s proposal could be read to require parties \nthat have completed the necessary study process to restart that process entirely.  In this way, PJM’s \nproposal will create further delays for parties that have already sought to pursue co-location \narrangements because those parties will have no way to preserve in-progress or completed \nnecessary studies.  Such delays are not only unnecessary but simply incompatible with the nation’s \nurgent need for computing power.  That result is also incompatible with the Commission’s Order \non Show Cause Proceedings, which indicated that this compliance filing should memorialize \nPJM’s existing approach to necessary studies, but that any “enhance[ment]” to the necessary study \nprocess should occur in a future section 205 filing.9  There should be no need for parties that are \nalready in the necessary study process to start over if the tariff revisions at issue here are limited \nto complying with the Commission’s directives.  Furthermore, requiring generators with executed \nnecessary study agreements to restart the process violates the rights of those existing generators \nthat relied on the existing rules to pursue facility modifications for co-location opportunities.10   \n \nFurther, by failing to provide a transition mechanism, PJM’s proposal represents an \nunexplained and unjustified departure from the Commission’s customary approach to \n \n7 See Order on Show Cause Proceedings, 193 FERC ¶ 61,217 at P 200 (acknowledging that co-location \narrangements can allow existing generating facilities to begin serving new large co-located loads rapidly and directing \nPJM to create a new interim, non-firm transmission service to facilitate more rapid interconnection and operation of \nco-located loads); see also id. (Rosner, Comm’r, concurring at P 11) (discussing how the new interim transmission \nservice leverages speed). \n8 See Affirmed Energy, LLC v. FERC, 166 F.4th 1070,1079 (D.C. Cir. 2026) (“An agency’s decision is arbitrary \nand capricious if the agency entirely fails to consider an important aspect of the problem before it or ignores the \nreasonable reliance interests of regulated parties.”). \n9 Order on Show Cause Proceedings, 193 FERC ¶ 61,217 at P 227. \n10 PJM Power Providers Grp. v. FERC, 96 F.4th 390, 400 (3d Cir. 2024) (“P3”) (explaining that the Commission \nmay not take actions that alter the legal consequences attached to past actions)."},{"page":5,"startToken":1211,"endToken":1615,"text":"- 5 - \ninterconnection reforms, in which the Commission regularly requires transition mechanisms to \navoid disruption and stranded capital investments.  Most recently, in Order No. 2023, the \nCommission required transmission providers to (i) tender an interconnection agreement to any \ncustomer that had received a final facilities study report before commencing transitional studies, 11 \nand (ii) allow late-stage interconnection customers that had already been tendered a facilities study \nagreement to opt to continue under a serial study process.12  The Commission explained that doing \nso appropriately respected the investments and expectations of interconnection customers at an \nadvanced stage in the existing process.13  And the Commission has consistently employed these \ntypes of transition mechanisms since it first created the standardized interconnection procedures \nin Order No. 2003, where the Commission allowed interconnection customers with executed study \nagreements to choose to continue under those existing processes or transition processes.14   \nGiven the Commission’s longstanding approach to interconnection reform, PJM’s \ncompliance proposal is flawed.  PJM does not justify its failure to include a transition mechanism, \nlet alone acknowledge that there are generators with executed necessary study agreements on file \nwith the Commission.  Thus, PJM has not provided the Commission with the justification it would \nneed to accept PJM’s proposal and depart from precedent requiring a transition mechanism for \n \n11  Improvements to Generator Interconnection Procs. & Agreements, Order No. 2023, 184 FERC ¶ 61,054, at \nP 865, order on reh’g, 185 FERC ¶ 61,063 (2023), order on reh’g, Order No. 2023-A, 186 FERC ¶ 61,199, errata \nnotice, 188 FERC ¶ 61,134 (2024)). \n12 Order No. 2023, 184 FERC ¶ 61,054 at PP 855, 865. \n13 Id. P 856. \n14 Standardization of Generator Interconnection Agreements & Procs., Order No. 2003, 104 FERC ¶ 61,103, at \nP 186 (2003), order on reh’g, Order No. 2003-A, 106 FERC ¶ 61,220, order on reh’g, Order No. 2003-B, 109 FERC \n¶ 61,287 (2004), order on reh’g, Order No. 2003-C, 111 FERC ¶ 61,401 (2005), aff’d sub nom. Nat’l Ass’n of Regul. \nUtil. Comm’rs v. FERC, 475 F.3d 1277 (D.C. Cir. 2007); see also Midcontinent Indep. Sys. Operator, 164 FERC ¶ \n61,234, at P 21 (2018); Midcontinent Indep. Sys. Operator, 158 FERC ¶ 61,003, at PP 45, 59 (2017); Midcontinent \nIndep. Sys. Operator, 166 FERC ¶ 61,187, at P 107 (2019); Sw. Power Pool, Inc., 167 FERC ¶ 61,275, at PP 19, 39 \n(2019); PJM Interconnection, L.L.C., 181 FERC ¶ 61,162, at P 60 (2022)."