{"document":{"slug":"rec-20260424-5110","title":"Reply Comments of Earthjustice in response to the stakeholder's comments re PJM Interconnection, LLC's 02/23/2026 Initial Brief et al","issued":"2026-04-24","accession":"20260424-5110","docket":"EL25-49-000","group":"PJM co-location compliance","filer":"EARTHJUSTICE","kind":"comments","file":"sources/filings/text/20260424-5110_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260424-5110","tier":"record","sha256":"02a81344144d46d3c44379aa3b873c3ab76c5c83e0d7b37cc05b3dc22a34517d","pages":27,"tokens":7855,"emptyPages":[],"textThemes":["flex","colo","study","cost"]},"pages":[{"page":1,"startToken":0,"endToken":302,"text":"1 \n \nUNITED STATES OF AMERICA  \nBEFORE THE  \nFEDERAL ENERGY REGULATORY COMMISSION  \n \n \n \n \nPJM Interconnection, LLC  \n)  \n)  \n) \nDocket No. EL25-49-000 \n   Docket No. ER26-1479-000  \n  \n  \nReply Comments of Earthjustice \nI. \nIntroduction \n \nOn February 23, 2026, PJM Interconnection, LLC (“PJM”) submitted its initial brief1 and \n60-day compliance filing2 in response to the Commission’s December 18, 2025, order on the \nshow cause proceeding.3  Earthjustice appreciates the opportunity to respond to the wide range of \ncomments that stakeholders submitted to the Commission in response to PJM’s filings.4 As PJM \nand other commenters remark, PJM is tasked with reimagining how it will provide transmission \nservices, among other system changes. To date, PJM’s region has absorbed more load growth \nfrom large load customers than any other grid operator in the Commission’s jurisdiction. And \nprojected load growth through 2030 is not slowing down.5   \n \n1 Initial Brief of PJM Interconnection, L.L.C., Docket No. EL25-49-000 (Feb. 23, 2026), Accession No. 20260223-\n5189 (“PJM Initial Brief”). \n2 60-Day Compliance Filing for Co-Located Load Related Revisions to Open Access Transmission Tariff to Comply \nwith Commission Order in Docket No. EL25-49, et. al, Docket No. ER26-1479-000 (Feb. 23, 2026), Accession No. \n20260223-5181 (“60-Day Compliance Filing”). \n3 PJM Interconnection, L.L.C., 193 FERC ¶ 61,217 (2025) (“Order on Show Cause Proceeding”). \n4 These comments are timely filed in Docket No. EL25-49-000. Though PJM chose to file its 60-Day Compliance \nFiling in a separate docket, ER26-1479-000, all of the issues discussed in these comments were initially raised in the \nCommission’s Order on the Show Cause Proceeding in Docket No. EL25-49-000. We respectfully request that the \nCommission consider these comments in both EL25-49-000 and ER26-1479-000.  \n5 John Wilson, et. al., Power Demand Forecasts Revised Up for Third Year Running, Led by Data Centers, Grid \nStrategies 5 (2025), https://gridstrategiesllc.com/wp-content/uploads/Grid-Strategies-National-Load-Growth-Report-\n2025.pdf."},{"page":2,"startToken":302,"endToken":675,"text":"2 \n \nWith this landscape, PJM has little margin for error in implementing the new and \nmodified services to avoid events that could devastate system reliability. As explained below, to \navoid such risks, the Commission should (1) accept PJM’s proposed operational penalties; \n(2) require PJM to clarify how and when curtailment directives will be enforced and how \nviolations will be communicated to the public; (3) decline to require that PJM rush the \nimplementation of protection mechanisms for its new non-firm transmission services; and \n(4) require PJM to make its co-located generator interconnection studies and retail-BTMG rules \nconsistent with the Commission’s Order on the Show Cause Proceeding and Order No. 2023.  \nAdditionally, several comments in this docket express concern about PJM’s \ninterconnection queue, with commenters fearing delays.6 The Commission is aware of PJM’s \nclogged interconnection queue and has raised concerns over PJM’s potential reliability and \nresource adequacy issues.7 Other regulators have expressed similar concerns.8 This docket \nreinforces that the Commission should require PJM to accelerate its interconnection process and \nensure consistency with open access. \nII. \nThe Commission should accept PJM’s operational penalty proposal.  \n \nThe Commission should accept PJM’s proposed operational penalties for data centers9 \ntaking PJM’s new transmission services because financial penalties alone are insufficient to \n \n6 See Limited Protest of Advanced Energy United and Solar Energy Industries Association, at 12, Docket No. ER26-\n1479-000 (Mar. 16, 2026), Accession No. 20260316-5300 (“AEU & SEIA Protest”); Protest of Joint Parties, at 7 n. \n32, Docket No. ER26-1479-000 (Mar. 16, 2026), Accession No. 20260316-5333 (“Joint Parties Protest”); \nComments of the Digital Power Network, at 5, Docket No. ER26-1479-000 (Mar. 16, 2026), Accession No. \n20260316-5220.  \n7 Order on Show Cause Proceeding, supra note 3, at P 243.  \n8 Statement of Principles Regarding PJM (Jan. 16, 2026), https://www.energy.gov/documents/statement-principles-\nregarding-pjm.  \n9 PJM’s proposal will apply to “Eligible Customers,” which PJM defines as “(1) any electric utility or any person \ngenerating electric energy for sale for resale, but with respect to transmission service that the Commission is \nprohibited from ordering by section 212(h) of the Federal Power Act, such entity is eligible only if the service is \nprovided pursuant to a state requirement that the Transmission Provider or Transmission Owner offer the unbundled"},{"page":3,"startToken":675,"endToken":1013,"text":"3 \n \nensure compliance with curtailment directives. The Commission’s Order on the Show Cause \nProceeding directs PJM to brief and establish an appropriate penalty charge and “any other \nremedial action” that PJM should take to address a customer’s unreserved use of the transmission \nsystem or excess energy withdrawals.10 Pursuant to the Commission’s order, PJM establishes \nthree different penalties—pause in service, disqualification, and financial penalties—\napplicable where data centers fail to follow Load Shedding and Curtailment directives, rely on \nnecessary control technologies that fail more than once, or make unreserved use of the \ntransmission system. While PJM and Transmission Owners (“TOs”) propose to assess additional \nfinancial penalties for a customer’s unreserved use of the transmission system, PJM and TOs \ncorrectly acknowledge that financial penalties alone are not enough to incentivize data centers to \nfollow curtailment procedures.11 Because financial penalties are insufficient to ensure that data \ncenters will curtail energy use, the Commission should accept PJM’s more rigorous operational \npenalties. \nA. Initial comments either support PJM proposed penalties or fail to adequately \naddress PJM’s argument that financial penalties are insufficient to ensure \ncompliance.  \n \nCommenters generally support penalties for data centers that fail to follow curtailment \nprocedures but disagree on whether PJM should impose its proposed operational penalties as \nopposed to solely financial penalties. Commenters who have a responsibility to ensure reliability, \n \ntransmission service, or pursuant to a voluntary offer of such service by a Transmission Owner or (2) any retail \ncustomer taking unbundled transmission service pursuant to a state requirement that the Transmission Provider or a \nTransmission Owner offer the transmission service, or pursuant to a voluntary offer of such service by a \nTransmission Owner.” PJM Open Access Transmission Tariff, Part VIII, Subpart A, Section 400, Definitions E. \nHowever, for simplicity, these comments refer to Eligible Customers as “data centers” because the majority of \nEligible Customers will be taking service on behalf of data center customers.  \n10 Order on Show Cause Proceeding, supra note 3, at P 212, 217. \n11 PJM’s Initial Brief, supra note 1, at 50."},{"page":4,"startToken":1013,"endToken":1343,"text":"4 \n \nincluding the Northern Virginia Electric Cooperative (“NOVEC”) and TOs, support PJM’s \noperational penalties and emphasize PJM’s obligation to protect the transmission system. \nNOVEC states that a pause in service and disqualification are appropriate and necessary to \nreliably manage co-location arrangements and protect the integrity of PJM’s transmission \nsystem.12 NOVEC also agrees that financial penalties alone are insufficient to ensure that data \ncenters comply with their curtailment obligations, though both NOVEC and TOs support \nimposing complementary financial penalties alongside PJM’s proposed operational penalties.13  \nUnsurprisingly, developers of co-located resources argue for a weaker penalty structure \nbased solely on financial penalties—but fail to show that financial penalties can actually affect \ntheir behavior. Joint Co-location Developers suggest PJM use a financial penalty similar to the \nNon-Performance Charge PJM assesses in the Capacity Resource context.14 They argue that \nPJM’s operational penalties are disproportionate to the harm caused by data centers that fail to \ncurtail.15 They assert that “failure to respond to a Load Shedding or Curtailment procedure would \nhave a similar impact to a capacity resource failing to perform during emergency events,” while \nthe opportunity cost of shutting down a data center could purportedly be higher than the penalty \ncharge ordinarily levied on capacity resources for failing to curtail.16 \nJoint Co-location Developers also argue that forcing a data center to take Network \nIntegration Transmission Service (“NITS”) after a single unauthorized withdrawal is unfair and \nwill threaten the commercial viability of PJM’s proposal.17 Other commenters argue that PJM’s \n \n12 Response of the Northern Virginia Electric Cooperative, Inc., at 11-13, Docket No. EL25-49-000 (Mar. 25, 2026), \nAccession No. 20260325-5220 (“NOVEC Comments”). \n13 See NOVEC Comments at 13; Joint Response of the Indicated PJM Transmission Owners, at 11, Docket No. \nEL25-49-000 (Mar. 25, 2026), Accession No. 20260325-5203 (“TOs Response Brief”).  \n14 Reply Brief of Joint Co-Location Developers, at 25, Docket No. EL25-49-000 (Mar. 25, 2026), Accession No. \n20260325-5236 (“Co-Location Developers Reply Brief”). \n15 Id.  \n16 Id. \n17 Id. at 23-24."},{"page":5,"startToken":1343,"endToken":1654,"text":"5 \n \nstrict liability rules unfairly assign penalties to load customers regardless of the cause or whether \na third party is at fault.18 \nCommenters opposing operational penalties believe instead that financial penalties are \nsufficient to deter wrongful conduct, although they provide no explanation of why this is \npurportedly the case other than their references to other PJM penalties levied in different \ncontexts. As detailed below, comments opposing PJM’s proposed operational penalties are \nunpersuasive because in addition to being self-serving, they ignore critical facts. Such comments \nfail to explain how financial penalties alone could be effective. They also disregard how data \ncenters’ failure to curtail can pose extreme risks to reliability.  \n1. PJM’s operational penalties are proportionate to the prospective harm \n \nassociated with a customer’s failure to follow curtailment orders. \n \n PJM explains that the consequences of a Remedial Action Scheme (“RAS”) \nmisoperation are more severe than failures of other fault protection schemes.19 A data center’s \nRAS misoperation or failure to comply with curtailment directives could have dire consequences \nfor reliability, including the loss of all interim or non-firm load in one area—or even cascading \noutages across the Eastern Interconnection.20 These serious consequences warrant serious \npenalties. While opposing commenters note that PJM’s proposed penalties are stricter than the \npenalties it has levied in other circumstances, those comments fail to acknowledge that the stakes \nhere are higher.  \nAs the Commission points out in its December 18 order, NERC has stated that “co-\nlocation of large loads with generation facilities can have substantial reliability impacts due \n \n18 Id. at 25-26, Response of the Data Center Coalition, at 8, Docket No. EL25-49-000 (Mar. 25, 2026), Accession \nNo. 20260325-5208 (“DCC Comments”). \n19 PJM Initial Brief, supra note 1, at 43. \n20 PJM Initial Brief, Attach C., Affidavit of Matthew Wharton on behalf of PJM Interconnection, L.L.C. at P 21, 22 \n(“Wharton Affidavit”)."},{"page":6,"startToken":1654,"endToken":1971,"text":"6 \n \nto . . .  loss of load incidents, while also presenting unique challenges and opportunities for grid \ntransformation that require special consideration.”21 The unique challenges and opportunities of \nco-location arrangements require unique solutions. It is not enough to hope that financial \npenalties used in other circumstances—which, as explained below, did not actually work—will \nencourage data centers taking these new services to follow curtailment directives, especially \nwhen the reliability risks here are greater. The Commission must ensure that the penalties for \nfailure to curtail are commensurate with the serious risks for PJM’s transmission system and \nultimately customers such as residential ratepayers.  \n2.  PJM’s obligation to offer non-firm service is not without limits. \nPJM’s proposal to require data centers to take NITS after failure to follow curtailment \norders is also reasonable. PJM’s new transmission services are explicitly designed for colocation \narrangements to connect faster in exchange for promises to curtail when directed. It is reasonable \nto revoke a data center’s ability to use these new transmission services if a data center fails to \nuphold its end of the bargain. Otherwise, data centers would receive the benefits of these \ntransmission services without providing a commensurate benefit to the grid. Simply put, large \nloads that fail to curtail when instructed cannot be trusted not to repeat that failure, especially in \nlight of the severe reliability risks they present. While data centers that fail to curtail when \ninstructed may have to wait for network upgrades before they can take NITS, that outcome is an \nentirely reasonable consequence for their failure to deliver promised flexibility. \n3. PJM’s penalty proposal is appropriately designed to protect system reliability, rather \nthan assign fault.  \n \nPJM’s proposal also reasonably addresses the concern that it may assign penalties to \nlarge load customers no matter who is at fault. Where failure to curtail results from a mishap \n \n21 Order on Show Cause Proceeding, supra note 3, at P 136."