{"document":{"slug":"rec-20260325-5237","title":"Reply Brief of Advanced Energy United and the Solar Energy Industries Association","issued":"2026-03-25","accession":"20260325-5237","docket":"EL25-49-000","group":"PJM co-location compliance","filer":"Advanced Energy UnitedSolar Energy Industries Association","kind":"brief","file":"sources/filings/text/20260325-5237_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260325-5237","tier":"record","sha256":"3f038c6528d8172685a2b0ea4e3641601c593554707c4f831de76a1d25416022","pages":23,"tokens":6020,"emptyPages":[],"textThemes":["flex","colo","study","adequacy"]},"pages":[{"page":1,"startToken":0,"endToken":127,"text":"UNITED STATES OF AMERICA  \nBEFORE THE  \nFEDERAL ENERGY REGULATORY COMMISSION  \n \n \n \n)  \n \nPJM Interconnection, L.L.C., et.al. \n)  \nDocket Nos.   EL25-49-000 \n \n \n \n \n \n \n) \n \n \nEL25-49-001 \n \n \n \n \n \n \n) \nLarge Loads Co-Locating at Generating ) \n \n \nAD24-11-000 \nFacilities  \n \n \n \n \n) \n) \n \nConstellation Energy Generation, LLC \n) \nv. \n \n \n \n \n \n) \n \n \nEL25-20-000 \nPJM Interconnection, L.L.C.  \n \n)  \n \n \n(Consolidated) \n) \n \n \nREPLY BRIEF OF ADVANCED ENERGY UNITED AND THE SOLAR ENERGY \nINDUSTRIES ASSOCIATION  \n \n \nI. \nIntroduction \n \nPursuant to paragraph 219 and ordering paragraphs (D) and (E) of the Order on Show \nCause Proceeding (“Co-Location Order”) Directing Compliance Filings, Establishing Paper \nHearing, and Granting in Part and Denying in Part Complaint issued by the Federal Energy  \nRegulatory Commission (“Commission”) on December 18, 2025,1 Advanced Energy United  \n \n1 PJM Interconnection, L.L.C., 193 FERC ¶ 61,217, at P 219 and Ordering Paragraphs (D) and (E) (2025) (“Co-\nLocation Order”)"},{"page":2,"startToken":127,"endToken":488,"text":"2 \n(“United”)2 and the Solar Energy Industries Association (“SEIA”)3 submit this brief in reply to \nPJM Interconnection, L.L.C.’s (“PJM”) February 23, 2026, Initial Brief (“PJM Brief”).4  \nThe Commission issued the Co-Location Order in response to an unprecedented surge in \nrequests to interconnect large co-located loads—most notably hyperscale data centers and \nadvanced manufacturing facilities—to generating facilities within the PJM Interconnection \nregion. The Commission found that PJM’s existing tariff was unjust and unreasonable because it \nlacked service options that allow customers to flexibly manage their withdrawals from the \ntransmission system, and lacked clarity and consistency in the rates, terms, and conditions \napplicable to co-located load arrangements.5 The Commission recognized that the absence of a \nclear, accessible regulatory framework was itself a barrier to the rapid integration of new load, \nwith significant consequences for reliability and economic development. The Commission \ntherefore directed PJM to develop three new transmission services as permanent and transitional \nalternatives to existing Network Integration Transmission Service (“NITS”) for Eligible \nCustomers serving co-located loads that are willing and able to control their withdrawals from \nthe transmission system: Firm Contract Demand Transmission Service, Non-Firm Contract \nDemand Transmission Service, and Interim Network Integration Transmission Service (“Interim \nNITS”).6 \n \n2 Advanced Energy United is a national association of businesses that are making the energy we use secure, \nclean and affordable. Advanced Energy United is the only industry association in the United States that represents \nthe full range of advanced energy technologies and services, both grid-scale and distributed. Advanced energy \nincludes energy efficiency, demand response, energy storage, wind, solar, hydro, nuclear, electric vehicles, and \nmore. The comments expressed in this filing represent the position of Advanced Energy United but may not \nrepresent the views of any particular member. \n3 The comments contained in this filing represent the position of SEIA as a trade organization on behalf of the solar \nindustry, but do not necessarily reflect the views of any particular member with respect to any issue. \n4 PJM Interconnection, L.L.C., Initial Brief of PJM Interconnection, L.L.C., Docket No. EL25-49-000 (Feb. 23, \n2026) (“PJM Brief”). \n5 Co-Location Order at P 2.  \n6 Id."},{"page":3,"startToken":488,"endToken":771,"text":"3 \nPJM submitted its initial brief on February 23, 2026, setting forth illustrative tariff \nlanguage and responding to the Commission's paper hearing questions on the non-rate terms and \nconditions of the three new transmission services. While PJM's proposed framework represents a \nmeaningful attempt to address the novel operational and reliability challenges associated with co-\nlocated load, PJM’s initial brief falls short of the Co-Location Order's requirements in several \nimportant respects that, if left unaddressed, would produce a framework unlikely to achieve the \nCommission's objectives.  \nFirst, PJM’s proposed Non-Firm Contract Demand Transmission Service departs \nmaterially from the Commission's directives by restricting the service to periods when the co-\nlocated generating facility is on outage. This converts a service the Commission designed as a \nflexible, as-available option during normal operating conditions into a narrow standby product. \nThe Commission was explicit: Non-Firm Contract Demand Transmission Service “must be \navailable during normal operations,” with reservations available “as needed during normal, non-\nemergency system operating conditions.”7 PJM’s illustrative tariff contradicts this by limiting \neligibility to obtain the service “only to the extent the portion of the Co-Located Generating \nFacility dedicated to serving the Co-Located Load is on outage.”8 The Commission should reject \nthis restriction and direct PJM to implement Non-Firm Contract Demand Transmission Service \nconsistent with the Co-Location Order. \nSecond, PJM’s curtailment framework fails to provide sufficient transparency for \nprospective customers to make informed commercial decisions about whether to take Interim \nNITS or Non-Firm Contract Demand Transmission Service. PJM has offered no meaningful \ninformation about the expected frequency or duration of curtailment under real system \n \n7 Id. at P 215. \n8 PJM Brief Attachment A, Illustrative Language for New Tariff, Part XI, Section 709.2 (b)."