{"document":{"slug":"rec-20260316-5351","title":"Limited Protest of American Municipal Power, Inc. to PJM Interconnection, L.L.C.’s 02/23/2026 Compliance filing","issued":"2026-03-16","accession":"20260316-5351","docket":"ER26-1479-000","group":"PJM co-location compliance","filer":"American Municipal Power, Inc.","kind":"protest","file":"sources/filings/text/20260316-5351_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260316-5351","tier":"record","sha256":"58b8a48a9b71bc7a070d3a12847b7a62c6783a37de0bc398a1eba3b1ba81e4a1","pages":10,"tokens":2791,"emptyPages":[],"textThemes":["colo"]},"pages":[{"page":1,"startToken":0,"endToken":292,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \nPJM Interconnection, L.L.C. \n) \nDocket No. ER26-1479-000 \nLIMITED PROTEST OF \nAMERICAN MUNICIPAL POWER, INC. \n \nAmerican Municipal Power, Inc. (“AMP”) hereby protests the February 23, 2026 \ncompliance filing by PJM Interconnection, L.L.C. (“PJM”) in the above-captioned docket,1 \nin which PJM proposes revisions to its Open Access Transmission Tariff (“Tariff”) to \ncomply with directives in the Federal Energy Regulatory Commission’s (“Commission” or \n“FERC”) December 18, 2025 order in Docket Nos. EL25-49-000, et al.2 As discussed \nbelow, AMP’s protest is limited to one specific aspect of the PJM Filing: the proposed \nrevised definition for Non-Retail Behind The Meter Generation (“Non-Retail BTMG”).3  \nI. \nBACKGROUND AND INTRODUCTION  \nUnder the existing PJM Tariff, load served by all Behind the Meter Generation \n(“BTMG”), and more particularly, Non-Retail BTMG is, subject to certain requirements \nand limitations, eligible to be netted from daily load under section 34.2 of the PJM Tariff \nfor purposes of calculating charges for Network Integration Transmission Service and \nother PJM charges.4 In the December 18 Order, the Commission found PJM’s existing \n \n1  PJM, 60-Day Compliance Filing for Co-Located Load Related Revisions to Open Access Transmission \nTariff to Comply with Commission Order in Docket No. EL25-49, et al., Docket No. ER26-1479-000 \n(February 23, 2026) (“PJM Filing”). \n2  PJM Interconnection, L.L.C., 193 FERC ¶ 61,217 (2025) (“December 18 Order”).  \n3  See PJM Filing, Transmittal Letter at 15-18; id. at Attachment B, p. 43. \n4  See, e.g., PJM Filing, Transmittal Letter at 4-6. PJM proposes to revise section 34.3 of the Tariff such \nthat it will now be the operative provision specifying the eligibility of Non-Retail BTMG to net against \nNetwork Load. See id. at 16 & n.48."},{"page":2,"startToken":292,"endToken":702,"text":"2 \nretail BTMG5 rules to be unjust and unreasonable, and directed PJM to revise the Tariff \nprovisions addressing certain generating units that are classified as retail BTMG.6 The \nCommission made clear, however, that it was not directing PJM to make any changes to \nits rules for Non-Retail BTMG.7 \nThe PJM Filing, submitted pursuant to section 206 of the Federal Power Act \n(“FPA”),8 proposes a number of changes to the Tariff provisions addressing BTMG, \nincluding a retail BTMG materiality threshold of 50 MW, and a three-year transition period \nfor existing retail BTMG.9 PJM also proposes new or revised Tariff definitions for Behind \nthe Meter Generation, Non-Retail Behind The Meter Generation, and Retail Behind The \nMeter Generation.10 In accordance with the Commission’s directions in the December 18 \nOrder, PJM indicates that it is not proposing any changes to the Tariff rules for Non-Retail \nBTMG.11 \nAMP and AMP’s load-serving utility members own and operate generating units in \nthe PJM region that qualify as Non-Retail BTMG. AMP therefore strongly supports the \n \n5  The December 18 Order notes that the Commission and others apply the label of “retail BTMG” to the \nclass of BTMG that does not qualify as Non-Retail BTMG, December 18 Order at P 7, while PJM’s filing \nincludes a new definition of “Retail Behind The Meter Generation,” e.g., PJM Filing, Transmittal Letter \nat 7; Attachment B, p. 89. \n6  Id. PP 179, 221-224. Specifically, the Commission directed PJM to “propose a new MW threshold for \nthe amount