{"document":{"slug":"rec-20260316-5346","title":"Protest and Comments of Constellation Energy Generation, LLC in response to PJM Interconnection, L.L.C.’s 02/23/2026 60-Day Compliance Filing","issued":"2026-03-16","accession":"20260316-5346","docket":"ER26-1479-000","group":"PJM co-location compliance","filer":"Constellation Energy Generation, LLC","kind":"protest","file":"sources/filings/text/20260316-5346_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260316-5346","tier":"record","sha256":"103941dad9c04bdeff0976f5d6f71688bf92c070164f80487494fe66da64e311","pages":22,"tokens":7428,"emptyPages":[],"textThemes":["colo","study","flex","retail"]},"pages":[{"page":1,"startToken":0,"endToken":352,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \nPJM Interconnection, L.L.C.\n) \nDocket No. ER26-1479-000 \nPROTEST AND COMMENTS OF CONSTELLATION ENERGY GENERATION, LLC  \nConstellation1 protests limited provisions in PJM’s Sixty-Day Compliance Filing2 that are \nnon-compliant with the Commission’s December 18, 2025 Order3 because they fail “to make the \ndirected changes.”4 First, the replacement of “Point of Interconnection” in the definition of Co-\nLocated Load with “Point of Change in Ownership” contradicts the Commission’s order. Second, \nthe proposed Behind the Meter Generation (“BTMG”) rules expand BTMG to include a 50-MW \nthreshold and thus create a large class of favored resources at the expense of Co-Located Load. \nConstellation also seeks clarification of PJM’s filing in several other areas to ensure compliance, \nto accelerate the interconnection of large loads, and to prevent undue discrimination against Co-\nLocated Load and the generators seeking to serve it. \nPROTEST \nIn two important areas, PJM’s proposal is outside the scope of compliance, falls short of \nthe Commission’s intent, and perpetuates existing undue discrimination that has delayed the \ninterconnection of large loads for years. \n \n1 Constellation Energy Generation, LLC (“Constellation”) files this protest pursuant to Rule 211 of the Commission’s \nRules of Practice and Procedure. 18 C.F.R. § 385.211 (2025). \n2 PJM Interconnection, L.L.C., Sixty-Day Compliance Filing for Co-Located Load Related Revisions to Open Access \nTransmission Tariff to Comply with Commission Order in Docket No. EL25-49-000, et al., Docket No. ER26-1479-\n000 (Feb. 23, 2026) (“Sixty-Day Compliance Filing”). \n3 PJM Interconnection, L.L.C., 193 FERC ¶ 61,217 (2025) (“December 18th Order”). \n4 NorthWestern Corp., 113 FERC ¶ 61,215, at P 9 (2005) (“The Commission has long established that compliance \nfilings must be limited to the specific directives ordered by the Commission. The purpose of a compliance filing is \nto make the directed changes and the Commission’s focus in reviewing them is whether or not they comply with the \nCommission’s previously-stated directives.”); see also Cal. Power Exch. Corp., 101 FERC ¶ 61,330, at P 25 (2002) \n(“The purpose of a compliance filing is to make only the revisions directed by the Commission.”)."},{"page":2,"startToken":352,"endToken":800,"text":"2 \nI. \nThe Commission Should Reject PJM’s New Definition of Co-Located Load as Outside \nthe Scope of Compliance, or in the Alternative, Require Further Modification \nAs with PJM’s Thirty-Day Compliance Filing,5 the Commission should reject PJM’s \nproposal to use its Sixty-Day Compliance Filing to replace the Commission-mandated “Point of \nInterconnection” in the definition of Co-Located Load with the “Point of Change in Ownership.”6 \nChanging the specific definition of Co-Located Load already approved by the Commission is \noutside the scope of compliance. The December 18th Order adopted the following definition of \nCo-Located Load: “a ‘configuration [that] refers to end-use customer load that is physically \nconnected to the facilities of an existing or planned Customer Facility on the Interconnection \nCustomer’s side of the Point of Interconnection to the PJM Transmission System.’”7 The \nCommission neither sought comment on nor directed PJM to propose a new definition of Co-\nLocated Load. Nor did the December 18th Order permit PJM to propose variations that PJM \nconsidered were “consistent with or superior to” the Commission’s adopted definition as the \nCommission does with amendments to the pro forma Generator Interconnection Agreements.8 \n \n5 See Comments and Conditional Protest of Constellation Energy, Docket No. ER26-1088-000 (Feb. 10, 2026) \n(“Constellation’s Thirty-Day Compliance Filing Comments”); id. at 5 (“The Commission must ensure that \nTransmission Owners are not permitted to exploit the interconnection process to continue to deny, delay, encumber, \nor tie interconnection services for large load configurations that they disfavor. Accordingly, the Commission should \nreject PJM’s new definition of Co-Located Load.”). \n6 See Sixty-Day Compliance Filing at 31-35; id. at Exhibit B (“Marked Tariff”) at 12, 74-75, 81-82. \n7 December 18th Order, 193 FERC ¶ 61,217 at P 164. \n8 Non-RTO/ISO transmission providers seeking deviations from the pro forma generator interconnection procedures \nand agreements must demonstrate that such deviations are “consistent with or superior to” the pro forma provisions. \nSee Standardization of Generator Interconnection Agreements and Procedures, Order No. 2003, 104 FERC \n¶ 61,103, at PP 825-26 (2003) (establishing the “consistent with or superior to” standard for non-RTO/ISO \ntransmission providers seeking variations from the pro forma Large Generator Interconnection Process (“LGIP”) \nand Large Generator Interconnection Agreement (“LGIA”), drawing from the approach taken in Order No. 888 for \nvariations from the OATT); Reform of Generator Interconnection Procedures and Agreements, Order No. 845, 163 \nFERC ¶ 61,043, at P 43 (2018) (confirming that non-RTO/ISO transmission providers must justify variations as \n“consistent with or superior to” the pro forma LGIP or LGIA); Improvements to Generator Interconnection \nProcedures and Agreements, Order No. 2023, 184 FERC ¶ 61,054, at P 10 (2023) (continuing to apply the \n“consistent with or superior to” standard for non-RTO/ISO transmission providers)."