},{"page":7,"startToken":1971,"endToken":2265,"text":"7 \n \nwith control technologies—for which a large load may not be at fault—PJM proposes a pause in \nservice to provide a chance to correct the problems. Throughout the subsequent evaluation \nperiod, PJM and TOs will be able to investigate the issue and implement fixes, while also \nallowing the data center to resume the service once the fixes are in place.22 This evaluation \nperiod reasonably allows PJM to get to the root of the issue without disqualifying the load \ncustomer.  \nSome commenters speculate that other factors outside their control could cause a failure \nto curtail, such as problems with TOs’ facilities or communication systems. Setting aside the \nspeculative nature of these concerns, PJM reasonably addresses this prospect by proposing an \nimplementation timeline that will allow PJM and TOs to develop sufficiently sophisticated \ncurtailment procedures. As PJM requires data centers to demonstrate their ability to fully comply \nwith Load Shedding and Curtailment Procedures before the Service Commencement Date to \nbegin service, PJM similarly must ensure that the systems that PJM and TOs will use to issue \nload shedding and curtailment directives will be robust.  \nThe Commission should not allow hypothetical mishaps to prevent PJM from \nimplementing meaningful operational penalties. PJM has correctly described the seriousness of \nmisoperation and failures to curtail and has given itself a three-year timeline to implement its \ncurtailment scheme to ensure that the necessary modifications can be made for curtailment \nprocedures.23 PJM’s decision to approach this issue with adequate caution and care is reasonable \nand will decrease the likelihood that the commenters’ hypothetical concerns will arise.  \n \n22 PJM Initial Brief, supra note 1, at 44-45. \n23 PJM Initial Brief, Attach. D, Affidavit of Timothy Horger on behalf of PJM Interconnection, L.L.C. at P 16. \n(“Horger Affidavit”)."},{"page":8,"startToken":2265,"endToken":2589,"text":"8 \n \nB. The Commission should accept PJM’s proposed penalties because financial \npenalties alone are insufficient to ensure that data centers will comply with \ncurtailment directives. \n \nPJM is correct that financial penalties alone are not enough to incentivize data centers to \nfollow curtailment or load shed procedures. Some commenters have suggested that financial \npenalties could in theory be sufficient to deter data centers from failing to curtail when \ninstructed,24 but no comments actually describe what financial penalty could be sufficient in \npractice. That notable silence is likely because none of the commenters know what financial \npenalty could convince large load customers—with virtually unlimited capital and very high \ncontractual uptime requirements—to curtail when directed. Though commenters argue that \noperational penalties are too strict, they are far more effective than financial penalties. To be \neffective, financial penalties must be more than merely the cost of doing business for well-\nfinanced large loads. However, because data centers are wealthy and have diverse business \npractices, calculating an effective financial penalty is extremely difficult. Moreover, payments \nmade after the fact will not prevent the harm from non-performance. \nData center spending is growing exponentially, making it increasingly difficult to \ndetermine a uniform financial rate that could convince this multi-billion dollar—soon trillion \ndollar—industry to follow curtailment procedures instead of just paying the penalties. As of \nDecember 2025, data center deals hit a new record of $61 billion globally.25 According to \nMcKinsey, global spending on data centers could reach $7 trillion by 2030.26 With data center \n \n24 Co-Location Developers Reply Brief, supra note 14, at 25. \n25 April Roach, Data Center Deals Hit Record $61 Billion in 2025 Amid Construction Frenzy, CNBC (Dec. 19, \n2025), https://www.cnbc.com/2025/12/19/data-center-deals-hit-record-amid-ai-funding-concerns-grip-\ninvestors.html. \n26 Maria Goodpaster, et. al., The $7 Trillion Data Center Build-Our: How Industrials Can Capture Their Share, \nMcKinsey & Company (Mar. 27, 2026), https://www.mckinsey.com/industries/technology-media-and-\ntelecommunications/our-insights/the-7-trillion-dollar-data-center-build-out-how-industrials-can-capture-their-share."},{"page":9,"startToken":2589,"endToken":2993,"text":"9 \n \nspending increasing by billions year over year, it is impossible to gauge what level of financial \npenalty could incentivize data centers to curtail their operations rather than just taking the \npenalty charge as an operating cost. Indeed, new research suggests that there is no price level \ncurrently observed in wholesale markets where certain data center loads will curtail.27  \nData centers’ low participation in demand response programs also indicates that financial \npenalties are unlikely to be effective. In a study examining the potential for data center \nflexibility, the Nicholas Institute for Energy, Environment & Sustainability found that data \ncenters have historically had low participation rates in demand response programs, likely as a \nresult of their operational priorities and low financial incentives.28 Data centers are designed to \nprovide uninterrupted service, often with mandated benchmarks, including uptime, latency, and \nquality of service.29 Responses to financial incentives, whether demand response payments or \nfinancial penalties, could vary based on a data center’s particular operational capabilities. Data \ncenters are organized by tiers, ranging from tier I to tier IV.30 At the most basic capacity, tier I \noffers 99.671% of uptime per year, leaving less than 28.8 hours of downtime per year, and tier \nIV offers 99.995% of uptime per year, leaving less than 26.3 minutes of downtime per \nyear.31 For large loads with “high utilization rates and controlling costs, the economic \n \n27 In February 2026, Hans Royal, Senior Director of Renewable Energy and Carbon Advisory at Schneider Electric, \nintroduced the Compute Heat Rate, which is the first measurement to quantify the maximum electricity price at \nwhich AI computation remains economically viable, i.e. the demand-side price tolerance for data centers relative to \ncurtailment thresholds. Royal’s preliminary analysis found that for four data center workload tiers, AI demand will \nnot curtail at any price level currently observed in U.S. wholesale markets. Hans Royal, The Compute Heat Rate: \nQuantifying AI-Driven Electricity Price Tolerance and its Implications for Wholesale Market Repricing 8 (Feb. 28, \n2026), https://ssrn.com/abstract=6322318.  \n28 Tyler Norris, et. al., Rethinking Load Growth: Assessing the Potential for Integration of Large Flexible Loads in \nUS Power Systems, Nicholos Institute for Energy, Environment & \nSustainability 9 (2025), https://nicholasinstitute.duke.edu/sites/default/files/publications/rethinking-load-\ngrowth.pdf. (“Rethinking Load Growth”).  \n29 Id.  \n30 Breaking Down Data Center Tier Level Classifications, CoreSite, https://www.coresite.com/blog/breaking-down-\ndata-center-tiers-classifications.  \n31 Id."