{"document":{"slug":"rec-20260414-5246","title":"Answer of Exelon Corporation to the Motion for Leave and Supplemental Protest of Constellation Energy Generation, LLC filed on 04/08/2026","issued":"2026-04-14","accession":"20260414-5246","docket":"ER26-1479-000","group":"PJM co-location compliance","filer":"Exelon Corporation","kind":"protest","file":"sources/filings/text/20260414-5246_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260414-5246","tier":"record","sha256":"0b570526bf8ae0b14bcc7946b3e3d78ef75fc21669825730296f439685e224a9","pages":28,"tokens":6996,"emptyPages":[],"textThemes":["study"]},"pages":[{"page":1,"startToken":0,"endToken":296,"text":"PUBLIC – Confidential Material Redacted \nUNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \nPJM Interconnection, L.L.C. \n \n) \nDocket No. ER26-1088-000 \nPJM Interconnection, L.L.C. \n \n) \nDocket No. ER26-1479-000 \n(not consolidated) \nANSWER OF EXELON CORPORATION TO THE MOTION FOR LEAVE AND \nSUPPLEMENTAL PROTEST OF CONSTELLATION ENERGY GENERATION, LLC \nPursuant to Rule 2131 of the Rules of Practice and Procedure of the Federal Energy \nRegulatory Commission (“FERC” or “Commission”), Exelon Corporation on behalf of its \nsubsidiaries2 (collectively, “Exelon”) submits this Answer to the Motion for Leave and \nSupplemental Protest that was filed by Constellation Energy Generation, LLC (“Constellation”) \non April 8, 2026 (“Constellation’s Motion”).   \nConstellation’s Motion adds nothing to the Commission’s analysis and should be rejected. \nThe motion suggests that Constellation’s limited engagement with one PJM transmission owner \nabout one proposed design implies a perverse policy of not only that one utility but of all PJM \ntransmission owners.  The motion goes on to imply that Constellation’s one experience somehow \nundermines the justness and reasonableness of PJM’s proposal.  Exelon files this Answer to correct \nany implication that Exelon, the ultimate parent corporation of various PJM transmission owners, \nor those various transmission owners are attempting to prevent large loads, co-located or \notherwise, and their load serving entities from receiving transmission services in the Exelon \nutilities’ service territories. \n1\nSee 18 C.F.R. § 385.213(d)(1) (“Any answer to a motion or to an amendment to a motion must be made within \n15 days after the motion or amendment is filed, except as described below or unless otherwise ordered.”). \n2\nExelon’s subsidiaries are as follows: Atlantic City Electric Company, Baltimore Gas and Electric Company, \nCommonwealth Edison Company (“ComEd”), Commonwealth Edison Company of Indiana, Inc., Delmarva \nPower and Light Company, PECO Energy Company, and Potomac Electric Power Company."},{"page":2,"startToken":296,"endToken":626,"text":"PUBLIC – Confidential Material Redacted \n \n2 \nI. \nREQUEST FOR CUI//PRIV//HC TREATMENT \nIn accordance with section 388.112 of the Commission’s regulations,3 Exelon requests \nprivileged treatment for a portion of this Answer containing certain confidential information.  \nExelon understands that the involved counterparty may view this information as competitively \nsensitive and the relevant Exelon utility also treats such information as non-public.  Accordingly, \ngood cause exists for the Commission to grant this request for privileged treatment of this \ninformation.   \nExelon is filing both a public version of this Answer with necessary redactions and a non-\npublic version of this Answer that contains the confidential information.  The non-public version \nhas been labelled “CUI//PRIV//HC” and should be made subject to privileged document protection \nby the Commission.  In accordance with 18 C.F.R. § 388.112(b)(2)(i), a proposed form of \nprotective agreement modeled on the Commission’s Model Protective Order is enclosed as \nAttachment B.  To respect the competitive concerns of its customer, the Protective Order has been \nmodified to provide additional protections for material deemed “Highly Confidential Privileged \nMaterial.”  Similar provisions have been included in other approved protective orders in recent \nyears.4  Any questions regarding this request for privileged treatment should be directed to the \nundersigned. \n \n3  \n18 C.F.R. § 388.112. \n4  \nSee, e.g., PJM Interconnection, L.L.C., Docket No. ER23-2214-000, Order of Chief Judge Adopting Protective \nOrder, at P 1 (Dec. 4, 2023) (adopting proposed protective order that “deviates from the Commission’s Model \nProtective Order by deleting inapplicable provisions related to oil pipeline proceedings” and also “includes \nprovisions to bar disclosure of commercially sensitive information to ‘Competitive Duty Personnel.’” (citation \nomitted)); DCR Transmission, L.L.C., Docket No. ER23-2309-000, Order of Chief Judge Adopting Protective \nOrder, at P 16 (Jan. 18, 2024); see also Duke Energy Progress, LLC, Docket No. ER25-3483-000, Application, \nat Attach. G (Sept. 22, 2025) (protective order in Federal Power Act section 205 filing with Highly Confidential \nPrivileged Material provisions)."},{"page":3,"startToken":626,"endToken":853,"text":"PUBLIC – Confidential Material Redacted \n \n3 \nII. \nANSWER \nIn its motion, Constellation points to a recent communication with a PJM transmission \nowner concerning a large load interconnection request.  Constellation argues that the transmission \nowner “informed Constellation that it would not study Constellation’s proposed design unless \nConstellation agreed to transfer ownership of the ring bus facilities to the Transmission Owner.”  \nConstellation does not address the circumstances in which that communication purportedly \noccurred, its formality or finality, or the seniority of the individuals involved.  Nonetheless, \nConstellation argues that this interaction demonstrates the inadequacy of PJM’s proposed \ndefinition of co-located load.  This is not correct.  <BEGIN CUI//PRIV//HC> \n \n \n \n \n  <END CUI//PRIV//HC> Constellation’s purported experience indicates neither a \nnefarious policy of one utility nor a reason for modifying PJM’s proposal. \n<BEGIN CUI//PRIV//HC> \n \n \n.5 \n<END CUI//PRIV//HC> As explained in earlier filings, the Exelon companies have seen numerous \nrecent requests for service to new large loads, imposing potentially immense new demands.6   The \nExelon utilities are in the business of delivering power to electric customers, and any notion that \nthey are antagonistic to delivering power to certain categories of load is absurd.  Exelon is totally \n \n5  \nSee Declaration of David Weaver, PE, ¶ 11 (“Weaver Declaration”).  The Weaver Declaration is enclosed as \nAttachment A. \n6  \nSee, Exelon December 8, 2025 Answer to Constellation in Docket No. EL25-49, et al."