},{"page":4,"startToken":771,"endToken":1050,"text":"4 \nconditions. Moreover, PJM's curtailment language is internally inconsistent—using “may” to \ndescribe curtailment before pre-emergency demand response in one instance and “will” in \nanother—introducing ambiguity that must be resolved.9 Without greater transparency and \ncertainty, curtailment risk will suppress participation in these new services and frustrate the \nCommission’s goals. \nThird, while appropriate study of co-located generating facilities is necessary to protect \ntransmission system reliability, PJM’s proposal to subject all co-located generating facilities,  \nincluding those that have no intention of ever exporting power to the grid, to the full PJM \ninterconnection queue process is unnecessarily burdensome and inconsistent with the Co-\nLocation Order’s speed-to-power objectives. The interconnection queue was designed to study \nthe deliverability and system impacts of exporting generators; applying it wholesale to non-\nexporting resources that will serve only their co-located load imposes multi-year delays and costs \nthat are disproportionate to any reliability benefit and would further burden an interconnection \nqueue that is already significantly backlogged, to the detriment of the broader PJM region. The \nCommission should direct PJM to develop a streamlined study and registration pathway for non-\nexporting co-located generating facilities that provides PJM with the operational visibility it \nneeds without subjecting these resources to the full burdens of the interconnection queue. \nFourth, PJM’s framework fails to honor the Co-Location Order’s directive that co-located \nloads curtailed from grid service under Interim NITS must be permitted to continue taking \nenergy directly from their co-located generating facility. The Commission stated that “when \ncurtailed, Eligible Customers taking this transmission service on behalf of Co-Located Loads \nmay be able to continue to take energy from the Interconnection Customer with which they are \n \n9 PJM Initial Brief at 63-64"},{"page":5,"startToken":1050,"endToken":1279,"text":"5 \nco-located if PJM’s Tariff otherwise allows.”10 This is the foundational commercial rationale for \nco-location with a new generating facility, and denying it directly conflicts with the Co-Location \nOrder’s speed-to-power objectives. \nThe Commission should direct PJM to revise its proposed terms and conditions to: (1) \nmake Non-Firm Contract Demand Transmission Service available during normal operating \nconditions, not solely during generating facility outages; (2) provide greater transparency \nregarding curtailment triggers and frequency, and resolve the ambiguity in its curtailment \npriority language; (3) establish a streamlined study and registration pathway for non-exporting \nco-located generating facilities in lieu of the full interconnection queue process; and (4) confirm \nthat Eligible Customers taking Interim NITS may continue to take energy from their co-located \ngenerating facility during curtailment periods, so long as there are no net injections or \nwithdrawals from the co-located facility, consistent with the Co-Location Order. \n \nII. \nREPLY AND PROTEST \n \nA. PJM’s Non-Firm Contract Demand Transmission Service Inverts the \nCommission’s Intent \n \nThe Commission directed PJM to develop Non-Firm Contract Demand Transmission \nService as a permanent transmission service option available to Eligible Customers seeking \nflexible, as-available access to the transmission system on behalf of co-located loads during \nnormal operating conditions.11 PJM’s proposed implementation of this service departs materially \nfrom that directive by restricting its availability to periods when the co-located generating \n \n10 Co-Location Order at P 201. \n11 Id. at P 215."},{"page":6,"startToken":1279,"endToken":1596,"text":"6 \nfacility is on outage.12 This restriction inverts the Commission’s intent, renders the service \ncommercially unworkable for the loads it was designed to serve, and must be rejected. \nThe Commission’s directive on Non-Firm Contract Demand Transmission Service is \nunambiguous. In the Co-Location Order, the Commission stated:  \nWe find that the new Non-Firm Contract Demand transmission \nservice must be available during normal operations and curtailed \nduring emergency operations (i.e., it will be curtailed before existing \nfirm transmission services and the new Firm Contract Demand \nTransmission Service). Under this service, Eligible Customers may \nreserve transmission service on behalf of a Co-Located Load as \nneeded during normal, non-emergency system operating conditions. \nReservations under this service would be available only when there \nis available transmission capacity, similar to existing non-firm \ntransmission service options in the Tariff.13 \n \nThe Commission further specified that reservations under Non-Firm Contract Demand \nTransmission Service “shall be available for terms ranging from one hour to one month, \nconsistent with the terms available for Non-Firm PTPS in the PJM Tariff.”14 The reference to \nNon-Firm Point-to-Point Transmission Service (“Non-Firm PTPS”) is instructive: Non-Firm \nPTPS is available on an as-available basis during normal system conditions across a range of \nreservation periods, and is not limited to any particular triggering event such as a generator \noutage as is required in PJM’s proposed tariffs.15 The Commission’s reference to Non-Firm \nPTPS makes clear that Non-Firm Contract Demand Transmission Service must function as a \nflexible, broadly available service option, not a narrow emergency backstop. \nAfter explaining that there are situations in which Co-Located Loads may withdraw \nenergy from the transmission system from time to time when transmission capacity is available, \n \n12 PJM Brief Attachment A, Illustrative Language for New Tariff, Part XI, Section 709.2(b).   \n13 Co-Location Order at P 215. \n14 Id. \n15 PJM Brief Attachment A, Illustrative Language for New Tariff, Part XI, Section 709.2(b)."},{"page":7,"startToken":1596,"endToken":1899,"text":"7 \nthe Commission provided an illustrative example of how Non-Firm Contract Demand \nTransmission Service might be used: “an Eligible Customer could seek a transmission \nreservation for a Co-Located Load in advance for the duration of an expected outage of the \nassociated generator.”16 This example describes one likely and common use case. It does not \ndefine or limit the circumstances under which the service may be available. That the \nCommission offered one example of how the service might be used does not mean that example \ndefines the only circumstances under which the service is available. The Co-Location Order \ncontains no such limitation.  \nContrary to the Commission’s clear directive, PJM's illustrative tariff restricts Non-Firm \nContract Demand Transmission Service to a narrow set of circumstances that bear little \nresemblance to the service the Commission ordered. Specifically, PJM proposes that “an Eligible \nCustomer with an effective Service Agreement will be eligible to obtain Non-Firm Contract \nDemand Transmission Service on a given Operating Day only to the extent the portion of the Co-\nLocated Generating Facility dedicated to serving the Co-Located Load is on outage.”17 PJM \nfurther characterizes the service as a  “standby product” to be relied upon “under limited \ncircumstances,”18 and states that it “anticipates that in practice, requests for Non-Firm Contract \nDemand Transmission Service will be at the MW level the Co-Located Generating Facility has \ndedicated to serving the Co-Located Load,” available “only up to the MW level that the Co-\nLocated Generating Facility is on outage.”19 \nThis is not the service the Commission ordered. The Co-Location Order contemplated a \nservice available “as needed during normal, non-emergency system operating conditions,” a \n \n16 Co-Location Order at P 214. \n17 PJM Brief Attachment A, Illustrative Language for New Tariff, Part XI, Section 709.2(b).   \n18 PJM Brief at 10.   \n19 Id. at 32."},{"page":8,"startToken":1899,"endToken":2176,"text":"8 \nstandard that encompasses a wide range of circumstances in which a co-located load may wish to \ndraw supplemental energy from the transmission system, not merely periods of generator \nunavailability. PJM has taken an illustrative example from the Co-Location Order and elevated it \ninto the governing rule, while discarding the broader principle the Commission established. This \napproach is inconsistent with the Co-Location Order and must be rejected. \nThe practical consequences of PJM's restriction are significant. Hybrid resources serving \nco-located loads, including storage paired with solar and other technologies with variable or \nintermittent output profiles, may require supplemental grid withdrawals not only during planned \noutages but during any period in which the co-located generating facility’s output is constrained, \nreduced, or otherwise insufficient to meet the full gross demand of the co-located load. Under \nPJM's proposed framework, such a customer could not access Non-Firm Contract Demand \nTransmission Service to cover that shortfall unless the generating facility is formally “on outage” \nas defined in PJM’s tariff. This creates a significant gap in service availability that would force \nmany customers to take full NITS—with all of its associated costs and planning obligations—\nsimply to access the flexibility that Non-Firm Contract Demand Transmission Service was \ndesigned to provide. \nPJM's supporting testimony attempts to justify this restriction on operational and \nplanning complexity grounds, pointing to the challenges of designing protection systems that \nadapt to varying system conditions and the risks of Remedial Action Scheme interactions in a \ntightly coupled network. These concerns do not support PJM’s proposed limitation. The \nCommission was fully aware that co-location arrangements would require novel operational \naccommodations when it issued the Co-Location Order; PJM had raised precisely these"},{"page":9,"startToken":2176,"endToken":2486,"text":"9 \nprotection scheme concerns as a reason to resist non-firm service,20 and the Commission directed \nestablishment of Non-Firm Contract Demand Transmission Service, nonetheless, finding it “just \nand reasonable.” 