{"document":{"slug":"rec-20260316-5339","title":"Comments or, in the Alternative, Limited Protest of Appalachian Voices in response to PJM Interconnection, L.L.C.’s 02/23/2026 compliance filing proposing…","issued":"2026-03-16","accession":"20260316-5339","docket":"ER26-1479-000","group":"PJM co-location compliance","filer":"Appalachian Voices","kind":"protest","file":"sources/filings/text/20260316-5339_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260316-5339","tier":"record","sha256":"5d576c649c51d2e02d860d65767120f54142491364d22628a4700b2a8c41a647","pages":7,"tokens":1544,"emptyPages":[],"textThemes":["colo","adequacy"]},"pages":[{"page":1,"startToken":0,"endToken":271,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \nPJM Interconnection, L.L.C. \n \n      \n \n             Docket No. ER26-1479-000 \n \n \n \n      \n \n \n \n \n \n \n \nCOMMENTS OR, IN THE ALTERNATIVE, LIMITED PROTEST  \nOF APPALACHIAN VOICES  \n \nPursuant to Rule 211 of the Federal Energy Regulatory Commission’s (FERC or \nCommission) Rules of Practice and Procedure,1 Appalachian Voices submits these comments or, \nin the alternative, limited protest in response to PJM Interconnection, L.L.C.’s (PJM) compliance \nfiling proposing revisions to its Open Access Transmission Tariff (Tariff) concerning co-located \nload (Compliance Filing).2  The Compliance Filing addresses the Commission’s directives in its \nDecember 18, 2025 order in Docket No. EL25-49-000, et al.3 (Order Directing Compliance) by \nproposing, among other things, to revise the Tariff provisions applicable to retail Behind-the-\nMeter Generation (BTMG).  For the avoidance of doubt, Appalachian Voices submits these \ncomments to seek clarification that the Compliance Filing’s proposed 50 MW materiality \nthreshold for BTMG applies to the aggregate capacity of all generation resources at a single \ncustomer site, rather than to each individual generating unit.  If PJM intended that this threshold \napply only to individual units, Appalachian Voices urges the Commission to reject this aspect of \nthe Compliance Filing and direct further compliance.  \nI. \nBACKGROUND \nThe proliferation of data centers has raised difficult questions about the impacts their \ninterconnection and the associated generation they require will have on other users of the grid, \n \n1 18 C.F.R. § 385.211 (2025).  \n2 PJM Interconnection, L.L.C., Compliance Filing, Transmittal Letter, at 11-12 (filed Feb. 23, 2026) (Compliance \nFiling). \n3 PJM Interconnection, L.L.C., 193 FERC ¶ 61,217, at P 2 (2025) (Order Directing Compliance)."},{"page":2,"startToken":271,"endToken":638,"text":"2 \n \nparticularly in the PJM region.  To address some of these challenges, the Commission issued an \norder on February 20, 2025, directing PJM to show cause as to why its Tariff remains just and \nreasonable and not unduly discriminatory or preferential without specific provisions addressing \nservice to co-location arrangements between large loads and generators.4  In response to public \ncomment, the Commission issued the Order Directing Compliance on December 18, 2025, \ndirecting PJM to revise its Tariff to set forth specific terms and conditions for customers seeking \nto interconnect load co-located with generation.5   \nThe Commission’s compliance directives included a requirement that PJM revise its \nTariff provisions related to retail BTMG.  PJM’s Tariff defines BTMG as “a generation unit that \ndelivers energy to load without using the Transmission System or any distribution facilities[.]”6  \nCurrently, the Tariff allows load serving entities that serve loads with BTMG to reduce their level \nof service and the associated costs by netting output from the BTMG in the calculation of their \npeak demand for the purpose of determining Network Integration Transmission Service charges.7   \nIn its Order Directing Compliance, the Commission found that changed circumstances \nhave made PJM’s existing Tariff provisions unjust and unreasonable, citing PJM’s own \nconclusion that the existing rules were “conceived for, and [have] been implemented for, \nsubstantially smaller loads . . . and not on the scale of large data centers.”8   Again echoing PJM, \nthe Commission noted that “[a]llowing very large loads like data centers to net is problematic \nbecause loads in this configuration do not carry reserves.”9  Yet, because load serving entities \nmust nevertheless serve these loads, the current rules would allow these loads to “lean on the \n \n4 PJM Interconnection, L.L.C., 190 FERC ¶ 61,115, at P 2 (2025).  \n5 Order Directing Compliance at P 2.  \n6 PJM, Intra-PJM Tariffs, OATT, § I.1 Definitions – A-B (21.0.0). \n7 PJM, Intra-PJM Tariffs, OATT, § III.34.2 Netting of Behind the Meter Generation (0.0.0). \n8 Order Directing Compliance at P 186 (citing PJM Interconnection, L.L.C., Answer, Docket No. EL25-49-000, et \nal., at 13 (filed Mar. 24, 2025) (PJM March 24th Answer)).  \n9 Id. (citing PJM March 24th Answer at 36)."},{"page":3,"startToken":638,"endToken":944,"text":"3 \n \nPJM system when the co-located generation is on a full or partial outage or if the load exceeds \nthe rating of the co-located generation.”10  The Commission concluded, therefore, that because \nPJM’s existing rules do not limit the amount of qualifying load that a Network Customer may net \nby using BTMG, PJM’s operative Tariff provisions “are no longer consistent with cost causation \nprinciples, because large loads configured in a BTMG arrangement with significant generation \nwill raise cost shifting concerns compared to loads pursuing smaller amounts of netting.”11  The \nCommission concluded that this could create reliability and resource adequacy risks. \nAs a result, the Commission directed PJM to revise the BTMG provisions in its Tariff.12  \nThe Commission acknowledged, however, that not all loads using BTMG are large enough to \ncreate reliability and resource adequacy risks.  The Commission therefore directed PJM “to \npropose a new MW threshold for the amount of load at a particular electrical location that \nNetwork Customers may net by using” BTMG.13   \nOn February 23, 2026, PJM submitted its Compliance Filing.  As relevant here, in its \ntransmittal letter, PJM proposed “to establish a materiality threshold of up to 50 MW for a \ngenerator at the same electrical location as the Network Load for generation units to qualify as \nRetail BTMG.”14  PJM proposed the following Tariff language to effectuate its materiality \nthreshold: “‘Retail Behind The Meter Generation’ shall refer to Behind The Meter Generation \nthat is used to serve a retail load served by a Network Customer located at the same electrical \nlocation, where such generation has a cumulative nameplate rating of no greater than 50 \nMW[.]”15 \n \n10 Id. (citing PJM March 24th Answer at 13 n.5). \n11 Id. \n12 Id. at P 221.  \n13 Id.  \n14 Compliance Filing, Transmittal Letter, at 11-12.  \n15 Id., Attach. A at 51."},{"page":4,"startToken":944,"endToken":1244,"text":"4 \n \nII. \nCOMMENTS OR, IN THE ALTERNATIVE, LIMITED PROTEST \nPJM’s proposed Tariff language sets the materiality threshold for BTMG at “a cumulative \nnameplate rating of no greater than 50 MW[.]”16  This would appear to subject all generation at a \nsingle customer site to a collective threshold of 50 MW for BTMG purposes, in keeping with the \nOrder Directing Compliance’s requirements.  However, PJM’s transmittal letter injects \nuncertainty into this application by stating that the 50 MW threshold applies to “a generator at \nthe same electrical location as the Network Load[.]”17  These equivocal descriptions make it \nunclear whether PJM intends the 50 MW threshold to apply to the aggregate nameplate ratings of \nall generation at a single site or only to each individual generator at the same electrical location \nas network load.  \nApplying the latter interpretation would undermine the Commission’s purpose in \nrequiring a materiality threshold in the first place.  