},{"page":10,"startToken":2993,"endToken":3305,"text":"10 \n \nproposition of demand response participation may be unattractive.”32 Just as demand response \npayments are insufficient to entice flexibility, financial penalties will be insufficient to compel \nflexibility.   \n Although some data centers may be more likely to respond to financial incentives, the \ndiversity among data centers makes a uniform financial penalty impossible to calculate. Some \ndata centers have different operational priorities that could allow for more flexibility in their \nenergy usage33 Data centers used for artificial intelligence (“AI”) training purposes may be better \nsuited for flexible operations because they are able to defer their training operations, whereas \nconventional data centers have less flexible real-time processing demands.34 For data centers \ntraining AI, financial penalties could theoretically be more meaningful. But without knowing a \ndata center’s operating structure, service agreements, and priorities, there is no clear way to \nfigure out what level of financial penalty would be enough to incentivize a data center to curtail. \nAdditionally, many predict that in the longer term, AI training data centers will become less \nimportant as AI models improve, and most data centers will ultimately be used for inference and \nother, less flexible real-time processing applications. According to research by McKinsey, “by \n2030 inference will surpass training to become the dominant workload in AI Data centers.”35 \nThis trend further calls into question the long-term viability of data center load flexibility.  \nAdditionally, some large-scale co-located data centers, like some at issue in this docket, house \nmultiple tenants, each with different operational requirements.36 A uniform financial penalty \n \n32 Rethinking Load Growth, supra note 28, at 9.  \n33 Id.  \n34 Id. at 11. \n35 Chhavi Arora, The Next Big Shifts in AI Workloads and Hyperscaler Strategies, Mckinsey & Company (Dec. 17, \n2025), https://www.mckinsey.com/industries/technology-media-and-telecommunications/our-insights/the-next-big-\nshifts-in-ai-workloads-and-hyperscaler-strategies. https://www.mckinsey.com/industries/technology-media-and-\ntelecommunications/our-insights/the-next-big-shifts-in-ai-workloads-and-hyperscaler-strategies \n36 Rethinking Load Growth, supra note 28, at 9."},{"page":11,"startToken":3305,"endToken":3610,"text":"11 \n \nalone would not be effective applied across all these different types of service arrangements, \nwhich all have different operational and financial priorities.   \nIndeed, PJM has used financial penalties in other contexts, and PJM is learning from its \nmistakes. Joint Co-Location Developers attempt to compare underperforming capacity resources \nto the data centers here, arguing that a rate similar to PJM’s Non-Performance Charge for a \ncapacity resource that fails to perform during an emergency would be appropriate and sufficient \nin this context.37 However, PJM’s penalty charges for poorly performing capacity resources are \nnot a model for a penalty for large loads that abuse new transmission services for three key \nreasons: (1) PJM’s Capacity Performance structure is ineffective; (2) PJM’s Capacity \nPerformance structure is designed to transfer penalties from underperforming resources to bonus \npayments for overperforming resources, and there is no comparable structure for the new \ntransmission services; and (3) the risks of nonperformance for PJM’s curtailment procedures are \nmuch graver than underperformance of a capacity resource during an emergency event.  \nFirst, PJM’s Capacity Performance structure is ineffective. PJM implemented its \nCapacity Performance system in response to capacity resource failures during the 2014 Polar \nVortex. The Polar Vortex hit the PJM region in January 2014, setting a record wintertime peak \ndemand.38 Twenty-two percent of PJM’s generation capacity failed to perform during the \nstorm.39 PJM attempted to address these nonperformance issues by creating a new Capacity \nPerformance system to incentivize capacity resources to perform during emergencies. PJM’s \nCapacity Performance system assesses penalties, or Non-Performance Charges, to resources that \n \n37 Co-Location Developers Reply Brief, supra note 14, at 25. \n38 PJM, Analysis of Operational Events and Market Impacts During the January 2014 Cold Weather Events, at 4 \n(May 8, 2014) (“Polar Vortex Report”), https://www.hydro.org/wp-content/uploads/2017/08/PJM-January-2014- \nreport.pdf. \n39 Id."},{"page":12,"startToken":3610,"endToken":3964,"text":"12 \n \nunderperform during emergencies.40 PJM then uses those penalties to fund bonuses to resources \nthat overperformed during the emergency.41 \nUnfortunately, PJM’s financial penalty system has not been an effective mechanism to \nensure that capacity resources perform when called. PJM created the Capacity Performance \nsystem because it anticipated that emergency events like the Polar Vortex would occur again. \nAnd PJM was right. But when an event like the Polar Vortex happened again, the Capacity \nPerformance system failed to incentivize resources to perform. Winter Storm Elliot hit the PJM \nregion in 2022 and despite PJM’s new penalty structure, PJM saw even more capacity resources \nfail to perform in Winter Storm Elliott than in the Polar Vortex.42 These capacity resource \nfailures resulted in the largest Capacity Performance penalties that PJM has ever assessed, with \nPJM charging underperforming resources $1.80 billion in Non-Performance Charges.43 \nHowever, in response to calls from generators to reduce the penalties, PJM has limited the \ndefinition of an “Emergency Action” that would trigger penalties, which reduces instances where \nPJM would assess penalties to nonperforming generators.44 PJM also entered into settlements to \nreduce the penalties that PJM assessed to generators that failed to perform during Winter Storm \nElliott.45 Additionally, in 2022, the Commission confirmed that generators can include the risk of \nincreased Capacity Performance penalties in their market bids.46 This history—in which \n \n40 See generally PJM Interconnection, LLC, 151 FERC ¶ 61,208 (2015). \n41 Id.  \n42 PJM, Winter Storm Elliott: Event Analysis and Recommendation Report, at 49 (July 17, 2023) (“Winter Storm \nElliott Report”), https://www.pjm.com/-/media/DotCom/library/reports-notices/special-reports/2023/20230717-\nwinter-storm-elliott-event-analysis-and-recommendation-report.pdf. \n43 Id. at 2.  \n44 Proposed Revisions to Prospectively Refine the Definition of Emergency Action, Request for Shortened Comment \nPeriod and Expedited Commission Action, at 4, Docket No. ER23-1996 (Aug. 28, 2023), Accession No. 20230828- \n5201. \n45 PJM, Offer of Settlement, at 4, 7 (Sept. 29, 2023), https://www.pjm.com/-\n/media/DotCom/documents/ferc/filings/2023/20230929-er23-2975-000.ashx. \n46 Indep. Mkt. Monitor for PJM v. PJM Interconnection, L.L.C., 178 FERC ¶ 61,121 at P 49 (2022)."