of load at a particular electrical location that Network Customers may net by using BTMG.” \nId. at P 221. Recognizing that customers may have relied on the existing BTMG rules, however, the \nCommission required PJM to maintain the current BTMG rules for customers that fall below the new \nMW threshold level. See id. at P 179. The Commission also adopted a transition process for “retail \nBTMG,” including a three-year transition period and grandfathering of certain parties with existing \ncontracts. See id. \n7  See id. at P 222. The Commission found that, given the existing Tariff limitation on the amount of Non-\nRetail BTMG that is eligible for netting, Non-Retail BTMG does not present the same resource adequacy \nand reliability concerns as BTMG. Id.; see also id. at P 179. \n8  See PJM Filing, Transmittal Letter at 1 (citing 16 U.S.C. § 824e). \n9  See id. at 11-15. \n10  See id. at 15-18. \n11  Id. at 7, 15-16."},{"page":3,"startToken":702,"endToken":988,"text":"3 \nCommission’s decision to preserve the current rules for Non-Retail BTMG. Likewise, AMP \nendorses PJM’s efforts to preserve the status quo as to those rules.12   \nAs discussed below, however, and notwithstanding PJM’s stated intent to preserve \nits existing Non-Retail BTMG rules in conformance with the Commission’s instructions, \nthe proposed revision to the definition of Non-Retail BTMG included in the PJM Filing \ncould be construed as preventing generating units that are merely eligible for application \nof the Non-Retail BTMG rules from ever participating in PJM’s newly established Co-\nLocated Load configurations. This literal reading would preclude a broad swath of PJM \ngenerators from supporting Co-Located Load because the set of generators eligible for \ntreatment as Non-Retail BTMG includes, without reservation, generators “used by \nmunicipal electric systems, electric cooperatives, or electric distribution companies to \nserve load.”13 \nSuch an outcome, which PJM has indicated is not what it intended, would be \nunjust, unreasonable, and unduly discriminatory. Further, revising the Non-Retail BTMG \ndefinition is unnecessary and outside the scope of the Commission’s compliance \ndirectives. Even if in-scope, the proposed revised definition is at best ambiguous, and \ncould be read to unjustifiably exclude otherwise eligible generation resources from \nparticipating in Co-Located Load configurations. Accordingly, in setting a just, reasonable, \nand not unduly discriminatory or preferential replacement rate in this compliance \nproceeding, the Commission should direct PJM to either revise the Tariff using the \n \n12  See id. at 16 (explaining that PJM is “seeking to avoid any inadvertent changes to the substantive rules \npertaining to Non-Retail Behind The Meter Generation,” and the proposed Tariff changes are intended \nto “preserve[] the status quo” regarding the ability of Non-Retail BTMG to net against load).  \n13 See PJM Filing, Attachment B, p. 43."},{"page":4,"startToken":988,"endToken":1389,"text":"4 \napproach suggested herein, or simply not revise the Tariff definition of Non-Retail BTMG, \nas discussed below. \nII. \nPROTEST \nA. \nPJM’s proposed definition of Non-Retail BTMG should be rejected \nbecause it is unnecessary and could exclude otherwise eligible \ngeneration facilities from Co-Located Load configurations. \nThe PJM Filing proposes the following revised Tariff definition of Non-Retail BTMG \n(new language underlined): \n“Non-Retail Behind The Meter Generation” shall mean Behind the \nMeter Generation that is used by municipal electric systems, electric \ncooperatives, or electric distribution companies to serve load. Any \nfacility that qualifies as a Non-Retail Behind The Meter Generation \nshall be excluded from Co-Located Load configurations.14 \nAs a threshold matter, there is no evident reason to modify the definition of Non-\nRetail BTMG as proposed by PJM. The PJM transmittal letter is silent as to why the \nunderlined language above has been added to the definition of Non-Retail BTMG, or why \nsuch language is needed to comply with the directives in the