},{"page":4,"startToken":853,"endToken":1006,"text":"PUBLIC – Confidential Material Redacted \n4 \nsupportive of service to new large loads, so long as the service is consistent with safe and reliable \nservice, adheres to state and federal legal and regulatory requirements, and properly contributes to \nthe services provided at both the transmission and distribution level.  For example, the effort by \nComEd to develop solutions to serve new large loads can be seen in recent filings concerning \nTransmission Security Agreements (“TSAs”) to accommodate these new arrangements.7 \n<BEGIN CUI//PRIV//HC> \n <END CUI//PRIV//HC> Constellation provides no support (sworn \nor otherwise) for its assertion that the transmission owner “informed Constellation that it would \nnot study Constellation’s proposed design.” <BEGIN CUI//PRIV//HC> \n.8  \n.9  \n.10 \n7\nSee, e.g., Commonwealth Edison Co., 194 FERC ¶ 61,181 (2026) (accepting TSA relating to a new data center). \n8\nWeaver Declaration ¶ 14. \n9\nWeaver Declaration, ¶ 12 & 15. \n10\nId. ¶ 13. \n <END CUI//PRIV//HC>"},{"page":5,"startToken":1006,"endToken":1075,"text":"PUBLIC – Confidential Material Redacted \n5 \n.11  \n <END CUI//PRIV//HC> \nConstellation argues that this is all very important to PJM’s proposed definition, which \nincludes the concept of the “Point of Change of Ownership.”  But whether a transmission owner \nowns certain equipment does not necessarily answer the question of where “the Project \nDeveloper’s Interconnection Facilities connect to the Transmission Owner’s Interconnection \n11\nWeaver Declaration ¶ 12–13. \n< BEGIN CUI//PRIV//HC>"},{"page":6,"startToken":1075,"endToken":1313,"text":"PUBLIC – Confidential Material Redacted \n6 \nFacilities.”12  A utility could and sometimes does own switches, breakers, or other equipment in a \nsubstation or facility owned by a customer, potentially with easement rights to ensure access. \nThus, a conversation about who will own certain equipment in Constellation’s proposed \narrangement is not only too preliminary to inform the Commission’s review, but also not \ninformative for the Commission’s review of the proposed PJM definition that refers to the “Point \nof Change in Ownership”.  PJM’s proposed definition is just and reasonable, as explained in \nvarious pleadings submitted in the above-captioned proceedings.13 \nConstellation’s Motion does not inform the Commission’s review and should be denied. \nRespectfully submitted, \n/s/ Bradley R. Perkins \nBradley R. Perkins \nVice President and Deputy General Counsel \nExelon Corporation \nChase Building \n10 S. Dearborn, 52nd Floor \nChicago, IL 60603 \nTelephone: 312-394-2632 \nEmail: bradley.perkins@exeloncorp.com \nOn behalf of Exelon Corporation \nDated: April 14, 2026 \n12\nSee PJM Interconnection, L.L.C. Open Access Transmission Tariff, Part VII, Subpart A, section 300, Definitions \nP (defining “Point of Change in Ownership”). \n13\nSee e.g., PJM Interconnection, L.L.C., 60-Day Compliance Filing for Co-Located Load Related Revisions to \nOpen Access Transmission Tariff to Comply with Commission Order in Docket No. EL25-49, et al., Docket No. \nER26-1479-000, at 31-35 (filed Feb. 23, 2026); Indicated PJM Transmission Owners, Answer of the Indicated \nPJM Transmission Owners, Docket No. ER26-1088-000 (filed Feb. 27, 2026)."},{"page":7,"startToken":1313,"endToken":1319,"text":"PUBLIC – Confidential Material Redacted \nATTACHMENT A"},{"page":8,"startToken":1319,"endToken":1532,"text":"PUBLIC – Confidential \nMaterial Redacted \nUNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \nPJM Interconnection, L.L.C. \n \n) \nDocket No. ER26-1088-000 \nPJM Interconnection, L.L.C. \n \n) \nDocket No. ER26-1479-000 \n(not consolidated) \nDECLARATION OF DAVID WEAVER, PE \nINTRODUCTION \n1.\nMy name is David Weaver.  I am the Vice President of Transmission Strategy for Exelon\nCorporation (“Exelon”).  I oversee the transmission strategy organization with\nresponsibility for transmission planning and analysis across all of the Exelon operating\ncompanies.  I began my career with Exelon in January 1996.  I have served in various roles\nat Exelon in engineering, investment strategy, transmission operations, transmission\nplanning, substation design, project management, and business planning.  Before joining\nExelon, I worked at Delmarva Power and Light as an engineer in Substation Design and\nTransmission Planning.  With more than 35 years of experience in the utility industry, I\nalso served as chair of NERC’s Planning Committee, President and board member of the\nWIRES transmission industry trade group, and board member of the North American\nTransmission Forum.  I received my bachelor’s degree in Electrical Engineering from\nDrexel University and I am a licensed professional engineer.\nPURPOSE OF THE DECLARATION \n2. I am providing this Declaration on behalf of Exelon and its transmission-owning subsidiaries:\nAtlantic City Electric Company, Baltimore Gas and Electric Company, Commonwealth"},{"page":9,"startToken":1532,"endToken":1777,"text":"PUBLIC – Confidential \nMaterial Redacted \n2 \nEdison Company (“ComEd”), Commonwealth Edison Company of Indiana, Inc., Delmarva \nPower and Light Company, PECO Energy Company, and Potomac Electric Power Company \n(collectively, the “Exelon Utilities”).   \n3. I am responding to the Motion for Leave and Supplemental Protest that was filed by\nConstellation Energy Generation, LLC (“Constellation”) on April 8, 2026 (“Constellation’s\nMotion”).  In its motion, Constellation points to recent discussions with a PJM transmission\nowner concerning a data center interconnection request.  Constellation argues that the\ntransmission owner “informed Constellation that it would not study Constellation’s proposed\ndesign unless Constellation agreed to transfer ownership of the ring bus facilities to the\nTransmission Owner.” <BEGIN CUI//PRIV//HC>\n <END CUI//PRIV//HC> \nEXELON LARGE LOAD STUDY PROCESS \n4. The Exelon Utilities, like others utilities around the nation, have received an unprecedented\ninflux of requests to interconnect new large loads to serve data centers.  At ComEd, for\ninstance, over the past two years, there have been many requests, with projected demands of\ntens of thousands of megawatts.  The projected demands exceed ComEd’s all-time system\npeak, which is to say that they would more than double ComEd’s overall demand.\n5. The Exelon Utilities are committed to serving these customers—that is their business and\nobligation.  It is what we do.  But it has to be done in a way that ensures that service is safe\nand reliable for both existing customers and new customers alike, and thus each request is\nsubject to study."},{"page":10,"startToken":1777,"endToken":2083,"text":"PUBLIC – Confidential \nMaterial Redacted \n3 \n6. The details of the study process are evolving, but in general, we have found that it is better\nfor all concerned to conduct studies in clusters, with projects submitted within particular time\nwindows studied in synchrony.  