{"document":{"slug":"rec-20260324-5119","title":"Motion for Leave to Answer and Second Answer of Constellation Energy Generation, LLC in response to the Answer filed by PJM Interconnection, L.L.C","issued":"2026-03-24","accession":"20260324-5119","docket":"EL25-49-000","group":"PJM co-location compliance","filer":"Constellation Energy Generation, LLC","kind":"answer","file":"sources/filings/text/20260324-5119_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260324-5119","tier":"record","sha256":"33c2bb34b328ed03bb75cd864d38890c6bade605b7019e291abe659a64d211e7","pages":8,"tokens":2283,"emptyPages":[],"textThemes":["colo","flex","adequacy"]},"pages":[{"page":1,"startToken":0,"endToken":269,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \nPJM Interconnection, L.L.C., et al. \n \n \nLarge Loads Co-Located at Generating Facilities \n \n \nConstellation Energy Generation, LLC \n \n     v. \n \nPJM Interconnection, L.L.C. \n) \n \n \n)  \n \n \n)  \n) \n) \n) \n) \n \nDocket No. EL25-49-000 \n \n \nDocket No. AD24-11-000 \n \n \n \n \nDocket No. EL25-20-000 \n(Consolidated) \nMOTION FOR LEAVE AND SECOND ANSWER OF \nCONSTELLATION ENERGY GENERATION, LLC  \nConstellation1 moves for leave and submits this second answer in response to the answer \nfiled by PJM.2 Constellation sought clarification that generators serving non-firm electricity to \nCo-Located Loads, and that could be recalled during emergencies by both PJM and the \ngenerator, do not have to delist and needlessly reduce the capacity available for existing PJM \ncustomers.3 PJM now opposes our request. We reiterate three discrete points in response. \nI. \nAllowing Capacity Resources Serving Non-Firm, Recallable Co-Located Loads to \nRemain Available to PJM is Good Policy \nThe Commission should encourage capacity resources serving non-firm, recallable Co-\nLocated Loads to remain committed to PJM to help meet the system’s resource adequacy needs. \n \n1 Constellation Energy Generation, LLC (“Constellation”) submits this answer and motion for leave pursuant to \nRules 212 and 213 of the Commission’s Rules of Practice and Procedure, 18 C.F.R. §§ 385.212 and 385.213. \nConstellation respectfully submits there is good cause for the Commission to accept this answer as it is intended to \naid the Commission in its decision-making. \n2 PJM Interconnection, L.L.C., Motion for Leave to Answer and Answer, Docket Nos. EL25-49, et al. (Mar. 9, \n2026) (“PJM Answer”). \n3 Request for Clarification, or in the Alternative, Rehearing, Docket Nos. EL25-49, et al. (Jan. 20, 2026) \n(“Clarification Request”)."},{"page":2,"startToken":269,"endToken":706,"text":"2 \nThis is good and sound policy. Indeed, there are several advantages of encouraging such \narrangements that align with the Commission’s4 and the Trump Administration’s priorities. \nFirst, it enhances reliability. Capacity resources serving non-firm Co-Located Loads will \nin fact be available to PJM to help meet resource adequacy needs. As the Commission found, \nlarge loads are “willing and able to limit [their] energy withdrawals from the transmission \nsystem.”5 Constellation specifically noted several available mechanisms to ensure Co-Located \nLoads are in fact interrupted when PJM calls upon the generator.6 Forcing the Co-Located \nGenerating Facility to relinquish its capacity status needlessly takes megawatts out of the system \nwithout impacting reliability. \nSecond, it saves consumers money. If capacity is lost due to a delist, PJM will need to \nprocure additional capacity resources to make up for that loss. It is also possible that, if forced to \ndelist, the capacity resource may choose not to serve the Co-Located Load. In that case, PJM \nwould also have to procure additional capacity resources and complete more transmission \nupgrades to serve the Co-Located Load.7 These otherwise avoidable costs would be shared \n \n4 See, e.g., Written Testimony of Chairman Laura V. Swett Before the U.S. House of Representatives Committee on \nEnergy and Commerce, at 2 (Feb. 3, 2026), https://www.ferc.gov/news-events/news/testimony-laura-v-swett-\nchairman-federal-energy-regulatory-commission-us-house (“And in December, we directed the nation’s largest \ngrid operator to establish transparent rules to serve AI-data centers and other