{"document":{"slug":"rec-20260316-5371","title":"Protest of Maryland Office of People's Counsel re PJM Interconnection, L.L.C.’s compliance filing submitted on 02/23/2026","issued":"2026-03-16","accession":"20260316-5371","docket":"ER26-1479-000","group":"PJM co-location compliance","filer":"Maryland Office of People's Counsel","kind":"protest","file":"sources/filings/text/20260316-5371_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260316-5371","tier":"record","sha256":"d244d3d1df2d2cf06ccf1bd38f792c3bc5e43108881c5c61bd9fa5b3c80ad74a","pages":13,"tokens":2724,"emptyPages":[],"textThemes":["colo"]},"pages":[{"page":1,"startToken":0,"endToken":57,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \n \nPJM INTERCONNECTION, L.L.C.  \nDOCKET NO. ER26-1479-000 \n \n \n \nPROTEST OF THE MARYLAND OFFICE OF PEOPLE’S COUNSEL ON PJM \nCOMPLIANCE FILING \n \nMarch 16, 2026 \nDAVID S. LAPP \nPEOPLE’S COUNSEL \n \nWilliam F. Fields \nDeputy People’s Counsel \n \nPhilip L. Sussler  \nSenior Assistant People’s Counsel \n \nMark S. Byrd \nAssistant People’s Counsel"},{"page":2,"startToken":57,"endToken":247,"text":"1 \nPursuant to Rules 211 of the Federal Energy Regulatory Commission’s Rules of \nPractice and Procedure,1 the Maryland Office of People’s Counsel (“MdOPC”) \nrespectfully submits the following protest regarding PJM Interconnection, L.L.C.’s \n(“PJM”) compliance filing submitted on February 23, 2026 in the above captioned \nproceeding (hereinafter, “February 23 Compliance Filing”) that proposes tariff revisions \nwith respect to behind-the-meter generation, and services available for co-located load, \namong other proposed revisions, to implement the Commission’s December 18, 2025 \ncompliance directives in the co-located load show-cause proceeding (“Show Cause \nOrder”).2 \nINTRODUCTION \nPJM’s February 23 Compliance Filing proposes tariff revisions in compliance with \nthe Commission’s Show Cause Order, that attempt to create clarity and consistency with \nregard to the rates, terms, and conditions applicable to co-location arrangements. \nParticularly, the February 23 Compliance Filing proposes to clarify how both new and \nexisting generation can interconnect co-location arrangements.  \nHowever, PJM’s proposed revisions are incompatible with the Statement of \nPrinciples agreed by the White House-Governors, dated January 15, 2026 (hereinafter, \n \n1 18 C.F.R. §§ 385.211 (2025). \n2 PJM Interconnection, L.L.C., 193 FERC ¶ 61,217 (2025) (“Show Cause Order”)."},{"page":3,"startToken":247,"endToken":609,"text":"2 \nthe “Statement of Principles”)3, the Ratepayer Protection Pledge4 issued by the White \nHouse dated March 4, 2026, and PJM’s recent initiative toward implementing a reliability \nbackstop auction (“RBA”) that began after the Show Cause Order (and in response to the \nStatement of Principles), and which is intended to attract revenue specifically toward new \ngeneration—not existing generators.   \nThe proposed revisions contained in PJM’s February 23 Compliance Filing \ndirectly contradict PJM’s plan for the RBA. Whereas PJM’s proposed revisions facilitate \nco-location arrangements for both new and existing generators, PJM’s RBA will procure \nonly new generation for co-located loads, not existing generation. In other words, the \nStatement of Principles (and the RBA intended to implement one of its pillars) \ncontemplates new generation to offset the adverse impact of data centers on supply-\ndemand. But it is unclear how PJM will achieve this RBA benefit if existing generators \ncan serve co-located load without limit. Additionally, PJM’s proposal does not clarify \nhow residential and other ratepayers will be protected, as required by the Ratepayer \nProtection Pledge, from the costs of acquiring new generation to replace existing \n \n3 With respect to a future RBA, the Statement of Principles provides in relevant part: “Provide Revenue \nCertainty to New Generation: Provide 15-year price certainty for new capacity resources. This can be \naccomplished by holding a Reliability Backstop Auction to procure new capacity