December 18 Order.15 \n \n14  PJM Filing, Attachment B, p. 43. This definition continues to define Non-Retail BTMG with reference to \nthe definition of BTMG, which PJM also proposes to clarify in the December 18 Order. PJM proposes \nthe following revised definition for BTMG (new language underlined): \n“Behind The Meter Generation” shall mean either Retail Behind the Meter \nGeneration or Non-Retail Behind The Meter Generation and refers to a generation \nunit that delivers energy to load without using the Transmission System or any \ndistribution facilities (unless the entity that owns or leases the distribution facilities \nhas consented to such use of the distribution facilities and such consent has been \ndemonstrated to the satisfaction of the Office of the Interconnection); provided, \nhowever, that Behind The Meter Generation does not include (i) at any time, any \nportion of such generating unit’s capacity that is designated as a Generation \nCapacity Resource or DER Capacity Aggregation Resource; or (ii) in an hour, any \nportion of the output of such generating unit that is sold to another entity for \nconsumption at another electrical location or into the PJM Interchange Energy \nMarket. \nPJM Filing, Attachment B, p. 80. \n15  PJM states that similar language in the definition of Retail BTMG “is intended to provide clarity and \ndirection to project developers about what pathways are available to serve load that is co-located, and \nto avoid unexpected and unintended hybrid scenarios mixing BTMG and the new transmission service"},{"page":5,"startToken":1389,"endToken":1745,"text":"5 \nIndeed, the Commission was clear that that it was “not direct[ing] PJM to change its rules \nfor non-retail BTMG.”16 Accordingly, the proposed revisions to the definition of Non-Retail \nBTMG should be rejected as outside the scope of the compliance filing.17  \nEven if PJM’s proposed changes to the definition of Non-Retail BTMG are deemed \nto fall within the scope of its compliance obligations, the revisions are at least ambiguous \nand could produce a result inconsistent with PJM’s stated intent and the Commission’s \ndirectives. The problem with PJM’s proposed definition of Non-Retail BTMG arises \nprincipally from the use of the word “qualifies” in the newly added text. For practical \npurposes, generation capacity that is designated as Non-Retail BTMG for load netting \npurposes under revised section 34.3 of the Tariff and is actually utilizing such netting \nprovisions and therefore “excluded from Co-Located Load configurations” in the event \nand to the extent that the generator output is netted against load, as PJM apparently \nintends to convey through the new definitional text, may not be denied access to relevant \nusable transmission service. But by triggering the exclusion from Co-Located Load \nconfigurations based on whether generation merely “qualifies” as Non-Retail BTMG \n(rather than focusing on whether it is actually engaged in netting and limiting the \npreclusion to the extent of that netting), the proposed definition sweeps too broadly. \nCurrently, generation “qualifies” as Non-Retail BTMG under the Tariff if it: (1) \nmeets the definition of BTMG; and (2) is “used by municipal electric systems, electric \n \nproducts the Commission has directed in the [December 18 Order].” PJM Filing, Transmittal Letter at \n18. As discussed herein, however, PJM’s proposed revised definition of Non-Retail BTMG would reduce \nthe clarity of options available to generation owners and developers considering pathways to serve co-\nlocated load under the Tariff. \n16  December 18 Order at P 222. \n17  See, e.g., PJM Interconnection, L.L.C., 173 FERC ¶ 61,244, at P 50 (2020) (explaining that \n“[c]ompliance filings must be limited to the specific directives ordered by the Commission,” and directing \nPJM to remove certain proposed Tariff provisions included in a compliance filing)."