large loads co-located with \ngeneration. These rules will safeguard reliability and protect consumers across the mid-Atlantic, impacting over \n67 million Americans.”). \n5 PJM Interconnection, L.L.C., 193 FERC ¶ 61,217, at P 159 (2025) (“December 18th Order”); see also id. P 160 \n(“Co-Located Load are willing and able to limit their energy withdrawals from the transmission system under \ncertain conditions.”). \n6 See Clarification Request at 5 (“To the extent there are concerns that PJM would be ‘in competition with non-\ncapacity backed co-located loads for output of a Capacity Resource,’ the Commission could require the Co-\nLocated Load to disclose information regarding protective relay scheme and its interruptible commitment, and \nimpose penalties on that Co-Located Load for failure to comply with its commitment. Those assurances could be \nprovided by the Co-located Load confirming its willingness and the ability to interrupt or demonstrating that it has \nback-up diesels or batteries that will take over its supply.”) (footnotes omitted). \n7 December 18th Order, 193 FERC ¶ 61,217 at P 177 (“[R]equiring such Eligible Customers to take NITS on behalf \nof these Co-Located Loads may in some circumstances result in costly and inefficient transmission system"},{"page":3,"startToken":706,"endToken":982,"text":"3 \namong all customers. The Commission can save customers these costs by allowing capacity \nresources serving non-firm Co-Located Loads to remain available to help meet the system’s \nresource adequacy needs.  \nThird, more large loads would be able to connect faster because more generation would \nbe available to serve their needs instead of sitting “idle” round-the-clock as under-utilized \ncapacity resources. That advances the Trump Administration’s policy priority of winning the AI \nrace by bringing data centers online as soon as possible, while mitigating customer impacts. By \ncontrast, forcing generators to delist when they are co-located with data centers receiving non-\nfirm service runs counter to that policy priority by forcing data centers to choose either NITS \nservice, with all the attendant delays and costs associated with transmission upgrades, or pull the \nco-located generator out of the capacity market, even though in choosing non-firm service, the \ndata center has made the decision not to be capacity-backed.  \nFourth, it respects the purpose served by the energy market must-offer obligation, \nconsistent with the definition of the Capacity Product. Capacity resources serving non-firm Co-\nLocated Loads are productively serving load that would otherwise have to be served by PJM and \nare recallable to serve PJM grid load when needed.  \nII. \nPJM’s Arguments Distinguishing Non-Firm Exports from Co-Located Loads are \nIrrelevant  \nPJM’s attempt to distinguish exports from Co-Located Load arrangements misses the \npoint. Whether exports are serving other Regional Transmission Organizations that have “their \n \nbuildout that may not be necessary if such Eligible Customers are willing and able to take a transmission service \nthat requires fewer Network Upgrades to provide, and therefore may result in lower Network Upgrade costs, than \nwould NITS.”)."},{"page":4,"startToken":982,"endToken":1313,"text":"4 \nown capacity requirements and resources,”8 or are doing so for potentially only a “limited \nduration,”9 is irrelevant. The key point is that, just like a non-firm export, the energy output of a \nPJM capacity resource serving a non-firm Co-Located Load is not being used to serve PJM \nNetwork Load and remains recallable by PJM to help the grid meet its resource adequacy needs \nat key times of grid stress. Non-firm exports are not required to delist.10 Neither should capacity \nresources serving non-firm Co-Located Loads. \nIII. \nThe Commission Has Broad Authority to Require Changes \nWe acknowledge that adjustments to PJM’s energy offer price rules may be needed to \naccommodate the non-firm supply of Co-Located Load from a capacity resource.11 Such \nadjustments are not “out of scope” as PJM claims.12 Adjustments to the energy offer rules are a \nlogical outcome of Constellation’s timely request for clarification that generators serving non-\nfirm, recallable Co-Located Load need not delist.13 If