},{"page":6,"startToken":1615,"endToken":2287,"text":"- 6 - \ninterconnection reforms.15  And by failing to include a transition mechanism that respects executed \nnecessary study agreements on file with the Commission, PJM’s proposal appears to render those \nfiled agreements a nullity, in violation of the filed rate doctrine.16   \nRequiring generators with executed necessary study agreements on file with the \nCommission to restart the entire process would undermine the central goal of this proceeding:  to \nexpeditiously facilitate the co-location of generation and load in PJM.17  And the delay caused by \nrequiring generators to restart the necessary study process is further compounded by the fact that \nPJM is seeking a June 1, 2029 effective date for the new transmission services, and will seek a \ncorresponding effective date for the revisions at issue in this proceeding.18  As Vistra will describe \n \n15 See F.C.C. v. Fox Television Stations, Inc., 556 U.S. 502, 515 (2009) (“An agency may not . . . depart from a \nprior policy sub silentio or simply disregard rules that are still on the books. And of course the agency must show that \nthere are good reasons for the new policy.” (citations omitted)).  In the Order on Show Cause Proceedings, the \nCommission indicated that PJM should formalize and clarify its existing necessary study process rather than make \nsubstantive changes.  See Order on Show Cause Proceedings, 193 FERC ¶ 61,217 at P 227.  To the extent PJM is \nseeking to make wholesale substantive changes to the necessary study process, such as by requiring generators that \nhave already completed the process to start the process again, it must propose such changes in a future section 205 \nproceeding rather than in this docket.  See id. (“To the extent that PJM seeks to enhance the necessary study process . \n. . PJM may submit such enhancements in an FPA section 205 filing.”). \n16 The filed rate doctrine “bind[s] regulated entities to charge only the rates filed with FERC and to change their \nrates only prospectively.”  Okla. Gas & Elec. Co. v. FERC, 11 F.4th 821, 829 (D.C. Cir. 2021).  It applies not just to \nrates, but also to matters directly affecting rates.  P3, 96 F.4th at 394.  Existing necessary study agreements on file \nwith the Commission are filed rates for purposes of the filed rate doctrine, and those agreements state that their terms \ncannot be changed without the consent of the parties.  See, e.g., PJM SA No. 7476, Necessary Studies Agreement \nbetween PJM and LSP Digital (0.0.0), § 21 (“This Agreement, or any part thereof, may not be amended, modified, or \nwaived other than by a writing signed by all Parties.”).  Were PJM to require parties with existing necessary study \nagreements to enter new agreements, this would impermissibly alter the legal consequences that attached when those \nparties initially filed executed necessary agreements with the Commission.  See P3, 96 F.4th at 394.  And nullifying \nnecessary study agreements would be patently unfair, as parties that have already paid for necessary studies would \nhave to pay a second time for the same studies. \n17  Order on Show Cause Proceedings, 193 FERC ¶ 61,217 at P 200 (“[T]o facilitate more rapid interconnection \nand operation of Co-Located Loads . . . .  [W]e direct PJM to submit, within 60 days of the date of issuance of this \norder, a compliance filing to create a new interim, non-firm transmission.”)); Order on Show Cause Proceedings, 193 \nFERC ¶ 61,217 (Chang, Comm’r concurring at P 3) (explaining that the “order represents the first step to developing \na package of solutions to address co-location in the PJM footprint” and that the Commission “will assess how [the] \nrates, terms, and conditions facilitate the efficient interconnection of co-located loads”). \n18 PJM Interconnection, L.L.C., Initial Brief of PJM Interconnection, L.L.C., Docket Nos. EL25-49-000 et. al, at \n79 (filed Feb. 23, 2026) (“PJM Paper Hearing Initial Brief”).  In this proceeding, PJM proposed a 12/31/9998 effective \ndate, which it indicated it will update to align with the effective date set in the paper hearing.  PJM Compliance Filing \nat 35."},{"page":7,"startToken":2287,"endToken":2681,"text":"- 7 - \nfurther in its paper hearing brief, PJM has not shown that this lengthy delay is just and reasonable.  \nPJM’s attempts to defend that delay based on its capacity market schedule and the need for \nsoftware updates are unpersuasive.  First, the 3-year forward capacity market schedule cannot \njustify a delay in the provision of non-firm, non-capacity backed transmission products.  The \ncapacity market schedule should not delay the provision of firm transmission products either, for \nthat matter, given that the forecasts used in the 2027/2028 and 2028/2029 BRAs included the new \nlarge loads that are likely to come online in that timeframe.19  Second, PJM has not explained why \nit will take until 2029 to update its software to accommodate the new curtailment logic—or why \nit cannot provide a transition process in the meantime to serve customers that agree to not pull \nenergy from the grid and therefore will not need to be curtailed.  \nCompounding the delay, PJM indicated that it will seek a corresponding effective date for \nthe tariff revisions in this proceeding,20 meaning that PJM’s new necessary study procedures and \nnew pro forma necessary study agreement would not be effective until halfway through 2029.  \nThat means that customers may need to wait until 2029 to even submit a request to begin the new \nnecessary study process.  