{"document":{"slug":"rec-20260408-5119","title":"Motion for Leave and Supplemental Protest of Constellation Energy Generation, LLC to advise FERC of an important factual development underscoring why FERC…","issued":"2026-04-08","accession":"20260408-5119","docket":"ER26-1479-000","group":"PJM co-location compliance","filer":"Constellation Energy Generation, LLC","kind":"protest","file":"sources/filings/text/20260408-5119_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260408-5119","tier":"record","sha256":"71f1e61323c94a60b9848aa0a58acd47eba5cacab660bd66b6df3b952833fcd6","pages":6,"tokens":1510,"emptyPages":[],"textThemes":["colo"]},"pages":[{"page":1,"startToken":0,"endToken":347,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \nPJM Interconnection, L.L.C. \n \nPJM Interconnection, L.L.C. \n) \n \n) \nDocket No. ER26-1088-000 \n \nDocket No. ER26-1479-000 \n                 (Not consolidated) \n \nMOTION FOR LEAVE AND SUPPLEMENTAL PROTEST OF \nCONSTELLATION ENERGY GENERATION, LLC  \nConstellation Energy Generation, LLC moves for leave1 to submit this supplemental \nprotest to advise the Commission of an important factual development underscoring why the \nCommission must reject PJM’s proposal to define Co-Located Load in relation to the “Point of \nChange in Ownership” which PJM proposed to do in both its 30-day and 60-day compliance \nfilings.2   \nThe Commission’s December 18, 2025 Order3 was explicit in defining Co-Located Load \nas “a ‘configuration [that] refers to end-use customer load that is physically connected to the \nfacilities or planned Customer Facility on the Interconnection Customer’s side of the Point of \nInterconnection to the PJM Transmission System.’”4 The Commission will recall that PJM’s \n \n1 Constellation Energy Generation, LLC (“Constellation”) submits this protest and motion for leave pursuant to \nRules 211 and 212 of the Commission’s Rules of Practice and Procedure, 18 C.F.R. §§ 385.211 and 385.212(2025). \nConstellation respectfully submits there is good cause for the Commission to accept this supplemental protest as it \nis intended to aid the Commission in its decision-making. \n2 See Comments and Conditional Protest of Constellation Energy, Docket No. ER26-1088-000 (Feb. 10, 2026) \n(“Constellation’s Thirty-Day Compliance Filing Comments”); id. at 5 (“The Commission must ensure that \nTransmission Owners are not permitted to exploit the interconnection process to continue to deny, delay, encumber, \nor tie interconnection services for large load configurations that they disfavor. Accordingly, the Commission should \nreject PJM’s new definition of Co-Located Load.”). See also Protest and Comments of Constellation Energy \nGeneration, LLC, Docket No. ER26-1479-000 (Mar. 16, 2026) (“Constellation’s Sixty-Day Compliance Filing \nComments”); id. at 3 (“Using the ‘Point of Change in Ownership’ could give the Transmission Owner an additional \ntool to discriminate against competing projects.”). \n3 PJM Interconnection, L.L.C., 193 FERC ¶ 61,217 (2025) (“December 18th Order”). \n4 December 18th Order, 193 FERC ¶ 61,217 at P 164."},{"page":2,"startToken":347,"endToken":583,"text":"2 \ncompliance filings diverged from the December 18th Order and instead sought to define Co-\nLocated Load in reference to the “Point of Change in Ownership” rather than the “Point of \nInterconnection.”   \nIn its protest of both PJM’s 30-day and 60-day compliance filings, Constellation explained \nthat PJM’s deviation from the Commission’s order would allow Transmission Owners to \neffectively block co-location arrangements. Specifically, a Transmission Owner could refuse to \ninterconnect load located on the generator’s side of the Point of Interconnection unless the \ngenerator acquiesced to the Transmission Owner’s ownership of all facilities connecting that load \nto the Point of Interconnection. While such load would still be Co-located Load under the \nDecember 18th Order’s definition—it is still on the generator’s side of the Point of \nInterconnection, notwithstanding the Transmission Owner’s ownership of facilities on that side—\nit would no longer count as Co-located Load under PJM’s alternative definition focused on the \nPoint of Change in Ownership. \nUnfortunately, recent experience has borne out Constellation’s concern. As part of a load \ninterconnection application for NITS, Constellation submitted to a PJM Transmission Owner a \nring bus design to co-locate load at one of its generating stations. The interconnection application \nreflected a ring bus located on the generator’s side of the Point of Interconnection that would allow \nthe load to access supply from the generation facility and the grid. Constellation’s protest to PJM’s \n60-day compliance filing depicted this as follows:"},{"page":3,"startToken":583,"endToken":780,"text":"3 \n \nDuring the week of March 30, 2026, the Transmission Owner informed Constellation that \nit would not study Constellation’s proposed design unless Constellation agreed to transfer \nownership of the ring bus facilities to the Transmission Owner. Under the December 18th Order’s \ndefinition, Constellation could do so, and the load—located on the generator’s side of the Point of \nInterconnection—would still qualify as Co-Located Load. But under PJM’s definition, transferring \nownership of the ring bus facilities would mean that the load no longer would be on the generator’s \nside of the Point of Change in Ownership. By conditioning the load’s interconnection on the \nTransmission Owner’s ownership of those facilities, the Transmission Owner will have effectively \nblocked Constellation’s ability to host Co-Located Load at that site and eliminated the co-located \nload’s ability to use the new transmission services adopted in the December 18th Order. \nThe fact that Transmission Owners are leveraging their monopoly position to stymie Co-\nLocation should come as no surprise. After all, the Transmission Owners’ joint comments to PJM’s \n60-day filing are unabashed in restating that “some” of those Transmission Owners “strongly \ndisagree” that “the new transmission services” adopted in the December 18th Order should"},{"page":4,"startToken":780,"endToken":1307,"text":"4 \n“ultimately [be] required to be implemented.”5 Such statements from Transmission Owners—and \nthe actions described herein—run exactly counter to the principal motivation of the Commission’s \nDecember Order to accommodate new ways for large loads to site more quickly.6 Given the depth \nof Transmission Owner resistance to the Commission’s December 18th Order, the Commission \nmust be on guard for attempts by the Transmission Owners to effectively block access to these \nnew transmission services, even while purporting to facially comply with the Order. PJM’s \nproposal to define Co-Located Load with reference to the Point of Change in Ownership, rather \nthan the Point of Interconnection, enables exactly that kind of gamesmanship and risks rendering \nthe Commission’s December 18th Order a dead letter. The Commission should reject PJM’s \nproposal in both the 30-day and 60-day compliance dockets. \n \n5 Joint Response of the Indicated PJM Transmission Owners, Docket Nos. EL25-49, et al. (Mar. 25, 2026) at 2-3.   \n6  See December 18th Order, 193 FERC ¶ 61,217 at P 201 (“This willingness to curtail would potentially allow them \nto obtain service more quickly.”); see also id. (Rosner, Comm’r, concurring at PP 3-4) (“Because of this, a business-\nas-usual approach to load growth—planning for generation and load separately—will not suffice to timely meet \ngrowing demand while also keeping prices reasonable. Today’s order helps break the logjam.”); id. (Rosner, \nComm’r, concurring at P 4) (“And co-located large loads and generators can get online faster and easier than would \notherwise be the case. Grid operators like PJM should allow and encourage large loads and generators to pursue \nthese time- and cost-saving co-location arrangements.”); FERC, Fact Sheet: FERC Directs Nation’s Largest Grid \nOperator to Create New Rules to Embrace Innovation and Protect Consumers (Dec. 18, 2025), \nhttps://www.ferc.gov/news-events/news/fact-sheet-ferc-directs-nations-largest-grid-operator-create-new-rules-\nembrace?new= (“As technology leaps forward, clear and fair regulations must keep pace to support advancement \n….”); FERC, News Release, FERC: Directs Nation’s Largest Grid Operator to Create New Rules to Embrace \nInnovation and Protect Consumers (Dec. 18, 2025), https://www.ferc.gov/news-events/news/ferc-directs-nations-\nlargest-grid-operator-create-new-rules-embrace-innovation-and?new= (“‘Clarifying new rules will help release the \nbottleneck of large load investments across the PJM footprint,’ said Chairman Swett.”); FERC, Transcript of 1131st \nCommission Meeting, at 24:25 to 25:1-2 (Dec. 18, 2025), https://www.ferc.gov/media/transcript-december-18-\n2025-open-meeting (“[W]hen done right co-location can be both a consumer forward tool and a critical avenue in \nbeating our national imperative of speed to power and winning the AI race.”) (remarks of Commissioner See); id. \n26:4-7 (“FERC is meeting the urgent demand for speed to power by creating flexibility for a rapidly evolving \nindustry without sacrificing reliability and affordability.”) (remarks of Commissioner See); id. at 37:11-12 (“We \ncan’t just pretend large loads don’t exist and wish them away.”) (remarks of Commissioner LaCerte); id. at 37:15-\n16 (“PJM is in dire need of leadership for their stakeholders.”) (remarks of Commissioner LaCerte); FERC, \nTranscript of 1132nd Commission Meeting, at 10:2-5 (Jan. 26, 2026) (“I warmly welcome engagement from great \noperators who share my commitment to helping ensure that datacenters can interconnect quickly and reliably.”) \n(remarks of Chairman Swett)."},{"page":5,"startToken":1307,"endToken":1432,"text":"5 \n \n \n \n \n \n \n \n    Respectfully submitted, \n \n \n \n \n \n \n \n    /s/ Paul F. Wight \n \n \n \nApril 8, 2026 \nCarrie Hill Allen \nSr. Vice President & Deputy General Counsel \nSeth T. Lucia \nAssistant General Counsel \nConstellation Energy Generation, LLC \n250 Massachusetts Ave. NW, Suite 760 \nWashington, D.C. 20001 \ncarrie.allen@constellation.com \nseth.lucia@constellation.com \n  \nChristopher A. Wilson \nManaging Director, Federal Regulatory Affairs \nConstellation Energy Generation, LLC \n250 Massachusetts Ave. NW, Suite 760 \nWashington, D.C. 20001 \n202-347-7500 \nFERCe-filings1@constellation.com \n \nPaul F. Wight \nCarolyn E. Clarkin \nDLA Piper LLP (US) \n500 Eighth Street NW \nWashington, D.C. 20004 \n703-773-4058 \npaul.wight@us.dlapiper.com  \ncarolyn.clarkin@us.dlapiper.com  \n \nSophia Browning \n4365 Executive Drive \nSuite 1100 \nSan Diego, CA 92121 \n858-677-1455 \nsophia.browning@us.dlapiper.com \n \nCounsel for Constellation Energy \nGeneration, LLC"},{"page":6,"startToken":1432,"endToken":1510,"text":"CERTIFICATE OF SERVICE \nI hereby certify that I have on this 8th day of April 2026, caused to be served a copy of the \nforegoing upon all parties on the service lists in these proceedings in accordance with the \nrequirement of Rule 2010 of the Commission’s Rules of Practice and Procedure, 18 C.F.R. \n§ 385.2010 (2025). \n/s/ Sophia Browning \n \n \nSophia Browning \n4365 Executive Drive \nSuite 1100 \nSan Diego, CA 92121 \n858-677-1455 \nsophia.browning@us.dlapiper.com"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":6,"endAt":0,"startToken":0,"endToken":1432},{"p":6,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":6,"endAt":463,"startToken":1432,"endToken":1510}]}