the Commission grants clarification or \nrehearing, adjustments may need to be made to implement Constellation’s recommendation to \nallow capacity resources to remain available to help meet the region’s resource adequacy \nneeds.14 Making those adjustments is well within the Commission’s powers granted by the \n \n8 PJM Answer at 3. \n9 Id. at 7. \n10 Firm exports are required to delist. See PJM Manual 18, § 4.6.3. (“If a portion of a generation resource is to be \nexported, appropriate documentation must be submitted to PJM to demonstrate that the party exporting the \ngeneration resource has a financially and physically firm commitment to an external sale of its capacity and \ntherefore, is exempt from the offer requirement for capacity resources in Attachment DD, Section 6.6 of the PJM \nOpen Access Tariff.”) (emphasis added). \n11 See Motion for Leave to Answer and Answer of Constellation Energy Generation, LLC, Docket Nos. EL25-49, et \nal. at 4 (Feb. 20, 2026). \n12 PJM Answer at 2. \n13 See Clarification Request at 1-6."},{"page":5,"startToken":1313,"endToken":1763,"text":"5 \nFederal Power Act to “modify” its order “in such a manner as it shall deem proper”15 and to \nfashion remedies.16 PJM can propose any necessary revisions in a compliance filing. \nIn short, PJM needs to stop finding ways to frustrate the Commission’s efforts to foster \ninnovative Co-Located Load arrangements that facilitate new large load while protecting \ncustomers, and start looking for solutions. “Saying no to innovation is not a winning strategy.”17 \nJust as with non-firm exports, PJM could develop rules to accommodate service to non-firm Co-\nLocated Loads. There are several options that the Commission and PJM may consider exploring, \nincluding an adjustment to energy market offer levels—either by quantity or price—to reflect the \ndelivery of energy to the Co-Located Load as unavailable.  \nThe Commission and PJM could also consider exempting capacity resources serving non-\nfirm Co-Located Load from the energy market must-offer rule. There is precedent for this \napproach. The Commission recently approved PJM’s proposal to treat Reliability Must Run \n(“RMR”) units as capacity for Reliability Pricing Model procurement purposes,18 but not impose \nthe full suite of Capacity Performance obligations upon them. Specifically, the Commission \n \n14 In fact, additional tariff changes must be made even under PJM’s preferred approach to require delisting. As \nConstellation explained in its Clarification Request, a Capacity Resource can currently only delist under certain \nenumerated circumstances, and serving non-firm Co-Located Load does not fall within those existing exceptions. \nSee Clarification Request at 4. \n15 16 U.S.C. § 825l(a). \n16 See, e.g., Niagara Mohawk Power Corp. v. Fed. Power Com., 379 F.2d 153 (D.C. Cir. 1967) (“[T]he breadth of \nagency discretion is, if anything, at [its] zenith when the action assailed relates primarily not to the issue of \nascertaining whether conduct violates the statute, or regulations, but rather to the fashioning of policies, remedies \nand sanctions”); FPC v. La. Power & Light Co., 406 U.S. 621, 642, 92 S. Ct. 1827, 32 L. Ed. 2d 369 (1972) \n(finding that the Commission has broad authority to make “pragmatic adjustments” based on circumstances). \n17 December 18th Order, 193 FERC ¶ 61,217 (Rosner, Comm’r, concurring at P 1). \n18 See H.A. Wagner, Joint Offer of Settlement, Docket No. ER24-1787-001, Transmittal Sheet, at 6 (Jan. 27, 2025) \n(“A commitment by Wagner to have its units offered into or administratively cleared in the PJM capacity markets, \nbut forbearance by Wagner of any financial remuneration if the units clear and a crediting of those capacity market \nrevenues against the CORS costs that are being borne by ratepayers, with any excess capacity market revenues \nbeing returned to ratepayers.”) (citing Stipulation and Agreement § 4.8; Settled CORS § 5.1(b))."