Moreover, the pro forma necessary study agreement sets forth a study \ntimeline of 270 days, with no consequences for study delays.21  In other words, between the study \nprocess itself and the construction of any necessary network upgrades, it is likely that no existing \n \n19 PJM determines how much capacity to procure based on a forecast of future demand, which includes an \nadjustment that specifically accounts for new large loads like data centers.  PJM, Load Forecast Development Process, \nForecast & Reports, Long-Term Load Forecast Tables, at B-9b (Feb. 6, 2026), https://www.pjm.com/-\n/media/DotCom/planning/res-adeq/load-forecast/2026-load-report-tables.xlsx (showing load adjustments to 2026 \nload forecast resulting from large load growth in transmission owner territories); see also PJM, 2026 PJM Load  \nForecast Report, at 5 (Jan. 14, 2026), https://www.pjm.com/-/media/DotCom/library/reports-notices/load-\nforecast/2026-load-report.pdf.   \n20 PJM Compliance Filing at 35. \n21 Id., Attach. A (Revisions to the PJM Open Access Transmission Tariff) at Part IX, Subpart G (Form of \nNecessary Studies Agreement), § 5 (“Proposed Tariff Revisions”)."},{"page":8,"startToken":2681,"endToken":3005,"text":"- 8 - \ngenerator could add co-located load under PJM’s proposed process until 2030 or 2031.  PJM’s \nproposal is, in effect, a 3- to 5-year moratorium on co-locating large loads with existing generators.  \nThat kind of delay in powering digital infrastructure—via the service option (i.e., co-location) that \nwill bring speed-to-power faster than any other—is both unnecessary and directly contrary to the \nAdministration’s efforts to ensure that the nation “has the power needed to win the global artificial \nintelligence [] race while continuing to meet growing demand for affordable, reliable and secure \nenergy.”22 \nB. \nPJM Has Not Demonstrated That Its Proposal for Delisting CIRs Is Just, \nReasonable, and Not Unduly Discriminatory, or That It Is Consistent with the \nCommission’s Compliance Directives  \nIn the Order on Show Cause Proceedings, the Commission explained that “an existing \ngenerating facility may not begin serving Co-Located Load that is not Network Load until it has \ndelisted its CIRs for the portion of the generating facility to be designated to serve any Co-Located \nLoad that is not receiving NITS.”23  The Commission also directed PJM to propose tariff revisions \nto clarify how the necessary study process works, including with regards to CIR reductions.24   \nWhile PJM claims that its proposed tariff revisions “promote clarity” by memorializing \nthis directive,25 PJM’s proposed language, in fact, perpetuates the very ambiguity that the \nCommission found renders the tariff unjust and unreasonable.26  PJM would require existing \ngenerators that seek to add co-located load to submit to PJM “the amount of reduction to Capacity \n \n22 Press Release, Dep’t of Energy, Energy Department Launches Speed to Power Initiative, Accelerating Large-\nScale Grid Infrastructure Projects (Sept. 18, 2025), https://www.energy.gov/articles/energy-department-launches-\nspeed-power-initiative-accelerating-large-scale-grid.  \n23 Order on Show Cause Proceedings, 193 FERC ¶ 61,217 at P 230 (emphasis added). \n24 Id. P 226. \n25 PJM Compliance Filing at 26 n.83. \n26 See Order on Show Cause Proceedings, 193 FERC ¶ 61,217 at P 175."},{"page":9,"startToken":3005,"endToken":3483,"text":"- 9 - \nInterconnection Rights to facilitate the Co-Located Load configuration.”27  PJM’s necessary study \nwill then “assess the impact of the reduction in Capacity Interconnection Rights.”28  But PJM does \nnot explain how a generator should calculate the amount of the reduction of its CIRs, nor does it \nclarify how PJM will assess the impact of that reduction.  Without these critical details, PJM’s \ntariff remains ambiguous—the exact issue the Commission sought to remedy in this proceeding.      \n1. \nPJM’s Proposal Is Impermissibly Vague Regarding How to Calculate \nCIR Reductions and Could Be Interpreted in an Unduly \nDiscriminatory Manner  \nPJM has failed to address the Commission’s directive to “clarify its interconnection \nprocedures and agreements to ensure that it is clear to both new and existing Interconnection \nCustomers how to interconnect in a Co-Location Arrangement.”29  Instead, PJM’s proposal would \nrequire existing generators to provide PJM with “the amount of reduction to Capacity \nInterconnection Rights to facilitate the Co-Located Load configuration,” a mandate that is \ninappropriately vague and could potentially be read to sweep far too broadly.30  Concerningly, \nPJM’s revisions could be read to require generators to include in their CIR reduction calculation \nany portion of a facility that will ever provide power to a co-located load.  That would mean that \n \n27 Proposed Tariff Revisions at Part VIII, Subpart A, section 401 (Applications for Cyle Process), § H(3)(b)(i)(c).  \nPJM identifies the language memorializing the Commission’s directive as located in “proposed revisions to Tariff, \nPart VII, Subpart A, section 401.H.3.a – b.”  PJM Compliance Filing at 26 n.83.  PJM’s proposed revisions do not \ninclude changes to Part VII of the tariff.  We assume PJM intended to reference Part VIII, but if that is the case, PJM \nmust clarify as much in a future filing.   \n28 Proposed Tariff Revisions at Part VIII, Subpart A, section 401 (Applications for Cyle Process), §  H(3)(b)(ii). \n29 Order on Show Cause Proceedings, 193 FERC ¶ 61,217 at P 161 (emphasis added).  