},{"page":3,"startToken":800,"endToken":1301,"text":"3 \nConsistent with the Federal Power Act and longstanding Commission precedent, if PJM “wished \nto depart from or challenge” the Commission’s adoption of PJM’s definition of Co-Located Load, \nit “should have filed for rehearing” of the December 18th Order.9 PJM did not do so. In fact, PJM \nhad multiple opportunities to express concerns with the Commission “adopt[ing] PJM’s \ndefinition.”10 The Commission should “not allow [PJM] to pursue such matters on compliance” \nand should reject PJM’s departure from the Order.11 \nSubsequent discussions between PJM and Constellation have not resolved Constellation’s \nconcerns regarding PJM’s definition.12 The “Point of Change in Ownership” definition will not \n“afford[] greater certainty to all interconnection parties.”13 PJM overlooks the record evidence of \ndiscrimination by Transmission Owners against Co-Located Load that does not connect directly \nwith the Transmission Owner. Using the “Point of Change in Ownership” could give the \nTransmission Owner an additional tool to discriminate against competing projects.14 Unlike the \n \n9 16 U.S.C. § 825l; see also, e.g., Ne. Utils. Serv. Co., 74 FERC ¶ 61,355, at n.10 (1996).  \n10 PJM Interconnection, L.L.C., 190 FERC ¶ 61,115, at PP 3-4 (2025). \n11 Ne. Utils. Serv. Co., 74 FERC ¶ 61,355 at n.10 (“We will direct that these provisos be deleted. They are outside the \nscope of the compliance filing ordered. If the NU companies had wished to depart from or challenge our conditions, \nthey should have filed for rehearing. They did not do so and we will not allow them to pursue such matters on \ncompliance.”); see also Nev. Power Co., 157 FERC ¶ 61,230, at P 54 (2016) (“We find that Barrick Mines’ \ncomments are an attempt to revisit issues the Commission has already decided and are outside the scope of the \ncompliance filing. Barrick Mines was a party to the section 206 proceeding and could have sought rehearing of the \nJune 9 Order. Instead, their comments in this compliance filing proceeding constitute a collateral attack on the \nJune 9 Order.”) (emphasis added). \n12 See Sixty-Day Compliance Filing at 33 (stating that “these concerns have benefited from discussion and further \nconsideration”). PJM has not withdrawn its new definition of Co-Located Load. \n13 Id. at 33-34. \n14 See, e.g., Complaint Requesting Fast Track Processing of Constellation Energy Generation, LLC, Constellation \nEnergy Generation, LLC v. PJM Interconnection, L.L.C., Docket No. EL25-20-000 at 7 (Nov. 22, 2024) (“Exelon \nis refusing to process necessary studies on these grounds, demanding expensive upgrades under their unfiled \ninterconnection procedures, delaying agreed-upon work which will force a nuclear plant to take additional outages, \nand forcing additional services to be procured.”) (“Constellation Complaint”); id at 7-8. (“Exelon fulfilled its \nresponsibilities as an interconnection provider to review PJM’s necessary studies for one Constellation nuclear \nstation, the LaSalle Clean Energy Center (‘LaSalle’), but later refused to do so at the other two stations, insisting \nthat Constellation or its potential customer must first apply for retail service and designate what sort of wholesale"},{"page":4,"startToken":1301,"endToken":1973,"text":"4 \n“Point of Change in Ownership,” the “Point of Interconnection” is a defined physical point where \nthe Interconnection Facilities connect to the grid.15 If parties cannot agree on the location of the \nPoint of Interconnection, there is a Tariff process for resolving the disagreement that helps prevent \ndiscrimination and unreasonable outcomes.16 By contrast, the “Point of Change in Ownership” is \nnot a defined physical point. A Transmission Owner could determine that equipment to serve the \nload is not “necessary to physically and electrically interconnect the Generating Facility with the \n \ntransmission service it will take from Exelon.”); id. at 17 (“But for Constellation’s … Limerick Clean Energy Center \n(‘Limerick’) in Pennsylvania, Exelon has refused to conduct its review of PJM’s completed necessary studies, \ninsisting that Constellation or its potential customer must first apply for retail service and designate what sort of \nwholesale transmission service it will take from Exelon.”); Constellation Complaint at 8 (“projects are being held \nhostage by a few monopolies refusing to cooperate with reliability studies related to interconnection modifications”); \nid. at 10 n.25 (“Exelon refuses to review co-location reliability studies as required by the OATT and pro forma ISA”) \n(citing Constellation PDO Protest, Exhibit 1, Declaration of James R. McCoskey at ¶ 13); id. at 16 (“Proposed Fully \nIsolated Co-Located data center projects in PJM are currently being held hostage by one or two monopoly utilities’ \nrefusal to cooperate … with reliability studies related to interconnection modifications.”); see also Supporting \nComments of Constellation Energy Generation, LLC, Interconnection of Large Loads to the Interstate Transmission \nSystem, Docket No. RM26-4-000, at 3-4 (Nov. 21, 2025) (“Some Transmission Owners have simply refused to \nparticipate in PJM’s studies to analyze reliability impacts; and some, acting under unfiled interconnection study \nprocedures, have changed their entire construct and timetable for processing load studies.”) (“Constellation ANOPR \nComments”); Answer of Constellation Energy Generation, LLC, PJM Interconnection, L.L.C. et al., Docket Nos. \nEL25-49-000, et al., at 3 (Apr. 23, 2025) (“The Indicated Transmission Owners read the existing Tariff to require \nthis one-size-fits-all limitation, and they have refused to perform studies for new load seeking a different \nconfiguration.”); id. at 7 (“What is more, regardless of what the Tariff actually says and does not say, some of the \nIndicated Transmission Owners have refused to cooperate in PJM’s ‘necessary studies’ process unless the load \nagrees to taking NITS, claiming justification under the Tariff. Some of the Indicated Transmission Owners have \nrefused to process necessary studies, demanded expensive upgrades under their unfiled interconnection procedures, \nand forced a generator seeking to serve co-located load to procure additional services not required by the Tariff.”) \n(citing Constellation Complaint at 7); Constellation Complaint at 9 (“Exelon’s also is refusing to perform work on \nLaSalle’s interconnection facilities to accommodate co-location, none of which affects the grid. Exelon’s refusal to \ncomplete previously agreed-upon work as scheduled during an upcoming planned outage will increase costs to \nConstellation by $15.3- $19 million at that site alone, just so Exelon can pursue its litigation positions.”); see also \nPJM Interconnection, L.L.C., 190 FERC ¶ 61,115, at P 75 (“there are allegations in the record that Exelon has \ndelayed work on Constellation’s requests to co-locate load with its generators at certain facilities due to Exelon’s \nconcerns that such requests are not allowed under the Tariff without arranging for wholesale transmission or retail \ndistribution service.”). \n15 OATT, Part VIII.A 400 Definitions (“‘Point of Interconnection’ shall mean the point or points where the \nInterconnection Facilities connect with the Transmission System.’”). \n16 Id. at Part IX.B GIA, Appendix 2 Standard Terms and Conditions, § 2.1 (“The location of the Point of \nInterconnection shall be mutually agreed by the Interconnected Entities, provided, however, that if the \nInterconnected Entities are unable to agree on the Point of Interconnection, the Transmission Provider shall \ndetermine the Point of Interconnection, provided that Transmission Provider shall not select a Point of \nInterconnection that would impose excessive costs on either of the Interconnected Entities and shall take material \nsystem reliability considerations into account in such selection.”)