resources commencing \nno later than September 2026” (emphasis in original). Regarding protecting residential customers, the \nStatement of Principles states that due to data centers’ size and risks they pose to resource adequacy, \n“PJM should allocate the cost of any new capacity procured through the aforementioned Reliability \nBackstop Auction to load serving entities (LSEs) with new data centers that have not self-procured new \ncapacity or agreed to be curtailable. Any remaining costs should be allocated to LSEs based on their \nremaining net short positions”) (emphasis in original). \n4 The Ratepayer Protection Pledge provides that the pledging companies agree to, in relevant part: “build, \nbring or buy the new generation resources needed to satisfy their new energy demands, paying the full \ncost of those resources whether by building or buying from, new or otherwise additive power plants.”"},{"page":4,"startToken":609,"endToken":856,"text":"3 \ngeneration that has chosen to shift to a co-location arrangement under the proposed tariff \nrevisions.  \nThus, rather than providing clarity and consistency as the Commission intended, \nintervening events have resulted in the proposed tariff contradicting PJM’s ongoing \ninitiatives. As a result, the proposed tariff revisions are unjust and unreasonable in their \npresent form, without addressing and avoiding their incompatibility with the Statement of \nPrinciples and Ratepayer Protection Pledge, and understanding how the proposed tariff \nrevisions will interact with the RBA. At a minimum, the Commission should defer action \non the proposed co-location framework until PJM’s RBA proposal is finalized. \nBACKGROUND \nShow Cause Proceeding \nOn February 20, 2025, the Commission initiated a show cause proceeding under \nsection 206 of the Federal Power Act to determine whether PJM’s tariff is just and \nreasonable and not unduly discriminatory or preferential without provisions addressing \nwith sufficient clarity or consistency the rates, terms, and conditions of service that apply \nto Co-Location Arrangements.5 On December 18, 2025, the Commission determined that \nPJM’s tariff is unjust and unreasonable, explaining that the tariff: \ndoes not contain provisions addressing with sufficient clarity or consistency \nthe rates, terms, and conditions of service that apply to Interconnection \nCustomers serving Co-Located Load, including generators serving Co-\nLocated Load in a configuration with special protection schemes to prevent \nthe Co-Located Load from taking energy from the transmission system.6  \n \n5 See PJM Interconnection, L.L.C., 190 FERC ¶ 61,115 (2025). \n6 Show Cause Order at P 249."},{"page":5,"startToken":856,"endToken":1160,"text":"4 \n \nThe Commission found that:  \nthe absence of such provisions leaves entities unable to determine what \nsteps they must take to effectuate Co-Location Arrangements, which creates \nuncertainty that has resulted in disparate treatment in PJM, where \ntransmission owners have taken different approaches to performing the \nnecessary steps that apply to Interconnection Customers seeking to serve \nCo-Located Load through a Co-Location Arrangement, leading to no \nconsistent understanding of entities’ responsibilities with respect to their \nplanned Co-Location Arrangements. We also find that PJM’s Tariff is unjust \nand unreasonable because it does not include transmission services that \nreflect an Eligible Customer taking service on behalf of a Co-Located Load \nthat is willing and able to limit its energy withdrawals from the \ntransmission system under certain conditions. Further, we find that PJM’s \nTariff is unjust and unreasonable because it does not address charges related \nto Co-Located Loads’ use of regulation and black start services, which \nintroduces the risk that Co-Located Loads may benefit from regulation and \nblack start services without contributing to cost recovery for such services \nand, thereby, the risk that costs may be allocated entirely to other \ntransmission customers and passed through to residential