The Commission required PJM to propose a \nmateriality threshold “because large loads configured in a BTMG arrangement with significant \ngeneration will raise cost shifting concerns compared to loads pursuing smaller amounts of \nnetting[,]”18 which, in turn, could create reliability and resource adequacy risks.  Applying the 50 \nMW materiality threshold separately to multiple, individual BTMG facilities at the same \nelectrical location as Network Load would not address this concern.  It would create a loophole \nwhereby load co-located with significant generation in the form of several generators under 50 \nMW could subtract their collective nameplate capacity from its peak load and effectively operate \noutside the constraints and oversight PJM proposes in the rest of its compliance filing.  This \n \n16 Id., Attach. A at 51 (emphasis added).  \n17 Id., Transmittal Letter, at 11-12 (applying the 50 MW threshold to “a generator at the same electrical location as \nthe Network Load[.]”).   \n18 Id."},{"page":5,"startToken":1244,"endToken":1470,"text":"5 \n \nwould unjustly and unreasonably shift costs and exacerbate the reliability and resource adequacy \nrisks the Commission has already identified.  \nAccordingly, for the avoidance of doubt, Appalachian Voices seeks clarification that \nPJM’s proposed Tariff language would establish a materiality threshold for Retail BTMG of no \nmore than 50 MW, inclusive of all generation at the same electrical location, despite the \nambiguous language in its transmittal letter.19  In the alternative, to the extent PJM’s proposed \nmateriality threshold of 50 MW would apply individually to multiple generators at the same \nelectrical location, Appalachian Voices requests that the Commission reject PJM’s proposal and \nrequire further compliance. \nIII. \nCONCLUSION  \nFor the foregoing reasons, Appalachian Voices respectfully requests the clarification \ndescribed above.  In the alternative, Appalachian Voices respectfully asks that the Commission \nreject this aspect of PJM’s Compliance Filing and require further compliance.  \n \n \n \n \n \n \n \n \n \nRespectfully submitted, \n \n \n \n \n \n \n \n \n/s/ Nicholas J. Guidi \n \n \n \n \n \n \n \nNicholas J. Guidi \n \n \n \n \n \n \n \nSenior Attorney \n \n \n \n \n \n \n \nSouthern Environmental Law Center \n \n \n \n \n \n \n \n500 New Jersey Ave NW, Suite 600 \n \n \n \n \n \n \n \nWashington, DC 20001 \n \n \n \n \n \n \n \nnguidi@selc.org \n \n \n \n \n \n \n \n \n/s/ Katherine L. Rogers \nKatherine L. Rogers \n \n \n \n \n \n \n \nAssociate Attorney \n \n \n \n \n \n \n \nSouthern Environmental Law Center \n \n \n \n \n \n \n \n500 New Jersey Ave NW, Suite 600 \n \n19 See PJM Interconnection, L.L.C., 164 FERC ¶ 61,170, at P 37 (2018) (“Commission precedent is clear that in the \nevent of a conflict between pleadings and proposed tariff language, the tariff language controls.”) (internal citations \nomitted))."},{"page":6,"startToken":1470,"endToken":1485,"text":"6 \n \n \n \n \n \n \n \n \nWashington, DC 20001 \n \n \n \n \n \n \n \nkrogers@selc.org \n \n \n \n \n \n \n \n \nCounsel for Appalachian Voices \n \nDate: March 16, 2026"},{"page":7,"startToken":1485,"endToken":1544,"text":"CERTIFICATE OF SERVICE \nPursuant to Rule 2010 of the Commission’s Rules of Practice and Procedure, I hereby \ncertify that I have this day served a copy of the foregoing on all persons designated on the \nofficial service list compiled by the Secretary in this proceeding.  \nDated this 16th day of March 2026.  \n \n/s/ Katherine L. Rogers  \nKatherine L. Rogers"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":1,"endAt":1436,"startToken":0,"endToken":198},{"p":1,"at":1436,"title":"I. BACKGROUND","method":"printed heading","endPage":4,"endAt":5,"startToken":198,"endToken":945},{"p":4,"at":5,"title":"II. COMMENTS OR, IN THE ALTERNATIVE, LIMITED PROTEST","method":"printed heading","endPage":5,"endAt":737,"startToken":945,"endToken":1348},{"p":5,"at":737,"title":"III. CONCLUSION","method":"printed heading","endPage":7,"endAt":0,"startToken":1348,"endToken":1485},{"p":7,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":7,"endAt":357,"startToken":1485,"endToken":1544}]}