."},{"page":5,"startToken":1973,"endToken":2148,"text":"5 \nTransmission System,”17 and take the position that the equipment is a Transmission Owner \nInterconnection Facility18 instead of a Project Developer Interconnection Facility. The \nTransmission Owner could assert that the equipment and load both fall on the Transmission \nOwner’s side of the Point of Change in Ownership and no longer qualify as Co-Located Load. \nBelow is an illustration of a hypothetical example to demonstrate this point. Even if such claims \nmight eventually be overturned by the Commission, changing the definition of Co-Located Load \nwould allow Transmission Owners to use the determination of the Point of Change in Ownership \nto cause unnecessary delay or other mischief for large load projects seeking speed to service from \ncompetitive suppliers. \n \n \n17 Id. at Part VIII.A 400 Definitions (“‘Point of Change in Ownership’ shall mean the point, as set forth Schedule B \nof the Generation Interconnection Agreement, where the Project Developer’s Interconnection Facilities connect to \nthe Transmission Owner’s Interconnection Facilities.”). \n18 Id. (“‘Transmission Owner Interconnection Facilities’ shall mean all Interconnection Facilities that are not Project \nDeveloper Interconnection Facilities.”)."},{"page":6,"startToken":2148,"endToken":2480,"text":"6 \nConstellation’s example of a new ring bus configuration added to accommodate a large \nload, included in its Thirty-Day Compliance Filing Comments, illustrates the difference, as shown \nabove.19 A ring bus allows the load to access supply from the generation facility and the grid. \nUsing the “Point of Interconnection” to define Co-Located Load allows any load connected on the \nring bus to be included as Co-Located Load—even if the Transmission Owner owns some or all \nof the new facilities on the ring bus. By contrast, using “Point of Change in Ownership” to define \nCo-Located Load could allow a Transmission Owner that owns some or all of the new facilities to \nassert the ring bus is not a Project Developer Interconnection Facility, thereby preventing the load \nfrom qualifying as a Co-Located Load at all. \nPJM’s justification for using the Point of Change in Ownership misses the mark because it \nignores the fact that new facilities will need to be added to tie in the new large loads and that \ngenerators do not have sole control over the configuration of these facilities and instead are subject \nto Transmission Owner and PJM interconnection specifications, with any attempt to dispute \nTransmission Owner requirements resulting in an interconnection delay.  \nIndicated Transmission Owners argue that Constellation’s concerns are “unsubstantiated” \nand “speculative.”20 This is incorrect. Significant record evidence shows that the Transmission \nOwners have engaged in discriminatory conduct to frustrate Co-Located Load configurations.21 \nThis includes, as the Indicated Transmission Owners acknowledge,22 letters sent by a PJM \nTransmission Owner stating it will resume work to allow Co-Located Load arrangements only if \n \n19 Constellation’s Thirty-Day Compliance Filing Comments at 5. \n20 Answer of Indicated PJM Transmission Owners, Docket No. ER26-1088-000, at 2 (Feb. 27, 2026) (“Indicated TO \nFeb. 27 Answer”). The Indicated PJM Transmission Owners are a subset of Transmission Owners in PJM, excluding \nPublic Service Electric and Gas Company, for example. \n21 See supra at note 14. \n22 Indicated TO Feb. 27 Answer at 3."},{"page":7,"startToken":2480,"endToken":2859,"text":"7 \nthe load submits an application for retail service.23 The Commission made preliminary findings \nregarding this record evidence,24 and it granted Constellation’s Complaint (except with regard to \nConstellation’s replacement rate of placing the PJM Guidance Document on file).25 \nThe Commission must ensure that Transmission Owners cannot exploit the study and \ninterconnection process to continue to deny, delay, encumber, or tie interconnection services for \nlarge load configurations that they disfavor. Alternatively, if the Commission accepts PJM’s \nproposed change from Point of Interconnection to Point of Change in Ownership, it should also \nadopt the same modifications Constellation proposed in its Thirty-Day Compliance Filing \nComments, grounded in the Commission’s broad authority to fashion a remedy.26 Specifically, the \nCommission should: \n Direct PJM to revise its Tariff to provide that PJM will determine the Point of \nChange in Ownership if the parties cannot agree, just as PJM currently does if the \nparties cannot agree on the Point of Interconnection.  \n Establish deadlines for Interconnected Entities to mutually agree to the location for \nPoint of Change in Ownership and for PJM to determine the location when mutual \nagreement cannot be reached. \n \n23 See Constellation Complaint, Attachment 1, at 2 (Exelon’s November 12, 2024 Letter) (“We continue to believe \nthere is no lawful path to interconnect end use load at LaSalle … without that load taking service as a retail customer \nof ComEd and we cannot continue to review proposals for co-location of end use load at LaSalle … on some other \nbasis. Furthermore, we will not be able to perform work at [LaSalle], including work during the upcoming refueling \noutage at LaSalle, without an application for retail service and the design addition identified above.”) (emphasis \nadded). \n24 The Commission did preliminarily find that the Transmission Owners had discriminated against co-located load, \nPJM Interconnection, L.L.C., 190 FERC ¶ 61,115 at P 75, and the Commission also obviously took numerous steps \nto clarify the rules and otherwise ensure that co-located loads could promptly connect to the grid. See December 18th \nOrder, 193 FERC ¶ 61,217 passim. \n25Id. PP 248-49. \n26 See Sixty-Day Compliance Filing at 33 (stating “one stakeholder’s conditional protest in Docket No. ER26-1088-\n000 offers another alternative for the Commission to consider in reliance on this Commission authority” “to fashion \na remedy”)."