{"document":{"slug":"rec-20260325-5238","title":"Reply Brief of Constellation Energy Generation, LLC","issued":"2026-03-25","accession":"20260325-5238","docket":"EL25-49-000","group":"PJM co-location compliance","filer":"Constellation Energy Generation, LLC","kind":"brief","file":"sources/filings/text/20260325-5238_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260325-5238","tier":"record","sha256":"936022f422c5f4fcb72441d4f740eef613ec0d14beb059d80e4a8e7a8baf7f78","pages":61,"tokens":16933,"emptyPages":[],"textThemes":["colo","flex","study","cost"]},"pages":[{"page":1,"startToken":0,"endToken":311,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \nPJM Interconnection, L.L.C., et al. \nLarge Loads Co-Located at Generating Facilities \nConstellation Energy Generation, LLC \n    v. \nPJM Interconnection, L.L.C. \n) \n \n \n)  \n \n \n)  \n) \n) \n) \n) \n) \nDocket No. EL25-49-000 \n   Docket No. EL25-49-001 \nDocket No. AD24-11-000 \nDocket No. EL25-20-000 \n(Consolidated) \nREPLY BRIEF OF CONSTELLATION ENERGY GENERATION, LLC \nConstellation submits this reply brief1 to address four issues. First, we urge the \nCommission to reject PJM’s proposal to delay by three years–until June 2029,2 beyond the second \nTrump Administration–the implementation of Interim Network Integration Transmission Service \n(“Interim NITS”). There is no good reason for such a delay, which will only harm PJM’s ability \nto timely interconnect new data center load while any needed transmission upgrades are being \nconstructed. Urgency, not delay, is needed. The Commission should therefore establish a separate \ntrack to promptly approve the rates and terms for Interim NITS as modified below and make them \neffective no later than October 1, 2026.3 Urgency was a principal motivation for the Commission’s \n \n1 Constellation Energy Generation, LLC (“Constellation”) files this answer pursuant to Rule 211 of the Commission’s \nRules of Practice and Procedure. 18 C.F.R. § 385.211 (2025). \n2 Initial Brief of PJM Interconnection, L.L.C. at 79 (Feb. 23, 2026) (“PJM Initial Brief”). \n3 See Constellation Apr. 23, 2025 Answer, Exhibit 1 at 9 (“Stockton Declaration”) (“Speed is of the essence for \nnational security.”); see also Written Testimony of Laura V. Swett, Chairman, Federal Energy Regulatory \nCommission, Before the U.S. House of Representatives, Committee on Energy and Commerce, Subcommittee on \nEnergy, at 1-2 (Feb. 3, 2026) https://www.ferc.gov/news-events/news/testimony-laura-v-swett-chairman-federal-\nenergy-regulatory-commission-us-house (“We’re in a global energy arms race created by the rise of technology, its \ntremendous load growth, and our push to onshore manufacturing and jobs. I want the United States to lead that race."},{"page":2,"startToken":311,"endToken":926,"text":"2 \ndirective that PJM create the Interim NITS service in the first instance.4 An effective date three-\nand-a-half years later fails to meet the spirit and letter of the Commission’s December 18 Order5 \nand “the administration’s goals to promptly resolve large load issues.”6  \nAdopting Interim NITS as soon as possible—for pending and future NITS applicants—\nshould not be difficult, especially because the Indicated Transmission Owners do not propose a \nnew rate methodology but instead propose to charge the same undiscounted NITS rate for Interim \n \nThis is the moment to cement America’s energy leadership.”). See also Written Testimony of Lindsay S. See, \nCommissioner, Federal Energy Regulatory Commission, Before the U.S. House of Representatives, Committee on \nEnergy and Commerce, Subcommittee on Energy, at 3 (Feb. 3, 2026), https://cms.ferc.gov/news-\nevents/news/testimony-lindsay-s-see-commissioner-federal-energy-regulatory-commission \n(“our \nnational \nimperative of speed to power and winning the AI race”); Written Testimony of David LaCerte, Commissioner, \nFederal Energy Regulatory Commission, Before the U.S. House of Representatives, Committee on Energy and \nCommerce, Subcommittee on Energy, at 1 (Feb. 3, 2026), https://cms.ferc.gov/news-events/news/testimony-david-\nlacerte-commissioner-federal-energy-regulatory-commission-house ) (“[T]he AI race, and even more importantly, \nwho ultimately wins, will also fundamentally transform how Americans engage, transact, and compete on the global \nstage. The AI race is here and America’s power grid is a major battlefield.”). \n4 PJM Interconnection, L.L.C., 193 FERC ¶ 61,217, at P 201 (2025) (“This willingness to curtail would potentially \nallow them to obtain service more quickly.”) (“December 18th Order”).  \n5 See id. PP 200-01; see also id. (Rosner, Comm’r, concurring at PP 3-4) (“Because of this, a business-as-usual \napproach to load growth—planning for generation and load separately—will not suffice to timely meet growing \ndemand while also keeping prices reasonable. Today’s order helps break the logjam.”); id. (Rosner, Comm’r, \nconcurring at P 4) (“And co-located large loads and generators can get online faster and easier than would otherwise \nbe the case. Grid operators like PJM should allow and encourage large loads and generators to pursue these time- \nand cost-saving co-location arrangements.”); FERC, Fact Sheet: FERC Directs Nation’s Largest Grid Operator to \nCreate New Rules to Embrace Innovation and Protect Consumers (Dec. 18, 2025), https://www.ferc.gov/news-\nevents/news/fact-sheet-ferc-directs-nations-largest-grid-operator-create-new-rules-embrace?new= (“As technology \nleaps forward, clear and fair regulations must keep pace to support advancement ….”); FERC, News Release, FERC: \nDirects Nation’s Largest Grid Operator to Create New Rules to Embrace Innovation and Protect Consumers \n(Dec. 18, 2025), https://www.ferc.gov/news-events/news/ferc-directs-nations-largest-grid-operator-create-new-\nrules-embrace-innovation-and?new= (“‘Clarifying new rules will help release the bottleneck of large load \ninvestments across the PJM footprint,’ said Chairman Swett.”); FERC, Transcript of 1131st Commission Meeting, \nat 24:25 to 25:1-2 (Dec. 18, 2025), https://www.ferc.gov/media/transcript-december-18-2025-open-meeting \n(“[W]hen done right co-location can be both a consumer forward tool and a critical avenue in beating our national \nimperative of speed to power and winning the AI race.”) (remarks of Commissioner See); id. 26:4-7 (“FERC is \nmeeting the urgent demand for speed to power by creating flexibility for a rapidly evolving industry without \nsacrificing reliability and affordability.”) (remarks of Commissioner See); id. at 37:11-12 (“We can’t just pretend \nlarge loads don’t exist and wish them away.”) (remarks of Commissioner LaCerte); id. at 37:15-16 (“PJM is in dire \nneed of leadership for their stakeholders.”) (remarks of Commissioner LaCerte); FERC, Transcript of 1132nd \nCommission Meeting, at 10:2-5 (Jan. 26, 2026) (“I warmly welcome engagement from great operators who share \nmy commitment to helping ensure that datacenters can interconnect quickly and reliably.”) (remarks of Chairman \nSwett).  \n6 FERC, Notice of Extension of Time, at 3 (Jan. 23, 2026)."},{"page":3,"startToken":926,"endToken":1308,"text":"3 \nNITS.7 Constellation does not protest that rate treatment given the urgency of getting data centers \nin service, but crafting an identical rate cannot possibly take over three years.  \nAs set forth below, the Commission can allow more time if needed, on a separate track, to \nestablish the rates and terms of new Contract Demand Services.8 Additional time is not needed for \nInterim NITS, which is “[g]enerally speaking” the same as NITS.9 \nSecond, the Commission should reject PJM’s unilateral attempt to restrict availability of \nNon-Firm Contract Demand Service. PJM proposes to make this service available only when the \nCo-Located Generating Facility is on outage. The Commission, however, did not limit Non-Firm \nContract Demand Service in this way. Nor, contrary to PJM’s proposal, did the Commission \nrequire Eligible Customers to take Firm Contract Demand Service for all Co-located Load not \nserved by a generator. PJM needs to stop resisting the innovative Co-Located Load arrangements10 \nendorsed by the Commission and start looking for solutions. “Saying no to innovation is not a \nwinning strategy.”11  \n \n7 Initial Brief and Joint Responses of the Indicated PJM Transmission Owners, Exh. No. PTO-0001 at 16:12-14 \n(Feb. 23, 2026) (“Indicated TO Initial Brief”). The Indicated PJM Transmission Owners are a subset of Transmission \nOwners in PJM, excluding Old Dominion Electric Cooperative, for example. \n8 Contract Demand Services refers collectively to Firm Contract Demand Transmission Service (“Firm Contract \nDemand Service”) and Non-Firm Contract Demand Transmission Service (“Non-Firm Contract Demand Service”). \n9 PJM Initial Brief at 67. \n10 See, e.g., id. at 48 (“Since at least its establishment as an Independent System Operator in 1997, PJM’s processes \nhave been built around the long-held practice and expectation that load internal to PJM will receive NITS. This has \nsignificant implications for PJM’s planning, markets, and operations functions, which are focused on serving \nNetwork Load.”). \n11 December 18th Order, 193 FERC ¶ 61,217 (Rosner, Comm’r, concurring at P 1). See also Judy W. Chang, et. al, \nIt’s all one system: Integrate transmission and interconnection planning to support load growth, UTILITY DIVE \n(Sept. 26, 2025), https://www.utilitydive.com/news/its-all-one-system-integrate-transmission-and-interconnection-\nplanning-Judy-Chang/761240 (“Generational change is occurring in the nation’s energy sector. While FERC is \nconsidering urgent short-term fixes, it also must evaluate longer-term solutions that shape the sector.”)."},{"page":4,"startToken":1308,"endToken":1626,"text":"4 \nThird, the Commission should reject PJM’s and Indicated Transmission Owners’12 \nproposals that restrict, delay, discriminate against or otherwise discourage the use of the \nCommission’s new Interim NITS and Contract Demand Services. The Federal Power Act prohibits \n“unreasonable differences” in services.13 Moreover, the Commission did not establish these “major \nnew transmission” services—“the first time since the 90’s”—for them to be so limited and \nburdensome that few would want to take them.14 The whole purpose of these services is to “release \nthe bottleneck of large load investments across the PJM footprint.”15 \nWe specifically challenge the following: \n• the lack of a transitional mechanism for large loads within pending NITS \napplications to apply for Interim NITS;16  \n• the ambiguity of PJM’s proposed studies and lack of mechanisms to prevent delay \nand discrimination by Transmission Owners;17 \n• the absence of a proposed penalty charge to comment on and the proposed \nsuspension and disqualification of Eligible Customers for unreserved use of the \ntransmission system;18  \n• unreasonable and discriminatory system protection scheme requirements, including \nthe Transmission Owners’ recommendation for a double system protection \nscheme;19  \n \n12 Indicated TO Initial Brief at 5 n.13. \n13 16 U.S.C. § 824d(b) (“No public utility shall, with respect to any transmission or sale subject to the jurisdiction of \nthe Commission … maintain any unreasonable difference in rates, charges, service, facilities, or in any other respect, \neither as between localities or as between classes of service.”). \n14 FERC, 1131st Commission Meeting Transcript, at 34:1-2 (Dec. 18, 2025), https://www.ferc.gov/media/transcript-\ndecember-18-2025-open-meeting (remarks of Commissioner LaCerte). \n15 FERC, FERC Directs Nation’s Largest Grid Operator to Create New Rules to Embrace Innovation and Protect \nConsumers (Dec. 18, 2025), https://www.ferc.gov/news-events/news/ferc-directs-nations-largest-grid-operator-\ncreate-new-rules-embrace-innovation-and?new= (quoting Chairman Swett). \n16 See infra at 14. \n17 See infra at 14-18. \n18 See infra at 18-21. \n19 See infra at 21-25."},{"page":5,"startToken":1626,"endToken":1930,"text":"5 \n• the lack of a cost-based Grid Reliance Charge;20 \n• the requirement that an Eligible Customer provide PJM authorization or \ncertification from the Relevant Electric Retail Regulatory Authority;21 and \n• the requirement to construct different feeders to take the new services.22 \nFourth, we seek clarification of PJM’s and the Indicated Transmission Owners’ filings to \nensure clarity and compliance with the December 18th Order. We recommend that PJM add to \nthe “Conditions Precedent for Receiving Service” the requirement that the Eligible Customer \nidentify the Customer Facilities associated with the Co-Located Load, and, if the Customer \nFacilities include an existing generator, to certify that the existing generator supports the request. \nWe also recommend that Indicated Transmission Owners confirm that the Firm Contract \nDemand Service rate is the actual NITS rate for the relevant Transmission Owner (the most \ncommon of which is a 5-coincident peak (“CP”) design). Last, we briefly reassert our arguments \nthat (1) the Commission should clarify that it did not intend to require a capacity resource to \ndelist even when it has no obligation to serve the Co-Located Load and remains fully capable of \nserving the grid during capacity emergencies;23 and (2) reject PJM’s proposal to override the \nCommission’s definition of Co-Located Load.24  \n \n20 See infra at 25-28. \n21 See infra at 29. \n22 See infra at 29-30. \n23 See infra at 31; Motion for Leave and Second Answer of Constellation passim (March 24, 2026) (“Mar. 24 Answer \nto PJM”); Request for Clarification, or in the Alternative, Rehearing, at 1-3 (Jan. 20, 2026) (“Clarification Request”). \n24 See infra at 32; Protest and Comments of Constellation Energy Generation, LLC, Docket No. ER26-1479-000, at \n2-8 (Mar. 16, 2026) (“Constellation 60-Day Compliance Filing Protest”); Comments and Conditional Protest of \nConstellation Energy Generation, LLC, Docket No. ER26-1088 (Feb. 20, 2026) (“Constellation 30-Day Compliance \nFiling Protest”)."},{"page":6,"startToken":1930,"endToken":2244,"text":"6 \nREPLY \nI. \nThe Commission Should Fast Track Interim NITS  \nThe fastest approach to “release the bottleneck of large load investments across the PJM \nfootprint”25 and obtain national and economic security is to quickly implement Interim NITS for \nnew and pending large load applicants. Taking three and half years to implement this transmission \nservice will not win the AI race, and such delay is inconsistent with the Commission’s \nDecember 18th Order.26 Immediately after the paper hearing briefing concludes, the Commission \nshould establish a separate track to promptly approve the rates and terms for Interim NITS as \nmodified below in Section III and make them effective no later than October 1, 2026. \nFive months is a reasonable amount of time to implement this service and advance the \nCommission’s goal of speedy interconnection. Indeed, PJM itself has been working on such a \nservice since at least March 2025 when it suggested its “Option 7” in its Answer to the \nFebruary 2025 Show Cause Order.27 Underscoring that there is no barrier to timely \nimplementation, the Southwest Power Pool (“SPP”) recently committed to making its version of \nInterim NITS, Conditional High Impact Large Loads Service (“CHILLS”), available on July 1 of \nthis year, less than five months after filing its revised tariff proposing the service and less than \nthree months after SPP’s requested action date by the Commission.28 PJM should be expected to \nact with comparable urgency.  \n \n25 FERC, FERC Directs Nation’s Largest Grid Operator to Create New Rules to Embrace Innovation and Protect \nConsumers (Dec. 18, 2025), https://www.ferc.gov/news-events/news/ferc-directs-nations-largest-grid-operator-\ncreate-new-rules-embrace-innovation-and?new= (quoting Chairman Swett). \n26 See supra note 5. \n27 PJM Answer to February 2025 Show Cause at 18-19 (March 24, 2025) \n28 Southwest Power Pool, Submission of Tariff Revisions to Add Conditional High Impact Large Load Service, Docket \nNo. ER26-1323, at 2 (Feb. 10, 2026) (“CHILLS Filing”)."},{"page":7,"startToken":2244,"endToken":2566,"text":"7 \nPJM offers no legitimate reason for proposing a three and half year delay. PJM first claims \nthat Interim NITS “will significantly affect the PJM Load Forecast and expected demand.”29 This \nis incorrect. The point of Interim NITS, as the Commission recognized, is that Co-Located Loads \nserved by Interim NITS are “interruptible loads” and “capacity will not be procured on their behalf \nuntil such time as the Network Upgrades are in place to serve them.”30 PJM has not explained how \nInterim NITS will impact its load forecast.  \nPJM next claims that the service should be delayed by more than three years because “the \naddition of the three new transmission services will require significant changes to PJM’s core \nMarkets and Operations systems”31 as they do not currently “automate Curtailment of Non-Firm \nContract Demand Transmission Service (or Interim NITS) before Firm Contract Demand \nTransmission Service.”32 PJM implies implementing these changes could be delayed by “vendor \navailability, the speed with which the system changes can be designed, and the interaction of these \nrequested changes with other competing priorities.”33 Possible logistical challenges will not risk \ndelay if the Commission separates and implements Interim NITS on a fast track. Like SPP, PJM \nwill only need to automate curtailment of Interim NITS before NITS just as it does for external \nNon-Firm Point to Point Transmission Service. Before entering Emergency Procedures, “PJM \n \n29 PJM Initial Brief at 79. \n30 December 18th Order, 193 FERC ¶ 61,217 at P 200 (emphasis added); see also Answer of PJM Interconnection, at \n18 (Mar. 24, 2025) (describing “Option 7” “Co-located load that takes Interruptible Service” as providing “as a non-\ncapacity backed load where it avoids capacity costs if willing to curtail to support reliability in advance of emergency \nconditions” and will require capacity “only for portion that is not non-capacity backed.”). \n31 PJM Initial Brief at 81. \n32 Id. at 65 (emphasis added). \n33 Id. at 61."},{"page":8,"startToken":2566,"endToken":2886,"text":"8 \nDispatch recalls export transactions, as needed, in accordance with Part II of the PJM OATT.”34 \nPJM also interrupts non-firm service for economic reasons to accommodate “a request for Firm \nTransmission Service” among other circumstances.35 SPP has not raised any administrative \nchallenges to implementing changes to its core systems. We should expect the same for PJM. \nMoreover, PJM could implement temporary operational and market workarounds until the changes \nto the core Markets and Operations systems are completed. \nLast, PJM argues the more-than-three-year delay is necessary because it “does not expect \nthat Eligible Customers and associated generation will be online and taking service under any of \nthe proposed transmission services before June 1, 2029.”36 This rationale ignores—and effectively \nprecludes—load co-locating with existing generation from selecting Interim NITS. Existing \ngenerators can serve Co-Located Loads after completing required Network Upgrades, and, \nconsistent with the December 18th Order, PJM should be trying to promote speedy connection, \nincluding through co-location arrangements with existing generation, rather than to stymie such \narrangements. Speed to service will not be achieved if discrimination is allowed against all the \nmegawatts already available and ready to reliably serve. \nAdopting Interim NITS as soon as possible should not be difficult. As PJM admits, \n“[g]enerally speaking, the non-rate terms and conditions for Interim NITS are the same as for \nNITS.”37 The Indicated Transmission Owners also propose to charge the same undiscounted NITS \n \n34 PJM Manual 13, § 2.3.2; see also OATT, Part II, § 14.7 (“The Transmission Provider reserves the right to Curtail, \nin whole or in part, Non-Firm Point-To-Point Transmission Service provided under the Tariff for reliability reasons \nwhen an emergency or other unforeseen condition threatens to impair or degrade the reliability of its Transmission \nSystem or the systems directly and indirectly interconnected with Transmission Provider’s Transmission System.”). \n35 OATT, Part II, § 14.7 \n36 PJM Initial Brief at 82. \n37 Id. at 67."},{"page":9,"startToken":2886,"endToken":3166,"text":"9 \nrate for Interim NITS.38 While we propose certain modifications that would apply to the proposed \nInterim NITS in Section III below, these modifications likely would decrease the time required \nfor PJM and the Transmission Owners to implement Interim NITS. Allowing large loads with \npending NITS applications to apply for Interim NITS may deliver immediate results.39 \nClarification of what additional studies need to be performed, and the timeline for such studies, \nwill streamline the process.40 Adopting PJM’s existing Tariff provisions on unreserved use for \nNon-Firm Point-to-Point Transmission Service for Interim NITS will simplify the development \nand implementation of penalty charges and other remedial actions.41 And removing the \ninapplicable and unnecessary requirements to obtain state authorization and to construct different \nfeeders will prevent needless delays.42 \nContract Demand Services can proceed on a separate track to allow the Commission to \ntake more time, if needed, to establish the rates and terms of the new services, including a \nreasonable and cost-based Grid Reliance Charge. However, we urge the Commission not to delay \nthese services until June 2029. “The risks of inaction or delayed action are simply too great.”43 \n \n38 See Indicated TO Initial Brief, Exh. No. PTO-0001 at 16:10-12. \n39 See infra at 14. \n40 See infra at 14-18. \n41 See infra at 18-21. \n42 See infra at 29-30. \n43 \nSee \nFERC, \n1130th \nCommission \nMeeting \nTranscript, \nat \n26:24-25 \n(Nov. \n20, \n2025), \nhttps://www.ferc.gov/media/transcript-november-20-2025-open-meeting (remarks of Commissioner LaCerte); see \nalso id. at 7:1-3 (“[M]y priority as Chairman is to ensure that our country can connect and power data centers as \nquickly and as durably as possible.”) (remarks of Chairman Swett)."},{"page":10,"startToken":3166,"endToken":3712,"text":"10 \nII. \nPJM Proposes to Restrict Contract Demand Services in Conflict with the December 18th \nOrder \nPJM proposes to restrict Contract Demand Services in two ways: first, by restricting Non-\nFirm Contract Demand Service to a Co-Located Generating Facility’s outage,44 and second, by \nrequiring Firm Contract Demand Service for any portion of the Co-Located Load not served by \nthe Co-Located Generating Facility.45 These restrictions contradict or are otherwise inconsistent \nwith the December 18th Order. They should be rejected.  \nFirst, the Commission did not limit Eligible Customers to taking Non-Firm Contract \nDemand Service only at times when the Co-Located Generating Facility is on outage. The \nDecember 18th Order made Non-Firm Contract Demand Service available for Eligible Customers \nto withdraw energy from the transmission system “when transmission capacity is available and \nnot needed by firm customers,” period.46 The use of the Non-Firm Contract Demand Service to \n \n44 PJM Initial Brief at 6; see also id. (“In short, for reliability reasons, the portion of the Co-Located Load for which \nthe Co-Located Generating Facility will dedicate its output (in whole or in part) may be covered by Non-Firm \nContract Demand Transmission Service, but any portion of the gross demand of the Co-Located Load not served by \nthe Co-Located Generating Facility must be covered by Firm Contract Demand Transmission Service.”); id. at 16 \n(“An Eligible Customer taking service on behalf of a Co-Located Load must request Non-Firm Contract Demand \nTransmission Service equivalent to the MW level of the Co-Located Generating Facility dedicated to serving the \nCo-Located Load, and an Eligible Customer with an effective Service Agreement will be eligible to obtain Non-\nFirm Contract Demand Transmission Service on a given Operating Day only to the extent the portion of the Co-\nLocated Generating Facility dedicated to serving the Co-Located Load is on outage.”). \n45 Id. at 6 (“any portion of the gross demand of the Co-Located Load not served by the Co-Located Generating Facility \nmust be covered by Firm Contract Demand Transmission Service”); see also id. at 9 (“A Co-Located Generating \nFacility will not always be available (e.g., due to planned or unforced outage). To the extent that the gross demand \nof a Co-Located Load is not covered by the Eligible Customer’s Firm Contract Demand Transmission Service, the \nEligible Customer must cover the remaining gross demand by applying for Non-Firm Contract Demand \nTransmission Service. In that case, the Non-Firm Contract Demand Transmission Service, if PJM determines it is \navailable for the requested period, will act as a backup to allow the Co-Located Load to meet its full demand, while \nthe portion of the Co-Located Generating Facility dedicated to the Co-Located Load is on outage and unable to \nprovide energy.”); id. at 16 (“Conversely, as discussed above in the overview section, an Eligible Customer taking \nservice on behalf of a Co-Located Load must request Firm Contract Demand Transmission Service for no less than \nthe MW level of the gross demand of the Co-Located Load that will not be served by the dedicated Co-Located \nGenerating Facility.”) \n46 Id. P 214 (emphasis added); see also id. P 215 (“As noted above, Eligible Customers may use Non-Firm Contract \nDemand transmission service to make use of the transmission system above their Firm Contract Demand \ntransmission service level, if transmission capacity is available.”)."},{"page":11,"startToken":3712,"endToken":4194,"text":"11 \nsupport load during an expected outage was simply an “example.”47  Nothing in the December 18th \nOrder limited  the service to that one scenario. \nPJM’s justifications for limiting Non-Firm Contract Demand Service are unpersuasive. \nPJM claims that it must limit Non-Firm Contract Demand Service to times when the Co-Located \nGenerating Facility is on outage to ensure that Co-Located Loads do not “compromis[e] the level \nof reliability to firm loads.”48 This argument fails to recognize “the reality … that large loads can \nbe flexible in the amount of transmission service they use.”49 The Commission repeatedly found \nthat “the record demonstrates that Eligible Customers taking transmission service on behalf of Co-\nLocated Loads are willing and able to limit their energy withdrawals from the transmission system \nunder certain conditions.”50 If PJM disagreed, it should have timely sought rehearing. \nPJM also claims that its limitation is necessary to ensure that Co-Located Loads do not \n“over-utiliz[e] their non-firm contract arrangements at the cost of firm service ratepayers.”51 This \n \n47 December 18th Order, 193 FERC ¶ 61,217 at P 214 (introducing its discussion of the scenario with the words “[f]or \nexample”). \n48 PJM Initial Brief, Attachment B at ¶ 17 (“Abdulsalam Affidavit”). \n49 FERC, Transcript of 1131st Commission Meeting, at 7:5-7 (Dec. 18, 2025) https://www.ferc.gov/media/transcript-\ndecember-18-2025-open-meeting (remarks of Chairman Swett). \n50 December 18th Order, 193 FERC ¶ 61,217 at P 199; id. P 2 (“we find that PJM’s Tariff is unjust and unreasonable \nbecause it does not include types of transmission service that reflect Eligible Customers taking service on behalf of \nCo-Located Loads that are willing and able to limit their use of the transmission system under certain conditions”); \nid. P 159 (“We also find that PJM’s Tariff is unjust and unreasonable because it does not include transmission \nservices that reflect an Eligible Customer taking service on behalf of a Co-Located Load that is willing and able to \nlimit its energy withdrawals from the transmission system under certain conditions.”); id. P 177 (“we also find that \nPJM’s Tariff is unjust and unreasonable because it does not include transmission services that reflect Eligible \nCustomers taking service on behalf of Co-Located Loads that are willing and able to limit their energy withdrawals \nfrom the transmission system under certain conditions”); id. P 193 (“we find that PJM’s Tariff is unjust and \nunreasonable because it does not include transmission services that reflect Eligible Customers taking service on \nbehalf of Co-Located Loads that are willing and able to limit their energy withdrawals from the transmission system \nunder certain conditions.”); see also FERC, Transcript of 1131st Commission Meeting,  at 7:11-14 (Dec. 18, 2025), \nhttps://www.ferc.gov/media/transcript-december-18-2025-open-meeting (“the order recognizes that PJM’s existing \ntransmission services are insufficient in that they do not recognize the controllable nature of co-location \narrangements.”) (remarks of Chairman Swett). \n51 Abdulsalam Affidavit at ¶ 17."