21 PJM's compliance filing is not the appropriate vehicle to relitigate that policy \njudgment. To the extent PJM identifies genuine implementation constraints, the appropriate \nresponse is a reasonable implementation timeline and clear Commission guidance on protection \nsystem requirements, not a fundamental narrowing of the service itself. Notably, PJM’s own \ntestimony acknowledges that protection scheme solutions are workable in the core co-location \nscenario: PJM witness Wharton concedes that a Remedial Action Scheme triggered by loss of the \nco-located generating facility “would be overwhelmingly beneficial and would have a minimal \nimpact on the overall grid.”22 The Commission should reject this additional restriction as \ninconsistent with the Co-Location Order's flexible service design. \nMoreover, from a resource adequacy and reliability perspective, there is no basis for \nrestricting Non-Firm Contract Demand Transmission Service to outage periods. Non-Firm \nContract Demand Transmission Service is by design curtailed before firm transmission services \nand before NITS in the curtailment hierarchy and is available only when transmission capacity \nexists.23 These safeguards already ensure that Non-Firm Contract Demand Transmission Service \ndoes not displace higher-priority service or impose undue reliability burdens on the system. \nArbitrarily restricting availability to outage periods provides no additional reliability protection, \nit simply reduces the utility of the service without any corresponding system benefit. \nPJM's proposed restriction of Non-Firm Contract Demand Transmission Service to \ngenerating facility outage periods is inconsistent with the Co-Location Order and must be \n \n20 “Answer of PJM Interconnection, L.L.C.” Docket No. EL25-49-000 (March 24, 2025) at pages 13-15. \n21 Co-Location Order at P205 and 215. \n22 PJM Brief, Attachment C “Affidavit of Matthew Wharton on Behalf of PJM, Interconnection, L.L.C.” at P 25. \n23 Co-Location Order at P 215."},{"page":10,"startToken":2486,"endToken":2752,"text":"10 \nrejected. The Commission should direct PJM to revise and file illustrative Tariff, Part XI, \nSubpart B, section 709.2(b) to remove the outage-only limitation and replace it with language \nconsistent with the Co-Location Order's directive that the service be available as needed during \nnormal, non-emergency system operating conditions, subject to available transmission capacity \nand the curtailment priority established in the Co-Location Order. This revision would restore the \nservice to the form the Commission intended: A flexible, as-available transmission option that \ngives co-located loads a meaningful and commercially viable alternative to full NITS. The \nCommission should find PJM’s outage-only restriction on Non-Firm Contract Demand \nTransmission Service to be unjust and unreasonable and direct PJM to revise its illustrative tariff \naccordingly. \nB. Additional Certainty Regarding Potential Curtailment is Needed to Enable \nUptake of the Non-Firm and Interim NITS Options \n \nThe Commission directed PJM to create Non-Firm Contract Demand Transmission \nService and Interim NITS to accommodate co-located load arrangements, and these services \nmust be genuinely accessible and commercially viable alternatives to full NITS for co-located \nloads willing and able to limit their grid withdrawals.24 For these services to achieve that \npurpose, prospective customers must be able to make informed business decisions about whether \nto take service, and that requires a clear, consistent, and transparent curtailment framework. \nPJM’s initial brief fails on both counts: it introduces internal inconsistency in the curtailment \npriority hierarchy, and it provides no meaningful information about the conditions under which \ncurtailment will occur in practice. The Commission should direct PJM to resolve these \ndeficiencies before these services are implemented. \n \n24 Id at P214-215."},{"page":11,"startToken":2752,"endToken":3020,"text":"11 \n1. PJM's Curtailment Priority Language Is Internally Inconsistent and \nMust Be Clarified \n \nThe Co-Location Order established a clear curtailment hierarchy: Interim NITS and Non-\nFirm Contract Demand Transmission Service are to be curtailed before firm transmission \nservices and existing NITS, and before pre-emergency demand response resources are \ndispatched.25 This hierarchy is a critical feature of the new services, making them compatible \nwith system reliability and defining the conditions under which co-located loads can expect their \nservice to be interrupted. \nPJM’s Brief implements this hierarchy but does so in contradictory terms that must be \nclarified and reconciled to confirm consistency with the Commission’s directive. In describing \ncurtailment procedures applicable to both Interim NITS and Non-Firm Contract Demand \nTransmission Service, PJM states that “the Transmission Provider may also curtail Interim NITS \nor Non-Firm Contract Demand Transmission Service prior to dispatching the Pre-Emergency \nLoad Response Program.”26 Yet in the very next sentence, PJM states that “this effectively \nmeans that Interim NITS and Non-Firm Contract Demand Transmission Service will be curtailed \nbefore Demand Response resources are called upon to reduce load.”27 PJM uses the same \ncontradictory language its discussion of the same curtailment trigger later in the brief when \ndiscussing Interim NITS curtailment procedures.28 \nThis inconsistency may be unintentional but must be resolved. The difference between a \ndiscretionary curtailment authority (“may”) and a mandatory curtailment obligation (“will”) has \nmaterial consequences for how co-located loads plan their operations and evaluate their \n \n25 Co-Location Order at P 215; see also PJM Brief at 63. \n26 PJM Brief at 63 (emphasis added). \n27 Id at 63-64. \n28 Id at 72."