{"document":{"slug":"rec-20260325-5234","title":"Responsive Brief of Industrial Customer Organizations and Amtrak","issued":"2026-03-25","accession":"20260325-5234","docket":"EL25-49-000","group":"PJM co-location compliance","filer":"PJM Industrial Customer Coalition and Industrial Energy ConsNational Railroad Passenger Corporation (\"Amtrak\")American Forest and Paper Association, Inc. ,","kind":"brief","file":"sources/filings/text/20260325-5234_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260325-5234","tier":"record","sha256":"57aa503159d62ff0f12f6723517d232180e47802dd4745e3eba01864337080ad","pages":86,"tokens":24086,"emptyPages":[],"textThemes":["colo","retail","flex","cost"]},"pages":[{"page":1,"startToken":0,"endToken":280,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \nPJM Interconnection, L.L.C., et al.\nLarge Loads Co-Located at Generating \nFacilities \nConstellation Energy, LLC \n        v.  \nPJM Interconnection, L.L.C.\n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \nDocket Nos. EL25-49-000 \n                     EL25-49-001 \n                     AD24-11-000 \n                     EL25-20-000 \n                     (Consolidated) \nRESPONSIVE BRIEF OF \nINDUSTRIAL CUSTOMER ORGANIZATIONS AND AMTRAK \nPursuant to the Order on Show Cause Proceeding, Directing Compliance Filings, \nEstablishing Paper Hearing, and Granting In Part and Denying In Part Complaint (“Order”) in the \nabove-captioned dockets,1 and the January 23, 2026, Notice of Extension of Time,2 the PJM \nIndustrial Customer Coalition (“PJMICC”), the Industrial Energy Consumers of America \n(“IECA”), the American Forest and Paper Association (“AF&PA”) (collectively, “Industrials”), \nand the National Railroad Passenger Corporation (“Amtrak”) hereby file this Responsive Brief in \nresponse to PJM Interconnection, L.L.C.’s (“PJM”) and the Indicated PJM Transmission Owners’ \n(“PJM Transmission Owners”) Initial Briefs in Docket No. EL25-49, et al. (“Initial Briefs”)3, \nwhich were filed at the Federal Energy Regulatory Commission (“FERC” or “Commission”) on \nFebruary 23, 2026, in the above-captioned dockets. \n1 PJM Interconnection, L.L.C., et al., Order on Show Cause Proceeding, Directing Compliance Filings, Establishing \nPaper Hearing, and Granting In Part and Denying In Part Complaint, Docket Nos. EL25-49-000, EL25-49-001, AD24-\n11-000, EL25-20-000 (“Consolidated Dockets”) (Dec. 18, 2025) (“Order”). \n2 Notice of Extension of Time, Docket Nos. EL25-49-000, EL25-49-001, AD24-11-000, EL25-20-000 (Jan. 23, 2026). \n3 PJM Interconnection, L.L.C., et al., Initial Brief of PJM Interconnection, L.L.C. (Feb. 23, 2026) (“PJM Initial \nBrief”); PJM Interconnection, L.L.C., et al., Initial Brief and Joint Responses of the Indicated PJM Transmission \nOwners to Paper Hearing Questions (Feb. 23, 2026) (“PJM Transmission Owners Initial Brief”)."},{"page":2,"startToken":280,"endToken":630,"text":"2\nI.\nEXECUTIVE SUMMARY \nAs retail customers with high energy consumption needs, the Industrials/Amtrak have long \nendorsed customer choice as a foundational principle for electric service. As such, the \nIndustrials/Amtrak appreciate the promise of new transmission services designed to support the \ntype and amount of service required by customers. Lessons can be learned from the optionality in \nthe natural gas industry, while also recognizing the utility’s obligation to serve and the right of \nindustrial, institutional, and transportation customers to receive reliable electric service under \nvarious federal and state laws. The proposed implementation of PJM’s three new transmission \nservices (“New Services”) may yield benefits and optionality, but the New Services must be just, \nreasonable, and not unduly discriminatory or preferential under Section 206 of the Federal Power \nAct.4 Consequently, implementation of the New Services requires careful consideration of \nregulatory and jurisdictional issues and adherence to cost-causation principles. As the Commission \ndevelops the details for the New Services, the Industrials/Amtrak emphasize the following:  \n1) A just and reasonable back-up service is missing from the new transmission services \nstructure. Back-up service provided without a default assumption that it will be used during \nsystem peaks is guaranteed to Qualifying Facilities (“QF”) under the Public Utility \nRegulatory Policies Act of 1978 (“PURPA”) and should be extended to other retail \ncustomers with on-site generation on a cost-causation basis, either through retail netting or \nthrough a firm, back-up service charged on a cost-causation basis (“cost-based”).  \n2) The outcome of PJM’s pending compliance proposal in FERC Docket No. ER26-1479 \n(“BTMG Compliance Docket”) regarding PJM’s retail Behind-the-Meter Generation \n(“BTMG”) applicability rules, including a yet-to-be-determined materiality threshold \n(“Retail Threshold”), directly impacts and relates to the New Services and whether the \nterms and conditions of the New Services are just and reasonable. While specific eligibility \nfor retail netting is under consideration in the BTMG Compliance Docket, no firm cost-\nbased back-up service has been proposed in the instant proceeding. \n3) The Commission should incorporate incentives for Co-Located Load to bring new \ngeneration, with appropriate inducements for such generation’s reliable operation. \n4 16 U.S.C. § 824e(a)."},{"page":3,"startToken":630,"endToken":976,"text":"3\n4) The terms for New Services must respect state/federal jurisdictional boundaries and \nclearly translate into transparent retail rates. \nIndustrial retail configurations are varied, complex, and unique. Generally, in contrast to \ntypical computational loads, industrial customers produce a physical product on-site; cannot shift \nload to other facilities; often must continue to operate for safety and environmental compliance \nreasons; and frequently have generation and load deeply integrated via cogeneration, a process that \ngenerates both electric power and useful thermal energy.5 Traditional industrial load \nconfigurations with BTMG also provide substantial benefits to the grid—this traditional, existing \ncustomer load did not trigger the current resource adequacy challenges on the grid, nor does it \npresent the reliability risks posed by super-sized loads rapidly seeking to come online today. In the \nBTMG Compliance Docket, the Industrials/Amtrak submitted the Affidavit of James R. \nDauphinais (“Dauphinais Affidavit”), in which Mr. Dauphinais provided testimony concerning the \nconfigurations of industrial, institutional, and transportation retail customers, particularly QFs, and \nthe technical and regulatory basis for ensuring such customers have access to back-up power at \njust and reasonable rates.6\nIn contrast to the “traditional” load described above, computational loads (including data \ncenters) do not generally have substantial cogeneration, typically do not operate large motors \n(which can help with grid stability), can turn on and off nearly instantaneously, and can reach \nextremely large sizes, well beyond most traditional industrial and institutional retail customers. \nThe size and scale of the computational load currently in the planning process across PJM is \n5 FERC regulations implementing PURPA define “cogeneration facility” as “equipment used to produce electric \nenergy and forms of useful thermal energy (such as heat or steam), used for industrial, commercial, heating, or cooling \npurposes, through the sequential use of energy.” 18 C.F.R. § 292.202(c). \n6 See PJM Interconnection, L.L.C., Joint Protest and Comments of Industrial Customer Organizations and Amtrak, \nDocket No. ER26-1479-000 (Mar. 16, 2026) (“Industrials/Amtrak Protest”), Exhibit No. IA-1. The Dauphinais \nAffidavit is attached to this filing as Attachment 1 and provides support for the arguments herein."},{"page":4,"startToken":976,"endToken":1274,"text":"4\nmassive, both in the size of individual facilities and in the scale of the projects coming online \nacross the PJM footprint.  \nAs most planned load growth is driven by load additions greater than 300 MW, the \nIndustrials/Amtrak proposed in the BTMG Compliance Docket a Retail Threshold of at least 200 \nMW, under which BTMG netting should continue.7 The Industrials/Amtrak also proposed that \nQFs maintain their continued eligibility for BTMG netting, in accordance with PURPA \nrequirements.8 If the FERC accepts these proposals, it will go a long way toward resolving the \nconcerns about back-up power in the design of the New Services. However, if the FERC denies \nthe Industrials/Amtrak’s proposals in the BTMG Compliance Docket, the lack of back-up service \nin the design of the New Services becomes a heightened concern.  \nRetail customers represented by the Industrials/Amtrak in this docket seldom grab \nheadlines and are often not at the center of large-load and transmission planning discussions \ntoday—yet they have operated such systems reliably for decades. The transmission system has \ngrown up around such traditional loads, worked in concert with them, and benefited from their \npresence, operations, and long-term planning. As explained further in Section III, infra, these retail \nBTMG configurations are varied and diverse. The facts of on-site generation configurations matter \nand must be understood to ensure just and reasonable determinations in this proceeding.  \nExamples are plentiful. For some retail customers, industrial processes with cogeneration \nand combined heat and power (“CHP”) assets may require steam heat produced from the \ngeneration, meaning if the generation goes down, the load follows. In that case, it would defy cost-\ncausation principles to require such a facility to pay for transmission services it cannot physically \n7 Industrials/Amtrak Protest at 23-33. \n8 Id. at 17-23."},{"page":5,"startToken":1274,"endToken":1564,"text":"5\nuse (such as via a Grid Reliance Charge as proposed in the PJM Transmission Owners’ Initial \nBrief).9\nOther industrial customers currently qualify, or could qualify, as QFs under PURPA, \ngranting them the right to back-up and maintenance power at rates/terms that do not assume that \nunits will be down during system peaks and do not assume that units will be down at the same time \nas the other QFs (unless there is data backing that assumption). Yet, as will be explained further \nherein, the current proposed design of the New Services in the Initial Briefs makes no allowance \nfor back-up power at cost-based rates. \nA third example is that, as a legacy of the buildout of the Northeast Corridor (NEC), \nAmtrak requires service at 25 Hz, which it receives, at least for some of its requirements, through \na contractual arrangement with a third-party generator that is neither a small power production QF \nnor a cogeneration QF. This arrangement provides the only black-start capability for Amtrak’s \nsouth end of its Northeast Corridor traction power system if the 60 Hz power grid goes out of \nservice. \nEach of these configurations, plus others, is described in greater detail in Section III, infra. \nThese configurations underscore the critical need for the FERC to consider the impact on \ntraditional large-load configurations to ensure a just and reasonable replacement rate when \nauthorizing a final design for the New Services. Absent a just and reasonable method of obtaining \nback-up power, many retail customers will face devastating economic consequences. For some, as \nfurther explained below and in the Dauphinais Affidavit, it will mean closure of generating units, \nexacerbating the current resource adequacy concerns in the region. \n9 PJM Transmission Owners Initial Brief at 5, 11."},{"page":6,"startToken":1564,"endToken":1840,"text":"6\nWith careful attention to the reasons, needs, and cost-causation basis for back-up service, \nthis result is avoidable. The Commission can authorize the New Services while also ensuring a \njust and reasonable back-up service is in place for QFs and other similarly situated retail customers. \nAccordingly, the Industrials/Amtrak respectfully request that the Commission develop the New \nServices, consistent with the comments and changes recommended herein, to ensure the avoidance \nof unintended and irreparable damage to America’s essential manufacturing sector and \ninstitutional and transportation service providers.\nII.\nBACKGROUND \nOn December 18, 2025, the Commission issued the Order, finding that the PJM Tariff is \nunjust and unreasonable due to the lack of specificity for the rates, terms, and conditions that apply \nto Co-Located Load and directing PJM to make several compliance and informational filings. The \nOrder directed PJM to create three New Services, including an interim, non-firm Network \nIntegration Transmission Service (“Interim NITS”), a Firm Contract Demand Service (“Firm \nCDS”), and a Non-Firm Contract Demand Service (“Non-Firm CDS”).10 Paper hearing procedures \nwere established to evaluate the rates, terms, and conditions of the New Services.  \nThe Order also addressed PJM’s retail BTMG rules, which have long allowed for \nmeasurement of a retail customer’s transmission (as well as capacity, energy and ancillary \nservices) cost responsibility by actual use of the system as measured at the meter. In light of its \nfinding that “circumstances have changed since the Commission approved PJM’s retail BTMG \nrules,” the Commission directed PJM to implement changes to BTMG rules above a yet-to-be-\ndetermined materiality threshold (“Retail Threshold”).11 PJM, the Industrials/Amtrak, and others \n10 Order at P 2. \n11 Order at P 186."},{"page":7,"startToken":1840,"endToken":2209,"text":"7\nhave subsequently made various proposals for the Retail Threshold and other proposed terms for \nretail BTMG rules in the BTMG Compliance Docket. \nOn February 23, 2026, PJM and the PJM Transmission Owners filed Initial Briefs in the \nabove-captioned dockets, kicking off the briefing stage of the Paper Hearing.12 PJM also convened \nseveral stakeholder workshops to solicit input on the design and pricing of the New Services.13\nTo provide additional perspective on issues set for the Paper Hearing, and to respond to \nproposals made in the Initial Briefs, the Industrials/Amtrak respectfully offer the following \nresponse for the Commission’s consideration.  \nIII.\nTHE INDUSTRIALS/AMTRAK \nThis Responsive Brief is being filed on behalf of many of the major American energy \nconsumers in the PJM region: industrial customers that manufacture products used in everyday \nlife and commerce; a provider of core transportation services across the nation; and institutions \nthat offer essential medical and educational services. In many cases, these traditional institutional, \nindustrial, and transportation customers own or operate their own generation—not because energy \nis their primary industry, but because their core work is energy-intensive. These customers have \nelected to construct or contract for retail BTMG in order to control their own energy costs, create \nefficiencies, and/or address reliability needs. Even though the Order was issued largely in response \nto the impacts of “super-sized” loads such as data centers on the grid, the resulting changes (as \ncurrently proposed in the Initial Briefs) will directly and deeply impact these traditional retail \n12 Also on February 23, 2026, in the BTMG Compliance Docket, PJM filed 60-Day Compliance Filing for Co-Located \nLoad Related Revisions to Open Access Transmission Tariff to Comply with Commission Order in Docket No. EL25-\n49, et al., Docket No. ER26-1479-000 (Feb. 23, 2026) (“Compliance Filing”). \n13 PJMICC and IECA (together, “Requestors”) jointly filed a Request For Clarification or, in the Alternative, \nRehearing of the Industrial Customer Coalitions (“Rehearing Request”) on January 20, 2026, in Docket No. EL25-\n49-000 and the other Consolidated Dockets. Nothing herein should be construed to modify the Rehearing Request. \nThe Requestors and the Industrials/Amtrak reserve their rights to supplement or modify this Protest and Comments in \nresponse to any order on rehearing."},{"page":8,"startToken":2209,"endToken":2519,"text":"8\ncustomers. Like all other retail customers, manufacturers, hospitals, universities, and \ntransportation providers have the same right to just and reasonable rates that are grounded in cost-\ncausation principles. \nThe Industrials, which include several associations of leading American manufacturing \ncompanies and other energy-intensive customers, represent well over $1 trillion in sales, including \nthousands of manufacturing facilities and millions of family-sustaining jobs in the United States. \nAs an industry, manufacturing is unique compared to all other sectors, employing over 15 million \npeople in the United States14 and contributing $2.3 trillion to U.S. Gross Domestic Product \n(“GDP”) in 2023 (amounting to 10.2% of total U.S. GDP, measured in chained 2017 dollars).15\nManufacturers produce the raw materials and inputs necessary for sustaining commerce and our \noverall standard of living. Manufacturers are energy-intensive, frequently operate 24/7, are price-\nsensitive, and compete globally. Unlike the surge in large-load demands from data centers and \ncomputational workloads, most manufacturers are simply trying to remain competitive and keep \ntheir facilities operational and financially healthy amid ever-rising operational costs. Expansions \nof existing facilities are carried out over years of deliberate planning. Small changes in electricity \nprices can have significant impacts on the competitiveness of existing facilities and serious \nimplications for reshoring and expanding facilities and production capabilities in the United States.  \nAmtrak is a corporation authorized by the Rail Passenger Service Act of 1970, codified at \n49 U.S.C. §§ 24101, et seq. Amtrak provides passenger rail service across the continental United \nStates, including within the PJM footprint. Amtrak consumes substantial amounts of electricity in \n14 See U.S. Bureau of Labor Statistics (2024 data), available at https://www.bls.gov/cps/cpsaat18.htm (last accessed \nMar. 12, 2026). \n15\nSee \nU.S. \nManufacturing \nEconomy, \nNIST, \navailable \nat \nhttps://www.nist.gov/el/applied-economics-\noffice/manufacturing/manufacturing-economy/total-us-manufacturing (last accessed Mar. 12, 2026)."},{"page":9,"startToken":2519,"endToken":2825,"text":"9\nits operations on the Northeast Corridor and requires reliable electric service to support its \noperations. While Amtrak is not a manufacturer, it is an industrial customer of utility services. For \nmany years, Amtrak has harnessed retail BTMG within PJM to support its business operations and \nreliability imperatives. Amtrak’s interests align with the Industrials and reflect the wide-ranging \ntypes of bespoke retail BTMG arrangements that support the region’s and the nation’s economy.  \nThe issues set for Paper Hearing carry great weight for retail customers like Amtrak and \nmembers of the Industrials. If the FERC determines in the BTMG Compliance Docket that existing \nindustrial, institutional, and transportation applications no longer qualify as BTMG and, as such, \ncustomers no longer have their cost responsibility for transmission (and possibly capacity) \nmeasured at the meter, these customers will be reliant on the FERC to ensure there are adequate \ntransmission services, grounded in cost-causation principles, to enable these customers to remain \neconomic. If the requirements and standards for the New Services are inadequately designed, \nexisting concerns about resource adequacy and cost causation will deepen. Such a result would \nrisk rendering uneconomic a vast array of existing on-site generation arrangements. This may have \ndevastating economic impacts on industrial customers, who, as noted by PJM in the BTMG \nCompliance Docket, may decide to shutter their on-site generating units, exacerbating the resource \nadequacy challenges.16\nFurther impacting the cost and regulatory analysis, it is important to recognize that \nindustrial retail configurations are varied, complex, and unique. In contrast to typical \ncomputational and data center load, industrial customers: (a) produce a physical product on-site; \n(b) typically cannot shift load to other facilities; (c) often must continue to operate for safety and \nenvironmental compliance reasons; (d) frequently have generation and load deeply integrated via \n16 Compliance Filing at 12-14. See also Dauphinais Affidavit at PP 42-44."