},{"page":12,"startToken":4194,"endToken":4578,"text":"12 \nargument similarly falls short. The Commission offered solutions for the precise issue of \nunreserved use: penalty charges, curtailment procedures, and technical and engineering \nrequirements of special protection schemes.52 Moreover, as the Commission recognized, Non-\nFirm Contract Demand Service benefits ratepayers by “potentially avoid[ing] costly and inefficient \ntransmission system buildout that may not be necessary.”53 In addition, as electricity market design \nexpert Zachary Ming explained, “[c]ollection of as-available transmission charges would directly \nbenefit existing ratepayers by reducing rates since as-available energy purchases by co-located \nloads would contribute to the recovery of transmission costs without requiring any additional costs \nto be incurred.”54 Others have stated similarly.55 \nSecond, the Commission did not require Eligible Customers to take a Firm Contract \nDemand Service along with Non-Firm Contract Demand Service. While Eligible Customers have \nthe option to take both services, they are not required to do so.56 They only must “choose at least \none of the required transmission services.”57 Nor is there the requirement that the Eligible \nCustomer must take Non-Firm Contract Demand up to the MW of the Co-Located Generating \nFacility. Crucially, the Commission specifically contemplated the arrangement where the Co-\n \n52 December 18th Order, 193 FERC ¶ 61,217 at PP 217, 219. \n53 Id. P 160; see also id. P 199 (““Requiring this could necessitate inefficient and costly transmission buildout and \ncosts paid by transmission customers that may not be necessary if Eligible Customers taking transmission service \non behalf of Co-Located Loads are willing to limit their energy withdrawals and take a transmission service that \nrequires fewer Network Upgrades to provide.”). \n54 Constellation Apr. 23 Reply Comments, Exhibit 2, Testimony of Zachary Ming 41:17-20. \n55 See, e.g., Norris, Tyler, et al., Rethinking Load Growth: Assessing the Potential for Integration of Large Flexible \nLoads \nin \nUS \nPower \nSystems, \nat \n11 \n(2025) \nhttps://nicholasinstitute.duke.edu/sites/default/files/publications/rethinking-load-growth.pdf \n(“By \nstrategically \ntiming or curtailing demand, these flexible loads can minimize their impact on peak periods. In doing so, they help \nexisting customers by improving the overall utilization rate—thereby lowering the per-unit cost of electricity—and \nreduce the likelihood that expensive new peaking plants or network expansions may be needed.”). \n56 December 18th Order, 193 FERC ¶ 61,217 at P 194 \n57 Id. (emphasis added)."},{"page":13,"startToken":4578,"endToken":4895,"text":"13 \nLocated Load “will not withdraw energy from the transmission system must take Non-Firm \nContract Demand transmission service at 0 MW.”58 Likewise, there is no requirement that Eligible \nCustomers must take Firm Contract Demand for the MWs of the Co-Located Load not served by \nthe Co-Located Generating Facility. If an Eligible Customer selects Firm Contract Demand \nService, the “Eligible Customer[] will have the right to request transmission service on behalf of \na Co-Located Load up to a specified MW quantity, i.e., the contract demand.”59 \nThe December 18th Order did not give PJM permission to dictate the transmission services \nthat an Eligible Customer must take when taking service on behalf of Co-Located Load. The \nCommission explicitly gave Eligible Customers that choice, stating that Eligible Customers \n“should be allowed to choose the transmission service that aligns with their use of the transmission \nsystem”60 and Eligible Customers “may choose the transmission services that match their \npreferred use of the transmission system.”61 \nIII. \nThe Commission Should Encourage Its New Transmission Services and Reject Attempts \nthat Frustrate Their Use \nPJM and Indicated Transmission Owners propose provisions that would restrict, delay or \notherwise discourage the use of Interim NITS and Contract Demand Services. The Commission \nshould reject these attempts and allow co-location arrangements to move forward as the \nDecember 18th Order envisions and consistent with the national interest in winning the AI race. \n \n58 Id. P 206. \n59 Id. P 208 (emphasis added). \n60 Id. P 199. \n61 Id. P 194 (emphasis added); see also Stockton Declaration at 1 (“Constellation Reply Comments”) (“The entities \nthat own or operate the AI facilities should be given the choice to determine which configuration for interconnecting \nthem is best for their needs, in close consultation with DOD and the other national security agencies that depend on \ntheir AI services. Neither FERC, PJM nor individual transmission owners should make that choice for them.”)."},{"page":14,"startToken":4895,"endToken":5178,"text":"14 \nThese revisions should shrink the timeline required to implement both Interim NITS (and thus \nfacilitate an earlier schedule) and the Contract Demand Services. \nA. The Commission Should Direct PJM to Include a Transitional Mechanism \nfor Pending Large Load NITS Applications \nPJM should revise its proposal to clarify that large loads with pending NITS applications \nmay apply for Interim NITS. Limiting Interim NITS availability to new applicants would \nunnecessarily restrict the availability of the service and eliminate an opportunity to serve large \nloads faster. PJM should clarify that Interim NITS is available for large loads meeting the \nCommission’s definition of Co-Located Load after PJM conducts a supplemental study, if \nnecessary, to find the requested Interim NITS could be provided reliably. The Interim NITS \napplication and study processes would take place simultaneously with the pending NITS \napplication. Clarifying that pending large load applications will be eligible to elect Interim NITS \nwill prevent future disputes and delays. The election of Interim NITS eligibility, which itself is \ncontingent upon a standard NITS application and meeting the definition of Co-Located Load, \nshould not be an excuse to force applicants to re-start the NITS process. \nB. PJM’s Proposed Study Procedures Lack Sufficient Detail to Prevent Needless \nDelay and Discrimination by Transmission Owners \nPJM’s proposed study procedures for both Interim NITS and the Contract Demand \nServices fall short of “addressing with sufficient clarity or consistency” the terms that apply to \nEligible Customers and that are necessary to ensure PJM’s Tariff is just and reasonable.62 Absent \nfrom the proposed procedures are descriptions of the studies to be performed. The studies that PJM \nwill perform when evaluating Interim NITS are described vaguely as “additional studies beyond \n \n62 Id. P 2."},{"page":15,"startToken":5178,"endToken":5489,"text":"15 \nwhat is required to evaluate the Eligible Customer’s request for NITS.”63 The studies that PJM \nwill perform when evaluating Firm Contract Demand Service are described as “necessary studies” \n“in accordance with PJM Manuals.”64 The studies PJM and the Transmission Owner will perform \nwhen evaluating Non-Firm Contract Demand are described as “additional studies”65 and “different \nevaluations to actually use such service on the Transmission System on any given day.”66 PJM \nprovides no further explanation. PJM must spell out in the Tariff the studies that it will perform in \nconjunction with the Co-Located Generating Facility and the timetable for completing these \nstudies. The scope of the “additional studies” and “necessary studies,” which will determine \nwhether PJM can provide the requested service and any upgrades required, “significantly affect \nthe rates, terms and conditions” of service and are “readily susceptible to specification.”67 They \nshould not be placed in PJM’s business manuals where PJM has unilateral discretion and may not \nbe enforced. They should be spelled out in the tariff, so that the Commission can review them and \nensure that the study process does not frustrate the Commission’s goals, and so that parties have a \nstandard they can enforce with the Commission if needed.68 \nIndeed, PJM’s proposed study procedures allow for the perpetuation of existing \ndiscrimination, delays, tying, and encumbrances of large load configurations by Transmission \n \n63 PJM Initial Brief at 70-71. \n64 Id. at 24. \n65 Id. at 33. \n66 Id.  \n67 Energy Storage Ass’n v. PJM Interconnection, L.L.C., 162 FERC ¶ 61,296, at P 103 (2018). \n68 See RWE Clean Energy, LLC v. PJM Interconnection, L.L.C., 194 FERC ¶ 61,212, at P 38 (2026) (“The \nCommission does not review and approve PJM’s manuals, as they are not filed with the Commission. As a result, \nwe have no statutory obligation to enforce the terms.”)."},{"page":16,"startToken":5489,"endToken":6193,"text":"16 \nOwners.69 In fact, PJM repeatedly makes clear that Transmission Owners will play a lead role in \ndetermining whether an Eligible Customer can take Interim NITS and Contract Demand Services: \n• “The Transmission Provider, in consultation with the affected Transmission \nOwner(s), will determine the amount of Interim Network Integration Transmission \nService that can be provided to an Eligible Customer, including through the use of \ntemporary solutions, while maintaining the reliability of the Transmission \nSystem.”70 \n• “PJM would ‘coordinate with the affected Transmission Owner(s) to complete \nstudies, including load integration studies, [to obtain] data relevant to the \n \n69 See, e.g., Complaint Requesting Fast Track Processing of Constellation Energy Generation, LLC, Constellation \nEnergy Generation, LLC v. PJM Interconnection, L.L.C., Docket No. EL25-20-000 at 7 (Nov. 22, 2024) (“Exelon \nis refusing to process necessary studies on these grounds, demanding expensive upgrades under their unfiled \ninterconnection procedures, delaying agreed-upon work which will force a nuclear plant to take additional outages, \nand forcing additional services to be procured.”) (“Constellation Complaint”); id at 7-8. (“Exelon fulfilled its \nresponsibilities as an interconnection provider to review PJM’s necessary studies for one Constellation nuclear \nstation, the LaSalle Clean Energy Center (‘LaSalle’), but later refused to do so at the other two stations, insisting \nthat Constellation or its potential customer must first apply for retail service and designate what sort of wholesale \ntransmission service it will take from Exelon.”); id. at 17 (“But for Constellation’s … Limerick Clean Energy Center \n(‘Limerick’) in Pennsylvania, Exelon has refused to conduct its review of PJM’s completed necessary studies, \ninsisting that Constellation or its potential customer must first apply for retail service and designate what sort of \nwholesale transmission service it will take from Exelon.”); Constellation Complaint at 8 (“projects are being held \nhostage by a few monopolies refusing to cooperate with reliability studies related to interconnection modifications”); \nid. at 10 n.25 (“Exelon refuses to review co-location reliability studies as required by the OATT and pro forma ISA”) \n(citing Constellation PDO Protest, Exhibit 1, Declaration of James R. McCoskey at ¶ 13); id. at 16 (“Proposed Fully \nIsolated Co-Located data center projects in PJM are currently being held hostage by one or two monopoly utilities’ \nrefusal to cooperate … with reliability studies related to interconnection modifications.”); see also Supporting \nComments of Constellation Energy Generation, LLC, Interconnection of Large Loads to the Interstate Transmission \nSystem, Docket No. RM26-4-000, at 3-4 (Nov. 21, 2025) (“Some Transmission Owners have simply refused to \nparticipate in PJM’s studies to analyze reliability impacts; and some, acting under unfiled interconnection study \nprocedures, have changed their entire construct and timetable for processing load studies.”) (“Constellation ANOPR \nComments”); Answer of Constellation Energy Generation, LLC, PJM Interconnection, L.L.C. et al., Docket Nos. \nEL25-49-000, et al., at 3 (Apr. 23, 2025) (“The Indicated Transmission Owners read the existing Tariff to require \nthis one-size-fits-all limitation, and they have refused to perform studies for new load seeking a different \nconfiguration.”); id. at 14 (“What is more, regardless of what the Tariff actually says and does not say, some of the \nIndicated Transmission Owners have refused to cooperate in PJM’s ‘necessary studies’ process unless the load \nagrees to taking NITS, claiming justification under the Tariff. Some of the Indicated Transmission Owners have \nrefused to process necessary studies, demanded expensive upgrades under their unfiled interconnection procedures, \nand forced a generator seeking to serve co-located load to procure additional services not required by the Tariff.”) \n(citing Constellation Complaint at 7); Constellation Complaint at 9 (“Exelon’s also is refusing to perform work on \nLaSalle’s interconnection facilities to accommodate co-location, none of which affects the grid. Exelon’s refusal to \ncomplete previously agreed-upon work as scheduled during an upcoming planned outage will increase costs to \nConstellation by $15.3-$19 million at that site alone, just so Exelon can pursue its litigation positions.”); see also \nPJM Interconnection, L.L.C., 190 FERC ¶ 61,115, at P 75 (“there are allegations in the record that Exelon has \ndelayed work on Constellation’s requests to co-locate load with its generators at certain facilities due to Exelon’s \nconcerns that such requests are not allowed under the Tariff without arranging for wholesale transmission or retail \ndistribution service.”). \n70 PJM Initial Brief, Illustrative Tariff, Part XI, § 702.3."},{"page":17,"startToken":6193,"endToken":6492,"text":"17 \ndetermination of whether (and to what level)’ Firm or Non-Firm Contract Demand \nTransmission Service ‘can be reliably provided’ and ‘identify any necessary \nenhancements to the Transmission System to accommodate the requested level of \nservice.’”71 \n• “PJM, in consultation with the affected PJM Transmission Owner(s), will \ndetermine the level of Firm Contract Demand Transmission Service or Non-Firm \nContract Demand Transmission Service that can be reliably provided and inform \nthe Eligible Customer.”72 \n• PJM states that “upon receiving a request for Non-Firm Contract Demand \nTransmission Service, [it] will coordinate with the affected Transmission Owner(s) \nto complete necessary studies to determine whether—and at what level—Non-Firm \nContract Demand Transmission Service can be reliably provided.”73 \n• “PJM will not study transmission service requests alone, but rather will coordinate \nand consult with any affected Transmission Owners to determine whether and how \nthe requested transmission service may be provided.”74 \n• “PJM and the affected Transmission Owner(s) will determine whether additional \nstudies are required ‘to assess whether the Transmission System has sufficient \navailable capacity to provide Non-Firm Contract Demand Transmission Service, \nand if so, which studies are appropriate.’”75 \nThere is reason to believe that Transmission Owners may use their role and their natural \nmonopoly market power to delay and deny co-location arrangements they do not favor. Delays \nassociated with the Transmission Owners’ refusal to process necessary studies are well \ndocumented in the record.76 To achieve speed to market, Transmission Owners should not be given \nthe opportunity to deny transmission service or, what amounts to the same, to delay transmission \nservice unreasonably. Deadlines and other mechanisms must be set forth in the Tariff to prevent \n \n71 PJM Initial Brief at 17-18. \n72 Id. at 18. \n73 Id. at 32-33. \n74 Id. at 33. \n75 Id. \n76 See supra note 69."