},{"page":12,"startToken":3020,"endToken":3296,"text":"12 \ncurtailment exposure. A customer deciding whether to take Non-Firm Contract Demand \nTransmission Service or Interim NITS needs to know whether curtailment before pre-emergency \ndemand response is a certainty or a possibility. Likewise, demand response providers require \ncertainty as to how their obligations will be impacted by the new Non-Firm Contract Demand \nTransmission Service and Interim NITS: Will customers on these non-firm services always be \ncurtailed prior to pre-emergency demand response? PJM's Brief answers both simultaneously \nand inconsistently, leaving the customer no clearer on their actual exposure than before. The \nCommission should direct PJM to resolve this inconsistency in its revised filing and confirm \nunambiguously whether curtailment prior to pre-emergency demand response dispatch is \nmandatory or discretionary. \n2. PJM's Curtailment Framework Provides Insufficient Transparency for \nCustomers to Make Informed Commercial Decisions \n \nBeyond the readily fixable “may/will” inconsistency, PJM’s curtailment framework \nsuffers from a deeper transparency problem: PJM has provided no information about the \nconditions that would actually trigger curtailment of Interim NITS or Non-Firm Contract \nDemand Transmission Service in practice. These are novel services for which no historical \ncurtailment data currently exists. There is no modeling of expected curtailment frequency or \nduration under the proposed framework, and no examples of how the curtailment process would \noperate for a hypothetical co-located arrangement. \nThis information must be provided for customers to make informed business decisions on \nthe transmission service that best serves their operational and commercial needs. The decision to \ntake Non-Firm Contract Demand Transmission Service or Interim NITS rather than full NITS is \nfundamentally a commercial decision about the tradeoff between lower service costs and \npotentially faster interconnection timelines and higher curtailment exposure. A co-located load"},{"page":13,"startToken":3296,"endToken":3598,"text":"13 \ncannot make an informed decision without understanding how often and under what conditions \nits service is likely to be interrupted. Without that information, the perceived risk of curtailment \nwill likely far outstrip the probable reality, and prospective customers will default to full NITS \nsimply to avoid uncertainty. The result would be exactly the opposite of what the Commission \nintended: Rather than expanding the range of viable service options for co-located loads, the new \nservices would go largely unused. \nThe Commission has long recognized that transparency is a prerequisite for competitive, \nwell-functioning markets. The same principle applies here. Just and reasonable rates, terms, and \nconditions are not merely those that are technically correct on paper, they must be sufficiently \nclear and transparent to enable customers to make informed decisions about whether and how to \nparticipate.29 PJM’s curtailment framework, as proposed, does not meet that standard. \n3. The Commission Should Direct PJM to Provide Curtailment \nTransparency Mechanisms Prior to Implementation \n \nWhile uncertainty cannot be entirely avoided for customers selecting the Non-Firm \nContract Demand Transmission Service and Interim NITS, it can be minimized. The \nCommission should direct PJM to take concrete steps to provide prospective customers with the \ninformation they need to evaluate their curtailment exposure under Non-Firm Contract Demand \nTransmission Service and Interim NITS before these services are implemented.  \nFirst, the Commission should require PJM to resolve the “may/will” inconsistency in its \ncurtailment priority language and confirm the specific conditions under which Interim NITS and \nNon-Firm Contract Demand Transmission Service will be curtailed relative to pre-emergency \ndemand response dispatch and other system conditions. \n \n29 “Promoting Wholesale Competition Through Open Access Non-Discriminatory Transmission Services by Public \nUtilities; Recovery of Stranded Costs by Public Utilities and Transmitting Utilities”, FERC Order No. 888, FERC \nStats. & Regs. ¶ 31,036, 61 Fed. Reg. 21,540 (1996)."},{"page":14,"startToken":3598,"endToken":3883,"text":"14 \nSecond, the Commission should require PJM to develop and publish historical analysis \nand forward-looking modeling of curtailment frequency and duration for Interim NITS and Non-\nFirm Contract Demand Transmission Service, informed by historical system conditions in PJM \nbroken down by zone, where available. This analysis should be made available to prospective \ncustomers and developers as part of the service application process so that they can evaluate their \ncurtailment exposure prior to committing to service.  \nThird, PJM should dedicate time at a stakeholder meeting prior to implementation to \nwalk through the curtailment study process with a hypothetical co-located arrangement. This \nexercise would give the market a concrete, practical understanding of how curtailment decisions \nare made, what triggers them, and what a customer can expect in terms of frequency and duration \nunder a range of system conditions. As a predicate to that stakeholder engagement, PJM should \nset out in its reply brief a written explanation of how it intends to operationalize curtailment for \nNon-Firm Contract Demand Transmission Service, including the criteria PJM will use to \ndetermine when curtailment is warranted, the sequence in which co-located loads will be \ncurtailed relative to other non-firm services, and the mechanism by which curtailment \ninstructions will be communicated and enforced. Without that written explanation in this \nproceeding and, ultimately, in PJM’s Business Practice Manuals, neither the Commission nor \naffected parties can evaluate whether PJM's proposed curtailment framework is consistent with \nthe Co-Location Order’s requirement that Non-Firm Contract Demand Transmission Service be \navailable “as needed during normal, non-emergency system operating conditions.”30 Greater \ntransparency at this stage will enable informed market participation and reduce the uncertainty \nthat would otherwise suppress uptake of these new services. \n \n30 Co-Location Order at P 215."