},{"page":10,"startToken":2825,"endToken":3308,"text":"10\ncogeneration; and (e) often provide valuable resource adequacy and reliability benefits to the \nbroader grid. These traditional load configurations are neither the essential cause of the current \nresource adequacy challenges on the grid, nor do they present the reliability risks posed by super-\nsized, inverter-based loads rapidly seeking to come online today. In fact, they provide substantial \nreliability and resource adequacy benefits to the grid.17 In contrast, the new computational loads \nentering the grid today do not have substantial cogeneration,18 do not typically operate large motors \n(which, in some cases, help with stability on the grid),19 can turn off and on nearly instantaneously, \nand can reach extremely large sizes (“super-sized”), well beyond most traditional industrial and \ninstitutional retail customers. As most planned load growth is driven by load greater than 300 MW, \nthe Industrials/Amtrak proposed a Retail Threshold in the BTMG Compliance Docket of at least \n200 MW, under which BTMG netting should continue.20\nThe above-listed characteristics of “traditional” large loads have direct implications for \nhow cost causation, grid risks, and other considerations should be evaluated. The Commission’s \ndecisions in this docket will directly impact cost and access issues such as: (a) who is eligible for \n17 These benefits are both 1) indirect: reducing large loads on the system and operating efficiently to reduce congestion \nand/or transmission system build-out; and 2) direct: being able to operate during system emergencies. Notably, the \nDepartment of Energy (“DOE”) recently issued an order indicating that it may rely on industrial customers’ generation \nduring emergencies. See U.S. Department of Energy, Emergency Order No. 202-26-06 (issued Jan. 26, 2026). \n18 See Dauphinais Affidavit at P 50 (“[V]ery large computational load processes are generally not highly thermally \nintegrated, if integrated at all, with any co-located generation facilities whose meter they may be located behind. This \nis because those generation facilities will either not be Cogeneration Facilities or would only be Cogeneration \nFacilities of greatly limited electrical capability relative to the total magnitude of the electrical load of their host retail \ncustomer.”) See also id. at PP 22-24. \n19 See Assessment of Gaps in Existing Practices, Requirements, and Reliability Standards for Emerging Large Loads: \nNERC \nLarge \nLoads \nWorking \nGroup \nWhite \nPaper \n(March \n2026), \nat \np. \n29, \navailable \nat \nhttps://www.nerc.com/globalassets/our-work/guidelines/reliability/white-paper---assessment-of-gaps.pdf. \n20 See Dauphinais Affidavit at PP 65-69 (providing evidence that most load added by large load additions is by \nadditions of 300 MW and higher). See also Interconnection of Large Loads to the Interstate Transmission System,\nReply Comments of the Indicated Transmission Owners, Docket No. RM26-4-000, at 2-3 (Dec. 5, 2025) (“To the \nextent the Commission asserts jurisdiction over large load interconnections, it should adopt a sufficiently narrow \ndefinition of ‘large load customer’ limited to large (200 MW or greater) data center customers. It is those customers \nthat are primarily driving load increases.”)"},{"page":11,"startToken":3308,"endToken":3774,"text":"11\nthe New Services; (b) how required amounts of contract demand are calculated; (c) retail cost \nallocation transparency; and (d) whether retail customers can access cost-based (and in many \ncases, legally-required) back-up service.  \nIndustrial, institutional, and transportation customers with on-site generation are rarely in \nthe news and are often not at the center of large load and transmission planning discussions; the \nreason for this is that they have operated such on-site generation systems reliably for decades. The \ntransmission system has grown up around such traditional loads, works in concert with them, and \nbenefits from their presence and operation. The facts of on-site generation configurations matter \nand must be understood to make just and reasonable determinations in this docket. The following \nare several examples of configurations that raise specific applicability and interpretation questions: \n\nIf a cogeneration facility and its associated manufacturing load is required to operate \nas a Co-Location Arrangement, the manufacturing load’s actual use of the transmission \nsystem may not equate to the actual maximum amount of load on-site, as the industrial \nprocess may require steam heat produced from the generation, meaning if the \ngeneration goes down, the load follows—in that case, it would defy cost causation \nprinciples to require such a facility to pay for transmission services it cannot physically \nuse (such as via a Grid Reliance Charge as proposed in the PJM Transmission Owners’ \nInitial Brief).21\n\nAmtrak, a retail customer, has a contractual arrangement for retail BTMG to support \nits Northeast Corridor operations. As a legacy of the buildout of the Northeast Corridor, \nAmtrak requires service at 25 Hz, which it receives, at least for some of its \nrequirements, through a contractual arrangement with a third-party generator that is \nneither a small power production QF nor a cogeneration QF. This arrangement provides \nthe only black-start capability for Amtrak’s south end of its Northeast Corridor traction \npower system if the 60 Hz power grid goes out of service. \n\nMany industrials currently qualify, or could qualify, as QFs under PURPA, granting \nthem the right to back-up and maintenance power at rates/terms that do not assume that \n21 Mr. Dauphinais explains in the Affidavit that when an outage of a cogeneration facility occurs, “significant electric \nload of the host retail customer can be lost immediately following, or very shortly following, the outage.” See\nDauphinais Affidavit at P 16. This can be due either to certain industrial or commercial processes “not being able to \noperate without thermal energy from the Cogeneration Facility if it is a Topping-Cycle facility” or due to “a thermal \nprocess being unable to operate because of the inability to dump its waste heat to the Cogeneration Facility if it is a \nBottoming-Cycle facility.” Id. Put simply, the very configuration of many industrial cogeneration facilities directly \nlimit use of the transmission system."},{"page":12,"startToken":3774,"endToken":4155,"text":"12\nunits will be down during system peaks and do not assume that units will be down at \nthe same time as the other QFs (unless there is data backing that assumption). Yet, as \nexplained further herein, the current proposed design of the Contract Demand Services \n(“CDS”) in the Initial Briefs makes no allowance for back-up power at cost-based rates. \n\nAn industrial customer represented by the Industrials has several dozen combined heat \nand power (“CHP”) assets, totaling between 80 MW and 200 MW in production \ncapacity, fueled by a mixture of coal and natural gas; the CHP assets are primarily \ndesigned to meet the thermal load; thermal energy is required for industrial processes; \nwhen a significant decrease in electricity generation occurs, thermal generation also \ndeclines, resulting in a simultaneous load shedding event decreasing the need for any \nexternal electricity purchases; there are physical limitations on amounts of power that \ncan be drawn from the grid; a standby service contract is in force, with decades of \ndemand history informing the contract; a purchased power contract has been in effect \nfor decades, as well, and is renewed on a year-to-year basis.22\n\nMany other examples exist of bespoke arrangements for industrial and institutional \ncustomers that may require firm back-up needs. As explained in the Dauphinais \nAffidavit, some of these units, particularly cogeneration units, are highly efficient and \nhighly reliable units, requiring limited downtime.23\nEach of these configurations underscores the critical need for the FERC to consider the \nimpact on traditional large load customers when authorizing a final design for the New Services. \nDue to the above examples and others, there are sound legal, regulatory, and cost-based reasons \nthat industrial and institutional applications should qualify for cost-based back-up power options, \nwhether through retail BTMG netting eligibility, or, alternatively, through a firm, cost-based back-\nup and maintenance service. Further, the New Services should be structured to support Bring Your \nOwn New Generation initiatives and to create efficient investment signals, as the industry faces a \ncrisis of resource adequacy. Finally, any New Services design finalized by the FERC should ensure \nsufficient clarity as to how cost responsibility will be assigned to retail customers, while respecting \nstate jurisdiction over retail rates.\n22 See Industrials/Amtrak Protest at 38. \n23 See Dauphinais Affidavit at PP 11-12, 29-35."},{"page":13,"startToken":4155,"endToken":4437,"text":"13\nTo that end, the Industrials/Amtrak respectfully request that the Commission consider the \nfollowing arguments in determining rates, terms, and conditions of the New Services. With the \nchanges recommended herein, the Commission can approve rules that effectuate the goals of the \nOrder while avoiding unintended damage to America’s essential manufacturing sector and \ninstitutional and transportation service providers. \nIV.\nARGUMENTS \nA.\nA just and reasonable back-up service is missing from the new transmission \nservices structure. A cost-based back-up service is guaranteed to Qualifying \nFacilities under PURPA and should be extended to other retail customers with \non-site generation on a cost-causation basis.  \nThe New Services represent a significant change to how transmission services are \ndesigned, bundled, and paid in the PJM region. However, as currently proposed, the New Services \nare missing a critical component. The current design lacks a back-up service that is based on cost-\ncausation and that meets the legal requirements of PURPA. Back-up service is an essential \ncomponent of energy management for many industrials and other retail customers with on-site \ngeneration, including QFs, which are guaranteed access to back-up service with specific cost-based \nassumptions.24\nBecause neither the New Services nor NITS calculated on a gross basis meet these \nrequirements, as explained below, at a bare minimum, QFs should retain access to longstanding \nretail BTMG netting rules. If the FERC determines otherwise, however, the FERC should ensure \nQFs have access to a cost-based back-up service. Retail customers with BTMG that is not a QF \nshould also, based on principles of cost causation, be provided with access to cost-based back-up \nservices, either through NITS with netting or through a cost-based back-up service. Access to \n24 18 C.F.R. § 292.305."},{"page":14,"startToken":4437,"endToken":4742,"text":"14\nback-up services is a critical component to allowing industrial, institutional, and transportation \nretail customers to continue to operate without significant economic damage, including likely \nclosures of some BTMG generating units.   \n1.\nPURPA ensures that QFs have access to back-up and maintenance \nservice that meets assumptions about generator uptime, and the NITS \nnetting construct meets this requirement. \nCongress passed PURPA in 1978 to encourage cogeneration, small power production, and \ngeothermal energy production.25 PURPA has played an important role for manufacturers and the \nelectric grid for nearly five decades, providing market access where none previously existed, \ntaking strain off the grid, and supporting American industry by enabling economic means to reduce \nenergy costs. Under PURPA, QFs fall into two broad categories: “qualifying small power \nproduction facilities,” which can be sized up to 80 MW, and “qualifying cogeneration facilities,” \nwhich have no size limit.26 Cogeneration QFs must achieve certain efficiency standards and are \nhighly efficient in their use of input fuels. Cogeneration QFs, which produce both electricity and \nheat from the same fuel source, make use of the “waste heat” in their manufacturing, heating, or \ncooling process. As explained by Mr. Dauphinais in the attached Affidavit (which was filed in the \nBTMG Compliance Docket), “Cogeneration Facilities can achieve efficiencies in excess of 80%, \nby using waste heat and avoiding electrical losses, compared to the efficiency of approximately \n50% for conventional electricity generation with a steam boiler.”27\nUnder FERC regulations (enacted at Congress’ direction), QFs are entitled to access to \nsupplementary power, back-up power, maintenance power, and interruptible power, pursuant to \n25 16 U.S. Code § 824a-3(a). \n26 16 U.S. Code § 824a-3. “Qualifying small power production facilities” are also referred to as “small power \nproduction QFs,” and “qualifying cogeneration facilities” are also referred to as “cogeneration QFs.” \n27 Dauphinais Affidavit at P 11."},{"page":15,"startToken":4742,"endToken":5139,"text":"15\nlong-established enacting regulations.28 “Back-up power” is defined in the regulations as “electric \nenergy or capacity supplied by an electric utility to replace energy ordinarily generated by a \nfacility’s own generation equipment during an unscheduled outage of the facility.”29\nCritically, rates for back-up or maintenance power “[s]hall not be based upon an \nassumption (unless supported by factual data) that forced outages or other reductions in electric \noutput by all qualifying facilities on an electric utility’s system will occur simultaneously, or \nduring the system peak, or both.”30 As explained by Mr. Dauphinais, the current BTMG netting \nconstruct for NITS permits QFs to receive the back-up power they are guaranteed—back-up power \nthat is charged without a default assumption that the back-up power will be needed during peak \ntimes.31 If back-up services are needed during peak times, the current NITS design ensures \ncustomers pay for them by appropriately measuring peak usage.32 As explained by Mr. Dauphinais, \n“With respect to the transmission component of back-up and maintenance power, Section 34.2 of \nthe PJM Open Access Transmission Tariff (“PJM Tariff”) currently excludes the load served by \nthe operating behind the meter generation of a retail customer from that retail customer’s daily \nload for [NITS].”33 He further states:  \nWhether a retail customer has behind the meter generation or not, its NITS \ncharges are based on the demand the retail customer has historically put on the \ntransmission system at the time of the annual peak of the transmission pricing \nzone. Given zonal transmission costs under the PJM Tariff are currently \n28 18 C.F.R. § 292.305(b). \n29 18 C.F.R. § 292.101(b)(9) (emphasis added). \n30 18 C.F.R. § 292.305(c)(1). \n31 See Dauphinais Affidavit at P 29 (explaining that the netting approach “is consistent with FERC’s rule for backup \nand maintenance power for Qualifying Facilities as it does not assume that a retail customer’s behind the meter \nQualifying Facility will be experiencing an outage at the time of the annual transmission system peak and instead \nrelies on factual data, in the form of the behind the meter Qualifying Facility’s historical performance during the time \nof the annual peak of the transmission pricing zone, when allocating transmission costs to the retail customer.”). See \nalso id. at P 49. \n32 Id. at P 29. \n33 Id. at P 28."},{"page":16,"startToken":5139,"endToken":5457,"text":"16\nallocated to load on an annual coincident peak demand basis, this netting \napproach is consistent with cost causation. Furthermore, it is consistent with \nFERC’s rule for backup and maintenance power for Qualifying Facilities as it \ndoes not assume that a retail customer’s behind the meter Qualifying Facility \nwill be experiencing an outage at the time of the annual transmission system \npeak and instead relies on factual data, in the form of the behind the meter \nQualifying Facility’s historical performance during the time of the annual peak \nof the transmission pricing zone, when allocating transmission costs to the retail \ncustomer.34\nBecause of this design, the BTMG netting construct meets the requirements of PURPA’s \nenacting regulations that QFs be guaranteed access to back-up and maintenance power with the \ncost-based assumptions required by the Regulations. To that end, in the BTMG Compliance \nDocket, the Industrials/Amtrak proposed that QFs be able to continue to net output and operate \nunder longstanding/historical retail BTMG rules.35 Not only does this comport with cost-causation \nprinciples, but it also meets the legal requirements of PURPA.36\n2.\nAs currently designed, the New Services do not provide for cost-based \nback-up service that meets the requirements of PURPA. \nThe CDS transmission services are designed to address various needs on the grid, including \nreserving enough transmission capacity and generating capacity to cover the firm needs of a large \ncustomer, and incorporating protections to prevent overdrawing from the grid. However, the CDS \nservices stop short of providing back-up service on a cost basis. Back-up power is, by its nature, \nunplanned.37\n34 Id. at P 29. \n35 Industrials/Amtrak Protest at 17-23. \n36 In contrast, transitioning to a gross-only approach would negate this alignment, as it calculates cost responsibility \nas if the on-site generation is always off by not including it in measurement of transmission cost responsibility.  \n37 18 C.F.R. § 292.101(b)(9)."},{"page":17,"startToken":5457,"endToken":5836,"text":"17\nMr. Dauphinais explains in the attached Affidavit the reasons neither Firm nor Non-Firm \nCDS provides a cost-based back-up service for cogeneration QFs and similarly-situated retail \ncustomers. As to Firm CDS, Mr. Dauphinais stated: \nWhile Contract Demand Transmission Service would provide reliable backup \nand maintenance power, it would not provide it at rates that are consistent with \ncost causation or FERC’s rules for the rates for the provision of backup and \nmaintenance power to Qualifying Facilities. Specifically, it requires payments \nfor the service based on the contracted amount. As a result, it would inherently \nassume, in violation of FERC’s rules for backup and maintenance power for \nQualifying Facilities, that forced outages or other reductions in electric output \nby all qualifying facilities on an electric utility's system will occur \nsimultaneously, or during the system peak, or both, without any factual data to \nsupport such an assumption. As I have discussed at length in this affidavit, this \nis not a reasonable assumption for Qualifying Cogeneration Facilities.38\nA simplified illustration highlights how Firm CDS fails to provide a back-up service based \non PURPA’s cost-based requirement. Consider an industrial load of 100 MW with 100 MW of \noffsetting BTMG. In this hypothetical, the BTMG experiences unplanned outages 1% of the time. \nIf the customer is forced to obtain 100 MW of Firm CDS, it will essentially be required to pay the \nsame as a customer that relies fully on the transmission system and uses that capacity 99% of the \ntime (rather than 1%). Taking the illustration a bit further, consider the impact if there are ten \nsimilar configurations within one transmission zone. Collectively, those ten customers would need \nto reserve 1,000 MW (1 GW) of transmission capacity through Firm CDS (or, if pricing for NITS \nis the same on a per-MW basis, pay the equivalent through a gross NITS product). Viewed as a \ngroup, however, it would be violative of cost-causation principles to bill for and collect 1,000 MW \nof transmission cost responsibility when these ten customers will not use more than a small \nfraction of that collective reservation at one time (based on any statistical analysis). As explained \nby Mr. Dauphinais in the attached Affidavit, “[T]he transmission system is not planned assuming \n38 Dauphinais Affidavit at P 44."},{"page":18,"startToken":5836,"endToken":6153,"text":"18\nthat all Cogeneration Facilities will experience an outage at the same time or will not otherwise be \nrunning…. Furthermore, in my experience, transmission planners do not study or examine \nscenarios where it is assumed large numbers of Cogeneration Facilities will be offline at the same \ntime, as there is no factual basis to support such an assumption.”39 While transmission planners \nmust consider many variables, it would not comport with cost-causation principles to require a full \nFirm CDS reservation for occasional back-up power needs, particularly where the history and risk \nof the individual unit is well-established or has met outside standards (such as qualifying as a QF). \nIn fact, such an approach would violate cost-causation principles and, for QFs, directly contradict \nthe PURPA regulations. \nEven more so, Non-Firm CDS would also fail to meet PURPA’s requirements for back-up \nservice. As explained by Mr. Dauphinais: \nNon-Firm Contract Demand Transmission Service would fall short in two \nrespects. First, it is incapable of providing backup power for forced outages of \nQualifying Cogeneration Facilities because the actual usage Non-Firm Contract \nDemand Transmission Service would have to be pre-scheduled with, and \napproved by, PJM in advance of its use, and forced outages cannot be known \nbeforehand. Second, the service is not reliable and risky to use as it is only \navailable on an as-available basis, subject to interruption during emergencies, \nand subject to automated interruption. It is not a product that could be used to \nprovide safe and environmentally compliant maintenance power to traditional \ncommercial, industrial and institutional retail customers with Qualifying \nCogeneration Facilities, never mind backup power to them.40\nConsequently, neither Firm CDS nor Non-Firm CDS are adequate services for industrial, \ninstitutional, transportation, and other retail customers who have invested in on-site generation and \nwho have qualified as QFs. Without clarity on how QFs will obtain back-up and maintenance \n39 Id. at P 32. \n40 Id. at P 45."