{"document":{"slug":"rec-20260316-5333","title":"Motion to Intervene and Protest of Eolian, L.P. et al. to PJM Interconnection, L.L.C.’s proposed revisions to the PJM Open Access Transmission Tariff","issued":"2026-03-16","accession":"20260316-5333","docket":"ER26-1479-000","group":"PJM co-location compliance","filer":"Eolian, L.P.Antora Energy LLCCalibrant Energy ,Convergent Energy and Power LP ,Mainspring Energy ,Verrus LLC ,","kind":"protest","file":"sources/filings/text/20260316-5333_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260316-5333","tier":"record","sha256":"3231a05538c61676368e960637aab1701850bdcbefe57a22645fe24b7eaf7aaa","pages":17,"tokens":4718,"emptyPages":[],"textThemes":["colo","study","flex","cost"]},"pages":[{"page":1,"startToken":0,"endToken":330,"text":"1 \nUNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \n) \nPJM Interconnection, L.L.C. \n) \nDocket No. ER26-1479-000 \n) \n \nMOTION TO INTERVENE AND PROTEST OF JOINT PARTIES TO COMPLIANCE \nFILING \n \n \nPursuant to Rules 211 and 214 of the Federal Energy Regulatory Commission’s \n(Commission) Rules of Practice and Procedure,1 Eolian L.P. (Eolian), Antora Energy, Inc. \n(Antora), Calibrant Energy (Calibrant), Convergent Energy and Power (Convergent), Mainspring \nEnergy, Inc. (Mainspring), and Verrus, LLC (Verrus) (together, Joint Parties) respectfully submit \nthis motion to intervene and protest to PJM Interconnection, L.L.C.’s (PJM) proposed revisions \nto the PJM Open Access Transmission Tariff (Tariff) to comply with the Commission’s \nDecember 18, 2025 order on service to Co-Located Loads.2  \nConsistent with the Request for Clarification of the Co-Location Order3 and protest in \nPJM’s prior compliance proceeding in Docket No. ER26-1088-000 filed by several of the above \nparties,4 Joint Parties respectfully request that the Commission require PJM to include minor \nadditional revisions to clarify that, in any generator interconnection process in which PJM \nstudies the Co-Located Load’s withdrawals from the grid for purposes of identifying network \nupgrades, including the Necessary Studies process,5 a Co-Located Load may nominate a net \n \n1 18 C.F.R. §§ 385.211, 385.214. \n2 See PJM Interconnection, LLC, 193 FERC ¶ 61,217 (2025) (Co-Location Order). \n3 Joint Parties, Request for Clarification, Docket Nos. EL25-49-000 & 001, AD24-11-000, EL25-20-000 (filed Jan. \n20, 2026). \n4 Joint Parties, Limited Protest, Docket No. ER26-1088-000 (filed Feb. 10, 2026). \n5 The PJM OATT does not resolve definitively the circumstances in which PJM will model withdrawals of a Co-\nLocated Load in the generator interconnection process. But because we expect that PJM may choose to study the \ncombined withdrawals of Co-Located Loads that include storage, we have filed the above-cited Request for \nClarification and are filing this limited protest to ensure that any such study process advances the principles set forth \nin the Co-Location Order and does not result in needless network upgrades."},{"page":2,"startToken":330,"endToken":577,"text":"2 \nwithdrawal limit in the same manner that it may nominate a net injection limit. Among other \npotential benefits, this clarification will ensure that Co-Located Loads paired with energy storage \ncan use their full technical capabilities to avoid unnecessary network upgrades, thereby \nadvancing the Commission’s twin goals of protecting ratepayers and advancing speed-to-power \nwithin PJM.  \nIn addition, Joint Parties request that the Commission reject or, at minimum, defer action \non PJM’s proposed Tariff revisions that preclude loads connected to generating facilities behind-\nthe-meter without interconnection rights from accessing the new Firm Contract Demand \nTransmission Service, Non-Firm Contract Demand Transmission Service, and Interim Network \nIntegration Transmission Service (NITS) options established in the Co-Location Order. PJM \nmust allow loads served by behind-the-meter generation (BTMG) to access the Commission’s \nnew transmission services in order to ensure that loads with similar willingness and ability to \nlimit withdrawals from the grid have access to similar service opportunities, and that therefore \nthe proposed rates are just, reasonable, and not unduly discriminatory. The Commission should \ndirect PJM to further revise its Tariff as part of the BTMG replacement rate to remove the \nrestrictions limiting the new transmission services to loads connected to generation resources that \nhave Interconnection Agreements with PJM.  \nI. \nMOTION TO INTERVENE \nEolian develops energy generation and storage assets throughout the United States and \nhas originated 27 GW of operating capacity to date. Eolian and its partners have developed \nprojects supporting large loads in multiple regions across the United States, including PJM."},{"page":3,"startToken":577,"endToken":864,"text":"3 \nAntora is a U.S. manufacturer of thermal batteries, which are domestically built in San \nJose, California, and developer of thermal storage projects for industrial facilities in the U.S. and \nabroad.  \nCalibrant develops energy generation and storage assets throughout the United States. \nCalibrant and its partners have developed and expect to continue to develop projects in PJM \nthrough a range of configurations, including BTMG and co-located projects supporting large \nloads. Specifically, Calibrant has several existing BTMG projects and projects that are currently \nbeing developed that will be impacted by PJM’s proposed revisions to its Retail BTMG rules.  \nConvergent develops, owns, and operates distributed energy storage and storage plus \nsolar resources for large commercial, industrial, and utility customers across North American \nmarkets, including PJM. Convergent has resources in operation and in development in PJM \nincluding behind-the-meter distribution and transmission connected battery energy storage \nsystems, front-of-the-meter distribution connected battery energy storage systems, both with and \nwithout attached solar systems, and a 20 MW flywheel resource in Hazleton, Pennsylvania.  \nMainspring is a U.S.-headquartered manufacturer of modular, fuel-flexible, and \ndispatchable linear generators, a new type of power generator. Mainspring was founded in 2010 \nand its first commercial units were deployed in 2020. The company has been rapidly scaling \nsince 2023, deploying its innovative technology across a wide spectrum of customer types and \nuse cases. The company’s customers include investor-owned utilities, public power utilities, \nmunicipal water treatment facilities, biogas facilities, data centers, grocery store chains, cold \nfood storage, and hospital systems.  Mainspring’s linear generators can be installed behind a \ncustomer’s utility meter or as a front of the meter grid asset. Mainspring linear generators are \ncurrently operating across multiple sites in PJM territory and are in development across"},{"page":4,"startToken":864,"endToken":1143,"text":"4 \nadditional sites.Verrus is a developer, owner, and operator of a first-of-its-kind fleet of purpose-\nbuilt, load-flexible hyperscale data centers. Verrus designs facilities from the ground up to \nfunction not only as digital infrastructure but also as grid assets—a new class of large customer \ncapable of dynamically adjusting electricity consumption to support reliability, efficiency, and \naffordability. Verrus’ facilities can provide these system benefits without disrupting the critical \ncomputing workloads that increasingly underpin the modern economy. Each Verrus campus \nintegrates on-site utility-scale battery energy storage, advanced load-management controls, and \ngrid-aware automation that collectively enable real-time coordination with utilities and regional \ntransmission operators.   \nEach of the Joint Parties expect to develop storage or generation assets co-located and/or \nbehind the meter with loads. They therefore each have a substantial interest in this proceeding \nthat cannot be adequately represented by another party. Granting this limited protest will \ncritically support development of Co-Located Loads, storage, and BTMG assets that avoid \n“costly and inefficient transmission system buildout.”6 The Joint Parties’ participation is \ntherefore in the public interest. \nII. \nLIMITED PROTEST \nA. \nPJM should be required to clarify that an existing interconnection customer \ncan nominate a joint withdrawal limit in the Necessary Study process. \n \nJoint Parties seek clarification, consistent with the Request for Clarification that the Joint \nParties filed in response to the Co-Location Order,7 that PJM’s filing will allow interconnection \ncustomers serving Co-Located Loads to nominate net withdrawal limitations for purposes of \nthese interconnection study processes. This clarification is necessary to realize the Co-Location \n \n6 Co-Location Order, 193 FERC ¶ 61,217 at P 177. \n7 Joint Parties, Request for Clarification, Docket Nos EL25-49-000 & 001, AD24-11-000, EL25-20-000 (filed Jan. \n20, 2026)."