},{"page":8,"startToken":2859,"endToken":3318,"text":"8 \n Ensure that the location selected for the Point of Change in Ownership does not \neliminate the load from being Co-Located Load altogether unless the Project \nDeveloper and Co-Located Load desire it. \n Not tolerate any discrimination or delay and use its enforcement authority or other \nmechanisms to ensure non-discriminatory open access. \nThe substance of these modifications is unopposed.27 The Commission should not delay \nimplementing them if PJM’s new definition is accepted so that co-location arrangements can move \nforward as the Commission’s Order envisions, consistent with our national interest in winning the \nAI race.28 \nII. \nThe Commission Should Reject PJM’s 50-MW Materiality Threshold for BTMG, or in \nthe Alternative, Address Constellation’s Arguments on Undue Discrimination \nThe December 18th Order stated that because the Commission “direct[ed] changes to \nPJM’s existing BTMG rules” the Commission “decline[d]” to address Constellation’s argument \n“that charging all Eligible Customers taking transmission service on behalf of large Co-Located \nLoads for NITS based on a gross demand basis would be unduly discriminatory because it is \n \n27 See id. (discussion of the definitions of Co-Located Load, including as proposed in the Thirty-Day Compliance \nfiling filed on January 20, 2026 in Docket No. ER26-1088-000, not including any reference to Constellation’s \nproposed modifications); Answer of the Indicated Transmission Owners, Docket No. ER26-1088-000, at 2-3 (Feb. \n27, 2026) (did not challenge substance of modifications); Answer and Motion for Leave to Answer of the \nIndependent Market Monitor for PJM, Docket No. ER26-1088-000, at 2-3 (Feb. 25, 2026) (same). \n28 See Written Testimony of Laura V. Swett Chairman, Federal Energy Regulatory Commission, Before the U.S. \nHouse of Representatives, Committee on Energy and Commerce, Subcommittee on Energy, at 1-2 (Feb. 3, 2026) \nhttps://www.ferc.gov/news-events/news/testimony-laura-v-swett-chairman-federal-energy-regulatory-commission-\nus-house (“We’re in a global energy arms race created by the rise of technology, its tremendous load growth, and \nour push to onshore manufacturing and jobs. I want the United States to lead that race. This is the moment to cement \nAmerica’s energy leadership.”);  Written Testimony of Lindsay S. See Commissioner, Federal Energy Regulatory \nCommission, Before the U.S. House of Representatives, Committee on Energy and Commerce, Subcommittee on \nEnergy, at 3 (Feb. 3, 2026), https://cms.ferc.gov/news-events/news/testimony-lindsay-s-see-commissioner-federal-\nenergy-regulatory-commission (“our national imperative of speed to power and winning the AI race”); Written \nTestimony of David LaCerte Commissioner, Federal Energy Regulatory Commission, Before the U.S. House of \nRepresentatives, Committee on Energy and Commerce, Subcommittee on Energy, at 1 (Feb. 3, 2026), \nhttps://cms.ferc.gov/news-events/news/testimony-david-lacerte-commissioner-federal-energy-regulatory-\ncommission-house ) (“[T]he AI race, and even more importantly, who ultimately wins, will also fundamentally \ntransform how Americans engage, transact, and compete on the global stage. The AI race is here and America’s \npower grid is a major battlefield.”)."},{"page":9,"startToken":3318,"endToken":3735,"text":"9 \ninconsistent with the treatment of BTMG.”29 PJM’s compliance filing, however, expands \neligibility for future BTMG to a 50-MW threshold and thus substantially adds to the ability to \nunduly discriminate against Co-Located Load. \nPJM’s 50-MW materiality threshold for BTMG is 150 percent larger than the 20-MW \nthreshold suggested by the Commission based on the definition of a Small Generator and \n400 percent larger than the 10-MW threshold it suggested based on PJM’s requirement for \nindividual generator metering.30 This broadly expands the availability of new special behind-the-\nmeter generation arrangements that will be constructed, or will have sufficient backup \ngeneration,31 to fall under the 50-MW threshold to take advantage of netting, reduce their \ntransmission costs and otherwise receive preferential treatment over Co-Located Load. Combined \nwith PJM’s proposed legacy treatment,32 the exceptions allowing for netting will swallow the rule \nagainst it. A vast swath of new PJM generators and loads would be allowed to follow the precise \nBTMG rules that the Commission deemed “unjust and unreasonable.”33 \nUnder PJM’s proposed 50-MW threshold, a significant number of loads with BTMG would \nbe able to take advantage of netting and include backup generation as offsetting BTMG. Such \n \n29 December 18th Order, 193 FERC ¶ 61,217 at P 197 (citing Constellation April 23 Reply Comments at 31). \n30 Id. P 221 (“Although we make no finding in this order on a threshold that would be just and reasonable, we note as \npoints of reference that PJM requires any generator larger than 10 MW to be individually metered and that the \nCommission’s definition of a small generator is 20 MW.”) (citations omitted). \n31 See Sixty-Day Compliance Filing at 12-13; Marked Tariff at 49-50, 89-90. \n32 See Sixty-Day Compliance Filing at 8-11; Marked Tariff at 49-50, 89-90. In addition to granting legacy treatment \nto existing retail BTMG with contracts effectuating BTMG arrangements before the issuance of the December 18th \nOrder, PJM proposes to grant legacy treatment to existing retail BTMG that “otherwise have QF status.” Sixty-Day \nCompliance Filing at 10. As PJM acknowledges, the December 18th Order “does not reference” Qualifying Facilities \nor the Public Utility Regulatory Policies Act of 1978. Id. at 9. Constellation acknowledges that the PJM Industrial \nCustomer Coalition has sought rehearing on this issue. While Constellation does not take a position with respect to \nthe PJM Industrial Customer Coalition’s request, it does note that an exemption for all Qualifying Facilities would \nbe very large indeed. \n33 December 18th Order, 193 FERC ¶ 61,217 at P 179."