},{"page":19,"startToken":6153,"endToken":6491,"text":"19\npower across all contexts, the FERC should permit QFs to continue under the current netting \nregime, as requested by the Industrials/Amtrak in the BTMG Compliance Docket. \n3.\nTo the extent netting is unavailable, a firm transmission service based \non actual use must be made available to QFs to meet the requirements \nof PURPA. \nAs explained above, the BTMG netting construct provides a framework that is compliant \nwith PURPA standards for QFs. However, with the changes to NITS rules initiated by the Order, \nNITS (with a gross load calculation) no longer meets this PURPA legal requirement.  \nBecause neither gross NITS nor Firm nor Non-Firm CDS meet the established PURPA \nrequirements, a firm transmission service must be available for QFs to meet the requirements of \nPURPA based on actual use. Practically speaking, this means that transmission services must be \ndeveloped that apply cost-causation standards to occasional, yet unplanned use of the transmission \nsystem. In short, if netting is no longer available to a customer with a QF, a cost-based back-up \nservice must be available to that retail customer to ensure just and reasonable rates. Alternatively, \nwithout clarity on how QFs will obtain back-up and maintenance power across all contexts, the \nFERC should permit QFs to continue under the current netting regime, as requested by the \nIndustrials/Amtrak in the BTMG Compliance Docket.41 The current retail BTMG netting structure \nis, quite literally, a cost-based structure based on actual use. QFs, which are either size-limited \n(non-cogeneration) or must meet efficiency requirements in integration with load (cogeneration), \nfit well within this structure, though it would also apply equally to other efficient BTMG \narrangements that only need occasional back-up and maintenance power.  \n41 Strong operational and financial incentives exist for cogeneration facilities to operate reliably and efficiently, even \nabove the ordinary cost-savings incentives of all generators. Further, to maintain QF status, the Regulations require \ncogeneration QFs (which includes any QF above 80 MW) to meet specified efficiency standards. See 16 U.S. Code § \n824a-3(n); 18 C.F.R. § 292.205."},{"page":20,"startToken":6491,"endToken":6831,"text":"20\nTo the extent netting is unavailable, a QF must have access to back-up and maintenance \npower that meets the standards of PURPA in a different way. \n4. Absent a sufficiently high Retail Threshold in the BTMG Compliance \nDocket, cost-causation principles dictate that the FERC should \nauthorize cost-based back-up service for all retail customers with \nBTMG, not only QFs. \nWhile allowing QFs to remain eligible for longstanding BTMG netting rules addresses the \nessential concern for QFs, many facilities operate on similar principles to QFs but do not have QF \nstatus. As Mr. Dauphinais notes, “[T]here may be some Cogeneration Facilities within the PJM \nfootprint that fully meet FERC’s requirements to be a Qualifying Cogeneration Facility (and, thus, \na Qualifying Facility), except they do not currently have a FERC-approved certification or self-\ncertification of their Qualifying Cogeneration Facility status because they do not makes sales of \nexcess power either at avoided cost to electric utilities or into the wholesale power market.”42\nAdditionally, many facilities may be eligible for QF status but did not seek or maintain such status \nbecause the existing netting construct provided these services.43 In other cases, there may be \nBTMG units that produce power behind-the-meter but do not meet PURPA’s technical \nrequirements (e.g., size or efficiency standards), but still, from a cost-causation standpoint, should \nbe given access to such services.  \nWhile PURPA regulations expressly recognize the need for QFs to occasionally draw from \nthe grid, including for occasional unscheduled outages, that need is not limited to QFs. To function \nproperly and under just and reasonable rates, other industrial, institutional, and transportation retail \nloads with on-site generation also require back-up service based on cost-causation. Absent access \n42 Dauphinais Affidavit at P 48. \n43 In the wake of the termination of the mandatory purchase obligation, many QF-eligible customers did not seek or \nmaintain QF status due to a combination of (1) having access to cost-based back-up power via BTMG netting rules, \nand (2) their utilities’ must-purchase obligations being terminated. See 16 U.S. Code § 824a-3(m)."},{"page":21,"startToken":6831,"endToken":7321,"text":"21\nto retail netting, there is a sound basis to provide back-up service that recognizes the cost-causation \nprinciples of back-up and maintenance service for BTMG facilities that do not have QF status. As \nrecognized by the D.C. Circuit Court of Appeals, the “cost-causation principle” has been \nrecognized “for decades” by “the Commission and the courts.”44 Under the cost-causation \nprinciple, “costs are to be allocated to those who cause the costs to be incurred and reap the \nresulting benefits.”45 Cost-causation has been described by the D.C. Circuit as a principle that \n“burden is matched with benefit.”46\nTo that point, PJM noted in the BTMG Compliance Docket that existing retail BTMG \narrangements—including QFs and other BTMG arrangements with existing contracts—“have \nbeen in place and netted against Network Loads within PJM without operational issues to date.”47\nLarge loads with large retail BTMG units have existed since the BTMG rules were established in \n2004 in PJM.48 Further, the illustration above—showing that ten 100-MW facilities would be \nrequired under Firm CDS to reserve 1,000 MW for back-up service, when those ten facilities would \nnever use more than a fraction of that transmission capacity—demonstrates that back-up service \n44 Old Dominion Elec. Coop. v. FERC, 898 F.3d 1254, 1255 (D.C. Cir. 2018). (“For decades, the Commission and the \ncourts have understood [the ‘just and reasonable’ rate requirement] to incorporate a ‘cost-causation principle’—the \nrates charged for electricity should reflect the costs of providing it.”). \n45 Nat’l Ass’n of Reg. Util. Comm’rs v. FERC, 475 F.3d 1277, 1285 (D.C. Cir. 2007). (See also K N Energy, Inc. v. \nFERC, 968 F.2d 1295, 1300 (D.C. Cir. 1992); City of Lincoln v. FERC, 89 F. 4th 926, 930 (D.C. Cir. 2024); see also\nMidwest ISO Transmission Owners v. FERC, 373 F.3d 1361, 1368 (D.C. Cir. 2004) (“we evaluate compliance with \nthis unremarkable [cost causation] principle by comparing the costs assessed against a party to the burdens imposed \nor benefits drawn by that party”). \n46 BNP Paribas Energy Trading GP v. FERC, 743 F.3d 264, 268 (D.C. Cir. 2014).  \n47 Compliance Filing at 10. \n48 From the beginning, large manufacturers have operated generating facilities behind-the-meter that offset their load. \nAt the establishment of BTMG rules in PJM over 20 years ago, large on-site generation units already existed and \nparticipated in the proceeding approving BTMG rules. For example, a refining company intervenor at the time \ndescribed its on-site generation as a “60 megawatt combined cycle cogeneration facility,” and an agricultural company \ndescribed its operational location as having “a combined load, net of the capabilities of [the company’s] onsite \ncogeneration, of between 200 and 300 MW,” implying a substantial presence of on-site generation. Motion to \nIntervene of Valero Refining Company – New Jersey, Docket No. ER04-608-000 (Mar. 23, 2004); Motion to Intervene \nof Archer-Daniels-Midland Company, Docket No. ER04-608-000 (Mar. 22, 2004)."},{"page":22,"startToken":7321,"endToken":7630,"text":"22\ncannot, based on principles of cost-causation, be priced the same as Firm CDS or gross-based \nNITS. Consequently, a cost-based back-up rate is the primary service missing from the \nCommission’s set of New Services.    \nThe economic impacts of the FERC’s decisions in this docket and in the BTMG \nCompliance Docket will be profound. Industrials are already grappling with the serious \nimplications of cost increases, resource adequacy concerns, and other economic pressures. Retail \ncustomers have developed on-site generation to minimize the load they place on the transmission \nsystem and, in many cases, to support thermal needs, such as heating facilities, operating chillers, \nor using steam in the manufacturing process. If continued BTMG eligibility is not granted by the \nFERC for members of the Industrials or Amtrak, the New Services, as designed, would force retail \ncustomers with on-site generation to a “gross load” measurement for NITS or Firm CDS for \noccasional back-up needs. In addition to violating cost-causation principles, this approach could \nseriously damage existing users’ economic viability by requiring customers to be charged for \ntransmission (and capacity, subject to clarification) as if their BTMG were not operating. Failing \nto provide (either by BTMG netting applicability or by an alternative back-up service) just and \nreasonable transmission and/or capacity cost allocation will render those units uneconomic, \nforcing them to operate at a loss, close and seek power from the grid, or shutter the plant entirely. \nAddressing cogeneration units in particular, Mr. Dauphinais explained that if the ability to operate \n“in a safe and environmentally compliant manner within the bounds of what can be supported by \nthe remaining thermal capability of the Cogeneration Facility at just and reasonable electric power \nrates” cannot be assured, “cogeneration may fail to be a practical and/or economic solution to the \nretail customer’s needs, causing the efficiency benefits of cogeneration to be forgone and/or the"},{"page":23,"startToken":7630,"endToken":7944,"text":"23\nretail customer to become economically unviable.”49 This issue is not limited to QFs. In the Protest \nand Comments of Eastman Chemical Company (“Eastman”) in the BTMG Compliance Docket, \nEastman explained that an arbitrarily low Retail Threshold (resulting in removal of BTMG netting) \n“renders Eastman’s BTMG uneconomic after almost 28 years of operations.”50\nFor some industrial and institutional customers, transmission and capacity cost savings are \na critical factor that makes it worth the investment to build and operate generation on their \npremises—investments these customers have already made (sometimes over decades).51 The \nIndustrials/Amtrak do not seek anything new that has not already been the regulatory context for \nthese units for multiple decades; rather, the Industrials/Amtrak seek to avoid a situation where \nexisting retail customers who have made such investments are suddenly forced to pay rates far \nabove cost for the services upon which they depend.  \nB.\nFor Co-Located Loads for which retail netting is not an option, Non-Firm CDS \nshould be designed to maximize efficient deployment of resources and advance \nincentives for large loads to “Bring Your Own New Generation.” \nAs set forth in the Order, Non-Firm CDS “must be available during normal operations and \ncurtailed during emergency operations (i.e., it will be curtailed before existing firm transmission \nservices and the new Firm Contract Demand Transmission Service).”52 However, “[r]eservations \nunder this service would be available only when there is available transmission capacity, similar \nto existing non-firm transmission service options in the Tariff.”53\n49 Dauphinais Affidavit at P 17.\n50 Protest and Comments of Eastman Chemical Company, PJM Interconnection, L.L.C., 60-Day Compliance Filing \nfor Co-Located Load Related Revisions to Open Access Transmission Tariff to Comply with Commission Order in \nDocket No. EL25-49, et al., Docket No. ER26-1479-000 (Mar. 16, 2026). \n51 See Dauphinais Affidavit at P 17. \n52 Order at P 215. \n53 Id."},{"page":24,"startToken":7944,"endToken":8384,"text":"24\nNon-Firm CDS should be designed to encourage new large loads to “Bring Your Own New \nGeneration” and prevent cost shifts to other customers, in accordance with cost-causation \nprinciples. In furtherance of those goals, the Industrials/Amtrak recommend the following \nprinciples and practices be adopted in the final design of Non-Firm CDS:  \n1. Hourly, actual use calculation – no standby fee. As an as-available service, Non-\nFirm CDS should not be charged a standby fee. Regardless of the merits of a standby \nfee in context of a firm service offering, a standby fee does not make sense when it \ncharges for “access” with no guarantee that such access will actually be available. \nRather, an actual use calculation on an hourly basis would be an appropriate way to \ncharge for Non-Firm CDS. Such an approach guarantees that retail customers pay for \nwhat they use; such revenues collected by transmission owners would go toward the \nrevenue requirement for that transmission owner, ultimately lowering rates for Firm \nCDS and NITS customers. \n2. No transmission planning based on Non-Firm CDS. As a non-firm, as-available \nservice, Non-Firm CDS should not be considered as a factor in transmission planning. \nIf transmission owners planned for additional transmission capacity for Non-Firm \nCDS, the costs of that transmission capacity would have to be recovered through rates. \nThis cost recovery would have the effect of raising rates for other transmission \ncustomers, because Non-Firm CDS, by design, should be less expensive than its Firm \nCDS and NITS cousins. \n3. Fuel contracts. Co-Located Load subscribing to Non-Firm CDS should have firm \nnatural gas capacity or other adequate alternatives to be able to utilize Non-Firm CDS. \nThe Commission should include such reasonable requirements to avoid misuse of the \nNon-Firm CDS service by generators who have the ability to operate but may want to \nrely on the grid when it appears to be more economical for that generator. From a \nresource adequacy perspective, policies surrounding Non-Firm CDS should encourage \nBring Your Own New Generation, which promotes building and operating on-site \ngeneration. \n4. Anti-manipulation. Non-Firm CDS should have clearly defined allowable \ncircumstances or standards for load to reserve non-firm transmission service. To \npreserve and support resource adequacy on the broader grid during times of system \nstress, switching from use of on-site generation to grid-supplied resources via Non-\nFirm CDS should not be for short-term economic reasons (such as when pricing for a \ngrid resource is lower than the on-site generation resource). Acknowledging efficiency \ngains from letting markets operate on economic signals, Non-Firm CDS should \ngenerally be available only if generation is unavailable for physical reasons—planned \nmaintenance, fuel outages, etc.—especially during times of system stress."},{"page":25,"startToken":8384,"endToken":8721,"text":"25\n5. Reasonable rules surrounding special protective schemes and required amounts \nof Non-Firm CDS. In the Order, the Commission asked for comment on “[w]hat \ninterconnection requirements and operational practices are necessary for special \nprotection schemes to maintain system reliability . . . in the event that a Co-Located \nLoad itself or its associated generator trips offline.”54 To the extent that special \nprotective schemes are required by the Commission for access to Non-Firm CDS, the \nrequirements should allow for a realistic assessment of what the facility can actually \ndraw from the grid. As explained in Section III, supra, some load/generation \nconfigurations allow only a limited amount of draw from the grid.55 The rules \ngoverning Non-Firm CDS should account for realistic on-site constraints. \nC.\nA durable solution must provide clear direction on cost allocation while \nrespecting federal-state jurisdictional distinctions. \nWith the sweeping, transformative changes initiated by the Order, it is critical to ensure \nretail customers have clear, accountable, and understandable rates and terms for these services. \nThis is particularly a concern considering interstate transmission services (the subject of this \ndocket) are a federal-jurisdictional service, yet the service must be translated to retail rates and \nbilled by Load-Serving Entities (“LSE”) or local distribution utilities.  \nMany distribution utilities across PJM’s footprint publish methodologies of how customer \ncost responsibility is calculated in the Attachment M-2s filed with the PJM Tariff at FERC. It is \nnot immediately clear from the Order how the retail cost allocation will be determined. Along \nthose lines, the FERC must ensure that transmission owners’ calculation of individual customer \nand zonal transmission cost allocation is transparent, whether through an Attachment M-2 filing \nor another publicly transparent and accountable method. Clear direction on how charges for New \nServices will be established is necessary for a durable final order in this proceeding. A simple \nexample of a lack of clarity would be a transmission owner that does not post its allocation \nmethodology in a publicly-available way. \n54 Order at P 219(6). \n55 See also Dauphinais Affidavit at P 16."},{"page":26,"startToken":8721,"endToken":8912,"text":"26\nFurther, the FERC must provide direction on how the revenue and the billing determinants \nfor the New Services would be incorporated into the existing transmission owners’ formula rates. \nBoth the revenue and billing determinants for Firm CDS should be treated in the same way as \nthose for NITS. The revenue for Non-Firm CDS should be treated comparably to the revenue from \nexisting non-firm Point-to-Point (“PTP”) service. \nThe end goal should be: (1) alignment with cost-causation principles; (2) clarity for retail \ncustomers and others on how those costs get translated to retail rates. During times of profound \nchange, traditional industrial, institutional, and transportation customers need clarity to be able to \noperate with predictability.  \nIn the Industrials/Amtrak’s view, changes authorized by the Commission will fall most \nheavily on existing retail customers. For many of these retail customers, particularly in heavy \nindustry, energy is one of the top costs of doing business. The on-site generation facilities these \ncustomers have developed were built based on certain assumptions and have been operated under \nthose assumptions. It is critical that these retail customers have clarity on how their needed services \nwill be delivered and charged."},{"page":27,"startToken":8912,"endToken":9042,"text":"27\nV.\nCONCLUSION & REQUEST FOR RELIEF \nThe Industrials/Amtrak respectfully request that the Commission ensure: (1) retail \ncustomers with on-site generation have access to cost-based back-up service; (2) the new \ntransmission services are designed to incentivize development of new generation and to avoid \nmanipulation; and (3) costs and obligations of retail customers are clear, publicly-available, and \nrespect federal-state jurisdictional lines.\nRespectfully submitted, \nBy: \n/s/ Susan E. Bruce \n \nSusan E. Bruce \nKenneth R. Stark \nMatthew L. Garber \nMcNees Wallace & Nurick LLC  \n100 Pine Street \nHarrisburg, PA  17101 \nTel:  717-232-8000 \nE-mail: sbruce@mcneeslaw.com \nE-mail: kstark@mcneeslaw.com \nE-mail: mgarber@mcneeslaw.com \nCounsel to the PJM Industrial Customer Coalition, \nthe Industrial Energy Consumers of America, the \nAmerican Forest and Paper Association, and the \nNational Railroad Passenger Corporation (Amtrak) \nDated:  March 25, 2026"},{"page":28,"startToken":9042,"endToken":9103,"text":"CERTIFICATE OF SERVICE \nI hereby certify that I have this day served via electronic transmission the foregoing upon \neach person designated on the official service list compiled by the Secretary in this proceeding.  \nDated this 25th day of March, 2026.  \n/s/ Matthew L. Garber \n \nMatthew L. Garber \n100 Pine Street \nHarrisburg, PA  17101 \nTel:  717-232-8000 \nFax:  717-237-5433 \nE-mail: mgarber@mcneeslaw.com"},{"page":29,"startToken":9103,"endToken":9115,"text":"ATTACHMENT 1  \nAffidavit of James R. Dauphinais  \nFiled in Docket No. ER26-1479-000"},{"page":30,"startToken":9115,"endToken":9141,"text":"Exhibit No. IA-1 \n \n \n \n \n \n \n \nUNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \n \n \nPJM Interconnection, L.L.C. \n \n  \n \n) \n \n \n \nDocket No. ER26-1479-000 \n \n \n \n \n \nAFFIDAVIT OF JAMES R. DAUPHINAIS"},{"page":31,"startToken":9141,"endToken":9295,"text":"Exhibit No. IA-1 \n \n \n \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \n \n \nPJM Interconnection, L.L.C. \n \n \n) \n \n \nDocket No. ER26-1479-000 \n \n \n \n \nAFFIDAVIT OF JAMES R. DAUPHINAIS \n \nTable of Contents \n \n \nI. \nINTRODUCTION .................................................................................................... 