PJM’s Paper Hearing \nInitial Brief attaches illustrative tariff language that states, “[t]he Eligible Customer must designate the individual Co-\nLocated Generating Facility that will serve the individual Co-Located Load . . . and provide the megawatt level of \nenergy from the Co-Located Generating Facility dedicated to serving the Co-Located Load.”  PJM Paper Hearing \nInitial Brief, Attach. A, Illustrative Language for New Tariff, Part XI, Subpart B, section 711.1.  PJM does not mention \nthe illustrative language in this proceeding, but even if PJM intended for the illustrative language to guide calculation \nof the CIR reductions, which is something PJM has not indicated, it would not cure the ambiguity in PJM’s proposed \nrevisions because the language does not explain what it means to be “dedicated to serv[e]” co-located load.   \n30 Proposed Tariff Revisions at Part VIII, Subpart A, section 401 (Applications for Cyle Process), § H(3)(b)(i)(c)."},{"page":10,"startToken":3483,"endToken":3838,"text":"- 10 - \na two-unit generator using one 50 MW unit to serve co-located load and one 50 MW unit to serve \nthe grid while providing occasional, interruptible backup service to the co-located load would need \nto delist 100 MWs of CIRs.  In other words, PJM’s proposal could potentially treat this two-unit \nconfiguration the same as a generator that serves 100 MW of co-located load, despite the fact that \neach configuration provides different amounts of capacity to the grid.  And if read in that manner, \nPJM’s proposal could require generators to delist more CIRs than those associated with the \n“portion” of the facility that is actually dedicated to providing firm service to a co-located load.   \nClarity is needed to ensure that the tariff language is not read in such a broad manner.  A \nbroad reading that would require units that provide only occasional, interruptible energy to co-\nlocated load to delist their CIRs would deprive ratepayers of generation that is generally available \nto serve the grid when needed and risk unnecessarily increasing capacity prices.  Allowing \nsecondary units providing occasional, interruptible service to co-located load to retain their CIRs \nwould also be consistent with other requirements in the PJM tariff.  PJM’s capacity market must-\noffer rules excuse generators with a “financially and physically firm commitment to an external \nsale of [their] capacity” from the obligation to offer capacity into PJM’s market. 31  No such \nexception applies for generators with a non-firm commitment to sell outside of PJM.  By \ndistinguishing between firm and non-firm sales, PJM’s tariff recognizes that firm energy sales pose \nunique concerns for capacity market commitments, while generators providing non-firm energy \nsales can be expected to perform in the capacity market.  The same distinction applies to generators \nthat serve co-located loads: primary units that provide firm energy to a co-located load clearly \n \n31 PJM Interconnection L.L.C., Open Access Transmission Tariff, Attach. DD.6, § 6.6 (Offer Requirement for \nCapacity Resources) (3.0.0), §§ 6.6 (a), (g); see also PJM Interconnection L.L.C., Constellation Request for \nClarification or, in the Alternative, Rehearing, Docket Nos. EL25-49-000 et. al, at 4 (filed Jan. 20, 2026)."},{"page":11,"startToken":3838,"endToken":4183,"text":"- 11 - \ncannot also provide capacity, but secondary units that provide only occasional, interruptible energy \nto co-located load can.   \nIt would also be unduly discriminatory to require secondary units that occasionally serve \nco-located load on an interruptible basis to delist their CIRs.  As PJM recently explained, it allows \ngenerators that export energy outside of PJM on a non-firm or recallable basis to function as \ncapacity resources.32  Those resources must still comply with their capacity obligations, including \nthe requirement to bid into the day-ahead market.33  But where the generator is not committed in \nthe day-ahead market, they are not required to “sit idle.”34  Interruptible backup units in a co-\nlocated configuration should receive the same treatment.  As Vistra has previously explained, \nsecondary units that occasionally provide interruptible back-up service to a co-located load can \nfulfill capacity obligations and be expected to perform when needed.35  Indeed, there are \ncommercial arrangements and associated energy offer rules that would allow such units to both be \navailable to serve the grid during emergency conditions, while also serving as a back-up to the co-\nlocated load.  There is no principled basis to treat an interruptible backup unit in a co-located \nconfiguration differently from recallable exports.  But PJM’s proposal for calculating CIR \nreductions could do just that, if read too broadly.  The Commission should reject vague tariff \n \n32 See PJM Interconnection, L.L.C., Mot. For Leave to Answer and Answer of PJM Interconnection, L.L.C., \nDocket No. EL25-49-000, at 6 (filed March 9, 2026). \n33 Id. \n34 Id. (citing PJM Interconnection, L.L.C., 139 FERC ¶ 61,057, at P 205 (2012)). \n35 As Vistra has further explained, secondary backup units are more suited to capacity market participation than \nthe reliability must-run resources that the Commission recently approved to participate on the basis that they “can be \nreasonably expected to perform.”   PJM Interconnection L.L.C., Comments of Vistra Corp., Docket No. EL25-49-\n000, at 30-31 (filed Apr. 23, 2025) (“2025 Vistra Comments”) (citing PJM Interconnection, L.L.C., 190 FERC ¶ \n61,088, at P 47 (2025))."