customers, among \nothers.7 \n \nThe Commission clarified that an existing generating facility may not begin \nserving Co-Located Load that is not Network Load until it has delisted its Capacity \nInterconnection Rights for the portion of the generating facility to be designated to serve \nany Co-Located Load that is not receiving NITS.8 \nThe Commission directed PJM to revise its tariff to provide sufficient clarity \nregarding the responsibilities of existing interconnection customers seeking to serve co-\nlocated load using their generating facilities.9 The Commission also directed PJM to file \ntariff changes specifying that an interconnection customer seeking to serve co-located \n \n7 Id. P 175. \n8 Id. P 230. \n9 Id. P 225."},{"page":6,"startToken":1160,"endToken":1368,"text":"5 \nload using an existing generating facility must bear the costs of all network upgrades that \nPJM finds are necessary to preserve transmission system reliability for existing \ntransmission customers.10  \nFurthermore, the Show Cause Order also required that PJM define “Co-Located \nLoad” as a “configuration [that] refers to end-use customer load that is physically \nconnected to the facilities of an existing or planned Customer Facility on the \nInterconnection Customer’s side of the Point of Interconnection to the PJM Transmission \nSystem.”11 \nFebruary 23 Compliance Filing \nPJM’s February 23 Compliance Filing generally sets forth the relative obligations \nof project developers seeking to serve co-located load, and PJM. The proposal defines \n“Co-Located Generating Facility” as “an existing or planned Generating Facility that is \nphysically connected to a Co-Located Load,” and “Co-Located Load” as “a configuration \nthat refers to end-use customer load that is physically connected to the facilities of an \nexisting or planned Generating Facility on the Project Developer’s side of the Point of \nChange in Ownership to the Transmission Provider’s Transmission System.”12 \nImportantly, these definitions appear to accommodate not only new generators, but \nexisting generators seeking to serve co-located load. \n \n10 Id. P 176. \n11 Id. P 164. \n12 Proposed Tariff Revisions, Part I, Definition of Co-Located Load."},{"page":7,"startToken":1368,"endToken":1621,"text":"6 \nAdditionally, the February 23 Compliance Filing proposes tariff revisions \nrequiring that “[a] Project Developer whose planned modifications include Co-Located \nLoad configuration shall be required to enter into a Necessary Studies Agreement with \nTransmission Provider in the form set forth in Tariff, Part IX, Subpart G.”13 The proposed \ntariff revisions would require a Project Developer to provide the Transmission Provider \nwith “the amount of reduction to Capacity Interconnection Rights to facilitate the Co-\nLocated Load configuration.”14 The proposed revisions also provide that:  \nProject Developer shall be responsible for the costs of any modifications or \nNetwork Upgrades identified by Transmission Provider, as applicable, as a \nresult of the change to the Interconnection Service Agreement or \nGeneration Interconnection Agreement to serve Co-Located Load, \nincluding to reflect any reduction in Capacity Interconnection Rights.15 \n \n“Capacity Interconnection Rights” (“CIRs”) are previously defined in PJM’s tariff as “the \nrights to input generation as a Generation Capacity Resource into the Transmission \nSystem at the Point of Interconnection where the generating facilities connect to the \nTransmission System.”16 Thus, the proposed revisions appear to accommodate new \ngenerators seeking to serve co-located load, as well as existing generators seeking to \nserve co-located load by reducing their CIRs, and thus their ability to input generation \nonto PJM’s transmission system. \n \n \n \n13 Id. Part VIII, Subpart A, section 401.H.3.b. \n14 Id. Section 401.H.3.b.i.c. \n15 Id. Section 401.H.3.b.iii. \n16 PJM, Intra-PJM Tariffs, OATT, § I.1 Definitions - C - D (40.1.1)."