1 \n \n \nAffiant Description ................................................................................................... 1 \n \nII. \nBACKGROUND ON THE USE OF COGENERATION FACILITIES BY \nTRADITIONAL LARGE INDUSTRIAL, INSTITUTIONAL AND \nCOMMERCIAL RETAIL CUSTOMERS ............................................................... 5 \n \n \nWhat are Cogeneration Facilities? ............................................................................ 5 \n \n \nCogeneration Efficiency ........................................................................................... 7 \n \n \nThe Integration of Cogeneration with Commercial, Industrial, and Institutional \nProcesses and the Critical Need for Reliable Backup and Maintenance Power \nat Just and Reasonable Rates .................................................................................... 8 \n \nIII. \nCOMMERCIAL, INDUSTRIAL AND INSTITUTIONAL CUSTOMERS \nUSING COGENERATION ARE NOT THE SAME AS VERY LARGE \nCOMPUTATIONAL LOADS CO-LOCATED BEHIND THE METER \nOF GENERATION FACILITIES .......................................................................... 12 \n \nIV. \nFOR TRADITIONAL LARGE LOADS SERVED BY COGENERATION \nFACILITIES, PJM’S CURRENT RETAIL BEHIND THE METER \nGENERATION PROVISIONS ARE CONSISTENT WITH COST \nCAUSATION AND FERC’S OWN BACKUP AND MAINTENANCE \nPOWER RULES FOR QUALIFYING FACILITIES ............................................ 13 \n \n \nRetail BTMG Netting for Transmission ................................................................. 13 \n \n \nRetail BTMG Netting for Capacity ......................................................................... 17"},{"page":32,"startToken":9295,"endToken":9426,"text":"Exhibit No. IA-1 \n \n \n \nV. \nFIRM CONTRACT DEMAND TRANSMISSION SERVICE AND \nNON-FIRM CONTRACT DEMAND TRANSMISSION SERVICE \nARE UNABLE TO PROVIDE JUST AND REASONABLE \nBACKUP AND MAINTENANCE SERVICE TO QUALIFYING \nCOGENERATION FACILITIES ........................................................................... 19 \n \nVI. \nPJM’S PROPOSAL WITH RESPECT TO ALLOWING EXISTING \nCERTIFIED QUALIFYING FACILITIES AS OF DECEMBER 18, 2025 \nTO CONTINUE TO USE RETAIL BTMG NETTING FOR NITS \nAND CAPACITY REQUIREMENTS FALLS SHORT OF BEING \nJUST AND REASONABLE .................................................................................. 23 \n \nVII. \nPJM’S PROPOSED 50 MW AND SMALLER LIMITATION FOR \nNON-QUALIFYING FACILITIES TO USE RETAIL BEHIND THE METER \nGENERATION NETTING ALSO FALLS SHORT OF BEING JUST AND \nREASONABLE ...................................................................................................... 26 \n \n \nThe Proposed 50 MW Limit is Inappropriately Applied to Cumulative \nNameplate Capacity Rather than the Amount of Retail Load that can be Netted .. 29 \n \n \nPJM’s Proposed 50 MW Limit is Too Low ............................................................ 32 \n \nVIII. \nCONCLUSION ....................................................................................................... 36"},{"page":33,"startToken":9426,"endToken":9507,"text":"Exhibit No. IA-1 \n \n \n \nUNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \n \n \nPJM Interconnection, L.L.C. \n \n) \n \nDocket No. ER26-1479-000 \n \n \n \n \nAFFIDAVIT OF JAMES R. DAUPHINAIS \n \nList of Attachments \n \n1 Qualifications of James R. Dauphinais \n2 \n \n \nAnalysis of MW Size of Consumers Energy Company Data Center Load \nAddition Inquiries \n \n3 \n \nMichigan Public Service Commission Case No. U-21859, Consumers Energy \nCompany Data Request Response U21859-DCC-CE-0045  \n4 \n \nIllinois Commerce Commission Docket No. 25-0677, Commonwealth Edison \nCompany Response to Data Request NRG-ComEd 1.02"},{"page":34,"startToken":9507,"endToken":9655,"text":"Exhibit No. IA-1 \n \n \n \nUNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \n \n \nPJM Interconnection, L.L.C. \n \n) \n \nDocket No. ER26-1479-000 \n \n \n \n \nAFFIDAVIT OF JAMES R. DAUPHINAIS \n \nGlossary of Abbreviations and Acronyms \n \nAF&PA \nAmerican Forest and Paper Association \nAmtrak \nNational Railroad Passenger Corporation \nBAI \nBrubaker & Associates, Inc.  \nBTMG \nBehind the Meter Generation \nCHP \nCombined Heat and Power \nComEd \nCommonwealth Edison Company \nDCPZ \nZonal Daily Load \nFERC \nFederal Energy Regulatory Commission  \nFPA \nFederal Power Act \nIECA \nIndustrial Energy Consumers of America \nICC \nIllinois Commerce Commission \nMISO \nMidcontinent Independent System Operator, Inc.  \nMPSC \nMichigan Public Service Commission \nNERC \nNorth American Electric Reliability Corporation \nNITS \nNetwork Integration Transmission Service \nNU \nNortheast Utilities Service Company, now Eversource \nPJM \nPJM Interconnection, L.L.C.  \nPJMICC \nPRA \nPJM Industrial Customer Coalition \nPlanning Resource Auction \nPURPA \nPublic Utility Regulatory Policies Act of 1978 \nRAA \nReliability Assurance Agreement  \nRAR \nResource Adequacy Requirements \nSMR \nSmall Modular Reactors"},{"page":35,"startToken":9655,"endToken":9874,"text":"Exhibit No. IA-1 \nPage 1 of 38 \n \n \nUNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \n \n \nPJM Interconnection, L.L.C. \n \n) \n \nDocket No. ER26-1479-000 \n \n \n \n \n \nAFFIDAVIT OF JAMES R. DAUPHINAIS \n \nI. \nINTRODUCTION \n \nTHE UNDERSIGNED, James R. Dauphinais, of Chesterfield, Missouri having been duly \nsworn on oath before a Notary Public, states the following: \n \nAffiant Description \n \n1. \nI am a Managing Principal of Brubaker & Associates, Inc. (“BAI”), an energy, \neconomic and regulatory consulting firm.  My business address is 16690 Swingley Ridge Road, \nSuite 140, Chesterfield, Missouri 63017.  I have worked in the electric utility industry for over \n40 years, and during my twenty-eight (28) years of my employment by BAI I have been engaged \nwith respect to resource planning, transmission planning, wholesale power market structure, \nmarket power, transmission access, transmission line routing, fuel cost, power procurement and \nrate issues throughout the United States and portions of Canada.  For at least twenty (20) of my \nover twenty-eight (28) years with BAI, I have monitored developments in the PJM \nInterconnection, L.L.C. (“PJM”) stakeholder process on behalf of a group of large end-use \ncustomers in Illinois.  This work has included, but not been limited to, providing \nrecommendations with respect to various market proposals made by PJM either in the \nstakeholder process or in filings with the Federal Energy Regulatory Commission (“FERC”)."},{"page":36,"startToken":9874,"endToken":10187,"text":"Exhibit No. IA-1 \nPage 2 of 38 \n \n \n \nI have also assisted end-use customers with establishing themselves as a load-serving PJM \nMember and understanding their obligations as a load-serving PJM Member.  For at least \ntwenty-six (26) years, I have also participated in the Midcontinent Independent System Operator, \nInc. (“MISO”) stakeholder process on behalf of several large end-use customer groups.1  This \nhas included, but not been limited to, providing extensive feedback to MISO and other MISO \nstakeholders during the design of MISO’s day-ahead and real-time energy markets and MISO’s \nResource Adequacy Requirements (“RAR”) construct including the MISO Planning Resource \nAuction (“PRA”).  It has also included extensive involvement with respect to treatment of Load \nModifying Resources and Non-Load Modifying Resource behind the meter generation within the \nMISO market.  During my time with BAI, I have also had over twenty-four (24) years of \nexperience with issues related to the purchase and sale of electric power from or to Public Utility \nRegulatory Policies Act of 1978 (“PURPA”) Qualifying Facilities that are large industrial or \ninstitutional customer cogeneration facilities.  This has included providing testimony on the \nutility purchase of excess electric power from such facilities at avoided cost, the sale of excess \nelectric power by such facilities into the wholesale market, and the sale of backup and \nmaintenance power to such facilities to serve their host load when the facilities are experiencing \noutages or derates.  Prior to my employment with BAI, I was a Senior Engineer in the \nTransmission Planning Department of the Northeast Utilities Service Company (“NU,” now \nEversource).  During my over twelve (12) years of employment with NU, I was extensively \ninvolved with transmission planning, transmission operation and open access transmission \n \n1 These groups have members who have facilities with traditional large industrial and institutional \nelectric loads located in the MISO portions of Illinois, Indiana, Iowa, Louisiana, Michigan and Texas or \nelsewhere within the MISO footprint."},{"page":37,"startToken":10187,"endToken":10544,"text":"Exhibit No. IA-1 \nPage 3 of 38 \n \n \n \nservice issues.  I have testified previously before FERC as well as many state and provincial \nregulatory commissions.  Attachment 1 to this Affidavit provides a more complete summary of \nmy background and experience. \n2. \nMy firm has been retained by the PJM Industrial Customer Coalition \n(“PJMICC”), the Industrial Energy Consumers of America (“IECA”), the American Forest and \nPaper Association (“AF&PA”) and the National Railroad Passenger Corporation (“Amtrak”) \n(collectively, “Industrials/Amtrak”) to: (i) provide background on the use of cogeneration \nfacilities by traditional large industrial, commercial and institutional retail customers, (ii) explain \nthe differences between the traditional use of cogeneration facilities by large retail customers \nversus co-location of very large computational loads2 behind the meter of very large generation \nfacilities, (iii) explain how PJM’s current retail behind the meter generation provisions are \nconsistent with cost causation for the traditional use of cogeneration facilities by large retail \ncustomers and FERC’s own longstanding rules with respect to the provision of backup and \nmaintenance power to those retail customers, (iv) explain why the new Firm Contract Demand \nService and Non-Firm Contract Demand Service options that FERC has proposed for co-location \nof large loads behind the meter of generation facilities do not reasonably provide for the backup \nand maintenance service required by traditional use of cogeneration facilities by large retail \ncustomers, (v) explain why PJM’s proposal with respect to the treatment of Qualifying Facilities \n \n2 For purposes of this affidavit, when I use the term “computational load”, I am referring to crypto \ncurrency, data center and other large computer system electric loads including the electric load of the \nauxiliary systems necessary to operate the foregoing.  The North American Electric Reliability Corporation \n(“NERC”) Large Load Task Force has focused its recent reliability impact review on computational loads, \nrecently observing that “[t]he penetration of large loads on the [Bulk Power System] is growing, especially \ncomputational loads.” Assessment of Gaps in Existing Practices, Requirements, and Reliability Standards \nfor Emerging Large Loads: NERC Large Loads Working Group White Paper (March 2026), at p. 46, \navailable at https://www.nerc.com/globalassets/our-work/guidelines/reliability/white-paper---assessment-\nof-gaps.pdf."},{"page":38,"startToken":10544,"endToken":10893,"text":"Exhibit No. IA-1 \nPage 4 of 38 \n \n \n \nin its compliance filing in this proceeding falls short of being just and reasonable with respect to \nthe provision of backup and maintenance power to retail customers using cogeneration facilities, \nand (vi) explain why PJM’s proposed 50 MW and smaller limitation for non-Qualifying Facility \nretail behind the meter generation netting falls short of being just and reasonable. \n3. \nAttachments 1 through 4 to this Affidavit were either prepared or obtained under \nmy direction and control.  They are part of my Affidavit. \n4. \nI conclude the following in this affidavit: \n Very large computational loads co-located behind the meter of generation \nfacilities are not similarly situated to traditional large commercial, \nindustrial, and institutional loads using Cogeneration Facilities located \nbehind their meter, as very large computational loads generally are not \nhighly thermally integrated with co-located generation facilities. \n \n For traditional large loads served by Cogeneration Facilities, PJM’s \ncurrent retail behind-the-meter generation netting provisions for NITS \ncharges and capacity requirements are consistent with cost causation \nprinciples and FERC’s own backup and maintenance power rules for \nQualifying Facilities, as they rely on factual data regarding each \nQualifying Facility’s historical performance rather than assumptions about \nwhen outages will occur and whether they will occur simultaneously. \n \n Firm Contract Demand Transmission Service and Non-Firm Contract \nDemand Transmission Service are not capable – either alone or in tandem \n– of providing reliable backup and maintenance power to traditional large \nretail customers that utilize Qualifying Cogeneration Facilities at rates \nconsistent with cost causation principles and FERC’s rules for providing \nbackup and maintenance service to Qualifying Facilities. \n \n PJM’s proposal to limit legacy retail behind-the-meter generation \ntreatment for Qualifying Facilities to those certified or self-certified as of \nDecember 18, 2025 falls short of being just and reasonable, and should be \nmodified to cover all Qualifying Facilities regardless of the date they \nentered service or the date of their certification or self-certification. \n \n PJM’s proposed 50 MW cumulative nameplate capacity limit for \ncontinued retail behind-the-meter generation netting for non-Qualifying \nFacility generation is not just and reasonable because the limit is \ninappropriately applied to cumulative nameplate capacity rather than to"},{"page":39,"startToken":10893,"endToken":11188,"text":"Exhibit No. IA-1 \nPage 5 of 38 \n \n \n \nthe amount of retail load that can be netted, and 50 MW is too low given \nthat the large computational load additions driving the Co-Located Loads \nissue are overwhelmingly 300 MW or larger in size; any limit should \ninitially be set no lower than 200 MW (if not closer to 300 MW). \n \n \nII. \nBACKGROUND ON THE USE OF COGENERATION FACILITIES BY \nTRADITIONAL LARGE INDUSTRIAL, INSTITUTIONAL AND \nCOMMERCIAL RETAIL CUSTOMERS \n  \nWhat are Cogeneration Facilities? \n \n5. \nFERC defines a Cogeneration Facility to be “equipment used to produce electric \nenergy and forms of useful thermal energy (such as heat or steam), used for industrial, \ncommercial, heating, or cooling purposes, through the sequential use of energy”.3  Given that on \na combined basis these facilities provide both thermal and electric energy, cogeneration facilities \nare also commonly referred to as Combined Heat and Power (“CHP”) facilities. \n6. \nThere are two types of Cogeneration Facilities – Topping-Cycle Cogeneration \nFacilities and Bottoming-Cycle Cogeneration Facilities. \n7. \nFERC defines a Topping-Cycle Cogeneration Facility as “a cogeneration facility \nin which the energy input to the facility is first used to produce useful power output, and at least \nsome of the reject heat from the power production process is then used to provide useful thermal \nenergy”.4  A common example of a Topping-Cycle Cogeneration Facility would be a facility \nwith combustion turbine generation fired by natural gas, combustible waste gases, or some \ncombination of the two, that produces electricity and provides steam for heating, cooling, and/or \nindustrial processes via heat recovery steam generators that collect waste heat from the \ncombustion turbine generator.  Another example would be a facility with boilers fired by fossil \n \n3 18 C.F.R. § 292.202(c). \n4 18 C.F.R. § 292.202(d)."},{"page":40,"startToken":11188,"endToken":11523,"text":"Exhibit No. IA-1 \nPage 6 of 38 \n \n \n \nfuel, combustible waste gases, other forms of combustible waste material, or some combination \nof the foregoing producing high pressure steam that is run through a steam turbine to produce \nelectricity with the lower pressure steam exiting the steam turbine then being used for heating, \ncooling, or industrial processes. 5 \n8. \nFERC defines a Bottoming-Cycle Cogeneration Facility as “a cogeneration \nfacility in which the energy input to the system is first applied to a useful thermal energy \napplication or process, and at least some of the reject heat emerging from the application or \nprocess is then used for power production”.6  A common example of a Bottoming-Cycle \nCogeneration Facility would be the use of a heat recovery steam generator to recover heat from \nan industrial process to produce steam that is then used to generate electricity via a steam \nturbine. \n9. \nCogeneration Facilities can include some amount of Supplementary Firing.  \nFERC defines Supplementary Firing as “an energy input to the cogeneration facility used only in \nthe thermal process of a topping-cycle cogeneration facility, or only in the electric generating \nprocess of a bottoming-cycle cogeneration facility”.7  An example of Supplementary Firing for a \nTopping-Cycle Cogeneration Facility would be the use of duct burners within the exhaust stream \nof a combustion turbine to increase the amount of steam that can be produced in the heat \nrecovery steam generator associated with the combustion turbine. An example of Supplementary \nFiring for a Bottoming-Cycle Cogeneration Facility would be the use of duct burners to stabilize \n \n5 It should be noted the use of Nuclear Small Modular Reactors (“SMR”) as the thermal source for \nTopping-Cycle Cogeneration Facilities is currently being actively explored in the industry and in at least \none case in the ERCOT portion of Texas is being actively pursued by X-Energy Reactor Company, LLC at \na Dow site.  See https://x-energy.com/media/news-releases/dow-and-x-energy-submit-construction-permit-\napplication-to-the-us-nuclear-regulatory-commission-for-proposed-advanced-nuclear-project-in-texas.  \n6 18 C.F.R. § 292.202(e). \n7 18 C.F.R. § 292.202(f)."},{"page":41,"startToken":11523,"endToken":11809,"text":"Exhibit No. IA-1 \nPage 7 of 38 \n \n \n \nthe steam produced from heat recovery from a waste heat source prior to that steam being used to \ngenerate electricity via a steam turbine. \nCogeneration Efficiency \n10. \nAs I have noted, FERC’s definition of Cogeneration Facility requires the \n“sequential use of energy”.8  Specifically, for a Topping-Cycle Cogeneration Facility, FERC \nrequires “the use of reject heat from a power production process in sufficient amounts in a \nthermal application or process to conform to the requirements of the operating standard”,9 where \nthe “operating standard” is “the useful thermal energy output of the facility must be no less than \n5 percent of the total energy output during the 12-month period beginning with the date the \nfacility first produces electric energy, and any calendar year subsequent to the year in which the \nfacility first produces electric energy.”10  For a Bottoming-Cycle Cogeneration Facility, FERC \nrequires “the use of reject heat from a thermal application or process, at least some of which is \nthen used for power production”. \n11. \nCogeneration Facilities, which, as I have noted, are also commonly referred to as \nCHP systems, are typically highly efficient because they capture heat that would otherwise be \nwasted and avoid electrical losses by generating electricity at the location where it will largely, if \nnot entirely, be consumed.  Specifically, Cogeneration Facilities can achieve efficiencies in \nexcess of 80%, by using waste heat and avoiding electrical losses, compared to the efficiency of \napproximately 50% for conventional electricity generation with a steam boiler.11 \n \n8 18 CFR § 292.202(c). \n9 18 CFR § 292.202(s)(1). \n10 18 CFR § 292.205(a)(1). \n11 https://www.epa.gov/chp/what-chp (last accessed 3/8/2026)."},{"page":42,"startToken":11809,"endToken":12109,"text":"Exhibit No. IA-1 \nPage 8 of 38 \n \n \n \n12. \nIn addition, pursuant to the Federal Power Act (“FPA”),12 FERC has a rule that \ndictates the requirements (including requirements respecting minimum size, fuel use and fuel \nefficiency) for a Cogeneration Facility to be a Qualifying Cogeneration Facility pursuant to \nPURPA.  