},{"page":12,"startToken":4183,"endToken":4491,"text":"- 12 - \nlanguage that could be read in an unduly discriminatory manner and could artificially restrict \ncapacity in PJM.  \nFinally, as a matter of policy, there is simply no reason to ignore the valuable contribution \nof back-up units that only occasionally serve co-located load, as capacity resources that help the \nregion achieve its resource adequacy needs.  Ignoring those MWs will force PJM to procure \nadditional MWs that truly are not needed and will ultimately add significant costs for ratepayers.  \n2. \nPJM Does Not Explain How It Will Study the Impact of a Reduction \nin CIRs \nPJM’s necessary study process aims to “determine whether a planned modification . . . will \nhave a permanent material impact on the Transmission System.”36  While some of PJM’s proposed \nrevisions are consistent with that aim, PJM’s proposal also indicates that PJM will “assess the \nimpact of the reduction in CIRs associated with the Co-Located Load and Co-Located Load \nGenerating Facility,”37 which could be interpreted to expand the scope of the necessary study \nprocess beyond what it is designed to consider.  By failing to explain how it will “assess the impact \nof the reduction of CIRs,” PJM appears to provide itself discretion to improperly shoehorn resource \nadequacy considerations into the necessary study process.  Vistra does not believe it is PJM’s intent \nto incorporate a resource adequacy assessment into its necessary study process, as such would be \nboth inconsistent with its long-standing practice for conducting such studies, and FERC’s \nDecember Order.  But PJM’s filing has introduced unnecessary ambiguity, and clarity is needed.   \n \nStudying resource adequacy in the necessary study process would be inconsistent with the \npurpose of the necessary study process, which is designed to evaluate the impacts of a change to \n \n36 PJM Compliance Filing at 27 n.87.  \n37 Proposed Tariff Revisions at Part VIII, Subpart A, section 401 (Applications for Cyle Process), § H(3)."},{"page":13,"startToken":4491,"endToken":4903,"text":"- 13 - \nan interconnection on the transmission system.  Its goal is to address engineering concerns and \nidentify transmission network upgrades needed to accommodate the modification, not address \nPJM-wide policy issues beyond the scope of interconnection service.  And it is unclear how PJM \nwould have the authority to consider resource adequacy issues in the necessary study process given \nthat PJM cannot require a generator to sell its capacity into PJM’s market.38   \nIt would also be unduly discriminatory to consider resource adequacy in the necessary \nstudy process for existing generators that are required to delist CIRs but not for other similarly \nsituated interconnection customers, because resource adequacy considerations associated with \nlarge load interconnection are not unique to co-location.39   For example, a retiring generator would \nhave the same impact on capacity prices as a generator that delists CIRs to serve co-located load \nbecause the capacity market would incorporate either change as a shift in the supply curve.  \nSimilarly, a new large load seeking to co-locate would have a similar (but lower) capacity price \nimpact as a new large load seeking to connect in front-of-the-meter.40  In both cases, the retiring \ngenerator and front-of-the-meter large load would impact capacity prices in a manner similar to a \ngenerator seeking to co-located as load, such that these entities are all similarly situated with \nrespect to their impact on the capacity market.41  It would therefore be unduly discriminatory to \n \n38 See PJM Interconnection, L.L.C., 178 FERC ¶ 61,121, at P 97 (2022) (“If a seller deems PJM’s capacity market \nrules undesirable, it can elect to pursue selling its capacity through other avenues, including via bilateral contracts \nwithin PJM, external sales outside of PJM, and other arrangements.”). \n39 PJM Interconnection, L.L.C., 190 FERC ¶ 61,115, at P 85 (2025) (“Show Cause Order”); see also 2025 Vistra \nComments, Attach. A, Affidavit of Dr. Roy J. Shanker, PhD, at 21 (“2025 Shanker Affidavit”) (“Without reason, \nmany people assume that if there were no co-location, the co-located load would not exist.  There is no reason to make \nthis assumption.”).  \n40 2025 Shanker Affidavit at 34. \n41 See N.Y. Indep. Sys. Operator, 162 FERC ¶ 61,124, at P 10 (2018) (“To say that entities are similarly situated \ndoes not mean that there are no differences between them; rather, it means that there are no differences that are material \nto the inquiry at hand.”).  In fact, the front-of-the-meter load would have a larger impact on capacity prices because"},{"page":14,"startToken":4903,"endToken":5277,"text":"- 14 - \nconsider resource adequacy only for the interconnection of co-located load and not for these other \nscenarios that have a similar (or more significant) impact on capacity prices.  \nC. PJM Has Not Justified the Requirement to Update Old Generator \nInterconnection Agreements or Explained How the Requirement Will Work in \nPractice \nOther aspects of PJM’s proposal appear to be entirely unresponsive to the Commission’s \ncompliance directives, would inject further ambiguity into the tariff, and could slow down the \nnecessary study process and the integration of new large loads.   \nAs a threshold matter, while PJM states that the proposed revisions to the necessary process \nare “intended to apply uniformly to all existing customers,”42 it is unclear whether that would be \ntrue in practice.  This is because PJM proposes to place the necessary study revisions in Part VIII \nof the tariff, which by its plain terms applies only to generating facilities that submitted new service \nrequests on or after October 1, 2021.43  Needless to say, to the extent that generators that began \nthe interconnection process before October 1, 2021 cannot use the necessary process described in \n \nPJM would accommodate the co-located load by shifting its supply curve by the size of the reduction in CIRs, while \nPJM would accommodate the front-of-the-meter load by shifting its demand curve by the size of the additional demand \nplus its planning reserve margin.  See 2025 Shanker Affidavit at 29-30, 34.  Nevertheless, PJM does not study the \nresource adequacy impacts of front-of-the-meter large load additions. \n42 PJM Compliance Filing at 24-25 (“These proposed revisions are intended to uniformly to all existing customers \nregardless of whether they have presently effective interconnection agreements issued pursuant to Parts IV, VI, VII, \nor VIII of the Tariff.”). \n43 PJM Interconnection, L.L.C., Open Access Transmission Tariff, Part VIII, Subpart A, section 401 (Applications \nfor Cycle Process Introduction) (2.0.0).  PJM’s proposed changes to the necessary study process are included under \nPart VIII, section 401(H), which states that “[i]n connection with interconnection with the Transmission System \npursuant to Tariff, Part VIII, Project Developer may be required, or may elect, to enter into one or more of the \nfollowing interconnection-related agreements,” including the necessary study agreement.  Id., section 404(H)  \n(emphasis added)."},{"page":15,"startToken":5277,"endToken":5714,"text":"- 15 - \nthis filing, then the proposal would be unduly discriminatory and inconsistent with the \nCommission’s directives.44   \n \nIn a similar vein, PJM also fails to justify its proposal to require generation developers with \nolder interconnection agreements—i.e., interconnection agreements for executed by generators \nthat initiated PJM’s interconnection process before October 1, 2021—to instead enter the new pro \nforma GIA housed in Part IX of the tariff.45  It is not clear whether PJM’s proposal would require \nthat such interconnection customers enter into new GIAs before they could initiate the necessary \nstudy process or whether PJM would require them to enter new GIAs after the necessary study \nprocess.46  In any event, under PJM’s proposal, it appears that generation owners with older forms \nof interconnection agreements would be unable to simply modify their existing interconnection \nagreement to serve co-located loads and would instead need to obtain an entirely new form of \ninterconnection agreement.  PJM fails to demonstrate how its proposal is consistent with the \nCommission’s directive to create a process for modifying existing agreements for interconnection \ncustomers seeking to serve co-located loads.47  \n \n44 Under PJM’s proposal, generation facilities the initiated the PJM interconnection process after October 1, 2021 \nwould need to follow a process for amending their GIAs to serve co-located load that is different from the process \nfollowed by generators that initiated the PJM interconnection process prior to October 1, 2021.  But there is no material \ndifference to justify that selective treatment.  \n45 PJM Compliance Filing at 25; Proposed Tariff Revisions at Part III (General).  PJM states that “[i]f there is an \nExisting Interconnection Customer that desires to serve Co-Located Load with a Service Agreement issued pursuant \nto Tariff, Parts IV and VI, proposed revisions to Part III of the Tariff will require such customers to begin the process \nof amending such service agreements by following the tariffed necessary study process in Part VIII.”  PJM Compliance \nFiling at 25.  But PJM does not explain how such interconnection customers can begin the necessary study process in \nPart VIII. \n46 To the extent PJM intends to impose this requirement at the beginning of the necessary study process, it has \nnot explained how generators can obtain the new form of GIA.  It may be that PJM’s intent is purely formalistic, such \nthat when it amends an interconnection agreement (ISA or GIA) after the necessary study process, it will merely \nupdate the interconnection customer’s GIA to a more recent version of PJM’s GIA.  If this is what PJM intends, it \nmust say so clearly. \n47 Order on Show Cause Proceedings, 193 FERC ¶ 61,217 at P 226."},{"page":16,"startToken":5714,"endToken":6120,"text":"- 16 - \n \nEven if PJM’s proposal is read as merely requiring PJM to use the updated pro forma GIA \nat the conclusion of the necessary study process—a reading that is not readily apparent from the \nproposed tariff language—PJM has not justified that requirement, which appears entirely unrelated \nto the Commission’s compliance directives.  And PJM’s proposal could lead to further disputes \nabout whether and how provisions in the updated pro forma GIA should apply to older generators.  \nFor instance, the most recent pro forma GIA includes certain power factor,48 primary frequency \nresponse,49 and ride-through requirements,50 that are not present in some older interconnection \nagreements.  