},{"page":8,"startToken":1621,"endToken":1867,"text":"7 \nWhite House and PJM Governors Statement of Principles and White House Pledge \nOn January 15, 2026, the National Energy Dominance Council within the White \nHouse and thirteen governors of states within PJM signed the Statement of Principles \nurging PJM to expeditiously file proposed tariff revisions with the Commission that \nreflect a set of principles for how generation capacity for data centers should be procured, \nand how costs should be allocated to data centers to protect residential customers.17 \nSpecifically, under these principles, PJM should hold a RBA to procure new capacity \nresources, with the costs of such new capacity going primarily to load serving entities \nwith new data centers that have not self-procured new capacity or agreed to be \ncurtailable.18  \n \nOn March 4, 2026, the White House issued the Ratepayer Protection Pledge that \ncompanies will build, bring, or buy the new generation resources and electricity needed \nto satisfy their new energy demands, paying the full cost of those resources whether by \nbuilding, or buying from, new or otherwise additive power plants.19 The pledge also \nprovides that where possible, these companies will also add more capacity that serves the \nbroader public by increasing supply.20 \n \n17 See Statement of Principles Regarding PJM, White House and 13 State Governors (Jan. 16, 2026),  \nhttps://www.energy.gov/documents/statement-principles-regarding-pjm. \n18 Id. at 1. \n19 See Donald J. Trump, Ratepayer Protection Pledge Proclamation, \nhttps://www.whitehouse.gov/presidential-actions/2026/03/ratepayer-protection-pledge-proclamation/ \n(Mar. 4, 2026). \n20 See id."},{"page":9,"startToken":1867,"endToken":2138,"text":"8 \nPROTEST \nI. \nPJM’s proposed tariff revisions are unjust and unreasonable because it is \nunclear how they will interact with PJM’s implementation of the RBA.  \nAs explained by the Commission in the Show Cause Order, PJM’s tariff is unjust \nand unreasonable because it does not contain provisions addressing with sufficient clarity \nor consistency the rates, terms, and conditions of service that apply to generators serving \nCo-Located Load and Eligible Customers taking transmission service on behalf of Co-\nLocated Load.21 However, in light of the Statement of Principles issued jointly by the \nWhite House and thirteen governors of states within PJM, the Ratepayer Protection \nPledge, and PJM’s subsequent responsive work toward instituting a RBA to be held \ntoward the end of 2026, PJM’s tariff remains without sufficient clarity and consistency.  \nThe Statement of Principles directed PJM to hold an RBA to procure new capacity \nresources.22 The Statement of Principles further urges that costs of such new capacity \nshould go primarily to load serving entities with new data centers that have not self-\nprocured new capacity or agreed to be curtailable.23 The Ratepayer Protection Pledge also \ncommits the major data center developers to procure new capacity resources to serve \ntheir needs. Thus, the thrust of the Statement of Principles and the Ratepayer Protection \nPledge is that generally new data centers should pay for new capacity.  \nUnder this framework, new data centers that are not served by self-procured new \nco-located generation could be subject to higher costs from the load serving entity as \n \n21 See Show Cause Order at P 2. \n22 See Statement of Principles at 1. \n23 See id."},{"page":10,"startToken":2138,"endToken":2423,"text":"9 \nresult of the RBA. But PJM’s proposed tariff revisions do not explain how existing \ncapacity resources that shift to co-located arrangements with new data centers would be \ntreated relative to the RBA. For example, it is unclear whether the capacity of existing \ngenerators that enter co-location arrangements with new data center load would be added \nto the capacity required to be procured in the RBA, or to the capacity procured in the \nregular base residual auction (“BRA”).  \nIf the capacity of existing generation that shifts to serve new co-located data center \nload is added to the BRA, ratepayers would be saddled with enormous costs that should \nbe assigned to the co-located load, in contravention of the Statement of Principles and the \nRatepayer Protection Pledge. For example, recent analysis by PJM’s Independent Market \nMonitor concluded that if 1,000 UCAP MW of nuclear capacity in Maryland was \nremoved—due to shifting to serving a co-located load for example—total market \nrevenues for the 2025/2026 BRA would increase by more than $3.6 billion.24 Yet PJM’s \ncompliance filing provides no explanation as to how such costs would be paid by new co-\nlocated data center load rather than being shifted to existing ratepayers. \nPJM’s compliance filing thus leaves significant and fundamental questions \nunanswered with respect to how existing generation can serve new co-located data center \nload. Without providing more details regarding how the proposal will align with PJM’s \nplans for the RBA, PJM’s proposal remains unclear and inconsistent with the Statement \n \n24 See Comments to the Maryland PSC Senate Bill 1 Co-location Study Administrative Docket PC 61 \n(Sep. 24, 2024) at 3, \nhttps://www.monitoringanalytics.com/filings/2024/IMM_Comments_MDPSC_PC61_20240924.pdf."},{"page":11,"startToken":2423,"endToken":2640,"text":"10 \nof Principles underpinning the RBA. This lack of clarity and consistency causes PJM’s \ntariff to remain unjust and unreasonable. At a minimum, the Commission should defer \naction on the proposed revisions until PJM announces details regarding its planned RBA, \nincluding specifics on how the RBA will interact with co-located arrangements to ensure \nthat new co-located loads pay the costs of any new capacity.  \nCONCLUSION \nThe issuance of the Statement of Principles by the White House and thirteen \ngovernors of states within PJM calling for an RBA to serve new data center load and the \nRatepayer Protection Pledge are salient intervening events that have occurred since the \nShow Cause Order issued. However, despite the significance of PJM’s work toward \nimplementing an RBA, fundamental issues surrounding how existing generators that shift \nto serve co-located load under PJM’s proposed tariff revisions will be treated relative to \nthe RBA remain unaddressed. As a result, PJM’s proposed revisions do not provide the \nclarity and consistency required by the Show Cause Order. PJM’s proposed tariff \nrevisions thus are unjust and unreasonable without a complete picture of how they will \ninteract with the RBA. At the very least, the Commission should defer action on the \nproposed revisions until PJM proposes tariff revisions to implement the RBA.  \n \nRespectfully submitted, \n \nDAVID S. LAPP \nPEOPLE’S COUNSEL"},{"page":12,"startToken":2640,"endToken":2676,"text":"11 \nWilliam F. Fields \nDeputy People’s Counsel \n \nPhilip L. Sussler \nAssistant People’s Counsel \n \n/electronic signature/ \nMark S. Byrd \nAssistant People’s Counsel \n \nOffice of People’s Counsel \n6 St. Paul Street, Suite 2102 \nBaltimore, Maryland 21202 \n(410) 767-3908"},{"page":13,"startToken":2676,"endToken":2724,"text":"12 \nCERTIFICATE OF SERVICE \nI hereby certify that I have this day caused the foregoing pleading to be served upon each \nperson designated on the official service list compiled by the Secretary in this proceeding. \nDated this 16th day of March, 2026. \n/s/ electronic signature----_____ \nMark S. Byrd"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":2,"endAt":675,"startToken":0,"endToken":149},{"p":2,"at":675,"title":"INTRODUCTION","method":"printed heading","endPage":4,"endAt":712,"startToken":149,"endToken":709},{"p":4,"at":712,"title":"BACKGROUND","method":"printed heading","endPage":9,"endAt":12,"startToken":709,"endToken":1869},{"p":9,"at":12,"title":"I. PJM’s proposed tariff revisions are unjust and unreasonable because it is","method":"printed heading","endPage":11,"endAt":417,"startToken":1869,"endToken":2487},{"p":11,"at":417,"title":"CONCLUSION","method":"printed heading","endPage":13,"endAt":4,"startToken":2487,"endToken":2677},{"p":13,"at":4,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":13,"endAt":298,"startToken":2677,"endToken":2724}]}