},{"page":6,"startToken":1745,"endToken":2017,"text":"6 \ncooperatives, or electric distribution companies to serve load.”18 Thus, any generating \nunit that could arguably fall within these criteria might be said to “qualify” as Non-Retail \nBTMG, even if the unit is not used to offset load for purposes of charges assessed under \nthe PJM Tariff. \nIt is possible that owners of generation resources including municipal electric \nsystems, electric cooperatives, or electric distribution companies (“EDCs”) with generator \ncapacity that is not netted against load (i.e., are not serving in whole or in part as Non-\nRetail BTMG) may seek to serve Co-Located Load, to the extent such resources are \notherwise eligible to do so under the PJM Tariff. Significantly, Part VIII, Subpart E, section \n415 of the currently effective Tariff allows Non-Retail BTMG resources to be partially \ntreated as Non-Retail BTMG and also to obtain Capacity Resource or Energy Resource \nstatus in PJM’s markets. Given that, there does not seem to be a valid rationale for \nexcluding these resources from a Co-Located Load configuration. \nBut to the extent that such resources might still be said to “qualify” as Non-Retail \nBTMG under the Tariff, these resources could be needlessly excluded from Co-Located \nLoad arrangements under PJM’s proposed revisions to the Non-Retail BTMG definition. \nPJM identifies no rationale for excluding otherwise eligible non-netting generation owned \nby municipal electric systems, electric cooperatives, or EDCs from participation in Co-\nLocated Load configurations simply because they might be deemed to “qualify” as Non-\nRetail BTMG. Such an (apparently unintentional) exclusion would frustrate the objective \nof making the three proposed new transmission service options available in these \n \n18  See PJM Filing, Attachment B, p. 43."},{"page":7,"startToken":2017,"endToken":2332,"text":"7 \ncircumstances to serve Co-Located Load, thereby restricting Co-Located Load from \naccessing service from this broad set of PJM generators. \nFinally, it is not clear that PJM’s proposed exclusionary language is needed in \nprinciple. To the extent that all or a portion of a municipal, cooperative, or EDC generator \nis engaged in netting under the existing Non-Retail BTMG Tariff provisions, the netted \nportion of its output necessarily will not need access to one of the three newly proposed \ntypes of transmission service. Furthermore, PJM has not explained on the record why it \nwould be reasonable to prohibit, for example, a municipal generating unit from serving a \nportion of a Co-Located Load, while the balance of that load is served from other \ngenerating resources or market purchases that are supported by any of the three new \ntypes of transmission service. Absent PJM’s proposed modification of the Non-Retail \nBTMG definition, it seems that the balance of PJM’s proposal, coupled with existing Tariff \nprovisions, would permit such a supply combination. Thus, without a rational explanation \nin the record, the Commission should reject PJM’s revisions to the Non-Retail BTMG \ndefinition as unduly discriminatory and inconsistent with the Commission’s directives in \nthe December 18 Order. \nB. \nAlternatively, the Commission should direct PJM to revise its \nproposed definition of Non-Retail BTMG. \nIf the Commission does not outright reject PJM’s revisions to the definition of Non-\nRetail BTMG, AMP proposes the following revised definition in lieu of PJM’s proposal:  \n“Non-Retail Behind The Meter Generation” shall mean Behind the \nMeter Generation that is used by municipal electric systems, electric \ncooperatives, or electric distribution companies to serve load. The \noutput from any facility that (1) qualifies as Non-Retail Behind The \nMeter Generation, and (2) is used for netting pursuant to Tariff, Part \nIII, \nsection \n34.3 shall \nbe \nexcluded \nfrom \nCo-Located \nLoad \nconfigurations, in the event of and to the extent of that netting."},{"page":8,"startToken":2332,"endToken":2585,"text":"8 \nAMP’s alternative preserves PJM’s apparent intent that generating capacity designated \nas Non-Retail BTMG for netting purposes should not be eligible for Co-Located Load \nconfigurations, while making clear that the mere fact that a generator, as a conceptual \nmatter, might qualify as Non-Retail BTMG does not render the generator wholly ineligible \nto participate in such configurations, to the extent it otherwise qualifies under the Tariff.  \n \nDirecting PJM to revise its proposal as described above is well within the \nCommission’s authority. PJM submitted its filing in this docket pursuant to FPA section \n206 for the purpose of establishing a just and reasonable replacement rate given the \nCommission’s finding that certain aspects of the existing PJM Tariff were unjust, \nunreasonable, and unduly discriminatory or preferential. The Commission has the \nobligation to fix the just and reasonable replacement rate,19 and it is not restricted to \naccepting or rejecting PJM’s compliance proposal submitted under FPA section 206.20 \n \n \n \n19  See, e.g., 16 U.S.C. § 824e(a); Advanced Energy Mgmt. All. v. FERC, 860 F.3d 656, 663 (D.C. Cir. \n2017) (citation modified) (“When the Commission changes an existing filed rate under section 206, it is \nthe Commission’s burden to prove the reasonableness of its change in methodology.”). \n20  See, e.g., Bldg. for the Future Through Elec. Reg’l Transmission Planning and Cost Allocation, Order \nNo. 1920-B, 191 FERC ¶ 61,026, at PP 46-51 (2025) (rejecting arguments that compliance filings in a \nFPA section 206 proceeding implicate public utilities’ FPA section 205 filing rights)."},{"page":9,"startToken":2585,"endToken":2727,"text":"9 \nIII. \nCONCLUSION \nWHEREFORE, for the foregoing reasons, American Municipal Power, Inc. \nrespectfully requests that the Commission reject PJM’s proposal to revise the existing \nTariff definition of Non-Retail BTMG as outside the scope of this compliance proceeding. \nEven if PJM’s proposed revisions to the Non-Retail BTMG definition are deemed to be \nwithin the scope of this proceeding, the Commission should direct PJM to revise the \nproposed definition of Non-Retail BTMG as described herein. \nRespectfully submitted, \n \n/s/ John McCaffrey               \nJohn McCaffrey \nStinson LLP  \n1775 Pennsylvania Avenue NW  \nSuite 800  \nWashington, DC 20006  \n(202) 728-3026  \njohn.mccaffrey@stinson.com \n \n \n \n \nDATED: March 16, 2026 \n/s/ Gerit F. Hull                                \nLisa G. McAlister                                                  \nSenior Vice President & General Counsel  \nGerit F. Hull                                                          \nDeputy General Counsel for Regulatory Affairs   \nAmerican Municipal Power, Inc.                           \n1111 Schrock Road, Suite 100  \nColumbus, OH 43229                                     \n(614) 540-1111 \nlmcalister@amppartners.org \nghull@amppartners.org"},{"page":10,"startToken":2727,"endToken":2791,"text":"CERTIFICATE OF SERVICE \n \nI hereby certify that I have this day served the foregoing document upon each \nperson designated on the official service list compiled by the Secretary in this proceeding. \nDated at Washington, D.C., this 16th day of March, 2026. \n/s/ John McCaffrey             \nJohn McCaffrey \nStinson LLP  \n1775 Pennsylvania Avenue NW  \nSuite 800  \nWashington, DC 20006  \n(202) 728-3026  \njohn.mccaffrey@stinson.com"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":1,"endAt":787,"startToken":0,"endToken":114},{"p":1,"at":787,"title":"I. BACKGROUND AND INTRODUCTION","method":"printed heading","endPage":4,"endAt":115,"startToken":114,"endToken":1005},{"p":4,"at":115,"title":"II. PROTEST","method":"printed heading","endPage":4,"endAt":129,"startToken":1005,"endToken":1007},{"p":4,"at":129,"title":"A. PJM’s proposed definition of Non-Retail BTMG should be rejected","method":"printed heading","endPage":7,"endAt":1308,"startToken":1007,"endToken":2217},{"p":7,"at":1308,"title":"B. Alternatively, the Commission should direct PJM to revise its","method":"printed heading","endPage":9,"endAt":3,"startToken":2217,"endToken":2586},{"p":9,"at":3,"title":"III. CONCLUSION","method":"printed heading","endPage":10,"endAt":0,"startToken":2586,"endToken":2727},{"p":10,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":10,"endAt":427,"startToken":2727,"endToken":2791}]}