},{"page":10,"startToken":3735,"endToken":4155,"text":"10 \ntreatment is not available to Co-Located Load even though there is “no physical, technical, or \neconomic reason why a netting construct should apply differently for customers with behind-the-\nmeter generation or co-located generation.”34 The December 18th Order required that “Eligible \nCustomers that elect to take NITS on behalf of Co-Located Loads … must … take NITS on a gross \ndemand basis”35 and PJM’s initial brief has no mechanism for Co-Located Load to offset with \nbackup generation.36   \nMoreover, none of PJM’s justifications for its 50-MW materiality threshold demonstrate \nthat the new threshold is a just and reasonable replacement rate. PJM states the “threshold aligns \nwith the PJM Board’s definition of large loads additions,”37 which PJM’s Board is proposing to \ninclude in Tariff and manual provisions being developed as a result of the Critical Issue Fast Path \nfor Large Load Additions.38 However, PJM provides no explanation for why that definition is \nrelevant to “reduc[ing] the reliability and resource adequacy risks that large or increasing BTMG \nmay pose to PJM.”39  \n \n34 Answer of Constellation Energy Generation, LLC, Docket No. EL25-49-000, et. al, (April 23, 2025) at Exhibit 2, \nTestimony of Zachary Ming at 55:17-19. \n35 December 18th Order, 193 FERC ¶ 61,217 at P 195; id. P 196 (“[W]e find that it would be unjust and unreasonable \nto allow Eligible Customers taking transmission service on behalf of Co-Located Loads to take NITS on a net \nbasis.”).  \n36 See Initial Brief of PJM Interconnection, L.L.C., Docket No. EL25-49-000, et. al, at 9 (Feb. 23, 2026) (“A Co-\nLocated Generating Facility will not always be available (e.g., due to planned or unforced outage). To the extent \nthat the gross demand of a Co-Located Load is not covered by the Eligible Customer’s Firm Contract Demand \nTransmission Service, the Eligible Customer must cover the remaining gross demand by applying for Non-Firm \nContract Demand Transmission Service. In that case, the Non-Firm Contract Demand Transmission Service, if PJM \ndetermines it is available for the requested period, will act as a backup to allow the Co-Located Load to meet its full \ndemand, while the portion of the Co-Located Generating Facility dedicated to the Co-Located Load is on outage and \nunable to provide energy.”). \n37 Sixty-Day Compliance Filing at 12. \n38 PJM, Board Decisional Letter on Critical Issue Fast Path – Large Load Additions (Jan. 16, 2026), \nhttps://www.pjm.com/-/media/DotCom/about-pjm/who-we-are/public-disclosures/2026/20260116-pjm-board-\nletter-re-results-of-the-cifp-process-large-load-additions.pdf. \n39 December 18th Order, 193 FERC ¶ 61,217 at P 179."},{"page":11,"startToken":4155,"endToken":4427,"text":"11 \nPJM also states that a 50-MW threshold would “avoid unneeded regulatory uncertainty for \nretail customers whose grid impacts on reliability are more limited”40 and “small or de minimis.”41 \nFifty MWs of power could serve a large town or small city.42 PJM provides no support for this \nclaim. In addition, PJM argues that “many of the existing Retail BTMG are decades old and may \nneed significant upgrades prior to directly interconnecting into the PJM system,” but “given the \ncosts associated with such significant upgrades, the owners of such resources may decide to forgo \nthe option of interconnecting into the PJM system altogether.”43 PJM again provides no support. \nNor does PJM explain how exempting load backed by capacity presumably unsuitable for \ninterconnection furthers the Commission’s goal of “reduc[ing] the reliability and resource \nadequacy risks that large or increasing BTMG may pose to PJM.”44 \nPJM’s 50-MW materiality threshold is unsupported and does not address Constellation’s \nundue discrimination arguments. The Commission should reject the threshold and direct further \ncompliance or require alternative modifications to address undue discrimination.  \nCOMMENTS \nThere are several other areas in the PJM compliance filing where clarification is needed or \nappropriate to ensure compliance with the December 18th Order. \n \n40 Sixty-Day Compliance Filing at 12. \n41 Id. \n42 See also The Law Dictionary, https://thelawdictionary.org/?s=de+minimis (defining “de minimis” as “a Latin phrase \nthat means of a trifling consequence and a matter that is so small that the court does not wish to even consider it.”). \n43 Sixty-Day Compliance Filing at 12-13. \n44 December 18th Order, 193 FERC ¶ 61,217 at P 179."},{"page":12,"startToken":4427,"endToken":4763,"text":"12 \nI. \nThe Commission Should Require PJM to Clarify the Necessary Studies Process for \nProject Developers to Ensure Speed to Market \nTo achieve speed to market, we recommend three clarifications to PJM’s proposed \nNecessary Studies Tariff language: (1) clarify the scope of the Necessary Studies analysis to ensure \nProject Developers are able provide the required information for PJM to timely complete its \nreviews; (2) clarify Project Developers with existing Necessary Studies for Co-Located Load \narrangements do not have to restart the Necessary Studies process and be further delayed; and \n(3) establish deadlines to complete the Necessary Studies process expeditiously and accelerate the \ninterconnection of Co-Located Loads.45  \nA. Additional Clarification on the Scope of the Necessary Studies Process Is \nNeeded \nAdditional clarity is needed regarding the scope of the Necessary Studies to be performed \nby PJM to ensure that Project Developers are able to provide the models and other information \nrequired for PJM to timely complete the Necessary Studies process.46 PJM proposes to define the \nscope of the Necessary Studies to “include thermal, short circuit, and stability studies under various \nseasonal and load conditions, as specified in more detail in the PJM Manuals.”47 It is not clear \nwhether PJM is proposing to use the existing Necessary Studies process or a new process. In \naddition, the Necessary Study Agreement requirements set forth in PJM Manual 14C do not \nspecifically reference the studies to be performed. To achieve the Commission’s goal of \n \n45 As PJM filed shells of the Service Agreements for the Interim Network Integration Transmission Service and \nContract Demand Service, we reserve our ability to comment on any necessary studies requirements. \n46 See PJM Manual 14C, § 1.9. \n47 See OATT, Part IV, Subpart G, § 2 (“Subject to this NSA, sections 4 through 14, Project Developer shall provide \nsufficient information regarding the Planned Modifications, including but not limited to relevant data, drawings, \nmodels, plans, and specifications, to enable Transmission Provider to evaluate the impact, if any, on the \nTransmission System of the Planned Modifications.”"