},{"page":13,"startToken":3964,"endToken":4273,"text":"13 \n \nCapacity Performance penalties failed to compel strong performance from generators during \nWinter Storm Elliott and were then watered down—makes clear that financial penalties are \ninsufficient to ensure performance in the Capacity Resource context. These financial penalties \nwould likely be even more inadequate to ensure that extremely wealthy data centers will curtail \nas directed, where PJM has already acknowledged that data centers would likely “absorb \nfinancial penalties” rather than follow curtailment procedures.47  \nSecond, even if financial penalties were effective in the Capacity Performance context, \nPJM’s Capacity Performance structure is not comparable to a penalty system for new \ntransmission services. To start, the Capacity Performance system is designed to provide a \nresettlement of the capacity market by charging penalties to underperforming resources that fund \nbonus payments to overperforming resources. No similar resettlement approach is possible in the \ncontext of these new transmission services, because there is no set of “overperforming” loads \nthat could ameliorate the harms from large loads that violate the terms of the new transmission \nproducts. In this context, the only way to reduce the harm caused by failures to curtail is to stop \nservice to the large loads that violate the terms.  \nFinally, large loads that violate the terms of new transmission products are not \ncomparable to underperforming generators because they pose far graver risks to reliability. PJM \nexplains that there could be dire loss of load events if all interim or non-firm loads in an \nelectrically close area have curtailment violations.48 If multiple customers in a close area have \nsimilar RAS violations, the loss of one facility could require reducing or dropping all interim or \nnon-firm load in the area.49 Even worse, the failure or misoperation of one RAS in PJM could \n \n47 PJM Initial Brief, supra note 1, at 50. \n48 Wharton Affidavit, supra note 20, at P 22. \n49 Id."},{"page":14,"startToken":4273,"endToken":4561,"text":"14 \n \nlead to cascading outages, which could affect the entire Eastern Interconnection.50 In contrast, \ngenerator underperformance has not historically caused such severe harm. While the Polar \nVortex and Winter Storm Elliott featured generator failures and subsequent penalty charges, the \nstorms never caused widespread system outages.51 In contrast, the stakes are much higher for \nPJM if customers taking its new transmission services fail to follow curtailment directives, and \nPJM cannot risk its entire system to appease one category of customers. The Commission must \nensure that PJM is prioritizing reliability over the commercial interests of large loads. The \nCommission should accept PJM’s operational penalty structure because financial incentives are \ninsufficient to incentivize performance or ensure reliability. \nIII. \nThe Commission should require PJM to clarify how and when PJM will enforce \nits curtailment procedures.  \n \nWhile PJM’s proposed curtailment procedures and penalty structure are generally \nreasonable, PJM has not provided sufficient detail about implementation. As failures to curtail \ncan cause dire ramifications for the transmission system, the Commission must have clarity on \nseveral important points: (1) how PJM will communicate its curtailment directives to \nTransmission Providers and Data centers; (2) how and when Transmission Providers will \ndetermine that load shed is necessary, which loads will be curtailed first, and at what stage \ncurtailments will occur; and (3) how a data center will be disqualified and the timeline for that \ndisqualification.  \nAdditionally, the Commission should require PJM to explain how the public can obtain \nrecords of violations of curtailment procedures and records of enforcement of penalties for those \nviolations. PJM has emphasized that misoperation of control technology and failures to respond \n \n50 Id.  \n51 Winter Storm Elliott Report, supra note 42, at 1; Polar Vortex Report, supra note 38, at 1."},{"page":15,"startToken":4561,"endToken":4864,"text":"15 \n \nto curtailment instructions can be detrimental to the transmission system, endanger reliability \nacross multiple regions, and even threaten the entire Eastern Interconnection. These reliability \nrisks mean that curtailment violations could significantly affect all of PJM’s ratepayers. With \nstakes this high, the public must have access to information about how these risks and violations \nplay out.  \nA. Initial comments urge the Commission to require PJM to clarify its proposed \ncurtailment procedures.  \n \nInitial comments explain that PJM’s initial brief did not provide sufficient detail about its \ncurtailment procedures. Several commenters argue that PJM did not provide adequate clarity \nabout key points, including (1) what specific conditions will trigger curtailments, (2) what the \nearliest point is at which a Non-Firm customer can be curtailed and how far in advance \ncurtailment information will be provided, and (3) what the expected duration or frequency of \ncurtailment events is.52 Joint Co-Location Developers also seek clarification as to how PJM will \ndetermine curtailment priority among its different classes of Non-Firm Service.53 Additionally, \nAdvanced Energy United (“AEU”) and the Solar Energy Industries Association (“SEIA”) \nprovide PJM with specific action items, requesting that PJM publish historical analysis and \nforward-looking modeling of curtailment frequency and duration for the new Non-Firm \ntransmission services and hold a presentation to walk stakeholders through the curtailment \nprocess.54 To address confusion around PJM’s curtailment procedures, the Commission should \nrequire PJM to provide more information about specific curtailment triggers, curtailment \nduration and frequency, and how the curtailment process will actually work.  \n \n52 See DCC Comments, supra note 18, at 7; Reply Brief of Advanced Energy United and the Solar Energy Industries \nAssociation, Docket No. EL25-49-000, at 11-12, Accession No. 20260325-5237 (Mar. 25, 2026) (“AEU & SEIA \nComments”). \n53 Co-Location Developers Reply Brief, supra note 14, at 17. \n54 AEU & SEIA Comments, supra note 52, at 13-14."},{"page":16,"startToken":4864,"endToken":5187,"text":"16 \n \nB. The Commission should require PJM to clarify its curtailment procedures to ensure \nthat PJM will adequately protect the reliability and safety of the transmission \nsystem. \n \nIn addition to the concerns raised in initial comments, PJM’s initial brief, tariff, and \nproposed service agreements fail to adequately state (1) how PJM and its Transmission Providers \nwill direct customers to curtail, (2) how and when Transmission Providers will decide that load \nshed is necessary and how they will choose which specific loads are curtailed first, (3) exactly \nhow and when disqualification will occur, and (4) how PJM will communicate curtailment \nviolations and disqualifications to the public. Without clarity on the issues, the Commission and \nthe public cannot be sure that PJM’s proposal can adequately protect the transmission system.  \nPJM fails to state how it will actually communicate its orders to the Transmission \nProviders and how the Transmission Providers will actually direct their customers to curtail. \nPJM’s initial brief states that PJM will issue a directive to curtail, and data centers must \nimplement that directive and respond to any real-time instruction to curtail within five minutes.55 \nPJM’s proposed tariff further establishes that “the Transmission Provider will notify the data \ncenter of any Curtailment in a timely manner” and that any requests to curtail will be consistent \nwith Good Utility Practice.56 Beyond that, PJM’s filings are silent as to how these directives will \nbe made known to data centers and what those directives will say. The Commission should \nrequire PJM to clarify what the content of these directives will be and how these directives will \nbe communicated to data centers.    \nPJM also fails to clarify how and when Transmission Providers will determine that load \nshed is necessary, how Transmission Providers will select specific loads to curtail, and at what \n \n55 PJM Initial Brief, supra note 1, at 25. \n56 PJM Initial Brief, Attach. A, Part XI, Subpart A, §§705.1, 713.1 (“Proposed Tariff”)."},{"page":17,"startToken":5187,"endToken":5500,"text":"17 \n \nstage curtailment will occur. Under PJM’s proposal, data centers that apply for Interim NITS, \nNon-Firm Contract Demand Service, or Firm Contract Demand Service must agree to follow \nPJM’s real-time curtailment instructions within 5 minutes or risk disqualification.57 PJM states \nthat Interim NITS will be curtailed prior to Firm Contract Demand Transmission Service and \nNITS and that PJM may curtail Interim NITS and Non-Firm Contract Demand Transmission \nService prior to the Pre-Emergency Load Response Program.58 However, PJM fails to clarify \nwith any more detail when and how it will actually implement these procedures. The tariff states \nthat data centers will curtail when Transmission Providers deem it necessary, but PJM provides \nno other information to explain how Transmission Providers will determine when load shedding \nis necessary.59 While there may be existing procedures that could apply to this circumstance, \nPJM and Transmission Providers should at least document what those procedures are and explain \nhow they are adequate to this circumstance.  \n  \nAdditionally, although PJM states that data centers taking Interim NITS or Contract \nDemand Services may be curtailed prior to initiating a pre-emergency event, it is unclear when \nexactly curtailment would occur before a pre-emergency event or whether there is some set \nthreshold that would need to be crossed for curtailment to begin.60 While PJM has detailed in its \noperating agreement when a pre-emergency event will be called, PJM has not provided a detailed \nexplanation for how it will determine that resources need to be curtailed before pre-emergency or \nemergency conditions have been triggered.61 Additionally, it is unclear how Transmission \nProviders will decide which specific loads will be curtailed. While the tariff states that Interim \n \n57 Id. \n58 PJM Initial Brief, supra note 1, at 7.    \n59 Proposed Tariff, supra note 56, at §705.3. \n60 Id. at § § 705.2, 713.4. \n61 PJM Operating Agreement, Schedule 1, Section 8.5."},{"page":18,"startToken":5500,"endToken":5792,"text":"18 \n \nNITS and Non-Firm Contract Demand Service will be curtailed before Firm Contract Demand \nService, NITS, and the Pre-Emergency Load Response Program, PJM provides no further \ninformation about how Transmission Providers will determine the order in which specific loads \nwill be curtailed.41 The Commission should require PJM and TOs to clarify their curtailment \nprocess to ensure that Transmission Providers and customers can adequately understand \ncurtailment protocols.  \nPJM similarly fails to adequately explain its disqualification procedures for customers \nthat fail to curtail when called. While PJM’s tariff states that data centers will be disqualified \nafter the first instance where they fail to respond to curtailment procedures or after the second \ninstance of a misoperation, the tariff fails to explain any further how that disqualification will \nactually happen.62 PJM fails to address important operational questions, like whether PJM will \nphysically disconnect the facility from the point of interconnection or will allow the connection \nto remain intact if the Customer applies for NITS. Though PJM states that disqualification \nautomatically applies after one instance of a data center failing to follow a curtailment directive \nor after control technology fails a second time, PJM never states how that disqualification will \noccur in practice or what the timeline is for disqualification. Important considerations like when \nthe data centers will stop receiving service or how PJM and Transmission Providers will disable \ntransmission service remain unanswered. Without more clarity on these points, PJM’s \ndisqualification scheme may not have real teeth to ensure customers comply with curtailment \ndirectives and, more importantly, may not sufficiently protect the transmission system. The \nCommission should require PJM to clarify its disqualification procedures to ensure that PJM has \ncreated a reliable and effective enforcement mechanism.  \n \n62 Proposed Tariff, supra note 56, at § 713.7."},{"page":19,"startToken":5792,"endToken":6085,"text":"19 \n \nFinally, the Commission should require PJM to explain how it will provide the public \nwith records of curtailment violations and subsequent disqualification. PJM is on the right track \nto ensure that data centers comply with curtailment procedures. However, without proper \nenforcement mechanisms and public transparency, regulators and the public will not be able to \nevaluate the scope of risks to reliability and the efficacy of PJM’s penalty scheme. PJM has \ndescribed in detail how misoperations and failures to curtail can threaten the reliability of its \nentire transmission system. The Commission should require PJM to post violations publicly, \nensuring that non-data center customers are aware of reliability threats and that violations are \nhandled appropriately. \nIV.  \nThe Commission should decline to require that PJM rush the implementation of \nprotection mechanisms for its new non-firm transmission services.   \n \n \nThe Commission should approve PJM’s requested timeline to implement new \ntransmission services and accompanying RAS and Special Protection Schemes (SPS). Though \nthere is a strong push from some commenters to rush this process, the Commission must ensure \nthat PJM does not sacrifice the reliability of the transmission system to fulfill data centers’ near-\nterm power demands. The Commission has already expressed concern about the reliability and \nresource adequacy implications of Co-Location Arrangements, stating in its December order that \n“the speed at which co-located load can be added to the grid may pose particular resource \nadequacy challenges, especially if co-location arrangements are not adequately and transparently \nreflected in existing RA planning mechanisms.”63 Similarly, PJM has acknowledged that its new \ntransmission services and protection schemes could threaten the reliability of the transmission \nsystem. Considering the serious threats to reliability, PJM must ensure that its systems are safe \n \n63 Order on Show Cause Proceeding, supra note 3, at P 243."