To this end, the Exelon Utilities define study “windows”\nduring which they collect requests from new large loads across their respective service\nterritories.  Each window has a set deadline for submission, and a new window opens once\nthe previous window closes. The utility then aggregates the demand schedules, or “ramp\nrates,” of all projects submitted during the same window and studies them collectively to\ndetermine the cumulative impact on the transmission system.  Through this analysis, the\nutility also identifies whether any transmission or high voltage system reinforcements or\nexpansions are needed to ensure the safety, reliability, and efficiency of those systems, as\nwell as the utility’s ability to serve all its customers.  A cluster study includes the\ndetermination of how customers are interconnected to the grid, a planning analysis to identify\nany necessary transmission upgrades to maintain reliability, and preliminary engineering,\nscope, cost, and schedule to connect customers and complete necessary network upgrades.\nOnce a cluster study is complete, customers that execute a transmission security agreement\nand remain committed to interconnect, have their direct connection needs and any necessary\nnetwork upgrades detail engineered and planned for actual construction.  That mode of\nanalysis is well-established at Exelon where ComEd, for instance, is completing study of\nCluster 2 and preparing to begin Cluster 3.\n7. The cluster studies were implemented because one-by-one studies delayed the utility’s ability\nto provide customers with critical information about potential in-service dates and sometimes\nrequired repeated re-studies as new projects entered and exited the queue.  The cluster study\nprocess resolves these issues by allowing the utility to evaluate projects together, improving"},{"page":11,"startToken":2083,"endToken":2395,"text":"PUBLIC – Confidential \nMaterial Redacted \n4 \nresponsiveness to customers and capturing economies of scale in study and planning \nprocesses.  This approach also provides a more comprehensive and transparent view of the \ncollective impacts of large demand growth.  When multiple projects are proposed in similar \ntimeframes, studying them as clusters enables the utility to better assess overall system \nreliability and the interrelationship of nearby loads—insights that cannot be achieved through \nisolated, piecemeal evaluations.  As a result, cluster studies produce more accurate, efficient, \nand forward-looking outcomes for both applicants and the broader customer base.  \n8. Because these are studies of service requests for new end users, aspects of their conduct and\ntheir application to those retail service applications are subject to regulation by state utility\ncommissions.  For example, the ComEd process was the subject of a proceeding at the Illinois\nCommerce Commission evaluating proposed tariff amendments to address service to such\nloads.   That ICC proceeding recently adopted the process proposed by ComEd.  See,\nhttps://www.icc.illinois.gov/docket/P2025-0677/documents/377910/files/662669.pdf.\n9. It is typical that prior to the study being conducted, there will be one or more informational\nmeetings with the customer to clarify the details of the project to be studied.  These meetings\nare an early opportunity for engagement, well before the actual studies occur.  The customer\nmay seek clarification on the parameters of the upcoming study, and the utility may obtain\ninformation to refine its understanding of the proposal.  Which is to say that the meetings are\na two-way street, each side developing a better understanding of what should be studied.\nThese meetings do not include policy or legal teams, and are thus not a place where decisions\nget resolved.  Where a policy or legal question may arise, those at the meeting will follow an\nestablished escalation path to ensure appropriate review by those with decision-making\nauthority."},{"page":12,"startToken":2395,"endToken":2493,"text":"PUBLIC – Confidential \nMaterial Redacted \n5 \n10. The Exelon Utilities use similar informational meetings when other interconnection-related\nissues arise.  Because of this, Constellation is very familiar with the process.  For example,\nConstellation owns several generation facilities that used to be owned by ComEd, scattered\naround the ComEd transmission system, and thus such meetings between ComEd and\nConstellation are routine.  Constellation understands the limited role of those who participate\nin the informational meetings, but also understands how to escalate an issue to Exelon utility\nleadership when a dispute arises.\n<BEGIN CUI//PRIV//HC> \n11.\n12. \n13.\n< END CUI//PRIV//HC>"},{"page":13,"startToken":2493,"endToken":2601,"text":"PUBLIC – Confidential \nMaterial Redacted \n6 \n14. \n15. \n<END CUI//PRIV//HC> \nCONCLUSION \n16. It is troubling to me that the engagement with the transmission owner the Constellation\nMotion references is being used to make a legal case.  For Exelon, informational meetings\nwith customers are never intended to be a place where policy or legal decisions are made.\nThey are intended in good faith as a place and time where engineers can talk freely so that\nstudies can be well conducted, and customers can move through the process and come online\nas expeditiously and efficiently as possible.  If instead, each party “lawyers up” before each\n<BEGIN CUI//PRIV//HC>"},{"page":14,"startToken":2601,"endToken":2672,"text":"PUBLIC – Confidential \nMaterial Redacted \n7 \nsuch meeting, I doubt that the meetings will have such free-flowing conversation or that they \nwill continue to serve much of a useful purpose.   \n17. <BEGIN CUI//PRIV//HC>\n <END CUI//PRIV//HC> \nThe suggestion in the Constellation Motion that Exelon utilities, as PJM transmission \nowners, have a policy of denying service based on this issue is incorrect. <BEGIN \nCUI//PRIV//HC> \n <END CUI//PRIV//HC>"},{"page":15,"startToken":2672,"endToken":2716,"text":"PUBLIC – Confidential \nMaterial Redacted \nVERIFICATION \nI declare under penalty of perjury that the foregoing Declaration is true and correct to the \nbest of my information, knowledge, and belief. \nExecuted this 14th day of April 2026. \n/s/ David Weaver \nVice President, Transmission Strategy \nExelon Corporation"},{"page":16,"startToken":2716,"endToken":2722,"text":"PUBLIC – Confidential Material Redacted \n \n \nATTACHMENT B"},{"page":17,"startToken":2722,"endToken":3141,"text":"PUBLIC – Confidential Material Redacted \n \n9 \n \nUNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \nPJM Interconnection, L.L.C.  \n \n) \nDocket No. ER26-1088-000 \n \nPJM Interconnection, L.L.C.  \n \n) \nDocket No. ER26-1479-000 \n(not consolidated) \n \nPROTECTIVE AGREEMENT \n \nThis Protective Agreement (“Agreement”), entered into this ___day of _______, 20_   by \nand between Exelon Corporation on behalf of its subsidiaries14 (“Exelon”) and ___________ \n(“Intervenor”), shall govern the use of all Privileged, Highly Confidential Privileged Material, \nand/or Critical Energy/Electric Infrastructure Information (“CEII”) Material produced by Exelon \nto Intervenor, or vice versa, in connection with the captioned proceeding before the Federal Energy \nRegulatory Commission (the “Commission”).  Exelon and Intervenor are sometimes referred to \nherein individually as a “Participant” or jointly as the “Participants.” \n \n1. Exelon filed in the above-referenced proceeding Privileged Material, Highly Confidential \nPrivileged Material, and/or CEII, as those terms are defined herein.  Intervenor is a Participant \nin such proceeding, as the term Participant is defined in 18 C.F.R. Section 385.102(b), or has \nfiled a motion to intervene or a notice of intervention in such proceeding.  Exelon and \nIntervenor enter into this Agreement to govern the use of Privileged Material, Highly \nConfidential Privileged Material, and/or CEII produced by, or on behalf of, Exelon and/or \nIntervenor in the above-referenced proceeding.  Notwithstanding any order terminating such \nproceeding, this Agreement shall remain in effect unless and until specifically modified or \nterminated by the Commission or a court of competent jurisdiction.  In the event this \nAgreement terminates, the obligations of Reviewing Representatives to maintain the \nconfidentiality of Privileged Material, Highly Confidential Privileged Material, and/or CEII \nas provided hereunder shall remain in effect for 18 months following the date of termination.  \n \n2. The Commission’s regulations15 and its policy governing the labelling of controlled \nunclassified information (“CUI”)16 establish and distinguish the respective designations of \nPrivileged Material and CEII.  As to these designations, this Protective Agreement provides \nthat a Participant: \n \n \n14  Exelon’s subsidiaries are as follows: Atlantic City Electric Company, Baltimore Gas and Electric Company, \nCommonwealth Edison Company, Commonwealth Edison Company of Indiana, Inc., Delmarva Power and Light \nCompany, PECO Energy Company, and Potomac Electric Power Company. \n15  Compare 18 C.F.R. § 388.112, with 18 C.F.R. § 388.113.  This Protective Agreement does not alter the respective \nrequirements imposed by these sections on Privileged Material or CEII. \n16  Notice of Document Labelling Guidance for Documents Submitted to or Filed with the Commission or Commission \nStaff, 82 Fed. Reg. 18,632 (Apr. 20, 2017) (issued by Commission Apr. 14, 2017)."},{"page":18,"startToken":3141,"endToken":3581,"text":"PUBLIC – Confidential Material Redacted \n \n10 \n \nA. may designate as Privileged Material any material which customarily is treated \nby that Participant as commercially sensitive or proprietary or material subject \nto a legal privilege, which is not otherwise available to the public, and which if \ndisclosed, would subject that Participant or its customers to risk of competitive \ndisadvantage or other business injury; and \n \nB. must designate as CEII, any material that meets the definition of that term as \nprovided by 18 C.F.R. §§ 388.113(a), (c). \n \n3. For the purposes of this Protective Agreement, the listed terms are defined as follows: \n \nA. Participant(s): As defined at 18 C.F.R. § 385.102(b). \nB. Privileged Material:17 \ni. \nMaterial (including depositions) provided by a Participant in response to \ndiscovery requests or filed with the Commission, and that is designated \nas Privileged Material by such Participant;18 \nii. \nMaterial that is privileged under federal, state, or foreign law, such as \nwork-product privilege, attorney-client privilege, or governmental \nprivilege, and that is designated as Privileged Material by such \nParticipant;19 \niii. \nAny information contained in or obtained from such designated \nmaterial; \niv. \nAny other material which is made subject to this Protective Agreement \nby the Presiding Administrative Law Judge (Presiding Judge) or the \nChief Administrative Law Judge (Chief Judge) in the absence of the \nPresiding Judge or where no presiding judge is designated, the \nCommission, any court, or other body having appropriate authority, or \nby agreement of the Participants (subject to approval by the relevant \nauthority); \n \n17  The Commission’s regulations state that “[f]or the purposes of the Commission’s filing requirements, non-CEII \nsubject to an outstanding claim of exemption from disclosure under FOIA will be referred to as privileged \nmaterial.”  18 C.F.R. § 388.112(a).  The regulations further state that “[f]or material filed in proceedings set for \ntrial-type hearing or settlement judge proceedings, a participant’s access to material for which privileged treatment \nis claimed is governed by the presiding official’s protective order.”  Id. § 388.112(b)(2)(v). \n18  See infra P 11 for the procedures governing the labeling of this designation. \n19  The Commission’s regulations state that “[a] presiding officer may, by order . . . restrict public disclosure of \ndiscoverable matter in order to . . . [p]reserve a privilege of a participant.” 18 C.F.R. § 385.410(c)(3).  To \nadjudicate such privileges, the regulations further state that “[i]n the absence of controlling Commission precedent, \nprivileges will be determined in accordance with decisions of the Federal courts with due consideration to the \nCommission’s need to obtain information necessary to discharge its regulatory responsibilities.”  Id. \n§ 385.410(d)(1)(i)."},{"page":19,"startToken":3581,"endToken":3976,"text":"PUBLIC – Confidential Material Redacted \n \n11 \n \nv. \nNotes of Privileged Material (memoranda, handwritten notes, or any \nother form of information (including electronic form) which copies or \ndiscloses Privileged Material);20 or \nvi. \nCopies of Privileged Material.  \nvii. \nPrivileged Material does not include: \n \n1. Any information or document that has been filed with and accepted \ninto the public files of the Commission, or contained in the public \nfiles of any other federal or state agency, or any federal or state court, \nunless the information or document has been determined to be \nprivileged by such agency or court; or \n2. Information that is public knowledge, or which becomes public \nknowledge, other than through disclosure in violation of this \nProtective Agreement.  \nC. Highly Confidential Privileged Material: A Participant may use this designation \nfor those materials that are of such a commercially sensitive nature among the \nParticipants or of such a private, personal nature that the producing Participant is \nable to justify a heightened level of confidential protection with respect to those \nmaterials.  