},{"page":15,"startToken":3883,"endToken":4152,"text":"15 \nPJM routinely gives market participants the information they need to evaluate the costs \nand risks of participating in other PJM services,31 and the novelty of these new transmission \nservices makes the need for upfront transparency a necessity. The Commission should ensure \nthat PJM’s implementation plan includes these transparency measures so that Non-Firm Contract \nDemand Transmission Service and Interim NITS can fulfill their intended purpose as genuinely \naccessible, commercially viable alternatives to full NITS for co-located loads across the PJM \nregion. \nC. PJM Would Unnecessarily Subject All Co-Located Generating Facilities to a \nFull Interconnection Study.  \n \nThe Co-Location Order was designed to accelerate the integration of new load and new \ngeneration into the PJM region at a time of unprecedented demand growth. PJM’s Brief \nundermines that objective by proposing that all co-located generating facilities—including those \nthat have no intention of ever exporting power to the grid—must navigate the full PJM \ninterconnection queue before they can participate in Non-Firm Contract Demand Transmission \nService or Interim NITS. While PJM indisputably requires sufficient information about both \nexporting and non-exporting co-located generating facilities to reliably plan and operate the \ntransmission system, subjecting non-exporting resources to the full interconnection queue \nimposes costs, delays, and administrative burdens that are wholly disproportionate to the \nreliability benefits achieved. This outcome would further strain an interconnection queue that is \nalready significantly backlogged, all to the detriment of the broader PJM region and the \ncustomers it serves. \n \n31 Such as the Base Residual Auction’s planning parameters and load forecasts, the interconnection queue with \ncluster study reports and cost estimates, and historical dispatch data for demand response customers."},{"page":16,"startToken":4152,"endToken":4434,"text":"16 \nPJM’s proposal appears to require all co-located generating facilities participating in the \nnew transmission services will be required to go through PJM’s interconnection queue, and it \nacknowledges that this will contribute to delays in the availability of the new transmission \nservices. PJM states that “the process of an Eligible Customer's generation getting through the \ninterconnection queue, being constructed, and becoming operational will likely take more than \nthree years, particularly in light of current supply chain issues, Transmission Owner and PJM \nqueue requirements, and RPM auction timelines.”32 PJM makes no distinction between \ngenerating facilities that intend to export power to the grid and those that are dedicated \nexclusively to serving their co-located load. \nThis one-size-fits-all approach is fundamentally misaligned with the purpose of the \ninterconnection queue and the objective of achieving speed-to-power. PJM’s interconnection \nprocess was designed to study the deliverability and system impact of generating facilities that \nintend to inject power into the transmission system and participate in PJM’s energy and capacity \nmarkets. The interconnection studies include network upgrades analysis, deliverability \nassessments, and capacity market participation determinations and are premised on the \nassumption that the generator will export power to the grid and that the grid must be capable of \nreceiving and delivering that power to load. These assumptions do not apply to a non-exporting \nco-located generating facility whose output is dedicated entirely to serving its co-located load \nand that will never inject power into the system. \nRequiring non-exporting co-located generating facilities to undergo this process does not \nmake the transmission system more reliable, it simply foists multi-year delays and significant \ncosts on resources that pose none of the deliverability risks the interconnection queue was \n \n32 PJM Brief at 82."},{"page":17,"startToken":4434,"endToken":4738,"text":"17 \ndesigned to address. As was argued in the related proceeding in Docket No. ER26-1479, non-\nexporting resources “do not require deliverability given their intent to serve only the co-located \nload” and will “rarely, if ever, trigger network upgrades,” making the full interconnection study \nprocess a “purely administrative hurdle with no technical or reliability benefit.”33 \nThe consequences of PJM’s approach extend beyond the individual customer. PJM itself \nacknowledges that its interconnection queue has been severely backlogged—it effectively closed \nthe queue to new applicants in 2022 and will not initiate the first cluster study of new requests \nuntil later this year.34 Forcing non-exporting co-located generating facilities into that queue \nwould artificially inflate the number of projects competing for study resources and queue \npositions, further delaying all projects in the queue, including the exporting generators whose \ndeliverability the interconnection process was actually designed to assess. This is precisely the \nkind of outcome the Co-Location Order sought to avoid. \nThe Co-Location Order’s objective is not merely a commercial convenience for \nindividual customers, it reflects the Commission’s recognition that the PJM region faces urgent \nresource adequacy challenges that require new generation and new load to come online as \nquickly as possible.35 