},{"page":20,"startToken":6085,"endToken":6415,"text":"20 \n \nand reliable for all customers. The Commission and PJM must not rush the process to serve \ncertain customers at the expense of overall reliability. \nCommenters who have a responsibility to ensure reliability support PJM’s proposed \nimplementation date. PJM’s Independent Market Monitor (“IMM”) and NOVEC both agree with \nMr. Horger’s explanation that the three-year timeline is necessary to give PJM enough time to \nimplement the modifications needed to support PJM’s new transmission services and curtailment \nprocedures.64 Similarly, NOVEC finds Mr. Horger’s explanation that it is no longer possible to \nimplement necessary changes to the 2028/2029 RPM to be well-founded and persuasive.65 \nPredictably, comments criticizing PJM’s deadline overwhelmingly come from entities with a \ndirect financial interest in developing co-located resources. These commenters push for urgency \nand speed, calling for the Commission to require PJM to push up its deadline.  \nThe Commission should find that PJM’s deadline is appropriate for the planning and \ntraining needed to implement PJM’s transmission services and curtailment protocols. PJM must \ntake appropriate time to implement new services and RAS. Getting it right is more important \nthan moving fast. Mr. Wharton’s affidavit acknowledges that the new transmission services and \nits RAS and SPS schemes pose significant reliability risks.66 To limit reliability risks, PJM will \nneed to develop telemetry requirements for Co-Located Loads and ensure that necessary control \ntechnologies and protective systems are properly designed.67 Typically, a RAS monitors one \nspecific, pre-determined condition, but those typical RASs would not be suitable here as PJM \nwill need an RAS or multiple RASs to monitor and activate for multiple conditions.68 As PJM \n \n64 Reply Brief of the Independent Market Monitor, Docket No. EL25-49-000, at 8, Accession No. 20260326-5062 \n(Mar. 26, 2025); NOVEC Comments, supra note 12, at 17. \n65 NOVEC Comments, supra note 12, at 17. \n66 Wharton Affidavit, supra note 20, at P 16, P 22. \n67 PJM Initial Brief, supra note 1, at 60.  \n68 Wharton Affidavit, supra note 20, at P 22."},{"page":21,"startToken":6415,"endToken":6724,"text":"21 \n \nwill be implementing RASs outside of their normal functions, PJM will need to take time to \nadapt these technologies to these new circumstances. Mr. Horger’s affidavit also notes that PJM \nneeds time to implement updates to software and automation to avoid “non-optimal, untimely, \nand inefficient outcomes.”69 PJM must ensure that its systems are sufficient to protect the safety \nand reliability of the transmission system. The Commission should not rush to expedite PJM’s \nimplementation process in favor of large load customers’ convenience and at the expense of the \nrest of PJM’s customers. The Commission should approve PJM’s proposed June 2029 effective \ndate to ensure that PJM has enough time to implement its new transmission services and \ncurtailment procedures safely and reliably.  \nV.  \nThe Commission should require PJM to ensure that rules governing generator \ninterconnection studies and behind-the-meter generation are consistent with the \nCommission’s Order on the Show Cause Proceeding and Order No. 2023.  \n \n PJM’s proposed rules are unjust and unreasonable because PJM’s proposed generator \ninterconnection study and behind-the-meter generation (“BTMG”) rules fail to comply with the \nCommission’s Order on the Show Cause Proceeding and Order No. 2023. To ensure that PJM’s \nrules are consistent with the Commission’s Orders, the Commission should: (1) require PJM to \nclarify that hybrid resources can nominate their net withdrawal limitations for purposes of the \ninterconnection study process and (2) require PJM to set a materiality threshold for the amount \nof load a generator can net using BTMG. \nThe Commission ordered PJM to amend its tariff because it did not include conditions of \nservice for co-location arrangements that are willing and able to limit their withdrawals from the \ntransmission system. Despite the Commission’s orders, PJM’s proposed tariff is silent as to \nwhether a hybrid co-located facility can nominate net withdrawals for the purposes of PJM’s \n \n69 Horger Affidavit, supra note 23, at P 16."},{"page":22,"startToken":6724,"endToken":7011,"text":"22 \n \nNecessary Study Process. Without incorporating the net withdrawal limitations of hybrid \ngenerators in the operating assumptions for the Necessary Study Process, PJM’s proposed rules \nwill likely force hybrid generators to pay for unnecessary upgrades because the Necessary Study \nProcess will not accurately reflect hybrid generators’ use of the transmission system. The \nCommission should require PJM to clarify that hybrid co-located facilities can nominate their net \nwithdrawal limitations for purposes of the Necessary Study Process to avoid excessive and \nunnecessary network upgrade costs for hybrid generators.  \nIn addition to the Commission’s order to clarify the terms of service for co-location \narrangements, the Commission also ordered PJM to amend its retail-BTMG rules. The \nCommission determined that PJM’s existing BTMG rules may lead to reliability and resource \nadequacy risk and ordered PJM to create a MW materiality threshold for the amount of load a \nNetwork Customer may net using BTMG.  However, PJM proposes a Retail BTMG rule that is \nfundamentally different from what the Commission ordered, limiting the size of generator that \ncan participate in BTMG netting instead of the amount of load that a generator may net. The \nCommission should reject PJM’s materiality threshold and require PJM to make its retail-BTMG \nrules consistent with the Commission’s Order on the Show Cause Proceeding. \nA. Initial Comments correctly urge the Commission to require PJM to clarify that \nhybrid resources can nominate net withdrawal limitations in PJM’s necessary study \nprocess. \n \nAs initial comments explain, the Commission should require PJM to clarify that hybrid \nresources may nominate net withdrawal limitations in PJM’s Necessary Study Process to avoid \ntriggering costly and unnecessary network upgrades. Joint Parties argue that without clear \nprovisions to allow hybrid generators to nominate net withdrawal limitations, PJM may include"},{"page":23,"startToken":7011,"endToken":7292,"text":"23 \n \ninaccurate operating assumptions for hybrid generators in its Necessary Study Process.70 These \nassumptions could inaccurately identify overlapping grid impacts where storage resources and \nco-located loads could instead manage withdrawals, triggering unnecessary network upgrades.71 \nIf PJM fails to clarify that hybrid customers can nominate their net withdrawal limits, hybrid \ngenerators may be forced to pay for and wait for network upgrades that they will not use.    \nThe Commission should require PJM to clarify that hybrid co-located facilities can \nnominate their net withdrawal limitations for the necessary study process. This clarification \nwould be consistent not only with the Commission’s Order on its Show Cause Proceeding, but \nalso consistent with the Commission’s Order No. 2023. In Order No. 2023, the Commission \nrequired transmission providers to use operating assumptions that reflect the proposed charging \nbehavior of storage resources, including hybrid facilities, in their interconnection studies.72 The \nCommission issued these reforms to ensure that transmission providers do not overestimate the \nimpact of storage resources on the transmission system and to ensure that transmission providers \navoid assigning excessive and unnecessary network upgrades.73 PJM’s current proposal would be \ninconsistent with Order No. 2023 by including inaccurate, overestimated assumptions in its \nnecessary study process for hybrid co-located resources. PJM’s proposal will likely trigger the \nsame excessive, unnecessary network upgrades that the Commission sought to prevent with \nOrder No. 2023. PJM must clarify that hybrid resources can nominate net withdrawal limitations \nto comply with both the Commission’s Order on the Show Causing Proceeding and Order No. \n2023.  \n \n70 Joint Parties Protest, supra note 6, at 7.  \n71 Id. \n72 Order No. 2023, 184 FERC ¶ 61,054 at P 1509 (2023). \n73 Id. at P 1510."},{"page":24,"startToken":7292,"endToken":7650,"text":"24 \n \nB. Initial comments correctly support revising PJM’s Retail-BTMG rules to be \nconsistent with the Commission’s Order on the Show Cause Proceeding. \n \nInitial comments also urge the Commission to require PJM to change its proposed BTMG \nrules because PJM’s proposal is unjust and unreasonable. PJM’s BTMG rules allow loads to \nreduce their costs by netting their output from BTMG to determine their transmission charges.74 \nPJM’s proposed threshold limits retail-BTMG to generation that has a cumulative nameplate \nrating of no greater than 50 MW.75 PJM’s proposed threshold is materially different from the \nthreshold that FERC ordered because PJM set a MW threshold for the size of generator that can \nparticipate in netting rather than a threshold for the amount of load a generator can net. \nGenerators argue that PJM’s nameplate capacity cap unnecessarily limits the types of generators \nthat can participate in BTMG netting.76 Resources that would be excluded under PJM‘s current \nproposal are technically capable of providing retail-BTMG and should be able to do so.77 Unlike \nPJM’s proposed nameplate capacity threshold, the Commission’s load netting threshold would \napply fairly across all resource types. The Commission should reject PJM’s proposed BTMG \nrules and require PJM to set a materiality threshold that is consistent with the Commission’s \nOrder on the Show Cause Proceeding.  \nVI. Conclusion  \n \nFor the reasons discussed above, the Commission should (1) accept PJM’s proposed \noperational penalties; (2) require PJM to clarify its curtailment procedures and clarify how \n \n74 Order on Show Cause Proceeding, supra note 3, at 7-8. \n75 60-Day Compliance Filing, supra note 2, at 7. \n76 AEU & SEIA Protest, supra note 6, at 4.  \n77 See e.g., PJM Interconnection, LLC, 162 FERC ¶ 61,127, at P 4 (2018) (ordering RTOs/ISOs to revise their tariff \nprovisions to ensure that electric storage resources are eligible to provide all services that they are technically \ncapable of providing in the RTO/ISO markets); PJM Interconnection, LLC, 172 FERC ¶ 61,247, at P 141 (2020) \n(requiring that each RTO’s/ISO’s rules cannot exclude particular types of technologies from being eligible to \nprovide all of the services that they are technically capable of providing)."},{"page":25,"startToken":7650,"endToken":7739,"text":"25 \n \nviolations will be communicated to the public; (3) decline to require PJM to rush its \nimplementation deadline for its new transmission services; and (4) require PJM to make its \nproposed rules consistent with the Commission’s Order on the Show Cause Proceeding and \nOrder No. 2023. The consequences of faulty rules for co-located loads could be dire. The \nCommission must ensure that PJM protects the reliability of its transmission system for all of its \ncustomers, rather than protecting the financial interests of a well-resourced few.  \nDATED: April 24, 2026"},{"page":26,"startToken":7739,"endToken":7791,"text":"26 \n \nRespectfully submitted,  \nEARTHJUSTICE \n/s/ Aaliyah Adkins \nAaliyah Adkins \nAssociate Attorney \nEarthjustice \n1400 L St NW  \nLobby 2, Unit 34117  \nWashington DC 20005 \n(202) 797-5253 \naadkins@earthjustice.org \n \n/s/ Nick Lawton \nNick Lawton \nSenior Attorney \nEarthjustice \n1400 L St NW  \nLobby 2, Unit 34117  \nWashington DC 20005 \n(202) 780-4835 \nnlawton@earthjustice.org"},{"page":27,"startToken":7791,"endToken":7855,"text":"27 \n \nCERTIFICATE OF SERVICE \nI hereby certify that the foregoing has been served in accordance with 18 C.F.R. § \n385.2010 upon each party designated in the official service list compiled by the Secretary in this \nproceeding, by email.  \n \n \n/s/ Aaliyah Adkins \nAaliyah Adkins \nAssociate Attorney \nEarthjustice \n1400 L St NW  \nLobby 2, Unit 34117  \nWashington DC 20005 \n(202) 797-5253 \naadkins@earthjustice.org"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":1,"endAt":222,"startToken":0,"endToken":24},{"p":1,"at":222,"title":"I. Introduction","method":"printed heading","endPage":2,"endAt":1212,"startToken":24,"endToken":477},{"p":2,"at":1212,"title":"II. The Commission should accept PJM’s operational penalty proposal.","method":"printed heading","endPage":3,"endAt":1139,"startToken":477,"endToken":835},{"p":3,"at":1139,"title":"A. Initial comments either support PJM proposed penalties or fail to adequately","method":"printed heading","endPage":8,"endAt":5,"startToken":835,"endToken":2266},{"p":8,"at":5,"title":"B. The Commission should accept PJM’s proposed penalties because financial","method":"printed heading","endPage":14,"endAt":830,"startToken":2266,"endToken":4389},{"p":14,"at":830,"title":"III. The Commission should require PJM to clarify how and when PJM will enforce","method":"printed heading","endPage":15,"endAt":409,"startToken":4389,"endToken":4617},{"p":15,"at":409,"title":"A. Initial comments urge the Commission to require PJM to clarify its proposed","method":"printed heading","endPage":16,"endAt":6,"startToken":4617,"endToken":4865},{"p":16,"at":6,"title":"B. The Commission should require PJM to clarify its curtailment procedures to ensure","method":"printed heading","endPage":19,"endAt":782,"startToken":4865,"endToken":5906},{"p":19,"at":782,"title":"IV. The Commission should decline to require that PJM rush the implementation of","method":"printed heading","endPage":21,"endAt":803,"startToken":5906,"endToken":6537},{"p":21,"at":803,"title":"V. The Commission should require PJM to ensure that rules governing generator","method":"printed heading","endPage":22,"endAt":1428,"startToken":6537,"endToken":6935},{"p":22,"at":1428,"title":"A. Initial Comments correctly urge the Commission to require PJM to clarify that","method":"printed heading","endPage":24,"endAt":6,"startToken":6935,"endToken":7293},{"p":24,"at":6,"title":"B. Initial comments correctly support revising PJM’s Retail-BTMG rules to be","method":"printed heading","endPage":24,"endAt":1404,"startToken":7293,"endToken":7508},{"p":24,"at":1404,"title":"VI. Conclusion","method":"printed heading","endPage":27,"endAt":6,"startToken":7508,"endToken":7792},{"p":27,"at":6,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":27,"endAt":410,"startToken":7792,"endToken":7855}]}