It is not clear whether PJM intends to impose these new requirements on older \nexisting generators.  Imposing new requirements on older existing generators would have far-\nreaching impacts.  The Commission very purposely exempted resources with existing signed \ngenerator interconnection agreements from many of these new requirements based on the cost \nexisting generators would incur to come into compliance.51   PJM appears to be proposing to \ndisrupt long-standing Commission precedent with no justification.     \n \n48 PJM Interconnection, L.L.C., Open Access Transmission Tariff, Part IX, Subpart B (Form of GIA Combined \nwith CSA), § 12 (3.0.0). \n49 Id., app. 2 (Standard Terms and Conditions), § 4.6.2 (Primary Frequency Response) (1.0.0). \n50 Id., app. 2 (Standard Terms and Conditions), § 4.7 (Under- and Over-Frequency and Under- and Over- Voltage \nConditions) (1.0.0). \n51 Order No. 2023, 184 FERC ¶ 61,054 at P 1725 (explaining that new ride-through requirements would apply \nonly prospectively to customers that execute a GIA after the effective date because the requirement was not intended \nto “impos[e] potentially significant retrofit or equipment costs on existing nonsynchronous generating facilities.”); \nEssential Reliability Services & the Evolving Bulk-Power System -- Primary Frequency Response, Order No. 842, 162 \nFERC ¶ 61,128, at P 143, order on reh’g and clarification, 164 FERC ¶ 61,135 (2018) (“We will not impose primary \nfrequency response requirements on existing generating facilities that do not submit new interconnection requests that \nresult in an executed or unexecuted interconnection agreement. We conclude that applying the proposed requirements \nonly to newly interconnecting generating facilities will adequately address the Commission’s concerns regarding \nprimary frequency response.  We are persuaded by commenters that requiring existing generating facilities that have \nnot submitted a new interconnection request to install and operate governors or equivalent controls would be overly \nexpensive and unnecessarily burdensome.”)."},{"page":17,"startToken":6120,"endToken":6413,"text":"- 17 - \n \nPJM’s proposal injects unnecessary uncertainty into the necessary study process, especially \nfor generators that initiated PJM’s interconnection process prior to October 1, 2021.  Such \nuncertainty will further delay the pace at which generators in PJM can serve critical digital \ninfrastructure.   \nII. \nPJM’s Proposal to Use of “Point of Change in Ownership” Versus “Point of \nInterconnection” in Co-Located Load Definition Creates New Opportunities for \nUndue Discrimination \nIn the Order on Show Cause Proceedings, the Commission defined co-located load as a \n“configuration [that] refers to end-use customer load that is physically connected to the facilities \nof an existing or planned Customer Facility on the interconnection customer’s side of the Point of \nInterconnection to the PJM Transmission System.”52  The Commission correctly reasoned that this \ndefinition is proper because it “reflects the fact that the Co-Location Arrangement is physically \nconnected to and synchronized to the transmission system” and that “this relationship, and \nspecifically the interconnection of the generator to the transmission system, is critical to the \ndeterminations” that the Commission made in its Order on Show Cause Proceedings.53  The \nCommission directed PJM to incorporate this definition into its tariff.54   \nThe Commission should reject PJM’s proposal to revise the Commission’s definition of \nco-located load to refer to “Point of Change in Ownership” (“POCO”) instead of “Point of \nInterconnection” (“POI”).55   The change in term breeds uncertainty and creates an opportunity for \ntransmission owners to unduly discriminate against certain customers because the transmission \nowners retain significantly more control over the designation of the POCO compared to the POI.  \n \n52 Show Cause Order, 190 FERC ¶ 61,115 at P 3 & n.4. \n53 Order on Show Cause Proceedings, 193 FERC ¶ 61,217 at P 164. \n54 Id. PP 163-164. \n \n55 See PJM Compliance Filing at 31."},{"page":18,"startToken":6413,"endToken":6771,"text":"- 18 - \nSpecifically, PJM’s tariff requires the transmission owner and project developer to mutually agree \non the POCO, with no specific timeline for doing so and no specific process for handling \ndisagreements.56  To contrast, PJM has discretion to determine the POI if the parties cannot agree.57  \nBy defining co-located load by reference to the POCO, transmission owners could delay large load \ninterconnections by refusing to cooperate on the designation of the POCO.  For instance, \ntransmission owners could refuse to designate the POCO unless the load agrees to take certain \nservices.  Transmission owners could also strategically manipulate the location of the POCO to \nfavor their preferred configurations and prevent some loads from meeting the definition of a co-\nlocated load.   \nNothing in PJM’s tariff would prevent transmission owners from exercising their discretion \nin unduly discriminatory ways because there are no consistent or reliable standards by which the \ntransmission owners decide whether to agree to a certain POCO.  