},{"page":18,"startToken":6492,"endToken":6775,"text":"18 \nTransmission Owners from needlessly delaying studies and unreasonably denying new \ntransmission services. \nC. PJM and Indicated Transmission Owners’ “To Be Determined” Penalty \nCharges and Remedial Actions are Not Just and Reasonable \nPJM and Indicated PJM Transmission Owners have failed to follow the Commission’s \ndirective to propose an “appropriate penalty charge or other remedial action that PJM should take \nto address any unreserved use”77 by an Eligible Customer taking Interim NITS and Contract \nDemand Services. \nFirst, they offer no proposal on a penalty charge. Penalty charges are “[t]o be determined”78 \nsubject to PJM’s and the Indicated Transmission Owners’ “inten[tion] to work” with each other \n“in continuing to explore the penalty options and will, if appropriate, offer a proposal at a \nsubsequent stage of this paper hearing process.”79 Whether and when to respond to a \nCommission’s directive is not optional. PJM and the Indicated Transmission Owners were to \nrespond to the Commission’s questions with “specificity”80 by the extended deadline.81 The \nCommission did not grant 30-day extension the Indicated Transmission Owners requested. The \nCommission shortened the extension to seven days after having recognized Constellation’s \ncomment that “the original 60-day deadline is consistent with the administration’s goals to \n \n77 December 18th Order, 193 FERC ¶ 61,217 at P 219 (Question Numbers 5 and 6). \n78 PJM Initial Brief at 41. \n79 Indicated TO Initial Brief at 20 (emphasis added); see also PJM Initial Brief at 50 (“With regard to the financial \npenalty, PJM intends to work with the PJM Transmission Owners to explore such a financial penalty.”). \n80 December 18th Order, 193 FERC ¶ 61,217 at P 219. \n81 See FERC, Notice of Extension of Time (Jan. 23, 2026)."},{"page":19,"startToken":6775,"endToken":7127,"text":"19 \npromptly resolve large load issues and that transmission owners have an interest in delaying \nimplementation of the new transmission services.”82  \nAs discussed in further detail below, using SPP’s proposed CHILLS as a model, the \nCommission can promptly direct PJM to align its treatment of unreserved use by Eligible \nCustomers taking Interim NITS and Non-Firm Contract Demand Services with its treatment of \nNon-Firm Point-To-Point Transmission Service. \nSecond, the “remedial actions” that PJM does propose—suspensions or disqualification of \nEligible Customers from taking Interim NITS and Contract Demand Services83—are not “remedial \nactions,” that is, actions “to correct, remove, or lessen a wrong, fault, or defect.”84 They are \nextreme punishments that were not contemplated by the December 18th Order85 and are placed \nonly upon Co-Located Load arrangements. Transmission Customers taking Non-Firm Point-To-\nPoint Transmission Service are not subject to suspension or disqualification for unreserved use of \nthe transmission system. PJM simply recalls export transactions and Transmission Customers are \nonly subject to “Curtailment or Interruption under the terms of the Tariff.”86  \nUnder PJM’s proposal, the failure by an Eligible Customer to follow one instance of \nCurtailment or Load Shed procedures, no matter who is at fault, disqualifies an Eligible Customer \n \n82 Id. at 3. \n83 PJM Initial Brief at 41-50. \n84 See Remedial, BLACK’S LAW DICTIONARY (12th ed. 2024) \n85 December 18th Order, 193 FERC ¶ 61,217 at P 212 (“We direct parties to brief the appropriate penalty charge for \na Firm Contract Demand transmission service customer’s unreserved use of the PJM transmission system. We also \ndirect parties to brief the appropriate procedures for PJM to curtail Eligible Customers taking the new Firm Contract \nDemand transmission service on behalf of Co-Located Loads that withdraw energy in excess of the contract demand \nand any other remedial action that PJM should take to address withdrawals in excess of the contract demand. We \nalso note that, as discussed in the briefing questions below, PJM will determine the technical and engineering \nrequirements of special protection schemes to help address reliability risks associated with unreserved use of the \ntransmission system.”). \n86 OATT, Part II, § 14.5."},{"page":20,"startToken":7127,"endToken":7386,"text":"20 \nindefinitely from taking Interim NITS or Contract Demand Services.87 If necessary control \ntechnology or protection scheme misoperates, the Eligible Customer is suspended 120 days from \ntaking Interim NITS and Contract Demand Services the first time and disqualified indefinitely the \nsecond time.88 For disqualified Eligible Customers, PJM emphasizes, not once but four times, that \n“[i]mportantly … such an Eligible Customer may take NITS, which would begin after all necessary \nupgrades are placed into service.”89 These Draconian punishments are not reasonable, as they are \nimposed regardless of fault and will make these services unduly risky for many loads. “Remedial \nactions” cannot be so extreme that they effectively make the alternatives to NITS dead letters. \nLike SPP’s proposed tariff provisions for CHILLS,90 the Commission should direct PJM \nto align the treatment of unreserved use by Interim NITS and Contract Demand Services with its \ntreatment of Non-Firm Point-To-Point Transmission Service. SPP has proposed that if a \nTransmission Customer exceed its CHILLS reserved capacity, similar to Non-Firm Point-To-Point \nTransmission Service, “the Transmission Customer may pay, in addition to the charges for all of \nthe CHILLS capacity used, one-hundred percent (100%) of the Non-Firm Point-To-Point \nTransmission Service charges under Schedules 8 and 11 for the period when the additional service \nwas used ….”91 SPP proposes no suspension or disqualification of interruptible loads. The \nCommission should adopt SPP’s approach and direct PJM to align unreserved use by Eligible \n \n87 PJM Initial Brief at 41-42. \n88 Id. at 44-46. \n89 Id. at 46. \n90 CHILLS Filing at 31. \n91 Id. at 30."},{"page":21,"startToken":7386,"endToken":7698,"text":"21 \nCustomers taking Interim NITS and Contract Demand Services with its treatment of Non-Firm \nPoint-To-Point Transmission Service in section 14.5 of Part II of its Tariff.92 \nD. Clarification of Proposed System Protection Scheme Requirements is Needed \nto Prevent Discrimination and Delays \nWe make two discrete comments on PJM’s proposal for system protection schemes, \nincluding special protection systems (“SPS”) and remedial action schemes (“RAS”). First, PJM \nshould make clear that its statement “[t]he interconnection requirements and operational practices \nnecessary for necessary control technologies and protection systems to maintain system reliability \n… will be set forth in the PJM Manuals”93 means that PJM will apply the requirements set forth \nin PJM Manual 3 to co-located arrangements. As “[t]here is no technical reason … to expect that \nprotective relaying in the context of co-location would perform any less reliably,”94 new \nrequirements should not be established solely for Co-Located Loads. Second, PJM should clarify \nthat it did not intend for its statement “[t]heir implementation is generally limited to temporary \nconditions involving the outage of critical equipment”95 to restrict the use of permanent system \nprotection schemes. The Commission intended special protection schemes to be a permanent \nfixtures for Co-Located Loads.96 Moreover, NERC does not recognize this temporal limitation.97 \n \n92 OATT, Part II, § 14.5 \n93 PJM Initial Brief  at 57. \n94 Constellation Reply Comments, Exhibit 4, at ¶ 23 (Affidavit of Steven Herling) (“Herling Aff.”). \n95 PJM Initial Brief at 58. \n96 December 18th Order, 193 FERC ¶ 61,217 at P 205. \n97 See NERC, Special Protection Systems (SPS) and Remedial Action Schemes (RAS): Assessment of Definition, \nRegional \nPractices, \nand \nApplication \nof \nRelated \nStandards, \nat \n8 \n(2013), \nhttps://www.nerc.com/globalassets/standards/projects/2010-\n05.2/system_protection_and_control_subcommittee_spcs_20_sams-spcs_sps_technic_02182014.pdf \n(explaining \nthe cases where permanent special protection schemes have been implanted)."},{"page":22,"startToken":7698,"endToken":8057,"text":"22 \nIn addition, we comment on eight of the nine recommendations proposed by Indicated \nTransmission Owners relating to special protection schemes for Co-Located Loads taking Interim \nNITS and Contract Demand Services.98 As Indicated Transmission Owners state they are “not \noffering a specific proposal at this time,” we also reserve our ability to comment on any proposal \nthat the Indicated Transmission Owners offer at a later date.99  \n1. Indicated Transmission Owner Recommendations 1 to 4 are Reasonable \nSubject to Clarification to Avoid Delay and Discrimination \nConstellation agrees with Indicated Transmission Owners’ first recommendation that “[a]ll \nSPS and RAS should be fully redundant.”100 However, clarification on what “full redundancy” \nmeans is necessary. As explained by Steven Herling, protective schemes can be designed so that \nthey are “completely redundant.”101 Mr. Herling provided the example of where “[t]here are two \ncircuit breakers placed in series supplying the co-located load, so that if one fails, the second will \nstill open the circuit. Each circuit breaker has two trip coils such that either the primary or backup \nprotective relay can successfully trip the load. All elements of the protective scheme, including the \nelectric current transformers, the fiber channels, and the trip relays, are redundant resulting in a \nsingle-failure-proof design.”102 To the extent Indicated Transmission Owners argue that more is \nrequired, we object. We reiterate, “[t]here is no technical reason … to expect that protective \n \n98 See Indicated TO Initial Brief at 22-26. We do not comment on Indicated Transmission Owner’s ninth \nrecommendation suggesting that “The Commission should direct NERC to establish requirements that Co-Located \nLoad customers register with NERC so that those customers may be responsible for meeting NERC’s reliability \nstandards, including NERC Reliability Standard PRC-012-2.” Id. at 24. We also note that Indicated Transmission \nOwners’ recommendations differ from PJM’s proposal in that PJM only applies its system protection schemes \nrequirements to Interim NITS and Non-Firm Contract Demand Service, not Firm Contract Demand Service. See \nPJM Initial Brief at 56. \n99 Indicated TO Initial Brief at 22. \n100 Id. at 23. \n101 Herling Aff. at ¶ 21; id. ¶ 23 (providing example of fully redundant design).  \n102 Id. at ¶ 22."},{"page":23,"startToken":8057,"endToken":8353,"text":"23 \nrelaying in the context of co-location would perform any less reliably.”103 The Commission has \nagreed. “[S]pecial protection schemes allow … Co-Located Load to effectively limit their \nwithdrawals from the transmission system.”104 \nConstellation agrees with Indicated Transmission Owners’ second recommendation that \nthe Co-Located Load customer should “pay for PJM and PJM Transmission Owner-administered \nstudies to ensure any SPS or RAS can effectively mitigate the risks of potential failure modes.”105 \nHowever, a detailed description of the studies to be performed and the timelines they are to be \ncompleted must be on file as they are a key element of the service to be provided and will directly \nimplicate the time to provide such service. To do otherwise risks delays and discriminatory conduct \nby Transmission Owners.106 \nWe do not oppose the third recommendation that “PJM Transmission Owners should have \nthe option to review and agree to any customer load curtailment procedures or operational control \nmechanisms.”107 However, there must be additional terms establishing deadlines for review and \npreventing Transmission Owners from unreasonably withholding approval over customer load.108 \nLast, Constellation agrees in principle with the fourth recommendation that “[a]ll SPS and \nRAS must fully meet PJM and PJM Transmission Owner technical criteria.”109 PJM Manual 3 sets \nforth PJM’s procedures for reviewing RAS based on the reliability-related considerations in \n \n103 Id. at ¶ 23. \n104 December 18th Order, 193 FERC ¶ 61,217 at P 205; see also id. (“We note that, in general, special protection \nschemes allow Eligible Customers on behalf of Co-Located Load to effectively limit their withdrawals from the \ntransmission system.”).  \n105 Indicated TO Initial Brief at 23. \n106 See supra note 69. \n107 Indicated TO Initial Brief  at 23. \n108 See supra note 69. \n109 Indicated TO Initial Brief at 23."},{"page":24,"startToken":8353,"endToken":8589,"text":"24 \nAttachment 2 of NERC Reliability Standard PRC-012-2 that the Reliability Coordinator must \nreview and verify for new and modified each RAS.110 New technical criteria should not be \nestablished solely for Co-Located Loads. \n2. Indicated Transmission Owner Recommendations 5 through 8 Should be \nRejected as Unsupported and Discriminatory \nThe Commission should reject Transmission Owners’ fifth, sixth, seventh, and eighth \nrecommendations. These recommendations are unsupported and unduly discriminatory towards \nCo-Located Load arrangements. As “[t]here is no technical reason … to expect that protective \nrelaying in the context of co-location would perform any less reliably,” there is no justification for \nIndicated Transmission Owner to require that only Co-Located Loads be subject to:  \n• “PJM Transmission Owners … requir[ing] the implementation of SPS or RAS on \nthe Transmission Owner’s side of the point of interconnection and to require that \nthe costs associated with such SPS or RAS be fully recoverable,”111 (Seventh \nRecommendation);  \n• allowing PJM Transmission Owners to “own, maintain, and operate any SPS or \nRAS installed on the customer’s side of the point of interconnection”112 (Eighth \nRecommendation); \n• “limits on the total amount of load that can be covered by SPS or RAS”113 (Sixth \nRecommendation); and \n• “more frequent testing of SPS and RAS than is currently required by NERC \nReliability Standards”114 (Fifth Recommendation).  \n \n110 PJM Manual 3, § 1.7. \n111 Indicated TO Initial Brief at 24.  \n112 Id. \n113 Id. at 24. \n114 Id. at 23."