Specifically, to be a Qualifying Cogeneration Facility, a Cogeneration Facility must \nmeet any applicable standards and criteria specified in 18 C.F.R. §§ 292.205(a), (b) and (d) and, \nunless exempted, has filed with the Commission a notice of self-certification, or has filed with \nthe Commission an application for Commission certification, that has been granted.13  Section \n292.205(a) is the operating and efficiency standard for Topping-Cycle Cogeneration Facilities.14  \nSection 292.205(b) is the efficiency standard for Bottoming-Cycle Cogeneration Facilities.15  \nSection 292.205(d) applies certain additional requirements to Cogeneration Facilities that do not \nmeet certain grandfathering requirements.16 \nThe Integration of Cogeneration with Commercial, Industrial, and Institutional Processes \nand the Critical Need for Reliable Backup and Maintenance Power at Just and Reasonable \nRates  \n \n13. \nBecause of the “sequential use of energy” requirement for Cogeneration Facilities \nthat I have discussed, Cogeneration Facilities are typically highly integrated with the industrial \nprocesses, commercial processes, heating processes and/or cooling processes of their host retail \ncustomer.  This has four major implications. \n14. \nFirst, there is a need for very high availability from the Cogeneration Facility to \nmeet the host retail customer’s thermal energy needs in order to assure the retail customer can \noperate its commercial or industrial processes that require thermal energy or to assure the retail \n \n12 Section 3(18)(A) of the FPA. \n13 18 CFR § 292.203(b). \n14 18 CFR § 292.205(a). \n15 18 CFR § 292.205(b). \n16 18 CFR § 292.205(d)."},{"page":43,"startToken":12109,"endToken":12449,"text":"Exhibit No. IA-1 \nPage 9 of 38 \n \n \n \ncustomer can operate its commercial or institutional cooling and heating systems.  This has the \nside effect of the Cogeneration Facility operating at a high electrical capacity factor, either due to \nthe need to produce the necessary thermal energy at a Topping-Cycle Cogeneration Facility or \ndue to the abundance of waste (i.e., reject) heat from the need to run the retail customer’s \nprimary thermal process at a Bottoming-Cycle Cogeneration Facility. \n15. \nSecond, the electrical output of the Cogeneration Facility can be much less than or \nmuch greater than the electrical load of the host retail customer.  This is because the thermal \nenergy needs of the retail customer typically dictate how much electric power must be produced \nby the Cogeneration Facility.  For example, if an industrial retail customer has a very high steam \nneed for its processes relative to its electrical needs, the Cogeneration Facility serving that \ncustomer will likely have to produce electric power well in excess of that retail customer’s needs \nfor its electrical load.  This requires there to be a reasonable outlet available to sell that excess \nelectric power at utility-avoided cost or at just and reasonable prices in the wholesale market.  In \ncontrast, if an industrial retail customer has a very limited steam need for its processes relative to \nits electrical needs, the Cogeneration Facility serving that customer will likely produce electric \npower well below the level that the retail customer needs for its electrical load.  This requires \nthat the retail customer be able to purchase supplementary (or supplemental) electric power to \ncover the deficit from either a utility under a regulated retail electric service rate or from the \nwholesale power market through a retail supplier at just and reasonable rates where retail \ncustomer choice is available. \n16. \nThird, when an outage of Cogeneration Facility occurs, significant electric load of \nthe host retail customer can be lost immediately following, or very shortly following, the outage \neither due to certain retail customer industrial or commercial processes not being able to operate"},{"page":44,"startToken":12449,"endToken":12785,"text":"Exhibit No. IA-1 \nPage 10 of 38 \n \n \n \nwithout thermal energy from the Cogeneration Facility if it is a Topping-Cycle facility or due to \na thermal process being unable to operate because of the inability to dump its waste heat to the \nCogeneration Facility if it is a Bottoming-Cycle facility. \n17. \nFinally, most relevant to this current proceeding, there is a very high need for the \nCogeneration Facility to be able to purchase reliable backup and maintenance electrical power \nfor the host retail load of the Cogeneration Facility from the local utility, or from the wholesale \nmarket via a retail supplier where there is retail customer choice, at a cost that is consistent with \ncost causation principles.  This is necessary to ensure the retail customer can, in a safe and \nenvironmentally compliant manner, continue to operate its processes at just and reasonable \nelectric power rates within the bounds of what the remaining thermal energy capability of the \nCogeneration Facility can support while it is under a full or partial outage or derate.   The ability \nto continue operation in a safe and environmentally compliant manner within the bounds of what \ncan be supported by the remaining thermal capability of the Cogeneration Facility at just and \nreasonable electric power rates is a critical requirement to ensure the retail customer can \neconomically meet the needs of its own customers and clients.  If that ability cannot be assured, \ncogeneration may fail to be a practical and/or economic solution to the retail customer’s needs, \ncausing the efficiency benefits of cogeneration to be forgone and/or the retail customer to \nbecome economically unviable. \n18. \nFERC’s rules recognize this critical need by requiring all electric utilities, except \nwhere exempted from doing so under FERC’s rules, to provide backup and maintenance power \nto Qualifying Facilities, including Qualifying Cogeneration Facilities, and placing two additional \nspecific requirements on the rates under which that backup and maintenance power is provided \nin addition to generally requiring the rates be just and reasonable and in the public interest; and"},{"page":45,"startToken":12785,"endToken":13076,"text":"Exhibit No. IA-1 \nPage 11 of 38 \n \n \n \nnot discriminate against any Qualifying Facility in comparison to rates for sales to other \ncustomers served by the electric utility.17 \n19. \nFERC defines backup power as “electric energy or capacity supplied by an \nelectric utility to replace energy ordinarily generated by a facility's own generation equipment \nduring an unscheduled outage of the facility.”18  This is electric power beyond the host retail \ncustomer’s supplemental power consumption that is required by the host retail customer when \nthe Cogeneration Facility experiences a full or partial forced outage or a forced deration.  \n20. \nFERC defines maintenance power as “electric energy or capacity supplied by an \nelectric utility during scheduled outages of the qualifying facility.”19  This is electric power \nbeyond host retail customer’s supplemental power consumption that is required by the host retail \ncustomer when the Cogeneration Facility experiences a full or partial scheduled maintenance \noutage or a scheduled maintenance derate. \n21. \nConsistent with cost causation principles, the aforementioned two additional \nspecific requirements for backup and maintenance power rates under FERC’s rules require that \nelectric utility rates for sales of back-up power or maintenance power to Qualifying Facilities, \nincluding Qualifying Cogeneration Facilities: \n(1) Shall not be based upon an assumption (unless supported by factual data) that \nforced outages or other reductions in electric output by all qualifying facilities on \nan electric utility's system will occur simultaneously, or during the system peak, \nor both; and \n \n(2) Shall take into account the extent to which scheduled outages of the qualifying \nfacilities can be usefully coordinated with scheduled outages of the utility's \nfacilities.20  \n \n17 18 CFR § 292.305. \n18 18 CFR § 292.101(b)(9). \n19 18 CFR § 292.101(b)(11). \n20 18 CFR § 292.305(c)."},{"page":46,"startToken":13076,"endToken":13338,"text":"Exhibit No. IA-1 \nPage 12 of 38 \n \n \n \nIII. \nCOMMERCIAL, INDUSTRIAL AND INSTITUTIONAL CUSTOMERS USING \nCOGENERATION ARE NOT THE SAME AS VERY LARGE \nCOMPUTATIONAL LOADS CO-LOCATED BEHIND THE METER OF \nGENERATION FACILITIES \n   \n22. \nVery large computational loads co-located behind the meter of generation \nfacilities are not similarly situated to traditional large commercial, industrial and institutional \nloads using Cogeneration Facilities located behind their meter. \n23. \nIn particular, very large computational loads by their very nature generally do not \nhave a high thermal energy need relative to the magnitude of their total electric load and do not \nproduce large amounts of waste heat relative to the magnitude of their total electrical load.  As \nsuch, they are not candidates for Cogeneration Facilities beyond potentially addressing their \ncooling and heating needs. \n24. \nThus, very large computational load processes are generally not highly thermally \nintegrated, if integrated at all, with the co-located generation facilities whose meter they may be \nlocated behind.  This is because those generation facilities will either not be Cogeneration \nFacilities or be Cogeneration Facilities of greatly limited electrical capability relative to the total \nmagnitude of the electrical load of their host retail customer. \n25. \nWithout such integration, the co-located generation facilities will not provide the \nefficiency benefits that are provided by Cogeneration Facilities in serving commercial, industrial, \nand institutional customers.  In addition, depending on the specific nature of the co-located \ngeneration facilities, the generation may be operated only intermittently rather than at the high \ncapacity factor typically required of Cogeneration Facilities to ensure their host retail customer \nthermal process needs are being reliably fully met."},{"page":47,"startToken":13338,"endToken":13672,"text":"Exhibit No. IA-1 \nPage 13 of 38 \n \n \n \n26. \nDue to these differences, from a cost causation perspective, very large \ncomputational load co-located behind the meter of generation facilities are more akin to \nwholesale customer load served by utility behind the meter generation21 than traditional large \ncommercial, industrial, and institutional load served by behind the meter Cogeneration Facilities. \n \nIV. \nFOR TRADITIONAL LARGE LOADS SERVED BY COGENERATION \nFACILITIES, PJM’S CURRENT RETAIL BEHIND THE METER \nGENERATION PROVISIONS ARE CONSISTENT WITH COST CAUSATION \nAND FERC’S OWN BACKUP AND MAINTENANCE POWER RULES FOR \nQUALIFYING FACILITIES \n  \n27. \nPJM’s longstanding provisions22 for the netting of retail customer load with \ngeneration located behind the meter of those customers are consistent with cost causation for \ntraditional large commercial, industrial, and institutional customers using Cogeneration \nFacilities, and consistent with FERC’s rules for backup and maintenance power for Qualifying \nFacilities. \nRetail BTMG Netting for Transmission \n  \n28. \nWith respect to the transmission component of backup and maintenance power, \nSection 34.2 of the PJM Open Access Transmission Tariff (“PJM Tariff”) currently excludes the \nload served by the operating behind the meter generation of a retail customer from that retail \ncustomer’s daily load for Network Integration Transmission Service (“NITS”).23  This has the \n \n21 An example of utility behind the meter generation, also known in PJM as non-retail behind the \nmeter generation, is a transmission dependent utility whose load is being served in part by the transmission \ndependent utility’s conventional generation facilities that are located on its side of the meter between it and \nits transmission provider.   \n22 I have been advised by counsel that the Commission found that these provisions may be subject \nto change in light of the Commission’s December 18, 2025 order issued in Docket No. EL25-49-000.  I am \nalso aware that PJMICC and IECA have a pending rehearing request, filed on January 20, 2026, challenging \nthe Commission’s determination with respect to findings concerning PJM’s rules for netting and retail \nbehind-the-meter generation.    \n23 PJM Tariff § 34.2 (Effective 9/17/2010 Docket No. ER10-2710-000)."},{"page":48,"startToken":13672,"endToken":14008,"text":"Exhibit No. IA-1 \nPage 14 of 38 \n \n \n \neffect of excluding the portion of a retail customer’s load served by its operating behind the \nmeter generation from its zonal daily load (“DCPZ”), which is the retail customer’s daily load \nwithin a transmission pricing zone coincident with the time of the annual peak of the zone.24   \nThis nets the output of the behind the meter generation from the retail customer’s load such that \nthe retail customer’s DCPZ is the retail customer’s demand placed on the transmission system at \nthe time of the annual peak of the transmission pricing zone the retail customer is located within, \njust like it is for retail customers who do not have behind the meter generation.  The DCPZ is \napplied to 1/365th of the annual NITS rate for the zone to determine the retail customer’s NITS \ncharges for each day.  Hence, whether a retail customer has behind the meter generation or not, \nits NITS charges are based on the demand the retail customer has historically put on the \ntransmission system at the time of the annual peak of the transmission pricing zone. \n29. \nGiven zonal transmission costs under the PJM Tariff are currently allocated to \nload on an annual coincident peak demand basis, this netting approach is consistent with cost \ncausation.  Furthermore, it is consistent with FERC’s rule for backup and maintenance power for \nQualifying Facilities25 as it does not assume that a retail customer’s behind the meter Qualifying \nFacility will be experiencing an outage at the time of the annual transmission system peak and \ninstead relies on factual data, in the form of the behind the meter Qualifying Facility’s historical \nperformance during the time of the annual peak of the transmission pricing zone, when allocating \ntransmission costs to the retail customer.  Also consistent with FERC’s backup and maintenance \nrule,26 this approach inherently avoids assuming that all Qualifying Facilities will be \n \n24 PJM Tariff § 34.1 (Effective 2/18/2020 Docket No. ER20-646-000). \n25 18 CFR § 292.305(c). \n26 Id."},{"page":49,"startToken":14008,"endToken":14325,"text":"Exhibit No. IA-1 \nPage 15 of 38 \n \n \n \nexperiencing an outage at the same time.  Again, it instead relies on factual data, in the form of \nthe historical performance of each Qualifying Facility, not an assumption with respect to whether \nthey will all be out of service at the same time. \n30. \nIt is also important to note the retail behind the meter generation netting approach \nwould work under different cost allocation methods besides the annual coincident peak demand \nmethod.  For example, if future facts and circumstances warranted a change from the annual \nzonal transmission system peak to the use of 12 monthly coincident peaks for the zone, to the top \n100 transmission system demand hours for the zone, or to the evening hours of annual \ntransmission peak day for the zone, the current retail behind the meter netting approach would \nstill properly allocate transmission costs to retail customers based on the historical demand they \nplace on the transmission system during the hours being used for the cost allocation consistent \nwith using factual data, not assumptions. \n31. \nFurthermore, given the high capacity factor typically associated with Qualifying \nCogeneration Facilities that I discussed earlier, Qualifying Facility Cogeneration would not be \nexpected to perform significantly less effectively using a larger number of hours for allocation \nrather than a smaller number of hours. \n32. \nIt is also important to understand that the transmission system is not planned \nassuming that all Cogeneration Facilities will experience an outage at the same time or will not \notherwise be running.  Based on my experience, consistent with their high capacity factor nature, \nCogeneration Facilities are generally modeled in power flow and stability analysis as electrically \nproducing power at the level necessary to support the thermal process needs of their retail host \nload, with only any stretch in electrical capability they may have through supplementary firing \npotentially being subject to economic dispatch.  Furthermore, in my experience, transmission"},{"page":50,"startToken":14325,"endToken":14608,"text":"Exhibit No. IA-1 \nPage 16 of 38 \n \n \n \nplanners do not study or examine scenarios where it is assumed large numbers of Cogeneration \nFacilities will be offline at the same time, as there is no factual basis to support such an \nassumption.  Both of these points further reinforce why transmission costs should be allocated to \nretail customers with Cogeneration Facilities on the basis of the net demand they place on the \ntransmission system during the hours used for cost allocation rather than their gross load during \nthose hours, as the sum of their individual gross loads is never under any circumstance placed on \nthe transmission system. \n33. \nAlso from my experience, while transmission planners do consider the \ncontingency loss of individual generation assets at Cogeneration Facilities, when those \ncontingencies are examined by transmission planners, those planners take into consideration how \nthe electrical load of the host retail customer will change both immediately following the \ncontingency and shortly thereafter due to the highly integrated nature of the Cogeneration \nFacility and its host retail customer.  Regardless, such contingencies at best drive local \ntransmission needs and only if the contingency is most severe generation contingency in that \nlocal area after subtracting off the electrical load that will be lost by the Cogeneration Facility’s \nhost retail customer.  As such, these contingencies are not driver of the bulk majority of \ntransmission system costs any more than the non-coincident peak demand of individual loads is a \ndriver of the bulk majority of transmission system costs.  Instead, the bulk majority transmission \nsystem costs are driven by total system demand on the transmission system, which is why \ntransmission costs are typically allocated to load using a coincident peak demand cost allocation \nmethod."},{"page":51,"startToken":14608,"endToken":14971,"text":"Exhibit No. IA-1 \nPage 17 of 38 \n \n \n \nRetail BTMG Netting for Capacity27 \n \n34. \nWith respect to the capacity component of backup and maintenance power, \nSchedule 8 of the PJM Reliability Assurance Agreement Among Load Serving Entities in the \nPJM Region (“PJM Reliability Assurance Agreement” or “RAA”) currently establishes the \nObligation Peak Load of a party to the RAA as the daily summation of the weather-adjusted \ncoincident summer peak, last preceding the Delivery Year, of the retail customers in the zone net \nof the operating behind the meter generation of those customers.28  The Daily Unforced Capacity \nObligation of the party is then determined as its Obligation Peak Load multiplied by the \napplicable Final Zonal Reliability Pricing Model  Scaling Factor and the PJM Forecast Pool \nRequirement.29 Thus, the PJM capacity requirement for retail customers is based on the weather \nadjusted demand of those customers at the time of the summer coincident peak net of the output \nof any behind the meter generation at that time of that summer coincident peak.  This nets the \noutput of the behind the meter generation from the retail customer’s load such that the retail \ncustomer’s capacity requirement is based the retail customer’s demand placed on the PJM \nmarket at the time of the summer coincident peak, just like it is for retail customers who do not \nhave behind the meter generation.  Hence, whether a retail customer has behind the meter \ngeneration or not, its PJM capacity requirement is based on the demand the retail customer has \nhistorically put on the PJM market at the time of the PJM summer coincident peak. \n \n27 While PJM did not include any proposed changes to the PJM Reliability Assurance Agreement \nin its filing in ER26-1479-000, PJM, in Footnote 2 of the first page of its transmittal letter for its February \n23, 2026 Compliance Filing, indicated it anticipates needing to make subsequent conforming clean-up \nfilings to the PJM Reliability Assurance Agreement, among other documents, in regard to the compliance \nfilings being submitted in response to the FERC’s Order to Show Cause in Docket No. EL25-49, et al.   \n28 PJM RAA, Schedule 8, Section A (Effective: 8/31/2024 – Docket No. ER24-2447-003). \n29 Id."},{"page":52,"startToken":14971,"endToken":15271,"text":"Exhibit No. IA-1 \nPage 18 of 38 \n \n \n \n \n35. \nGiven capacity requirements under the PJM RAA are currently allocated to load \non a summer coincident peak demand basis, this netting approach is consistent with cost \ncausation.  Furthermore, like with retail behind the meter generation netting for NITS charges, it \nis consistent with FERC’s rule for backup and maintenance power for Qualifying Facilities30 as it \ndoes not assume that a retail customer’s behind the meter Qualifying Facility will be \nexperiencing an outage at the time of the summer coincident peak and instead relies on factual \ndata, in the form of the behind the meter Qualifying Facility’s historical performance during the \ntime of the summer coincident peak, when allocating transmission costs to the retail customer.  \nAlso consistent with FERC’s backup and maintenance rule,31 this approach inherently avoids \nassuming that all Qualifying Facilities will be experiencing an outage at the same time.  Again, it \ninstead again relies on factual data, in the form of the historical performance of each Qualifying \nFacility, not an assumption with respect to whether they will all be out of service at the same \ntime. \n \n36. \nAlso, like with retail behind-the-meter netting for NITS charges, the current retail \nbehind-the-meter generation netting approach for capacity requirements would still work under \ndifferent cost allocation methods than the current summer coincident peak demand method.  \nSpecifically, regardless of the hours used for allocation, the current retail behind-the-meter \nnetting approach would still properly allocate capacity requirements to retail customers based on \nthe historical demand they place on the transmission system during the hours being used for the \nallocation of capacity requirements, consistent with using factual data, not assumptions.  This \nsends a strong cost signal for retail behind the meter generation to operate and fully serve the \n \n30 18 CFR § 292.305(c). \n31 Id."},{"page":53,"startToken":15271,"endToken":15534,"text":"Exhibit No. IA-1 \nPage 19 of 38 \n \n \n \nelectric load of their host retail customer during times of grid stress.  It does so because the times \nof grid stress generally align with the time periods used for cost allocation and it is at those very \ntimes that NITS billing units and capacity requirements are determined under retail behind the \nmeter generation netting.  \n \n37. \nFinally, just as with retail behind-the-meter generation netting for NITS charges, \ngiven the high capacity factor typically associated with Qualifying Cogeneration Facilities that I \ndiscussed earlier above, Qualifying Facility Cogeneration would not be expected to perform \nsignificantly less effectively using a larger number of hours allocating capacity requirements \nrather than a smaller number of hours. \n \nV. \nFIRM CONTRACT DEMAND TRANSMISSION SERVICE AND NON-FIRM \nCONTRACT DEMAND TRANSMISSION SERVICE ARE UNABLE TO \nPROVIDE JUST AND REASONABLE BACKUP AND MAINTENANCE \nSERVICE TO QUALIFYING COGENERATION FACILITIES  \n  \n38. \nFERC in its December 18, 2025 order in Docket No. EL25-49, et al., ordered \nPJM to provide two new transmission services for large loads co-located behind the meter of \ngeneration facilities (“Co-Located Loads”) – who would not be permitted to take NITS based on \ntheir net load --  as an alternative to taking NITS based on their gross load: (i) Firm Contract \nDemand Service and (ii) Non-Firm Contract Demand Service.32  While I understand from \ncounsel that these services are subject to the paper hearing in Docket No. EL25-49-000, these \nnew  services have direct bearing on the just and reasonableness of continued availability of \nretail behind-the-meter generation netting for Qualifying Facilities. \n \n32 193 FERC ¶ 61,127 (2025), at P 193."},{"page":54,"startToken":15534,"endToken":15844,"text":"Exhibit No. IA-1 \nPage 20 of 38 \n \n \n \n39. \nFirm Contract Demand Transmission Service would allow Co-Located Loads to \ntake firm transmission service up to a pre-specified MW quantity rather than having to take \nNITS based on their gross demand.33 \n40. \nNon-Firm Contract Demand Transmission Service would allow non-firm \ntransmission service when such service is not needed on a regular basis.34  It would need to be \nreserved in advance on an as-available basis during normal, non-emergency operating conditions \nand would be subject to curtailment during emergency conditions.35  There would be no charge \nfor generation capacity for the portion of the load taking the service, and PJM would have no \nobligation to obtain generation capacity for the load.36 \n41. \nWhile its specific provisions for these two transmission services are the subject of \na paper hearing in Docket No. EL25-49-000, PJM in its February 23, 2026 initial brief in that \npaper hearing (“PJM Paper Hearing Initial Brief”) in part proposed: \n The entire gross load of the Co-Located Load be covered by a \ncombination of Firm Contract Demand Transmission Service and Non-\nFirm Contract Demand Transmission Service.37 \n \n Actual deliveries of power under Non-Firm Contract Demand \nTransmission Service would need to be pre-scheduled with, and approved \nby, PJM.38 \n \n To the extent the Co-Located Load takes any Non-Firm Contract Demand \nService it must install control technologies, potentially in the form of a \nRemedial Action Scheme (“RAS”), to assure its load can be curtailed \n \n33 Id. at P 208 through P 213. \n34 Id. at P 214. \n35 Id. at P 215. \n36 Id. at P 218. \n37 Docket No. EL25-49-000, et al., Initial Brief of PJM Interconnection, LLC, February 23, 2026, \nAttachment A at Section 709.2(c).  \n38  Docket No. EL25-49-000, et al., Initial Brief of PJM Interconnection, LLC, February 23, 2026 \nat 9-10 and Attachment B at ¶ 12."},{"page":55,"startToken":15844,"endToken":16162,"text":"Exhibit No. IA-1 \nPage 21 of 38 \n \n \n \nwhen required by PJM and the Non-Firm Contract Demand Service taken \nby the Co-Located Load does not exceed the amount approved by PJM.39 \n \n Penalties and potential disqualification that would apply when a Co-\nLocated Load takes Contract Demand Service in excess of that authorized \nby PJM, fails to respond to load shedding and curtailment procedures, or \nhas a misoperation of control technologies and protection systems.40  \n \n42. \nFirm Contract Demand Transmission Service and Non-Firm Contract Demand \nTransmission Service, neither alone nor in tandem, are capable of providing reliable backup and \nmaintenance power to traditional large commercial, industrial and institutional retail customers \nthat utilize Qualifying Cogeneration Facilities at a cost that is consistent with cost causation \nprinciples and FERC’s rules for providing backup and maintenance service to Qualifying \nFacilities. \n43. \nAs I noted earlier, reliable backup and maintenance power consistent with cost \ncausation principles and FERC’s rules for backup and maintenance power is necessary for these \nretail customers to ensure they can in a safe and environmentally compliant manner continue to \noperate their processes at just and reasonable electric power rates within the bounds of what the \nremaining thermal energy capability of their Qualifying Cogeneration Facility can support while \nit is under a full or partial outage or derate.   The ability to continue operation in a safe and \nenvironmentally compliant manner within the bounds of what can be supported by the remaining \nthermal capability of the Cogeneration Facility at just and reasonable electric power rates is a \ncritical requirement to ensure the retail customer can economically meet the needs of its own \ncustomers and clients.  If that ability cannot be assured, cogeneration may fail to be a practical \n \n39  Docket No. EL25-49-000, et al., Initial Brief of PJM Interconnection, LLC, February 23, 2026, \nAttachment A at Sections 708(c) and 713.6. \n40 Id. at Sections 713.7 and 713.8."},{"page":56,"startToken":16162,"endToken":16443,"text":"Exhibit No. IA-1 \nPage 22 of 38 \n \n \n \nand/or economic solution to the retail customer’s needs, causing the efficiency benefits of \ncogeneration to be forgone and/or the retail customer to become economically unviable. \n \n44. \nWhile Contract Demand Transmission Service would provide reliable backup and \nmaintenance power, it would not provide it at rates that are consistent with cost causation or \nFERC’s rules for the rates for the provision of backup and maintenance power to Qualifying \nFacilities.  Specifically, it requires payments for the service based on the contracted amount.  As \na result, it would inherently assume, in violation of FERC’s rules for backup and maintenance \npower for Qualifying Facilities,41 that forced outages or other reductions in electric output by all \nqualifying facilities on an electric utility's system will occur simultaneously, or during the system \npeak, or both, without any factual data to support such an assumption.  As I have discussed at \nlength in this affidavit, this is not a reasonable assumption for Qualifying Cogeneration \nFacilities. \n \n45. \nNon-Firm Contract Demand Transmission Service would fall short in two \nrespects.  First, it is incapable of providing backup power for forced outages of Qualifying \nCogeneration Facilities because the actual usage Non-Firm Contract Demand Transmission \nService would have to be pre-scheduled with, and approved by, PJM in advance of its use, and \nforced outages cannot be known beforehand.  Second, the service is not reliable and risky to use \nas it is only available on an as-available basis, subject to interruption during emergencies, and \nsubject to automated interruption.  It is not a product that could be used to provide safe and \nenvironmentally compliant maintenance power to traditional commercial, industrial and \n \n41 18 CFR 292.305(c)."},{"page":57,"startToken":16443,"endToken":16727,"text":"Exhibit No. IA-1 \nPage 23 of 38 \n \n \n \ninstitutional retail customers with Qualifying Cogeneration Facilities, never mind backup power \nto them.     \n \nVI. \nPJM’S PROPOSAL WITH RESPECT TO ALLOWING EXISTING CERTIFIED \nQUALIFYING FACILITIES AS OF DECEMBER 18, 2025 TO CONTINUE TO \nUSE RETAIL BTMG NETTING FOR NITS AND CAPACITY REQUIREMENTS \nFALLS SHORT OF BEING JUST AND REASONABLE \n \n46. \nPJM in its February 23, 2026 compliance filing in this proceeding has proposed to \nallow all retail customer behind-the-meter generation that as of December 18, 2025 was a \nQualifying Facility under PURPA to continue to be able to be netted with its load for NITS \ncharges and capacity requirements after the completion of three-year transition period that would \notherwise end such netting for this generation.42  PJM indicates it made this proposal in its \ncompliance filing as an extension of the legacy treatment of this generation under PURPA.43  \nPJM also notes that given these retail behind-the-meter generation arrangements have been in \nplace and netted against Network Loads within PJM without known operational issues to date, \nPJM proposes to allow such arrangements (some of which have been in place for decades) to \nqualify for legacy treatment and continue to be eligible to net under existing behind-the-meter \ngeneration rules.44 \n47. \nPJM’s proposal for legacy retail behind-the-meter generation treatment for retail \ncustomers with behind-the-meter generation that, as of December 18, 2025, was a Qualifying \nFacility is a step toward providing a just and reasonable outcome for Qualifying Cogeneration \n \n42 PJM February 23, 2026 Compliance Filing Transmittal Letter at Section III.A.2. and Attachment \nA, Definitions R-S, Retail behind the Meter Generation. \n43 PJM February 23, 2026 Compliance Filing Transmittal Letter at Section III.A.2.a. \n44 Id."},{"page":58,"startToken":16727,"endToken":17036,"text":"Exhibit No. IA-1 \nPage 24 of 38 \n \n \n \nFacilities.  However, the step falls short of providing a just and reasonable outcome for \nQualifying Cogeneration Facilities in two respects. \n \n48. \nFirst, PJM’s proposal fails to recognize there may be some Cogeneration \nFacilities within the PJM footprint that fully meet FERC’s requirements to be a Qualifying \nCogeneration Facility (and, thus, a Qualifying Facility), except they do not currently have a \nFERC-approved certification or self-certification of their Qualifying Cogeneration Facility status \nbecause they do not makes sales of excess power either at avoided cost to electric utilities or into \nthe wholesale power market.  In addition, these Cogeneration Facilities have historically not \nneeded certification or self-certification as a Qualifying Cogeneration Facility in order for the \nelectrical load of their host retail customer to have reliable access to backup and maintenance \npower through just and reasonable rates through PJM’s current retail behind the meter generation \nnetting provisions for NITS charges and capacity requirements.  To address this first \nshortcoming that prevents PJM’s Qualifying Facility proposal from being just and reasonable, \nthe proposal would need to be modified to cover all Qualifying Facilities that were in service on \nor prior to December 18, 2025, regardless of the date of their certification or self-certification as \na Qualifying Facility.  This would ensure that generation facilities that were in service on \nDecember 18, 2025 that were fully able to meet FERC’s requirements to be a Qualifying \nFacility, except for not having a FERC-approved certification or self-certification due to not \npreviously having a need for such certification or self-certification, would be able to remedy \ntheir lack of certification or self-certification prior to the conclusion of the proposed three-year \ntransition period for the end of the current PJM retail behind the meter generation netting \nprovisions in order to preserve their ability to use those provisions after the end of the transition \nperiod."},{"page":59,"startToken":17036,"endToken":17336,"text":"Exhibit No. IA-1 \nPage 25 of 38 \n \n \n \n49. \nSecond, PJM has effectively erroneously concluded FERC’s rules for the provision of \nbackup and maintenance power to Qualifying Facilities45 ceased to be applicable in PJM \nfootprint upon FERC’s issuance of its December 18, 2025, Show Cause Order in Docket No. \nEL25-49-000, et al.  FERC made no such finding in its December 18, 2025, Show Cause Order \nas it does not address its PURPA backup and maintenance power rules for Qualifying Facilities \nin that order.  Given this, and the proposed Firm Contract Demand Transmission Service and \nNon-Firm Contract Demand Transmission Service options for Co-Located Loads are unable to \nprovide just and reasonable backup and maintenance power to Qualifying Cogeneration \nFacilities for the reasons I have discussed earlier in this affidavit, the proper legacy treatment for \nQualifying Facilities would be to allow all Qualifying Facilities to continue to be eligible to use \nPJM’s current retail behind-the-meter generation netting provisions for NITS charges and \ncapacity requirements regardless of when that Qualifying Facility entered service or was certified \nor self-certified as a Qualifying Facility.  Therefore, to address this second shortcoming that \nprevents PJM’s Qualifying Facility proposal from being just and reasonable, the proposal would \nneed to be modified to cover all Qualifying Facilities, regardless of the date they entered service \nor the date of their certification or self-certification as a Qualifying Facility. \n50. \nIt is important to note that providing legacy retail behind-the-meter generation \nnetting treatment for all Qualifying Facilities would not provide a “back door” for very large \ncomputational loads to bypass the Co-Located Load provisions of FERC’s December 18, 2025, \nShow Cause Order in Docket No. EL25-49-000, et al.  As I have discussed earlier in this \naffidavit, very large computational load processes are generally not highly thermally integrated, \n \n45 18 CFR § 292.305(c)."},{"page":60,"startToken":17336,"endToken":17633,"text":"Exhibit No. IA-1 \nPage 26 of 38 \n \n \n \nif integrated at all, with any co-located generation facilities whose meter they may be located \nbehind.  This is because those generation facilities will either not be Cogeneration Facilities or \nwould only be Cogeneration Facilities of greatly limited electrical capability relative to the total \nmagnitude of the electrical load of their host retail customer.  Furthermore, Qualifying Small \nPower Production Facilities, the other type of Qualifying Facility besides Qualifying \nCogeneration Facilities, are, except when a waiver is granted by FERC, limited to 80 MW in size \nunder FERC’s rules.46  As a result, the total electrical capability of a Qualifying Small \nProduction Facility would also be greatly limited relative to the total magnitude of a large \ncomputational load, which as I will discuss later in this affidavit, would likely be 300 MW or \nmore.  Therefore, providing legacy retail behind-the-meter generation netting treatment to all \nQualifying Facilities would not provide “back door” for very large computational loads to bypass \nFERC’s Co-Located Load provisions of its December 18, 2025, Show Cause Order in Docket \nNo. EL25-49-000, et al. \n \nVII. \nPJM’S PROPOSED 50 MW AND SMALLER LIMITATION FOR NON-\nQUALIFYING FACILITIES TO USE RETAIL BEHIND THE METER \nGENERATION NETTING ALSO FALLS SHORT OF BEING JUST AND \nREASONABLE \n \n51. \nIn addition to proposing to allow all retail customer behind-the-meter generation \nthat as of December 18, 2025 was a Qualifying Facility under PURPA to continue to be able to \nbe netted with its load for NITS charges and capacity requirements after the completion of three-\nyear transition period that would otherwise end such netting for this generation, PJM in its \nFebruary 23, 2026 compliance filing in this proceeding is also proposing two other such \n \n46 18 CFR §§ 292.203(a), 292.203(c) and 292.204(a)."},{"page":61,"startToken":17633,"endToken":17952,"text":"Exhibit No. IA-1 \nPage 27 of 38 \n \n \n \ncontinuations of retail behind the meter generation netting for NITS charges and capacity \nrequirements. \n \n52. \nFirst, PJM proposes to continue to allow retail behind the meter generation netting \nfor NITS charges and capacity requirements beyond the three-year transition period for all \ngeneration used to serve a retail load served by a Network Customer if the retail behind the meter \ngeneration is subject to contractual arrangements (including but not limited to a bilateral \nagreement or an interconnection agreement) that were in effect as of December 18, 2025 through \nthe end of the term of such agreement, which may be renewed or extended per the terms of such \nagreement. 47  PJM indicates it made this proposal in its compliance filing pursuant to the legacy \ntreatment of existing contractual agreements provided for by FERC under its December 18, \n2025, Show Cause Order in Docket No. EL25-49-000, et al.48  PJM also notes that, given these \nretail behind the meter generation arrangements, like those for PURPA Qualifying Facilities, \nhave been in place and netted against Network Loads within PJM without known operational \nissues to date, it proposes to allow such arrangements, which in some cases have been in place \nfor decades, to qualify for legacy treatment and continue to be eligible to net under existing \nbehind the meter generation rules.49  I agree with this first additional proposed extension of retail \nbehind-the-meter generation netting beyond the three-year transition period, and also agree with \nPJM’s arguments with respect to it. \n \n53. \nSecond, PJM proposes to continue to allow retail behind the meter generation \nnetting for NITS charges and capacity requirements beyond the three-year transition period for \n \n47 PJM February 23, 2026 Compliance Filing Transmittal Letter at Section III.A.2. and Attachment \nA, Definitions R-S, Retail behind the Meter Generation. \n48 PJM February 23, 2026 Compliance Filing Transmittal Letter at Section III.A.2.a. \n49 Id."},{"page":62,"startToken":17952,"endToken":18339,"text":"Exhibit No. IA-1 \nPage 28 of 38 \n \n \n \nall generation whose cumulative nameplate capacity rating is no greater than 50 MW (not \nincluding back-up generation at the same electrical location as the retail load that can only be \nused to serve such retail load during conditions that may threaten the integrity or the PJM Region \nor the regional power system). 50  PJM justifies its proposed cumulative nameplate capacity limit \nfor the continued retail behind the meter generation netting for generators not otherwise eligible \nfor continuation of netting under PJM’s Qualifying Facility and existing contract proposals as \nnot being too high when compared to a lower 10 or 20 MW limit: (i) excluding a much larger \nvolume of retail customers whose grid impacts are small or de minimis when compared with Co-\nLocated Loads coming online today and (ii) potentially causing loss of that generation altogether \ndue to significant transmission upgrades that may be required for that generation to become a \nmarket resource. 51  With respect to justifying why the 50 MW limit is not too low, PJM solely \nrelies on referencing a PJM Board letter defining large load additions as individual load additions \nat or above 50 MW at a single point of interconnection.52 Furthermore, PJM requests that, if its \nproposed Qualifying Facility continuation of retail behind-the-meter generation meeting for \nNITS charges and capacity requirements is not accepted, FERC accept as a potential stop gap a \nhigher limit of possibly as high as 200 MW to avoid the same potential loss of generation \ncapacity issue that it claims would be associated with a 10 or 20 MW limit.53  Under such an \napproach, PJM would commit to reviewing additional data on the size and extent of retail \n \n50 PJM February 23, 2026, Compliance Filing Transmittal Letter at Section III.A.2. and Attachment \nA, Definitions R-S, Retail behind the Meter Generation. \n51 PJM February 23, 2026, Compliance Filing Transmittal Letter at Section III.A.2.c. \n52 Id.  