},{"page":13,"startToken":4763,"endToken":5100,"text":"13 \n“provid[ing] additional clarity and transparency”48 and ensuring timely interconnection, the \nCommission should direct PJM to explain in a compliance filing the specific provisions in the PJM \nManuals to which it refers when PJM’s proposed language states, “as specified in more detail in \nthe PJM Manuals.” \nIn addition, the proposed Tariff’s scope of the analysis should also be revised to explicitly \nrelate to transmission system reliability, consistent with the Commission’s direction. The \nCommission “direct[ed] PJM to revise its Tariff to clarify the procedures for the study necessary \nto determine any modifications to interconnection facilities or Network Upgrades to the \ntransmission system PJM finds are needed to maintain transmission system reliability as a result \nof the Interconnection Customer’s request to modify its interconnection service level for an \nexisting generating facility to serve Co-Located Load.”49 The Commission was deliberate in \nwording this requirement to relate to transmission system reliability only, compared to other \nrequirements in the December 18th Order where the Commission considered both transmission \nreliability and resource adequacy.50  \nTo further this intent, Constellation proposes the below additions to the language at Tariff \nPart VIII, Subpart A, Section 401 (H)(3)(b)(ii) and (iii): \nii. Necessary Studies to be performed by Transmission Provider \ninclude thermal, short circuit, and stability studies under various \nseasonal and load conditions, as specified in more detail in the PJM \nManuals. Transmission Provider shall assess the impact on \nmaintaining transmission system reliability of the reduction in \nCapacity Interconnection Rights associated with the planned Co-\n \n48 December 18th Order, 193 FERC ¶ 61,217 at P 227. \n49 See id. P 161 (emphasis added); see also id. P 227 (the Necessary Studies process “should provide additional clarity \nand transparency regarding the steps that PJM and Interconnection Customers are taking to maintain transmission \nsystem reliability before an existing generating facility can serve Co-Located Load.” (emphasis added)). \n50 See, e.g., id. P 186 (describing how current BTMG arrangements “do not provide any protections against this \npotential transmission and resource adequacy planning problem.”)."},{"page":14,"startToken":5100,"endToken":5408,"text":"14 \nLocated Load and Co-Located Generating Facility, any necessary \ncontrol technologies and protection systems required as part of the \nCo-Located Load configuration, and any other changed conditions \nidentified by Project Developer or Transmission Owner associated \nwith the Co-Located Load configuration. \n \niii. Project Developer shall be responsible for the costs of any \nmodifications or Network Upgrades identified by Transmission \nProvider to maintain transmission system reliability, as applicable, \nas a result of the change to the Interconnection Service Agreement \nor Generation Interconnection Agreement to serve Co-Located \nLoad, including to reflect any reduction in Capacity Interconnection \nRights. Subject to Project Developer having a fully executed and \neffective Generation Interconnection Agreement governing a Co-\nLocated Load configuration, Project Developer may not begin \nserving Co-Located Load from the existing Generating Facility until \nall required Network Upgrades, necessary control technologies and \nprotection systems, and metering identified as necessary are \ncomplete and in service. \n \nThis clarification must be made in the Tariff. The scope of the Necessary Studies analysis, which \nwill determine the upgrades required, “significantly affect[s] rates, terms and conditions” of \nservice and is “readily susceptible to specification.”51 It should not be placed in PJM’s business \nmanuals where PJM has unilateral discretion.  \nB. New Requirements Regarding Necessary Studies Should Not Retroactively \nApply to Existing Necessary Studies \nThe PJM proposed Tariff language includes a new requirement that “Project Developer \nprovide Transmission Provider with all information needed to perform the Necessary Studies” \nincluding “the type of Transmission Service the Eligible Customer will take on behalf of the Co-\nLocated Load.”52 As this was not a requirement previously, existing study requests will not include \nthis information. Constellation requests clarification that Project Developers who have already \n \n51 Energy Storage Ass’n v. PJM Interconnection, L.L.C., 162 FERC ¶ 61,296 (2018). \n52 Marked Tariff, Part VII, Subpart A, section 401.H.3.b.(i)(b)."},{"page":15,"startToken":5408,"endToken":5774,"text":"15 \nsubmitted requests for Necessary Studies prior to implementation of these new requirements will \nbe allowed to rely on the results of those studies to the extent relevant in light of the transmission \nservice their co-located load plans to request. For example, to the extent that a generator submitted \na Necessary Study for a co-located load and notified PJM of its intent to delist its capacity (as \nthose were the rules in place at the time), and the study showed that no network upgrades beyond \na capacitor bank were needed, the Project Developer and Co-Located Load should not be forced \nto return to square one and wait for new Necessary Studies to be completed. \nGenerators such as Constellation that attempted in good faith to follow the process and \nwere stymied by a transmission owner’s refusal to cooperate should not be forced to wait for new \nNecessary Studies to be completed. It is a foundational principle of American administrative law \nthat “retroactivity is not favored in the law,” and that “administrative rules will not be construed \nto have retroactive effect unless their language requires this result.”53 This avoidance of retroactive \nimpact principle is solidly embodied in sections 205 and 206 of the Federal Power Act through the \nfiled-rate doctrine and rule against retroactive ratemaking. The retroactive application of new \nregulatory requirements would effectively penalize parties for failing to comply with rules that did \nnot exist at the time they acted—an outcome fundamentally at odds with the rule of law. Preserving \nthe progress made for projects already in process on the Necessary Studies is imperative given the \nextensive timelines associated with completing the study (approximately one year), modifying the \ngenerator interconnection agreement, and constructing any interconnection facilities. Currently it \ntakes PJM seven to ten years to complete the study process and build all the transmission upgrades \n \n53 Bowen v. Georgetown University Hospital, 488 U.S. 204, 208 (1988); As the Supreme Court explained in Landgraf \nv. USI Film Products, “[e]lementary considerations of fairness dictate that individuals should have an opportunity \nto know what the law is and to conform their conduct accordingly; settled expectations should not be lightly \ndisrupted.” 511 U.S. 244, 265 (1994)."