},{"page":5,"startToken":1143,"endToken":1488,"text":"5 \nOrder’s stated intent of ensuring that Co-Located Loads do not pay for services that they do not \nuse and do not trigger network upgrades that they do not need.8  \nThe Co-Location Order is built on the concept that Co-Located Loads can control their \nnet withdrawals from the grid, and that market structures should be in place that allow them to do \nso efficiently. The Co-Location Order requires PJM to develop transmission service frameworks \nthat allow customers to take as-available service based on the use of special protection schemes \nthat enable reliable, as-available service based on technical and engineering requirements set by \nPJM,9 and requires PJM to enable an interconnection customer to request the “minimum level of \ninterconnection service it deems necessary.”10   \nPJM’s Tariff revisions proposed here, however, appear to remain silent as to how it will \ntreat withdrawals in studying Co-Located Load interconnection requests. We therefore seek \nmodest clarification from PJM that, to the extent PJM performs interconnection study steps \ninvolving withdrawal assumptions for Co-Located Loads, an energy storage interconnection \ncustomer will be able to specify limits to the injection and withdrawal rights reflecting the \nproposed integration of the storage and Co-Located Load facilities. \nJoint Parties submit this protest to preserve their rights and to ensure that PJM does not \ninclude assumptions in interconnection studies that the load and storage resource withdrawals to \ncharge create bluntly overlapping grid impacts (e.g. coincident withdrawals at peak), when in \nfact the storage resources and Co-Located Load could be managed to limit the overall \nwithdrawal of the Co-Located Load and to avoid withdrawal when doing so would create grid \n \n8 See, e.g., Co-Location Order, 193 FERC ¶ 61,217 at P 162 (“Collectively, the replacement rate provides pathways \nthat recognize Co-Located Loads that limit their energy withdrawals from the transmission system, which may \nrequire fewer Network Upgrades, and therefore may result in lower Network Upgrade costs as compared to \nrequiring all Eligible Customers taking service on behalf of Co-Located Load to take [Network Integration \nTransmission Service].”). \n9 Id. P 212. \n10 Id. P 232."},{"page":6,"startToken":1488,"endToken":1787,"text":"6 \nimpacts necessitating network upgrades. Accordingly, Joint Parties request that the Commission \nrequire PJM to propose narrow Tariff additions to clarify that a Co-Located Load may nominate \na net withdrawal limit in the same manner that it may nominate a net injection limit.  \na. \nThe Commission should require PJM to propose further \ncompliance revisions to ensure compliance with the Co-Location \nOrder \n \nPJM here proposes Tariff revisions related to Necessary Studies and Necessary Study \nAgreements, including the information needed to perform Necessary Studies.11 PJM does not \nappear to specify in these revisions or elsewhere in the filing how it will treat energy storage \nwithdrawals in interconnection studies, or that, to the extent that PJM includes Co-Located Load \nin interconnection studies, interconnection customers may provide withdrawal limits for both the \nenergy storage resource components and the Co-Located Load. To remedy these deficiencies, the \nCommission should require PJM to file revisions clarifying that (1) interconnection customers \nmay nominate joint withdrawal limits and include information in their requests to modify \ninterconnection agreements to demonstrate the ability to operate within such limits; and (2) the \ndetermination of Network Upgrades, Interconnection Facilities, and any other infrastructure that \nmay be required shall account for such limits.  \nThe Co-Location Order finds the existing PJM tariff unjust and unreasonable because it \nlacks clear provisions to govern the “rates, terms, and conditions of service that apply to \nInterconnection Customers serving Co-Located Load and Eligible Customers taking transmission \nservice on behalf of Co-Located Load.”12 The requested revision aims to address precisely this \ndefect: the absence of clear rules that govern how Co-Located Load paired with storage will be \n \n11 PJM Filing, Transmittal at 26 (citing Proposed Tariff, Part VII, Subpart A, section 401.H.3.b.i – iii). \n12 Co-Location Order, 193 FERC ¶ 61,217 at P 175."