The January 16, 2026 PJM Board Letter does not include any factual or technical detail or \nsupport for the proposed 50 MW threshold.  See Board Decisional Letter on Critical Issue Fast Path - Large \nLoad Additions (Jan. 16, 2026) at p. 2, available at https://www.pjm.com/-/media/DotCom/about-\npjm/who-we-are/public-disclosures/2026/20260116-pjm-board-letter-re-results-of-the-cifp-process-large-\nload-additions.pdf. \n53 Id."},{"page":63,"startToken":18339,"endToken":18638,"text":"Exhibit No. IA-1 \nPage 29 of 38 \n \n \n \nbehind-the-meter generation, which could inform whether the initial higher stop gap limit should \nbe further refined through a separate future filing.54 \n \n54. \nPJM’s proposed 50 MW cumulative nameplate capacity limit for determining \nwhich retail behind-the-meter generation facilities, besides those who qualify under its \nQualifying Facility and existing contract proposals, would be eligible for continued retail behind \nthe meter generation netting treatment after the three-year transition period is not just and \nreasonable.  The proposed limit is not just and reasonable for two reasons.  First, it imposes a cap \nbased on the cumulative nameplate capacity of the generation behind the customer's meter, rather \nthan limiting the amount of load that can be netted behind the meter.  Second, the proposed \nthreshold amount of 50 MW is too low. \nThe Proposed 50 MW Limit is Inappropriately Applied to Cumulative Nameplate Capacity \nRather than the Amount of Retail Load that can be Netted \n     \n \n55. \nPJM’s proposal to apply its proposed 50 MW limit to cumulative nameplate \ncapacity rather than the amount of retail load that can be netted against generation located behind \nthat load’s meter is not just and reasonable for at least four reasons. \n56. \nFirst, nameplate capacity does not necessarily indicate the actual electrical \ncapability of behind-the-meter generation.  This can be particularly the case with generation \nserved from a common steam system, where it is the total capability of the steam system that \nlimits the combined electrical capability of the steam turbine generation facilities fed from it, not \nthe cumulative (i.e., the sum of the) nameplate capacity of the steam turbines.  In such situations, \nit would be inappropriate to apply the limit to cumulative nameplate capacity, as that amount \ncould be significantly higher than the actual electrical capability of the generation. \n \n54 Id."},{"page":64,"startToken":18638,"endToken":18973,"text":"Exhibit No. IA-1 \nPage 30 of 38 \n \n \n \n \n57. \nSecond, the cumulative nameplate capacity of the behind-the-meter generation, \neven when it does indicate the actual electrical capability of that behind-the-meter generation, \nmay be intentionally much larger than the retail load at its location in order to provide \nredundancy with respect to serving that load.  In this situation, it would also be inappropriate to \napply the limit to the cumulative nameplate capacity of the generation as that amount could be \nsignificantly higher than the actual retail load being served by that generation solely due to the \nredundancy being provided to improve the reliability of serving that load with behind the meter \ngeneration. \n \n58. \nThird, the proposal to use the cumulative nameplate capacity of the behind-the-\nmeter generation fails to account for a critical operational limitation.  Specifically, the generation \ncould not be operated in excess of the retail load it is serving behind the meter unless the \ngeneration has an interconnection agreement with PJM or the applicable transmission owner that \nallows it to put its power in excess of the retail load it is serving behind the meter onto the \ntransmission system.  Without such an agreement, the generation is effectively constrained to \nserving only the retail load behind the meter.  When limited in this matter, the largest generation \ncontingency the generator could place onto the PJM transmission system is a loss of generation \nequal to the amount of retail load the behind-the-meter generation is serving, not its cumulative \nnameplate capacity.  Furthermore, this concept is readily extendable to a situation where there is \na limit on the amount of retail load that can be served behind the meter by limiting the output of \nthe generation to the lesser of: (i) the current demand of the retail load or (ii) the MW limit \nplaced on retail behind the meter generation netting. \n59. \nFinally, the proposal fails to consider a large portion of behind the meter \ngeneration may not be associated with serving the electrical load of the host retail customer"},{"page":65,"startToken":18973,"endToken":19323,"text":"Exhibit No. IA-1 \nPage 31 of 38 \n \n \n \nbehind that customer’s meter but rather associated with either PURPA Qualifying Facility sales \nat avoided cost to an electric utility or sales into the wholesale market within the bounds the \ngeneration facility’s interconnection agreement.  As I noted earlier in this affidavit, this situation \nis not uncommon for Qualifying Cogeneration Facilities with a host retail customer that has a \nvery large steam need as the level of electric power production necessary by the Cogeneration \nFacility to produce the heat needed to meet the steam requirement of the host retail customer \nmay be much higher than the electrical load of the Cogeneration Facility’s host retail customer.55  \nIn addition, for non-Cogeneration Facilities, this situation can exist due the economy of scale \nbenefits of constructing a generation facility to not only serve the electrical load of the host retail \ncustomer behind the meter but to also make wholesale power sales.  Regardless of why the \nbehind the meter generation facility makes avoided cost or wholesale market sales, it is \nimportant to note the loss of the total electrical capability of the generation facility, less any \nelectrical load of the host retail customer that is lost with the loss of that electrical capability, has \nalready been considered as a generation contingency in determining the transmission upgrades \nthat were necessary to allow interconnection of the generation facility, and, as a result, the \ntransmission system has been built to accommodate that level of generation contingency.  \nTherefore, provided the generation operates within the bounds of its interconnection agreement \nand the bounds of PJM’s wholesale market rules, retail behind the meter generation with excess \npower sales does not introduce any circumstances that should preclude it from still being able to \nutilize retail behind the meter generation netting for NITS charges and capacity requirements for \n \n55 As an aside, it is important to note FERC’s rules for backup and maintenance power must be met \nfor all Qualifying Facilities regardless of whether a Qualifying Facility has any excess power sales either \nat avoided cost to an electric utility or into the wholesale power market."},{"page":66,"startToken":19323,"endToken":19659,"text":"Exhibit No. IA-1 \nPage 32 of 38 \n \n \n \nits host retail customer up to any MW limit on such netting.   This would be accomplished by \ncalculating the output of the generation to the PJM market (including any avoided costs sales to \nan electric utility) as the gross output of the generation less the lower of: (i) the current demand \nof the retail load being served by the generation behind the meter or (ii) the MW limit placed on \nretail behind the meter generation netting. \n \n60. \nFor the above reasons, the MW limit that is ultimately approved by FERC should \nbe a limit on the maximum MW of retail load that can be netted with behind-the-meter \ngeneration when determining NITS charges and capacity requirements for that retail load.  It \nshould not be a cumulative nameplate capacity limit that determines which locations where retail \nbehind-the-meter generation netting will be allowed, as proposed by PJM. \nPJM’s Proposed 50 MW Limit is Too Low \n \n61. \nPJM’s proposed 50 MW limit is too low for at least four reasons. \n \n62. \nFirst, PJM is solely relying on the PJM Board’s definition of large load additions \nas 50 MW at a single site to justify its proposed 50 MW limit as not being too low.  The PJM \nBoard is not a regulatory body that has made a finding of fact that 50 MW is the appropriate \nlimit for retail behind-the-meter generation netting.  Furthermore, the PJM Board did not develop \nits large load definition in the context of establishing a limit on retail behind-the-meter \ngeneration netting.  As such, it should be given no weight with respect to setting a limit on retail \nbehind-the-meter netting. \n \n63. \nSecond, PJM has not provided any evidence that the concerns it expressed with \nrespect to a limit of 10 or 20 MW – (i) excluding a large volume of retail customers whose grid \nimpacts are small or de minimis when compared with Co-Located Loads coming online today \nand (ii) potentially causing a loss of that generation altogether due to significant transmission"},{"page":67,"startToken":19659,"endToken":19975,"text":"Exhibit No. IA-1 \nPage 33 of 38 \n \n \n \nupgrades that may be required for them to become market resources – are not still present with a \n50 MW limit.  Also, it appears PJM is concerned its 50 MW limit may be too low in this respect, \nparticularly if its proposal for Qualifying Facilities is not accepted by FERC.  Specifically, as I \nnoted earlier in this affidavit, PJM has requested that FERC adopt a higher limit, potentially as \nhigh as 200 MW, as a stopgap if FERC chooses not to accept PJM’s proposal with respect to \nQualifying Facilities.56 \n \n64. \nThird, PJM, in its February 23, 2026 compliance filing in this proceeding, \nindicated that Qualifying Facility retail behind the meter generation and retail behind the meter \ngeneration with existing contracts have been in place and netted against Network Loads within \nPJM without known operational issues to date, and in some cases have been in place for decades.  \nWhile I certainly agree this is true for Qualifying Facilities and retail behind the generation with \nexisting contracts, it must also be generally true for all other existing retail behind-the-meter \ngeneration that has been in place for many years within the PJM footprint.  Furthermore, its \nexistence suggests that retail behind-the-meter generation netting at the MW level for individual \nretail customer locations for which it has historically occurred is something that can be readily \naccommodated in normal transmission planning and transmission operations such that it does not \nneed extraordinary treatment, such as prohibiting it.  This in turn suggests that a better basis for \ndeveloping a limit on how much retail behind the meter generation netting should be permitted \nbehind each retail customer’s meter would be to examine the largest amount of retail behind the \nmeter generation netting that has been readily accommodated in recent years and comparing that \n \n56 PJM February 23, 2026 Compliance Filing Transmittal Letter at Section III.A.2.c."},{"page":68,"startToken":19975,"endToken":20336,"text":"Exhibit No. IA-1 \nPage 34 of 38 \n \n \n \nto the typical size of the very large computational load additions that have triggered the need to \nconsider the Co-Located Loads issue in the first place. \n \n65. \nFinally, there is evidence that the typical size of very large computational load \nadditions, which are the load additions driving the need to examine the Co-Located Loads issue, \nis much larger than 50 MW. \n66. \nFor example, in the context of FERC’s Advanced Notice of Proposed Rulemaking \nin Docket No. RM26-4-000, Indicated PJM Transmission Owners stated: \nTo the extent the Commission asserts jurisdiction over large load \ninterconnections, it should adopt a sufficiently narrow definition of ‘large load \ncustomer’ limited to large (200 MW or greater) data center customers. It is those \ncustomers that are primarily driving load increases.57 \n \n \n67. \nIn addition, in early July 2025, in Michigan Public Service Commission \n(“MPSC”) Case No. U-21859, I performed and presented in rebuttal testimony an analysis of the \nMW size of the data center load addition inquiries that Consumers Energy Company had \nreceived up to that point in time.  A summary of the results of that analysis is presented in \nAttachment 2 of this affidavit, and the raw data upon which it was performed is provided in \nAttachment 3 of this affidavit.58  As shown in Attachment 2, my analysis indicated that the sum \nof the MWs of potential data center load addition inquiries Consumers Energy Company had \nreceived associated with a MW size of 300 MW or less makes up less than 7% (1,049 MW) of \nthe 15,249 MW in total large data center load addition inquiries that it had received.  In other \nwords, over 93% (14,200 MW) of the total MWs of large data center load addition inquiries \nConsumers Energy Company had received were from load additions greater than or equal to 300 \n \n57 Reply Comments of the Indicated PJM Transmission Owners, Interconnection of Large Loads to \nthe Interstate Transmission System, Docket No. RM26-4-000 (Dec. 5, 2025) at 2-3. \n58 The workpaper used to produce Attachment 2 of this affidavit is available on request to parties \nin this current proceeding from Industrials/Amtrak Counsel."},{"page":69,"startToken":20336,"endToken":20682,"text":"Exhibit No. IA-1 \nPage 35 of 38 \n \n \n \nMW in size.  While Consumers Energy Company is located within MISO rather than PJM, there \nis no reason to believe the results for Consumers Energy Company are not indicative of what a \nsimilar analysis would likely show for similar large electric utilities in PJM.  In other words, the \nlarge load additions to be concerned with are not all large load additions 50 MW and larger, but \nrather those 300 MW or higher, as evidenced by my analysis, since they make up the vast \nmajority of what is being proposed.  Accordingly, more concrete evidence exists to support a 300 \nMW threshold than a 50 MW threshold. \n \n68. \nIn addition, in September 2025, subsequent to the performance of my early July \n2025 analysis based on Consumers Energy Company data, I became involved in Illinois \nCommerce Commission (“ICC”) Docket No. 25-0677.  That Illinois proceeding concerned \nCommonwealth Edison Company (“ComEd”) – a very large Illinois electric utility located within \nPJM.  In that proceeding, ComEd Witness Max Leichtman in direct testimony indicated “the \naverage size of a unique large demand project that began the process of obtaining electric service \nfrom ComEd in the last twelve months is approximately 700 MWs, roughly the equivalent of \n1,400 big box stores.”59  Furthermore, in response to discovery in that proceeding, ComEd \nprovided a data request response that publicly disclosed the MW size of each of the \naforementioned projects.60  A copy of this ComEd discovery response in ICC Docket No. 25-\n0677 is provided as Attachment 4 to my affidavit.  As can be seen in Attachment 4, in 2025, \nthrough the August 29, 2025 date of the ComEd discovery response, twelve (12) load additions \nbegan the process of obtaining electric service from ComEd.  Ten (10) of the twelve (12) \nproposed load additions, representing 8,212 MW (98.86%) of the total of 8,307 MW of requested \n \n59 ICC Docket No. 25-0677, ComEd Ex. 1.0, Direct Testimony of Max Leichtman at 6. \n60 ICC Docket No. 25-0677, ComEd Response to Data Request No. NRG-ComEd 1.02."},{"page":70,"startToken":20682,"endToken":20991,"text":"Exhibit No. IA-1 \nPage 36 of 38 \n \n \n \nelectric service, were from proposed loads with a magnitude of 300 MW or greater.  This \nprovides further concrete evidence to support a 300 MW threshold rather than a 50 MW \nthreshold.   \n \n69. \nFor the foregoing reasons, PJM’s proposed limit of 50 MW is too low.  Concrete \nevidence exists to support a 300 MW threshold, and any limit should instead initially be set no \nlower than 200 MW (if not closer to 300 MW), regardless of whether PJM’s proposal for \nQualifying Facilities is accepted or that proposal is modified as I have recommended earlier in \nthis affidavit. \n          \nVIII. CONCLUSION \n70. \nIn summary, I conclude the following: \n Very large computational loads co-located behind the meter of generation \nfacilities are not similarly situated to traditional large commercial, \nindustrial, and institutional loads using Cogeneration Facilities located \nbehind their meter, as very large computational loads generally are not \nhighly thermally integrated with any co-located generation facilities. \n \n For traditional large loads served by Cogeneration Facilities, PJM’s \ncurrent retail behind-the-meter generation netting provisions for NITS \ncharges and capacity requirements are consistent with cost causation \nprinciples and FERC’s own backup and maintenance power rules for \nQualifying Facilities, as they rely on factual data regarding each \nQualifying Facility’s historical performance rather than assumptions about \nwhen outages will occur and whether they will occur simultaneously. \n \n Firm Contract Demand Transmission Service and Non-Firm Contract \nDemand Transmission Service are not capable – either alone or in tandem \n– of providing reliable backup and maintenance power to traditional large \nretail customers that utilize Qualifying Cogeneration Facilities at rates \nconsistent with cost causation principles and FERC’s rules for providing \nbackup and maintenance service to Qualifying Facilities. \n \n PJM’s proposal to limit legacy retail behind-the-meter generation \ntreatment for Qualifying Facilities to those certified or self-certified as of \nDecember 18, 2025 falls short of being just and reasonable, and should be"},{"page":71,"startToken":20991,"endToken":21112,"text":"Exhibit No. IA-1 \nPage 37 of 38 \n \n \n \nmodified to cover all Qualifying Facilities regardless of the date they \nentered service or the date of their certification or self-certification. \n \n PJM’s proposed 50 MW cumulative nameplate capacity limit for \ncontinued retail behind-the-meter generation netting for non-Qualifying \nFacility generation is not just and reasonable because the limit is \ninappropriately applied to cumulative nameplate capacity rather than to \nthe amount of retail load that can be netted, and 50 MW is too low given \nthat the large computational load additions driving the Co-Located Loads \nissue are overwhelmingly 300 MW or larger in size; any limit should \ninitially be set no lower than 200 MW (if not closer to 300 MW). \n \n \n71. \nFurther Affiant sayeth naught."},{"page":72,"startToken":21112,"endToken":21160,"text":"Exhibit No.IA-1\nPage 38 of38\nes R. Dauph\nSTATE OF'MISSOURI\nCOUNTY OF ST. LOUIS\nSubscribed and sworn to before me this 16th day of March,2026.\nNotary Public\n)\n)\n)\nSS\nNotary Public - Notary Soal\nSTATE OF MISSOURI\nJetferson County\nCommission Expiresr Mar, 22,2029\nMy\n# 21989987\nADRIENNE J."},{"page":73,"startToken":21160,"endToken":21373,"text":"Exhibit No. IA-1 \nAttachment 1 \nPage 1 of 6 \n \n \n \nBRUBAKER & ASSOCIATES, INC. \nQualifications of James R. Dauphinais \n \nQ \nPLEASE STATE YOUR NAME AND BUSINESS ADDRESS. \n1 \nA \nJames R. Dauphinais.  My business address is 16690 Swingley Ridge Road, Suite 140, \n2 \nChesterfield, MO 63017, USA. \n3 \n \nQ \nPLEASE STATE YOUR OCCUPATION.    \n4 \nA \nI am a consultant in the field of public utility regulation and a Managing Principal with \n5 \nthe firm of Brubaker & Associates, Inc. (“BAI”), energy, economic and regulatory \n6 \nconsultants. \n7 \n \nQ \nPLEASE SUMMARIZE YOUR EDUCATIONAL BACKGROUND AND \n8 \nEXPERIENCE.  \n9 \nA \nI graduated from Hartford State Technical College in 1983 with an Associate's Degree \n10 \nin Electrical Engineering Technology.  Subsequent to graduation, I was employed by \n11 \nthe Transmission Planning Department of the Northeast Utilities Service Company1 as \n12 \nan Engineering Technician. \n13 \n \n \nWhile employed as an Engineering Technician, I completed undergraduate \n14 \nstudies at the University of Hartford.  I graduated in 1990 with a Bachelor's Degree in \n15 \nElectrical Engineering.  Subsequent to graduation, I was promoted to the position of \n16 \nAssociate Engineer.  Between 1993 and 1994, I completed graduate level courses in the \n17 \nstudy of power system analysis, power system transients and power system protection \n18 \n \n \n1In 2015, Northeast Utilities changed its name to Eversource Energy."},{"page":74,"startToken":21373,"endToken":21668,"text":"Exhibit No. IA-1 \nAttachment 1 \nPage 2 of 6 \n \n \n \nBRUBAKER & ASSOCIATES, INC. \nthrough the Engineering Outreach Program of the University of Idaho.  