},{"page":16,"startToken":5774,"endToken":6054,"text":"16 \nnecessary to provide NITS to a hyperscale data center.54 Co-location, and particularly the Firm \nContract Demand Service that requires delisting, were designed to provide a more expeditious \napproach, consistent with reliability. Resetting the existing and on-going processes for Necessary \nStudies to retroactively apply the new Tariff requirements to Project that have already submitted \ntheir study requests is inconsistent with reason, law, and national policy. The Commission should \nclarify that existing studies processes will not be required to pay and wait for a second study to \nmeet the new requirements. \nC. Speed to Market Demands Deadlines for Completing the Necessary Studies \nProcess \nThe Commission ruled that its designation of “Eligible Customer” would render requests \nthat the Commission “require transmission owners to cooperate in the necessary stud[ies] process \n… unnecessary.”55 PJM’s compliance language does not resolve these concerns that transmission \nowners could use their natural monopoly market power to delay other parties’ projects. \nSpecifically, PJM’s proposed requirement that “[t]he Eligible Customer has been designated to \ntake transmission service on behalf of a Co-Located Load in the Application and Study Agreement \nor the Generation Interconnection Agreement”56 does nothing to reduce concerns about, or affect, \nhow transmission owners approach Interconnection Customer’s requests to use their generating \nfacilities. Nor have existing Tariff provisions requiring the Interconnection Customer or the \nTransmission Owner to not withhold, condition, or delay agreement on modifications to facilities \n \n54 See Answer of Constellation Energy Generation (April 23, 2025) at 15; Patterson Aff. at ¶ 17; Kormos Aff. at ¶ 3 \n(citing examples); Stockton Declaration at 9, n.35 (citing examples). \n55 December 18th Order, 193 FERC ¶ 61,217 at P 226. \n56 Marked Tariff, Part III, §29.1."},{"page":17,"startToken":6054,"endToken":6394,"text":"17 \nbeen a successful deterrent.57 The delays associated with the Transmission Owners’ refusal to \nprocess Necessary Studies are well documented in the record.58 These delays could continue unless \nTransmission Owners are clearly required to do otherwise. To achieve speed to market, there must \nbe deadlines set forth in the Tariff to prevent needless and discriminatory delays. \nII. \nThe Proposed Definition of Co-Located Generating Facility Should Be Limited to the \nPortion of a Facility Serving Co-Located Load, Consistent with the Commission’s \nDirection \nThe Commission should direct that PJM modify its proposed definition of “Co-Located \nGenerating Facility” to confirm compliance with the December 18th Order. PJM proposes to \ndefine “Co-Located Generating Facility” as “an existing or planned Generating Facility that is \nphysically connected to a Co-Located Load.”59 PJM’s proposed definition could be interpreted as \napplying to the entire Generating Facility based solely on physical connection to a Co-Located \nload. However, the Commission recognized that a generating facility may not be entirely \ncommitted to a Co-Located Load, but instead in some cases only a “portion of the generating \nfacility [will] be designated to serve any Co-Located Load.”60 To conform the definition to the \nCommission’s intent, Constellation recommends that the Commission direct PJM to revise the \ndefinition to “mean the portion of an existing or planned Generating Facility that the \nInterconnection Customer designates to serve and is physically connected to a Co-Located Load.” \n \n57 See, e.g., Protest of Constellation Energy Generation, LLC, Exhibit 2, Document 9 at 1 (2024.09.05 Constellation \nLetter re Limerick) (citing 6.1.2 of the Generator Interconnection Agreement); Limerick Generator Interconnection \nAgreement filed in Docket No. ER00-803-003 (requiring “The design of the Modifications … shall be subject to \nreview and acceptance by the [Transmission Owner] which shall not be untimely nor unreasonably withheld.”). \n58 See supra note 14. \n59 Marked Tariff, Definitions C-D; Marked Tariff, Part VII, Subpart A, section 300, Definitions C; Tariff, Part VIII, \nSubpart A, section 400 Definitions C. \n60 See December 18th Order, 193 FERC ¶ 61,217 at P 230."},{"page":18,"startToken":6394,"endToken":6670,"text":"18 \nIII. \nThe Commission Should Require Other Modifications to Ensure Interim NITS \nProvisions Comply with the December 18th Order \nThree other simple modifications to PJM’s proposed Tariff revisions are needed to \neffectuate the December 18th Order’s mandate for Interim Network Integrated Transmission \nService. First, in Part III of the Tariff, a load’s “option to seek” Interim NITS should be replaced \nwith an “option to take.” This modification conforms the Tariff with the December 18th Order, \nwhich stated that Interim Network Integration Transmission Service “must allow an Eligible \nCustomer that has requested NITS on behalf of a Co-Located Load to take non-firm transmission \nservice that can be interrupted until the Network Upgrades necessary to provide NITS are \ncomplete.”61 As revised, Part III of the Tariff would read, “Eligible Customers taking transmission \nservice on behalf of Co-Located Load must take one of the following services: (1) Network \nIntegration Transmission Service under Tariff, Part III, with the option to take Interim Network \nIntegration Transmission Service….” \nSecond, Section 28.1 should be revised to clarify that Interim Network Integration \nTransmission Service is available to Eligible Customers taking service on behalf of Co-Located \nLoad. We recommend that Section 28.1 read, “Subject to the terms of the Tariff, Part III, Eligible \nCustomers taking service on behalf of Co-Located Load may also receive Network Integration \nTransmission Service [with the option to take Interim Network Integration Transmission \nService.]”62 \n \n61 Id. P 200. We also acknowledge that the Commission stated that Interim Network Integration Transmission Service \n“would only be available to the extent PJM determines that it can provide some level of interim service reliably.” \nId. \n62 Sixty-Day Compliance Filing at 62."