Highly Confidential Privileged Material shall include Privileged \nMaterial that present a higher risk of competitive injury if disclosed to \nCompetitive Duty Personnel as determined in good faith by the producing \nParticipant and includes materials such as: (1) information regarding contract \nnegotiations and contract buyouts and (2) strategic business or financial plans.  \nExcept for the more limited list of persons who qualify as Reviewing \nRepresentatives for the purposes of Reviewing Highly Confidential Privileged \nMaterial (i.e., Reviewing Representatives that are not Competitive Duty \nPersonnel), such materials are subject to the same provisions in the Protective \nAgreement as other Privileged Material. \nD. Critical Energy/Electric Infrastructure Information (“CEII”): As defined at 18 \nC.F.R. §§ 388.113(a), (c). \nE. Non-Disclosure Certificate: The certificate attached to this Protective Agreement, \nby which Participants granted access to Privileged Material, Highly Confidential \nPrivileged Material, and/or CEII must certify their understanding that such access \nto such material is provided pursuant to the terms and restrictions of this \nProtective Agreement, and that such Participants have read the Protective \nAgreement and agree to be bound by it.  All executed Non-Disclosure Certificates \nmust be served on all Participants on the official service list maintained by the \nSecretary of the Commission for this proceeding. \n \n20  Notes of Privileged Material are subject to the same restrictions for Privileged Material except as specifically \nprovided in this Protective Agreement."},{"page":20,"startToken":3976,"endToken":4350,"text":"PUBLIC – Confidential Material Redacted \n \n12 \n \nF. Reviewing Representative: A person who has signed a Non-Disclosure \nCertificate and who is: \ni. \nCommission Trial Staff designated as such in this proceeding; \nii. \nAn attorney who has made an appearance in this proceeding for a      \nParticipant; \niii. \nAttorneys, paralegals, and other employees associated for purposes of \nthis case with an attorney who has made an appearance in this \nproceeding on behalf of a Participant; \niv. \nAn expert or an employee of an expert retained by a Participant for the \npurpose of advising, preparing for, submitting evidence or testifying in \nthis proceeding; \nv. \nA person designated as a Reviewing Representative by order of the \nPresiding Judge, the Chief Judge, or the Commission; or \nvi. \nEmployees or other representatives of Participants appearing in this \nproceeding with significant responsibility for this docket. \nG. The term “Reviewing Representative” for purposes of reviewing Highly \nConfidential Privileged Material defined in Paragraph 3(C) shall mean a person \nwho has signed a Non-Disclosure Certificate who is:  \ni. \nListed in Paragraph 3(F), but is not Competitive Duty Personnel as \ndefined in Paragraph 3(H); or \nii. \nDesignated as a Reviewing Representative for purposes of reviewing \nHighly Confidential Privileged Material by agreement of the producing \nParticipant or by order of the Presiding Judge. \nH. The term “Competitive Duty Personnel” shall mean any individual(s) whose \nscope of employment or engagement includes the marketing, sale, or purchase \nof coal, natural gas, or electricity (collectively, “Energy”), the direct supervision \nof any employee or employees whose duties include the marketing of Energy, \nor other Energy services in competition with the producing Participant, all of \nwhich are considered “Competitive Duties,” except that Competitive Duty \nPersonnel shall not include employees of the Commission, any state utilities \ncommission which is a Participant, in-house or outside counsel, and/or an \noutside consultant retained by a Participant for the purpose of advising, \npreparing for, submitting evidence, or testifying in this proceeding. \n \n4. Privileged Material, Highly Confidential Privileged Material, and/or CEII shall be made \navailable under the terms of this Protective Agreement only to Participants and only to their \nReviewing Representatives as provided in Paragraphs 6–10 of this Protective Agreement.  \nThe contents of Privileged Material, Highly Confidential Privileged Material, CEII or any"},{"page":21,"startToken":4350,"endToken":4807,"text":"PUBLIC – Confidential Material Redacted \n \n13 \n \nother form of information that copies or discloses such materials shall not be disclosed to \nanyone other than in accordance with this Protective Agreement and shall be used only in \nconnection with this specific proceeding.  \n5. All Privileged Material, Highly Confidential Privileged Material, and/or CEII must be \nmaintained in a secure place.  Access to those materials must be limited to Reviewing \nRepresentatives specifically authorized pursuant to Paragraphs 7–9 of this Protective \nAgreement. \n6. Privileged Material, Highly Confidential Privileged Material, and/or CEII must be handled \nby each Participant and by each Reviewing Representative in accordance with the Non-\nDisclosure Certificate executed pursuant to Paragraph 9 of this Protective Agreement.  \nPrivileged Material, Highly Confidential Privileged Material, and/or CEII shall not be used \nexcept as necessary for the conduct of this proceeding, nor shall they (or the substance of \ntheir contents) be disclosed in any manner to any person except a Reviewing Representative \nwho is engaged in this proceeding and who needs to know the information in order to carry \nout that person’s responsibilities in this proceeding.  A Reviewing Representative shall not \ndisclose Highly Confidential Privileged Material to Competitive Duty Personnel, except as \nauthorized pursuant to Paragraph 3(G).  Reviewing Representatives may make copies of \nPrivileged Material, Highly Confidential Privileged Material, and/or CEII, but such copies \nautomatically become Privileged Material, Highly Confidential Privileged Material, and/or \nCEII.  Reviewing Representatives may make notes of Privileged Material, which shall be \ntreated as Notes of Privileged Material if they reflect the contents of Privileged Material. \n7. If a Reviewing Representative’s scope of employment includes any of the activities listed \nunder this Paragraph 7, such Reviewing Representative may not use information contained \nin any Privileged Material, Highly Confidential Privileged Material, and/or CEII obtained \nin this proceeding for a commercial purpose (e.g., to give a Participant or competitor of any \nParticipant a commercial advantage): \nA. Energy marketing; \nB. Direct supervision of any employee or employees whose duties include energy \nmarketing; or \nC. The provision of consulting services to any person whose duties include energy \nmarketing. \n8. If a Participant wishes to designate a person not described in Paragraph 3(F) above as a \nReviewing Representative, the Participant must seek agreement from the Participant \nproviding the Privileged Material, Highly Confidential Privileged Material, and/or CEII.  