},{"page":25,"startToken":8589,"endToken":8957,"text":"25 \nProtection schemes “regularly employed on the PJM transmission system” are not subject to these \nnew requirements. There is no legitimate basis for treating Co-Located Load arrangements \ndifferently.115 \nMoreover, the Indicated Transmission Owners’ proposal to take ownership over special \nprotection schemes is the exact scenario of discrimination that Constellation identified in its \ncomments opposing PJM’s proposal to revise the Commission-mandated definition of Co-Located \nLoad.116 If the Transmission Owners takes ownership of all or part of the ring bus, as they propose, \nthe ring bus would be a Transmission Owner Interconnection Facility and fall on the Transmission \nOwner’s side of the Point of Change in Ownership. Under PJM’s proposed definition of “Co-\nLocated Load,” the new load would not qualify. Thus, the Commission should not be fooled by \nthe Indicated Transmission Owners’ insistence on owning special protection schemes: if they \nprevail, then they can stymie all non-NITS services by claiming that the load falls outside the \ndefinition of “Co-Located Load,” at least as PJM would define it.  \nE. The Grid Reliance Charge Must be Economically Grounded and Rational \nThe Indicated Transmission Owners’ proposed Grid Reliance Charge for Contract Demand \nService customers not drawing power from the PJM network is derived from an unsound \nmethodology that violates cost causation principles. Put simply, the rate is not just and reasonable \nand does not represent the “fair share” of such Contract Demand Service customers.117 The \n \n115 See supra note 104 (citing December 18th Order, 193 FERC ¶ 61,217 at P 205).  \n116 See Constellation 60-Day Compliance Filing Protest at 2-8; Constellation 30-Day Compliance Filing Protest \npassim. \n117 See December 18th Order, 193 FERC ¶ 61,217 (Chang, Comm’r, concurring at P 10) (“given that all Co-Located \nLoads rely on the existence of the PJM grid and are synchronized to it, such loads should pay for at least their fair \nshare of the system’s operations and maintenance costs”); id. (Chang, Comm’r concurring at P 9) (“This minimum \ncharge would provide a floor to the Co-Located Load’s cost responsibilities to pay for a portion of system costs, \ncommensurate with the benefits that the Co-Located Load receives from the system, even where it plans to draw \nlittle or no energy from that system.”)."},{"page":26,"startToken":8957,"endToken":9292,"text":"26 \nCommission should reject the proposed Grid Reliance Charge, and instead direct the Transmission \nOwners to adopt the well-established methodology, the “minimum system” method, proposed by \nelectric market design expert Zachary Ming in the attached analysis118 and recalculate the Grid \nReliance Charge using that method. This should be done on a track separate from Interim NITS as \nthe Grid Reliance Charge does not apply to Interim NITS.119 A separate track will provide the \nCommission with sufficient time to evaluate and establish this new minimum charge while \nensuring Interim NITS is implemented immediately to facilitate the timely provision of \ntransmission service. \n1. The Proposed Grid Reliance Charge is Not a Just and Reasonable Rate \nThe proposed Grid Reliance Charge equal to 25.8% of NITS is not just and reasonable \nbecause, as Mr. Ming states, the methodology used to calculate the charge is “not grounded in \nsound ratemaking principles, cost causation principles or … any relevant precedent.”120 \nThe Indicated Transmission Owners assert the proposed Grid Reliance Charge is calculated \n“using a standardized, percentage-based methodology that relies on publicly available FERC Form \nNo. 1 data for PJM Transmission Owners to determine the portion of transmission depreciation \nand operation and maintenance (‘O&M’) expense associated with grid reliance capability.”121 \nHowever, as Mr. Ming explains, the Indicated Transmission Owners “are both excluding \nreasonable costs and including unreasonable costs”122 in the grid reliance capability O&M and \n \n118 See Attachment 1 at 13:1-22:9 (“Mar. 25, 2026 Ming Testimony”). \n119 Indicated TO Initial Brief at 14 (proposing the Grid Reliance Charge for “Eligible Customers taking the new \nContract Demand services.”). See also December 18th Order, 193 FERC ¶ 61,217 (Chang, Comm’r, concurring at \nP 5) (limiting “the need to establish a minimum charge for the Firm and Non-Firm Contract Demand transmission \nservices.”) (emphasis added).  \n120 Mar. 25, 2026 Ming Testimony at 11:19-20. \n121 Indicated TO Initial Brief, Exh. No. PTO-0001 at 19:10-13. \n122 Mar. 25, 2026 Ming Testimony at 11:20 to 12:1."},{"page":27,"startToken":9292,"endToken":9679,"text":"27 \nprovide “very little justification” for doing so.123 For example, the Indicated Transmission Owners’ \npropose to exclude return on rate base and associated income taxes despite “well-established cost-\nof-service-regulation principles recogniz[ing] that the rate of return and taxes are just as much a \ncost of providing service as depreciation.”124  \nIn addition, the Indicated Transmission Owners propose to inappropriately include the “full \ndepreciation costs for a variety of transmission components … that are sized to meet the actual \npeak demand requirements of the PJM system, even though customers paying the [Grid Reliance \nCharge], by definition, do not impose any demand or withdraw any energy from the PJM \nsystem.”125 Not only is this inclusion not based on precedent, but it violates cost causation \nprinciples.126 A Grid Reliance Charge equal to 25.8% of NITS “fails the fundamental requirement \nof cost causation, which is that a customer should pay rates that ‘match, as closely as practicable, \nthe costs to serve’ the customer.”127 \n2. The “Minimum System” Method Produces a Just and Reasonable Grid \nReliance Charge \nThe simplest way to ensure that Co-Located Load pays its “fair share” is to calculate the \nGrid Reliance Charge using the “minimum system” method. As Mr. Ming states, the “minimum \n \n123 Id. at 11:7. \n124 Id. at 12:1-3. \n125 Id. at 12:5-10 (emphasis added). \n126 Id. at 12:16-21 (explaining “the Transmission Owners’ GRC proposal violates cost causation principles by charging \nfor demand-driven transmission costs that co-located customers with zero demand that their service does not cause”). \n127 Antero Res. Corp. v. FERC, 156 F.4th 654, 662 (D.C. Cir. 2025) (quoting Gulf South Pipeline Co., LP v. FERC, \n955 F.3d 1001, 1009 (D.C. Cir. 2020). See also Consol. Edison Co. of N.Y. v. PJM Interconnection, L.L.C., 194 \nFERC ¶ 61,179, at P 63 (2026) (rejecting settlement that “cannot be approved as just and reasonable because it \nleaves in place the de minimis threshold exemption that violates the cost causation principle”); Ill. Commerce \nComm’n v. FERC, 576 F.3d 470, 480 (7th Cir. 2009) (“Cost causation requires that “approved rates reflect to some \ndegree the costs actually caused by the customer who must pay them.”) (quoting Midwest ISO Transmission Owners \nv. FERC, 373 F.3d 1361, 1368 (D.C. Cir. 2004))."},{"page":28,"startToken":9679,"endToken":9935,"text":"28 \nsystem” method is “well-established,”128 is designed to calculate “precisely the set of costs that a \nco-located load that benefits from the existence of wires but imposes no demand on the grid should \nshare,”129 and “has substantial precedent in electricity-sector ratemaking, particularly in \ndistribution cost allocation and rate design”130—including by utility affiliates of Indicated \nTransmission Owners.131  \nUnder the “minimum system” method, Mr. Ming explains a “transmission minimum \nsystem study could estimate the customer-driven share of transmission costs as a fraction of the \ntotal PJM transmission revenue requirement.”132 The “customer-driven share of transmission \ncosts” would be calculated by “determining the minimum size of all electricity system components \n(e.g., poles, conductors, transformers, etc.) that could be used by the utility to recreate its system \nand connect each customer to the grid.”133 This fraction then would “be applied to each PJM \nTransmission Owner’s [NITS] rate to estimate the [Grid Reliance Charge] in dollars per kW-\nyear.”134 Using relatively high-level publicly available data, Mr. Ming illustrates how this method \ncould be implemented.135 \n \n128 Mar. 25, 2026 Ming Testimony at 14:15. \n129 Id. at 13:15-16. \n130 Id. at 17:5-6. \n131 Id. at 16:4-6 (“Many utilities within PJM use minimum system studies in distribution cost allocation, including at \nleast two Indicated PJM Transmission Owners: PPL Electric Utilities Corporation and FirstEnergy Service \nCompany.”) (citations omitted). \n132 Id. at 17:10-11. \n133 Id. at 14:21 to 15:1-2. \n134 Id. at 17:12-14. \n135 Id. at 19:1-20:3."},{"page":29,"startToken":9935,"endToken":10230,"text":"29 \nF. PJM’s Proposal to Require Retail Sale Authorization Will Delay \nInterconnections \nConstellation conditionally opposes PJM’s new requirement for both Interim NITS and the \nContract Demand Services that the Eligible Customer must “provide PJM with ‘an authorization \nor certification from its Relevant Electric Retail Regulatory Authority which affirms that the \nEligible Customer is authorized to provide energy to the Co-Located Load.’”136 As we stated in \nour Clarification Request,137 often a generator will not serve Co-Located Load directly. Rather the \ngenerator will first sell electricity at wholesale to an entity, such as a retail supplier, that will then \nengage in the ultimate retail sale to the Co-Located Load. If the generator is the Eligible Customer, \nit would be unreasonable and cause needless delay to require the generator to have to go to the \nstate commission for a special approval if the load is located in a retail competition state. PJM \nshould require Eligible Customers to provide no more than a showing that the load will ultimately \nbe served by the Transmission Owner or a licensed competitive retail supplier. PJM should not be \nestablishing additional state regulatory hoops (or roadblocks) for Eligible Customers to navigate.  \nG. Requiring Different Feeders is Potentially Unnecessary, Discriminatory and \nServes to Delay the Interconnection of Co-Located Load \nWithout explanation, PJM states, “Eligible Customers taking transmission service on \nbehalf of Co-Located Load, would need to take these different forms of transmission service on \ndifferent feeders, or cables leaving substations, to ultimately serve the Co-Located Load.”138 On \nits face, the multiple feeders requirement appears discriminatory and serves only to further prolong \nor discourage Co-Located Load arrangements and require additional, unnecessary construction of \n \n136 PJM Initial Brief at 19. \n137 Clarification Request at 6-7. \n138 PJM Initial Brief at 66 (emphasis added)."},{"page":30,"startToken":10230,"endToken":10549,"text":"30 \ntransmission lines, which is likely to delay service. The Commission should direct PJM and \nIndicated Transmission Owners to provide sufficient justification and explanation for any \nrequirement to require multiple feeders. To the extent that PJM proposes to require different \nfeeders to allow “selective curtailment” 139  for Co-Located Load receiving non-firm and firm \nservices, the requirement should not apply to Interim NITS. Eligible Customers taking Interim \nNITS take only non-firm service until they are transitioned to full NITS when they only take firm \nservice. \nIV. \nOther Clarifications on Co-Located Loads and the Requirements of Existing Capacity \nResources are Recommended \nLast, we seek clarification of PJM’s and the Indicated Transmission Owners’ filings to \nensure clarity and compliance with the December 18th Order.  \nWe recommend that PJM add to the “Conditions Precedent for Receiving Service” in \nPart XI, Subparts A and B of its Illustrative Tariff140 the requirement that the Eligible Customer \nidentify the Co-located Arrangement, including the Customer Facilities that will be associated with \nthe Co-Located Load for which the Eligible Customer is taking the service. If the Customer \nFacilities include an existing generator, certification that the existing generator supports the request \nshould also be required. This clarification will ensure the Co-Located Load “is physically \nconnected to the facilities of the existing or planned Customer Facility,” consistent with the \nCommission’s mandated definition of Co-Located Load.141 \n \n139 Indicated TO Initial Brief, Ex. No. PTO-0001, at 39:6-10.  \n140 See PJM Initial Brief, Illustrative Tariff, Part XI, Subpart A, § 702.1 (Conditions Precedent for Receiving Service); \nIllustrative Tariff, Part XI, Subpart B, § 710.1 (Conditions Precedent for Receiving Service). \n141 December 18th Order, 193 FERC ¶ 61,217 at P 164 (defining Co-Located Load as “a ‘configuration [that] refers \nto end-use customer load that is physically connected to the facilities of an existing or planned Customer Facility on \nthe Interconnection Customer’s side of the Point of Interconnection to the PJM Transmission System.’”)."},{"page":31,"startToken":10549,"endToken":10863,"text":"31 \nIn addition, we recommend that the Indicated Transmission Owners clarify the rate they \npropose to charge for Firm Contract Demand Service. The Indicated Transmission Owners propose \nthat “the transmission rate for Firm Contract Demand Service will be the same rate as the rate for \nNITS.”142 The Indicated Transmission Owners also propose “the calculation of the transmission \nrate for … Firm Contract Demand Service … will necessarily need to include … the measure of \nthe single coincident peak (‘CP’) for NITS.”143 However, the majority of PJM Transmission \nOwners do not use a single coincident peak (“1-CP”) methodology to calculate the NITS rate. The \nmost common methodology is “5-CP.”144 We request that Indicated Transmission Owners confirm \nthe Firm Contract Demand Service Rate will be equal the applicable Transmission Owner’s NITS \nrate calculated using that Transmission Owner’s CP methodology. \nWe also briefly reassert two of our arguments made on rehearing and in response to PJM’s \ncompliance filings and need not further elaborate here. First, the Commission should clarify that \nit did not intend to require a capacity resource to delist even when it has no obligation to serve the \nCo-Located Load and remains fully capable of serving the grid during capacity emergencies.145 In \nexplaining what Contract Demand Services an Eligible Customer must take under PJM’s proposal, \nPJM states “the portion of Co-Located Generating Facility dedicated to the Co-Located Load \nwould be ineligible to participate in PJM’s capacity market.”146  \n \n142 Indicated TO Initial Brief, Exh. No. PTO-0001 at 26:7-8. \n143 Id. at 26:9-12. \n144 See OATT, Attachment M-2 (ComEd) (using a 5-CP methodology); id. at Attachment M-2 (PECO) (same); \nAttachment M-2 (PSE&G) (same); Mar 25, 2026 Ming Testimony at 13 n.20 (“Utilities that use a 5-CP methodology \ninclude ComEd, PECO, BGE, and PSE&G.”). \n145 Clarification Request at 1-3; Mar. 24 Answer to PJM passim. \n146 PJM Initial Brief at 8."