},{"page":7,"startToken":1787,"endToken":2057,"text":"7 \nstudied in the generator interconnection process. The Proposed Tariff, as currently drafted, does \nnot specify how storage withdrawals will be modeled when a storage facility is seeking to co-\nlocate with a large load. \nThis absence of clear provisions means that without clarification, there is a risk that the \nnecessary study process could include assumptions that the load and the charging load of the \nstorage resource create bluntly overlapping grid impacts (e.g. coincident withdrawals at peak), \nwhen in fact the storage resources and Co-Located Load could be managed to limit the overall \nwithdrawal of the co-located resource and to avoid withdrawal when doing so would create grid \nimpacts necessitating network upgrades. Accordingly, the Commission should require modest \nrevisions to clarify that an interconnection customer can nominate a joint withdrawal limit to \navoid uncertainty. \nb. \nThe principles set forth in the Co-Location Order require PJM \nto allow interconnection customers to nominate joint withdrawal \nlimits \n \nIn the Co-Location Order, the Commission found that “the PJM Tariff is unjust and \nunreasonable because it lacks sufficient clarity and consistency with respect to the rules for Co-\nLocation Arrangements” and directed changes to the new service request process, as well as the \nnecessary study process for modifications to existing facilities.13 With regard to “Interconnection \nCustomers seeking to use new generating facilities to serve Co-Located Load,” the Commission \nrequired PJM to clarify that it “shall consider requests for interconnection service below the full \ngenerating capability of the generating facility, so that an Interconnection Customer may request \ninterconnection service at a level below its maximum facility output to serve Co-Located \n \n13 Id. P 225."},{"page":8,"startToken":2057,"endToken":2349,"text":"8 \nLoad.”14 The Co-Location Order aims to minimize infrastructure needs based on interconnection \ncustomer capabilities including the Co-Located Load’s characteristics, specifying that “[t]his \nrevision will clarify that an Interconnection Customer seeking to use a new generating facility to \nserve a Co-Located Load may request only the minimum level of interconnection service it \ndeems necessary to effectuate its Co-Location Arrangement.”15  \nWith regard to the necessary study process, the Commission required PJM “to add to the \nTariff a description of the scope of the analysis that it will perform as part of the necessary study \nprocess when an Interconnection Customer seeks to use its existing generating facility to serve \nCo-Located Load,” which must include a description of “the information that the Interconnection \nCustomer must provide about the Co-Located Load for purposes of the necessary study.”16 The \nCo-Location Order contemplates that PJM will use this information in determining “any \nmodifications or Network Upgrades that are needed as a result of PJM’s study of the change to \nthe ISA or GIA to allow the existing generating facility to serve Co-Located Load.”17 And the \nCo-Location Order explains that such upgrades should account for “special protection \nschemes.”18 The implication of these directives is that information about the Co-Located Load \nand special protection schemes may influence what modifications and Network Upgrades may be \nrequired, because the Interconnection Customer may operate the Generating Facility and Co-\nLocated Load in a coordinated fashion so as to minimize infrastructure needs. Given the \nambiguity of the tariff proposed by PJM, we urge the Commission to clarify that such \ninformation must include the ability to nominate joint withdrawal limits between the Generating \n \n14 Id. P 232. \n15 Id. \n16 Id. P 227.  \n17 Id. P 228. \n18 Id."},{"page":9,"startToken":2349,"endToken":2644,"text":"9 \nFacility and Co-Located Load, as such limits may be a critical factor affecting the infrastructure \nthat may be triggered by study results where both the Generating Facility and the Co-Located \nLoad withdraw electric energy from the system.    \nThe minor revision we are requesting is necessary to ensure that “the Tariff will have \nsufficient clarity and consistency to facilitate Co-Location Arrangements in a just and reasonable \nand not unduly discriminatory or preferential manner.”19 Just as an Interconnection Customer \nseeking to use a new storage facility to serve a Co-Located Load “may request only the \nminimum level of interconnection service it deems necessary to effectuate its Co-Location \nArrangement,” similar treatment of an existing Interconnection Customer requires such \ncustomers to request the minimum level of service necessary to serve the Co-Located Load when \nproceeding through the necessary study process.  \nAllowing both new and existing customers the ability to nominate joint withdrawal limits \nis also necessary to give the Co-Location Order’s transmission service reforms meaning. The Co-\nLocation Order recognizes in the context of requiring PJM to offer non-firm transmission service \nthat co-located resources can be integrated so as to “limit [the] energy withdrawals” of Co-\nLocated Loads in order to prevent “inefficient and costly transmission buildout.”20 In requiring \nPJM to offer Co-Located Loads a menu of transmission service options, the Co-Location Order \nensures that such loads have the opportunity to receive service that “reflect[s] their actual impact \non the transmission system.”21 But the value presented by the option to obtain non-firm \ntransmission service requires reading PJM’s interconnection service compliance requirements to \navoid separately forcing Co-Located Loads to bear the cost and delay of unnecessary network \n \n19 Id. P 229. \n20 Co-Location Order, 193 FERC ¶ 61,217 at P 199. \n21 Id. P 162."},{"page":10,"startToken":2644,"endToken":2951,"text":"10 \nupgrades that do not “reflect[s] their actual impact on the transmission system.”22 To achieve the \nobjectives of the Co-Location Order, the Commission should therefore require PJM to allow for \nnon-firm withdrawal and integrated operation of co-located facilities including net withdrawal \nlimits to be integrated into interconnection study assumptions because failing to do so “could \nnecessitate inefficient and costly transmission buildout.”23   \nB. \nThe Commission should reject PJM’s proposed Tariff revisions that preclude \nretail loads served by behind-the-meter generation from taking the new \ntransmission services and otherwise limit eligibility for the new transmission \nservices to load that is connecting to a generator with interconnection rights.  \n \nPJM’s compliance filing is also unjust, unreasonable and unduly discriminatory for \nprecluding loads connected to behind-the-meter generation without interconnection rights from \ntaking the new Firm and Non-Firm Contract Demand Transmission Services and Interim NITS \nthat will be offered to Co-Located Loads. These retail loads are similarly situated to Co-Located \nLoads in their willingness and ability to limit their energy withdrawals from the transmission \nsystem under certain conditions in the same manner as Co-Located Loads. Just, reasonable, and \nnot unduly discriminatory treatment requires that these similarly-situated loads receive similar \ntreatment: access to these new transmission service classes.  \nThe Commission is requiring revisions to PJM’s Tariff with respect to certain BTMG \nloads because such loads “are not fully accounted for in resource adequacy planning and shift \ncosts onto other transmission customers.”24 This directive speaks to a desire to render such loads \nvisible to the PJM transmission system and require them to pay for transmission service used by \nthe load customer that relies on BTMG. The Commission’s stated goals do not suggest a desire \nto force BTMG to move through PJM’s queue even where it does not plan to inject into the \n \n22 Id.  \n23 Id. P 199. \n24 Id. P 2."},{"page":11,"startToken":2951,"endToken":3229,"text":"11 \nsystem, or to require purchase of more transmission service than similarly situated customers. \nYet, absent removal of the eligibility restrictions proposed by PJM for the new transmission \nservices, that is exactly the result that will occur.  \nPJM could remedy the deficiency of its proposed replacement rate by removing the \nrestrictions on eligibility that allow only Co-Located Loads to access the new transmission \nservices. Extending this transmission service eligibility will also further the Co-Location Order’s \ngoals of ensuring that loads have the opportunity to receive service that “reflect[s] their actual \nimpact on the transmission system”25 and preventing “inefficient and costly transmission \nbuildout.”26 \nPJM’s compliance filing prohibits retail loads served by “[a]ny facility that qualifies as a \nRetail Behind The Meter Generation . . . from Co-Located Load configurations.”27 By proposing \nto restrict availability of the new transmission services to “Eligible Customers taking \ntransmission service on behalf of Co-Located Load,”28 this provision prevents retail customers \nserved by behind-the-meter generation lacking interconnection rights from taking the new \ntransmission services. These customers are also excluded from new transmission service options \nby PJM’s proposal to define Co-Located Load as “end-use customer load that is physically \nconnected to the facilities of an existing or planned Generating Facility on the Project \nDeveloper’s side of the Point of Change in Ownership to the Transmission Provider’s \nTransmission System.”29 Retail loads served by behind-the-meter generation do not qualify \nunder this definition because Generating Facilities under the Tariff must have gone through the \n \n25 Id. P 162. \n26 Id. P 199. \n27 PJM Filing, Transmittal at 7-8 & Proposed Tariff, Definitions – R – S.  \n28 PJM, Proposed Tariff, § III. \n29 PJM, Proposed Tariff, Definitions – A - B"},{"page":12,"startToken":3229,"endToken":3601,"text":"12 \ninterconnection process and have injection rights, which do not apply to behind-the-meter \ngeneration.30  \nPJM’s compliance filing therefore excludes loads served by behind-the-meter generation \nthat lack interconnection rights from accessing the new transmission service options despite their \nabilities to limit withdrawals. This result is particularly absurd in light of PJM’s proposal, in \ncompliance with the Co-Location Order, to allow Generating Facilities connected to Co-Located \nLoads to nominate net injection limits below their nameplate capacity.31 These provisions would \nenable an interconnection customer to reduce its net injection to 1 MW and receive the new \ntransmission services, while prohibiting a BTMG to engage in a nearly-identical arrangement \nthat places even less strain on the grid by limiting its net injection to zero (and therefore \neliminating the need an interconnection agreement for the Generating Facility). \nWhile PJM’s compliance proposal is generally responsive to the PJM Co-location \nOrder’s focus on Co-Located Loads, it does not provide for a just, reasonable, and not unduly \ndiscriminatory replacement rate with regard to loads connected to behind-the-meter generation. \nCritically, in contrast to the services available to Co-Located Loads, PJM’s proposal does not \nallow customers served by behind-the-meter generation that are similarly situated to Co-Located \nLoads in their willingness and ability to limit withdrawals a similar pathway to use new \ntransmission services to limit their impacts on the system.32 Under PJM’s proposal, loads served \n \n30 See PJM, PJM Interconnection, L.L.C./Intra-PJM Tariffs, G-H, OATT Definitions - G - H (9.0.1) (defining \n“Generating Facilities” as “Interconnection Customer’s device for the production and/or storage for later injection of \nelectricity identified in the Interconnection Request . . . .”). \n31 PJM, Filing, Docket No. ER26-1088-000, at 4 (filed Jan. 20, 2026) (citing Proposed Tariff, Part VIII, Subpart B, \nsection 403 (A)(1)(q) (requiring Applicants, in Generation Interconnection Requests, to “[i]ndicate the level of \nInterconnection Service requested, including whether Project Developer requests Interconnection Service below the \nfull generating capability of a new Generating Facility or the requested increase in generation capability of an \nexisting Generating Facility to serve Co-Located Load.”)). \n32 The Commission recognized “that Co-Location Arrangements may interact with the transmission system in a \nsimilar way to BTMG arrangements,” and therefore “sought briefing on how any proposed replacement rate adopted"},{"page":13,"startToken":3601,"endToken":3987,"text":"13 \nby behind-the-meter generation must purchase NITS, even where the behind-the-meter \ngeneration capabilities would allow for use of the more limited transmission services. PJM \nshould instead make such services available to other customers with substantively the same \ncapabilities to limit withdrawals, including customers served by behind-the-meter generation as \nwell as others with inherently flexible demand profiles (such as thermal storage)33 or customers \nlocated adjacent to generation such that the electrical impacts of the combined load and \ngeneration are the same with respect to system curtailment needs.34 \nThe Commission has authority to require PJM to make the new Firm Contract Demand, \nNon-Firm Contract Demand, and Interim NITS services available to loads served by behind-the-\nmeter generation. In the Co-Location Order, the Commission required PJM to develop BTMG \nrules that address the reliability and resource adequacy risks created by some loads using \nBTMG35 because such loads may “lean on the PJM system when the co-located generation is on \na full or partial outage or if the load exceeds the rating of the co-located generation.”36 But in \nrequiring revised BTMG rules, the Commission recognized “the potential impacts of the \nCommission changing PJM’s BTMG rules for existing BTMG customers,” and therefore \nrequired PJM to take steps to “minimize the impact of [the BTMG rule] transition on existing \nBTMG customers.”37  \n \nin this proceeding would interact with existing BTMG arrangements.” Co-Location Order, 193 FERC ¶ 61,217 at P \n9. Given the delays inherent to interconnecting to the PJM system, obtaining an Interconnection Agreement is likely \nnot a viable pathway for most behind-the-meter generators. Moreover, where the load customer behind whose meter \nthe generator is connected does not inject into the system, a generator Interconnection Agreement should not be a \ncondition of service. \n33 See Antora Energy LLC, Motion to Intervene and Comments, Docket Nos. EL25-49-000, EL25-20-000, & AD24-\n11-000, at 3 (filed Apr. 23, 2025). \n34 See Eolian L.P., Initial Comments, Docket No. RM26-4-000, Attach. A at 8 (filed. Nov. 21, 2026) (noting that \n“[C]ases in which the large load is electrically close to the paired generation, metered separately, and not necessarily \nat the same site . . . can provide many of the same benefits as strictly on-site generation and load”). \n35 Co-Location Order, 193 FERC ¶ 61,217 at P 221. \n36 Id. P 186. \n37 Id. P 222."},{"page":14,"startToken":3987,"endToken":4302,"text":"14 \nImportantly, unlike the Commission’s other findings in the Co-Location Order that were \nlimited to Co-Located Loads, the Commission’s finding with respect to the BTMG rules “applies \nto all Network Load.”38 The replacement rate must therefore provide for just, reasonable, and not \nunduly discriminatory BTMG rules for all Network Load. This broad finding both requires and \npermits the Commission to require PJM’s replacement rate to allow retail customers who can \nlimit withdrawals but who are nevertheless not connected to “Generating Facilities” with \ninterconnection rights under the Tariff to take the new transmission services. Alternately, the \nCommission could provide for the same result by granting the PJM Industrial Consumer \nCoalitions pending request for clarification or, in the alternative, rehearing seeking to clarify that \n“[n]ew transmission services outlined in the Order will be made available to retail BTMG \ncustomers and load-only customers, not just Co-Located Load.”39 Or, the Commission could \nensure non-discriminatory eligibility for the new transmission services in the Commission’s \npending paper hearing proceeding in Docket No. EL25-49 et al. to develop the new transmission \nservice replacement rate.40  \nIn the instant proceeding, however, the Commission may not approve PJM’s proposed \nunjust, unreasonable, and unduly discriminatory compliance filing that allows some loads that \ncan limit withdrawals to take the new transmission services but denies the same opportunities to \nothers with the same technical abilities. Rather, the Commission should reject PJM’s compliance \nfiling and direct PJM to allow customers with generation behind their load to access transmission \nservices that match their ability to limit withdrawals, similar to customers with load connected to \nGenerating Facilities. In the alternative, or in addition, the Commission could defer action on this \n \n38 Id. P 186. \n39 PJM Industrial Customer Coalition et al., Request for Rehearing, Docket Nos. EL25-49-000 & 001, AD24-11,000, \n& EL25-20-000, at 7 (filed Jan. 20, 2026). \n40 Co-Location Order, 193 FERC ¶ 61,217 at P 207."