If \nan agreement is reached, the designee shall be a Reviewing Representative pursuant to \nParagraph 3(E) of this Protective Agreement with respect to those materials.  If no \nagreement is reached, the matter must be submitted to the Presiding Judge or the \nCommission for resolution. \n9. A Reviewing Representative shall not be permitted to inspect, participate in discussions \nregarding, or otherwise be permitted access to Privileged Material, Highly Confidential"},{"page":22,"startToken":4807,"endToken":5320,"text":"PUBLIC – Confidential Material Redacted \n \n14 \n \nPrivileged Material, and/or CEII pursuant to this Protective Agreement until three business \ndays after that Reviewing Representative first has executed and served a Non-Disclosure \nCertificate.21  However, if an attorney qualified as a Reviewing Representative has executed \na Non-Disclosure Certificate, any participating paralegal, secretarial and clerical personnel \nunder the attorney’s instruction, supervision or control need not do so.  Attorneys \ndesignated Reviewing Representatives are responsible for ensuring that persons under their \nsupervision or control comply with this Protective Agreement, and must take all reasonable \nprecautions to ensure that Privileged Material, Highly Confidential Privileged Material, \nand/or CEII are not disclosed to unauthorized persons.  Reviewing Representatives that are \nCompetitive Duty Personnel as defined in Paragraph 3(H) must execute a Non-Disclosure \nCertificate for Competitive Duty Personnel in the form attached hereto.  All executed Non-\nDisclosure Certificates must be served on all Participants on the official service list \nmaintained by the Secretary of the Commission for the proceeding. \n10. Any Reviewing Representative may, consistent with the requirements in Paragraph 3(G), \ndisclose Privileged Material, Highly Confidential Privileged Material, and/or CEII to any \nother Reviewing Representative as long as both Reviewing Representatives have executed a \nNon-Disclosure Certificate.  In the event any Reviewing Representative to whom Privileged \nMaterial, Highly Confidential Privileged Material, and/or CEII are disclosed ceases to \nparticipate in this proceeding, or becomes employed or retained for a position that renders him \nor her ineligible to be a Reviewing Representative under Paragraph 3(F) of this Protective \nAgreement, access to such materials by that person shall be terminated.  Even if no longer \nengaged in this proceeding, every person who has executed a Non-Disclosure Certificate shall \ncontinue to be bound by the provisions of this Protective Agreement and the Non-Disclosure \nCertificate for as long as the Protective Agreement is in effect.22  \n11. All Privileged Material, Highly Confidential Privileged Material, and/or CEII in this \nproceeding filed with the Commission, submitted to the Presiding Judge, or submitted to any \nCommission personnel, must comply with the Commission’s Notice of Document Labelling \nGuidance for Documents Submitted to or Filed with the Commission or Commission Staff.23  \nConsistent with those requirements: \nA. Documents that contain Privileged Material must include a top center header on \neach page of the document with the following text: CUI//PRIV or \nCUI//PRIV//HC for Highly Confidential Privileged Material.  Any corresponding \nelectronic files must also include this text in the file name. \nB. Documents that contain CEII must include a top center header on each page of \nthe document with the following text: CUI//CEII.  Any corresponding electronic \nfiles must also include this text in the file name. \n \n21  During this three-day period, a Participant may file an objection with the Presiding Judge or the Commission \ncontesting that an individual qualifies as a Reviewing Representative, and the individual shall not receive access \nto the Privileged Material, Highly Confidential Privileged Material, and/or CEII until resolution of the dispute. \n22  See infra P 19. \n23  82 Fed. Reg. 18,632 (Apr. 20, 2017) (issued by Commission Apr. 14, 2017)."},{"page":23,"startToken":5320,"endToken":5802,"text":"PUBLIC – Confidential Material Redacted \n \n15 \n \nC. Documents that contain both Privileged Material and CEII must include a top \ncenter header on each page of the document with the following text: \nCUI//CEII/PRIV.  Any corresponding electronic files must also include this text \nin the file name. \nD. The specific content on each page of the document that constitutes Privileged \nMaterial and/or CEII must also be clearly identified.  For example, lines or \nindividual words or numbers that include both Privileged Material and CEII \nshall be prefaced and end with “BEGIN CUI//CEII/PRIV” and “END \nCUI//CEII/PRIV”. \n12. If any Participant desires to include, utilize, or refer to Privileged Material (or Highly \nConfidential Privileged Material) or information derived from Privileged Material (or Highly \nConfidential Privileged Material) in testimony or other exhibits during the hearing in this \nproceeding in a manner that might require disclosure of such materials to persons other than \nReviewing Representatives, that Participant first must notify both counsel for the disclosing \nParticipant and the Presiding Judge (or the Commission), and identify all such Privileged \nMaterial (or Highly Confidential Privileged Material).  Thereafter, use of such Privileged \nMaterial (or Highly Confidential Privileged Material) will be governed by procedures \ndetermined by the Presiding Judge (or the Commission). \n13. Nothing in this Protective Agreement shall be construed as precluding any Participant from \nobjecting to the production or use of Privileged Material, Highly Confidential Privileged \nMaterial, and/or CEII on any appropriate ground.  \n14. Nothing in this Protective Agreement shall preclude any Participant from requesting the \nPresiding Judge (or the Chief Judge in the Presiding Judge’s absence or where no presiding \njudge is designated), the Commission, or any other body having appropriate authority, to find \nthis Protective Agreement should not apply to all or any materials previously designated \nPrivileged Material (or Highly Confidential Privileged Material) pursuant to this Protective \nAgreement.  The Presiding Judge (or the Chief Judge in the Presiding Judge’s absence or where \nno presiding judge is designated), the Commission, or any other body having appropriate \nauthority may alter or amend this Protective Agreement as circumstances warrant at any time \nduring the course of this proceeding. \n15. Each Participant governed by this Protective Agreement has the right to seek changes in it as \nappropriate from the Presiding Judge (or the Chief Judge in the Presiding Judge’s absence or \nwhere no presiding judge is designated), the Commission, or any other body having appropriate \nauthority. \n16. Subject to Paragraph 17, the Presiding Judge (or the Chief Judge in the Presiding Judge’s \nabsence or where no presiding judge is designated), or the Commission shall resolve any \ndisputes arising under this Protective Agreement pertaining to Privileged Material (or \nHighly Confidential Privileged Material) according to the following procedures.  