},{"page":32,"startToken":10863,"endToken":11025,"text":"32 \nSecond, the Commission should make clear that the definition of Co-Located Load means \na “configuration [that] refers to end-use customer load that is physically connected to the facilities \nof an existing or planned Customer Facility on the Interconnection Customer’s side of the Point of \nInterconnection to the PJM Transmission System.”147 Alternatively, the Commission should adopt \nthe modifications that Constellation proposed if the Commission revises the definition to replace \n“Point of Interconnection” with “Point of Change in Ownership.”148 \nCONCLUSION \nFor the reasons stated above, Constellation respectfully requests that the Commission \npromptly approve and make Interim NITS effective October 1, 2026, reject PJM’s and the \nIndicated Transmission Owners’ attempts to restrict, delay, or otherwise discourage new \n \n147 December 18th Order, 193 FERC ¶ 61,217 at P 1 n.3. See also Constellation 60-Day Compliance Filing Protest at \n2-8; Constellation 30-Day Compliance Filing Protest passim. \n148 See Constellation 60-Day Compliance Filing Protest at 7-8; Constellation 30-Day Compliance Filing Protest at 5-\n6."},{"page":33,"startToken":11025,"endToken":11163,"text":"33 \ntransmission services in contradiction with the December 18th Order, and grant the requested \nclarifications. \n \n \n \n \n \n \n \n    Respectfully submitted, \n \n \n \n \n \n \n \n    /s/ Paul F. Wight \n \n \n \nMarch 25, 2026 \nCarrie Hill Allen \nSr. Vice President & Deputy General Counsel \nSeth Lucia \nAssistant General Counsel \nConstellation Energy Generation, LLC \n250 Massachusetts Ave. NW, Suite 760 \nWashington, D.C. 20001 \ncarrie.allen@constellation.com \nseth.lucia@constellation.com \n  \nChristopher A. Wilson \nManaging Director, Federal Regulatory Affairs \nConstellation Energy Generation, LLC \n250 Massachusetts Ave. NW, Suite 760 \nWashington, D.C. 20001 \n202-347-7500 \nFERCe-filings1@constellation.com \n \nPaul F. Wight \nCarolyn E. Clarkin \nDLA Piper LLP (US) \n500 Eighth Street NW \nWashington, D.C. 20004 \n703-773-4058 \npaul.wight@us.dlapiper.com  \ncarolyn.clarkin@us.dlapiper.com  \n \nSophia Browning \n4365 Executive Drive \nSuite 1100 \nSan Diego, CA 92121 \n858-677-1455 \nsophia.browning@us.dlapiper.com \n \nCounsel for Constellation Energy \nGeneration, LLC"},{"page":34,"startToken":11163,"endToken":11241,"text":"CERTIFICATE OF SERVICE \nI hereby certify that I have on this 25th day of March, 2026, caused to be served a copy of \nthe foregoing upon all parties on the service lists in these proceedings in accordance with the \nrequirement of Rule 2010 of the Commission’s Rules of Practice and Procedure, 18 C.F.R. \n§ 385.2010 (2025). \n/s/ Sophia Browning \n \n \nSophia Browning \n4365 Executive Drive \nSuite 1100 \nSan Diego, CA 92121 \n858-677-1455 \nsophia.browning@us.dlapiper.com"},{"page":35,"startToken":11241,"endToken":11247,"text":"ATTACHMENT 1 \n \nTESTIMONY OF ZACHARY MING"},{"page":36,"startToken":11247,"endToken":11315,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \nPJM Interconnection, L.L.C., et al. \n \n \nLarge Loads Co-Located at Generating \nFacilities \n \n \nConstellation Energy Generation, LLC \n \nv. \n \nPJM Interconnection, L.L.C. \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n \n \nDocket No. EL25-49-000 \nDocket No. EL25-49-001 \n \n \nDocket No. AD24-11-000 \n \n \n \nDocket No. EL25-20-000 \n(Consolidated) \n \n \nTestimony of Zachary Ming \n Partner \nEnergy and Environmental Economics, Inc. (“E3”) \n \n \nOn behalf of \nConstellation Energy Generation, LLC (“Constellation”) \n \nMarch 25, 2026"},{"page":37,"startToken":11315,"endToken":11343,"text":"2 \nTable of Contents \n1 \nIntroduction .............................................................................................. 3 \n2 \nBackground ............................................................................................... 6 \n3 \nEvaluation of PJM Transmission Owners’ GRC Proposal .................... 10 \n4 \nE3 GRC Proposal ................................................................................... 14 \n5 \nRecommendations & Summary .............................................................. 24"},{"page":38,"startToken":11343,"endToken":11537,"text":"3 \nConstellation \n1 \n \n2 \nTransmission Tariffs for Co-Located Load – Grid Reliance Charge \n3 \n \n4 \n \n5 \nTestimony of Zachary Ming, Partner, Energy and Environmental Economics, Inc. \n6 \n(“E3”) \n7 \n1 Introduction \n8 \nQ1. \nPLEASE STATE YOUR NAME, OCCUPATION, AND BUSINESS \n9 \nADDRESS. \n10 \nA1. \nMy name is Zachary Ming. My current position is Partner at Energy and \n11 \nEnvironmental Economics (“E3”). My business address is 44 Montgomery Street \n12 \nSuite 1250, San Francisco, California 94104. \n13 \nQ2. \nPLEASE STATE ON WHOSE BEHALF YOU ARE FILING TESTIMONY. \n14 \nA2. \nI am filing this testimony as an independent expert, and it represents my own \n15 \npositions and perspectives. Constellation compensated for my testimony, but my \n16 \ncompensation did not depend on my conclusions. \n17 \nQ3. \nARE YOU THE SAME ZACHARY MING THAT PREVIOUSLY \n18 \nSUBMITTED TESTIMONY IN THIS DOCKET? \n19 \nA3. \nYes. I am the same Zachary Ming who previously submitted testimony in this \n20 \ndocket regarding the appropriate rate designs that should be applied to different \n21 \nconfigurations of co-located load.1 \n22 \n \n1 Testimony of Zachary Ming, on behalf of Constellation Energy Generation, LLC, Docket Nos. EL25-49-\n000, AD24-11-000, and EL25-20-000 (filed Apr. 23, 2025)."},{"page":39,"startToken":11537,"endToken":11922,"text":"4 \nQ4. \nARE YOUR QUALIFICATIONS THE SAME AS THOSE SET FORTH IN \n1 \nYOUR PRIOR TESTIMONY IN THESE DOCKETS? \n2 \nA4. \nMy qualifications are the same as those set forth in my prior testimony in this docket \n3 \nand include testimony before FERC and multiple state and provincial utility \n4 \ncommissions. Since then, I have additionally testified before the Puerto Rico \n5 \nEnergy Board on the topic of rate design.2 \n6 \nQ5. \nPLEASE PROVIDE A SUMMARY OF YOUR TESTIMONY. \n7 \nA5. \nMy testimony outlines that the concept of a Grid Reliance Charge (“GRC”) for co-\n8 \nlocated load is just and reasonable. However, I show that the Indicated PJM \n9 \nTransmission Owners’3 (the “Transmission Owners”) proposal for calculating the \n10 \nGRC is not grounded in sound ratemaking principles, violates cost causation \n11 \nprinciples, and is unreasonably high. Finally, I propose an alternative methodology \n12 \nto calculate the GRC that is based on both sound theory and precedent, and I provide \n13 \na reasonable range for the value of this charge.  \n14 \n \n2 NEPR-AP-2023-0003. \n3 The Indicated PJM Transmission Owners are: American Electric Power Service Corporation on behalf of \nits affiliates, Appalachian Power Company, Indiana Michigan Power Company, Kentucky Power \nCompany, Kingsport Power Company, Ohio Power Company, Wheeling Power Company, AEP \nAppalachian Transmission Company, AEP Indiana Michigan Transmission Company, AEP Kentucky \nTransmission Company, AEP Ohio Transmission Company, and AEP West Virginia Transmission \nCompany; The Dayton Power and Light Company d/b/a AES Ohio; Dominion Energy Services, Inc. on \nbehalf of Virginia Electric and Power Company d/b/a Dominion Energy Virginia; Duke Energy Business \nServices, LLC for Duke Energy Kentucky, Inc. and Duke Energy Ohio, Inc.; Duquesne Light Company; \nEast Kentucky Power Cooperative; Exelon Corporation on behalf of its affiliates Atlantic City Electric \nCompany, Baltimore Gas and Electric Company, Commonwealth Edison Company, Commonwealth \nEdison Company of Indiana, Inc., Delmarva Power & Light Company, PECO Energy Company (“PECO”), \nand Potomac Electric Power Company; FirstEnergy Service Company, on behalf of its affiliates American \nTransmission Systems, Incorporated, Jersey Central Power & Light Company, Mid-Atlantic Interstate \nTransmission LLC, The Potomac Edison Company, Monongahela Power Company, Keystone Appalachian \nTransmission Company, and Trans-Allegheny Interstate Line Company (collectively, the “FirstEnergy \nCompanies”); PPL Electric Utilities Corporation; Public Service Electric and Gas Company (“PSE&G”); \nRockland Electric Company; and the Southern Maryland Electric Cooperative (“SMECO”)."},{"page":40,"startToken":11922,"endToken":12039,"text":"5 \nQ6. \nPLEASE PROVIDE AN OUTLINE OF YOUR TESTIMONY. \n1 \nA6. \nMy testimony is organized as follows:  \n2 \n• In Section 2, I provide the background on the Grid Reliance Charge (“GRC”), \n3 \nincluding its intended purpose, my assessment of the charge, and how it relates \n4 \nto customers’ reliance on the grid; \n5 \n• In Section 3, I demonstrate why the Transmission Owners’ proposal for the \n6 \ncalculation and value of the GRC is unjust and unreasonable; \n7 \n• In Section 4, I outline a theoretically sound and fundamentals-based proposal \n8 \nto calculate the GRC and provide a reasonable range for the value of this charge; \n9 \nand \n10 \n• In Section 5, I summarize my arguments and recommendations.  \n11"},{"page":41,"startToken":12039,"endToken":12245,"text":"6 \n2 Background \n1 \nQ7. \nON WHAT BASIS DO REGULATORS TYPICALLY ALLOCATE \n2 \nELECTRICITY SYSTEM COSTS? \n3 \nA7. \nIn electric system ratemaking, regulators primarily allocate costs based on “cost \n4 \ncausation” principles. In other words, regulators allocate costs based on how \n5 \ncustomers cause the utility to incur costs. As the National Association of Regulatory \n6 \nUtility Commissioners (“NARUC”) explains, cost allocation should “attempt to \n7 \ndetermine what, or who, is causing costs to be incurred by the utility.”4 Broadly \n8 \nspeaking, cost drivers are classified into three categories: energy, demand, and \n9 \ncustomer. Energy-classified costs are driven by total energy consumption of \n10 \ncustomers. Demand-classified costs are driven by peak demand of all customers. \n11 \nCustomer-classified costs are driven by the existence of the system and usually \n12 \nscale with the number of customers. In other words, customer-classified costs are \n13 \ncosts that the utility incurs regardless of the energy or demand imposed by its \n14 \ncustomers. \n15 \nQ8. \nHOW ARE TRANSMISSION COSTS TYPICALLY ALLOCATED TO \n16 \nCUSTOMERS? \n17 \nA8. \nBecause transmission facilities are built to serve peak demand conditions, \n18 \ncustomers are typically allocated transmission costs on the basis of their \n19 \n \n4 NARUC, Electric Utility Cost Allocation Manual (Jan. 1992), page 38."},{"page":42,"startToken":12245,"endToken":12527,"text":"7 \ncontribution to peak demand. This is the standard approach in many markets \n1 \nincluding PJM,5 ISO New England,6 MISO,7 and ERCOT.8 \n2 \nCustomer demand is typically measured using a coincident peak (“CP”) \n3 \nmethodology. In other words, the relevant billing determinant is the customer’s load \n4 \nat the time of the applicable system or zonal peak load. Depending on the system \n5 \nor region, customer demand may be based on a single coincident peak (“1-CP”) or \n6 \non multiple coincident peaks across different months (e.g., “5-CP” or “12-CP”). \n7 \nThe same demand-based methodology is used by Indicated PJM \n8 \nTransmission Owners (the “Transmission Owners”) today, although the specific \n9 \ncoincident-peak methodology varies by transmission owner. For example, First \n10 \nEnergy9 uses a 1-CP approach, Baltimore Gas and Electric10 uses a 5-CP approach, \n11 \nand Dominion11 uses a 12-CP approach. \n12 \nQ9. \nDESCRIBE THE GRID RELIANCE CHARGE (“GRC”) AS PROPOSED \n13 \nBY THE PJM TRANSMISSION OWNERS. \n14 \nA9. \nThe Transmission Owners propose a new GRC that would assign costs not on the \n15 \nbasis of contribution to peak demand but rather on the quantity of demand \n16 \nconsumed directly from a generator in a co-located configuration. \n17 \n \n5 https://www.pjm.com/markets-and-operations/billing-settlements-and-credit/theo-plc-and-nspl. \n6 https://www.iso-ne.com/static-assets/documents/100026/2025_06_nlcr_final.pdf. \n7 https://docs.misoenergy.org/miso12-legalcontent/Schedule_09_-\n_Network_Integration_Transmission_Service.pdf. \n8 https://www.ercot.com/mktinfo/data_agg/4cp. \n9 https://www.firstenergycorp.com/content/dam/customer/Customer%20Choice/Files/PA/tariffs/fe-pa-\nretail-tariff.pdf . \n10 https://supplier.bge.com/electric/load/plcs.asp. \n11 https://www.ferc.gov/sites/default/files/2020-05/E-7_45.pdf."},{"page":43,"startToken":12527,"endToken":12824,"text":"8 \nQ10. WHAT LEVEL OF DEMAND DO CUSTOMERS THAT PAY THE GRC \n1 \nIMPOSE ON THE TRANSMISSION SYSTEM? \n2 \nA10. Zero, by definition. The GRC, as proposed by the Transmission Owners, applies \n3 \nonly to load that is not withdrawn from the transmission system via Firm or Non-\n4 \nFirm Contract Demand Service. Therefore, load that pays the GRC definitionally \n5 \nimposes zero demand on the PJM transmission system. \n6 \nQ11. DESCRIBE THE RATIONALE OF THE GRC. \n7 \nA11. The Transmission Owners propose a GRC as a new charge “designed to reflect the \n8 \ncosts of using the transmission system to deliver black start and regulation \n9 \nservices.”12 The GRC is intended to capture some contribution toward the cost of \n10 \nthe physical wires that are used to deliver black start, regulation, and other \n11 \nsynchronization support to co-located loads. The GRC is, in essence, the type of \n12 \n“minimum transmission service charge” Commissioner Chang suggested PJM \n13 \nshould include in its new transmission tariff to protect against cost shifts when co-\n14 \nlocated customers with minimal, or even zero, demand remain reliant on the grid.13 \n15 \nQ12. DO YOU AGREE THAT SOME FORM OF GRC IS APPROPRIATE? \n16 \nA12. Yes, the basic concept of the GRC is reasonable. Even though the ancillary services \n17 \nthat a co-located load consumes do not impose any incremental wires cost on the \n18 \nPJM system (because delivery of these services does not result in any withdrawal \n19 \nof energy), they nevertheless must be delivered over the wires of the PJM \n20 \n \n12 Initial Brief and Joint Responses of the Indicated PJM Transmission Owners to Paper Hearing Questions, \nDocket Nos. EL25-49-000, EL25-49-001, AD24-11-000, and EL25-20-000 (filed Feb. 23, 2026), page 14. \n13 https://www.ferc.gov/news-events/news/e-1-commissioner-changs-concurrence-pjm-co-location."