},{"page":6,"startToken":1763,"endToken":2034,"text":"6 \nendorsed an exemption from the energy market must-offer obligation, while nonetheless treating \nthe RMR resources as capacity to avoid “PJM over-procuring capacity”19—which in this case \nwould occur if the capacity resource serving non-firm load were required to delist. The \nCommission found that these RMR units served a “unique function in PJM” as they would avoid \n“PJM over-procuring capacity,” would be a “reasonable substitute for a capacity resource,” and \nwould be “reasonably expected to be available for dispatch by PJM in expectation of any PJM \nemergencies and to perform to address emergencies.”20 Based on this function, the Commission \nfound “it reasonable for PJM not to extend to qualifying RMR resources all the rights and \nobligations of capacity resources, including those [specifically] related to [energy market] must-\noffer requirements and the imposition of capacity performance penalties.”21 \nCapacity resources serving non-firm Co-Located Load also warrant an innovative \nsolution, such as an exemption from the must-offer requirements. In fact, as compared to RMR \nunits, capacity resources serving non-firm Co-Located Load are actual capacity resources that \nprovide significant performance certainty and can be called upon to provide reliability support to \nthe grid at any time. They are also subject to full testing, performance and penalty requirements \nof any capacity resource (which are far more stringent performance requirements than those \napplicable to the RMR resources), and just as with the RMRs, “excluding [them] from the \ncapacity market supply stack would result in PJM over-procuring capacity.”22  \n \n19 PJM Interconnection, L.L.C., 190 FERC ¶ 61,088, at P 48 (2025). \n20 Id. PP 48-49. \n21 Id. P 49. \n22 Id. P 48."},{"page":7,"startToken":2034,"endToken":2205,"text":"7 \nCONCLUSION \nFor the reasons stated above, Constellation respectfully requests that the Commission \naccept this Answer and grant its Clarification Request. Capacity resources serving non-firm Co-\nLocated Load should not be required to delist, needlessly deprive PJM of capacity, and further \ncompound the region’s resource adequacy challenges. \n \n \n \n \n \n \n \n    Respectfully submitted, \n \n \n \n \n \n \n \n \nMarch 24, 2026 \nCarrie Hill Allen \nSr. Vice President & Deputy General Counsel \nSeth T. Lucia \nAssistant General Counsel \nConstellation Energy Generation, LLC \n250 Massachusetts Ave. NW, Suite 760 \nWashington, D.C. 20001 \ncarrie.allen@constellation.com \nseth.lucia@constellation.com \n  \nChristopher A. Wilson \nManaging Director, Federal Regulatory Affairs \nConstellation Energy Generation, LLC \n250 Massachusetts Ave. NW, Suite 760 \nWashington, D.C. 20001 \n202-347-7500 \nFERCe-filings1@constellation.com \n \n/s/Paul F. Wight  \n \n \nPaul F. Wight \nCarolyn E. Clarkin \nDLA Piper LLP (US) \n500 Eighth Street NW \nWashington, D.C. 20004 \n703-773-4058 \npaul.wight@us.dlapiper.com  \ncarolyn.clarkin@us.dlapiper.com  \n \nSophia Browning \n4365 Executive Drive \nSuite 1100 \nSan Diego, CA 92121 \n858-677-1455 \nsophia.browning@us.dlapiper.com \n \nCounsel for Constellation Energy \nGeneration, LLC"},{"page":8,"startToken":2205,"endToken":2283,"text":"CERTIFICATE OF SERVICE \nI hereby certify that I have on this 24th day of March 2026, caused to be served a copy of \nthe foregoing upon all parties on the service lists in these proceedings in accordance with the \nrequirement of Rule 2010 of the Commission’s Rules of Practice and Procedure, 18 C.F.R. \n§ 385.2010 (2025). \n/s/ Sophia Browning \n \n \nSophia Browning \n4365 Executive Drive \nSuite 1100 \nSan Diego, CA 92121 \n858-677-1455 \nsophia.browning@us.dlapiper.com"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":1,"endAt":920,"startToken":0,"endToken":124},{"p":1,"at":920,"title":"I. Allowing Capacity Resources Serving Non-Firm, Recallable Co-Located Loads to","method":"printed heading","endPage":3,"endAt":1367,"startToken":124,"endToken":910},{"p":3,"at":1367,"title":"II. PJM’s Arguments Distinguishing Non-Firm Exports from Co-Located Loads are","method":"printed heading","endPage":4,"endAt":528,"startToken":910,"endToken":1070},{"p":4,"at":528,"title":"III. The Commission Has Broad Authority to Require Changes","method":"printed heading","endPage":7,"endAt":3,"startToken":1070,"endToken":2035},{"p":7,"at":3,"title":"CONCLUSION","method":"printed heading","endPage":8,"endAt":0,"startToken":2035,"endToken":2205},{"p":8,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":8,"endAt":464,"startToken":2205,"endToken":2283}]}