Prior to \npresenting any such dispute to the Presiding Judge, the Chief Judge or the Commission, the \nParticipants to the dispute shall employ good faith best efforts to resolve it."},{"page":24,"startToken":5802,"endToken":6371,"text":"PUBLIC – Confidential Material Redacted \n \n16 \n \nA.  Any Participant that contests the designation of material as Privileged Material \n(or Highly Confidential Privileged Material) shall notify the Participant that \nprovided the Privileged Material (or Highly Confidential Privileged Material) \nby specifying in writing the material for which the designation is contested. \nB.  In any challenge to the designation of material as Privileged Material (or Highly \nConfidential Privileged Material), the burden of proof shall be on the Participant \nseeking protection.  If the Presiding Judge, the Chief Judge, or the Commission \nfinds that the material at issue is not entitled to the designation, the procedures of \nParagraph 17 shall apply. \nC. The procedures described above shall not apply to material designated by a \nParticipant as CEII.  Material so designated shall remain subject to the \nprovisions of this Protective Agreement, unless a Participant requests and \nobtains a determination from the Commission’s CEII Coordinator that such \nmaterial need not retain that designation. \n17. The designator will have five (5) days in which to respond to any pleading requesting \ndisclosure of Privileged Material (or Highly Confidential Privileged Material).  Should the \nPresiding Judge, the Chief Judge, or the Commission, as appropriate, determine that the \ninformation should be made public, the Presiding Judge, the Chief Judge, or the Commission \nwill provide notice to the designator no less than five (5) days prior to the date on which the \nmaterial will become public.  This Protective Agreement shall automatically cease to apply \nto such material on the sixth (6th) calendar day after the notification is made unless the \ndesignator files a motion with the Presiding Judge, the Chief Judge, or the Commission, as \nappropriate, with supporting affidavits, demonstrating why the material should continue to \nbe privileged.  Should such a motion be filed, the material will remain confidential until such \ntime as the interlocutory appeal or certified question has been addressed by the Motions \nCommissioner or the Commission, as provided in the Commission’s regulations, 18 C.F.R. \n§§ 385.714 and 385.715.  No Participant waives its rights to seek additional administrative \nor judicial remedies after a Presiding Judge or Chief Judge decision regarding Privileged \nMaterial (or Highly Confidential Privileged Material) or the Commission’s denial of any \nappeal thereof or determination in response to any certified question.  The provisions of 18 \nC.F.R. §§ 388.112 and 388.113 shall apply to any requests under the Freedom of Information \nAct (5 U.S.C. § 552) for Privileged Material (or Highly Confidential Privileged Material) \nand/or CEII in the files of the Commission. \n18. Privileged Material, Highly Confidential Privileged Material, and/or CEII shall remain \navailable to Participants until the later of 1) the date an order terminating this proceeding no \nlonger is subject to judicial review, or 2) the date any other Commission proceeding relating \nto the Privileged Material, Highly Confidential Privileged Material, and/or CEII is concluded \nand no longer subject to judicial review.  After this time, the Participant that produced the \nPrivileged Material, Highly Confidential Privileged Material, and/or CEII may request (in \nwriting) that all other Participants return or destroy the Privileged Material, Highly \nConfidential Privileged Material, and/or CEII.  This request must be satisfied with within \nfifteen (15) days of the date the request is made.  However, copies of filings, official transcripts \nand exhibits in this proceeding containing Privileged Material, Highly Confidential Privileged \nMaterial, or Notes of Privileged Material, may be retained if they are maintained in accordance"},{"page":25,"startToken":6371,"endToken":6539,"text":"PUBLIC – Confidential Material Redacted \n \n17 \n \nwith Paragraph 5 of this Protective Agreement.  If requested, each Participant also must submit \nto the Participant making the request an affidavit stating that to the best of its knowledge it has \nsatisfied the request to return or destroy the Privileged Material, Highly Confidential Privileged \nMaterial, and/or CEII.  To the extent Privileged Material, Highly Confidential Privileged \nMaterial, and/or CEII are not returned or destroyed, they shall remain subject to this Protective \nAgreement. \n19. Regardless of any order terminating this proceeding, this Protective Agreement shall \nremain in effect until specifically modified or terminated by the Presiding Judge, the Chief \nJudge, or the Commission.  All CEII designations shall be subject to the “[d]uration of the \nCEII designation” provisions of 18 C.F.R. § 388.113(e). \n20. Any violation of this Protective Agreement and of any Non-Disclosure Certificate executed \nhereunder shall constitute a violation of an order of the Commission. \n \nFor Exelon: \nSigned:  ______________________________  \nPrinted Name:  ________________________ \nDate: ________________________________ \n \n \nFor Intervenor: \nSigned:  ______________________________ \nPrinted Name:  _________________________  \nDate:  ________________________________"},{"page":26,"startToken":6539,"endToken":6709,"text":"PUBLIC – Confidential Material Redacted \n \n \n \nUNITED STATES OF AMERICA  \nFEDERAL ENERGY REGULATORY COMMISSION \n \nPJM Interconnection, L.L.C.  \n \n) \nDocket No. ER26-1088-000 \n \nPJM Interconnection, L.L.C.  \n \n) \nDocket No. ER26-1479-000 \n(not consolidated) \n \nNON-DISCLOSURE CERTIFICATE FOR NON-COMPETITIVE DUTY PERSONNEL \nI hereby certify my understanding that access to Privileged Material, Highly Confidential \nPrivileged Material, and/or Critical Energy/Electric Infrastructure Information (CEII) is provided to \nme pursuant to the terms and restrictions of the Protective Agreement in this proceeding, that I have \nbeen given a copy of and have read the Protective Agreement, and that I agree to be bound by it.  I \nunderstand that the contents of Privileged Material, Highly Confidential Privileged Material, and/or \nCEII, any notes or other memoranda, or any other form of information that copies or discloses such \nmaterials, shall not be disclosed to anyone other than in accordance with the Protective Agreement.  \nI acknowledge that a violation of this certificate constitutes a violation of an order of the Federal \nEnergy Regulatory Commission. \nBy: ______________________________________   \nPrinted Name: ______________________________   \nTitle: _____________________________________   \nRepresenting: ____________________________   \nDate: _____________________________________"},{"page":27,"startToken":6709,"endToken":6944,"text":"PUBLIC – Confidential Material Redacted \n \n \n \nUNITED STATES OF AMERICA  \nFEDERAL ENERGY REGULATORY COMMISSION \n \nPJM Interconnection, L.L.C.  \n \n) \nDocket No. ER26-1088-000 \n \nPJM Interconnection, L.L.C.  \n \n) \nDocket No. ER26-1479-000 \n(not consolidated) \n \n \nNON-DISCLOSURE CERTIFICATE   \nFOR COMPETITIVE DUTY PERSONNEL \nI hereby certify my understanding that access to Privileged Material in the above-captioned \ncase is provided to me pursuant to the terms and restrictions of the Protective  Agreement in this \nproceeding, that I have been given a copy of and have read the Protective Agreement, and that I \nagree to be bound by it.  I understand that the contents of Privileged Material, any notes or other \nmemoranda, or any other form of information that copies or discloses Privileged  Material shall \nnot be disclosed to anyone other than in accordance with the Protective Agreement and shall be \nused only in connection with this proceeding.  I acknowledge that my duties and responsibilities \ninclude “Competitive Duties” as described in the Protective Agreement and, as such, I understand \nthat I shall neither have access to, nor disclose, the contents of the Highly Confidential Privileged \nMaterial that are marked as “CUI//PRIV//HC,” any notes or other memoranda, or any other form \nof information that copies or discloses Privileged Material that is marked as “CUI//PRIV//HC.”  I \nacknowledge that a violation of this certificate constitutes a violation of an order of the Federal \nEnergy Regulatory Commission.  \n By: \n  \nBy: ______________________________________   \nPrinted Name: ______________________________   \nTitle: _____________________________________   \nRepresenting: ____________________________   \nDate: _____________________________________"},{"page":28,"startToken":6944,"endToken":6996,"text":"PUBLIC – Confidential Material Redacted \n \n \n \n \nCERTIFICATE OF SERVICE \n \nI hereby certify that I have this day served the foregoing document upon each person \ndesignated on the official service list compiled by the Secretary in this proceeding. \nDated at Chicago, IL this 14h day of April, 2026. \n \n \n/s/ Geneva Kennedy  \nGeneva Kennedy  \nExelon Corporation"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":2,"endAt":46,"startToken":0,"endToken":301},{"p":2,"at":46,"title":"I. REQUEST FOR CUI//PRIV//HC TREATMENT","method":"printed heading","endPage":3,"endAt":46,"startToken":301,"endToken":631},{"p":3,"at":46,"title":"II. ANSWER","method":"printed heading","endPage":7,"endAt":41,"startToken":631,"endToken":1317},{"p":7,"at":41,"title":"ATTACHMENT A","method":"printed heading","endPage":8,"endAt":291,"startToken":1317,"endToken":1356},{"p":8,"at":291,"title":"INTRODUCTION","method":"printed heading","endPage":13,"endAt":76,"startToken":1356,"endToken":2504},{"p":13,"at":76,"title":"CONCLUSION","method":"printed heading","endPage":16,"endAt":45,"startToken":2504,"endToken":2720},{"p":16,"at":45,"title":"ATTACHMENT B","method":"printed heading","endPage":18,"endAt":649,"startToken":2720,"endToken":3242},{"p":18,"at":649,"title":"A. Participant(s): As defined at 18 C.F.R. § 385.102(b).","method":"printed heading","endPage":18,"endAt":707,"startToken":3242,"endToken":3255},{"p":18,"at":707,"title":"B. Privileged Material:17","method":"printed heading","endPage":19,"endAt":785,"startToken":3255,"endToken":3698},{"p":19,"at":785,"title":"C. Highly Confidential Privileged Material: A Participant may use this designation","method":"printed heading","endPage":19,"endAt":1963,"startToken":3698,"endToken":3866},{"p":19,"at":1963,"title":"E. Non-Disclosure Certificate: The certificate attached to this Protective Agreement,","method":"printed heading","endPage":20,"endAt":49,"startToken":3866,"endToken":3981},{"p":20,"at":49,"title":"F. Reviewing Representative: A person who has signed a Non-Disclosure","method":"printed heading","endPage":20,"endAt":915,"startToken":3981,"endToken":4112},{"p":20,"at":915,"title":"G. The term “Reviewing Representative” for purposes of reviewing Highly","method":"printed heading","endPage":20,"endAt":1418,"startToken":4112,"endToken":4188},{"p":20,"at":1418,"title":"H. The term “Competitive Duty Personnel” shall mean any individual(s) whose","method":"printed heading","endPage":21,"endAt":2231,"startToken":4188,"endToken":4668},{"p":21,"at":2231,"title":"A. Energy marketing;","method":"printed heading","endPage":21,"endAt":2253,"startToken":4668,"endToken":4671},{"p":21,"at":2253,"title":"B. Direct supervision of any employee or employees whose duties include energy","method":"printed heading","endPage":21,"endAt":2348,"startToken":4671,"endToken":4685},{"p":21,"at":2348,"title":"C. The provision of consulting services to any person whose duties include energy","method":"printed heading","endPage":22,"endAt":2590,"startToken":4685,"endToken":5168},{"p":22,"at":2590,"title":"A. Documents that contain Privileged Material must include a top center header on","method":"printed heading","endPage":22,"endAt":2881,"startToken":5168,"endToken":5214},{"p":22,"at":2881,"title":"B. Documents that contain CEII must include a top center header on each page of","method":"printed heading","endPage":23,"endAt":49,"startToken":5214,"endToken":5325},{"p":23,"at":49,"title":"C. Documents that contain both Privileged Material and CEII must include a top","method":"printed heading","endPage":23,"endAt":298,"startToken":5325,"endToken":5366},{"p":23,"at":298,"title":"D. The specific content on each page of the document that constitutes Privileged","method":"printed heading","endPage":24,"endAt":49,"startToken":5366,"endToken":5807},{"p":24,"at":49,"title":"A. Any Participant that contests the designation of material as Privileged Material","method":"printed heading","endPage":24,"endAt":373,"startToken":5807,"endToken":5850},{"p":24,"at":373,"title":"B. In any challenge to the designation of material as Privileged Material (or Highly","method":"printed heading","endPage":24,"endAt":740,"startToken":5850,"endToken":5907},{"p":24,"at":740,"title":"C. The procedures described above shall not apply to material designated by a","method":"printed heading","endPage":28,"endAt":49,"startToken":5907,"endToken":6948},{"p":28,"at":49,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":28,"endAt":359,"startToken":6948,"endToken":6996}]}