},{"page":44,"startToken":12824,"endToken":12859,"text":"9 \ntransmission system. As a result, it is reasonable for co-located load customers to \n1 \nmake some contribution to the cost of wires of the PJM system in the form of a \n2 \nGRC. \n \n3"},{"page":45,"startToken":12859,"endToken":13113,"text":"10 \n3 Evaluation of PJM Transmission Owners’ GRC Proposal \n1 \nQ13. PLEASE DESCRIBE THE GRID RELIANCE CHARGE (“GRC”) \n2 \nPROPOSED BY THE PJM TRANSMISSION OWNERS. \n3 \nA13. At a high level, the Transmission Owners propose to calculate a GRC that they say \n4 \nis “designed to recover the costs of delivering ancillary services, including the \n5 \ndelivery of black start and regulation, and providing synchronization and grid \n6 \nreliance support … regardless of whether they withdraw energy from the grid.”14 \n7 \nThe Transmission Owners propose to calculate the GRC based on a fraction of the \n8 \ntotal transmission revenue requirement, functionally yielding a charge that is \n9 \napplied to co-located load that is a fraction of the NITS rate. They propose that this \n10 \nrate be applied to the gross peak demand of co-located load that is not served \n11 \nthrough Firm Contract Demand. \n12 \nQ14. WHAT CALCULATION METHODOLOGY DO THE TRANSMISSION \n13 \nOWNERS PROPOSE FOR THE GRC? \n14 \nA14. The Transmission Owners identify a portion of costs that they assert are “associated \n15 \nwith grid reliance capability” and use public FERC Form 1 data to calculate these \n16 \ncosts as a fraction of the total PJM transmission revenue requirement. Specifically, \n17 \nthe Transmission Owners include a portion of transmission depreciation and \n18 \noperation and maintenance expenses, while excluding costs related to amortization \n19 \n \n14 Direct Joint Testimony of Peter Blazunas, Lance Schafer, and Hanhan Hammer (Concentric), Exhibit No. \nPTO-0001 at Page 17, Docket Nos. EL25-49-000, EL25-49-001, AD24-11-000, and EL25-20-000 (filed \nFeb. 23, 2026)."},{"page":46,"startToken":13113,"endToken":13367,"text":"11 \nand general-plant depreciation and Administrative and General expenses. Dividing \n1 \nthe sum of these costs by the total PJM transmission revenue yields a GRC charge \n2 \nequal to 25.8% of the NITS rate. \n3 \nQ15. WHAT BASIS DO THE TRANSMISSION OWNERS PROVIDE FOR \n4 \nINCLUDING AND EXCLUDING PARTICULAR COSTS IN THEIR \n5 \nPROPOSED GRC METHODOLOGY? \n6 \nA15. The Transmission Owners provide very little justification for which costs are \n7 \nincluded or excluded from the GRC and why. For example, the entirety of their \n8 \njustification for including depreciation and operations and maintenance (“O&M”) \n9 \ncosts appears to be their statement that “depreciation reflects the annualized \n10 \nconsumption of the transmission infrastructure that enables customers to rely on the \n11 \ngrid, while O&M reflects the ongoing expense required to keep that infrastructure \n12 \nfunctional.”15 They then further state that they exclude return on rate base and \n13 \nassociated income taxes to produce a “conservative result focused on cost recovery \n14 \nrather than investment return.”16  \n15 \nQ16. WHAT IS YOUR ASSESSMENT OF THE TRANSMISSION OWNERS’ \n16 \nGRC PROPOSAL? \n17 \nA16. The Transmission Owners’ proposal to include certain costs and exclude others is \n18 \nnot grounded in sound ratemaking principles, cost causation principles or, to my \n19 \nknowledge, any relevant precedent. In important regards, they are both excluding \n20 \n \n15 Direct Joint Testimony of Peter Blazunas, Lance Schafer, and Hanhan Hammer (Concentric), Exhibit No. \nPTO-0001 at Page 24, Docket Nos. EL25-49-000, EL25-49-001, AD24-11-000, and EL25-20-000 (filed \nFeb. 23, 2026). \n16 Id."},{"page":47,"startToken":13367,"endToken":13622,"text":"12 \nreasonable costs and including unreasonable costs. First, well-established cost-of-\n1 \nservice-regulation principles recognize that the rate of return and taxes are just as \n2 \nmuch a cost of providing service as depreciation.17 The Transmission Owners do \n3 \nnot substantiate why these costs are excluded other than to produce a \n4 \n“conservative” outcome. Second, the Transmission Owners attribute the full \n5 \ndepreciation costs for a variety of transmission components (i.e., towers and \n6 \nfixtures, poles and fixtures, overhead conductors, etc.) that are sized to meet the \n7 \nactual peak demand requirements of the PJM system, even though customers \n8 \npaying the GRC, by definition, do not impose any demand or withdraw any energy \n9 \nfrom the PJM system (if they did they would be paying either Firm Contract \n10 \nDemand Service or Non-Firm Contract Demand Service). Put differently, the PJM \n11 \nsystem could be sized to a much smaller level and still deliver the ancillary services \n12 \nthat co-located customers consume.    \n13 \nQ17. DOES THE TRANSMISSION OWNERS’ GRC PROPOSAL ADHERE TO \n14 \nCOST CAUSATION PRINCIPLES? \n15 \nA17. No. The Transmission Owners’ GRC proposal assigns GRC customers a share of \n16 \nthe costs of a transmission system sized to serve PJM’s peak demand, even though \n17 \nthese customers, by definition, impose zero demand on that system. Therefore, the \n18 \nTransmission Owners’ GRC proposal violates cost causation principles by charging \n19 \nfor demand-driven transmission costs that co-located customers with zero demand \n20 \nthat their service does not cause. \n21 \n \n17 https://www.ferc.gov/formula-rates-electric-transmission-proceedings-key-concepts-and-how-participate"},{"page":48,"startToken":13622,"endToken":13832,"text":"13 \nQ18. ARE ALL OTHER ASPECTS OF THE TRANSMISSION OWNERS’ RATE \n1 \nDESIGN PROPOSAL CLEAR? \n2 \nA18. No. On one hand, the Transmission Owners’ rate design proposal states that “the \n3 \ntransmission rate for Firm Contract Demand Service will be the same rate as the \n4 \nrate for NITS.”18 On the other hand, the Transmission Owners’ proposal states that \n5 \n“the calculation of the [Firm Contract Demand Service] rate will necessarily need \n6 \nto include … the measure of the single coincident peak (“CP”) for NITS.” 19 \n7 \nHowever, the majority of PJM Transmission Owners do not use a single coincident \n8 \npeak (“1-CP”) methodology to calculate the NITS rate. The most common \n9 \nmethodology is “5-CP.”20 Thus it is not clear if Transmission Owners are proposing \n10 \nthat the Firm Contract Demand Service Rate be calculated on the basis of its 1-CP \n11 \nshare or whether the Firm Contract Demand Service Rate would simply be equal to \n12 \nthe NITS rate. If the latter, the Transmission Owners should clarify why they \n13 \nrepeatedly mention 1 CP throughout their filing in both explanations and example \n14 \ncalculations. \n \n15 \n \n18 Concentric Testimony, page 26. \n19 Id. \n20 Utilities that use a 5-CP methodology include ComEd, PECO, BGE, and PSE&G."},{"page":49,"startToken":13832,"endToken":14100,"text":"14 \n4 E3 GRC Proposal \n1 \nQ19. WHAT IS THE APPROPRIATE BASIS FOR DETERMINING A GRID \n2 \nRELIANCE CHARGE (“GRC”)? \n3 \nA19. Customers subject to the GRC are, by definition, not drawing power from the PJM \n4 \nnetwork in order to serve their load. If they were drawing power from the system \n5 \nto serve their load, they would be required to purchase Firm or Non-Firm Contract \n6 \nDemand Service. In this sense, co-located load customers receive ancillary services \n7 \nfrom the existence of the wires that synchronize them to the rest of the PJM system.  \n8 \nHowever, PJM’s wires are sized and built to serve PJM’s actual peak \n9 \ndemand. That creates a cost causation distinction. The incremental costs of sizing \n10 \nthe PJM system to serve actual peak demand should reasonably be borne by \n11 \ncustomers who cause this demand, while customers benefitting from the existence \n12 \nof the wires should be responsible for their share of costs that would be necessary \n13 \nto construct the wires without sizing them to meet peak demand. Within the context \n14 \nof electricity system ratemaking, there is a well-established methodology designed \n15 \nto calculate precisely the costs of constructing wires to connect all customers, i.e., \n16 \ncustomer-driven costs. It is called the “minimum system” method.  \n17 \nQ20. WHAT IS A “MINIMUM SYSTEM”? \n18 \nA20. A “minimum system” is a theoretical electricity system designed only to connect \n19 \neach customer and deliver a de minimis amount of power. An analyst can calculate \n20 \nthe cost of such a system by determining the minimum size of all electricity system \n21"},{"page":50,"startToken":14100,"endToken":14345,"text":"15 \ncomponents (e.g., poles, conductors, transformers, etc.) that could be used by the \n1 \nutility to recreate its system and connect each customer to the grid.  \n2 \nQ21. IS THE MINIMUM SYSTEM METHOD RELATED TO COST \n3 \nCAUSATION PRINCIPLES? \n4 \nA21. Yes. The minimum system method is specifically designed to identify the portion \n5 \nof system costs that are customer-driven rather than demand- or energy-driven. It \n6 \nanswers the question of what it would cost to construct a system to connect all \n7 \ncustomers before the system is upsized to serve actual peak demand or energy \n8 \nusage. That is precisely relevant to the question at hand. Co-located load subject to \n9 \nthe GRC benefits from the existence of wires but, by definition, does not impose \n10 \nany demand on the PJM system. The minimum system framework therefore \n11 \nprovides the appropriate cost causation-aligned methodology for calculating the \n12 \nGRC. \n13 \nQ22. DOES THE MINIMUM SYSTEM FRAMEWORK HAVE PRECEDENT IN \n14 \nELECTRICITY SECTOR RATEMAKING? \n15 \nA22. Yes. The minimum system framework has substantial precedent in electricity-\n16 \nsector ratemaking, particularly in distribution cost allocation and rate design. It is \n17 \nwidely used to identify the portion of system costs that are customer-driven; that is, \n18 \ncosts incurred because the customer is connected to the system. NARUC recognizes \n19 \nthis framework, referring to it as the “minimum-size method,” as one of the “[t]wo \n20 \nmethods … used to determine the … customer components of distribution \n21"},{"page":51,"startToken":14345,"endToken":14618,"text":"16 \nfacilities.” 21 These costs are distinct from the additional costs of facilities needed \n1 \nto serve higher levels of demand that should be appropriately allocated based on \n2 \nhow much demand each customer is drawing from the network. \n3 \nMany utilities within PJM use minimum system studies in distribution cost \n4 \nallocation, including at least two Indicated PJM Transmission Owners: PPL \n5 \nElectric Utilities Corporation22 and FirstEnergy Service Company.23 \n6 \nQ23. IS THE MINIMUM SYSTEM METHOD TYPICALLY USED IN THE \n7 \nCONTEXT OF THE TRANSMISSION SYSTEM AND WHY? \n8 \nA23. The minimum system method is generally not used in the context of transmission \n9 \nsystem cost allocation and rate design. Transmission system components are \n10 \ngenerally much larger and more costly relative to a minimum system. This \n11 \ninherently shrinks the quantity of costs that could be customer-classified and makes \n12 \nthe need to perform this step less important. Additionally, transmission \n13 \ncustomers—whether large individual loads or aggregations of smaller loads—have \n14 \ntraditionally imposed a meaningful level of demand on the system, meaning there \n15 \nhas not been a significant need to allocate a portion of transmission system costs to \n16 \ncustomers that are not actually drawing power from the grid. Against this backdrop, \n17 \nutilities typically allocate transmission costs largely on the basis of demand. In \n18 \neffect, this classifies 0% of transmission costs to the “customer” cost driver. \n19 \n \n21 NARUC, Electric Utility Cost Allocation Manual (Jan. 1992), page 90. \n22 https://www.pplelectric.com/site/-/media/ppl-jss-app/assets/Home/Landing-Pages/Public-Utility-\nCommission/PDFs/PPL--2025-Rate-Case--Volume-XI-PPL-Electric-Exhibit-BR2.pdf. \n23 https://www.puc.pa.gov/pcdocs/1822988.pdf."},{"page":52,"startToken":14618,"endToken":14870,"text":"17 \nQ24. IS THE MINIMUM SYSTEM METHOD APPROPRIATE IN THE \n1 \nCONTEXT OF THE GRC AND WHY? \n2 \nA24. Yes. While the minimum system method is typically not used in the context of \n3 \ntransmission cost allocation or ratemaking, the cost of the minimum system is \n4 \nprecisely the set of costs that a co-located load that benefits from the existence of \n5 \nwires but imposes no demand on the grid should share. The costs of the minimum \n6 \nsystem therefore provide a theoretically-sound basis to calculate the GRC. \n7 \nQ25. HOW CAN THE RESULTS OF A MINIMUM SYSTEM STUDY BE USED \n8 \nTO ESTIMATE THE GRC? \n9 \nA25. A transmission minimum system study could estimate the customer-driven share of \n10 \ntransmission costs as a fraction of the total PJM transmission revenue requirement. \n11 \nThis fraction could then be applied to each PJM Transmission Owner’s Network \n12 \nIntegration Transmission Service (“NITS”) rate to estimate the GRC in dollars per \n13 \nkW-year. For example, if the minimum system study indicates that 5% of \n14 \ntransmission costs are customer-driven, the GRC would be 5% of the applicable \n15 \nNITS rate. \n16 \nQ26. WHAT RANGES DO MINIMUM SYSTEM STUDIES GENERALLY \n17 \nYIELD FOR THE FRACTION OF COSTS THAT ARE CUSTOMER-\n18 \nDRIVEN? \n19 \nA26. As stated previously, utilities typically only use the minimum system method to \n20 \nclassify distribution costs, not transmission costs, to the “customer” cost driver. \n21 \nWhile these results vary by utility, a typical range of results may show that between \n22"},{"page":53,"startToken":14870,"endToken":15166,"text":"18 \n30% – 50% of distribution costs are driven by the number of customers on the \n1 \nsystem. For example, a recent filing from PPL shows that 43% of distribution costs \n2 \nwere categorized to the customer category using the minimum system method.24 \n3 \nQ27. HOW WOULD THESE RESULTS CHANGE IF APPLIED TO THE \n4 \nTRANSMISSION SYSTEM INSTEAD OF THE DISTRIBUTION SYSTEM? \n5 \nA27. Applying the minimum system method to the transmission system would \n6 \ndefinitionally yield a smaller fraction than the distribution-level values discussed \n7 \nabove. This is because transmission system components are much larger than \n8 \ndistribution system components, so the minimum system is a smaller fraction of \n9 \ntotal transmission system costs. \n10 \nAs discussed above, no utilities that I am aware of classify any transmission \n11 \ncosts to the customer cost driver, meaning they are implicitly assuming a minimum \n12 \nsystem value of 0% for the transmission system. Thus, it is reasonable to assume \n13 \nthat a proper minimum system study when applied to the transmission system \n14 \nwould yield a value significantly lower than 25.8%. \n15 \n \n24 https://www.pplelectric.com/site/-/media/ppl-jss-app/assets/Home/Landing-Pages/Public-Utility-\nCommission/PDFs/PPL--2025-Rate-Case--Volume-XI-PPL-Electric-Exhibit-BR2.pdf, pages 10-12. The \n43% distribution-system-wide value is a cost-weighted average across the asset categories included in \nPPL’s minimum-size study. Customer-categorized minimum-system costs total $2,220,555,755, consisting \nof primary and secondary poles ($521,359,795 + $249,684,941), overhead conductors ($306,415,614 + \n$56,927,365), underground conductors and conduit ($276,309,292 + $10,958,340), and line transformers \n($798,900,408). Total plant costs for those same asset categories equal $5,164,745,630 ($1,167,387,366 + \n$948,692,824 + $897,426,932 + $2,151,238,508). The resulting ratio is 43.0%."