Nevertheless, the Commission should not exempt non-exporting co-located \ngenerating facilities from all study or registration requirements. PJM needs sufficient \ninformation about these resources to model them accurately, ensure the reliability and stability of \nthe transmission system, and establish the necessary systems required under the new \ntransmission services. Those are legitimate operational needs. \n \n33 “Limited Protest of Advanced Energy United and the Solar Energy Industries Association,” Docket No. ER26-\n1479-000, at 24 (Mar. 16, 2026). \n34 See PJM Interconnection, L.L.C., PJM Completes Interconnection Reform Transition Cycle 1 Studies (Sept. 22, \n2025), https://insidelines.pjm.com/pjm-completes-interconnection-reform-transition-cycle-1-studies/. \n35 Co-Location Order at P 200"},{"page":18,"startToken":4738,"endToken":5047,"text":"18 \nThe Commission should instead direct PJM to develop a study and registration pathway \nthat is proportional to the actual technical impact that non-exporting resources have on the \ntransmission system. This process should provide PJM with the information it needs without \nsubjecting non-exporting resources to the full burdens of the interconnection queue. Such a \npathway could include, at a minimum, standardized submission of key technical data including \nnameplate capacity, generation profile and operational parameters, a binding non-export \ncommitment enforceable through the service agreement, telemetry and metering capabilities \nsufficient to support PJM's real-time operational visibility, and single-line diagram and delivery \npoint information. These requirements would give PJM the information it needs to reliably \nincorporate non-exporting co-located generating facilities into its planning and operations \nwithout the multi-year delays and costs associated with a full interconnection study. \nThis approach is consistent with the Commission's broader policy of tailoring \ninterconnection requirements to the actual system impacts of the resource seeking \ninterconnection.36 It is also consistent with the position advanced in the related proceeding in \nDocket No. ER26-1479, where United and SEIA explained that PJM should “establish a \nstreamlined, expedited process specifically for resources that do not intend to export to the grid” \nwith requirements “proportional to the actual technical impact the resources have on the grid.”37 \nThis same logic has been used on other regions. In another proceeding Commissioner Rosner \nhighlighted SPP’s approach of limiting a generator’s grid output to match co-located load \ndemand as a model worth emulating because, when generation is matched to load, “the impacts \nof adding load and generation to the transmission system effectively cancel each other out, which \n \n36 “Reform of Generator Interconnection Procedures and Agreements,” Order No. 845, 163 FERC ¶ 61,043 (2018) \n37 “Limited Protest of Advanced Energy United and the Solar Energy Industries Association,” Docket No. ER26-\n1479-000, at 24 (Mar. 16, 2026)"},{"page":19,"startToken":5047,"endToken":5349,"text":"19 \nminimizes the need for time-consuming transmission upgrades.”38 A non-exporting co-located \ngenerator presents an even more clear-cut example of this principle, and PJM's interconnection \nrequirements should reflect it. The Commission should adopt that principle here and direct PJM \nto develop and implement a streamlined registration and study pathway for non-exporting co-\nlocated generating facilities as part of its revised terms and conditions for the new transmission \nservices. \nD. The Commission Should Direct PJM to Explicitly Allow Co-Located Loads \nUnder New Transmission Service to Access On-site Generation During \nSystem Constraint Periods \nThe Interim NITS as currently proposed leaves unclear whether co-located loads may \naccess on-site generation during system constraint periods. PJM’s brief outlines significant \noperational complexities and restrictions for Co-Location but is unclear on the use of on-site \ngeneration post-curtailment. This ambiguity creates uncertainty, which almost certainly will \ndeter loads from considering Interim NITS. To provide clarity, encourage fair access, and align \nwith the Commission’s Order, the Commission should direct PJM to explicitly allow co-located \nloads employing Interim NITS to use on-site generation during system constraints. \nPJM is explicit that interim NITS will be among the first services curtailed during \nemergencies and must be prepared to shed load when system reliability requires it.39 \nAdditionally, Interim NITS may be curtailed prior to dispatching emergency programs.40 Given \nthe curtailment hierarchy, it is likely that interim NITS will be curtailed from the grid early and \noften during system constraints to shed load and ensure reliability. However, it is unclear \n \n38 Southwest Power Pool, Inc. 194 FERC ¶ 61,031, Rosner Concurrence at P 2. \n39 Initial brief at 63. (Response to Question 11, § A: Under the illustrative Tariff provisions, Interim NITS and Non-\nFirm Contract Demand Transmission Service will be curtailed before Firm Contract Demand Transmission Service \nand NITS.”) \n40 PJM brief at 63."},{"page":20,"startToken":5349,"endToken":5662,"text":"20 \nwhether loads taking interim NITS will be able to rely on their own co-located generating facility \nduring these times of curtailment. PJM’s filing makes no clear statement on restricting on-site \ngeneration; however, PJM was clear in stakeholder discussions that, if curtailed, interim NITS \ncustomers “cannot take energy from co-located generator (no netting under system conditions \nthat required curtailment).”41 Such a restrictive approach is inconsistent with the Co-Location \nOrder, which clearly states: “when curtailed, Eligible Customers taking this transmission service \non behalf of Co-Located Loads may be able to continue to take energy from the Interconnection \nCustomer with which they are co-located if PJM’s Tariff otherwise allows.”42 If PJM intends to \nrestrict co-located loads from accessing on-site generation while using interim NITS, this would \nbe a fundamental flaw in the Interim NITS framework and a direct violation of the \nCommission’s order.  \nDuring system constraints, without clearer tariff language, co-located loads could be \nrestricted from both the grid and on-site generation to serve their load. This removes the benefit \nof co-locating with a generator. On-site generation resources are critical tools for customers to \nmanage their energy needs and enhance reliability. One of the main benefits of the Interim NITS \noption for co-located loads comes from being able to connect to on-site generation quickly while \nstill meeting reliability needs. The grid benefits from adding load that does not impact system \nreliability, if the generation serving the load is new generation. While PJM's concern about \nexisting generation being repurposed to serve new loads is understandable, the proposed \nframework would confine on-site generation resources during curtailment, undermining the \noperational flexibility that Non-Firm Demand and Interim NITS should provide. \n \n41 PJM Staff Preliminary/Working Draft of Concepts as of January 23, 2026, 4 (Jan. 23, 2026). \nhttps://www.pjm.com/-/media/DotCom/committees-groups/workshops/cllsco/2026/20260126/20260126-item-01---\ntransmission-services-concepts-for-discussion.pdf  \n42 Co-Location Order at P 201."},{"page":21,"startToken":5662,"endToken":5899,"text":"21 \nThis on-site generation should be allowed to serve the load and the load, in turn, should \nbe allowed to be interim NITS provided: (1) it is new generation that has not previously been in \nthe capacity market; and (2) the load is not consuming from the grid during these curtailment \nperiods. By disallowing on-site generation to serve load under the proposed interim NITS, PJM \nwould undermine the utility of the interim NITS service. The Commission should direct PJM to \nrevise its interim NITS proposal to explicitly allow Eligible Customers to use on-site generation \nto serve load continuously, consistent with the Order, provided that the generation is new and has \nnot previously participated in PJM’s capacity market and that the co-located load does not \nsimultaneously withdraw energy from the transmission system. This clarity will ensure \ncompliance with the Order and support speed to power while maintaining reliability and \naffordability for all customers.  \nIII. \nCONCLUSION \nFor the foregoing reasons, United and SEIA respectfully request that the Commission \nfind that PJM's initial brief does not fully satisfy the requirements of the Co-Location Order and \ndirect PJM to revise its proposed terms and conditions to address the deficiencies identified \nherein. The Commission's prompt action on these issues is essential to ensure that the new \ntransmission services established by the Co-Location Order fulfill their intended purpose of \ndelivering reliable, flexible, and affordable energy service to co-located loads across the PJM \nregion."},{"page":22,"startToken":5899,"endToken":5978,"text":"22 \nRespectfully submitted,  \n/s/ Mike Haugh           \n \n   \nCaitlin Marquis, Managing Director    \nMike Haugh, Director   \nKelsey Koenig  \nAdvanced Energy United    \n1801 Pennsylvania Ave. N.W., Suite 410     \nWashington, D.C. 20006     \ncmarquis@advancedenergyunited.org  \nmhaugh@advancedenergyunited.org  \nkkoenig@advancedenergyunited.org  \n \n \n \n \n \n \n \n/s/ Melissa Alfano   \nMelissa Alfano   \nSenior Director of Energy Markets Counsel    \nGreg Giunta  \nSenior Manager of Regulatory Affairs and \nCounsel \nSolar Energy Industries Association   \n1425 K St NW Ste. 1000   \nWashington, DC 20005   \n(202) 566-2873   \nmalfano@seia.org  \nggiunta@seia.org"},{"page":23,"startToken":5978,"endToken":6020,"text":"23 \nCERTIFICATE OF SERVICE  \n \nI hereby certify that I have this day served the foregoing document upon each \nperson designated on the official service list compiled by the Secretary in this proceeding.  \n \nDated this 25th day of March 2026. \n  \n/s/ Mike Haugh"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":1,"endAt":520,"startToken":0,"endToken":52},{"p":1,"at":520,"title":"I. Introduction","method":"printed heading","endPage":5,"endAt":1063,"startToken":52,"endToken":1193},{"p":5,"at":1063,"title":"II. REPLY AND PROTEST","method":"printed heading","endPage":5,"endAt":1089,"startToken":1193,"endToken":1197},{"p":5,"at":1089,"title":"A. PJM’s Non-Firm Contract Demand Transmission Service Inverts the","method":"printed heading","endPage":10,"endAt":869,"startToken":1197,"endToken":2607},{"p":10,"at":869,"title":"B. Additional Certainty Regarding Potential Curtailment is Needed to Enable","method":"printed heading","endPage":15,"endAt":573,"startToken":2607,"endToken":3965},{"p":15,"at":573,"title":"C. PJM Would Unnecessarily Subject All Co-Located Generating Facilities to a","method":"printed heading","endPage":19,"endAt":491,"startToken":3965,"endToken":5115},{"p":19,"at":491,"title":"D. The Commission Should Direct PJM to Explicitly Allow Co-Located Loads","method":"printed heading","endPage":21,"endAt":978,"startToken":5115,"endToken":5814},{"p":21,"at":978,"title":"III. CONCLUSION","method":"printed heading","endPage":23,"endAt":4,"startToken":5814,"endToken":5979},{"p":23,"at":4,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":23,"endAt":260,"startToken":5979,"endToken":6020}]}