By 1996 I had \n1 \nbeen promoted to the position of Senior Engineer. \n2 \n \n \nIn the employment of the Northeast Utilities Service Company, I was \n3 \nresponsible for conducting thermal, voltage and stability analyses of the Northeast \n4 \nUtilities' transmission system to support planning and operating decisions.  This \n5 \ninvolved the use of load flow, power system stability and production cost computer \n6 \nsimulations.  It also involved examination of potential solutions to operational and \n7 \nplanning problems including, but not limited to, transmission line solutions and the \n8 \nroutes that might be utilized by such transmission line solutions.  Among the most \n9 \nnotable achievements I had in this area include the solution of a transient stability \n10 \nproblem near Millstone Nuclear Power Station, and the solution of a small signal (or \n11 \ndynamic) stability problem near Seabrook Nuclear Power Station.  In 1993 I was \n12 \nawarded the Chairman's Award, Northeast Utilities’ highest employee award, for my \n13 \nwork involving stability analysis in the vicinity of Millstone Nuclear Power Station. \n14 \nFrom 1990 to 1996, I represented Northeast Utilities on the New England Power \n15 \nPool Stability Task Force.  I also represented Northeast Utilities on several other \n16 \ntechnical working groups within the New England Power Pool (“NEPOOL”) and the \n17 \nNortheast Power Coordinating Council (“NPCC”), including the 1992-1996 New York-\n18 \nNew England Transmission Working Group, the Southeastern Massachusetts/Rhode \n19 \nIsland Transmission Working Group, the NPCC CPSS-2 Working Group on Extreme \n20 \nDisturbances and the NPCC SS-38 Working Group on Interarea Dynamic Analysis.  \n21 \nThis latter working group also included participation from a number of ECAR, PJM and \n22 \nVACAR utilities.  \n23"},{"page":75,"startToken":21668,"endToken":21955,"text":"Exhibit No. IA-1 \nAttachment 1 \nPage 3 of 6 \n \n \n \nBRUBAKER & ASSOCIATES, INC. \nFrom 1990 to 1995, I also acted as an internal consultant to the \n1 \nNuclear Electrical Engineering Department of Northeast Utilities.  This included \n2 \ninteractions with the electrical engineering personnel of the Connecticut Yankee, \n3 \nMillstone and Seabrook nuclear generation stations and inspectors from the Nuclear \n4 \nRegulatory Commission (“NRC”). \n5 \nIn addition to my technical responsibilities, from 1995 to 1997, I was also \n6 \nresponsible for oversight of the day-to-day administration of Northeast Utilities' Open \n7 \nAccess Transmission Tariff.  This included the creation of Northeast Utilities' pre-FERC \n8 \nOrder No. 889 transmission electronic bulletin board and the coordination of Northeast \n9 \nUtilities' transmission tariff filings prior to and after the issuance of Federal Energy \n10 \nRegulatory Commission (“FERC” or “Commission”) FERC Order No. 888.  I was also \n11 \nresponsible for spearheading the implementation of Northeast Utilities' Open Access \n12 \nSame-Time Information System and Northeast Utilities’ Standard of Conduct under \n13 \nFERC Order No. 889.  During this time, I represented Northeast Utilities on the Federal \n14 \nEnergy Regulatory Commission's \"What\" Working Group on Real-Time Information \n15 \nNetworks.  Later I served as Vice Chairman of the NEPOOL OASIS Working Group \n16 \nand Co-Chair of the Joint Transmission Services Information Network Functional \n17 \nProcess Committee.  I also served for a brief time on the Electric Power Research \n18 \nInstitute facilitated \"How\" Working Group on OASIS and the North American Electric \n19 \nReliability Council facilitated Commercial Practices Working Group. \n20 \nIn 1997 I joined the firm of Brubaker & Associates, Inc.  The firm includes \n21 \nconsultants with backgrounds in accounting, engineering, economics, mathematics, \n22 \ncomputer science and business.  Since my employment with the firm, I have filed or \n23"},{"page":76,"startToken":21955,"endToken":22217,"text":"Exhibit No. IA-1 \nAttachment 1 \nPage 4 of 6 \n \n \n \nBRUBAKER & ASSOCIATES, INC. \npresented testimony before the Federal Energy Regulatory Commission in Consumers \n1 \nEnergy Company, Docket No. OA96-77-000; Midwest Independent Transmission \n2 \nSystem Operator, Inc., Docket No. ER98-1438-000; Montana Power Company, Docket \n3 \nNo. ER98-2382-000; Inquiry Concerning the Commission’s Policy on Independent \n4 \nSystem Operators, Docket No. PL98-5-003; SkyGen Energy LLC v. Southern Company \n5 \nServices, Inc., Docket No. EL00-77-000; Alliance Companies, et al., Docket No. EL02-\n6 \n65-000, et al.; Entergy Services, Inc., Docket No. ER01-2201-000; Remedying Undue \n7 \nDiscrimination through Open Access Transmission Service, Standard Electricity \n8 \nMarket Design, Docket No. RM01-12-000; Midwest Independent Transmission System \n9 \nOperator, Inc., Docket No. ER10-1791-000; NorthWestern Corporation, Docket No. \n10 \nER10-1138-001, et al.; Illinois Industrial Energy Consumers v. Midcontinent \n11 \nIndependent System Operator, Inc., Docket No. EL15-82-000; Midcontinent \n12 \nIndependent System Operator, Inc., Docket No. ER16-833-000; Midcontinent \n13 \nIndependent System Operator, Inc., Docket No. ER17-284-000; and Midcontinent \n14 \nIndependent System Operator, Inc. and Ameren Services Company Docket No. ER18-\n15 \n463-000.  I have also filed or presented testimony before the Alberta Utilities \n16 \nCommission, the California Public Utilities Commission, the Colorado Public Utilities \n17 \nCommission, the Connecticut Department of Public Utility Control, the Florida Public \n18 \nService Commission, the Idaho Public Service Commission, the Illinois Commerce \n19 \nCommission, the Indiana Utility Regulatory Commission, the Iowa Utilities Board, the \n20 \nKentucky Public Service Commission, the Louisiana Public Service Commission, the \n21 \nMichigan Public Service Commission, the Missouri Public Service Commission, the \n22 \nMontana Public Service Commission, the Nevada Public Utilities Commission, the New \n23"},{"page":77,"startToken":22217,"endToken":22497,"text":"Exhibit No. IA-1 \nAttachment 1 \nPage 5 of 6 \n \n \n \nBRUBAKER & ASSOCIATES, INC. \nMexico Public Regulation Commission, the Council of the City of New Orleans, the \n1 \nState of New York Public Service Commission, the Oklahoma Corporation \n2 \nCommission, the Public Utility Commission of Texas, the Public Service Commission \n3 \nof Utah, the Virginia State Corporation Commission, the Wisconsin Public Service \n4 \nCommission, the Wyoming Public Service Commission, Federal District Court and \n5 \nvarious committees of the Illinois, Missouri and South Carolina state legislatures.  This \n6 \ntestimony has been given regarding a wide variety of issues including, but not limited \n7 \nto, ancillary service rates, avoided cost calculations, certification of public convenience \n8 \nand necessity, class cost of service, cost allocation, fuel adjustment clauses, fuel costs, \n9 \ngeneration interconnection, interruptible rates, market power, market structure, \n10 \noff-system sales, prudency, purchased power costs, resource adequacy, resource \n11 \nplanning, rate design, retail open access, standby rates, transmission losses, transmission \n12 \nplanning, transmission rates and transmission line routing. \n13 \nI have also participated on behalf of clients in the Southwest Power Pool \n14 \nCongestion Management System Working Group, the Alliance Market Development \n15 \nAdvisory Group and several committees and working groups of the Midcontinent \n16 \nIndependent System Operator, Inc. (“MISO”), including the Congestion Management \n17 \nWorking Group; Economic Planning Users Group; Loss of Load Expectation Working \n18 \nGroup; Market Subcommittee; Michigan Transmission Studies Task Force; Planning \n19 \nSubcommittee; Regional Expansion, Criteria and Benefits Working Group; Resource \n20 \nAdequacy Subcommittee (formerly the Supply Adequacy Working Group); and \n21 \nReliability Subcommittee.  I am currently a member of the MISO Advisory Committee \n22 \nin the end-use customer sector on behalf of industrial customer groups in Illinois, \n23"},{"page":78,"startToken":22497,"endToken":22581,"text":"Exhibit No. IA-1 \nAttachment 1 \nPage 6 of 6 \nBRUBAKER & ASSOCIATES, INC. \nLouisiana, Michigan and Texas.  I am also the past Chairman of the Issues/Solutions \n1 \nSubgroup of the MISO Revenue Sufficiency Guarantee (“RSG”) Task Force.   \n2 \nIn 2009, I completed the University of Wisconsin-Madison High Voltage Direct \n3 \nCurrent (“HVDC”) Transmission course for Planners that was sponsored by MISO.  I \n4 \nam a member of the Power and Energy Society (“PES”) of the Institute of Electrical and \n5 \nElectronics Engineers (“IEEE”).   \n6"},{"page":79,"startToken":22581,"endToken":22714,"text":"Exhibit No. IA-1 \nAtatchment 2 \nPage 1 of 1\n<100 MW\n< 150 MW\n< 200 MW\n< 250 MW\n< 300 MW\n< 350 MW\n< 400 MW\n< 1,000 MW <= 1,200 MW\nUknown MW\nTotal # of Load Inquiries\n2\n  \n5\n  \n5\n  \n7\n  \n8\n  \n16\n  \n16\n  \n26\n  \n32\n  \n6\n  \nTotal Amount of MW\n54\n  \n399\n  \n399\n  \n799\n  \n1,049\n  \n3,449\n  \n3,449\n  \n9,049\n  \n15,249\n  \n% of 15,249 MW\n0.35%\n2.62%\n2.62%\n5.24%\n6.88%\n22.62%\n22.62%\n59.34%\n100.00%\n% of 15,249 MW above\n99.65%\n97.38%\n97.38%\n94.76%\n93.12%\n77.38%\n77.38%\n40.66%\n0.00%\nSource:  Attachment to Consumers' Data Request Response U21859-DCC-CE-0045 (Exhibit No. IA-1, Attachment 3)\nAnalysis of MW Size of Consumers' Large Data Center Load Addition Inquiries"},{"page":80,"startToken":22714,"endToken":22817,"text":"U21859-DCC-CE-0045 \nPage 1 of 1 \nQuestion: \n21859-DCC-CE-0013. Please refer to Connolly Direct at 4:7-8. “The Company has data center inquiries that \ntotal over 15 gigawatts of electric load in the economic development pipeline.” Please provide a \nspreadsheet or other document listing each of the referenced “data center inquiries,” and identify, for \neach inquiry: a) the proposed location; b) the associated electric load and/or contract capacity; and c) the \ntimeline for energization and delivery of requested capacity, including any proposed load ramp. \nResponse: \nSee attached \nWitness: Laura M. Connolly \nDate: May 13, 2025 \nExhibit No. IA-1 \nAttachment 3\nPage 1 of 3"},{"page":81,"startToken":22817,"endToken":23159,"text":"1\nDescription\nDate of Inquiry\nPeak demand \nreached year\n50% of peak year\nRequested in-\nservice year\nLoad\n(MW)\nLocation\nId\nData Center\n10/7/2024\nUnknown\nUnknown\nAs soon as possible\n400\nEast Central Region\nA\nData Center\n10/4/2024\nQ1 2040\nQ2 2033\nQ1 2026\n1,000\nSouth Central Region\nB\nData Center\n11/6/2024\nUnknown\nUnknown\nUnknown\n300\nUnknown\nC\nData Center\n7/15/2024\nUnknown\nUnknown\nAs soon as possible\n300\nEast Central Region\nD\nData Center\n5/7/2024\nWithin 36 months\nUnknown\nAs soon as possible\n200\nUnknown\nE\nData Center\n12/3/2024\nUnknown\nUnknown\nUnknown\nUnknown\nSouthwest Region\nF\nData Center\n11/19/2024\nUnknown\nUnknown\nUnknown\n200\nUnknown\nG\nData Center\n3/10/2025\nUnknown\nUnknown\nAs soon as possible\n250\nUnknown\nH\nData Center\n2/26/2025\nWithin 36 months\nUnknown\nAs soon as possible\n1,000\nEast Central Region\nI\nData Center\n3/1/2024\nQ4 2033\nQ4 2030\nQ1 2029\n300\nWest Region\nJ\nData Center\n6/6/2024\nQ4 2033\nQ2 2030\nQ4 2029\n300\nUnknown\nK\nData Center\n1/9/2025\nUnknown\nUnknown\nUnknown\n100\nEast Region\nL\nData Center\n12/4/2024\nQ1 2030\nUnknown\nUnknown\n300\nUnknown\nM\nData Center\n2/4/2025\nUnknown\nUnknown\nUnknown\n700\nEast Region\nN\nData Center\n2/28/2025\nWithin 5-10 years\nUnknown\nWithin 2-3 years\n1,000\nUnknown\nO\nData Center\n3/10/2025\nUnknown\nUnknown\nUnknown\n300\nEast Central Region\nP\nData Center\n7/29/2024\nUnknown\nUnknown\nUnknown\nUnknown\nUnknown\nQ\nData Center\n8/7/2024\nUnknown\nUnknown\nUnknown\n500\nUnknown\nR\nData Center\n10/4/2024\nUnknown\nUnknown\nUnknown\n100\nSouth Central Region\nS\nData Center\n10/31/2024\nQ1 2031\nUnknown\nQ1 2027\nUnknown\nUnknown\nT\nData Center\n12/19/2024\nUnknown\nUnknown\nUnknown\n50\nSouthwest Region\nU\nData Center\n10/16/2024\nQ4 2030\nQ2 2029\nQ1 2028\n1,200\nUnknown\nV\nData Center\n8/19/2024\nUnknown\nUnknown\nUnknown\n300\nUnknown\nW\nExhibit No. IA-1 \nAttachment 3\nPage 2 of 3"},{"page":82,"startToken":23159,"endToken":23369,"text":"2\nDescription\nDate of Inquiry\nPeak demand \nreached year\n50% of peak year\nRequested in-service \nyear\nLoad\n(MW)\nLocation\nId\nData Center\n7/25/2024\n2024\n2024\n2024\n4\nSouthwest Region\nX\nData Center\n1/15/2025\nUnknown\nUnknown\nUnknown\n300\nUnknown\nY\nData Center\n10/31/2024\nUnknown\nUnknown\nUnknown\nUnknown\nUnknown\nZ\nData Center\n9/10/2024\nUnknown\nUnknown\nUnknown\n500\nUnknown\nAA\nData Center\n10/31/2024\nUnknown\nUnknown\nQ1 2029\n1,000\nUnknown\nAB\nData Center\n7/12/2024\nQ1 2029\nUnknown\nQ1 2026\n500\nUnknown\nAC\nData Center\n10/29/2024\nUnknown\nUnknown\nUnknown\nUnknown\nUnknown\nAD\nData Center\n7/25/2024\nQ3 2029\nQ3 2027\nQ3 2026\n500\nUnknown\nAE\nData Center\n10/10/2024\nUnknown\nUnknown\nUnknown\n500\nUnknown\nAF\nData Center\n12/11/2024\n2030\nUnknown\nQ4 2027\n600\nUnknown\nAG\nData Center\n7/31/2024\nUnknown\nUnknown\nUnknown\n145\nUnknown\nAH\nData Center\n2/4/2025\nUnknown\nUnknown\n2027\n1,000\nUnknown\nAI\nData Center\n1/6/2025\nQ1 2029\nUnknown\nUnknown\n500\nSoutheasterly Region\nAJ\nData Center\n9/11/2024\nQ4 2029\nQ4 2028\nQ4 2027\n900\nUnknown\nAK\nData Center\n11/21/2024\nUnknown\nUnknown\nUnknown\nUnknown\nEast Central\nAL\nExhibit No. IA-1 \nAttachment 3\nPage 3 of 3"},{"page":83,"startToken":23369,"endToken":23545,"text":"ICC Docket Nos. 25-0677 & 25-0679 (Cons.) \nCommonwealth Edison Company’s Response to \nNRG Energy, Inc. (“NRG”) Information Requests \nNRG-ComEd 1.01-NRG-ComEd 1.20 \nDate Received:  August 22, 2025 \nDate Served:  August 29, 2025 \nREQUEST NO. NRG-ComEd 1.02: \nPlease provide all workpapers, analyses, data, and information used or relied upon by Max \nLeichtman in relation to ComEd Ex. 1.0, the Direct Testimony of Max Leichtman. \nRESPONSE: \nComEd objects to this request as overly broad and unduly burdensome to the extent it seeks “all \n… data and information … relied upon” by ComEd witness Leichtman, and to the extent that \nmuch of the “data and information” is not relevant and not calculated to lead to the discovery of \nrelevant and admissible evidence.  Subject to and without waiving those objections, ComEd \nresponds as follows: \nSee NRG-ComEd 1.02_Attach 1 for the data supporting Figure 1 in the direct testimony of Max \nLeichtman (ComEd Ex. 1.0) at lines 122-123.  There are no other workpapers supporting Mr. \nLeichtman’s testimony. \n2025LLT 0000007\nExhibit No. IA-1 \nAttachment 4\nPage 1 of 4"},{"page":84,"startToken":23545,"endToken":23737,"text":"Year\nNew/Expansion\nComEd New \nUltimate \n2018\nNew\n2.000\n    \n2018\nNew\n14.000\n     \n2018\nNew\n22.000\n     \n2018\nNew\n24.000\n     \n2018\nNew\n4.000\n    \n2018\nExpansion\n24.000\n     \n2018\nNew\n3.500\n    \n2018 Total\n93.500\n  \n2019\nNew\n4.100\n    \n2019\nNew\n4.050\n    \n2019\nExpansion\n3.000\n    \n2019\nExpansion\n4.100\n    \n2019\nExpansion\n12.310\n     \n2019\nExpansion\n2.700\n    \n2019\nNew\n5.370\n    \n2019\nExpansion\n1.200\n    \n2019\nNew\n5.000\n    \n2019\nNew\n37.787\n     \n2019 Total\n79.617\n \n2020\nNew\n13.70\n2020\nNew\n0.10\n2020\nNew\n2.00\n2020\nNew\n71.80\n2020\nNew\n68.30\n2020\nNew\n48.00\n2020\nNew\n28.98\n2020\nNew\n16.00\n2020\nExpansion\n5.00\n2020\nNew\n5.30\n2020\nNew\n4.00\n2020\nNew\n1.25\n2020\nNew\n12.29\n2020\nNew\n5.80\n2020\nNew\n11.25\n2020\nNew\n15.70\n2020\nNew\n7.70\n2020\nNew\n208.00\n2020 Total\n525.16\n2021\nNew\n108.00\n2021\nNew\n4.00\n-\n-\nICC Dkt Nos. 25-0677 / 25-0679 (Cons.)\nNRG-ComEd 1.02_Attach 1 \nPage 1 of 3\n2025LLT 0000008\nExhibit No. IA-1 \nAttachment 4\nPage 2 of 4"},{"page":85,"startToken":23737,"endToken":23932,"text":"2021\nNew\n250.00\n2021\nExpansion\n10.00\n2021\nNew\n34.00\n2021\nNew\n3.00\n2021\nNew\n2.10\n2021\nNew/Expansion\n4.00\n2021\nNew\n24.00\n2021\nNew\n10.00\n2021\nNew\n24.00\n2021\nNew\n1.00\n2021\nNew\n6.50\n2021\nNew\n5.20\n2021\nNew\n8.00\n2021\nNew\n5.00\n2021 Total\n498.80\n2022\nNew\n24.00\n2022\nNew\n5.00\n2022\nNew\n120.00\n2022\nNew\n250.00\n2022\nExpansion\n135.00\n2022\nNew\n2.00\n2022\nExpansion\n92.00\n2022\nNew\n5.00\n2022\nNew\n3.00\n2022\nNew\n8.00\n2022\nNew\n2.00\n2022\nNew\n5.50\n2022 Total\n651.50\n2023\nNew\n612.00\n2023\nNew\n288.00\n2023\nNew\n378.00\n2023\nNew\n325.00\n2023\nNew\n7.00\n2023\nExpansion\n24.00\n2023\nExpansion\n12.00\n2023\nExpansion\n11.00\n2023\nNew\n250.00\n2023\nNew\n135.00\n2023\nNew\n6.50\n2023\nNew\n110.00\n2023\nNew\n2.00\n2023\nNew\n12.00\n-\n-\nICC Dkt Nos. 25-0677 / 25-0679 (Cons.)\nNRG-ComEd 1.02_Attach 1 \nPage 2 of 3\n2025LLT 0000009\nExhibit No. IA-1 \nAttachment 4\nPage 3 of 4"},{"page":86,"startToken":23932,"endToken":24086,"text":"2023\nNew\n49.00\n2023 Total\n2221.50\n2024\nNew\n16.00\n2024\nNew\n1500.00\n2024\nNew\n45.00\n2024\nNew\n94.00\n2024\nNew\n587.00\n2024\nNew\n480.00\n2024\nNew\n350.00\n2024\nNew\n600.00\n2024\nExpansion\n20.00\n2024\nExpansion\n40.00\n2024\nExpansion\n60.00\n2024\nNew\n10.00\n2024\nExpansion\n25.00\n2024\nNew\n50.00\n2024\nNew\n54.00\n2024 Total\n3931.00\n2025\nNew \n600.00\n2025\nNew \n505.00\n2025\nAttraction\n300.00\n2025\nAttraction\n860.00\n2025\nAttraction\n1000.00\n2025\nAttraction\n750.00\n2025\nAttraction\n1296.00\n2025\nAttraction\n600.00\n2025\nExpansion\n1870.00\n2025\nAttraction \n431.00\n2025\nAttraction\n54.00\n2025\nAttraction\n41.00\n2025 Total\n8307.00\nGrand Total\n16308.08\n-\n-\nICC Dkt Nos. 25-0677 / 25-0679 (Cons.)\nNRG-ComEd 1.02_Attach 1 \nPage 3 of 3\n2025LLT 0000010\nExhibit No. IA-1 \nAttachment 4\nPage 4 of 4"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":2,"endAt":2,"startToken":0,"endToken":281},{"p":2,"at":2,"title":"I. EXECUTIVE SUMMARY","method":"printed heading","endPage":6,"endAt":622,"startToken":281,"endToken":1650},{"p":6,"at":622,"title":"II. BACKGROUND","method":"printed heading","endPage":7,"endAt":662,"startToken":1650,"endToken":1942},{"p":7,"at":662,"title":"III. THE INDUSTRIALS/AMTRAK","method":"printed heading","endPage":13,"endAt":425,"startToken":1942,"endToken":4213},{"p":13,"at":425,"title":"IV. ARGUMENTS","method":"printed heading","endPage":23,"endAt":985,"startToken":4213,"endToken":7780},{"p":23,"at":985,"title":"B. For Co-Located Loads for which retail netting is not an option, Non-Firm CDS","method":"printed heading","endPage":27,"endAt":3,"startToken":7780,"endToken":8913},{"p":27,"at":3,"title":"V. CONCLUSION & REQUEST FOR RELIEF","method":"printed heading","endPage":28,"endAt":0,"startToken":8913,"endToken":9042},{"p":28,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":31,"endAt":190,"startToken":9042,"endToken":9163},{"p":31,"at":190,"title":"Table of Contents","method":"printed heading","endPage":31,"endAt":463,"startToken":9163,"endToken":9172},{"p":31,"at":463,"title":"II. BACKGROUND ON THE USE OF COGENERATION FACILITIES BY","method":"printed heading","endPage":31,"endAt":1184,"startToken":9172,"endToken":9224},{"p":31,"at":1184,"title":"III. COMMERCIAL, INDUSTRIAL AND INSTITUTIONAL CUSTOMERS","method":"printed heading","endPage":31,"endAt":1448,"startToken":9224,"endToken":9249},{"p":31,"at":1448,"title":"IV. FOR TRADITIONAL LARGE LOADS SERVED BY COGENERATION","method":"printed heading","endPage":32,"endAt":24,"startToken":9249,"endToken":9298},{"p":32,"at":24,"title":"V. FIRM CONTRACT DEMAND TRANSMISSION SERVICE AND","method":"printed heading","endPage":32,"endAt":317,"startToken":9298,"endToken":9326},{"p":32,"at":317,"title":"VI. PJM’S PROPOSAL WITH RESPECT TO ALLOWING EXISTING","method":"printed heading","endPage":32,"endAt":635,"startToken":9326,"endToken":9362},{"p":32,"at":635,"title":"VII. PJM’S PROPOSED 50 MW AND SMALLER LIMITATION FOR","method":"printed heading","endPage":35,"endAt":226,"startToken":9362,"endToken":9685},{"p":35,"at":226,"title":"I. INTRODUCTION","method":"printed heading","endPage":39,"endAt":325,"startToken":9685,"endToken":10952},{"p":39,"at":325,"title":"II. BACKGROUND ON THE USE OF COGENERATION FACILITIES BY","method":"printed heading","endPage":46,"endAt":39,"startToken":10952,"endToken":13083},{"p":46,"at":39,"title":"III. COMMERCIAL, INDUSTRIAL AND INSTITUTIONAL CUSTOMERS USING","method":"printed heading","endPage":47,"endAt":405,"startToken":13083,"endToken":13395},{"p":47,"at":405,"title":"IV. FOR TRADITIONAL LARGE LOADS SERVED BY COGENERATION","method":"printed heading","endPage":53,"endAt":791,"startToken":13395,"endToken":15388},{"p":53,"at":791,"title":"V. FIRM CONTRACT DEMAND TRANSMISSION SERVICE AND NON-FIRM","method":"printed heading","endPage":57,"endAt":152,"startToken":15388,"endToken":16463},{"p":57,"at":152,"title":"VI. PJM’S PROPOSAL WITH RESPECT TO ALLOWING EXISTING CERTIFIED","method":"printed heading","endPage":60,"endAt":1208,"startToken":16463,"endToken":17517},{"p":60,"at":1208,"title":"VII. PJM’S PROPOSED 50 MW AND SMALLER LIMITATION FOR NON-","method":"printed heading","endPage":70,"endAt":624,"startToken":17517,"endToken":20785},{"p":70,"at":624,"title":"VIII. CONCLUSION","method":"printed heading","endPage":86,"endAt":751,"startToken":20785,"endToken":24086}]}