},{"page":54,"startToken":15166,"endToken":15381,"text":"19 \nQ28. CAN YOU ESTIMATE MINIMUM SYSTEM COSTS AS A FRACTION OF \n1 \nTHE PJM TRANSMISSION SYSTEM? \n2 \nA28. Using publicly available data, I estimate that a minimum transmission system in \n3 \nPJM would constitute approximately 6% of the costs of the actual PJM transmission \n4 \nsystem. This estimate is based on an approximate count of assets in the PJM \n5 \ntransmission system for four major categories: overhead conductors, transmission \n6 \npoles, transmission towers, and transmission substations. \n7 \nTo approximate cost of PJM’s existing (not minimum) system, I \n8 \ndisaggregated the component counts by voltage level and multiplied by their unit \n9 \ncosts. The result is an approximate cost to build a “new” PJM system using the \n10 \nexisting mix of components, allowing for an apples-to-apples comparison to a \n11 \n“new” minimum system. It is not intended to replicate total transmission plant-in-\n12 \nservice across all PJM transmission owners. \n13 \nTo approximate the cost of the minimum system, I identified the relevant \n14 \nminimum system components and associated unit costs and applied them to the \n15 \ncomponent count estimate. In effect, the analysis assumes the same categories and \n16 \ncount of components. The assumptions, calculations, and results from my high-\n17 \nlevel minimum system study for PJM’s transmission system are shown in Table 1. \n18"},{"page":55,"startToken":15381,"endToken":15845,"text":"20 \nTable 1: PJM Minimum System Study Assumptions, Calculations, and Results \n1 \n \n \nOverhead \nConductors \nPoles \nTowers \nSubstations \nTotal \n \n(1) Component \nCount Estimate25 \n~265,000 \nconductor miles \n~365,000 \npoles \n~210,000 \ntowers \n~8,000 \nsubstations \n \n \nMinimum System \n \n \n \n \n \n \n(2) Minimum System \nComponent \n267 kcmil ACSR \nDistribution \nwood pole \nDistribution \nwood pole \n15 kVA \ntransformer \n \n \n(3) Minimum System \nUnit Cost26 \n$7,500/mile \n$7,000/pole \n$7,000/pole \n$15,000/transf.  \n(1) x (3) = (4) Minimum System \nCost \n$2.0 billion \n$2.6 billion \n$1.5 billion \n$0.1 billion \n$6.2 billion \n Existing System  \n  \n  \n  \n  \n  \n (5) Existing System \nComponent \n336-2,156 kcmil \nACSR \nTransmission \nsteel pole \nTransmission \nsteel tower \n<69/69 kV-\n500/765 kV \ntransformer \n \n (6) \nExisting System \nUnit Cost (wtd. \naverage)27 \n$70,000/mile \n$80,000/pole \n$125,000/tower \n$3,000,000 \n/transformer \n \n(1) x (6) = (7) Existing System \nCost \n$18.6 billion \n$29.2 billion \n$26.3 billion \n$24.0 billion \n$98.1 billion \n \nMinimum Study Result \n  \n  \n  \n  \n(4) / (7) = (8) Minimum System \nFraction (%) \n11% \n9% \n6% \n1% \n6% \nAs shown in the table above, this calculation yields a minimum system that \n2 \nis approximately 6% of the cost of the actual PJM system. \n3 \n \n25 Component counts are high-level estimates. PJM reports 88,333 miles of transmission lines in its system \n(https://www.pjm.com/-/media/DotCom/about-pjm/newsroom/fact-sheets/pjm-at-a-glance.pdf). Assuming \nthree phase conductors per line-mile yields about 265,000 conductor-miles. Based on the system’s voltage \nprofile and my experience, I assumed a 50/50 split of line-miles between pole-supported and tower-\nsupported lines and spacing of about eight poles per mile and five towers per mile, respectively. The \nsubstation count was estimated using geographic information system (“GIS”) data for PJM substations. \n26 Minimum-system unit costs are simplifying assumptions intended to reflect the least-cost configuration \nneeded to maintain a de minimis level of service. For conductors, I selected the smallest ACSR conductor \nlisted in MISO’s public cost guide since PJM does not publish their own transmission cost guide \n(https://cdn.misoenergy.org/20240501%20PSC%20Item%2004%20MISO%20Transmission%20Cost%20E\nstimation%20Guide%20for%20MTEP24632680.pdf). For poles and towers, I assumed a distribution pole \nstructure; the $6,500 unit cost reflects my experience, informed by public benchmark pricing for \ndistribution wood-pole installations. The substation unit cost similarly reflects my judgment regarding a \nminimal 15 kVA configuration sufficient to keep the load connected and synchronized with the grid. \n27 Existing system unit costs are weighted averages. I first allocated the estimated PJM system components \nacross voltage classes and selected a representative standard asset type for each class. For these unit cost \nestimates, I also used MISO’s public cost guide. The table values reflect the weighted average of those \nvoltage-specific unit costs across the estimated component mix by asset type."},{"page":56,"startToken":15845,"endToken":16124,"text":"21 \nQ29. HOW SHOULD AN ACTUAL MINIMUM TRANSMISSION SYSTEM \n1 \nVALUE BE CALCULATED FOR APPLICATION TO THE GRC? \n2 \nA29. While the results of my calculation above are reasonable, they are based on \n3 \nrelatively high-level publicly available data. For specific application to the GRC, \n4 \nthe Transmission Owners should perform a minimum system study for the PJM \n5 \ntransmission system using more detailed information about their system. \n6 \nQ30. HOW WOULD YOU ASSESS WHETHER THE RESULTS OF ANY PJM-\n7 \nSPECIFIC MINIMUM SYSTEM STUDY ARE REASONABLE? \n8 \nA30. As discussed above, there is little to no precedent for applying the minimum system \n9 \nmethod to the transmission system, so there is relatively little available data upon \n10 \nwhich to benchmark results. Nonetheless, it is the case that most utilities implicitly \n11 \nclassify transmission costs 100% to demand and 0% to customer. This implicitly \n12 \nmeans that something significantly lower than the 25.8% charge proposed by the \n13 \nTransmission Owners. It is also definitionally true that applying the minimum \n14 \nsystem to the transmission system should yield a smaller fraction than if applying \n15 \nit to the distribution system. \n16 \nBased on this information and my calculation estimate above, a minimum \n17 \nsystem that yields between 2% to 10% of actual system costs is reasonable based \n18 \non the sheer differences of minimum components relative to the large towers and \n19 \nconductors that constitute the PJM system. Any result higher than 10% would be \n20 \nunreasonable and should call into question the methodological approach or \n21 \nassumptions used in the study, with demand-driven transmission costs likely being \n22 \nimproperly assigned to customers that do not cause them.  \n23"},{"page":57,"startToken":16124,"endToken":16443,"text":"22 \nQ31. HOW SHOULD THE OUTPUT OF A MINIMUM SYSTEM STUDY BE \n1 \nUSED TO CALCULATE THE GRC? \n2 \nA31. The minimum system study will yield a percentage value that is substitutable for \n3 \n(but lower than) the 25.8% value that the Transmission Owners have proposed as \n4 \ntheir Grid Reliance Percentage Allocator to calculate the GRC. The only difference \n5 \nis that a value calculated using the minimum system that is below 10% will be both \n6 \ntheoretically sound, fair, just, and reasonable. With a new and lower Grid Reliance \n7 \nPercentage Allocator, the Transmission Owners should re-calculate the GRC using \n8 \nthe same methodology that they have already proposed. \n9 \nQ32. WHAT ARE THE IMPACTS OF A GRC THAT IS TOO HIGH? \n10 \nA32. Customers that pay the GRC by definition do not impose any incremental cost on \n11 \nthe transmission system. Thus, all GRC charges that the Transmission Owners \n12 \ncollect are used to directly reduce the NITS rate for all other customers.28 In this \n13 \nregard, it may seem that a higher GRC rate would yield higher GRC revenues and \n14 \nthus higher reductions to the NITS rate for all other customers. However, basic \n15 \neconomics tells us that this is not necessarily the case. As Art Laffer artfully \n16 \ndemonstrated, higher tax rates can actually yield lower tax revenues to the extent \n17 \nthat they discourage work and investment.29  \n18 \nIn the case of the GRC, inappropriately increasing the rate to too high of a \n19 \nlevel could have the effect of reducing absolute GRC revenues for two reasons. \n20 \nFirst, it could discourage the development of co-located load in the PJM region. \n21 \n \n28 Initial Brief and Joint Responses of the Indicated PJM Transmission Owners to Paper Hearing Questions, \nDocket Nos. EL25-49-000, EL25-49-001, AD24-11-000, and EL25-20-000 (filed Feb. 23, 2026), page 17. \n29 https://en.wikipedia.org/wiki/Laffer_curve."},{"page":58,"startToken":16443,"endToken":16569,"text":"23 \nSecond, it could disincentivize the configuration of load in a lower cost co-located \n1 \nconfiguration and instead incentivize configuration of load in a higher cost NITS \n2 \nconfiguration that would require inefficient buildout of the transmission system. An \n3 \nexplicit objective of this proceeding is to “avoid costly and inefficient transmission \n4 \nsystem buildout that may not be necessary.”30 Thus, a GRC that is too high risks \n5 \ninefficiently increasing system costs and reducing GRC collections that can be used \n6 \nto reduce the NITS rate for other customers. It is therefore not in the best interest \n7 \nof PJM’s consumers for Transmission Owners to seek a high GRC that would \n8 \nultimately reduce GRC revenue collections. \n \n9 \n \n30 FERC Order EL25-49-000, page 70."},{"page":59,"startToken":16569,"endToken":16809,"text":"24 \n5 Recommendations & Summary \n1 \nQ33. IN LIGHT OF THE ARGUMENTS YOU MAKE, DO YOU HAVE A \n2 \nRECOMMENDATION? \n3 \nA33. Yes. I recommend that FERC not approve either the methodology or value for the \n4 \nGrid Reliance Charge (“GRC”) that the Transmission Owners have put forward. It \n5 \nis not theoretically sound, has no precedent, and is unreasonably high. Instead, I \n6 \nrecommend that FERC order PJM to conduct a minimum system study to determine \n7 \na percentage that can be applied to the NITS rate to calculate the GRC. I estimate \n8 \nthat 6% of NITS is a reasonable basis for the GRC, but any value between 2% to \n9 \n10% may be reasonable. FERC should ensure that PJM does not produce a GRC \n10 \nrate higher than 10% of the NITS rate which would be unreasonable, not aligned \n11 \nwith cost causation principles, and would call into question the methodological \n12 \napproach or assumptions.  \n13 \nQ34. PLEASE SUMMARIZE YOUR TESTIMONY. \n14 \nA34. Yes. The key takeaways of my testimony are: \n15 \n• The concept of a GRC is reasonable so that co-located loads make some \n16 \ncontribution to the cost of the wires that deliver the ancillary services they \n17 \nconsume; \n18 \n• The Transmission Owners’ proposal for the GRC is unjust and unreasonable \n19 \nbecause it is not based on sound ratemaking principles, has no precedent, is \n20 \ninconsistent with cost causation principles, and is unreasonably high; \n21"},{"page":60,"startToken":16809,"endToken":16900,"text":"25 \n• The minimum system method provides a theoretically sound basis for \n1 \ndeveloping a GRC; \n2 \n• Using the minimum system method, I estimate an appropriate GRC should be \n3 \n6% of the NITS rate, although a value between 2% to 10% may be reasonable; \n4 \nand \n5 \n• A GRC rate that is too high could have the unintended negative consequences \n6 \nof both reducing GRC revenues and causing inefficient transmission buildout, \n7 \ncontrary to the objective of the FERC Order. \n8 \nQ35. DOES THIS CONCLUDE YOUR TESTIMONY? \n9 \nA35. Yes \n10"},{"page":61,"startToken":16900,"endToken":16933,"text":"VERIFICATION \nI declare under penalty of perjury that the foregoing Testimony is true and correct to the best \nof my knowledge, information, and belief.  \nExecuted this 25th day of March, 2026.\n________________________ \nZachary Ming"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":6,"endAt":10,"startToken":0,"endToken":1932},{"p":6,"at":10,"title":"I. The Commission Should Fast Track Interim NITS","method":"printed heading","endPage":10,"endAt":4,"startToken":1932,"endToken":3167},{"p":10,"at":4,"title":"II. PJM Proposes to Restrict Contract Demand Services in Conflict with the December 18th","method":"printed heading","endPage":13,"endAt":1061,"startToken":3167,"endToken":4741},{"p":13,"at":1061,"title":"III. The Commission Should Encourage Its New Transmission Services and Reject Attempts","method":"printed heading","endPage":14,"endAt":165,"startToken":4741,"endToken":4919},{"p":14,"at":165,"title":"A. The Commission Should Direct PJM to Include a Transitional Mechanism","method":"printed heading","endPage":14,"endAt":1287,"startToken":4919,"endToken":5085},{"p":14,"at":1287,"title":"B. PJM’s Proposed Study Procedures Lack Sufficient Detail to Prevent Needless","method":"printed heading","endPage":18,"endAt":111,"startToken":5085,"endToken":6505},{"p":18,"at":111,"title":"C. PJM and Indicated Transmission Owners’ “To Be Determined” Penalty","method":"printed heading","endPage":21,"endAt":176,"startToken":6505,"endToken":7414},{"p":21,"at":176,"title":"D. Clarification of Proposed System Protection Scheme Requirements is Needed","method":"printed heading","endPage":25,"endAt":1125,"startToken":7414,"endToken":8757},{"p":25,"at":1125,"title":"E. The Grid Reliance Charge Must be Economically Grounded and Rational","method":"printed heading","endPage":29,"endAt":4,"startToken":8757,"endToken":9936},{"p":29,"at":4,"title":"F. PJM’s Proposal to Require Retail Sale Authorization Will Delay","method":"printed heading","endPage":29,"endAt":1270,"startToken":9936,"endToken":10130},{"p":29,"at":1270,"title":"G. Requiring Different Feeders is Potentially Unnecessary, Discriminatory and","method":"printed heading","endPage":30,"endAt":581,"startToken":10130,"endToken":10314},{"p":30,"at":581,"title":"IV. Other Clarifications on Co-Located Loads and the Requirements of Existing Capacity","method":"printed heading","endPage":31,"endAt":1748,"startToken":10314,"endToken":10819},{"p":31,"at":1748,"title":"Attachment M-2 (PSE&G) (same); Mar 25, 2026 Ming Testimony at 13 n.20 (“Utilities that use a 5-CP methodology","method":"printed heading","endPage":32,"endAt":558,"startToken":10819,"endToken":10943},{"p":32,"at":558,"title":"CONCLUSION","method":"printed heading","endPage":34,"endAt":0,"startToken":10943,"endToken":11163},{"p":34,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":37,"endAt":3,"startToken":11163,"endToken":11316},{"p":37,"at":3,"title":"Table of Contents","method":"printed heading","endPage":61,"endAt":232,"startToken":11316,"endToken":16933}]}