},{"page":19,"startToken":6670,"endToken":7001,"text":"19 \nThird, similar to Section 28.1, Section 29.1 should be revised to read, “Any Eligible \nCustomer taking service on behalf of Co-Located Load must also satisfy these conditions to \nreceive Network Integration Transmission Service [and/or Interim Network Integration \nTransmission Service].”63 \nIV. \nThe Commission Should Clarify that Capacity Serving Non-Firm Load Need Not Delist \nand Direct Further Compliance  \nPJM’s proposed Tariff revisions direct that the “Project Developer shall provide \nTransmission Provider with all information needed to perform the Necessary Studies” including \n“the amount of reduction to Capacity Interconnection Rights to facilitate the Co-Located Load \nconfiguration.”64 PJM states this revision complies with the December 18th Order’s statement that \n“an existing generating facility may not begin serving Co-Located Load that is not Network Load \nuntil it has delisted its [Capacity Interconnection Rights] for the portion of the generating facility \nto be designated to serve any Co-Located Load that is not receiving NITS.”65 \nAs Constellation explained in its Request for Clarification, the Commission should clarify \nthat it did not intend to require a capacity resource to delist even when it has no obligation to serve \nthe Co-Located Load and remains fully capable of serving the grid during capacity emergencies.66 \nIndeed, the Commission should encourage arrangements in which Co-Located Load can receive \nnon-NITS service (such as non-firm contract service) and also curtail its reliance on the Co-\nLocated generator during capacity emergencies. Such an arrangement is consistent with existing \n \n63 Id. at 63-64. \n64 See id. at 25-26; Marked Tariff, Part VII, Subpart A, section 401.H.3.b.(i)(c).   \n65 December 18th Order, 193 FERC ¶ 61,217 at P 230 (citing PJM, Intra-PJM Tariffs, OATT, attach. DD.6, § 6.6 \nOffer Requirement for Capacity Resources (3.0.0); PJM March 24 Response at 58) (emphasis added); see Sixty-Day \nCompliance Filing at n. 83. \n66 Request for Clarification or, in the Alternative, Rehearing of Constellation Energy Generation, LLC, Docket \nNo. EL25-49-000, et. al, at 1-3 (Jan. 20, 2026)."},{"page":20,"startToken":7001,"endToken":7190,"text":"20 \nPJM rules; enables the speedy interconnection of new data center load, important to our economic \ncompetitiveness and national security; allows the co-location of that load, minimizing the need for \ngrid upgrades; and allows for the continued availability of the co-located generator to serve the \ngrid when it is needed to ensure resource adequacy. Forcing such capacity nevertheless to delist \nwould needlessly remove available capacity from serving the grid, inconsistent with PJM \nprecedent.67 \nUpon granting Constellation’s requested clarification or rehearing, the Commission could \ndirect PJM to revise its Tariff to clarify that only when capacity will serve physically firm \ncommitments must Project Developers declare the amount of reduction to Capacity \nInterconnection Rights to facilitate the Co-Located Load configuration. \n \n67 See PJM Interconnection, L.L.C., 192 FERC ¶ 61,135, at P 21 (2025) (the Commission’s analysis of whether a PJM \nproposal would be just and reasonable to count certain Reliability Must-Run (“RMR”) resources in the capacity \nmarket—despite the RMR units not being “a perfect substitute” for capacity—focused on “whether PJM can commit \nan RMR resource during emergency conditions to help meet the system’s resource adequacy needs”)."},{"page":21,"startToken":7190,"endToken":7350,"text":"21 \nCONCLUSION \nFor the reasons stated above, Constellation respectfully requests that the Commission grant \nthis protest and accept these comments and direct further compliance to ensure PJM’s Tariff \nfollows the directives of the December 18th Order. \n \n \n \n \n \n \n \n    Respectfully submitted, \n \n \n \n \n \n \n \n    /s/ Paul F. Wight \n \n \nMarch 16, 2026 \nCarrie Hill Allen \nSr. Vice President & Deputy General Counsel \nSeth T. Lucia \nAssistant General Counsel \nConstellation Energy Generation, LLC \n250 Massachusetts Ave. NW, Suite 760 \nWashington, D.C. 20001 \ncarrie.allen@constellation.com \nseth.lucia@constellation.com \n  \nChristopher A. Wilson \nManaging Director, Federal Regulatory Affairs \nConstellation Energy Generation, LLC \n250 Massachusetts Ave. NW, Suite 760 \nWashington, D.C. 20001 \n202-347-7500 \nFERCe-filings1@constellation.com \n \nPaul F. Wight \nCarolyn E. Clarkin \nDLA Piper LLP (US) \n500 Eighth Street NW \nWashington, D.C. 20004 \n703-773-4058 \npaul.wight@us.dlapiper.com  \ncarolyn.clarkin@us.dlapiper.com  \n \nSophia Browning \n4365 Executive Drive \nSuite 1100 \nSan Diego, CA 92121 \n858-677-1455 \nsophia.browning@us.dlapiper.com \n \nCounsel for Constellation Energy \nGeneration, LLC"},{"page":22,"startToken":7350,"endToken":7428,"text":"CERTIFICATE OF SERVICE \nI hereby certify that I have on this 16th day of March, 2026, caused to be served a copy of \nthe foregoing upon all parties on the service lists in these proceedings in accordance with the \nrequirement of Rule 2010 of the Commission’s Rules of Practice and Procedure, 18 C.F.R. \n§ 385.2010 (2025). \n/s/ Sophia Browning \n \n \nSophia Browning \n4365 Executive Drive \nSuite 1100 \nSan Diego, CA 92121 \n858-677-1455 \nsophia.browning@us.dlapiper.com"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":2,"endAt":3,"startToken":0,"endToken":353},{"p":2,"at":3,"title":"I. The Commission Should Reject PJM’s New Definition of Co-Located Load as Outside","method":"printed heading","endPage":8,"endAt":640,"startToken":353,"endToken":2954},{"p":8,"at":640,"title":"II. The Commission Should Reject PJM’s 50-MW Materiality Threshold for BTMG, or in","method":"printed heading","endPage":12,"endAt":4,"startToken":2954,"endToken":4428},{"p":12,"at":4,"title":"I. The Commission Should Require PJM to Clarify the Necessary Studies Process for","method":"printed heading","endPage":12,"endAt":739,"startToken":4428,"endToken":4534},{"p":12,"at":739,"title":"A. Additional Clarification on the Scope of the Necessary Studies Process Is","method":"printed heading","endPage":14,"endAt":1466,"startToken":4534,"endToken":5298},{"p":14,"at":1466,"title":"B. New Requirements Regarding Necessary Studies Should Not Retroactively","method":"printed heading","endPage":16,"endAt":621,"startToken":5298,"endToken":5865},{"p":16,"at":621,"title":"C. Speed to Market Demands Deadlines for Completing the Necessary Studies","method":"printed heading","endPage":17,"endAt":381,"startToken":5865,"endToken":6112},{"p":17,"at":381,"title":"II. The Proposed Definition of Co-Located Generating Facility Should Be Limited to the","method":"printed heading","endPage":18,"endAt":4,"startToken":6112,"endToken":6395},{"p":18,"at":4,"title":"III. The Commission Should Require Other Modifications to Ensure Interim NITS","method":"printed heading","endPage":19,"endAt":296,"startToken":6395,"endToken":6714},{"p":19,"at":296,"title":"IV. The Commission Should Clarify that Capacity Serving Non-Firm Load Need Not Delist","method":"printed heading","endPage":21,"endAt":4,"startToken":6714,"endToken":7191},{"p":21,"at":4,"title":"CONCLUSION","method":"printed heading","endPage":22,"endAt":0,"startToken":7191,"endToken":7350},{"p":22,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":22,"endAt":465,"startToken":7350,"endToken":7428}]}