That clear opportunity for undue \ndiscrimination will perpetuate the “uncertainty that has resulted in disparate treatment in PJM, \nwhere transmission owners have taken different approaches to performing the necessary steps that \napply to Interconnection Customers seeking to serve Co-Located Load Arrangement.”58  \nIf the Commission accepts PJM’s new definition of co-located load, then it should direct \nfurther compliance to prevent undue discrimination.  First, the Commission should direct PJM to \nrevise its tariff to include clear timelines for mutual agreement on the POCO.  Providing a distinct \n \n56 See PJM Interconnection, L.L.C., Open Access Transmission Tariff, Part VII, Subpart A, 300 Definitions “P” \n(2.0.0) (defining the Point of Change in Ownership as to be specified in the GIA); Id., Part VIII, Subpart A, 400 \nDefinitions “P” (2.0.0) (same). \n57 PJM, Open Access Transmission Tariff, Attach. O, App. 2, § 2.1 (Scope of Service) (0.0.0) (“The location of \nthe Point of Interconnection shall be mutually agreed by the Interconnected Entities, provided, however, that if the \nInterconnected Entities are unable to agree on the Point of Interconnection, [PJM] shall determine the Point of \nInterconnection . . . .”). \n58 Order on Show Cause Proceedings, 193 FERC ¶ 61,217 at P 159."},{"page":19,"startToken":6771,"endToken":7050,"text":"- 19 - \ndeadline avoids unnecessary delays and encourages competitive open access.  Second, the \nCommission should allow PJM to provide a final determination should the parties fail to come to \na mutual agreement, consistent with PJM’s practice for POIs.  Finally, the Commission should \nestablish guidelines that prohibit transmission owners from effectuating discrimination and \nneedless delay against large loads that do not suit their preference.  These measures are necessary \nto avoid undue discrimination and ensure that PJM and the transmission owners meet the goals of \nthe Order on Show Cause Proceedings by “reduc[ing] both technical and financial barriers to \nbuilding new generation and efficiently connect[ing] large loads.”59 \nIII. \nConclusion \nPJM’s compliance proposal threatens to impose a 3- to 5-year moratorium on co-location \nand thereby throttle the development of digital infrastructure at the very moment that the nation \nneeds to rapidly build and energize the computing power needed to win the AI race.   In the Order \non Show Cause Proceedings, the Commission gave PJM straightforward directions for how it must \nrevise its tariff to ensure that existing interconnection customers seeking to serve co-located \nunderstand their responsibilities.  Rather than follow those directions for clarifying the necessary \nstudy process, PJM inexplicably veered in the opposite direction with its compliance filing, by \nimpeding co-location opportunities and muddying the waters to make it even more challenging for \ninterconnection customers to discern how to revise their existing interconnection agreements to \nserve co-located loads.  The Commission must reject PJM’s counterproductive proposal and ensure \nthat PJM complies with the Commission’s clear and common-sense mandates from the Order on \nShow Cause Proceedings. \n \n \n59 Order on Show Cause Proceedings, 193 FERC ¶ 61,217 (Rosner, Comm’r concurring at P 3)."},{"page":20,"startToken":7050,"endToken":7124,"text":"- 20 - \nRespectfully submitted, \n  \n \n/s/ J. Arnold Quinn \nJ. Arnold Quinn \nSVP of Regulatory Policy  \n \nAndrew Weinstein \nVice President, FERC Market Policy \n \nVistra Corp. \n325 7th Street NW \nSuite 520 \nWashington, DC 20004 \narnie.quinn@vistracorp.com  \nandrew.weinstein@vistracorp.com \n                         \nNicholas M. Gladd \nSarah Greenberg \nWilson Sonsini Goodrich & Rosati \n1700 K Street NW \nFifth Floor \nWashington, DC 20006 \n(617) 598-7871 \nngladd@wsgr.com  \nsgreenberg@wsgr.com  \n \nCounsel for Vistra Corp. \n \nDated:  March 16, 2026"},{"page":21,"startToken":7124,"endToken":7183,"text":"CERTIFICATE OF SERVICE \n \nI hereby certify that I have this day served the foregoing document upon each person \ndesignated on the official service lists compiled by the Secretary of the Commission in these \nproceedings. \n \nDated:  March 16, 2026 \nWashington, D.C. \n \n \n/s/ Sarah Greenberg \nSarah Greenberg \nWilson Sonsini Goodrich & Rosati \n1700 K Street NW \nFifth Floor \nWashington, DC 20006"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":2,"endAt":1018,"startToken":0,"endToken":415},{"p":2,"at":1018,"title":"I. PJM Has Not Demonstrated That the Proposed Revisions to the Necessary Study","method":"printed heading","endPage":3,"endAt":852,"startToken":415,"endToken":703},{"p":3,"at":852,"title":"A. PJM’s Proposal Fails to Include a Transition Mechanism for Customers","method":"printed heading","endPage":8,"endAt":619,"startToken":703,"endToken":2774},{"p":8,"at":619,"title":"B. PJM Has Not Demonstrated That Its Proposal for Delisting CIRs Is Just,","method":"printed heading","endPage":14,"endAt":189,"startToken":2774,"endToken":4931},{"p":14,"at":189,"title":"C. PJM Has Not Justified the Requirement to Update Old Generator","method":"printed heading","endPage":17,"endAt":310,"startToken":4931,"endToken":6161},{"p":17,"at":310,"title":"II. PJM’s Proposal to Use of “Point of Change in Ownership” Versus “Point of","method":"printed heading","endPage":19,"endAt":742,"startToken":6161,"endToken":6878},{"p":19,"at":742,"title":"III. Conclusion","method":"printed heading","endPage":21,"endAt":0,"startToken":6878,"endToken":7124},{"p":21,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":21,"endAt":392,"startToken":7124,"endToken":7183}]}