},{"page":15,"startToken":4302,"endToken":4561,"text":"15 \ncompliance filing and grant the request for clarification or rehearing arguing that the new \ntransmission services must be available to Retail BTMG and load-only customers41 and accept \nthis compliance filing after PJM has proposed other revisions to ensure similar transmission \nservice access for similarly situated customers.  \nIII. \nCONCLUSION \nFor the foregoing reasons, the Commission should reject PJM’s compliance filing and \nrequire PJM to: (1) clarify that, in any generator interconnection study process in which PJM \nstudies the Co-Located Load’s withdrawals from the grid for purposes of identifying network \nupgrades, including the necessary study process, a Co-Located Load may nominate a net \nwithdrawal limit in the same manner that it may nominate a net injection limit; and (2) allow \nloads that can limit their withdrawals similarly to Co-Located Loads to have access to the same \nFirm Contract Demand Transmission Service, Non-Firm Contract Demand Transmission \nService, and Interim NITS that PJM proposes to provide to Co-Located Loads. \n \n \nRespectfully submitted, \n/s/ Eric Stoutenburg  \n \n \n/s/ Miles Farmer \nEric Stoutenburg \n  \n \n \nMiles Farmer \nChief Development Officer  \n \nSam Walsh \nEolian L.P. \n  \n \n \n \nNathan Lobel \n988 Howard Ave. Suite 200   \n \nRoselle LLP \nBurlingame, CA 94010 \n  \n \n300 New Jersey Ave. NW, Suite 300 \neric.stoutenburg@eolianenergy.com   \nWashington, DC 20001 \n \n \n \n \n \n \nmiles.farmer@rosellellp.com \n/s/ Noah Long  \n \n \n \nsam.walsh@rosellellp.com \nNoah Long  \n \n \n \n \nnathan.lobel@rosellellp.com \nDirector, State and Regulatory Affairs  \n \nAntora Energy, Inc.   \n \n \n \n200 West De Vargas St  \nSanta Fe, NM 87501  \n \n41 PJM Industrial Customer Coalition et al., Request for Rehearing, Docket Nos. EL25-49-000 & 001, AD24-11,000, \n& EL25-20-000, at 7 (filed Jan. 20, 2026)."},{"page":16,"startToken":4561,"endToken":4658,"text":"16 \nnoah.long@antora.com   \n \n/s/ Matt Barnes \nMatt Barnes \nChief Commercial Officer \nCalibrant Energy \n4830 W. Kennedy Blvd, Suite 600 \nTampa, Florida 33609 \nmatthew.barnes@calibrantenergy.com \n \n/s/ Katie Guerry  \nKatie Guerry \nSVP Regulatory and Government Affairs \nConvergent Energy and Power \n7 Time Square, Suite 3504 \nNY, NY 10036 \nkguerry@convergentep.com \n \n/s/ Brian Kauffman \nBrian Kauffman \nDirect, Wholesale Market Development \nMainspring Energy, Inc. \n3601 Haven Ave. \nMenlo Park, CA 94025 \nbrian.kauffman@mainspringenergy.com \n \n/s/ Jeff Bladen \nJeff Bladen  \nHead of Energy  \nVerrus, LLC  \n918 N Rengstorff Ave.  \n \n  \nMountain View, CA 94043 \n \n  \nbladen@verrusdata.com"},{"page":17,"startToken":4658,"endToken":4718,"text":"17 \nCERTIFICATE OF SERVICE \n \nI hereby certify that I have this day served the foregoing document upon each person \ndesignated on the official service list compiled by the Secretary of the Commission in this \nproceeding. \n \nDated: March 16, 2026 \n/s/ Nathan Lobel \nNathan Lobel \nRoselle LLP \n300 New Jersey Ave. NW, Suite 300 \nWashington, DC 20001 \nnathan.lobel@rosellellp.com"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":2,"endAt":1468,"startToken":0,"endToken":533},{"p":2,"at":1468,"title":"I. MOTION TO INTERVENE","method":"printed heading","endPage":4,"endAt":1305,"startToken":533,"endToken":1039},{"p":4,"at":1305,"title":"II. LIMITED PROTEST","method":"printed heading","endPage":4,"endAt":1327,"startToken":1039,"endToken":1042},{"p":4,"at":1327,"title":"A. PJM should be required to clarify that an existing interconnection customer","method":"printed heading","endPage":10,"endAt":455,"startToken":1042,"endToken":2708},{"p":10,"at":455,"title":"B. The Commission should reject PJM’s proposed Tariff revisions that preclude","method":"printed heading","endPage":15,"endAt":335,"startToken":2708,"endToken":4349},{"p":15,"at":335,"title":"III. CONCLUSION","method":"printed heading","endPage":17,"endAt":4,"startToken":4349,"endToken":4659},{"p":17,"at":4,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":17,"endAt":376,"startToken":4659,"endToken":4718}]}